FORM 1
(I) Basic Information
S.No Item Details
1 Name of the project/s Development of Residential Apartment project
2 S. No. in the schedule Category B1 of EIA Notification 2006 “8(b)”
3 Proposed capacity/ area / length / tonnage
to be handled / command area / lease area
/ number wells to be drilled be.
Total Site Area: 40974.98Sq m
Total Built-up area 136425.088 Sq.m
Proposed units: 762 apartments & clubhouse
4 New/ Expansion/Modernization New
5 Existing Capacity / Area etc NA
6 Category of Project. 'A' or 'B' ‘B1’ Category
7 Does it attract the general condition? If
'yes, please specify.
NA
8 Does it attract the specific condition? If
'yes, please specify.
NA
9 Location Hosahalli, Bangalore North
Plot/Survey/Khatha No Survey No 132/1, 132/2, 133/1, 133/2, 133/3
135/1 & 136/1 at Hosahalli, Bangalore North
Village Hosahalli, Bangalore North
Tahsildar Jala Hobli
District Bangalore
State Karnataka
10 Nearest railway station/airport long with
Distance in kms.
Yelahanka Railway station (SW)-8.8 Km
Kempegowda International Airport (NE)–16 Km
11 Nearest Town, city, District Headquarters
along with distance in kms
Located in Bangalore city
12 Village Panchayat Zilla Parishad
Municipal Corporation, Local body
(complete postal addresses with
telephone nos. to be given
BIAAPA
13 Name of the applicant Puravankara Limited
14 Registered Address Puravankara Limited
#130/1, Ulsoor road,
Bangalore – 42
15 Address of correspondence
Name Mr Prashanth Marathe
Designation(Owner /Partner/CEO) Sr. Manager
(Authorized Signatory)
Address Puravankara Limited.
130/1, Ulsoor Road
Bangalore
Pin Code 560042
E-mail [email protected]
Telephone No. 080 25599000
Fax No. 080 25599350
16 Details of Alternative sites examined, if
any. Location of these sites should be
shown on a top sheet
NA
17 Interlinked Projects NA
18 Whether separate application of
interlinked project has been submitted
No
19 If yes, date of submission NA
20 If no, reason -
21 Whether the proposal involves approval /
clearance under: if yes, details of the
same and their status to be given
(a)Forest (conservation) Act, 1980?
(b)The Wild Life (Protection) Act 1972?
(c)The CRZ Notification, 1991?
NA
22 Whether there is any Government Order/
Policy relevant/ relating to the site?
No
23 Forest land involved (hectares) Not involved
24 Whether there is any litigation pending
against the project and/ or land in which
the project is propose to be set up?
Name of the site Case No Orders /
Directions of the court, if any and its
relevance with the proposed project
No
(II) Activity
1. Construction, operation or decommissioning of the Project involving actions, which will cause
physical changes in the locality (topography, land use, changes in water bodies, etc.)
S. No. Information/Checklist confirmation Yes/
No
Details thereof (with approximate
quantities /rates, wherever possible)
with source of information data
1.1 Permanent or temporary change in
land use, land cover or topography
including increase in intensity of land
use (with respect to local land use
plan)
No Undeveloped land is being developed
into residential purpose. As per the CDP
the proposed project site is designated as
residential use. Copy of CDP is enclosed
in report.
1.2 Clearance of existing land, vegetation
and buildings?
No No trees are observed.
1.3 Creation of new land uses? No NA
1.4 Pre-construction investigations e.g.
bore houses, soil testing?
Yes Soil testing under process. Will submit
the details once completed.
1.5 Construction works? No To be taken up once the project gets
cleared from concerned authorities
1.6 Demolition works? No -NA-
1.7 Temporary sites used for construction
works or housing of construction
workers?
No -NA-
1.8 Above ground buildings, structures or
earthworks including linear structures,
cut and fill or excavations
Yes Earthwork excavation quantity is
about 80000 cubic meters and
filling quantity is about 32000
cubic meters. The remaining
48000 cubic meters soil can be
used for preparation of soil
blocks at site (which can be used
for construction of compound
wall). Hence no transportation of
soil is required from site.
.9 Underground works including mining
or tunneling?
No -
1.10 Reclamation works? No -
1.11 Dredging? No -
1.12 Offshore structures? No NA
1.13 Production and manufacturing
processes?
No Construction project.
1.14 Facilities for storage of goods or
materials?
No During construction period construction
materials will be stored within the site
which is non-hazardous in nature.
During operation period fuel, lube oil for
DG sets & waste oil from DG sets will be
stored in leak proof containers on
impervious floor in a designated place
within the site premises.
1.15 Facilities for treatment or disposal of
solid waste or liquid effluents?
Yes During construction period-mobile STP
of about 10 KLD will be provided.
During operation period- STP of 500
KLD will be provided for treatment of
sewage.
For solid waste, Organic waste converter
will be used for converting organic
waste into manure which can be used for
gardening
1.16 Facilities for long term housing of
operational workers?
No There is no residential facility for
operational workers as they will be
deployed from local area.
1.17 New road, rail or sea traffic during
construction or operation?
No NA
1.18 New road, rail, air waterborne or other
transport infrastructure including new
or altered routes and stations, ports,
airports etc?
No NA
1.19 Closure or diversion of existing
transport routes or infrastructure
leading to changes in traffic
movements?
No NA
1.20 New or diverted transmission lines or
pipelines?
No NA
1.21 Impoundment, damming, culverting,
realignment or other changes to the
hydrology of watercourses or
aquifers?
No -
1.22 Stream crossings? No -
1.23 Abstraction or transfers of water form
ground or surface w
aters?
Yes Water requirement during Construction
phase will be met through samy’s
projects next to the project site. For
drinking 10 KLD fresh water will be
provided and operation phase will be met
through BWSSB water supply.
1.24 Changes in water bodies or the land
surface affecting drainage or run-off?
No There shall be no changes in water
bodies or the land surface.
It is proposed to collect rain water from
roof surfaces in collection storage sumps,
paved surfaces & unpaved surfaces will
be collected & recharged in harvesting
pits within the proposed development to
the rain water harvesting pits.
1.25 Transport of personnel or materials for
construction, operation or
decommissioning.
Yes There will be temporary influx of
construction labor, however upon
operation there will be permanent
settlement of people.
1.26 Long-term dismantling or
decommissioning or restoration
works?
No -
1.27 Ongoing activity during
decommissioning which could have an
impact on the environment?
No -
1.28 Influx of people to an area in either
temporarily or permanently?
Yes There will only be a temporary influx of
construction laborer’s, and this will be
only for a short period until the
completion of the construction activity.
However upon completion the occupants
will reside here thus resulting in
permanent influx of people.
1.29 Introduction of alien species? No -
1.30 Loss of native species or genetic
diversity?
No -
1.31 Any other actions? No Eco-friendly activities like tree plantation
& landscaping will be undertaken.
2. Use of Natural resources for construction or operation of the Project (such as land, water,
materials or energy, especially any resources which are non-renewable or in short supply):
S.No
.
Information/Checklist
confirmation
Yes
/No
Details thereof (with approximate
quantities /rates, wherever possible) with
source of information data
2.1 Land especially undeveloped or
agricultural land users) (ha)
Yes 40974.98 Sq m of vacant land, converted for
residential purpose.
2.2 Water (expected source &
competing unit: KLD)
Yes During construction phase
For construction :15 KLD
Domestic: 10 KLD is required.
During Operational phase
290KLD of fresh water for domestic purpose
& 240KLD of recycled water being used for
Domestic use, flushing & 87 KLD for green
belt development.
2.3 Minerals (MT) No -NA-
2.4 Construction material – stone,
aggregates, sand / soil (expected
source – MT)
Yes Material
Description
Units of
Measurement
Approx
Qty
Concrete m3
Steel M T
Cement m3
Sand m3
Aggregate m3
2.5 Forests & timber(source– MT) No Usage of timber will be minimal
2.6 Energy including electricity and
fuels (source, competing users)
Unit: fuel (MT), energy (MW)
Yes During construction
100 kVA power is required
During Operation
BESCOM to provide about 4000 KVA
2.7 Any other natural resources (use
appropriate standard units)
Yes Solar energy will be used for street and
common area lighting & for water heating at
top floors.
3. Use, storage, transport, handling or production of substances or materials, which could be
harmful to human health or the environment or raise concerns about actual or perceived risks to
human health.
S.No
.
Information/Checklist
confirmation
Yes
/No
Details thereof (with approximate
quantities /rates, wherever possible) with
source of information data
3.1 Use of substances or materials,
which are hazardous (as per MSIHC
rules) to human health or the
environment (flora, fauna, and
water supplies)
No -NA-
3.2 Changes in occurrence of disease or
affect disease vectors (e.g. insect or
water borne diseases)
No -NA-
3.3 Affect the welfare of people e.g. by
changing living conditions?
No -NA-
3.4 Vulnerable groups of people who
could be affected by the project e.g.
hospital patients, children, the
elderly etc.
No -NA-
3.5 Any other causes No -NA-
4. Production of solid wastes during construction or operation or decommissioning (MT/month)
Sl.No. Information/Checklist confirmation Yes/
No
Details thereof (with approximate
quantities /rates, wherever possible) with
source of information data
4.1 Spoil, overburden or mine wastes No -NA-
4.2 Municipal waste (domestic and or
commercial wastes)
Yes During operation :
Organic Waste : 914.4 kg/day
Inorganic Waste: 609.6kg/day
Organic waste is converted into manure and
Inorganic waste will be sent for recycling.
4.3 Hazardous wastes (as per Hazardous
Waste Management Rules)
Yes Spent oil from DG sets which will be stored
in leak proof containers & sent to authorized
authority for disposal
4.4 Other industrial process wastes No -NA-
4.5 Surplus product No -NA-
4.6 Sewage sludge or other sludge from
effluent treatment
Yes STP sludge of about 42 Kg/day which will be
filter pressed & used for gardening as manure
4.7 Construction or demolition wastes
Yes The construction debris will be segregated
viz.; steel, metal, plastics, papers etc. and
these will be sold to scrap dealers.
4.8 Redundant machinery or equipment No -NA-
4.9 Contaminated soils or other materials No -NA-
4.10 Agricultural wastes No -NA-
4.11 Other solid wastes No -NA-
5. Release of pollutants or any hazardous, toxic or noxious substances to air (Kg/hr.)
Sl.No Information/Checklist
confirmation
Yes
/No
Details thereof (with approximate quantities
/rates, wherever possible) with source of
information data
5.1 Emissions from combustion of
fossil fuels from stationary or
mobile sources
Yes The gaseous emissions are expected from
transport vehicles moving inside the project
site. This will be minimized/ eliminated by
slow movement of vehicles, hiring well
maintained vehicles, planting trees and
spraying water periodically.
The emissions are expected from Diesel
Generator during operation phase. The DG
stack height will be as per CPCB norms
5.2 Emissions from production
processes
No -NA-
5.3 Emissions from materials handling
including storage or transport
Yes Emissions like dust will arise during the
transportation of materials and the dust will
be controlled by slow movement of vehicles,
covering the materials properly and by
Periodical water spraying.
5.4 Emissions from construction
activities including plant and
equipment
Yes Apart from fugitive dust emissions, there will
be emissions from concrete mixers, dozers,
diesel pumps etc during construction. These
equipments will be maintained properly to
have minimum impact.
5.5 Dust or odors from handling of
materials including construction
materials, sewage and waste
Yes During construction phase the dust is
suppressed by sprinkling water. The dust
barricades will be provided all around the
project site.
Proper sanitation measures to be taken within
the site to remove odor problem
5.6 Emissions from incineration of
waste
No -NA-
5.7 Emissions from burning of waste in
open air (e.g. slash materials,
construction debris)
No -NA-
5.8 Emissions from any other sources No -NA-
6. Generation of Noise and Vibration, and Emissions of Light and Heat:
SI.
No
Information/Checklist
confirmation
Yes/
No
Details thereof (with approximate
quantities /rates, wherever possible)
with source of information data
6.1 From operation of equipment e.g.
engines, ventilation plant, crushers
Yes Readymade concrete will be used at site.
In case of any usage of machinery/
equipment, then they will be properly
covered and the workers will be given ear
plugs in noisy area.
D.G Set: Acoustic enclosures and
adequate stack height will be provided for
the D.G. set as per CPCB norms.
6.2 From industrial or similar processes No -NA-
6.3 From construction or demolition Yes Noise levels in the range of 75-80 dB (A)
will be generated occasionally during the
construction activities. Workers in the
noisy areas will be provided with
earmuffs and earplugs.
6.4 From blasting or piling No -NA-
6.5 From construction or operational
traffic
Yes Traffic both during construction and
operational phase. The noise will be
reduced by proper maintenance of
vehicles & proper traffic management, etc.
6.6 From lighting or cooling systems No -NA-
6.7 From any other sources No -NA-
7. Risks of contamination of land or water from releases of pollutants into the ground, or into
sewers surface waters, groundwater, coastal waters or the sea:
S.No Information/Checklist
confirmation
Yes/
No
Details thereof (with approximate
quantities /rates, wherever possible)
with source of information data
7.1 From handling, storage, use or
spillage of hazardous materials
Yes DG sets spent oil will be stored in leak
proof containers and sent to authorized
agencies for disposal
7.2 From discharge of sewage or other Yes Liquid waste
effluents to water or the land
(expected mode and place of
discharge)
During construction period-sewage will be
disposed using 10KLD mobile STP
During operation period- sewage water
will be treated using 500 KLD STP .The
treated wastewater will be reused for
domestic usage, toilet flushing and green
belt development.
7.3 By deposition of pollutants emitted
to air into the land or into water
No -NA-
7.4 From any other sources No -NA-
7.5 Is there a risk of long term build up
of pollutants in the environment
from these sources?
No -NA-
8. Risk of accidents during construction or operation of the Project, which could affect human
health or the environment
S.No Information/Checklist
confirmation
Yes/
No
Details thereof (with approximate
quantities /rates, wherever possible) with
source of information data
8.1 From explosions, spillages, fires etc
from storage, handling, use or
production of hazardous substances
No -NA-
8.2 From any other causes No -NA-
8.3 Could the project be affected by
natural disasters causing
environmental damage (e.g. floods)
No The area under study falls in Zone-II
according to the Indian Standard Seismic
Zoning Map. The structure was designed
to be earthquake resistant. The proposed
project will not be affected by natural
disasters causing environmental damage.
9. Factors which should be considered (such as consequential development) which could lead to
environmental effects or the potential for cumulative impacts with other existing or planned
activities in the locality
S.No Information/Checklist
confirmation
Yes
/No
Details thereof (with approximate
quantities /rates, wherever possible) with
source of information data
9.1 Lead to development of supporting.
facilities, ancillary development or
development stimulated by the
project which could have impact on
the environment e.g.
• Supporting infrastructure (roads,
power supply, waste or waste water
treatment, etc.)
• housing development
• Extractive industries
• Supply industries
Yes
Yes
No
No
Supporting and ancillary development will
take place which in turn will improve
environment (e.g.,) Plantation of trees,
rainwater harvesting, Storm water drains
etc., Basic infrastructure will be developed
in the proposed area.
Residential Building will be constructed.
No Extraction
No Industrial activity
9.2 Lead to after-use of the site, which
could haven impact on the
environment
No -NA-
9.3 Set a precedent for later
developments
Yes -
9.4 Have cumulative effects due to
proximity to other
No -NA-
(III) Environmental Sensitivity
S.No Area Name/
Identity
Aerial distance (within 15 km.)
Proposed project location boundary
1 Areas protected under international
conventions, national or local
legislation for their ecological,
Yes Banneraghatta National Park(S) – 60
Km
landscape, cultural or other related
value
2 Areas which are important or
sensitive for other water bodies,
coastal zone, biospheres,
ecological reasons - Wetlands,
watercourses or mountains, forests
Yes Banneraghatta National Park(S) –
60 Km
Bagalur Lake(SE) -1.01 KM
3 Areas used by protected, important
or sensitive species of flora or
fauna for breeding, nesting,
foraging, resting, over wintering,
migration
No No Significant Species
4 Inland, coastal, marine or
underground waters
Yes Bagalur Lake(SE) -1.01 KM
5 State, National boundaries No No State, National boundaries
6 Routes or facilities used by the
public for access to recreation or
other tourist, pilgrim areas
No The proposed site is in a residential
zone.
7 Defense installations No Nil
8 Densely populated or built-up area Yes The proposed Residential project is
located inside Bangalore.
9 Areas occupied by sensitive man-
made land uses(hospitals, schools,
places of worship, community
facilities)
Yes Primary schools, temples and health
care facilities and residential buildings
are seen in a 5 km radius from the
project site.
10 Areas containing important, high
quality or scarce resources(ground
water resources, surface resources,
forestry, agriculture, fisheries,
tourism, minerals)
No There is no high quality or scarce
resources
11 Areas already subjected to
pollution or environmental
No Not applicable
damage. (those where existing
legal environmental standards are
exceeded)
12 Areas susceptible to natural hazard
which could cause the project to
present environmental problems
(earthquakes, subsidence,
landslides, erosion, flooding)
Yes The area under study falls in Zone-II,
according to the Indian Standard
Seismic Zoning Map.
(IV) Proposed Terms of Reference for EIA studies: NA
“I hereby given undertaking that data and information given in the application and enclosures
are true to the best of the knowledge and belief and I am aware that if any part of the data and
information submitted is found to be false or misleading at any stage, the project will be rejected
and clearance given, if any to the project will be revoked at our risk and cost.”
Date: 25th November 2017
Place: Bangalore Signature of the applicant
Name: Prashanth Marathe
Designation: Senior Manager
Address: No. 130/1, Ulsoor Road
Bangalore - 560042