Upload
ada-caldwell
View
221
Download
0
Embed Size (px)
DESCRIPTION
3 Part A Section 1.1.2, Planning Team –Removed lands administration, fire management, parks and natural heritage, and enforcement staff as members –Added requirement for MNR District Manager to appoint a Project Manager –Steering committee now a requirement
Citation preview
Forest Management Planning Manual, 2009
Part A January, 2009
2
Part A• Section 1.0, Preparing the 10-year FMP
– Updated preparation time to 36 months
– Updated Figure A-1 to reflect 36 months
– Removed Figure A-2
3
Part A• Section 1.1.2, Planning Team
– Removed lands administration, fire management, parks and natural heritage, and enforcement staff as members
– Added requirement for MNR District Manager to appoint a Project Manager
– Steering committee now a requirement
4
Part A• Section 1.1.2.1, Terms of Reference
– Recognize previous planning effort – review, and confirm, update or revise
– No longer updated throughout planning process
– Moved some requirements to project plan• Section 1.1.2.2, Project Plan
– Now a requirement– Must be updated throughout planning process
5
Part A• Section 1.1.5, Decision Support Systems
– Moved from section 1.2
• Section 1.1.6, Progress Checkpoints– Changed four checkpoints
6
Part A• Section 1.1.8, Background Information
– Recognize previous planning effort – review, and confirm, update or revise
• Section 1.1.8.1, Sources of Direction– Added endangered species, species of
special concern and habitat regulations under ESA, 2007
7
Part A• Section 1.1.8.2, Provincial Audits and
Reports– Reference to availability on internet
• Section 1.1.8.3, Forest Management Guides
– Reference to internet site where guides can be accessed
8
Part A• Section 1.1.8.5, Planning Inventory
– FMP-1 and FMP-2 no longer part of Planning Inventory check point
• Section 1.1.8.7, Inventories and Information for Species at Risk
– New, specific to species at risk
9
Part A• Section 1.1.8.9, Values Maps
– Removed text stating values maps available for public distribution upon request
• Section 1.1.8.10, Roads Inventory– Information Product– Portray as per FIM, 2009
10
Part A• Section 1.1.9.1, Aboriginal Background
Information Report– Added to section 1.1 as part of
background information.
11
Part A• Section 1.2, Preparing for Stage Two –
Proposed Long Term Management Direction– Removed Figure A-3 (FMPM, 2004)– Recognize previous planning effort –
review, and confirm, update or revise– Updated Figure for LTMD Process– Removed requirement for Natural Benchmark– Replaced references to “management
strategy” with “Long Term Management Direction”
12
Part A• Section 1.2.2.3, Forest Landscape
Biodiversity Classifications– Replace Habitat Classifications– Facilitate use of the Landscape Guide
• Section 1.2.3, Management Considerations
– Added climate change
13
Part A• Section 1.2.4, Base Model
– Recognize previous planning effort – review, and confirm, update or revise
• Section 1.2.4.1, Forest Dynamics - Growth and Yield
– Added requirement to provide separate estimates for yield (biofibre)
14
Part A• Section 1.2.2.4, Strategic Silvicultural
Options– Removed similar silviculture
expenditures as a criteria for grouping SGRs
– Strategic silvicultural options in base model must be consistent with most common SGR
15
Part A• Section 1.2.4.5, Management Zones
– Provide spatial context– Strategic and Operational– Must provide a description in text
16
Part A• Section 1.2.6, Developing management
Objectives– Incorporated desired forest and
benefits meeting• Targets
– Established for first ten-year period of the FMP at a minimum
– Consider past plans and historical objective achievement
17
Part A• Figure A-3, Indicators of Objective
Achievement (Figure A-5 FMPM, 2004)– Separated indicators assessed during
plan preparation and implementation– Removed criterion column– Facilitate implementation of Landscape
Guide and Stand and Site Guide– Modified compliance indicators
18
Part A• Section 1.2.7.2, Spatial Assessment
– Added management zones to the considerations for preferred harvest areas
– Added direction for selecting preferred harvest areas regarding spatial and non-spatial models
19
Part A• Section 1.2.7.3, Social and Economic
Assessment– Removed requirement to use a social
and economic model• Section 1.2.10, LTMD Summary
– Removed FMP table requirements
20
Part A• Section 1.3, Planning of Proposed
Operations– Recognize previous planning effort –
review, and confirm, update or revise– Removed all references to “selected”
harvest areas
21
Part A• Section 1.3.3.1, Harvest Areas
– One year harvest area from term 2 available for unforeseen circumstance in term 1
– Removed frequency distribution template requirements
• Section 1.3.4.1, Bridging Operations– Extended to one year
22
Part A• Section 1.3.5, Prescriptions for
Operations– Preliminary prescriptions may be
developed for 2nd five year term– Added text for operational prescriptions
for Species at Risk• Section 1.3.5.1Operational Prescriptions
for Areas of concern– Added that these are also required for
areas of renewal and tending
23
Part A• Section 1.3.5.2 Prescriptions for Harvest,
Renewal and Tending Areas– Added conditions on regular
operations
24
Part A• Section 1.3.6.3, AOC Crossings, Primary
and Branch Roads– Crossing of AOCs for the 2nd five year
term may be developed and mapped in Phase I
• Section 1.3.6.4, Operational Roads– Operational road boundary
25
Part A• Section 1.3.6.6, Aggregate
– Extraction Areasa) New to Part Ab) Existing Roadsc) Within 500 metres
– Clarified where aggregate may be removed
Category 14 aggregate pits now regulated by FMPM and applicable guide
26
Part A• Section 1.3.6.7, Use Management Strategies
– Added direction for biofibre collection– Removed reference to existing roads table
• Section 1.3.7, Expenditures– Removed revenues requirements
• Section 1.3.8, Monitoring and Assessment– New to part A
27
Part A• Section 1.3.9, Spatial Assessment
– Conditional upon amount of change
• Section 1.3.12, Summary Map– Removed past and approved harvest
areas for the current fmp, and previous 10 yrs
28
Part A• Section 1.4, Preparation/Submission of
Draft Forest Management Plan– Deleted Figure A-7
• Section 1.4.2, Preparation of Draft FMP– Portal submission identifier on
Certification page
29
Part A• Section 1.4.3, Draft Plan Submission
– Removed reference to copies and distribution of fmps
– French language for summaries mandatory
• Section 1.5.2, Final List of Required Alterations
– Receive list (SFL, plan author, LCC)– Receive written response
30
Part A• Section 1.5.3, Preparation of the FMP
and FMP Summary– MNR Regional Director presentation of
the FMP no longer mandatory– Removed mandatory attendance for
MNR District Manager and Senior SFL Official
31
Part A• Section 2.0 Phase II Planning
– 20 months to prepare, review and approve
– Recognize previous planning effort – review, and confirm, update or revise
• Section 2.1.8.2, Prescriptions for Harvest, Renewal and Tending Areas
– Consider year ten AR analysis
32
Part A• Section 2.2.3, Submission of Draft
Planned Operations– Removed references to copies of draft
fmp
• Section 2.2.5, Draft Plan Operations Summary
– French version must be prepared
33
Part A• Section 2.2.6, Availability of Draft
Planned Operations– Removed references to locations for
public review• Section 2.3.1, Revision and Approval of
Planned Operations– Plan author may discuss alterations
with MNR reviewers
34
Part A• Section, 2.2.3, Preparation of Planned
Operations– Removed mandatory requirement to
present to MNR Regional Director– Removed mandatory attendance for
MNR District Manager and Senior SFL Official
35
Part A• Section 3.0, Public Consultation
– Removed locations of Management Unit list availability (internet)
– Removed requirement to provide Management Unit List
36
Part A• Section 3.2.4, LCC Terms of Reference
– Removed requirement for public distribution
– Removed background material and training required
• Section 3.3.2.1, Supplemental Notices– 7 day supplemental notice is now
optional
37
Part A• Section 3.3.2.3, Responses to Comments
– Direction for form letters• Section 3.3.3, Consultation
– Removed requirement for a display
38
Part A• Section 3.3.3.1, Phase I, Stage I,
Invitation to participate– Information available
• Removed planning inventory• Added landscape pattern map• Removed map of the management
unit• Removed FMP-1 and FMP-2
39
Part A• Section 3.3.3.3, Phase I, Stage III, Review
of Proposed Operations– Removed requirement to portray
optional harvest areas on summary map
• Section 3.3.3.4, Phase I, Stage IV, Review of Draft FMP
– Removed insect pest management requirements for information centre
40
Part A• Section 3.3.4.1, Phase II, Stage I, Review
of Proposed Operations– Require existing roads map and road
responsibility– Removed all AWSs from info centre– Removed requirement for MNR District
Manager to attend
41
Part A• Section 3.4.1, Issue Resolution Process
– Identified where process applies– Representative for a concerned group– Rational for decision included in
summary of public consultation– Adjusted timelines in issue resolution
figures
42
Part A• Section 3.4.1, Issue Resolution Process
– added requirement for concerned person to provide dates for a meeting
– Step 6, removed requirement for additional 15 days if a meeting could not be arranged
– Combined MNR DM portion of Step 9 with Step 8, Step 9 now RD stage only
Forest Management Planning Manual, 2009
Part B January, 2009
Craig Crosson R.P.F.
44
Part B• Section 1.0, Introduction
– Removed map requirement• Section 2.1 Forest Description
– Removed geology, soils and sites– Removed historic forest discussion– Added forest unit discussion– Added habitat discussion– Added inventories and information for
species at risk discussion
45
Part B• Section 3.4, Management Zones
– Added discussion on management zones
• Section 4.0, Planned Operations– Text to describe all ten years of
operations
46
Part B• Section 4.2, Prescriptions for Operations
– Information product for AOCs– Conditions on regular operations– Information product for silvicultural
treatments of special public interest
47
Part B• Section 4.3.1, Harvest Areas
– “selected” and “forecast” now “planned” harvest area
– Harvest Area information product• Section 4.3.6, Harvest Volume
– Includes undersize material for bio-fibre• Section 4.3.7, Wood Utilization
– Undersize material will be identified (bio-fibre)
48
Part B• Section 4.4, Renewal and Tending
Operations– Information product
• Section 4.5.1.1, Operational Road Boundaries
– New, for aggregate purposes• Section 4.5.1.3, Area of Concern Crossings
– Operational Roads– Conditions now summarized in FMP-10
49
Part B• Section 4.5.2, Existing Roads
– New discussion section
• Section 4.5.3, – Road Information Product
50
Part B• Section 4.6, Expenditures
– Removed revenue requirements• Section 4.7.5, Fire Prevention and
Preparedness– New, description of measures to be
implemented
51
Part B• Section 4.8, Comparison of Proposed
Operations to the LTMD– Outlined assessment and discussion
requirements• Section 5.0, Determination of
Sustainability– Outlined documentation requirements
52
Part B• Section 6.1 Supplementary Documentation
– Updated to accommodate manual changes
• Section 7.0, FMP Summary– Removed map of management unit– Removed general description of forest– Removed index to EA components of
fmp
53
Part B• Section 8.0, Planned Operations for the
Second Five-Year Term– Updated whole section to be
consistent with Phase I planning requirements and clarified requirements for Phase II Planning
54
Part B• Section 9.0, FMP Tables
– FMP-1, removed all ownerships not Crown
– FMP-2, removed table from FMPM– FMP-6, removed table from FMPM– FMP-11, removed table from FMPM– FMP-12, removed table from FMPM– FMP-13, added timing of assessment
55
Part B• Section 9.0, FMP Tables
– FMP-14, removed sgr, objection, and primary or branch road crossing columns
– FMP-14, added conditions on locations and construction of operational roads
– FMP-15, removed projected column– FMP-16, removed statistics and
clearcuts < 260 requirements
56
Part B• Section 9.0, FMP Tables
– FMP-17, added net merchantable and bio-fibre as volume types
– FMP-18, added under size as a product– FMP-22, includes existing and planned
roads– FMP -23, removed operational roads– FMP-24, removed revenue portion– Existing Roads Table, deleted
Forest Management Planning Manual, 2009
Part C January, 2009
58
Part C• Section 1.0, Introduction
– Removed information repeated elsewhere• Section 2.0, Plan Amendments
– MNR may initiate amendment to change LTMD
– New certification page for LTMD amendments
– Removed information repeated elsewhere
59
Part C• Section 2.2.1
– Added direction for amendments required to provide protection for Species at risk (ESA 2007)
– Added text to clarify who receives amendment decisions
60
Part C• Section 2.6, Amendment Documentation
– All amendment documentation requirements
– Removed reference to “maps” – Reduced documentation requirements
for consultation• Section 2.7, Amendment Availability
– Added MNR web site
61
Part C• Removed Section 2.8 (FMPM 2004),
“Changes During AWS Implementation”
• Section 3.0– Forest management plan extensions
62
Part C• Section 3.2.2 Delay in Preparation of a
FMP– Details by stage of plan preparation – Requirements prior to and after LTMD
endorsement• 3.2.4 Contingency Plan Availability
– Refer to MNR website– Removed MOE documentation
requirement
63
Part C• Section 3.3, Plan Extension (New)
– Purpose– Eligibility requirements (FMPM 1996)– Preparation requirements– Documentation requirements
64
Part C• Section 4.0, Early Plan Renewals
– Removed Year Three Annual Report
• Section 5.0, Delay in Approval of 2nd five-Year Term Operations
– Provide details for selecting areas of operations for year six AWS
65
Part C• Section 6.2, Minor Amendment
Consultation– Consultation opportunity during
preparation
Forest Management Planning Manual, 2009
Part D, Annual Operations January, 2009
67
Part D• General
– Information Products (coverages)– Removed references to maps and lists– Minimal text and tables
68
Part D• Section 2.0, Forest Operations
Prescriptions– Changes to silvicultural treatments, no
longer appended to AWS– Change of SGRs required to be
submitted and appended to AWS
69
Part D• Section 3.2, Introduction
– Requirements removed, only state purpose of the AWS
70
Part D• Section 3.2.3, Harvest
– Up to two years of harvest area by forest unit may be identified
– SFL must ensure AHA is not exceeded due to AOC changes during ten-year plan period
– No text requirement for second pass and bridging operations
• Deleted wood utilization section
71
Part D• Section 3.2.5.2, Other Crossings of AOCs
– Review and approve changes to other crossings of AOCs
• Section 3.2.5.3, Water Crossing Decommissioning
– Review using criteria for the removal of water crossings
– Fisheries Act review
72
Part D• Section 3.2.6, Fire Prevention and
Preparedness– Removed standard information from
AWS• Revenues and Expenditures
– Removed requirements
73
Part D• Section 3.2.7, Monitoring and
Assessment– Removed redundancies– Water crossing monitoring now part of
information product– Assessment of regeneration success is
an information product
74
Part D• Section 3.3.4, Aggregates
– Removed text requirements• Provide clarification and information
product requirements for:– New category 14 pits– Existing category 14 pits– Aggregate Extraction Areas– Annual updates to aggregate information
75
Part D• Section 3.5, Changes during AWS
implementation– Incorporated all information from Part
C, Section 2.8– Direction for incorrectly identified
values– Deleted increased protection text– Ability to harvest areas when AOC no
longer exists
76
Part D• Section 3.6, AWS Tables
– Deleted AWS Tables 1,2,3,4,6,7– Two AWS Tables
a) Water Crossings to be constructed/reviewed
b) Water Crossings to be decommissioned
77
Part D• Section 4.0, Prescribed Burns
– Changed operational plan to prescribed burn plan
– Referrred to Manual for Prescribed Burns for all preparation, review and approval for PBs
– Removed references to High and Low complexity
– Changed posting requirements from seven to fourteen days
78
Part D• Section 5.0, Aerial Herbicide and
Insecticide Projects– Removed reference to MNR Aerial
Spray Manual– Added RD approves aerial insecticide
projects– Changed appended to available– Removed post operations report text
79
Part D• Section 6.0, Insect Pest Management
Programs– Plan must be developed with Forest
Management Branch Specialist
80
Part D• Section 7.0, Public Consultation
– Removed reference to high complexity PBs
– Added reference to AWS availability on the internet
– Added text stating one notice may be issued for multiple AWSs in a MNR District
81
Part D• Section 7.0, Public Consultation -
Notices– Removed text stating AWS public
notice may serve as notice for aerial herbicide projects
– Removed PBs and aerial spray from information to be available with AWS inspection notice
– Simplified notice requirements
82
Part D• Section 7.3, Prescribed Burns
– Removed reference to high complexity PBs
– Single notice may be used for multiple PBs
– Notice must identify MU and purpose
83
Part D• Section 7.4, Aerial Herbicide and
Insecticide Projects– AWS notice may not be used as aerial
herbicide/insecticide spray notice
84
Part D• Section 7.4, Insect Pest Management
Programs– Public notice for Stage I reduced to 15
days prior to information centre– Removed consultation schedule from
notice– Shortened public comment period
(Stage I) to 15 days
Forest Management Planning Manual, 2009
Part E, Annual Reporting January, 2009
86
Part E• Section 1.0, Introduction
– Information Products (coverages)– Clarified when year ten AR
requirements apply
87
Part E• Section 2.0, Content Requirements for
all ARs– Removed all references to stand lists– All text and discussion requirements
have been incorporated into Sections 2.1.3 and 2.1.4
– Only discuss SFL exception monitoring
88
Part E• Section 2.2, AR Tables
– Removed AR Tables 1, 2, 3, 6, 7, 10– Removed all year-to-date columns– Updated AR-9 to MOE/MNR Form– Removed Revenues from AR-11– AR-12 and 13 - Forest Operations
Inspections are combined– Moved AR-14 to Enhanced ARs
89
Part E• Section 2.3, Prescribed Burn Reports
– New section added for PBs– Moved from AWS to AR– Reference PB Manual for requirements– Consistency of FMPM reporting
requirements
90
Part E• Section 2.4, Information Products
– Harvest Area– Natural Disturbances– Renewal and Maintenance– Roads and Water Crossings– Assessment of Regeneration Success
91
Part E• Section 3.0, Year Three Annual Report
– Clarified focus of Year Three AR– Yr 3 AR to contain summaries of:
1. Implementation of operations to date;2. Monitoring and assessment to date;
and3. Analysis of renewal and tending from
Yr 10 AR of previous plan• Clarified minor adjustments to the LTMD
92
Part E• Section 4.0, Year Seven and Ten Annual
Reports– Incorporated IFA trend analysis– AR Tables 16 to 20 are replaced with
tables consistent with IFA trend analysis
– Removed requirement to discuss size and frequency of forest disturbances
– Removed summary of IFA action plans
93
Part E• Section 4.1, Implementation of Operations• Trend analysis will discuss:
Harvest area;Harvest volume;Renewal and maintenance;Harvest and regeneration;Forest condition;Wildlife habitat; andMonitoring and assessment
94
Part E• Section 4.5, Assessment of Objective
Achievement– Added requirement to provide
recommendations for future planning• Section 4.6, Determination of
Sustainability– Changed “on” balance to “a” balance– Added IFA action plan requirements to
determination of sustainability
95
Part E• Section 4.6, Determination of
Sustainability– Removed social and economic review– Removed recommendation section
• Section 5.1 All AR Submissions– Removed requirement for hard copy of
certification page
96
Part E• Section 5.2, Submission and Review of
Year 3, 7, and 10 ARs– Clarified MNR DM endorsement of Year
3 AR – Removed requirement for MNR RD to
notify MOE if a new plan is recommended in Year 3 AR
Forest Management Planning Manual, 2009
Appendices January, 2009
Craig Crosson R.P.F.
98
Appendices• Appendix 1, Management Units within
the AOU– updated Management Unit list and
associated map• Appendix 2, Existing Roads Table
– Deleted table, all in FMP-18
99
Appendices• Appendix 2, FMPM, 2009, Analysis
Package– Provided clarification of analysis
package contents– Requirements by check point– Reduced documentation requirements
(summarize and rationalize decisions)
100
Appendices• Appendix VI, Information Requirements
for Analysis Tools Used in Strategic Analysis
– Removed from appendices, incorporated in Part A, Section 1.1.5, Decision Support Systems