Upload
venkatws1
View
1.805
Download
1
Embed Size (px)
Citation preview
1
Gas Insulated SwitchgearJuly 16, 2010Kerala State Electricity Board, Kozhikode
1Name : Ankur Aggarwal Division : EPD Category : General
2
ContentsIntroductionWhy only SF6 GasMain Drivers for GIS ApplicationProduct Development CycleCharacteristics of Gas Insulated SwitchgearsMain Parts of GIS
Primary ComponentsGas Compartments
Sealing System of GISPressure LevelsEarthing SystemSecondary Control SystemDelivery & StorageErection of GISCommissioning of GISGIS Testing at SiteInspection & Maintenance of GISHybrid Sub StationComparison of AIS & GISLife Cycle Cost AnalysisSafety & Security IssuesPartial DischargeMaintenance (Typical)
33
INTRODUCTION
4
INTRODUCTION
What is GIS????GIS stands for GAS INSULATED SWITCHGEARA metal enclosed switchgear in which the insulation is obtained, at least partly, by an insulating gas other than airat atmospheric pressure (IEC 62271-203)
This term generally applies to High Voltage SwitchgearsThe gas used is generally SF6 or SF6 mixtures
Considering that the basic aspect of substation design i.e. installation, operation, maintenance and extension is possible with a maximum of one circuit and one section of bus bar out of service simultaneously.
5
INTRODUCTION
GIS using SF6 is now a well established technology and have been in service since the 1960’s.GIS Technology is typically of modular design and filled with a minimum quantity of SF6.GIS can have low life cycle cost compared to AIS and can be used for indoor as well as outdoor applications.There has been a rapid growth in the application of this technology with an estimated 80,000 bays now in service and increasing at a rate of over 6,000 bays per year. (Source CIGRE Working Group B3.17 report 381 June 2009)
6
INTRODUCTION
The Gas Insulated Switchgear has got hermetically sealed cast aluminum enclosures, flanges, covers and aluminum castings.
The GIS is built up from modular units which are designed not to burn through in the event of an internal arcing in the time limited by the recommendation of IEC 62271-203.
The modules join to each other with flanges.
The live parts are supported by epoxy resin based insulator discs which always can be found between flanges of the neighbor modular units.
7
INTRODUCTION
The key advantages that GIS can offer of compactness, immunity from environmental conditions and reliability are well understood and documented.
In today’s environment where assessments of capital projects are made on a total life time basis; there GIS can be the most cost effective solution in comparison with AIS.
Life Cycle Cost (LCC) assessments are enabling the one perceived disadvantages of GIS, i.e. its higher initial cost, to be overcome.
With this background, GIS technology is expected to become the preferred choice of many users in the future.
88
WHY ONLY SF6 GAS
9
WHY ONLY SF6 GAS
SF6 Gas is a colorless, odourless, non-toxic, non-flammable synthetic gas.SF6 Gas is around 5 times heavier than air and is among one of the heaviest known gases.Under normal conditions SF6 gas is chemically inert & stable; its reactivity is among the lowest of all substances.The excellent insulating properties of SF6 are resulting from tothe strong electron affinity (electro-negativity) of the molecule.This is based on two mechanisms a) resonance capture and b) dissociative attachment of electrons, in accordance with the equations:
10
WHY ONLY SF6 GASSF6 Gas break down is possible only at relatively high field strengths.
The breakdown voltage at 50Hz & 1 Bar in a homogenous field is around 2.5 to 3 times higher than the corresponding values of air or nitrogen.
On account of its thermal properties and low ionisation temperature SF6 exhibits outstanding characteristics for extinguishing the electric arcs.
The arc quenching time using SF6 gas is around 100 times less than that using the air.
1111
MAIN DRIVERS FOR GIS APPLICATION
12
MAIN DRIVERS
Short Planning, Delivery & Installation RequirementsHigh Level of Reliability & AvailabilityMinimal Maintenance EffortsHigh Degree of Safety for Operating PersonnelLong Operating Life > 50 YearsFactory Pre Assembled and Tested UnitsProtection from Environmental ConditionsCustomer Tailored Solution due to modular designsExtension of AIS under operation or restricted space availabilitySimple constructionRestricted Space AvailabilityHigh Land Acquisition Costs
1313
PRODUCT DEVELOPMENT CYCLE
14
GIS PRODUCT DEVELOPMENT CYCLE
CIGRE Report on GIS Product Development Cycle
1515
CHARACTERISTICS OF GIS
16
CHARACTERISTICS OF GIS
Compact space saving design with uncomplicated foundations.
Minimal weight by light weight construction through the use of aluminum housings and use of computer aided design tools to optimize the shape and size.
Complete safety to the personnel under all operating and fault conditions based on new manufacturing methods and quality control procedures.
• Environmental compatibility enables no restrictions on choice of location by means of minimum space requirement, low noise emission and effective gas tightness using sealing systems with guaranteed leakage rates < 0.5% p.a. per gas compartment.
17
CHARACTERISTICS OF GIS
Economical transport of several bays connected together as maximum possible shipping unit.
Minimal operating cost of practically maintenance free equipment, designed for extremely long service life up to 50 years. This ensures that first inspection will not be necessary until after 25 years of operation, however depending upon the status of the switchgear.
Highest reliability by a product concept which includes most modern design tools, development programs and appropriate quality control measures.
Easy and efficient installation and commissioning with transport units already fully assembled and tested in the factory, pre-filled with SF6 gas at reduced pressure.
18
CHARACTERISTIC OF GIS
Technology Design
Insulation Insulating Medium
Enclosure
AIS Technology
External Insulation
Air, SF6 Gas Live PorcelainOr
Composite InsulatorsGIS
TechnologyGas
InsulationSF6 or SF6
MixturesMetal Enclosures
(Aluminum) effectively earthed
Hybrid Technology
Mixed Insulation
SF6 or Sf6 Mixtures and
Air
Permutation & Combination of all
1919
MAIN PARTS OF GIS
2020
PRIMARY COMPONENTS
21
PRIMARY COMPONENTS
Isolator
CB PT
CT
Bus Bar
22
PRIMARY COMPONENTS
23
PRIMARY COMPONENTS
24
PRIMARY COMPONENTS
25
PRIMARY COMPONENTS
26
PRIMARY COMPONENTS
1-Phase Bus Bar with Connecting Element
27
PRIMARY COMPONENTS
28
PRIMARY COMPONENTS
29
PRIMARY COMPONENTS
30
PRIMARY COMPONENTS
3131
GAS COMPARTMENTS
32
GAS COMPARTMENTS
GIS contains several independent gas compartments.
The internal barriers between the gas compartments are provided by solid insulator discs.
The system gives possibility
For decreasing gas losses
For restriction of damages caused by fault arc
For reducing the time of gas manipulations
Different gas compartments contains usually different gas volumes
33
GAS COMPARTMENTS
34
GAS COMPARTMENTS
All the gas compartments include the following basic parts:
A Metal Rupture disc assembly with deflector cover (as PRD)
A temperature compensated contact manometer for continuous monitoring of internal gas pressure
A set of gas connection valves
A set of gas filters
These basic parts basically act as safety and security devices for satisfactory performance of GIS during actual site conditions.
3535
SEALING SYSTEM OF GIS
36
SEALING SYSTEM OF GIS
GIS represents closed pressure system
Gas leakage rates are < 0.5% p.a. i.e. a undisturbed life of 20 years is guaranteed for GIS before the gas has to be replenished.
GIS is built in modular units (for single phase design) which are joined with each other through flanges.
Epoxy resin insulator discs are placed between the flanges of the neighboring units to support the live parts.
To ensure static gas tight sealing ethylene-propylene rubber rings are placed.
37
SEALING SYSTEM OF GIS
3838
PRESSURE LEVELS
39
PRESSURE LEVELS
GIS uses SF6 gas as insulation & arc quenching material.
Therefore pressure in puffer type circuit breaker is high because of better arc quenching properties.
The figure shown below depicts the various pressure levels and their relationship as specified and governed by various IEC and IN Standards.
However, the exact pressure values are not fixed and vary from manufacturer to manufacturer and specifically design wise orientation in pressure values is also more or less applicable.
40
PRESSURE LEVELS (IEC 62271-203)
41
PRESSURE LEVELS GAI3 245 kV
42
PRESSURE LEVELS GT01 145 kV
43
PRESSURE LEVELS
• Design Pressure:– Abstract value used at determining the wall
thickness of enclosure elements.– It is valid at the design temperature which is the
average of the permissible temperatures of the active parts and the enclosures.
– According to IEC 62271- 1, the maximum temperature for silver coated contacts in SF6 is 105 deg C and for accessible parts expected to be touched in normal operation is 70 deg C.
– Therefore the design temperature shall be (105+70)/2 = 87.5 deg C
44
PRESSURE LEVELS
• Rated Filling Pressure:– This is the actual working value on which the
equipment is filled up under normal conditions.– It is valid at 20 deg C gas temperature– Some Type Tests are performed at rated gas
pressure like gas tightness test, mechanical endurance test, internal arc test and inductive current breaking capacity test.
• Alarm Pressure:– This value is approximately 90% of the rated value.– This is basically the setting level for the first step of
gas protection– At this value the gas monitoring device and relay
gives alarm signal for refilling.
45
PRESSURE LEVELS
• Minimum Functional/ Lock Out Pressure:– The minimum permissible pressure of the equipment.– Dielectric Test, Switching Test & Temperature rise test
are performed at this value.– If the pressure falls under this value the second level of
gas protection has to provide the electrical isolation of the defected gas compartment.
• Routine Test & Bursting Test Pressure:– RTP = k x Design Pressure– Where k = 1.3 for welded and 2 for cast aluminum
enclosures– This is dominated by IEC 62271-203.– BTP = m x Design Pressure– Where m = 3 for welded and 5 for cast aluminum casing
4646
EARTHING SYSTEM
47
EARTHING SYSTEM
GIS Earthing System is designed according to IEEE Guide for safety in AC Substation grounding (IEEE Std 80).
Earthing eliminates all the hazardous potential differences caused by:
Fault Situation (Short Circuit) or
Return Currents (electromagnetically induced among the phases during normal operation)
Earthing also protects the personnel from shock hazard voltage by maintaining low touch/ step voltage among the different parts ofswitchgear.
Earthing of GIS is established by using two different types of earthing conductors i.e. interconnecting earthing bars among the phases and earthing conductors between the enclosure and Earth Mat.
From Safety point of view, LCC and Structural elements are also earthed.
48
EARTHING SYSTEM
4949
SECONDARY CONTROL SYSTEM
50
SECONDARY CONTROL SYSTEM
Secondary Cables: For Controlling, power supply of drives, and GIS signaling.
LCC (Local Control Cubicle): Connection between substation control system and GIS.
LCC gives possibilities to check the service conditions and healthiness of switches and devices. Position signal of all the switches appear in mimic diagram of LCC.
Operation of switches is possible either from control room or locally through LCC.
In normal service the LOCAL/ REMOTE Selector switch are in REMOTE control position to operate the GIS from Control room. If the selector switch is turned to LOCAL position, the switches of theconcerned bay can be operated from LCC.
51
SECONDARY CONTROL SYSTEM
5252
DELIVERY & STORAGE
53
DELIVERY & STORAGE
54
Delivery & Storage
• Packing:– GIS Unit and all other parts and materials required for
erection & operation are seaworthy packed in wooden cases &
– Packing is provided with signs for transport & storage as well as instructions for proper handling.
• Storage of Shipping Units:– If GIS is not planned to assemble immediately after delivery it
is recommended to leave the shipping units in weatherproof transport packing.
– Wooden cases can be stored either in open air or in ware houses.
– To safeguard the packing unit from ground moisture and for better ventilation, the unit is raised on planks and covered with waterproof sheets.
– The temperature of storage shall be in the range of -15 deg C to +25 deg C and humidity shall be < 50%
– SF6 gas cylinders shall be handled and stored carefully in a cool, dry and away from flames and sunlight.
55
DELIVERY & STORAGE
5656
ERECTION OF GIS
57
SAFETY PRECAUTIONS FOR ERECTION
To prevent accidents, fire hazards, shocks the utility operator to ensure that:
A responsible person and supervisor caries out the erection
Only qualified and trained personnel are designated for the work
Installation and operation manual (manufacturer specific) shall be strictly followed.
Tools, tackles and other devices for installation are available
Only manufacturer approved lubricants, materials, fillers, degassers etc are used.
Death, severe injuries and considerable damage to property and environmental damages may result if the safety and erection procedures are not followed.
58
SAFETY PRECAUTIONS FOR ERECTION
59
PREPERATORY WORK FOR ERECTION
Since for GIS erection an absolute cleanliness is required, no installation work of any kind may be carried out at the same time.
The following aspects are substantial:
Foundations and Earthing System
Cables and Cable Ducts
Transport Routes & Lifting arrangements
Tools, devices and consumables
Lighting, power & water supplies
Civil Works
6060
COMMISSIONING OF GIS
61
COMMISSIONING OF GIS
GIS Commissioning should not commence before:
GIS erection is complete
Auxiliary and control cables have been connected
All auxiliary and control voltages are available at the switches
SF6 gas filling has been completed
GIS is connected to earthing system.
62
COMMISSIONING OF GIS
Checks and Verifications:
Switchgear conformity with manufacturer drawings and instructions
Conformity of secondary control & protection circuits
Conformity of earthing system
Sealing of all enclosure flanges and tightness of bolts & connections
Proper functioning of AC & DC auxiliary supply systems
Proper operation, alarm and position indication of each drive
Proper function of electrical interlocks between LCC & GIS
Proper filling pressure of each gas compartment
6363
GIS Testing at Site
64
GIS Testing at Site
Before putting into service the GIS shall be tested to check the correct operation and dielectric strength of the equipment.
These tests comprise:
Dielectric tests on auxiliary circuits
Measurement of the resistance of the main circuits
Measurement of gas condition
Gas Tightness Test
Checking the ratio and polarity of the CT
High Voltage AC Test on Main Circuits
65
GIS Testing at Site
Dielectric Test on Auxiliary Circuits:
After the site erection is completed, the auxiliary cables that were not tested in the factory have to be tested for checking the correct wiring.
The test is performed with HV AC Test Equipment
1 kV AC Voltage shall be applied between the terminal blocks and the earth points for 1 sec with neutral points of the circuit to be removed during testing
66
GIS Testing at Site
Measurement of Resistance of Main Circuit:
During the erection the resultant resistance of all bays between the bus bar and the outgoing terminal shall be checked.
The resistance shall be calculated from the voltage drop measured at min 100 A DC loading current.
67
GIS Testing at Site
Measurement of Gas Condition:
The moisture content of SF6 gas should be measured with dew point measuring device
Similarly the gas percentage measurement shall also be carried out using gas measuring device. SF6 percentage should be > 95%.
68
GIS Testing at Site
Gas Tightness Test:
Generally gas leakage test with gas leak detector is being done at site to ensure that there is practically no gas leakage after erection and commissioning of GIS and before putting it into service.
CT Ratio & Polarity Test:
The ratio and polarity of the current transformer is checked using primary current injection method.
69
GIS Testing at Site
High Voltage Test of GIS (AC Test):
This test is carried out to ensure the dielectric strength of the switchgear which if unhealthy can lead to an internal fault in future thereby leading to Partial Discharges.
The test voltage to be applied as per IEC 62271-203 is 380 kV rms for 1 minute.
7070
INSPECTION & MAINTENANCE OF GIS
71
INSPECTION OF GIS
GIS Life Cycle is ~ 50 years. There is a small risk of failure which can often be avoided by proper monitoring and inspection of GIS
72
MAINTENANCE OF GIS
GIS is hermetically closed system.
Primary contacts and conductors are under protective gas atmosphere and therefore no corrosion may occur due to humidity
No internal or external parts are designed to be replaced withinthe life cycle of GIS.
Practically GIS is maintenance free since the same is tested forhigher number of operations viz 10000 for circuit breakers.
However, within the scope of general overhauling only checking and replacing of contacts, nozzles etc is carried out till the time GIS operations are in prescribed limit of the IEC recommendations and Type Test Certifications.
7373
HYBRID SUB STATION
74
HYBRID SUB STATION
A sub station of which the bays are made from a mix of GIS and AIS technology components and interconnections, i.e. a sub station that consists of bays where some of the bays are made of a mix of AISand GIS technology components or some of bays are made of GIS technology components and their interconnections only are considered as HYBRID SUB STATIONS.
There are two exceptions from this rule:
If the only one component in AIS technology is the HV connection(bushing, box) to O/H line, cable or transformer then the S/s isconsidered as GIS S/s.
AIS where only one component is in GIS technology or where additional elements have a mixture of Air & Gas Insulation but the primary insulation to earth is still air (as in dead tank) they are still considered as AIS S/s.
7575
COMPARISON AIS & GIS
76
COMPARISON AIS & GIS
LAND
Less as compared to AIS.
App. 70% Land Reduction for a 400 kV GIS S/s wrt AIS
ENGINEERING
Less Engineering Required for GIS wrt AIS.
Engineering Standardization is a continuous process.
Project Specific influence (Cabling, Connections, Soil)
CIVIL WORKS
Involved in both, however, substantial reduction for GIS
AIS requires Equipment and Tower Foundations, cable trenches etc
GIS required GIS Room.
77
COMPARISON AIS & GIS
EQUIPMENT
Equipment Cost AIS viz a viz GIS is nearly double.
With Auxiliaries GIS cost is 1.2 to 1.5 times of AIS
AUXILIARIES (EARTHING, LIGHTING, FIRE FIGHTING etc)
AIS has more area means more requirement
More Fencing, More Earthing, More Lighting
More Cables required for AIS since HV equipments are a distance apart and therefore the distances are longer.
Site preparation, mobilization cost, earth leveling, fencing androads cost are more in AIS compared to GIS.
78
COMPARISON AIS & GIS
ERECTION & COMMISSIONING
Assemblies pre tested at factory and dispatched as single unit in form of complete bays
Time required is < 40% of the time required for erection & commissioning of AIS
Very few cable requirement i.e. between LCC to GIS and between GIS to CRP.
OPERATION & MAINTENANCE
Time for AIS O&M > 2 x Time for GIS O&M
GIS O&M requires only some preliminary checks.
No Environmental Issues
GIS Room and floor are always kept clean.
79
COMPARISON AIS & GIS
ENVIRONMENTAL ASPECTS
No Pollution, Moisture or Temperature Difference Issues.
Less Ecological disturbances since land used is less
Sealed System with optimum earthing, thus no EMF emission
No RIV Interference due to sealed system
ASTHETIC VALUES
GIS is better compared to AIS
All housed beautifully in a room
High profile appearance.
No acoustic load on environment
Less corona discharges
80
COMPARISON AIS & GIS (145 kV)
8181
LIFE CYCLE COST ANALYSIS
82
LIFE CYCLE COST ANALYSIS
83
LIFE CYCLE COST ANALYSIS
84
LIFE CYCLE COST ANALYSIS
Life Cycle costing is a process to determine the sum of all the costs associated with an asset or a part thereof including acquisition, installation, operation & maintenance, refurbishment and disposal costs.
LCC = Acq. Cost + Ownership Cost + O&M Cost + Disposal Cost
GIS Primary Hardware (Acquisition Cost)
When comparing the equivalent primary HV components, GIS is moreexpensive than AIS. However if the prices of the gantries, supports, conductors, earthing, illumination, fire fighting for AIS s/s are included in the comparison, the difference between GIS and AIS can be significantly reduced, because they are already included in the GIS System. Comparison including the cost of land, installation, building etc as well as the cost of secondary control & protection and monitoring equipment is also very important and can lead to more cost attractive solution for GIS in any circumstances.
85
LIFE CYCLE COST ANALYSIS
Maintenance (Ownership Cost)
In comparison of the failure rate, GIS has better features than AIS. In general, failure rate of GIS components are 0.25 times that of AIS components (viz. CB, CT, CVT, ISO) and especially 0.10 times in case of bus bar. Thus, GIS needs less repair maintenance cost through out its lifetime. The cost of preventive and predictive maintenance are well reduced, because of less possibility of failure.
Operation Cost (Ownership Cost)
Operating cost including the maintenance cost of GIS shall be substantially low as compared to AIS. However, the cost of training, spare holding for new GIS installation is high as compared to AIS.
86
LIFE CYCLE COST ANALYSIS
Outage Cost (Operating Cost)
Since failure rate of GIS components is lower than that of AIS and therefore, outage cost of AIS including the possible loss ofrevenue by the outage shall be bigger.
However, it shall also be considered that the outage time for GIS can be longer than that of AIS, in case of certain failures.
Disposal Cost
Cost of decommissioning and disposal after use and after subtracting earnings which can be received by selling the reusable materials like aluminum, copper etc have to be capitalized. Now a days CIGRE is studying the feasibility on re usage of SF6 gas up to 99%.
87
LIFE CYCLE COST ANALYSIS
88
LIFE CYCLE COST ANALYSIS
89
LIFE CYCLE COST ANALYSIS
90
LIFE CYCLE COST ANALYSIS
91
LIFE CYCLE COST ANALYSIS
9292
SAFETY & SECURITY ISSUES
93
SAFETY & SECURITY ISSUES
Substation Security has always been important factor.
Importance of a secure and uninterrupted electricity supply continues to increase.
Outages and failures due to insufficient substation security becomes less and less acceptable to customers.
Substation security is important to:
Maintain the availability of the power supply
Prevent public access to the plants, for the purpose of safety of general public, prevention of vandalism and intruders
Protect other parts and components in a S/s against violent deterioration of high voltage equipment caused by failures.
Prevent and minimize the financial risk due to all the occurrences mentioned above
94
SAFETY & SECURITY ISSUES
Protection Measures to obtain an adequate security level include:
Protection against intruders
Outdoor substations: Fence design (height, shape, minimum clearance to ground, mechanical strength, reduction of height due to snow depth)
Indoor Substations: Building design (windows, doors, access control).
Protect other parts and components in S/s against violent deterioration of HV equipment caused by failures
Outdoor parts: Fence Design, Passive protection of components by concrete structures
Indoor parts: Quality of building material, wall thickness
GIS is inherently well placed to meet these demands and considerations in an excellent way due to:
Small space requirements, these s/s are easier to protect.
The enclosure gives protection against access to live parts
GIS are often located indoor to give additional security compared to outdoor substations.
95
SAFETY & SECURITY ISSUES
CIGRE Report on Power Supply Network with GIS Technology Report 381 Working Group B3.17 Jun 2009
0%
20%
40%60%
80%
100%
PrimaryEnergy
SpaceConsumption
GlobalWarmingPotential
Acid RainPotential
NutrificationPotential
AIS GIS
9696
PARTIAL DISCHARGE
97
PARTIAL DISCHARGE - AN OVERVIEW
Partial Discharge is
Localized Electrical Break down
Of a small portion of electrical insulation system
Under High Voltage Stresses
Which does not bridge the space b/w conductors
98
PARTIAL DISCHARGE – AN OVERVIEW
Expectations from GIS
High Reliability
Long Life Space Economization
Maintenance Free
99
PARTIAL DISCHARGE – AN OVERVIEW
Preventive Maintenance is required for GIS to ensure maintenance free.
Most Important aspect of Preventive Maintenance is to analyze the type & location of internal fault.
Internal Faults in GIS:
Insulation
Loose Particles
Arcing
Thus Partial Discharge Measurement are very much helpful to evaluate the integrity of the equipment.
100
PARTIAL DISCHARGE – AN OVERVIEW
PD Measurement can be taken:
Continuously
Intermittently
On-Line
Off-Line
101101
MAINTENANCE (TYPICAL)
102
MAINTENANCE (TYPICAL)
GIS General
General Conditions of Equipments
Support Structures
Earthing Connections
Gas Pressure Density/ Level & Trend Analysis
Calibration of Pressure Transmitter/ Transducer/ Pressure Gauges/ Manometers
Alarm Setting & Operations
103
MAINTENANCE (TYPICAL)
CIRCUIT BREAKER
Number of Operations
Trial Operations
Contact Timing. Travel Record
Mechanism Type (i.e. Spring/ Hydraulic/ Pneumatic)
104
MAINTENANCE (TYPICAL)
DISCONNECTOR & EARTHING SWITCHES
Number of Operations
Trial Operations
Motor Operating Time & Current
Operation of position indicating valve
Condition of auxiliary switches, wiring & connections
Conditions of gears, linkages, lubrication
Interlocking operation
105105
THANK YOU
106
CGL CONTACTS
For Further Information, Please Contact
Crompton Greaves Ltd.
Engineering Projects Division
3rd Floor, Tower A, DLF Cyber Greens, DLF Phase III,
Gurgaon (Haryana) – 122 002
Contact Persons:a) Mr. Reshu Madan – Dy. General Manager (+91-9711206415) [email protected]
b) Mr. Kapil Verma – Dy. Manager (+91-9711206425) [email protected]
c) Mr. Ankur Aggarwal – Dy. Manager (+91-9711206437) [email protected]