SCOPE OF WORKS
Void refurbishment, The void had previously suffered
Flat 7, 17 Park Road N18 2UQ
TOPCOAT CONSTRUCTION LTDA sidebar is a standalone supplement to the main document. It is often aligned on the left or right of the page, or located at the top or bottom. Use the Text Box Tools tab to change the formatting of the sidebar text box.]
Void refurbishment
This void is in a building that is
warden assisted 24Hours a day 7
days a week. We needed to
finish this void extremely quickly
as our client had already signed
up the new tenant to move in just
5 Days after the void was raised.
The work was carried out on a
very low budget, and was
completed for £925.37 this
included a through clearance and
extensive cleansing of the
property, it was partly decorated
where it was felt necessary and
some minor overhauling of doors,
windows and sanitary fittings. We
had to use one of our specialised
teams due to the nature of some
of the tenant with special needs.
All works were completed and
handed back to the client within 4
working days.
PROJECT
CLIENT: Morrison
(OHG Camden)
TCL SERVICES: Void
refurbishment
PROJECT DURATION:
Start:
07.04.11
Completion:
11.04.11
VALUE: £925.37p
www.topcoatconstructionltd.co.uk