Imagine the resul t Allied Paper, Inc./Portage Creek/ Kalamazoo River Superfund Site Plainwell No. 2 Dam Area Time-Critical Removal Action Final Construction Completion Report Georgia-Pacific LLC February 2011
Report Template w/Numbered HeadingsFinal Construction Completion
Report
Prepared for:
Georgia-Pacific LLC
Prepared by:
ARCADIS G&M of Michigan, LLC 10559 Citation Drive Suite 100
Brighton Michigan 48116 Tel 810.229.8594 Fax 810.229.8837
Our Ref.:
B0064536.0002.00675
Date:
February 25, 2011 This document is intended only for the use of the
individual or entity for which it was prepared and may contain
information that is privileged, confidential and exempt from
disclosure under applicable law. Any dissemination, distribution or
copying of this document is strictly prohibited.
Stephen Garbaciak Jr., P.E. Vice President Michael J. Erickson,
P.E. SRI/FS Project Coordinator
Table of Contents
1. Introduction 1-1
1.1 General 1-1
1.2 Project Area Description 1-2
1.3 Overview of Response Actions and Summary of Work
Performed 1-3
1.4 Scope of the Completion Report 1-5
1.5 Report Organization 1-6
2. Project Overview 2-1
2.1 Project Organization 2-1
2.3 Deviations from the Design Report 2-3
2.3.1 Backfilling of Excavated Areas 2-3
2.3.2 Removal Area 5 2-4
2.3.3 Habitat Reconstruction Plant Species 2-4
2.3.4 Oxbow Removal 2-5
2.3.4.2 Removal Footprint 2-6
3. Removal Activities 3-1
3.2.2 Permitting 3-2
3.2.5 Mobilization and Project Area Preparation
3-3
3.2.5.1 Access Road Construction 3-4
3.2.5.2 Staging Area Construction 3-5
3.2.5.3 Installation of Erosion Controls 3-6
G:\Aproject\Kalamazoo\Plainwell #2\B0064536\00675\Final
Construction Completion Report\Plainwell 2 TCRA Final Construction
Completion Report.doc i Project Number: B0064536.00675
Table of Contents
3.3.1 Turbidity Curtains 3-7
3.3.3.1 Turbidity Monitoring 3-8
3.4 Soil and Sediment Removal 3-11
3.4.1 Excavation Confirmation 3-12
3.4.1.2 Confirmation Sampling 3-14
3.4.2 Removal Areas 3-14
3.4.2.3 Island Removal Areas 3-17
3.4.2.4 Confirmation Sampling Surveying and Analytical Data
3-17
3.4.3 2009 Removal Activities 3-17
3.4.3.1 Clearing and Grubbing 3-17
3.4.3.2 Removal Area 1 3-18
3.4.3.3 Removal Area 2 3-18
3.4.3.4 Removal Area 3A 3-19
3.4.3.5 Removal Area 4A 3-19
3.4.3.6 Removal Area 5A 3-19
3.4.3.7 Island 1 3-20
G:\Aproject\Kalamazoo\Plainwell #2\B0064536\00675\Final
Construction Completion Report\Plainwell 2 TCRA Final Construction
Completion Report.doc ii Project Number: B0064536.00675
Table of Contents
3.4.4.6 Island 2 3-25
3.4.4.7 Oxbow Area 3-26
3.5.1 Dry Soil Mixing 3-31
3.5.1.1 Solidification Agents 3-31
3.5.2 Water Treatment 3-31
3.6 Transportation and Disposal of Sediment and Soil
3-35
3.7 Bank Stabilization and Habitat Reconstruction
3-35
3.7.1 Bank Stabilization Materials 3-36
3.7.1.1 Backfill 3-36
3.7.1.3 Coir Log 3-37
3.7.1.5 Topsoil 3-37
3.8.1 Restoration of Disturbed Vegetation 3-42
3.8.2 Access Roads and Staging Areas 3-42
3.8.3 Contractor Demobilization 3-44
3.8.5 Individual Node Sample Submittal 3-44
3.9 Summary 3-45
G:\Aproject\Kalamazoo\Plainwell #2\B0064536\00675\Final
Construction Completion Report\Plainwell 2 TCRA Final Construction
Completion Report.doc iii Project Number: B0064536.00675
Table of Contents
5. Summary 5-1
6. References 6-1
Table 2 Summary of Pre- and Post-Construction Sampling Analytical
Results
Table 3 Staging Area Size and Operating Dates (in text)
Table 4 Summary of Surface Water Sampling Analytical Results
Table 5 Summary of Confirmation Sampling Analytical Results
Table 6 Water Treatment System Period of Use (in text)
Table 7 Summary of Wipe Sampling Analytical Results
Table 8 Discharge Monitoring Parameters (in text)
Table 9 Summary of Water Treatment Sampling Analytical
Results
Table 10 Status of Access Roads (in text)
Table 11 Summary of Individual Node Sampling Analytical
Results
Table 12 Summary of Removal and Habitat Reconstruction Activities
(in text)
Figures
Figure 2 Site Plan
Figure 4.1 Excavation Site Layout (11+25 to 21+75)
Figure 4.2 Excavation Site Layout (21+75 to 32+25)
G:\Aproject\Kalamazoo\Plainwell #2\B0064536\00675\Final
Construction Completion Report\Plainwell 2 TCRA Final Construction
Completion Report.doc iv Project Number: B0064536.00675
Table of Contents
Figure 4.4 Excavation Site Layout (32+25 to 45+25)
Figure 4.5 Excavation Site Layout (45+25 to 54+75)
Figure 4.6 Excavation Site Layout (54+75 to 67+25)
Figure 4.7 Excavation Site Layout (67+25 to 80+00)
Figure 5.1 Excavation Cross-Sections 1 to 14
Figure 5.2 Excavation Cross-Sections 15 to 28
Figure 5.3 Excavation Cross-Sections 29 to 44
Figure 5.4 Excavation Cross-Sections 45 to 60
Figure 5.5 Excavation Cross-Sections 61 to 76
Figure 5.6 Excavation Cross-Sections 77 to 94
Figure 5.7 Excavation Cross-Sections 95 to 112
Figure 5.8 Excavation Cross-Sections 113 to 130
Figure 5.9 Excavation Cross-Sections 131 to 148
Figure 5.10 Excavation Cross-Sections 149 to 166
Figure 5.11 Excavation Cross-Sections 167 to 182
Figure 5.12 Excavation Cross-Sections 183 to 202
Figure 5.13 Excavation Cross-Sections 203 to 210 and 219 to
224
Figure 5.14 Excavation Cross-Sections 211 to 215
Figure 5.15 Excavation Cross-Sections 216 to 218
Figure 5.16 Excavation Cross-Sections OX1 to OX13
Figure 5.17 Excavation Cross-Sections OX14 to OX25
Figure 6.1 Confirmation Sampling Removal Area 6
Figure 6.2 Confirmation Sampling Oxbow Removal Area
Figure 6.3 Confirmation Sampling Removal Area 5B Floodplain
Figure 6.4 Confirmation Sampling Removal Area 5B
Figure 6.5 Confirmation Sampling Removal Area 4B
G:\Aproject\Kalamazoo\Plainwell #2\B0064536\00675\Final
Construction Completion Report\Plainwell 2 TCRA Final Construction
Completion Report.doc v Project Number: B0064536.00675
Table of Contents
Figure 6.7 Confirmation Sampling Island 2
Figure 6.8 Confirmation Sampling Removal Area 4A and 5A
Figure 6.9 Confirmation Sampling Removal Area 3A
Figure 6.10 Confirmation Sampling Removal Area 2
Figure 6.11 Confirmation Sampling Removal Area 1 and Island 1
Figure 7 Water Treatment Process Flow Diagram
Figure 8.1 Restoration As-Built (11+25 to 21+75)
Figure 8.2 Restoration As-Built (21+75 to 32+25)
Figure 8.3 Restoration As-Built (Oxbow)
Figure 8.4 Restoration As-Built (32+25 to 45+25)
Figure 8.5 Restoration As-Built (45+25 to 54+75)
Figure 8.6 Restoration As-Built (54+75 to 67+25)
Figure 8.7 Restoration As-Built (67+25 to 80+00)
Figure 8.8 Restoration Notes and Specifications
Figure 9 Canoe Portage As-Built
Appendices
Appendix B Photographic Record
Appendix D Material Specifications
Appendix F Turbidity Monitoring Records
Appendix G RTK GPS Calibration Logs
Appendix H Water Treatment Logs
Appendix I Waste Manifests
G:\Aproject\Kalamazoo\Plainwell #2\B0064536\00675\Final
Construction Completion Report\Plainwell 2 TCRA Final Construction
Completion Report.doc vi Project Number: B0064536.00675
G:\Aproject\Kalamazoo\Plainwell #2\B0064536\00675\Final
Construction Completion Report\Plainwell 2 TCRA Final Construction
Completion Report.doc vii Project Number: B0064536.00675
Table of Contents
AOC Administrative Settlement Agreement and Order of Consent BBL
Blasland, Bouck, and Lee, Inc. CERCLA Comprehensive Environmental
Response, Compensation, and Liability
Act CKD cement kiln dust CQA construction quality assurance cy
cubic yards HDPE high-density polyethylene iSIC Intelligent Sensor
Interface & Control MDEQ Michigan Department of Environmental
Quality MDNR Michigan Department of Natural Resources MDNRE
Michigan Department of Natural Resources and Environment mg/kg
milligrams per kilogram mg/L milligrams per liter µg/L micrograms
per liter MHLLC Millennium Holdings, LLC NAD 83 North American
Datum 1983 OSC On-Scene Coordinator PCBs polychlorinated biphenyls
QAPP Quality Assurance Project Plan RTK GPS real time kinematic
global positioning system sf square feet SRD Substantive
Requirements Document SRI/FS Supplemental Remedial
Investigation/Feasibility Study TAL Test America Laboratories TCL
target compound list TCRA time-critical removal action TIN
triangular irregular network TSS total suspended solids USACE
United States Army Corps of Engineers USEPA United States
Environmental Protection Agency USFWS United States Fish and
Wildlife Service
G:\Aproject\Kalamazoo\Plainwell #2\B0064536\00675\Final
Construction Completion Report\Plainwell 2 TCRA Final Construction
Completion Report.doc viii Project Number: B0064536.00675
G:\Aproject\Kalamazoo\Plainwell #2\B0064536\00675\Final
Construction Completion Report\Plainwell 2 TCRA Final Construction
Completion Report.doc Project Number: B0064536.00675
Plainwell No. 2 Dam Area TCRA Final Construction Completion
Report
Statement by Supervising Contractor
I am a registered Professional Engineer and represent ARCADIS as
the Supervising Contractor for work conducted by Georgia-Pacific
LLC for the Allied Paper, Inc./Portage Creek/Kalamazoo River
Superfund Site Plainwell No. 2 Dam Area Time-Critical Removal
Action. This report is submitted in accordance with Paragraph 20 of
the June 2009 Administrative Settlement Agreement and Order on
Consent for Removal Action (Docket No. V-W-09-C-925).
Under penalty of law, I certify that to the best of my knowledge,
after appropriate inquiries of all relevant persons involved in the
preparation of the report that the information submitted is true,
accurate, and complete. I am aware that there are significant
penalties for submitting false information, including the
possibility of fine and imprisonment for knowing violations
____________________________ Stephen Garbaciak Jr., P.E.
Supervising Contractor ARCADIS G&M of Michigan, LLC
Date: February 2011
Plainwell No. 2 Dam Area TCRA Final Construction Completion
Report
1. Introduction
This Plainwell No. 2 Dam Area TCRA Final Construction Completion
Report (Completion Report) has been prepared on behalf of
Georgia-Pacific LLC (Georgia-Pacific) to summarize the efforts
associated with the time-critical removal action (TCRA) conducted
in the Plainwell No. 2 Dam Area located along the Kalamazoo River
near Plainwell, Michigan. The TCRA was completed in accordance with
the Administrative Settlement Agreement and Order of Consent for
Removal Action, Docket No. V-W-09-C-925 (AOC), dated June 8, 2009
(United States Environmental Protection Agency [USEPA] 2009a). Work
activities in support of the TCRA were completed from August 2009
through October 2010.
1.1 General
On February 21, 2007 Georgia-Pacific and Millennium Holdings, LLC
(MHLLC) voluntarily entered into an AOC with USEPA. This agreement,
which described a series of supplemental remedial investigations
and feasibility studies (SRIs/FSs) to be carried out at the Allied
Paper, Inc./Portage Creek/Kalamazoo River Superfund Site (Site or
Superfund Site), is referred to as the SRI/FS AOC (Comprehensive
Environmental Response, Compensation, and Liability Act [CERCLA]
Docket No. V-W-07-C-864). On February 5, 2009, MHLLC notified USEPA
in writing that they would not be participating in any further work
on the Site from that date forward, as a result of the Lyondell
Chemical Company (Lyondell) bankruptcy. An outcome of the
bankruptcy process was that Lyondell was released of responsibility
for continued work on the Kalamazoo River by the United States in
exchange for a cash settlement that included approximately $49.5
million for river-related work.
The SRI/FS work conducted to date has been focused in Area 1 of the
Site – defined as the reach of the Kalamazoo River between Morrow
Dam and the Plainwell Dam and a stretch of Portage Creek – as
described in the USEPA-approved Supplemental Remedial
Investigation/Feasibility Study Work Plan – Morrow Dam to Plainwell
Dam (Area 1 SRI/FS Work Plan; ARCADIS BBL 2007a). After reviewing
the results of sampling and investigation work in the Plainwell No.
2 Dam Area completed pursuant to the Area 1 SRI/FS Work Plan
(ARCADIS BBL 2007a), USEPA determined that a TCRA was necessary to
address areas that may represent potential sources of
polychlorinated biphenyls (PCBs) to the river. Locations targeted
included bank soils, sediments in a portion of a historical oxbow
channel, and soils in a floodplain area adjacent to the
oxbow.
The Plainwell No. 2 Dam Area Time-Critical Removal Action Design
Report (Design Report) (ARCADIS 2009a) provided a detailed
description of the TCRA, including contract drawings and associated
specifications followed during implementation of the remedial
design in
G:\Aproject\Kalamazoo\Plainwell #2\B0064536\00675\Final
Construction Completion Report\Plainwell 2 TCRA Final Construction
Completion Report.doc 1-1 Project Number: B0064536.00675
Plainwell No. 2 Dam Area TCRA Final Construction Completion
Report
accordance with the AOC (USEPA 2009a). The Design Report (ARCADIS
2009a) was submitted to USEPA in July 2009, approved on July 24,
2009 (USEPA 2009b), and served as the work plan for removal
activities.
This Completion Report is designed to satisfy the requirements of
Paragraph 20 of the AOC (USEPA 2009a) and provide USEPA with
documentation that the actions described in the AOC are
complete.
1.2 Project Area Description
The Plainwell No. 2 Dam Area is located on the Kalamazoo River
approximately 3.5 miles upstream of the former Plainwell Dam in the
city of Plainwell and Gun Plain Township, Allegan County (Figure
1).
As described in Section 1.3 of the Design Report (ARCADIS 2009a),
the Plainwell No. 2 Dam consists of four separate remnant
structures—a waste gate structure (located approximately one mile
downstream of the project area), a right diversion structure, a
left diversion structure, and a head gate structure — all of which
were initially constructed in 1856 by the Plainwell Water Power
Company1. Earthen embankments, approximately 2,520 feet in total
length, are also present to connect the two diversion structures.
The right and left diversion structures consist of concrete
spillway gate bays and a concrete spillway, respectively, although
no gates remain in the right diversion structure. An earthen
embankment connects the left abutment of the left diversion
structure and the head gate structure (United States Army Corps of
Engineers [USACE] 1979). The diversion structures direct water from
the main stem of the river into a mill race/power canal that was
once used to generate electric power for a flour mill, the City of
Plainwell, and several other businesses.
The head gate and waste gate structures in the power canal were
formerly used to regulate the head and discharge through the
powerhouse. The head gate structure consists of a concrete spillway
with no control devices. The waste gate structure consisted of two
sluice ways for which the gates are no longer in place (USACE
1979).
The Plainwell No. 2 Dam structures did not significantly alter the
shape or surface area of the river, nor did they create lake-like
impoundments as in the case of the former hydroelectric dam
construction in downstream areas. They did, however, alter flooding
characteristics of the river to some degree upstream.
1 Documentation of any subsequent construction activities is not
available.
G:\Aproject\Kalamazoo\Plainwell #2\B0064536\00675\Final
Construction Completion Report\Plainwell 2 TCRA Final Construction
Completion Report.doc 1-2 Project Number: B0064536.00675
Plainwell No. 2 Dam Area TCRA Final Construction Completion
Report
According to the Michigan Department of Environmental Quality
(MDEQ) (now the Michigan Department of Natural Resources and
Environment [MDNRE]), the dam and associated structures were
partially removed in the early 1980s such that there is no longer
any “significant amount of water” (Hayes 1998a) impounded in the
area. The waste gate structure’s lift gate and stoplog guides were
still present in 1980, and at that time there were no active
operational procedures in place other than to permanently leave all
discharge control structures adjusted so that they would permit
maximum discharge capacity (USACE 1979). It was the opinion of the
Michigan Department of Natural Resources (MDNR) (now MDNRE) that
the dam structures “will not significantly impound any water that
would pose a hazardous condition to the public safety” (Cook
1980).
In 1979, the Plainwell No. 2 Dam was classified as a small size dam
with high hazard potential in accordance with the National Dam
Safety Program Criteria (USACE 1979). Following the partial removal
of the dam and associated structures in the 1980s, the dam was
reclassified as a low hazard potential (Hayes 1998b). The primary
continuing purpose of the remaining structures is to maintain flow
through the mill race/power canal, which along with the Kalamazoo
River, encircles the city of Plainwell and gives it the name
“Island City.” State and local officials have expressed intentions
to leave the Plainwell No. 2 Dam structures in place to continue to
provide flow through the mill race and preserve the character of
the city.
As described in Section 1.4 of the Design Report (ARCADIS 2009a),
the Plainwell No. 2 Dam Area has been the focus of a series of
investigations by ARCADIS (formerly known as Blasland, Bouck &
Lee, Inc [BBL] and ARCADIS BBL), MDEQ (now MDNRE), and USEPA since
2000. The most recent PCB data were collected during a sampling
effort conducted by ARCADIS between 2008 and 2009. A variety of
targeted studies of the impoundment were also conducted in 2008 and
2009 to further characterize project area topography, bank
stability/disposition, flow hydrodynamics, equipment accessibility,
and habitat quality.
1.3 Overview of Response Actions and Summary of Work
Performed
The activities completed at the Plainwell No. 2 Dam Area were
consistent with the requirements of the Design Report. In summary,
the TCRA was performed to achieve the following objectives set
forth in the Design Report (ARCADIS 2009a):
1. Stem the potential loading of PCBs to the Kalamazoo River from
river banks in the Plainwell No. 2 Dam Area.
2. Remove sediments located at the mouth of and along the western
side of the former oxbow channel.
G:\Aproject\Kalamazoo\Plainwell #2\B0064536\00675\Final
Construction Completion Report\Plainwell 2 TCRA Final Construction
Completion Report.doc 1-3 Project Number: B0064536.00675
Plainwell No. 2 Dam Area TCRA Final Construction Completion
Report
3. Dispose removed PCB-containing bank soils and sediment in a way
that does not present unreasonable risk to human health or the
environment.
4. Mitigate potential adverse environmental impacts of
construction.
5. Complete habitat enhancement to potentially address past
releases of PCBs from Georgia- Pacific facilities – the Natural
Resource Trustees will determine if and to what degree these
enhancements may compensate for natural resource injuries in the
project area.
To accomplish these objectives, the removal action in the Plainwell
No. 2 Dam Area included the following specific elements of
work:
a) Removal of a defined area of sediments at the mouth of and along
the western side of the former oxbow channel which yielded samples
with elevated PCB concentrations as described in Section 2.2 of the
Design Report (ARCADIS 2009a).
-- See Section 3.4 for a description of the removal
operations.
b) Removal of PCB-containing bank soils, with bank cutbacks to
stable slopes and backfill of the removal areas to original grade
where appropriate. Some areas were not fully backfilled to
encourage redevelopment of native habitat. The full range of
restoration options are outlined in Contract Drawings R-1.1 through
R-1.7.
-- See Sections 3.4.3, 3.4.4, and 3.7 for a summary of how the
materials were removed and backfilled.
-- See Section 3.4.1 for a summary of how excavation limits were
confirmed.
c) Disposal of PCB-impacted sediments and soils in licensed
commercial landfills.
-- See Section 3.6 for a description of how the excavated materials
were disposed.
d) Mitigate potential adverse effects of construction.
-- See Section 3.2 for a description of the Indiana bat survey, air
monitoring, and erosion control.
-- See Section 3.3 for a description of resuspended sediment
control.
-- See Section 3.5 for a description of water treatment.
-- See Section 3.6 for a description of soil and sediment
transportation.
G:\Aproject\Kalamazoo\Plainwell #2\B0064536\00675\Final
Construction Completion Report\Plainwell 2 TCRA Final Construction
Completion Report.doc 1-4 Project Number: B0064536.00675
Plainwell No. 2 Dam Area TCRA Final Construction Completion
Report
e) Complete habitat enhancement to potentially address past
releases of PCBs from Georgia- Pacific facilities.
-- See Section 3.7 for a description of restoration
activities.
Construction activities performed to achieve these objectives are
described in the sections referenced after each bullet point.
1.4 Scope of the Completion Report
This Completion Report describes the completed response actions at
the Plainwell No. 2 Dam Area and contains the following
information:
• Material testing and certification results
• Sediment and soil removal narrative
• Waste disposal manifests
• Confirmation sample results
• Final sediment excavation elevations, documented on as-built
cross-sections with elevations referenced to the appropriate
vertical datum
• Daily activity logs, which include equipment calibration records,
air monitoring records, construction dewatering, sediment/soil
drainage, water treatment records, and daily weather
conditions
• Turbidity monitoring records
• A good faith estimate of total project cost
• Certification by the Supervising Contractor that based on the
Supervising Contractor’s knowledge and review of the construction
records, the construction met the requirements of the engineering
plans
The scope of this Completion Report is limited to the activities
necessary to complete the TCRA.
G:\Aproject\Kalamazoo\Plainwell #2\B0064536\00675\Final
Construction Completion Report\Plainwell 2 TCRA Final Construction
Completion Report.doc 1-5 Project Number: B0064536.00675
G:\Aproject\Kalamazoo\Plainwell #2\B0064536\00675\Final
Construction Completion Report\Plainwell 2 TCRA Final Construction
Completion Report.doc 1-6 Project Number: B0064536.00675
Plainwell No. 2 Dam Area TCRA Final Construction Completion
Report
1.5 Report Organization
The remainder of this Completion Report is organized into five
sections. A brief overview of each of the subsequent sections is
presented below.
• Section 2 – Project Overview; describes the project organization,
provides a summary of the work performed, and describes deviations
from the Design Report (ARCADIS 2009a).
• Section 3 – Removal Activities; presents a summary of activities
for each element of the project.
• Section 4 – Post-Removal Controls; describes post-construction
activities focusing on several aspects of the work, including
monitoring of the banks and revegetation efforts.
• Section 5 – Summary; summarizes how the removal activities
achieved the objectives set forth in the Design Report.
• Section 6 – References; lists documents used in preparation of
this Completion Report.
Tables, figures, and appendices are also included to provide
further detail, as appropriate.
Plainwell No. 2 Dam Area TCRA Final Construction Completion
Report
2. Project Overview
This section describes the project organization, provides a summary
of the work performed and the performance standards for the TCRA,
and describes deviations from the Design Report (ARCADIS
2009a).
2.1 Project Organization
Several organizations were responsible for completion of the TCRA
in the Plainwell No. 2 Dam Area. These organizations and their
associated roles and responsibilities are described below.
Georgia-Pacific entered into the AOC and was responsible for
performing the TCRA in the Plainwell No. 2 Dam Area.
USEPA signed the AOC with Georgia-Pacific and provided oversight
and documentation of construction activities. Design changes and
construction issues were discussed with USEPA, as necessary. USEPA
consulted with other government agencies as necessary, including,
but not limited to the United States Fish and Wildlife Services
(USFWS), MDNRE (formerly MDNR and MDEQ), and the National Oceanic
and Atmospheric Administration.
ARCADIS served as the Supervising Contractor for the project. In
this role, ARCADIS implemented the TCRA on behalf of
Georgia-Pacific and provided full-time construction management and
construction quality assurance (CQA) services for the duration of
removal activities. ARCADIS documented that the TCRA was
implemented in conformance with the approved work plan (the Design
Report [ARCADIS 2009a]), documented progress towards meeting design
objectives, recorded daily work activities, performed construction
monitoring, directed subcontractors, provided health and safety
oversight, and approved field changes.
ARCADIS appointed a CQA Observer who was responsible for daily
construction oversight to verify that the construction was
performed in general conformance with the Design Report (ARCADIS
2009a). CQA also included observation, testing, and documentation
of certain construction phases on a periodic basis to verify
conformance with the approved guidance and design documents. The
CQA Observer reviewed pre-removal submittals and conformance test
results and prepared Daily Construction Reports with photographs to
communicate the project’s progress to the project team throughout
the course of construction.
The CQA Observer identified and documented construction problems or
deficiencies and discussed them with the Supervising Contractor
(who had ultimate technical responsibility for the work performed),
as necessary, and related parties as required to implement
corrective
G:\Aproject\Kalamazoo\Plainwell #2\B0064536\00675\Final
Construction Completion Report\Plainwell 2 TCRA Final Construction
Completion Report.doc 2-1 Project Number: B0064536.00675
Plainwell No. 2 Dam Area TCRA Final Construction Completion
Report
action. A team of environmental and geotechnical engineers and
other experts, as appropriate, provided engineering and
construction support and management. Corrective actions to resolve
problems or deficiencies were implemented by subcontractors and
observed and documented by the CQA Observer. Significant problems
and corrective actions are discussed in Section 2.3. On a daily
basis, the CQA observer documented and corrected, if necessary,
actions including, but not limited to excavation depth
confirmation, sampling procedures and results, restoration methods,
re-suspension control effectiveness, and survey data
collection.
ARCADIS retained various subcontractors to perform construction
activities associated with the TCRA. Terra Contracting, LLC of
Kalamazoo, Michigan was selected as the primary removal contractor
and was responsible for support facilities and access road
construction, soil and sediment excavation activities, installation
of resuspended sediment controls, construction dewatering and water
treatment, management of waste transport and disposal, and
restoration of excavated areas. American Environmental Group of
Richfield, Ohio installed geotextile fabric and liner at the
staging areas, and JF New of Walkerton, Indiana revegetated the
excavated and restored areas. Subcontractors retained other firms,
as necessary, to complete their scope of work.
2.2 Summary of Work Performed
The following activities (described further in Sections 3.2 through
3.8) were completed to achieve the objectives of the TCRA, as
described in Section 1.3:
• Completion of pre-construction activities
• Dewatering, processing, and treatment, as necessary, of excavated
materials
• Transportation and disposal of sediments and soils
• Bank stabilization and habitat reconstruction
• Project area restoration and demobilization
The TCRA was completed from August 2009 through October 2010. The
2009 construction season was completed from August through December
2009. The 2010 construction season was completed from January
through October 2010. Removal activities were suspended from
November 2009 through May 2010. During that time equipment and
materials were removed
G:\Aproject\Kalamazoo\Plainwell #2\B0064536\00675\Final
Construction Completion Report\Plainwell 2 TCRA Final Construction
Completion Report.doc 2-2 Project Number: B0064536.00675
Plainwell No. 2 Dam Area TCRA Final Construction Completion
Report
from the north side of the river and remobilized to the south side
of the river. Project area preparation was performed on the south
side of the river, and demobilization and restoration activities
were performed on the north side of the river.
2.3 Deviations from the Design Report
Work activities that deviated from the Design Report were performed
due to unexpected conditions encountered in the field or at the
request of the regulatory agencies. All changes were discussed by
the Supervising Contractor and USEPA prior to implementation, and
were documented by the CQA Observer and through correspondence with
the regulatory agencies. The text of the Design Report was not
modified. Specific deviations from the Design Report are discussed
below.
2.3.1 Backfilling of Excavated Areas
As operations were completed within a removal area, the banks were
reconstructed to a stable condition and revegetated. Restored banks
were backfilled to the specific design elevations, graded, and
provided with toe protection, where appropriate, to minimize bank
erosion and allow bank access for semi-aquatic wildlife. Typical
restored bank cross-sections and planned bank restoration
techniques were provided on Contract Drawings R-2.1 and R-2.2 and
R-1.1 through R-1.7, respectively, of the Design Report (ARCADIS
2009a).
According to Section 2.10 of the Design Report (ARCADIS 2009a), of
primary importance for final bank elevation was the relationship of
the restored bank elevation to the corresponding elevation of the
opposite bank. When the opposing bank was lower or banks were at a
similar elevation, this elevation controlled the frequency and
duration of inundation. Therefore, maintaining the final bank
elevation at or above the same elevation as the opposite bank was
critical to maintaining the frequency and duration of inundation in
floodplain wetlands as the river water level rises with storm
flows. However, the final elevation of disturbed high banks
provided some flexibility in final elevations as long as the higher
bank remained the higher bank. Disturbed high banks could be left
at post-excavation elevations if that elevation remained higher
than the low bank. Figure 2-7 of the Design Report (ARCADIS 2009a)
illustrated where these different relationships occur in the
Plainwell No. 2 Dam Area.
Using this as direction, ARCADIS, in consultation with USEPA,
determined that backfilling to pre-excavation elevations was not
warranted in all areas. As such, actual restoration activities
deviated from the plan established in Contract Drawings R-1.1
through R1.7 and R-2.1 and R- 2.2 of the Design Report (ARCADIS
2009a). Restoration activities and construction of stable banks
focused on maintaining the elevation relationship between opposing
banks more so than
G:\Aproject\Kalamazoo\Plainwell #2\B0064536\00675\Final
Construction Completion Report\Plainwell 2 TCRA Final Construction
Completion Report.doc 2-3 Project Number: B0064536.00675
Plainwell No. 2 Dam Area TCRA Final Construction Completion
Report
re-building the bank to its pre-construction elevation. Backfill
was used when necessary to preserve the relationship between
opposing banks (i.e. the higher bank remained the higher bank), and
topsoil was installed as necessary in areas where post-excavation
soil composition would not support vegetation growth. Additional
information regarding restoration activities is included in Section
3.8.
2.3.2 Removal Area 5
Visual observations in the downstream portion of Removal Area 5
revealed a guy wire used to support the high-tension power lines
crossing the Kalamazoo River near the right diversion structure. In
order to avoid compromising the integrity of the guy wire, the
excavation limits of Removal Area 5 were modified to provide a
25-foot offset from the guy wire. In addition, at the request of
USEPA, a canoe portage was designed and installed at the downstream
end of Removal Area 5. These modifications were approved by USEPA
on October 14, 2009 (USEPA 2009c). See Section 3.7.3 for additional
information.
2.3.3 Habitat Reconstruction Plant Species
The species to be used for re-vegetation are described in Section
3.7 and Contract Drawing G- 5.2 of the Design Report (ARCADIS
2009a). Through discussions with the habitat reconstruction
subcontractor, ARCADIS determined that some tree, shrub, and grass
species scheduled to be planted as a part of habitat reconstruction
activities on the north side of the river would not be available.
The planting plan was revised to reflect available tree and shrub
species. The following modifications to the planting plan were
made:
2009 Construction Season
• Rice Cutgrass was included in the emergent wetland and forested
wetland seed mix instead of American Slough Grass.
• Panicled Aster was included in the emergent wetland and forested
wetland seed mix instead of New England Aster.
• Heath Aster was included in the forested upland seed mix instead
of Annual Rye.
• Bottlebrush Grass was included in the forested upland seed mix
instead of Thickspike Wheatgrass.
• Troublesome Sedge was included in the forested upland seed mix
instead of Plains Oval Sedge.
G:\Aproject\Kalamazoo\Plainwell #2\B0064536\00675\Final
Construction Completion Report\Plainwell 2 TCRA Final Construction
Completion Report.doc 2-4 Project Number: B0064536.00675
Plainwell No. 2 Dam Area TCRA Final Construction Completion
Report
• Swan’s Sedge was included in the forested upland seed mix instead
of Sand Bracted Sedge.
• Prairie Junegrass was included in the forested upland seed mix
instead of Junegrass.
• Prairie Dropseed was included in the forested upland seed mix
instead of Sand Dropseed.
• Prairie Milkweed was included in the forested upland seed mix
instead of Common Milkweed.
• Few Leaf Sunflower was included in the forested upland seed mix
instead of Tall Coreopsis.
• Prairie Cinquefoil was included in the forested upland seed mix
instead of Flowering Spurge.
• Canadian Milkvetch was included in the forested upland seed mix
instead of American Vetch.
• Swamp Rose and Black Willow were planted instead of Speckled
Alder.
• White Meadowsweet was planted instead of American
Elderberry.
2010 Construction Season
• White Meadowsweet and American Winterberry were planted instead
of Speckled Alder.
See Section 3.7 for additional information regarding habitat
reconstruction.
2.3.4 Oxbow Removal
2.3.4.1 Sediment Removal Method
According to Section 2.6 of the Design Report (ARCADIS 2009a),
sediment removal was to be performed using a closed-bucket
clamshell or a visor-equipped excavator bucket (with no drainage
holes), unless productivity was negatively impacted such that
USEPA’s on-scene coordinator (OSC) allowed the use of a standard
clamshell or excavator bucket.
Prior to commencing removal activities, the OSC and ARCADIS
inspected the sediment excavation area (the oxbow). Based on visual
observations and limited probing, it was determined that due to the
presences of tree limbs and branches, a closed-bucket clamshell or
equivalent bucket head would not be appropriate for removal in the
oxbow; therefore, a standard excavator bucket was used to remove
material in the oxbow. See Section 3.4.4.7 for additional
information.
G:\Aproject\Kalamazoo\Plainwell #2\B0064536\00675\Final
Construction Completion Report\Plainwell 2 TCRA Final Construction
Completion Report.doc 2-5 Project Number: B0064536.00675
G:\Aproject\Kalamazoo\Plainwell #2\B0064536\00675\Final
Construction Completion Report\Plainwell 2 TCRA Final Construction
Completion Report.doc 2-6 Project Number: B0064536.00675
Plainwell No. 2 Dam Area TCRA Final Construction Completion
Report
2.3.4.2 Removal Footprint
Prior to commencing removal activities in the mouth of the oxbow in
August 2010, ARCADIS and the USEPA OSC probed the soft sediment
located in the mouth of the oxbow. Through this probing activity,
it was determined that no soft sediment was present throughout much
of the northern portion of the oxbow mouth. Because no soft
sediment was observed, no excavation was required in this area. The
planned removal footprint in the oxbow mouth was revised to
incorporate only areas where soft sediment was present. See Section
3.4.4.7 for additional information.
Plainwell No. 2 Dam Area TCRA Final Construction Completion
Report
3. Removal Activities
This section describes the actions performed to complete removal
activities at the Plainwell No. 2 Dam Area. Removal activities were
implemented between August 2009 and October 2010, and included
pre-construction activities; installation of resuspended sediment
control structures; soil/sediment removal; material dewatering,
processing, and water treatment; transportation and disposal of
excavated material; bank stabilization and habitat reconstruction;
and project area restoration and demobilization. Daily activity
reports are included in Appendix A and a photographic log is
included in Appendix B.
3.2 Pre-Construction Activities
Pre-construction activities, such as endangered species survey;
permitting; obtaining property access; identifying aggregate
sources; mobilization and project area preparation; access road and
staging area construction; and installation of erosion controls
were performed by ARCADIS and its subcontractors in preparation for
the TCRA. These activities are described in the following
sections.
3.2.1 Indiana Bat Survey
The Indiana bat (Myotis sodalis) is listed as an endangered species
by USFWS. The bats hibernate in caves over the winter and then
migrate to summer habitat in wooded areas where they usually roost
under loose tree bark on dead or dying trees (USFWS 2009). Habitat
that has the potential to accommodate the Indiana bat was
identified in the project area. Therefore, a site survey was
conducted on March 4, 2009 to identify trees in the project area
where Indiana bats might roost. The survey, required by and
conducted under USFWS oversight, was led by Dr. Allen Kurta,
Professor of Biology at Eastern Michigan University in Ypsilanti,
Michigan. Dr. Kurta identified 11 trees where the Indiana bat might
roost, and those trees were removed on March 30, 2009, at the
direction of USFWS.
According to USFWS, the Indiana bat typically roosts in the area
between April 15 and September 15. By the time clearing and
grubbing was scheduled to begin in August 2009, any bats in the
area would have already roosted in the trees identified by Dr.
Kurta - trees scheduled to be removed to facilitate TCRA
activities. Therefore, these trees were removed prior to April 15
to prevent the Indiana bat from roosting in the trees and being
displaced or harmed during clearing and grubbing activities. Bats
attempting to roost in the area would seek trees outside the TCRA
area to establish habitat.
G:\Aproject\Kalamazoo\Plainwell #2\B0064536\00675\Final
Construction Completion Report\Plainwell 2 TCRA Final Construction
Completion Report.doc 3-1 Project Number: B0064536.00675
Plainwell No. 2 Dam Area TCRA Final Construction Completion
Report
3.2.2 Permitting
Consistent with the provisions of CERCLA Section 121(e) (1), no
permits for removal activities were required because all removal
activities were conducted onsite.
ARCADIS received a permit from MDNR to install buoys in the river
(MDNR 2009) to mark construction areas. MDNR closed the river to
recreational use during construction activities. See Section 3.2.2
for additional information. The water generated during soil and
sediment dewatering was managed in accordance with Substantive
Requirements Document (SRD) – No. MIU990028 (MDEQ 2009). See
Section 3.5.2 for additional information.
3.2.3 Property Access
ARCADIS obtained property access from private property owners and
MDNR to conduct construction activities on their properties.
3.2.4 Identification of Borrow Material
Sources of sand backfill, aggregate material, river run rock,
concrete, and topsoil (collectively, borrow material) were
identified prior to construction. Borrow material sources were
contacted to verify that material was available in the required
quantities.
Borrow material used in restoration or grading activities was
sampled at a rate of one composite sample per 10,000 cubic yards
(cy) prior to use. Composite samples consisted of nine subsamples
collected from various areas of the offsite source material
selected in the field and biased towards areas of staining, if
present. Backfill samples were analyzed for Target Compound List
(TCL) volatile organic compounds, TCL semivolatile organic
compounds, TCL pesticide/PCBs, Resource Conservation & Recovery
Act metals, and total petroleum hydrocarbons (diesel range organics
and gasoline range organics). Topsoil sources were also analyzed
for grain size, pH, and total organic content to verify that they
would support vegetation. Results of the sampling are summarized in
Table 1 and laboratory analytical data are included in Appendix
C-1. Samples were collected in accordance with the project-specific
Quality Assurance Project Plan (QAPP) (ARCADIS BBL 2007b).
Analytical results were compared to applicable Part 201 cleanup
criteria and Part 213 risk- based screening levels provided in
Operational Memorandum No. 1 (Table 2, Column #19, Direct Contact
Criteria & RMSLs), issued by the Remediation and Redevelopment
Division of MDEQ on December 10, 2004. Sampling results indicate
that all material from the borrow sources were acceptable for
use.
G:\Aproject\Kalamazoo\Plainwell #2\B0064536\00675\Final
Construction Completion Report\Plainwell 2 TCRA Final Construction
Completion Report.doc 3-2 Project Number: B0064536.00675
Plainwell No. 2 Dam Area TCRA Final Construction Completion
Report
Aggregate material used to construct access roads was re-used from
the former Plainwell Impoundment TCRA completed in June 2009 and
summarized in the former Plainwell Impoundment TCRA Final
Construction Completion Report (ARCADIS 2010a). Virgin aggregate
material from offsite borrow sources was used to supplement the
re-used aggregate material as necessary. See Section 3.2.5 for
additional information.
3.2.5 Mobilization and Project Area Preparation
Clearing and grubbing of vegetation from wooded areas was performed
to the extent required throughout the project to establish access
roads, staging areas, project support areas, and excavation areas.
Cleared vegetation was chipped and used for dust and erosion
control, hauled to landfills for offsite disposal, salvaged for
marketable timber, used for constructing roads, or staged for later
use.
Project area preparation activities commenced in August 2009 and
included mobilization and construction of equipment, materials,
support facilities, and personnel necessary for completion of the
project. Support facilities included two temporary trailers for the
subcontractor, one temporary office trailer for USEPA, and one
temporary office trailer for ARCADIS. Facilities also included
worker sanitation areas, equipment maintenance and storage areas,
break areas, and personal decontamination areas.
Security measures including chain link fence and locked access
gates were installed at each active work area within the project
area. Temporary high-visibility fencing was used in areas where
work did not warrant permanent fencing or to distinguish areas such
as exclusion zones. Notification and warning signs were also posted
where appropriate to label work areas.
With the cooperation of MDNR, the river was closed to public access
throughout the duration of the project. ARCADIS provided signage
stating that the river was closed. These signs and standard
regulatory buoys were deployed by ARCADIS both upstream and
downstream of the project area and at major boat launches in the
area. Public notices were issued through MDNR and ARCADIS public
communications specialists.
The Plainwell No. 2 Dam Area Traffic Control Plan Allied Paper,
Inc./Portage Creek/Kalamazoo River Superfund Site (Traffic Control
Plan, ARCADIS 2009b) was issued in July 2009 to detail traffic
routes, entrances to public roads, traffic control measures, safety
procedures, communication, and manifesting procedures. A revised
Traffic Control Plan (Rev. 1 was issued in March 2010 (ARCADIS
2010b) to address alternate truck routes to the landfills due to
potential construction or road closures.
G:\Aproject\Kalamazoo\Plainwell #2\B0064536\00675\Final
Construction Completion Report\Plainwell 2 TCRA Final Construction
Completion Report.doc 3-3 Project Number: B0064536.00675
Plainwell No. 2 Dam Area TCRA Final Construction Completion
Report
3.2.5.1 Access Road Construction
Access roads were constructed to provide access to work areas along
the banks of the Kalamazoo River and material staging areas, and to
connect staging areas to public roadways (Figure 2). Three access
points located on private residential property were established to
access work areas.
The roads were constructed of geotextile material underlying
aggregate material. Material specifications for these materials are
included in Appendix D. Aggregate material imported from an offsite
borrow source or from the former Plainwell Impoundment TCRA was
used at the Plainwell No. 2 Dam Area TCRA. Aggregate imported from
the borrow source was sampled according to the parameters described
in Section 3.2.4. Aggregate material re-used from the former
Plainwell Impoundment TCRA had previously been sampled as described
in Section 3.2.3 of the Former Plainwell Impoundment Time-Critical
Removal Action Final Construction Completion Report (ARCADIS
2010a).
Access roads connecting the work areas to the staging areas were
referred to as haul roads. Prior to leaving the project area,
vehicles that used the haul roads were decontaminated by pressure
washing or by a truck tire wash installed at each staging area.
Water from the truck tire wash was collected and treated with the
decant water. See Section 3.5.2 for additional information
regarding water treatment.
Where appropriate, pre- and post-construction soil samples were
collected from access roads constructed on private property. Pre-
and post-construction soil sampling was not required on MDNRE
property. Air was monitored for particulate matter as activities
required (such as truck traffic, pug mill operations) and based on
the discretion of the health and safety officer. Air monitoring
logs are included in the daily activity reports in Appendix A
The pre- and post-construction soil samples were collected to
document the PCB concentration of subsurface soil before and after
the TCRA. Samples were collected from 0 to 6 inches below the
surface using a stainless steel trowel and submitted to KAR
Laboratories in Kalamazoo, Michigan or Test America Laboratories
(TAL) in Burlington, Vermont for PCB analysis. Access roads were
sampled at a rate of one sample every 200 feet. Pre- and
post-construction sampling results are included in Table 2.
Laboratory analytical data are included in Appendix C- 2. Samples
were collected and analyzed in accordance with the project-specific
QAPP (ARCADIS BBL 2007b).
G:\Aproject\Kalamazoo\Plainwell #2\B0064536\00675\Final
Construction Completion Report\Plainwell 2 TCRA Final Construction
Completion Report.doc 3-4 Project Number: B0064536.00675
Plainwell No. 2 Dam Area TCRA Final Construction Completion
Report
3.2.5.2 Staging Area Construction
Three staging areas were constructed for sediment and soil
dewatering, processing, and staging before transport for offsite
disposal. The staging areas were also used to collect and treat
decant water from gravity drainage of the excavated sediments and
soils. The staging areas, identified as Staging Areas 1, 2, and 3,
varied in size (Figure 2). Staging area construction included
grading and constructing berms from the underlying material to
facilitate the collection of decant water for water treatment,
installation of geosynthetic liner material, installation of
aggregate material, set-up of material processing facilities, and
installation of the water treatment system (Staging Areas 1 and 3
only). Dewatering water collected at Staging Area 2 was transported
to Staging Area 1 for treatment. Trailers were only located at
Staging Areas 1 and 3. See Section 3.5.2 for additional information
regarding water treatment.
The size, location, and layout of the staging areas described in
the Design Report (ARCADIS 2009a) were modified as necessary based
on field conditions. Locations and orientations were modified at
the request of the land owner whose property was utilized for
staging area construction. Size was modified based on the estimated
quantity of material to be processed in the area, and the layout of
the staging area was modified to maximize the material processing
area. See Figure 3 for a typical as-built layout of the staging
areas. Table 3 summarizes the size and operating dates of the three
staging areas.
Table 3 -- Staging Area Size and Operating Dates
Staging Area Approximate
Area (square feet)
1 122,000 May 2010 October 2010
2 45,000 May 2010 October 2010
3 90,000 August 2009 December 2009
The staging areas were cleared of vegetation and graded to collect
water at one end. A sand base was installed at Staging Areas 1 and
3 to grade the construction area to a flat surface and berms were
constructed around the sides of all staging areas to control water
runoff. A sand base was not required to evenly grade Staging Area
2. Three layers of geosynthetic material were installed on top of
underlying sand material. The geosynthetic layers served as a
barrier between excavated material and the ground surface, and
consisted of 40-millimeter high- density polyethylene (HDPE)
geomembrane liner installed between two layers of non-woven
geotextile fabric. The geotextile fabric was used to provide
support and to prevent damage to the geomembrane liner. The HDPE
layer served to prevent rainwater and decant water from
G:\Aproject\Kalamazoo\Plainwell #2\B0064536\00675\Final
Construction Completion Report\Plainwell 2 TCRA Final Construction
Completion Report.doc 3-5 Project Number: B0064536.00675
Plainwell No. 2 Dam Area TCRA Final Construction Completion
Report
dewatering activities from migrating into the subsurface soils.
Material specifications for these materials are included in
Appendix D. The HDPE was seamed and tested to verify proper
installation. Seaming records can be found in Appendix E. Aggregate
material was installed above the second layer of geotextile fabric
to serve as a base for work activities.
Depending on the intended use of the area, two types of aggregate
material were placed above the geotextile material. 21AA aggregate
was installed in areas used by off-road trucks and gravel-train
trucks. Both natural and crushed concrete types of aggregate
material were used. 6A rounded stone aggregate was used in sediment
and soil decanting, processing, and staging areas. The material was
sampled prior to use according to the sampling procedures outlined
in Section 3.2.4. Results of the sampling are summarized in Table 1
and laboratory analytical data are included in Appendix C-1. A
water truck was used in the staging areas for dust control as
conditions warranted. Air was monitored for particulate matter as
needed near the staging areas. Air monitoring logs are included in
the daily activity reports in Appendix A.
As described in Section 3.2.5.1 for access road construction, pre-
and post-construction samples were collected from the staging
areas. A five-part composite sample, composited from the four
corners and center of the staging area, was collected from each
staging area. Samples were analyzed as described in Section
3.2.5.1.
Pre- and post-construction sampling results are included in Table
2. Laboratory analytical data are included in Appendix C-2.
3.2.5.3 Installation of Erosion Controls
Temporary erosion and sediment controls were installed before
construction activities were initiated and were maintained through
the duration of the project. Location-specific erosion and sediment
controls were implemented at each removal area consistent with the
measures described in the Design Report (ARCADIS 2009a). The
specific locations of erosion and sediment controls were selected
based on project area-specific considerations related to drainage,
topography, and work activities. The selection of erosion and
sediment control measures was based on, but not limited to, the
scope of removal activities, location and topography, type of
ground cover, type of material excavated, anticipated run-off from
the project area, and operational/maintenance considerations.
Silt fencing consisting of a non-woven, needle-punched, polyester
or polypropylene silt fence was used as the primary means of
erosion control around all surface soil disturbances and potential
run-off areas. Material specifications for the silt fence were
reviewed and approved by ARCADIS prior to use (Appendix D).
G:\Aproject\Kalamazoo\Plainwell #2\B0064536\00675\Final
Construction Completion Report\Plainwell 2 TCRA Final Construction
Completion Report.doc 3-6 Project Number: B0064536.00675
Plainwell No. 2 Dam Area TCRA Final Construction Completion
Report
Additional erosion control measures included spreading wood chips
generated during clearing and grubbing activities throughout the
area to reduce wind erosion.
During active work periods throughout the duration of the project,
temporary erosion and sediment controls were inspected by the CQA
Observer, documented in the daily reports, and maintained and/or
modified on a daily basis, consistent with the recommended
frequencies outlined in the Guidebook of Best Management Practices
for Michigan Watersheds (MDEQ 1998). Temporary erosion and sediment
controls were maintained, as appropriate, until a final surface
cover was established as part of restoration activities.
3.3 Resuspended Sediment Control Structures
Control systems were installed in the river to minimize downstream
transport of resuspended materials associated with the removal of
sediments and soils. The selected systems had a relatively short
setup/breakdown time and could be easily modified to adapt to
changes in field conditions. The structures used to control
resuspended sediment were capable of functioning under a variety of
potential river flow and depth scenarios. The system used
throughout the TCRA included a combination of turbidity curtains
with a flow deflector wall.
Inspections of the sediment resuspension control systems were
conducted each day at the beginning of removal activities, in
response to visible sediment plumes migrating from the project
area, or in response to turbidity levels measured above the action
level. Routine daily resuspended sediment control system
inspections consisted of a surface assessment of the condition,
location, and anchoring of curtains and flow deflector walls.
Inspections in response to turbidity levels above the action level
metric began with a surface inspection using a boat. Additional
inspections were conducted, as appropriate, following higher-flow
periods, noticeable turbidity increases outside the system,
unexpected system position/behavior, contact with the system by
equipment or debris, or other abnormal events. Due to changing
water levels and flow velocities, turbidity curtains were adjusted
on a regular basis throughout the course of the project. Visible
silt plumes were observed on several occasions, but did not result
in elevated turbidity readings. Upon observation of a visible silt
plume, excavation activities were suspended, and resuspended
sediment controls were inspected and repaired.
3.3.1 Turbidity Curtains
Turbidity curtains were used extensively throughout the TCRA to
control resuspended sediments. Curtains consisted of 22-ounce
impermeable fabric, 8-inch diameter closed cell foam floatation
devices, and double continuous 1/4-inch (upper) and 3/8-inch
(lower) chain ballast enclosed in fabric pockets at the bottom edge
of the curtain. The curtains had dual center tension cables that
were reefable for water depth variation adjustments. A
material
G:\Aproject\Kalamazoo\Plainwell #2\B0064536\00675\Final
Construction Completion Report\Plainwell 2 TCRA Final Construction
Completion Report.doc 3-7 Project Number: B0064536.00675
Plainwell No. 2 Dam Area TCRA Final Construction Completion
Report
specification is included in Appendix D. One hundred-foot curtain
segments were joined by metal side connecters and laced grommet
edges to create a continuous barrier the length of an entire
removal area (Figures 4.1 through 4.7). The curtains were anchored
upstream to downstream using primarily steel sheeting driven to the
river bed. Steel sheeting was generally used to connect adjacent
100-foot sections of turbidity curtain. Some galvanized steel fence
posts were used in areas of low flow. The downstream and upstream
ends of the curtains were attached to the shore. Throughout the
project, the curtains were installed or removed as necessary.
Some damage to turbidity curtains occurred during excavation
activities as a result of normal wear and tear. Damage was
discovered by visual inspection of the curtains, identification of
a silt plume escaping the curtain, and/or a turbidity exceedance.
Curtains were repaired as soon as possible after damage was
identified. Curtains that could not be repaired were replaced and
staged for offsite disposal. At the conclusion of the project,
curtains that were in good condition and could be re-used in the
future were decontaminated, folded, and placed in storage.
3.3.2 Flow Deflector Walls
Flow deflector walls were used in conjunction with turbidity
curtains to control resuspended sediments in areas where increased
water depths or flow velocities were encountered. The use of flow
deflector walls reduced the frontal impact of currents on the silt
curtain system. The sheet pile used to construct the flow deflector
walls was installed by machinery located on shore and was not
affected by high flow velocities.
3.3.3 Resuspended Sediment Monitoring
Turbidity monitoring and surface water sampling were conducted
throughout construction activities to monitor the effectiveness of
the resuspended sediment control structures. Methods and results
are described below.
3.3.3.1 Turbidity Monitoring
Real-time turbidity data were collected daily during removal
activities using NexSens iSIC (Intelligent Sensor Interface &
Control) automated meters from one fixed location upstream
(approximately 200 feet) and from two fixed locations downstream
(approximately 200 and 300 feet) of an active work area. A copy of
the specification for the iSIC meter is included in Appendix D.
Turbidity readings were collected from approximately mid-depth at
all locations. The specific monitoring locations were adapted based
on field conditions and river flow path. The USEPA OSC was
typically consulted when selecting monitoring locations. The
assessments were relative: downstream data were compared to
concurrent upstream data to
G:\Aproject\Kalamazoo\Plainwell #2\B0064536\00675\Final
Construction Completion Report\Plainwell 2 TCRA Final Construction
Completion Report.doc 3-8 Project Number: B0064536.00675
Plainwell No. 2 Dam Area TCRA Final Construction Completion
Report
identify increases in turbidity. Turbidity monitoring devices with
associated telemetry equipment were installed at the locations
upstream and downstream of the removal area. Four readings were
collected each hour and processed to generate a moving average.
That hourly average was compared to the standard.
A handheld YSI 650 MDS multi-parameter probe was present onsite in
the event one of the automatic meters was to fail. In this event,
workers could collect turbidity readings from the monitoring
location every hour until the automatic meter was repaired. The
turbidity meter was calibrated, operated, and maintained according
to the manufacturer’s instructions and was able to measure
turbidity at a resolution of +/- 1 nephelometric turbidity
unit.
Turbidity readings were collected from all monitoring locations at
the following times:
• Prior to placement of any equipment or materials in a work
area.
• Following placement of equipment and materials but prior to
removal actions.
• Every hour during removal actions.
• At the beginning of each work day and 2 hours after work was
initiated in a given work area.
• At the end of each work day after activities were completed in a
given work area.
The measurements collected at the location 200 feet downstream of
the work area were used as an early warning of potential
exceedances. The measurement collected at the location 300 feet
downstream of the work area was compared against the upstream data.
If the most downstream (usually approximately 300 feet) turbidity
data were two times (2x) the concurrent upstream data, specific
steps were initiated until the exceedance was mitigated to below
the action level. Due to the proximity to the right diversion
structure, turbidity monitoring locations could not be established
300 feet downstream of Removal Area 5A. Turbidity monitoring
locations were installed as far downstream as possible (150 to 200
feet) without compromising worker safety by encroaching upon the
right diversion structure.
Turbidity monitoring records are included in Appendix F. In the
event turbidity reached unacceptable levels (i.e., downstream
turbidity data were 2x the concurrent upstream data), a range of
mitigation measures was implemented based on the magnitude of the
turbidity changes noted.
An inspection of turbidity monitoring devices and resuspension
controls was performed if an elevated turbidity reading was
recorded at the 200 feet downstream location. However, no formal
mitigation measures were performed unless the reading at the
furthest downstream monitoring location exceeded 2x the concurrent
upstream data.
G:\Aproject\Kalamazoo\Plainwell #2\B0064536\00675\Final
Construction Completion Report\Plainwell 2 TCRA Final Construction
Completion Report.doc 3-9 Project Number: B0064536.00675
Plainwell No. 2 Dam Area TCRA Final Construction Completion
Report
Mitigation measures included inspecting resuspended sediment
control systems for visible plumes, inspecting the turbidity meter
to verify proper function, and slowing or halting excavation
activities until turbidity levels returned to acceptable levels.
During high river flow events, crews inspected the turbidity
curtains twice daily and adjusted the turbidity curtains as
needed.
3.3.3.2 Surface Water Samples
Surface water grab samples were collected for PCB analysis near the
turbidity monitoring locations upstream and downstream of the
active removal area on a weekly basis to observe spatial and
temporal trends in PCB concentrations and were not used as a metric
to control the rate of excavation. One grab sample each was
collected from the furthest downstream location (approximately 300
feet downstream) and the upstream location (Figures 4.1 through
4.7). Samples were collected from mid-depth of the river channel
using a Kemmerer™ stainless steel bomb sampler at approximately the
same time for each weekly sampling event (2 hours after the start
of excavation activities). Water quality parameters (temperature,
conductivity, and turbidity) were recorded using an YSI 650R
multi-parameter probe before collecting the sample.
Sampling procedures, preservation and handling, and analytical
protocols for monitoring of PCBs were consistent with USEPA Method
608, with a quantification level of 0.1 microgram per liter (μg/L)
(in accordance with the project-specific QAPP [ARCADIS BBL 2007b]).
Samples were analyzed by TAL. A rinse blank was collected from the
bomb sampler during each sampling event. A duplicate sample and
matrix spike/ matrix spike duplicate samples were collected for one
out of every 20 samples.
Surface water samples were only collected during excavation
activities (September through October 2009 and June through
September 2010). A total of 76 surface water samples (38
upstream/downstream pairs), 5 duplicate samples, and 38 rinse blank
samples were collected.
Surface water sample results are summarized in Table 4 and
laboratory analytical reports are included in Appendix C-4.
PCBs were detected in one sample (TS30143). Sample TS30143 was
collected on October 15, 2009 from the turbidity monitoring
location located 300 feet downstream of Removal Area 3. PCBs were
not detected in any of the rinse blank samples. The PCB detection
was an estimated concentration, as noted by the ‘J’ qualifier. This
qualifier means that PCBs were positively identified at a
concentration above the method detection limit, but below the
quantification limit.
G:\Aproject\Kalamazoo\Plainwell #2\B0064536\00675\Final
Construction Completion Report\Plainwell 2 TCRA Final Construction
Completion Report.doc 3-10 Project Number: B0064536.00675
Plainwell No. 2 Dam Area TCRA Final Construction Completion
Report
3.4 Soil and Sediment Removal
Areas to be removed as a part of the TCRA were delineated in the
Design Report (ARCADIS 2009a) based upon a review of analytical
studies performed on sediments, bank soils, and floodplain
soils.
Background
As described in Section 1.2 of the Design Report, the Plainwell No.
2 Dam Area has been the focus of a series of investigations by
ARCADIS, MDNR (now MDNRE), and USEPA since 2000. The most recent
PCB data were generated during a sampling effort conducted by
ARCADIS between 2008 and 2009. A variety of targeted studies of the
impoundment were also conducted in 2009 to further characterize
site topography, bank stability/disposition, flow hydrodynamics,
equipment accessibility, and habitat quality. The results of these
investigations were used to define the horizontal and vertical
extents of soil excavation. The results of the delineation process
are summarized in Section 1.4 and Drawings SR-1.1 through SR-1.7 of
the Design Report (ARCADIS 2009a). Soil excavation was performed to
these extents and confirmed complete per the requirements of the
Design Report (ARCADIS 2009a).
Excavation Technique
Excavation was performed from the top-of-bank using an open bucket
excavator equipped with a real time kinematic global positioning
system (RTK GPS).
Excavated soil and sediment was loaded into off-road trucks and
hauled to the nearest staging area for temporary storage,
processing and/or reloaded for offsite disposal. Dry material was
loaded directly into gravel-train trucks for transport to the
offsite disposal facility. See Sections 3.5 and 3.6 for additional
information regarding soil and sediment processing and
disposal.
Soil and sediment removal areas were divided into three general
categories:
1. Oxbow Sediments
2. Bank Soils
3. Islands
Sediment and soil removal areas were divided into six general
removal areas, numbered 1 through 6, with Removal Area 1 being the
most upstream removal area and Removal Area 6 being the most
downstream removal area. Removal areas were further subdivided to
facilitate efficiencies during excavation work. The letter “A”
indicates the portion of the removal area
G:\Aproject\Kalamazoo\Plainwell #2\B0064536\00675\Final
Construction Completion Report\Plainwell 2 TCRA Final Construction
Completion Report.doc 3-11 Project Number: B0064536.00675
Plainwell No. 2 Dam Area TCRA Final Construction Completion
Report
located along the northern bank of the river (e.g., 3A), while the
letter “B” indicates the portion of the removal area located along
the southern bank of the river (e.g., 3B). Not all six removal
areas included portions on both sides of the river. If only one
bank was removed, an ‘A’ or ‘B’ notation was not included (e.g.,
Removal Area 6).
Removal activities on the north side of the river were performed in
2009 and removal activities on the south side of the river were
performed in 2010. Soil removal work generally progressed from
upstream to downstream, beginning with Removal Area 1 on the north
side of the river during the 2009 construction season. Soil and
sediment removal work on the south side of the river began with
Island 2, and then generally progressed from Removal Area 3B to
Removal Area 6. The river stationing increased downstream to
upstream, with Station 15+00 located at the downstream end of
Removal Area 6. Stationing is presented in hundreds of feet
upstream of the dam.
Oxbow sediment areas and islands were delineated independently from
bank removal areas. Removal Areas 1 through 6 contained bank soils.
Removal activities in these areas are discussed in the following
sections.
Sediment and soil removal activities were performed over two
construction seasons; from August 2009 through September 2010. 2009
removal activities were performed from September through October
2009; 2010 removal activities were performed from June through
September 2010. Mobilization and demobilization activities occurred
in the intermittent months.
At the completion of construction, approximately 15,700 cy of
material had been removed and disposed at commercial offsite
landfills.
3.4.1 Excavation Confirmation
Confirmation monitoring was performed to verify that the design
specifications had been achieved and varied according to the work
area being monitoring. Confirmation monitoring was conducted as
soon as practical following completion of excavation so that
additional response actions, if necessary, could be taken quickly,
while the equipment was nearby. An RTK GPS- equipped excavator was
used to give preliminary confirmation that excavation was completed
in an area. Confirmation sampling was performed in all removal
areas to verify completeness of excavation.
3.4.1.1 Surface Elevation Confirmation
Excavation of soil was initially confirmed by documenting the final
surface elevation and comparing it to the neat line established in
the Design Report (ARCADIS 2009a). Surface
G:\Aproject\Kalamazoo\Plainwell #2\B0064536\00675\Final
Construction Completion Report\Plainwell 2 TCRA Final Construction
Completion Report.doc 3-12 Project Number: B0064536.00675
Plainwell No. 2 Dam Area TCRA Final Construction Completion
Report
elevation measurements were monitored as described below using a
RTK GPS-equipped excavator.
Excavation of sediment was performed by recording a
pre-construction surface elevation with the RTK GPS and excavating
to the required depth as established in the Design Report (ARCADIS
2009a). The final post-excavation surface elevation was compared to
the pre- construction surface elevation. See Section 3.4.2.1 for
additional information on excavation.
The position of the excavator bucket as it removed sediments was
displayed using a RTK GPS as manufactured by Topcon (Model 3DXi). A
RTK GPS system was mounted on the excavator used during the project
and communicated with a surveyed base station installed in an open
area away from the river. The location of the base station changed
as work progressed through the removal areas.
Three position sensors were mounted on the cab, boom, and bucket of
the excavator. The three sensors worked together to triangulate the
position of the bucket. The signals from these sensors were relayed
to the base station which calculated errors from cover, rainfall,
atmosphere, and other factors to improve accuracy.
3.4.1.1.1 RTK GPS Calibration
Prior to use of the RTK GPS unit, an initial calibration was
completed by the manufacturer’s authorized representative. The
initial calibration included equipment measurements and
installation of the tilt sensors. During removal activities,
vertical and horizontal checks were performed twice daily – once
prior to commencing excavation activities and once during the day.
Vertical and horizontal checks were completed by placing the
excavator bucket on a pre- surveyed check-point located at a
stationary point in the project area.
Additional calibrations were completed by a manufacturer’s
authorized representative if one of the following occurred:
• Within 2 months after initial calibration and at least 2 months
after each follow-up calibration.
• Upon equipment change or modification which affects the tilt
sensor placements, including changes to the excavator bucket.
• When the vertical and horizontal twice daily checks were not
within the specified manufacturer’s vertical tolerance limits of +
0.2 feet.
RTK GPS calibration logs are included in Appendix G.
G:\Aproject\Kalamazoo\Plainwell #2\B0064536\00675\Final
Construction Completion Report\Plainwell 2 TCRA Final Construction
Completion Report.doc 3-13 Project Number: B0064536.00675
Plainwell No. 2 Dam Area TCRA Final Construction Completion
Report
3.4.1.1.2 RTK GPS Data Collection
The vertical and lateral extents of excavation are defined in
Contract Drawings SR1.1 to SR1.7 in the Design Report (ARCADIS
2009a). Cross-sections of the excavation plan were converted to a
three dimensional surface known as a triangular irregular network
(TIN) that was viewed in real-time by the excavator operator.
The display mounted within the cab of the excavator showed the TIN
as a plot of the maximum depth of penetration of the bucket versus
the design neat line. Excavation proceeded until the neat line was
reached.
Although bucket elevation data were displayed in real time, the
data were not collected. Confirmation sampling was performed to
verify that excavation was complete.
3.4.1.2 Confirmation Sampling
Completion of excavation to the extent defined in the Design Report
(ARCADIS 2009a) was confirmed through PCB soil confirmation
sampling for all excavation areas. The purpose of the confirmation
sampling was to verify that no unacceptable PCB concentrations were
left behind within the excavation boundaries. Therefore,
confirmation sampling affected the depth of excavation but did not
affect the lateral extent of removal which was determined using
historical data before completion of the Design Report (ARCADIS
2009a). The PCB sampling performance standard was generally 5
milligrams per kilogram (mg/kg). The PCB confirmation sampling
performance standard in the oxbow was 1 mg/kg. Confirmation sample
locations for each removal area (as appropriate) were surveyed to
document sample locations.
3.4.2 Removal Areas
The definition of each removal area and the excavation confirmation
protocol performed varied for the three general categories of soil
and sediment removed. The oxbow was excavated and sampled according
to different methodology than the island and bank soil areas.
3.4.2.1 Oxbow
The oxbow area is located between Removal Areas 5B and 6. Material
removed in the oxbow area included sediment in the mouth and
channel of the oxbow. Due to limited pre-construction survey data,
a neat line was not used to control the vertical extent of
excavation in the oxbow. Instead, the sediment surface in the oxbow
was surveyed immediately prior to excavation activities. The
surface was then excavated from the surveyed pre-construction
sediment elevation to the cut depth established in the Design
Report (ARCADIS 2009a). Post-excavation sediment surface elevation
was collected to confirm that excavation was complete.
Excavation
G:\Aproject\Kalamazoo\Plainwell #2\B0064536\00675\Final
Construction Completion Report\Plainwell 2 TCRA Final Construction
Completion Report.doc 3-14 Project Number: B0064536.00675
Plainwell No. 2 Dam Area TCRA Final Construction Completion
Report
was initially considered complete when the removal was performed to
the prescribed excavation depth based on the maximum depth of
penetration of the bucket as measured by the RTK GPS.
Confirmation sampling grids were generally established in the oxbow
area in 50-foot lengths that spanned the width of the sediment
removal area. At the mouth of the oxbow, the confirmation sampling
grids were adjusted to be approximately 50 feet long and 50 feet
wide (2,500 square feet [sf]). Due to the uneven dimensions of the
oxbow, some confirmation sampling grids were modified to different
configurations. The areas of these units did not exceed 2,500
sf.
Each confirmation grid was divided into six equal-sized cells
(approximately 25 feet by 17 feet). Each of the six cells was
divided into nine equally sized sub-sample locations. These
locations were assigned a unique number from 1 to 9. A random
number generator was used to generate a numerical value between 1
and 9 for each of the six cells, and the sub-sample was collected
from the corresponding numerical location. Sediment samples were
collected with a hand- driven push core from a depth of
approximately 6 inches below the sediment surface. Soft sediment
depth data were also collected by pushing a core to refusal while
collecting samples or by using a rod to measure thickness. Water
overlying the sediment in the core was decanted from the core
sample prior to compositing the six sub-samples for submittal to
the laboratory for PCB analysis. If the laboratory data confirmed
that the PCB concentration for the composite sample was less than
or equal to 1.0 mg/kg, the excavation of the unit was considered
complete and no additional excavation was required. If the PCB
concentration was greater than or equal to 1.0 mg/kg, an additional
6 inches was removed from the entire confirmation unit.
After additional excavation of sediments, sub-samples were
collected from a random location within each of the six cells,
composited, and submitted for laboratory PCB analysis. If the PCB
concentration from the second round of sampling was less than or
equal to 5.0 mg/kg, no further excavation of the area was required.
However, if the PCB concentration remained greater than 5.0 mg/kg,
an additional 6 inches was removed and the sampling process and
analysis repeated at the direction of the USEPA OSC.
In some oxbow confirmation sampling grids, all soft sediment was
removed down to the native riverbed. This generally occurred when
excavation to the TIN was within 6 inches of the riverbed and
excavating additional material was more time and cost effective
than sampling the area and waiting for analytical data. The native
riverbed consisted of sand and cobbles and could not be sampled. In
these areas, the USEPA OSC and ARCADIS probed the area to determine
if all soft sediment had been removed. If the USEPA OSC confirmed
that all soft sediment had been removed and the area could not be
sampled, excavation in the area was considered complete. Any soft
sediment observed during probing was removed until the
G:\Aproject\Kalamazoo\Plainwell #2\B0064536\00675\Final
Construction Completion Report\Plainwell 2 TCRA Final Construction
Completion Report.doc 3-15 Project Number: B0064536.00675
Plainwell No. 2 Dam Area TCRA Final Construction Completion
Report
USEPA OSC confirmed excavation to be complete in the area. See
Section 3.4.4.7 for additional information regarding where sediment
was excavated to native riverbed.
3.4.2.2 Bank Soil Removal Areas
Bank soil removal areas included soil materials located on the face
of the bank between the toe- of-slope and top-of-bank, and soil
materials located within a distance 30 feet landward from the
median water line. A floodplain area adjacent to Removal Area 5B
was included in the TCRA due to PCB concentrations identified
during investigation activities. A neat line was established to
delineate the lateral and vertical extent of excavation. The
lateral and vertical extent of excavation was based on PCB sampling
data as defined in Section 2.1 of the Design Report (ARCADIS
2009a).
Bank soils were removed and river banks were excavated at slopes no
steeper than 3H:1V (horizontal: vertical) to reduce the potential
for future erosion and sloughing, and to improve conditions for
restored habitat features. Approximately 10,000 linear feet of
river bank was addressed as part of the TCRA. The depth of soil
removal in each targeted area varied and is depicted on Figures 5.1
through 5.17.
For the bank and floodplain soil removal areas, a nominal 75-foot
long by 30-foot wide confirmation grid divided into six 25-foot by
15-foot cells was established. As soon as practical following
excavation of a bank or floodplain soil confirmation grid, a
sub-sample was collected from a random location within each of the
six cells. Each of the six cells was divided into nine equally
sized sub-sample locations. These locations were assigned a unique
number from 1 to 9. A random number generator was used to generate
a numerical value between 1 and 9 for each of the six cells, and
the sub-sample was collected from the corresponding numerical
location. Samples did not include sediment from the toe-of-bank.
The sub-sample location could be modified in the field (at the
direction of the USEPA OSC) if the majority of the surface area of
a cell contained materials that appeared to be the materials
targeted for removal. Soil samples were collected from the 6-inch
depth increment below the floor of the excavation, composited, and
submitted to the laboratory for PCB analysis. If the laboratory
data confirmed that the PCB concentration for the composite sample
was less than or equal to 5.0 mg/kg, the excavation of the
confirmation grid was considered complete and no additional
excavation was required. If the PCB concentration was greater than
5.0 mg/kg, an additional 6 inches was removed from the entire
confirmation grid. Soil samples were again collected from a random
location within each of the six cells, composited, and submitted
for laboratory PCB analysis. If the PCB concentration from the
second round of sampling was less than or equal to 5.0 mg/kg, no
further excavation of the area was required. However, if the PCB
concentration remained greater than 5.0 mg/kg, the confirmation
grid was backfilled and restored unless USEPA and Georgia-Pacific
determined that additional excavation should be conducted.
G:\Aproject\Kalamazoo\Plainwell #2\B0064536\00675\Final
Construction Completion Report\Plainwell 2 TCRA Final Construction
Completion Report.doc 3-16 Project Number: B0064536.00675
Plainwell No. 2 Dam Area TCRA Final Construction Completion
Report
At the request of USEPA, split samples were collected from each of
the individual sub-samples at 5% of the confirmation units prior to
the homogenization process. The split samples were stored in
accordance with the procedures identified in the Multi-Area QAPP
(ARCADIS BBL 2007b) for analysis at the conclusion of the removal
action. The confirmation sampling grids where sub-samples were
split were identified prior to the start of removal activities each
construction season. The selection was designed to obtain a
distribution of confirmation units for this sampling purpose over
the entire project area. Split samples were collected from Removal
Area 2 Grid 3, Removal Area 3A Grids 10 and 13, Removal Area 4A
Grid 2, Island 2 Grids 8 and 21, Removal Area 4B Grid 7, and
Removal Area 6 Grid 5. The split samples were analyzed and compared
to the composite data within 60 days after the TCRA was completed
for use in the future evaluation of removal and/or remedial
projects. The results of the sampling are included in Table 11.
Laboratory analytical reports are included in Appendix C-3.
3.4.2.3 Island Removal Areas
Soil materials from two islands (Islands 1 and 2) were also removed
as part of the TCRA. Islands 1 and 2 were excavated to a neat line
established based on pre-construction sampling data. Island areas
were excavated to the neat line and confirmation samples were
collected according to the bank soil sample protocol described in
Section 3.4.2.2.
3.4.2.4 Confirmation Sampling Surveying and Analytical Data
Sample locations were surveyed using the State Plane, North
American Datum 1983 (NAD 83), Michigan South Zone for horizontal
datum and National Geodetic Vertical Datum 29 for vertical datum.
All analytical laboratory sampling and analysis were conducted in
accordance with the project-specific QAPP (ARCADIS BBL 2007b). Soil
samples were analyzed by KAR Labs and TAL for PCBs. The results of
soil sampling are included on Figures 6.1 through 6.11 and Table 5.
Laboratory analytical reports are included in Appendix C-3.
3.4.3 2009 Removal Activities
2009 removal activities included soil removal at Removal Area 1, 2,
3A, 4A, and 5A. Approximately 4,450 cy of material was disposed of
at offsite commercial landfills. Excavation occurred upstream to
downstream. The following sections summarize removal activities in
each area. Bank stabilization activities and habitat reconstruction
are discussed in Section 3.7.
3.4.3.1 Clearing and Grubbing
Vegetation was cleared from Removal Areas 1 through 5A in August
and September 2009 to provide access for construction
activities.
G:\Aproject\Kalamazoo\Plainwell #2\B0064536\00675\Final
Construction Completion Report\Plainwell 2 TCRA Final Construction
Completion Report.doc 3-17 Project Number: B0064536.00675
Plainwell No. 2 Dam Area TCRA Final Construction Completion
Report
3.4.3.2 Removal Area 1
A flow deflector wall was installed at the upstream portion of
Removal Area 1. Turbidity curtains were installed around Grids 1
through 8 and then Grids 9 through 12 in September 2009 to control
resuspended sediments. Excavation of bank soil in Removal Area 1
was performed in September and October 2009. Excavated material was
removed from this area and transported to Staging Area 3 for
processing and disposal.
Approximately 1,050 cy of material from 840 linear feet of bank was
excavated to the neat line from Removal Area 1. The removal area
was divided into 12 confirmation sampling grids. Laboratory data
confirmed that PCB concentrations in one grid (Grid 6) exceeded the
PCB performance standard of 5 mg/kg. See Figure 6.11 and Table 5
for confirmation sampling grid locations and results. Laboratory
analytical data are included in Appendix C-3.
The PCB concentration detected in sample TS20279 (6.9 mg/kg),
collected from Removal Area 1, Grid 6 on September 24, 2009,
exceeded the performance standard of 5 mg/kg. An additional 6
inches of material were removed on October 2, 2009 and the grid was
resampled (TS20294). PCBs were not detected in sample TS20294 (0.33
mg/kg U2). Therefore, additional excavation was not warranted, and
removal in the area was considered complete.
3.4.3.3 Removal Area 2
A flow deflector wall was installed at the upstream portion of
Removal Area 2. Turbidity curtains were installed around Grids 1 th