File 7 Floodrisk Drainage Report

Embed Size (px)

Citation preview

  • 8/13/2019 File 7 Floodrisk Drainage Report

    1/72

    Shelford Road,

    Radcliffe on Trent

    Flood Risk Assessment and Drainage Strategy

    for

    William Davis

  • 8/13/2019 File 7 Floodrisk Drainage Report

    2/72

    BSP Consulting 12568/FRA/DS/Rev AShelford Road, Radcliffe on Trent Flood Risk Assessment and Drainage Strategy

    Flood Risk Assessment and Drainage Strategy

    Shelford Road, Radcliffe on Trent

    Prepared By:

    Tony Goddard BEng (Hons) CEng MICEAssociate Director

    [email protected]

    Checked By:

    Matthew Viggars MEng (Hons) CEng MICE

    Chartered Civil Engineer

    [email protected]

    Revision: - A

    Contents

    Executive Summary

    1.0 Introduction

    2.0 Background Information

    3.0 Flood Risk Assessment and Drainage Strategy

    4.0 Recommendations

    Appendix A Detailed Site Location Plan

    mailto:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]:[email protected]
  • 8/13/2019 File 7 Floodrisk Drainage Report

    3/72

    BSP Consulting 12568/FRA/DS/Rev AShelford Road, Radcliffe on Trent Flood Risk Assessment and Drainage Strategy

    Executive Summary

    Introduction BSP Consulting has been commissioned by William Davis to undertake a Flood Risk

    Assessment and Drainage Strategy for the development of land at Shelford Road,

    Radcliffe on Trent, Nottinghamshire. This Flood Risk Assessment has been prepared

    in accordance with the Department for Communities and Local Government (DCLG)

    publication Technical Guidance to the National Planning Policy Framework

    Existing Site

    Conditions

    The site is currently open fields and farm buildings. An unnamed watercourse,

    Stream A, passes east to west along the southern edge of the site. Site levels vary

    from over 49.5m AOD in the north east to 31m AOD at the outfall of Stream A in the

    south west. There is a fall of 3m along Stream A at the site.Development

    Description and

    Planning Context

    The development proposals are for the construction of residential dwellings,

    attenuation ponds, adoptable roads and sewers, hardstandings and soft landscaping. In

    accordance with the National Planning Policy Framework, the proposed residential

    use falls under the more vulnerable category in terms of flood risk.

    Definition of Flood

    Hazard

    The River Trent is the primary Main River in the Nottingham area. Land adjacent the

    River Trent at the point where Stream A outfalls is at a level of approximately 20m

    AOD. This is some 11m below the lowest level of Stream A on site. Stream A has the

    potential to be the primary source of flood risk to the lower reaches of the site.

    Probability The EA website indicative flood mapping confirms that site would not be at risk offlooding in a 0.1% (1:1000 year) probability flood event due to flooding from the

    River Trent or other significant fluvial sources. A detailed modelling study of Stream

    A has been undertaken to confirm the flood risk associated with this watercourse. The

    modelling results show only the south west of the site is likely to be subject to

    flooding in the 1:100 year plus climate change flood emanating from Stream A.

    Climate Change The implications of climate change are taken into account in the flood modelling

    exercise.

    Detailed

    DevelopmentProposals

    The National Planning Policy Framework states that developments of a more

    vulnerable category such as the proposed residential use are appropriate within FloodZone 1.

    Flood Risk

    Management

    Measures

    It is recommended that the finished floor levels are set at least 600mm above the

    1:100 year plus climate change flood levels at the adjacent modelled watercourse

    sections. SuDS techniques will be employed to provide a minimum of two treatment

    trains of water quality improvement prior to the final discharge to Stream A. SuDS

    features such as permeable paved private drives/parking courts and filter strips/filter

    drains are proposed for use as source control and treatment features for surface water

    runoff. Site control will be provided by two linked attenuation ponds that will balance

    all surface water from the impermeable development areas back to the 1 in 1 yeargreenfield runoff rate. The ponds are indicated to be at the same invert level and are

    to be linked by a pipe or narrow swale.

    Off Site Impacts The proposed development surface water discharge rate will be limited to the existing

    1 in 1 year greenfield runoff rate prior to entry to Stream A in a 1 in 100 year plus30% climate change rainfall event therefore the proposed development reduces

    fluvial flooding problems adjacent to or downstream of the site for the proposed

  • 8/13/2019 File 7 Floodrisk Drainage Report

    4/72

    BSP Consulting 12568/FRA/DS/Rev AShelford Road, Radcliffe on Trent Flood Risk Assessment and Drainage Strategy

    drawing 12568/100 and included in Appendix D.

    Foul water from the proposed development will be drained to the existing adoptedfoul sewerage in Shelford Road to the north of the site.

    1.0 INTRODUCTION

    1.1 TERMS OF REFERENCE

    1.1.1 BSP Consulting has been commissioned by William Davis to undertake a Flood

    Risk Assessment and Drainage Strategy for the development of land at ShelfordRoad, Radcliffe on Trent, Nottinghamshire.

    1.1.2 In the preparation of this report, consultations have been undertaken with the

    Environment Agency (EA), Rushcliffe Borough Council (RBC) and Severn Trent

    Water (STW). A site visit was made in November 2012, to walk the local

    watercourse catchment, to assess the local topography and current site use. The

    Greater Nottingham Strategic Flood Risk Assessment 2010 has also been referred

    to.

    1.1.3 This Flood Risk Assessment has been prepared in accordance with the Department

    for Communities and Local Government (DCLG) publication Technical Guidance

    to the National Planning Policy Framework while retaining the layout as

    recommended in the superseded Planning Policy Statement 25 (PPS25)

    Development and Flood Risk.

    1.1.4 This report has been produced on behalf of the client, William Davis, and no

    responsibility is accepted to any third party for all or any part. This report should

    not be relied upon or transferred to any other parties without the express written

    authorisation of BSP Consulting. If any unauthorised third party comes into

    possession of this report, they rely on it at their own risk and the authors owe them

    no duty of care or skill.

    1.2 NATIONAL PLANNING POLICY FRAMEWORK

    1.2.1 The National Planning Policy Framework was published on 27 March 2012. This

    replaces Planning Policy Statement 25: Development and Flood Risk.

    1.2.2 Technical Guidance to the National Planning Policy Framework has been

  • 8/13/2019 File 7 Floodrisk Drainage Report

    5/72

    BSP Consulting 12568/FRA/DS/Rev AShelford Road, Radcliffe on Trent Flood Risk Assessment and Drainage Strategy

    2.0 BACKGROUND INFORMATION

    2.1 SITE LOCATION, DESCRIPTION AND DETAILS2.1.1 Figure 2.1 below indicates the location of the site; a more detailed site plan is

    located in Appendix A. A site visit was made in November 2012, to walk the local

    watercourse catchment, to assess the local topography and current site use.

    Ordnance Survey Crown copyright 2010 All rights reserved. Licence number 100041272

    Figure 2.1 Shelford Road, Radcliffe on Trent - Site Location Plan2.1.2 The approximate site boundary is outlined in red on Figure 2.1 above. The overall

    site occupies an area of approximately 18.6 hectares and is located to the south of

    Shelford Road, Radcliffe on Trent, Nottinghamshire at OSNGR 465600E340000N. The site is currently open fields and farm buildings. An unnamed

    watercourse, Stream A, passes east to west along the southern edge of the site

    indicated in Figure 2.1 above.

    2 1 3 The topographical survey of the site in Appendix B indicates that all of the land

    RiverTrent

    Site

    Unnamed

    Watercourse

    (Stream A)

  • 8/13/2019 File 7 Floodrisk Drainage Report

    6/72

    BSP Consulting 12568/FRA/DS/Rev AShelford Road, Radcliffe on Trent Flood Risk Assessment and Drainage Strategy

    2.1.6 Site and Watercourse Photographs

    Figure 2.2 Site frontage onto Shelford

    Road. (Looking south west)

    Figure 2.3 General site view across the

    centre of the site. (Looking north east)

    Figure 2.4 Culvert outlet to site from

    under the railway. (Looking east)

    Figure 2.5 View downstream at Section

    18. (Looking west)

  • 8/13/2019 File 7 Floodrisk Drainage Report

    7/72

  • 8/13/2019 File 7 Floodrisk Drainage Report

    8/72

    BSP Consulting 12568/FRA/DS/Rev AShelford Road, Radcliffe on Trent Flood Risk Assessment and Drainage Strategy

    Borough Council and Nottinghamshire County Council. This assessment seeks to

    draw together the relevant information from these sources and to collate this withthe findings of our investigations, analysis and discussions to assess the flood risk

    at this site.

    3.0 FLOOD RISK ASSESSMENT AND DRAINAGE STRATEGY

    3.1 DEVELOPMENT DESCRIPTION AND PLANNING CONTEXT

    3.1.1 The development proposals are for the construction of residential dwellings,

    attenuation ponds, adoptable roads and sewers, hardstandings and soft

    landscaping. A proposed master planning layout is included in Appendix C.

    3.1.2 The local area benefits from a Strategic Flood Risk Assessment. This assessment is

    the Greater Nottingham Strategic Flood Risk Assessment October 2010. This

    assessment was produced by Black & Veatch Limited for the Greater Nottingham

    SFRA Partnership. The GNSFRA covered the River Trent but did not include any

    modelling of Stream A.

    3.1.3 In accordance with the National Planning Policy Framework, the proposed

    residential use falls under the more vulnerable category in terms of flood risk.

    3.2 DEFINITION OF THE FLOOD HAZARD

    3.2.1 The potential sources of flooding in the vicinity of the site are as detailed below:

    3.2.2 Fluvial Flood Risk

    3.2.3 The River Trent is the primary Main River in the Nottingham area. Land adjacent

    the River Trent at the point where Stream A outfalls is at a level of approximately

    20m AOD. This is some 11m below the lowest level of Stream A on site.

    3.2.4 Figure 3.1 below indicates the indicative floodplain associated with the River

    Trent. The site can be seen to lie outside of the River Trent floodplain. This main

    river can therefore be discounted as a significant source of flood risk to the site.

    3 2 5 St A fl t t t l th th d f th it d h th

  • 8/13/2019 File 7 Floodrisk Drainage Report

    9/72

    BSP Consulting 12568/FRA/DS/Rev AShelford Road, Radcliffe on Trent Flood Risk Assessment and Drainage Strategy

    Figure 3.1 Shelford Road, Radcliffe on TrentEnvironment Agency Flood Mapping

    3.2.7 Tidal Flood Risk

    3.2.8 The site is at a minimum level of approximately 31m above mean sea level. The

    site is therefore not at risk of flooding from tidal sources.

    3.2.9 Surface Water Flood Risk

    3.2.10 The land to the North of the site falls towards the site but is separated from the site

    by Shelford Road. The area to the north is insubstantial and does not have the

    potential to generate any significant volume of surface water following majorrainfall events.

    3.2.11 Any overland flow from the land to the north would be channelled away from the

    site along Shelford road towards the west.

    Site

  • 8/13/2019 File 7 Floodrisk Drainage Report

    10/72

    BSP Consulting 12568/FRA/DS/Rev AShelford Road, Radcliffe on Trent Flood Risk Assessment and Drainage Strategy

    flowing across the site. The topographical survey does not indicate any notable

    low spot at this location. This localised feature is therefore not of any significanceto the proposed development. The site is therefore not at risk of significant

    flooding from surface water runoff from adjacent land.

    3.2.14 Flood Risk from Ground Water

    3.2.15 With regard to groundwater the phase 1 SI confirms the following. The data

    indicates that there is a very high likelihood of persistent or seasonably shallow

    groundwater across the southern part of the site which may impact on soakawaydrainage.

    In addition, the data indicates that the bedrock deposits are likely to be poorly

    draining below the site.

    3.2.16 No springs were noted at the ground surface during our site walkover. It is

    therefore confirmed that the site is therefore not at significant risk of flooding from

    ground water.

    3.2.17 Flood Risk from Sewers and Infrastructure

    3.2.18 The site lies upstream of the local developed areas therefore any flooding from

    sewerage or water utilities would be conveyed away from the site towards the

    west. A 450mm diameter surface water sewer is noted to run along the western site

    boundary. This is understood to be a highway drain that drains part of ShelfordRoad. This sewer would be maintained and incorporated into the development

    proposals.

    3.2.19 The site is not within close proximity of any reservoirs or wet process industrial

    works. The sewers and infrastructure flood risk source can therefore be discounted

    as a significant source of flood risk to the site.

    3.3 PROBABILITY

    3.3.1 The EA website indicative flood mapping confirms that site would not be at risk of

    flooding in a 0.1% (1:1000 year) probability flood event due to flooding from the

    River Trent or other significant fluvial sources. This map shows the indicative

    t t f th t l fl d l i if th fl d d f t i th

  • 8/13/2019 File 7 Floodrisk Drainage Report

    11/72

    BSP Consulting 12568/FRA/DS/Rev AShelford Road, Radcliffe on Trent Flood Risk Assessment and Drainage Strategy

    3.3.4 Watercourse Description

    3.3.4.1 Stream A, as it exits the site, has a catchment area of about 3.24km2. The upstream

    catchment is mainly arable land with some urban contribution. The bed and stream

    channel are clearly defined. There is a hedge along both sides of Stream A but the

    main channel is not heavily overgrown.

    3.3.4.2 At the east of the site Stream A emerges from a brick culvert that conveys the

    stream under the adjacent railway.

    3.3.4.3 At the western site perimeter Stream A flows into a concrete culvert which flows

    west, to the south of 87 Clumber Drive. The stream remains in culvert until it

    emerges 320m to the west of the site.

    3.3.5 Hydrology

    3.3.5.1 No gauged flow data is available for Stream A.

    3.3.5.2 In order to make an estimation of the likely flood flow rates from this un-gauged

    catchment a hydrological analysis has been carried out using the FEH Revitalised

    Rainfall Run-off method (ReFH). This analysis has been undertaken for the

    watercourse as it exits the site towards Clumber Drive. The catchment area

    includes for all of the upstream rural and urbanised areas to this point.

    3.3.5.3 This methodology was selected on the basis that the catchment is un-gauged andthere are no local and suitable hydrologically similar sites available to act as a

    donor for refining the Qmed estimate and growth curve. A summary of the peak

    flow results are shown in Table 1 below with full calculations contained in

    Appendix D.

    Table 1Estimated Watercourse Flow Rates

    Flood Return Period Flood Flow Rate (m3/s)1:2 Year 0.83

    1:30 Year 1.72

    1:100 year 2.29

    1:100 year +20% 2.75

    1:1000 4 19

  • 8/13/2019 File 7 Floodrisk Drainage Report

    12/72

    BSP Consulting 12568/FRA/DS/Rev AShelford Road, Radcliffe on Trent Flood Risk Assessment and Drainage Strategy

    3.3.5.6 None of the catchment descriptors have been altered as all appear to be appropriatefor the catchment. These are listed in Appendix D.

    3.3.5.7 We have queried the connectivity of the area of the Harlequin, to the south of the

    A52, which is indicated as contributing to the catchment. This 0.21km2urbanised

    area is remote from the site. It is separated from the site by both the A52 and the

    railway. Severn Trent Water sewer records indicate only foul sewerage in this

    area. Discussions with an experienced local Municipal Engineer have however

    confirmed that the highways in this area are drained to a surface water sewer thatdischarges to Stream A just upstream of the culvert under the railway. This

    arrangement has been verified during a second site visit.

    3.3.5.8 The newer development at Hudson Way, to the north of the A52 is drained by a

    surface water network that is noted to be constructed using oversized pipes to

    attenuate flows.

    3.3.5.9 As URBEXT is less than 0.125 the winter season has been used in accordance with

    CEH guidance. All other ReFH design standards have been used in the

    calculations.

    3.3.6 Hydraulic Model

    3.3.6.1 A steady state one dimensional mathematical hydraulic model of the watercourse

    has been constructed using ISIS version 3.6. This modelling software has beenchosen as it is accepted by the Environment Agency and is widely used within the

    industry.

    3.3.6.2 Cross sections of Stream A have been surveyed by BluePlan. The model extends

    from the culvert outlet to site from under the railway in the east to 53m

    downstream of the western edge of the site. Sections and the section locations are

    illustrated on drawing 1627Sectionsand drawing 1627Topographical Survey

    included within Appendix B.

    3.3.6.3 The farm access bridge downstream of Section 11 has only been modelled as a

    structure in the 1:1000 year event (with no culvert downstream for model stability

    reasons) as the bridge soffit is above all other modelled flood levels at this point.

    Th t t h j t t f S ti 2 h t b d ll d th

  • 8/13/2019 File 7 Floodrisk Drainage Report

    13/72

    BSP Consulting 12568/FRA/DS/Rev AShelford Road, Radcliffe on Trent Flood Risk Assessment and Drainage Strategy

    3.3.6.5 Mannings n values for the circular concrete culvert has been taken as 0.010 in

    accordance with the CIRIA Culvert Design and Operation Guide 2010.

    3.3.6.6 A ReFH hydrograph was introduced as the upstream boundary and flows were

    generated by the ISIS software for the peak outflow at the required return periods.

    The flow plots were checked for each return period and these all correlated with

    the CEH ReFH Spreadsheet results.

    3.3.6.7 The downstream culvert was initially included in the model at a length of 320m

    but the model was very unstable. The culvert operates under entry controltherefore the culvert has been shortened to 53m. This should not affect the

    accuracy of the final results. Four arbitrary river sections at the outfall of the

    model and replicated sections have been added in line with ISIS guidance.

    3.3.6.8 A Round Nosed Broad Crested Weir with a crest level of 33.150m was introduced

    in parallel with the downstream culvert to represent the potential overland flood

    flow route that exists in the more onerous flood flow events between the culvert

    entry and Clumber Drive.

    3.3.6.9 The downstream boundary has been taken as the normal flow depth for the

    gradient of the culvert (1:122). As the culvert is laid at an average gradient of

    1:122 for the following 267m downstream this is a reasonable assumption.

    3.3.7 Modelling Results

    3.3.7.1 The ISIS model has been run under steady state conditions to generate water levels

    for the 1:2year(Qmed), 1:30year, 1:100year, 1:100year+20% climate change and

    1:1000 year floods. Full results for these model runs are included within Appendix

    D. Figure 3.2 below shows the results for the long section along the watercourse

    adjacent to the site for the 1:100year+20% climate change flood.

    Table 2Estimated Watercourse Flood Levels at Section 1

    Flood Return Period Peak Flood Level

    (mAOD)

    1:2 year 31.876

    1: 30 year 32.622

    1:100 year 33.342

  • 8/13/2019 File 7 Floodrisk Drainage Report

    14/72

    BSP Consulting 12568/FRA/DS/Rev AShelford Road, Radcliffe on Trent Flood Risk Assessment and Drainage Strategy

    Figure 3.2- Modelling Results Long Section1:100year+20% climate change Peak Stage

    3.3.7.3 The model was unstable when the bridge unit was added at Section 11 so this was

    modelled separately for the 1:1000 year event without the downstream culvert.

    Section 11 is sufficiently remote that it is unaffected by the backing up of flows at

    the culvert entry. The 1:1000 year model run indicated minor afflux at theupstream bridge face but no overtopping. A long section indicating this portion of

    the watercourse in the 1:1000 year modelled event is indicated below in Figure

    3.3.

  • 8/13/2019 File 7 Floodrisk Drainage Report

    15/72

    BSP Consulting 12568/FRA/DS/Rev AShelford Road, Radcliffe on Trent Flood Risk Assessment and Drainage Strategy

    3.3.7.4 No flooding is modelled to occur on site other than at the extreme south west of

    the site.

    3.3.7.5 The modelled flood contours are included on the modelled flood extents plan

    included in Appendix D.

    3.3.8 Sensitivity Analysis

    3.3.8.1 Unfortunately no historical data is available to calibrate the model. The only

    reference to potential flooding of Stream A is contained in the GNSFRA at Table6.1 where under a reference to Clumber Drive, Radcliffe on Trent it states Thedyke on the field side of Clumber Drive overflowed into the fields and up to the

    properties but did not affect them. This entry is referenced to the Planning

    Department at Rushcliffe Borough Council. No entry has been made by Radcliffe

    on Trent Parish Council regarding this issue. We have therefore performed a

    sensitivity analysis on the model variables.

    3.3.8.2 Mannings n has been estimated for the channel based upon recommendations in

    technical literature. We have therefore carried out a sensitivity analysis on the

    value of n by +/-20%, the results are shown within Table 3 below for the 1:100

    year flood, full results can be found in Appendix D.

    3.3.8.3 The results of this sensitivity analysis show that a 20% change in the value of ndoes not cause a change in the water level at the critical culvert entry section and

    does not cause any significant change in modelled flood extents along the model.

    It is therefore considered that the hydraulic model is not sensitive to changes in

    mannings n and that the estimated values provide a robust assessment. This is

    t lik l d t th d i f th d t l t th h d li t

    Table 3Mannings n Sensitivity Analysis

    Water Level (m AOD) 1:100 yr flood

    Cross Section n -20% Existing n n +20%

    1 33.342 33.342 33.342

  • 8/13/2019 File 7 Floodrisk Drainage Report

    16/72

    BSP Consulting 12568/FRA/DS/Rev AShelford Road, Radcliffe on Trent Flood Risk Assessment and Drainage Strategy

    Table 4Downstream Boundary Sensitivity Analysis

    3.4 CLIMATE CHANGE

    3.4.1 Climate change is recognised as a factor for consideration in terms of its effects on

    flood risk. This issue affects the local catchment from fluvial sources in as much as

    fluvial flood flows are estimated to increase by up to 20% over the next 100 years.

    3.4.2 The implications of climate change have been taken into account in the modelling

    work that has been carried out in the discussions on probability above.

    3.4.3 The proposed surface water drainage system should be designed to accommodate

    the 1 in 30 year rainfall event without any surface water flooding and should be

    capable of retaining the 1 in 100 year plus climate change storm event on site

    without flooding any buildings. Climate change should be allowed for in the

    detailed surface water design calculations as an additional 30% on the modelled

    rainfall intensity.

    3.5 DETAILED DEVELOPMENT PROPOSALS

    3.5.1 The proposed development and vulnerability classification are discussed in Section

    3.1 above. A draft master planning layout plan is included in Appendix C.

    3.5.2 The National Planning Policy Framework states that developments of a more

    vulnerable category such as the proposed residential use are appropriate withinFlood Zone 1.

    3.6 FLOOD RISK MANAGEMENT MEASURES

    3 6 1 E i ti Fl d D f d St t

    Water Level

    (m AOD) 1:100 yr flood

    Cross Section Existing DS Boundary 1:1000

    1 33.342 33.342

  • 8/13/2019 File 7 Floodrisk Drainage Report

    17/72

    BSP Consulting 12568/FRA/DS/Rev AShelford Road, Radcliffe on Trent Flood Risk Assessment and Drainage Strategy

    site in its present form and it is intended that the development proposals will

    enhance the ecological value of this watercourse by developing the woodland

    buffer and landscaping as noted on the proposed masterplan in Appendix C.

    3.6.2 Proposed Site Development and Finished Floor Levels

    3.6.2.1 The development proposals are for the construction of residential dwellings,

    adoptable roads and sewers, hardstandings and soft landscaping. It is

    recommended that the finished floor levels are set at least 600mm above the 1:100

    year plus climate change flood levels at the adjacent modelled watercoursesections. As the fields fall relatively steeply towards the south of the site it is likely

    that floor levels will be set higher than these levels for other practical reasons.

    3.6.3 Sustainable Site Drainage Systems

    3.6.3.1 The existing site can be seen to be almost entirely farm land. The current runoff

    regime is therefore that of a greenfield site. The Phase 1site investigation suggests

    that the superficial soils will be head deposits (mixed clays, silts, sands andgravels) with red brown clays, mudstones, siltstone and sandstone beds with some

    gypsum veins.

    3.6.3.2 No intrusive investigations have been undertaken however on the basis of the

    available information the Phase 1 site investigation concludes that Preliminary

    assessment indicates the soils generally present below the site are unlikely to

    prove suitable for soakaway drainage.

    3.6.3.3 The existing runoff regime from the 18.6 ha site has been evaluated in accordance

    with the ICOP for SUDS. The 1 in 1 year greenfield site peak runoff rate for this

    site area is 43.9 l/s. A copy of the greenfield runoff calculations are included in

    Appendix F. An approximate evaluation of the likely site drainage area has been

    carried out at an estimated level of impermeability of 60% of the total site area.

    This equates to an impermeable area of 11.16 ha.

    3.6.3.4 At this stage it is proposed that surface water runoff from the proposed

    development will be drained from the proposed impermeable areas utilising, where

    possible, SuDS techniques but not employing infiltration techniques unless this

    proves to be viable following further investigation. SuDS techniques will be

    l d t id i i f t t t t t i f t lit

  • 8/13/2019 File 7 Floodrisk Drainage Report

    18/72

    BSP Consulting 12568/FRA/DS/Rev AShelford Road, Radcliffe on Trent Flood Risk Assessment and Drainage Strategy

    A. The preliminary design calculations associated with these ponds are included in

    Appendix F. These calculations indicate that the ponds have sufficient capacity to

    attenuate the 1 in 100 year plus 30% climate change rainfall event.

    3.6.3.6 As indicated on drawing 12568/100 the ponds are located in an elevated location

    adjacent to Stream A. The proposed ponds lie outside of the modelled flood

    extents associated with Stream A. The precise detailing of the ponds is not fixed at

    this stage but they are to be set out as linear features to give enhanced water

    quality benefits in line with CIRIA recommendations.

    3.6.4 Foul Water Drainage

    3.6.4.1 The site is green field in its predevelopment state therefore there is no current

    discharge of foul water from the site.

    3.6.4.2 Severn Trent Water (STW) have been consulted and have provided a preliminary

    developer enquiry response that confirmed that sufficient foul water capacity may

    exist within the existing network and waste water treatment works but that thiswould need to be verified by further detailed modelling. A copy of this response is

    included in Appendix E.

    3.6.4.3 STW were subsequently engaged to model the impact of the proposed

    development. This study concluded that the proposed development presents a low

    risk to the existing adopted sewer network. A copy of the STW Sewer Capacity

    Assessment is included in Appendix E.

    3.6.4.4 Foul water from the proposed development will therefore be drained under gravity

    to an adoptable pumping station at the south of the site. From here it will be

    pumped to the existing adopted foul sewerage in Shelford Road to the north of the

    site.

    3.7 OFF SITE IMPACTS

    3.7.1 The proposed development surface water discharge rate will be limited to the

    existing 1 in 1 year greenfield runoff rate prior to entry to Stream A in a 1 in 100

    year plus 30% climate change rainfall event therefore the proposed development

    reduces fluvial flooding problems adjacent to or downstream of the site for the

    d lif ti f th d l t

  • 8/13/2019 File 7 Floodrisk Drainage Report

    19/72

    BSP Consulting 12568/FRA/DS/Rev AShelford Road, Radcliffe on Trent Flood Risk Assessment and Drainage Strategy

    4.0 RECOMMENDATIONS

    4.1 The following recommendations are made to reduce flood risk and promote a

    sustainable and practicable drainage strategy at the proposed development:

    Finished floor levels are to be set at least 600mm above the 1:100 year plusclimate change flood levels at the adjacent modelled watercourse sections.

    SuDS techniques will be employed to provide a minimum of two treatmenttrains of water quality improvement prior to the final discharge to Stream A.

    The SuDS features will be a combination of source control and site controlfeatures.

    Two linked attenuation ponds shall be utilised to provide two treatment trainsfor water quality and attenuate surface water runoff from the impermeable

    development area back to greenfield runoff rates. A preliminary attenuation

    strategy is outlined on drawing 12568/100 and included in Appendix D.

    Foul water from the proposed development will be drained to the existingadopted foul sewerage in Shelford Road to the north of the site.

    Disclaimer

    We would note that all comments made in this report are based on the sources stated in

    Section 1.1. This report and its recommendations are intended for the use of William Davis

    for the above site only.

  • 8/13/2019 File 7 Floodrisk Drainage Report

    20/72

    BSP Consulting 12568/FRA/DS/Rev AShelford Road, Radcliffe on Trent Flood Risk Assessment and Drainage Strategy

    Appendix A

    Detailed Site Location Plan

  • 8/13/2019 File 7 Floodrisk Drainage Report

    21/72

    BSP Consulting 12568/FRA/DS/Rev AShelford Road, Radcliffe on Trent Flood Risk Assessment and Drainage Strategy

    Appendix B

    Topographical Survey

  • 8/13/2019 File 7 Floodrisk Drainage Report

    22/72

  • 8/13/2019 File 7 Floodrisk Drainage Report

    23/72

  • 8/13/2019 File 7 Floodrisk Drainage Report

    24/72

  • 8/13/2019 File 7 Floodrisk Drainage Report

    25/72

  • 8/13/2019 File 7 Floodrisk Drainage Report

    26/72

    BSP Consulting 12568/FRA/DS/Rev AShelford Road, Radcliffe on Trent Flood Risk Assessment and Drainage Strategy

    Appendix CDevelopment Proposals

  • 8/13/2019 File 7 Floodrisk Drainage Report

    27/72

  • 8/13/2019 File 7 Floodrisk Drainage Report

    28/72

  • 8/13/2019 File 7 Floodrisk Drainage Report

    29/72

  • 8/13/2019 File 7 Floodrisk Drainage Report

    30/72

    VERSION FEHCDROM Version 3 exportedat 08:10:39 GMT Mon 12Nov12

    CATCHMENT GB 465550 339650 SK6555039650

    AREA 3.24

    ALTBAR 52

    ASPBAR 203ASPVAR 0.22

    BFIHOST 0.465

    DPLBAR 1.29

    DPSBAR 31.8

    FARL 1

    LDP 2.53

    PROPWET 0.27

    RMED1H 10

    RMED1D 28.9

    RMED2D 37.4

    SAAR 597

    SAAR4170 592

    SPRHOST 47.12

    URBCONC1990 0.679

    URBEXT1990 0.0409

    URBLOC1990 0.555URBCONC2000 0.774

    URBEXT2000 0.0444

    URBLOC2000 0.491

    C 0.02349

    D1 0.33135

    D2 0.33982

    D3 0.25521

    E 0.30769F 2.33395

    C(1km) 0.024

    D1(1km) 0.338

    D2(1km) 0.334

    D3(1km) 0.261

    E(1km) 0.308

    F(1km) 2.331

  • 8/13/2019 File 7 Floodrisk Drainage Report

    31/72

  • 8/13/2019 File 7 Floodrisk Drainage Report

    32/72

    Revitalised FSR/FEH rainfall runoff methodSpreadsheet application report

    Rainfall

    Recommended season is Winter, as URBEXT < 0.125

    ReFH design standard Seasonal Correction Factor of 0.63 applied

    ReFH design standard Areal Reduction Factor of 0.97 applied

    Loss Model

    CMaxderived from catchment descriptors

    ReFH design standard Ciniused

    ReFH design standard factor used

    Routing Model

    Tpderived from catchment descriptors

    ReFH design standard used for Up

    ReFH design standard used for Uk

    Baseflow Model

    BL derived from catchment descriptors

    BR derived from catchment descriptors

    ReFH design standard BF0used

  • 8/13/2019 File 7 Floodrisk Drainage Report

    33/72

  • 8/13/2019 File 7 Floodrisk Drainage Report

    34/72

  • 8/13/2019 File 7 Floodrisk Drainage Report

    35/72

  • 8/13/2019 File 7 Floodrisk Drainage Report

    36/72

  • 8/13/2019 File 7 Floodrisk Drainage Report

    37/72

  • 8/13/2019 File 7 Floodrisk Drainage Report

    38/72

    12568 WCM NO CULVERT FILE=12568 WCM NO CUL ISIS VER= 6.6.0.81

    results from the direct method at time 5.0000 hourslabel12 ? flow stage froude velocity umode ustate z

    SECTION_1 y 4.194 32.231 0.415 1.329 0.000 0.000 31.160SECTION_2 y 4.194 32.344 0.273 0.867 0.000 0.000 31.192SECTION_3 y 4.194 32.416 0.465 1.258 0.000 0.000 31.384SECTION_4 y 4.194 32.607 0.513 1.356 0.000 0.000 31.619SECTION_5 y 4.194 32.850 0.594 1.554 0.000 0.000 31.898SECTION_6 y 4.194 33.151 0.574 1.490 0.000 0.000 32.179SECTION_7 y 4.194 33.439 0.589 1.500 0.000 0.000 32.461SECTION_8 y 4.194 33.691 0.456 1.238 0.000 0.000 32.550SECTION_9 y 4.194 33.843 0.347 1.033 0.000 0.000 32.550SECTION_10 y 4.194 33.828 0.413 1.282 0.000 0.000 32.550SECTION_11 y 4.194 33.942 0.412 1.310 1.000 0.000 32.555

    SECTION_12 y 4.194 34.071 0.368 1.153 0.000 0.000 32.666SECTION_13 y 4.194 34.201 0.395 1.196 0.000 0.000 32.820SECTION_14 y 4.194 34.339 0.344 1.054 0.000 0.000 32.929SECTION_15 y 4.194 34.450 0.337 0.913 0.000 0.000 33.083SECTION_16 y 4.194 34.609 0.850 1.953 0.000 0.000 33.832SECTION_17 y 4.194 35.074 0.810 1.801 0.000 0.000 33.992SECTION_18 y 4.194 35.479 0.554 1.706 0.000 0.000 34.110

    Page 1

  • 8/13/2019 File 7 Floodrisk Drainage Report

    39/72

  • 8/13/2019 File 7 Floodrisk Drainage Report

    40/72

  • 8/13/2019 File 7 Floodrisk Drainage Report

    41/72

  • 8/13/2019 File 7 Floodrisk Drainage Report

    42/72

    BSP Consulting 12568/FRA/DS/Rev AShelford Road Radcliffe on Trent Flood Risk Assessment and Drainage Strategy

  • 8/13/2019 File 7 Floodrisk Drainage Report

    43/72

    Shelford Road, Radcliffe on Trent Flood Risk Assessment and Drainage Strategy

    Appendix ESevern Trent Water Correspondence

  • 8/13/2019 File 7 Floodrisk Drainage Report

    44/72

  • 8/13/2019 File 7 Floodrisk Drainage Report

    45/72

  • 8/13/2019 File 7 Floodrisk Drainage Report

    46/72

  • 8/13/2019 File 7 Floodrisk Drainage Report

    47/72

  • 8/13/2019 File 7 Floodrisk Drainage Report

    48/72

    Sewer Capacity Assessment

    Shelford RoadRadcliffe On Trent, Nottinghamshire

    DE-1210-072 (WT26939)

    Version 1

    Date: 02/May/13

    Radcliffe on TrentShelford Road SCA Sewer Capacity Assessment Severn Trent Water

  • 8/13/2019 File 7 Floodrisk Drainage Report

    49/72

    Sewer Capacity Assessment Summary

    Sewer Capacity

    Assessment prepared for

    William Davis Ltd.

    Forest Field, Forest Road, Loughborough, Leics. LE11 3NS

    Development location and

    existing use

    Land at Shelford Road Farm, Shelford Road, Radcliffe on Trent, Nottingham

    NG12 1BA. Greenfield with associated farm dwelling and out buildings.

    Development proposals

    Development includes building 350 mixed residential dwellings. Foul

    effluent is proposed to be pumped into the existing Severn Trent Water

    network. Storm flows are proposed to flow to the watercourse south of

    development site and have not been assessed as part of this assessment.

    Planning application was not submitted as of 17/04/13. There is no knownphasing or construction programme at this stage.

    Study aimThe aim of the study is to identify the potential impact of foul flows only

    from the proposed development on the existing sewerage system.

    Impact of proposed

    development on public

    sewer network

    Sewer flooding LOW

    Combined Sewer Overflows LOW

    Sewage Pumping Stations LOW

    Requirement for Capacity

    Improvements

    Capacity improvements are not required to accommodate flows from the

    proposed development.

    Sewage Treatment Works

    capacity

    The site drains to Radcliffe on Trent sewage treatment work. There is not

    sufficient capacity at the STW to accommodate flows from this

    development

    Radcliffe on TrentShelford Road SCA Sewer Capacity Assessment Severn Trent Water

  • 8/13/2019 File 7 Floodrisk Drainage Report

    50/72

    Table of Contents

    1 Introduction _______________________________________________________________________ 12 Sewer Capacity Assessment ___________________________________________________________ 33 Conclusions and Recommendations _____________________________________________________ 94 Appendicies_______________________________________________________________________ 13

    Radcliffe on TrentShelford Road SCA Sewer Capacity Assessment Severn Trent Water

  • 8/13/2019 File 7 Floodrisk Drainage Report

    51/72

    1 Introduction1.1 Site LocationDevelopment site is located on the south side of Shelford Road in north-east Radcliffe on Trent.

    Easting: 465559

    Northing: 340049

    Existing land use is a rural Greenfield site with farm buildings and residential dwelling. The proposed

    development site is bounded to the north by Shelford Road, to the west by residential properties, to the

    south by a watercourse and railway line and to the east by greenfield. Adjacent land uses include residential,

    farmland and railway.

    The site location is shown in Figure A-1, Appendix A.

    1.2 Local Sewerage NetworkFlows from the Shelford Road area cross under a railway line to Bingham Road, then along Main Road to

    Sydney Grove sewerage pumping station (SPS). From here effluent is pumped 1.4 km to Radcliffe on Trent

    sewage treatment works (STW) via a 300mm diameter rising main. Between the development and Sydney

    Grove SPS there are two combined sewer overflows (CSOs), with a third CSO located inside the SPS

    compound. Spills from these sites drain to a local ditch that flows to the River Trent at Radcliffe Park.

    Sydney Grove SPS was upgraded as part of a Capital scheme in 2006 and surveyed in 2013. It has two

    variable speed pumps arranged duty/standby which can discharge between 29-79 litres per second. There is

    a combined sewer overflow to a storm wet wet well. Spills from this site are pumped to the surface water

    system to the same outfall as the two previously mentioned CSOs .

    The local sewerage network and the location of critical sewer assets are shown in Figure A-2, Appendix A.

    1.3 Proposed DevelopmentThe proposed development covers 18.7ha on an existing farm site and consists of 350 mixed residential

    dwellings. Foul flows are proposed to gravitate to the south end of the site and pumped to the existing

    225mm diameter foul sewer on Shelford Road at MH SK65404201.

    Radcliffe on TrentShelford Road SCA Sewer Capacity Assessment Severn Trent Water

  • 8/13/2019 File 7 Floodrisk Drainage Report

    52/72

    Development Type Units

    Mixed Residential 350 dwellings

    1.4 Study Aims and ObjectivesThe aim of the study is to identify the potential impact of flows from the proposed development on the

    public sewer network. This will be achieved through undertaking hydraulic computer modelling of the

    proposed development and assessing the impact at key points on the sewer network.

    Radcliffe on TrentShelford Road SCA Sewer Capacity Assessment Severn Trent Water

  • 8/13/2019 File 7 Floodrisk Drainage Report

    53/72

    2 Sewer Capacity Assessment2.1 MethodologyHydraulic modelling has been used to assess the impacts of the proposed development. The methodology is

    summarised below:

    The best available model for the area was used as the baseline model. A review of the model wasundertaken to ensure that it is suitable to inform the assessment.

    The base model used for the study was taken from the current live Rushcliffe Residual SMP (523-136). The network 523-136 Rushcliffe Residual#26 was verified in 2003.The model was re-verified

    and upgraded to asset management period (AMP) 5 specifications. This network includes a new

    asset survey of six relevant manholes in Radcliffe on Trent, Bingham Road CSO and Sydney Grove

    SPS. The master database has been compiled in InfoWorks CS version 9.5.

    o To update the model with the proposed development, local 150mm sewers were modelledto serve the development draining to the south end of the site. From here a pumping station

    was modelled to return flow to the 225mm sewer at MH SK65404201 on Shelford Road. The

    wet well storage volume of 35.44m3and pump rate of 5 l/s were calculated using the Severn

    Trent design standards and Sewers for Adoption design guide. Cover and invert levels for the

    network were estimated from surrounding manholes.

    Details of proposed development flows used in the assessment are included in Section2.2. The baseline model and proposed model were run for dry weather flow analysis and the 20 and

    40 year return period events for a suite of storm durations. The results for the critical storm duration

    (20 year 240 minute and 40 year 240 minute) are reported throughout this report. The models were

    also run for the 1 year 60 minute and 5 year 90 minute storms, to enable an assessment of CSO

    performance.

    The model results were analysed to determine the impact of the additional flows on networkperformance and identify whether capacity improvements are required.

    2.2 Proposed Development Flows

  • 8/13/2019 File 7 Floodrisk Drainage Report

    54/72

    Radcliffe on TrentShelford Road SCA Sewer Capacity Assessment Severn Trent Water

    Table 2-1: Predicted impact on sewer flooding >1m3for modelled scenarios (baseline and post-development)

  • 8/13/2019 File 7 Floodrisk Drainage Report

    55/72

    Mouchel 5 April 2013

    Location Baseline performance Post-development impactImpact

    Risk Level

    Road DWF 20 year event 40 year event DWF 20 year event 40 year event

    Shelford Rd No surcharge 143.2m3 196.4m3 No surcharge 150.8m3(+5%) 204.3m3(+4%) Low

    Addington Court No surcharge 111.1m3 896.1m3 No surcharge 112.6m3(+1%)898.7m

    3

    (+/-0%)Low

    Bingham Road No surcharge 52.0m3 240.9m

    3 No surcharge 58.3m

    3(+12%) 244.3m

    3(+1%) Low

    Berkeley Crescent No surcharge 28.6m3 260.7m3 No surcharge 31.7m

    3(+11%) 262.7m3(+1%) Low

    Radcliffe on TrentShelford Road SCA Sewer Capacity Assessment Severn Trent Water

    Table 2-2: Predicted Combined Sewer Overflow performance for modelled scenarios (baseline and post-development)

    C bi d S O fl

    Receiving watercourse Baseline spill volume (m3) Post-development spill volume (m

    3)

    Impact

  • 8/13/2019 File 7 Floodrisk Drainage Report

    56/72

    Mouchel 6 April 2013

    Combined Sewer OverflowRisk LevelName

    Special

    designation?*

    1year 60 minute

    event

    5 year 90 minute

    event

    1year 60 minute

    event

    5 year 90 minute

    event

    CSO Radcliffe on Trent -

    Bingham Road (SOQ-948-99-53) River Trent No 1057.3m

    3

    1767.8m

    3

    1066.3m

    3

    (+1%)

    1780.2m3 (+/-

    0%) Low

    EO Radcliffe on Trent - Main

    Road (SOQ-948-99-52)River Trent No 372.7m

    3 610.2m

    3 371.2m

    3(+/-0%) 615.0m3(+1%) Low

    CSO Radcliffe on Trent - Sydney

    Grove SPS (SOQ-948-99-56)River Trent No 711.4m

    3 1047.6m

    3 720.7m

    3(+1%)

    1052.5m3(+/-

    0%)Low

    * Special designation refers to environmental designations such as Special Areas of Conservation (SAC) and Sites of Special Scientific Interest (SSSI). The special

    designation may be at the location of the overflow or in downstream reaches of the receiving watercourse.

    Radcliffe on TrentShelford Road SCA Sewer Capacity Assessment Severn Trent Water

    Table 2-3: Predicted Sewage Pumping Station performance for modelled scenarios (baseline and post -development)

    Sewage Pumping Station

    Emergency overflow Baseline performance (m3) Post-development performance (m

    3)

    Impact

  • 8/13/2019 File 7 Floodrisk Drainage Report

    57/72

    Mouchel 7 April 2013

    Sewage Pumping StationRisk Level

    Receiving

    watercourse

    Special

    designation?DWF

    20 year

    event

    40 year

    eventDWF

    20 year

    event

    40 year

    event

    Radcliffe on Trent -

    Sydney Grove SPSRiver Trent No

    Pump

    operates 0.79times/hr;

    Storage for

    2hrs @

    3DWF=

    330.07m3;

    Meets

    storage

    requirement -

    has 363.65m3

    Spills

    1724.3m3

    Spills

    1881.7m3

    Pump

    operates 0.79times/hr;

    Storage for

    2hrs @

    3DWF=

    346.41m3;

    Meets

    storage

    requirement -

    has 363.65m3

    Spills

    1742.2m3

    (+1%)

    Spills

    1892.1m3

    (+1%)

    Low

    Radcliffe on TrentShelford Road SCA Sewer Capacity Assessment Severn Trent Water

    2 4 C it I t R i t

  • 8/13/2019 File 7 Floodrisk Drainage Report

    58/72

    2.4 Capacity Improvement RequirementsThe overall impact of the development is LOW based on the analysis in Tables 2-1 to 2-3. Impact of the

    proposed development based on flooding is LOW due to predicted flood volume increases being less than

    20m3 per manhole and predicted flooding locations are not near any reported flooding. Impact from the

    proposed development based on CSO performance is LOW due to predicted overflow volumes increasing

    less than 10% and outfalls do not drain to specially designated watercourses. Impact of the proposed

    development based on SPS performance is LOW due to current sufficient storage capacity and minimal

    increase in overflow operation as well as the age and condition of Sydney Grove SPS. Sewer network

    capacity improvements are not likely to be required to accommodate flows from the proposed

    development.

    Radcliffe on TrentShelford Road SCA Sewer Capacity Assessment Severn Trent Water

    3 C l i d R d ti

  • 8/13/2019 File 7 Floodrisk Drainage Report

    59/72

    3 Conclusions and Recommendations3.1 Conclusions

    The impact of foul flows arising from the proposed development at Shelford Road on the sewernetwork has been assessed using hydraulic modelling.

    The proposed development is predicted to have the following impacts:o Sewer Flooding: LOWo Combined Sewer Overflows: LOWo Sewage Pumping Stations: LOW

    3.2 Recommendations Based on current model, there are no recommendations to further network capacity investigations.

    Radcliffe on TrentShelford Road SCA Sewer Capacity Assessment Severn Trent Water

    Appendix A: Site and Development Information

    Figure A-1: Site location plan

  • 8/13/2019 File 7 Floodrisk Drainage Report

    60/72

    Mouchel April 2013

    Radcliffe on TrentShelford Road SCA Sewer Capacity Assessment Severn Trent Water

    Figure A-2: Local sewerage network and critical assets

  • 8/13/2019 File 7 Floodrisk Drainage Report

    61/72

    Mouchel April 2013

    Radcliffe on TrentShelford Road SCA Sewer Capacity Assessment Severn Trent Water

    Figure A-3: Known flooding locations

  • 8/13/2019 File 7 Floodrisk Drainage Report

    62/72

    Mouchel April 2013

    Radcliffe on TrentShelford Road SCA Sewer Capacity Assessment Severn Trent Water

    Figure A-4: Modelled flooding nodes

  • 8/13/2019 File 7 Floodrisk Drainage Report

    63/72

    Mouchel April 2013

    Radcliffe on TrentShelford Road SCA Sewer Capacity Assessment Severn Trent Water

    Figure A-5: Location plan from developer

  • 8/13/2019 File 7 Floodrisk Drainage Report

    64/72

    Mouchel April 2013

    Radcliffe on TrentShelford Road SCA Sewer Capacity Assessment Severn Trent Water

    Appendix B: Model Review Proforma

  • 8/13/2019 File 7 Floodrisk Drainage Report

    65/72

    Appendix B: Model Review Proforma

    This appendix is for internal use only and has been removed prior to external distribution

    Information contained within this appendix must notbe referred to elsewhere within this report

    Radcliffe on TrentShelford Road SCA Sewer Capacity Assessment Severn Trent Water

    Appendix C: Supplementary Information

  • 8/13/2019 File 7 Floodrisk Drainage Report

    66/72

    This appendix is for internal use only and has been removed prior to external distribution

    Information contained within this appendix must notbe referred to elsewhere within this report

    BSP Consulting 12568/FRA/DS/Rev AShelford Road, Radcliffe on Trent Flood Risk Assessment and Drainage Strategy

  • 8/13/2019 File 7 Floodrisk Drainage Report

    67/72

    Appendix F

    Surface Water Drainage Proposals

    BSP Consulting Ltd Page 1

    12 Oxford Street Shelford Road

  • 8/13/2019 File 7 Floodrisk Drainage Report

    68/72

    Nottingham Radcliffe on Trent

    NG1 5BG William Davis

    Date March 2013 Designed by AG

    File Checked by

    Micro Drainage Source Control 2013.1

    ICP SUDS Mean Annual Flood

    Input

    Return Period (years) 100 Soil 0.400Area (ha) 18.600 Urban 0.000

    SAAR (mm) 600 Region Number Region 4

    Results l/s

    QBAR Rural 52.8

    QBAR Urban 52.8

    Q100 years 135.8

    Q1 year 43.9

    Q30 years 103.5

    Q100 years 135.8

    BSP Consulting Ltd Page 1

    12 Oxford Street Shelford Road

    i h d liff

  • 8/13/2019 File 7 Floodrisk Drainage Report

    69/72

    Nottingham Radcliffe on Trent

    NG1 5BG Single Pond

    Date March 2013 Designed by AG

    File 12568 Linked Twi... Checked by

    Micro Drainage Source Control 2013.1

    Summary of Results for 100 year Return Period (+30%)

    Storm

    Event

    Max

    Level

    (m)

    Max

    Depth

    (m)

    Max

    Control

    (l/s)

    Max

    Overflow

    (l/s)

    Max

    Outflow

    (l/s)

    Max

    Volume

    (m)

    Status

    480 min Summer 33.148 1.148 39.1 0.0 39.1 5990.8 O K

    600 min Summer 33.167 1.167 39.3 0.0 39.3 6108.7 O K

    720 min Summer 33.177 1.177 39.5 0.0 39.5 6175.0 O K

    960 min Summer 33.182 1.182 39.5 0.0 39.5 6208.1 O K

    1440 min Summer 33.166 1.166 39.3 0.0 39.3 6103.7 O K

    2160 min Summer 33.134 1.134 38.9 0.0 38.9 5900.4 O K

    2880 min Summer 33.098 1.098 38.5 0.0 38.5 5671.5 O K

    480 min Winter 33.270 1.270 40.7 0.0 40.7 6779.7 O K

    600 min Winter 33.292 1.292 41.0 0.0 41.0 6930.3 O K720 min Winter 33.306 1.306 41.1 0.0 41.1 7023.6 O K

    960 min Winter 33.318 1.318 41.3 0.0 41.3 7101.2 O K

    1440 min Winter 33.306 1.306 41.1 0.0 41.1 7021.2 O K

    2160 min Winter 33.262 1.262 40.6 0.0 40.6 6731.4 O K

    2880 min Winter 33.216 1.216 40.0 0.0 40.0 6428.0 O K

    Storm

    Event

    Rain

    (mm/hr)

    Flooded

    Volume

    (m)

    Discharge

    Volume

    (m)

    Overflow

    Volume

    (m)

    Time-Peak

    (mins)

    480 min Summer 10.143 0.0 5888.9 0.0 486

    600 min Summer 8.503 0.0 5951.3 0.0 604

    720 min Summer 7.359 0.0 5951.7 0.0 724

    960 min Summer 5.854 0.0 5874.3 0.0 962

    1440 min Summer 4.234 0.0 5637.6 0.0 1238

    2160 min Summer 3.057 0.0 9032.5 0.0 1604

    2880 min Summer 2.424 0.0 9468.6 0.0 2000

    480 min Winter 10.143 0.0 6155.1 0.0 476

    600 min Winter 8.503 0.0 6151.1 0.0 592

    720 min Winter 7.359 0.0 6122.8 0.0 708

    960 min Winter 5.854 0.0 6045.3 0.0 932

    1440 min Winter 4.234 0.0 5862.4 0.0 13622160 min Winter 3.057 0.0 10065.7 0.0 1700

    2880 min Winter 2.424 0.0 10491.5 0.0 2164

    BSP Consulting Ltd Page 2

    12 Oxford Street Shelford Road

    Nottingham Radcliffe on Trent

  • 8/13/2019 File 7 Floodrisk Drainage Report

    70/72

    Nottingham Radcliffe on Trent

    NG1 5BG Single Pond

    Date March 2013 Designed by AG

    File 12568 Linked Twi... Checked by

    Micro Drainage Source Control 2013.1

    Rainfall Details

    Rainfall Model FSR Winter Storms Yes

    Return Period (years) 100 Cv (Summer) 0.750

    Region England and Wales Cv (Winter) 0.840M5-60 (mm) 18.600 Shortest Storm (mins) 480

    Ratio R 0.400 Longest Storm (mins) 2880

    Summer Storms Yes Climate Change % +30

    Time Area Diagram

    Total Area (ha) 11.160

    Time

    From:

    (mins)

    To:

    Area

    (ha)

    Time

    From:

    (mins)

    To:

    Area

    (ha)

    Time

    From:

    (mins)

    To:

    Area

    (ha)

    0 4 3.720 4 8 3.720 8 12 3.720

    BSP Consulting Ltd Page 3

    12 Oxford Street Shelford Road

    Nottingham Radcliffe on Trent

  • 8/13/2019 File 7 Floodrisk Drainage Report

    71/72

    Nottingham Radcliffe on Trent

    NG1 5BG Single Pond

    Date March 2013 Designed by AG

    File 12568 Linked Twi... Checked by

    Micro Drainage Source Control 2013.1

    Model Details

    Storage is Online Cover Level (m) 34.000

    Tank or Pond Structure

    Invert Level (m) 32.000

    Depth (m) Area (m) Depth (m) Area (m) Depth (m) Area (m) Depth (m) Area (m)

    0.000 4122.0 0.750 5563.0 1.500 7116.0 2.000 8000.0

    Hydro-Brake Outflow Control

    Design Head (m) 1.500 Hydro-Brake Type Md5 SW Only Invert Level (m) 32.000

    Design Flow (l/s) 43.9 Diameter (mm) 243

    Depth (m) Flow (l/s) Depth (m) Flow (l/s) Depth (m) Flow (l/s) Depth (m) Flow (l/s)

    0.100 8.7 1.200 39.8 3.000 61.6 7.000 94.0

    0.200 21.7 1.400 42.4 3.500 66.5 7.500 97.3

    0.300 31.3 1.600 45.1 4.000 71.1 8.000 100.5

    0.400 35.4 1.800 47.7 4.500 75.4 8.500 103.6

    0.500 36.5 2.000 50.3 5.000 79.5 9.000 106.6

    0.600 36.3 2.200 52.7 5.500 83.3 9.500 109.50.800 36.1 2.400 55.1 6.000 87.1

    1.000 37.5 2.600 57.3 6.500 90.6

    Weir Overflow Control

    Discharge Coef 0.544 Width (m) 10.000 Invert Level (m) 34.000

  • 8/13/2019 File 7 Floodrisk Drainage Report

    72/72