Facilities UpdateAugust 16, 2010
Board of Education Workshop
Presentation Summary
Mid-Year Update
December 2009 – July 2010
I. Implementation Update
II. Current Projects Update
III. Project Development Update
IV. Master Program Schedule Update
V. Master Program Budget Update
VI. Facility Master Plan Review
VII. Facilities Statistics, Lessons Learned, Program
Successes
2
I. Implementation Update
Program Management
Citizens’ Oversight Committee (COC) Coordination
3
• COC Meetings
• December 17, 2009 (Quarterly Financial Update, 2008/2009 Annual Financial and Performance Audit, COC
Annual Report Format and Schedule, Measure K Bond Program Update, 2009/2010 Annual Financial and Performance Audit, Additional Meetings)
• April 1, 2010(COC Bylaws Review and Revisions, Brown Act Review, Measure K Bond Program Update, Quarterly Financial Update, 2009/2010 Annual Financial and Performance Audit,
COC Annual Report, COC One-Year Term Member Renewal, Tentative 2010/2011 COC Meeting Schedule)
• June 24, 2010(Introduction of 2010/2011 COC Members, Measure K Bond Program Update, Quarterly Financial Update, Tentative 2010/2011 COC Meeting Schedule, Selection and
Confirmation of 2010/2011 Chair and Vice-Chair, Tour of New 6-8 Middle School #1 –GTE Site)
I. Implementation Update
Program ManagementCitizens’ Oversight Committee (COC) Coordination
(continued)
4
)
• 2008/2009 Annual Financial and Performance Audit to
Board (December 15, 2009)
• COC Bylaws Revised by Board Action (January 19, 2010)
• COC Annual Report to Board (May 11, 2010)
• Reappointment of One-Year Term Members – Julie
Jackson and Byron Bolton (May 11, 2010)
• New Member – Anna Ulaszewski (Appointed June 8, 2010)
• New Chair Selected – Karen Hilburn
• New Vice Chair Selected – Julie Jackson
I. Implementation Update
Program ManagementCitizens’ Oversight Committee (COC) Coordination
(continued)
5
)
• New Member Training (June 2010)
• 2009/2010 Annual Financial and Performance Audit
Underway
• Upcoming Meetings (through December 2010)
• Construction Site Tour - New 6-8 Middle School
#1 at former GTE site (August 19, 2010)
• September 23, 2010
• December 16, 2010
I. Implementation Update
• Program Management
• Planning
• Program Accounting and Financials
• Project Support
• Project Execution
For additional information on progress and work effort across all areas of Program
Implementation, please refer to Board Workbook.
6
II. Current Projects Update
New 6-8 Middle School #1
• 6-8 Middle School in the
Poly Planning Area
• Site Located at E. 20th
Street/Cherry Avenue (8+
acres) – Former GTE Site
• 800 Students (840 capacity)
• 31 Classrooms (89,288
square feet)
• Library/Media Center,
Gymnasium, Multipurpose Room, Other Support
Facilities including a Soccer
Field and Hard Court Areas
• Total Project Cost - $ 54.4M
• Expended to Date - $ 18.9M
7
• Construction Budget: GMP - $38.3 M
• State Funding of $12.9 M Under Critically
Overcrowded Schools (COS) Program
• Construction Contract Awarded July 7, 2009
• Notice to Proceed Issued on July 30, 2009
• Anticipated Construction Duration – 22
months
• Anticipated School Opening – September 6,
2011
II. Current Projects Update
New 6-8 Middle School #1
Construction Progress Photos
8
E
D
CB
ASite Overview
II. Current Projects Update
New 6-8 Middle School #1
Construction Progress Photos
9
Building C Slab on Grade
Building A Metal Deck
II. Current Projects Update
New 6-8 Middle School #1
Construction Progress Photos
10
Building A Entrance Canopy Steel
Buildings B and C Steel
Building D CMU
II. Current Projects UpdateNew High School #1 – ECATS – Site Conversion
DeMille Middle School
(Current Site Lay-Out)
New High School #1 – ECATS
(Site Lay-Out)
11
II. Current Projects Update
New High School #1 – Early College and
Academic Technical School (ECATS)
12
• 1,080 Students in Grades 9th – 12th
• 7 New Buildings (Administration,
North Academy, Science, Food Service, Gym, South Academy,
Lecture Hall)
• 43 Total Classrooms
• Self-Contained Athletics/Extra-
Curricular Programs
II. Current Projects Update
New High School #1 (ECATS)
• Approval of Drawings and Specifications from
DSA Received
• No Further Action Letter Received from DTSC
• CDE Final Plan Approval Submittal Pending
• OPSC Submittal Pending
• Constructability Reviews by Third Party
Complete
• Bidding in Progress
13
II. Current Projects Update
New High School #1 – ECATS
Budget
• Facility Master Plan Estimated Cost:
$72.8 M - $103.3 M
• Current Estimated Construction Cost:
$75.5 M
• Current Estimated Total Project Budget:
$100.5 M
• Expended to Date:
$4.8 M
14
II. Current Projects Update
New High School #1 – ECATS
Grant Applications
• Submitted on September 18, 2009 to California
Department of Education (CDE) for Career
Technical Education (CTE) Facilities Program
• March 8, 2010 SAB 50-10/Reservation of Funds
• 171 Applications – 22 Health/Medical, 13 Engineering Design, 4
Public Services
• Available CTE Funds - $93.6 M
• Three Separate Grant Applications Requesting State Matching
Funds
• $1.5 M for Health/Medical (ranked 37th)
• $1.5 M for Engineering Design (ranked 44th)
• $3.0 M for Public Services - Legal/Law
Enforcement/Forensics (ranked 122nd)
15
II. Current Projects Update
New High School #1 – ECATS
Anticipated Schedule
• Architectural Design Submitted to DSA 8/24/09
• CEQA Comment Period Closed 11/23/09
• Board Consideration of Project 12/15/09
• DSA Approval 8/24/09 – 4/24/10
• Demo & Abatement Construction 10/19/10 – 2/21/11
• Building Construction
Construction Contract Approval 4/19/11
Construction (24 months) 5/11/11 – 5/1/13
• Target School Opening Date 9/3/13
16
II. Current Projects Update
District-Wide Projects – Technology Upgrades
Core Switch and Uninterrupted Power Supply (UPS)
Replacement Project 2010
17
Project Sites (52 campuses)
Addams E.S. Alvarado E.S. Avalon Bancroft M.S. Barton E.S.
Birney E.S. Bixby E.S. Bryant E.S. Buffum E.S. Burbank E.S.Burcham K-8 Burnett E.S. Burroughs E.S. Butler M.S. Cabrillo H.S.
Edison E.S. Franklin M.S. Garfield E.S. Grant E.S. Hamilton M.S.Harte E.S. Hill M.S. Holmes E.S. Hoover E.S. Hudson K-8Hughes M.S. International E.S. Jefferson M.S. Jordan H.S. Keller E.S.
King E.S. Lafayette E.S. Lee E.S. Lincoln E.S. Lindberg M.S.Lindsey M.S. MacArthur E.S. Mann E.S. Marshall M.S. McKinley E.S.
Monroe K-8 Muir E.S. Riley E.S. Robinson K-8 Roosevelt E.S.Signal Hill E.S. Stephens M.S. Stevenson E.S. Washington M.S. Webster E.S.Whittier E.S. Willard E.S.
Measure K and E-Rate Funding Total Project Cost = $1,152,612E-Rate = $413,024
Measure K = $739,588
II. Current Projects Update
District-Wide Projects – Deportablization
Phase I DOH Removal Project
• Remove DOH (Department of Housing) Buildings at 14 SitesAddams E.S.
Grant E.S.
Hamilton M.S.
Harte E.S.
Keller E.S.
Kettering E.S.
Long Beach School for Adults
McKinley E.S.
Robinson E.S.
Signal Hill E.S.
Stephens M.S.
Webster E.S.
Willard E.S.
Wilson H.S.
• Lionakis Completing Scope of Work Assessment
• Anticipated Bidding – January 2011
• Anticipated Removal – March through July 2011
18
II. Current Projects Update
District-Wide Projects - Facility Component Improvements
Boiler Replacement Project
19
• 24 Boilers at 10 SitesBancroft M.S.
Gant E.S.
Kettering E.S.
Lakewood H.S.
Long Beach School for Adults
Lowell E.S.
McKinley E.S.
Millikan H.S.
Tincher Preparatory School
Wilson H.S.
• Ruhnau Ruhnau Clarke Completing Scope of Work Assessment
• Anticipated Bidding – December 2011
• Anticipated Replacement – May through September 2013
III. Project Development Update
Project Prioritization
20
III. Project Development Update
Primary and Influencing Criteria
Impacts and Changes
• Major Projects
• Roosevelt Elementary School (Area E)
Facility Master Plan Group 1
• Jordan High School (Area A)
Facility Master Plan Group 1
• Cabrillo High School – Pool (Area D)
Facility Master Plan Group 1
• New High School #2 at Browning Site (Area E)Facility Master Plan Group 1
• District-Wide Projects
• AB 300: Newcomb K-8 Academy (Area C)
Facility Master Plan Group 2
21
III. Project Development Update
Project Steps and Work Effort
Overall Project Summary
• Durations subject to change based upon type of project
(major, small, pilot)• Many phases and work efforts overlap
22
III. Project Development Update
Project Steps and Work Effort
Exponential Growth
Roosevelt Elementary School - rebuild
Jordan High School – major modernization
Cabrillo High School – Pool Addition
New High School #2 (Browning Site)
Newcomb K-8 Academy – major modernization
Core Switch and UPS Replacement Project 2010
Access Compliance Projects (multiple)
Boiler Replacement Project
Lighting and Ceiling Replacement Project
Window Replacement Project
Door and Door Hardware Replacement Project
Phase I DOH Removal Project
DSA Certification and Close-Out Projects (multiple)
23
III. Project Development Update
Project Steps and Work Effort
Delays and Course Changes
24
Originally Planned
Destination
Let’s go on a
safari
instead!
IV. Master Program Schedule
25
Schedule Adjustments
• Refinement of Major and District-Wide Project Planning Cost
Estimates Noted
• Changes in Completion and Occupancy Dates• New High School #1 (ECATS) – moved to a later occupancy
• Jordan High School – moved to a later occupancy
• New High Scholl #2 (Browning Site) - moved to an earlier
occupancy
• Cabrillo High School – Pool Addition – moved to an earlier occupancy
• AB 300 Buildings Phase 1 Project – Newcomb K-8 Academy• Project Identified and Schedule Adjusted Accordingly
• Deportablization• Phase 1 Project – DOH Removal – moved to a later completion
date
• Facility Component Improvements – Projects Identified
IV. Master Program ScheduleMajor Projects – Five-Year Look Ahead Schedule
26
IV. Master Program ScheduleDistrict-Wide Projects – Five-Year Look Ahead Schedule
27
V. Master Program Budget Update
Budget Adjustments and
Expenditure Summary
• Addition of New Major Project and District-Wide Project
Budgets
• Refinements in Major Project and District-Wide Project
Budgets
Quarter by Quarter Expenditure Summary
28
V. Master Program Budget Update
29
VI. Facility Master Plan Review
Changes in Facility Master Plan
Community Advisory Committee
Recommendations Review
• Projects and Priorities List from
Executive Committee (Newcomb
moved up from Group 2 Projects)
• Facilities Branch Develop Internal
Capacity and Authorize
Professional Services to
Implement Facility Master Plan
30
VII. Facilities Statistics
Year In Review (July 2009 – June 2010)
RFQs and SOQs
31
Annual Totals
Number of RFQs/SOQs Issued 7
Number of Responses 210Received and Reviewed
Number of Interviews Conducted 42
Month-to-Month Comparison
Issued Received Interviewed
June 2009 1 12 0
2010 3 59 11
July 2009 0 0 0
2010 1 15 0
VII. Facilities Statistics
Year In Review (July 2009 – June 2010)
RFPs
32
Annual Totals
Number of RFPs Issued 9
Number of Responses 51Received and Reviewed
Number of Interviews Conducted 6
Month-to-Month Comparison
Issued Received Interviewed
June 2009 0 0 0
2010 0 0 0
July 2009 4 42 5
2010 10 22 0
VII. Facilities Statistics
Year In Review (July 2009 – June 2010)
Contracts and Buy-Outs
33
Annual Totals
Number of Contracts/Buy-Outs 193
Contracts 98
Buy-Outs 95
Dollar Value of Contracts/ $24.27M
Buy-Outs
Contracts $23.70M
Buy-Outs $ 0.57M
VII. Facilities Statistics
Year In Review (July 2009 – June 2010)
Invoices and Payments
34
Annual Totals
Number of Invoices 654
Dollar Value of $23.2M
Invoices Paid
VII. Facilities Statistics
Year In Review (July 2009 – June 2010)
Developer Fees
35
Annual Totals
Number Fees Processed 144
Dollar Value of Fees $570.6K
Month-to-Month Comparison
Fees Value ofProcessed Fees
June 2009 0 $0K2010 16 $93.7K
July 2009 3 $3.7KJuly 2010 14 $109.1K
VII. Facilities Statistics
Year In Review (July 2009 – June 2010)
Facilities Information Requests
36
Annual Totals
Number Open Requests Prior to 7/1/09 7
Number of New Requests Received 71/09 – 6/30/10 144
151
Number Requests Closed 7/1/09 – 6/30/10 108
Number Requests Still Open 43
VII. Program Successes
Efficiencies and Best Practices
37
• Program and Project Accounting Protocols and
Procedures
• Routine and Regular Staff Training (continued)
• Insurance and Risk Management Review and Analysis
• Development and Implementation of Boilerplate Contracts
• Development and Implementation of Program
Management Tools (such as standardized RFP, RFQ and
SOQ documents; school site records “binder” format)
• Design Standards Review on New High School #1 –
ECATS Project
38
Next 12 Months
• Numerous Stakeholder
Meetings
• Major Project Planning
Activities
• Enrollment Capacity and Use
Studies
• Opening of New 6-8 Middle
School #1 at GTE Site
• Roosevelt Elementary School
Interim Housing
Phase I DOH Removal Project
Pilot Projects
Technology Upgrade Projects
For More Information
This Presentation
(along with Board Workbook Materials)
is available at:
www.lbschools.net
39