217
Florida State University Libraries Electronic Theses, Treatises and Dissertations The Graduate School 2007 Real-Time Construction Project Progress Tracking: A Hybrid Model for Wireless Technologies Selection, Assessment, and Implementation Amine Ghanem Follow this and additional works at the FSU Digital Library. For more information, please contact [email protected]

Florida State University Libraries182481/... · 2015. 4. 24. · Florida State University Libraries Electronic Theses, Treatises and Dissertations The Graduate School 2007 Real-Time

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

  • Florida State University Libraries

    Electronic Theses, Treatises and Dissertations The Graduate School

    2007

    Real-Time Construction Project ProgressTracking: A Hybrid Model for WirelessTechnologies Selection, Assessment, andImplementationAmine Ghanem

    Follow this and additional works at the FSU Digital Library. For more information, please contact [email protected]

    http://fsu.digital.flvc.org/mailto:[email protected]

  • THE FLORIDA STATE UNIVERSITY

    COLLEGE OF ENGINEERING

    REAL-TIME CONSTRUCTION PROJECT PROGRESS TRACKING: A HYBRID MODEL FOR WIRELESS TECHNOLOGIES SELECTION, ASSESSMENT, AND

    IMPLEMENTATION

    By

    AMINE GHANEM

    A Dissertation submitted to the Department of Civil and Environmental Engineering

    in partial fulfillment of the requirements for the degree of

    Doctor of Philosophy

    Degree Awarded: Summer Semester, 2007

  • ii

    The members of the Committee approve the Dissertation of Amine Ghanem defended on June 8, 2007.

    ________________________ Yassir A. AbdelRazig

    Professor Directing Dissertation ________________________

    Jeffrey R. Brown Outside Committee Member

    ________________________ John O. Sobanjo

    Committee Member

    ________________________

    Wei-Chou V. Ping Committee Member

    Approved: ___________________________________________________________ C. J. Chen, Dean, College of Engineering, Florida State University The Office of Graduate Studies has verified and approved the above named committee members.

  • iii

    To My parents,

    Abdallah and Aicha And my sisters

    Lina, Dima, and Nadine Who made all of this possible

    For their endless encouragement and support

    And also to My fiancé

    Nermine Majzoub For her love and patience

  • iv

    ACKNOWLEDGEMENTS

    First and foremost, I thank Allah for His continuous bounties and guidance

    in my life.

    This dissertation concludes a learning journey at Florida State University. I

    am grateful to many individuals who contributed to my learning experience at

    Florida State University.

    I would like to express my sincerest thanks to many key people: At the top

    of the list, my advisor, Dr. Yassir AbdelRazig for his valuable guidance,

    inspiration, and advice. Sincere appreciation is also extended to my committee

    members: Dr. Jeffrey R. Brown, Dr. John O. Sobanjo, and Dr. Wei-Chou V. Ping,

    who gave their time and input to my research. I would like also to thank Dr.

    Garold Oberlender for his unconditional support and valuable advice and

    feedback.

    The assistance offered by Sperry & Associates and Haskell Company to

    collect valuable data should be gratefully acknowledged here.

    This research would not have been possible without the people who took

    part of the survey I performed, and to whom I have promised anonymity. I am

    also very thankful to my colleagues Dr. Mohamad El-Gafy, Mr. Rassem Awwad,

    and Mr. Hassan Ghanem whose help in some of the conceptual thinking was

    invaluable.

  • v

    TABLE OF CONTENTS List of Tables ....................................................................................Page ix List of Figures .....................................................................................Page xi Abstract ..........................................................................................Page xiii Chapter 1 Introduction ............................................................................Page 1 1.1 Background .......................................................................Page 1 1.2 Problem Statement............................................................Page 4 1.3 Research Objectives .........................................................Page 6 1.4 Research Methodology......................................................Page 7 1.4.1 Problem Identification...................................................Page 7 1.4.2 Model Formulation .......................................................Page 8 1.4.3 Model Implementation..................................................Page 8 1.5 Dissertation Organization ..................................................Page 10 Chapter 2 Prior Research Efforts............................................................Page 12 2.1 Project Tracking ................................................................Page 12 2.1.1 Technology in Material Tracking........................................Page 15 2.1.2 Technology in Equipment and Labor Tracking ..................Page 17 2.2 Computer & Wireless Integrated Construction ..................Page 18 2.3 Bar Code ...........................................................................Page 20 2.3.1 Bar Codes Applications in Construction ............................Page 21 2.4 RFID ..................................................................................Page 22 2.4.1 Tags or Transponder.........................................................Page 22 2.4.2 Antenna .............................................................................Page 23 2.4.3 Reader...............................................................................Page 24 2.4.4 RFID Applications in Construction.....................................Page 25 2.5 Construction Site Information ...........................................Page 26 2.5.1 Construction Site Information Needs.................................Page 27 2.5.2 Construction Site Information Users..................................Page 28 2.6 Survey of Wireless Technologies in Construction .............Page 29 2.6.1 Wireless Technologies in Construction..............................Page 29 2.6.2 Barriers to Wireless Applications in Construction ..............Page 30 Chapter 3 Background .......................................................................Page 32 3.1 Wireless Technologies ......................................................Page 32 3.1.1 Mobile Hardware ...............................................................Page 32 3.1.1.1 Personal Digital Assistants...........................................Page 33 3.1.1.2 Handheld Computers ...................................................Page 33

  • vi

    3.1.1.3 Pen Tablet/Touch PC...................................................Page 33 3.1.1.4 Rugged Notebooks ......................................................Page 34 3.1.1.5 Wearable Computers/Digital Hardhats.........................Page 34 3.1.1.6 Digital Pen....................................................................Page 34 3.1.2 Networks............................................................................Page 35 3.1.2.1 Wireless Wide Area Networks......................................Page 36 3.1.2.2 Wireless Local Area Networks .....................................Page 36 3.1.2.3 Satellites Networks.......................................................Page 38 3.1.3 Mobile Applications ............................................................Page 39 3.1.3.1 CAD Applications .........................................................Page 39 3.1.3.2 Data Capture Applications...........................................Page 39 3.1.3.3 Project Management Application..................................Page 40 3.2 Technology Assessment Methods.....................................Page 40 3.2.1 Assumptions and Fundamentals of Utility Theory .............Page 41 3.2.2 Types of Utility Functions .................................................Page 43 3.2.3 Hierarchical Structure of MAUT.........................................Page 45 3.2.3.1 Defining Evaluation Objectives ....................................Page 45 3.2.3.2 Defining Alternative Attributes......................................Page 45 3.2.3.3 Attribute Characteristics ...............................................Page 46 3.2.3.4 Assigning Attribute Weights .........................................Page 46 3.2.4 Analytical Hierarchy Process.............................................Page 48 3.2.4.1 Setting Priorities ..........................................................Page 49 3.2.4.2 Pairwise Comparison Scale.........................................Page 49 3.2.4.3 Eigenvector Prioritization Method ................................Page 50 3.3 Computer Construction Simulation....................................Page 53 3.3.1 General Modeling and Simulation Systems.......................Page 53 3.3.1.1 GPSS...........................................................................Page 54 3.3.1.2 HOCUS ........................................................................Page 54 3.3.1.3 ITHINK.........................................................................Page 55 3.3.1.4 SLAMII.........................................................................Page 55 3.3.2 Construction Simulation Using Networks...........................Page 55 3.3.2.1 Cyclone........................................................................Page 55 3.3.2.2 RESQUE.....................................................................Page 56 3.3.2.3 COOPS........................................................................Page 57 3.3.2.4 CIPROS ......................................................................Page 57 3.3.2.5 STROBOSCOPE ........................................................Page 57 Chapter 4 Real time project progress tracking model ........................Page 59 4.1 Framework for real time project progress tracking.............Page 59 4.2 Hardware and Software Selection .....................................Page 61 4.2.1 Hardware Selection......................................................Page 61 4.2.1.1 Computer Alternatives .................................................Page 61 4.2.1.2 Wireless Infrastructure Alternatives.............................Page 64 4.2.1.3 Smart Chips Alternatives .............................................Page 65 4.2.2 Software Selection .......................................................Page 66

  • vii

    4.3 Implementation Steps........................................................Page 66 4.3.1 Work Progress Measurement ......................................Page 69 4.4 Construction of Data Management System ......................Page 69 4.4.1 Data Dictionary..................................................................Page 70 4.4.2 Project Database...............................................................Page 73 4.4.2.1 Database Queries ........................................................Page 74 Chapter 5 Technology Selection and Assessment..................................Page 77 5.1 Assessment Model ............................................................Page 77 5.1.1 Defining the Problem.........................................................Page 77 5.1.2 Explanation of Model Attributes.........................................Page 79 5.1.3 Defining Attribute Measuring Scales..................................Page 82 5.2 Utility Function Survey.......................................................Page 83 5.2.1 Measuring Weights............................................................Page 84 5.2.2 Consistency Checks..........................................................Page 86 5.3 Procedure for Constructing Single AUF.............................Page 89 5.3.1 Multiple Attribute Utility Function Development .................Page 91 5.4 Sensitivity Analysis ............................................................Page 96 5.4.1 Effect of Changing Cost.....................................................Page 96 5.4.2 Effect of Changing Risk Weight.........................................Page 98 Chapter 6 Steel Construction Process Case Studies..............................Page 100 6.1 Case Study........................................................................Page 100 6.1.1 Case Study 1: Turbocor Project ........................................Page 100 6.1.2 Case Study 2: Jefferson County High School Project........Page 102 6.2 Steel Construction Process Overview ...............................Page 104 6.2.1 Preplanning and Fabrication..............................................Page 104 6.2.2 Shipment and Unloading ...................................................Page 105 6.2.3 Steel Erection ....................................................................Page 106 6.3 Model Existing Steel Construction Processes ...................Page 106 6.4 Productivity Measurement .................................................Page 108 6.4.1 PEB Simulation Model.......................................................Page 109 6.4.2 Process Inefficiency...........................................................Page 112 6.5 Steel Construction Process Updated.................................Page 114 6.5.1 Development of a Data Flow Diagram...............................Page 114 6.5.2 Proposed Process .............................................................Page 116 6.5.3 Simulation Model...............................................................Page 118 6.6 Simulation Outputs ............................................................Page 120 6.7 Proposed Model Benefits ..................................................Page 122 6.7.1 Function A: Site Inspection Savings ..................................Page 129 6.7.2 Function B: Problem Solving Savings................................Page 130 6.7.2.1 Cost Benefit Analysis ...................................................Page 132 6.7.2.2 Sensitivity and Break-Even Analysis ............................Page 133 6.7.3 Function C: Wireless Data Access Savings.......................Page 134

  • viii

    6.7.3.1 Cost Benefit Analysis ...................................................Page 136 6.7.4 Function D: E-Document Management .............................Page 137 Chapter 7 Conclusions and Recommendations......................................Page 139 7.1 Summary of the Research.................................................Page 139 7.2 Research Contribution.......................................................Page 140 7.3 Limitations .........................................................................Page 142 7.4 Recommendations for Future Work...................................Page 142 APPENDICES .....................................................................................Page 144 A Smart Chips...............................................................................Page 144 B Survey .....................................................................................Page 152 C Case Study Documents.............................................................Page 160 D Simulation Input/Output Files ....................................................Page 176 REFERENCES .....................................................................................Page 190 BIOGRAPHICAL SKETCH ....................................................................Page 198

  • ix

    LIST OF TABLES Table 2.1: Tracking Methods ..................................................................Page 13 Table 3.1: Pairwise Comparison Scale Presented by Saaty ...................Page 50 Table 3.2: Approximated Random Indices RI .........................................Page 52 Table 4.1: Rugged Mobile Device Comparison.......................................Page 63 Table 4.2: Database Dictionary...............................................................Page 71 Table 5.1: Attribute Measures.................................................................Page 82 Table 5.2: Assessment of UL...................................................................Page 90 Table 5.3: Assessment of UH ..................................................................Page 90 Table 5.4: Single Attribute Utility Functions ............................................Page 93 Table 5.5: Technology Alternatives.........................................................Page 94 Table 5.6: Alternatives Measures............................................................Page 94 Table 5.7: Utility of Alternatives Case Study 1 ........................................Page 95 Table 5.8: Utility of Alternatives Case Study 2 ........................................Page 95 Table 5.9: Utility Variations Based on Costs Changes............................Page 97 Table 5.10: Utility Variations Based on Risk Weight Changes................Page 98 Table 6.1: Productivity Ratings ...............................................................Page 109 Table 6.2: Simulated Productivity Results...............................................Page 121 Table 6.3: LCC Input Data ......................................................................Page 123 Table 6.4: LCC Calculation .....................................................................Page 124 Table 6.5: LCC Summary Case Study 1 .................................................Page 127 Table 6.6: LCC Summary Case Study 2 .................................................Page 128

  • x

    Table 6.7: Benefits Calculation of Function A Case Study 1...................Page 129 Table 6.8: Benefits Calculation of Function A Case Study 2...................Page 130 Table 6.9: Benefits Calculation of Function B Case Study 1...................Page 131 Table 6.10: Benefits Calculation of Function B Case Study 2.................Page 132 Table 6.11: Cost Benefit Analysis of Function B Case Study 1...............Page 132 Table 6.12: Cost Benefit Analysis of Function B Case Study 2...............Page 132 Table 6.13: Benefits Calculation of Function C .......................................Page 134 Table 6.14: Rework & Process Elimination Savings Case Study 1.........Page 135 Table 6.15: Rework & Process Elimination Savings Case Study 2.........Page 135 Table 6.16: Summary of Benefits of Function C Case Study 1 ...............Page 135 Table 6.17: Summary of Benefits of Function C Case Study 2 ...............Page 135 Table 6.18: Cost Benefit Analysis of Function C Case Study 1 ..............Page 136 Table 6.19: Cost Benefit Analysis of Function C Case Study 2 ..............Page 136 Table 6.20: Benefits Calculation of Function D .......................................Page 137 Table 6.21: Summary of Benefits Case Study 1 .....................................Page 137 Table 6.22: Summary of Benefits Case Study 2 .....................................Page 138

  • xi

    LIST OF FIGURES Figure 1.1: Construction Labor Productivity ............................................Page 2 Figure 1.2: Research Methodologies .....................................................Page 9 Figure 2.1: Basic Barcode Structure .......................................................Page 20 Figure 2.2: Antenna Sealed with RFID Tag ............................................Page 23 Figure 2.3: Handheld Stationary Readers...............................................Page 24 Figure 2.4: Digital Hardware Used in the Construction ...........................Page 29

    Figure 2.5: Cutting Edge Tools Used in the Construction ......................Page 30

    Figure 2.6: Barriers to Wireless Applications in Construction .................Page 31 Figure 3.1: Types of Mobile PC’s............................................................Page 35 Figure 3.2: Types of Utility Curves ..........................................................Page 44 Figure 3.3: Sample Comparison Matrix...................................................Page 49 Figure 3.4: Normalized Matrix.................................................................Page 50 Figure 3.5: Eigenvector Matrix ................................................................Page 51 Figure 3.6: Transition Matrix ...................................................................Page 51 Figure 4.1: Model Framework .................................................................Page 60 Figure 4.2: Data Exchange and Reporting..............................................Page 67 Figure 4.3: General System Configuration..............................................Page 68 Figure 4.4: Database Management System............................................Page 70 Figure 4.5: Project Database Tables and their Relationships .................Page 74 Figure 4.6: User Interface .......................................................................Page 75 Figure 4.7: Project Updates ....................................................................Page 75

  • xii

    Figure 4.8: Erection Drawings.................................................................Page 76 Figure 5.1: Analytic Hierarchy Process ...................................................Page 78 Figure 5.2: Hierarchy of Influence as Applied in the Study .....................Page 81 Figure 5.3: Job Title Survey Respondents ..............................................Page 84 Figure 5.4: Pairwise Comparisons ..........................................................Page 85 Figure 5.5: Consistency Checks .............................................................Page 89 Figure 5.6: Cost Analysis ........................................................................Page 97 Figure 5.7: Risk Weight Analysis ............................................................Page 98 Figure 6.1: Different Construction Phases ..............................................Page 102 Figure 6.2: Aerial View of JCHS Site ......................................................Page 103 Figure 6.3: MSC Panel Fabrication.........................................................Page 103 Figure 6.4: Tilt-Up Panel Wall Erection ...................................................Page 104 Figure 6.5: PEB Fabrication....................................................................Page 105 Figure 6.6: Unloading Steel Members.....................................................Page 105 Figure 6.7: Erection.................................................................................Page 106 Figure 6.8: Materials and Information Flow.............................................Page 107 Figure 6.9: Shipping Simulation Model ...................................................Page 111 Figure 6.10: Erection Simulation Model ..................................................Page 112 Figure 6.11: To Be Materials and Information Flow ................................Page 115 Figure 6.12: Copying Information to the RFID Tags................................Page 117 Figure 6.13: Proposed Shipping Simulation Model .................................Page 119 Figure 6.14: Proposed Erection Simulation Model..................................Page 120 Figure 6.15: Cost-Benefit Chart for Two Variables..................................Page 133

  • xiii

    ABSTRACT

    A construction project is considered as a process that involves many

    activities and a large amount of information of various types that are related to

    each other. Successful project management requires controlling all aspects of a

    construction project: quality and quantity of work, costs, and schedules to

    guarantee the success of the project. So the construction project control aims to

    effectively obtain real-time information of activities taking place on the site.

    Meanwhile, paper-based documents of project management used are becoming

    ineffective and can’t get quick responses to the office and project control center.

    Integrating promising information technologies such as radio frequency

    identification (RFID), mobile computing devices, and wireless technology can be

    extremely useful for improving the effectiveness and convenience of information

    flow in construction projects. The probable benefits are potentially enormous, but

    the barriers associated with technology adoption within the construction industry,

    currently outweigh this potential.

    This research develops a control system for construction projects. The main

    objectives of this research include (1) developing a framework for real time

    construction project tracking; (2) applying such a system that integrates RFID

    technology with mobile computing and wireless technology to increase the

    efficiency of jobsite communication and data collection; (3) designing a database

    system for construction activities and updates, providing real-time information

    and wireless communication between offices and sites, subcontractors and

    suppliers; (4) developing a hybrid model for wireless technologies selection,

    assessment and implementation; (5) applying the model on pre-engineered steel

    construction projects and performing life cycle cost and cost benefit analysis.

    This model will greatly increase productivity and efficiency, will reduce labor

    hours and time required for tracking.

  • 1

    CHAPTER 1

    INTRODUCTION

    1.1 Background

    Construction is one of the largest industries in the United States, and its

    second largest employer after government agencies. According to an

    employment report from the U.S. Bureau Labor Statistics, construction

    employment in the U.S. in the second quarter of 2005 account for roughly 7.2

    million, or 5.4 percent of non-farm payroll employment (U.S. Census Bureau

    2004). Moreover, the value of construction invested, a measure of the amount

    spent on design, engineering, and construction, totaled $ 1 trillion in May 2004,

    according to the Census Bureau. This amount is equivalent to roughly eight

    percent of the U.S. gross domestic product (GDP). However the construction

    industry has suffered from low performance due to low productivity, high accident

    rates, late completion, and poor quality (Kashiwagi et al., 2004). In 2003, the U.S.

    Bureau of Labor Statistics showed that labor productivity in construction has

    been lagging behind other U.S. industries (see Figure 1) for the past 40 years.

    A study performed by Nuntasunti (2003) summarized five factors

    preventing the construction industry from improving performance: 1)

    Fragmentation of the construction industry; 2) project specific nature of

    construction; 3) temporary nature of relationships; 4) competitive bidding system;

    and 5) stand alone islands of communication.

    A construction project essentially involves a large amount of information of

    various types. This is due to the fact that different parties perform independent

    tasks on a project to produce a single final product. Since the design of a project

    must somehow be communicated to many parties on the construction site, it is

    important that clear information, coherent and efficient communication exist to

    ensure successful work by all participants in the project. The specifications must

  • 2

    be translated into information that all parties can use in fulfilling their tasks.

    Hence, the need for drawings, contracts, specifications, building codes, and other

    forms of information emerges. At the same time, the performance of the project

    must also be communicated back to management so that it can be controlled

    effectively.

    Figure 1.1: Construction Labor Productivity Index versus All Non-farm U.S. Industries

    As projects become more complex, the amount and detail of the

    information required increases. This increase in turn makes the process of

    storing, retrieving, and analyzing the control information more complicated and

    subject to mistakes. A large amount of information is created by independent

    organizations and individuals involved in the project.

    One commonly cited means of overcoming labor shortages and improving

    productivity, cost effectiveness, and competitiveness is through the use of

    advanced technologies such as information technology (Johnson and Tatum

  • 3

    1993). Information technology (IT) was developed as a means of meeting

    complex information demands and of automating the tasks associated with them.

    Advances in IT promised great leaps in productivity in the late 20th century,

    however few industries have truly profited from IT’s promises. In the same

    manner, automation technologies such as robotics offered similar benefits to the

    construction industry with few tangible benefits yet realized (Skibniewsky and

    Hendrickson 1990, Farid 1993).

    The construction industry lags behind other industries in adopting

    innovative new technologies. The need to accelerate the rate of technological

    adoption in the construction industry has been well documented in the literature

    (Mitropoulos and Tatum, 2000). This adoption comes from continuously seeking,

    recognizing, and implementing new technologies that improve construction

    processes (Laborde and Sanvido 1994). Each technology has its own technical,

    economic, and risk considerations that make the selection process a difficult one.

    The selection decision involves many tradeoffs among technology attributes.

    Unlike the structured environment and highly repetitive processes in

    manufacturing, construction poses many barriers to the implementation of

    advanced technologies. Characteristic fragmentation, diversity, and fierce

    competition of the construction industry combine to make research and

    development (R&D) difficult (Tucker 1988). In a fiercely competitive environment

    with thin profit margins, individual firms, especially the smaller ones, simply can’t

    afford to conduct R&D or pay added regulatory costs of introducing new

    technologies. In 1997, the industry spent only 0.6 percent of total revenues on

    R&D, whereas most other industries committed 4 to 6 percent. An unfocused and

    uncoordinated effort among the various R&D sectors makes this chronic under-

    funding worse. The National Institute for Standards and Technology (NIST), the

    Department of Transportation, and the Department of Energy sponsor conduct,

    or cost-share with industry and academia research activities. The National

    Science Foundation (NSF) funds more than 70 percent of academia’s

    construction R&D efforts. The Army Corps of Engineer’s Engineering Research

    and Development Center and the Naval Facilities Engineer Command’s

  • 4

    Engineering Service Center conduct lion’s share of government R&D. The

    construction industry has barely just begun to examine ways of integrating its

    management processes with information technology into a unified system. Non-

    profit organizations such as the Construction Industry Institute (CII) and the

    National Institute of Standards and Technology (NIST) are spearheading these

    efforts through their FIATECH (Fully Integrated and Automated Technology) and

    CONSIAT (Construction Integrated and Automation Technology) programs,

    respectively, and are starting to address the barriers that stand in the way along

    with research in Enterprise Resource Planning (ERP) in construction at other

    institutions (O’Connor and Dodd 2000).

    1.2 Problem Statement

    During the construction phase of a project it is essential that efficient and

    timely flow of information prevail throughout the process. The construction

    industry is dynamic by nature and requires that all parties be kept informed of

    activities that can ultimately affect the cost, schedule or performance of the work.

    The paper-based documentation of site processes is ineffective anymore as it is

    unable to deliver just in time information. At the same time paper documentation

    can’t get the quick response from the office to the construction site and vice

    versa. As a result, a gap in time and space between the job site and office

    causes the lack and confusion of data and information. The effectiveness of

    information and data acquisition influences the flow of information between the

    office and the construction site. Field supervisory personnel on construction site

    spend between 30-50% of their time recording and analyzing field data

    (McCullouch 1997) and 2% of the work on construction sites is devoted to

    manual tracking and recording of progress data (Cheok et al. 2000). Accuracy of

    the collected data depends on judgments and writing skills of the people

    collecting data (Liu 1995). In addition, since most data items are not captured

    digitally, data transfer from a site to a field office requires additional time. When

    the required data is not captured accurately or completely, extra communication

  • 5

    is needed between the site office and field personnel (Thorpe and Mead 2001).

    These extra efforts are time consuming and waste of money. These inefficiencies

    are embedded and distributed among many different activities and project

    participants, and hence, the project team is generally not aware of the

    implications and aggregate time and money waste associated with them.

    Wireless technologies can be used to improve the accuracy and timeliness of the

    data collected from sites and to improve communication flow. Previous research

    on such technologies mainly discussed the technological feasibility of using a

    particular technology to support various construction project tasks (Akinci et al.

    2005, Jaselskis et al. 1995). But still there is a need for a comprehensive

    framework to assess the effectiveness of using such technologies that

    encompasses all different merits together: performance, reliability, risk, and cost.

    The following section summarizes several problem areas in the

    construction that this thesis will address:

    (1) Independent islands of communication on the construction site:

    Lacks of effective communication among various parties involved in

    construction projects make information exchange inefficient. Moreover,

    paper-based handling of change orders and Request for Information

    (RFIs) increases difficulties in information exchange in a timely manner.

    Even though project participants have been using various project

    management tools to improve communication, there are still deficiencies

    in updating the schedule and the progress of the construction project in a

    real time fashion

    (2) Obsolete paper-based and as-built drawings:

    Paper prints are currently used to exchange design, shop, erection, and

    as built drawings between project participants. Duplication of effort,

    inconsistencies, errors, missing information, and extensive time needed to

    find relevant information are common in paper-based documents.

    (3) Decrease in productivity created by ineffective flow of information:

    This problem is created by lack of information about availability of

    materials on the construction site. Materials handling and storing is also a

  • 6

    problem. Time is commonly wasted trying to figure out where materials

    are on the construction site, and whether or not there is enough quantity.

    (4) Lack of assessing method for decision makers to select a

    technology:

    Each technology has its own technical, economic and risk consideration

    that make the selection process difficult. Considering one aspect in

    choosing and ignoring the others may not lead to the optimal decision.

    Currently there are no tool that rationalizes and facilitates this complicated

    decision making process.

    1.3 Research Objectives

    The overall objective of this research is to develop a hybrid model, based

    on a combination of Radio Frequency Identification tags (RFID), mobile

    computing, and wireless technologies in tracking the progress of construction

    project. This research develops a project progress control system for

    construction projects. Mainly, the control system is a central database that will

    provide real-time and updated information for different parties on a construction

    project. In addition, a multi-attribute utility model is developed to help decision

    makers select the appropriate IT to the required construction application. Two

    pre-engineered steel construction buildings are used as case studies application

    of the proposed model

    The detailed objectives of this research include:

    (1) Investigating integration of RFID technology with Mobile computing and

    wireless technology as a communication and data collection tool for

    construction jobsite.

    (2) Designing a central Database for construction activities and updates,

    providing real-time information and facilitating wireless communication

    between offices and sites, subcontractors and suppliers.

    (3) Developing a framework for real-time construction project tracking.

  • 7

    (4) Developing a hybrid model for wireless technologies selection,

    assessment and implementation.

    (5) Applying the model on a pre-engineered steel construction and performing

    a life cycle cost and cost benefit analysis, to illustrate the model

    framework.

    1.4 Research Methodology

    This research is divided into three main phases: problem identification

    phase, model formulation phase, and system implementation through real case

    studies. Each phase includes several steps to achieve the objectives of that

    particular phase. Figure 1.2 illustrates the different phases and steps for the

    research methodology.

    1.4.1 Problem Identification

    This phase include reviewing current practices of project progress tracking

    and information flow on the construction site to pinpoint the deficiencies in these

    practices. The objective of this step is to establish the need for a more efficient,

    up-to-date, and reliable practice for project control and monitoring. Another step

    is reviewing the use of smart chips and wireless technologies in construction, and

    discussing the different application of each technology. Moreover, another step is

    to review a survey conducted by ASCE to identify barriers to wireless application.

    The objective of the previous two steps is to find ways of to implement

    technologies in construction and how to overcome the barriers to its

    implementation.

    The objectives of the problem identification phase are to define the scope

    of the research and to establish the background necessary to accomplish the

    research objectives. The focus of the research is to develop a framework for real

    time project tracking, and to develop a hybrid assessment model for wireless

    technologies. The system is considered hybrid because it uses two quantification

    methods in assessment: subjective and objective.

  • 8

    1.4.2 Models Formulation

    The first step in this phase is to acquire and set up the hardware and

    software required for the different phases of the research. Another step is to

    establish the procedure of how resources on the construction site will be tracked,

    by identifying the appropriate type of measurement method. This step is

    achieved by investigating each activity in the main schedule, and assigning the

    appropriate resources whether it is equipment, materials or labors resources.

    The following step is to develop a central database where all information

    captured on the construction site is sent to this database. This step is achieved

    by creating different kind of relationships between the proposed tables using

    Microsoft access. In this case SQL is used to establish appropriate queries.

    The next step is to choose the right hardware and software for the real-

    time tracking model by formulating a multi attribute utility model. The main part of

    this stage is to construct a hierarchy of influence that includes the main objective,

    criteria of evaluation and alternatives to be assessed. Then it uses eigenvector

    prioritization method to develop a hybrid model for wireless selection and

    assessment. The objective of this phase is to formulate the basic structure of the

    hybrid assessment model for wireless technologies selection.

    1.4.3 Model Implementation

    The final stage of the research is utilizing case studies from construction

    projects, in the State of Florida, to illustrate and apply the framework of real-time

    project progress tracking. This step is achieved by formulating an information

    flow model of steel construction, and then performing simulation of different cycle

    of the project to quantify the benefits of the proposed model.

    The next step would be to synthesize all the previous steps to finalize and

    refine the framework. More examples, if needed, would be used to validate the

    reliability of the framework and necessary adjustments will be made. Finally, the

    write-up of the completed dissertation will be provided.

  • 9

    Figure 1.2: Research Methodology

  • 10

    1.5 Dissertation Organization

    This thesis is organized into seven chapters. Chapter 1 gives an overview

    of project progress tracking problems in the construction industry and

    emphasizes on the importance of data exchange and communication among

    project parties. This chapter also sheds some light on the lack of information to

    assess usage of wireless technologies in construction. Research problem

    statement and objectives are also presented. Chapter 2 describes available

    technologies necessary for conducting this research. At the same time a

    summary of previous research that has been done in this field is presented. Then

    the results of a survey conducted by the ASCE Construction Institute Wireless

    Committee to identify barriers to wireless technologies application in construction

    are discussed. Chapter 3 lays down the background to conduct this research. It

    starts with identifying different wireless technologies: hardware and software.

    Then different methods to assess technologies are presented. Finally, the

    chapter is completed with a description of computer simulation in construction.

    Chapter 4 presents the developed construction project progress-tracking model

    based on wireless technologies. This model provides updates in real-time

    allowing the user to track the progress of percentage completed on the

    construction site and to access project information from a central database.

    Chapter 5 describes a quantitative process to select and assess the appropriate

    IT to be used in the proposed real-time system using multi-attribute utility theory.

    Chapter 6 presents two case studies for pre-engineered steel buildings where the

    proposed model is applied. A detailed study of pre-fabricated steel process will

    be discussed to show how the model functions. Then a simulation model of the

    pre-engineered steel process is presented in order to illustrate the benefits of

    applying the model. Conducting a value assessment analysis to quantify the

    benefits concludes this chapter. Chapter 7 concludes the thesis with a summary,

    conclusions, and recommendations for future study. Research contributions and

    limitations are also outlined in this chapter. The appendices contain detailed

    information of some of the issues discussed in the thesis. Appendix A contains

  • 11

    information about smart chips. Appendix B contains information of the survey

    conducted in this research. Appendix C contains information about the data

    gathered from both case studies. Appendix D contains information about the

    simulation input and output files.

  • 12

    CHAPTER 2

    PRIOR RESEARCH EFFORTS

    This chapter lays necessary foundation for the research and includes

    review of prior research efforts. The literature review of prior research efforts

    includes reviewing the application of information technologies and the use of

    barcode and Radio Frequency Identification (RFID) in the construction industry

    and discusses the different application of each technology. In addition to the use

    of smart chips, this chapter describes wireless technologies and its application on

    the construction site. Then an ASCE survey presented by the CI wireless

    committee is presented to identify barriers to wireless application. Finally the

    needs for information and for users on the construction site are identified.

    2.1 Project Tracking

    A simple project can be planned as a list of tasks with their start and finish

    dates written on a piece of paper. A complex plan on the other hand, might deal

    with thousands of tasks, resources, and a project budget of billions of dollars. As

    the project becomes more and more complex, so does the requirement for a

    project management system. It is a good practice to monitor a project’s

    performance continuously throughout its various phases in order to maintain

    certain cost, time, quality, and safety criteria. This will also help ensure that a

    project can be completed within budget, on schedule, at the desired quality, and

    with an acceptable safety record.

    One of the main way of controlling a project’s quality, cost, and schedule

    performance is to continuously monitor activities during the construction phase in

    order to keep track of work done: materials and equipments used versus installed

  • 13

    quantities. These quantities can then be compared against quantities estimated

    during the planning phase to gauge the project’s performance.

    Construction Industry Institute (CII) uses six different methods to measure

    the work progress at the construction jobsite, depending on the type of work to

    be done. Table 2.1 summarizes these methods.

    Table 2.1: Tracking Methods (adapted from CII 1987a) Method Suitable for Measuring Examples

    Units Completed

    Activities that involve repeated production of easily measured work packages that consume roughly equal resources

    Linear feet of wire or pipe installed, or cubic yards of concrete placed, etc.

    Incremental Milestone

    Sequential activities with clearly defined milestones

    Pipe received/inspected, pipes supported, pipes aligned, pipes welded, pipes tested, pipes completed

    Start/Finish Activities that do not have interim milestones or that are hard to quantify in terms of time and cost

    Cleaning, testing, aligning, etc.

    Supervisor Opinion

    Minor activities where detailed analysis is not necessary

    Painting, constructing support facilities, etc.

    Cost Ratio Long term activities that may span the life of a project and are allocated bulk cost/time

    Project management, quality assurance, etc.

    Weighted or Equivalent Units

    Long term activities that include multiple subtasks with different units of measurement

    Structural steel erection (includes bolting, shimming, connecting, aligning, etc.)

    In the 1980s, many project management packages were introduced to the

    market. Primavera Project Planner and Microsoft Project are two of such

    recognized standard commercial software. These programs provide an

    automated means for project tracking and scheduling. However, access to these

    softwares was limited to trained personnel working on certain machines in a

    specific location (Pena-Mora et al. 2002). So once a project has started with an

    original schedule, the actual field data is recorded on paper, email, word

  • 14

    processor, or a spreadsheet documents before reaching the scheduler on a

    weekly or monthly basis.

    Repass et al. (1995) developed a new tool called updater to improve

    efficiency and effectiveness of construction schedule updating. It employs

    emerging palm-held computer technology to automate processes currently bound

    to manual paper-based methods due to incompatibilities between computers and

    the harsh construction environment.

    Chin et al. (2005) presented a real time 4D CAD + RFID for project

    progress managements. The model mainly presented building elements in 3D

    CAD models according to as-built progress, where the as-built information is

    collected in real-time by sensing the progress throughout the supply chain using

    RFID. 4D+RFID aimed at supporting processes with a focus on structural and

    curtain wall elements, such as steel columns and beams, concrete slabs, and

    curtain walls, which are typically on the critical path of project schedules in high-

    rise building construction projects. The process is that RFID is applied to sense

    the progress status of ordering, delivery, receiving, and erection of building

    elements, and then the as-built progress information is presented in 3D CAD

    models.

    Poku et al. (2006) developed a system called PMS-GIS (Progress

    Monitoring System with Geographical Information Systems) to represent

    construction progress not only in terms of a CPM schedule but also in terms of a

    graphical representation of the construction that is synchronized with the work

    schedule. In PMS-GIS, the architectural design is executed using a computer-

    aided drafting (CAD) program (AutoCAD), the work schedule is generated using

    a project management software primavera (P3), the design and schedule

    information (including percent complete information) are plugged into a GIS

    package (ArcViewGIS), and for every update, the system produces a CPM-

    generated bar chart alongside a 3D rendering of the project marked for progress.

    The GIS-based system developed in this study helps to effectively communicate

    the schedule/progress information to the parties involved in the project, because

  • 15

    they will be able to see in detail the spatial aspects of the project alongside the

    schedule.

    Memon et al. (2005) presented a system that integrated Auto CAD and

    digital photos to track the progress of construction project. The system proposed

    is called Digitalizing Construction Monitoring (DCM) Model. It has made a

    practical attempt to automate the process of producing as-built construction

    schedule by applying modern photogrammetry techniques to photographs and

    integrating with CAD drawings. The applications of DCM model in monitoring the

    progress enables project management team to better track and control the

    productivity and quality of construction projects.

    2.1.1 Technology in Material Tracking

    Regardless of the type of project, enough resources must be allocated on

    quantity tracking to acquire accurate and timely data that can be used effectively

    to control a project and to make progress payment.

    In any construction project the cost of materials can exceed half the cost

    of construction. Many researches have indicated that in a typical industrial facility

    50% to 60% of the total cost is for equipment and materials. The proportion in

    terms of cost of materials has increased more than labor. Bernold and Treseler

    (1991) stated that costs of materials have increased more than labor and they

    pointed out that the construction industry spends 0.15% in material management

    systems.

    Some studies have shown that an effective material management system

    can produce 6% improvement in labor productivity and a computerized system

    can produce additional 4 -6% in savings (Stukhart 1995) . Researchers have

    acknowledged the importance of materials and the impact that these have in the

    total project cost, plan and operations.

    The project management team must focus on materials management in

    the following stages: Planning, Preliminary design, Final design, Procurement,

    Vendor control, Construction, and Closeout. It is a mean of acquiring information

  • 16

    about installed quantities at the jobsite, which can then be matched with resource

    expenditures such as labor hours, equipment use, etc. (Halpin 1985).

    Potential application for materials tracking in commercial construction

    include concrete placement operations and steel frame components tracking.

    These applications provide viable uses because they offer incremental

    improvements over existing methods, reduced labor costs, real-time identification

    and tracking and they provide the potential for automatic billing upon receipt of

    materials at a jobsite.

    Jaselskis et al. (1995) proposed a system using RFID technology to

    control concreting operations that would ensure proper delivery, billing, and

    quality control for concrete. The process starts when the contractor places an

    order with the concrete supplier. The requirements for the concrete mix and the

    ID numbers for the assigned trucks would be transmitted to a computer in the

    batch plant. Next the RFID tag would be programmed to provide concrete mix

    admixtures, time of loading, and delivery location. When the truck arrives at the

    jobsites, a scanner would read the RFID tag and communicate by RF link to the

    jobsite computer. The RFID tag information would be matched with the electronic

    data information from the plant. After the concrete placement is completed, the

    concrete truck would again pass the scanner and the delivery completion time

    would be transmitted to the concrete supplier to make plans for the next truck. In

    the same paper, Jaselskis presented a system to manage critical materials on

    the construction site. The system consists of assigning an RFID tag for each

    material delivery vehicle. Each package of critical material would also have an

    RFID tag. Both the vehicle and package tags would be read at the gate and

    recorded on the jobsite computer. The jobsite computer would maintain

    databases of materials on hand and their storage location, as well as materials

    installed. The saved information was used to trigger payments from the

    contractor to suppliers and generate requests for progress payments from the

    contractor to the owner (Jaselskis et al. 1995)

    Yagi et al. (2005) proposed the concept of parts and packets unified

    architecture that allows parts or units to signal change in their attributes as they

  • 17

    go through the complex production system. The combination of RFID and glue

    logic or active database was proposed as a possible control mechanism, which

    achieves the required dynamic equilibrium for construction activity without

    hindrance or halt of production at worst. When a chip implanted part passes

    through a gate, the gate reads the product URL of the part. It determines what it

    is, where it is, when it is, as well as in what state it is. The corresponding data

    point in the glue logic is then altered, which generates an event and a chain of

    succeeding actions.

    Tserng et al. (2005) presented a web-based portal system that

    incorporates wireless technology and mobile devices to improve the efficiency

    and effectiveness of data acquisition on site and information sharing between

    participants to assist the managers to control and monitor the delivery progress

    in a construction supply chain delivery. The MConSCM system not only improves

    the data acquisition on site efficiency by using automated bar code enabled PDA,

    but also provides a monitor to control the construction progress.

    2.1.2 Technology in Equipment Tracking

    The jobsite productivity of a project involving considerable amount of time

    and effort is affected by the selection of the appropriate type and size of

    construction equipment. It is therefore important for site managers and

    construction planners to be familiar with the characteristics of the major types of

    equipment most commonly used in construction. Typically, construction

    equipment is used to perform essentially repetitive operations and can be broadly

    classified according to two basic functions: (1) operators such as cranes,

    graders, etc. which stay within the confines of the construction site, and (2)

    haulers such as dump trucks, ready mixed concrete truck, etc. which transport

    materials to and from the site (Hendrickson 1998).

    Real-time tracking of construction equipment, utilizing the GPS technology

    and wireless communications to avoid collisions, offers a multitude of benefits

    and can be used for optimizing productivity, in addition to safety and security

  • 18

    applications. The technology has applications in both automated as well as

    traditional construction sites (Oloufa et al. 2003).

    Goodrum et al. developed a prototype tool tracking system to track tools in

    a mobile environment and to inventory hand tools that may be located in either

    mobile gang boxes or truck boxes. Active RFID technology has significant

    potential to improve tool inventory and allocation on a construction jobsite. The

    RFID tags have the capability to provide adequate read range and durability

    needed for a tool tracking and inventory system research used active RFID tags

    in the prototype tool tracking system (Goodrum et al. 2005).

    2.2 Computer and Wireless Integrated Construction

    Advances in information technology have gradually changed how

    construction data are managed in the field. These advances, such as mobile

    computers, wireless communications, video conferencing, collaboration systems,

    3D laser scanning, digital close range photogrammetry, and sensors have

    provided new ways for collecting and managing project information.

    Considerable amount of research is being done to remove the

    dependency of a person on the desktop computer as the only means of

    collaboration and accessing the network, as most projects tend to have a

    substantial work force working on site or out of the office where it is not always

    possible to have a desktop computer (Pena-Mora et al. 2002).

    Some research at Carnegie Mellon University has explored the use of

    handheld computing devices in the field for bridge inspection (Garrett et al.

    1998). The equipment is non-encumbering and allows the engineer to perform

    inspection in a natural manner.

    Work at the University of Kent at Canterbury concentrated on examining

    the special needs and environment of the field worker, reflecting on the handheld

    computing instrument features required for a successful PDA for use in the field.

    The research effort also involves development of novel software tools for the

  • 19

    mobile field workers but exploit existing handheld computing and sensor

    technology (Pascoe 1998).

    Liu et al. (1997) proposed the Digital Hard Hat (DHH) technology, which

    enables dispersed users to capture and communicate multimedia field data to

    collaboratively solve problems, and collect and share information. The DHH is a

    pen based personal computer running Windows XP. It is used to collect

    multimedia information. Special software called Multimedia Facility Reporting

    System allows the field representative to save multimedia information into a

    project specific database, which is then accessible to others through the World

    Wide Web. The pen-based computer can also be used to communicate between

    the construction site and other locations using a direct network connection, a

    wireless network connection or any means of cellular communications.

    Brilakis (2006) presented a case study on long-range, wireless

    communications suitable for data exchange between construction sites and

    engineering headquarters. He defined the requirements for a reliable wireless

    communications model where common types of electronic construction data will

    be exchanged in a fast and efficient manner, and construction site personnel will

    be able to interact and share knowledge, information and electronic resources

    with the office staff.

    Singhvi et al. (2003) developed a context-aware information system

    designed to deliver up to-date project information from the main office to the

    construction site. The objective was to help the user manage the complexity of

    the construction data by proactively tracking current resource requirements and

    proactively obtaining access to context-relevant information and services. To

    achieve this, the system used off-the-shelf handheld computing devices and an

    on-site wireless network for local communication. This allowed continuous

    access to data and resources as users moved around the job site. This work

    highlighted the benefits of context-aware computing for on-site information

    delivery at a construction site and the need for better communication methods.

    Tsai et al. (2006) developed a synchronous system integrated with

    wireless and speech technologies for on-site data collection. The system was

  • 20

    applied in a material management case study, in which construction workers

    communicated directly with application devices to achieve synchronous

    operations and simplify manual data entry. After the system tests, analytical

    results relating to efficiency improvement indicate that the proposed synchronous

    system increased productivity, time efficiency and comparative work efficiency

    due to the decreased lead processes and operation time.

    2.3 Barcode

    The use of technology to improve the availability of tools and materials is

    not a novel concept. Barcode have a long history of tracking materials not only in

    construction but also in other industries. Barcode system components basically

    consist of a reader, barcode labels, and printers. Many barcode symbologies are

    used in a variety of applications. Each symbology represents the rules for

    character encodation, error checking, printing and decoding requirements, and

    many other features.

    The basic structure of a barcode consists of a leading and trailing quiet zone, a

    start pattern, one or more data characters, optionally one or two check

    characters and a stop pattern (Figure 2.1).

    Figure 2.1 Basic Barcode Structure

    Source: (http://www.taltech.com/resources/intro_to_bc/bcbascs.htm)

    The most popular ones are the Universal Product Code (UPC), the

    European Article Numbering (EAN), Code 39, Interleaved 2 of 5 Code, and Code

    128….etc. Code 39 is being used in construction and most construction related

    applications (Blakey1990). In general, barcodes can be classified into three main

    categories: linear, stacked, and matrix barcodes. Compared to linear barcode,

  • 21

    stacked and matrix barcodes have more data capacity and resist damage. More

    information is presented in appendix A.

    2.3.1 Barcodes Applications in Construction

    As explained previously, barcode is an automatic identification solution

    that streamlines identification and data acquisition. In the construction industry

    barcode has been the point of attraction of a lot of research and it was

    documented in some literatures. The application of barcode has been used in

    many areas in the construction industry as follows: (1) to identify and find

    materials and build components on a construction jobsite (Bell and McCulloch,

    1988; Bernold, 1990; Anderson, 1993; Skibniewski and Wooldrige, 1992); (2) to

    reduce loss and misidentification of material and equipment. With the utilization

    of barcode system, it is possible to track construction assets such as tools and

    equipment, identify them electronically, and track their movements. The

    warehouse clerk can know where the asset was, and where it is now and, who

    has it (Lundberg and Beliveau, 1989); (3) to manage construction equipment on

    the jobsite (Wirt et al., 1999); (4) to track workers on the construction site. Some

    construction companies are currently using time cards supplied with barcode

    labels to access employee information such as the name, work area, and cost

    accounting code. Work accomplished is credited to the employee account by

    scanning the label on the time card (Bell and McCulloch, 1988); (5) to identify

    documentation, drawings, material, equipment, and project activities. A barcode

    label can be applied to construction blueprints and important construction

    documents. The barcode labels can include data or instructions that enhance the

    safety, the quality, and performance of construction activities (Stuckhart and

    Cook, 1990; Rasdorf and Herbert, 1989); (6) to integrate barcode and GIS for

    monitoring construction progress. Through systematic monitoring of the

    construction process and representation of the erection progress, the scheduled

    components for erection are repetitively tracked (Cheng and Chen, 2002).

    Although an affordable technology, barcodes’ usage in construction

    suffers some problems like short range and durability. Barcodes require a line of

  • 22

    sight and become unreadable if they are scratched or dirty. Radio Frequency

    Identification technology seems to solve all these problems encountered by the

    use of barcode.

    2.4 RFID

    Radio Frequency Identification (RFID) is identified as a part of automatic

    identification technologies in which radio frequencies are used to capture and

    transmit data. Information is communicated electronically via radio waves and

    does not require contact or line-of-sight to transmit stored data; therefore, using

    RFID technology for the collection and transfer of information provides one with

    an inexpensive and non-labor intensive means of identifying and tracking

    products. The RFID tag can contain all pertinent information about the item.

    Unlike bar codes, RFID has the ability to offer the possibility of reading, writing,

    transmitting, and storing and updating information, identify and track products

    and equipment in real-time without contact or line-of-sight and the tags can

    withstand harsh, rugged environments. An RFID system is composed of tags,

    which carry the data in suitable transponders, and an RFID reader, which

    retrieves the data from the tags (CII, 2002).

    2.4.1 Tags or Transponder

    The word transponder is derived from the two words: TRANSmitter and

    resPONDER. The transponder or tag contains an antenna and integrated circuit

    ship that is encapsulated to protect against the environment (see figure 2.2).

    Tags are programmed with the data that identifies the item to which the tag is

    attached. The tag can be either read only, read once/write many, or volatile

    read/write. Read only tags are low capacity tags, usually hold approximately 8 to

    128 bits of memory and used for identification purposes. In read/write tags, the

    user can alter the information on the tag as many times.

  • 23

    Figure 2.2 Antenna sealed with RFID tag

    There are two classifications of RFID tags: passive and active. The means

    in which they receive power for transmission determines their classification.

    Passive tags depend on a power source provided by the RFID reader’s energy

    field and may have read-write or read-only capabilities, whereas, the active tags

    have an internal power source and are rewritable. Passive tags generally have

    shorter read ranges but have a life that usually outlasts the object that it is

    identifying. Active tags have longer reading ranges, high memory, and better

    noise protection. However, these tags are larger and heavier, more expensive,

    and have a shorter life (3 – 10 years) than passive tags. Read-only tags are used

    for simple identification purposes because they can only store a limited amount

    of information that cannot be altered. Such tags may be used to identify a

    package of nails or screws because they have many applications and are not

    designated to a particular item or activity.

    2.4.2 Antenna

    The function of the antenna attached to a reader is to transmit an

    electromagnetic field that activates a passive tag when it is within reading range.

    Once a passive tag is activated it can transmit information from its antenna to

    that of the reader where it is processed. During rewriting applications the antenna

    of the reader acts as a relay device in the reverse direction, the reader

    communicates a message through its antenna, which transfers and stores the

  • 24

    new data to the activated transducer via its antenna. The RFID tag’s antenna is

    practically maintenance free and can be configured in a variety of shapes and

    sizes ranging in size from a grain of rice to the size of a brick (Zebra

    Technologies, 2002).

    2.4.3 Reader

    Reader monitors incoming signals from the transponders to ensure valid

    tag data and error free operation. Depending on the applications, readers may be

    integrated into handheld computers or they may be stationary and positioned at

    strategic points, such as a facility entrance or on an assembly line (Zebra RFID

    Passive Tag Reader) (see Figure 2.3). The handheld readers offer portability,

    however, the stationary devices offer a larger reading range. As stated above,

    readers have an antenna for sending and receiving signals and a processor for

    decoding them. The reader receives instructions and information from the

    antenna through the scanner, which is a part of the reader that examines analog

    output from the antenna. The scanner’s information is then converted into a

    digital format by the reader, which the computer or processor can then use for

    data analysis, recording, and reporting (CII, 2001). There are readers today that

    can simultaneously read 100 to 2000 tags per second.

    Figure 2.3 Handheld Stationary Readers

  • 25

    2.4.4 RFID Applications in Construction

    Radio Frequency Identification technologies provide a wireless means of

    communication between objects and readers. RFID has a place in construction

    because it provides the industry a potential to improve construction productivity,

    quality, safety, and economy, cutting labor and material costs and enhancing

    project schedules. There have been quite few publications on RFID research and

    applications in construction.

    Radio Frequency Identification (RFID) has emerged as a technology that

    can be effectively applied for real time measurement of project information in the

    construction industry, such as for labor management, safety management,

    equipment management, and progress management of various works including

    concrete, pipe spools, earthwork, structural steel works, and curtain walls.

    Furthermore, it is expected that RFID will improve the limits on progress

    management (Jaselski 2003, Yagi 2005, and Song 2005).

    The most prominent application of RFID in construction has been its ability

    to improve the efficiency of the materials and equipment management process.

    In a case study conducted by Bechtel in their $338 million Red Hills Project, time

    spent locating and tracking pipe support and hangers was reduced by 30% (CII,

    2002).

    Rohm & Hass conducted an RFID pilot study that received, identified, and

    tracked Honeywell smart instrument installation. Benefits outlined from this case

    study can be summarized in inventory shrinkage, decrease of rework costs,

    improvement in data integrity (CII, 2001).

    Ngai et al. (2005) presented a case study on the development of an RFID

    prototype system that is integrated with mobile commerce in a container depot.

    They concluded that the system keeps track of the locations of stackers and

    containers, provides greater visibility of the operations data, and improves the

    control processes.

    El-Misalami (2003) proposed a system using RFID to track the activities of

    workers and equipment at the construction site. The resulting records were used

    to update the cost control system. Each worker would have a read write RFID tag

  • 26

    to record his activities. The tag would be approximately the size of a credit card

    and could be used as a worker identification badge. The use of equipment would

    be tracked by associating the equipment with the operator and the operator’s

    activity. The system was adapted for both tool-room checkout and large

    equipment management.

    RFID can also provide security to construction jobsites. Workers,

    operators, and equipment tagged with RFID can record and make certain proper

    usage and handling of equipment, materials, and documents. These systems

    would also ensure that only qualified equipment operators have the ability to

    operate restricted equipment, reducing the likelihood of misuse and accidents

    (Durfee 2002).

    Song et al. (2006) presented a case study of fabricated pipe spools in

    industrial projects. Field tests of current RFID technology were conducted to

    determine technical feasibility for automatically identifying and tracking individual

    pipe spools in lay down are yards and under shipping portals Potential benefits

    found from the use of RFID technology in automated pipe spool tracking may

    include (1) reduced time in identifying and locating pipe spools upon receipt and

    prior to shipping, (2) more accurate and timely information on shipping, receiving,

    and inventory, (3) reduced misplaced pipes and search time, and increased

    reliability of pipe fitting schedule.

    2.5 Construction Site Information

    A construction project is considered as a process that involves many

    activities and a large amount of information that are related to each other. During

    the construction phase of a project it is essential that good and timely flow of

    information prevail throughout the process. A construction project essentially

    involves a large amount of information of various types. This is due to the fact

    that different parties perform independent tasks on a project to produce a single

    final product. Since the design of a project must somehow be communicated to a

    lot of parties on the construction site, it is important that clear information,

  • 27

    coherent and efficient communication exist to ensure successful work by all

    participants in the project. The specifications must be translated into information

    that all parties can use in fulfilling their tasks. Hence, the need for drawings,

    contracts, specifications, building codes, and other forms of information emerges.

    At the same time, the performance of the project must also be communicated

    back to management so that it can be controlled effectively. In order to explore

    and develop new effective methods of information management on the

    construction site, the starting point should be identification of on site construction

    information.

    2.5.1 Construction Site Information Needs

    Information needs in construction have increased as projects have

    become more complex and owner demands have become more challenging.

    During jobsite project execution, there are three variables which can either hold

    back or facilitate successful results, mainly quality, quantity, and timing of

    information. The information needs on a construction project have been

    extensively documented in the construction IT literature and have been

    organized into thirteen major categories from a generic construction project

    perspective (Stuckhart and Nomani 1992, de la Garza and Howitt 1998). These

    thirteen categories include employee time, attendance, and work tracking;

    schedule and resource control; materials management; tool tracking; document

    control; drawing control; quality control; equipment management; request for

    information (RFI); cost management; jobsite record keeping; submittals; and

    safety monitoring. Each category was further divided into more detailed

    subcategories. For example, the group of request for information contains the

    following seven subcategories: design intent and clarification, subcontractor

    information, contract specifications, contract drawings, work package information,

    means and methods, and implementation problems. Refer to Appendix A to see

    a detailed table of jobsite information needs as presented by De la Garza and

    Howitt.

  • 28

    Another study performed by Chen and Kamara showed that on site

    construction information is grouped into twelve categories including drawings,

    material information, equipment information, contract, progress, safety

    information, sub-contractor information, design clarification, construction

    methods, specification, labor information, and quality information (Chen and

    Kamara 2006).

    Scott and Assadi summarized sites records into three main categories

    which consist of information related to finance, quality, and progress. Especially

    the progress records typically kept by contractors and supervisors aim to identify

    the project life cycle information consisting of weekly progress reports, day work

    sheets, photographs, as-built schedule, and minutes of progress meetings (Scott

    and Assadi 1999).

    Bowden et al. indicated that the main type of information that the people

    onsite deal with is paper based, which constitutes a disadvantage for site

    information communication and exchange (Bowden et al. 2004). Lack or

    inefficiency of information exchange can result in people on construction site

    overlooking important issues that require immediate response and often causes

    on site delays and loses in schedule and cost (Singhvi and Terk 2003).

    2.5.2 Construction Site Information Users

    In addition to information needs on a construction project there are people

    who may be considered users as well as sources of information. The following is

    a list of eighteen users and suppliers of information presented by Shahid and

    Froese: upper management; construction manager; chief engineer; procurement

    manager; project manager; project engineer; planning/scheduling engineer; cost

    engineer; estimator/quantity surveyor; accountant; purchasing agent; field office

    engineer; field engineer; superintendents; foremen; craft worker; laborer

    helper/apprentice.

    The most effective way for construction people to exchange information on

    construction sites is to retrieve or capture information at the point where they

    occurred and at the time when they need it. However, this situation is still ideal

  • 29

    and can’t be applied with traditional information management methods, relying

    mostly on paper-based documents. The next section presents a framework of a

    real time model to track the progress of the construction project.

    2.6 Survey of Wireless Technologies in Construction

    ENR published in 2004 that mobile communication, which is the most

    prevailing form of wireless technology, is one of the 10 technology that changed

    construction (Sawyer 2004). Wireless technology holds further potential to bring

    significant changes to the process operations at the construction sites. However,

    it was expected barriers exist to the implementation of the new wireless and

    mobile technologies in the construction industry. A survey was conducted by the

    ASCE-CI wireless construction committee to identify the current use of wireless

    technologies in the construction industry and identify industry’s opinions on

    barriers and opportunities (Williams et al. 2006).

    2.6.1 Wireless Technologies in Construction

    Laptops and Desktop are the top digital tools used in construction. With an

    edge slightly less than 90% they overcome phone and still camera (figure 2.4).

    Also it was noticed there is a rise in using sensors and tablet PC on the

    construction site. PDA percentage is slightly less than 60% and is being used

    more than video camera. Usage rate was calculated by adding the scores for one

    question and dividing it by the maximum possible score for the same.

    Figure 2.4 Digital Hardware Used in the Construction

  • 30

    Using another set of questions regarding the use of cutting edge computer

    tools and means, CAD percentage was the most used with a percentage of more

    than 60%. Video conference, web portal, and e-Learning come in second place

    with 42%. RFID and GIS are still underused and have low percentage of less

    than 20%. What is surprising is the percentage of barcode which is relatively low

    especially that it has been introduced to the construction industry for a while.

    ��

    ���

    ���

    ���

    ���

    ����

    ��

    ����������

    �������

    �����������

    ���!!����

    "#

    �$

    %����&���'������

    Figure 2.5 Cutting Edge Tools Used in the Construction

    2.6.2 Barriers to Wireless Applications in Construction

    It appears the respondents did not reach a consensus about the major

    barrier to the uses of new technology. Lack of collaboration, high cost, and

    insufficient tech support and training are among the primary reasons given for a

    reluctance to implement information technologies (Figure 2.6). A main concern

    for owners, general managers or any person in charge on job site is the amount

    of money to spend in order to get benefit from the technology in question.

    Wireless communication is an expensive technology. There are a lot of expenses

    to be taken into consideration, and a detailed study should be completed to make

    sure that the importance and savings resulting from the usage of this technology

    worth the expenses. Some of the costs of investing in wireless technology that

    need to be considered are: the purchase of the equipment and software, the

    maintenance and upgrading of the hardware, the upgrading and licensing of

  • 31

    software, the fee of wireless services providers, the salaries of in-house technical

    support personnel, the training of the users (De la Garza & Howitt, 1998).

    The typical construction project brings together several disciplines and a

    large number of subcontractors that have little incentive for sharing risks. Each

    subcontractor is held responsible for their individual work which promotes a low

    tolerance for risk within the industry. This prevents technology adoption.

    Training and tech support need is another major concern of the

    respondents. This lack of expertise may be a sign that use of wireless technology

    in construction is still at its early stage. Data security and risk of data loss also

    are barriers to its application. Till now, all communication systems are

    susceptible to being violated and there is possibility that the information

    transmitted being received by undesired users. So the information sent has to be

    classified according to importance and how sensible it is so that precautions

    would be taken.

    Another factor that we can’t overlook is the lack of metrics to assess value

    and quantify benefits of applying these technologies.

    Figure 2.6 Barriers to Wireless Applications in Construction

  • 32

    CHAPTER 3

    BACKGROUND

    This chapter lays necessary background for the research and includes

    necessary information to conduct the research. First a detailed description of

    wireless technologies is given, accompanied with identification of different parts

    pertaining to this technology. Then a review of the concept of decision-making

    and utility theory is presented. That includes an outline about the basics and

    assumptions of the utility theory, followed by a description of different techniques

    used in multi criteria decision-making. Furthermore, a definition of computer

    simulation and its uses in construction is discussed to lay the necessary

    background for the coming chapters.

    3.1 Wireless Technologies

    Wireless services represent a progression of technology, and a new era of

    telecommunications, but these services have been used for over a century and

    remain synonymous with radio. There are several evolving technologies that

    have the ability to improve the efficiency of the construction process. In this

    research we are limiting evolving technologies to mobile computing. The concept

    of mobile computing has been considered to consist of three major components:

    computer, networks and mobile applications (Rebolj and Menzel 2004).

    Computers, which can be used indoors, and outdoors by users include table

    PCs, all kinds of pocket computers, palmtops and wearable computers.

    3.1.1 Mobile Hardware

    Primary mobile computing hardware that’s available today for the

    construction site application are made up of the following groupings: 1) personal

  • 33

    digital assistants, 2) handheld computers, 3) pen tablet/touch PC, 4) rugged

    notebook PC, 5) wearable computers/digital hardhats, and 6) digital pens

    (COMIT 2005).

    3.1.1.1 Personal Digital Assistants

    A PD