Fit Out Guidelines

Embed Size (px)

Citation preview

  • 8/18/2019 Fit Out Guidelines

    1/46

     

    3C FACILITY MANAGEMENT

    FIT-OUT GUIDELINES

    1

     

  • 8/18/2019 Fit Out Guidelines

    2/46

     

    3C FACILITY MANAGEMENT

    FIT-OUT GUIDELINES

    2

     

    CONTENTS

    1.1 INTRODUCTION.................................................................................................... 6

    1.2 WHAT IS A GREEN BUILDING? ........................................................................ 6

    1.3 THE STRATEGIES ADOPTED FOR THE GREEN BUILDING ARE: .......... 7

    1.4 TENANT DESIGN & CONSTRUCTION GUIDELINES……............................ 9

    2.1 INTRODUCTIONS................................................................................................ 14

    2.2 COMMUNICATION / SITE LIAISON............................................................... 14

    2.3 CONTACT DETAILS FOR FIT OUT RELATED WORKS............................ 14

    2.4 FIT OUT COMMENCEMENT LETTER........................................................... 152.5 DESIGN SUBMISSION & REVIEW................................................................... 15

    2.6 FINAL DESIGN APPROVAL ............................................................................. 15

    2.7 PRE FITOUT ......................................................................................................... 16

    3.1 ACCESS………………………………………………………………….................18

    3.2 PARKING ............................................................................................................... 18

    3.3 MATERIAL DELIVERIES .................................................................................. 18

    4.1 GENERAL HOUSE RULES ................................................................................. 20

    4.2 FLEX ....................................................................................................................... 20

    4.3 CONSTRUCTION PROCEDURE ...................................................................... 204.4 TIME OF WORK .................................................................................................. 20

    4.5 EXECUTION OF WORK...................................................................................... 21

    4.6 CLEANLINESS/WASTE MANAGEMENT (MALBA/DEBRIS) .................... 21

    4.7 MATERIAL STORAGE........................................................................................ 21

    4.8 PROTECTION........................................................................................................ 22

    4.9 INSURANCE .......................................................................................................... 22

    5.1 SERVICES ............................................................................................................. 24

    5.2 TEMPORARY SERVICES .................................................................................. 24

    5.3 REGULAR SERVICES ........................................................................................ 24

    5.4 SERVICES COMMISSIONING .......................................................................... 24

    5.5 TOOLS & EQUIPMENT....................................................................................... 25

    6.1 BADGES.................................................................................................................. 27

    6.2 ITEMS DELIVERED AND ITEMS REMOVED............................................... 27

    6.3 ACCESS TO ADJOINING AREAS..................................................................... 27

    6.4 PROTECTION OF FINISH WORK ................................................................... 27

    6.5 WORKING HOURS ............................................................................................. 27

    6.6 GENERAL SAFETY.............................................................................................. 28

    6.7 ELECTRICAL SAFETY ...................................................................................... 29

  • 8/18/2019 Fit Out Guidelines

    3/46

     

    3C FACILITY MANAGEMENT

    FIT-OUT GUIDELINES

    3

    6.8 FALL PROTECTION........................................................................................... 30

    6.9 WELDING AND CUTTING ............................................................................... 31

    6.10 ENVIRONMENTAL CONSTRAINTS.............................................................. 31

    6.11 FIRE SAFETY MANAGEMENT........................................................................326.12 SITE SECURITY.................................................................................................. 32

    6.13 HEALTH AND SAFETY.................................................................................... 33

    6.14 SCHEDULE COORDINATION ....................................................................... 33

    7.1 DO’S....................................................................................................................... 36

    7.2 DON’TS ................................................................................................................. 37

    8.1 ANNEXURE 1 HOT WORK PERMIT................................................................. 39

    8.2 ANNEXURE 2 ID CARD REQUISITION FORM FOR WORKERS............... 40

    8.3 ANNEXURE 3 – TENANT/CLIENT FIT OUT FORMS................................... 41

    8.4 ANNEXURE 4 FIT OUT COMMENCEMENT LETTER................................. 448.5 ANNEXURE 5 SITE ACCESS PLAN................................................................... 45

    8.6 ANNEXURE 6 ACKNOWLEDGEMENT FORM.............................................. 46

  • 8/18/2019 Fit Out Guidelines

    4/46

     

    3C FACILITY MANAGEMENT

    FIT-OUT GUIDELINES

    4

     

  • 8/18/2019 Fit Out Guidelines

    5/46

     

    3C FACILITY MANAGEMENT

    FIT-OUT GUIDELINES

    5

     

    1Green Buildings: An Overview 

  • 8/18/2019 Fit Out Guidelines

    6/46

     

    3C FACILITY MANAGEMENT

    FIT-OUT GUIDELINES

    6

    1.1 Introduction

     As a part of our new economy, more and more companies are drawn to, and motivated to stay in,

    areas offering a higher quality of life. There is a widespread evidence of the importance of a clean

    environment and other quality of life considerations. The Green Buildings at Noida (India) have beendesigned as per world class systems & procedures qualifying for LEED certification.

    1.2 As we understand Green Building

     A Green Building is one, which in appearance and functionality is the same, as any other building. Any

    green building would show tremendous concern on efficient utilization of conventional resources and

    exploring utilization of non conventional source of energy, thereby reducing the impact on

    environment.

    In general, a Green building would incorporate the following green features:

    1. 1. Use of energy efficient and Eco-friendly equipment2. 2. Use of recycled and Environmental friendly Building materials3. 3. Quality indoor air quality for human safety and comfort4. 4. Efficient use of water5. 5. Use of Nontoxic & recycled materials6. 6. Effective controls and building management system

    The development of the Green Building would bring many benefits to the occupants. Support from our

    tenants in designing their space using the principles outlined in this handbook will ensure that the

    benefits of the Green Building designed are optimized.

    Some of the benefits for the occupants:

    . Lower Operating costs

    . Improved Worker Productivity

    . Future proofing for the utility rates

    . Positive Corporate Image

    . Good for the Environment

    The following world class systems & procedures are being considered at the design stage of thebuilding:

    1. Energy efficiency of equipment & systems ASHRAE 90.1.20042. Lighting – IESNA standards3. Indoor air quality ASHRAE 62.120044. Thermal Comfort – ASHRAE 552004

    The building has been evaluated on the basis of the methodology outlined in ASHRAE/IESNA 90.1-

    2004. Visual DOE4.1, a front-end to the DOE2.1E engine, has been used as the simulation tool.

    The performance of the building will also be monitored by an Intelligent Building Management Systems

    (IBMS) and international standards & procedure, IPMVP protocols.

  • 8/18/2019 Fit Out Guidelines

    7/46

     

    3C FACILITY MANAGEMENT

    FIT-OUT GUIDELINES

    7

     1.3 The strategies adopted for the Green Building are:

    1. Construction

    Wall Construction:

    The building uses autoclaved aerated concrete (AAC) blocks with a ‘U’ value of 0.12 Btu/hr/ft/ºF which

    have a very high insulation property. Their high fly ash content (60%) further helps the building to

    address environmental concerns.

    Roof Construction and Finish:

    The building uses overdeck R15 extruded polystyrene insulation. In addition to the insulation, the

    building roof has a Green Roof. The Green Roof ensures that a large percentage of the incident heat

    energy is not absorbed by the roof.

    High Performance Glazing:

    Most of the glazing area is on the north façade of the building – the shading coefficient and lighttransmittance for this glass were developed very carefully in order to enhance available daylight in the

    space and maintain visual comfort for the occupants without comprising on energy efficiency. These

    high performance glazing will also provide external connectivity for the building occupants.

    2. Indoor Environmental Quality

    Temperature and humidity:

    The equipments & systems are designed in such a way that the air-conditioned space will be

    maintained at a temperature of 24 deg C and with the humidity level of 50-60 %, throughout the

    operation of the building (24x7), irrespective of the occupancy levels & outside ambient conditions.

    CO2 monitoring:

    CO2 levels in the conditioned space will also be continuously monitored and compared with the outside

    ambient CO2 level. If the difference rises above 530 ppm, then more fresh air will be taken and blown

    in the conditioned area. This will further enhance the productivity of the building occupants due to

    lower CO2 levels.

    Elimination of the Environmental Tobacco Smoke:

    Green Building understands the Environment concerns and adopts the policy of providing dedicated

    smoking zones on the terrace.

    Finishes:

     Adhesives, Sealants, Paints, Resins used in finishes (core & shell and common areas) are selected

    with low VOC content. These features will also enhance the human comfort levels.

    Efficient Lighting:

    Efficient fluorescent lamps (T5s) and luminaries with high coefficient of utilization have been selected

    (for common areas) to achieve efficient lighting.

  • 8/18/2019 Fit Out Guidelines

    8/46

     

    3C FACILITY MANAGEMENT

    FIT-OUT GUIDELINES

    8

    3. HVAC System

    Efficient Chillers:

    The chillers provided for this building are water cooled screw chillers having a COP of 6.1

    Secondary Chilled Water Pumps:

    The building has primary & secondary chilled water pumping with variable speed drive to economize

    on pump usage and in turn energy. Also the Air Handling units with Variable speed drives are used

    which would modulate on the basis of actual temperature in the conditioning area. Energy efficient

    equipment & systems will reduce the operating cost from the day one, of operation of the building.

    These equipment & systems are designed, without comprising the human comfort levels, such as,

    lighting levels, temperature in the conditioned space.

    Metering:

    Individual Energy meters are installed for each floor and the billing to the tenants would be done as per

    the actual readings of these meters. This means that any energy saved would directly reflect in the

    bottom line. The energy meters are linked to the central BMS. This would enable the tenants tomonitor/compare their consumption.

    4. Water efficiency

    Water efficient fixtures will be installed in the building. This will result in tremendous reduction in water

    consumption. Flow of fixtures shall adhere to following:

    Water Closets : 0.8 GPF

    Urinals : 0.5 GPF or waterless

    Hand wash : 2.0 GPM

    Shower : 2.0 GPM

    Kitchen Sink : 2.0 GPM

    Water balance for the building has been developed. This has also helped the water consultant to

    design & size the water treatment plant. Recycled & treated water would be used for landscape and

    irrigation thus reducing the need of any excess amount of potable water use.

    5. Waste management

    The project has allocated a separate space for segregation waste. This will enable the propertymanagement group to segregate the waste generated in the building at the source itself.

    The above mentioned design features considered will have an impact on energy efficiency levels and

    will result in tangible & intangible benefits for the occupants.

  • 8/18/2019 Fit Out Guidelines

    9/46

     

    3C FACILITY MANAGEMENT

    FIT-OUT GUIDELINES

    9

     

    1.4 Tenant Design & Construction Guidelines

    In order to further enhance the added values of Green Buildings we would like to have participation of

    all In-house clients utilizing the space facilities in Green Building. Salient guidelines to be considered

    by clients while designing interiors/fit outs are enumerated as below which they may like to consider

    positively:

    1. Promote use of eco-friendly vehicles

    Being a green building, provisions have been provided to charge the Electric vehicles at parking area.The tenants can avail the charging facility by going in for energy efficient and environment friendlyalternate fuel vehicles, such as, electric vehicles, or CNG vehicles.

    2. Avail preferred car parking

     A carpool arrangement in which two or more members share a vehicle for transportation could be

    encouraged. A preferred car parking has been provided for carpools or vanpools. The tenants may

    encourage the carpooling amongst the employees through interoffice memo. This will facilitate the

    occupants to participate & avail the carpooling programmes.

    3. Energy performance criteria

    Interior lighting:

    The interior lighting should be designed with overall lighting power density less than 1.0 Watts per sft.

    The tenants could look for energy efficient lamps, luminaries and control gears. An illustrative list oflamps & control gears is listed for reference:

    � Compact fluorescent lamps (CFL’s) with mercury content (Hg), less than 2 mg per lamp but not with

    liquid mercury

    �T5 series of fluorescent lamps with HPF of not less than 0.98

    � Colour 80 series fluorescent lamps

    � Dimmable ballast

    � Movement sensors

    � Lux level based sensors

    �Occupancy sensors

    � Toggle switches for individual controls

    � Controls for blinds on the select glazing.

    Plug loads

    Office Equipments:

    Office equipments, Computers, monitors, copiers, fax machines Refrigerators, Micro ovens Coffee

    makers etc come in energy savings versions. Select the equipment keeping in mind energy efficiency.

    Look for ‘Energy Star’ labels.

  • 8/18/2019 Fit Out Guidelines

    10/46

     

    3C FACILITY MANAGEMENT

    FIT-OUT GUIDELINES

    10

    Consider LCD in lieu of conventional CRT monitors. The advantages of the LCD in comparison with

    the conventional CRT monitors are:. •Occupies 1/6

    th

    depth and 85% of the width and height.. •Requires 1/3

    rd

    the power.. •Display reduced glare, long term gain in vision and human comfort.

    Task Lighting

     A key component to a comfortable lighting system is giving the users control of their local lights. One of

    the best ways to offer this is to provide a flexible and efficient task light. Using task lighting can also

    mean that the overall ambient lighting can be reduced, saving both initial cost and overall energy use.

    4. CFC reduction in Fire suppression system

     Avoid Chlorofluorocarbons (CFC’s) based refrigerants in Fire suppression systems. CFC’s could

    impact environment and health. Use only non CFC based refrigerants for fire suppression systems.

     Alternatives are either HCFC’s (Hydro chlorofluorocarbons) or HFC’s (Hydro fluorocarbons).

    5. Storage & collection of recyclables

    The buildings has provided a dedicated storage and collection area to segregate, collect and storage

    of materials for recycling which includes, paper, cardboard, glass, plastics, metal, etc. During interior

    fit-outs, segregate these materials to facilitate recycling.

    During occupancy, segregate waste at source to help the property management group to recycle.

    6. Recycled content

    Tenants could explore the possibility of using building products that incorporate recycled content

    materials. By doing so, it reduces the impacts resulting from extraction and processing of new virgin

    materials and giving a new life to the recycled content material.

     An illustrative list of building products with recycled content materials are as follows:

    1. False ceiling material, which comprises of gypsum (which is industrial byproduct or waste)2. Door panels made out of baggasse3. Aluminum door and window frames, with very high recycled content

    7. Rapidly renewable materials

    Tenants could use rapidly renewable building materials and products (made from plants that are

    typically harvested within a ten year period or shorter).

    Typical examples of rapidly renewable materials are as follows:

    . MDF (Eucalyptus, Cotton straw)

    . Composite wood (Baggasse)

    . Bamboo flooring

    . Linoleum flooring

    . Sunflower seed board

    . Wheat grass cabinetry

    . Wool carpet

  • 8/18/2019 Fit Out Guidelines

    11/46

     

    3C FACILITY MANAGEMENT

    FIT-OUT GUIDELINES

    11

     

    8. Regional Material

    Interior material can be procured within area of 500 miles to promote local materials and reducetraveling distance.

    9. Low emitting materials

    To reduce the quantity of indoor air contaminants that is odorous, irritating and/or harmful to the

    comfort and well-being of installation workers and occupants.

    Volatile Organic Compound (VOC’s) present in finishing products has harmful effect on the building

    occupants. The VOC’s vaporize (become a gas) at normal room temperature. Hence, the interior

    designers can use products with VOC’s within the specified limits.

    The VOC limits for Adhesives and sealants are as follows:

     Architectural sealant Non membrane roof Roadway Single ply roof membrane Others

    250 (grams per litre)

    300 (grams per litre)

    250 (grams per litre)

    450 (grams per litre)

    420 (grams per litre)

    The VOC limits for interior paints

    � Nonflat 150 (g/litre)

    � Flat 50 (g/litre)

    Most of the paint manufactures (like Asian Paints, etc) do manufacture paints with low or no VOCcontent.

    Carpets Emission factor limit mg/m2

    h

    � Carpet total VOC’s 0.50

    � Adhesives total VOC’s 10.0

    � Cushion total VOC’s 1.00

    Composite woods

    Composite woods and agrifiber products should free from urea-formaldehyde resins. Hence, the

    interior designer team should specify the composite wood be free from urea-formaldehyde resins. Atpresent, composite woods are available made with Phenol formaldehyde resin.

    10. Indoor Chemical & Pollutant Source control

    The tenants are advised to provide dedicated room for locating copying and fax machines. These

    rooms have to be physically separated with deck-to-deck partitions with independent exhaust

    ventilation.

  • 8/18/2019 Fit Out Guidelines

    12/46

     

    3C FACILITY MANAGEMENT

    FIT-OUT GUIDELINES

    12

     

    11. Daylight & Views

    The building is designed to provide excellent day-lighting and views for the occupants. The tenants areadvised that the Interior layouts and fit-outs should be designed in such a way that the design provides

    the building occupants a connection between indoor spaces and the outdoor through the introduction

    of daylight and views.

    Providing day lighting and views for occupants, will enhance the productivity of occupants by

    10 – 15 %.

    12. LEED for Commercial Interiors

    The above mentioned design features considered will have an impact on energy efficiency levels and

    will result in tangible & intangible benefits for the tenants. As explained, Green Buildings are aspiring

    for LEED Core & Shell rating of USGBC. The tenants could design & construct their fit-outs in

    accordance with the guidelines provided, as above. This will further enhance the performance of the

    whole building. In order to facilitate the tenants of base buildings, USGBC has introduced an exclusive

    rating programme for commercial interiors, LEED for Commercial Interiors (LEEDCI). Hence, we would

    encourage the tenants to apply the above guidelines & attempt for LEEDCI ratings.

    For further details on LEEDCI & green design, the tenants are requested to

    visit the USGBC website, www.usgbc.org.

  • 8/18/2019 Fit Out Guidelines

    13/46

     

    3C FACILITY MANAGEMENT

    FIT-OUT GUIDELINES

    13

     

    2Communication/Site liaison 

  • 8/18/2019 Fit Out Guidelines

    14/46

     

    3C FACILITY MANAGEMENT

    FIT-OUT GUIDELINES

    14

     

    2.1 IntroductionIt is imperative that all Tenants/Clients undertake their works at The Building by coordinating their work

    with the Contractor and the Property Management Team so as to ensure that neither Party is hindered

    in completing the work required for the joint opening.

    The Tenants/Clients Contractors must coordinate the work as per the following guidelines. These

    guidelines are for the construction and fitout to the time of the initial opening of the property. This

    document does not in any way substitute the meetings which are required to be held prior to the start

    of a Tenants/Clients work at Site.

    The Fitout Manager is a focal point in the management of Tenants/Clients. Each Contractor should

    assign a coordinator to be available on Site during all normal working hours and available during non-

    working hours as may be required. Each Contractor will be responsible for proper execution of his

    work and will be required to attend meetings as required for the purpose of coordinating all fitout

    activity in the Property.

    It is utmost important that lines of communication are open at all times therefore it is necessary for

    each Tenants/Clients Contractor to have a Cell Phone available for use on Site. The following are the

    guidelines for communication and site liaison during fit out stage:

    2.2 Communication / Site Liaison

    The Tenants/Clients shall inform The Three C Facili ty Management Team for any fit out related work.

    The Three C Facility Management Team will have an overall responsibility for the site. All

    welding, cutting or brazing work etc. must be informed

    to the management in advance. A hot work permit (Refer Annexure 1) has to be obtained from

    Management office.

    Work permits will be required to be taken for all works outside the individual units including the

    common areas, corridors, roofs, service yards etc.

    Before the commencement of fit out work the Tenants/Clients must collect ID Cards for their

    respective workers from the

    Management office for which requisition form will be submitted (Refer Annexure 2).

    The procedure of carrying out such works will be checked by Management Team and

    amended in consultation with the

    Tenants/Clients contractor before the work is carried out.

    2.3 CONTACT DETAILS FOR FIT OUT RELATED WORKS

    Fitout Manager

    In case of any emergency the following people can be contacted;

    Tenants/Clients Information Tenants/Clients will be provided with Tenants/Clients Fit out

    Forms (Refer Annexure 3) which they will fill and submit to Fitout manger/Management Team.

  • 8/18/2019 Fit Out Guidelines

    15/46

     

    3C FACILITY MANAGEMENT

    FIT-OUT GUIDELINES

    15

    2.4 Fit out Commencement Letter

    The client will fill up all details in the commencement letter and submit for

    approval of Property Management Team. The format of commencement letter isattached in the Annexure 4.

    2.5 Design Submission & ReviewTenants/Clients fit out Designer will submit their preliminary design concept to our Fit-out Manager,

    who will approve it in coordination with Management Team. This submission will include following

    docs:Floor plans, reflected ceiling plan, front elevations, sections and internal elevations @ 1:50

    scale

    Services layout including load requirement (Fire, HVAC ducting, Electrical and Mechanical)

    The submission must be complete in order to evaluate proposal fairly for adequacy of services.Wherever it is required that preliminary design submission need to be revised will be resubmitted for

    further review after needful amendments.

    2.6 Final Design Approval

    The Fit-out Manager will issue final design approval once the design submission is reviewed. This

    approval shall be subject to comments and/or advisory notes on the design drawings.

    It is important that Tenants/Clients give his contractor a copy of the stamped drawings for accurate

    pricing and construction purpose.

    The ‘as built’ fit out must reflect the final Fit-out Manager approved drawings and conditions. Any

    deviation from the approved drawings and conditions not expressly approved by the Fit-out Manager

    shall be considered invalid and must be rectified before work is executed at site.

  • 8/18/2019 Fit Out Guidelines

    16/46

     

    3C FACILITY MANAGEMENT

    FIT-OUT GUIDELINES

    16

    2.7 PRE FITOUT

    Following Steps of activities are necessary Prior to start Fit out Work:

    It is your responsibility to check and confirm all services locations and dimensions and inform us of anydiscrepancies.

  • 8/18/2019 Fit Out Guidelines

    17/46

     

    3C FACILITY MANAGEMENT

    FIT-OUT GUIDELINES

    17

     

    3 Access 

  • 8/18/2019 Fit Out Guidelines

    18/46

     

    3C FACILITY MANAGEMENT

    FIT-OUT GUIDELINES

    18

     3.1 Access

     All access for materials/Personnel will be through specified location as shown in the site plan

    attached (Refer Annexure 5).

     Access to the roof is strictly prohibited. For those Fit out Contractors who require access a

    special permit system will be in place.

    Use of main floor, lobbies, or elevator lobbies is prohibited for storing material even on a

    temporary basis.

     Access to the designated fire exits escape routes must be always kept clear without any

    interruption. 

    Tenant’s /Client’s contractor will fill up the ID card requisition form (attached in Annexure 2)

    and submit a copy to property management team for issue of temporary ID Cards. 

    3.2 Parking

    Delivery vehicles are not allowed to park inside the property, it should immediately leave the

    premises after unloading the deliveries.

    No vehicle parking is allowed within the development area without approval of Property

    Management (where applicable).

    3.3 Material Deliveries

     All materials are to be delivered directly to the leased premises and will not be allowed to be

    stored outside the occupied area or outside the building at street level for any reason. Material

    deliveries should be staged to coincide with the work about to be performed.

    Passage to upper levels will be by indicated staircase only, near loading unloading.

    Materials shall be bagged and manually handled and no materials shall be dragged or

    dropped on the floor surfaces, particular care shall be taken to ensure that the floor tiles and

    fabric are not damaged.

    The Tenant’s /Client’s Contractor representative shall be present on Site to receive all

    material deliveries. He shall witness all material movements to and from the leased premises.

    The security of the delivered fit out materials will be under complete responsibility of Tenant’s

    /Client’s or his contractor. No material shall be stored adjacent to or against any finished

    surfaces.

  • 8/18/2019 Fit Out Guidelines

    19/46

     

    3C FACILITY MANAGEMENT

    FIT-OUT GUIDELINES

    19

     

    4OperationalGuidelines 

  • 8/18/2019 Fit Out Guidelines

    20/46

     

    3C FACILITY MANAGEMENT

    FIT-OUT GUIDELINES

    20

    4.1 General House Rules

    The following rules and guidelines for Fit-Out must be adhered to at all times:

     All work must be carried out by Contractors who are registered and operate in a professional

    manner.

     All Contractors must have current Workers Compensation Insurance (unlimited) and Public

    Liability Insurance as applicable.

     All materials used onsite are supposed to be new and materially sound safe to handle,

    serviceable and all work is to be completed in a professional manner with the minimum

    interruption to the trading of the Building.

    Tenant’s /Client’s contractor, Project Manager must be present during site induction.

    Tenants /Client’s must provide a copy of commencement letter as per the standard format.

    Tenants /Client’s must provide a copy of fit out schedule to Management prior to commencingwork Onsite.

    Tenant’s /Client’s need to fill up and submit the hot work permit form (attached in Annexure 1)

    to process any hot work during fit out period in advance.

    4.2 Flex

    To maintain the esthetics and deco of the Building, you are required to cover the front and

    rear glass façade of your leased premises opening in the common area from inside with flex

    during the fit out period. You are required to do the same before starting the FitOuts. This

    should only be removed after the completion of the fit-outs and clearance obtained from

    Property Management Team.

    In case of non compliance for the same the management will put own flex and the cost of

    same will be debited to you.

    4.3 Construction procedure

    The hoarding put by client/ tenants shall be dust and fireproof. Damages to property if any will be atthe cost of the Tenant’s /Client’s. AT NO TIME WHATSOEVER, MAY BE WORK OF ANY NATUREBE CARRIED OUT ON THE PROPERTY CONCOURSE AND COMMON AREA.

    4.4 TIME OF WORKThe general hours of work will be between 0900hrs to 2000hrs. However, these hours may beextended on request at the discretion of Building Management for which advance notice shall be givenby the Tenant’s /Client’s for which client has to take up case for approval from property managementbefore 1500 hrs so that necessary arrangements like security is organized accordingly.

  • 8/18/2019 Fit Out Guidelines

    21/46

     

    3C FACILITY MANAGEMENT

    FIT-OUT GUIDELINES

    21

     4.5 EXECUTION OF WORK

    Prior to the commencement of Work, the Contractor shall provide Fit-out Manager with aprojected schedule showing the major activities of work with the dates of their start and finishwith significant milestones for management to inspect.

    Wherever applicable, permits must be obtained from property management prior to thecommencement of work. The fit-out Manager may approve deviations if any on exceptions inwriting.

    Mixing of cement PCC etc. for flooring or otherwise can be done in their own licensed space.

    Protect Glazing: Tenants/Clients will ensure that brown sheets/temporary branding sheets/flexis covered on the glass door/frontage of their premises during fit outs to avoid any damage tothe glazing and door.

    Tenants/Clients will ensure that a door mat is placed outside the licensed space during fit outsto avoid spoiling of floor.

    4.6 CLEANLINESS/WASTE MANAGEMENT (Malba/Debris)

    The Intended Tenants/Clients shall ensure that all debris (malba) generated by them is stored

    temporarily safe from fire hazard within their space and is daily cleared. The Contractor will

    provide facility for removal of waste and debris from the building at his own expenses.

    Construction personnel shall at all times maintain the highest level of project cleanliness. In

    the event that the Contractor fails or refuses to keep the demised premises free of

    accumulated waste, the management Office reserves the right to enter the said premises andremove the debris at the Contractor's/Tenants/Clients expenses as applicable.

    Each Tenants/Clients should discuss their requirements regarding the material waste directly

    with the Property Management Team. This will be handled separately from main construction

    waste.

    In case the need arises, the Fit out Manager will provide extra assistance to dispose of waste.

     Any costs arising from this shall be charged extra to the Tenant’s/Client’s. No waste materials

    are to be flushed in the Property drainage system. The drainage system should be kept clean

    and clear.

    Tenants/clients have to arrange for the toilets/washrooms for their workers/laborers. Common

    area washrooms should not be used by their laborers in any case.

    4.7 Material Storage

    Materials/goods cannot be stored in any area other than the area provided to the

    Tenant’s/Client’s. Incase, the need arises a prior written approval has to be taken from the

    Fitout Manager on its merits.

  • 8/18/2019 Fit Out Guidelines

    22/46

     

    3C FACILITY MANAGEMENT

    FIT-OUT GUIDELINES

    22

      All Tenants/Clients fit out Contractors must recognize that the area outside their own space is

    not to be used for any kind of storage or any other activities. When materials are unloaded

    they must be received and taken out of common area immediately. Failure to

    do so will result in materials being removed, without prior notification.

    Building Property Management is not liable for any loss due to fire, natural calamities, theft or

    damage to the furniture, fixture, material or supplies belonging to the Tenants/Clients.

    No explosive, inflammable or hazardous material will be used or stored anywhere on site or

    incorporated within the Licensee Fit Out works.

    4.8 PROTECTION

    No damage should be caused to the property, and incase of any, the Tenants/Clients will be

    responsible to make it good.

    The sign displaying the name of the Tenant’s/Client’s, their principle contractor and

    emergency call numbers of key personnel’s must be available at all times.

    The final removing and disposing of temporary signage’s will be undertaken by the

    Tenants/Clients contractor and will only be permitted when all works likely to cause

    interruption in the operation have been completed.

    Tenants/Clients must take all measures necessary to protect adjacent Tenants/Clients

    finishes, their own finishes and the Base Building Property finishes from any kind of physical

    damage, dust, noise, vibration or any other nuisance.

    4.9 Insurance

    Each contractor employed at the project shall provide the Property Manager with current

    certificates of insurance. Each contractor is responsible for obtaining acceptable certificates of

    insurance from all subcontractors as applicable.

    Worker’s Compensation and Employer’s Liability: As required by the laws of the State in

    which the work is to be permitted these liabilities will be applicable to all contractors. The

    responsibilities and lawful liabilities as principal employer will be of such contractors/Tenants

    as applicable.

    General Liability: Commercial General Liability or Comprehensive General Liability on an

    Occurrence Form (Claims Made coverage not acceptable) insuring Body Injury, Property

    Damage and Personal Injury against the hazards of licensed space and Operations (including

    the use of mobile equipment), Products and Completed Operations shall be of the

    Tenants/Clients Contractor.

  • 8/18/2019 Fit Out Guidelines

    23/46

     

    3C FACILITY MANAGEMENT

    FIT-OUT GUIDELINES

    23

     

    5Services 

  • 8/18/2019 Fit Out Guidelines

    24/46

     

    3C FACILITY MANAGEMENT

    FIT-OUT GUIDELINES

    24

    5.1 ServicesThe Intended Tenants/Clients or its contractors will not tamper with or relocate the fire safety

    systems.

    No disturbance should be caused to the services already laid except for extending its length

    below or above false ceiling as applicable without any temporary joints.

    5.2 Temporary Services

    Each Occupant should notify capacity of all temporary services, which they would require

    during fit out period prior to commencement of fit out.

     All cost associated with it shall be borne by the Tenant’s/Client’s.

    Temporary water and electricity required during the fit outs can be arranged at the premises.

    The same can be procured in consultation with Fitout Manager and the payment to be done

    based on actual metered consumption as applicable directly by the Tenants/Clients to theBuilding Management or as mutually decided with vendor/supplier for prorate charges.

    Rates of recovery of water, electricity consumption shall be as notified by the Property

    Management based on prevailing tariff rates of state govt. /bulk supplier and on cost

    expenditure as well as losses.

    5.3 Regular Services

    The provision for regular services has been made in the licensed space. However, these

    services will be connected to leased area internal services only after internal services are

    completed and are tested for its adequacy and found fit for commissioning.

    Note:  Services will not be made live till the time Tenants/Clients contractor provide

    satisfactory evidence that their system is complete and is certified that the system is capable

    of receiving the live load and has been tested for maintaining norms/engineering practice.

    Each Tenants/Clients shall ensure that any discharge to the drainage system from their unit

    does not default any of the local regulations. If damage to the main drains occurs due to any

    action of an occupant, the cost of rectification of such damage will be recovered from the

    offending occupant.

    5.4 Services Commissioning

    Base Building engineering and electrical systems may be undergoing final commissioning and

    witness testing during the fit out period. These systems will therefore be subject to

    interruptions.

    Fit out contractor should therefore make necessary arrangement to withstand these

    interruptions. Final connection and testing of supplies or interface services to Tenants/Clients

    units will not be started unless:

  • 8/18/2019 Fit Out Guidelines

    25/46

     

    3C FACILITY MANAGEMENT

    FIT-OUT GUIDELINES

    25

    a. All information requested is received and approved.

    b.Fit Out completion must be intimated 10 days in advance to facilitate

    arrangement of testing and commissioning.

    c. All dues are cleared by Tenant’s/Client’s.

    d. Fit out site of Tenants/Clients is cleared from malba /debris.

    Competent Technical Personnel will address any issues arising during the commissioning

    operation. However, representative from the Base Building Management and the

    Tenants/Clients must be in attendance to witness all commissioning operations. The

    Tenants/Clients must only carry out final connection to any service once authority has been

    received from the Fit out Manager.

    5.5 Tools & Equipment

    Equipments and machines must be clearly marked with indelible marker or paint with the

    Tenants/Clients Contractors name, in order to be permitted inside. The Tenants/Clients

    should disclose the rating of the equipments they will be using for execution that needs to be

    approved by the Fit out Manager for availability of adequacy of services.

    Tools and Equipment will not be allowed to leave the Site without proper authorization/gate

    pass.

    Construction equipment must be compatible with the Site power source available. Tenant

    should declare the rating of various equipments to be used during fitout time to assess the

    total power requirement. Equipment will only be permitted to use once it is ensured that total

    power drawn is within the permitted limits.

    Equipment must be properly fitted for its use. Equipment must not drip oils or grease and shall

    be fitted with proper wheels etc.

     Any temporary power connections for tools and equipment will be arranged on payment.

    The Tenants/Clients Contractor shall utilize floor vacuums or sweeping compounds to

    maintain dust levels to a minimum.

    Tools for Equipment must not be plugged into the Common Property Power supply.

    No equipment/machinery shall be dragged on floor unless it is on soft wheels or else will be

    manually lifted to avoid damage to floor

  • 8/18/2019 Fit Out Guidelines

    26/46

     

    3C FACILITY MANAGEMENT

    FIT-OUT GUIDELINES

    26

     

    6Safety and Security

  • 8/18/2019 Fit Out Guidelines

    27/46

     

    3C FACILITY MANAGEMENT

    FIT-OUT GUIDELINES

    27

     

    The security and safety of man, material and machinery in and around the site of Base Building isparamount requirement of Property Management. To ensure this, The Tenants/Clients and their

    employees and Contractors are required to strictly observe following rules and norms which are just

    guidelines only, which will be updated by Tenants/Clients as suitable to their Space/Offices.

    6.1 Badges

     All personnel shall be identified with a badge of identification denoting the Unit they are fitting out and

    the Company they represent. The Tenants/Clients will prepare his own badges or will be given by

    Property Management Team on request.

    6.2 Items Delivered and Items Removed

    Materials delivered and removed will be subject to search by the Security Staff. Materials or tools or

    equipment must be signed out of the Site with an authorized signature of the Security through validgate pass duly signed by the authorized signatory.

    6.3 Access to Adjoining Areas

    No access is allowed out of the demised area or on to the property concourse; to adjoining

    areas of the Project; or neighborhood. No access whatsoever is allowed into adjoining areas

    without the prior permission of the neighboring Tenants/Clients Contractor.

    6.4 Protection of Finish Work

    Each Tenant/Client is responsible for the protection of his finished product.

    The Tenants/Clients Contractor will be responsible to maintain the building services clean and capped.

    The Tenants/Clients will provide for access to his leased area/space for inspections by the fit out

    coordination team as the workprogresses.

    6.5 Working Hours

    The Tenants/Clients shall be afforded access to his Space beyond normal working hours by

    permission from Fit out Manager for which they should give advance notice to the Property

    Management Team and additional security required shall be at the cost of Tenant’s/Client’s.

    No lady worker will be allowed to work after normal working hours unless permission is taken

    for the same and lady security guard is made available on the duty.

    No child laborer is permitted to work at any cost and circumstances.

  • 8/18/2019 Fit Out Guidelines

    28/46

     

    3C FACILITY MANAGEMENT

    FIT-OUT GUIDELINES

    28

    6.6 GENERAL SAFETY

    CONTRACTORS AND SUBCONTRACTORS:

    Provide all safety and personal protective equipment (PPE) like hard hats and safety glasses

    etc., required to complete the contracted scope of work. PPE must meet the Standards.

    In the event of an incident, the Tenants/Clients shall ensure that copies of Material Safety

    Data Sheets are immediately available for all products.

    Notify Property Management Team when hot work is to be performed (welding, cutting,

    hazardous activity etc.). Hot Work Permit  (Refer Annexure1) should be obtained and filed

    with Property Management Team. The necessary fire fighting equipments required at site will

    be made available by the Tenants/Clients contractor. Work shall be permitted only in

    presence of accredited engineers/ Supervisors. Property Management will have right to

    terminate the work progress if requirement is not met.

    Work areas should be properly secured and proper signage should be posted to identify PPE

    required at the project site.

    Proper signage like  Men at Work, Hot Work in Progress  etc. should be placed at

    appropriate place.

    The contractors employed by Tenants/Clients will get work executed from only trained and

    qualified tradesmen’s. Specially while working on Electricity, HVAC and Fire fighting works.

    Tenants/clients will have first aid box in their space for all emergency treatments

    PROTECTION OF EMPLOYEES:

    No contractor shall permit a labor/worker to work in close proximity to any part of an electric

    power circuit that the worker could contact the electric power circuit in the course of work,

    unless the worker is protected against electric shock by de-energizing the circuit and

    grounding it or by guarding it effectively by insulation or other means. Contractor will obtain

    line clearance permit from Fitout Manager to work on such electricity live lines.

    In work areas where the exact location of underground electric power lines is unknown,employees using jack-hammers, bars, or other hand tools which may contact a line shall be

    provided with insulated protective gloves.

    Before work is begun the employer shall ascertain by inquiry or direct observation, or by

    instruments, whether any part of an energized electric power circuit, exposed or concealed, is

    so located that the performance of the work may bring any person, tool, or machine into

    physical or electrical contact with the electric power circuit. The contractor shall post and

  • 8/18/2019 Fit Out Guidelines

    29/46

     

    3C FACILITY MANAGEMENT

    FIT-OUT GUIDELINES

    29

    maintain proper warning signs where such a circuit exists. The contractor shall advise workers

    of the location of such lines, the hazards involved, and the protective measures to be taken.

    Fit out contractors are responsible for ensuring that each and every personnel working on

    their site is fully aware of all safety updates.

     All accidents should be immediately notified to Property Management Team.

    Each Tenants/Clients principal contractor will appoint a responsible person to act as a Fire

    Marshall and will be responsible for all

    personnel under his control in the event of an evacuation of the site is warranted.

    Base Building Property Management Team shall have free access to any Tenants/Clients unit

    to inspect and confirm that the rules and regulations are being adhered too for the purposes of

    overall fire control. If management observes that work is not conformity to safety rules

    management will have power to stop work till safety rules are adopted

    PASSAGEWAYS AND OPEN SPACES:

    Barriers or other means of guarding shall be provided to ensure that workspace for electrical

    equipment will not be used as a passageway during the period when energized parts of

    electrical equipment are exposed.

    Working spaces, walkways, and similar locations shall be kept clear of cords in order to keep

    employees away from any type of hazard.

    Proper signage should be placed in the common area and spaces where hazardous work is in

    progress.

    6.7 ELECTRICAL SAFETY

    The use of wet methods increases the chances for electrical shock when an employee is

    working around electrical panels, conduit, light fixtures, alarm systems, junction boxes,

    computers, transformers, etc. It is important for workers to be aware of locations of

    hazards before they resume their work.

    Load ratings: In existing installations, no changes in circuit protection shall be made to

    increase the load in excess of the load rating of the circuit wiring.

    Fuses: When fuses are installed or removed with one or both terminals energized, special

    tools fuse carriers insulated for the voltage shall be used.

    Worn or frayed electric cords or cables shall not be used.

    Extension cords should not be fastened with staples, hung from nails, or suspended by wire.

    De-energize as much equipment as possible. Use portable light systems for lighting.

    Ensure area adjacent to energized electrical equipment is dry, if de-energizing is not feasible.

  • 8/18/2019 Fit Out Guidelines

    30/46

     

    3C FACILITY MANAGEMENT

    FIT-OUT GUIDELINES

    30

      Use nonconductive scrapers and vacuum attachments (wood, plastic, rubber).

    Wear heavy insulated rubber boots and gloves when working around energized wiring.

    Put "hot line" covers over energized cables and power lines.

    Make sure all electrical equipment in use has a Ground Fault Circuit Interrupter (GFCI) before

    the job starts. This means checking outlets, wiring, extension cords, and power pickups.

    Check for the ground pin on plugs.

    Care should be taken not to damage insulated coverings with scrapers, scaffolding wheels,

    etc.

    Do not string electrical wiring across floors.

    Do not allow water to accumulate in puddles on work area floors.

    Ensure electrical outlets on site are tightly sealed and taped to avoid water spray.

     Always perform a pre-work walk-through to identify potential sources of electrical hazards to

    workers, as well as any equipment that may be damaged by wet removal methods.

    Electrical equipment and lines should be considered energized, unless tested and determined

    otherwise.

     Adopt line clearance permit system to de energize/ energize the service lines while working

    on live lines.

    6.8 FALL PROTECTION

    Whenever work takes place at heights there should be an evaluation of the proper methods of

    access and protection from falls. Following are some general guidelines for storage and

    maintenance of fall protection systems:

     Always place your system where it cannot be damaged. Don't throw it in the bottom of the

    toolbox or on the ground. Hang it up.

    Inspect the equipment everyday and any damaged equipment noticed should be removed

    from service immediately.

    Never store equipment near excessive heat, chemicals, fumes or sunlight.

     Avoid dirt buildup. Clean with a mild, nonabrasive soap and hang dry.

    Never use equipment for anything other than a fall arrest system.

    Once exposed to a fall, immediately remove system from service.

    Use ladders of adequate load carrying capacity and ensure that it is jammed on the floor while

    putting on hard surfaces and sand bags while working on smooth and slippery surface.

    Further ensure that telescopic ladders on wheels/towers are not shifted from one point to

    another when men are at work.

    The tradesmen working on high rise scrap folding/ towers will wear safety belts, helmets and

    always will be assisted by trained assistant.

  • 8/18/2019 Fit Out Guidelines

    31/46

     

    3C FACILITY MANAGEMENT

    FIT-OUT GUIDELINES

    31

     6.9 Welding and cutting

    Clogged torch tip openings shall be cleaned with suitable cleaning wires, drills, or other

    devices designed for such purpose.

    Torches in use shall be inspected at the beginning of each working shift for leaking shutoff

    valves, hose couplings, and tip connections. Defective torches shall not be used.

    Torches shall be lighted by friction lighters or other approved devices, and not by match box

    or from hot work.

    Regulators and gauges: Oxygen and fuel gas pressure regulators, including their related

    gauges, shall be in proper working order while in use.

    Oil and grease hazards: Oxygen cylinders and fittings shall be kept away from oil or grease.

    Cylinders, cylinder caps and valves, couplings, regulators, hose, and apparatus shall be kept

    free from oil or greasy substances and shall not be handled with oily hands or gloves.

    6.10 Environmental Constraints

     All Contractors are advised that stringent environmental practices are in force for all works carried out

    on their site. This includes the following:

    Working hours

    Noise level of machines, equipment and operatives

    Vibration

    Dust Control

    Fumes

     Any other environmental hazard

    Tenants/Clients Fit out Contractors must comply with the Base Building Property Management

    directions in all aspects of environmental considerations.

  • 8/18/2019 Fit Out Guidelines

    32/46

     

    3C FACILITY MANAGEMENT

    FIT-OUT GUIDELINES

    32

     6.11 FIRE SAFETY MANAGEMENT

    Tenants/Client’s shall adhere to the fire safety guidelines issued by Base Building Property

    Management time to time.

    Salient guidelines are highlighted as mentioned below:

    Each unit will ensure that fire protection system is placed at site during their fit out time.

    Each unit will be provided with termination of wiring of fire detection system which will be

    further looped by Tenants/Clients contractor as per approved layout.

    Cabling to these units shall have adequate spare cabling to allow detectors to be relocated onto the Licensees false ceilings when fitted.

     An audible alarm should be provided by wall mounted sirens in order to provide clear audibility

    in the event of system activation.

    The Tenants/Clients shall be responsible for the removal of all equipment and cabling whenthe temporary system is no longer required i.e. when the center permanent fire safety systemshave been commissioned.

     Any hoardings etc. must be constructed of noncombustible materials.

    The Fit Out main Contractor must follow and implement the hot works permits system.

    Base Building Property Management Team will carry out periodic site inspections of theTenants/Clients units in order to ensure that the Tenants/Clients are following the site rulesand regulation.

    6.12 Site Security

    Only authorized persons will be allowed to pass through security i.e. persons who have beenproperly inductive and carry an identification pass.

     Any persons not on the approved Contractor list will be denied access to the property, therewould be no exception to this requirement.

    The Contractor’s workers and their belongings can be subjected to scrutiny and inspection bythe appointed security staff of Base Building.

    The Tenants/Clients Fit-out Contractor will be entirely responsible for the internal securityarrangements of their own Fit Out operations.

     Any temporary doors, locks etc. at the Base Building interfaces to be provided by theTenant’s/Client’s fit Out Contractor.

    Base Building Management is not responsible for any loss or damage to the fit-out fitters ortheir agents while on site.

    Base Building Management will have power to break open locks in case of emergency whereendanger to man, material and machinery is involved.

  • 8/18/2019 Fit Out Guidelines

    33/46

     

    3C FACILITY MANAGEMENT

    FIT-OUT GUIDELINES

    33

     

    6.13 Health and Safety

    Each Fit out Contractor is responsible for ensuring that every operator working on their site isfully aware of all safety updates.

     All accidents and dangerous occurrences shall be immediately notified to the ManagementTeam.

    Each Tenants/Clients Principle Contractor will appoint a responsible person to act as FireMarshall and will be responsible for accounting for all personnel under their control in theevent of an evacuation of the site.

    No diesel / petrol engines to be used within the development except at notified places.

    The Property Management team shall have free access to any business associate unit to

    inspect and confirm the rules and regulation are being adhered to for the purposes of overallfire control.

    No smoking/ Chewing of Pan, Gutka is permitted within the confines of the property premises.

    The Property Management at designated locations of common area has provided toilets.Furthermore it is the responsibility of each Tenants/Clients to provide their own welfare andsite facilities as necessary for the staff incl. first aid box.

    6.14 SCHEDULE COORDINATION

    Screeding Operations

    The Tenants/Clients Contractor must start with his Temporary/Permanent power work and his

    screed work, first.

    Screeding materials shall be bagged and delivered to the point of usage. Mixing of water is to

    be carried out in containers at the point of usage. All materials shall always be bagged and

    carried to the leased unit.

    Water must be controlled and no leakage will be allowed to spill out or down from the space.

    In the event of damage to any neighborhood whatsoever, the offending Party will be required

    to reinstate such to its original condition, at his cost.

     All Screeding operations must be completed no later than one month after start but in no case

    later than the agreed schedule of works supplied to the Business Associate coordination

    department.

    The protection against any damage of property, its common areas and surface is the

    responsibility of the Tenants/Clients till his fit-out is completed.

    Electrical & Mechanical Services Terminations

    Tenants/Clients contractor should not connect their various services to main terminal points /

    DB’s till system is verified and cleared for commissioning. Tenants/Clients will inform in writing

    to Fit-out Manager that services are laid and ready for connection. Fit-out Manager in turn will

  • 8/18/2019 Fit Out Guidelines

    34/46

     

    3C FACILITY MANAGEMENT

    FIT-OUT GUIDELINES

    34

    verify status at site and then arrange connection with the liaison of concerned service

    contractor.

    Upon completion of connections, the service contractors of management team will be allowedaccess to leased areas for the purpose of testing & commissioning and balancing of systems

    as may be required and as agreed to Tenant’s/Client’s. The Service Contractors in

    coordination with the Tenants/Clients will program the time frame to tie to the Base Building

    distribution systems in order to limit the interruption of services and to limit the duplication of

    work.

    The Tenants/Clients Contractors are strongly advised to ensure that proper access can be

    gained to all equipment – common or otherwise – in the leased space roof.

    Testing & Inspections

    The Tenants/Clients Contractor will arrange to have his work tested and accepted as required and

    transmit documentation to the Fit-out Manager.

  • 8/18/2019 Fit Out Guidelines

    35/46

     

    3C FACILITY MANAGEMENT

    FIT-OUT GUIDELINES

    35

     

    Do’s and Don’ts

  • 8/18/2019 Fit Out Guidelines

    36/46

     

    3C FACILITY MANAGEMENT

    FIT-OUT GUIDELINES

    36

     7.1 Do’s

    �  Approval for drawings to be obtained from the Base Building Management Team.

    � Obtain the written approval/work order from the Base Building Management team for fit out

    execution commencement.

    � Provide the list of contractors contact details.

    � Comply with all safety regulations of the site.

    � Wear suitable personal protective equipments (PPE’s) as appropriate.

    � Provide adequate barricading of the work location.

    � Obtain appropriate “hot work” permit from the Fit-out Manager before commencement of any

    welding/hot works/hazardous work.

    � Loading and unloading should be done in the designated area only (Refer annexure 5)

    �  All unloading, distribution and material handling to be carried out by the contractor.

    � Goods unloaded should be cleared immediately from common area/staircases.

    � Enter and exit through a designated entrance only.

    �  All works necessitated access to terrace must be requested in advance.

    � Drivers are subject to adhere with normal safety rules and regulation.

    � Vehicles to enter through a designated driveway and up to loading/unloading bay only.

    � Surroundings to be kept clean and clear.

    � Debris generated by the Tenants/Clients should be stored temporarily within their designated

    space and should be cleared immediately.

    � Removal of waste and debris at contractor’s expense.

    � Oxygen and fuel gas pressure regulators should be in proper working pressure.

    � Occupants must comply with all Base Building environmental considerations.

    � Use nonconductive scrapers and vacuum attachments.

    � Heavy insulated rubber boots and gloves should be worn while working around energized wiring.

  • 8/18/2019 Fit Out Guidelines

    37/46

     

    3C FACILITY MANAGEMENT

    FIT-OUT GUIDELINES

    37

    � Electrical equipment in use must have a Ground Fault Circuit Interrupter (GFCI).

    � “Hot Line” covers over energized cables and power lines should be put.

    7.2 Don’ts

    � Don’t work in common area like corridors/lobbies.

    � No disturbance to be caused to the existing circuits and fitments except for extending its length.

    � No staging of trucks or material.

    � No tool or material would be permitted to leave the site without prior authorization/permission.

    � No additions or renovation is to be made to the building exterior.

    � No extension cords to be fastened with staples or hung from nails.

    � No using of worn out electric cords.

    � Don’t leave electric wires loose on floors.

    � Don’t store any equipment near excessive heat.

    � No dirt builds up.

    � No explosive, inflammable or dangerous material to be used.

    � Don’t allow water to accumulate in puddles on work floors areas.

    � No smoking, cooking, chewing of beetle leaves, or consumption of alcohol or drugs permitted.

  • 8/18/2019 Fit Out Guidelines

    38/46

     

    3C FACILITY MANAGEMENT

    FIT-OUT GUIDELINES

    38

     

     Annexure

  • 8/18/2019 Fit Out Guidelines

    39/46

     

    3C FACILITY MANAGEMENT

    FIT-OUT GUIDELINES

    39

     

    8.1 Annexure 1 -HOT WORK PERMIT

    Permit Initiation

    Permit Initiator: Phone:

    Date: Work Start Time: AMPM

    Work Close Time: AMPM

    Location: Equipment:

    Description of Work:

    Pre-Work Job Site Inspection 

    Fit-out Manager Signature: Type of work to be taken up:

    Safety Specialist Signature (if needed): Safety systems made available at site

    Name of Responsible Supervisor detailed to supervise Hot Work

    Property Manager’s Signature for Authorization toProceed:

    Fire Extinguisher (Dry Chemical /CO2)

    Fire Watch Required? (Y/N)

    Special Precautions:

    On Site Job Communication 

    Signature of Person Doing Work: Phone:

    Fit-out Manager Signature:Post Hard Copy At Work Site

    Permit Close-out 

    Job Completed? Y/N

    Job worked hot is now cold Y/ N

    Return Hard Copy to the Property Manager

    Signature of Person Doing Work:

  • 8/18/2019 Fit Out Guidelines

    40/46

     

    3C FACILITY MANAGEMENT

    FIT-OUT GUIDELINES

    40

    8.2 Annexure 2 -ID CARD REQUISITION FORM FOR WORKERS

    Unit No.

    Tenants/Clients

    Name

    Company Name

    Fit Out StartDate

    Contractor

    Name

    Telephone No.

    S.No. Name of Sub-Contractor Contact No.

    Purpose: (i.e. A/C,Electrical, Plumbing,

    Flooring, Carpenter, Civil

    work etc.)

    No. of ID Cards

    to be issued

     ______________________ _____________________

    Fit-out Manager Signature Occupant/Contractor Sign

     ______________________Property Manager Signature

  • 8/18/2019 Fit Out Guidelines

    41/46

     

    3C FACILITY MANAGEMENT

    FIT-OUT GUIDELINES

    41

     

    8.3 Annexure 3 – Tenant/Client Fit Out Forms

    Form – 1(LICENSEE’S INTRODUCTION)

    Unit #: Area: Sq. ft.

    Licensee

    Company:

     Address: Nature of Trade

    City Date of License

    Tel Duration of License

    Fax End of License

    E-Mail

    Representative

    Title

    First Name

    Middle Name

    Last Name

    Fit Out

    Proposed date of Fit out:Commencement:Proposed date step 1 briefing: 

    Landlord Representative: Licensee’s Representative:

    Date: Date:Name Name:

     _________________________ ___________________________Signature: Signature:

    The Licensee must be aware that no information will be given by the shop Fitting Co-ordinationTeam before receiving this filled and signed form.

  • 8/18/2019 Fit Out Guidelines

    42/46

     

    3C FACILITY MANAGEMENT

    FIT-OUT GUIDELINES

    42

     FORM – 2

    (LICENSEE’S CONTACT DETAILS)

    Unit: Company Name:

    Date of License: Duration of License: Fit-out Commencement:

    I. Operation II. Fit-Out Designer

    Title Company:

    First Name: Contact Name

    Middle Name: Address 1:

    Last Name: Address 2:

    Tel.1 (Office) City:

    Tel.2 (Mobile) Country:Tel.3 (Emergency) Telephone:

    Fax: Fax:

    E-Mail: E-mail:

    III. MEP Contractor  

    Contractor Name:

    P.O.Box:

    City

    Country

    Telephone

    Fax

    E-Mail

  • 8/18/2019 Fit Out Guidelines

    43/46

     

    3C FACILITY MANAGEMENT

    FIT-OUT GUIDELINES

    43

    Form – 3(Unit Handover)

    Unit: Handing over date:

    Licensee Schedule date:

    Brand: Relinquishment date:

    Units Description Acceptable  Remarks By Licensee if requiredGeneral Aspect

    Walls

    Ceiling

    Lighting

    Signage

    Windows

    Front Doors

    Back Doors

    Floors

    Fixtures

    MEP

    Water Meter Yes/No Reading:

    Electricity Meter Yes/No Reading:

    Gas Meter Yes/No Reading:

    If Yes, Note the meter numbers under remarks

    If any goods or removable fixtures are to be kept for outstanding purposes. Attach the list signed by both partieson pages. Stored in:_____________________

    If any additional comments attach them & signed by both parties on ____________ pages

    Licensee’s Representative Property Manager

    Name: Name:

    Title: Title:

    Signature: Signature

  • 8/18/2019 Fit Out Guidelines

    44/46

     

    3C FACILITY MANAGEMENT

    FIT-OUT GUIDELINES

    44

    8.4  Annexure 4 -Fit out Commencement Letter

    Name of the Party_ _________________________________________

    Project: ______________________________

    Unit/Premises No.________________ on__________________ floor._____________

    To,

    M/s.

    Sub: Intimation of Commencement of Interior Works in Unit/ Premises No._______.

    Dear Sir,

    We wish to inform you that we would be commencing the Interior Works from _______________________________.

    We have obtained the necessary permission to carry out the Interior Works and a copy of the same is enclosed herewith.

     As per your requirements we are enclosing the list of following agencies / persons with their names and contact numbers,

    who have been engaged by us for Interior Works.

    a. Project Management Consultant

    b. Architects

    c. Contractors1. Civil2. Electrical3. Air-conditioning

    4. Plumbing5. Carpentry6. Signage7. Other (please specify)

    d. Site in-charge.

    We will be solely responsible as principal employer for any legal / financial obligation that may arise due to our InteriorWorks from any Government Authorities and we indemnify you of the same.

    The Interior Works Date of completion is___________________________

    Thanking you.

     __________________________

    Signature of authorized signatory

    Date:

    Note: It is requested to inform ‘Three C FM’ 10 days in advance prior to the start of Interior Works. It is advisable to

    have one start off meeting with all the agencies together with our Property Management team for smooth co-

    ordination of work.

  • 8/18/2019 Fit Out Guidelines

    45/46

     

    3C FACILITY MANAGEMENT

    FIT-OUT GUIDELINES

    45

     

    8.5 Annexure 5 – SITE ACCESS PLAN

  • 8/18/2019 Fit Out Guidelines

    46/46

     

    3C FACILITY MANAGEMENT

    FIT-OUT GUIDELINES

     

    8.6 Annexure 6 ACKNOWLEDGEMENT FORM

    To Date: _______________

     ____________________________________________

     ____________________________________________

    Subject: Fit-out Guidelines Acknowledgment

    Kindly receive and acknowledge the Fit-out Guidelines.

    You are requested to go through the guidelines and brief your Staff/Contractor to follow the same.

    Should you encounter any difficulties with the smooth fit out of your unit, please do not hesitate to contact uson the contact nos. provided in the fit-out manual.

    Office/ Unit No: ________________________________________

    Company Name: ______________________________________

    Name of the representative: ______________________________

    Designation: ___________________________________________

    Email:

    Signatures: __________________________________________