Gas Regional Initiative North-WestTransmission Transparency

Transmission Transparency Project

GRI North-West Operators‘ Group

Stakeholder Group Meeting

London, 14 November 2008

Contact:Oliver AltenhoffE.ON Gastransport GmbHOliver.altenhoff@eon-gastransport.comwww.eon-gastransport.com

Page 2: Gas Regional Initiative North-West Transmission Transparency Transmission Transparency Project GRI North-West Operators‘ Group Stakeholder Group Meeting

Page 2

Stakeholder Group Meeting; London 14 November

Gas Regional Initiative North-WestTransmission Transparency

Agenda:

Intro-duction

Project

Moni-toring

Next steps

Outlook

Agenda

Introduction

Transmission transparency project

Monitoring

Next steps in the project

Transparency workstream outlook

Page 3: Gas Regional Initiative North-West Transmission Transparency Transmission Transparency Project GRI North-West Operators‘ Group Stakeholder Group Meeting

Page 3

Stakeholder Group Meeting; London 14 November

Gas Regional Initiative North-WestTransmission Transparency

Agenda:

Intro-duction

Project

Moni-toring

Next steps

Outlook

Introduction

Market request

Wish list

Ofgem-Workshop

Project- Plan

Implementationat TSO

Progress-Report

Page 4: Gas Regional Initiative North-West Transmission Transparency Transmission Transparency Project GRI North-West Operators‘ Group Stakeholder Group Meeting

Page 4

Stakeholder Group Meeting; London 14 November

Gas Regional Initiative North-WestTransmission Transparency

Agenda:

Intro-duction

Project

Moni-toring

Next steps

Outlook

Participating TSO

Page 5: Gas Regional Initiative North-West Transmission Transparency Transmission Transparency Project GRI North-West Operators‘ Group Stakeholder Group Meeting

Page 5

Stakeholder Group Meeting; London 14 November

Gas Regional Initiative North-WestTransmission Transparency

Agenda:

Intro-duction

Project

Moni-toring

Next steps

Outlook

Project Overview

Objective of the transmission transparency project:

Improve the publication of capacity and flow data

Provide clarity over published data

Steps:

Enlist participating operators

Develop anticipated time schedule

Establish individual TSO implementation plans

Monitor improvements

Page 6: Gas Regional Initiative North-West Transmission Transparency Transmission Transparency Project GRI North-West Operators‘ Group Stakeholder Group Meeting

Page 6

Stakeholder Group Meeting; London 14 November

Gas Regional Initiative North-WestTransmission Transparency

Agenda:

Intro-duction

Project

Moni-toring

Next steps

Outlook

Information to be published

Capacity Information(C1) Max technical capacity of the transmission system

(C2) Level of interruption probability

(C3) Daily commercial firm and interruptible capacity

Flow Information(F1) Daily flow and interruptions

(F2) Daily prompt allocation information to each shipper

(F3) Daily aggregate day-ahead nominations

(F4) Historic gas flow information database

Page 7: Gas Regional Initiative North-West Transmission Transparency Transmission Transparency Project GRI North-West Operators‘ Group Stakeholder Group Meeting

Gas Regional Initiative North-WestTransmission Transparency

Examples of the project

Page 8: Gas Regional Initiative North-West Transmission Transparency Transmission Transparency Project GRI North-West Operators‘ Group Stakeholder Group Meeting

Page 8

Stakeholder Group Meeting; London 14 November

Gas Regional Initiative North-WestTransmission Transparency

Agenda:

Intro-duction

Project

Moni-toring

Next steps

Outlook

Daily flow

Page 9: Gas Regional Initiative North-West Transmission Transparency Transmission Transparency Project GRI North-West Operators‘ Group Stakeholder Group Meeting

Page 9

Stakeholder Group Meeting; London 14 November

Gas Regional Initiative North-WestTransmission Transparency

Agenda:

Intro-duction

Project

Moni-toring

Next steps

Outlook

Daily aggregate day-ahead nominations

Page 10: Gas Regional Initiative North-West Transmission Transparency Transmission Transparency Project GRI North-West Operators‘ Group Stakeholder Group Meeting

Page 10

Stakeholder Group Meeting; London 14 November

Gas Regional Initiative North-WestTransmission Transparency

Agenda:

Intro-duction

Project

Moni-toring

Next steps

Outlook

Daily Nominations and Allocations

Page 11: Gas Regional Initiative North-West Transmission Transparency Transmission Transparency Project GRI North-West Operators‘ Group Stakeholder Group Meeting

Page 11

Stakeholder Group Meeting; London 14 November

Gas Regional Initiative North-WestTransmission Transparency

Agenda:

Intro-duction

Project

Moni-toring

Next steps

Outlook

Capacity Information

Page 12: Gas Regional Initiative North-West Transmission Transparency Transmission Transparency Project GRI North-West Operators‘ Group Stakeholder Group Meeting

Page 12

Stakeholder Group Meeting; London 14 November

Gas Regional Initiative North-WestTransmission Transparency

Agenda:

Intro-duction

Project

Moni-toring

Next steps

Outlook

Level of Interruption

Page 13: Gas Regional Initiative North-West Transmission Transparency Transmission Transparency Project GRI North-West Operators‘ Group Stakeholder Group Meeting

Page 13

Stakeholder Group Meeting; London 14 November

Gas Regional Initiative North-WestTransmission Transparency

Agenda:

Intro-duction

Project

Moni-toring

Next steps

Outlook

Progress: January to October 2008

11

14

15

16

5

6

11

13

9

1313

16

4

9 9

14

13

14

16 16

2

3

4

10

7

11

12

15

0

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

Max technicalcapacity

Interruption Daily commercialfirm and interruptible

capacity

Dailyflow/aggregated

allocation

Daily promptallocation information

Daily aggregate day-ahead nominations

Historic gas flowinformation database

Jan 08

Apr 08

Oct 08

Dec 08 (expected)

Page 14: Gas Regional Initiative North-West Transmission Transparency Transmission Transparency Project GRI North-West Operators‘ Group Stakeholder Group Meeting

Page 14

Stakeholder Group Meeting; London 14 November

Gas Regional Initiative North-WestTransmission Transparency

Agenda:

Intro-duction

Project

Moni-toring

Next steps

Outlook

Next Steps

Jan. 2009: Implementation monitoring

Jan. 2009: review the results

of the project

Feb. 2009: lessons learned

Feb. 2009: Any improvements left?

Page 15: Gas Regional Initiative North-West Transmission Transparency Transmission Transparency Project GRI North-West Operators‘ Group Stakeholder Group Meeting

Page 15

Stakeholder Group Meeting; London 14 November

Gas Regional Initiative North-WestTransmission Transparency

Agenda:

Intro-duction

Project

Moni-toring

Next steps

Outlook

Outlook

Road map - work plan 2009:

Discussion on further requirements with stakeholders

Less than 3 rule applicable

TSOs´ websites harmonized

Further Information

Project schedule

Deliverables