5
GLAST LAT Project DOE/NASA Review, March 31, 2004 1 GLAST Large Area GLAST Large Area Telescope: Telescope: Lowell A. Klaisner Stanford Linear Accelerator Center Project Manager [email protected] 650-926-2726 Gamma-ray Large Gamma-ray Large Area Space Area Space Telescope Telescope Summary Summary April 1, 2004 April 1, 2004

GLAST LAT Project DOE/NASA Review, March 31, 2004 1 GLAST Large Area Telescope: Lowell A. Klaisner Stanford Linear Accelerator Center Project Manager [email protected]

Embed Size (px)

Citation preview

Page 1: GLAST LAT Project DOE/NASA Review, March 31, 2004 1 GLAST Large Area Telescope: Lowell A. Klaisner Stanford Linear Accelerator Center Project Manager Klaisner@slac.stanford.edu

GLAST LAT Project DOE/NASA Review, March 31, 2004

1

GLAST Large Area Telescope:GLAST Large Area Telescope:

Lowell A. KlaisnerStanford Linear Accelerator CenterProject Manager

[email protected]

Gamma-ray Large Gamma-ray Large Area Space Area Space TelescopeTelescope SummarySummary

April 1, 2004April 1, 2004

Page 2: GLAST LAT Project DOE/NASA Review, March 31, 2004 1 GLAST Large Area Telescope: Lowell A. Klaisner Stanford Linear Accelerator Center Project Manager Klaisner@slac.stanford.edu

GLAST LAT Project DOE/NASA Review, March 31, 2004

2

MCM Burn-In & Test

Apr 29, 2004

Tower Assembly & Test

Jul 7, 2004

Tower ARFI

Aug 18, 2004

Working Critical Path, 3/31/04Working Critical Path, 3/31/04

Tower 14RFI

Feb 15, 2005

LAT Assembly Complete

Apr 8, 2005

System Test Complete

Jun 28, 2005

Environmental Test Complete

November 12 2005

LATRFI

November 12, 2005

Pre-ship/CD-4 Review

June 29, 2005

This critical path based on Tracker estimates presented March 31, 2004.

The schedule after Tower A will be worked to mitigate the resulting delay in LAT RFI.

Page 3: GLAST LAT Project DOE/NASA Review, March 31, 2004 1 GLAST Large Area Telescope: Lowell A. Klaisner Stanford Linear Accelerator Center Project Manager Klaisner@slac.stanford.edu

GLAST LAT Project DOE/NASA Review, March 31, 2004

3

Mitigating late module arrivalMitigating late module arrival

• The project is focusing on integration and test of the first tower. The following are areas to work as we learn more about actual performance– I&T can use the additional time for more training and

testing to reduce risk in integration and improve productivity.

– Some part of System Test could be moved earlier and tested with a partial LAT configuration

– System Test Period is 2 Shift/5 Days, could be up to 3 Shift/7 Days

– Increase the production rate of modules by working second shifts, etc.

– Investigate compressing the environmental test schedule from the present 15 weeks

Page 4: GLAST LAT Project DOE/NASA Review, March 31, 2004 1 GLAST Large Area Telescope: Lowell A. Klaisner Stanford Linear Accelerator Center Project Manager Klaisner@slac.stanford.edu

GLAST LAT Project DOE/NASA Review, March 31, 2004

4

SummarySummary

• The LAT is a challenging instrument

• Significant technical progress -- no major issues outstanding

• Producing flight hardware

• Overall project funding is adequate if stay on schedule

• Funding in the current fiscal year is an issue being worked

• Schedule is challenging

– Focusing on installation of the first flight tower in the grid

– Mitigating delays as they occur

• Delay in completing Grid design – Qualify 2nd grid

• Delay in arrival of CAL ASICs -- Load parts before qualification

• Tracker delay due to test anomalies – Proceed with fabrication before testing is complete

• Project management needs to be proactive in identifying plans to mitigate potential future schedule delays

• A strong, talented staff that is committed to delivering this instrument and doing the science

Page 5: GLAST LAT Project DOE/NASA Review, March 31, 2004 1 GLAST Large Area Telescope: Lowell A. Klaisner Stanford Linear Accelerator Center Project Manager Klaisner@slac.stanford.edu

GLAST LAT Project DOE/NASA Review, March 31, 2004

5

GLAST Feb 2007 launch