    Time is of Essence

    Delays are inevitable on construction projects

    The only project to have completed on time is a Mosque. Divine

    intervention (or Gods help) was understood to be the force behind the

    timely completion of this Mosque.

    Time and Money go hand-in-hand. When projects get late, additional

    costs are incurred.

    This makes it imperative to take control of project delays; timely and

    effectively.

  • 7/27/2019 Fidic Construction Claim

    3/39

  • 7/27/2019 Fidic Construction Claim

    4/39

    www.cspk.org

    The FIDIC Provisions define the conditions where delay may beclaimed as the basis for an Extension of Time (EOT). Some examples are;

    Late provision of design or drawings

    Unforeseeable Physical Conditions encountered on Site

    Inclement Weather

    Variations instructed by the Engineer (Additional Works etc.)

  • 7/27/2019 Fidic Construction Claim

    5/39

    www.cspk.org

    Meanwhile the principles of how delay and relatedcosts should be calculated are not defined by FIDIC.This leads to issues; issues which are usually

    contentious due to various 'schools of thoughts' andvaried interpretations existing worldwide.

    Disputes are the usual outcome.

  • 7/27/2019 Fidic Construction Claim

    6/39

    Contentious Issues in Delay Analysisresulting in Disputes

    Critical Path

    Who owns the Float?

    Concurrent (or Contractor) Delays and how these effectEntitlement

    EOT and its relation with Compensation for Delay

    Which is the best Method of Delay Analysis?

    As-Planned Vs. As-Built Comparison

    Impacted As-Planned

    Collapsed As-Built / But-For

    Time Slice / Sub-Networks / Time-Impact

    Etc.

    www.cspk.org

  • 7/27/2019 Fidic Construction Claim

    7/39

    www.cspk.org

    In order to eliminate disputes or facilitate settlement ofdisputes, there are now certain standards used worldwide.The leading standards are;

    Society of Construction LawsDelay and Disruption Protocol (SCL Protocol)

    AACE 29R-03 (Forensic Schedule Analysis)

  • 7/27/2019 Fidic Construction Claim

    8/39

    www.cspk.org

    The SCL Protocol wasfinalized in October 2002 afterseveral years of deliberations

    and considerable debate andagreement between expertsfrom different backgrounds

  • 7/27/2019 Fidic Construction Claim

    9/39

    www.cspk.org

    The objective of the SCL Protocolwas to bring reasonableness and

    fairness into the delay assessment

    process and to eliminatewidespread manipulation of

    complex delay issues

  • 7/27/2019 Fidic Construction Claim

    10/39

    www.cspk.org

    The SCL Protocol tried to standardize

    the issues such that disputes would be

    reduced or eliminated

  • 7/27/2019 Fidic Construction Claim

    11/39

    www.cspk.org

    It is recommended that;

    should be adopted as a Standardand should be, where possible,

    incorporated in the Construction

    Contracts

  • 7/27/2019 Fidic Construction Claim

    12/39

    www.cspk.org

    The SCL Protocol can be downloaded from:

    www.eotprotocol.com

    http://www.eotprotocol.com/http://www.eotprotocol.com/
  • 7/27/2019 Fidic Construction Claim

    13/39

    www.cspk.org

    The remaining slides of this lecture will

    review and discuss the basic Principlessuggested and recommended by the

    SCL Protocol

  • 7/27/2019 Fidic Construction Claim

    14/39

    www.cspk.org

    Basic Principlessuggested and recommended by

    the SCL Protocol

  • 7/27/2019 Fidic Construction Claim

    15/39

    www.cspk.org

    The Principles suggested by theSCL Protocol are simple.

    Some of the key principles suggestedby the Protocol are;

  • 7/27/2019 Fidic Construction Claim

    16/39

    www.cspk.org

    RULE NO. 1

    If there is an Employers delay, which is beyond the Contractorscontrol, and if this delay impacts the Completion Date of the Works,

    the Contractor should be entitled to receive an

    Extension of Time (EOT).[This will effectively result in an extended Time for Completion and will

    relieve the Contractor from having to pay penalties for delay (orDelay Damages under FIDIC)]

  • 7/27/2019 Fidic Construction Claim

    17/39

    www.cspk.org

    RULE NO. 2

    For the case of recovery of delay (or prolongation) costs incurred due tothe Employer delays, the Contractor must be able to prove that there hasbeen no other delay, which is in his own control, and which is equally

    (or partly) contributing for delaying the Time for Completion.

    This category of delay is called a Concurrent(or Contractors) Delay

    [In order to win a Delay Costs Claim, the Contractor must be able toprove that he has not been responsible for Concurrent Delays to

    the Time for Completion]

  • 7/27/2019 Fidic Construction Claim

    18/39

    www.cspk.org

    RULE NO. 3

    Where Contractors Delay to Completionoccurs concurrently with Employers Delayto Completion, the Contractors concurrent

    delay should NOT reduce anyExtension of Time (EOT), which is due.

    [Result of Rule No. 1 will not change and is irrespective of the resultof Rule No. 2]

  • 7/27/2019 Fidic Construction Claim

    19/39

    www.cspk.org

    The foregoing Rules proposed by the SCL Protocol aremeant to bring fairness and reasonableness into the

    delay assessment process.

    [The emphasis of the SCL Protocol is that no one Partyshould benefit from default of the other Party]

  • 7/27/2019 Fidic Construction Claim

    20/39

    www.cspk.org

    The Illustrations demonstrating the principles of the SCLProtocol are contained in the following Figures A to G

  • 7/27/2019 Fidic Construction Claim

    21/39

    www.cspk.org

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22

    Path 1 Float = 3.5 Weeks

    Path 2 Float = 5.5 Weeks

    Path 2

    Figure A - Accepted Contract Programme

    Weeks

    Path 1

    Contract Start

    Date

    Contract

    Completion Date

  • 7/27/2019 Fidic Construction Claim

    22/39

    www.cspk.org

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22

    PRIOR TO EXCUSABLE DELAY (UPDATE WITH ACTUAL PROGRESS)

    Path 1 Float = 3.0 Weeks

    Path 2 Float = 5.5 Weeks

    AFTER EXCUSABLE DELAY

    Excusable Delay

    Path 1 Float = 1.0 Week

    Path 2 Float = 5.5 Weeks

    (a) 2.0 Weeks (a) 5.5 Weeks

    (b) 1.0 Weeks (b) 0 Weeks

    (c) 0 Weeks (c) 1.0 Weeks

    (d) 5.5 Weeks (d) 2.0 Weeks

    (a) 2.0 Weeks (a) 0.1% of Contract Price

    (b) 1.0 Weeks (b) Direct Costs of Excusable Delay

    (c) 0 Weeks (c) NIL

    (d) 5.5 Weeks (d) (a) plus (b)

  • 7/27/2019 Fidic Construction Claim

    23/39

    www.cspk.org

    Principles & Provisions of the SCL Protocolrelevant to Figure B

    Core Principle No. 7 - Float as it relates to timeUnless there is express provision to the contrary in the contract, where there is remainingfloat in the programme at the time of an Employer Risk Event, an EOT should only begranted to the extent that the Employer Delay is predicted to reduce to below zero the total

    float on the activity paths affected by the Employer Delay.

    Guidance Section 1.12.1If as a result of an Employer Delay, the Contractor is prevented from completing the worksby the Contractors planned completion date (being a date earlier than the contractcompletion date), the Contractor should in principle be entitled to be paid the costs

    directly caused by the Employer Delay, notwithstanding that there is no delay to thecontract completion date (and therefore no entitlement to an EOT), provided also that atthe time they enter into the contract, the Employer is aware of the Contractors intention tocomplete the works prior to the contract completion date, and that intention is realistic andachievable.

  • 7/27/2019 Fidic Construction Claim

    24/39

    www.cspk.org

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22

    PRIOR TO EXCUSABLE DELAY (UPDATE WITH ACTUAL PROGRESS)

    Path 1 Float = 3.0 Weeks

    Path 2 Float = 5.5 Weeks

    AFTER EXCUSABLE DELAY

    Excusable Delay

    Float = -0.5 Week

    (a) 0.5 Weeks (a) 5.5 Weeks

    (b) 3.5 Weeks (b) 0.5 Weeks

    (c) 0 Weeks (c) 3.5 Weeks

    (d) 5.5 Weeks (d) 0 Weeks

    (a) 3.5 Weeks (a) 0.15% of Contract Price

    (b) 0.5 Weeks (b) Direct Costs of Excusable Delay

    (c) 0 Weeks (c) (a) plus (b)

    (d) 3.0 Weeks (d) NIL

    Contract

    Completion Date

    Impact on Path 1

    = 3.5 Weeks

    Path 2

    Path 1

    Path 2

    (3) Compensation for Delay to

    Pro ress

    (1) EOT Entitlement (2) Period of Prolongation Costs

    (4) Other Compensation

  • 7/27/2019 Fidic Construction Claim

    25/39

    www.cspk.org

    Core Principle No. 4 - Procedure for granting extension of timeThe EOT should be granted to the extent that the Employer Risk Event isreasonably predicted to prevent the works being completed by the thenprevailing contract completion date..The goal of the EOT procedure isthe ascertainment of the appropriate contractual entitlement to an EOT; theprocedure is not to be based on whether or not the Contractor needs anEOT in order not to be liable for liquidated damages.

    Core Principle No. 5 Effect of delayFor an EOT to be granted, it is not necessary for the Employer Risk Eventalready to have begun to affect the Contractors progress with the works,or for the effect of the Employer Risk Event to have ended.

    Principles & Provisions of the SCL Protocolrelevant to Figure C

  • 7/27/2019 Fidic Construction Claim

    26/39

    www.cspk.org

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22

    PRIOR TO EXCUSABLE DELAY (UPDATE WITH ACTUAL PROGRESS)

    Path 1 Float = 3.0 Weeks

    Path 2 Float = 5.5 Weeks

    AFTER EXCUSABLE DELAY

    Float = -0.5 Week

    Excusable DelayImpact on Path 2 = 6.0 Weeks

    (a) 0 Weeks (a) 5.5 Weeks(b) 6.0 Weeks (b) 0 Weeks

    (c) 0.5 Weeks (c) 6.0 Weeks

    (d) 5.5 Weeks (d) 0.5 Weeks

    (a) 3.5 Weeks (a) (d) minus (c)

    (b) 0.5 Weeks (b) NIL

    (c) 6.0 Weeks (c) Direct Costs of Excusable Delay

    (d) 3.0 Weeks (d) 0.2% of Contract Price

  • 7/27/2019 Fidic Construction Claim

    27/39

    www.cspk.org

    Core Principle No. 4 - Procedure for granting extension of timeThe EOT should be granted to the extent that the Employer Risk Event isreasonably predicted to prevent the works being completed by the thenprevailing contract completion date..The goal of the EOT procedure isthe ascertainment of the appropriate contractual entitlement to an EOT; the

    procedure is not to be based on whether or not the Contractor needs anEOT in order not to be liable for liquidated damages.

    Core Principle No. 5 Effect of delayFor an EOT to be granted, it is not necessary for the Employer Risk Eventalready to have begun to affect the Contractors progress with the works,

    or for the effect of the Employer Risk Event to have ended.

    Principles & Provisions of the SCL Protocolrelevant to Figure D

  • 7/27/2019 Fidic Construction Claim

    28/39

    www.cspk.org

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22

    PRIOR TO EXCUSABLE DELAY (UPDATE WITH ACTUAL PROGRESS)

    Contract Completion Date

    Float = -1.5 Weeks

    AFTER EXCUSABLE DELAY

    Contract Completion Date

    Excusable DelayImpact on Path 1 = 2.0 Weeks

    Float = -3.5 Weeks

    (a) 3.5 Weeks (a) 2.0 Weeks

    (b) 2.0 Weeks (b) 0 Weeks(c) 1.5 Weeks (c) 3.5 Weeks

    (d) 0 Weeks (d) 1.5 Weeks

    (a) 3.5 Weeks (a) (c) plus (d)

    (b) 2.0 Weeks (b) NIL

    (c) 3.0 Weeks (c) Direct Costs of Excusable Delay

    (d) 0 Weeks (d) 0.1% of Contract Price

    Figure E - Delay Impact 4

    Weeks

    Path 1

    Contract Start

    Date

  • 7/27/2019 Fidic Construction Claim

    29/39

    www.cspk.org

    Guidance Section 1.2.11an EOT should be granted to the extent that the Employer Risk Event ispredicted to prevent the works being completed by the then prevailingcontract completion date. This process requires consideration of theavailable float

    Guidance Section 1.4.12Where there has been Employer Delay, this may prevent the Employercharging the Contractor with LDs for failure to achieve a contractcompletion date

    Principles & Provisions of the SCL Protocolrelevant to Figure E

  • 7/27/2019 Fidic Construction Claim

    30/39

    www.cspk.org

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22

    PRIOR TO EXCUSABLE DELAY (UPDATE WITH ACTUAL PROGRESS)

  • 7/27/2019 Fidic Construction Claim

    31/39

    www.cspk.org

    Guidance Section 1.4.8Where an Employer Risk Event occurs after the contract completion date, in asituation where failure to complete by the contract completion date has been causedby Contractor Delays, the principle set out in Section 1.4.7 above should apply,

    except where the Employer Risk Event is a non-compensable Employer Risk Event.In such an event, no EOT (or compensation) should be due. Where an EOT is dueafter the contract completion date, the Employer Risk Event does not exonerate theContractor for all its delays prior to the Employer Risk Event occurring. The effectof the Employer Risk Event should be assessed as described above and any EOTfound due should simply be added to the contract completion date.

    Principles & Provisions of the SCL Protocolrelevant to Figure F

  • 7/27/2019 Fidic Construction Claim

    32/39

    www.cspk.org

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22

    PRIOR TO EXCUSABLE DELAY (UPDATE WITH ACTUAL PROGRESS)

  • 7/27/2019 Fidic Construction Claim

    33/39

    www.cspk.org

    Guidance Section 1.4.1Where Contractor Delay to Completion occurs concurrently with Employer Delay toCompletion, the Contractors concurrent delay should not reduce any EOT due.

    Guidance Section 1.4.7Where Employer Risk Events and Contractor Risk Events occur sequentially buthave concurrent effects, here again any Contractor Delay should not reduce the

    amount of EOT due to the Contractor as a result of the Employer Delay.

    Concurrency (Appendix A Definations and Glossary)True concurrent delay is the occurrence of two or more delay events at the sametime, one an Employer Risk Event, the other a Contractor Risk Event and the effectsof which are felt at the same time. The term concurrent delay is often used to

    describe the situation where two or more delay events arise at different times, butthe effects of them are felt (in whole or in part) at the same time. To avoidconfusion, this is more correctly termed the concurrenteffect of sequential delayevents.

    Principles & Provisions of the SCL Protocolrelevant to Figure G Slide 1/2

  • 7/27/2019 Fidic Construction Claim

    34/39

    www.cspk.org

    Core Principle No. 9 - Concurrent delay its effect on entitlement to extension of timeWhere Contractor Delay to Completion occurs or has effect concurrently with EmployerDelay to Completion, the Contractors concurrent delay should not reduce any EOTdue.

    Core Principle No. 14 - Link between extension of time and compensationEntitlement to an EOT does not automatically lead to entitlement to compensation (and

    vice versa).

    Core Principle No. 10 - Concurrent delay its effect on entitlement to compensation forprolongationIf the Contractor incurs additional costs that are caused both by Employer Delay andconcurrent Contractor Delay, then the Contractor should only recover compensation to

    the extent it is able to separately identify the additional costs caused by the EmployerDelay from those caused by the Contractor Delay. If it would have incurred theadditional costs in any event as a result of Contractor Delays, the Contractor will not beentitled to recover those additional costs.

    Principles & Provisions of the SCL Protocolrelevant to Figure G Slide 2/2

  • 7/27/2019 Fidic Construction Claim

    35/39

    www.cspk.org

    Guidance Section 3.2.13Although the programme should be the primary tool for guiding theCA in his determination of EOT, it should be used in conjunctionwith the contemporary evidence to ensure that the resulting EOT isfair and reasonable. It will also be necessary for the parties to apply

    common sense and experience to the process to ensure that allrelevant factors are taken into account, and that any anomalousresults generated by the programme analysis are managed properly.

    Key Guideline, Suggestion and Advice of theSCL Protocol

  • 7/27/2019 Fidic Construction Claim

    36/39

    www.cspk.org

    Figure No. Question 1 Question 2 Question 3 Question 4B (c) (b) (a) (b)C (a) (b) (d) (b)D (c) (d) (d) (c)E (b) (a) (d) (c)F (a) (b) (d) (c)G (c) (a) (a) (b)

    Correct Responses for Figures B to G

  • 7/27/2019 Fidic Construction Claim

    37/39

    Congratulations wehave come to the end of

    the Lecture.

    You are now a

    Qualified and CertifiedDelay Claims Analyst

    and Expert.

    www.cspk.org

  • 7/27/2019 Fidic Construction Claim

    38/39

    FIDIC and Construction Solutionsthank you for your attendance and contribution.

    We wish you all Good Luck.

    www.cspk.org

  • 7/27/2019 Fidic Construction Claim

    39/39

    We urge all participants to review the SCL Protocol on their own.Construction Solutions Claims Management Division

    (www.cspk.org)will remain available for further discussions on theforegoing and any other relevant issue.

    This Lecture was delivered by the Managing Partner of Construction Solutions,Mr. Khalil Tayab Hasan. For any queries and clarifications, please feel free to