Upload
kenneth-d-pacada
View
218
Download
0
Embed Size (px)
Citation preview
8/6/2019 Finals Ref
http://slidepdf.com/reader/full/finals-ref 1/22
8/6/2019 Finals Ref
http://slidepdf.com/reader/full/finals-ref 2/22
requiring new water to be added to keep the reactor cores covered. Damage has occurred to fuel rods in
the cores where water levels have dropped leaving them uncovered and overheated.
A decay heat output of 7 MW (typical of a Fukushima reactor a few days after shutdown) has
the capacity to boil off about 200-300 tonnes of water per day, which puts the requirement for cooling
water in context.
8/6/2019 Finals Ref
http://slidepdf.com/reader/full/finals-ref 3/22
8/6/2019 Finals Ref
http://slidepdf.com/reader/full/finals-ref 4/22
8/6/2019 Finals Ref
http://slidepdf.com/reader/full/finals-ref 5/22
Releasing gases from the reactor is necessary if pressure becomes too high and has the benefit
of cooling the reactor as water boils off, but this also means cooling water is being lost and must be
replaced. Assuming no damage to the fuel elements, water inside the reactor should be only very
slightly radioactive.
In a press release at 07:00 JST 12 March, TEPCO stated, "Measurement of radioactive material(iodine, etc.) by monitoring car indicates increasing value compared to normal level. One of the
monitoring posts is also indicating higher than normal level." Dose rates recorded on the main gate rose
from 69 nGy/h (for gamma radiation, equivalent to 69 nSv/h) at 04:00 JST, 12 March, to 866 nGy/h
(equivalent to 0.866 µSv/h) 40 minutes later, before hitting a peak of 385.5 Sv/h at 10:30 JST. At 13:30
JST, workers detected radioactive caesium-137 and iodine-131 near reactor 1,
which indicated some of
the core's fuel had been damaged.[91]
Cooling water levels had fallen so much that parts of the nuclear
fuel rods were exposed and partial melting might have occurred. Radiation levels at the site boundary
exceeded the regulatory limits.[94]
On 14 March 2011, radiation levels had continued to increase on the premises, measuring at
02:20 an intensity of 751 Sv/hour on one location and at 02:40 an intensity of 650 Sv/hour at another
location on the premises. On 16 March the maximum readings peaked at 10850 Sv/hour.
Explosion of reactor 1 building
At 15:36 JST on 12 March 2011 there was an explosion at Unit 1. Four workers were injured, and
the upper shell of the reactor building was blown away leaving in place its steel frame. The outer
building is designed to provide ordinary weather protection for the areas inside, but not to withstand
the high pressure of an explosion or to act as containment for the reactor. In the Fukushima I reactors
the primary containment consists of "drywell" and "wetwell" concrete structures immediately
surrounding the reactor pressure vessel.
Experts soon agreed the cause was a hydrogen explosion. Almost certainly the hydrogen was
formed inside the reactor vessel because of falling water levels, and this hydrogen then leaked into the
containment building. Exposed Zircaloy cladded fuel rods became very hot and reacted with steam,
oxidising the alloy, and releasing hydrogen. Safety devices normally burn the generated hydrogen when
it is vented before explosive concentrations are reached but these systems failed, possibly due to the
shortage of electrical power.
Officials indicated the container of the reactor had remained intact and there had been no large
leaks of radioactive material, although an increase in radiation levels was confirmed following the
explosion. ABC News (Australia) reported that according to the Fukushima prefectural government,
radiation dose rates at the plant reached 1015 microsievert per hour (1015 µSv/h). Two independent
nuclear experts cited design differences between theChernobyl Nuclear Power Plant and the Fukushima
I Nuclear Power Plant, one of them saying he did not believe that a Chernobyl-style disaster will occur.
The IAEA stated on 13 March that four workers had been injured by the explosion at the Unit 1 reactor,
and that three injuries were reported in other incidents at the site. They also reported one worker was
8/6/2019 Finals Ref
http://slidepdf.com/reader/full/finals-ref 6/22
exposed to higher-than-normal radiation levels but that fell below their guidance for emergency
situations.
Seawater used for cooling
At 20:05 on 12 March 2011, under the terms of the Nuclear Regulation Act, paragraph 3, article
64 and a directive issued by the Prime Minister, the Japanese government ordered seawater to be
injected into Unit 1 in an ultimate effort to cool the degraded reactor core. At 21:00 JST TEPCO
announced they planned to cool the reactor with seawater (started at 20:20 JST), adding boric acid to
act as a neutron absorber to prevent a criticality accident. The water was to take five to ten hours to fill
the reactor core, after which the reactor would cool down in around ten days. At 23:00 JST TEPCO
announced due to the quake at 22:15, workers had temporarily suspended filling of the reactor but
filling resumed after a short while. The last resort decision to use seawater as coolant in the reactor
implied the reactor would have to be decommissioned because of contamination by salt and other
impurities.
NISA reported that injection of seawater into the Reactor Pressure Vessel through the fire
extinguisher system commenced at 11:55 on 13 March, though this was corrected to state 12 March in
later press releases. Some reports refer to injection into the Primary Containment Vessel and exact
details are confused. At 01:10 on 14 March injection of seawater was halted because all available water
in the plant pools had run out (similarly, feed to unit 3 was halted). Water supply was restored at 03:20.
NISA stated 70% of the fuel rods were damaged in news reports the morning of 16 March.
On 18 March work was proceeding to install a new electrical distribution panel in an office
adjacent to unit 1 which was to supply power from a transmission grid transformer at unit 2. It was
anticipated power would be restored to units 1 and 2 by the following Saturday (19 March). Power
became available at unit 2 on 20 March As of 21 March injection of sea water for cooling was continuing
but the unit seemed to be in a stable conditon. Repairs to restore control instrumentation were
proceeding. On 23 March it became possible to inject water into the reactor using the feed water system
rather than the fire extinguisher line, raising the rate of adding seawater from 2m3/hr to18m
3/hr, later
lowered to 11m3/hr.
8/6/2019 Finals Ref
http://slidepdf.com/reader/full/finals-ref 7/22
REACTOR UNIT 2
Unit two was operating at the time of the earthquake and experienced the same controlled
initial shutdown as the other units. Diesel generators and other systems failed when the tsunami
overran the plant. Reactor core isolation cooling system (RCIC) initially operated to cool the core but by
midnight the status of the reactor was unclear although some monitoring equipment was still operatingon temporary power. Coolant level was stable, but preparations were underway to reduce pressure in
the reactor containment vessel should this become necessary, though TEPCO did not state in press
releases what these were, and the government had been advised that this might happen. RCIC was
reported by TEPCO shut down around 19:00 JST on 12 March, but again reported to be operating as of
09:00 JST 13 March. Pressure reduction of the reactor containment vessel commenced before midnight
on 12 March though IAEA reported as of 13:15 JST 14 March that according to information supplied to
them, no venting had taken place at the plant. A report in the New York Times suggested that plant
officials initially concentrated efforts on a damaged fuel storage pool at unit 2, distracting attention
from problems arising at the other reactors, but this incident is not reported in official press
releases. IAEA report that on 14 March at 09:30 RCIC was still operating and that power was beingprovided by mobile generator.
Cooling problems at unit 2
On 14 Mar TEPCO reported the failure of the RCIC system. Fuel rods had been fully exposed for
140 minutes and there was a risk of a core meltdown. Reactor water level indicators were reported to
be showing minimum values at 19:30 JST 14 March.
At 22:29 JST, workers had succeeded in refilling half the reactor with water but parts of the rods
were still exposed, and technicians could not rule out the possibility that some had melted. Holes blown
in the walls of reactor building 2 by the earlier blast from unit 3 would allow the escape of hydrogenvented from the reactor and hopefully prevent a similar explosion. At 21:37 JST the measured dose
rates at the gate of the plant reached a maximum of 3.13 millisievert per hour, which was enough to
reach the annual limit for non-nuclear workers in twenty minutes,[122]
but had fallen back to 0.326
millisieverts per hour by 22:35.
It was believed that around 23:00 JST the 4 m long fuel rods in the reactor were fully exposed
for the second time. At 00:30 JST of 15 March, NHK ran a live press conference with TEPCO stating that
the water level had sunk under the rods once again and pressure in the vessel was raised. The utility said
that the hydrogen explosion at unit 3 might have caused a glitch in the cooling system of unit 2: Four out
of five water pumps being used to cool unit 2 reactor had failed after the explosion at unit 3. In addition,
the last pump had briefly stopped working when fuel ran out. To replenish the water, the contained
pressure would have to be lowered first by opening a valve of the vessel. The unit's air flow gauge was
accidentally turned off and, with the gauge turned off, flow of water into the reactor was blocked
leading to full exposure of the rods.
As of 04:11 JST, 15 March, water was being pumped into the reactor of unit 2 again. At 10:38
JST, 15 March, water level was reported to be at 1.20 meters and rising.
8/6/2019 Finals Ref
http://slidepdf.com/reader/full/finals-ref 8/22
Explosion in reactor 2 building
An explosion was heard after 06:14 JST on 15 March in unit 2, possibly damaging the pressure-
suppression system, which is at the bottom part of the containment vessel.[131][132] The radiation level
was reported to exceed the legal limit and the plant's operator started to evacuate all non-essential
workers from the plant. Only a minimum crew of 50 men, also referred to as the Fukushima 50, was leftat the site. Soon after, radiation equivalent dose rates had risen to 8.2 mSv/h around two hours after
the explosion and again down to 2.4 mSv/h, shortly after. Three hours after the explosion, the rates had
risen to 11.9 mSv/h.
While admitting that the suppression pool at the bottom of the containment vessel had been
damaged in the explosion, causing a drop of pressure there, Japanese nuclear authorities emphasized
that the containment had not been breached as a result of the explosion and contained no obvious
holes.
In a news conference on 15 March the director general of the IAEA, Yukiya Amano, said that
there was a "possibility of core damage" at the No. 2 unit of the damaged Fukushima power plant. He
went on to add that the damage was estimated as being "less than five percent".[139] The Nuclear and
Industrial Safety Agency stated 33% of the fuel rods were damaged, in news reports the morning of 16
March.
Work
Work was to continue through the night aimed at reconnecting mains power to the reactor from
the transmission grid once water spraying of unit 3 ceased at 20:09 on 17 March. By midday on 19
March grid power had been connected to the existing transformer at unit 2 but work continued to
connect the transformer to the new distribution panel installed in a nearby building. Mains electricity
became available at unit 2 at 15:46 JST on 20 March but equipment still had to be repaired and
reconnected.
Spent fuel pool
40 tonnes of sea water was added to the spent fuel pool on 20 March. The temperature in the
spent fuel pool was 53 °C as of 22 March 11:00 JST.[57]
8/6/2019 Finals Ref
http://slidepdf.com/reader/full/finals-ref 9/22
REACTOR UNIT 3
Unlike the other five reactor units, reactor 3 runs on mixed uranium and plutonium oxide,
or MOX fuel, making it potentially more dangerous in an incident due to the neutronic effects of
plutonium on the reactor, the very long half-life of plutonium's radioactivity, and
the carcinogenic effects
in the event of release to the environment. Units 3 and 4 have a shared controlroom.
Cooling problems at unit 3
Early on 13 March 2011, an official of the Japan Nuclear and Industrial Safety Agency told a
news conference that the emergency cooling system of Unit 3 had failed, spurring an urgent search for a
means to supply cooling water to the reactor vessel in order to prevent a meltdown of its reactor
core. At 05:38 there was no means of adding coolant to the reactor due to loss of power. Work to
restore power and vent pressure continued. At one point, the top three meters of mixed oxide (MOX)
fuel rods were not covered by coolant.
At 07:30 JST, TEPCO prepared to release radioactive steam, indicating that "the amount of
radiation to be released would be small and not of a level that would affect human health"[149]
and
manual venting took place at 08:41 and 09:20. At 09:25 JST on 13 March 2011, operators began injecting
water containing boric acid into the primary containment vessel (PCV) via a fire pump. When water
levels continued to fall and pressure to rise, the injected water was switched to sea water at 13:12. By
15:00 it was noted that despite adding water the level in the reactor did not rise and radiation had
increased. A rise was eventually recorded but the level stuck at 2 m below the top of reactor core. Other
readings suggested that this could not be the case and the gauge was malfunctioning.
Injection of sea water into the PCV was discontinued at 01:10 on 14 March because all the water
in the reserve pool had been used up. Supplies were restored by 03:20 and injection of water
resumed.[152] On the morning of 15 March 2011 (JST), Secretary Edano announced that according to the
TEPCO, at one location near reactor units 3 and 4, radiation at an equivalent dose rate of 400 mSv/h was
detected. This might have been due to debris from the explosion in unit 4.
Explosion of reactor 3 building
At 12:33 JST on 13 March 2011, the chief spokesman of the Japanese government, Yukio Edano
said hydrogen was building up inside the outer building of Unit 3 just as had occurred in Unit 1,
threatening the same kind of explosion. At 11:15 JST on 14 March 2011, the envisaged explosion of the
building surrounding reactor 3 of Fukushima 1 occurred, due to the ignition of built up hydrogengas. The Nuclear and Industrial Safety Agency of Japan reported, as with Unit 1, the top section of the
reactor building was blown apart, but the inner containment vessel was not breached. The explosion
was larger than that in Unit 1 and felt 40 kilometers away. Pressure readings within the reactor
remained steady at around 380 kPa at 11:13 and 360 kPa at 11:55 compared to nominal levels of
400 kPa and a maximum recorded of 840 kPa. Water injection continued. Dose rates of 0.05 mSv//h
8/6/2019 Finals Ref
http://slidepdf.com/reader/full/finals-ref 10/22
were recorded in the service hall and of 0.02 mSv/h at the plant entrance. Eleven people were reported
injured in the blast.
Spent fuel pool
Around 10:00 JST, 16 March, NHK helicopters flying 30 km away videotaped white fumes rising
from the Fukushima I facility. Officials suggested that the reactor 3 building was the most likely source,
and said that its containment systems may have been breached. The control room for reactors 3 and 4
was evacuated at 10:45 JST but staff were cleared to return and resume water injection into the reactor
at 11:30 JST. At 16:12 JST Self Defence Force (SDF) Chinook helicopters were preparing to pour water on
unit 3, where white fumes rising from the building was believed to be water boiling away from the fuel
rod cooling pond on the top floor of the reactor building, and on unit 4 where the cooling pool was also
short of water. The mission was cancelled when helicopter measurements reported radiation levels of
50 mSv. At 21:06 pm JST government reported that major damage to reactor 3 was unlikely but that it
nonetheless remained their highest priority.
Early on 17 March, TEPCO requested another attempt by the military to put water on the
reactor using a helicopter and four helicopter drops of seawater took place around 10:00 JST. The riot
police used a water cannon to spray water onto the top of the reactor building and then were replaced
by members of the SDF with spray vehicles. On 18 March a crew of firemen took over the task with six
fire engines each spraying 6 tons of water in 40 minutes. 30 further hyper rescue vehicles were involved
in spraying operations. Spraying continued each day to 23 March because of concerns the explosion in
unit 3 may have damaged the pool (total 3,742 tonnes of water sprayed up to 22 March) with changing
crews to minimise radiation exposure. Lighting in the control room was restored on 22 March after a
connection was made to a new grid power supply and by 24 March it was possible to add 35 tonnes of
seawater to the spent fuel pool using the cooling and purification system.
Ongoing Emissions
Grey smoke was reported to be rising from the southeast corner of reactor 3 on Monday
afternoon, 21 March 2011. The spent fuel pool is located at this part of the building. Workers were
evacuated from the area. Later measurements showed no significant change in radiation levels and the
smoke subsided later on the same day.
Per AP reports on Wed, 23 March, black smoke billowed from Unit 3, prompting another
evacuation of workers from the plant Wednesday afternoon, Tokyo Electric Power Co. officials said, but
they said there had been no corresponding spike in radiation at the plant. "We don't know the reason
for the smoke", Hidehiko Nishiyama of the Nuclear Safety Agency said.
8/6/2019 Finals Ref
http://slidepdf.com/reader/full/finals-ref 11/22
REACTOR UNIT 4
At the time of the earthquake unit 4 had been shut down for a scheduled periodic inspection
since 30 November 2010. All 548 fuel rods had been transferred in December 2010 from the reactor to
thespent fuel pool on an upper floor of the reactor building where they were held in racks containing
boron to damp down any nuclear reaction. The pool is used to store rods for some time after removalfrom the reactor and now contains 1,479 rods. Recently active fuel rods produce more decay heat than
older ones. At 04:00 JST on Monday 14 March, water in the pool had reached a temperature of 84 °C
compared to a normal value of 4050 °C. IAEA was advised that the temperature value remained 84 °C
at 19:00 JST on 15 March, but as of 18 March, no further information was reported.
Explosion of reactor 4 building
At approximately 06:00 JST on 15 March, an explosionthought to have been caused by
hydrogen accumulating near the spent fuel ponddamaged the 4th floor rooftop area of the Unit 4
reactor as well as part of the adjacent Unit 3. At 09:40 JST, the Unit 4 spent fuel pool caught fire, likely
releasing radioactive contamination from the fuel stored there. TEPCO said workers extinguished the
fire by 12:00. As radiation levels rose, some of the employees still at the plant were evacuated.
On the morning of 15 March 2011 (JST), Secretary Edano announced that according to the Tokyo
Electric Power Company, radiation dose equivalent rates measured from the reactor unit 4 reached 100
mSv per hour. Government speaker Edano has stated that there was no continued release of "high
radiation".
Japan's nuclear safety agency reported two holes, each 8 meters square (64 m2 or 689 sq. feet)
in a wall of the outer building of the number 4 reactor after an explosion there. Further, at 17:48 JST it
was reported that water in the spent fuel pool might be boiling.
As of 15 March 2011 21:13 JST, radiation inside unit 4 had increased so much inside the control
room that employees could not stay there permanently any more. Seventy staff remained on site but
800 had been evacuated. By 22:30 JST, TEPCO was reported to be unable to pour water into No. 4
reactor's storage pool for spent fuel. At around 22:50 JST, it was reported that the company was
considering the use of helicopters to drop water on the spent fuel storage pool but this was postponed
because of concerns over safety and effectiveness. and the use of high-pressure fire hoses was
considered instead.
A fire was discovered at 05:45 JST on 16 March in the north west corner of the reactor building
by a worker taking batteries to the central control room of unit 4. This was reported to the authorities,but on further inspection at 06:15 no fire was found. Other reports stated that the fire was under
control. At 11:57 JST, TEPCO released a photograph of No.4 reactor showing that "a large portion of the
building's outer wall has collapsed." Technicians reportedly considered spraying boric acid on the
building from a helicopter.
On 18 March, it was reported that water sprayed into the spent fuel pool was disappearing
faster than evaporation could explain, suggesting leakage.
8/6/2019 Finals Ref
http://slidepdf.com/reader/full/finals-ref 12/22
SDF trucks sprayed water onto the building to try to replenish the pool on 20 March.
On 22 March, the Australian military flew in Bechtel-owned robotic equipment for remote
spraying and viewing of the pool. The Australian reported this would give the first clear view of the pool
in the "most dangerous" of the reactor buildings.
Possibility of criticality in the spent fuel pool
At approximately 14:30 on 16 March, TEPCO announced that the storage pool, located outside
the containment area, might be boiling, and if so the exposed rods could reach criticality. The BBC
commented that criticality would not mean a nuclear bomb-like explosion, but could cause a sustained
release of radioactive materials. Around 20:00 JST it was planned to use a police water cannon to spray
water on unit 4.
On 16 March the chairman of United States Nuclear Regulatory Commission (NRC), Gregory
Jaczko, said in Congressional testimony that the NRC believed all of the water in the spent fuel pool had
boiled dry. Japanese nuclear authorities and TEPCO contradicted this report, but later in the day Jaczkostood by his claim saying it had been confirmed by sources in Japan. At 13:00 TEPCO claimed that
helicopter observation indicated that the pool had not boiled off. The French Institut de radioprotection
et de sûreté nucléaire agreed, stating that helicopter crews diverted planned water dumps to unit 3 on
the basis of their visual inspection of unit 4.
On 18 March, Japan was reportedly planning to import about 150 tons of boric acid, a neutron
poison, from South Korea and France to counter the threat of criticality.
On 23 March it was reported that low level Neutron radiation (reported as "neutron beam") was
observed several times, which may indicate damaged fuel reaching criticality somewhere at the plant.
8/6/2019 Finals Ref
http://slidepdf.com/reader/full/finals-ref 13/22
REACTOR UNIT 5 AND 6
Both reactors were off line at the time the earthquake struck (reactor 5 had been shut down on
3 January 2011 and reactor 6 on 14 August 2010), although they were still fueled, unlike reactor 4 where
the fuel rods had been removed prior to the earthquake.
Government spokesman Edano stated on 15 March that reactors 5 and 6 were being closely
monitored, as cooling processes were not functioning well. At 09:16 JST the removal of roof panels from
reactor buildings 5 and 6 was being considered in order to allow any hydrogen build-up to escape. At
21:00 on 15 March, water levels in unit 5 were reported to be 2 m above fuel rods, but were falling at a
rate of 8 cm per hour.
On 17 March, Unit 6 was reported to have operational diesel-generated power and this was to
be used to power pumps in unit 5 to run the Makeup Water Condensate System (MUWC) to supply
more water. Preparations were made to inject water into the reactor pressure vessel once mains power
could be restored to the plant, as water levels in the reactors were said to be declining. It was estimated
that grid power might be restored on 20 March through cables laid from a new temporary supply being
constructed at units 1 and 2.
Information provided to the IAEA indicated that storage pool temperatures at both units 5 and 6
remained steady around 6068 °C between 19:00 JST 14 March and 21:00 JST 18 March, though rising
slowly. On 18 March reactor water levels remained around 2m above the top of fuel rods. It was
confirmed that panels had been removed from the roofs of units 5 and 6 to allow any hydrogen gas to
escape. At 04:22 on 19 March the second unit of emergency generator A for unit 6 was restarted which
allowed operation of pump C of the residual heat removal system (RHR) in unit 5 to cool the spent fuel
storage pool. Later in the day pump B in unit 6 was also restarted to allow cooling of the spent fuel pool
there. Temperature at unit 5 pool decreased to 48 °C on 19 March 18:00 JST, and 37 °C on 20 Marchwhen unit 6 pool temperature had fallen to 41 °C. On 20 March NISA announced that both reactors had
been returned to a condition of cold shutdown. External power was partially restored to unit 5 via
transformers at unit 6 connected to the Yonoromi power transmission line on 21 March.
On 23rd March, it was reported that the cooling pump at reactor No 5 stopped working when it
was transferred from backup power to the grid supply.
Used fuel assemblies taken from reactors are initially stored for at least 18 months in the pools adjacent
to their reactors. They can then be transferred to the central fuel storage pond. This contains 6375 fuel
assemblies and was reported 'secured' with a temperature of 55 °C. After further cooling, fuel can be
transferred to dry cask storage, which has shown no signs of abnormalities. On 21 March temperatures
in the fuel pond had risen a little to 61 °C and water was sprayed over the pool.
8/6/2019 Finals Ref
http://slidepdf.com/reader/full/finals-ref 14/22
REACTOR STATUS SUMMARY
The Japan Atomic Industrial Forum (JAIF) has developed a status summary table for the Fukushima
nuclear power plants and is publishing updates twice each day.
Legend
No immediate concern Concern Severe Condition
Status of
Fukushima I at
23 March 21:00
JST (23 March
12:00 UTC)[226]
Unit 1 Unit 2 Unit 3 Unit 4 Unit 5 Unit 6
Power output(MWe)
460 784 784 784 784 1,100
Type of reactor BWR-3 BWR-4 BWR-4 BWR-4 BWR-4 BWR-5
Core fuel
assemblies[228] 400 548 548 0
[170]548 764
Spent fuel
assemblies[170]
292 587 514 1,331 946 876
Spent fuel
residual decay
heat[229][230]
60 kW 400 kW 200 kW 2,000 kW 700 kW 600 kW
Fuel typeLow-enriched
uranium
Low-enriched
uranium
Mixed-oxide
(MOX) and
low-enriched
uranium
Low-enriched
uranium
Low-
enriched
uranium
Low-
enriched
uranium
Status at
earthquakeIn service In service In service
Outage
(scheduled)
Outage(scheduled
)
Outage(schedule
d)
Fuel integrity Damaged Damaged DamagedSpent fuel
damaged
Not
damaged
Not
damaged
8/6/2019 Finals Ref
http://slidepdf.com/reader/full/finals-ref 15/22
Reactor
pressure
vesselintegrity
Unknown Unknown UnknownNot damaged
(defueled)
Not
damaged
Not
damaged
Containment
integrity Not damaged
Damage
suspected Not Damaged Not damaged
Not
damaged
Not
damaged
Core cooling
system 1
(ECCS/RHR)
Not functional Not functional Not functionalNot necessary
(defueled)Functional
Functiona
l
Core cooling
system 2
(RCIC/MUWC)
Not functional Not functional Not functionalNot necessary
(defueled)
Functional
(in cold
shutdown)
Functiona
l (in cold
shutdown
)
Building
integrity
Severely
damaged
Slightly
damaged, also
panel removed
to prevent
hydrogen
explosion
Severely
damaged
Severely
damaged
Panel
removed
to prevent
hydrogen
explosion
Panel
removed
to
prevent
hydrogen
explosion
Pressure
vessel, water
level
Fuel exposed
partially or
fully
Fuel exposed
partially or
fully
Fuel exposed
partially or
fully
Safe (defueled)
Safe (in
cold
shutdown)
Safe (in
coldshutdown
)
Pressure
vessel,
pressure
Stable Unknown Unknown Safe (defueled)
Safe (in
cold
shutdown)
Safe (in
cold
shutdown
)
Containment
pressure
Stable Stable Decreasing Safe Safe Safe
Seawater
injection into
core
Continuing Continuing ContinuingNot necessary
(defueled)
Not
necessary
Not
necessary
8/6/2019 Finals Ref
http://slidepdf.com/reader/full/finals-ref 16/22
Seawater
injection into
containment
vessel
ContinuingPerformed 19
March[231]
Continuing Not necessary
Not
necessary
Not
necessary
Containment
venting
Temporarily
stopped
Temporarily
stopped
Temporarily
stoppedNot necessary
Not
necessary
Not
necessary
INES Level 5 Level 5 Level 5 Level 3
Environmental
effect
Main Gate: 265.4 Sv/hour at 23 March 15:00; North of Service Building:
2015.0 Sv/hour at 21 March 16:30. Radionuclides were detected in milk produced in
Fukushima and Ibaraki prefectures and spinach and other vegetables from Fukushima,
Ibaraki, and other prefectures.[232] Radioactive Iodine-131 has been found in tap water
in Fukushima prefecture, and radioactive Iodine-131, Caesium-134, and Caesium-137 have been detected in seawater samples in the vicinity of the station.
Evacuation radi
us
20 km from Nuclear Power Station (NPS). People who live between 20 km to 30 km
from the Fukushima I Nuclear Power Station are to stay indoors.
General status
from all
sources
regardingreactor cores
Stabilized by
injecting sea
water and
boron[233]
Stabilized by
injecting sea
water and
boron[233]
Stabilized by
injecting sea
water and
boron;
pressureelevated on 20
March[233]
Defueled
Cold
shutdown
on 20
March
14:30
JST[51][233]
Cold
shutdown
on 20
March
19:27
JST[51][233]
General status
from all
sources
regarding Spen
t Fuel
Pools (SFP)
Water
injection
considered, 60
°C on 20
March byinfrared
helicopter
measurement[
234]
Water
injection
concluded on
20
March,[51]
40
°C on 20March by
infrared
helicopter
measurement[
234]
Water level
low, sprayed
water injection
continues, 60
°C on 20
March by
infrared
helicopter
measurement[
234]
Water level
low, sprayed
water injection
continues after
hydrogen
explosion from
pool, 40 °C on
20 March by
infrared
helicopter
measurement[
234]
Cooling
system
restored,
39.0 °C on
23 March
12:00
JST[235]
Cooling
system
restored,
20.0 °C on
23 March
12:00
JST[235]
8/6/2019 Finals Ref
http://slidepdf.com/reader/full/finals-ref 17/22
As of 18 March 2011, the French nuclear authorityand as of 15 March 2011, the Finnish nuclear
authorityestimate the unfolding crisis at Fukushima to be a Level 6 on the INES.
USA, Australia and Sweden have instructed their citizens to evacuate a radius of minimum 80 km. Spain
has advised their citizens to leave an area of 120 km, Germany has advised their citizens to leave even
the metropolitan area of Tokyo, and South Korea advises to leave farther than 80 km and to have plansto evacuate by all possible means. Travel to Japan is very low, but additional flights have been chartered
by some countries to assist those who wish to leave. Official evacuation of Japan have been started by
several nations.
SOLUTIONS CONSIDERED OR ATTEMPTED
Legend
Effective Partiallyeffective
Noteffective
Not applicable or unknown
Solution General effectiveness
Specific effectiveness
Reactor
cores
Spent fuel
pools
1 2 3 4 5 6 1 2 3 4 5 6
Backup diesel generators:
The backup diesel generators
operated initially.
All generators disabled by the
tsunami. One generator repaired 17
March at units 5 and 6 to cool spent
fuel pools. A second on 19 March
powered reactor cooling and
reactors 5 and 6 were brought back
to cold shutdown.
Backup batteries:
The backup batteries maintained
some control functions and limited
cooling for 8 hours after the
Effective but only designed to work
for 8 hours. The operators were
unable to connect portable
generators before the 8 hours ran
out. However limited cooling was
not designed to stabilise reactors
8/6/2019 Finals Ref
http://slidepdf.com/reader/full/finals-ref 18/22
generators failed. indefinitely even if batteries were
recharged.
Mobile power units:
After the power loss due to the
earthquake and tsunami, mobile
power units were sent to the plant.
Flooding of plant prevented mobile
generators being connected andsufficiently large units were not
available
Some central monitoring
systems
Repair power lines to provide
electricity:
1 km of new grid cable and
replacement switchgear wasinstalled to provide power to plant.
Power was connected to the
distribution panels of Units 2 and 5
on Sunday 20 March and power is
now available to Units 1, 2, 5 and
6 but only equipment in units 5 and
6 is sufficiently repaired to function.
Units 3 and 4 are scheduled to have
electricity connected to their
distribution panels on 22 March.
Central control room
Emergency cooling systems:
The Emergency Core Cooling System
(ECCS) includes: High Pressure
Coolant Injection System (HPCI),
Reactor Core Isolation Cooling
System (RCIC), Automatic
Depressurization System (ADS), Low
Pressure Core Spray System (LPCS),
Low Pressure Coolant Injection
System (LPCI), Depressurization
Valve System (DPVS), Passive
Containment Cooling System (PCCS),
and Gravity Driven Cooling System
(GDCS).
The RCIC operated initially and the
HPCI worked until the toruses
overheated. Cooling systems were
restored to Units 5 and 6 on 20
March. BBC news reported on 17
March, that some of the original
water pumps might be inoperable
due to damage from injected sea
water, the earthquake, tsunami or
explosions.
Cooling core containment areas by
adding sea water:
Sea water with neutron absorbing
boric acid is being manually injected
into the Reactor Pressure Vessel of
Sea water cooling has been partially
effective for the cooling reactor
core but fuel damage has taken
place. At one point available water
in site pools ran out. White smoke
or steam was reported rising from
8/6/2019 Finals Ref
http://slidepdf.com/reader/full/finals-ref 19/22
units 1, 2 and 3 via fire extinguisher
system line.
Unit 3.
Spraying water into spent fuel pools
with water cannon and fire engines:
Police, military and firemen working
in shifts to reduce radiation exposure
used water cannons and fire engines
to spray water onto the roofs and
into the spent fuel pools of reactor
unit Number 3 although it is unclearif any water reached the spent fuel
pool. Unit 4 was sprayed also.
SFP 1: As of Saturday 19 March, SFP
1's decrease in water level suggests
it may have a leak and spraying may
be attempted. SFP was 60 °C on 20
March according to an infrared
helicopter measurement.
SFP 2: On 20 March, 40 tons of sea
water was sprayed into unit 2. SFP
was 40 °C on 20 March according to
an infrared helicopter
measurement. Spraying appeared
to have been effective even though
the building is nearly intact and
there were few holes to spray water
into.
SFP 3: On Thursday 17 March,
steam emanated from the roof of
unit 3 after spraying which
suggested that spraying was at least
partially successful in reaching
overheated spent fuelrods. Radiation levels dropped
slightly after the steam had
dissipated suggesting the cooling
may have been successful. SFP 3
may have a leak and reduced water
holding capacity due to a previous
explosion. SFP 3 was sprayed for 13
hours on 20 March using unmanned
vehicles and spraying is continuing.
SFP was 60 °C on 20 March
according to an infrared helicopter
measurement.
Water in SFP 4 was disappearing
faster than evaporation could
explain and some suspected that a
8/6/2019 Finals Ref
http://slidepdf.com/reader/full/finals-ref 20/22
hole was leaking water from that
pool.
However, inspection during
helicopter water drops indicated
there was water in the pool of Unit
4; so, spraying on Friday 18 March
focused on Unit 3. SFP 4 stopped
boiling although it is releasing a
large amount of heat due to the
large amount of fuel stored there.
On Sunday 20 March, SFP 4 was
sprayed with 100 tons of water
using unmanned vehicles. SFP was
40 °C on 20 March according to an
infrared helicopter measurement.
Helicopter dumping of sea water into
spent fuel pools:
Helicopters used for forest fire
suppression dumped sea water onto
the reactors.
Strong winds prevented effective
targeting of the dumped water since
high radiation levels prevented the
helicopters from flying low. Video
appeared to show much of the
water dispersing in mid-air
weakening the intensity of the
water to cool the overheating
reactor.
Boron:
Officials have considered insertion or
targeted aerial dropping of boric
acid, boronated plastic beads or
boron carbide pellets into the spent
fuel pools to absorb neutrons.
France is flying 95 tonnes of boron
to Japan on Thursday, 17 March
2011. Neutron absorbing boric acid
is being injected into the reactor
cores with the sea water but it is
unclear if boric acid is included with
the spraying of SFPs. Effectiveness
unknown.
Liquid metal cooling:
On 17 March, KyivPost reported that
a Ukrainian group of specialists who
were involved in the aftermath of
the Chernobyl nuclear
disaster proposed low-melting and
This solution has similarities withthe 2400 metric tonnes of lead (see
alsoLead-cooled fast reactor ) used
to successfully cool and cover
the Chernobyl nuclear plant but
avoids the toxic lead. Liquid metal
cooled reactors were used in
8/6/2019 Finals Ref
http://slidepdf.com/reader/full/finals-ref 21/22
chemically neutral metal, such as tin,
to cool the fuel rods even if molten
or damaged. [267]
Chopped tin can be injected in the
reactor through the existing cooling
water pipes with compressed inert
gas, helium or argon. Melted tin
creates a crust (low vapor pressure),
cools the reactor and delays
the decay productsrecovery. Liquid
metal cooled reactors need no pump
and due to no pressure and a wider
temperature-range are less likely to
a Loss-of-coolant accident.
several Soviet submarines which
shows additional basic feasibility.
It also avoids the danger of
additional explosions caused by
water breaking down to hydrogen
and oxygen starting at temperatures
around 800 °C due toThermolysis.
A team of Ukrainian nuclear
specialists is ready to fly out for
realizing this in practice. The
Japanese Embassy was informed.
"Sarcophagus":
On 18 March, Reuters reportedthat
Hidehiko Nishiyama, Japan's nuclear
agency spokesman when asked
about burying the reactors in sand
and concrete, said: "That solution is
in the back of our minds, but we are
focused on cooling the reactors
down."
1800 metric tonnes of sand and clay
used after the Chernobyl disaster
were counter-productive, acting
as thermal insulators and
accumulating heat.
So first a non-evaporating coolant
like liquid (and minimum surface-
frozen) metal has to be applied, and
after temperature has decreased,a sarcophagus.
8/6/2019 Finals Ref
http://slidepdf.com/reader/full/finals-ref 22/22
NEW ERA UNIVERSITYCOLLEGE OF ENGINEERING AND TECHMOLOGY
MECHANICAL ENGINEERING DEPARTMENT
Fukushima Nuclear Power Plant(FINAL EXAM ± ME481)
Kenneth D. Pacada
BSME / 4th Year
0710375
Engr. Nelio S. Gesmundo Jr.Instructor