BUILDING QUALITY THROUGH TEAMWORK 2200 Centrepark West Drive, Suite 100 West Palm Beach, FL 33409 Main: 561-689-8880 Fax: 561-689-8860 www.hedrickbrothers.com GMP BINDER for Northboro Elementary Modernization / Phase 2 Table of Contents SECTION 0: 1. Transmittals 2. Table of Contents SECTION 1: 3. GMP 4. Qualifications & Clarifications SECTION 2: 5. GMP Summary (Spreadsheet) 6. General Conditions Summary (Spreadsheet) 7. Construction Phase Fee Summary (Spreadsheet) SECTION 3: 8. Exhibit B: GMP Summary 9. Exhibit D: HBC Personnel Assigned During Construction 10. Exhibit E: Const. Manager’s Staff Per Diem Rates (for time extensions) 11. Exhibit F: Construction Team Assigned Representatives 12. Exhibit I: Builder’s Risk Questionnaire SECTION 4 13. Drawing Log 14. Specifications SECTION 5: 15. Exhibit S1: Subcontractor’s Participation (by Division) 16. Exhibit S2: List of Major Subcontractors (by Trade) 17. APPENDIX C: Construction Vendors MWBE Letters of Intent 18. M/WBE Confirmation Letters SECTION 6: 19. Project Schedule SECTION 7: 20. Beneficial Interest & Disclosure of Ownership Affidavit

GMP BINDER for Northboro Elementary Modernization / … Board Meeting on Tuesday... · Takeoff Quantity Labor Amount Material Amount Sub Amount Total Amount 1000.000 GENERAL REQUIREMENTS

  • Upload
    dothuy

  • View
    217

  • Download
    0

Embed Size (px)

Citation preview

BUILDING QUALITY THROUGH TEAMWORK

2200 Centrepark West Drive, Suite 100 West Palm Beach, FL 33409 Main: 561-689-8880 Fax: 561-689-8860 www.hedrickbrothers.com

GMP BINDER for Northboro Elementary Modernization / Phase 2

Table of Contents SECTION 0:

1. Transmittals 2. Table of Contents

SECTION 1:

3. GMP 4. Qualifications & Clarifications

SECTION 2:

5. GMP Summary (Spreadsheet) 6. General Conditions Summary (Spreadsheet) 7. Construction Phase Fee Summary (Spreadsheet)

SECTION 3:

8. Exhibit B: GMP Summary 9. Exhibit D: HBC Personnel Assigned During Construction 10. Exhibit E: Const. Manager’s Staff Per Diem Rates (for time extensions) 11. Exhibit F: Construction Team Assigned Representatives 12. Exhibit I: Builder’s Risk Questionnaire

SECTION 4 13. Drawing Log 14. Specifications

SECTION 5:

15. Exhibit S1: Subcontractor’s Participation (by Division) 16. Exhibit S2: List of Major Subcontractors (by Trade) 17. APPENDIX C: Construction Vendors MWBE Letters of Intent 18. M/WBE Confirmation Letters

SECTION 6:

19. Project Schedule

SECTION 7: 20. Beneficial Interest & Disclosure of Ownership Affidavit

BRINGING VISIONS TO REALITY

2200 Centrepark West Drive, Suite 100, West Palm Beach, FL 33409 Main: 561-689-8880 Fax: 561-689-8860 www.hedrickbrothers.com

Northboro Elementary School

Guaranteed Maximum Price (GMP) Phase II

Qualifications & Clarifications

October 29, 2008

Phase II Construction costs totals $23,528,427.00

DIV 02 SITEWORK

1. A $275,000 ALLOWANCE for the Playground Equipment and Playground Surfacing is included. A

$10,000 ALLOWANCE for FPL pole relocation is also included.

DIV 09 FINISHES

1. Acoustical ceilings exclude hurricane, hold down, or retention clips as called for in the specifications, as

the drawings do not specify where this is required. This can be added to the project if requested.

Acoustical wall panels are included at the multi-purpose room and music room.

DIV 10 SPECIALTIES

1. Floor Mats are excluded.

DIV 11 EQUIPMENT

1. Safe at Administration area is excluded.

DIV 16 ELECTRICAL

1. A Class A “Dual Pipe” Fire Alarm system with 2 conduits per panel is included.

2. A $10,000 ALLOWANCE to remove / relocate FPL power lines & utility poles, phone lines, and cable

lines, at the „to be removed‟ road, is included.

HEDRICK BROTHERS GMP SUMMARY Page 1

NORTHBORO ELEMENTARY - PHASE II - GMP 10/29/2008 5:33 PM

Division DescriptionTakeoff

Quantity

Labor

Amount

Material

Amount

Sub

Amount

Total

Amount

1000.000 GENERAL REQUIREMENTS

Scheduling

Schedule Preparation 4,000.00 ls - - 4,000 4,000

Schedule Updates 18.00 mo - - 6,300 6,300

Scheduling 10,300 10,300

Temp: Supplies

Blue Prints 300.00 sets - 31,950 - 31,950

Temp: Supplies 31,950 31,950

Temp: Traffic Control

Security Guard 65.00 wk - - 39,000 39,000

traffic control barricades signs 7.00 mo - 3,728 - 3,728

Temp: Traffic Control 3,728 39,000 42,728

Temp: Protection

Temporary Protection 7,500.00 ls - - 7,500 7,500

Hurricane Prep 5,000.00 ls - - 5,000 5,000

Temporary Fence w/ screen & Removal 1,200.00 lf - - 10,362 10,362

Temp: Protection 22,862 22,862

Controls: Erosion

Maintain Erosion Control 14.00 mo - - 7,000 7,000

Dust Control 360,000.00 sf - - 10,800 10,800

Controls: Erosion 17,800 17,800

Layout

Layout (Own Forces) 17.33 wk 12,911 9,228 - 22,139

Layout 12,911 9,228 22,139

Clean Up

Final Cleanup 48,525.00 ls - - 48,525 48,525

Current Cleanup 90.00 wk 60,346 1,438 - 61,783

Haul Dumpster 133.00 ea - 46,035 - 46,035

Clean Up 60,346 47,473 48,525 156,343

Project Closeout

Project Closeout 1.00 ea 4,098 2,929 - 7,026

Project Closeout 4,098 2,929 7,026

GENERAL REQUIREMENTS

77,354 95,307 138,487 311,148

2000.000 SITE CONSTRUCTION

Surveying

Surveying - Sitework & Buildings 38,885.00 ls - - 38,885 38,885

Utility line locator at conc. demo/util install 2,500.00 ls - - 2,500 2,500

Surveying 41,385 41,385

Demo: Site

Demo Curb & Concrete 10,075.00 ls - - 10,075 10,075

Demo Utilities Sheet C-106 4,670.00 ls - - 4,670 4,670

Demo Utilities 1,820.00 ls - - 1,820 1,820

Demo Utilities @ Phase 1 -1,820.00 ls - - (1,820) (1,820)

Demo: Site 14,745 14,745

Clearing: Site

Clear & Grubbing 2,695.00 ls - - 2,695 2,695

HEDRICK BROTHERS GMP SUMMARY Page 2

NORTHBORO ELEMENTARY - PHASE II - GMP 10/29/2008 5:33 PM

Division DescriptionTakeoff

Quantity

Labor

Amount

Material

Amount

Sub

Amount

Total

Amount

Clearing: Site 2,695 2,695

Earthwk: Site Grading

Crane Access Road 6,910.00 ls - - 6,910 6,910

Earthwork 184,040.00 ls - - 184,040 184,040

Earthwork @ Phase 1 -74,115.00 ls - - (74,115) (74,115)

Grading & Paving as-builts 8,555.00 ls - - 8,555 8,555

Grading & Paving as-builts @ Phase 1 -1,815.00 ls - - (1,815) (1,815)

P & P Bond 8,954.00 ls - - 8,954 8,954

P & P Bond @ Phase 1 -1,965.00 ls - - (1,965) (1,965)

Earthwk: Site Grading 130,564 130,564

Erosion & Sediment Contrl

Maintain Erosion Control & Street Sweeping 17,635.00 ls - - 17,635 17,635

Erosion & Sediment Contrl 17,635 17,635

Water Distribution

Domestic Water Distribution 44,270.00 ls - - 44,270 44,270

Utility stake w/ asbuilts 9,945.00 ls - - 9,945 9,945

Utility stake w/ asbuilts @ Phase 1 -1,300.00 ls - - (1,300) (1,300)

Water Distribution 52,915 52,915

Sanitary Sewer

Sanitary Sewage 36,085.00 ls - - 36,085 36,085

Sanitary Sewer 36,085 36,085

Fire Main

Fire Line Distribution 133,615.00 ls - - 133,615 133,615

4' Dia Check Valve Manhole - 4 ea 8,360.00 ls - - 8,360 8,360

6" Stub-ups @ Bldgs 5,150.00 ls - - 5,150 5,150

Fire Main 147,125 147,125

Storm Drainage

Storm Drainage 247,060.00 ls - - 247,060 247,060

Storm Drainage @ Phase 1 -120,955.00 ls - - (120,955) (120,955)

Storm Drain Condensate 5,765.00 ls - - 5,765 5,765

Storm Drainage 131,870 131,870

Asphalt Paving

Off-site Asphalt Paving turn lane 20,495.00 ls - - 20,495 20,495

Off-site Asphalt Mill & Overlay 38th street 17,100.00 ls - - 17,100 17,100

Turnlane Revision 2,935.00 ls - - 2,935 2,935

Asphalt Paving 40,530 40,530

Sidewalks

Off-site Sidewalks, Demo, HC Ramps 66,735.00 ls - - 66,735 66,735

Sidewalks 66,735 66,735

Parking Lines

Stripage, Signage, & Wheelstops 19,670.00 ls - - 19,670 19,670

Parking Lines 19,670 19,670

Paving: Curbs & Gutters

Type D & F Curbs 38,615.00 ls - - 38,615 38,615

Valley Gutters @ Entrances 3,180.00 ls - - 3,180 3,180

Paving: Curbs & Gutters 41,795 41,795

Athletic/Recreate Surface

Plexicoat Surface & Striping 25,225.00 ls - - 25,225 25,225

Athletic/Recreate Surface 25,225 25,225

Irrigation System

HEDRICK BROTHERS GMP SUMMARY Page 3

NORTHBORO ELEMENTARY - PHASE II - GMP 10/29/2008 5:33 PM

Division DescriptionTakeoff

Quantity

Labor

Amount

Material

Amount

Sub

Amount

Total

Amount

Irrigation System

Irrigation System 116,348.00 ls - - 116,348 116,348

Irrigation System 116,348 116,348

Fencing

Perimeter Fence 138,847.00 ls - - 138,847 138,847

Demo Existing Perimeter Fencing 3,000.00 ls - - 3,000 3,000

Card Reader Prep @ Entry Gates 3.00 ea - - 750 750

Motorized Operators @ Entry Gates 3.00 ea - - 4,500 4,500

Food Service Compressor Enclosure 2,000.00 ls - - 2,000 2,000

Fencing 149,097 149,097

Site Equip: PlayingFields

Basketball Goals-fixed exterior 6,900.00 ls 0 0 6,900 6,900

Playground:Equipment,Surface, & Turf - SEEALLOWANCES

0.00 ls - - 0 0

Site Equip: PlayingFields 6,900 6,900

Landscape

Landscaping 98,299.00 ls - - 98,299 98,299

Sodding 134,700.00 sf - - 28,287 28,287

Roof Barier 500.00 lf - - 6,000 6,000

sodding @ perimeter of site 6,000.00 sf - - 2,100 2,100

Maintenance of perimeter/interior site 82.00 wK - - 10,250 10,250

Landscape 144,936 144,936

SITE CONSTRUCTION 1,186,255 1,186,255

3000.000 CONCRETE

Concrete Work

Soil Treatment 55,000.00 sf - - 4,300 4,300

Concrete Paving 94,314.00 sf - - 334,900 334,900

On-site Sidewalks, w/ Turn Down Curb @

Parent Drop Off

23,669.00 sf - - 143,880 143,880

Sawcut & Demo Driveways 3,500.00 ls - - 3,500 3,500

Off-site Sidewalk 2,095.00 sf - - 6,800 6,800

Site Wall, Sign, Play Yard, Chiller & FPL

Pads

78,500.00 ls - - 78,500 78,500

Picture Frame Finsih @ Courtyard 4,600.00 ls - - 4,600 4,600

Bldg #1 Entry Sturcture inc/ CMU & Brick 26,950.00 ls - - 26,950 26,950

Add Columns w/ Brick Veneer @ Courtyard

Gates, A504, Detail #4

7.00 ea - - 12,600 12,600

Delete 4" Conc Base @ Bldg #3 Courtyard -30,200.00 ls - - (30,200) (30,200)

Site Monument Sign Foundation 2 ea 2.00 ea - - 4,920 4,920

6' 'Backless' & 'Art' Bench Seats (no backs) 22.00 ea - - 7,550 7,550

Building Concrete 99,000.00 sf - - 915,400 915,400

Add Haunch @ CMU Infill Walls,

R266A001504, Detail #3 & #4

105.00 lf - - 7,400 7,400

Bond on Total Scope 1.58% 40,004.00 ls - - 40,004 40,004

MEP Trades concrete flr replace. bldg #2 3,700.00 ls - - 3,700 3,700

Surface Dewatering @ Foundations 1,500.00 ls - - 1,500 1,500

Concrete Grout @ Below grade utility

penetrations

1,000.00 ls - - 1,000 1,000

Arched/reg beams (missing in ctyd/bldg #2)

- 80 cy

58.05 cy - - 73,314 73,314

HEDRICK BROTHERS GMP SUMMARY Page 4

NORTHBORO ELEMENTARY - PHASE II - GMP 10/29/2008 5:33 PM

Division DescriptionTakeoff

Quantity

Labor

Amount

Material

Amount

Sub

Amount

Total

Amount

Concrete Work

Perimeter protection 1,200.00 lf - - 4,500 4,500

Asphalt coating @ HM Frames @ CMU

Walls

75.00 ea - - 4,000 4,000

Brick Veneer 15,500.00 sf - - 221,500 221,500

F & I Brick Lintels (Releaving Angles) 550.00 lf - - 10,040 10,040

CMU Masonry, Rebar, Filled Cells 60,000.00 sf - - 761,500 761,500

Furnish Precast Window Sills 10,350.00 ls - - 10,350 10,350

Install Precast Window Sills 6,400.00 ls - - 6,400 6,400

CMU bullnose adder 1,000.00 ls - - 1,000 1,000

CMU dovetail anchors supply/instl bldg #3 2,400.00 ls - - 2,400 2,400

Concrete Work 2,662,308 2,662,308

Deck: Insulating ConcRoof

Lt Wt Concrete Roof @ Main Areas 100,000.00 ls - - 100,000 100,000

Lt Wt Concrete Roof @ Below Mansards 30,000.00 ls - - 30,000 30,000

Deck: Insulating ConcRoof 130,000 130,000

CONCRETE 2,792,308 2,792,308

5000.000 STEEL

Structural Steel

Pipe Bollard 2.00 ea - - 700 700

Bike Rack 20.00 ea - - 3,450 3,450

Structural Steel - 2 story w/ stairs 1,276,895.00 ls - - 1,276,895 1,276,895

Structural Steel Support @ Roof Hatches 3.00 ea - - 1,500 1,500

Kitchen Hood Support Frame 1.00 ea - - 3,500 3,500

Angle Iron Drywall Bracing 1,800.00 ls - - 1,800 1,800

Grout Column Bases 31.00 ea - - 465 465

Add Pipe Columns @ Mansard Girder

Trusses

31.00 ea - - 7,750 7,750

Stage Curtaqin Support Frame 22.00 lf - - 4,400 4,400

Add Supports for Classroom Projectors 65.00 ea - - 6,500 6,500

Expansion Joints & Misc Angle Iron 30,000.00 ls - - 30,000 30,000

Refurbish Existing Fence @ NE Corner 6,900.00 ls - - 6,900 6,900

Structural Steel 1,343,860 1,343,860

Metal Framing Systems

Lt Gauge Girder & Mansard Trusses, 20 ga

G-90 Metal Deck, 5/8" Plywood, 2x & 1x

Fascia

15,465.00 ls - - 319,028 319,028

Lt Gauge Framing, Plywood, @ Copper

Roofing

585.00 sf - - 8,775 8,775

Metal Framing Systems 327,803 327,803

Metal Fabrications

Metal Fabrication - Alum Railings, Alum

Fencing

286,872.00 ls - - 286,872 286,872

Alum Fencing @ East & West Site

Perimeters

100.00 lf - - 10,000 10,000

5' Alum Gates @ East & West Site

Perimeters

2.00 ea - - 1,500 1,500

4' Alum Gates @ East & West Site

Perimeters

2.00 ea - - 1,300 1,300

Metal Fabrications 299,672 299,672

HEDRICK BROTHERS GMP SUMMARY Page 5

NORTHBORO ELEMENTARY - PHASE II - GMP 10/29/2008 5:33 PM

Division DescriptionTakeoff

Quantity

Labor

Amount

Material

Amount

Sub

Amount

Total

Amount

STEEL 1,971,335 1,971,335

6000.000 CARPENTRY

Rough Carpentry

Rough Carpentry 66,160.00 ls 49,290 35,230 0 84,520

Rough Carpentry 49,290 35,230 84,520

CARPENTRY 49,290 35,230 84,520

7000.000 THERMAL/MOISTURE

Waterproofng

Waterproofing & Brick Seal 43,462.00 ls - - 43,462 43,462

Waterproof CMU @ Brick Veneer 5,351.00 sf - - 13,378 13,378

Waterproofng 56,840 56,840

Foam Insulation

Foam Insulation @ Exterior CMU walls 23,377.00 ls - - 23,377 23,377

Foam Insulation 23,377 23,377

Shingles: Metal

Metal Shingles, Flashing, Underlayments,

Gutter & Downspouts

29,185.00 sf - - 424,500 424,500

Shingles: Metal 424,500 424,500

Metal Roof Panels

Standing Seam Copper, Flashing,

Underlayments, Gutters & Downspouts

585.00 sf - - 28,500 28,500

Metal Roof Panels 28,500 28,500

Roofing Demo

Tear Off Bldg #2 Roof Membrane &

Flashings

37,460.00 ls - - 37,460 37,460

Roofing Demo 37,460 37,460

Membrane: BUR Bitumen

Modified Bituminous Roof w/ Roof Hatches 289,541.00 ls - - 289,541 289,541

Roofing Material 205,000.00 ls - - 205,000 205,000

Material Escalation 29,600.00 ls - - 29,600 29,600

Repair existing bldg #2 lghtwgt deck 5% 565.00 sf - - 5,650 5,650

Lt Wt Concrete Supervision & Mgmt 24,670.00 ls - - 24,670 24,670

Membrane: BUR Bitumen 554,461 554,461

Firestopping

Firestopping / Fire caulking 56,853.00 ls - - 56,853 56,853

Firestopping 56,853 56,853

Joint Sealants

Caulking & Sealants 68,986.00 ls - - 68,986 68,986

Joint Sealants 68,986 68,986

THERMAL/MOISTURE 1,250,977 1,250,977

8000.000 WINDOWS AND DOORS

Frames, Doors & Hardware

HM Frames & HM Doors 145,880.00 ls - - 145,880 145,880

FSC Wood Doors 109,570.00 ls - - 109,570 109,570

Door Hardware 297,330.00 ls - - 297,330 297,330

New Door Slabs @ Bldg #2 22,653.00 ls - - 22,653 22,653

Asphalt Coating @ HM Frames @ CMU

Walls

5,426.00 ls - - 5,426 5,426

HEDRICK BROTHERS GMP SUMMARY Page 6

NORTHBORO ELEMENTARY - PHASE II - GMP 10/29/2008 5:33 PM

Division DescriptionTakeoff

Quantity

Labor

Amount

Material

Amount

Sub

Amount

Total

Amount

Frames, Doors & Hardware

Grey Tint Impact Glass @ Ext HM Doors 13,275.00 ls - - 13,275 13,275

Glass @ Interior Wood Doors 9,894.00 ls - - 9,894 9,894

Frames, Doors & Hardware Installation 79,095.00 ls - - 79,095 79,095

New Door Slabs @ Bldg #2 Installation 59.00 ea - - 6,608 6,608

Frames, Doors & Hardware 689,731 689,731

Doors: Access

Access Doors - 9,000.00 ls 6,705 4,793 0 11,498

Doors: Access 6,705 4,793 11,498

Doors: Coiling

Coiling Door 6,770.00 ls - - 6,770 6,770

Add Door Insulation @ Ext Doors 850.00 ls - - 850 850

Doors: Coiling 7,620 7,620

Windows: Metal

Windows, Door Lites, Storefront, & Curtain

Wall

525,000.00 ls - - 525,000 525,000

Firelite Door Glass @ Bldg #2 25,000.00 ls - - 25,000 25,000

Window Testing 15,000.00 ls - - 15,000 15,000

Windows: Metal 565,000 565,000

WINDOWS AND DOORS 6,705 4,793 1,262,351 1,273,849

9000.000 FINISHES

Stucco

Stucco Repair @ Bldg 2 Windows 1,840.00 lf - - 18,400 18,400

Stucco 18,400 18,400

Drywall & Metal Framing

Metal Framing, Ext Sheathing, Int Drywall, &

Stucco

1,297,800.00 ls - - 1,297,800 1,297,800

Metal Framing @ Ext Soffit @ Mansard 1,460.00 lf - - 7,300 7,300

Drywall & Metal Framing 1,305,100 1,305,100

Acoustic Ceiling

Acoustical Ceiling and Acoustic Panels 172,596.00 ls - - 172,596 172,596

Acoustic Ceiling 172,596 172,596

Flooring

VCT, Carpet, Sht Vinyl, Stairs & Rubber

Base

322,114.00 ls - - 322,114 322,114

Ceramic Tile & Quarry Tile 53,832.00 ls - - 53,832 53,832

Epoxy Grout @ Quarry Tile 4,158.00 sf - - 13,064 13,064

Mud Set @ Quarry Tile 4,158.00 sf - - 13,285 13,285

Bond @ 2% 8,046.00 ls - - 8,046 8,046

Quarry Wall Tile 3,130.00 sf - - 20,439 20,439

Crack Suppression 6,871.00 ls - - 6,871 6,871

Add VCT @ Stage 1,030.00 sf - - 2,575 2,575

8 Coats of Wax @ VCT 67,581.00 sf - - 16,895 16,895

Flooring 457,121 457,121

Flooring Epoxy

Epoxy Flooring w/ Shotblast Prep 7,000.00 unit - - 44,275 44,275

Adjust Quanity 300.00 unit - - 1,898 1,898

Waterproof Membrane 7,975.00 ls - - 7,975 7,975

Flooring Epoxy 54,148 54,148

Flooring Preparition

HEDRICK BROTHERS GMP SUMMARY Page 7

NORTHBORO ELEMENTARY - PHASE II - GMP 10/29/2008 5:33 PM

Division DescriptionTakeoff

Quantity

Labor

Amount

Material

Amount

Sub

Amount

Total

Amount

Flooring Preparition

Flooring Prep @ VCT @ Bldg #2 30,821.00 sf - - 57,000 57,000

Flooring Prep @ VCT @ Bldg #2 Additional

Qty

714.00 sf - - 1,320 1,320

Flooring Prep @ Bldgs #1 & #3 100,000.00 sf - - 10,000 10,000

Flooring Preparition 68,320 68,320

Paints & Coatings

Painting 274,197.00 ls - - 274,197 274,197

Stucco @ Back of Mansard 8,000.00 sf - - 7,600 7,600

Paints & Coatings 281,797 281,797

FINISHES 2,357,482 2,357,482

10000.000 SPECIALTIES

Visual Display Boards

Visual Display Boards 64,793.00 ls - - 64,793 64,793

Visual Display Boards 64,793 64,793

Toilet Compartments

Toilet Compartment & Toilet Accessories 100,410.00 ls - - 100,410 100,410

Electric Hand Dryers @ Gang Bathroom 4.00 ea - - 3,000 3,000

Toilet Compartments 103,410 103,410

Louvers and Vents

Louvers - 15,000.00 ls - - 15,000 15,000

Louvers and Vents 15,000 15,000

Wall & Corner Guards

Corner Guards - 25,000.00 ls - - 25,000 25,000

Wall & Corner Guards 25,000 25,000

Flagpoles

Flagpole 30' hgt page 12 ed spec 4,293.00 ls - - 4,293 4,293

Flagpole Concrete 500.00 ls - - 500 500

Flagpoles 4,793 4,793

Signs and Letters

Signage 69,505.00 ls - - 69,505 69,505

Signage @ Monument Sign (add 1) 1.00 ea - - 2,600 2,600

Signs and Letters 72,105 72,105

Fire Extinguishers Etc

Fire Extinguisher & Cabinet 24,523.00 ls - - 24,523 24,523

Fire blanket 3.00 ea - - 197 197

Fiist Aid kit 3.00 ea - - 189 189

Fire Extinguishers Etc 24,909 24,909

Walkway Covers

Walkway Canopy w/ Bond 195,636.00 ls - - 195,636 195,636

Walkway Covers 195,636 195,636

Partitions

Wire Mesh Partitions 17,213.00 ls - - 17,213 17,213

Partitions 17,213 17,213

Storage Cabinets & Shelving

Metal Lockers 16.00 ea - - 4,984 4,984

Metal Cabinets & Metal Utility Shelving 51,661.00 ls - - 51,661 51,661

Key Cabinet 1.00 ea - - 250 250

HEDRICK BROTHERS GMP SUMMARY Page 8

NORTHBORO ELEMENTARY - PHASE II - GMP 10/29/2008 5:33 PM

Division DescriptionTakeoff

Quantity

Labor

Amount

Material

Amount

Sub

Amount

Total

Amount

Storage Cabinets & Shelving

Lockable Narcotics Cabinet 24"w x 30"hx

10"d @ Clinic

1.00 ea - - 250 250

Lockable Storage Cabinet @ Clinic 1.00 ea - - 250 250

Storage Cabinets & Shelving 57,395 57,395

Misc Specialties

Clock - INSTALLATION 56.00 ea 459 0 0 459

Clock - INSTALLATION 14.00 ea 115 - 115

Clock - INSTALLATION 19.00 ea 156 - 156

Misc Specialties 729 729

SPECIALTIES 729 580,254 580,983

11000.000 EQUIPMENT

Equip: Bank & Vault

Knox box 4.00 ea - - 2,000 2,000

Drop Safe 2.00 ea - - 850 850

Equip: Bank & Vault 2,850 2,850

Equip: Curtains & Window

Treatrment

Cubicle Curtain Track Ceilinf Mounted @

Clinic

1,060.00 ls - - 1,060 1,060

Curtain track assembly @ CCTV room 40.00 lf 167 275 0 442

Curtain @ CCTV room 360.00 sf 499 709 0 1,208

Pipe rail to hang lights @ CCTV room 140.00 lf 586 962 0 1,548

Stage Curtains 9,063.00 ls - - 9,063 9,063

Window Treatment 16,747.00 ls - - 16,747 16,747

Equip: Curtains & Window

Treatrment

1,253 1,946 26,870 30,068

Equip: Audio Visual

(62) 80" x 60" Manual and (1) 10' x 12'

Motorized Projector Screens

12,662.00 ls - - 12,662 12,662

Additional Projection Screens 80" x 60" 5.00 ea - - 875 875

Motorized Projection Screens 12' x 5' 1.00 ea - - 1,275 1,275

Motorized Projection Screens Supports 2.00 ea - - 600 600

Equip: Audio Visual 15,412 15,412

Equip: Commercial Food

Kitchen Equipment, Commercial Washer &

Dryer

452,880.00 ls - - 452,880 452,880

Equip: Commercial Food 452,880 452,880

Equip: Residental Food

Kitchen Appliance 10,367.00 ls - - 10,367 10,367

Equip: Residental Food 10,367 10,367

Equip: Educational

Educational Equipment Sub(lsum)

ls - -

Equip: Industrial/Process

Kiln 1.00 EA 0 0 5,500 5,500

Equip: Industrial/Process 5,500 5,500

EQUIPMENT 1,253 1,946 513,879 517,077

12000.000 FURNISHINGS

HEDRICK BROTHERS GMP SUMMARY Page 9

NORTHBORO ELEMENTARY - PHASE II - GMP 10/29/2008 5:33 PM

Division DescriptionTakeoff

Quantity

Labor

Amount

Material

Amount

Sub

Amount

Total

Amount

Manufactured Casework

Manufact. Casework-recessed display case 883,789.00 ls - - 883,789 883,789

Delete Metal Cabinets -219,059.00 ls - - (219,059) (219,059)

Bond @ 2.5% 16,618.00 ls - - 16,618 16,618

Adjust Plastic Laminate Qtys 60,411.00 ls - - 60,411 60,411

Bond on HB Add @ 2.5% 1,510.00 ls - - 1,510 1,510

Manufactured Casework 743,269 743,269

FURNISHINGS 743,269 743,269

14000.000 ELEVATOR

Hydraulic Elevators

Hydraulic Elevator 53,897.00 ls - - 53,897 53,897

Hydraulic Elevators 53,897 53,897

ELEVATOR 53,897 53,897

15000.000 MECHANICAL

Fire Sprinkler

Fire Sprinkler 281,604.00 ls - - 281,604 281,604

Fire Penetrations Safing 1,527.00 ls - - 1,527 1,527

Fire Sprinkler 283,131 283,131

Plumbing

Plumbing inc Bond 734,905.00 ls - - 734,905 734,905

Grease Traps inc Bond 22,440.00 ls - - 22,440 22,440

Plumbing 757,345 757,345

HVAC Systems

TEMPORARY HVAC (mo) 8.00 mo - 42,600 0 42,600

HVAC Sub (lsum) 2,475,000.00 ls - - 2,475,000 2,475,000

HVAC Systems 42,600 2,475,000 2,517,600

MECHANICAL 42,600 3,515,476 3,558,076

16000.000 ELECTRICAL

Electrical

ELECTRICAL inc Bond 2,726,000.00 ls - - 2,726,000 2,726,000

Fire Alarm @ PIV 24,300.00 ls - - 24,300 24,300

Lutron Lighting Ctl Sys & Piperail @ CCTV

Prod Rm

6,300.00 ls - - 6,300 6,300

Intercom 3" Riser System 14,000.00 ls - - 14,000 14,000

120v Heat Detector & Contactor @ Kilns 2,800.00 ls - - 2,800 2,800

Heat Detector @ Elev Landing 2,700.00 ls - - 2,700 2,700

Class 'A' "Dual Pipe" Fire Alarm System 18,000.00 ls - 18,000 18,000

Additional Fire Alarm Devices 10,000.00 ls - 10,000 10,000

Replace Bldg #2 Devices & Wiring 21,800.00 ls - 21,800 21,800

Emergency Panel Coordination Study &

Panel Upgrade

10,000.00 ls - 10,000 10,000

Lightning Detection & Warning System 1,750.00 ls - - 1,750 1,750

Add 13 GPS Clocks 2,500.00 ls - - 2,500 2,500

Concrete @ Tranformer Pad 5,000.00 ls - 5,325 5,325

PA & Intercom Systems 79,800.00 ls - - 79,800 79,800

Art-Tronics Wireless Speakers @ Stage 10,000.00 ls - - 10,000 10,000

Electrical 5,325 2,929,950 2,935,275

Power Generation

Fuel / auto transfer switch / exhaust /

controls systems

34,865.00 INC - 37,131 0 37,131

HEDRICK BROTHERS GMP SUMMARY Page 10

NORTHBORO ELEMENTARY - PHASE II - GMP 10/29/2008 5:33 PM

Division DescriptionTakeoff

Quantity

Labor

Amount

Material

Amount

Sub

Amount

Total

Amount

Power Generation 37,131 37,131

High Voltage Distribution

Relocate FPL Power Poleswithin easements - SEEALLOWANCES

0.00 ls - - 0 0

ELECTRICAL 42,456 2,929,950 2,972,406

HEDRICK BROTHERS GMP SUMMARY Page 11

NORTHBORO ELEMENTARY - PHASE II - GMP 10/29/2008 5:33 PM

Estimate Totals

Description Amount Totals Rate

Labor 135,331

Material 222,332

Subcontract 19,295,919

TOTAL DIVISIONS 1-16 19,653,582

INSURANCE & BOND 468,589

CONSTRUCTION PHASE FEE 1,422,424

GENERAL CONDITIONS 335,748

CONSTRUCTION MANAGER'S FEE 1,109,405

OWNER'S CONST CONTINGENCY 491,340

OWNER'S ALLOWANCE 285,000

SUB-TOTAL 23,766,088

DEDUCT: SALES TAX RECOVERY (237,661)

TOTAL GMP PHASE II 23,528,427

TOTAL GMP PHASE I 2,002,889

PRECONSTRUCTION PHASE FEE 179,971

TOTAL CONSTRUCTION COST 25,711,287

HEDRICK BROTHERS GENERAL CONDITIONS SUMMARY Page 1

NORTHBORO ELEMENTARY - PHASE II - GC'S 10/29/2008 11:34 AM

Phase DescriptionTakeoff

Quantity

Labor

Amount

Material

Amount

Sub

Amount

Equip

Amount

Total

Amount

GENERAL CONDITIONS

1300.010 Personnel: Supervision

Superintendent Vehicle Expense 71.00 wk - 11,342 - 8,696 20,038

Asst. Superintendent Vehicle Expense 71.00 wk - 11,342 - 7,183 18,526

Personnel: Supervision 22,685 15,879 38,564

1310.010 Personnel: Proj. Managmnt

Senior Project Manager Vehicle

Expense

71.00 wk - 6,805 - 8,696 15,501

HB Truck/Hauling 35.00 wk 4,555 - - 1,491 6,046

Personnel: Proj. Managmnt 4,555 6,805 10,187 21,547

1510.010 Utilities: Temporary

Temp Electricity 16.25 mo - 43,266 - - 43,266

Rework Temp Electricity to Job

Trailers

4,758.00 ls - 5,067 - - 5,067

Temp Phone - HB Phone & Fax 21.50 mo - 10,304 - - 10,304

Temp Phone - SD Phone & Fax 21.50 mo - 10,304 - - 10,304

Temp Phone - SD T-1 21.50 mo - 11,449 - - 11,449

Supt Phone 16.25 mo - 1,731 - - 1,731

Asst Supt Phone 16.25 mo - 1,731 - - 1,731

Senior Project Mgr Phone 16.25 mo - 1,385 - - 1,385

Asst Project Mgr Phone 16.25 mo - 1,385 - - 1,385

LEED Asst Project Mgr Phone 16.25 mo - 415 - - 415

Project Coordinator Phone 16.25 mo - 1,385 - - 1,385

Temp Water 16.25 mo - 17,306 - - 17,306

Temp Toilets (8) 16.25 mo - 15,576 - - 15,576

SD Trailer Chemical Toilet 16.50 mo - 14,058 - - 14,058

Utilities: Temporary 135,359 135,359

1520.010 Temp: Facilities

SD Office Trailer 16.50 mo - 8,786 - - 8,786

SD Office Trailer - Security System 16.50 mo - 3,515 - - 3,515

SD Office Trailer - Drinking Water

Service

16.50 mo - 2,636 - - 2,636

SD Office Trailer - Coffee Service 16.50 mo - 1,757 - - 1,757

HB Trailer #1 - Mgmt 16.50 mo - 8,786 - - 8,786

HB Trailer #2 - Supt / Conference 16.50 mo - 8,786 - - 8,786

HB Trailer #1 & #2 - Security System 16.50 mo - 3,515 - - 3,515

Office Trailer - Janitorial Service 16.50 mo - 6,590 - - 6,590

Tool Trailers - 2 ea 13.25 mo - 3,528 - - 3,528

Job Site Consumables 16.25 mo - 8,653 - - 8,653

Computer Service - HB, M.O.

Equipment

16.25 mo - 6,094 - 6,094

Computer Leasing 21.50 mo - 2,365 - 2,365

Computer Leasing 19.50 mo - 2,145 - 2,145

Software Licensing 16.25 mo - 5,281 - 5,281

Temp: Facilities 56,551 15,885 72,437

1520.020 Temp: Supplies

Cups & Ice 13.25 mo - 3,528 - - 3,528

Office Supplies 16.25 mo - 10,384 - - 10,384

Progress Photographs 3,000.00 ls - 3,195 - - 3,195

Aerial Photographs 13.25 mo - 1,764 - - 1,764

Temp: Supplies 18,870 18,870

1520.030 Temp: Office Supplies

Copy Expense 16.25 mo - 2,163 - - 2,163

Postage/FedEx 16.25 mo - 6,057 - - 6,057

HEDRICK BROTHERS GENERAL CONDITIONS SUMMARY Page 2

NORTHBORO ELEMENTARY - PHASE II - GC'S 10/29/2008 11:34 AM

Phase DescriptionTakeoff

Quantity

Labor

Amount

Material

Amount

Sub

Amount

Equip

Amount

Total

Amount

Temp: Office Supplies 8,220 8,220

1540.010 Temp: Tools & Equipment

Tools & Equipment 13.25 mo - 7,056 - - 7,056

Project Fuel Expense 13.25 mo - 21,167 - - 21,167

Temp: Tools & Equipment 28,223 28,223

1562.010 Controls: Safety

First Aid Equip 13.25 mo - 3,528 - - 3,528

Safety - Site Visits 36.00 ea - - 9,000 - 9,000

Controls: Safety 3,528 9,000 12,528

GENERAL CONDITIONS 4,555 280,242 24,885 26,066 335,748

Estimate Totals

Description Amount

Labor 4,555

Material 280,242

Subcontract 24,885

Equipment 26,066

TOTAL 335,748

HEDRICK BROTHERS PHASE FEE SUMMARY Page 1

NORTHBORO ELEMENTARY - PHASE II - PHASE FEE10/29/2008 11:36 AM

Phase DescriptionTakeoff

QuantityLabor Amount Sub Amount Total Amount

CONSTRUCTION PHASE FEE

1210.010 Teaming Mgmt

MBE Mentoring - Milton Grey 71.00 wk - 59,669 59,669

MBE Foreman - Gavin Grey 71.00 wk - 153,695 153,695

Teaming Mgmt 213,364 213,364

1300.010 Personnel: Supervision

Superintendent 71.00 wk 238,674 - 238,674

Asst. Superintendent 63.00 wk 148,252 - 148,252

Personnel: Supervision 386,925 386,925

1310.010 Personnel: Proj. Managmnt

Project Executive 65.00 wk 98,327 - 98,327

Senior Project Manager 71.00 wk 270,512 - 270,512

Assistant Project Manager 71.00 wk 179,005 - 179,005

LEED Assistant Project Manager 63.00 wk 67,768 - 67,768

Project Coordinator 71.00 wk 143,193 - 143,193

Accounting 71.00 wk 31,950 - 31,950

Executive Assistant 65.00 wk 31,379 - 31,379

Personnel: Proj. Managmnt 822,134 822,134

CONSTRUCTION PHASE

FEE

1,209,060 213,364 1,422,424

Estimate Totals

Description Amount

Labor 1,209,060

Subcontract 213,364

TOTAL 1,422,424

Name/Title % Time Hours/Week Rate/Hour

Duration in

Weeks Total

Snowden Hernandez, Senior Project Manager 100% 40 95.25 71 $270,512

Jim Kleen II, Assistant Project Manager 100% 40 63.03 71 $179,005

Berretta Davis, Project Coordinator 100% 40 50.42 71 $143,193

Rusty Boatwright, Superintendent 100% 40 84.04 71 $238,674

David Smith, Assistant Superintendent 100% 40 58.83 63 $148,252

Gavin Grey, Foreman 100% 40 54.118 71 $153,695

Name/Title % Time Hours/Week Rate/Hour

Duration in

Weeks Total

James E. Kleen, V.P. of Education 30% 12 126.06 65 $98,327

Robyn Chamberlain, Executive Asst 30% 12 40.23 65 $31,379

Cathy Longworth, Accounting 25% 10 45.00 71 $31,950

John Banting, LEED Assistant Project Manager 40% 16 67.23 63 $67,768

Milton Grey, CM Consultant 20% 8 105.05 71 $59,669

TOTAL $1,422,424

PHASE II EXHIBIT D

PERSONNEL ASSIGNED DURING CONSTRUCTION

SUMMARY OF CONSTRUCTION PHASE FEES

NORTHBORO ELEMENTARY MODERNIZATION

PROJECT NO.: 0291-7504

PHASE II EXHIBIT E CONSTRUCTION MANAGER’S STAFF PER DIEM FOR TIME EXTENSIONS

PROJECT NAME: NORTHBORO ELEMENTARY MODERNIZATION

PROJECT NO.: 0291-7504

Name/Title Hrs/Day Rate/Hr. Per Diem Rate Snowden Hernandez 8 95.25 $762.01 Sr. Project Manager Jim Kleen II 8 63.03 $504.24 Assistant Project Manager Rusty Boatwright 8 84.04 $672.32 Superintendent Berretta Davis 8 50.42 $403.36 Project Coordinator Gavin Grey 8 54.118 $432.95 Foreman Total Per Diem $ 2,774.88

PHASE II EXHIBIT F CONSTRUCTION TEAM ASSIGNED REPRESENTATIVES

PROJECT NAME: NORTHBORO ELEMENTARY MODERNIZATION

PROJECT NO.: 0291-7504 Owner: School District of Palm Beach County 3300 Summit Blvd West Palm Beach, FL 33406 Owner’s Authorized Representative: Glen Armbruster, Sr. Projects Administrator 3300 Summit Blvd West Palm Beach, FL 33406 Construction Manager: Hedrick Brothers Construction Co., Inc. 2200 Centre Park West Drive, Ste 100 West Palm Beach, FL 33409 Contact: Snowden Hernandez Architect - Engineer: BRPH ARCHITECTS, ENGINEERS,

CONSTRUCTORS 1475 Centrepark Blvd West Palm Beach, FL 33401 Contact: Leila Rouady

Northboro Elementary School Modernization Project # 07-609-01 Hedrick Brothers Construction Co., Inc.

400 40th Street West Palm Beach, FL 33407 Tel: 561-689-8880 Fax: 561-689-8860

West Palm Beach, FL 33407

COVER

Drawing Number Rev # Rev Date Title % Complete Status Category

C-000 0 6/6/2008 Cover Sheet 100 GMP Phase 2 Construction Set

GENERAL, LIFE SAFETY AND SIGNAGE

Drawing Number Rev # Rev Date Title % Complete Status Category

G-101 1 7/31/2008 Life Safety - Site Plan - Narrative 100 GMP Phase 2 Construction Set

G-102 1 7/31/2008 Life Safety - Composite Plans 100 GMP Phase 2 Construction Set

G-103 1 7/31/2008 Life Safety - Bldg 1 100 GMP Phase 2 Construction Set

G-104 1 7/31/2008 Life Safety - Bldg 2 First Floor 100 GMP Phase 2 Construction Set

G-105 1 7/31/2008 Life Safety - Bldg 2 Second Floor 100 GMP Phase 2 Construction Set

G-106 1 7/31/2008 Life Safety - Bldg 3 First Floor 100 GMP Phase 2 Construction Set

G-107 1 7/31/2008 Life Safety - Bldg 3 Second Floor 100 GMP Phase 2 Construction Set

G-108 1 7/31/2008 Signage Plan - Bldg 1 100 GMP Phase 2 Construction Set

G-109 1 7/31/2008 Signage Plan - Bldg 2 100 GMP Phase 2 Construction Set

G-110 0 6/6/2008 Signage Plan - Bldg 3 100 GMP Phase 2 Construction Set

SURVEY

Drawing Number Rev # Rev Date Title % Complete Status Category

SUR-1 0 6/6/2008 SFRN Survey 100 GMP Phase 2 Construction Set

SUR-2 0 6/6/2008 SFRN Survey 100 GMP Phase 2 Construction Set

CIVILS

Drawing Number Rev # Rev Date Title % Complete Status Category

C-100 0 6/6/2008 Cover Sheet - Civil 100 GMP Phase 2 Construction Set

C-101 1 7/31/2008 Demolition Plan 100 GMP Phase 2 Construction Set

C-102 1 7/31/2008 Stormwater Pollution Prevention Plan 100 GMP Phase 2 Construction Set

C-103 1 7/31/2008 Drainage Map 100 GMP Phase 2 Construction Set

C-104 1 7/31/2008 Horizontal Dimensioning Plan 100 GMP Phase 2 Construction Set

C-105 1 7/31/2008 Grading, Paving & Drainage Plan 100 GMP Phase 2 Construction Set

C-106 1 7/31/2008 Water & Wastewater Plan 100 GMP Phase 2 Construction Set

2200 CENTREPARK WEST DRIVE, SUITE 100

MAIN: 561-689-8880 FAX: 561-689-8860

CURRENT DRAWING LISTWEST PALM BEACH, FL 33409

Page 1 of 8

Northboro Elementary School Modernization Project # 07-609-01 Hedrick Brothers Construction Co., Inc.

400 40th Street West Palm Beach, FL 33407 Tel: 561-689-8880 Fax: 561-689-8860

West Palm Beach, FL 33407

2200 CENTREPARK WEST DRIVE, SUITE 100

MAIN: 561-689-8880 FAX: 561-689-8860

CURRENT DRAWING LISTWEST PALM BEACH, FL 33409

C-107 1 7/31/2008 Signage & Pavement Marking Plan 100 GMP Phase 2 Construction Set

C-108 1 7/31/2008 Grading, Paving & Drainage Details 100 GMP Phase 2 Construction Set

C-109 1 7/31/2008 Grading, Paving & Drainage Details 100 GMP Phase 2 Construction Set

C-110 0 6/6/2008 Water Details 100 GMP Phase 2 Construction Set

C-111 0 6/6/2008 Water & Wastewater Details 100 GMP Phase 2 Construction Set

C-112 1 7/31/2008 Wastewater Details & Profile 100 GMP Phase 2 Construction Set

LANDSCAPE AND IRRIGATION

Drawing Number Rev # Rev Date Title % Complete Status Category

LA-1 0 6/6/2008 Tree Alteration Plan 100 GMP Phase 2 Construction Set

LA-2 0 6/6/2008 Tree Alteration Plan 100 GMP Phase 2 Construction Set

LA-3 1 7/31/2008 Landscape Plan 100 GMP Phase 2 Construction Set

LA-4 1 7/31/2008 Landscape Plan 100 GMP Phase 2 Construction Set

LA-5 0 6/6/2008 Landscape Plan 100 GMP Phase 2 Construction Set

LA-6 1 7/31/2008 Landscape Plan 100 GMP Phase 2 Construction Set

IR-1 1 7/31/2008 Irrigation Plan 100 GMP Phase 2 Construction Set

IR-2 1 7/31/2008 Irrigation Legend & Details 100 GMP Phase 2 Construction Set

IR-3 1 7/31/2008 Rainwater Tank & Pump Details 100 GMP Phase 2 Construction Set

STRUCTURAL

Drawing Number Rev # Rev Date Title % Complete Status Category

S-001 0 6/6/2008 Design Information & General Notes 100 GMP Phase 2 Construction Set

S-101 1 7/31/2008 Foundation Layout Building 1 100 GMP Phase 2 Construction Set

S-102 1 7/31/2008 Foundation Layout Building 2 100 GMP Phase 2 Construction Set

S-103 1 7/31/2008 Foundation Layout Building 3 100 GMP Phase 2 Construction Set

S-113 1 7/31/2008 2nd Floor Framing Plan Building 3 100 GMP Phase 2 Construction Set

S-121 1 7/31/2008 Roof Framing Plan Building 1 100 GMP Phase 2 Construction Set

S-123 1 7/31/2008 Roof Framing Plan Building 3 100 GMP Phase 2 Construction Set

S-131 1 7/31/2008 Mansard Framing Plan Building 1 100 GMP Phase 2 Construction Set

S-133 1 7/31/2008 Mansard Framing Plan Building 3 100 GMP Phase 2 Construction Set

S-501 1 7/31/2008 Foundation Details 100 GMP Phase 2 Construction Set

S-502 1 7/31/2008 Foundation Details 100 GMP Phase 2 Construction Set

Page 2 of 8

Northboro Elementary School Modernization Project # 07-609-01 Hedrick Brothers Construction Co., Inc.

400 40th Street West Palm Beach, FL 33407 Tel: 561-689-8880 Fax: 561-689-8860

West Palm Beach, FL 33407

2200 CENTREPARK WEST DRIVE, SUITE 100

MAIN: 561-689-8880 FAX: 561-689-8860

CURRENT DRAWING LISTWEST PALM BEACH, FL 33409

S-511 1 7/31/2008 Floor Framing Details 100 GMP Phase 2 Construction Set

S-512 1 7/31/2008 Framing Details 100 GMP Phase 2 Construction Set

S-521 1 7/31/2008 Roof Framing Details 100 GMP Phase 2 Construction Set

ARCHITECTURAL

Drawing Number Rev # Rev Date Title % Complete Status Category

A-001 1 7/31/2008 Demolition Plan - Bldg 2 First Floor 100 GMP Phase 2 Construction Set

A-002 0 6/6/2008 Demolition Plan - Bldg 2 Second Floor 100 GMP Phase 2 Construction Set

A-003 1 7/31/2008 Site Plan - Overall 100 GMP Phase 2 Construction Set

A-004 1 7/31/2008 Site Plan - Partial 100 GMP Phase 2 Construction Set

A-005 1 7/31/2008 Site Plan - Partial 100 GMP Phase 2 Construction Set

A-102 1 7/31/2008 Floor Plan - Bldg 1 100 GMP Phase 2 Construction Set

A-103 1 7/31/2008 Floor Plan - Bldg 2 First Floor 100 GMP Phase 2 Construction Set

A-104 1 7/31/2008 Floor Plan - Bldg 2 Second Floor 100 GMP Phase 2 Construction Set

A-105 1 7/31/2008 Floor Plan - Bldg 3 First Floor 100 GMP Phase 2 Construction Set

A-106 1 7/31/2008 Floor Plan - Bldg 3 Second Floor 100 GMP Phase 2 Construction Set

A-107 1 7/31/2008 Floor Plan - Courtyard 100 GMP Phase 2 Construction Set

A-108 1 7/31/2008 RCP Plan - Bldg 1 100 GMP Phase 2 Construction Set

A-109 1 7/31/2008 RCP Plan - Bldg 2 First Floor 100 GMP Phase 2 Construction Set

A-110 1 7/31/2008 RCP Plan - Bldg 2 Ssecond Floor 100 GMP Phase 2 Construction Set

A-111 0 6/6/2008 RCP Plan - Bldg 3 First Floor 100 GMP Phase 2 Construction Set

A-112 1 7/31/2008 RCP Plan - Bldg 3 Second Floor 100 GMP Phase 2 Construction Set

A-113 1 7/31/2008 Roof Plan - Bldg 1 100 GMP Phase 2 Construction Set

A-114 1 7/31/2008 Roof Plan - Bldg 2 100 GMP Phase 2 Construction Set

A-115 1 7/31/2008 Roof Plan - Bldg 3 100 GMP Phase 2 Construction Set

A-116 1 7/31/2008 FF&E Plan - Bldg 1 100 GMP Phase 2 Construction Set

A-117 1 7/31/2008 FF&E Plan - Bldg 2 First Floor 100 GMP Phase 2 Construction Set

A-118 1 7/31/2008 FF&E Plan - Bldg 2 Second Floor 100 GMP Phase 2 Construction Set

A-119 1 7/31/2008 FF&E Plan - Bldg 3 First Floor 100 GMP Phase 2 Construction Set

A-120 1 7/31/2008 FF&E Plan - Bldg 3 Second Floor 100 GMP Phase 2 Construction Set

A-201 0 6/6/2008 Perspectives 100 GMP Phase 2 Construction Set

A-202 1 7/31/2008 Exterior Elevations 100 GMP Phase 2 Construction Set

Page 3 of 8

Northboro Elementary School Modernization Project # 07-609-01 Hedrick Brothers Construction Co., Inc.

400 40th Street West Palm Beach, FL 33407 Tel: 561-689-8880 Fax: 561-689-8860

West Palm Beach, FL 33407

2200 CENTREPARK WEST DRIVE, SUITE 100

MAIN: 561-689-8880 FAX: 561-689-8860

CURRENT DRAWING LISTWEST PALM BEACH, FL 33409

A-203 1 7/31/2008 Exterior Elevations 100 GMP Phase 2 Construction Set

A-204 1 7/31/2008 Exterior Elevations 100 GMP Phase 2 Construction Set

A-205 1 7/31/2008 Exterior Elevations 100 GMP Phase 2 Construction Set

A-206 0 6/6/2008 Exterior Elevations 100 GMP Phase 2 Construction Set

A-301 1 7/31/2008 Building Sections - Bldg 1 100 GMP Phase 2 Construction Set

A-302 0 6/6/2008 Building Sections - Bldg 3 100 GMP Phase 2 Construction Set

A-303 1 7/31/2008 Wall Sections 100 GMP Phase 2 Construction Set

A-304 1 7/31/2008 Wall Sections 100 GMP Phase 2 Construction Set

A-305 1 7/31/2008 Wall Types 100 GMP Phase 2 Construction Set

A-306 1 7/31/2008 Wall Types 100 GMP Phase 2 Construction Set

A-401 1 7/31/2008 Enlarged Interior Plans 100 GMP Phase 2 Construction Set

A-402 1 7/31/2008 Enlarged Interior Plans 100 GMP Phase 2 Construction Set

A-403 1 7/31/2008 Enlarged Plans 100 GMP Phase 2 Construction Set

A-404 1 7/31/2008 Enlarged Plans - Toilets 100 GMP Phase 2 Construction Set

A-405 0 6/6/2008 Enlarged Plans - Toilets 100 GMP Phase 2 Construction Set

A-406 1 7/31/2008 Enlarged Plans - Stairs 100 GMP Phase 2 Construction Set

A-407 1 7/31/2008 Enlarged Plans - Stairs 100 GMP Phase 2 Construction Set

A-408 1 7/31/2008 Enlarged Plans - Elevator 100 GMP Phase 2 Construction Set

A-409 0 6/6/2008 Enlarged Plans - Canopy (Site) 100 GMP Phase 2 Construction Set

A-411 1 7/31/2008 Millwork 100 GMP Phase 2 Construction Set

A-412 1 7/31/2008 Millwork 100 GMP Phase 2 Construction Set

A-501 1 7/31/2008 Site Details - Canopy Plans 100 GMP Phase 2 Construction Set

A-502 1 7/31/2008 Site Details 100 GMP Phase 2 Construction Set

A-503 1 7/31/2008 Site Details 100 GMP Phase 2 Construction Set

A-504 1 7/31/2008 Site Details - Exterior Courtyard 100 GMP Phase 2 Construction Set

A-505 1 7/31/2008 Details - Doors 100 GMP Phase 2 Construction Set

A-506 0 6/6/2008 Details - Doors 100 GMP Phase 2 Construction Set

A-507 1 7/31/2008 Details - Windows 100 GMP Phase 2 Construction Set

A-508 1 7/31/2008 Details - Roof 100 GMP Phase 2 Construction Set

A-509 1 7/31/2008 Details - Roof 100 GMP Phase 2 Construction Set

A-510 0 6/6/2008 Column Details 100 GMP Phase 2 Construction Set

A-511 0 6/6/2008 Details - Ceilings 100 GMP Phase 2 Construction Set

Page 4 of 8

Northboro Elementary School Modernization Project # 07-609-01 Hedrick Brothers Construction Co., Inc.

400 40th Street West Palm Beach, FL 33407 Tel: 561-689-8880 Fax: 561-689-8860

West Palm Beach, FL 33407

2200 CENTREPARK WEST DRIVE, SUITE 100

MAIN: 561-689-8880 FAX: 561-689-8860

CURRENT DRAWING LISTWEST PALM BEACH, FL 33409

A-512 1 7/31/2008 Details 100 GMP Phase 2 Construction Set

A-513 1 7/31/2008 Details - Play Court Stripping 100 GMP Phase 3 Construction Set

A-514 1 7/31/2008 Site Details 100 GMP Phase 4 Construction Set

A-601 1 7/31/2008 Schedule - Door 100 GMP Phase 2 Construction Set

A-602 1 7/31/2008 Schedule - Finish 100 GMP Phase 2 Construction Set

FOOD SERVICES

Drawing Number Rev # Rev Date Title % Complete Status Category

FS-001 1 7/31/2008 Food Service Equipment Layout 100 GMP Phase 2

FS-002 1 7/31/2008 Food Service Electrical Plan 100 GMP Phase 2

FS-003 1 7/31/2008 Food Service Plumbing Plan 100 GMP Phase 2

FS-004 1 7/31/2008 Food Service Special Conditions Plan 100 GMP Phase 2

FIRE PROTECTION

Drawing Number Rev # Rev Date Title % Complete Status Category

FP-001 1 7/31/2008 Notes, Abbreviations & Symbols 100 GMP Phase 2 Construction Set

FP-101 1 7/31/2008 Fire Protection Plan - Bldg 1 & 2 100 GMP Phase 2 Construction Set

FP-102 0 6/6/2008 Fire Protection Plan - Bldg 3 100 GMP Phase 2 Construction Set

PLUMBING

Drawing Number Rev # Rev Date Title % Complete Status Category

P-001 0 6/6/2008 Notes, Abbreviations & Symbols 100 GMP Phase 2 Construction Set

P-101 1 7/31/2008 Plumbing Plan - Bldg 1 100 GMP Phase 2 Construction Set

P-102 1 7/31/2008 Plumbing Demo Plan - Bldg 2 - 1st Floor 100 GMP Phase 2 Construction Set

P-103 0 6/6/2008 Plumbing Demo Plan - Bldg 2 - 2nd Floor 100 GMP Phase 2 Construction Set

P-104 1 7/31/2008 Plumbing Plan - Bldg 2 - 1st Floor 100 GMP Phase 2 Construction Set

P-105 0 6/6/2008 Plumbing Plan - Bldg 2 - 2nd Floor 100 GMP Phase 2 Construction Set

P-106 1 7/31/2008 Plumbing Plan - Bldg 3 - 1st Floor 100 GMP Phase 2 Construction Set

P-107 1 7/31/2008 Plumbing Plan - Bldg 3 - 2nd Floor 100 GMP Phase 2 Construction Set

P-401 0 6/6/2008 Kithcen Plumbing Plan 100 GMP Phase 2 Construction Set

P-501 1 7/31/2008 Plumbing Details 100 GMP Phase 2 Construction Set

P-502 1 7/31/2008 Plumbing Details 100 GMP Phase 2 Construction Set

Page 5 of 8

Northboro Elementary School Modernization Project # 07-609-01 Hedrick Brothers Construction Co., Inc.

400 40th Street West Palm Beach, FL 33407 Tel: 561-689-8880 Fax: 561-689-8860

West Palm Beach, FL 33407

2200 CENTREPARK WEST DRIVE, SUITE 100

MAIN: 561-689-8880 FAX: 561-689-8860

CURRENT DRAWING LISTWEST PALM BEACH, FL 33409

P-601 1 7/31/2008 Plumbing Schedule 100 GMP Phase 2 Construction Set

P-901 1 7/31/2008 Riser Diagrams - Building 1 100 GMP Phase 2 Construction Set

P-902 1 7/31/2008 Riser Diagrams - Building 2 100 GMP Phase 2 Construction Set

P-903 1 7/31/2008 Sanitary Riser Diagram - Building 3 100 GMP Phase 2 Construction Set

P-904 1 7/31/2008 Water Riser Diagram - Building 3 100 GMP Phase 2 Construction Set

MECHANICAL

Drawing Number Rev # Rev Date Title % Complete Status Category

M-001 0 6/6/2008 Notes, Abbreviations & Symbols 100 GMP Phase 2 Construction Set

M-003 1 7/31/2008 Mechanical Site Plan 100 GMP Phase 2 Construction Set

M-004 1 7/31/2008 Mechanical Roof Plan 100 GMP Phase 2 Construction Set

M-101 1 7/31/2008 Mechanical Plan - Bldg 1 100 GMP Phase 2 Construction Set

M-102 0 6/6/2008 Mechanical Demo Plan - Bldg 2 - 1st Floor 100 GMP Phase 2 Construction Set

M-103 0 6/6/2008 Mechanical Demo Plan - Bldg 2 - 2nd Floor 100 GMP Phase 2 Construction Set

M-104 1 7/31/2008 Mechanical Plan - Bldg 2 - 1st Floor 100 GMP Phase 2 Construction Set

M-105 1 7/31/2008 Mechanical Plan - Bldg 2 - 2nd Floor 100 GMP Phase 2 Construction Set

M-106 1 7/31/2008 Mechanical Plan - Bldg 3 - 1st Floor 100 GMP Phase 2 Construction Set

M-107 1 7/31/2008 Mechanical Plan - Bldg 3 - 2nd Floor 100 GMP Phase 2 Construction Set

M-401 1 7/31/2008 Enlarged Mechanical Room Plans 100 GMP Phase 2 Construction Set

M-402 0 6/6/2008 Enlarged Mechanical Room Plans 100 GMP Phase 2 Construction Set

M-403 0 6/6/2008 Enlarged Mechanical Room Plans 100 GMP Phase 2 Construction Set

M-404 0 6/6/2008 Enlarged Mechanical Room Plans 100 GMP Phase 2 Construction Set

M-501 1 7/31/2008 Mechanical Details 100 GMP Phase 2 Construction Set

M-502 1 7/31/2008 Mechanical Details 100 GMP Phase 2 Construction Set

M-503 1 7/31/2008 Mechanical Details 100 GMP Phase 2 Construction Set

M-601 1 7/31/2008 Mechanical Schedules 100 GMP Phase 2 Construction Set

M-602 1 7/31/2008 Mechanical Schedules 100 GMP Phase 2 Construction Set

M-603 1 7/31/2008 Mechanical Schedules 100 GMP Phase 2 Construction Set

M-604 0 6/6/2008 Chilled Water Flow Diagram 100 GMP Phase 2 Construction Set

M-701 0 6/6/2008 Mechanical Controls 100 GMP Phase 2 Construction Set

M-702 1 7/31/2008 Mechanical Controls 100 GMP Phase 2 Construction Set

M-703 1 7/31/2008 Mechanical Controls 100 GMP Phase 2 Construction Set

Page 6 of 8

Northboro Elementary School Modernization Project # 07-609-01 Hedrick Brothers Construction Co., Inc.

400 40th Street West Palm Beach, FL 33407 Tel: 561-689-8880 Fax: 561-689-8860

West Palm Beach, FL 33407

2200 CENTREPARK WEST DRIVE, SUITE 100

MAIN: 561-689-8880 FAX: 561-689-8860

CURRENT DRAWING LISTWEST PALM BEACH, FL 33409

ELECTRICAL

Drawing Number Rev # Rev Date Title % Complete Status Category

E-001 1 7/31/2008 Legend & Abbreviations 100 GMP Phase 2 Construction Set

E-002 0 6/6/2008 General Notes 100 GMP Phase 2 Construction Set

E-101 1 7/31/2008 Site Lighting & Photometric Plan 100 GMP Phase 2 Construction Set

E-102 1 7/31/2008 Site Power & Systems 100 GMP Phase 2 Construction Set

E-103 0 6/6/2008 Site Canopy Plan 100 GMP Phase 2 Construction Set

E-104 1 7/31/2008 Building 1 Lighting Plan 100 GMP Phase 2 Construction Set

E-105 1 7/31/2008 Building 1 Power Plan 100 GMP Phase 2 Construction Set

E-106 1 7/31/2008 Building 1 Systems Plan 100 GMP Phase 2 Construction Set

E-107 0 6/6/2008 Building 2 First Demo 100 GMP Phase 2 Construction Set

E-108 1 7/31/2008 Building 2 First Floor Lighting Plan 100 GMP Phase 2 Construction Set

E-109 1 7/31/2008 Building 2 First Floor Power Plan 100 GMP Phase 2 Construction Set

E-110 1 7/31/2008 Building 2 First Floor Systems Plan 100 GMP Phase 2 Construction Set

E-111 0 6/6/2008 Building 2 Second Floor Demo 100 GMP Phase 2 Construction Set

E-112 0 6/6/2008 Building 2 Second Floor Lighting Plan 100 GMP Phase 2 Construction Set

E-113 0 6/6/2008 Building 2 Second Floor Power Plan 100 GMP Phase 2 Construction Set

E-114 1 7/31/2008 Building 2 Second Floor Systems Plan 100 GMP Phase 2 Construction Set

E-115 1 7/31/2008 Building 3 First Floor Lighting Plan 100 GMP Phase 2 Construction Set

E-116 1 7/31/2008 Building 3 First Floor Power Plan 100 GMP Phase 2 Construction Set

E-117 1 7/31/2008 Building 3 First Floor Systems Plan 100 GMP Phase 2 Construction Set

E-118 1 7/31/2008 Building 3 Second Floor Lighting Plan 100 GMP Phase 2 Construction Set

E-119 1 7/31/2008 Building 3 Second Floor Power Plan 100 GMP Phase 2 Construction Set

E-120 1 7/31/2008 Building 3 Second Floor Systems Plan 100 GMP Phase 2 Construction Set

E-501 0 6/6/2008 Enlargements 100 GMP Phase 2 Construction Set

E-502 1 7/31/2008 Enlargements 100 GMP Phase 2 Construction Set

E-503 0 6/6/2008 Enlargements 100 GMP Phase 2 Construction Set

E-504 1 7/31/2008 Enlargements 100 GMP Phase 2 Construction Set

E-601 1 7/31/2008 Partial Electrical One-Line Diagram 100 GMP Phase 2 Construction Set

E-602 0 6/6/2008 Partial Electrical One Line Diagram 100 GMP Phase 2 Construction Set

E-701 1 7/31/2008 Intercom Riser Diagram 100 GMP Phase 2 Construction Set

Page 7 of 8

Northboro Elementary School Modernization Project # 07-609-01 Hedrick Brothers Construction Co., Inc.

400 40th Street West Palm Beach, FL 33407 Tel: 561-689-8880 Fax: 561-689-8860

West Palm Beach, FL 33407

2200 CENTREPARK WEST DRIVE, SUITE 100

MAIN: 561-689-8880 FAX: 561-689-8860

CURRENT DRAWING LISTWEST PALM BEACH, FL 33409

E-702 1 7/31/2008 TV & Data Riser Diaagram 100 GMP Phase 2 Construction Set

E-703 1 7/31/2008 Security Riser Diagram 100 GMP Phase 2 Construction Set

E-704 0 6/6/2008 Fire Alarm Riser Diagram 100 GMP Phase 2 Construction Set

E-705 0 6/6/2008 EMCS Riser Diagram 100 GMP Phase 2 Construction Set

E-801 1 7/31/2008 Voice Data & Card Access Details 100 GMP Phase 2 Construction Set

E-802 0 6/6/2008 Details 100 GMP Phase 2 Construction Set

E-803 1 7/31/2008 Video Surveillance Systems Details 100 GMP Phase 2 Construction Set

E-804 0 6/6/2008 Details 100 GMP Phase 2 Construction Set

E-805 0 6/6/2008 Classroom Projector Wiring Detail 100 GMP Phase 2 Construction Set

E-806 0 6/6/2008 Cafeteria-Media Projector Wiring Detail 100 GMP Phase 2 Construction Set

E-807 0 6/6/2008 Details 100 GMP Phase 2 Construction Set

E-901 1 7/31/2008 Schedules 100 GMP Phase 2 Construction Set

E-902 1 7/31/2008 Schedules 100 GMP Phase 2 Construction Set

E-903 1 7/31/2008 Schedules 100 GMP Phase 2 Construction Set

E-904 1 7/31/2008 Schedules 100 GMP Phase 2 Construction Set

E-905 1 7/31/2008 Schedules 100 GMP Phase 2 Construction Set

E-906 1 7/31/2008 Schedules 100 GMP Phase 2 Construction Set

Page 8 of 8

NORTHBORO ELEMENTARY SCHOOL

BRPH ARCHITECTS/ENGINEERS, INC.TABLE OF CONTENTS

DIVISION 1 - GENERAL REQUIREMENTS

Section 01010 Summary of Work 06.16.08

Section 01027 Applications for Payment 06.09.08

Section 01028 Modification Requirements 06.09.08

Section 01039 Coordination and Meetings 06.16.08

Section 01045 Cutting and Patching 06.09.08

Section 01060 Regulatory Requirements 06.16.08

Section 01120 Alteration Project Procedures 06.09.08

Section 01300 Submittals Procedures 06.16.08

Section 01311 Network Analysis Schedules 06.09.08

Section 01351 Construction Waste Management 06.09.08

Section 01353 Noise and Acoustics Management 06.09.08

Section 01354 Environmental Management 06.16.08

Section 01400 Quality Control 06.16.08

Section 01410 Testing Laboratory Services 06.09.08

Section 01421 References 06.16.08

Section 01500 Construction Facilities and Temporary Controls 06.09.08

Section 01540 Security 06.09.08

Section 01560 Temporary Controls 06.09.08

Section 01600 Material, Equipment, and Approved Equals 06.16.08

Section 01611 Environmental Requirements for Products 06.16.08

Section 01650 Starting of Systems 06.09.08

Section 01700 Contract Closeout 06.16.08

Section 01730 Operation and Maintenance Data 06.16.08

Section 01740 Warranties 06.16.08

Section 01810 Commissioning 06.09.08

Section 01811 Sustainable Design Requirements 06.09.08

TECHNICAL SPECIFICATIONS

5859.01 1

NORTHBORO ELEMENTARY SCHOOL

BRPH ARCHITECTS/ENGINEERS, INC.TABLE OF CONTENTS

DIVISION 2 - SITE WORK

Section 02060 Building Demoliton 06.09.08

Section 02070 Selective Demolition 06.09.08

Section 02110 Site Clearing 06.09.08

Section 02200 Earth Moving 06.09.08

Section 02400 Asphalt Paving 06.09.08

Section 02520 Concrete Paving 06.09.08

Section 02580 Pavement Marking 06.09.08

Section 02660 Water Distribution System 06.09.08

Section 02700 Storm Drainage Utilities 06.09.08

Section 02730 Sanitary Sewerage Utilities 06.09.08

Section 02810 Underground Irrigation System 06.09.08

Section 02853 Parking Bumpers 06.09.08

Section 02938 Grass Sodding 06.09.08

Section 02950 Trees, Plants, and Ground Cover 06.09.08

5859.01 2

NORTHBORO ELEMENTARY SCHOOL

BRPH ARCHITECTS/ENGINEERS, INC.TABLE OF CONTENTS

DIVISION 3 – CONCRETE

Section 03100 Concrete Formwork 06.09.08

Section 03200 Concrete Reinforcement 06.09.08

Section 03300 Cast-in-Place Concrete 06.09.08

Section 03341 Fibrous Concrete Reinforcing 06.09.08

Section 03346 Concrete Floor Finishing 06.09.08

Section 03521 Lightweight Insulating Concrete 06.09.08

DIVISION 4 – MASONRY

Section 04100 Masonry Mortar and Grout 06.09.08

Section 04300 Masonry Unit 06.09.08

Section 04340 Reinforced Masony Unit 06.09.08

DIVISION 5 – METALS

Section 05120 Structural Steel 06.09.08

Section 05210 Steel Joists and Joist Girders 06.09.08

Section 05310 Steel Deck 06.09.08

Section 05400 Cold Formed Metal Framing 06.09.08

Section 05500 Metal Fabrications 06.09.08

Section 05510 Metal Stairs 06.09.08

Section 05520 Metal Railings 06.09.08

5859.01 3

NORTHBORO ELEMENTARY SCHOOL

BRPH ARCHITECTS/ENGINEERS, INC.TABLE OF CONTENTS

DIVISION 6 – WOOD AND PLASTICS

Section 06100 Rough Carpentry 06.09.08

Section 06410 Custom Casework 06.16.08

DIVISION 7 – THERMAL AND MOISTURE PROTECTION

Section 07120 Fluid Applied Waterproofing 06.16.08

Section 07160 Bituminous Dampproofing 06.16.08

Section 07170 Bentonite Waterproofing 06.09.08

Section 07181 Water Repellent Penetrant 06.16.08

Section 07191 Vapor Retarders 06.16.08

Section 07212 Extruded Polystyrene Board Insulation 06.16.08

Section 07213 Batt Insulation 06.16.08

Section 07214 Foamed-in-Place Insulation 06.09.08

Section 07255 Cementitious Fireproofing 06.09.08

Section 07270 Firestopping 06.09.08

Section 07341 Metal Shake Roof SystemADDED REV. 1

(7/31/08)

Section 07536 Modified Bitumen Roofing System 06.09.08

Section 07610 Standing Seam Roof and Wall Panels 06.16.08

Section 07615 Metal Roof PanelsADDED REV. 1

(7/31/08)

Section 07620 Flashing, Gutters, Downspouts, and Other Accessories 06.16.08

Section 07724 Roof Hatches 06.09.08

Section 07900 Joint Sealants 06.16.08

DIVISION 8 – DOORS AND WINDOWS

Section 08110 Metal Doors and Frames 06.16.08

Section 08210 Solid Core Wood Doors 06.16.08

Section 08305 Access Doors/Hatches 06.16.08

Section 08331 Rolling Service Doors 06.16.08

Section 08520 Aluminum Windows 06.16.08

Section 08710 Door Hardware 06.16.08

Section 08800 Glazing 06.09.08

DIVISION 9 – FINISHES

Section 09111 Metal Stud Framing System 06.16.08

Section 09220 Portland Cement Plaster 06.16.08

Section 09250 Gypsum Board Systems 06.16.08

Section 09311 Ceramic Tile 06.16.08

Section 09330 Quarry Tile 06.16.08

Section 09511 Suspended Acoustical Ceiling System 06.16.08

Section 09520 Acoustical Wall Panels 06.16.08

Section 09610 Stain Finishing for Concrete Floors 06.09.08

Section 09650 Resilient Flooring 06.16.08

Section 09656 Resilient Terrazzo Tile 06.09.08

Section 09682 Carpet Modular 06.16.08

Section 09705 Epoxy Resin Composition Flooring 06.09.08

Section 09840 Acoustical Wall Treatment 06.09.08

Section 09900 Painting 06.19.08

Section 09963 Interior Acrylic Texture Coating 06.16.08

5859.01 4

NORTHBORO ELEMENTARY SCHOOL

BRPH ARCHITECTS/ENGINEERS, INC.TABLE OF CONTENTS

DIVISION 10 – SPECIALTIES

Section 10100 Marker Boards, Tack Boards, and Walk-off Logo Mats 06.16.08

Section 10171 Toilet Compartments, Urinal Screens, Shower Cubicles 06.16.08

Section 10196 Cubicle Curtains 06.09.08

Section 10211 Fixed Metal Wall Louvers 06.16.08

Section 10250 Door and Wall Protection 06.09.08

Section 10260 Wall Protection Systems 06.09.08

Section 10350 Flagpoles 06.09.08

Section 10415 Display Cases 06.09.08

Section 10420 Plaque 06.16.08

Section 10441 Signage 06.09.08

Section 10508 General/Corridor Lockers 06.09.08

Section 10522 Fire Extinguishers, Cabinets, and Accessories 06.09.08

Section 10532 Aluminum Walkway Covers 06.16.08

Section 10605 Wire Mesh Partitions 06.16.08

Section 10675 Metal Shelving 06.16.08

Section 10700 Window Solar ShadeDELETED REV. 1

(7/31/08)

Section 10800 Toilet and Bath Accessories 06.16.08

Section 10900 Synthetic TurfADDED REV. 1

(7/31/08)

DIVISION 11 – EQUIPMENT

Section 11026 Safe 06.09.08

Section 11050 Library Steel Bookstack Shelving 06.09.08

Section 11062 Stage Curtains - Cotton 06.09.08

Section 11063 Stage Curtains - Polyester 06.09.08

Section 11131 Projection Screens 06.16.08

Section 11400 Foodservice Equipment 06.09.08

Section 11450 Residential Appliances 06.16.08

Section 11480 Athletic Equipment REV. 1 (7/31/08)

Section 11515 Kilns 06.09.08

DIVISION 12 – FURNISHINGS

Section 12345 Laboratory Casework and Equipment 06.09.08

Section 12500 Window Veritcal Blinds 06.16.08

DIVISION 13 - SPECIAL CONSTRUCTION

NOT USED

DIVISION 14 - CONVEYING SYSTEMS

Section 14245 Hydraulic Elevators - Passenger REV. 1 (7/31/08)

5859.01 5

NORTHBORO ELEMENTARY SCHOOL

BRPH ARCHITECTS/ENGINEERS, INC.TABLE OF CONTENTS

DIVISION 15 – MECHANICAL

Section 15000 Basic Mechanical Requirements 06.09.08

Section 15073 Minor HVAC Demolition 06.09.08

Section 15075 Minor Plumbing Demolition 06.09.08

Section 15135 Meters, Gages, and Thermometers for HVAC Piping 06.09.08

Section 15140 Hangers and Supports for Plumbing Piping 06.09.08

Section 15145 Hangers and Supports for HVAC Piping 06.09.08

Section 15170 Motor Requirements for HVAC 06.09.08

Section 15190 Identification for HVAC Piping and Equipment 06.09.08

Section 15242 HVAC Vibration Isolation 06.09.08

Section 15260 Plumbing Piping Insulation 06.09.08

Section 15280 HVAC Equipment Insulation 06.09.08

Section 15290 Ductwork Insulation 06.09.08

Section 15411 Facility Water Distribution 06.09.08

Section 15412 Facility Sanitary Distribution 06.09.08

Section 15413 Facility Storm Drainage 06.09.08

Section 15420 Plumbing Piping 06.09.08

Section 15430 Plumbing Specialties 06.09.08

Section 15440 Plumbing Fixtures 06.09.08

Section 15450 Plumbing Equipment 06.09.08

Section 15500 Fire Suppression 06.09.08

Section 15510 Hydronic Piping 06.09.08

Section 15515 Hydronic Specialties 06.09.08

Section 15535 Refrigeration Piping 06.09.08

Section 15540 HVAC Pumps 06.09.08

Section 15671 Air-Cooled Refrigerant Condensers 06.09.08

Section 15682 Air Cooled Water Chillers 06.09.08

Section 15765 Variable Frequency Motor Controls 06.09.08

Section 15801 HVAC Water Treatment 06.09.08

Section 15817 Electric Resistance Duct Heaters 06.09.08

Section 15855 Air Handling Units 06.09.08

Section 15870 HVAC Power Ventilators 06.09.08

Section 15885 HVAC Air Filters 06.09.08

Section 15890 Ductwork 06.09.08

Section 15895 Air Duct Accessories 06.09.08

Section 15900 Energy Management and Control System 06.09.08

Section 15930 Variable Air Volume Units 06.09.08

Section 15936 Grilles, Registers, Diffusers 06.09.08

Section 15990 Commissioning of HVAC Systems 06.09.08

Section 15991 HVAC Testing, Adjusting and Balancing 06.09.08

Section 15992 Tests – Plumbing Piping Systems 06.09.08

Section 15993 Tests – HVAC Piping Systems 06.09.08

5859.01 6

NORTHBORO ELEMENTARY SCHOOL

BRPH ARCHITECTS/ENGINEERS, INC.TABLE OF CONTENTS

DIVISION 16 – ELECTRICAL

Section 16010 Basic Electrical Requirements 06.09.08

Section 16020 Work Included 06.09.08

Section 16025 Codes, Fees, and Standards 06.09.08

Section 16050 Basic Materials and Methods 06.09.08

Section 16111 Conduit 06.09.08

Section 16112 Cable Trays 06.09.08

Section 16117 Manholes 06.09.08

Section 16123 Building Wire and Cable 06.09.08

Section 16130 Boxes 06.09.08

Section 16141 Wiring Devices 06.09.08

Section 16160 Cabinets and Enclosures 06.09.08

Section 16180 Equipment Wiring Systems 06.09.08

Section 16190 Supporting Devices 06.09.08

Section 16195 Electrical Identification 06.09.08

Section 16420 Service Entrance 06.09.08

Section 16425 Switchboards REV. 2 (9/15/08)

Section 16440 Disconnect Switches 06.09.08

Section 16450 Grounding 06.09.08

Section 16461 Dry Type Transformers 06.09.08

Section 16470 Panelboards 06.09.08

Section 16476 Enclosed Circuit Breakers 06.09.08

Section 16477 Fuses (600-Volt and Below) 06.09.08

Section 16480 Motor Control 06.09.08

Section 16485 Contactors 06.09.08

Section 16495 Transfer Switch 06.09.08

Section 16510 Interior Luminaries 06.09.08

Section 16530 Site Lighting 06.09.08

Section 16535 Emergency Lighting Equipment 06.09.08

Section 16610 Transient Voltage Surge Suppression 06.09.08

Section 16622 Packaged Engine Generator Systems 06.09.08

Section 16650 Energy Management and Control System 06.09.08

Section 16670 Lightning Protection Systems 06.09.08

Section 16721 Fire Alarm and Smoke Detection Systems 06.09.08

Section 16722 Intrusion Detection and Security Access System 06.09.08

Section 16723 Video Surveillance System 06.09.08

Section 16724 Emergency Radio Communications Systems 06.09.08

Section 16725 Access System 06.09.08

Section 16730 GPS Wireless Clock Systems 06.09.08

Section 16765 Intercom Systems 06.09.08

Section 16770 Public Address Systems 06.09.08

Section 16781 Master Television Antenna System (MTAS) 06.09.08

Section 16902 Electric Controls and Relays 06.09.08

Section 16905 Communications System (Data and Voice) 06.09.08

Section 16906 Ceiling Projector System REV. 1 (7/31/08)

Section 16995 Electrical Commissioning 06.09.08

5859.01 7

PHASE II EXHIBIT S LIST OF MAJOR SUBCONTRACTORS

PROJECT NAME: NORTHBORO ELEMENTARY MODERNIZATION

PROJECT NO.: 0291-7504

DIVISION OF WORK

Sitework Concrete

Metals Thermal & Moisture Protection Doors & Windows Doors & Windows Finishes

CORPORATE NAME & ADDRESS AMERICAN ENGINEERING & DEVELOPING 11765 W Okeechobee Rd. Hialeah Gardens, FL 33018 EAGLE METAL FABRICATORS, INC. 4300 SW 59th Ave Davie, FL 33460 STEEL FABRICATORS 3801 Dawes Ave West Palm Beach, FL 33460 HI-TECH ROOFING & SHEET METAL, INC. 2266 4th Ave North Lake Worth, 33461 STUART PAINT & SUPPLY 657 NE Dixie Highway Jensen Beach, FL 34957 SUNRYSE CONSTRUCTION 44575 SE Commerce Avenue, Stuart, FL 34997 D&D QUALITY 1409 Forsythe Road West Palm Beach, FL 33405

PRINCIPAL OR OFFICER’S NAME

Thomas McDonough Patricia A. Fye Michael Daley Robert F. Johnston David Walter Blanka Diamond

LICENSE NO. CGC 020569 U-20235 CCC 058213 CBC 025081 CGC 1511260 CGC 010017

PHASE II EXHIBIT S LIST OF MAJOR SUBCONTRACTORS

PROJECT NAME: NORTHBORO ELEMENTARY MODERNIZATION

PROJECT NO.: 0291-7504

DIVISION OF WORK

Finishes Finishes Finishes Specialties Equipment Furnishings Mechanical Mechanical Mechanical

Electrical

CORPORATE NAME & ADDRESS PHOENIX PAINTING CO. 6303 N. Powerline Rd. Ft. Lauderdale, FL 33309 SUPERIOR INTEROR SYSTEMS, INC. 959 Shotgun Rd. Sunrise, FL 33326 ZAHARION’S FLOORING 1338 South Killian Drive Suite 11 Lake Park, FL 33403 DWYER INDUSTRIES 7025 CR 46A Suite 1071-513 Lake Mary, FL 32746 DESIGN FURNISHINGS 889 Brentwood Drive, Daytona Beach, FL 32117 NEW RIVER CABINETS 700 NW 57th Court Ft. Lauderdale, FL 33309 DODEC 3140 W 84th Street #2 Hialeah, FL 33018 FRANCIS ENGINEERING 1232 SW 31st Avenue Ft. Lauderdale, FL 33312 HPI PLUMBING CONTRACTORS, INC. 2545 Old Okeechobee Rd. West Palm Beach, FL 33409 FASTRAC ELECTRIC CORP 810 Saturn St. #25 Jupiter, FL 33477

PRINCIPAL OR OFFICER’S NAME Richard Gardella

Mary Cooper

Rebecca Zaharion David W. Dwyer Mike McKernan Keith Mosley Trevor Pantry Orrett Francis Glenroy Hessing Shawn Bly

LICENSE NO. U-12253 U-17723 U-17022 PSL08-9486 85012290 2700002665 CMC 03464 6005000011990 CFC 021473 EC 002876

Activity

ID

Activity

Description

Orig

Dur

Early

Start

Early

Finish

Total

Float

PHASE 1

COMMENCEMENT

01000.00 ABATEMENT CLEARANCE LETTER RECEIVED 1 09JUN08 09JUN08 0

01010.00 NOTICE TO PROCEED 1 10JUN08 10JUN08 0

01020.00 DISTRICT MOVE & SALVAGE 5 10JUN08 16JUN08 1

01030.00 PRE-CONSTRUCTION MEETING 1 11JUN08 11JUN08 0

01050.00 MOBILIZATION 4 12JUN08 17JUN08 0

LEED DOCUMENTATION

01120.00 DEMOLITION PROGRESS PHOTOS 56 09JUN08 25AUG08 12

01110.00 SALVAGE PHOTOS, REUSE 46 09JUN08 11AUG08 22

01130.00 MEP RECOVERY DOCUMENTATION 10 09JUN08 20JUN08 58

01100.00 EROSION CONTROL PHOTOS 4 09JUN08 12JUN08 64

SITEWORK

TREE, ROOT PRUNING

02000.99 ROOT PRUNING 20 17JUN08 14JUL08 17

02010.99 TREE RELOCATION 25 15JUL08 18AUG08 17

TEMPORARY PARKING (COMPOUND)

02520.99 TEMPORARY PARKING (COMPOUND) 3 27JUN08 01JUL08 51

SITE DEMOLITION

02020.99 PAVING & CONCRETE FLATWORK REMOVAL 5 18JUN08 24JUN08 0

02030.99 UTILITY DEMOLITION 5 25JUN08 01JUL08 0

02040.99 CHILLER PLANT 4 26JUN08 01JUL08 0

02050.99 ITV TOWER 2 27JUN08 30JUN08 0

02060.99 CUT & STOCKPILE BASE MATERIAL 2 01JUL08 02JUL08 0

02061.99 AUTHORIZATION TO DEMO INTERIOR ROADS 9 15AUG08 27AUG08 0

02062.99 DEMO INTERIOR ROADS ON-SITE 12 28AUG08 10SEP08 0

SITE UTILITIES

02720.99 STORM DRAINAGE SYSTEM - SITE 20 11SEP08 08OCT08 0

02210.99 BACKFILL & COMPACT UTILITIES - SITE 10 09OCT08 22OCT08 0

02730.99 SEWER LINE - SITE 20 09OCT08 05NOV08 0

02220.99 BUILDING PADS 16 23OCT08 13NOV08 0

02660.99 WATER DISTRIBUTION - SITE 20 06NOV08 04DEC08 0

02540.99 U/G CISTERNS/TANKS - SITE 10 02DEC08 15DEC08 0

16101.99 ELECTRICAL U\G R-I - SITE 20 05DEC08 05JAN09 164

2008 2009 2010J J A S O N D J F M A M J J A S O N D J F M A M JJUL

ABATEMENT CLEARANCE LETTER RECEIVED

NOTICE TO PROCEED

DISTRICT MOVE & SALVAGE

PRE-CONSTRUCTION MEETING

MOBILIZATION

DEMOLITION PROGRESS PHOTOS

SALVAGE PHOTOS, REUSE

MEP RECOVERY DOCUMENTATION

EROSION CONTROL PHOTOS

ROOT PRUNING

TREE RELOCATION

TEMPORARY PARKING (COMPOUND)

PAVING & CONCRETE FLATWORK REMOVAL

UTILITY DEMOLITION

CHILLER PLANT

ITV TOWER

CUT & STOCKPILE BASE MATERIAL

AUTHORIZATION TO DEMO INTERIOR ROADS

DEMO INTERIOR ROADS ON-SITE

STORM DRAINAGE SYSTEM - SITE

BACKFILL & COMPACT UTILITIES - SITE

SEWER LINE - SITE

BUILDING PADS

WATER DISTRIBUTION - SITE

U/G CISTERNS/TANKS - SITE

ELECTRICAL U\G R-I - SITE

© Primavera Systems, Inc.

Start Date 09JUN08

Finish Date 07JUN10

Data Date 09JUN08

Run Date 08OCT08 08:10

Early Bar

Progress Bar

Critical Activity

BASZ

HEDRICK BROTHERS CONSTRUCTIONNORTHBORO ELEMENTARY SCHOOL

Sheet 1 of 16

ORGANIZED BY AREA

Activity

ID

Activity

Description

Orig

Dur

Early

Start

Early

Finish

Total

Float

PORTABLE CLASSROOM DEMOLITION

02000.70 UTILITY DISCONNECT & CAP 2 18JUN08 19JUN08 0

02010.70 DEMOLITION & REMOVAL 5 20JUN08 26JUN08 0

MAIN BUILDIINGS DEMOLITION

CAFETERIA - EXISTING

02080.99 EXISTING - CAFETERIA DEMOLITION 5 25JUN08 01JUL08 0

BUILDING #1 - EXISTING

02090.99 EXISTING - BUILDING #1 SELECTIVE DEMOLITION 30 02JUL08 12AUG08 0

02091.99 HISTORICAL RESTORATION WEST WALL 10 30JUL08 12AUG08 0

02092.99 COMPLETE DEBRIS REMOVAL 15 06AUG08 26AUG08 0

FINAL SITE PREP

02200.99 GRADE SITE & BALANCE 11 27AUG08 10SEP08 0

BUILDING #3 - EXISTING

02095.99 SELECTIVE DEMOLITION - 1ST FLR - BLDG 3 - EXISTI 15 11SEP08 01OCT08 0

02096.99 SELECTIVE DEMOLITION - 2ND FLR - BLDG 3 - EXISTI 15 29SEP08 17OCT08 0

COMPLETION

17000.01 SUBSTANTIAL COMPLETION - PHASE 1 19 20OCT08 13NOV08 0

PHASE 2

COMMENCEMENT

01000.02 NOTICE TO PROCEED - PHASE 2 11 14NOV08 01DEC08 0

FOUNDATIONS

NEW BUILDING 3

15400.03 INSTALL U/G WATER/SEWER - BLDG 3 - NEW 7 02DEC08 10DEC08 0

15410.03 INSTALL PLUMB R-I - U/G - BLDG 3 - NEW 7 02DEC08 10DEC08 0

15420.03 INSTALL CHILLED WATER R-I U/G- BLDG 3 - NEW 7 02DEC08 10DEC08 0

16110.03 INSTALL ELECT R-I - U/G - BLDG 3 - NEW 7 02DEC08 10DEC08 0

16111.03 INSTALL ELEC U/G DUCTBANK - BLDG 3 - NEW 7 02DEC08 10DEC08 0

01601.03 INSPECT - U/G - BLDG 3 - NEW 3 11DEC08 15DEC08 0

03000.03 LAYOUT FTGS - BLDG 3 - NEW 1 16DEC08 16DEC08 0

03002.03 EXCAVATE INTERIOR FTGS - BLDG 3 - NEW 4 17DEC08 22DEC08 0

03003.03 FORM INTERIOR FTGS - BLDG 3 - NEW 5 19DEC08 26DEC08 2

03005.03 EXCAVATE PERIMETER FTGS - BLDG 3 - NEW 5 23DEC08 30DEC08 0

03200.03 PLACE REBAR INTERIOR FTGS - BLDG 3 - NEW 4 24DEC08 30DEC08 2

2008 2009 2010J J A S O N D J F M A M J J A S O N D J F M A M JJUL

UTILITY DISCONNECT & CAP

DEMOLITION & REMOVAL

EXISTING - CAFETERIA DEMOLITION

EXISTING - BUILDING #1 SELECTIVE DEMOLITION

HISTORICAL RESTORATION WEST WALL

COMPLETE DEBRIS REMOVAL

GRADE SITE & BALANCE

SELECTIVE DEMOLITION - 1ST FLR - BLDG 3 - EXISTI

SELECTIVE DEMOLITION - 2ND FLR - BLDG 3 - EXISTI

SUBSTANTIAL COMPLETION - PHASE 1

NOTICE TO PROCEED - PHASE 2

INSTALL U/G WATER/SEWER - BLDG 3 - NEW

INSTALL PLUMB R-I - U/G - BLDG 3 - NEW

INSTALL CHILLED WATER R-I U/G- BLDG 3 - NEW

INSTALL ELECT R-I - U/G - BLDG 3 - NEW

INSTALL ELEC U/G DUCTBANK - BLDG 3 - NEW

INSPECT - U/G - BLDG 3 - NEW

LAYOUT FTGS - BLDG 3 - NEW

EXCAVATE INTERIOR FTGS - BLDG 3 - NEW

FORM INTERIOR FTGS - BLDG 3 - NEW

EXCAVATE PERIMETER FTGS - BLDG 3 - NEW

PLACE REBAR INTERIOR FTGS - BLDG 3 - NEW

© Primavera Systems, Inc.

Start Date 09JUN08

Finish Date 07JUN10

Data Date 09JUN08

Run Date 08OCT08 08:10

Early Bar

Progress Bar

Critical Activity

BASZ

HEDRICK BROTHERS CONSTRUCTIONNORTHBORO ELEMENTARY SCHOOL

Sheet 2 of 16

ORGANIZED BY AREA

Activity

ID

Activity

Description

Orig

Dur

Early

Start

Early

Finish

Total

Float

03006.03 FORM PERIMETER FTGS - BLDG 3 - NEW 5 29DEC08 05JAN09 0

03201.03 PLACE REBAR PERIMETER FTGS - BLDG 3 - NEW 5 31DEC08 07JAN09 0

01630.03 INSPECT - INTERIOR FDNS - BLDG 3 - NEW 2 31DEC08 02JAN09 2

03300.03 POUR INTERIOR FTGS - BLDG 3 - NEW 3 05JAN09 07JAN09 2

01631.03 INSPECT - PERIMETER FDNS - BLDG 3 - NEW 2 08JAN09 09JAN09 0

03301.03 POUR PERIMETER FTGS - BLDG 3 - NEW 4 12JAN09 15JAN09 0

04200.03 MASONRY STEM WALL - BLDG 3 - NEW 1 16JAN09 16JAN09 0

04201.03 SET CMU'S - BLDG 3 - NEW 3 19JAN09 21JAN09 0

03331.03 GROUT CMU'S - BLDG 3 - NEW 1 22JAN09 22JAN09 0

03332.03 TIE COLS - STEM WALL - BLDG 3 - NEW 2 23JAN09 26JAN09 0

02215.03 TERMITE CONTROL - BLDG 3 - NEW 1 27JAN09 27JAN09 0

15411.03 PLUMBING ROUGH-IN - S.O.G. - BLDG 3 - NEW 10 28JAN09 10FEB09 0

16112.03 ELECTRICAL ROUGH-IN - S.O.G. - BLDG 3 - NEW 10 28JAN09 10FEB09 0

02210.03 ROUGH GRADE - S.O.G. - BLDG 3 - NEW 3 11FEB09 13FEB09 0

02211.03 FINE GRADE - S.O.G. - BLDG 3 - NEW 5 16FEB09 20FEB09 0

03100.03 WIRE MESH - S.O.G - BLDG 3 - NEW 2 23FEB09 24FEB09 0

01632.03 INSPECT - SOG - BLDG 3 - NEW 2 25FEB09 26FEB09 0

03310.03 POUR SOG - BLDG 3 - NEW 1 27FEB09 27FEB09 0

NEW BUILDING 1

15400.01 INSTALL U/G WATER/SEWER - BLDG 1 - NEW 7 09DEC08 17DEC08 38

15410.01 INSTALL PLUMB R-I - U/G - BLDG 1 - NEW 7 09DEC08 17DEC08 38

15420.01 INSTALL CHILLED WATER R-I U/G- BLDG 1 - NEW 7 09DEC08 17DEC08 38

16110.01 INSTALL ELECT R-I - U/G - BLDG 1 - NEW 7 09DEC08 17DEC08 38

16111.01 INSTALL ELEC U/G DUCTBANK - BLDG 1 - NEW 7 09DEC08 17DEC08 38

01601.01 INSPECT - U/G - BLDG 1 - NEW 3 18DEC08 22DEC08 38

03000.01 LAYOUT FTGS - BLDG 1 - NEW 1 23DEC08 23DEC08 38

03002.01 EXCAVATE INTERIOR FTGS - BLDG 1 - NEW 4 24DEC08 30DEC08 38

03003.01 FORM INTERIOR FTGS - BLDG 1 - NEW 5 29DEC08 05JAN09 40

03005.01 EXCAVATE PERIMETER FTGS - BLDG 1 - NEW 5 31DEC08 07JAN09 38

03200.01 PLACE REBAR INTERIOR FTGS - BLDG 1 - NEW 4 02JAN09 07JAN09 40

03006.01 FORM PERIMETER FTGS - BLDG 1 - NEW 5 05JAN09 09JAN09 38

03201.01 PLACE REBAR PERIMETER FTGS - BLDG 1 - NEW 5 08JAN09 14JAN09 38

01630.01 INSPECT - INTERIOR FDNS - BLDG 1 - NEW 2 08JAN09 09JAN09 40

03300.01 POUR INTERIOR FTGS - BLDG 1 - NEW 3 12JAN09 14JAN09 40

01631.01 INSPECT - PERIMETER FDNS - BLDG 1 - NEW 2 15JAN09 16JAN09 38

03301.01 POUR PERIMETER FTGS - BLDG 1 - NEW 4 19JAN09 22JAN09 38

04200.01 MASONRY STEM WALL - BLDG 1 - NEW 1 23JAN09 23JAN09 38

2008 2009 2010J J A S O N D J F M A M J J A S O N D J F M A M JJUL

FORM PERIMETER FTGS - BLDG 3 - NEW

PLACE REBAR PERIMETER FTGS - BLDG 3 - NEW

INSPECT - INTERIOR FDNS - BLDG 3 - NEW

POUR INTERIOR FTGS - BLDG 3 - NEW

INSPECT - PERIMETER FDNS - BLDG 3 - NEW

POUR PERIMETER FTGS - BLDG 3 - NEW

MASONRY STEM WALL - BLDG 3 - NEW

SET CMU'S - BLDG 3 - NEW

GROUT CMU'S - BLDG 3 - NEW

TIE COLS - STEM WALL - BLDG 3 - NEW

TERMITE CONTROL - BLDG 3 - NEW

PLUMBING ROUGH-IN - S.O.G. - BLDG 3 - NEW

ELECTRICAL ROUGH-IN - S.O.G. - BLDG 3 - NEW

ROUGH GRADE - S.O.G. - BLDG 3 - NEW

FINE GRADE - S.O.G. - BLDG 3 - NEW

WIRE MESH - S.O.G - BLDG 3 - NEW

INSPECT - SOG - BLDG 3 - NEW

POUR SOG - BLDG 3 - NEW

INSTALL U/G WATER/SEWER - BLDG 1 - NEW

INSTALL PLUMB R-I - U/G - BLDG 1 - NEW

INSTALL CHILLED WATER R-I U/G- BLDG 1 - NEW

INSTALL ELECT R-I - U/G - BLDG 1 - NEW

INSTALL ELEC U/G DUCTBANK - BLDG 1 - NEW

INSPECT - U/G - BLDG 1 - NEW

LAYOUT FTGS - BLDG 1 - NEW

EXCAVATE INTERIOR FTGS - BLDG 1 - NEW

FORM INTERIOR FTGS - BLDG 1 - NEW

EXCAVATE PERIMETER FTGS - BLDG 1 - NEW

PLACE REBAR INTERIOR FTGS - BLDG 1 - NEW

FORM PERIMETER FTGS - BLDG 1 - NEW

PLACE REBAR PERIMETER FTGS - BLDG 1 - NEW

INSPECT - INTERIOR FDNS - BLDG 1 - NEW

POUR INTERIOR FTGS - BLDG 1 - NEW

INSPECT - PERIMETER FDNS - BLDG 1 - NEW

POUR PERIMETER FTGS - BLDG 1 - NEW

MASONRY STEM WALL - BLDG 1 - NEW

© Primavera Systems, Inc.

Start Date 09JUN08

Finish Date 07JUN10

Data Date 09JUN08

Run Date 08OCT08 08:10

Early Bar

Progress Bar

Critical Activity

BASZ

HEDRICK BROTHERS CONSTRUCTIONNORTHBORO ELEMENTARY SCHOOL

Sheet 3 of 16

ORGANIZED BY AREA

Activity

ID

Activity

Description

Orig

Dur

Early

Start

Early

Finish

Total

Float

04201.01 SET CMU'S - BLDG 1 - NEW 3 26JAN09 28JAN09 38

03331.01 GROUT CMU'S - BLDG 1 - NEW 1 29JAN09 29JAN09 38

03332.01 TIE COLS - STEM WALL - BLDG 1 - NEW 2 30JAN09 02FEB09 38

02215.01 TERMITE CONTROL - BLDG 1 - NEW 1 03FEB09 03FEB09 38

15411.01 PLUMBING ROUGH-IN - S.O.G. - BLDG 1 - NEW 10 04FEB09 17FEB09 38

16112.01 ELECTRICAL ROUGH-IN - S.O.G. - BLDG 1 - NEW 10 04FEB09 17FEB09 38

02210.01 ROUGH GRADE - S.O.G. - BLDG 1 - NEW 3 18FEB09 20FEB09 38

02211.01 FINE GRADE - S.O.G. - BLDG 1 - NEW 5 23FEB09 27FEB09 38

03100.01 WIRE MESH - S.O.G - BLDG 1 - NEW 2 02MAR09 03MAR09 38

01632.01 INSPECT - SOG - BLDG 1 - NEW 2 04MAR09 05MAR09 38

03310.01 POUR SOG - BLDG 1 - NEW 1 06MAR09 06MAR09 38

NEW BUILDING 3

1ST FLOOR

04200.0301 ERECT MASONRY WALLS TO BEAM - 1ST FLR - BLDG 3 - 20 02MAR09 27MAR09 0

03330.0301 FORM/POUR TIE COLS/BEAMS - 1ST FLR - BLDG 3 - NE 15 12MAR09 01APR09 0

03331.0301 INSTALL EMBEDS - 1ST FLR - BLDG 3 - NEW 5 02APR09 08APR09 0

05100.0301 ERECT STRUCTURAL STEEL/JOISTS - 2ND FLR - BLDG 3 10 09APR09 22APR09 0

09231.0301 METAL FRAMING - TOP TRACK - BLDG 3 - 1ST FLR - N 5 11MAY09 15MAY09 53

08500.0301 WINDOWS - BLDG 3 - 1ST FLR - NEW 10 11MAY09 22MAY09 87

15890.0301 INSTALL DUCTWORK - BLDG 3 - 1ST FLR - NEW 20 18MAY09 15JUN09 53

09230.0301 INSTALL METAL FRAMING - BLDG 3 - 1ST FLR - NEW 20 26MAY09 22JUN09 53

15530.0301 INSTALL HVAC PIPING - BLDG 3 - 1ST FLR - NEW 17 29MAY09 22JUN09 63

15300.0301 INSTALL FIRE SPRKLR ROUGH - BLDG 3 - 1ST FLR - N 20 02JUN09 29JUN09 102

15415.0301 INSTALL PLUMBING ROUGH - BLDG 3 - 1ST FLR - NEW 20 04JUN09 01JUL09 56

15655.0301 INSTALL HVAC EQUIP - BLDG 3 - 1ST FLR - NEW 17 05JUN09 29JUN09 90

16115.0301 INSTALL ELECTRIC ROUGH - BLDG 3 - 1ST FLR - NEW 20 09JUN09 07JUL09 53

13100.0301 INSTALL INTERCOM BACKBOXES - BLDG 3 - 1ST FLR - 15 16JUN09 07JUL09 53

15895.0301 INSTALL DUCTWORK INSULATION - BLDG 3 - 1ST FLR - 20 16JUN09 14JUL09 94

15656.0301 HVAC DUCT CONNECT/HOOK-UP - BLDG 3 - 1ST FLR - N 7 30JUN09 09JUL09 90

01618.0301 INSPECT FIRE SPRINKLER ABOVE CLG - BLDG 3 - 1ST 2 30JUN09 01JUL09 102

01614.0301 INSPECT PLUMBING - BLDG 3 - 1ST FLR - NEW 2 02JUL09 06JUL09 56

01616.0301 INSPECT ELECTRICAL ROUGH - BLDG 3 - 1ST FLR - NE 2 08JUL09 09JUL09 53

01617.0301 INSPECT FRAMING - BLDG 3 - 1ST FLR - NEW 2 10JUL09 13JUL09 53

15657.0301 HVAC PIPING CONNECT/HOOK-UP - BLDG 3 - 1ST FLR - 7 10JUL09 20JUL09 90

01615.0301 INSPECT HVAC - BLDG 3 - 1ST FLR - NEW 2 13JUL09 14JUL09 94

09250.0301 HANG DRYWALL - BLDG 3 - 1ST FLR - NEW 15 14JUL09 03AUG09 53

14102.0301 ELEVATOR RAILS - BLDG 3 - NEW 20 24JUL09 20AUG09 63

2008 2009 2010J J A S O N D J F M A M J J A S O N D J F M A M JJUL

SET CMU'S - BLDG 1 - NEW

GROUT CMU'S - BLDG 1 - NEW

TIE COLS - STEM WALL - BLDG 1 - NEW

TERMITE CONTROL - BLDG 1 - NEW

PLUMBING ROUGH-IN - S.O.G. - BLDG 1 - NEW

ELECTRICAL ROUGH-IN - S.O.G. - BLDG 1 - NEW

ROUGH GRADE - S.O.G. - BLDG 1 - NEW

FINE GRADE - S.O.G. - BLDG 1 - NEW

WIRE MESH - S.O.G - BLDG 1 - NEW

INSPECT - SOG - BLDG 1 - NEW

POUR SOG - BLDG 1 - NEW

ERECT MASONRY WALLS TO BEAM - 1ST FLR - BLDG 3 -

FORM/POUR TIE COLS/BEAMS - 1ST FLR - BLDG 3 - NE

INSTALL EMBEDS - 1ST FLR - BLDG 3 - NEW

ERECT STRUCTURAL STEEL/JOISTS - 2ND FLR - BLDG

METAL FRAMING - TOP TRACK - BLDG 3 - 1ST FLR -

WINDOWS - BLDG 3 - 1ST FLR - NEW

INSTALL DUCTWORK - BLDG 3 - 1ST FLR - NEW

INSTALL METAL FRAMING - BLDG 3 - 1ST FLR -

INSTALL HVAC PIPING - BLDG 3 - 1ST FLR - NEW

INSTALL FIRE SPRKLR ROUGH - BLDG 3 - 1ST

INSTALL PLUMBING ROUGH - BLDG 3 - 1ST FL

INSTALL HVAC EQUIP - BLDG 3 - 1ST FLR - NEW

INSTALL ELECTRIC ROUGH - BLDG 3 - 1ST FL

INSTALL INTERCOM BACKBOXES - BLDG 3 - 1

INSTALL DUCTWORK INSULATION - BLDG 3 -

HVAC DUCT CONNECT/HOOK-UP - BLDG 3 - 1

INSPECT FIRE SPRINKLER ABOVE CLG - BLDG

INSPECT PLUMBING - BLDG 3 - 1ST FLR - NEW

INSPECT ELECTRICAL ROUGH - BLDG 3 - 1ST

INSPECT FRAMING - BLDG 3 - 1ST FLR - NEW

HVAC PIPING CONNECT/HOOK-UP - BLDG 3

INSPECT HVAC - BLDG 3 - 1ST FLR - NEW

HANG DRYWALL - BLDG 3 - 1ST FLR - NEW

ELEVATOR RAILS - BLDG 3 - NEW

© Primavera Systems, Inc.

Start Date 09JUN08

Finish Date 07JUN10

Data Date 09JUN08

Run Date 08OCT08 08:10

Early Bar

Progress Bar

Critical Activity

BASZ

HEDRICK BROTHERS CONSTRUCTIONNORTHBORO ELEMENTARY SCHOOL

Sheet 4 of 16

ORGANIZED BY AREA

Activity

ID

Activity

Description

Orig

Dur

Early

Start

Early

Finish

Total

Float

09251.0301 FINISH DRYWALL - BLDG 3 - 1ST FLR - NEW 15 27JUL09 14AUG09 53

09900.0301 PAINT INTERIOR PRIME COAT - BLDG 3 - 1ST FLR - N 8 17AUG09 26AUG09 53

09310.0301 INSTALL CERAMIC TILE - BLDG 3 - 1ST FLR - NEW 15 17AUG09 04SEP09 56

14104.0301 INSTL ELEV. FRAMES/EQ/CABS - BLDG 3 - NEW 40 21AUG09 16OCT09 63

09901.0301 PAINT INTERIOR FINISH COAT - BLDG 3 - 1ST FLR - 15 27AUG09 17SEP09 53

06410.0301 INSTALL CABINETS - BLDG 3 - 1ST FLR - NEW 17 08SEP09 30SEP09 56

09510.0301 INSTALL ACOUSTICAL CLG GRID - BLDG 3 - 1ST FLR - 15 11SEP09 01OCT09 53

08100.0301 HANG DOORS - BLDG 3 - 1ST FLR - NEW 12 18SEP09 05OCT09 75

10100.0301 INSTALL CHALK/TACKBOARD - BLDG 3 - 1ST FLR - NEW 8 18SEP09 29SEP09 82

15940.0301 INSTALL HVAC GRILLS/TRIM - BLDG 3 - 1ST FLR - NE 15 21SEP09 09OCT09 53

16500.0301 INSTALL ELEC FIXTURES - BLDG 3 - 1ST FLR - NEW 20 21SEP09 16OCT09 58

15440.0301 INSTALL PLUMB FIXTURES - BLDG 3 - 1ST FLR - NEW 20 01OCT09 28OCT09 56

13129.0301 INTERCOM INSTALLATION - BLDG 3 - 1ST FLR - NEW 15 02OCT09 22OCT09 62

11132.0301 INSTALL PROJECTION SCREENS - BLDG 3 - 1ST FLR - 5 02OCT09 08OCT09 72

08710.0301 INSTALL FINISH HARDWARE - BLDG 3 - 1ST FLR - NEW 10 06OCT09 19OCT09 75

15980.0301 START-UP HVAC SYSTEM - BLDG 3 - 1ST FLR - NEW 10 12OCT09 23OCT09 53

14106.0301 INTERIOR ELEVATOR FINISHES - BLDG 3 - NEW 15 19OCT09 06NOV09 63

09515.0301 INSTALL ACOUSTICAL CLG TILE - BLDG 3 - 1ST FLR - 8 26OCT09 04NOV09 53

15990.0301 PERFORM TEST & BALANCE - BLDG 3 - 1ST FLR - NEW 5 26OCT09 30OCT09 66

16505.0301 INSTALL ELEC TRIM - BLDG 3 - 1ST FLR - NEW 10 29OCT09 11NOV09 53

16710.0301 INSTALL SYSTEMS TRIM/DEVICES - BLDG 3 - 1ST FLR 10 29OCT09 11NOV09 53

10801.0301 INSTALL TOILET PARTITIONS - BLDG 3 - 1ST FLR - 7 29OCT09 06NOV09 56

08800.0301 INSTALL INTERIOR GLAZING - BLDG 3 - 1ST FLR - NE 5 29OCT09 04NOV09 63

15310.0301 INSTALL FIRE SPRKLR HEADS/TRIM - BLDG 3 - 1ST FL 7 02NOV09 10NOV09 54

09680.0301 INSTALL CARPET/FLOORING - BLDG 3 - 1ST FLR - NEW 10 05NOV09 18NOV09 53

10600.0301 METAL SHELVING/LOCKERS - BLDG 3 - 1ST FLR - NEW 7 05NOV09 13NOV09 56

10024.0301 INSTALL FIRE EXTINGUISHERS - BLDG 3 - 1ST FLR - 5 05NOV09 11NOV09 58

10800.0301 INSTALL BATH ACCESSORIES - BLDG 3 - 1ST FLR - NE 5 09NOV09 13NOV09 56

01690.0301 INSPECT - FINISHES - BLDG 3 - 1ST FLR - NEW 2 19NOV09 20NOV09 53

17000.0301 CONTRACTOR COMPLETION - BLDG 3 - 1ST FLR - NEW 0 20NOV09 53

2ND FLOOR

05200.0302 ERECT METAL DECK - 2ND FLR - BLDG 3 - NEW 5 23APR09 29APR09 0

01611.0302 INSPECT WELDS - METAL DECK - 2ND FLR - BLDG 3 - 2 30APR09 01MAY09 0

03310.0302 FORM/POUR 2ND FLR DECK - BLDG 3 - NEW 5 04MAY09 08MAY09 0

01612.0302 INSPECT REBAR - 2ND FLR - BLDG 3 - NEW 2 07MAY09 08MAY09 0

04200.0302 ERECT MASONRY WALLS TO BEAMS - 2ND FLR - BLDG 3 20 11MAY09 08JUN09 0

03330.0302 FORM/POUR TIE COLS/BEAMS - 2ND FLR - BLDG 3 - NE 15 21MAY09 11JUN09 0

2008 2009 2010J J A S O N D J F M A M J J A S O N D J F M A M JJUL

FINISH DRYWALL - BLDG 3 - 1ST FLR - NEW

PAINT INTERIOR PRIME COAT - BLDG 3 - 1ST FLR - N

INSTALL CERAMIC TILE - BLDG 3 - 1ST FLR - NEW

INSTL ELEV. FRAMES/EQ/CABS - BLDG 3 - NEW

PAINT INTERIOR FINISH COAT - BLDG 3 - 1ST FLR -

INSTALL CABINETS - BLDG 3 - 1ST FLR - NEW

INSTALL ACOUSTICAL CLG GRID - BLDG 3 - 1ST FLR -

HANG DOORS - BLDG 3 - 1ST FLR - NEW

INSTALL CHALK/TACKBOARD - BLDG 3 - 1ST FLR - NEW

INSTALL HVAC GRILLS/TRIM - BLDG 3 - 1ST FLR - NE

INSTALL ELEC FIXTURES - BLDG 3 - 1ST FLR - NEW

INSTALL PLUMB FIXTURES - BLDG 3 - 1ST FLR - NEW

INTERCOM INSTALLATION - BLDG 3 - 1ST FLR - NEW

INSTALL PROJECTION SCREENS - BLDG 3 - 1ST FLR -

INSTALL FINISH HARDWARE - BLDG 3 - 1ST FLR - NEW

START-UP HVAC SYSTEM - BLDG 3 - 1ST FLR - NEW

INTERIOR ELEVATOR FINISHES - BLDG 3 - NEW

INSTALL ACOUSTICAL CLG TILE - BLDG 3 - 1ST FLR -

PERFORM TEST & BALANCE - BLDG 3 - 1ST FLR - NEW

INSTALL ELEC TRIM - BLDG 3 - 1ST FLR - NEW

INSTALL SYSTEMS TRIM/DEVICES - BLDG 3 - 1ST FLR

INSTALL TOILET PARTITIONS - BLDG 3 - 1ST FLR -

INSTALL INTERIOR GLAZING - BLDG 3 - 1ST FLR - NE

INSTALL FIRE SPRKLR HEADS/TRIM - BLDG 3 - 1ST FL

INSTALL CARPET/FLOORING - BLDG 3 - 1ST FLR - NEW

METAL SHELVING/LOCKERS - BLDG 3 - 1ST FLR - NEW

INSTALL FIRE EXTINGUISHERS - BLDG 3 - 1ST FLR -

INSTALL BATH ACCESSORIES - BLDG 3 - 1ST FLR - NE

INSPECT - FINISHES - BLDG 3 - 1ST FLR - NEW

CONTRACTOR COMPLETION - BLDG 3 - 1ST FLR - NEW

ERECT METAL DECK - 2ND FLR - BLDG 3 - NEW

INSPECT WELDS - METAL DECK - 2ND FLR - BLDG 3 -

FORM/POUR 2ND FLR DECK - BLDG 3 - NEW

INSPECT REBAR - 2ND FLR - BLDG 3 - NEW

ERECT MASONRY WALLS TO BEAMS - 2ND FLR -

FORM/POUR TIE COLS/BEAMS - 2ND FLR - BLDG

© Primavera Systems, Inc.

Start Date 09JUN08

Finish Date 07JUN10

Data Date 09JUN08

Run Date 08OCT08 08:10

Early Bar

Progress Bar

Critical Activity

BASZ

HEDRICK BROTHERS CONSTRUCTIONNORTHBORO ELEMENTARY SCHOOL

Sheet 5 of 16

ORGANIZED BY AREA

Activity

ID

Activity

Description

Orig

Dur

Early

Start

Early

Finish

Total

Float

03331.0302 INSTALL EMBEDS - 2ND FLR - BLDG 3 - NEW 5 12JUN09 18JUN09 0

01613.0302 INSPECT BEAMS - 2ND FLR - BLDG 3 - NEW 2 19JUN09 22JUN09 0

05100.0302 ERECT STRUCTURAL STEEL/JOISTS - ROOF - BLDG 3 - 10 23JUN09 07JUL09 0

09231.0302 METAL FRAMING - TOP TRACK - BLDG 3 - 2ND FLR - N 5 24JUL09 30JUL09 0

08500.0302 WINDOWS - BLDG 3 - 2ND FLR - NEW 10 29JUL09 11AUG09 31

15890.0302 INSTALL DUCTWORK - BLDG 3 - 2ND FLR - NEW 20 31JUL09 27AUG09 0

09230.0302 INSTALL METAL FRAMING - BLDG 3 - 2ND FLR - NEW 20 07AUG09 03SEP09 0

15530.0302 INSTALL HVAC PIPING - BLDG 3 - 2ND FLR - NEW 17 12AUG09 03SEP09 10

15300.0302 INSTALL FIRE SPRKLR ROUGH - BLDG 3 - 2ND FLR - N 17 14AUG09 08SEP09 53

15415.0302 INSTALL PLUMBING ROUGH - BLDG 3 - 2ND FLR - NEW 20 18AUG09 15SEP09 3

15655.0302 INSTALL HVAC EQUIP - BLDG 3 - 2ND FLR - NEW 17 19AUG09 11SEP09 35

16115.0302 INSTALL ELECTRIC ROUGH - BLDG 3 - 2ND FLR - NEW 20 21AUG09 18SEP09 0

13100.0302 INSTALL INTERCOM BACKBOXES - BLDG 3 - 2ND FLR - 15 28AUG09 18SEP09 0

15895.0302 INSTALL DUCTWORK INSULATION - BLDG 3 - 2ND FLR - 20 28AUG09 25SEP09 42

01618.0302 INSPECT FIRE SPRINKLER ABOVE CLG - 2ND FLR - B 3 2 09SEP09 10SEP09 53

15656.0302 HVAC DUCT CONNECT/HOOK-UP - BLDG 3 - 2ND FLR - N 10 14SEP09 25SEP09 35

01614.0302 INSPECT PLUMBING - BLDG 3 - 2ND FLR - NEW 2 16SEP09 17SEP09 3

01616.0302 INSPECT ELECTRICAL ROUGH - BLDG 3 - 2ND FLR - NE 2 21SEP09 22SEP09 0

01617.0302 INSPECT FRAMING - 2ND FLR - BLDG 3 - NEW 2 23SEP09 24SEP09 0

01615.0302 INSPECT HVAC - BLDG 3 - 2ND FLR - NEW 2 24SEP09 25SEP09 42

09250.0302 HANG DRYWALL - BLDG 3 - 2ND FLR - NEW 15 25SEP09 15OCT09 0

15657.0302 HVAC PIPING CONNECT/HOOK-UP - BLDG 3 - 2ND FLR - 7 28SEP09 06OCT09 35

09251.0302 FINISH DRYWALL - BLDG 3 - 2ND FLR - NEW 15 08OCT09 28OCT09 0

09310.0302 INSTALL CERAMIC TILE - BLDG 3 - 2ND FLR - NEW 15 29OCT09 18NOV09 0

09900.0302 PAINT INTERIOR PRIME COAT - BLDG 3 - 2ND FLR - N 8 29OCT09 09NOV09 1

09901.0302 PAINT INTERIOR FINISH COAT - BLDG 3 - 2ND FLR - 15 10NOV09 01DEC09 1

06410.0302 INSTALL CABINETS - BLDG 3 - 2ND FLR - NEW 17 19NOV09 14DEC09 0

09510.0302 INSTALL ACOUSTICAL CLG GRID - BLDG 3 - 2ND FLR - 15 24NOV09 15DEC09 1

08100.0302 HANG DOORS - BLDG 3 - 2ND FLR - NEW 12 02DEC09 17DEC09 15

10100.0302 INSTALL CHALK/TACKBOARD - BLDG 3 - 2ND FLR - NEW 10 02DEC09 15DEC09 22

15940.0302 INSTALL HVAC GRILLS/TRIM - BLDG 3 - 2ND FLR - NE 12 03DEC09 18DEC09 1

16500.0302 INSTALL ELEC FIXTURES - BLDG 3 - 2ND FLR - NEW 17 03DEC09 28DEC09 1

15440.0302 INSTALL PLUMB FIXTURES - BLDG 3 - 2ND FLR - NEW 13 15DEC09 04JAN10 0

13129.0302 INTERCOM INSTALLATION - BLDG 3 - 2ND FLR - NEW 15 16DEC09 07JAN10 2

11132.0302 INSTALL PROJECTION SCREENS - BLDG 3 - 2ND FLR - 5 16DEC09 22DEC09 12

08710.0302 INSTALL FINISH HARDWARE - BLDG 3 - 2ND FLR - NEW 10 18DEC09 04JAN10 15

15980.0302 START-UP HVAC SYSTEM - BLDG 3 - 2ND FLR - NEW 5 21DEC09 28DEC09 1

09515.0302 INSTALL ACOUSTICAL CLG TILE - BLDG 3 - 2ND FLR - 8 29DEC09 08JAN10 1

2008 2009 2010J J A S O N D J F M A M J J A S O N D J F M A M JJUL

INSTALL EMBEDS - 2ND FLR - BLDG 3 - NEW

INSPECT BEAMS - 2ND FLR - BLDG 3 - NEW

ERECT STRUCTURAL STEEL/JOISTS - ROOF -

METAL FRAMING - TOP TRACK - BLDG 3 - 2

WINDOWS - BLDG 3 - 2ND FLR - NEW

INSTALL DUCTWORK - BLDG 3 - 2ND FLR - NEW

INSTALL METAL FRAMING - BLDG 3 - 2

INSTALL HVAC PIPING - BLDG 3 - 2ND FLR - NEW

INSTALL FIRE SPRKLR ROUGH - BLDG

INSTALL PLUMBING ROUGH - BLDG 3

INSTALL HVAC EQUIP - BLDG 3 - 2ND FLR - NEW

INSTALL ELECTRIC ROUGH - BLDG 3

INSTALL INTERCOM BACKBOXES - BLDG 3 - 2ND FLR -

INSTALL DUCTWORK INSULATION -

INSPECT FIRE SPRINKLER ABOVE CLG - 2ND FLR - B 3

HVAC DUCT CONNECT/HOOK-UP - BLDG 3 - 2ND FLR - N

INSPECT PLUMBING - BLDG 3 - 2ND FLR - NEW

INSPECT ELECTRICAL ROUGH - BLDG 3 - 2ND FLR - NE

INSPECT FRAMING - 2ND FLR - BLDG 3 - NEW

INSPECT HVAC - BLDG 3 - 2ND FLR - NEW

HANG DRYWALL - BLDG 3 - 2ND FLR - NEW

HVAC PIPING CONNECT/HOOK-UP - BLDG 3 - 2ND FLR -

FINISH DRYWALL - BLDG 3 - 2ND FLR - NEW

INSTALL CERAMIC TILE - BLDG 3 - 2ND FLR - NEW

PAINT INTERIOR PRIME COAT - BLDG 3 - 2ND FLR - N

PAINT INTERIOR FINISH COAT - BLDG 3 - 2ND FLR -

INSTALL CABINETS - BLDG 3 - 2ND FLR - NEW

INSTALL ACOUSTICAL CLG GRID - BLDG 3 - 2ND FLR -

HANG DOORS - BLDG 3 - 2ND FLR - NEW

INSTALL CHALK/TACKBOARD - BLDG 3 - 2ND FLR - NEW

INSTALL HVAC GRILLS/TRIM - BLDG 3 - 2ND FLR - NE

INSTALL ELEC FIXTURES - BLDG 3 - 2ND FLR - NEW

INSTALL PLUMB FIXTURES - BLDG 3 - 2ND FLR - NEW

INTERCOM INSTALLATION - BLDG 3 - 2ND FLR - NEW

INSTALL PROJECTION SCREENS - BLDG 3 - 2ND FLR -

INSTALL FINISH HARDWARE - BLDG 3 - 2ND FLR - NEW

START-UP HVAC SYSTEM - BLDG 3 - 2ND FLR - NEW

INSTALL ACOUSTICAL CLG TILE - BLDG 3 - 2ND FLR -

© Primavera Systems, Inc.

Start Date 09JUN08

Finish Date 07JUN10

Data Date 09JUN08

Run Date 08OCT08 08:10

Early Bar

Progress Bar

Critical Activity

BASZ

HEDRICK BROTHERS CONSTRUCTIONNORTHBORO ELEMENTARY SCHOOL

Sheet 6 of 16

ORGANIZED BY AREA

Activity

ID

Activity

Description

Orig

Dur

Early

Start

Early

Finish

Total

Float

15990.0302 PERFORM TEST & BALANCE - BLDG 3 - 2ND FLR - NEW 5 29DEC09 05JAN10 14

16505.0302 INSTALL ELEC TRIM - BLDG 3 - 2ND FLR - NEW 10 04JAN10 15JAN10 1

16710.0302 INSTALL SYSTEMS TRIM/DEVICES - BLDG 3 - 2ND FLR 10 04JAN10 15JAN10 1

10801.0302 INSTALL TOILET PARTITIONS - BLDG 3 - 2ND FLR - 10 05JAN10 18JAN10 0

08800.0302 INSTALL INTERIOR GLAZING - BLDG 3 - 2ND FLR - NE 5 05JAN10 11JAN10 10

15310.0302 INSTALL FIRE SPRKLR HEADS/TRIM - BLDG 3 - 2ND FL 7 06JAN10 14JAN10 2

09680.0302 INSTALL CARPET/FLOORING - BLDG 3 - 2ND FLR - NEW 10 11JAN10 22JAN10 1

10600.0302 METAL SHELVING/LOCKERS - BLDG 3 - 2ND FLR - NEW 7 11JAN10 19JAN10 4

10024.0302 INSTALL FIRE EXTINGUISHERS - BLDG 3 - 2ND FLR - 5 11JAN10 15JAN10 6

10800.0302 INSTALL BATH ACCESSORIES - BLDG 3 - 2ND FLR - NE 5 19JAN10 25JAN10 0

01690.0302 FINAL INSPECTIONS - BLDG 3 - NEW 10 26JAN10 08FEB10 0

17000.0302 CONTRACTOR COMPLETION - BLDG 3 - 2ND FLR - NEW 0 08FEB10 0

ROOF & EXTERIOR

05200.0303 ERECT METAL DECK - ROOF - BLDG 3 - NEW 5 08JUL09 14JUL09 0

01610.0303 INSPECT WELDS - METAL DECK - ROOF - BLDG 3 - NEW 2 15JUL09 16JUL09 0

03310.0303 FORM/REBAR ROOF DECK - BLDG 3 - NEW 5 17JUL09 23JUL09 0

01611.0303 INSPECT REBAR - ROOF - BLDG 3 - NEW 2 24JUL09 27JUL09 31

03311.0303 POUR ROOF DECK - BLDG 3 - NEW 1 28JUL09 28JUL09 31

04200.0303 PARAPET WALL - BLDG 3 - ROOF - NEW 5 29JUL09 04AUG09 62

07450.0303 1ST LAYOUT ROOFING - BLDG 3 - NEW 1 05AUG09 05AUG09 62

07400.0303 TRUSSES - BLDG 3 - NEW 15 06AUG09 26AUG09 62

07500.0303 ROOFING - BLDG 3 - NEW 10 27AUG09 10SEP09 62

01620.0303 ROOFING FINAL - BLDG 3 - NEW 2 11SEP09 14SEP09 62

04400.0303 BRICK VENEER - BLDG 3 - NEW 10 15SEP09 28SEP09 62

09100.0303 EXTERIOR STUCCO - BLDG 3 - NEW 15 29SEP09 19OCT09 62

09950.0303 EXTERIOR PAINTING - BLDG 3 - NEW 15 20OCT09 09NOV09 62

NEW BUILDING 1

1ST FLOOR

04200.0101 ERECT MASONRY WALLS - BLDG 1 - NEW 20 09MAR09 03APR09 38

03330.0101 FORM/POUR TIE COLS/BEAMS - BLDG 1 - NEW 15 19MAR09 08APR09 38

03331.0101 INSTALL EMBEDS - BLDG 1 - NEW 5 09APR09 15APR09 38

05100.0101 ERECT STRUCTURAL STEEL/JOISTS - BLDG 1 - NEW 7 16APR09 24APR09 38

09231.0101 METAL FRAMING - TOP TRACK - BLDG 1 - NEW 5 13MAY09 19MAY09 40

15890.0101 INSTALL DUCTWORK - BLDG 1 - NEW 20 20MAY09 17JUN09 40

09230.0101 INSTALL METAL FRAMING - BLDG 1 - NEW 20 28MAY09 24JUN09 40

15530.0101 INSTALL HVAC PIPING - BLDG 1 - NEW 17 02JUN09 24JUN09 50

15300.0101 INSTALL FIRE SPRKLR ROUGH - BLDG 1 - NEW 17 04JUN09 26JUN09 94

2008 2009 2010J J A S O N D J F M A M J J A S O N D J F M A M JJUL

PERFORM TEST & BALANCE - BLDG 3 - 2ND FLR - NEW

INSTALL ELEC TRIM - BLDG 3 - 2ND FLR - NEW

INSTALL SYSTEMS TRIM/DEVICES - BLDG 3 - 2ND FLR

INSTALL TOILET PARTITIONS - BLDG 3 - 2ND FLR -

INSTALL INTERIOR GLAZING - BLDG 3 - 2ND FLR - NE

INSTALL FIRE SPRKLR HEADS/TRIM - BLDG 3 - 2ND FL

INSTALL CARPET/FLOORING - BLDG 3 - 2ND FLR - NEW

METAL SHELVING/LOCKERS - BLDG 3 - 2ND FLR - NEW

INSTALL FIRE EXTINGUISHERS - BLDG 3 - 2ND FLR -

INSTALL BATH ACCESSORIES - BLDG 3 - 2ND FLR - NE

FINAL INSPECTIONS - BLDG 3 - NEW

CONTRACTOR COMPLETION - BLDG 3 - 2ND FLR - NEW

ERECT METAL DECK - ROOF - BLDG 3 - NEW

INSPECT WELDS - METAL DECK - ROOF - BL

FORM/REBAR ROOF DECK - BLDG 3 - NEW

INSPECT REBAR - ROOF - BLDG 3 - NEW

POUR ROOF DECK - BLDG 3 - NEW

PARAPET WALL - BLDG 3 - ROOF - NEW

1ST LAYOUT ROOFING - BLDG 3 - NEW

TRUSSES - BLDG 3 - NEW

ROOFING - BLDG 3 - NEW

ROOFING FINAL - BLDG 3 - NEW

BRICK VENEER - BLDG 3 - NEW

EXTERIOR STUCCO - BLDG 3 - NEW

EXTERIOR PAINTING - BLDG 3 - NEW

ERECT MASONRY WALLS - BLDG 1 - NEW

FORM/POUR TIE COLS/BEAMS - BLDG 1 - NEW

INSTALL EMBEDS - BLDG 1 - NEW

ERECT STRUCTURAL STEEL/JOISTS - BLDG 1 - NEW

METAL FRAMING - TOP TRACK - BLDG 1 - NEW

INSTALL DUCTWORK - BLDG 1 - NEW

INSTALL METAL FRAMING - BLDG 1 - NEW

INSTALL HVAC PIPING - BLDG 1 - NEW

INSTALL FIRE SPRKLR ROUGH - BLDG 1 - NEW

© Primavera Systems, Inc.

Start Date 09JUN08

Finish Date 07JUN10

Data Date 09JUN08

Run Date 08OCT08 08:10

Early Bar

Progress Bar

Critical Activity

BASZ

HEDRICK BROTHERS CONSTRUCTIONNORTHBORO ELEMENTARY SCHOOL

Sheet 7 of 16

ORGANIZED BY AREA

Activity

ID

Activity

Description

Orig

Dur

Early

Start

Early

Finish

Total

Float

15415.0101 INSTALL PLUMBING ROUGH - BLDG 1 - NEW 20 08JUN09 06JUL09 43

15655.0101 INSTALL HVAC EQUIP - BLDG 1 - NEW 17 09JUN09 01JUL09 78

16115.0101 INSTALL ELECTRIC ROUGH - BLDG 1 - NEW 20 11JUN09 09JUL09 40

13100.0101 INSTALL INTERCOM BACKBOXES - BLDG 1 - NEW 15 18JUN09 09JUL09 40

15895.0101 INSTALL DUCTWORK INSULATION - BLDG 1 - NEW 20 18JUN09 16JUL09 82

01619.0101 INSPECT FIRE SPRINKLER ABOVE CLG - 1ST FLR - B 1 1 29JUN09 29JUN09 94

15656.0101 HVAC DUCT CONNECT/HOOK-UP - BLDG 1 - NEW 7 02JUL09 13JUL09 78

01614.0101 INSPECT PLUMBING - BLDG 1 - NEW 2 07JUL09 08JUL09 43

01616.0101 INSPECT ELECTRICAL ROUGH - BLDG 1 - NEW 2 10JUL09 13JUL09 40

01617.0101 INSPECT FRAMING - 1ST FLR - BLDG 1 - NEW 2 14JUL09 15JUL09 40

15657.0101 HVAC PIPING CONNECT/HOOK-UP - BLDG 1 - NEW 7 14JUL09 22JUL09 78

01618.0101 EXT. INSULATION INSPECTION - 1ST FLR - BLDG 1 - 1 16JUL09 16JUL09 40

01615.0101 INSPECT HVAC - BLDG 1 - NEW 1 16JUL09 16JUL09 82

09250.0101 HANG DRYWALL - BLDG 1 - NEW 15 17JUL09 06AUG09 40

09251.0101 FINISH DRYWALL - BLDG 1 - NEW 15 30JUL09 19AUG09 40

09900.0101 PAINT INTERIOR PRIME COAT - BLDG 1 - NEW 8 20AUG09 31AUG09 40

09310.0101 INSTALL QUARRY/CERAMIC TILE - BLDG 1 - NEW 20 20AUG09 17SEP09 43

09901.0101 PAINT INTERIOR FINISH COAT - BLDG 1 - NEW 15 01SEP09 22SEP09 40

09510.0101 INSTALL ACOUSTICAL CLG GRID - BLDG 1 - NEW 15 16SEP09 06OCT09 40

06410.0101 INSTALL CABINETS - BLDG 1 - NEW 17 18SEP09 12OCT09 43

11400.0101 INSTALL FOOD SERVICE EQUIPMENT - BLDG 1 - NEW 30 18SEP09 29OCT09 59

08200.0101 HANG DOORS - BLDG 1 - NEW 12 23SEP09 08OCT09 64

15940.0101 INSTALL HVAC GRILLS/TRIM - BLDG 1 - NEW 12 24SEP09 09OCT09 40

16500.0101 INSTALL ELEC FIXTURES - BLDG 1 - NEW 17 24SEP09 16OCT09 40

13129.0101 INTERCOM INSTALLATION - BLDG 1 - NEW 15 07OCT09 27OCT09 46

08710.0101 INSTALL FINISH HARDWARE - BLDG 1 - NEW 10 09OCT09 22OCT09 64

15980.0101 START-UP HVAC SYSTEM - BLDG 1 - NEW 5 12OCT09 16OCT09 40

15440.0101 INSTALL PLUMB FIXTURES - BLDG 1 - NEW 17 13OCT09 04NOV09 43

09515.0101 INSTALL ACOUSTICAL CLG TILE - BLDG 1 - NEW 8 19OCT09 28OCT09 40

15990.0101 PERFORM TEST & BALANCE - BLDG 1 - NEW 5 19OCT09 23OCT09 63

16505.0101 INSTALL ELEC TRIM - BLDG 1 - NEW 10 22OCT09 04NOV09 40

16710.0101 INSTALL SYSTEMS TRIM/DEVICES - BLDG 1 - NEW 10 22OCT09 04NOV09 40

15310.0101 INSTALL FIRE SPRKLR HEADS/TRIM - BLDG 1 - NEW 7 26OCT09 03NOV09 41

10600.0101 METAL SHELVING/LOCKERS - BLDG 1 - NEW 7 29OCT09 06NOV09 53

10024.0101 INSTALL FIRE EXTINGUISHERS - BLDG 1 - NEW 5 29OCT09 04NOV09 55

15450.0101 HOOK-UP PLUMBING - FOOD SERV EQ - BLDG 1 - NEW 10 30OCT09 12NOV09 59

16490.0101 HOOK-UP ELECTRICAL - FOOD SERV EQ - BLDG 1 - NEW 10 30OCT09 12NOV09 59

09680.0101 INSTALL FLOORING - BLDG 1 - NEW 15 05NOV09 25NOV09 40

2008 2009 2010J J A S O N D J F M A M J J A S O N D J F M A M JJUL

INSTALL PLUMBING ROUGH - BLDG 1 - NEW

INSTALL HVAC EQUIP - BLDG 1 - NEW

INSTALL ELECTRIC ROUGH - BLDG 1 - NEW

INSTALL INTERCOM BACKBOXES - BLDG 1 - N

INSTALL DUCTWORK INSULATION - BLDG 1

INSPECT FIRE SPRINKLER ABOVE CLG - 1ST F

HVAC DUCT CONNECT/HOOK-UP - BLDG 1 - N

INSPECT PLUMBING - BLDG 1 - NEW

INSPECT ELECTRICAL ROUGH - BLDG 1 - NEW

INSPECT FRAMING - 1ST FLR - BLDG 1 - NEW

HVAC PIPING CONNECT/HOOK-UP - BLDG 1

EXT. INSULATION INSPECTION - 1ST FLR - B

INSPECT HVAC - BLDG 1 - NEW

HANG DRYWALL - BLDG 1 - NEW

FINISH DRYWALL - BLDG 1 - NEW

PAINT INTERIOR PRIME COAT - BLDG 1 - NEW

INSTALL QUARRY/CERAMIC TILE - BLDG 1 - NEW

PAINT INTERIOR FINISH COAT - BLDG 1 - NEW

INSTALL ACOUSTICAL CLG GRID - BLDG 1 - NEW

INSTALL CABINETS - BLDG 1 - NEW

INSTALL FOOD SERVICE EQUIPMENT - BLDG 1 - NEW

HANG DOORS - BLDG 1 - NEW

INSTALL HVAC GRILLS/TRIM - BLDG 1 - NEW

INSTALL ELEC FIXTURES - BLDG 1 - NEW

INTERCOM INSTALLATION - BLDG 1 - NEW

INSTALL FINISH HARDWARE - BLDG 1 - NEW

START-UP HVAC SYSTEM - BLDG 1 - NEW

INSTALL PLUMB FIXTURES - BLDG 1 - NEW

INSTALL ACOUSTICAL CLG TILE - BLDG 1 - NEW

PERFORM TEST & BALANCE - BLDG 1 - NEW

INSTALL ELEC TRIM - BLDG 1 - NEW

INSTALL SYSTEMS TRIM/DEVICES - BLDG 1 - NEW

INSTALL FIRE SPRKLR HEADS/TRIM - BLDG 1 - NEW

METAL SHELVING/LOCKERS - BLDG 1 - NEW

INSTALL FIRE EXTINGUISHERS - BLDG 1 - NEW

HOOK-UP PLUMBING - FOOD SERV EQ - BLDG 1 - NEW

HOOK-UP ELECTRICAL - FOOD SERV EQ - BLDG 1 - NEW

INSTALL FLOORING - BLDG 1 - NEW

© Primavera Systems, Inc.

Start Date 09JUN08

Finish Date 07JUN10

Data Date 09JUN08

Run Date 08OCT08 08:10

Early Bar

Progress Bar

Critical Activity

BASZ

HEDRICK BROTHERS CONSTRUCTIONNORTHBORO ELEMENTARY SCHOOL

Sheet 8 of 16

ORGANIZED BY AREA

Activity

ID

Activity

Description

Orig

Dur

Early

Start

Early

Finish

Total

Float

10801.0101 INSTALL TOILET PARTITIONS - BLDG 1 - NEW 7 05NOV09 13NOV09 43

08800.0101 INSTALL INTERIOR GLAZING - BLDG 1 - NEW 5 05NOV09 11NOV09 50

10800.0101 INSTALL BATH ACCESSORIES - BLDG 1 - NEW 5 16NOV09 20NOV09 43

01690.0101 FINAL INSPECTIONS - BLDG 1 - NEW 10 27NOV09 10DEC09 40

17000.0101 CONTRACTOR COMPLETION - BLDG 1 - NEW 0 10DEC09 40

ROOF & EXTERIOR

05200.0102 ERECT METAL DECK - ROOF - BLDG 1 - NEW 5 27APR09 01MAY09 38

01620.0102 INSPECT WELDS - ROOF DECK - BLDG 1 - NEW 2 04MAY09 05MAY09 38

03310.0102 FORM/REBAR ROOF DECK - BLDG 1 - NEW 5 06MAY09 12MAY09 38

01621.0102 INSPECT REBAR - ROOF DECK - BLDG 1 - NEW 2 13MAY09 14MAY09 38

03311.0102 POUR ROOF DECK - BLDG 1 - NEW 1 15MAY09 15MAY09 38

04200.0102 PARAPET WALL - BLDG 1 - ROOF - NEW 5 18MAY09 22MAY09 38

07450.0102 1ST LAYOUT ROOFING - BLDG 1 - NEW 1 26MAY09 26MAY09 38

07400.0102 TRUSSES - BLDG 1 - NEW 7 27MAY09 04JUN09 38

01622.0102 INSPECT TRUSSES - BLDG 1 - NEW 2 05JUN09 08JUN09 38

03320.0102 L/W CONC ROOFING - BLDG 1 - NEW 5 09JUN09 15JUN09 38

01623.0102 INSPECT L/W CONC ROOFING - BLDG 1 - NEW 2 16JUN09 17JUN09 38

07500.0102 ROOFING - BLDG 1 - NEW 10 18JUN09 01JUL09 38

01624.0102 FINAL ROOFING - BLDG 1 - NEW 2 02JUL09 06JUL09 111

04400.0102 BRICK VENEER - BLDG 1 - NEW 10 07JUL09 20JUL09 111

09100.0102 EXTERIOR STUCCO - BLDG 1 - NEW 15 21JUL09 10AUG09 111

09950.0102 EXTERIOR PAINTING - BLDG 1 - NEW 15 11AUG09 31AUG09 111

CHILLER ENCLOSURE

03000.0104 LAYOUT FTGS - CHILLER - NEW 1 09MAR09 09MAR09 80

03002.0104 EXCAVATE FTGS - CHILLER - NEW 3 10MAR09 12MAR09 80

03003.0104 FORM FTGS - CHILLER - NEW 3 12MAR09 16MAR09 80

03200.0104 PLACE REBAR FTGS - CHILLER - NEW 3 16MAR09 18MAR09 80

01630.0104 INSPECT - FDNS - CHILLER - NEW 1 19MAR09 19MAR09 80

03300.0104 POUR FTGS - CHILLER - NEW 2 20MAR09 23MAR09 80

15100.0104 INSTALL U/G MECH R-I - CHILLER - NEW 6 24MAR09 31MAR09 80

15540.0104 U/G CHILLED PIPING - CHILLER - NEW 6 24MAR09 31MAR09 80

16100.0104 INSTALL U/G ELECT R-I - CHILLER - NEW 4 01APR09 06APR09 80

02210.0104 FINE GRADE - S.O.G. - CHILLER - NEW 4 07APR09 10APR09 80

02215.0104 TERMITE CONTROL - CHILLER - NEW 1 13APR09 13APR09 80

03100.0104 WIRE MESH - S.O.G - CHILLER - NEW 1 14APR09 14APR09 80

01632.0104 INSPECT - SOG - CHILLER - NEW 1 15APR09 15APR09 80

03310.0104 POUR SOG - CHILLER - NEW 1 16APR09 16APR09 80

2008 2009 2010J J A S O N D J F M A M J J A S O N D J F M A M JJUL

INSTALL TOILET PARTITIONS - BLDG 1 - NEW

INSTALL INTERIOR GLAZING - BLDG 1 - NEW

INSTALL BATH ACCESSORIES - BLDG 1 - NEW

FINAL INSPECTIONS - BLDG 1 - NEW

CONTRACTOR COMPLETION - BLDG 1 - NEW

ERECT METAL DECK - ROOF - BLDG 1 - NEW

INSPECT WELDS - ROOF DECK - BLDG 1 - NEW

FORM/REBAR ROOF DECK - BLDG 1 - NEW

INSPECT REBAR - ROOF DECK - BLDG 1 - NEW

POUR ROOF DECK - BLDG 1 - NEW

PARAPET WALL - BLDG 1 - ROOF - NEW

1ST LAYOUT ROOFING - BLDG 1 - NEW

TRUSSES - BLDG 1 - NEW

INSPECT TRUSSES - BLDG 1 - NEW

L/W CONC ROOFING - BLDG 1 - NEW

INSPECT L/W CONC ROOFING - BLDG 1 - NEW

ROOFING - BLDG 1 - NEW

FINAL ROOFING - BLDG 1 - NEW

BRICK VENEER - BLDG 1 - NEW

EXTERIOR STUCCO - BLDG 1 - NEW

EXTERIOR PAINTING - BLDG 1 - NEW

LAYOUT FTGS - CHILLER - NEW

EXCAVATE FTGS - CHILLER - NEW

FORM FTGS - CHILLER - NEW

PLACE REBAR FTGS - CHILLER - NEW

INSPECT - FDNS - CHILLER - NEW

POUR FTGS - CHILLER - NEW

INSTALL U/G MECH R-I - CHILLER - NEW

U/G CHILLED PIPING - CHILLER - NEW

INSTALL U/G ELECT R-I - CHILLER - NEW

FINE GRADE - S.O.G. - CHILLER - NEW

TERMITE CONTROL - CHILLER - NEW

WIRE MESH - S.O.G - CHILLER - NEW

INSPECT - SOG - CHILLER - NEW

POUR SOG - CHILLER - NEW

© Primavera Systems, Inc.

Start Date 09JUN08

Finish Date 07JUN10

Data Date 09JUN08

Run Date 08OCT08 08:10

Early Bar

Progress Bar

Critical Activity

BASZ

HEDRICK BROTHERS CONSTRUCTIONNORTHBORO ELEMENTARY SCHOOL

Sheet 9 of 16

ORGANIZED BY AREA

Activity

ID

Activity

Description

Orig

Dur

Early

Start

Early

Finish

Total

Float

04200.0104 MASONRY WALLS - CHILLER - NEW 5 17APR09 23APR09 80

03330.0104 FORM/POUR TIE COLS/BEAMS - CHILLER - NEW 5 22APR09 28APR09 80

15900.0104 SET CHILLERS/PUMPS,ETC. - CHILLER - NEW 20 29APR09 27MAY09 80

15910.0104 COOLING TOWER - CHILLER - NEW 20 13MAY09 10JUN09 80

15541.0104 HVAC CHILLER PIPING - CHILLER - NEW 15 11JUN09 01JUL09 80

15550.0104 INSTALL HYDRONIC SPECIALITIES - CHILLER - NEW 15 02JUL09 23JUL09 80

15901.0104 HVAC - START-UP CHILLER PLANT - NEW 10 24JUL09 06AUG09 80

NEW BUILDING 2

1ST FLOOR

09231.0201 METAL FRAMING - TOP TRACK - BLDG 2 - 1ST FLR - N 5 09MAR09 13MAR09 67

03301.0201 SAWCUT CONCRETE SLAB - 1ST FLR - BLDG 2 - NEW 2 16MAR09 17MAR09 67

15410.0201 PLUMBING ROUGH - SLAB - 1ST FLR - BLDG 2 - NEW 5 18MAR09 24MAR09 67

16110.0201 ELECTRIC ROUGH - SLAB - 1ST FLR - BLDG 2 - NEW 5 20MAR09 26MAR09 67

03310.0201 PLACE & FINISH S.O.G. - 1ST FLR - BLDG 2 - NEW 2 27MAR09 30MAR09 67

15890.0201 INSTALL DUCTWORK - BLDG 2 - 1ST FLR - NEW 20 31MAR09 27APR09 67

09230.0201 INSTALL METAL FRAMING - BLDG 2 - 1ST FLR - NEW 20 07APR09 04MAY09 67

15530.0201 INSTALL HVAC PIPING - BLDG 2 - 1ST FLR - NEW 17 10APR09 04MAY09 77

15300.0201 INSTALL FIRE SPRKLR ROUGH - BLDG 2 - 1ST FLR - N 17 14APR09 06MAY09 124

15415.0201 INSTALL PLUMBING ROUGH - BLDG 2 - 1ST FLR - NEW 20 16APR09 13MAY09 70

15655.0201 INSTALL HVAC EQUIP - BLDG 2 - 1ST FLR - NEW 17 17APR09 11MAY09 109

16115.0201 INSTALL ELECTRIC ROUGH - BLDG 2 - 1ST FLR - NEW 20 21APR09 18MAY09 67

13100.0201 INSTALL INTERCOM BACKBOXES - BLDG 2 - 1ST FLR - 15 28APR09 18MAY09 67

15895.0201 INSTALL DUCTWORK INSULATION - BLDG 2 - 1ST FLR - 20 28APR09 26MAY09 113

01618.0201 INSPECT FIRE SPRINKLER ABOVE CLG - 1ST FLR - B 2 2 07MAY09 08MAY09 124

15656.0201 HVAC DUCT CONNECT/HOOK-UP - BLDG 2 - 1ST FLR - N 7 12MAY09 20MAY09 109

01614.0201 INSPECT PLUMBING - BLDG 2 - 1ST FLR - NEW 2 14MAY09 15MAY09 70

01616.0201 INSPECT ELECTRICAL ROUGH - BLDG 2 - 1ST FLR - NE 2 19MAY09 20MAY09 67

01617.0201 INSPECT FRAMING - 1ST FLR - BLDG 2 - NEW 2 21MAY09 22MAY09 67

15657.0201 HVAC PIPING CONNECT/HOOK-UP - BLDG 2 - 1ST FLR - 7 21MAY09 01JUN09 109

01615.0201 INSPECT HVAC - BLDG 2 - 1ST FLR - NEW 2 22MAY09 26MAY09 113

09250.0201 HANG DRYWALL - BLDG 2 - 1ST FLR - NEW 15 26MAY09 15JUN09 67

09251.0201 FINISH DRYWALL - BLDG 2 - 1ST FLR - NEW 15 08JUN09 26JUN09 67

09900.0201 PAINT INTERIOR PRIME COAT - BLDG 2 - 1ST FLR - N 8 29JUN09 09JUL09 67

09310.0201 INSTALL CERAMIC TILE - BLDG 2 - 1ST FLR - NEW 15 29JUN09 20JUL09 89

09901.0201 PAINT INTERIOR FINISH COAT - BLDG 2 - 1ST FLR - 15 10JUL09 30JUL09 67

06410.0201 INSTALL CABINETS - BLDG 2 - 1ST FLR - NEW 17 21JUL09 12AUG09 89

09510.0201 INSTALL ACOUSTICAL CLG GRID - BLDG 2 - 1ST FLR - 15 31JUL09 20AUG09 67

2008 2009 2010J J A S O N D J F M A M J J A S O N D J F M A M JJUL

MASONRY WALLS - CHILLER - NEW

FORM/POUR TIE COLS/BEAMS - CHILLER - NEW

SET CHILLERS/PUMPS,ETC. - CHILLER - NEW

COOLING TOWER - CHILLER - NEW

HVAC CHILLER PIPING - CHILLER - NEW

INSTALL HYDRONIC SPECIALITIES - CHILLE

HVAC - START-UP CHILLER PLANT - NEW

METAL FRAMING - TOP TRACK - BLDG 2 - 1ST FLR - N

SAWCUT CONCRETE SLAB - 1ST FLR - BLDG 2 - NEW

PLUMBING ROUGH - SLAB - 1ST FLR - BLDG 2 - NEW

ELECTRIC ROUGH - SLAB - 1ST FLR - BLDG 2 - NEW

PLACE & FINISH S.O.G. - 1ST FLR - BLDG 2 - NEW

INSTALL DUCTWORK - BLDG 2 - 1ST FLR - NEW

INSTALL METAL FRAMING - BLDG 2 - 1ST FLR - NEW

INSTALL HVAC PIPING - BLDG 2 - 1ST FLR - NEW

INSTALL FIRE SPRKLR ROUGH - BLDG 2 - 1ST FLR - N

INSTALL PLUMBING ROUGH - BLDG 2 - 1ST FLR - NE

INSTALL HVAC EQUIP - BLDG 2 - 1ST FLR - NEW

INSTALL ELECTRIC ROUGH - BLDG 2 - 1ST FLR - NE

INSTALL INTERCOM BACKBOXES - BLDG 2 - 1ST FL

INSTALL DUCTWORK INSULATION - BLDG 2 - 1ST F

INSPECT FIRE SPRINKLER ABOVE CLG - 1ST FLR - B

HVAC DUCT CONNECT/HOOK-UP - BLDG 2 - 1ST FLR

INSPECT PLUMBING - BLDG 2 - 1ST FLR - NEW

INSPECT ELECTRICAL ROUGH - BLDG 2 - 1ST FLR -

INSPECT FRAMING - 1ST FLR - BLDG 2 - NEW

HVAC PIPING CONNECT/HOOK-UP - BLDG 2 - 1ST F

INSPECT HVAC - BLDG 2 - 1ST FLR - NEW

HANG DRYWALL - BLDG 2 - 1ST FLR - NEW

FINISH DRYWALL - BLDG 2 - 1ST FLR - NEW

PAINT INTERIOR PRIME COAT - BLDG 2 - 1ST

INSTALL CERAMIC TILE - BLDG 2 - 1ST FLR

PAINT INTERIOR FINISH COAT - BLDG 2 - 1S

INSTALL CABINETS - BLDG 2 - 1ST FLR - NEW

INSTALL ACOUSTICAL CLG GRID - BLDG

© Primavera Systems, Inc.

Start Date 09JUN08

Finish Date 07JUN10

Data Date 09JUN08

Run Date 08OCT08 08:10

Early Bar

Progress Bar

Critical Activity

BASZ

HEDRICK BROTHERS CONSTRUCTIONNORTHBORO ELEMENTARY SCHOOL

Sheet 10 of 16

ORGANIZED BY AREA

Activity

ID

Activity

Description

Orig

Dur

Early

Start

Early

Finish

Total

Float

08100.0201 HANG DOORS - BLDG 2 - 1ST FLR - NEW 12 31JUL09 17AUG09 101

15940.0201 INSTALL HVAC GRILLS/TRIM - BLDG 2 - 1ST FLR - NE 12 10AUG09 25AUG09 67

16500.0201 INSTALL ELEC FIXTURES - BLDG 3 - 1ST FLR - NEW 17 10AUG09 01SEP09 67

15440.0201 INSTALL PLUMB FIXTURES - BLDG 2 - 1ST FLR - NEW 13 13AUG09 31AUG09 89

08710.0201 INSTALL FINISH HARDWARE - BLDG 2 - 1ST FLR - NEW 10 18AUG09 31AUG09 101

13129.0201 INTERCOM INSTALLATION - BLDG 2 - 1ST FLR - NEW 15 21AUG09 11SEP09 78

11132.0201 INSTALL PROJECTION SCREENS - BLDG 2 - 1ST FLR - 5 21AUG09 27AUG09 88

15980.0201 START-UP HVAC SYSTEM - BLDG 2 - 1ST FLR - NEW 5 26AUG09 01SEP09 67

10801.0201 INSTALL TOILET PARTITIONS - BLDG 2 - 1ST FLR - 7 01SEP09 10SEP09 89

08800.0201 INSTALL INTERIOR GLAZING - BLDG 2 - 1ST FLR - NE 5 01SEP09 08SEP09 96

09515.0201 INSTALL ACOUSTICAL CLG TILE - BLDG 2 - 1ST FLR - 8 02SEP09 14SEP09 67

15990.0201 PERFORM TEST & BALANCE - BLDG 2 - 1ST FLR - NEW 5 02SEP09 09SEP09 95

10800.0201 INSTALL BATH ACCESSORIES - BLDG 2 - 1ST FLR - NE 5 11SEP09 17SEP09 89

16505.0201 INSTALL ELEC TRIM - BLDG 2 - 1ST FLR - NEW 10 15SEP09 28SEP09 67

16710.0201 INSTALL SYSTEMS TRIM/DEVICES - BLDG 2 - 1ST FLR 10 15SEP09 28SEP09 67

15310.0201 INSTALL FIRE SPRKLR HEADS/TRIM - BLDG 2 - 1ST FL 7 15SEP09 23SEP09 70

10100.0201 INSTALL CHALK/TACKBOARD - BLDG 2 - 1ST FLR - NEW 8 15SEP09 24SEP09 72

10600.0201 METAL SHELVING/LOCKERS - BLDG 2 - 1ST FLR - NEW 7 15SEP09 23SEP09 85

10024.0201 INSTALL FIRE EXTINGUISHERS - BLDG 2 - 1ST FLR - 5 15SEP09 21SEP09 87

09680.0201 INSTALL CARPET/FLOORING - BLDG 2 - 1ST FLR - NEW 15 29SEP09 19OCT09 67

01690.0201 FINAL INSPECTIONS - BLDG 2 - 1ST FLR - NEW 10 20OCT09 02NOV09 67

17000.0201 CONTRACTOR COMPLETION - BLDG 2 - 1ST FLR - NEW 0 02NOV09 67

2ND FLOOR

09231.0202 METAL FRAMING - TOP TRACK - BLDG 2 - 2ND FLR - N 5 16MAR09 20MAR09 73

15890.0202 INSTALL DUCTWORK - BLDG 2 - 2ND FLR - NEW 20 23MAR09 17APR09 73

09230.0202 INSTALL METAL FRAMING - BLDG 2 - 2ND FLR - NEW 20 30MAR09 24APR09 73

15530.0202 INSTALL HVAC PIPING - BLDG 2 - 2ND FLR - NEW 17 02APR09 24APR09 83

15300.0202 INSTALL FIRE SPRKLR ROUGH - BLDG 2 - 2ND FLR - N 17 06APR09 28APR09 130

15415.0202 INSTALL PLUMBING ROUGH - BLDG 2 - 2ND FLR - NEW 20 08APR09 05MAY09 80

15655.0202 INSTALL HVAC EQUIP - BLDG 2 - 2ND FLR - NEW 17 09APR09 01MAY09 115

16115.0202 INSTALL ELECTRIC ROUGH - BLDG 2 - 2ND FLR - NEW 20 13APR09 08MAY09 73

13100.0202 INSTALL INTERCOM BACKBOXES - BLDG 2 - 2ND FLR - 15 20APR09 08MAY09 73

15895.0202 INSTALL DUCTWORK INSULATION - BLDG 2 - 2ND FLR - 20 20APR09 15MAY09 119

01618.0202 INSPECT FIRE SPRINKLER ABOVE CLG - 2ND FLR - B 2 2 29APR09 30APR09 130

15656.0202 HVAC DUCT CONNECT/HOOK-UP - BLDG 2 - 2ND FLR - N 7 04MAY09 12MAY09 115

01614.0202 INSPECT PLUMBING - BLDG 2 - 2ND FLR - NEW 2 06MAY09 07MAY09 125

01616.0202 INSPECT ELECTRICAL ROUGH - BLDG 2 - 2ND FLR - NE 2 11MAY09 12MAY09 73

2008 2009 2010J J A S O N D J F M A M J J A S O N D J F M A M JJUL

HANG DOORS - BLDG 2 - 1ST FLR - NEW

INSTALL HVAC GRILLS/TRIM - BLDG 2 -

INSTALL ELEC FIXTURES - BLDG 3 - 1ST FLR - NEW

INSTALL PLUMB FIXTURES - BLDG 2 - 1

INSTALL FINISH HARDWARE - BLDG 2 -

INTERCOM INSTALLATION - BLDG 2 - 1ST FLR - NEW

INSTALL PROJECTION SCREENS - BLDG 2 - 1ST FLR -

START-UP HVAC SYSTEM - BLDG 2 - 1ST FLR - NEW

INSTALL TOILET PARTITIONS - BLDG 2 - 1ST FLR -

INSTALL INTERIOR GLAZING - BLDG 2 - 1ST FLR - NE

INSTALL ACOUSTICAL CLG TILE - BLDG 2 - 1ST FLR -

PERFORM TEST & BALANCE - BLDG 2 - 1ST FLR - NEW

INSTALL BATH ACCESSORIES - BLDG 2 - 1ST FLR - NE

INSTALL ELEC TRIM - BLDG 2 - 1ST FLR - NEW

INSTALL SYSTEMS TRIM/DEVICES - BLDG 2 - 1ST FLR

INSTALL FIRE SPRKLR HEADS/TRIM - BLDG 2 - 1ST FL

INSTALL CHALK/TACKBOARD - BLDG 2 - 1ST FLR - NEW

METAL SHELVING/LOCKERS - BLDG 2 - 1ST FLR - NEW

INSTALL FIRE EXTINGUISHERS - BLDG 2 - 1ST FLR -

INSTALL CARPET/FLOORING - BLDG 2 - 1ST FLR - NEW

FINAL INSPECTIONS - BLDG 2 - 1ST FLR - NEW

CONTRACTOR COMPLETION - BLDG 2 - 1ST FLR - NEW

METAL FRAMING - TOP TRACK - BLDG 2 - 2ND FLR - N

INSTALL DUCTWORK - BLDG 2 - 2ND FLR - NEW

INSTALL METAL FRAMING - BLDG 2 - 2ND FLR - NEW

INSTALL HVAC PIPING - BLDG 2 - 2ND FLR - NEW

INSTALL FIRE SPRKLR ROUGH - BLDG 2 - 2ND FLR - N

INSTALL PLUMBING ROUGH - BLDG 2 - 2ND FLR - NEW

INSTALL HVAC EQUIP - BLDG 2 - 2ND FLR - NEW

INSTALL ELECTRIC ROUGH - BLDG 2 - 2ND FLR - NEW

INSTALL INTERCOM BACKBOXES - BLDG 2 - 2ND FLR

INSTALL DUCTWORK INSULATION - BLDG 2 - 2ND FL

INSPECT FIRE SPRINKLER ABOVE CLG - 2ND FLR - B 2

HVAC DUCT CONNECT/HOOK-UP - BLDG 2 - 2ND FLR

INSPECT PLUMBING - BLDG 2 - 2ND FLR - NEW

INSPECT ELECTRICAL ROUGH - BLDG 2 - 2ND FLR - N

© Primavera Systems, Inc.

Start Date 09JUN08

Finish Date 07JUN10

Data Date 09JUN08

Run Date 08OCT08 08:10

Early Bar

Progress Bar

Critical Activity

BASZ

HEDRICK BROTHERS CONSTRUCTIONNORTHBORO ELEMENTARY SCHOOL

Sheet 11 of 16

ORGANIZED BY AREA

Activity

ID

Activity

Description

Orig

Dur

Early

Start

Early

Finish

Total

Float

01617.0202 INSPECT FRAMING - 2ND FLR - BLDG 2 - NEW 2 13MAY09 14MAY09 73

15657.0202 HVAC PIPING CONNECT/HOOK-UP - BLDG 2 - 2ND FLR - 7 13MAY09 21MAY09 115

01615.0202 INSPECT HVAC - BLDG 2 - 2ND FLR - NEW 2 14MAY09 15MAY09 119

09250.0202 HANG DRYWALL - BLDG 2 - 2ND FLR - NEW 15 15MAY09 05JUN09 73

09251.0202 FINISH DRYWALL - BLDG 2 - 2ND FLR - NEW 15 29MAY09 18JUN09 73

09900.0202 PAINT INTERIOR PRIME COAT - BLDG 2 - 2ND FLR - N 8 19JUN09 30JUN09 73

09310.0202 INSTALL CERAMIC TILE - BLDG 2 - 2ND FLR - NEW 15 19JUN09 10JUL09 95

09901.0202 PAINT INTERIOR FINISH COAT - BLDG 2 - 2ND FLR - 15 01JUL09 22JUL09 73

06410.0202 INSTALL CABINETS - BLDG 2 - 2ND FLR - NEW 17 13JUL09 04AUG09 95

09510.0202 INSTALL ACOUSTICAL CLG GRID - BLDG 2 - 2ND FLR - 15 23JUL09 12AUG09 73

08100.0202 HANG DOORS - BLDG 2 - 2ND FLR - NEW 12 23JUL09 07AUG09 107

15940.0202 INSTALL HVAC GRILLS/TRIM - BLDG 2 - 2ND FLR - NE 12 31JUL09 17AUG09 73

16500.0202 INSTALL ELEC FIXTURES - BLDG 3 - 2ND FLR - NEW 17 31JUL09 24AUG09 73

15440.0202 INSTALL PLUMB FIXTURES - BLDG 2 - 2ND FLR - NEW 13 05AUG09 21AUG09 95

08710.0202 INSTALL FINISH HARDWARE - BLDG 2 - 2ND FLR - NEW 10 10AUG09 21AUG09 107

13129.0202 INTERCOM INSTALLATION - BLDG 2 - 2ND FLR - NEW 15 13AUG09 02SEP09 84

11132.0202 INSTALL PROJECTION SCREENS - BLDG 2 - 2ND FLR - 5 13AUG09 19AUG09 94

15980.0202 START-UP HVAC SYSTEM - BLDG 2 - 2ND FLR - NEW 5 18AUG09 24AUG09 73

10801.0202 INSTALL TOILET PARTITIONS - BLDG 2 - 2ND FLR - 7 24AUG09 01SEP09 95

08800.0202 INSTALL INTERIOR GLAZING - BLDG 2 - 2ND FLR - NE 5 24AUG09 28AUG09 102

09515.0202 INSTALL ACOUSTICAL CLG TILE - BLDG 2 - 2ND FLR - 8 25AUG09 03SEP09 73

15990.0202 PERFORM TEST & BALANCE - BLDG 2 - 2ND FLR - NEW 5 25AUG09 31AUG09 101

10800.0202 INSTALL BATH ACCESSORIES - BLDG 2 - 2ND FLR - NE 5 02SEP09 09SEP09 95

16505.0202 INSTALL ELEC TRIM - BLDG 2 - 2ND FLR - NEW 10 04SEP09 18SEP09 73

16710.0202 INSTALL SYSTEMS TRIM/DEVICES - BLDG 2 - 2ND FLR 10 04SEP09 18SEP09 73

15310.0202 INSTALL FIRE SPRKLR HEADS/TRIM - BLDG 2 - 2ND FL 7 04SEP09 15SEP09 76

10100.0202 INSTALL CHALK/TACKBOARD - BLDG 2 - 2ND FLR - NEW 8 04SEP09 16SEP09 78

10600.0202 METAL SHELVING/LOCKERS - BLDG 2 - 2ND FLR - NEW 7 04SEP09 15SEP09 91

10024.0202 INSTALL FIRE EXTINGUISHERS - BLDG 2 - 2ND FLR - 5 04SEP09 11SEP09 93

09680.0202 INSTALL CARPET/FLOORING - BLDG 2 - 2ND FLR - NEW 15 21SEP09 09OCT09 73

01690.0202 FINAL INSPECTIONS - BLDG 2 - 2ND FLR - NEW 10 12OCT09 23OCT09 73

17000.0202 CONTRACTOR COMPLETION - BLDG 2 - 2ND FLR - NEW 0 23OCT09 73

PARENT DROP-OFF

02200.75 EARTHWORK - PARENT DROP OFF 10 02JUL09 16JUL09 38

03300.75 COVERED WALK FTGS - PARENT DROP OFF 15 17JUL09 06AUG09 73

02720.75 STORM DRAINAGE SYSTEM - PARENT DROP OFF 5 17JUL09 23JUL09 78

2008 2009 2010J J A S O N D J F M A M J J A S O N D J F M A M JJUL

INSPECT FRAMING - 2ND FLR - BLDG 2 - NEW

HVAC PIPING CONNECT/HOOK-UP - BLDG 2 - 2ND F

INSPECT HVAC - BLDG 2 - 2ND FLR - NEW

HANG DRYWALL - BLDG 2 - 2ND FLR - NEW

FINISH DRYWALL - BLDG 2 - 2ND FLR - NEW

PAINT INTERIOR PRIME COAT - BLDG 2 - 2ND F

INSTALL CERAMIC TILE - BLDG 2 - 2ND FLR -

PAINT INTERIOR FINISH COAT - BLDG 2 - 2N

INSTALL CABINETS - BLDG 2 - 2ND FLR - NEW

INSTALL ACOUSTICAL CLG GRID - BLDG

HANG DOORS - BLDG 2 - 2ND FLR - NEW

INSTALL HVAC GRILLS/TRIM - BLDG 2 - 2

INSTALL ELEC FIXTURES - BLDG 3 - 2ND

INSTALL PLUMB FIXTURES - BLDG 2 - 2N

INSTALL FINISH HARDWARE - BLDG 2 - 2

INTERCOM INSTALLATION - BLDG 2 - 2ND FLR - NEW

INSTALL PROJECTION SCREENS - BLDG

START-UP HVAC SYSTEM - BLDG 2 - 2ND FLR - NEW

INSTALL TOILET PARTITIONS - BLDG 2 - 2ND FLR -

INSTALL INTERIOR GLAZING - BLDG 2 - 2ND FLR - NE

INSTALL ACOUSTICAL CLG TILE - BLDG 2 - 2ND FLR -

PERFORM TEST & BALANCE - BLDG 2

INSTALL BATH ACCESSORIES - BLDG 2 - 2ND FLR - NE

INSTALL ELEC TRIM - BLDG 2 - 2ND FLR - NEW

INSTALL SYSTEMS TRIM/DEVICES - BLDG 2 - 2ND FLR

INSTALL FIRE SPRKLR HEADS/TRIM - BLDG 2 - 2ND FL

INSTALL CHALK/TACKBOARD - BLDG

METAL SHELVING/LOCKERS - BLDG 2 - 2ND FLR - NEW

INSTALL FIRE EXTINGUISHERS - BLDG 2 - 2ND FLR -

INSTALL CARPET/FLOORING - BLDG 2 - 2ND FLR - NEW

FINAL INSPECTIONS - BLDG 2 - 2ND FLR - NEW

CONTRACTOR COMPLETION - BLDG 2 - 2ND FLR - NEW

EARTHWORK - PARENT DROP OFF

COVERED WALK FTGS - PARENT DROP OFF

STORM DRAINAGE SYSTEM - PARENT DROP OFF

© Primavera Systems, Inc.

Start Date 09JUN08

Finish Date 07JUN10

Data Date 09JUN08

Run Date 08OCT08 08:10

Early Bar

Progress Bar

Critical Activity

BASZ

HEDRICK BROTHERS CONSTRUCTIONNORTHBORO ELEMENTARY SCHOOL

Sheet 12 of 16

ORGANIZED BY AREA

Activity

ID

Activity

Description

Orig

Dur

Early

Start

Early

Finish

Total

Float

02510.75 STABILIZE SUBGRADE - PARENT DROP OFF 10 24JUL09 06AUG09 78

03310.75 COVERED WALK STRUCTURE - PARENT DROP OFF 15 07AUG09 27AUG09 73

02520.75 CONCRETE CURBS - PARENT DROP OFF 10 07AUG09 20AUG09 78

02810.75 IRRIGATION SLEEVES - PARENT DROP OFF 5 07AUG09 13AUG09 83

02511.75 LIMEROCK BASE - PARENT DROP OFF 10 21AUG09 03SEP09 78

16530.75 INSTALL ELEC POLES/FIXTURES - PARENT DROP OFF 10 21AUG09 03SEP09 93

03330.75 SIDEWALKS - PARENT DROP OFF 10 28AUG09 11SEP09 73

02512.75 ASPHALT PAVING - PARENT DROP OFF 10 14SEP09 25SEP09 73

02811.75 IRRIGATION - PARENT DROP OFF 10 28SEP09 09OCT09 73

02830.75 CHAIN LINK FENCING - PARENT DROP OFF 5 28SEP09 02OCT09 83

02580.75 STRIPING - PARENT DROP OFF 3 28SEP09 30SEP09 90

02900.75 LANDSCAPING/GRASSING - PARENT DROP OFF 15 05OCT09 23OCT09 73

17000.75 CONTRACTOR COMPLETION - PARENT DROP OFF 0 23OCT09 73

BUS DROP-OFF

02200.76 EARTHWORK - BUS DROP-OFF 10 10JUL09 23JUL09 38

03300.76 COVERED WALK FTGS - BUS DROP-OFF 15 24JUL09 13AUG09 68

02720.76 STORM DRAINAGE SYSTEM - BUS DROP-OFF 5 24JUL09 30JUL09 73

02510.76 STABILIZE SUBGRADE - BUS DROP-OFF 10 31JUL09 13AUG09 73

03310.76 COVERED WALK STRUCTURE - BUS DROP-OFF 15 14AUG09 03SEP09 68

02520.76 CONCRETE CURBS - BUS DROP-OFF 10 14AUG09 27AUG09 73

02810.76 IRRIGATION SLEEVES - BUS DROP-OFF 5 14AUG09 20AUG09 78

02511.76 LIMEROCK BASE - BUS DROP-OFF 10 28AUG09 11SEP09 73

16530.76 INSTALL ELEC POLES/FIXTURES - BUS DROP-OFF 10 28AUG09 11SEP09 88

03330.76 SIDEWALKS - BUS DROP-OFF 10 04SEP09 18SEP09 68

02512.76 ASPHALT PAVING - BUS DROP-OFF 10 21SEP09 02OCT09 68

02811.76 IRRIGATION - BUS DROP-OFF 10 05OCT09 16OCT09 68

02830.76 CHAIN LINK FENCING - BUS DROP-OFF 5 05OCT09 09OCT09 78

02580.76 STRIPING - BUS DROP-OFF 3 05OCT09 07OCT09 85

02900.76 LANDSCAPING/GRASSING - BUS DROP-OFF 15 12OCT09 30OCT09 68

17000.76 CONTRACTOR COMPLETION - BUS DROP-OFF 0 30OCT09 68

STAFF PARKING

02200.77 EARTHWORK - STAFF PARKING 10 17JUL09 30JUL09 38

03300.77 COVERED WALK FTGS - STAFF PARKING 15 31JUL09 20AUG09 63

02720.77 STORM DRAINAGE SYSTEM - STAFF PARKING 5 31JUL09 06AUG09 68

02510.77 STABILIZE SUBGRADE - STAFF PARKING 10 07AUG09 20AUG09 68

2008 2009 2010J J A S O N D J F M A M J J A S O N D J F M A M JJUL

STABILIZE SUBGRADE - PARENT DROP OFF

COVERED WALK STRUCTURE - PARENT DROP OFF

CONCRETE CURBS - PARENT DROP OFF

IRRIGATION SLEEVES - PARENT DROP OFF

LIMEROCK BASE - PARENT DROP OFF

INSTALL ELEC POLES/FIXTURES - PAR

SIDEWALKS - PARENT DROP OFF

ASPHALT PAVING - PARENT DROP OFF

IRRIGATION - PARENT DROP OFF

CHAIN LINK FENCING - PARENT DROP OFF

STRIPING - PARENT DROP OFF

LANDSCAPING/GRASSING - PARENT DROP OFF

CONTRACTOR COMPLETION - PARENT DROP OFF

EARTHWORK - BUS DROP-OFF

COVERED WALK FTGS - BUS DROP-OFF

STORM DRAINAGE SYSTEM - BUS DROP-OFF

STABILIZE SUBGRADE - BUS DROP-OFF

COVERED WALK STRUCTURE - BUS DROP-OFF

CONCRETE CURBS - BUS DROP-OFF

IRRIGATION SLEEVES - BUS DROP-OFF

LIMEROCK BASE - BUS DROP-OFF

INSTALL ELEC POLES/FIXTURES - BUS DROP-OFF

SIDEWALKS - BUS DROP-OFF

ASPHALT PAVING - BUS DROP-OFF

IRRIGATION - BUS DROP-OFF

CHAIN LINK FENCING - BUS DROP-OFF

STRIPING - BUS DROP-OFF

LANDSCAPING/GRASSING - BUS DROP-OFF

CONTRACTOR COMPLETION - BUS DROP-OFF

EARTHWORK - STAFF PARKING

COVERED WALK FTGS - STAFF PARKING

STORM DRAINAGE SYSTEM - STAFF PARKING

STABILIZE SUBGRADE - STAFF PARKING

© Primavera Systems, Inc.

Start Date 09JUN08

Finish Date 07JUN10

Data Date 09JUN08

Run Date 08OCT08 08:10

Early Bar

Progress Bar

Critical Activity

BASZ

HEDRICK BROTHERS CONSTRUCTIONNORTHBORO ELEMENTARY SCHOOL

Sheet 13 of 16

ORGANIZED BY AREA

Activity

ID

Activity

Description

Orig

Dur

Early

Start

Early

Finish

Total

Float

03310.77 COVERED WALK STRUCTURE - STAFF PARKING 15 21AUG09 11SEP09 63

02520.77 CONCRETE CURBS - STAFF PARKING 10 21AUG09 03SEP09 68

02810.77 IRRIGATION SLEEVES - STAFF PARKING 5 21AUG09 27AUG09 73

02511.77 LIMEROCK BASE - STAFF PARKING 10 04SEP09 18SEP09 68

16530.77 INSTALL ELEC POLES/FIXTURES - STAFF PARKING 10 04SEP09 18SEP09 83

03330.77 SIDEWALKS - STAFF PARKING 10 14SEP09 25SEP09 63

02512.77 ASPHALT PAVING - STAFF PARKING 10 28SEP09 09OCT09 63

02811.77 IRRIGATION - STAFF PARKING 10 12OCT09 23OCT09 63

02830.77 CHAIN LINK FENCING - STAFF PARKING 5 12OCT09 16OCT09 73

02580.77 STRIPING - STAFF PARKING 3 12OCT09 14OCT09 80

02900.77 LANDSCAPING/GRASSING - STAFF PARKING 15 19OCT09 06NOV09 63

17000.77 CONTRACTOR COMPLETION - STAFF PARKING 0 06NOV09 63

VISITOR PARKING

02200.78 EARTHWORK - VISITOR PARKING 10 31JUL09 13AUG09 38

03300.78 COVERED WALK FTGS - VISITOR PARKING 15 14AUG09 03SEP09 53

02720.78 STORM DRAINAGE SYSTEM - VISITOR PARKING 5 14AUG09 20AUG09 58

02510.78 STABILIZE SUBGRADE - VISITOR PARKING 10 21AUG09 03SEP09 58

03310.78 COVERED WALK STRUCTURE - VISITOR PARKING 15 04SEP09 25SEP09 53

02520.78 CONCRETE CURBS - VISITOR PARKING 10 04SEP09 18SEP09 58

02810.78 IRRIGATION SLEEVES - VISITOR PARKING 5 04SEP09 11SEP09 63

02511.78 LIMEROCK BASE - VISITOR PARKING 10 21SEP09 02OCT09 58

16530.78 INSTALL ELEC POLES/FIXTURES - VISITOR PARKING 10 21SEP09 02OCT09 73

03330.78 SIDEWALKS - VISITOR PARKING 10 28SEP09 09OCT09 53

02512.78 ASPHALT PAVING - VISITOR PARKING 10 12OCT09 23OCT09 53

02811.78 IRRIGATION - VISITOR PARKING 10 26OCT09 06NOV09 53

02830.78 CHAIN LINK FENCING - VISITOR PARKING 5 26OCT09 30OCT09 63

02580.78 STRIPING - VISITOR PARKING 3 26OCT09 28OCT09 70

02900.78 LANDSCAPING/GRASSING - VISITOR PARKING 15 02NOV09 20NOV09 53

17000.78 CONTRACTOR COMPLETION - VISITOR PARKING 0 20NOV09 53

SERVICE YARD/STAFF PARKING

02200.79 EARTHWORK - SERVICE YARD/PARKING 10 14AUG09 27AUG09 38

02720.79 STORM DRAINAGE SYSTEM - SERVICE YARD/PARKING 5 28AUG09 03SEP09 48

02510.79 STABILIZE SUBGRADE - SERVICE YARD/PARKING 10 04SEP09 18SEP09 48

03330.79 SIDEWALKS - SERVICE YARD/PARKING 10 14SEP09 25SEP09 63

02520.79 CONCRETE CURBS - SERVICE YARD/PARKING 10 21SEP09 02OCT09 48

2008 2009 2010J J A S O N D J F M A M J J A S O N D J F M A M JJUL

COVERED WALK STRUCTURE - STAFF PARKING

CONCRETE CURBS - STAFF PARKING

IRRIGATION SLEEVES - STAFF PARKING

LIMEROCK BASE - STAFF PARKING

INSTALL ELEC POLES/FIXTURES - STAFF PARKING

SIDEWALKS - STAFF PARKING

ASPHALT PAVING - STAFF PARKING

IRRIGATION - STAFF PARKING

CHAIN LINK FENCING - STAFF PARKING

STRIPING - STAFF PARKING

LANDSCAPING/GRASSING - STAFF PARKING

CONTRACTOR COMPLETION - STAFF PARKING

EARTHWORK - VISITOR PARKING

COVERED WALK FTGS - VISITOR PARKING

STORM DRAINAGE SYSTEM - VISITOR PARKING

STABILIZE SUBGRADE - VISITOR PARKING

COVERED WALK STRUCTURE - VISITOR PARKING

CONCRETE CURBS - VISITOR PARKING

IRRIGATION SLEEVES - VISITOR PARKING

LIMEROCK BASE - VISITOR PARKING

INSTALL ELEC POLES/FIXTURES - VISITOR PARKING

SIDEWALKS - VISITOR PARKING

ASPHALT PAVING - VISITOR PARKING

IRRIGATION - VISITOR PARKING

CHAIN LINK FENCING - VISITOR PARKING

STRIPING - VISITOR PARKING

LANDSCAPING/GRASSING - VISITOR PARKING

CONTRACTOR COMPLETION - VISITOR PARKING

EARTHWORK - SERVICE YARD/PARKING

STORM DRAINAGE SYSTEM - SERVICE YARD/PARKING

STABILIZE SUBGRADE - SERVICE YARD/PARKING

SIDEWALKS - SERVICE YARD/PARKING

CONCRETE CURBS - SERVICE YARD/PARKING

© Primavera Systems, Inc.

Start Date 09JUN08

Finish Date 07JUN10

Data Date 09JUN08

Run Date 08OCT08 08:10

Early Bar

Progress Bar

Critical Activity

BASZ

HEDRICK BROTHERS CONSTRUCTIONNORTHBORO ELEMENTARY SCHOOL

Sheet 14 of 16

ORGANIZED BY AREA

Activity

ID

Activity

Description

Orig

Dur

Early

Start

Early

Finish

Total

Float

02810.79 IRRIGATION SLEEVES - SERVICE YARD/PARKING 5 21SEP09 25SEP09 53

02511.79 LIMEROCK BASE - SERVICE YARD/PARKING 10 05OCT09 16OCT09 48

16530.79 INSTALL ELEC POLES/FIXTURES - SERVICE YARD/PARKI 10 05OCT09 16OCT09 63

02512.79 ASPHALT PAVING - SERVICE YARD/PARKING 10 19OCT09 30OCT09 48

02811.79 IRRIGATION - SERVICE YARD/PARKING 10 02NOV09 13NOV09 48

02830.79 CHAIN LINK FENCING - SERVICE YARD/PARKING 5 02NOV09 06NOV09 58

02580.79 STRIPING - SERVICE YARD/PARKING 3 02NOV09 04NOV09 65

02900.79 LANDSCAPING/GRASSING - SERVICE YARD/PARKING 15 09NOV09 30NOV09 48

17000.79 CONTRACTOR COMPLETION - SERVICE YARD/PARKING 0 30NOV09 48

PLAYCOURTS

02200.80 DEMO/CLEARING/EARTHWORK - HARDCOURTS 10 24JUL09 06AUG09 42

16101.80 ELECTRICAL U\G R-I - HARDCOURTS 7 07AUG09 17AUG09 54

02512.80 HARDCOURT SURFACE - HARDCOURTS 10 18AUG09 31AUG09 54

16530.80 ELECTRICAL POLES/FIXTURES - HARDCOURTS 7 01SEP09 10SEP09 54

02890.80 ATHLETIC SURFACE - HARDCOURTS 10 11SEP09 24SEP09 54

02830.80 CHAIN LINK FENCING - HARDCOURTS 10 25SEP09 08OCT09 54

02811.80 IRRIGATION - HARDCOURTS 12 30SEP09 15OCT09 54

02900.80 LANDSCAPING/GRASSING - HARDCOURTS 15 16OCT09 05NOV09 54

11485.80 ATHLETIC EQUIPMENT - HARDCOURTS 10 06NOV09 19NOV09 54

17000.80 CONTRACTOR COMPLETION - HARDCOURTS 0 19NOV09 54

COURTYARDS & COVERED PLAY AREA

02200.82 EARTHWORK - COURTYARD 10 07AUG09 20AUG09 42

02720.82 STORM DRAINAGE - COURTYARD 15 21AUG09 11SEP09 42

16101.82 ELECTRICAL U\G R-I - COURTYARD 15 14SEP09 02OCT09 42

02810.82 IRRIGATION SLEEVES - COURTYARD 4 29SEP09 02OCT09 42

03310.82 CONC WALKS - COURTYARD 15 05OCT09 23OCT09 42

16140.82 ELECTRICAL WIRE/CABLE - COURTYARD 15 05OCT09 23OCT09 47

03300.82 CONC PLANTER WALLS -COURTYARD 10 05OCT09 16OCT09 52

02550.82 UNIT PAVERS - COURTYARD 15 26OCT09 13NOV09 42

02811.82 IRRIGATION - COURTYARD 10 26OCT09 06NOV09 47

16530.82 ELECTRICAL POLES/FIXTURES - COURTYARD 10 26OCT09 06NOV09 47

10005.82 INSTALL FLAG POLE - COURTYARD 5 26OCT09 30OCT09 52

03320.82 CONC BENCHES - COURTYARD 5 26OCT09 30OCT09 68

02900.82 LANDSCAPING - COURTYARD 16 16NOV09 08DEC09 42

17000.82 CONTRACTOR COMPLETION - COURTYARD 0 08DEC09 42

2008 2009 2010J J A S O N D J F M A M J J A S O N D J F M A M JJUL

IRRIGATION SLEEVES - SERVICE YARD/PARKING

LIMEROCK BASE - SERVICE YARD/PARKING

INSTALL ELEC POLES/FIXTURES - SERVICE YARD/PARKI

ASPHALT PAVING - SERVICE YARD/PARKING

IRRIGATION - SERVICE YARD/PARKING

CHAIN LINK FENCING - SERVICE YARD/PARKING

STRIPING - SERVICE YARD/PARKING

LANDSCAPING/GRASSING - SERVICE YARD/PARKING

CONTRACTOR COMPLETION - SERVICE YARD/PARKING

DEMO/CLEARING/EARTHWORK - HARDCOURTS

ELECTRICAL U\G R-I - HARDCOURTS

HARDCOURT SURFACE - HARDCOURTS

ELECTRICAL POLES/FIXTURES - HARDCOURTS

ATHLETIC SURFACE - HARDCOURTS

CHAIN LINK FENCING - HARDCOURTS

IRRIGATION - HARDCOURTS

LANDSCAPING/GRASSING - HARDCOURTS

ATHLETIC EQUIPMENT - HARDCOURTS

CONTRACTOR COMPLETION - HARDCOURTS

EARTHWORK - COURTYARD

STORM DRAINAGE - COURTYARD

ELECTRICAL U\G R-I - COURTYARD

IRRIGATION SLEEVES - COURTYARD

CONC WALKS - COURTYARD

ELECTRICAL WIRE/CABLE - COURTYARD

CONC PLANTER WALLS -COURTYARD

UNIT PAVERS - COURTYARD

IRRIGATION - COURTYARD

ELECTRICAL POLES/FIXTURES - COURTYARD

INSTALL FLAG POLE - COURTYARD

CONC BENCHES - COURTYARD

LANDSCAPING - COURTYARD

CONTRACTOR COMPLETION - COURTYARD

© Primavera Systems, Inc.

Start Date 09JUN08

Finish Date 07JUN10

Data Date 09JUN08

Run Date 08OCT08 08:10

Early Bar

Progress Bar

Critical Activity

BASZ

HEDRICK BROTHERS CONSTRUCTIONNORTHBORO ELEMENTARY SCHOOL

Sheet 15 of 16

ORGANIZED BY AREA

Activity

ID

Activity

Description

Orig

Dur

Early

Start

Early

Finish

Total

Float

OFF-SITE - FLAGLER

02200.81 CLEARING & EARTHWORK - OFF-SITE - FLAGLER 10 28AUG09 11SEP09 38

02720.81 STORM DRAINAGE - OFF-SITE - FLAGLER 10 14SEP09 25SEP09 38

02510.81 STABILIZATION - OFF-SITE - FLAGLER 10 28SEP09 09OCT09 38

02511.81 LIMEROCK BASE - OFF-SITE - FLAGLER 15 12OCT09 30OCT09 38

02520.81 CONCRETE CURBS - OFF-SITE - FLAGLER 15 02NOV09 20NOV09 38

02512.81 ASPHALT PAVING - OFF-SITE - FLAGLER 10 23NOV09 07DEC09 38

02580.81 STRIPING & SIGNAGE - OFF-SITE - FLAGLER 5 08DEC09 14DEC09 38

02900.81 GRASSING/SOD - OFF-SITE - FLAGLER 5 08DEC09 14DEC09 38

17000.81 CONTRACTOR COMPLETION - OFF-SITE - FLAGLER 0 14DEC09 38

COMPLETION

17000.02 SUBSTANTIAL COMPLETION - PHASE 2 0 08FEB10 0

17100.02 PUNCHLIST & CLOSEOUT 84 09FEB10 07JUN10 0

17200.02 FINAL COMPLETION 0 07JUN10 0

2008 2009 2010J J A S O N D J F M A M J J A S O N D J F M A M JJUL

CLEARING & EARTHWORK - OFF-SITE - FLAGLER

STORM DRAINAGE - OFF-SITE - FLAGLER

STABILIZATION - OFF-SITE - FLAGLER

LIMEROCK BASE - OFF-SITE - FLAGLER

CONCRETE CURBS - OFF-SITE - FLAGLER

ASPHALT PAVING - OFF-SITE - FLAGLER

STRIPING & SIGNAGE - OFF-SITE - FLAGLER

GRASSING/SOD - OFF-SITE - FLAGLER

CONTRACTOR COMPLETION - OFF-SITE - FLAGLER

SUBSTANTIAL COMPLETION - PHASE 2

PUNCHLIST & CLOSEOUT

FINAL COMPLETION

© Primavera Systems, Inc.

Start Date 09JUN08

Finish Date 07JUN10

Data Date 09JUN08

Run Date 08OCT08 08:10

Early Bar

Progress Bar

Critical Activity

BASZ

HEDRICK BROTHERS CONSTRUCTIONNORTHBORO ELEMENTARY SCHOOL

Sheet 16 of 16

ORGANIZED BY AREA