Upload
dangdien
View
236
Download
1
Embed Size (px)
Citation preview
Feasibility Study of Flare Reduction Concept for Operating LNG Trains by Dynamic Simulation
© Chiyoda Corporation 2017, All Rights Reserved.
Presented by Kyoko Kamei
6 April, 2017
2
1. Introduction
2. Qatargas Flare Reduction Project (Off-spec Recycle)a) Overviewb) Conceptc) Upset Scenariod) Expected Concerns
3. Dynamic Simulationa) Model Scopeb) Simulation Resultsc) Key Results
4. Conclusion
5. Acknowledgements
Agenda
1. Introduction
4
EPC Contractor
Est. 1948
HQ - Yokohama, Japan
Designed and constructed LNG (Liquefied Natural Gas) plants for 35 years
Completed six mega LNG trains in Qatar in 2010
Developing efficient LNG process and protecting the environment
Yokohama-Minatomirai
1. Introduction
5
Dynamic Simulation
Concerns
✓ Troubleshooting
✓ Environmental Requirement
✓ Operation / Profit Improvement
Plant Design by Steady State
Simulation
Design
VerificationChiyoda’s Solutions
Data Review
Planning
FEEDOperationEPC
Design Know-how
1. Introduction
FEED: Front End Engineering Design, EPC: Engineering Procurement and Construction
Utilize Dynamic Simulation
Valuable Solution Providing Tool
2. Qatargas Flare Reduction Project (Off –spec Recycle)
7
Overview
• Qatar National Vision 2030 and Qatargas Direction Statement provide direction to reduce flaring.
• Qatargas and Chiyoda Almana are carrying out a “Flare Reduction Project” to mitigate CO2
emissions since 2009.
• Dynamic simulation verified feasibility of one of the concepts (Off-Spec Recycle).
Dynamic Simulation is
a good solution!
Scope includes 4 LNG trains including upstream
facilities
Complicated self-heating recovery systems and
control systems affecting each other
Expander-Compressor process in NGL system
CO2: Carbon Dioxide, Spec: Specification
2. Qatargas Flare Reduction Project (Off –spec Recycle)
8
Concept
Current OperationFlaring during start-up
takes several hours
Huge amount of gas
is flared leading to
higher CO2 emission
2. Qatargas Flare Reduction Project (Off –spec Recycle)
AGR: Acid Gas Removal, NGL: Natural Gas Liquid
Inlet
Facility
Feed
Gas
(QG 3&4)
AGRNGL Recovery
& Liquefaction
Normal Operating Train-7 FFF
NGL
LNG
Off-Spec Gas
Acid Gas
Inlet
Facility
Feed
Gas
(QG 2)
Starting up Train-4
Dehydration
Water
AGRNGL Recovery
& Liquefaction
Normal Operating Train-5 FFF
NGL
LNG
Acid Gas
Dehydration
Water
AGRNGL Recovery
& Liquefaction
Normal Operating Train-6 FFF
NGL
LNG
Acid Gas
Dehydration
Water
AGR NGL Recovery
FFF
NGL
LNG
Acid Gas
Dehydration
Water
9
Recycle off-spec gas
instead of flaring
Need to assess the impact of a
sudden loss of off-spec recycle gas
due to a trip of the start-up train
×
Concept
2. Qatargas Flare Reduction Project (Off –spec Recycle)
Inlet
Facility
Feed
Gas
(QG 3&4)
AGRNGL Recovery
& Liquefaction
Receiving Train-7 FFF
NGL
LNG
Acid Gas
Inlet
Facility
Feed
Gas
(QG 2)
Starting up Train-4
Dehydration
Water
On/Off
valve
Off-Spec Recycle Gas
AGRNGL Recovery
& Liquefaction
Normal Operating Train-5 FFF
NGL
LNG
Acid Gas
Dehydration
Water
AGRNGL Recovery
& Liquefaction
Normal Operating Train-6 FFF
NGL
LNG
Acid Gas
Dehydration
Water
AGR NGL Recovery
FFF
NGL
LNG
Acid Gas
Dehydration
Water
10
Upset Scenario: Loss of Recycle Gas from Starting-up Train
What happens to the operation of the receiving Train (Train-7)?
Tr-7 inlet flow reduces ⇒Recovered by increasing flow from Inlet facility
Tr-7 inlet gas composition becomes heavier
2. Qatargas Flare Reduction Project (Off –spec Recycle)
Inlet
Facility
Feed Gas
(QG 3&4)
AGRNGL Recovery
& Liquefaction
On/Off
valveReceiving Train-7 FFF
NGL
LNG
Off-Spec Recycle Gas from NGL
Acid Gas
Normal Operating Train-6
Dehydration
Water
60% Heavy Flow→100%
40% Lean Flow→0%
Flow & composition disturbance
(Rapid change) @ Train-7 AGR inlet!
11
Inlet
Facility
Feed Gas
(QG 3&4)
AGRNGL Recovery
& Liquefaction
On/Off
valveReceiving Train-7 FFF
NGL
LNG
Off-Spec Recycle Gas from NGL
Acid Gas
Normal Operating Train-6
Dehydration
Water
60% Heavy Flow→100%
40% Lean Flow→0%
Concerns in Inlet Facility, AGR, and Dehydration
• Determine if stable pressure and flow rate are maintained for good
separation performance
Evaluate Controller
Performance
2. Qatargas Flare Reduction Project (Off –spec Recycle)
12
Feed Gas
NGL
Lean Gas
Expander/Compressor
Deethanizer
J-T Valve
Concerns in NGL Recovery (Typical Scheme)
Disturbances in feed
flow & composition
Performance of Deethanizer
Heavy component in LNG
Light component in NGL
Stability of Controllers
Multiple pressure controllers
Expander-Compressor speed controller
Deethanizer liquid level controller
Temperature excursions in Aluminum
Blazed Heat Exchangers
2. Qatargas Flare Reduction Project (Off spec Recycle)
3. Dynamic Simulation
14
Dynamic Simulation Model Scope
Prepared for Train-4 and 7
Adjusted process variables of Train-7 to
meet actual operating conditions during
start-up when off-spec gas is recycled
from Train-4 NGL Recovery Unit
Tested whether Train-7 can maintain
stable operation & Train-4 can safely
shutdown without problems in case of
loss of recycle gas to receiving train
3. Dynamic Simulation
×
Inlet FacilityFeed Gas
(QG 3&4)
AGR &
Dehydration
NGL Recovery
& Liquefaction
Receiving Train-7
Normal Operating
Train-6
FFF
NGL
LNG
Recycle Gas
Acid Gas
& Water
Inlet FacilityFeed Gas
(QG2)
Starting up Train-4
AGR &
DehydrationNGL Recovery
NGLAcid Gas
& Water
Normal Operating
Train-5
On/Off
valve
15
3. Dynamic Simulation
16
Simulation Results with Current Configuration
System ResultsRecommendations
(software modification)
AGRAGR Absorber pressure decreases below the allowable minimum
Control system should be updated
NGLLean gas pressure decreases, which opens the expander IGV leading to JT operation
NGLDeethanizer bottom (NGL) flow reduces to zero for a while (below the minimum turndown rate of 40% flow) Deethanizer reboiler operation
should be modified to respond to the rapid change of feed gas composition
NGLDeethanizer bottom liquid level fluctuates
LiquefactionHeavy component in LNG exceeds the allowable range
Found that operational disturbances of the receiving
train could not be avoided
3. Dynamic Simulation
17
Key Results
(a) Pressure Fluctuations in AGR Unit
0
20
40
60
80
100
80
85
90
95
100
0 180 360 540 720 900 1,080O
utp
ut
(%)
PV
(%
No
rma
l P
ress)
Time (sec)
AGR Pressure ControllerPV
OP
0
20
40
60
80
100
80
85
90
95
100
0 200 400 600 800 1,000
Outp
ut
(%)
PV
(%
Norm
al P
ress)
Time (sec)
AGR Pressure ControllerPV
OP
Min P = 81% Normal Press.
Min P = 98% Normal Press.
Original Modified Controller
0
20
40
60
80
100
80
85
90
95
100
0 180 360 540 720 900 1,080
Ou
tpu
t (%
)
PV
(%
No
rma
l P
ress)
Time (sec)
AGR Pressure ControllerPV
OP
0
20
40
60
80
100
80
85
90
95
100
0 200 400 600 800 1,000
Outp
ut
(%)
PV
(%
Norm
al P
ress)
Time (sec)
AGR Pressure ControllerPV
OP
Min P = 81% Normal Press.
Min P = 98% Normal Press.
Stable operation achieved!Decreases below the allowable pressure, leading to
unacceptable disruption!
3. Dynamic Simulation
PV: Process Variable, OP: Output
18
Feed Gas
NGL
Lean Gas
Expander/Compressor
Deethanizer
J-T Valve
Key Results
(b) Deethanizer Bottom Liquid Level
Modified Reboiler Operation
3. Dynamic Simulation
0
20
40
60
80
100
0
20
40
60
80
100
0 200 400 600 800 1000 1200
Outp
ut (%
)
Liq
uid
Level (%
)
Time (sec)
Deethanizer Bottom Level ControllerPV
OP
0
20
40
60
80
100
0
20
40
60
80
100
0 200 400 600 800 1,000 1,200
Outp
ut (%
)
Liq
uid
Level (%
)
Time (sec)
Deethanizer Bottom Level ControllerPV
OP
0
20
40
60
80
100
0
20
40
60
80
100
0 200 400 600 800 1000 1200
Outp
ut (%
)
Liq
uid
Level (%
)
Time (sec)
Deethanizer Bottom Level ControllerPV
OP
0
20
40
60
80
100
0
20
40
60
80
100
0 200 400 600 800 1,000 1,200
Outp
ut (%
)
Liq
uid
Level (%
)
Time (sec)
Deethanizer Bottom Level ControllerPV
OP
Unstable Operation! Stable operation maintained!
Original
4. Conclusion
20
Findings
1. Dynamic Simulation verified the feasibility of Flare Reduction Concept
• It is not feasible with the current design configuration
• It was found feasible with some software modification
2. Dynamic Simulation suggested solutions for Flare Reduction
4. Conclusion
Effective and fit-for-purpose Dynamic Simulation
with given schedule and cost!
No hardware modification necessary!
21
What Chiyoda Provides
• Solutions to problems that occur during operation: “Flare Reduction.”• All in consideration of safety, availability, operability, controllability, and maintainability,
including dynamic aspects of operation
• We identify possible scenarios with large impacts to the operation for the proposed
modification and propose an effective approach using advanced technology.
• Close communications with the Client every step of the process allowed us to define issues, develop scope and scenarios, suggest countermeasures, change the scenario if necessary—all in a timely manner.
4. Conclusion
5. Acknowledgements
23
Qatargas Operating CompanyMr. Hassan Sawan, Project Division Manager
Mr. Abdulla Radi Al-Hajri, Surveillance Division Manager
Mr. Fadi Ghaya, Head of Project Engineering
Ms. Ranya Gornass, Senior Process Engineer
Mr. Krishnakumar Raghunatha Rao, Senior Process Engineer
Chiyoda Almana Engineering LLCMr. Kei Masuda, Deputy Engineering Dept. Manager
Mr. Shinya Endo, Engineering Manager
Mr. Shankar Dharmadas, Lead Process Engineer
5. Acknowledgements
24
Thank You
© Chiyoda Corporation 2017, All Rights Reserved.