Approval for permission of laying Gas pipelines along and across NHs
Step No.
Authority Action to be taken Timeline
1 Applicant (Agency)
Submission of the application, as per the
Guidelines of NHAI and MoRT&H along with
related undertakings and Draft License
Agreement, to the respective NHAI Project
Implementation Unit (PIU) office in the
prescribed format available online.
Process
Initiation
2 Project Director
The application, documents and related undertaking are checked as per guidelines. After examination of the application : (i) If there are deficiencies in the Proposal or if the Proposal is not admissible; The same is communicated to Applicant. Applicant may submit the revised proposal. (ii) If Proposal is OK, forward the proposal to Independent/Authority Consultant and Concessionaire.
15 Days from
date of
submission of
physical
proposal at
NHAI PIU
office
3 Independent/Authority Consultant and Concessionaire
Examination of the proposal and a joint site
inspection is done. A site visit report is
prepared and forwarded to the Project
Director.
30 Days
from date of
receipt of
proposal
from Project
Director
4 Project Director
The site inspection is carried out and forwards the proposal with recommendations for approval to NHAI Regional Officer.
15 Days
5 NHAI Regional Officer
Grants approval or rejection and communicates to the Project Director.
30 Days
6 Project Director
Conveys approval/rejection to Applicant (Agency) and in case of approval, issues Demand Note to Applicant (Agency).
7 Days
7 Applicant (Agency)
Completes the necessary payment for the Demand Note issued.
15 Days
8 Project Director
Executes the agreement after verification of
Bank Guarantee and issues the Final
Permission to the Applicant (Agency).
15 Days