2
Project components include: Build 2 miles of double-circuit 138-kilovolt (kV) transmission line. Build 1 mile of double-circuit 69 kV transmission line. Build a new substation. Acquire an approximate 100-foot-wide right-of-way from landowners. Remove Cliffview Substation. The need for the Glendale Area Improvements project was identified in PJM Interconnection’s 2021 Winter Analysis. The study found the need for increased power supply to support demand during extreme weather conditions. PJM Interconnection is the regional transmission organization that monitors the electric grid in 13 states, including Virginia. Building new transmission infrastructure will strengthen the local grid and reduce the likelihood of outages. The project area includes the proposed substation site off Glendale Road and study segments that cross Creekview Drive and continue for about a mile before connecting to an existing transmission line. WHAT WHY WHERE GLENDALE AREA IMPROVEMENTS PROJECT Appalachian Power plans to increase electric reliability by making upgrades to the transmission system in southwest Virginia. The Glendale Area Improvements Project includes building approximately 3 miles of new transmission line, a new substation and removing an existing substation to reduce the likelihood of customer outages. Later this year, Appalachian Power will file an application with the Virginia State Corporation Commis- sion seeking approval for the project. If approved, construction is expected to start in early 2020 and be complete by the summer of 2021. Estimated budget for the project is $40 million. PROJECT SCHEDULE DATA GATHERING BEGINS February 2018 PROJECT OPEN HOUSE August 2018 APPLICATION TO BE FILED WITH THE SCC* October 2018 TREE CLEARING/PRE-CONSTRUCTION BEGINS February 2020 PROJECT IN-SERVICE June 2021 SUBSTATION CONSTRUCTION BEGINS March 2020 TRANSMISSION LINE CONSTRUCTION BEGINS April 2020 ANTICIPATED APPROVAL FROM THE SCC* June 2019 RIGHT-OF-WAY ACQUISITION BEGINS August 2019 PROJECT ANNOUNCEMENT July 2018 INCORPORATE PUBLIC INPUT & DEVELOP LINE ROUTE September 2018 *Timeline subject to change. *Timeline subject to change. *SCC: Virginia State Corporation Commission *SCC: Virginia State Corporation Commission 2018 2019 2021 2020 2022

Glendale Factsheet V15 - American Electric Power€¦ · The Glendale Area Improvements Project includes building approximately 3 miles of new transmission line, a new substation

  • Upload
    others

  • View
    4

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Glendale Factsheet V15 - American Electric Power€¦ · The Glendale Area Improvements Project includes building approximately 3 miles of new transmission line, a new substation

Project components include:

• Build 2 miles of double-circuit 138-kilovolt

(kV) transmission line.

• Build 1 mile of double-circuit 69 kV

transmission line.

• Build a new substation.

• Acquire an approximate 100-foot-wide

right-of-way from landowners.

• Remove Cliffview Substation.

The need for the Glendale Area Improvements

project was identified in PJM Interconnection’s

2021 Winter Analysis. The study found the need

for increased power supply to support demand

during extreme weather conditions. PJM

Interconnection is the regional transmission

organization that monitors the electric grid in 13

states, including Virginia. Building new

transmission infrastructure will strengthen the

local grid and reduce the likelihood of outages.

The project area includes the proposed

substation site off Glendale Road and study

segments that cross Creekview Drive and

continue for about a mile before connecting to

an existing transmission line.

WHAT WHY WHERE

GLENDALEAREA IMPROVEMENTS PROJECT

Appalachian Power plans to increase electric reliability by

making upgrades to the transmission system in southwest

Virginia. The Glendale Area Improvements Project includes

building approximately 3 miles of new transmission line, a new

substation and removing an existing substation to reduce the

likelihood of customer outages. Later this year, Appalachian Power

will file an application with the Virginia State Corporation Commis-

sion seeking approval for the project. If approved, construction is

expected to start in early 2020 and be complete by the summer of

2021. Estimated budget for the project is $40 million.

PROJECT SCHEDULE

DATA GATHERING BEGINSFebruary 2018

PROJECT OPEN HOUSEAugust 2018

APPLICATION TO BE FILED WITH THE SCC*October 2018

TREE CLEARING/PRE-CONSTRUCTION BEGINSFebruary 2020

PROJECT IN-SERVICEJune 2021

SUBSTATION CONSTRUCTION BEGINSMarch 2020TRANSMISSION LINE CONSTRUCTION BEGINSApril 2020

ANTICIPATED APPROVAL FROM THE SCC*June 2019RIGHT-OF-WAY ACQUISITION BEGINSAugust 2019

PROJECT ANNOUNCEMENTJuly 2018

INCORPORATE PUBLIC INPUT & DEVELOP LINE ROUTESeptember 2018

*Timeline subject to change.*Timeline subject to change. *SCC: Virginia State Corporation Commission*SCC: Virginia State Corporation Commission

2018 2019 20212020 2022

Page 2: Glendale Factsheet V15 - American Electric Power€¦ · The Glendale Area Improvements Project includes building approximately 3 miles of new transmission line, a new substation

*Exact structure, height and right-of-way requirements may vary

*To view a map of the transmission line to be retired visit the website.

735

721

58

E STUART DR

E STUART DR

GLEN

DALE

RD

GLEN

DALE

RD

CREEKVIEW DRCREEKVIEW DR

FRIES

RD

FRIES

RD

HEBRON

RDH

EBRON RD

CRANBERRY RD

CRANBERRY RD

CARROLL COUNTYCARROLL COUNTY

APPALACHIAN POWER VALUES YOUR INPUT ABOUT THIS PROJECT. PLEASE SEND COMMENTS AND QUESTIONS TO:

07/05/201807/05/2018

Appalachian Power will use galvanized steel double-circuit lattice tower structures and monopole structures to construct the new transmission lines. Proposed structures will vary depending on location. Structure Height: Approximately 110 feetRight-of-Way Width: Approximately 100 feet

TYPICAL STRUCTURES

*Substation shown is a general depiction of the proposed facility that will be built for this project. It does not represent final design.

Substations serve as electrical intersections converting the power to voltage levels for use in homes, businesses and industrial facilities.

TYPICAL SUBSTATIONS

CORTNEY MUSTARDProject Outreach [email protected]/Glendale

EXISTING TRANSMISSION LINES

STUDY SEGMENTS FOR 138 KV TRANSMISSION LINE

STUDY SEGMENTS FOR 69 KV TRANSMISSION LINE

N

GLENDALE AREA IMPROVEMENTS PROJECT

PROPOSED SUBSTATION

SUBSTATION TO BE REMOVED

CLIFFVIEWSUBSTATION

CITY OF GALAXCITY OF GALAX

LATTICE TOWER STRUCTURE MONOPOLE STRUCTURE