Upload
others
View
14
Download
5
Embed Size (px)
Citation preview
City of Greater Geelong
Geotechnical Investigation,
Jetty Development
Clifton Springs Boat Harbour
Report No: 880a/01/15
Date: 01 October 2015
FINAL VERSION 1 - 06 02 2016
(Issued Without Comments from Client)
Prepared for Ralph Roob
Senior Environmental Engineer
PO Box 104
Geelong, VIC, 3220
Geotechnical Investigation at Clifton Spring Boat Harbour.
A.S.Miner Geotechnical – Report 880/01/15
Contents
1. Introduction and Background 4
2. Desk Study 5
3. Regional Setting 6
Regional Geology 6
Regional Landscape Evolution 7
Local Geology 8
4. Fieldwork 9
Site Observations 9
CPT Investigation Program 9
5. Interpretation of Results at the Proposed Jetty Site at the CS Boat Harbour 12
Profile 12
Strength 12
6. Discussion and Recommendations 13
7. Information about this report 14
Geotechnical Investigation at Clifton Spring Boat Harbour.
A.S.Miner Geotechnical – Report 880/01/15
Appendices
A Site Photos
B Drilling Bore logs
C DCP results
D Lab testing results
Important Disclaimer
This document has been prepared for use by the City of Greater Geelong by A.S.Miner Geotechnical and has been compiled by using the consultants’ expert knowledge, due care and professional expertise. A.S.Miner Geotechnical do not guarantee that the publication is without flaw of any kind or is wholly appropriate for every purpose for which it may be used. No reliance or actions must therefore be made on the information contained within this report without seeking prior expert professional, scientific and technical advice.
To the extent permitted by law, A.S.Miner Geotechnical (including its employees and consultants) excludes all liability to any person for any consequences, including but not limited to all losses, damages, costs, expenses and any other compensation, arising directly or indirectly from using this publication (in part or in whole) and any information or material contained in it.
A.S.Miner Geotechnical – Report 880a/01/15 4
1. Introduction and Background
As part of ongoing development and upgrade works at the Clifton Springs Boat Harbour (see
location plan in Figure 1), it is understood that a new jetty is to be built perpendicular to the
northern causeway of the boat harbour. This follows other works involving a small boat ramp
and causeway which are to be constructed on the foreshore in the southern shoreline sector of
the facility.
A.S.Miner Geotechnical (ASMG) understands the initial design for the jetty has yet to be
completed but that the jetty structure will include a lightweight deck and piled foundations. Tie
up facilities are to be provided from the jetty.
A series of discussions were held with the City of Greater Geelong (COGG) to assess
requirements for the foundations for this new jetty facility. In particular, it was requested that
geotechnical strength parameters be provided to allow the design of piles for the jetty once the
exact nature of the piles and the structure were known. This follows a similar investigation for
the boat ramp and causeway development to the south.
This investigation report details the results of specialist Cone Penetrometer Testing (CPT)
conducted onshore at the proposed jetty site and makes relevant comments and
recommendations for future assessment and analysis once further details of the overall jetty
structure is known.
Figure 1 Location Map
A.S.Miner Geotechnical – Report 880a/01/15 5
2. Desk Study
A preliminary review of previous geotechnical information relating to the Clifton Springs Boat
Harbour was conducted by ASMG in September 2014. This report detailed information
obtained from the following studies:
• Coffey (2006a) Landslide Risk Assessment. The Dell, Clifton Springs. Prepared
for City of Greater Geelong. M6022/1-AG Dated 14th January 2006.
• Coffey (2006b) Assessment of risks to beach users from geological hazards
between Edgewater stairs and the Dell, Clifton Springs
• ASMG (2008) Clifton Springs Hydro Study Report 416/01/08 Dated 13 October
2008.
• ASMG (2011) Coastal erosion and stability study, Clifton Springs Report No
533/01/11. Dated 30 June 2011.
As part of this current investigation a number of other relevant reports and documents were
identified and these included:
• Ladd P.G. (1971). Some aspects of the geology of the Bellarine peninsula.
B.Sc. (Hons) Thesis. University of Melbourne, 1971.
• Glennon (1980) Coastal Slope Stability Investigation at Curlewis. Thesis
submitted in fulfilment of Bachelor of Engineering. School of Engineering and
Architecture, Deakin University. November 1980
• Peck W, Neilson, J., Olds, R and Seddon K (1992). Engineering geology of
Melbourne. Proceedings of seminar on engineering geology of Melbourne, 16
September 1992 Baklema, Rotterdam.
• PB (2003) The Dell Clifton Springs. Investigation and Monitoring of a Slow
Moving Landslide. Interim Report. Prepared for City of Greater Geelong 26th
August 2003.
• ASMG (2009) Edgewater Drive Stormwater Outfall Stability Assessment.
Prepared for City of Greater Geelong. Report No 479/01/09. Dated 31st May
2009.
• Wilson R. and Miner A. (2012). Landslides on the Bellarine and Nepean
Peninsulas, Victoria. Australian Geomechanics
A significant amount of previous soil parameter testing and overall profile understanding has
been able to be assessed from these previous reports and correlated.
As a result information has been correlated and cross referenced with the profile encountered
during the current investigation with these other sources of data appropriately identified in this
report.
A.S.Miner Geotechnical – Report 880a/01/15 6
3. Regional Setting
Regional Geology
The Bellarine Peninsula is about 30 km long (east – west) by about 15 km wide. Relief on the
Bellarine Peninsula is typically low with the exception being the prominent 20 m high cliffs that
extend along the north side of the peninsula. The highest point on the peninsula is Mt Bellarine
(RL 137 m AHD).
The Bellarine Peninsula is an uplifted horst block bounded by an unnamed fault in the west,
the Curlewis Monocline to the north and the Bellarine Fault in the east (see Figure 2).
Figure 2 Geology of the Bellarine and Nepean Peninsula (modified after 1:250,000
Queenscliff Sheet). From Wilson and Miner (2012)
Despite its small size, the Bellarine Peninsula hosts an extensive sequence of Quaternary and
Tertiary geological units that include:
• Quaternary (Holocene) age alluvium including coastal and inland calcareous and
siliceous dunes and sand sheets, as well as alluvium, lacustrine and swamp
deposits.
• Quaternary (Pleistocene) age Bridgewater Formation calcareous and siliceous
dunes and Newer Volcanic basalt with minor scoria and ash.
• Tertiary (Pliocene) age non-marine to marginal marine, partly ferruginous sands,
clayey sands, clay, and gravels of the Moorabool Viaduct Sands (equivalent to
Brighton Group in Melbourne).
A.S.Miner Geotechnical – Report 880a/01/15 7
• Tertiary age marine sediments including limestones, marls, calcareous clays,
sand and silt of the Jan Juc Formation, Curlewis Limestone and Fyansford
Formation; overlying Tertiary age basalts and tuffs of the Older Volcanics and
non-marine gravels, sands and clays of the Werribee Formation.
• Cretaceous age sandstone, arkose, shale and mudstone of the Eumeralla
Formation and Barrabool Sandstones which generally form the basement to the
peninsula.
Regional Landscape Evolution
A summary of landscape evolution in the southern end of what is known as the Port Phillip
Sunkland (which includes the Bellarine Peninsula) was provided by Wilson and Miner (2012)
and is presented below as Table 1.
It is important to note the period of deposition under an advancing sea in the late Eocene to
Early Miocene resulted in the deposition of marls and calcareous clays of the Fyansford
Formation within a marine environment. Later deposition under a retreating sea deposited
much of the sandy marls, calcarenites and limestone of the Curlewis Formation so prevalent
along the northern Bellarine Peninsula coastline.
Renewed tectonic activity in the Late Miocene induced gradual uplift causing folding and
faulting on regional structural elements including the Curlewis Monocline. It is likely that
significant landslides and erosion were experienced at this time along the coast causing lateral
stresses and deformations in the Fyansford Formation.
A.S.Miner Geotechnical – Report 880a/01/15 8
Local Geology
Ladd (1971) provided insight into the local geology at the Clifton Springs Boat Harbour site
through detailed geological mapping during the early 1970’s
Ladd’s mapping of the onshore profile at the Boat Harbour site specifically records a sequence
as follows:
Pleistocene age Sandy Clays, gravel, carbonate nodules and buckshot
Overlying
Pliocene age Moorabool Viaduct sands (equivalent of the re designated Brighton Group)
comprising Sand, clay, sandy clay, calcified clay, ferruginous sandstone and gravel.
with a shoreline deposit of
Holocene age beach sand and in some places to the east raised beaches of shell beds and
coarse sands and mud.
An onshore outcrop/exposure of Miocene age Curlewis Limestone comprising indurated
limestone, marl and fossiliferous clay is shown on Ladd’s maps approximately 500 m to the
east of the boat harbour site. Ladd’s mapping did not include any significant offshore mapping
other than limestone reefs of the Curlewis Formation.t
However Wilson and Miner (2102) did detail a cross section originally produced by Leonard
(1992) which passes almost directly through the boat harbour site providing a conceptual
model of both the onshore and offshore profile at this location. The cross section shows the
offshore profile possibly consisting of the calcareous clays and occasional limestone bands of
the Fyansford Formation overlying intercalated sequence of Older Volcanics and
gravels/sands of the Werribee Formation (see Figure 3)
Figure 3 Section through the Bellarine and Nepean Peninsula (modified after
Leonard, 1992). This section passes close to the Clifton Springs Boat Harbour site
A.S.Miner Geotechnical – Report 880a/01/15 9
4. Fieldwork
Site Observations
The area for construction of the new jetty facility is located on the northern shoreline of the
boat harbour facility and is adjacent to a short geotextile breakwater. A broad sandy beach
sweeps in from the west and terminates against the breakwater. The remains of an old timber
jetty are located approximately 100 m to the west.
A rock revetment armoured causeway which forms the outer arm of the harbour is located
directly above the beach and continues east onto the boat harbour entrances
The sand beach appears to have been renourished at some point in the past and there are no
other visible exposures or outcrops in the area. The offshore waters appear to be relatively
shallow with evidence of seagrass beds well offshore.
Selected site photos are shown in Appendix A.
CPT Investigation Program
Subsurface investigation was completed on the 28th September 2015. 4 x CPT tests were
conducted using a GeoProbe 7822DT drilling rig operated by Black Geotechnical.
CPT cone and rods were advanced using the GoeProbe rig with information recorded by an
infield data logger/ field computer.
CPT test details are provided in Appendix B as supplied by Black Geotechnical
Location of the 4 CPT tests are shown on Figure 5 and 6 with details of the tests shown in
Tables 2 to 5.
Interpreted soil classifications from the four locations are also detailed in Appendix B with a
summary of the inferred profile provided in Table 6
CPT 1
Northing 5774212.3
Easting 285473.7
Depth 4.5m
Depth to water at end of test 0.0 m
Reason for termination Unable to advance beyond hard layer (assumed to
be indurated/ferruginous sand) at base of hole
Other comments Tides were rising quickly as test was right on edge
of water
Table 2 Details for CPT 1
A.S.Miner Geotechnical – Report 880a/01/15 10
CPT 2
Northing 5774209.9
Easting 285478.3
Depth 5.25 m
Depth to water at end of test 0.08 m
Reason for termination Unable to advance beyond hard layer (assumed to
be indurated/ferruginous sand) at base of hole
Other comments Unscheduled test included due to inability to break
thru hard layer. Multiple hard bands noted with
depth
Table 3 Details for CPT 2
Bore CPT 3
Northing 5774195.2
Easting 285476.7
Depth 4.80 m
Depth to water at end of test 0.55 m
Reason for termination Unable to advance beyond hard layer (assumed to
be indurated/ferruginous sand) at base of hole
Other comments Initial location was closer to groyne but unable to
penetrate rock revetment. Hence move further
west.
Table 4 Details for CPT 3
Bore CPT 4
Northing 5774123.5
Easting 285607.1
Depth 8.45 m
Depth to water at end of test 0.75 m
Reason for termination Unable to advance beyond hard layer (assumed to
be limestone /calcrete in silty clays) at base of hole
Other comments This location chosen to calibrate against previous
BH2
Table 5 Details for CPT 4
A.S.Miner Geotechnical – Report 880a/01/15 11
Material Type Geology CPT 1 CPT 2 CPT 3 CPT 4
Depth (m) Comment Depth (m) Comment Depth (m) Comment Depth (m) Comment
Not Defined (0): Upper
loose sands??
Recent 0.0 to 1.1 Loose sands 0.0 to 1.5 Loose sands 0.0 to 0.1 Loose sands 0.0 to 1.9 Loose sands
SAND (6) to Gravelly
SAND (7): Mixed and
inter-layered
Moorabool
Viaduct
Sands
1.1 to 1.55 1.5 to 1.65 0.1 to 0.9 1.9 to 2.0
SAND (6) and SAND
mixtures (5) silty sands
to sandy silts
1.55 to 1.90 1.65 to 1.95 0.9 to 2.05
Very Stiff Fine Grained
(9) Sandy Clay over-
consolidated
1.90 to 2.70 1.95 to 2.65 2.05 to 2.65 Initial layer of stiff
silty clay
SAND (6) and
Dense/Cemented
SAND to Clayey
SAND(8)
2.70 to 4.5 Thicker sequence
of cemented sand
than other
locations
2.65 to 5.25 Numerous hard
cemented layers
Increasing
hardness
2.65 to 4.85 Dense sands with
occasional hard
cemented band
2.0 to 3.2 Only two distinct
hard bands within
dense sand
Cemented SAND (8)
very hard
4.5 Refusal
End of Test
Unable to
penetrate qc>30
MPa
5.25 Refusal
End of Test
Unable to
penetrate qc>30
MPa
4.85 Refusal
End of Test
Unable to
penetrate qc>28
MPa
Clayey SILT to Silty
CLAY (4) with some
lenses of Sand /silt
Mixtures(5)
Fyansford
Formation
3.2 to 8.4 Weathered marls as
calibrated from BH2
Hard Band
(limestone??)
8.4 Refusal
End of Test
Table 6 Summary of CPT Investigation on the 28th September 2015.
A.S.Miner Geotechnical – Report 880a/01/15 12
5. Interpretation of Results at the Proposed Jetty Site at the CS Boat Harbour
Profile
The onshore profile encountered at the site of the onshore section of the proposed jetty has
been interpreted to indicate the presence of between 4.5 and 5.25 m of recent sands and
deposits of the local geological unit known as the Moorabool Viaduct Sands. These deposits
present as a profile of medium dense sands overlying over consolidated very stiff sandy clays
which in turn overlie a sequence of interbedded layers of cemented (and possibly laterised)
sand and sandy clay. These lower layers are very hard in parts and caused refusal with a cone
resistance (qc) of >30 MPa.
No penetration below these hard cemented /laterised layers was possible at the jetty site due
to the hard layers encountered. However based on the local geology and the previous drilling
at the site of the small boat ramp and causeway, it is postulated that a deep sequence of stiff
Fyansford Formation marls/silty clays may exist directly below the hard layers encountered.
CPT4 (which coincides with the previous BH2) was able to penetrate deep into these clays at
the site of the proposed small boat ramp and causeway and a detailed description of the clays
based on classification of retrieved samples is provided in the previous geotechnical report
(ASMG 880/01/15).
Strength
The upper 1.0 m or so of the profile at the jetty site is comprised of very loose to loose sand.
A sequence of interlayered sand and gravelly sand (possibly more likely to be shell grit) is also
of a loose relative density with an end cone resistance of between 2 and 4 MPa. This
sequence in the profile extends to a depth of around 2.0m.
Below a depth of 2.0 m, a stiff to very stiff (Cu approximately 100 kPa), over-consolidated
(sandy) clay is present with a thickness of around 0.50 m to 0.80 m.
Underlying this clay is a sequence of interlayered medium dense to dense sands and harder
cemented sands. Cone resistance in the harder but relatively thin cemented bands is typically
> 16 MPa and can be as high as 30 MPa.
A very hard layer (possibly cemented and ferruginised sand) was present in all three CPTs at
the jetty site at depths ranging from 4.5 m to 5.25 m. Cone resistance was typically > 30 MPa
and caused refusal with no penetration beyond these layers possible
Whilst the upper sands are probably of recent deposition, the underlying sequence is thought
to represent Moorabool Viaduct Sands. It is postulated that directly below the Moorabool
Viaduct Sands lies deep deposits of the Fyansford Formation silty clays which have been
shown in the earlier geotechnical investigation at the boat harbour to be of a stiff consistency
with an undrained shear strength (Cu) typically =75 KPa..
IMPORTANT NOTE: It must however be emphasised that such clays were not directly
encountered at the jetty site due to refusal on the lower harder layers in the Moorabool Viaduct
Sand sediments.
A.S.Miner Geotechnical – Report 880a/01/15 13
6. Discussion and Recommendations
Based on the information reviewed and additional understanding gained from this study, the
following comments are made:
The site of the onshore section of the proposed jetty consist of around 4.80 m of recent sands
and deposits of the Moorabool Viaduct Sands. These deposits consist of medium dense sands
overlying over consolidated very stiff sandy clays which in turn overlie a sequence of
interbedded layers of cemented (and possibly laterised) sand and sandy clay.
Based on a geological model developed with input from the recent geotechnical investigation
on the southern shores of the facility, it is postulated that a deep sequence of stiff Fyansford
Formation silty clay exists below these deposits
The upper 1.0 m of the profile is comprised of very loose to loose sands and should be ignored
in the design of piled foundations.
Assessment of pile type, size and capacity will be dependent on a number of factors which
include:
• The overall nature of the final jetty structure including construction materials and
aesthetics.
• The final intended purpose for the jetty and the amenity required.
• The axial and lateral loadings to the pile foundations
• The availability of suitable pile driving equipment
Following the development of a conceptual design for the jetty including the overall amenity
required, it is recommended that a suitably qualified marine designer then provide loadings
and material recommendations for the piles.
Based on the geotechnical data obtained during this investigation, it is recommended that an
assessment of pile size, capacity and performance under axial and lateral loads be
undertaken.
Whilst it is expected that any piles would be founded in the upper Moorabool Viaducts Sands
and not penetrate deeper into the stiff clays below, (as is postulated to be the case with the
timber foundations for the old jetty structure to the west), it must be stated that any final pile
design decisions will be wholly dependent on the factors listed above.
A.S.Miner Geotechnical – Report 880a/01/15 14
7. Information about this report
Important Disclaimer
This document has been prepared for use by City of Greater Geelong by A.S. Miner
Geotechnical and has been compiled by using the consultants’ expert knowledge, due care
and professional expertise. A.S. Miner Geotechnical do not guarantee that the publication is
without flaw of any kind or is wholly appropriate for every purpose for which it may be used. No
reliance or actions must therefore be made on the information contained within this report
without seeking prior expert professional, scientific and technical advice.
To the extent permitted by law, A.S. Miner Geotechnical (including its employees and
consultants) excludes all liability to any person for any consequences, including but not limited
to all losses, damages, costs, expenses and any other compensation, arising directly or
indirectly from using this publication (in part or in whole) and any information or material
contained in it.
Currency of information
This report is based in part on information which was provided to us by the client and/or others
and which is not under our control. We do not warrant or guarantee the accuracy of this
information.
This document has been prepared as at the date stated within (or, if not date is stated, as at
the date of delivery to the named client). This document:
1. Supersedes any previous report or communications (whether interim or otherwise)
dealing with any matter that is the subject of this document; and
2. Takes no account of any matters coming to the notice of A.S. Miner Geotechnical after
the date of this document (including any matters that existed at that date but which were not
know to A.S. Miner Geotechnical until subsequently).
We believe that the conclusions and recommendations contained herein were reasonable at
the time of issue of the report. However, the user is cautioned that fundamental input
assumptions upon which this report is based may change with time. It is the user’s
responsibility to ensure that input assumptions remain valid.
Confidentiality
This report and its contents are confidential and may not be disclosed or published in any
manner (except as required by law) unless A.S. Miner Geotechnical has given its prior written
consent to the form and context of the disclosure or publication and the identity of the
person(s) to whom it is to be disclosed or published.
Distribution of report
This report has been prepared for specific purposes and persons. To avoid misuse of the
information contained within this report, it is recommended that you confer with A.S. Miner
Geotechnical before providing your report to another party who may not be familiar with the
A.S.Miner Geotechnical – Report 880a/01/15 15
background and the purpose of the report. The report should not be applied to any project
other than that originally specified at the time that the report was originally issued.
Unless specifically agreed otherwise in the contract of engagement, A.S. Miner Geotechnical
retains Intellectual Property Rights over the contents of this report. The client is granted a
licence to use the report for the purposes for which it was commissioned.
Reproduction of Reports
Where it is desired to reproduce the information contained in our report, or other technical
information, for the inclusion in contract documents or engineering specification or the subject
development, such reproductions should include at least all of the relevant figures, drawings,
logs, data, standard description sheets with remarks made in the report of a factual or
descriptive nature etc. These should not be redrawn for inclusion in any other document or
separated from the report in any way.
Reports are the subject of copyright and shall not be reproduced either totally or in part without
the express permission of A S Miner Geotechnical.
Statement of Limitations - Geotechnical Investigations
The following statement of limitations is in accordance with the standard adopted by ASMG for
reports and data presentations. As such it applies to any data or full or partial elements of the
report produced by ASMG.
The report contains results of a geotechnical investigation conducted for a specific purpose
and client. The results should not be used by other parties, or for other purposes, as they may
contain neither adequate nor appropriate information. In particular, the investigation does not
cover contamination issues unless specifically required to do so by the client.
Test Hole Logging
The information on the test hole logs (boreholes, test pits, exposures etc.) is based on a visual
and tactile assessment, except at the discrete locations where test information is available
(field and/or laboratory results). The test hole logs include both factual data and inferred
information. Reference should be made to the relevant sheets for the explanation of logging
procedures (Soil and Rock descriptions, core log Sheet Notes etc.).
Groundwater
Unless otherwise indicated, the water levels presented on the test hole logs are the levels of
free water or seepage in the test hole recorded at the given time of measuring. The actual
groundwater level may differ from this recorded level depending on material permeabilities (i.e.
depending on response time of the measuring instrument). Further variations of this level could
occur with time due to such effects as seasonal, environmental and tidal fluctuations or
construction activities. Confirmation of groundwater levels, phreatic surfaces or piezometric
pressures can only be made by appropriate instrumentation techniques and monitoring
programmes.
A.S.Miner Geotechnical – Report 880a/01/15 16
Interpretation of Results
The discussion or recommendations contained within this report normally are based on a site
evaluation from discrete test hole data. Generalised, idealised or inferred subsurface
conditions (including any geotechnical cross-sections) have been assumed or prepared by
interpretation and must be considered as a guide only.
Change in Conditions
Local variations or anomalies in the generalised ground conditions do occur in the natural
environment, particularly between discrete test hole locations. Additionally, certain design or
construction procedures may have been assumed in assessing the soil-structure interaction
behaviour of the site. Furthermore, conditions may change at the site from those encountered
at the time of the geotechnical investigation through construction activities and constantly
changing natural forces.
Any change in design, in construction methods, or in ground conditions as noted during
construction, from those assumed or reported should be referred to ASMG for appropriate
assessment and comment.
Geotechnical Verification
Verification of the geotechnical assumptions and/or model is an integral part of the design
process – investigation, construction verification, and performance monitoring. Variability is a
feature of the natural environment and, in many instances, verification of soil or rock quality, or
foundation levels, is required. There may be a requirement to extend foundation depths, to
modify a foundation system or to conduct monitoring as a result of this natural variability.
Allowance for verification by geotechnical personnel accordingly should be recognised and
programmed during construction.
Foundations
Where referred to in the report, the soil or rock quality, or the recommended depth of any
foundation (piles, caissons, footings etc.) is an engineering estimate. The estimate is
influenced, and perhaps limited, by the fieldwork method and testing carried out in connection
with the site investigation, and other pertinent information as has been made available. The
material quality and/or foundation depth remains, however, an estimate and therefore liable to
variation. Foundation drawings, designs and specifications should provide for variations in the
final depth, depending upon the ground conditions at each point of support, and allow for
geotechnical verification.
.
A.S.Miner Geotechnical – Report 880a/01/15
Appendix A
Site Photos
A.S.Miner Geotechnical – Report 880a/01/15
Photo A1 Overview of Clifton Springs Boat Harbour site
Photo A2 Area of proposed jetty adjacent to existing geotextile groyne
A.S.Miner Geotechnical – Report 880a/01/15
Photo A3 GeoProbe set up at CPT1 with cone penetrometer rods on the rack in the foreground
Photo A4 Installation of one of the ground anchors used to generate pull out capacity for the CPT
test.
A.S.Miner Geotechnical – Report 880a/01/15
Photo A5 Pushing of cone and rods with cabling running back to on site laptop computer/logger.
Photo A6 CPT test at site of previous BH2 on temporary causeway
A.S.Miner Geotechnical – Report 880a/01/15
Appendix B
CPT logs as supplied by Black Geotechnical
CPT4
CPT3
CPT1CPT2
Client:
Project:
Title: Figure 1Report No. 880a
City of Greater Geelong
Boat Harbour JettyGeotechnical InvestigationCPT Testing Locations
Scale
Data: CoGG - Imagery 2012Filename: 880_Location_Plan_A4.mxd
Map Created:01 Octobert 2015
(at A4 page size)1:1,000
0 2010Metres
Corio Bay
CliftonSprings
0 500Metres
LegendCPT Locations Je
tty R
oad
CPT3
CPT1CPT2
0 5 10Metres
Detailed Map at Right
Client :A.S.Miner Geotechnical
G.L.:
Predrill:
W.L.: Date:
Cone no.:
Project no.:
CPT no.:
0.00 m Predrilled
0.00 m 28/09/20150.00 m
C10CFIIP.C12130D157CPT_01 1/2
Project:Location:Position: 0, 0
Boat harbourClifton Springs
u2
cm² cm² 150 10
Processed : TH Checked: RB
1.44
0
-0.5
-1
-1.5
-2
-2.5
-3
-3.5
-4
-4.5
-5
-5.5
-6
-6.5
-7
-7.5
-8
-8.5
-9
-9.5
-10
-10.5
-11
<- D
epth
in m
bel
ow g
roun
d le
vel (
G.L
.) / c
orre
cted
for i
nclin
atio
n
0 10 20 30 40
qt in MPa
Refusal at 4.51m Max safe push
Water at surface
0 0.2 0.4 0.6 0.8
Sleeve f riction (fs) in MPa
Refusal at 4.51m Max safe push
Water at surface
-0.1 0 0.1 0.2 0.3
u2 in MPa
Refusal at 4.51m Max safe push
Water at surface
0 2 4 6 8
Friction ratio (Rf ) in %
Refusal at 4.51m Max safe push
Water at surface
Client :A.S.Miner Geotechnical
G.L.:
Predrill:
W.L.: Date:
Cone no.:
Project no.:
CPT no.:
0.00 m Predrilled
0.00 m 28/09/20150.00 m
C10CFIIP.C12130D157CPT_01 2/2
Project:Location:Position: 0, 0
Boat harbourClifton Springs
u2
cm² cm² 150 10
Processed : TH Checked: RB
1.44
0
-0.5
-1
-1.5
-2
-2.5
-3
-3.5
-4
-4.5
-5
-5.5
-6
-6.5
-7
-7.5
-8
-8.5
-9
-9.5
-10
-10.5
-11
<- D
epth
in m
bel
ow g
roun
d le
vel (
G.L
.) / c
orre
cted
for i
nclin
atio
n
0 8 16 24 32 40
Cone resistance (qc) in MPa
Refusal at 4.51m Max safe push
Water at surface
Soil Classification (using Fr)
(0)
(6)
(9)
(8)
(0) Not defined(1) Sensitive, fine grained(2) Organic soils-peats(3) Clays-clay to silty clay(4) Clayey silt to silty clay(5) Sand mixtures(6) Sands(7) Gravelly sand to sand(8) Very stiff sand to clayey sand(9) Very stiff fine grained
Client :A.S.Miner Geotechnical
G.L.:
Predrill:
W.L.: Date:
Cone no.:
Project no.:
CPT no.:
0.00 m Predrilled
-0.10 m 28/09/20150.00 m
C10CFIIP.C12130D157CPT_02 1/2
Project:Location:Position: 0, 0
Boat harbourClifton Springs
u2
cm² cm² 150 10
Processed : TH Checked: RB
1.44
0
-0.5
-1
-1.5
-2
-2.5
-3
-3.5
-4
-4.5
-5
-5.5
-6
-6.5
-7
-7.5
-8
-8.5
-9
-9.5
-10
-10.5
-11
<- D
epth
in m
bel
ow g
roun
d le
vel (
G.L
.) / c
orre
cted
for i
nclin
atio
n
0 10 20 30 40
qt in MPa
Refusal at 5.28m Max safe push
0 0.2 0.4 0.6 0.8
Sleeve f riction (fs) in MPa
Refusal at 5.28m Max safe push
-0.1 0 0.1 0.2 0.3
u2 in MPa
Refusal at 5.28m Max safe push
0 2 4 6 8
Friction ratio (Rf ) in %
Refusal at 5.28m Max safe push
Client :A.S.Miner Geotechnical
G.L.:
Predrill:
W.L.: Date:
Cone no.:
Project no.:
CPT no.:
0.00 m Predrilled
-0.10 m 28/09/20150.00 m
C10CFIIP.C12130D157CPT_02 2/2
Project:Location:Position: 0, 0
Boat harbourClifton Springs
u2
cm² cm² 150 10
Processed : TH Checked: RB
1.44
0
-0.5
-1
-1.5
-2
-2.5
-3
-3.5
-4
-4.5
-5
-5.5
-6
-6.5
-7
-7.5
-8
-8.5
-9
-9.5
-10
-10.5
-11
<- D
epth
in m
bel
ow g
roun
d le
vel (
G.L
.) / c
orre
cted
for i
nclin
atio
n
0 8 16 24 32 40
Cone resistance (qc) in MPa
Refusal at 5.28m Max safe push
Soil Classification (using Fr)
(0)
(6)
(9)
(8)
(6)
(8)
(0) Not defined(1) Sensitive, fine grained(2) Organic soils-peats(3) Clays-clay to silty clay(4) Clayey silt to silty clay(5) Sand mixtures(6) Sands(7) Gravelly sand to sand(8) Very stiff sand to clayey sand(9) Very stiff fine grained
Client :A.S.Miner Geotechnical
G.L.:
Predrill:
W.L.: Date:
Cone no.:
Project no.:
CPT no.:
0.00 m Predrilled
-0.57 m 28/09/20150.00 m
C10CFIIP.C12130D157CPT_03 1/2
Project:Location:Position: 0, 0
Boat harbourClifton Springs
u2
cm² cm² 150 10
Processed : TH Checked: RB
1.44
0
-0.5
-1
-1.5
-2
-2.5
-3
-3.5
-4
-4.5
-5
-5.5
-6
-6.5
-7
-7.5
-8
-8.5
-9
-9.5
-10
-10.5
-11
<- D
epth
in m
bel
ow g
roun
d le
vel (
G.L
.) / c
orre
cted
for i
nclin
atio
n
0 10 20 30 40
qt in MPa
Refusal at 4.86m Max safe push
0 0.2 0.4 0.6 0.8
Sleeve f riction (fs) in MPa
Refusal at 4.86m Max safe push
-0.1 0 0.1 0.2 0.3
u2 in MPa
Refusal at 4.86m Max safe push
0 2 4 6 8
Friction ratio (Rf ) in %
Refusal at 4.86m Max safe push
Client :A.S.Miner Geotechnical
G.L.:
Predrill:
W.L.: Date:
Cone no.:
Project no.:
CPT no.:
0.00 m Predrilled
-0.57 m 28/09/20150.00 m
C10CFIIP.C12130D157CPT_03 2/2
Project:Location:Position: 0, 0
Boat harbourClifton Springs
u2
cm² cm² 150 10
Processed : TH Checked: RB
1.44
0
-0.5
-1
-1.5
-2
-2.5
-3
-3.5
-4
-4.5
-5
-5.5
-6
-6.5
-7
-7.5
-8
-8.5
-9
-9.5
-10
-10.5
-11
<- D
epth
in m
bel
ow g
roun
d le
vel (
G.L
.) / c
orre
cted
for i
nclin
atio
n
0 8 16 24 32 40
Cone resistance (qc) in MPa
Refusal at 4.86m Max safe push
Soil Classification (using Fr)
(6)
(6)
(4)
(6)
(6)
(7)
(6)
(0) Not defined(1) Sensitive, fine grained(2) Organic soils-peats(3) Clays-clay to silty clay(4) Clayey silt to silty clay(5) Sand mixtures(6) Sands(7) Gravelly sand to sand(8) Very stiff sand to clayey sand(9) Very stiff fine grained
Client :A.S.Miner Geotechnical
G.L.:
Predrill:
W.L.: Date:
Cone no.:
Project no.:
CPT no.:
0.80 m Predrilled
-0.80 m 28/09/20150.00 m
C10CFIIP.C12130D157CPT_04 1/2
Project:Location:Position: 0, 0
Boat harbourClifton Springs
u2
cm² cm² 150 10
Processed : TH Checked: RB
1.44
0
-0.5
-1
-1.5
-2
-2.5
-3
-3.5
-4
-4.5
-5
-5.5
-6
-6.5
-7
-7.5
-8
-8.5
-9
-9.5
-10
-10.5
-11
<- D
epth
in m
bel
ow g
roun
d le
vel (
G.L
.) / c
orre
cted
for i
nclin
atio
n
0 10 20 30 40
qt in MPa
Refusal at 8.44m Inclination
Hole dipped to 0.8m
0 0.2 0.4 0.6 0.8
Sleeve f riction (fs) in MPa
Refusal at 8.44m Inclination
Hole dipped to 0.8m
-0.1 0 0.1 0.2 0.3
u2 in MPa
Refusal at 8.44m Inclination
Hole dipped to 0.8m
0 2 4 6 8
Friction ratio (Rf ) in %
Refusal at 8.44m Inclination
Hole dipped to 0.8m
Client :A.S.Miner Geotechnical
G.L.:
Predrill:
W.L.: Date:
Cone no.:
Project no.:
CPT no.:
0.80 m Predrilled
-0.80 m 28/09/20150.00 m
C10CFIIP.C12130D157CPT_04 2/2
Project:Location:Position: 0, 0
Boat harbourClifton Springs
u2
cm² cm² 150 10
Processed : TH Checked: RB
1.44
0
-0.5
-1
-1.5
-2
-2.5
-3
-3.5
-4
-4.5
-5
-5.5
-6
-6.5
-7
-7.5
-8
-8.5
-9
-9.5
-10
-10.5
-11
<- D
epth
in m
bel
ow g
roun
d le
vel (
G.L
.) / c
orre
cted
for i
nclin
atio
n
0 8 16 24 32 40
Cone resistance (qc) in MPa
Refusal at 8.44m Inclination
Hole dipped to 0.8m
Soil Classification (using Fr)
(0)
(6)
(6)
(5)
(4)
(4)
(4)
(5)
(4)
(4)
(0) Not defined(1) Sensitive, fine grained(2) Organic soils-peats(3) Clays-clay to silty clay(4) Clayey silt to silty clay(5) Sand mixtures(6) Sands(7) Gravelly sand to sand(8) Very stiff sand to clayey sand(9) Very stiff fine grained
Client :A.S.Miner Geotechnical
G.L.:
Predrill:
W.L.: Date:
Cone no.:
Project no.:
CPT no.:
0.00 m Predrilled
0.00 m 28/09/20150.00 m
C10CFIIP.C12130D157CPT_01 1/2
Project:Location:Position: 0, 0
Boat harbourClifton Springs
u2
cm² cm² 150 10
Processed : TH Checked: RB
1.44
0
-0.5
-1
-1.5
-2
-2.5
-3
-3.5
-4
-4.5
-5
-5.5
-6
-6.5
-7
-7.5
-8
-8.5
-9
-9.5
-10
-10.5
-11
<- D
epth
in m
bel
ow g
roun
d le
vel (
G.L
.) / c
orre
cted
for i
nclin
atio
n
0 10 20 30 40
qt in MPa
Refusal at 4.51m Max safe push
Water at surface
0 0.2 0.4 0.6 0.8
Sleeve f riction (fs) in MPa
Refusal at 4.51m Max safe push
Water at surface
-0.1 0 0.1 0.2 0.3
u2 in MPa
Refusal at 4.51m Max safe push
Water at surface
0 2 4 6 8
Friction ratio (Rf ) in %
Refusal at 4.51m Max safe push
Water at surface
Client :A.S.Miner Geotechnical
G.L.:
Predrill:
W.L.: Date:
Cone no.:
Project no.:
CPT no.:
0.00 m Predrilled
0.00 m 28/09/20150.00 m
C10CFIIP.C12130D157CPT_01 2/2
Project:Location:Position: 0, 0
Boat harbourClifton Springs
u2
cm² cm² 150 10
Processed : TH Checked: RB
1.44
0
-0.5
-1
-1.5
-2
-2.5
-3
-3.5
-4
-4.5
-5
-5.5
-6
-6.5
-7
-7.5
-8
-8.5
-9
-9.5
-10
-10.5
-11
<- D
epth
in m
bel
ow g
roun
d le
vel (
G.L
.) / c
orre
cted
for i
nclin
atio
n
0 10 20 30 40 50
Equivalent SPT N60 Value
Refusal at 4.51m Max safe push
Water at surface
0 20 40 60 80 100
Relative density (consolidated) in %
Refusal at 4.51m Max safe push
Water at surface
0 10 20 30 40 50
Internal friction angle in degrees
Refusal at 4.51m Max safe push
Water at surface
Client :A.S.Miner Geotechnical
G.L.:
Predrill:
W.L.: Date:
Cone no.:
Project no.:
CPT no.:
0.00 m Predrilled
-0.10 m 28/09/20150.00 m
C10CFIIP.C12130D157CPT_02 1/2
Project:Location:Position: 0, 0
Boat harbourClifton Springs
u2
cm² cm² 150 10
Processed : TH Checked: RB
1.44
0
-0.5
-1
-1.5
-2
-2.5
-3
-3.5
-4
-4.5
-5
-5.5
-6
-6.5
-7
-7.5
-8
-8.5
-9
-9.5
-10
-10.5
-11
<- D
epth
in m
bel
ow g
roun
d le
vel (
G.L
.) / c
orre
cted
for i
nclin
atio
n
0 10 20 30 40
qt in MPa
Refusal at 5.28m Max safe push
0 0.2 0.4 0.6 0.8
Sleeve f riction (fs) in MPa
Refusal at 5.28m Max safe push
-0.1 0 0.1 0.2 0.3
u2 in MPa
Refusal at 5.28m Max safe push
0 2 4 6 8
Friction ratio (Rf ) in %
Refusal at 5.28m Max safe push
Client :A.S.Miner Geotechnical
G.L.:
Predrill:
W.L.: Date:
Cone no.:
Project no.:
CPT no.:
0.00 m Predrilled
-0.10 m 28/09/20150.00 m
C10CFIIP.C12130D157CPT_02 2/2
Project:Location:Position: 0, 0
Boat harbourClifton Springs
u2
cm² cm² 150 10
Processed : TH Checked: RB
1.44
0
-0.5
-1
-1.5
-2
-2.5
-3
-3.5
-4
-4.5
-5
-5.5
-6
-6.5
-7
-7.5
-8
-8.5
-9
-9.5
-10
-10.5
-11
<- D
epth
in m
bel
ow g
roun
d le
vel (
G.L
.) / c
orre
cted
for i
nclin
atio
n
0 10 20 30 40 50
Equivalent SPT N60 Value
Refusal at 5.28m Max safe push
0 20 40 60 80 100
Relative density (consolidated) in %
143.53 ->
Refusal at 5.28m Max safe push
0 10 20 30 40 50
Internal friction angle in degrees
Refusal at 5.28m Max safe push
Client :A.S.Miner Geotechnical
G.L.:
Predrill:
W.L.: Date:
Cone no.:
Project no.:
CPT no.:
0.00 m Predrilled
-0.57 m 28/09/20150.00 m
C10CFIIP.C12130D157CPT_03 1/2
Project:Location:Position: 0, 0
Boat harbourClifton Springs
u2
cm² cm² 150 10
Processed : TH Checked: RB
1.44
0
-0.5
-1
-1.5
-2
-2.5
-3
-3.5
-4
-4.5
-5
-5.5
-6
-6.5
-7
-7.5
-8
-8.5
-9
-9.5
-10
-10.5
-11
<- D
epth
in m
bel
ow g
roun
d le
vel (
G.L
.) / c
orre
cted
for i
nclin
atio
n
0 10 20 30 40
qt in MPa
Refusal at 4.86m Max safe push
0 0.2 0.4 0.6 0.8
Sleeve f riction (fs) in MPa
Refusal at 4.86m Max safe push
-0.1 0 0.1 0.2 0.3
u2 in MPa
Refusal at 4.86m Max safe push
0 2 4 6 8
Friction ratio (Rf ) in %
Refusal at 4.86m Max safe push
Client :A.S.Miner Geotechnical
G.L.:
Predrill:
W.L.: Date:
Cone no.:
Project no.:
CPT no.:
0.00 m Predrilled
-0.57 m 28/09/20150.00 m
C10CFIIP.C12130D157CPT_03 2/2
Project:Location:Position: 0, 0
Boat harbourClifton Springs
u2
cm² cm² 150 10
Processed : TH Checked: RB
1.44
0
-0.5
-1
-1.5
-2
-2.5
-3
-3.5
-4
-4.5
-5
-5.5
-6
-6.5
-7
-7.5
-8
-8.5
-9
-9.5
-10
-10.5
-11
<- D
epth
in m
bel
ow g
roun
d le
vel (
G.L
.) / c
orre
cted
for i
nclin
atio
n
0 10 20 30 40 50
Equivalent SPT N60 Value
Refusal at 4.86m Max safe push
0 20 40 60 80 100
Relative density (consolidated) in %
139.46 ->
124.6 ->
Refusal at 4.86m Max safe push
0 10 20 30 40 50
Internal friction angle in degrees
Refusal at 4.86m Max safe push
Client :A.S.Miner Geotechnical
G.L.:
Predrill:
W.L.: Date:
Cone no.:
Project no.:
CPT no.:
0.80 m Predrilled
-0.80 m 28/09/20150.00 m
C10CFIIP.C12130D157CPT_04 1/2
Project:Location:Position: 0, 0
Boat harbourClifton Springs
u2
cm² cm² 150 10
Processed : TH Checked: RB
1.44
0
-0.5
-1
-1.5
-2
-2.5
-3
-3.5
-4
-4.5
-5
-5.5
-6
-6.5
-7
-7.5
-8
-8.5
-9
-9.5
-10
-10.5
-11
<- D
epth
in m
bel
ow g
roun
d le
vel (
G.L
.) / c
orre
cted
for i
nclin
atio
n
0 10 20 30 40
qt in MPa
Refusal at 8.44m Inclination
Hole dipped to 0.8m
0 0.2 0.4 0.6 0.8
Sleeve f riction (fs) in MPa
Refusal at 8.44m Inclination
Hole dipped to 0.8m
-0.1 0 0.1 0.2 0.3
u2 in MPa
Refusal at 8.44m Inclination
Hole dipped to 0.8m
0 2 4 6 8
Friction ratio (Rf ) in %
Refusal at 8.44m Inclination
Hole dipped to 0.8m
Client :A.S.Miner Geotechnical
G.L.:
Predrill:
W.L.: Date:
Cone no.:
Project no.:
CPT no.:
0.80 m Predrilled
-0.80 m 28/09/20150.00 m
C10CFIIP.C12130D157CPT_04 2/2
Project:Location:Position: 0, 0
Boat harbourClifton Springs
u2
cm² cm² 150 10
Processed : TH Checked: RB
1.44
0
-0.5
-1
-1.5
-2
-2.5
-3
-3.5
-4
-4.5
-5
-5.5
-6
-6.5
-7
-7.5
-8
-8.5
-9
-9.5
-10
-10.5
-11
<- D
epth
in m
bel
ow g
roun
d le
vel (
G.L
.) / c
orre
cted
for i
nclin
atio
n
0 8 16 24 32 40
Corrected cone resistance (qt) in MPa
Refusal at 8.44m Inclination
Hole dipped to 0.8m
0 40 80 120 160 200
Su(min) in kPa
Refusal at 8.44m Inclination
Hole dipped to 0.8m
0 40 80 120 160 200
Su(max) in kPa
Refusal at 8.44m Inclination
Hole dipped to 0.8m