Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
EXPLORATORY STUDY INTO THE USE
OF LAST PLANNER® SYSTEM AND
COLLABORATIVE PLANNING FOR
CONSTRUCTION PROCESS
IMPROVEMENT
EMMANUEL ITODO DANIEL
A thesis submitted in partial fulfilment of the requirements of
Nottingham Trent University for the degree of Doctor of
Philosophy
May 2017
Preliminary Pages
i
Copyright Statement
This work is the intellectual property of the Author, Emmanuel Itodo Daniel. You
may copy up to 5% of this work for private study, or personal, non-commercial
research. Any reuse of the information contained within this document should be
fully referenced, quoting the author, title, university, degree level, and pagination.
Queries or requests for any other use, or if a more substantial copy is required,
should be directed in the owner of the Intellectual Property Rights.
Declaration
I hereby, declare that this dissertation has not been submitted in part or in whole as
paperwork for a degree at any other university. I hereby declare that this dissertation
is entirely my own work and that all parts and thoughts which have been taken from
other persons are marked and identified by reference.
Signature:………………………….
Date:………………………………
Preliminary Pages
ii
Abstract
The Egan report, generally called Rethinking Construction, challenged the lack of
collaboration in planning, designing, and executing work on site, and recommended
the adoption of lean production principles such as the Last Planner System (LPS) to
enhance the image and efficiency of the industry. Recent evidence from different
parts of the world suggests that the implementation of the LPS has gained
prominence in the construction industry and its influence on the production system is
rapid and significant. However, the application of this system in the UK construction
industry has not been fully explored among industry practitioners. In addition, a
systematic understanding of how Collaborative Planning (CP) practice in the UK
aligns with the LPS is still lacking. The absence of authoritative research and
empirical data makes it difficult for an appropriate approach to be developed to
improve current practice.
In view of these problems, this research was under taken to unravel how the current
application of CP for delivering construction projects in the UK align with the LPS
principles and to develop an approach to support construction stakeholders in the
implementation of the LPS. Both qualitative and quantitative methods were used in
this investigation. Data were collected from across these sectors (building, highways
infrastructure, and rail) of the UK construction industry. A total of 58 interviews
were conducted, 15 projects observed, 3 case studies conducted and 10 evaluation
surveys received. The study found that the current practice of CP as observed in the
major sectors of the UK construction industry only align partially with some of the
generally advocated principles of the LPS acknowledged in the literature. Analysis of
the results reveals that the current practice of CP in the UK has not explored all
components of the LPS and depth of application of the more complex attributes
contained in the LPS is weak or missing.
The information gleaned from the finding uncovers and highlights the need to
develop an approach to support construction stakeholders in the implementation of
the LPS. Accordingly, this study developed the Last Planner System Path Clearing
Approach (LPS-PCA) that includes organisational and external path clearing levels.
This expands previous approaches to the implementation of the LPS in construction
which focused more on the project level. Pilot implementation on a live project
indicates that the developed LPS-PCA supports LPS implementation.
Preliminary Pages
iii
Dedication
This thesis is dedicated to my loving wife Dr. Oluwabukola Daniel for all her
immeasurable support and to my daughter Covenant Daniel for the joy she has
brought into our family.
“Let us hear the conclusion of the
whole matter: Fear God, and
keep his commandments: for this
is the whole duty of man”
The Bible: Ecclesiastes 12:13
Preliminary Pages
iv
Acknowledgement
Glory to God in the highest heavens, for all his marvellous works! My utmost
appreciation is to the almighty God for His guidance, wisdom, provision, and
sustaining grace throughout my PhD Journey at Nottingham Trent University.
The effort of my Director of Studies; Professor Christine Pasquire cannot be
overemphasised as without her, my research would not have started at NTU. Her
motherly advice and supports during the course of my studies helped in making my
PhD journey a lot smoother than envisaged. The guidance and mentorship received
from her have greatly enhanced my knowledge on lean construction and the final
output of this thesis. I equally like to thank my supervisor Dr. Graham Dickens for
his critical but constructive review of all aspects of my work which has helped in the
final output of this thesis. I cannot but mention your arranging visits and conveying
me to numerous construction sites during the data collection period.
My appreciation goes to all lean construction professionals interviewed in this study
and all those that contributed towards the success of the case studies such as Darren
Raunen, Rob Sangster, Kate Seller; Martin Wing, and John Studd. I also
acknowledge the contributions of the Lean Construction Institute UK and its Board
of Directors chaired by Derek Drysdale, for providing travel allowance for my data
collection. The advice and guidance received from lean construction community has
helped in shaping this study, notable is that from Prof. Glenn Ballard, Prof. Lauri
Koskela, and Alan Mossman among others. Thank you to all my friends and PhD
colleagues at the Centre for Lean Project- you are kind. The support of friends such
Olalekan Oshodi, and Agabi Yusuf is heart-warming. The spiritual support and
encouragement from the members and leadership of Deeper Life Bible Church
Nottingham is highly appreciated.
I would like to thank the entire Daniel Itodo family for their patience while I’m away
from them. Especially my Mum; Esther Daniel and my Dad; late Mr Daniel Itodo for
believing and instilling the faith in me that I would attain this height. I remember my
late sister Hannah who was taken away by death during the course of this research.
The support of my in-laws and their family cannot be forgotten; the Okes’, the
Idowus’ and the Akintans’ – you are awesome. Thank you to Mummy Oke for your
prayers.
To my loving wife Dr. Oluwabukola Daniel; I lack words to express my
appreciation; I value all your contributions to the success of this journey especially in
reading through every piece of my writing. Also, for the emotional support you and
my gorgeous daughter Covenant have provided. We did this together! - Thank you.
Preliminary Pages
v
Table of Content
Copyright Statement i
Declaration i
Abstract ii
Dedication iii
Acknowledgement iv
Table of Content v
List of Figures xv
List of Tables xvii
List of Abbreviations xix
CHAPTER ONE: INTRODUCTION TO THE STUDY 1
1.1 Study Context 1
1.2 The Research Problem 3
1.3 Rationale and Justification of the Study 5
1.4 Research Questions 7
1.5 Research Aim 7
1.6 Research Objective 7
1.7 Scope of the Study 8
1.8 Overview of Work Done 8
1.8.1 Overview of Research Methodology. 8
1.8.2 Overview of Research Process 9
1.8.3 Overview of Research Contribution to Knowledge 11
1.8.4 Thesis Structure 11
1.9 Chapter Summary 14
CHAPTER 2: CONSTRUCTION PROCESS IMPROVEMENT AND THE
DEVELOPMENT OF PRODUCTION PLANNING AND CONTROL BASED ON
THE LAST PLANNER SYSTEM IN THE UK CONSTRUCTION INDUSTRY 15
2.1 Introduction 15
2.2 Process Improvement in the Construction Industry 15
2.2.1 The UK Construction Industry 15
2.2.2 The Concept of Construction Process Improvement 16
2.2.3 Current State of Construction Process Improvement in the Industry 18
2.2.5 Demand for Construction Process Improvement in the UK 18
2.2.6 Review of Construction Industry Reports 19
2.2.6.1 Latham Report: Constructing the Team 20
2.2.6.2 Egan Report: Rethinking Construction 21
Preliminary Pages
vi
2.2.6.3 Accelerating Change 21
2.2.6.4 Never Waste Good Crisis 22
2.2.6.5 Government Construction Strategy 22
2.2.6.6 Construction 2025 Report 23
2.2.6.7 Summaries and Major Outcomes of the Construction Industry Reports 23
2.3 Development of the Last Planner System in the UK 25
2.4 Emergence of Improvement Programmes in the UK Construction Industry 28
2.4.1 Overview of the Construction Lean Improvement Programme (CLIP) 28
2.4.2 Review of CLIP Pilot Projects 30
2.4.3 CLIP: Collaborative Planning Practice Review Discussed 35
2.5 Chapter Summary 36
CHAPTER THREE: COLLABORATION IN CONSTRUCTION AND THE
DEVELOPMENTS OF COLLABORATION IN PLANNING IN OTHER FIELDS:
IMPLICATION FOR CONSTRUCTION MANAGEMENT 38
3.1 Introduction 38
3.2 The Concept of Collaboration 38
3.2.1 Current State of Collaborative Working in the Construction Industry 40
3.3 Collaboration and Construction Planning 41
3.3.1 Concept of Planning 41
3.3.2 Overview of Construction Planning 42
3.3.3 The Current State Construction Planning and Collaboration 44
3.4 Development of Collaboration in Planning in other Fields 45
3.4.1 Historical Development of Collaboration in Urban Planning 45
3.4.1.1 The Rational Comprehensive Model of Planning 46
3.4.1.2 Advocacy Planning Model 46
3.4.1.3 Collaborative Planning Model in Urban Planning 47
3.4.2 Critical Path Method and Rational Comprehensive Model in Planning 48
3.5 Collaboration in Planning: Search in Software Design 49
3.5.1 Waterfall Process Model 50
3.5.2 Iterative Process Model. 51
3.5.3 Agile Process Models 51
3.5.3.1 Scrum 52
3.6 Comparing the CPM, RCM, Collaborative Planning and the LPS 53
3.7 Development of Collaboration in Planning in other Fields: Implication for Construction
Project Management 56
3.7.1 Implication for Construction Project Management Practice 56
3.7.2 Implication for Construction Project Management Theory 58
Preliminary Pages
vii
3.8 Chapter Summary 60
CHAPTER FOUR: PRODUCTION PLANNING AND CONTROL IN
CONSTRUCTION BASED ON THE LAST PLANNER SYSTEM 62
4.1 Introduction 62
4.2 Production Planning and Control 63
4.2.1 Production Planning: The Search in Management Science 63
4.2.2 Production Planning: The Search in Lean Production 63
4.2.3 Application of Lean Production Philosophy in Construction 64
4.2.4 Criticism of Lean Construction 65
4.2.5 Lean Philosophy in Production Planning and Control in Construction 67
4.2.6 Evaluating Production Planning and Control in construction 68
4.3 The Last Planner System of Production Control 69
4.3.1 The Last Planner System: An Overview 69
4.3.2 Components of the Last Planner System 70
4.3.2.1 The Master Plan or Milestone Planning 71
4.3.2.2 Phase Planning or Collaborative Programming 71
4.3.2.3 Look-Ahead Planning 73
4.3.2.4 Make-Ready Process 74
4.3.2.5 Weekly Work Plan (WWP) 75
4.3.2.6 First Run Studies 77
4.4 Theories used in Explaining the Last Planner System 78
4.4.1 Transformation and Flow Theory in the Last Planner System 79
4.4.2 Management-as-Planning and Management-as-Organising Theory in the LPS 80
4.4.3 Language/Action Perspective Theory in the Last Planner System 80
4.4.4 Scientific Experimental Model 81
4.5 Last Planner System Implementation and Developments- Review of IGLC papers 82
4.5.1 Overview of the Review 82
4.5.2 Review Framework 83
4.5.3 Last Planner System Implementation across Countries 86
4.5.4 Major Components of Last Planner System Implemented 87
4.5.5 Trends in the Implementation of LPS Components 88
4.5.6 Last Planner System Implementation Success Factors 88
4.5.7 Last Planner System Implementation Drivers 90
4.5.8 The Impact and Benefits Last Planner System on Construction Process Improvement 90
4.5.9 LPS Implementation Challenges in Construction 91
4.5.10 Past and Current Developments in the Last Planner System 93
4.6 Summary of Chapter 97
Preliminary Pages
viii
CHAPTER FIVE: RESEARCH METHODOLOGY AND DESIGN 99
5.1 Introduction 99
5.2 Understanding Research Methodology and Methods 99
5.3 Research Philosophy 100
5.3.1 Ontology 101
5.3.2 Epistemology 102
5.3.3 The Relationship between Ontology, Epistemology, Methodology, and Research
Methods 103
5.4 Research Paradigms 104
5.4.1 Positivism 104
5.4.2 Interpretivism 105
5.4.3 The Chosen Paradigm and the Rationale 106
5.5 Research Strategy 107
5.5.1 Quantitative Approach 107
5.5.2 Qualitative Approach 108
5.6 Research Method Consideration and Choice of Research Method for the Study 110
5.6.1 Ethnography Evaluation 111
5.6.2 Design Science/ Action Research Evaluation 112
5.6.3 Surveys Approach Evaluation 113
5.6.4 Interviews 114
5.6.5 Case Study 116
5.6.6 Rationales for Choosing Mixed Method 118
5.7 Research Design and Phases 120
5.7.1 Stage 1: Literature Review 122
5.7.2 Stage 2: Semi-structured Interviews 124
5.7.2.1 Interview Plan 125
5.7.2.2 Interview Protocol 125
5.7.2.3 Sampling 127
5.7.2.4 Conducting the Interview 129
5.7.2.5 Interview Transcription 131
5.7.2.6 Analysis of Interview 131
5.7.3 Stage 3: Structured Observation 133
5.7.3.1 Observation Schedule 134
5.7.3.2 Observation Checklists 135
5.7.3.3 Structured Observation Sampling 136
5.7.3.4 Data Collection and Analysis of Structured Observation 137
5.7.4 Stage 4: Multiple Case Study 138
Preliminary Pages
ix
5.7.4.1 Case Study Planning 139
5.7.4.2 Case Study Selection 139
5.7.4.3 Data Collection Protocol 141
5.7.4.4 Data Collection 142
5.7.4.5 Data Analysis 145
5.7.4.6 Cross Case Analysis 148
5.7.4.7 Post Case Study Evaluation Survey 149
5.7.5 Phase 5: Development and Validation of Last Planner System Path Clearing Approach
149
5.8 Quality of Research 150
5.8.1 Credibility (Internal validity) 150
5.8.2 Transferability (External validity) 151
5.8.3 Dependability (Reliability) 151
5.8.4 Confirmability (Objectivity) 152
5.9 Summary of Chapter 152
CHAPTER SIX: RESULTS AND DISCUSSIONS ON EXPLORATORY
INTERVIEWS AND STRUCTURED OBSERVATIONS 154
6.1 Introduction 154
6.2 Phase 2: Semi-Structured Interviews 154
6.2.1 Analysis, Presentation, and Discussion of Semi-Structured Interviews 154
6.2.2 Demographic Information of Interviewees 155
6.2.3 Current View on Construction Planning and Programming. 158
6.2.3.1 Un-collaboratively developed 159
6.2.3.2 Too much Assumption and Unrealistic 159
6.2.4 Current Industrial Perception of Last Planner System and Collaborative Planning in the
UK 160
6.2.4.1 Use of the terms “Collaborative Planning” and “Last Planner System” 160
6.2.4.2 Meaning Ascribed to the Last Planner System and Collaborative Planning 162
6.2.4.3 Time and Programme Compression 164
6.2.4.4 Common Understanding of Construction Programme 164
6.2.4.5 Intervention Measure 164
6.2.5 Current Success Factors for Implementing LPS/CP in the UK 165
6.2.5.1 Early Engagement with the Supply Chain 166
6.2.5.2 Use of Integrated Supply Chain Model 166
6.2.5.3 Inclusion of LPS/CP in the Contract 167
6.2.5.4 Appointment of Lean Champions and Support from Lean Consultants 168
6.2.5.5 Procurement of Supply chain based Collaborative Practice 168
6.2.6 Current Drivers for Implementing LPS/CP in UK Construction 169
Preliminary Pages
x
6.2.6.1 Client and Public sector Demand 170
6.2.6.2 Internal Drive for Continuous Improvement by Organisation 171
6.2.6.3 Benefit from Previous Implementation and Quest for Improved Working
Relationship 171
6.2.6.4 Quest for on Time delivery of Project and to Overcome Past Failures 172
6.2.7 Benefits of Implementing LPS/CP Observed in the UK construction 172
6.2.7.1 General Benefits of Implementing LPS/CP Observed in the UK 173
6.1.7.2 Social Benefits of Implementing LPS/CP in Construction 174
6.2.7.3 Process Benefits of Implementing LPS/CP Observed in the UK 175
6.2.7.4 Level of Benefits from LPS/CP Implementation on Projects in the UK 176
6.2.7.5 Modelling the Benefits of Implementing LPS/CP Observed in the UK 177
6.2.8 Barriers to Implementing LPS/CP in the UK Construction 178
6.2.8.1 Cultural Issues at Project and Organisational Levels 178
6.2.8.2 The Use of Fragmented Subcontracting Model 180
6.2.8.3 Partial Involvement of Subcontractors 180
6.2.8.4 Time Pressure and Lack of Discipline 181
6.2.8.5 Self Protectionism 181
6.3 Stage 3: Structured Observations 182
6.3.1 Results and Discussion 182
6.3.2 Description of Projects Observed 182
6.3.3 Results of Record and Physical Condition Analysis 184
6.3.4 Results of Physical Process Analysis 186
6.3.4.1 Production Planning and Control Practices Observed 186
6.3.4.2 Effectiveness of Production Planning and Control Practices Observed Across
Projects in the UK 189
6.3.5 Mapping of Collaborative Planning Practice in the UK with the Last Planner System
191
6.4 Discussion of Findings on Collaborative Planning Practice Observed with LPS Principles
192
6.5 Chapter Summary 194
CHAPTER SEVEN: MULTIPLE CASE STUDY DATA ANALYSIS, CROSS CASE-
COMPARISON AND DISCUSSION 196
7.1 Introduction 196
7.2 Stage 4: Multiple Case Studies Overview 196
7.3 Case Study Project One (CSP01): Highways and Infrastructure 197
7.3.1 Last Planner/Collaborative Planning Practice on CSP01 199
7.3.1.1 Application of Last Planner/Collaborative Planning on CSP01 199
7.3.1.2 Pre-construction Practice 200
Preliminary Pages
xi
7.3.1.3 Nature of Last Planner/Collaborative Planning Meeting on CSP01 201
7.3.1.4 Percentage Plan Complete and Reason for Non-Completion Practice 201
7.3.2 Support required for LPS/CP Implementation as Observed on CSP01 203
7.3.2.1 Process and Support required at the Organisational Level. 203
7.3.2.2 Process and Support required at the Project Level 206
7.3.2.3 External Process Support Required 207
7.3.3 Procurement and LPS/CP on CSP01 208
7.3.3.1 Procurement Practice Observed on CSP01 208
7.3.3.2 Impact of Procurement Practice on LPS/CP on CSP01 209
7.3.4 Impact of LPS/CP Practice on Construction Process Improvement on CSP01 211
7.3.4.1 Impact on Time 212
7.3.4.2 Collaborative Working Practice, Communication, and Process Transparency 212
7.3.4.3 Impact on Re-work, Safety, and General Process Improvement 214
7.4 Case Study Project Two (CSP02): Highways Infrastructure 215
7.4.1 Last Planner/Collaborative Planning Practice Observed on CSP02 217
7.4.1.1 Application of Last Planner and Collaborative Planning on CSP02 217
7.4.1.2 Pre-construction Practice 217
7.4.1.3 Nature of Production Planning Meetings on CSP02 218
7.4.1.4 Percentage Plan Complete and Reason for Non-completion Practice 218
7.4.2 Support required for Last Planner/Collaborative Planning 220
7.4.2.1 Support required at the Organisational Level 220
7.4.2.2 Support Required at the Project Level 223
7.4.2.3 External Support required for LP and CP Implementation 224
7.4.3 Procurement and LPS/CP on CSP02 226
7.4.3.1 Procurement Practice on CSP02 226
7.4.3.2 Impact of Procurement on LPS/CP Practice on CSP02 226
7.4.4 Impact of LPS/ CP Practice on Construction Process Improvement on CSP02 228
7.4.4.1 Impact on Time and Programme 228
7.4.4.2 Collaborative Working Practice, Communication, and Process Transparency 229
7.4.4.3 Impact on Re-work, Safety, and General Process Improvement 231
7.5 Case Study Project Three (CSP03): Educational New Build 231
7.5.1 Last Planner /Collaborative Planning Practice Observed on CSP03 233
7.5.1.1 Application of Last Planner and Collaborative Planning on CSP03 233
7.5.1.2 Activity Scheduling as Observed on CSP03 234
7.5.1.3 Nature of Production Planning and Control Meetings on CSP03 234
7.5.2 Procurement and LPS/CP on CSP03 235
7.5.2.1 Pre-construction Practice 235
Preliminary Pages
xii
7.5.2.2 Impact of Procurement Practice on LPS/CP Implementation on CSP03 236
7.5.3 Support required for Last Planner/Collaborative Planning 237
7.5.3.1 Support required at the Organisational Level 237
7.5.3.2 Process and Support required at the Project Level on CSP03 239
7.5.3.3 External Support required for LPS/CP implementation 240
7.5.4 Impact of LPS/CP Practice on Construction Process Improvement 241
7. 5.4.1 Impact on Time and Programme 241
7.5.4.2 Collaborative Working Practice, Communication, and Process Transparency 243
7.5.4.3 Impact on Re-work, Safety, Non-value Adding Activities, and General Process
Improvement 243
7.6 Cross Case Study Analysis and Discussion 244
7.6.1 Case Study Context and Description of Case Study Projects 244
7.6.2 Demographic Information of Research Participants 245
7.6.3 Cross-case Comparison of Last Planner/ Collaborative Planning Practice 246
7.6.4 Cross-case Comparison and Discussion on Procurement and LPS/CP Practice 249
7.6.5 Cross-case Comparison and Discussion on the nature of Support Required for LPS/CP
Implementation. 251
7.6.5.1 Support Required for LPS/CP Successful Implementation at the Organisation
Level 252
7.6.5.2 Support required for LPS/CP Successful Implementation at the Project Level 253
7.6.5.3 External Support Required for LPS/CP Successful Implementation 254
7.6.6 Cross-case Comparison and Discussion on the Impact of LPS/CP Implementation on
Construction Improvement. 255
7.6.6.1 Impact on Time and Programme. 255
7.6.6.2 Impact on Collaborative Working Practice 256
7.6.6.3 Impact on Rework and Quality 256
7.6.6.4 Impact on Safety 257
7.7 Chapter Summary 257
CHAPTER 8: DEVELOPMENT AND EVALUATION OF THE LAST PLANNER
SYSTEM PATH CLEARING APPROACH 259
8.1 Introduction 259
8.2 Rationale for the Last Planner System-Path Clearing Approach 259
8.3 Theoretical Overview of the Proposed Approach 260
8.4 Background to the Last Planner System Path Clearing Approach 261
8.4.1 The LPS Path Clearing Approach 261
8.4.2 What the proposed Approach is not 262
8.4.3 The Reason for Using LPS-PCA 262
8.4.4 Basic Diagram of LPS Path Clearing Approach 262
Preliminary Pages
xiii
8.4.5 Schematic Diagram of LPS Path Clearing Approach 263
8.4.6 Definitions of Key Components in the LPS-PCA 264
8.5 Description of the Composition of the LPS-PCA 265
8.5.1 Organisational Level 265
8.5.1.1 Organisational Level Process Input Factors 265
8.5.1.2 Contextual Inputs Factors (Behaviours arising from the contract) 268
8.5.2 Project Level 270
8.5.2.1 Project Level Process Input Factors 270
8.5.2.2 Project Level Contextual Input Factors (Social Behaviour) 274
8.5.3 External Enablers 275
8.5.4 Continual Learning Action and Feedback Loop 275
8.6 Evaluation and Refinement of the LPS-PCA 276
8.6.1 Rationale for Evaluation of the Proposed Approach 276
8.6.2 LPS-PCA Evaluation Method 277
8.6.3 Demographic Information of Participants used in the Evaluation 278
8.6.4 Discussion of the Evaluation Results 279
8.6.4.1 Completeness of Components and Contents of the Proposed Approach 280
8.6.4.2 Application and Usefulness of the Proposed Approach 281
8.6.4.3 Refinements to LPS-PCA Following Evaluation Feedbacks 282
8.6.4.4 Emerging Influence of the LPS-PCA and the Pilot Implementation 282
8.6.4.4 Feedback on Pilot Implementation LPS-PCA in a Client Organisation 283
8.7 Chapter Summary 284
CHAPTER 9: CONCLUSIONS AND RECOMMENDATIONS 285
9.1 Introduction 285
9.2 Re-statement of Research Aim, Objectives and Process 285
9.3 Summary of Research Findings 285
9.4 Conclusions on Research Objectives 287
9.4.1 Objective 1 288
9.4.2 Objective 2 289
9.4.3 Objective 3 290
9.4.4 Objective 4 290
9.4.5 Objective 5 291
9.4.6 Objective 6 292
9.5 Conclusion on Research Questions 292
9.6 Original Contribution of Research to Knowledge 293
9.6.1 Contribution to Theory. 293
9.6.2 Contribution to Practice 294
Preliminary Pages
xiv
9.6 Research Publications 294
9.6.3 Conference papers 294
9.6.4 Journal Publications 295
9.6.5 Future Publication Plan 295
9.7 Research Limitations 296
9.8 Recommendations 296
9.8.1 Recommendation for Industry Practitioners 296
9.8.2 Recommendation for Further Research 297
References 299
APPENDICES 341
Appendix 1: Sample of Semi –structured interview guide 341
Appendix 2: Approval Letter from College Ethical Committee 343
Appendix 3: Sample of Interview Invitation/Consent Letter Issued 344
Appendix 4: Transcribed Interview Sample 345
Appendix 5: Last Planner System Practice Evaluation Instrument 350
Appendix 6: Sample of Case Study Consent Letter Issued 351
Appendix 7: Case Study Interview Guide 352
Appendix 8: Post Case Study Survey Instrument 354
Appendix 9: Last Planner Path Clearing Approach Evaluation Survey Guide 357
Appendix 10: Last Planner System Path Clearing Approach A3 Size 359
Appendix 11: Last Planner System Path Clearing Approach Industry Guide 360
Preliminary Pages
xv
List of Figures
Figure 1.1: Thesis Structure 12
Figure 2. 1: Timeline of construction industry report that magnify the need for Collaboration
in the delivery of construction projects 20
Figure 2. 2: Timeline highlighting the development of the Last Planner System and
Collaborative Planning in the UK 26
Figure 2. 3: Fundamental Approach of CLIP 30
Figure 3.1: Development of collaborative planning model in Urban and Regional planning
46
Figure 3.2: Development of collaborative planning in software design 49
Figure 3.3: Waterfall process model 50
Figure 3.4: The Scrum Process 52
Figure 4.1: The Last Planner System of Production Control Model 71
Figure 4.2: The learning loop in the Last Planner System 77
Figure 4.3: The review framework 83
Figure 4.4: Components of LPS reported in the review 87
Figure 4.5: Trend in LPS Elements Implemented across the Years 88
Figure 4.6: Last Planner System implementation success factors in construction 89
Figure 4.7: LPS Implementation Benefits in Construction 91
Figure 4.8: Last Planner Implementation Challenges in Construction 93
Figure 4.9: Timeline highlighting major developments in the Last Planner System 95
Figure 5.1: The relationship between research philosophy and methods 100
Figure 5.2: The Logic of Research building block 103
Figure 5.3: Research Design and Process 121
Figure 5.4: Literature Review Chapter Flowchart 123
Figure 5.5: Interview Process 125
Figure 5.6: Interview Questions Development Protocol 127
Figure 5.7: Interview Data Analysis Process used in the Study 132
Figure 5.8: Case Study Research Design 138
Figure 5.9: Case Study Data Collection Sources 142
Figure 5.10: Case Study Analysis Process 145
Figure 5.11: Distribution of Interviewees across the Case Studies 146
Figure 5.12: Emerging Concept and Theme Tree 147
Figure 5.13: Result of procurement practice on CSP01 graphically presented with ‘model
tool’ as exported from NVivo 10 148
Figure 6.1: Positions Occupied by Interviewees 157
Figure 6.2: Current View on Master Programme 158
xvi
Figure 6.3: Current industrial perceptions on LPS and CP in the UK 160
Figure 6.4: LPS/CP success factors in the UK Construction industry 165
Figure 6.5: Drivers for implementing LPS/CP in the UK construction industry 170
Figure 6.6: Categorisation of the benefits of implementing LPS/CP in the UK 173
Figure 6.7: Current LPS/CP implementation barriers in the UK 179
Figure 6.8: Pull Planning or Collaborative Programming board with Sticky-Notes for
scheduling 184
Figure 6.9: Pull Planning or Collaborative Programming board with temporary marker for
scheduling 184
Figure 6.10: Visual Management Board to Communicate Progress of Work 186
Figure 6.11: Level of Implementation of production planning and control principles on
projects observed 187
Figure 6.12: Comparing Collaborative Planning in the UK with the Last Planner System
Components 191
Figure 7.1: Average PPC on CSP01 (A sample of document analysed) 202
Figure 7.3: Reason for non-completion of activities on CSP01 202
Figure 7.4: Support for successful implementation of Last Planner/Collaborative Planning
205
Figure 7.5: Impacts of LPS/CP on CPI observed on CSP01 (interview results) 211
Figure 7.6: Last Planner/Collaborative planning impacts on construction process
improvement on CSP01 213
Figure 7.7: Average PPC chart on CSP02 (A sample of document analysed). 219
Figure 7.8: Reasons for non-completion of activities (A sample of document analysed) 219
Figure 7.9: Support for successful implementation of LPS/CP 222
Figure 7.10: Impacts of LPS/CP practice on CPI observed on CSP02 (interview results) 228
Figure 7.11: Last Planner/Collaborative planning impacts on construction process
improvement on CSP02 230
Figure 7.12: Support required for successful implementation of LPS/CP Observed on CSP03
238
Figure 7.13: Impacts of LPS/CP on CPI observed CSP03 (interview results) 241
Figure 7.14: Last Planner/Collaborative planning impacts on construction process
improvement on CSP03 242
Figure 7.15: Cross Case-comparison of research participants 246
Figure 8.1: LPS Path Clearing Approach Block Diagram 262
Figure 8.2: LPS Path Clearing Approach 264
Preliminary Pages
xvii
List of Tables
Table 2 1: Major Construction Industry Reports showing the need for Collaboration in the
Design, Planning, and Execution of Work 24
Table 2.2: The Seven CLIP Focus Development Areas 29
Table 2.3: Collaborative Planning Practice Reported on CLIP Demonstration Projects 31
Table 3.1: Rational Comprehensive Model Compared with Collaborative Planning Model 47
Table 3.2: Comparing CPM, RCM, Collaborative Planning in UP, Agile process model and
the Last Planner System 55
Table 4.1: Underlying Theories of the Last Planner System 79
Table 4.2: IGLC Papers on LPS Implementation between 1993 and 2014 Retrieved 84
Table 4.3: Last Planner System Implementation across Countries 86
Table 5.1: Comparing Positivist and Interpretivist Research Philosophies 106
Table 5.2: Differences between Quantitative and Qualitative Strategies 109
Table 5.3: Strengths and Weaknesses of the Interview Approach 115
Table 5.4: Interview Type in Relation to the Nature of the Study 115
Table 5.5: Strengths and Weaknesses of Sources of Evidence in Case Study 117
Table 5.6: Relationship between the Research Objectives and Phases of the Study 122
Table 5.7: Research Quality Criteria 150
Table 6. 1: Descriptions and Distribution of Interviewees across the UK Construction Sector
155
Table 6.2: Meaning ascribed to the Last Planner System and Collaborative Planning 162
Table 6.3: Prioritisation of LPS/CP benefits using the lens of the stakeholders 177
Table 6.4: Description of project observed & evaluated for production planning and control
Practice 183
Table 6.5: Practices observed across projects 190
Table 7.1: CSPO1 Project Attributes 197
Table 7.3: Description of respondents interviewed CSP01 199
Table 7.4: CSPO2 Project Attributes 215
Table 7.5: Demographic Information of the Respondents on CSP02 216
Table 7.6: CSP01 Project Attributes 232
Table 7.7: Demographic information of respondents interviewed on CSP03 233
Table 7.8: Cross -case Comparison of Project Attributes 244
Table 7. 9: Cross-case Analysis of Last Planner System/Collaborative Planning 246
Table 7.10: Cross-case Comparison of Procurement Practice 250
Table 7.11: Summary of the nature support required for LPS/CP implementation from the
Case Studies 251
Table 8. 1: Background Information of the Participant used for the evaluation 278
Table 8. 2: Results of LPS-PCA Evaluation 279
xviii
Table 9. 1: Research Objectives and How they were Achieved 287
Preliminary Pages
xix
List of Abbreviations
AR Action Research
BAA British Air Authority
BEA Bureau of Economic Analysis
BIM Building Information Modelling
BRE Building Research Establishment
CDM Construction (Design and Management)
CIOB Charted Institute of Building
CL Client
CLIP Construction Lean Improvement Programme
CO Consultant
CP Collaborative Planning
CPI Construction Process Improvement
CPM Critical Path Method
CSP Case Study Project
CW Collaborative Working
D&B Design and Build
DBB Design Bid Build
DSR Design Science Research
DTI Department of Trade and Industry
ECI Early Contractor Involvement
EU European Union
FRS First Run Studies
GDP Gross Domestic Product
HE Highways England
IGLC International Group for Lean Construction
JIT Just In Time
JV Joint Venture
LAP Language /Action Perspective
LC Lean Construction
Preliminary Pages
xx
LCI Lean Construction Institute
LPS Last Planner System
LPS/CP Last Planner System/Collaborative Planning
MAO Management-as- Organising
MAP Management-as- Planning
MC Main Contractor
MM Middle Manager
NSP Non Study Participant
NTU Nottingham Trent University
OL Organisational Level
OP Operational Planning
PBP Planning Best Practice
PL Project Level
PMBOK Project Management Body of Knowledge
PMI Project Management Institute
PP&C Production Planning and Control
PPC Percent Plan Complete
RNC Reasons for Non- Completion
SC Subcontractor
SE Software Engineering
SM Senior Manager
SP Study Participant
TA Task Anticipated
TFV Transformation Flow and Value
TMR Task Made Ready
TPS Toyota Production System
UK United Kingdom
UP Urban Planning
US United States
VFRS Virtual First Run Studies
Preliminary Pages
xxi
WWP Weekly Work Plan
1
CHAPTER ONE: INTRODUCTION TO THE
STUDY
1.1 Study Context
Globally, the construction industry plays a significant role in economic development
of any nation. For instance, the construction industry accounts for approximately
6.5 % of the UK’s GDP (Rhodes 2014); 3.7% of GDP in US (US BEA, 2014); 8% of
GDP in Australia (Toth et al., 2015) and 4.1% of GDP in Nigeria (Oluwakiyesi,
2011). This shows the importance of the industry in the economy. However, its
efficiency is low when compared to other sectors such as the manufacturing industry
(Gann, 1996; Love, and Gunasekaran, 1996; Koskela, 1992). It has been
acknowledged that the construction industry has the most dented image in the eyes of
the public when compared with other sectors, due to its inefficiency (Santos et al.,
2000). The inefficiency in the construction industry has been a thing of concern in
the past and has steered different construction reports globally. Cain, (2004)
identified these reports in the case of Canada, America, Australia, Singapore and the
UK.
In the UK, the call for improvement in the construction industry and the
dissatisfaction from stakeholders has been a subject of debate over many years with
the first report to review the performance of the UK construction industry
commissioned back in 1929 (Cain, 2004). The Egan report, generally called
Rethinking Construction, challenged the lack of collaboration in planning, designing,
and executing work on site, and recommended the adoption of lean production
principles to enhance the image and efficiency of the industry (Egan, 1998).
However, the prevailing approach to planning does not support lean production
principles (Ballard and Howell, 1997). According to Ballard and Howell, (1998),
Ballard and Howell, (1994), the current model used in planning and managing the
execution of work in the construction industry is ‘project’ control rather than
‘production’ control. This contributes to the non-achievement of tasks as planned.
The problem with this is that planned tasks are not achieved as planned due to the
lack of collaboration and involvement of stakeholders in the planning process
Introduction Chapter One
2
(Ballard and Howell, 1994; Ballard, 2000). These stakeholders include the client,
designers, subcontractors, main contractors, and site operatives among others.
The impact of poor performance is evident in the construction industry globally
(Nasir et al. ., 2013; Cain, 2004), including the UK. For instance, it has been reported
that about 50% of construction projects suffer both cost and time overrun in the UK
(Crotty, 2012). To overcome this irregularity and engender construction process
improvement (CPI), a paradigm shift is required from functional activity thinking to
system thinking, based on production philosophy (Koskela and Howell, 2002;
Ballard and Howell, 1998; Jeong, 2004).
The Last Planner®
System (LPS) (a lean production approach) invented by Ballard
and Howell in the 1990s has been identified as a production planning and control
(PP&C) methodology for construction, that engenders collaboration among the
project stakeholders (Papke, 2013; Ballard, 2000). Over the years, planning and
control have been understood to be among the core management functions in
construction management (Burke, 2013). However, while planning and control are
separated in traditional construction project management, they are seen as an
integrated process in the LPS of construction management (Ballard and Howell,
2004; Ballard, 1997). This makes the planned construction programme more
predictable and reliable, thus leading to reduction in lead time in the construction
phase (Alsehaimi et al., 2014; Ballard et al., 2009; Alarcón et al., 2005; Ballard and
Howell, 1997).
In practice, the LPS stabilises the production (construction) process on a project by
identifying relationships, matching them with plans and balancing resources
(Mossman, 2014; Ballard and Howell, 2003). The LPS establishes relationships
between people, tasks, locations, materials, drawings, time, information, and
resources, so as to develop a common understanding of the project goals among
stakeholders (Pasquire, 2012; Koskela, 2000). This supports smooth flow of work,
collaboration, and commitment from all project participants, thus delivering value for
all the stakeholders on the project (Koskela and Ballard, 2006).
Introduction Chapter One
3
1.2 The Research Problem
The implementation of the LPS has gained prominence in the construction industry
and its influence on the production system seems to be rapid and significant (LCI,
2015; Daniel et al., 2015). The impact of its implementation on construction process
improvement is enormous. Mossman, (2014), Fernandez-Solis et al., (2012) asserted
that the implementation of the LPS helps in creating overriding improvement in
project programme predictions, productivity, workflow, reduces project time and site
accidents, increases profit, enhanced collaboration among project stakeholders, while
giving due consideration to employee satisfaction among others. A comprehensive
review of conference papers published by the International Group for Lean
Construction (IGLC) indicates that the LPS has been implemented in 16 countries
(Daniel et al., 2015). Also, the Lean Construction Institute (LCI) and the IGLC have
documented the implementation of the LPS on over 200 case study projects
(Fernandez-Solis et al., 2012). In addition to this, Shang and Pheng, (2014);
McGraw-Hill report (2013) identified that the LPS is the most implemented lean
construction technique on construction projects. According to McGraw-Hill report
(2013) the LPS is one of the lean techniques with prospects of higher future
implementation by construction stakeholders such as clients and main contractors.
However, the application of this system in the UK construction industry has not been
fully explored among industry practitioners (Sarhan and Fox, 2013; Mossman, 2009;
Common et al., 2000).
In the UK, there is confusion in the use of the terms “Collaborative Planning” (CP)
and “Last Planner” and what happens in practice (Daniel et al., 2015a; Koch et al.,
2015; Drysdale 2013; BRE, 2006). The term Collaborative Planning and Last
Planner are used interchangeably to describe the application of production planning
and control principles based on the LPS by construction practitioners in the UK
(Daniel et al., 2016; Dave et al, 2015; Zemina and Pasquire, 2012). However, it is
not clear how the current use of the CP approach for delivering construction projects
in the UK align with the advocated principles and practice of the LPS.
In fact, there is dearth of empirical studies that examine the practice across the major
sectors of the construction industry. For instance Mossman, (2009) only speculated
that the practice of the LPS in the UK was largely stalled at collaborative planning or
Introduction Chapter One
4
collaborative programming. Also, Sarhan (2013) and Mossman, (2009) opined that
the LPS is viewed as activity scheduling tools in the UK, rather than an integrated
system with many components. The lack of authoritative research and empirical data
makes it difficult for an appropriate approach to be developed to improve current
practice.
Furthermore, recent studies reveal that the application of LPS principles (also known
as CP in UK) in the UK construction industry is fragmented (Daniel et al., 2016;
Daniel et al., 2015a; Dave et al., 2015; Koch et al., 2015). Daniel et al., (2016)
observed that the more complex and crucial elements of the LPS are not
implemented in current practice in the UK. The danger with such application is that
the intended benefits of the implementation would not be realised both in the
organisation and at the project level (Daniel et al., 2014). According to Mcconaughy
and Shirkey (2013), lack of full implementation has adverse effects on both the
upstream and downstream flow of construction activities.
However, the fragmentation in the implementation of the LPS is not only in the UK
construction industry, as this has been reported in; a Norwegian study (Kalsaas et al.,
2014); a Vietnamese study (Khanh and Kim, 2015) and a Danish study (Lindhard
and Wandahl, 2014) among others. While this is not meant to rationalise the current
practice in the UK, it demonstrates the need to develop an approach to support
construction stakeholders in the implementation of the LPS, even at the global level.
At the global front, previous approaches developed to support LPS implementation
focused more on the project level, which is not holistic (Lindhard and Wandahl,
2014; Hamzeh, 2011; Dombrowski et al., 2010). However, to develop a
representative approach to generate such needed support, empirical evidence on the
current practice is essential.
In the light of these problems, this study focuses on investigating the current
application of Collaborative Planning for delivering construction projects in the UK
construction industry from production planning and control practice across the major
sectors of the UK construction industry using the LPS lens. This is important as it
directs the development of an approach that supports construction stakeholders in the
implementation of the LPS.
Introduction Chapter One
5
1.3 Rationale and Justification of the Study
This study is compelled by two main factors:
The need for an all-inclusive approach to support construction stakeholders
in their LPS implementation journey.
The dearth in studies that examine the application of production planning
and control practice based on the LPS across the major sectors of the UK
construction industry.
The need for supporting the implementation of new techniques, and practice using
some sets of guidelines, frameworks, roadmaps, approaches, or success factors have
been acknowledged in the literature (Nesensohn, 2014; Ogunbiyi, 2014, Sacks et al.,
2009). Various frameworks have been developed to support lean implementation in
the construction industry; however, these frameworks are too general and less
technique specific. For instance, Nesensohn (2014) developed a framework for
assessing lean maturity, with focus on how to assess an organisation’s lean journey.
Ogunbiyi, (2014) developed a framework for lean and sustainable construction, that
focused on integrating lean construction with sustainable construction. Sacks et al.,
(2009) suggested a research framework to relate lean to BIM; Forbes (2002)
developed a framework to provide technical support for implementing lean. All these
show the need for developing a framework or roadmap for guiding organisations in
implementing lean principles.
However, in the UK, very limited studies have been conducted to investigate the
application of the Last Planner System/Collaborative Planning (LPS/CP). No study
has examined LPS practice across the major sectors of the UK construction industry
with a view to generate an approach to support construction stakeholders in its
implementation. Previous studies on LPS/CP in the UK construction industry
reported pilot implementation while others are organisation specific (Drysdale, 2013;
Ryall et al., 2012, BRE, 2006; Johansen and Porter, 2003). Most of these studies are
too narrow and unable to reflect the current practice of LPS/CP across the major
sectors. Hence, they cannot be used as a basis to develop an approach to support LPS
implementation.
For instance, in the UK, Ballard (2000) piloted LPS concepts in precast concrete
production; the focus was to stabilise production. Johansen and Porter (2003) piloted
Introduction Chapter One
6
the LPS on a building construction project, BRE (2006) reported CP practice on a
demonstration project; while Drysdale (2013) reported the application of CP on a
pilot project. Similarly, Dave et al., (2015) reported an LPS application on a case
study project and Koch et al., (2015) reported the application of CP on a case study
project. However, the focus of these studies was not to create an approach that would
support construction stakeholders in the implementation of the LPS. In contrast, the
study reported in this thesis examined the current LPS/CP practice across the major
construction sectors (building, highways infrastructure, and rail) in the UK, thus
offering a more comprehensive view on the current practice. The findings directed
the development of an approach to support construction stakeholders in the
implementation of the LPS.
At the global level, studies have attempted to propose an approach for implementing
specific lean techniques such as LPS in construction, but they tend to focus more on
the project level (Lindhard and Wandahl, 2014; Hamzeh,2011; Hamzeh and
Bergstrom (2010), Dombrowski et al., 2010). For instance, Lindhard and Wandahl
(2014) developed a framework that focused on supporting on-site scheduling;
Dombrowski et al.’s (2010) framework focused on the implementation of LPS
components at the project level. Ballard et al., (2007) suggested a general roadmap
for lean implementation with focus on the project level, while Hamzeh, (2011),
Hamzeh and Bergstrom’s (2010) framework provided an operational guideline for
LPS implementation that focused more on the project level.
This is despite the fact that it has been suggested that the implementation of lean
techniques should expand beyond project focus and include other organisational and
human factors that could influence the process (Pevez and Alarcon, 2006). The study
reported in this thesis fills this gap by developing an approach to direct LPS
implementation known as Last Planner System Path Clearing Approach (LPS-PCA)
that incorporates an organisational path clearing level and external enablers
alongside the project path clearing level. The approach is not intended for a one off
improvement, as common with the implementation of lean tools and methodologies
(Pevez and Alarcon, 2006), rather, it supports embedding the process into the
organisation through the learning loops. According to Howell and Ballard, (1998)
lean implementation does not only impact on how the project is managed, it also
influences the organisation’s behaviour.
Introduction Chapter One
7
Furthermore, since the LPS-PCA is developed based on empirical findings from
across the UK construction industry, it recognises cultural, structural, and contextual
issues germane to it, which are not addressed by other approaches developed
elsewhere. Johansen et al., (2004) Johansen and Porter, (2003) and Seymour, (1998)
posited that an understanding of cultural context is important for the successful
implementation of lean principles in the UK construction industry. This does not
mean that the use of the proposed approach is limited to the UK construction
industry alone, as evaluation result have shown that the proposed approach could be
adopted anywhere.
1.4 Research Questions
The study seeks to answer the following overarching questions:
1. How does the current understanding and application of “Collaborative
Planning” (CP) for delivering construction projects in the UK align with the
advocated principles of the LPS?
2. How can construction stakeholders (client, main contractors, and
subcontractors) be supported for rapid and successful implementation of the
LPS to achieve construction process improvement.
1.5 Research Aim
The aim of this research is to develop an approach to support construction
stakeholders for a rapid and successful implementation of the Last Planner System
for a sustainable construction process improvement.
1.6 Research Objective
The following objectives are used to achieve the aim of this study.
1. To critically review the need for construction process improvement (CPI) and
the development of production planning and control practice in the UK
construction industry.
2. To critically evaluate the development of collaboration in design, planning
and execution of work in other fields and identify the implication for
collaboration in construction planning practice and theory
Introduction Chapter One
8
3. To critically evaluate the applications and developments in the Last Planner
System for managing project production in the construction industry globally.
4. To investigate the current understanding and application of Collaborative
Planning for delivering current projects in the UK from a production planning
and control perspective through the lens of the LPS
5. To determine the nature of support needed for rapid and successful
implementation of the LPS and to identify the impacts of LPS
implementation on CPI.
6. To propose and validate an approach to support construction stakeholders in
implementing the LPS.
1.7 Scope of the Study
This research focuses on the UK construction industry. The research respondents
were drawn from England, Scotland, and Wales, however the study was unable to
engage with research participants from Northern Ireland. Also, only the top
construction companies participated in the study. This means that supply chain
companies who do not work for top contractors are omitted in this study.
Furthermore, the empirical data for this research are mainly on the construction
phase. This indicates that the application of production planning and control
principles explored did not capture the practice in the design phase sufficiently. It is
worth noting that the production planning and control (PP&C) practices investigated
are those based on the Last Planner System principles and did not include other
production planning and control practices such as Line of Balance , and critical path
method among others.
1.8 Overview of Work Done
This section gives a high level overview on the work done as reported in this thesis.
1.8.1 Overview of Research Methodology.
It has been observed that the success of every research lies on the appropriateness of
the research methodology and methods used in the investigation. This is also
influenced by the research philosophical stance. The ontological position of this
study is a combination of social constructivism and objectivism. Thus, it relies on the
epistemology of interpretivism and positivism to answer the research question,
Introduction Chapter One
9
though largely concentrating on interpretivism. The effective combination of
interpretivism and positivism in conducting construction management research has
been widely reported in the literature (Dainty, 2008; Fellow and Liu, 2008). Dainty,
(2008) asserted that both positivism (quantitative) and interpretivism (qualitative)
research have their root in ontology and epistemology, thus they can be combined.
Accordingly, both qualitative and quantitative methods were used in collecting data
for the study. Specifically, data were collected via interviews, structured
observations, case studies, and surveys.
These approaches were used to complement each other and to strengthen the research
contribution to knowledge. Some of the qualitative data were analysed using
qualitative data software known as 1NVivo 10 while the quantitative data were
analysed using 2SPSS 22. An overview of the research stages are highlighted below.
1.8.2 Overview of Research Process
There are five key stages in this study.
Stage 1: Literature review
The literature review examined literature on Collaborative Planning approach in the
UK construction industry, production planning and control principles using the lens
of the LPS, construction process improvement, the development of collaboration in
planning in urban planning and software engineering. From the literature review, the
knowledge gap for the study was identified. Publications and collections sourced
from databases such as Emerald, Elsevier, Construction Industry Institute , the
International Group for Lean Group for Lean Construction (IGLC), Construction
Economics and Management Journals, Journals of construction engineering and
management, and Lean Construction Journals among others were reviewed.
Stage 2: Exploratory Semi-Structured Interviews
Following the literature review, the research instrument was developed to investigate
the current practice of Collaborative Planning for delivering construction projects
from a production planning and control (PP&C) perspective in the UK. Purposive
sampling was used in selecting the research participants. The research participants
1 Software that supports in the analysis of qualitative data
2 Statistical Package for the Social Science for analysing quantitative data
Introduction Chapter One
10
include; clients, main contractors, subcontractors, and lean construction consultants.
The respondents were drawn from building, highways infrastructure and rail sectors
of the UK construction industry. Thirty in-depth interviews were conducted over a 12
month period comprising 18 main contractors, 2 clients, 4 lean construction
consultants, and 6 subcontractors.
Stage 3: Structured Observations
At the end of the interviews, further exploration was done to obtain objective data on
how the application of PP&C principles in the UK, align with the advocated
principles of LPS. Evidence on this was obtained from the physical process analysis
using the Planning Best Practice (PBP) checklist; a survey tool used in evaluating
production planning practice based on the LPS (Bernades and Formoso, 2002). The
PBP consists of 15 practices associated with the LPS. The assessments was done
using three Likert Scale where 1= full implementation 0.5= partial implementations
and 0= no evidence of implementation. In all, 15 projects drawn from building,
highways infrastructure, and rail were evaluated. Simple descriptive statistics were
used in the analysis of survey data. Evidences were also sourced from record
analysis, and physical condition analysis.
Stage 4: Case Study
The aim of the case study is to identify the nature of support required for the
effective implementation of the LPS and the impact of implementing PP&C
principles based on LPS principles on construction process improvement in the UK.
This was done using three case studies. The case studies were conducted over a 10
month period. Two of the projects studied were highways infrastructure projects and
one a building project. On each project, evidences were sourced through interviews,
document analysis, observations, and a post-implementation survey. All these were
done for triangulation of research findings.
Stage 5: Development and Evaluation of Last Planner Path Clearing Approach
Following the activities in Stages 1 to 4, an approach was developed to support
construction stakeholders in the implementations of the LPS for sustainable
construction process improvement. The developed approach is known as Last
Planner System Path Clearing Approach (LPS-PCA), and includes organisational and
Introduction Chapter One
11
project path clearing levels, and external enablers. To determine its functionality,
LPS-PCA was introduced, evaluated, and validated by 10 construction industry
practitioners. Also, the LPS-PCA was piloted on a live project. Following feedback
from the evaluation and the preliminary findings from the pilot implementation, the
LPS-PCA was refined. A guidance note was also developed to support construction
stakeholders in using the LPS-PCA following the evaluation feedback.
1.8.3 Overview of Research Contribution to Knowledge
The contribution of this research emerges from revealing the mismatches in current
applications of Collaborative Planning for delivering construction projects in the UK
using the lens of the LPS. This informed the development of an approach known as
“Last Planner System Path Clearing Approach” to support construction stakeholders
in the implementation of the LPS.
1.8.4 Thesis Structure
Figure 1.1 presents the structure of this thesis. It comprises of nine chapters, a brief
overview on each chapters is presented below.
Chapter One: Introduction to the Study
This chapter presents the background to the study and captures the knowledge gap
for the study. It identifies the research aims, objectives, and the research questions. It
also presents the rationale and justification for the study. Furthermore, an overview
of the study contribution to knowledge, overview of work done and the thesis
structure are also presented in this chapter.
Chapter Two: Construction Process Improvement and Production Planning
Control in the UK Construction Industry
This chapter explores the need for construction process improvement (CPI) in both
design and construction phases and the development of production planning and
control (PP&C) practice in the UK construction industry.
It presents the nature of the construction industry and examines the concept of CPI in
the industry. It further discusses the development of PP&C practice based on the Last
Planner System (LPS) in the UK, by presenting the historical perspectives of the LPS
and collaborative planning (CP) in the UK construction industry.
Introduction Chapter One
12
CHAPTER ONE
INTRODUCTION
CHAPTER THREE
Development of
collaboration in planning in
other knowledge areas
CHAPTER FOUR
Production planning
and control in
construction based on
the Last Planner
System
CHAPTER TWO
Construction process
improvement and the
development of production
planning control in the UK
CHAPTER FIVE
Research methodology and
design
CHAPTER SIX
Results and discussion of
exploratory interviews and
structured observation
CHAPTER SEVEN
Multiple case study
analysis and discussion
CHAPTER EIGHT
Development and Evaluation of LPS
implementation approach
CHAPTER NINE
Conclusions and recommendations
Figure 1.1: Thesis Structure
Chapter Three: Development of Collaboration in Planning in Other Knowledge
Areas
This chapter brings in a broader standpoint on the need for collaboration in
construction planning by exploring the concept of collaboration and collaborative
working (CW), and the development of collaboration in design, planning, and
execution of work in other fields. Precisely, it reviews the development of
collaboration in planning, in urban planning (UP) and in software engineering (SE)
development. The implications of the developments of collaboration in design,
planning, and execution of work in these knowledge areas are examined for
construction project management
Introduction Chapter One
13
Chapter Four: Production Planning and Control in Construction Based on the
Last Planner System
This chapter examines the LPS of production control in details as a production
planning and control (PP&C) methodology in construction, with focus on its
evolutions and its practical implementation in construction. It highlights the
development of PP&C in construction with focus on the LPS and its supportive
components. The chapter also presents the theories that explain the effectiveness of
the implementation of the LPS in construction. The chapter highlights the practical
implementation of the LPS in construction projects through a comprehensive and
systematic review of the International Group for lean Construction (IGLC) papers on
LPS implementations.
Chapter Five: Research Methodology and Design
This chapter presents a detailed account on the research methodology and design
used in capturing the evidences in answering the objectives proposed in Chapter One.
It also justifies the research methodology and design used. The chapter presents the
overall research design and discusses the five major stages involved in the study in
detail.
Chapter Six: Results and Discussion of Exploratory Interviews and Structured
Observation
This chapter presents and discusses the findings from the semi-structured interview
on the current use of Collaborative Planning for delivering construction project from
production planning and control perspective in the UK construction industry. It also
presents and discusses the structured survey on PP&C practice using the lens of the
LPS.
Chapter Seven: Multiple Case Study Analysis and Discussion
This chapter analyses, presents and discusses the findings from the three case studies.
It also presents a cross case study analysis and discussion.
Chapter Eight: Development and Evaluation of LPS Implementation Approach
This chapter presents the LPS-PCA approach developed based on the empirical data
from Stages 3 and 4 of this study. It presents both the quantitative and qualitative
Introduction Chapter One
14
evaluation feedback on the LPS-PCA received from construction professionals. In
addition, the chapter reports the preliminary findings from a pilot implementation of
the LPS-PCA.
Chapter Nine: Conclusions and Recommendations
This final chapter captures the main conclusions and recommendations from this
study. The chapter presents the conclusions on each research objective and the
research questions and itemises the original contribution of the study to knowledge.
It identifies the study limitations and made recommendations for further research and
for the industry.
1.9 Chapter Summary
This first chapter provided a high level overview of the research reported in this
thesis including the contributions of the study to knowledge. The next chapter
(Chapter Two) presents the literature review on construction process improvement
and development of the production planning and control practice in the UK
construction industry.
15
CHAPTER 2: CONSTRUCTION PROCESS
IMPROVEMENT AND THE DEVELOPMENT
OF PRODUCTION PLANNING AND
CONTROL BASED ON THE LAST PLANNER
SYSTEM IN THE UK CONSTRUCTION
INDUSTRY
2.1 Introduction
This chapter explores the need for construction process improvement (CPI) in both
design and construction phases and the development of production planning and
control (PP&C) practice in the UK construction industry. Firstly, it presents the
nature of the construction industry and examines the concept of CPI in the industry.
The chapter highlights the demand for an integrated approach in the design, planning,
and execution of projects for an enhanced construction process improvement from a
review of UK construction industry reports. It further discusses the development of
PP&C practice based on the Last Planner System (LPS) in the UK, by presenting the
historical perspective on the Last Planner System and collaborative planning (CP) in
the UK construction industry. The chapter partly compares CP practice on UK
Construction Lean Improvement programme (CLIP) demonstration projects with the
LPS components. The chapter also presents the knowledge gap for the study and
thus, sets the foundation for further explorations on the application of PP&C for
construction process improvement in the UK.
2.2 Process Improvement in the Construction Industry
2.2.1 The UK Construction Industry
The construction industry activities have been identified among the major drivers
commonly used in measuring the performance of the economy of a nation (Ofori,
2001). Globally, the construction industry plays a significant role in economic
development of any nation. In the UK the construction industry plays a significant
Literature Review Chapter Two
16
role in the country’s economic growth and development. The Gross Value Added by
the UK construction industry to the overall economy in 2011 was £89.5 billion; this
amounts to 6.7% contribution to the overall economy. A current report indicates that
the sector contributes about 6% to the overall GDP of the UK (Rhodes, 2014). In the
UK, the industry comprises of over 280,000 companies and employs over 3 million
workers (Construction 2025 Report, 2013). The public sector is the single largest
client in the UK construction industry (House of Commons, 2008; Egan, 1998).
The smaller construction firms in the UK construction industry are more in number
compared to the larger firms. But their contribution to the economic output and
employment is low (House of Commons, 2008). For instance, some of the smaller
companies employ less than eight people (Construction Satistics Annual, 2007). The
larger firms on the other hand contribute about 12% to value output and provide
about 10% of employment in the sector (Construction Statistics Annual, 2007).
Again, all these show the level of fragmentation in the sector. This has led to a
consistent call for collaborative working in the design, planning, and execution of
work among stakeholders in order to achieve enhanced construction process
improvement.
2.2.2 The Concept of Construction Process Improvement
Process improvement has remained an object of focus in various disciplines for many
decades. This includes manufacturing, business management, process engineering
and more recently in the construction industry. The quest for process improvement
could be traced to “The Scientific Management Principles” proposed by Frederick
Taylor (Taylor, 1911). In his search to achieve increased productivity and faster
output, Taylor embarked on a study that investigated work process scientifically
(Taylor, 1911). Many attempts have been made to define the term ‘process’. Jeong et
al., (2004) observed that people give different meaning to the term which seems to
be based on the sector, function and the market in which they operate. This implies
that the meaning accrued to the term ‘process’ could vary from one sector to another.
Nevertheless, the Cambridge Dictionary, (2015) defines process as “a series of
actions that you take in order to achieve a result”. This suggests that process relates
to structured actions to be adhered to in order to achieve a result.
Literature Review Chapter Two
17
According to Harrington, (1991) process consists of activities that take inputs,
enhance them, and provide output to both internal and external customers. However,
Ould, (1995) opined that a process comprises of activities, people, and equipment
which are required to work collaboratively. Shingo (1998) also asserted that
production comprises of network of processes and operations, that is processes and
operations are opposite sides of the same coin. Process is not merely a collection of
activities but also involves materials, men, and machines which must be connected
collaboratively for better output. In view of this, Jeong et al., (2004) argued that
since a process involves a wide range of actors, it must be clearly defined to all the
actors involved in order to achieve the needed improvement. To realise this, the
focus should be on all the various steps identified in the process.
Paulk et al., (1995) and Imai (1986) pointed out that continuous process
improvement relies on many steps in the production process and not a revolution of
the system as thought by some. This suggests that process improvement should
follow defined procedures. For example, Juran, (1992) and Deming (1986) suggested
that process improvement should follow a series of steps starting with the visible
which could be later made repeatable and measurable. Generally, construction
projects occur in various steps and stages. According to Austen and Neale (1984),
construction consists of several steps known as processes. This suggests that the final
output of a construction project relies greatly on how these interphases or series of
steps are effectively managed.
In view of this, Stewart and Spencer, (2006) emphasised the need for managing these
series of steps effectively as it supports productivity, efficiency, and capacity
development in the industry. This implies that productivity and efficiency will
remain unachievable if these series of steps in the construction process are not well
managed. However, managing this series of steps must be done collaboratively as
each process involves materials, men, machines, and information among others. In
addition, since construction and process involves a lot of actors, each process must
be clearly defined to all parties at the earliest possible moment for a collective
improvement and development of each process (Jeong, 2004; Ould, 1995).
Literature Review Chapter Two
18
2.2.3 Current State of Construction Process Improvement in the Industry
It has been observed that the construction industry lacks a defined approach for
managing its processes. According to Van der Aalst et al., (2003) construction
processes keep changing especially in the execution phase. The lack of involvement
of the actors in developing the process and the inherent variability in construction
could have contributed to this (Ballard and Howell, 1998). Also, Stewart and
Spencer, (2006) identified the absence of a clear framework and guideline to support
process improvement in the construction industry. This implies that benefits from the
process are seen in isolation and thus, cannot be coordinated. This does not only
retard CPI initiative in the industry, but also hinders any repetition of such initiative.
It is no surprise that the process improvement initiative varies from project to project
even within the same organisation. Hence, a framework to support CPI using a
systematic approach is required in the industry. For instance, Sarshar et al., (2000)
observed that the construction industry is unable to coordinate CPI because it is yet
to assess construction process, prioritise CPI and allocate resources to it as required.
The absence of a clear framework for managing construction among other things
informed Egan’s recommendation for the adoption of lean production principles in
the UK construction industry (Egan, 1998). Prior to Egan’s report, various reports
had been commissioned in the UK, which all called for collaboration and
construction process improvement in the planning, design, and execution phases of
projects.
2.2.5 Demand for Construction Process Improvement in the UK
The demand for improvement in the UK construction industry and the dissatisfaction
from end users has been a topic for debate over many years. To be precise, the first
construction industry report to review the performance of the UK construction
industry was commissioned in the 1930s (Cain, 2004). The government in its effort
to keep the construction industry on the firing line, considering its significant
contribution to economic growth and development, has never relented its effort in
reviewing the performance of the industry; so as to identify areas for improvement.
For instance, between 1929 and 2009, over 14 construction industry reports were
produced in the UK. These reports emphasised the removal of inefficiency and waste
Literature Review Chapter Two
19
from the construction industry through collaboration and early involvement of
stakeholders.
The earliest among these reports is “Reaching for the skies” by Alfred Bosom in
1934 (Cain, 2004). He argued that construction is like every engineering process
which should be planned adequately in advance with work executed on an agreed
time scale. Unfortunately, this was not the situation in the UK construction industry
as of the time of the report. Describing the UK construction industry at the time, he
stated that: “All rents and costs of production throughout Great Britain are higher
than should be because houses and factories cost too much and take too long to
build” (Cain, 2004 pp. 20). The picture painted here is no doubt, that of cost and time
overrun, in an industry that is marked with fragmentation and unproductiveness.
Chan and Chan, (2004) and Kumaraswamy, (1997) observed that the major causes of
time and cost overrun are poor project planning and scheduling, and inadequate
control of change.
The above report gives an early description of the UK construction industry and the
earliest call for collaborative approach in planning, design, and execution of work in
the UK construction industry. Subsequently, other construction industry reports were
commissioned to better understand the need for construction process improvement
through collaboration and collaborative working approaches.
2.2.6 Review of Construction Industry Reports
Figure 2.1 presents a timeline of the construction industry reports commissioned by
the UK Government between the 1930s and 2014. Again, this shows the level of
attention the UK Government pays to the sector. A critical examination of these
reports indicate that they all emphasise the need for collaboration and collaborative
working in design, planning and execution of work for better construction process in
the industry. Among the reports shown in the figure, the Latham and Egan reports in
particular, mounted pressure on the UK construction industry to embrace or adopt
collaborative approaches at all stages of procuring construction projects. Also, the
figure reveals that there has been an increase in the number of reports commissioned
in recent times compared to the earlier years. This could mean that the industry is
Literature Review Chapter Two
20
Banwell 1967
Latham Report 1994
Simon 1944
Egan report 1998
Egan report 2002
Wolstenholme report, 2009
Government construction strategy, 2011
Alfred Bossom 1934
Construction 2025, 2013
Creation of construction Improvement programmes
Constructing Excellence
CBPP CLIPMovement for
InnovationCIB
Emmerson report1962
Figure 2. 1: Timeline of construction industry report that magnify the need for
Collaboration in the delivery of construction projects
still not performing as expected and could still be driven to perform better. Some of
these reports are reviewed below.
2.2.6.1 Latham Report: Constructing the Team
The Latham report, also known as “Constructing the Team” made over twenty
recommendations for the UK construction industry to ensure more efficient project
delivery. It reveals that previous reports such as Simon report, Harold Emmerson
report and Banwell report failed to address the identified problems. It went further to
recommend a turning point for the UK construction industry, which should start from
building better relationship between clients, contractors, consultants and
subcontractors. The report emphasised that contracts should be based on the principle
of fairness, mutual trust, and team work rather than low price alone and adversarial
nature which used to be the common practice. The report originates and magnifies
the need for collaboration in the UK construction industry. This is not to say that the
need for collaboration in construction was limited to the Latham report as other
reports such as the 1998 Egan report: Rethinking Construction; the 2002 Egan report:
Accelerating Change; and the 2009 Wolstenholme report: Never Waste Good Crisis
among others also discuss the need for collaboration.
Literature Review Chapter Two
21
2.2.6.2 Egan Report: Rethinking Construction
The Egan report was commissioned as a result of the slow implementation of the
Latham report and the inability of the industry to meet the expectations of clients
(Wolstenholme, 2009; Egan, 1998). The report did not only highlight the problems
the industry was facing, but went further to identify major drivers for change.
Interestingly, the five drivers identified revolve around collaboration. These are;
committed leadership, focus on the customer, integrating the process and the team
around the product, quality driven agenda, and commitment to people. The report
also identified four project process improvements drivers which are: product
development, partnering the supply chain, project implementation, and production of
components. In addition, it highlighted seven specific improvement targets.
The focus of the five drivers is to effectively integrate both the demand and supply
arms of the project chain. According to Cain, (2004) all the construction industry
reports placed great emphasis on collaboration in the procurement and execution of
construction projects. This can be attributed to the fragmented nature of the
construction industry and the one-off nature of its product (Oliva and Granja, 2013).
However, current reports indicate increased awareness and potentials in delivering
value for clients and end users through collaboration in the design, planning, and
execution of work.
2.2.6.3 Accelerating Change
Building on the ‘Rethinking Construction’ report, ‘Accelerating Change’ was
commissioned in 2002. The essence of the report was to assess the progress of the
Egan 1998 report (Egan, 2002). According to Wolsteholme, (2009) the report
identified the various impact made by the ‘Rethinking Construction’ report and
defines a headline goal that 20% of construction projects must be executed by an
integrated project team and supply chain by 2004. This was expected to increase to
50% in a three year period.
Again, the call for the use of an integrated team in project delivery in the report
further magnifies the need for collaborative planning among the stakeholders in the
industry. This move could be due to the improvement experienced on the
demonstration projects executed as part of the implementation process of the
‘Rethinking construction’ report (Wolsteholme, 2009). In fact, the call for partnering
Literature Review Chapter Two
22
with the supply chain especially in planning and execution of complex projects is
because of its obvious benefits for all the stakeholders. According to Kastali and
Neely, (2006); Barlow, (2000), complex situations on a project can easily be solved
with innovative solutions that could emerge in the collaborative planning process.
2.2.6.4 Never Waste Good Crisis
The report examined the progress of the Egan report after its ten years of
inauguration. More importantly, it identified five blockers that had retarded the
implementation of the Egan report (Wolsteholme, 2009). The result of the survey
indicated the various improvements made since the implementation of Egan’s
recommendations. For instance, the report showed an increasing level of awareness
on the need for collaboration in planning and team working among major
stakeholders in the construction industry. The report indicated that 56% of the
respondents considered an integrated approach in project delivery to be very
important for the most desired improvement process in the construction industry to
occur (Wolsteholme, 2009). This shows that there is an increase in understanding
among construction stakeholders in the UK on the need for collaboration and
integrated working approach in achieving CPI following the Egan report.
2.2.6.5 Government Construction Strategy
In May 2011, the Government construction strategy report was published. The report
acknowledged the importance of the construction industry to the economic growth of
the country and further highlights some of the improvements made in the sector
following recommendations of the Latham report. More importantly, the report
pointed out the inability of the sector to deliver value for its customers and end users
due to its unwholesome practices (Construction Strategy Report, 2011). For instance,
the report challenged the prevalent adversarial relationship that has become a norm
in the industry and calls for a replacement with collaborative approach. This renewed
call is a pointer that the industry has not fully embraced previous calls from previous
construction industry reports for integrated working among the stakeholders. It could
also mean that the industry is slow to change. Sabol, (2007) argued that the
construction industry is slow to adopt innovation and change thus making the
industry to underperform when compared with other sectors. However, Wilkerson,
(2005) identified architects as early adapters of innovation in the construction
industry.
Literature Review Chapter Two
23
The report further magnified the need for designers and constructors to work together
as a team to develop integrated solutions in project delivery. Although these points
are not in any way new to what has been highlighted by the previous reports, it
establishes the relevance of collaborative effort such as in planning, design, and in
project execution for meaningful progress to be made in the construction industry.
2.2.6.6 Construction 2025 Report
The ‘Construction 2025’ report was a product of over six months of extensive
evaluation of the industry by the government and other major stakeholders in the UK
construction industry. The report identified the strategic position of the UK
construction industry, both locally and globally, especially its competitive edge over
other sectors. The aim of the report is to empower all the stakeholders in the
construction industry with valuable information on the available opportunities and
threats to the industry which need to be harnessed collaboratively to better position
the industry to contribute more to the economy. The report was not written in
isolation; indeed the report acknowledged the improvements made in the industry as
a result of other construction industry reports such as Latham, Egan and
Wolsteholme’s reports. This clearly suggests that all the construction industry needs
is to build on earlier foundations that have been laid. Again, this re-emphasises the
importance of previous reports and its correlation to the present construction industry
report. The report identified there is weakness in collaborative strength across the
supply chain due to fragmentation, lack of trust and the absence of a sense of
belonging.
2.2.6.7 Summaries and Major Outcomes of the Construction Industry Reports
Table 2.1 summarises the various construction industry reports and identifies the
need for collaboration in design, planning, and execution of work. This is done to
clearly present the picture of the need for collaboration in the design, planning, and
execution as emphasised in the past and present. Table 2.1 reveals that the need for
collaboration in the construction industry has been and still is emphasised in all the
construction industry reports. However, in reality, collaborative practice within the
industry is still patchy. This could be due to the individualistic tendencies among the
stakeholders procuring construction projects. According to Pasquire et al., (2015)
construction stakeholders always seek to protect their self-interest on the project
rather than the overall goal of the project.
Literature Review Chapter Two
24
Table 2 1: Major Construction Industry Reports showing the need for Collaboration in the
Design, Planning, and Execution of Work
Year Construction Industry
Report
Collaborative Approach Emphasised in the
Design, Planning & Construction Phases
1934 Bossom Report: Reaching
for the Skies
Raised concern about fragmentation and
adversarial relationship
Highlighted time and cost overrun due to
inadequate planning
1944 Simon’s Report: Placing
and Management of
Building Contracts
Called for collaborative approach to design and
construction
Recommended early contractor involvement
1962 Emmerson Report:
Survey of Problems Before
the Construction Industry
Identified lack of cohesion between parties
procuring construction projects
Suggested the adoption of a common form of
contract
1967 Banwell Report: The
Placing and Management
of Contracts for Building
and Civil Engineering
Work
Criticised the separation between design and
construction
Emphasised more focus on team working and
relationship building
1994 Latham Report: Constructing the Team
Called for an integrated approach to work
Called for partnering at all levels of the project
Recommended the use of forms of contracts that
encourage team working
1998 Egan Report: Rethinking
Construction
Integrating the process and the team around the
product
Strong focus on customer and commitment to
people
Called for strong partnering across the supply
chain
2002 Egan Report: ‘Accelerating Change’
Called for 20% of all construction projects to be
executed by an integrated team and supply chain
Emphasised client leadership in the execution of
construction project
2009 Wolstenholme Report: ‘Never Waste Good Crisis’
Called for a collaborative and integrated team
Highlighted lack of an integrated process for
delivering project
Stated that pushing down of risk by contractors
along the supply chain prevents team working
Identified the need for lean approach in pre-
planning activities and procurement from a case
study visit in Japan
2011 Government Construction
Strategy
Called for the adoption of procurement options
that enhance integration of the supply chain
(NECs)
Developing a collaborative and integrated
relationship to minimise waste
Called for use of BIM to enhance collaboration
in planning and execution of project
Created lean supply chain/product
Literature Review Chapter Two
25
Created procurement /lean client task force
Called for effective and clear communication of
work during plan.
2013 Construction 2025 Called for partnership at all levels among the
stakeholders in the industry to reduce
construction cost by 33%, and time by 50%
Observed low integration and a call to create
resilient supply
Highlighted lost opportunities to innovate due to
lack of integration between design and
construction management
Called for early and continuous involvement of
contractors and supply chain in design
development
As shown in Table 2.1, all the reports highlighted the need for collaboration in
design, planning and execution phases of the project before meaningful achievement
of construction process improvement. However, the call for collaboration by
successive reports presents a picture that these calls have not been fully adopted in
the UK construction industry. This could be due to the age long use of the traditional
project management approaches that do not support genuine collaboration
(adversarialism) (Latham, 1994; Ballard and Howell, 1998). With this
understanding, Sir John Egan in Rethinking Construction report, 1998 brought a new
perspective with a categorical recommendation for the adoption of lean production
techniques in the UK construction industry. Specifically, the Last Planner System
(LPS) which is a lean technique was recommended in the report for use in production
planning and control for delivering construction projects (Egan, 1998).
2.3 Development of the Last Planner System in the UK
Figure 2.2 shows the major timeline in the development of the Last Planner System
in the UK construction industry. It reveals that the application of the LPS in the UK
is as a result of Egan’s 1998 report recommendations. The practical application of
this production planning and control methodology in the UK dates back to its use on
Heathrow Terminal projects by the British Airport Authority (BAA) in the late 1990s
and in the early 2000 (BAA, 2000). According to Reynolds, (1999) the approach was
tried on the construction of Heathrow - T4 Coaching Gate, T1 British Midland, T4
Arrivals Phase 2, and T1 International Arrivals. It was reported that the LPS
approach was beneficial as it allowed the team to be in full control of the project
programme, with two weeks gain on T4 arrival phase of the project.
Literature Review Chapter Two
26
2006
Phase II
implementation of
collaborative planning
in participating
organisations by BRE
CLIP engrs.
Client and
contractor’s
initiative for CP
implementation
on projects
Latham report
Egan reports –
Rethinking Construction
Accelerating Change
Early
construction
industry
reports calling
for
improvement
19941998- 2002
Implementatio
ns of
collaborative
planning & CPI
on projects by
CLIP engrs
2004-20052009 -2015
LPS Last Planner System
BRE Building Research
Establishment
CP Collaborative planning
CLIP Construction Lean
Improvement Programme
CIB Construction Industry board
MI Movement for Innovation
CE Constructing Excellence
CBPP Construction Best Practice
Programme
Abbreviation key
Alfred Bossom
Simon
Banwell
1930- 1967
Call for an
integrated
approach to work
Partnering at all
levels of the
project
Use of
collaborative form
of working
Recommend the
adoption of lean in
construction
Call for integration of
people and process
Strong focus on
customer
Partnering with
supply chain
Formation of
construction
improvement
programmes
following
Latham &
Egan reports
CLIP
CE
CIB
CBPP
MI
2003
Implementation of CP & CPI
in participating organisation
projects
CP &CPI training for
organisation by CLIP engrs.
Oct. 2003 publications of 7
CLIP demonstration projects
by BRE
April, 2005 BRE
published 11 CLIP
demonstration
projects where CP
is used
Early use of
LPS in UK
2000 concrete batching
production( Ballard et al, 2000)
2002 Hathrow Terminal 5
Project(Gil and Ward, 2011)
2003 Building project Johansen
and Porter, (2003)
Emergence of
lean
construction
consultants
The process
largely facilitated
by lean
construction
consultants
Clients
mandating
the use of CP
on its projects
Highways
Agency
Ministry of
Justice
Servern Trent
water
Anglian one etc
Started
2006
Figure 2. 2: Timeline highlighting the development of the Last Planner System and Collaborative Planning in the UK
Literature Review Chapter Two
27
Also, Gerry Chick of BAA commented that the LPS helped in “delivering bad news
early” (Mossman, 2005), but keeps on top of what is happening.
Building on these early successes, the LPS was used in managing all the phases of
construction on the Heathrow Terminal 5 project (BAA, 2000). The £4.2 billion
mega project that lasted between 2002 and 2008 was managed with the LPS (Gil and
Ward, 2011). Gil and Ward, (2011) observed that the Heathrow Terminal 5 project is
viewed as an example of a successful mega project in the UK. At this point in time,
Sir John Egan was the CEO of the British Airport Authority.
It is important to note that the early application of LPS in the UK is not limited to
this alone, as other studies have reported the application of the LPS in the UK. For
instance, Ballard et al., (2000) reported the application of the LPS in concrete
batching production for a UK contractor, while Johansen and Porter, (2003) reported
the pilot implementation of the LPS on building construction project for a contractor-
a joint research with the Northumbria University.
Following early application and benefits of this approach in construction, an
increased call for the application of the approach was made. Various construction
process improvement programmes were initiated to support the approaches of
managing construction from lean production perspectives in 2003 as shown in Figure
2.2. Specifically, the formation of the Construction Lean Improvement Programme
(CLIP) by the Building Research Establishment (BRE) in 2003, led to the
implementation of “Collaborative Planning” (CP). CP was the name given to the
approach used by CLIP for delivering process improvement on the demonstration
projects. However, before this time, as shown on the timeline, the LPS and its
collaborative planning elements had been developed, and also implemented in the
UK construction industry (Ballard and Howell, 1998; Ballard et al., 2002; Gil and
Ward, 2011).
Furthermore, a comparison between elements of LPS in its earlier implementations
in the UK with collaborative planning implemented by CLIP revealed some
variations (Daniel et al., 2014). The use of the term CP for describing the
management of construction from a production planning and control perspective in
the UK could be traced to the work Ballard and Howell on the LPS and the CLIP(Gil
and Ward, 2011; Ballard et al., 2000; Clip report, 2006). Figure 2.2 reveals that in the
Literature Review Chapter Two
28
UK, big clients and contractors such as the Highways England (formerly Highways
Agency), Ministry of Justice, Severn Trent Water, Anglian One, Carillion Plc,
Shepherd Construction, and Costain Plc also use the CP approach. This is claimed to
be based on the LPS principles. For instance, a current report claims that the LPS is
commonly known as collaborative planning workflow within Highways England
(HE) and across its supply chains (Atkins, 2013). Drysdale, (2013) and Fullalove,
(2013) also reported that the LPS is commonly known as collaborative planning in
the HE. However, how this claimed practice aligns with the advocated principles and
theory of the LPS in reality is unclear, as it has been speculated that the LPS practice
in the UK is stalled at collaborative programming (phase planning) (Sarhan and Fox,
2013; Mossman, 2009; Common et al., 2000).
2.4 Emergence of Improvement Programmes in the UK
Construction Industry
As shown in Figure 2.3, various construction improvement programmes were
initiated to drive the recommended construction process improvement practice
suggested in the reports. Some of these construction improvement programmes
include; Movement for Innovation (MI), Constructing Excellence (CE), Construction
Best Practice Programme (CBPP), and Construction Lean Improvement Programme
(CLIP) among others. Most of these programmes were initiated following the
recommendation of Latham report in 1994 and Egan reports in 1998 and 2002.
Specifically, CLIP was formed in 2003 following Sir John Egan’s recommendations
for the adoption of lean principles in the UK construction industry (BRE, 2006).
2.4.1 Overview of the Construction Lean Improvement Programme
(CLIP)
The Construction Lean Improvement Programme (CLIP) was established in 2003, by
the Building Research Establishment (BRE) and Department of Trade and Industry
(DTI). The creation of CLIP was a direct response to Egan report in Rethinking
Construction that charged the construction industry to adopt lean practices from the
manufacturing sector (Egan, 1998, Egan, 2002; Cain; 2004). According to Cain,
(2004) the resistance of the construction industry to change is due to lack of
migration of its managers to other sectors of the economy. Embracing lean
philosophy, the CLIP objectives include: to improve UK Construction industry profit
Literature Review Chapter Two
29
margin, address skills gap and offering of improved service to end users. It was
argued that alot of lean literature seem to be theoretical. In view of this, BRE and
DTI proposed a practical lean approach for skills development which they hope will
bring change in the construction industry for greater benefit.
CLIP Engineers are those responsible for the implementation on site and in
boardroom on practical basis. This is done in conjunction with the project team and
staff of the company that intend to implement CLIP. From the pilot implementations
on demonstration projects, it has been claimed that CLIP implementation has led to
measurable progress on projects in terms of quality, cost, project delivery time, and
improved relationship between the demand and supply chains (BRE, 2006).
Although most of these benefits seem to be limited to the demonstration projects and
subject to bias, it shows that with properly tailored programmes, the construction
industry could also improve like every other industry. This result could mean that
collaborative approaches have the potentials to improve the performance of the
construction industry. According to Margerum, (2002) collaborative planning makes
implementation of all phases of the project easy.
Generally, CLIP programme is designed to suit the need of the organisation,
although it focuses on seven development areas in order to bring about the desired
change in the organisation. The seven focus areas are shown in Table 2.2.
Table 2.2: The Seven CLIP Focus Development Areas
1 Product and process benchmarking and recommendations
2 Strategy development programme
3 Process improvement
4 Integrated supply chain development programme
5 Communication and team work development
6 Lean assessment
7 Company and project team roll-out programme
Source: BRE, 2006
Focusing on these seven areas shown in Table 2.2, CLIP expert engineers, in
collaboration with the organisation, identify the problem areas in order to develop the
right strategy. To achieve these set objectives, two fundamental approaches were
commonly adopted by the CLIP engineers. These are; process improvement and
Literature Review Chapter Two
30
collaborative planning, and integrated supply chain working as shown in Figure 2.3.
The focus of this study is on the collaborative planning element.
Collaborative Planning and Integration of the Supply Chain
Process Improvement
CLIP Approach
Figure 2. 3: Fundamental Approach of CLIP
Through this approach, CLIP has been implemented by over 100 UK based
construction companies on demonstration projects. However, this is a small
percentage of the over 280,000 construction businesses in the UK (Construction
2025 report, 2013).
2.4.2 Review of CLIP Pilot Projects
To understand the practice of production planning and control (PP&C) in the CLIP in
relation to the LPS, the published CLIP demonstration projects reports were retrieved
and analysed. Some of the CLIP demonstration projects are available at;
http://www.constructingexcellence.org.uk/resources/themes/clip/clip.jsp,
http://www.bre.co.uk/page.jsp?id=355. The aim is to understand the specific practice
with regard to PP&C and the name given to the process. Twenty seven CLIP
demonstration projects were analysed. From the review, it emerged that the practice
of PP&C on the CLIP pilot projects is known as “Collaborative Planning” (CP). The
CP practice reported from the demonstration projects are presented in Table 2.3. For
confidentiality, the name of the organisations involved in the demonstration projects
are not mentioned in this review, the projects are simply identified as demonstration
project 1, 2, 3, …, 27.
Literature Review Chapter Two
31
Table 2.3: Collaborative Planning Practice Reported on CLIP Demonstration Projects
CLIP Demonstration
Project
Collaborative Planning Practice Reported
Demonstration
Project 1
Initial workshop facilitated
Receiving feedback to identify value and culture
Early involvement of designer, contractor and suppliers
Open book and honesty
Planning with management team
Demonstration
Project 2
Relationship improvement with client
Collaboration in material planning and procurement
Collaboratively agree on milestones
Collaboratively plan and agree on project lead time
Virtual chart to help in collaborative planning
Brainstorming with all team members
Collaboration at pre-construction stage
Demonstration
Project 3
Collaborative agreement with client
Single specification sheet for suppliers with detail design
Demonstration
Project 4
Collaboration at pre-construction stage
Strategic thinking among team
Agreeing and breaking the project into manageable phases
Improved framework between client, contactor and supplier
Use of virtual framework
Demonstration
Project 5
Feedback to management and project teams
Analyse risk with client at early stage of project
Visual site management for better communication
Demonstration
Project 6
Display two week project plan on visual notice board
Involve client, supplier and supplier in planning process
Develop relationship with subcontractor
Identify common goal with team
Demonstration
Project 7
Get subcontractor involved early
Visual management board to improve communication
Bring subcontractor together to avoid conflict
Literature Review Chapter Two
32
Feedback to management and project teams
Demonstration
Project 8
Collaboration with suppliers
Working together to solve common problem
Improve in level and type of communication
Willingness to change
Management support
Demonstration
Project 9
Training and facilitation in form of workshops
Developing collaborative plan with team
Place collaborative plan on board
Demonstration
Project 10
Post-it note to show sequence of work
Display work plan over the next 5-6 weeks on board
Weekly site meeting to review progress
KPI to monitor contractor progress on board
Display productivity quality and H&S
Demonstration
Project 11
Tradesmen collaborative deliberation on H&S
Visual production board
Early involvement of Designer, contractor and suppliers
Holding of workshop to explain initiative
Using champions to monitor progress
Visual board for communication
Feedback to management and project team
Demonstration
Project 12
Involvement of client
Regular meeting with team members
Setting up work group
Subcontractors sharing office to build trust
Demonstration
Project 13
Visual management to aid communication
Site map photos, planned sequence of work
Safety report
Team commitment to work from the identification of project
goals
Foremen, subcontractor involvement in weekly site meeting
Planning in details next activities in weekly site meeting
Workshop process facilitator
Literature Review Chapter Two
33
Early involvement of subcontractors to bring their expertise to
bare
Demonstration
Project 14
Involvement of management in pre-diagnostic workshop
Weekly site meeting to review progress
Four week plan with all
Detailed plan of next week work with all
Use of visual management board
Early involvement of client to aid partnering
Involvement of all project team in site meeting to
communicate 1 month project plan
Discussing in detail next week project plan
Early involvement of team and communication of benefits
Demonstration
Project 15
Involvement of subcontractor at the early stage of the project
Development of clear strategy for spreading lean
Pre-design planning to involve all team members
Allow all to make contribution to keep team committed
Demonstration
Project 16
Create sense of team ownership in the end product
Collaborative agree on project time scale
Plan information by CP
Common approach to working
Early agreement on aim, time and scale of project
CP on information and activities of work
CP in detailed planning of activities
Demonstration
Project 17
Greater involvement of subcontractors in project planning
Team work and communication
Team produce weekly plan
Review of previous plan by team to identify areas for
improvement
Visual planning tool based on CP
Use of facilitator
Display of project status on board
Demonstration
Project 18
Planning with client, consultant and facilitator
Input from all project team at planning stage
Literature Review Chapter Two
34
Collectively identify problem
Specifying means of improvement collaboratively
Openness in planning
Trusting in team work
Demonstration
Project 19
Collaborative approach used to make order in advance
Collaborative approach used to improve flow of material to
site
Demonstration
Project 20
Collaborative planning with designer, contractor and facility
manager
Demonstration
Project 21
Participatory planning process by all
Trade men contribution
Sharing of lessons learnt
Team involvement and openness
Demonstration
Project 22
Early involvement of tradesmen
Working as an integrated team
Explaining benefit to all
Detailed planning
Use of facilitator
Demonstration
Project 23
Collaborative planning workshop with suppliers
Collaborative identification of what needs to be done
Group discussion on work plan
Daily site meeting
Weekly site meeting
Team working
Having time will suppliers to build relationship
Demonstration
Project 24
Use of facilitator
Visual management board to improve communication
Early involvement of subcontractor for input at planning
Documenting lessons learned
Demonstration
Project 25
Creating a collaborative environment
Team member interaction
Ownership of work belongs to team members
Literature Review Chapter Two
35
Demonstration
Project 26
Collaborative discussion of problems
Develop common understanding of what to be done
Feedback to project team
Stating lesson learned
Harnessing of ideas from team
Demonstration
Project 27
Detailed review of construction process at early stage
The report claimed that the use of CP on these demonstration projects supports
construction process improvement. The approach encourages learning, prompt
feedback on performance for participating organisation, and develops and sustains
the skill of site operatives (Constructing Excellence, 2007). However, it is unclear
from the reports where the learning occurs; if it is during or at the end of the project.
This needs to be investigated empirically.
2.4.3 CLIP: Collaborative Planning Practice Review Discussed
Some of the CP practices in CLIP demonstration projects report as presented in
Table 2.3 include; developing a collaborative programme with the project
stakeholders from master programme, having 4-8 weeks look-ahead planning
meeting sessions, having of weekly planning meeting to review previous week’s
work and plan for the coming week, display of work plan using post-it note to show
sequence of works, collaborative working to identify and solve problems, use of
visual management device to communicate progress, documentation and learning
among others. However, the practices vary from one demonstration project to
another. This shows that the current CP practice is not systematic.
The LPS process is based on five components which support collaboration through
social conversations and the planning and execution of work with all the stakeholders
on the project. LPS integrated components include; master plan, collaborative
programming or phases planning, make ready process, production planning,
production management and learning (Mossman, 2014; Ballard, 2000). The concept
of LPS, its theories, and principles among others are fully discussed in Chapter Four.
Some of the production planning and control practices identified from the review
such as the 4-8 weeks look-ahead planning, collaborative development of
Literature Review Chapter Two
36
construction programme, and weekly planning meeting seen in the report could be
likened to some LPS practices. However, the way this was done practically on the
CLIP demonstration projects could not be ascertained from the review of the reports.
The review indicated that other practices associated with the LPS such as make ready
process, development of workable backlog, phase planning, measuring percentage
plan complete, and recording reasons for non-completion among others were not
mentioned in the report. This further makes it difficult to ascertain from the review,
if the term “Collaborative Planning” used for delivering construction project from
production planning and control perspective in the UK relates to the LPS of
production control.
Furthermore, it has been speculated that the LPS is stalled at collaborative
programming (phase planning) in the UK and it is viewed in the UK construction
industry as an activity scheduling tool (Sarhan and Fox (2013; Mossman, 2009;
Common, 2000). However, this claim is not based on empirical data. Also, no
conclusive statement could be made based on the observed CP practices in the CLIP
reports as they are based on desktop reviews. For instance, there is likelihood of bias
in the CLIP CP practice reported since they are meant to be demonstration projects.
Similarly, there is the possibility of omission of other practices from the report. This
identified gap needs to be substantiated with empirical data through an industry wide
study. This is also important considering that earlier implementations of
collaborative planning in the UK through the CLIP revealed some variations (Daniel
et al., 2014).
2.5 Chapter Summary
This chapter explored the concept of collaboration, construction process
improvement, and the development of collaborative planning in the UK construction
industry. The review established that the demand for construction process
improvement is not limited to the UK construction industry alone; rather it is a global
call. More importantly, the review showed that the demand for construction process
improvement was hinged on collaboration in the design, planning and in the
execution of the planned task, especially as detailed in the UK construction industry
reports. However, the lack of genuine framework for CP has retarded its application
in the industry.
Literature Review Chapter Two
37
Furthermore, the review demonstrated that in order to achieve construction process
improvement, an integrated approach in design, planning, and execution of task is
essential. The chapter also revealed that though various construction industry reports
were commissioned, the recommendations were not implemented, unless supported
by the Government. Again, this shows the reluctance to change in the industry.
The review established that the earliest application of the LPS for delivering
construction projects from a PP&C perspective in the UK was on the Heathrow T4
coaching gate, T4 Arrival phase 2 projects in 1999 and fully on Heathrow T5 project
in 2001 by the BAA. This was followed by the Lean Construction Improvement
Programme (CLIP) under the term “Collaborative Planning” (CP) which was
implemented on demonstration projects. The review showed that the reported
practice of CP on the demonstration project has some resemblance with the LPS
while other elements of the LPS were not reported. However, this could not be
substantiated from the review as empirical data from the industry is required for
authentication. This became one of the knowledge gaps which informed research
question one for the study, as presented below and also in Chapter One.
How does the current understanding and application of “Collaborative Planning” (CP) for
delivering construction projects in the UK align with the advocated principles and theories
of the Last Planner System (LPS)?”
Among other things, this chapter contributes to literature on the need for an
integrated approach in design, planning, and in the execution phase of construction
projects and the vital role of collaboration in achieving construction process
improvement. The next chapter (Chapter Three) brings in a wider perspective on the
need for collaboration in planning by examining its development in other knowledge
areas.
38
CHAPTER THREE: COLLABORATION IN
CONSTRUCTION AND THE
DEVELOPMENTS OF COLLABORATION IN
PLANNING IN OTHER FIELDS:
IMPLICATION FOR CONSTRUCTION
MANAGEMENT
3.1 Introduction
Chapter Two explored the need for construction process improvement and the
development of production planning and control practice based on the LPS in the UK
construction industry. This chapter brings in a wider perspective to this, by exploring
the concept of collaboration and collaborative working (CW), and the development
of collaboration in design, planning, and execution of work in other fields.
Specifically, it reviews the development of collaboration in Urban Planning (UP) and
in software development. The first section examines the current state of collaboration
and CW in the construction industry. It further reviews and presents the current state
of construction planning. The chapter highlights the development of collaboration in
planning in UP.
It also examines how software development progressed from the use of the waterfall
process model to the agile process models. The Rational Comprehensive Model
(RCM) used in UP is compared with the Critical Path Method (CPM) in
construction. This chapter contributes to construction planning theory and
construction project management practice, and analyses how collaboration in
construction planning can be improved using learning from other knowledge areas.
3.2 The Concept of Collaboration
The term collaboration or to collaborate is gaining prominence in businesses such as
information technology, organisation development and service delivery because of
its unifying role and its benefits. According to Shelbourn et al., (2005) various
Literature Review Chapter Three
39
researches on collaboration with regard to information technology have been
conducted and the crucial role the human element plays in achieving collaboration
has been recognised. Wilkinson, (2005) observed that collaboration is not restricted
to information technology alone, as there is the human and organisational aspect of
collaboration. The Cambridge Business dictionary (2015) states that “collaboration is
the act of working together with other people or organisations to create or achieve
something”. However, this definition varies from how the term is used in the
construction industry (Xue et al., 2010).
Schrage, (1990 pp20) defined collaboration as “the process of shared creation
between two or more individuals with complementary skills interacting to create
shared understanding that none had previously shared or could have come to on their
own”. This implies that the underlying principle of collaboration is that there must be
an interaction between the parties which will culminate in the creation of shared
understanding for both parties. Similarly, Shelbourne et al., (2012) opined that
collaboration is a process in which a group of people or organisations agree to
deliver a task by sharing their expertise, information, and knowledge, with all,
working as a team to achieve the intended product in a shared environment. The
shared environment could use physical (human interactions), digital or virtual
resources in the collaboration process. Collaboration also implies that the team is
properly integrated to work, so as to achieve the overall project goal. It is worth
noting that integrated working tends to be used in relation to information technology
in a virtual environment while collaborative working is used in relation to face to
face meetings. However, in this study, both terms are used interchangeably to explain
the concept of collaboration.
Attaran and Attaran, (2007) maintained that collaboration does not only include the
joint working of two or more organisations. They went further to state three core
criteria that must be satisfied which are; (1) having shared common information (2)
ensuring plans are made based on the shared information and (3) executing the
planned task collectively rather than individually. Again, this suggests that
collaboration does not just occur by going into joint venture with an organisation in
which each organisation still acts independently with the aim of achieving the goal of
their individual organisations in the joint venture.
Literature Review Chapter Three
40
3.2.1 Current State of Collaborative Working in the Construction
Industry
Collaborative working (CW) is a common term used to denote collaboration in the
construction industry. CW is concerned with the joint working of all stakeholders on
the construction project, to efficiently and effectively deliver the project to the
specified standard (Xue et al., 2010). Another closely used concept with regard to
CW is partnering. According to Wu et al., (2008) partnering is a type of CW. But,
they however, argued that partnering is only an aspect or an element in CW. This
means CW is wider in scope than partnering. It is worth noting that it is possible for
organisations to claim to be partnering, but never work collaboratively (Pasquire et
al., 2015a; Udom, 2013; Wu et al., 2008). The concept of collaborative working is
gaining more attention in the construction industry, both at the organisational and
project levels. This is because the knowledge and technical ability needed to deliver
a project is dispersed across the project team members (Hayek, 1945). However,
some organisations who claim to be involved in collaborative working still base their
working practices on the traditional project management model. Wilkinson, (2005)
argued that collaboration cannot be easily achieved in the traditional hierarchical
organisational system which characterises the construction industry.
Also, Xue et al., (2010) and Baiden et al., (2006) opined that in the current
traditional approach to procuring projects, construction project stakeholders tend to
seek their individual benefit at the expense of the collective goal of the project; this
hinders CW among the stakeholders. In reality, this approach to working will hinder
the industry from reaping the benefits of CW. According to Baiden et al., (2006) and
Evbuomwan and Anumba, (1998), time and cost overruns are common occurrences
on construction projects, which is partly due to the lack of collaborative working
among the stakeholders. For instance, in the UK construction industry, a current
report indicates that about 50% of construction projects experience both cost and
time overruns (Crotty, 2012).
It can be argued that some so called CW arrangements put in place by organisations
lack the capacity to develop into genuine collaborative relationships among the
stakeholders on the project due to adversarial attitudes and hierarchical structures.
This is because some of the projects still operate based on a claim and blame culture
with a focus on individual benefit. This characterises the traditional approach of
Literature Review Chapter Three
41
managing construction projects and is a coherent paradigm (Pasquire et al., 2015a).
Udom, (2013) observed that CW seems to exist in principle rather than in practice. It
was further observed that on some of the projects that claim to be applying CW, not
all the participants on the project were allowed to sign into the collaborative contract.
This could be due to the quest by the parties on the project to safeguard their
individual interests which promotes a transaction rather than relational approach
(Pasquire et al., 2015a).
According to Briscoe and Dainty, (2005) construction clients distrust their main
contractors while the main contractors also keep their subcontractors at a distance
This implies that for genuine CW to develop, trust and openness must exist among
the stakeholders (Latham, 1994). Udom, (2013) suggested that in developing CW
beyond the contractual provisions, soft skills such as having regular meetings with all
the stakeholders on the project should be encouraged. This is an integral part of the
LPS that focuses on managing of tasks and networks of relationships in production
(construction) from a production perspective (Ballard et al., 2009).
In this approach, construction planning is done collaboratively with those executing
the work. However, this seems to rarely exist in the current state of collaboration in
the construction industry. For instance, Daniel et al., (2016), Daniel et al., (2015a) in
a study in the UK observed that subcontractors are not fully involved in the planning
of task on a project that claims to be using some form of CW. This will not only
result into the development of unrealistic plan, but also lower commitment to the
plan by the subcontractor. This implies that without a realistic and genuine CW
culture, collaboration in construction planning in the project environment cannot be
achieved.
3.3 Collaboration and Construction Planning
3.3.1 Concept of Planning
Planning has been identified as a major project management function. The Project
Management Body of Knowledge (PMBOK) defines planning as “the process of
devising and maintaining a workable scheme to accomplish the business need that
the project was undertaken to address” (PMI, 2015). Planning entails the various
course of actions required for successful completion of a task. According to Cardwell
Literature Review Chapter Three
42
and Redican, (2009, pp 1) “Planning is an activity devoted to clearly identifying,
defining, and determining courses of action before their initiation, and necessary to
achieve predetermined goals and objectives”. These definitions of planning suggest
that planning alone cannot guarantee the achievement and the quality of the planned
task. In view of this, Morton, (2007) argued that planning at its best could meet the
yearning of the people and at the other times it could generate conflict. This implies
that not all forms of planning benefits the stakeholders equally.
There are compendium of literatures on various forms of planning such as
communicative planning, argumentative planning, planning through debate,
inclusionary discourse, and collaborative planning in different fields (Guton and
Day, 2003; Allmendinger, 2002; Mortun, 2007). According to Johansen, (1995) there
is no general definition for planning.
For instance, Lichfield, (2013) remarked that planning refers to series of activities
designed to provide an understanding on a problem that needs examination. While
the Cambridge Advanced Learner’s Dictionary (2015) defines planning as “the act of
deciding how to do something”. This shows that the term planning could have
different meanings in different fields. Basically, there are three levels of planning;
strategic planning, tactical planning and operational planning (PMI, 2015). While
strategic planning, also known as ‘management planning’ focuses on the long-term
plan of the organisation, operational planning focuses on the short-term plan with
specific objectives for a particular section or area of work (Shrader et al., 1989).
Tactical and operational plans support the achievement of the strategic plan. In
practice, day to day operational planning is usually done by the field and lower level
management. For example, operational planning (OP) is used in managing the day to
day activities on construction projects and also in the military on the battle front.
3.3.2 Overview of Construction Planning
Planning is an essential undertaking in construction project management. For
instance, Stevens (1993) and Turner, (1993) observed that without planning,
construction projects cannot be managed successfully. Little wonder a lot of time is
committed to planning when beginning projects generally. It has been observed that
construction and project managers spend 33% of their time in planning and
coordination (Mustapha and Langford, 1990). This shows the vital role of planning
Literature Review Chapter Three
43
in construction management. According to Faniran et al., (1998) construction
planning is the approach used to arrive at the right strategies to be used in achieving
the predefined project goals and objectives. Also, Hayes-Roth and Hayes-Roth,
(1979) opined that planning is concerned with the predetermination of what is to be
done with the sole aim of achieving the specific goal of the project, but
predominantly people goals. The definition of planning in Hayes-Roth and Hayes-
Roth, (1979 pp 275-276) seemed to be highly supported and used in construction
management research by the likes of Birrel, (1980); Laufer and Tucker, (1987);
Johansen (1995); and Ballard, (2000).
Planning in construction could be viewed from two perspectives; the first part being
“planning” and the second “control” (Hayes-Roth and Hayes-Roth, 1979). Planning
determines what needs to be done and control focuses on monitoring the task that has
been planned and modifying it as information evolves. Furthermore, Johansen,
(1995) observed that researchers in construction management view construction
planning from two perspectives; planning techniques and their improvement, and the
planning process. This explains why construction planners and managers tend to
separate project planning from project control which dominates the traditional
approach to managing project.
Faniran et al., (1998) argued that the goal of construction planning is to execute the
prescribed amount of work at the right time, on cost and to the specified quality
standard. However, previous studies confirm that most construction planning efforts
have not truly achieved the target (Laufer and Tucker, 1987; Coheca et al., 1989;
Ballard and Howell, 2004). For instance, Ballard and Howell, (2004); Ballard and
Howell, (1988) observed that in construction, only 54% of planned task are achieved
as planned. This could be due to too much focus on planning techniques rather on the
planning process, or lack of collaboration. Also, the attempt to separate “planning”
from “control” could contribute to this (Ballard, 2000; Faniran et al., 1994). In view
of this, Faniran et al., (1997) suggested that the research focus in construction
planning should be tailored towards improving the planning process rather than on
planning techniques through the adoption of lean production principles that support
collaboration.
Literature Review Chapter Three
44
3.3.3 The Current State Construction Planning and Collaboration
The current state of planning in the construction industry has been criticised. Faniran
et al., (1997) observed that the current focus of construction planning is on
forecasting project performance based on the specified milestone, with less regard to
the process to achieve it. Due to this, planned tasks are usually pushed to conform to
the predetermined milestones. Also, only a little time is invested in the planning,
while much emphasis is on project control as soon as construction commences on
site. For instance, Johansen, (1996) observed that construction managers and project
managers complain of lack of time to engage in detailed planning. In addition to this,
there could be insufficient details while developing the plan. All these further
heightening the uncertainty in the construction process.
Uncertainty and variability are common features associated with construction
planning. Laufer et al., (1992) observed that uncertainty is an integral element in
construction, and further argue that the higher the uncertainty, the less effective the
planning. The impact of uncertainty and variability in workflow in construction has
been identified. Tommelein et al., (1999) showed the effect of variability on the
performance of construction trade through simulation. Ashley, (1999) revealed the
impact of the uncertainty on construction planning and cost. Even with these
empirical evidences, current construction planners and managers seem not to
acknowledge this in the planning process. Most times, plans are too detailed, too
early, and too rigid with less care for inherent uncertainty in the construction
environment (Faniran et al., 1998; Ballard, 1995). Also, it has been observed that
construction planners tend to ignore the inherent uncertainty in the construction
process in planning (Ballard and Howell, 2004; Arditi, 1981).
Johansen, (1995) presented two opposing views to the concept of uncertainty in
construction; hard and soft approach. He argued that the hard system approach
school of thought centres the success of the construction programme around a rigid
production of plan based on network analysis and monitoring of the critical path.
While the soft system approach school thought believes that the rigid approach
cannot yield the intended result because of the inherent uncertainty and complexity
in the project environment. This soft approach to construction planning is deficient in
the current planning practice in the industry as observed in Johansen, (1996).
Literature Review Chapter Three
45
Daniel et al., (2014) observed that the current approach used in construction planning
is based on Rational Compressive Model (RCM). The RCM view planning as a rigid
and scientific process and claims that the knowledge needed for planning is with
planners alone. The RCM approach dominates the Critical Path Method (CPM)
which is now used in construction planning. This approach hinders collaboration and
barriers other stakeholders from contributing to the planning process. However,
Hayek, (1945) argued that the knowledge needed for planning is usually dispersed
among the stakeholders. Due to the inability of the hard approach and RCM model to
support collaboration and manage uncertainty, other soft approaches such as the LPS
are increasingly used in managing construction project (Daniel et al., 2015; LCI,
2015; Gonzalez et al., 2007; Alarcon et al., 2005).The LPS is described in Chapter
Four.
It can be argued that the level of collaboration in construction planning is very low
compared to other industries, thus hindering the performance of the construction
industry. The next sections examine the development of collaboration in planning
outside construction management literature and identify the implications for
construction project management practice and theory.
3.4 Development of Collaboration in Planning in other Fields
3.4.1 Historical Development of Collaboration in Urban Planning
The approach to planning in North America at the end of World War II was based on
what is called Rational Comprehensive Model (RCM) or technocratic planning
(Guton and Day, 2003 Mortun, 2007). This school of thought views planning as a
technical and scientific discipline which can only be performed by experts without
any form of input from the community (Guton, 1984; Susskind, 2000; Wondolleck
and Yaffe, 2000). According to Susskind et al., (2003) technocratic planning is
mainly concerned about the efficient use of resources. In view of this, government
through the planners imposes planning decisions on the community without
stakeholders’ participation.
Literature Review Chapter Three
46
Figure 3.1: Development of collaborative planning model in Urban and Regional planning
Source: Susskind et al., 2000.
However, in the 1960’s the technocratic model of planning was greatly challenged
because of its many shortfalls, especially, the lack of representation of stakeholders’
views in the decision making processes (Guton and Day, 2003 Mortun, 2007). Figure
3.1 shows the progression from the RCM to the collaborative planning model in UP.
3.4.1.1 The Rational Comprehensive Model of Planning
As earlier mentioned, the RCM dominated UP in North America after World War II.
According to Susskind et al., (2000) the RCM views planning as the singular
responsibility of the planner who is seen to be the expert in making major decisions
on assignments to be executed. The champions of the RCM believe that planning is a
technical undertaking that uses scientific principles, thus decisions should be left in
the hands of the planning experts (Guton, 1984; Beierle and Cayford, 2002). The
fundamental contention is in the area of individual rationality and collective
rationality (Stiftel, 2000). While collaborative planning model in UP believes in
collective rationality, the RCM does not.
The failure of RCM led to the development of other models that allow for collective
public participation in the planning and decision making process such as advocacy
planning and collaborative planning models.
3.4.1.2 Advocacy Planning Model
Advocacy planning came into being due to the shortfall of the RCM. The origin of
advocacy planning could be traced to the work of Davideoff published in 1965 in the
Journal of American Institute of Planners (Mazziotti, 1971). According to Susskind
et al., (2000) the proponents of advocacy planning aim at empowering the
stakeholders or interest group to fully represent themselves in the decision making
Rational comprehensive Planning model
Advocacy planning model
Collaborative planning model
Literature Review Chapter Three
47
process. This approach gives stakeholders an opportunity to contribute to the
planning process, and could lead to innovation.
However, Stiftel, (2000) argued that this approach could be taxing and demanding.
This suggests that adopting collaborative approach in the advocacy planning model
requires commitment from all the stakeholders.
3.4.1.3 Collaborative Planning Model in Urban Planning
The collaborative planning model is a step ahead of advocacy planning, although
both are based on a singular goal; that is the collective participation of the
stakeholders in the planning and decision making process (Stiftel, 2000; Susskind et
al., 2000). The collaborative planning model has its unique characteristic that
distinguishes it from other forms of planning as shown in Table 3.1. The
collaborative planning model is a consensus based planning approach that brings all
the stakeholders together with the sole aim of collectively devising the best means of
attaining the intended goal (Morton, 2009; Cardwell and Redican, 2009). The major
target of collaborative planning is to create a platform for stakeholders’ participation
before decisions are made. Although this approach to planning has been criticised,
that it tends to take away power from those it has been vested with (Allmendiger,
2002; Hearley, 2003).
Table 3.1: Rational Comprehensive Model Compared with Collaborative Planning Model
Descriptors Technocratic (Traditional)
Planning Model
Collaborative Planning Model
Tasks Planner operates as technically
skilled decision maker.
The planner is concerned with
achieving efficiency through trust
and concession building.
Focus of Activity Plan produced based on best
solution assumed by selected
decision makers.
Ensures interest of all
stakeholders is considered.
Products/Solution Comprehensive plan for
allocation of resources.
Negotiated agreement that is fair
and achievable.
Skills Technical skill in preparing
efficient plans.
Facilitation of interaction with
stakeholders to produce detailed
plan.
Primary Client City planning commission and
decision makers.
All stakeholders.
Literature Review Chapter Three
48
Basis of Planned
Task Legitimacy
Having technical expertise in the
chosen work.
Achieving mutual agreement with
all stakeholders.
Source: Hearley, 2003; Allmendiger, 2002; Susskind et al., 2000.
It has been observed that the increased understanding developed through the
collaborative planning process contributes to effective CW and support innovations
(Kastalli and Neely, 2006
3.4.2 Critical Path Method and Rational Comprehensive Model in
Planning
The use of RCM in decision making in UP is similar in the use of CPM in
construction planning. The CPM developed in the 1950s was used to develop formal
construction programmes (Koskela et al., 2014; Senior, 2007; Kelley and Walker
1959). The CPM approach is the process of developing construction programme
right from pre-construction to commissioning using activity breakdown structure to
generate list of activities. It is usually done by the expert construction planner.
According to Koskela et al., (2014) the CPM has been hailed as one of the most
important innovations in construction management in the 20th
Century. It is not only
advocated for by clients and construction professionals, but also taught in most
construction management programmes (Senior, 2007). Despite its popularity, it is
less used by field workers in managing the construction process on site. Senior
(2009) observed that the low use of CPM by site workers is due to its unrealistic
nature emanating from the non-involvement of those doing work (the site workers) in
the planning process.
According to Happin, (1993) the CPM approach focuses on the “What” instead of
the “how” of an activity which makes programmes developed based on it of no value
to workers on site. The focus of the CPM includes, but is not limited to; what is the
start date? and what is the finish date?. These are usually arrived at based on the
planner’s experience. The approach used in scheduling activities in CPM is a
prototype of how planners make planning decisions in UP using the RCM, where
only the planner decides what is best for the community. As expected, most planning
decisions made based on the RCM are of low benefit to the community. So also is
the scheduling decision made based on CPM to the team working on site.
Literature Review Chapter Three
49
Docherty, (1972) observed that programmes developed, based on the CPM tend to
decorate the site office wall, while work execution on site are usually managed by
short term planning by site workers. This suggests that the CPM in construction lacks
the capacity to develop a collaborative relationship. This was also evident in the use
of RCM in UP. This shortfall in the RCM informed the agitation for the adoption of
more collaborative approaches in planning and allocation of resources in the UP in
the 1960s. However, in construction collaboration in planning needs to be supported
with a standard operational planning framework, such as the LPS for construction
projects.
3.5 Collaboration in Planning: Search in Software Design
The term “Software engineering or design” came into limelight in the late 1950’s and
1960’s. Specifically, it is believed to have become an official profession following
the NATO Science Committee conference held in Germany in 1969 (Rayl, 2008).
Software engineering is the process of designing and managing the complex
processes involved in the development of programmes to meet customer satisfaction
(NATO Science Committee, 1968). In a bid to satisfy its users, software engineering
design has experienced various forms of challenges which was termed “software
crisis” which resulted in both extreme time and cost overruns especially in 1968,
1979, and 1985 (NATO Science Committee, 1968).
The approach used in planning and developing of software was also among the
factors that contributed to the crisis experienced. According to Highsmith and
Cockburn, (2001) the traditional approach used in software design tends to focus on
how to conform design to plan, which in reality is not achievable and contributes to
time and cost overruns. To overcome these challenges, various planning models have
been adopted in the software development process as shown Figure 3.2.
Figure 3.2: Development of collaborative planning in software design
Source: Munassar and Govardhan, 2010; Dyba and Dingsoyr, 2008.
Waterfall Process Model
Iterative Process Model
Agile Process Models
Literature Review Chapter Three
50
These process model includes the waterfall model, V-Model, Incremental model,
iterative and the agile models such as Extreme programming, Scrum, and Adaptive
software development among others.
3.5.1 Waterfall Process Model
It is the oldest classical model used in the planning of software engineering design.
Munassar and Govardhan, (2010) observed that the model is used extensively in
government projects and in many organisations. The approach is based on sequential
and structured steps which must be adhered to by the designer as indicated in Figure
3.3.
Figure 3.3: Waterfall process model
Source: Munassar and Govardhan, 2010
According to Jaitly, (2014) the traditional waterfall software programming or
planning approach focuses on the process rather than on the people and the customer.
As shown in Figure 3.3, the process could be likened to the network diagram used in
construction programming which is based on the critical path method, where the
focus seems to be on the link between each activity. For instance, Hahmann, (2006)
stated that the model enables customers to get a defined process at the beginning of
the product development. In reality, it is usually impossible to obtain all the
Literature Review Chapter Three
51
requirements for software development at the onset of the project due to external
factors that could arise from the environment (Highsmith and Cockburn, 2001).
The task of defining the entire goal of the project (detail planning) at the onset is
similar to the assumption used in designing construction programmes based on the
CPM. In CPM, no consideration is given for the inherent variability and uncertainty
in the production process and information is based on previous projects, so it looks
backward rather than forward.
3.5.2 Iterative Process Model.
The iterative process model focuses on overcoming the problems presented in the
waterfall process model. The goal of the iterative process model is to allow for
flexibility in the planning process while also providing quicker information to the
team and reducing upfront information overload (Munassar and Govardhan, 2010).
This is opposed to the waterfall process model in which the planning process is
structured and rigid. Marciniak, (2001) and Wirth, (1971) opined that in the iterative
process model, development occurs through the refinement and improvement of the
successive process using the learning acquired from each stage of the development.
The approach allows the team to determine the feasibility of the product early
enough and for outright feedback from the prospective users and customers.
3.5.3 Agile Process Models
The Agile software development process shows a clear departure from the traditional
classical approach to software development. It is a movement initiated with the goal
of developing a faster, cheaper, and better solution to overcome the problems in
traditional approach (Dyba and Dingsoyr, 2008). According to Dyba, (2000) the
movement was initiated to overcome the traditionalist view that tends to emphasise a
rigid engineering approach to the design process. The “traditionalist” believes that
through comprehensive planning based on the knowledge of the planner, the
planning process could be made efficient without considering the variability in the
environment (Boehm, 2002). In contrast to this, the Agile process model sets to
overcome the variability in the process by depending on people rather than on
techniques alone. The unique feature of the Agile process is that it is developed
around the customer and users (Jailty, 2014). Ericksson et al., (2005 p89) gave a
Literature Review Chapter Three
52
vivid definition of agility in relations to software development: “agility means to
strip away as much of the heaviness commonly associated with the traditional
software-development methodologies, as possible to promote quick response to
changing environments, changes in user requirements and accelerated project
deadline and the like”. Some of these Agile methodologies include Scrum , Extreme
programming etc.
3.5.3.1 Scrum
Scrum is an Agile process model methodology used in software development. It is
meant to overcome the uncertainty associate with software design (Schwaber and
Beedle, 2002). Unlike the traditional classical process models, it incorporates the
social value (human) element in the development process. The approach is used in in
the development of products with tight timeline and changing business requirements
(Pressman, 2005). It entails two key processes; the backlog stage and sprint stage.
The backlog refers to the activities to be undertaken by the team while the sprint
refers to the work that is already at hand to be done by the team and it occurs in
phases. Koskela and Howell, (2002) perceived that the theory behind Scrum
approach is based on management-as-organising, language action perspective and
theory of flow and value. The LPS is also based on the above theories.
Figure 3.4: The Scrum Process
Source: Schwaber and Beedle, 2002
The approach allows the team to self-organise work collaboratively in the software
development process. Rising and Janoff, (2000) stated that in the sprint process, the
Literature Review Chapter Three
53
project team makes promises on tasks they are confident could be done within the
chosen sprint as shown in Figure 3.4. The sprint period could be likened to the
production planning stage in the LPS, where the last planners are expected to make
reliable process (Pasquire et al., 2015, Ballard, 2000; Ballard, 1994). Also, at this
stage, the plans are made visible with input from other stakeholders on the project.
Specifically, at the end of the sprint, a more feasible and realistic programme is
developed. The backlog (that is the task to be done) is usually reviewed and reasons
for non-achievement of the backlog are identified and acted upon.
Other processes associated with Scrum include; daily and monthly Scrum meetings,
absence of work breakdown structure, identification of impediment at daily Scrum
meeting, and viewing teams as direct customers to each other. This approach is a
total deviation from the traditional doctrine of project management where all
programmes of work must be centralised before being dispatched to the work phase.
Koskela and Howell, (2002) offered a theoretical insight on the success of Scrum as
a project management approach.
3.6 Comparing the CPM, RCM, Collaborative Planning and the LPS
With the examination of the CPM in construction, RCM in UP, collaborative
planning model in UP, and the Agile model in software development, these are now
compared with the LPS in Table 3.3. The focus of the collaborative planning model
in UP is on the full engagement of all the stakeholders in the decision making
process. Some of these principles were demonstrated in the Scrum process in the
Agile methodology and in the LPS. For instance, the development of tasks in Scrum
is decentralised to allow all stakeholders, including the customer to make input so as
to arrive at a realistic estimate.
Rising and Jannof, (2000) confirmed that at the end of the sprint process, more
realistic estimate in terms of durations are arrived at as a result of input from all the
stakeholders on the project. Furthermore, in software development using Scrum
methodology, teams are direct customers to each other including the client (Koskela
and Howell, 2002). Also, in the collaborative planning model in UP and in the LPS,
all the stakeholders in the planning process are viewed as the primary client and
customer. This is contrary to the CPM and RCM approaches that tend to view only
the project financiers and the planning authority as the primary client or customer.
Literature Review Chapter Three
54
However, collaborative planning and RCM (in UP) and CPM (in construction) differ
from the Scrum method (in software design) and LPS in the nature and structure of
planning. While the nature of planning in UP and CPM is strategic or management
planning, it is operational planning in Scrum and the LPS.This suggests that the
collaborative planning model and CPM approaches alone, cannot be used to manage
short term planning on a construction project.
A closer look at Table 3.2 also shows similarities between the agile methods such as
Scrum and the LPS. For instance, the LPS supports the idea of stakeholders’
engagement and involvement in a collaborative manner in phase planning, and
Weekly Work Planning (WWP) meeting among others as practiced in the sprint.
Furthermore, the publication of the Percentage Planned Complete (PPC) and Reason
for Non-Completion (RNC) in the LPS for team learning and improvement are
similar to the visual progress monitoring approach used in Scrum. Though
similarities exist between Scrum and the LPS; however, Scrum is less developed as it
cannot be used in managing complex projects (Dyba and Dingsoyr, 2008).
In addition to this, its application is still limited to the design stage because of the
industry it operates in. The LPS is not only applicable to complex projects, it is also
used in design, construction, ship building, and mining among others (Daniel et al.,
2015). Also, there are empirical evidences that the LPS has been implemented in 16
countries that cut across all the continents of the world with good output (Daniel et
al., 2015). This show that the LPS is and still remains the most advanced production
planning and control for construction project management.
Literature Review Chapter Three
55
Table 3.2: Comparing CPM, RCM, Collaborative Planning in UP, Agile process model and the Last Planner System
Fundamental
Processes
CPM (Construction) RCM (Urban Planning) Collaborative Planning in
(Urban Planning)
Agile process model
(software design)
Last Planner System
Level of planning Comprehensive,
disciplined plan with long
term focus
Detail and comprehensive
plan
Long term
Long term, but in
consultation with
stakeholders and flexible
Continuous control of
requirement and short term
focus
“Only plan in detail as nearer the
task” with a short term plan
focus (Phase scheduling, WWP).
Note: The Phase Scheduling is
usually developed from the
master programme.
Communication Consultation absent Consultation absent Consultation Consultation Consultation
Review Review after task
completion
Review absent Review before decisions
are made
Review process embedded
in the development process
(Sprint reviews)
Review embedded in the
production planning process
(PPC measurement, RCN)
Management style Command and control Command and control
from planner and planning
authority
Leadership and
collaboration with the
stakeholders
Leadership and
collaboration
Collaboration and empowerment
of “last planner”
Knowledge
management
Explicit Explicit Tacit Tacit Tacit
Focus Rigid and process focused Rigid approach Flexible and community
focused
Flexible and human
focused
Understand the presence of
variability in production and
human focused
Feedback Only management gives
feedback
Only management gives
feedback
Everyone gives and get
feedback
Everyone gives and gets
feedback
Everyone gives and gets
feedback
Primary Client Project sponsor or owner City planning commission
and decision makers.
All stakeholders in the
community
Intended customers and the
software designer
All the stakeholders on the
project
Nature of plan Strategic planning Management planning Management planning Operational planning Operational planning
Basis of Planned
Task Legitimacy
Technical expertise in the
const. planning
Technical expertise in
Urban planning
Endorsement of all
stakeholders in the
community
Input and agreement with
customers and designers
Input and agreement with the
‘last planners’
© Daniel et al., 2016
Literature Review Chapter Three
56
3.7 Development of Collaboration in Planning in other Fields:
Implication for Construction Project Management
3.7.1 Implication for Construction Project Management Practice
These developments (changes) in the field of UP and in software development in the
approach towards planning should serve as a great learning point for construction
project management practice. For instance, the RCM that previously formed the basis
of planning decisions in UP has been established to form the basis of planning
practice in the construction industry as seen in the CPM. However, with the
realisation of the negative impact of the RCM approach to planning decisions, the
urban and regional planning profession opted out of the RCM approach to advocacy
planning model and collaborative planning model (Morton, 2009; Stiftel, 2000;
Mazziotti, 1971). This suggests that the RCM that views planning as a scientific
discipline and claims that the knowledge needed for planning is with the expert
planner alone, is an illusion that needs to be avoided.
In view of this, construction management practice should also move from the current
practice where planning decision is left with the construction planner or the planning
engineer alone. Although, Hayek, (1945) made this assertion many decades ago, that
the knowledge needed for planning is not in the hand of a single individual, but
rather dispersed among people. This reality is yet to be fully accepted in construction
project management practice. Leaving the planning decision to the expert planner
alone, means the planned duration will largely be based on guess work. Johansen and
Greenwood, (1999) observed that relying on the knowledge of the planner alone to
decide on activity duration is always a guess work, which contributes to the high
level of uncertainty in construction planning. It can be argued that the failure of
construction project management with regard to planning is due to its focus on rigid
planning techniques than on adopting planning processes that are more collaborative
and efficient. According to Faniran, (1994a) and Cohenca et al., (1989) even with the
emergence of various planning techniques, construction planning has not been able
to improve the efficiency of construction project management practice.
The change experienced in UP and software development with regard to improved
planning practice could be attributed to the inclusion of people and process into the
planning and decision making system, rather than rigidly focusing on planning
Literature Review Chapter Three
57
techniques alone. For instance, Faniran et al., (1997) suggested that construction
project management should improve the efficiency of the industry by focusing on
improving the construction planning process instead of holding on to rigid planning
techniques alone. Furthermore, the incorporation of human elements in UP
(collaborative planning model) and software development (Agile process models)
contributed immensely to the development of collaborative approaches in the fields.
The importance of the human element (social) as opposed to the technical element in
construction project management has been emphasised (Ballard, 2000; Brasen et al.,
2003). This approach was demonstrated in the planning and allocation of space in
UP, in software development and the LPS. For example, in the Scrum approach, the
client and all the other stakeholders in the software development process are fully
involved and seen as direct customers to each other. This improves the level of
conversation and commitment to the task, thus improving the quality of the final
product (Jannof and Rising, 2000). As seen in this approach, the focus is not on a
single individual in the team, but rather the teams are self-organised to deliver the
task. This implies that construction project management should create the
environment that could empower all stakeholders to make a contribution, especially
in the construction planning process.
The collaborative approach to planning has the potential to empower teams to
communicate and make a useful contribution to the planning process (Pasquire et al.,
2015; Mossman, 2014; Daniel et al., 2014; Ballard, 200). The need to adopt this
approach in construction planning is now more crucial considering the uncertainty
associated with construction planning (Faniran et al., 1997; Johansen, 1995).
Gonzalez, (2008) observed that the failure of construction planning does not only
contribute to poor construction management decisions, but also the failure in
construction project management practice. Considering the fact that the variability
and uncertainty are inescapable in construction planning and in a project
environment in general, the goal therefore should not just be on how to stop change
by focusing on rigid and long term plans. Rather, the goal should be on how to
handle the inevitable changes that could occur over the life of the projects. This can
be done by focusing on short term plans and planning in detail as close to the task as
used in software development and the LPS (Highsmith and Cockburn, 2001; Ballard,
Literature Review Chapter Three
58
2000). Construction project management practice must come to term with the current
realities in the project environment in order to improve practice.
3.7.2 Implication for Construction Project Management Theory
The evaluation of the development of collaboration in planning in other fields has
implications for construction project management theory. This is crucial as various
construction management scientists would argue that there is no uniform theory
guiding the construction management practice (Koskela, 2000; Harris, 1998; Halpin,
1993). For instance, Halpin, (1993) opine that if there is any theory for construction
management, such theory is still in hiding. Also, Koskela, (2000) acknowledged the
fact that there is no defined theory guiding construction management practice. He,
however showed that the current practice in construction project management is
based on the theory of production that emerged from economics. Koskela therefore
postulated that the concept of Transformation, Flow, and Value (TFV) be adopted as
the fundamental theory to build construction project management upon (Koskela,
1992).
In reality, the current practice of construction project management is only limited to
the ‘transformation view’. The transformation view entails the conversion of input
into output. The RCM used in UP in the planning process could be said to be based
on the transformation view theory. So also is the Waterfall process model used in
software development and the traditional approach to planning in construction which
is based on CPM. This is so, since the tenet of the transformation view is on how
tasks would be executed effectively following a defined or structured process without
considering the influence of external phenomena. Koskela, (2011) argued that the
focus of the transformation view is on task management. As good as this may look, it
lacks the capacity to manage variability and meet customer requirement. This would
mean that the application of transformation view alone in construction project
management and planning lacks the capacity to mitigate variability in the
construction process.
However, Koskela, (1999) proposed that the inclusion of the flow and value views in
construction project management will no doubt help in overcoming the current
deficiency associated with the transformation view. The concept of flow and value
generation from customer perspective has been in production for decades (Shewhart,
Literature Review Chapter Three
59
1931; Gilbreths, 1992); but construction project management is yet to fully embrace
this reality. The development of collaboration in planning in these fields of
knowledge has shown that the incorporation of the concept of flow and value to the
transformation view could support better collaboration in construction management
process (Highsmith and Cockburn, 2001; Stiftel, 2000). For example, the move from
the waterfall process model (transformation only view) in software development to
the use of Scrum and Extreme programming (Agile process model based) is due to
the inclusion of the flow and value generation theory concept.
Koskela and Howell, (2002) argued that the decision making process that supports
value generation should be decentralised and all the stakeholders in the development
process should be given a clear say. They suggest that project planning and
management should be viewed as management-as-organising and management-as-
planning rather than as management-as-planning alone as enshrined in the
transformation view. This shows the level of improvement achievable in construction
project management practice when built on sound theories; such as the inclusion of
the flow and value theory in construction project management. The successful
application of this in software development implies its application in construction
project management is realistic and could be beneficial.
More importantly, this theoretical concept of transformation and flow is now also
applied in the LPS developed by Ballard and Howell in 1992 for the construction
industry (Daniel et al., 2015; Ballard and Howell, 1998), with significant impacts in
manging project production in construction. Koskela, (2000) argued that the
application of sound theory to construction project management practice will
improve performance while its absence will support poor performance. This suggests
that more focus should be given to theory in construction management to inform
better practice.
However, Seymour et al., (1997) observed that researches in construction project
management tend to pay less attention to interpretivism approach that is rigorous
enough to develop sound theory.
Literature Review Chapter Three
60
3.8 Chapter Summary
This chapter examined the concept of collaboration and the development of
collaboration in design, planning, and execution of work in different knowledge
areas in a bid to contribute to construction project management theory and practice.
The review indicates that the desire for collaboration and CW is on the increase in
almost every sector including construction. However, the current practice within the
construction industry where construction stakeholders tend to seek their
individualistic goal even when they claim to be using some form of CW cannot
support genuine collaboration in the industry. The chapter shows that without
genuine CW built on relational principles, collaboration in planning cannot be
achieved.
The review indicates that planning is an important function in construction project
management. However, the current approach to planning in construction tends to
focus more on planning techniques and pays less attention to the planning process
and the uncertainty and variability inherent in the project environment. The current
planning approach separates ‘project planning’ from ‘project control’ which hinders
project stakeholders from collaborating effectively in the planning process. Thus, the
chapter identified the need for the adoption of collaborative approaches to improve
construction planning.
The review established that the rational or technical approach to planning is not
germane to the construction industry alone. Rather, it seems to exist in various
disciplines as seen in the RCM used in UP and in the waterfall process model used in
software development. This suggests that the construction industry should not only
be criticised for its current practice, but should also be supported to move up from its
present position that has less apparatus to support collaboration in planning and in
the execution of work.
However, the paradigm shift from the rational approach to planning in UP and in the
software development to a more collaborative approach should be of a great
significance to construction project management. The successful adoption of
collaborative approaches in these knowledge areas shows that the construction
industry could also move from its current technical approach to a more social
approach that encourages collaboration. This entails focusing on system thinking
Literature Review Chapter Three
61
rather than the current functional ‘activity to activity’ thinking that dominates the
industry.
The review shows that the application of the current theory of project planning, that
is ‘management-as-planning’ (the Transformation view) alone, lacks the capacity to
develop collaborative relationship among project stakeholders. To overcome this,
project planning and management should include the concept of management-as-
organising that supports the ‘Flow’ and ‘Value’ view for a smooth running of the
production system. The Last planner System of production control as described
briefly in this chapter and fully in Chapter Four is the most advanced methodology
that supports the production and flow view in managing construction projects. It also
embraces the social elements used in the development of the collaborative planning
model used in UP and software development. The LPS is now discussed extensively
in Chapter Four.
62
CHAPTER FOUR: PRODUCTION
PLANNING AND CONTROL IN
CONSTRUCTION BASED ON THE LAST
PLANNER SYSTEM
4.1 Introduction
Chapter three examined the development of collaboration in planning in other
knowledge areas and suggested the adoption of the Last Planner System (LPS) in
construction because of its capacity to manage production in construction. This
chapter examines the LPS of production control in detail, as a production planning
and control (PP&C) methodology in construction with focus on its evolution and
practical implementation in construction. The first section examines the evolution of
PP&C in management science, manufacturing, lean production and in the Toyota
Production System (TPS). The eventual application of lean production to
construction projects through the seminal work of Koskela is presented. This chapter
highlights the development of PP&C in construction with focus on the LPS and its
supporting components. The chapter also presents the theories that explain the
effectiveness of the implementation of the LPS in construction.
The chapter highlights the practical implementation of the LPS in construction
projects through a comprehensive and systematic review of the International Group
for lean Construction (IGLC) papers on LPS implementations. It further identifies
LPS implementation drivers, success factors, benefits, challenges, trends in
implementations and its impact on construction process improvement. It also reports,
the current developments in LPS. This chapter does not only set the foundation for
the empirical exploration of the PP&C practice based on the LPS in the UK, it also
contributes to the creation of Last Planner System Path Clearing Approach presented
in Chapter Eight.
Literature Review Chapter Four
63
4.2 Production Planning and Control
4.2.1 Production Planning: The Search in Management Science
The concept of production planning became popular in the manufacturing industry
and management science after World War II. According to Koenisberg and Mckay,
(2010) production planning and control are among the topics addressed in
management science since the end of the World War II. It seeks to know what, why,
how, and who of the production system, while also analysing the production system
for continuous improvement. The concept of production planning and control in
management science dates back to the work of scientific management theorist
Frederick Taylor, where he emphasised the need for production planning and
production control in the manufacturing process in order to eliminate waste and
improve productivity (Taylor, 1939). Grimsley, (2014) asserted that the improvement
achieved from the adoption of Taylor’s approach in the production process not only
benefits the employer, but also the employees and the society in general. This shows
the benefit of production planning and control to stakeholders was wide in the
manufacturing industry at its earliest stage. However, prior to these theories,
Herrman, (2006) observed that the focus of planning in the manufacturing industry at
the end of the 1800’s was to optimise the efficiency of the plant and machines and
not the production system.
However, this approach changed in the manufacturing industry at the beginning of
the 1890 due to complexity in the manufacturing process, giving rise to the concept
of formal scheduling or production planning (Herrman, 2006). Fredrick Taylor
formally put forward the concept of production planning in manufacturing at the end
of World War I to overcome these associated complexities in the production system
(Taylor, 1934; 1911). This suggests that the concept of production planning emerged
as a result of the complexity and uncertainty associated with the production system in
the manufacturing industry.
4.2.2 Production Planning: The Search in Lean Production
Lean production has its origin in the Toyota production System (TPS) developed by
Engr. Taaichi Ohno for Toyota in Japan after World War II. Various authors have
described extensively the evolution of lean production and the TPS in the
Literature Review Chapter Four
64
manufacturing industry (Shah and Ward, 2007; Holweg, 2007; Womack and Jones,
2003; Ohno, 1998). It is worth noting that lean production philosophy is also
applicable in other sectors such as the construction industry (Koskela, 2000). The
goal of lean production is to add value and eliminate waste from the product right
from design through to the manufacturing or production stage. However, Shah and
Ward, (2007) cautioned that lean production should not only be viewed as waste
elimination, continuous improvement, JIT, pull planning, and quality management
among others, rather it should be viewed as a multifaceted concept that spans across
philosophical characteristics that cannot be easily defined. This implies that lean
production is not just a singular concept, but an integrated approach used in
delivering products with much value.
Before the emergence of lean production in manufacturing, mass production was the
common approach used in production (Womack et al., 1990). The weakness of this
approach is obvious from the lack of synergy or collaboration from the employee
working on the production line since labour is divided.
According to Dilworth, (1992); Murdick et al., (1990) production planning does not
only produce the overall plan for production, it also gives the details and exact
number of units that needs to be produced per hour, day or week. This approach is
termed, production schedule in lean production (Schniederjans, 1992). Again, this
illustrates the level of detail achievable in production planning in a controlled
environment. It can therefore be said that production planning shows the minutest
detail of all the processes in the production process, indicates the interrelationship of
activities in the production line and emphasises the place of the human element in
developing a reliable plan.
4.2.3 Application of Lean Production Philosophy in Construction
Lean construction (LC) principles are based on the Toyota Production System (TPS)
principles. This may be due to the similarities that exist between manufacturing and
the construction industry. For instance, McCrary et al., (2006) Howell, (1999) and
Koskela, (1997) argued that both industries create products with the aim of meeting
their client requirements and they both look forward to earning profits. However, the
view of likening the manufacturing industry to the construction industry projects is
not accepted by all. For example, Gann, (1996) opined that construction products are
Literature Review Chapter Four
65
usually large and immobile; this implies that construction products are created at the
point of consumption unlike manufacturing where materials are fully produced in the
factory before sending it to the market. Although, Salem et al., (2006), agreed that
there are clear differences between the manufacturing and the construction industry;
he conceded that both operations involve ‘production’ and ‘services’ with the aim of
meeting customer demands and requirements. Tommelein et al., (1999) argued that
both the manufacturing industry and the construction industry can be seen as
production systems that use processing points and hand over partially completed
work to the next person on the production line. Furthermore, the one-off nature of
construction products makes it unique and different from the manufacturing industry
(McCrary et al., 2006; Salem et al., 2005).
However, Koskela, (1997) asserted this is not only akin to the construction industry,
as it also exists in product development in the manufacturing industry. He therefore
suggested that the problem associated with the one off nature of construction product
could be reduced through modular construction and standardisation in controlled
environments. This implies that the lean production philosophy is applicable to
construction and is now termed as lean construction. It is worth to note that the
present approach used in delivering construction projects will not readily support
lean production philosophy in construction due to some peculiarities of construction.
In view of this, Koskela, (1997) underscored the need for change in attitude and
adoption of methods and techniques that could drive a new system.
Lean construction is the application of lean thinking in the design and production of
construction facilities through systematic elimination of waste, thus improving value
for construction stakeholders (Womack and Jones, 2003; Howell, 1999; Koskela,
1992). The aim is to minimise waste from the construction process and to challenge
construction practitioners to move towards continuous improvement, thus delivering
value to customers (Koskela, 2000; Pasquire and Conally, 2002).
4.2.4 Criticism of Lean Construction
Lean production philosophy has been criticised as a mere collection of tools that
could only be used for one-off improvement in an operation (William et al., 1995;
Berggren, 1990). Green, (2002); Lewis, (2000); Green, (1999); Pheng and Tan,
(1998) critiqued that the application of lean production principles supports
Literature Review Chapter Four
66
unpleasant practices such as repression of worker’s rights as practiced in Japan, and
lack of due consideration for the social, moral and political significance of the
process. The critics are of the view that if this is what lean production is associated
with in the manufacturing industry; it is not worth bringing it to the construction
industry. This could be due to the view that the construction industry is imitating the
manufacturing industry, but not in a controlled environment.
According to Ballard and Koskela, (2011) lean construction only attempts to abstract
and adapt lean production principles that address the deficiencies in the construction
industry. The full application of lean production principles into the construction
industry following the initial of work of Koskela, (1992) has received wide criticism
from construction management researchers such as in Green, (1999; 2000; 2002);
Green and May, (2005), and Winch, (2005; 2006; 2010) among others.
For instance, Green, (1999) argued that lean construction advocates such as Koskela,
Ballard, and Howell base their conclusion on the potentials of lean production
principles in construction on one-sided literature of lean production while ignoring
the critical view regarding human cost in lean production method such as stress,
accident, long working hours etc. But in response to Green, Howell and Ballard,
(1999) argued that lean production is a new approach of organising the production
system to make work more efficient. They further stated that the application of lean
principles results in better working condition for workers than the craft and mass
production regime. In fact, there are empirical evidences that the application of lean
construction principles reduce health and safety issues on site and improves the
wellbeing of workers (Fernandez-Solis et al., 2012).
Additionally, Winch (2010) critiqued that LC is limited to site construction and
production of standard products, separates design from making, and is a form of
bureaucracy which is opposed to professionalism. However, Ballard and Koskela
(2011) provided convincing rebuttal to all the criticisms of Winch. For example,
Koskela and Ballard, (2011) argued that LC is not only applicable to the site
construction as misrepresented in Winch, (2010), but also used in target costing. This
is backed up by Ballard and Paul, (2004) that reported the first successful application
of lean construction approach in target costing and other publications on its
successful implementations such as in Do et al., (2014a); Zimina, Ballard and
Pasquire, (2012); and Ballard, (2006). This shows that LC is not applicable to site
Literature Review Chapter Four
67
construction only. Koskela and Ballard concluded that Winch’s critique could be due
to the complexities associated in understanding the LC concept which they attributed
to the low number of lean construction publications in the mainstream journals.
It is no surprise that lean construction researchers have taken up this challenge, with
publications in mainstream journals is on the increase in recent times. These, coupled
with empirical evidences of the impacts of the application and the increase in the
number of LC techniques used in construction (LCI, 2015; Daniel et al., 2015;
Fernandez-Silos et al., 2012; McGraw Hill, 2013) could have contributed to the
reduction in the criticism of LC in recent time. For instance, a recent research
indicates that the Last Planner System; a lean construction techniques has been
implemented in 16 countries that cut across the major continents of the world (Daniel
et al., 2015). This shows the application of LC techniques could be beneficial, with
increasing acceptance.
4.2.5 Lean Philosophy in Production Planning and Control in
Construction
Construction projects are considered to be complex and characterised with
uncertainties arising from both the process and the delivery mechanism (Barlow,
2000). Planning and control have been considered to be an important management
function and used extensively in construction management. However, the current
approach used in managing construction projects separates project “planning” from
“control” which contributes to the uncertainties in the construction project
environment (Ballard and Howell, 2003). Ballard and Howell, (1998) observed that
construction project management lacks a defined theory for “production control”,
thus all attention seems to be shifted to “project control”. Project control focuses on
analysing ‘the effects’ which contributed to non-achievement of tasks as planned
(Hamzeh et al., 2015; Fiallo and Revelo, 2002; Ballard, 1994).
However, in production planning and control (PP&C) “planning” and “control” are
seen as an integrated process (Daniel et al., 2016; Ballard and Howell, 2004). This
makes the planned construction programme more predictable and reliable, thus
leading to reduction in lead time in the construction phase. The Last Planner System
(LPS) has been identified to be among the most developed lean construction
technique that effectively support project production control in construction (Khanh
Literature Review Chapter Four
68
and Kim, 2015; Papke and Dove, 2013; Ballard and Howell, 2004). It is a production
planning and control methodology developed for managing the production process in
construction (Hamzeh et al., 2015a; Papke and Dove, 2013; Ballard, 2000). LPS
plays a central role in improving workflow reliability and predictability of planned
construction activities at the work phase because of its capacity to shield projects
from workflow uncertainty (Khanh and Kim, 2015; Khanh and Kim, 2014; Ballard
and Howell, 2003; Ballard and Howell, 1998).
4.2.6 Evaluating Production Planning and Control in construction
The need for production planning in construction cannot be overstated due to much
variability in the construction process. The argument that construction should be
viewed as a production system as presented by Ballard, Howell, and Koskela has
indeed brought a paradigm shift in the construction industry (Ballard, 2000; Koskela,
1992; Ballard and Howell, 1997). Previous studies confirm that construction
planning can become reliable and predictable when work is planned using production
planning and control processes (Ballard, 2000; Howell and Ballard, 1997). This
shows the benefit of production planning in construction. However, it is worth noting
that a system could deviate unknowingly if it lacks proper mechanism for evaluating
it.
Bernardes and Formoso, (2002) suggested a method for evaluating production
planning and control practices in construction based on the Last Planner System
methodology. The PP&C principles were identified from numerous studies on LPS
implementation in construction usually termed as Planning Best Practice (PBP) index
(Sterzi et al., 2007; Bernades and Formoso, 2002). The identified practices have been
used to examine the implementation of PP&C in relation to the LPS on construction
projects including 12 projects in Israel (Priven and Sacks, 2015); 6 case study
projects in Brazil (Bernardes and Formoso 2002) and in observing 5 projects in
Brazil (Sterzi et al., 2007). They argued that identifying the basic practices through
an evaluation process could provide a basis to initiate the process and practice that
could support improvement in the LPS implementation.
Literature Review Chapter Four
69
4.3 The Last Planner System of Production Control
4.3.1 The Last Planner System: An Overview
The Last Planner System (LPS) was developed by Ballard and Howell in the 1990’s
following a research in the industrial construction sector (Daniel et al., 2015; Ballard
and Howell, 1988). The LPS focuses on reducing workflow uncertainty identified as
a missing component in the traditional project management kit (Baldwin and
Bordoli, 2014; Ballard and Howell, 2003; Koskela, 1999). This missing component
has been identified by lean construction researchers as a contributory factor to the
poor performance of construction projects (Ballard and Howell, 2004; Howell and
Ballard, 1998). The LPS is an integrated and comprehensive approach that intends
planned construction activities are predictable and reliable at the implementation
stage on a construction site (Forbes and Ahmed, 2011; Mossman, 2014; Chee et al.,
2009). It is worth noting that its application is not limited to the construction stage
alone, as it is also effective at the design stage and in decommissioning.
LPS supports the creation of a platform for stakeholders on the project to plan
together in order to reduce uncertainty and improve the quality of the construction
programme. According to Howell and Ballard, (1994) the level of uncertainty in the
traditional project management approach is at a high level and most times is due to
the manner in which tasks are planned. The LPS is designed to address this shortfall
in the traditional project management approach. Koskela and Howell (2002) argued
that the traditional project management approach is obsolete and has failed to address
the many problems confronting the construction industry, but it is still being used.
Unlike the traditional approach of project management that focuses only on activities
on the programme; the LPS in addition to this manages relationships, conversations,
and commitments, and ensures construction planning decisions are agreed
collaboratively among the stakeholders at the lowest level of the project (Gonzelez et
al., 2015; Hamzeh et al., 2015; Mossman, 2014; Ballard, 2000). The influence of the
LPS in managing the production process in construction has been posteriorly
rationalised through theories relating to decision-making and uncertainty in the
production process (Ballard et al., 2009). These theories and principles include:
Transformation, Flow, and Value theory (Koskela, 1992; Koskela and
Ballard, 2006)
Literature Review Chapter Four
70
The Language/action perspectives (Macomber and Howell, 2003; Flores,
1982) and
Hayek’s, (1945) comment about the way knowledge needed for planning
is dispersed among individuals.
More importantly, the underlying theories of the LPS revolve around planning,
execution, and control. According to Baldwin and Bordoli, (2014); Ballard and
Howell (2003), LPS focuses on planning and production control as opposed to
directing and adjusting resources in the traditional project management approach
(thermostat model). There are 5 key principles in the LPS (Ballard et al., 2009), and
these are;
ensure tasks are planned in increasing detail the closer the task execution
approaches
ensure tasks are planned with those who are to execute them
identify constraints on the planned task to be removed by the team
beforehand
ensure promises made are secure and reliable, and
continuously learn from failures that occur when executing tasks to prevent
future reoccurrence.
Ballard (2000, p. G-14) stated that “the Last Planner(s) is the person or group that
make assignments to direct workers”. Last Planners are actively involved in
developing the programme for the work and ensuring the work is made ready before
sending it to the work phase (Alsehaimi et al., 2014; Mossman, 2014, Ballard, 2000).
The duties of the Last Planners are therefore to ensure that work is broken down,
structured and planned efficiently to create flow in the construction process and to
ensure such work is executed at the optimal level (Lindhard and Wandahl, 2013;
Ballard, 2000).
4.3.2 3Components of the Last Planner System
The Last Planner System implementation comprises of 5 key processes as shown in
Figure 4.1 and subsequently discussed. These progressive processes yield significant
benefits especially in developing a collaborative relationship. However, lack of full
implementation has adverse effects on both the upstream and downstream flow of
3 Part of this section has been published in Pasquire, Daniel and Dickens, (2015a)
Literature Review Chapter Four
71
construction activities (Mcconaughy and Shirkey 2013, Mossman, 2014).
Unfortunately, many construction organisations are yet to pay full attention to flow
in their implementation effort and continue to focus on optimising tasks
(transformation).
Figure 4.1: The Last Planner System of Production Control Model
Source: Ballard (2011)
4.3.2.1 The Master Plan or Milestone Planning
The Master Plan or milestone planning captures the entire tasks to be executed
throughout the project and at the same time shows the length of time required for
each activity to be completed. It identifies the project milestones and initiates the
means for achieving them (Forbes and Ahmed, 2011; Zimina and Pasquire, 2012;
Ballard et al., 2007). This is usually referred to as the contract programme and
presented on a Gantt chart or in Primavera. It forms the basis for the development of
the collaborative programme or phase planning. The purpose of the Master Plan
therefore, is to show the target (milestone) for accomplishing a given task, and to use
such information to steer the project delivery through the collaborative programming
or phase planning meetings (Ballard, 2000). The master programme shows how the
enire project can be achieved.
4.3.2.2 Phase Planning or Collaborative Programming
Phase planning or Collaborative programming is a process used in developing a
reliable construction programme from the master or contract programme by direct
involvement of the subcontractors, contractors, suppliers, designers and other
Literature Review Chapter Four
72
stakeholders including the client on the project. It builds strongly on the concept of
“next customer” to understand the interfaces in the process. It is prepared early in the
project planning through logical arguments used to agree how one activity ends and
the next starts - called handing off (Mossman, 2014; Anderson et al., 2011; Ballard,
2000). The phase planning is usually developed from the master programme through
series of dialogues and input from subcontractors, suppliers, specialist contractors,
designers and others who are party to the project (Baldwin and Bordoli, 2014,
Mossman, 2014; Hans et al., 2006). This increases transparency and builds trust
within the project team and is essential in developing a common understanding (the
eighth flow) of all aspects of the project (Pasquire, 2012).
However, this approach is considered to be non-existent in the traditional approach
of project planning which is characterised by a lack of trust and little collaboration in
agreeing procedures for delivering the project (Zaghloul and Hartman, 2003; Austin
and Baldwin, 2002). Ballard and Howell (1998) argued that the non-existence of
collaborative programming in developing construction tasks and activities is among
the major causes of construction project failures. Other terms used for collaborative
programming in the construction industry include: Detail planning; Detail
programming to completion; Phase Scheduling; Collaborative programming, Pull
planning and High level programming among others. It is worth noting that this
process is commonly called collaborative programming by practitioners in the UK,
while phase scheduling is the common name used for it in Lean Construction
Institute literature (LCI, 2015; Ballard, 2000; Ballard and Howell, 2004).
In practice, the approach not only leads to a reduction in construction programme,
but also enables the team to develop a common understanding of the tasks (Pasquire,
2012). Hans et al., (2006), Anderson et al., (2011), asserted that collaborative
programming of construction activities reduces incidences of change in orders,
delays, rework, non-value adding activities, and litigation at the construction phase.
Furthermore, Hans et al., (2006); Ballard and Howell, (2004); Ballard and Howell,
(1998) stressed that in collaborative programming, planning activities and tasks must
be done in detail and collaboratively with the team. This will make the construction
programme transparent, reliable, and predictable.
Literature Review Chapter Four
73
Process of Phase Planning
Adequate collaborative programming of construction activities adds value to the
entire project delivery process (Mossman, 2014). This is because the client
requirements are most times clearly defined and the supply chain proposals are
constantly deliberated on to arrive at best optimal solution. Ballard and Howell,
(2004) identified eleven key processes in developing a Phase Scheduling or
collaborative programming which must be done collaboratively by those required to
do the work.
1. Define the work to be included in the phase
2. Determine the completion date for the phase
3. Use team planning notes to develop network of activities
4. Apply duration to each activities
5. Re-examine logic to shorten the duration
6. Determine the earliest start date for the task
7. Decide on activities to buffer by asking
a. Which activity duration are most fragile
b. Rank order the fragile activities by degree of uncertainties
c. Allocate available time to the most fragile activities.
8. Remember the contingency is meant to be spent
9. Check to be sure the teams are comfortable with available buffers, if not re-
plan or shift milestones
10. If there is time in excess, accelerate the schedule or use it to predict on-time
completion
11. Reverse unallocated time in a general contingency buffer for the phase.
This approach provides opportunity for the subcontractors and the suppliers to
participate meaningfully in developing the overall programme for the project, thus
gaining their commitment.According to Ballard and Howell, (2004) the process is
used in producing a plan that is mostly based on team approach and uses reverse
phase scheduling.
4.3.2.3 Look-Ahead Planning
The look-ahead planning is a medium term plan for project activities and is developed
from the collaborative programme. Usually, tasks that will occur within three to six
weeks in the look-ahead window will be screened for constraints in all eight flows
Literature Review Chapter Four
74
including information, permissions, resources, space etc. The project team members then
identify every constraint for the proposed assignments for action in the make-ready
process (see below). In doing this, the problems that could affect the task negatively will
be identified so they can be removed before the commencement of the task, thus
eliminating delays and waste from the production process (Zimina and Pasquire, 2012;
Porwal, 2010; Ballard, 1997).
However, in the traditional way of managing projects, the look-ahead plan (master
programme) only provides advance notice of the start date of an activity and does not
consider work flow sequence, matching work flow with capacity, or maintaining a
backlog of workable activities (Ballard et al., 2009). In implementing the LPS, the
purpose of the look-ahead planning is: (1) to create workflow between activities in the
project (2) to ensure that the available labour and resource matches the work (3) to
ensure prerequisite tasks are completed as planned (4) to group works that are closely
related together for easy execution and (5) to identify tasks that need to be planned
together. In this way, constraints to all eight flows are properly recognised to enable
effective “make-ready” and eliminate the waste of making do (Koskela 2004).
4.3.2.4 Make-Ready Process
The make-ready process is used to eradicate the constraints to planned activities
identified in the look-ahead programme before they pass into production on site. The
make-ready process focuses on matching the available resources for work with the
present realities on the construction site, so as to ensure production can proceed at an
optimum level (Ballard, 2000, Ballard and Howell, 1998). Daniel et al., (2014b);
Ballard, (2000) observed that the make-ready process helps in controlling the
production system on site. Baldwin and Bordoli, (2014); Ballard, (2000) observed
that most scheduled activities in the traditional approach to planning are not achieved
as planned because they are not “made-ready” before the commencement of the task
on site. The implication of this for the production system is that the expected work
flow will be elusive. Lindhard and Wandahl, (2012) and Koskela, (2000) affirmed
that the lack of flow and the failure in removing constraints from the construction
process generates numerous non-value adding activities in the construction phase.
The goal of the make-ready process is to ensure that only sound activities move into
the backlog of sound assignments for use in the Weekly Work Plan (Mossman, 2014;
Lindhard and Wandahl; 2012, Ballard, 2000). This ensures that only sound works
Literature Review Chapter Four
75
enter the production phase on site. The make-ready process is undertaken
collaboratively so that agreement can be reached on what “Can Be Done” – which
makes it consider all eight flows. The eight flows are the people required to do the
work, the information required for the work, the equipment needed to execute the
work, the material for the work, prerequisite assignment that need to completed,
creating safe external conditions, safe place for work and developing a common
understanding (Koskela,2000; Pasquire, 2012). For an activity to be “made-ready”
for the next work phase, it is expedient these conditions are clearly satisfied.
The impact of the make-ready process is felt across the entire production system. The
make-ready process improves construction planning reliability even on complex
projects by using systematic approaches (Jang and Kim, 2008; Ballard and Howell,
1998,). However, Lindhard and Wandahl, (2012) cautioned that the project planner
must be meticulous in identifying all the necessary preconditions in order to make a
sound activity, else the entire process could be interrupted.
4.3.2.5 Weekly Work Plan (WWP)
Weekly Work Plan is done to review tasks planned in the previous week in order to
plan for the week ahead collaboratively with the team. During the WWP, only
activities that meet the specified criteria and that have been collaboratively
developed from the make-ready process are allowed into production. The criteria
require that work must be 1. well defined (detailed task breakdown), 2. sound (can be
done), 3. sequenced (interdependencies assessed) and 4. properly sized (load matches
capacity) (Ballard, 2000).
Here, the Last Planners that are responsible for doing the work make promises
(commitments) on what “Will Be Done”. The reliability and predictability of the
construction programme is a function of the soundness of works or assignments sent
into the WWP and the commitment of the work force to do them. This approach
requires stakeholders on the project to report the position of the previous week’s
planned tasks. Only a “Yes” or “No” answer is given to indicate if the planned tasks
were achieved or not, whilst also recording the reasons for non-completion. In
recording the reason for non-completion (RNC), 99% completion is a “No” answer.
The RNC enables the team to identify the root causes for the failure. This in turn
enables the team take necessary actions to address the identified reasons for future
Literature Review Chapter Four
76
learning (Mossman, 2014; Ballard, 2000) and for error proofing future activities to
prevent reoccurrence. In practice, the WWP meeting enables each subcontractor or
team leader on site to propose the production plan for the week ahead after
successfully reviewing the previous week’s work plan. This not only enables the
team to understand the interdependencies of tasks (next customer), but also requires
the team to only promise what they are sure they will do, and not what they might or
will try to do (Ballard, 2000).
Daily Coordination
It is part of part the WWP (Ballard, 2015). It is a daily conversation that occurs on
the day of production with the Last Planners either at the start of work or at the end
of work to assess the progress of the planned tasks for the day and review the next
day’s production. Through this meeting, “bad” news is delivered early which
considerably helps in taking mitigating actions to address problems early and
accordingly (Mossman, 2014). The daily coordination meeting could be weekly
during the design stage and daily at the construction stage. The approach is used to
maintain the entire production system thus ensuring the designed or intended output
is achieved at the end of the production process. It is worth noting that the ‘daily
coordination meeting’ is commonly referred to as ‘daily stand up meeting’ among
construction practitioners in the UK (Daniel et al., 2016).
Measurement and Learning
Mossman, (2014) observed that production evaluation and measurement in the LPS
context enables the team to maintain commitment to the overall goal of the project. This
addresses the client’s needs while also making the supply chain aware of what is
required of them. However, to achieve and maintain the commitment requires cultural
shift, especially when LPS is not included in the contract. The key metrics measured in
the LPS implementation are; the Percentage Plan Complete (PPC), Reliability Index
using metrics from Tasks Made Ready (TMR), and Tasks Anticipated (TA) (Hamzeh et
al., 2015; Ballard, 2000). TA is a metric used to measure the performance of the look-
ahead planning process for tasks due to be performed in two to three weeks.
The TMR is the ratio of the tasks that has its constraints removed within two weeks
ahead of execution in relation to all the tasks anticipated in the look-ahead window
(Hamzeh et al., 2015a; Ballard and Howell 2003; Ballard, 1997). Hamzeh et al., (2015)
observed that TA supports in-process performance measurement, however, it is less used
Literature Review Chapter Four
77
or done when compare with PPC measurement on projects that claim to use the LPS in
managing the production process. PPC is used to measure the completed work against
the actual work promised to give an indication of productivity. RNC can be presented
statistically to provide visibility of the frequency and distribution of the factors
inhibiting production.
(𝑃𝑃𝐶) =𝑇𝑜𝑡𝑎𝑙 𝑁𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝐴𝑐𝑡𝑖𝑣𝑖𝑡𝑖𝑒𝑠 𝐶𝑜𝑚𝑝𝑙𝑒𝑡𝑒𝑑
𝑇𝑜𝑡𝑎𝑙 𝑁𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝐴𝑐𝑡𝑖𝑣𝑖𝑡𝑖𝑒𝑠 𝑃𝑟𝑜𝑚𝑖𝑠𝑒𝑑× 100%
In practice, PPC measurement, and recording of RNC not only encourage learning
but also provide a clear indication of productivity (Kalsaas, 2012; Liu and Ballard,
2008). This has been confirmed in Liu and Ballard, (2008) where their study reveals
a strong correlation between PPC and productivity. Ballard, (2000) asserted that the
uniqueness of LPS metric measurement is the learning loop which is embedded in
the system as shown in Figure 4.2. This is contrary to the ‘push’ approach used in
traditional project management which hinders learning.
Figure 4.2: The learning loop in the Last Planner System
Adapted after: Ballard, (2000)
When PPC and RNC are considered together in this way, learning is coupled with
action at the moment, as opposed to at the end of the project. Kalsaas (2012) and
Ballard, (2000) observed that learning is a key element of the Last Planner System
which will further lead to higher productivity of the project team. The measurement
and evaluation process allows the team to have a more transparent and realistic
approach to work as it gives the team opportunity to evaluate the past and
purposively propose the next week’s task (Ballard, 2000).
4.3.2.6 First Run Studies
A First Run Study (FRS) is an approach used to aid understanding of the
construction process before actual production or execution on site. It is used in the
Literature Review Chapter Four
78
redesign of activities that are considered to be critical in the production process
which may also be repetitive in nature, for instance, a prototype building (Ballard
and Howell, 1998). However, Mossman, (2014) argued that FRS is not limited to
repetitive tasks alone, but on all activities that are critical to the success of the project
in terms of time, quality, cost, and safety. In the UK, this process is commonly called
Mock-up or Prototype among others. The process encourages continuous
improvement and allows standard works to be developed and constraints to be
identified. Hackett and Pasquire, (2014) identified Virtual First Run Studies (VFRS)
as a form of “Proof of production” based on collaboration and discussion in advance
of the physical First Run .
According to Salem et al., (2005) FRS is an approach that encourages continuous
improvement which entails productivity studies, understanding work method and
redesigning the different action in the production process collaboratively by the
team. In practice, FRS is based on the Plan-Act-Check-Do cycle (Shewart and
Deming, 1939). This allows the team, through collaborative conversations to
brainstorm, explore opportunities, and identify the best approach to deliver the
product more efficiently before the actual production. This approach enables the
team to understand the construction process and what is required of them at each
stage beforehand. In addition, it helps in driving out non-value adding activities and
maintaining quality of the finished product.
The LPS implementation processes as discussed enables all stakeholders on the
project to develop a collaborative relationship during the planning and execution of
tasks on site. In fact, Daniel et al.,(2014b) and Mossman, (2014) described the LPS
implementation process as a set of social conversations that enables the team to build
trust and commitment, thus making the construction programme more predictable
and reliable. Various theories have been used to explain the working of the LPS in
managing project production system as discussed in the next section (Ballard et al.,
2009; Macomber and Howell, 2003; Koskela, 1992).
4.4 Theories used in Explaining the Last Planner System
The LPS practice revolves around planning, execution, and control. Koskela and
Ballard, (2006); Macomber et al., (2005); Macomber and Howell, (2003) Koskela
and Howell, (2002) analyse the theories that support the practice of the LPS in
Literature Review Chapter Four
79
construction. Table 4.1 presents construction project management practices and the
theories that explain them in relation to the LPS approach.
Table 4.1: Underlying Theories of the Last Planner System
Subject of Theory Practice Theories Further supportive
literature
Project Transformation
Flow Koskela, (1992)
Management
Planning
Management-as-
planning
Management-as-
organising
Hayek,(1945)
Johnston and
Brennan, (1996)
Execution Language/action
perspective
Flores, (1982);
Winograd and
Flores, (1986)
Control
Scientific
experimentation
model
Shewhart and
Deming (1939)
Adapted from: Koskela and Ballard, (2006)
4.4.1 Transformation and Flow Theory in the Last Planner System
Koskela developed the Transformation Flow and Value(TFV) theory mostly referred
to as TFV theory (Koskela, 1992). It has been observed that the current approach
used in managing construction project tends to support only the transformation view.
The transformation view focuses on the conversion of input into output with less
regard to what happens in the project environment (Koskela and Howell, 2002). In
this approach, it is assumed that the tasks are independent and that requirement for
the execution of tasks can be captured completely at the outset of the project (Ballard
and Howell, 2004; Koskela and Howell, 2002). However, such view is false and
counterproductive due to the uncertainty and variability inherent in the construction
environment.
In view of this, Koskela and Howell, (2002) proposed that the Flow and Value
concept should be added to the Transformation concept on which the current theory
of project management is conceptualised. The understanding and usefulness of the
flow concept has been demonstrated in the LPS (Bertelsen et al., 2007; Koskela and
Howell, 2002). The LPS uses the flow concept to identify and ensure task
preconditions are satisfied before sending them to the work phase. It ensures that the
seven plus one conditions for smooth workflow are fulfilled (Pasquire et al., 2015;
Literature Review Chapter Four
80
Bertelsen et al., 2007). This implies that the flow theory recognises the complexity
and uncertainty inherent in the construction production environment, while the
transformation view does not. Koskela, (2000) observed that the limited view on the
production system in construction is one of the major issues facing construction.
4.4.2 Management-as-Planning and Management-as-Organising Theory
in the LPS
The management-as-planning (MAP) theory dominates the current approach used in
construction planning. The theory advocates that project consists of two parts; “the
managerial part” (the planner who does the planning) and ‘the effector part” (field
workers) who are responsible for translating the plan into action (Johnston and
Brennan, 1996). Koskela and Howell, (2002) observed that the management-as-
planning theory advocates for plan centralisation, revision of plan and then
implementation. This implies that in this approach, field workers are not involved in
the planning at the beginning although they could be during revision. To overcome
this, the management-as-organising (MAO) view is presented (Johnston and
Brennan, 1996; Johnston, 1995). In this approach, it is believed that each sub-unit in
the system has the capacity to plan, sense and act, thus, the planning decision should
not be left with “the managerial part” alone. In construction, this approach supports
the inclusion of the supply chain in the planning process as demonstrated in the LPS.
The MAO theory also aligns with the position of Hayek (1945) on social planning
where he argued that the knowledge needed for planning is dispersed among the
people doing the work. Apparently, this view supports and further shows the need for
the planner to involve subcontractors, foremen, and site engineers in developing the
construction programme. This will not only provide an opportunity for the people
doing the work to do the plan, but will also lead to the development of a more
realistic and predictable plan which the LPS supports (Koskela and Ballard, 2006;
Koskela and Howell, 2002).
4.4.3 Language/Action Perspective Theory in the Last Planner System
In the conventional project management approach, the nature of communication that
occurs at the execution stage on site is one-way, and is characterised by lack of
commitment. As compelling as this may seem, it is contrary to the nature of
conversations that occur in the LPS; which is usually in two ways. The work of
Literature Review Chapter Four
81
Flores (1982) on language/action perspective (LAP) which centred around five
conversations; coordination of action, assessment, discourse, trust between workers
and mood explains the nature of conversations that occur in the LPS (Flores, 1982;
Winograd and Flores, 1986). The LAP theory as applied in the LPS has been
evaluated in Macomber and Howell, (2003), and its practical application in
construction was demonstrated in Viana et al., (2011).
According to Macomber and Howell, (2003) LAP supports conversations that could
lead to the development of a reliable promise as encouraged in the LPS approach of
managing production in construction. Viana et al., (2011) confirmed from an
empirical study that LAP supports mutual commitment from project stakeholders.
This is opposed to the dispatch model in conventional project management which
believes that tasks can always be sent to the work phase as soon as the start date is
due without conversation and commitment from those doing the work (Koskela and
Howell, 2002).
4.4.4 Scientific Experimental Model
It has been argued that the “model” of control used in the construction industry is
based on project control rather than production control (Koskela, 2002, Ballard and
Howell, 1998). This approach of managing construction is known as the “thermostat
model”. It emphasises conformity of tasks to plan, not minding the overall effect of
changes on the production system. However, the scientific experimental model of
production control as advocated by Shewart and Deming (1939) identified the cause
of nonconformities to plan and suggested the means to act on them, rather than
pushing the system to conform to the predefined goal. The scientific experimentation
model is the approach used in the LPS. It provides opportunity for the production
system to be evaluated at regular intervals through some metric such as measuring
the PPC; this also encourages learning (Liu and Ballard, 2008; Koskela and Ballard,
2006). In addition, the transformation and flow theories play roles in the LPS at both
the execution and control stages, and specifically, during the short term planning
(Koskela and Howell 2002; Ballard, 2000; Koskela, 1999). The LPS achieves this by
ensuring that planning and execution are fully integrated. These theoretical
conjectures are used to comprehend the current understanding and application of
PP&C principles based on the LPS in the UK construction industry.
Literature Review Chapter Four
82
Amundson, (1998) opined that the use of theory as a lens has the potential to create
an understanding and better development of situational awareness of the problem
under investigation. According to Koskela and Howell (2000), theory enables us to
understand behaviours in the social world thereby contributing to knowledge. This
study deems it important to use the theoretical lens as it will enable it to critically
screen current practices on LPS logically and coherently. In reality, this could lead to
the development of new theories, and confirmation or improvement of existing
theories or practice. Amundson, (1998) asserted that using theories as lens could
guide a study in screening out unwanted practices while identifying new practices,
thus developing more understanding on the research problem. However, the theory
that explains the practice of the LPS in construction is not limited to those described
above.
4.5 Last Planner System Implementation and Developments- Review
of IGLC papers
4.5.1 Overview of the Review
The aim of this review section is to enable the study to understand the extent of
application of the Last Planner® System in construction from previous studies. Thus,
a systematic review of the International Group for Lean Construction (IGLC)
conference papers on LPS implementation reported between 1993 and 2014 and
other publications elsewhere is carried out.
This review not only serve as a solid foundation to the current study which is
exploring the practice of LPS in construction projects, it also enables the study to
compare the reported practices elsewhere with the practices observed in the UK
construction industry. It also supports the LPS-PCA developed in this study. 4The
systematic review identifies the trend in the LPS implementation, LPS
implementation drivers, its success factors, benefits and the reported challenges.
4 Part of this review has been published in Daniel, Pasquire and Dickens, (2015a) Exploring the
implementation of the Last Planner® System through IGLC community: twenty one years of
experience
Literature Review Chapter Four
83
4.5.2 Review Framework
The framework for the review is based on the approach recommended for content
analysis by Berg and Lune (2011) and Robson (2002) as shown in Figure 4.3. Berg
and Lune (2011) asserted that content analysis is applicable in any field of human
communication such as written documents, audio and video information, and it has
been used in various fields for research, including construction management (Jacob,
2010). Content analysis is used in research to achieve the following: (1) identify
cultural trend in a group, institution or society (2) show trend in communication
contents (3) identify response to communication (4) identify propaganda in
information content and (5) show focus in communication by group, institution or
society (Weber, 1985). Again, this shows that the choice of content analysis for this
study is not only appropriate, but also robust.
Identify the
reseach question
Sampling strategydefine recording
unit
construct
categories for
analysis
sort data into
categories/
counting
Consider
pattern and
relate to theory
How has the Last
Planner System
developed and
implemented
globally
IGLC conference
papers between
1993 and 2014
IGLC LPS
implementation
conference papers
between 1993 and
2014
LPS Component
LPS trend
Research method
Counting of
recorded texts and
descriptive analysis
Findings,
recommendation and
conclusion based on
existing literature and
theory
Figure 4.3: The review framework
(Adapted after Berg and Lune (2011) and Robson (2002))
The sample was arrived at through reading on the topic, abstracts of various sections
and using keyword searches. These include publications from the production
planning and control section; the case study and implementation section among
others. Keyword searches such as Last Planner System and case study were made on
the database in each publication year. This approach was used to avoid omission of
papers on LPS implementation. Based on this, a total of 57 publications from 16
countries that reported LPS implementation were retrieved from www.iglc.net as
shown in Table 4.2. Of these, 42 reports contained implementation on sites, 4 on
design, while 11 show no actual implementation. The 42 studies that reported LPS
Literature Review Chapter Four
84
implementation on construction sites were analysed. The selected papers were read
thrice, with a focus on obtaining information on the stated objectives. The table also
shows the list of the papers retrieved.
Table 4.2: IGLC Papers on LPS Implementation between 1993 and 2014 Retrieved
S/NO Year of
publication
Author(s)
1 1993 Ballard
2
1994
Howell
3 Ballard
4 Ballard
5 1996 Ballard et al.
6 1997 Ballard
7
1998
Junior et al.
8 Conte
9 Miles
10 1999 Mendez and Heineck
12
2002
Ballard et al.
13 Fiallo and Revelo
14 Soares et al.
15 Alarcon et al.
16 Conte
17 2003
Johansen and Porter
18 Mastroianni and Abdelhamid
19
2005
Kim and Jang
20 Alarcon et al.
21 Bortolazza et al.
22
2006
Kim and Jang
23 Knapp et al.
24 Lim et al.
25 2007
Kim et al.
26 Ansell et al.
Literature Review Chapter Four
85
27 Kemmer et al.
28 2008
Aslesen and Bertelsen
29 Hamzeh et al.
30
2009
Kalsaas et al.
31 Alsehaimi et al.
32 Hamzeh et al.
33 Olano et al.
34 Ballard et al.
35 Liu and Ballard
36 2010* Skinnarland and Yndesdal
37
2011
Viana et al.
38 Rosas et al.
39 Hamzeh
40 Aves and Britt
41
2012
Samudio and Alves
42 Kerosuo et al.
43 Hamzeh et al.
44 Skinnarland
45 Porwal et al.
46 Adamu and Howell
47
2013
Drysdale
48 Barbosa et al.
49 MCconaughy and Shirkey
50 Fauchier and Alves
51 Aihaikwo et al.
52 Zegarra et al.
53 Fuemana, and Puolitaival
54 Cerver-Romeno et al.
55 Kalsaas
56 2014
Kalsaas et al.
57 Fundi and Drevland
Source: Author’s review of IGLC paper on LPS implementation
Literature Review Chapter Four
86
(*link not working as at the time of the review)
4.5.3 Last Planner System Implementation across Countries
Table 4.3 presents a glossary view of the LPS implementation in construction across
the globe. The study reveals that the uptake of the LPS is not limited to North
America alone, as implementation has been reported in almost all the continents of
the world. This shows the universal applicability of the LPS; overcoming language
and geographical barriers.
However, it is worth noting that cultural barriers such as attitude to work could
influence the LPS implementation (Johansen and Porter, 2003). To be specific,
Johansen and Porter (2004) revealed from their study that cultural and structural
issues are among the barriers to LPS implementation in the UK construction
industry.
Table 4.3: Last Planner System Implementation across Countries
Country Number of cases
USA 15
Brazil 10
Norway 5
Venezuela 5
UK 4
Chile 4
Korea 3
Nigeria 2
Finland 2
Lebanon 1
Peru 1
Mexico 1
Ecuador 1
India 1
Saudi Arabia 1
New Zealand 1
Total 57
Literature Review Chapter Four
87
Source: Author’s review of IGLC paper on LPS implementation
4.5.4 Major Components of Last Planner System Implemented
As shown in Figure 4.4, measuring PPC, Weekly Work Planning (WWP) meeting,
and recording reasons for non-completion (RNC) are among the commonly
implemented components of the LPS in the IGLC papers reviewed. This finding
aligns with recent empirical findings such as Dave et al., (2015) where they observed
that WWP was the most commonly implemented LPS element from the evaluation of
five projects and a detailed case study. Daniel et al., (2015) also observed that phase
planning/collaborative programming, PPC measurement, and WWP meetings were
the most fully implemented LPS elements from their evaluation of 15 construction
projects in the UK. The frequent reporting of the measurement of PPC in the studies
reviewed seems to show PPC measurement is among the early indicators of LPS
implementation in construction.
Figure 4.4: Components of LPS reported in the review
Source: Author’s review of IGLC paper on LPS implementation
Ballard (2000) asserted that PPC measurement supports continuous improvement as
it allows the team to learn from the reasons for non-completion. These are collected
at the WWP meetings which is part of the PPC measurement process. This implies
0 10 20 30 40
First Run Studies
Visual management
Consideration for flow
Preparing workable Backlog
Daily Huddle Meeting
Collaborative Programming/ Phase Planning
Use of Master Programme
Taking action to correct RNC
Constraint analysis/ Make Ready process
Lookahead (6-8 weeks)
Populating and RNC
Weekly Work Plan meeting
Measuring PPC
Number of studies
Literature Review Chapter Four
88
that the PPC measurement does not only show plan reliability, but also other project
performance indicators such as productivity (Liu and Ballard, 2008).
4.5.5 Trends in the Implementation of LPS Components
The review of the IGLC papers indicates that the LPS elements implemented were
not consistent across all the years. This could be due to the evolution of the LPS over
this time. For instance, phase scheduling/collaborative programming became
prominent after 2000. This could be due to the publication of a white paper by LCI in
2000 to back its use (Ballard, 2000). Furthermore, the review reveals a progressive
increase in the use of most of the elements in recent years, as shown in Figure 4.5,
with few exceptions such as workable backlog and FRS. This confirms that the
implementation LPS’s elements is growing (LCI, 2015).
However, the extent of the implementation of these reported elements (i.e. in terms
of partial or full implementation) still remains an issue to contend as recent empirical
studies have shown some of these elements are not fully implemented as claimed.
Figure 4.5: Trend in LPS Elements Implemented across the Years
Source: Author’s review of IGLC paper on LPS implementation
4.5.6 Last Planner System Implementation Success Factors
Hamzeh and Bergstrom (2010) identified harnessing the support of the project
owner, training and retraining of workers, developing a clear vision, having internal
champions, and mapping the current planning process as factors that contribute to the
success of LPS implementation in construction. Similarly, Ballard et al., (2007)
0
10
20
30
40
50
60
1993 1996 1998 2000 2003 2006 2008 2010 2012 2014
Taking action to correct RNC
Populating and RNC
Measuring PPC
Daily Huddle Meeting
Weekly Work Plan meeting
Consideration for flow
Visual management
First Run Studies
Preparing workable Backlog
Constraint analysis/ Make Ready process
Literature Review Chapter Four
89
identified LPS implementation success factors from their implementations
experience in seven construction organisations. The factors include; provision of
training at the project and field level, developing lean champions, top management
commitment, use of contracts that favour collaboration, use of demonstration
projects, collaborative involvement of all the stakeholders, use of long term alliance
and team building exercises.
Furthermore, a comprehensive and systematic review of LPS implementation case
studies published by the IGLC between 1993 and 2014 carried out in this study
reveals about 15 LPS success factors as presented in Figure 4.6.
Figure 4.6: Last Planner System implementation success factors in construction
Source: Author systematic review of IGLC papers on LPS implementation
The review reveals training, management support, and early involvement of
stakeholders are among the most emphasised LPS success factors for LPS
implementation in construction. This finding is further confirmed by the studies of
Hamzeh, (2011) and Ballard et al., (2007). This does not imply that other factors are
not crucial, as all the above mentioned factors are needed for the successful
implementation of the LPS in construction. However, the emphasis on the factors by
these studies could be due to their capacity to support the success of the other
identified factors.
2 2 2
4
5
7
7 8 9
9
13
13
17
24
DisciplineCompanies-institutionresearch partnership
Incremental implementation
Prior academic and practiceknowledge of LPS by project…
Focus on flow
Plan ownership defined
Formation of internalchampions
Adopting procurement routethat favours collaboration
Continuous coaching andmonitoring of the process
Communication of results
Early understanding of projectgoal by the team
Employees and supply chainengagement
Management support
Training on LPS principles andearly stakeholder engagement
0
5
10
15
20
25
Literature Review Chapter Four
90
4.5.7 Last Planner System Implementation Drivers
Ballard et al., (2007) identified the following drivers for the implementation of LC
techniques in construction; (1) Owner and client demand, (2) internal demand for a
better way of working (3) desire to reduce stress on project managers (3) desire to
reduce variation and waste and (5) desire to improve communication with project
team. Additionally, Ogunbiyi, (2014) identified drivers such as the need to meet
customer or client expectation, gaining a competitive edge, and the desire for
continuous improvement.
This suggests that the drivers for implementing LC techniques such as LPS could be
viewed from two perspectives; external drivers and internal drivers. For example, the
demand from the owner or client for LPS implementation is externally motivated.
While factors such as the desire for LPS implementation for better way of working
for enhanced performance, the desire to improve communication between project
teams, and desire for continuous improvement could be viewed as internal drivers,
since they can be initiated by supply chain organisations. This shows that the driver
for LPS implementation is not from client alone, but it could also come from the
contractor’s quest for continuous process improvement.
4.5.8 The Impact and Benefits Last Planner System on Construction
Process Improvement
Lean construction (LC) researchers have observed that the implementation of LC
techniques support construction process improvement (Adamu and Howell, 2012;
Ballard, 2000). In recent times, the implementation of the LPS in construction is on
the increase, this could be due to its benefits (LCI, 2015; Daniel et al., 2015).
Mossman, (2014) asserted that the LPS helps in creating overriding improvement in
project programme predictions, productivity, reduces project time and site accidents,
increases profit, while giving due consideration to employee satisfaction. Fernandez-
Solis et al., (2012) also identified 9 major benefits of implementing LPS in
construction from the review 26 case studies projects where the LPS was
implemented. The LPS benefits identified from the study are; increased work flow
reliability, improved supply chain integration, reduced project delivery or production
time, improved communication among project participants, less firefighting or fewer
day-to-day problems, improvement in quality of work practice at construction site,
Literature Review Chapter Four
91
enhancement of managerial practices in construction projects, knowledge expansion
and learning among project teams and reduced stress levels on construction sites.
Their study was only based on selected case study projects where the LPS was
implemented between 2000 and 2009.
Also a review of IGLC papers in this thesis identifies 13 benefits of LPS
implementation as shown in Figure 4.7. The figure reveals that LPS implementation
supports the development of reliable and predictable programme, improves
workflow, and develops common understanding of the project goal among others.
Figure 4.7: LPS Implementation Benefits in Construction
Source: Author’s review of IGLC paper on LPS implementation
This shows that LPS implementation in construction has the potential to maintain
stable workflow. According to Ballard, (2000) the goal of the LPS is to stabilise the
production process. However, workflow reliability in the construction industry is still
very low in the traditional approach of project management (Ballard, 1999).
4.5.9 LPS Implementation Challenges in Construction
Researchers in LC have attempted to underscore the implementation challenges of
LPS in construction (Ballard, et al., 2007; Hamzeh, 2009; Porwal,et al., 2010;
Fernandez-Solis et al., 2014). For example, Porwal et al., (2010) identified 12 major
challenges associated with LPS implementation as observed from previous studies
between 2002 and 2009. The study revealed that lack of training and resistance to
0 5 10 15 20
Makes organisation more competitiveSecure client confidence in the team
Enhanced learningProvide early signal of deviation from plan
Improved coordination of project stakeholdersBetter resource allocation
Reduced adversarial relationshipImproved quality/performance
Developed common understanding of the projectProgramme reduction and early delivery
Ehanced commitment from the teamImproved construction workflow
More reliable and predictable programme
Number of occurence in the studies
Ben
efit
s id
enti
fiel
d f
rom
th
e p
aper
s an
alys
ed
Literature Review Chapter Four
92
change are among the commonly reported challenges in the studies presented.
Furthermore, in a related study, Fernandez-Silos et al., (2012) identified 13 specific
LPS implementation challenges from the review of 26 case studies. The topmost
implementation challenges from the review were resistance to change, lack of
commitment to LPS, lack of training and experience, and lack of management
support among others.
It is worth noting that some of the LPS implementation challenges identified in
Porwal et al., (2010) were also identified in Fernandez-Solis et al., (2012). This
shows that the implementation challenges identified by Porwal et al., (2010) are
valid and more needs to be done to overcome them.
Hamzeh, (2009) also classified the LPS implementation challenges into local factors
and general factors. The local factors relate to the project related challenges while the
general factors are those relating to the organisation implementing the LPS. This
implies likely strategies for overcoming LPS implementation should take due
consideration for these classifications. According to Liker, (2004) in implementing
lean, the organisation must be willing to change and the people (workers) must be
ready to accept the new approach for the needed change to happen.
Figure 4.8 indicates recent findings on LPS implementation challenges in
construction from a systematic and comprehensive review of IGLC papers conducted
in this research. The findings in this present study presented in Figure 4.8 and those
from previous studies such as Fernandez-Solis et al., (2012) and Porwal, (2010)
show the need for training to improve on LPS implementation. Liker in his book The
Toyota Way highlighted the need for training in its 9th
principle (Liker, 2004). The
principle states that “Grow leaders who thoroughly understand the work, live the
philosophy, and teach it to others”. Training as emphasised here is not just in having
mere technical knowledge of the LPS process, but rather, a mind-set change training,
which could further help in overcoming some of the other identified challenges.
Literature Review Chapter Four
93
Figure 4.8: Last Planner Implementation Challenges in Construction
Source: Author’s review of IGLC paper on LPS implementation
This shows that any organisation seeking to deploy the system across its business
must be committed to training at all levels. According to Fernandez-Solis et al.,
(2012) developing human capital within the organisation will enable the organisation
to implement LPS effectively. Loosemore et al., (2003) also argued that the best
investment to improve the construction industry should be in human resource
development. However, as crucial as training is to LPS implementation, it is initially
an additional cost to the organisation even though it can be offset by improved
performance.
4.5.10 Past and Current Developments in the Last Planner System
Figure 4.9 shows the timeline of the developments in the LPS. According to Glenn
Ballard, one of the inventors of the Last Planner System (LPS), an earlier study on
Crew Planning in the 1980s was a precursor to its development (Ballard, 2015a). At
that time, Glenn was the Productivity Improvement Manager for Brown & Root’s
Construction in the US. Some key LPS principles such as ‘make ready’ and
‘shielding workers from bad assignments’ were practiced then.
While this and other studies contributed to the emergence of the LPS, it took another
10 years before the “Last Planner System” formally emerged as a system for
0 5 10 15 20 25
Low understanding of LPS concept and principles
Use of incompatible procurement strategies
Lack of link between commitment planning and…
Lack of shared understanding of the project goal
Inadequate planning skill
Use of adhoc personnel s as Last Planners
Combining contract management with production…
Resistance to change
Cultural and structural issues
Short-term vision
Parallel implementation
Low commitment from subcontractors and LP
Short project duration
Partial involvement of stakeholders
Lack of plan ownership
Linking LPS implementation with cost
C h a l l e n ge s o f L P S i m p l e m e nt a t i o n o n s i t e a s r e p o r te d i n I G L C c o n f r e n c e p a p e r s ( 1 9 9 3 - 2 0 1 4 )
Number of occurrence in papers
Literature Review Chapter Four
94
managing production in construction (Ballard, 2015a; Daniel et al., 2015; Ballard,
1993). It shows that Glenn Ballard and Gregory Howell’s consulting work in the
industrial construction sector led directly to the development of the LPS in the early
1990s (Daniel et al., 2015; Ballard and Howell, 1998). The timeline reveals that the
LPS did not emerge from the Toyota Production System, rather, it is an approach
developed by construction practitioners specifically for the construction industry.
The initial principles of the LPS were to: (1) improve workflow and (2) improve plan
reliability and predictability (Ballard, 2000; Ballard and Howell, 1998). These
principles have not changed but the list of LPS principles have been supplemented
over time with on-going research and development.
The history of the LPS would be incomplete without mentioning its early marriage
with Lauri Koskela’s seminal work in 1992
on the application of production
principles in construction (Ballard, 1993; Koskela, 1993). This union created the
field now known as ‘Lean Construction’ and led to the formation of the International
Group Lean Construction in 1993 with its inaugural conference held in Espoo,
Finland (Ballard, 1993). The term “Last Planner” was first mentioned at this
conference and published in the Proceedings (Ballard, 1993). Early experimentations
and implementations of the LPS on construction projects occurred between 1993 and
1994, with a full implementation of the system carried out on a major refinery project
in Venezuela between 1995 and 1996 (Ballard and Howell, 1998; Ballard, 1993).
Literature Review Chapter Four
95
2001-2007
Addition of
Phase planning/
collaborative
programming to
the LPS
The Last
Planner
System and its
integration
Initial
research and
development in
production
management systems
in construction by
Ballard and
Howell
Implementation
and first data
collection on Last
Planner System in
construction by
Ballard and
Howell
Consulting
and research
work in
industrial
construction
sector by
Ballard and
Howell
The term ‘lean
construction’
was coined by
IGLC following
the work of Lauri
Koskela on the
application
production to
construction (
Koskela, 1993;
Ballard, 1993)
1993 IGLC formed
1993 Ist IGLC conf.
in Expoo, Finland
1993 First mention
and publication on
‘Last Planner’
1994 2nd
IGLC
devoted to
publication on last
planner
1992 1993-1994 1995-1996
Further
research and
implementation
of last planner
on larger
projects
1995 Full
implementation on
refinery expansion
in Venezuela
1995-1996
Implementation for
specialist
contractor
Used to evaluate
the PCS on a
chemical plant
construction
project
1996 detail
specification for
Look-ahead
planning
1996 linking of
Look-ahead
Planning to
Make Ready
process
Case study that
shows the
impact of Look-
ahead Planning
PPC
improvement
Some
development
in lookahead
planning
2000 Publication
of the white
paper on Phase
planning by LCI
(Ballard, 2000a)
2000 Professor
Ballard complete
a PhD thesis on
the LPS
(Ballard, 2000)
LPS update on
phase planning
(Ballard and
Howell, 2003)
2000-2003
Sacks et al (2009)
proposal for the
integration of the LPS
and BIM
(Bhata and Leite,
2012) implemented
LPS & BIM
Tasks Anticipated and
other LPS metrics
(Hamzeh and
Langerud, 2011
LPS and Location
based management
system (Seppanen et
al, 2010)
Look-ahead Planning
framework( Hamzeh
et al , 2012)
LPS theories
and other
development
in the LPS
(Koskela and
Howell, 2002)
(Koskela and
Ballard, 2006)
(Abdelhamid et al,
2010)
LPS and
productivity( Liu
and Ballard, 2008)
Production control
principles( Ballard
et al, 2009)
LPS Workbook(
Ballard et al,2007)
2009-2013
Further
development
in the Last
Planner
System
2013 -2015
LPS benchmarking(Ballard,
2015)
LPS and Takt time planning
(Frandson et al, 2014)
Geometrical increase in
implementation, (LCI, 2015)
Understanding Task
Anticipated in LAh using
simulations (Hamzeh et al
2015)
LPS and Visual
Management- vPlanner
(Ghafari, 2014)
Ballard (1997)Ballard (1993)
Ballard and Howell,
(1998)
Ballard, (1993)
Ballard
(1993)
Ballard and
Howell,
(1998)
LPS Last Planner System
PCS Production control systems
LCI Lean construction institute
PPC Percentage Plan Complete
IGLC International Group for Lean
Construction
BIM Building Information Modelling
Abbreviation key
19971990's
Language Action Perspective
(Macomber and Howell, 2001)
© Daniel, 2016
Figure 4.9: Timeline highlighting major developments in the Last Planner System
96
How it has Developed
Figure 4.9 reveals that various developments have occurred over time. For instance,
in 1996, the link between look-ahead planning, the make-ready process, and the
impacts of look-ahead planning in improving the PPC was first discovered and
incorporated into the LPS. In terms of research, the most influential publication is
Glenn Ballard’s PhD thesis “Last Planner System of Production Control” published
in 2000. A recent Google scholar search showed 909 citations of this work (Google
scholar, 2016), the most cited publication on the LPS to date. Ballard’s thesis has
informed research into the LPS in both industry practice and academic activity. It is a
core part of the Lean Construction education for undergraduates, Masters students,
and PhD scholars around the world.
The figure also shows how theory can be used to underpin the system and explain
how it works. Some of the studies that exemplify this include: the work of Lauri
Koskela on the TFV (Transformation Flow Value) model of production (Koskela
2000), language action perspective (Macomber and Howell 2003), and the
development of production control principles (Ballard et al., 2009) to mention a few.
The LPS has also been integrated with other systems such as Building Information
Modelling (BIM), Location Based Management System, Takt Time planning and
visual management. Several commercial software products have also been developed
based on the LPS.
In terms of implementation, there has been an exponential increase in LPS
implementation (LCI, 2016) in the construction industry with written evidence of
LPS implementation in 16 countries and in all the major continents of the world
(Daniel et al., 2015). Currently, Glenn Ballard is creating a LPS benchmark with
inputs from both industry practitioners and academics around the world (Ballard,
2015). The goal of the benchmark is to: list the current best practices of the LPS,
provide Q&A to common questions on the LPS, give organisations the ability to
measure their implementation of the LPS relative to the ideal state, and standardise
the language used by the industry when referring to different components of the LPS.
Literature Review Chapter Four
97
4.6 Summary of Chapter
This chapter examined the evolution of production planning and control in
management science, lean production and its eventual application in construction as
demonstrated in the LPS of production control. The review indicates that the concept
of production planning and control (PP&C) dates back to the work of a scientific
management theorist, Frederick Taylor, and this idea was formally put forward after
the World I with the aim of improving efficiency in the production line. The chapter
showed that this approach is used extensively in the manufacturing industry as
demonstrated in the lean production approach used in the Toyota production System.
However, the application of lean production principles into construction was based
on the seminal work of Koskela in 1992, which is not without criticism.
The chapter established that the LPS is a PP&C methodology for managing project
production in construction, a system developed by Ballard and Howell from research
in the industrial construction sector. The chapter reveals that the LPS supports the
development of collaborative relationship among construction stakeholders through
the key components when implemented holistically. It also shows that the success of
the LPS in construction has been explained with robust theories. This is opposed to
the theory, if any, on which the traditional project management is built on. The
chapter demonstrates that the LPS has developed in terms of its level of
implementation, theory development, and is now used as a vehicle to improve
construction management practice in different parts of the world.
The chapter established that despite the initial criticism of the application of lean
techniques in construction, the implementations of the LPS (a lean technique) in
managing production in construction is on the increase. The review indicates that it
has been implemented across 16 countries which cut across the major continents of
the world. The review shows that the LPS is not static, but has evolved greatly in
managing production in construction as demonstrated in its successful integration
with other emerging concepts such as BIM, and vplanner.
Also, the trend in the implementation of its elements, progress in research, and
building practice on sound theory among others attest to its development. The
chapter reveals the drivers, benefits and the challenges for implementing the LPS in
construction from the review of IGLC conference papers on LPS implementation
Literature Review Chapter Four
98
between 1993 and 2014. This chapter presents a global perspective on LPS
implementations in the construction industry and its influence on construction
process improvement. The LPS has shown its potential to improve construction
projects’ cost, schedule, productivity, and safety.
Many researchers from around the world are actively conducting research on the LPS
and new findings are continuously integrated into the LPS. Currently, the LPS is
being benchmarked with input from across the world, the participants are drawn from
both industry and academia. The intention for this is to reflect on the initial
framework and to correlate that with current practice in the industry in order to
strengthen its application and influence.
99
CHAPTER FIVE: RESEARCH
METHODOLOGY AND DESIGN
5.1 Introduction
The previous three chapters (2, 3 and 4) presented the depth of literature covered in
this study, and have thus been used as the basis to consider how the research should
be carried out. This chapter presents a detailed account on the research methodology
and design used in capturing the evidence used in answering the objectives proposed
in chapter one. The chapter critically examines the philosophical assumptions and the
research paradigm adopted for the study. It further justifies the chosen paradigm used
in the study. In the chapter, the research strategy and methods were critically
examined, and justification for the choice of mixed research method is presented.
The chapter also presents the overall research design and discusses the five major
stages involved in the study in detail. The measures taken to ensure that the data
collected were valid and reliable are also examined in the chapter. Sections 5.3 and
5.4 centre on the research philosophy and paradigm, while sections 5.6 and 5.7
present the research strategy and justification for the methods. Furthermore, section
5.8 provides a detailed account of the six major phases of the research, while sections
5.9 and 5.10 discuss the quality of the research and the chapter summary
respectively.
5.2 Understanding Research Methodology and Methods
It has been observed that the success of every research lies on the appropriateness of
the research methodology and methods used in the investigation. However, as
important as they are, some researchers misuse these terms which further affect its
application in the study. Henn et al., (2006) observed that it is vital to understand the
difference between research methodology and research methods from the onset as it
will help in designing the research process. Fellows and Liu (2008) defined “research
methodology as procedures of logical thought process that applies to scientific
investigations while research method refers to the specific techniques that are
available which are actually used in conducting the research”. Collis and Hussey
(2003) also concluded that research methodology is the sum of the approaches and
Methodology Chapter Five
100
perspectives used in the research process that focuses on stating the reason for data
collection, what data need to be collected, where to collect the data, how to collect
the data and how these data will be analysed, while research methods are the specific
tools used in collecting and analysing the data.
Dainty (2008) argued that the success of a social science research is not just in
selecting the methods but rather on the philosophical assumptions considered in
selecting the methods. Furthermore Henn et al., (2006) asserted that research
philosophy influences the choice of research strategy and methodology.
5.3 Research Philosophy
It is vital to clarify the issue of research philosophical position as this is very crucial
in determining the right methodology and methods to be used in carrying out an
investigation. The two major schools of thought on research philosophy are
epistemology and ontology (Saunders et al., 2012; Bryman, 2012; Henn et al., 2006),
and they are housed in the outer layer as shown in Figure 5.1. In Figure 5.1, the outer
layer (research philosophy) is the shell shielding the entire research process.
Figure 5.1: The relationship between research philosophy and methods
Source: Adapted from Sanders et al., (2012)
Research philosophy
Research methodlogy/
approach
Research methods/ strategies
Data collection techniques and
analysis
Methodology Chapter Five
101
The implication of this is that without proper positioning or establishment of the of
the research philosophy, i.e. the outermost layer, the remaining layers in the research
framework cannot be accessed or achieved. According to Saunders et al.,(2012) and
Henn et al., (2006), research philosophy determines the acceptable knowledge and
the processes to undertake in order to answer the research question. However,
Johnson and Clark (2006) cautioned that the focus of the researcher should not be
only on ensuring that the study is philosophically informed; but should be able to
reflect on the chosen philosophy and as well justify why the alternate philosophy is
not chosen. Thus, the two research philosophical positions are considered.
5.3.1 Ontology
Every research has its own ontology. Ontology is concerned with the assumptions
and claims the researcher made about knowledge that exists out there, with focus on
the form in which the knowledge exists, the different parts that make up the
knowledge and how they interact (Saunders et al., 2012; Blaikie, 2007). Creswell,
(2013) and Ritchie and Lowis (2003) submitted that ontology is concerned with
understanding the social world and its characteristics. The goal of ontology is to
identify the knowledge that exists out there and how they can be presented. Different
ontological positions have been identified in the literature. Easterby-Smith et al.,
(2012) identified four positions which include; realism, internal realism, relativism
and nominalism while Ritchie and Lowis (2003) identified three major positions
which are; realism, materialism and idealism.
According to Easterby-Smith et al., (2012) and Richie and Lowis (2003), realism is
the belief on the existence of only one truth and on external reality of the world
which is independent of people’s view or belief. Relativism on the other hand is a
belief that truth should not be validated on the basis of the process used in
ascertaining it and that there are many truths while the nominalism position argues
that there is nothing called reality; and that all realities are created by human actions
(Easterby-Smith et al., 2012). Contrary to these is the materialism view which
believes in reality; though the reality here is limited to physical characteristics that
can be touched.
Other authors broadly classified ontological positions into two which are;
objectivism and constructivism (Saunders et al., 2012; Grix, 2002; Crotty, 1998).
Methodology Chapter Five
102
Objectivism and constructivism are also expressed in epistemology which further
shows the link between ontology and epistemology. The ontological position of this
study is a combination of constructivism and objectivism as presented and justified
in subsequent sections. The discussion in this section has shown that ontological
consideration is vital for every research as it will guide the researcher to know the
nature of reality that exists in the world before commencing the investigation on how
to know that reality i.e. epistemology.
5.3.2 Epistemology
To a social scientist, epistemology is concerned with the theory of knowledge with
special focus on the process used in gaining the knowledge about social reality (Grix,
2002). The word is derived from two Greek words i.e. episteme (knowledge) and
logos (reason). Its focus is on what should be considered as an acceptable knowledge
in a given field of study (Saunders et al., 2012; Bryman, 2012; Henn, 2006). These
suggest that epistemology aims at investigating the kind of knowledge produced,
how the knowledge was developed and the conditions to use in differentiating valid
knowledge from invalid knowledge (Blaikie, 2007). It is worth to state that every
study must identify and take a specific epistemological position throughout the
research process. Two contrasting epistemological positions have been identified;
though they are presented under different names, they have the same meaning. For
instance, while Crotty (1998) named the two epistemological positions as
objectivism and constructivism; Grix (2002) viewed them as positivism and
interpretivism.
Objectivists and positivists believe that social reality can only be known and
understood via the application of natural science methods. While constructionists and
interpretivists believe that in order to understand the social reality, there is need to
study the actors that are involved in the process, this implies that social realities are
created by the actors (Saunders et al., 2012). From the above discussion, it is obvious
that choosing or taking a particular epistemological position will influence the
methodology that will be used in the investigation. This implies that different
methodologies could be used to study even similar phenomena if the epistemological
positions are different. The epistemological position of this study is a combination of
Methodology Chapter Five
103
both interpretivism and positivism. The justification for this is presented in
subsequent section
5.3.3 The Relationship between Ontology, Epistemology, Methodology,
and Research Methods
As earlier stated, every research has its ontological and epistemological positions or
assumptions. Grix (2002) asserted that ontology and epistemology are the
fundamentals of every genuine research as they play a major role in deciding the
research methodology and methods. However, many have failed to understand the
relationship that exists between these key terms, which leads to muddling up of the
research process. This is clearly discussed here to prevent the author from making
similar mistakes. For instance, it has been observed that ontology is usually confused
with epistemology while methodology is usually confused with methods (Grix, 2002;
Blaxter, 2010). The consequence of these confusions is the omission of the logical
sequence that exists between each concept. Figure 5.2 shows the relationship
between each concept and the logical sequence.
Ontology Epistemology Methodology Methods Source
What is out there to
know?
What and how can
we know about it?
How can we go
about acquiring
that knowledge?
What is the precise
procedure for
acquiring the
knowledge?
Which data can
we collect?
Figure 5.2: The Logic of Research building block
Source: Adapted from Hay (2002)
As shown above, these logic needs to be maintained in developing the research
process. According to Grix (2002), the implication of this interrelationship is that
Methodology Chapter Five
104
research cannot just commence at any point in the diagram. This further emphasises
the need to allow an ontological and epistemological position to shape the research
process and not the research methods. It is obvious that choosing a research method
before developing the research question is against the logic presented in Figure 5.2 as
it will eventually lead to research question and method misfit (Saunders et al., 2012;
Grix, 2002). The ontology and epistemology in the research building block presented
in Figure 5.3 formed the basis of the research paradigm.
5.4 Research Paradigms
According to Henn et al., (2006 P10), paradigm “is a set of assumptions about how
the issue of concern to researcher should be studied”. It is a means of evaluating
social phenomena with a view to determining the approach to be used in conducting
the investigation and how the phenomena can be explained (Saunders et al., 2012;
Bryman, 2012; Fellows and Liu, 2008). Research paradigm has been classified into
three, these include; positivism, interpretivism and mixed approach) (Saunders et al.,
2012; Bryman, 2012; Fellow and Liu, 2008, Smith, 2006).
5.4.1 Positivism
The dominance of positivism and interpretivism in construction management
research has been widely acknowledged in the literature (Dainty, 2008; Neville,
2007; Love et al., 2002). Positivism is based on the assumptions that there is an
objective reality that must be studied, touched, and known in the physical world
(Lincoln, 1994). It focuses on identifying, measuring, and evaluating problems in
order to establish any available causal relationship (Henn, 2006; Neville, 2007). The
proponents argued that social science research should be viewed and investigated
like any other natural science research by adopting the empirical methodologies in
the natural sciences (Berg, 2007; Collin and Hussey, 2003). Guba and Lincoln (2005)
noted that the approach allows the researcher to investigate the problem without
influencing it. The commonly used research method or strategy with positivistic view
is quantitative research method or strategy. The research methods used in positivistic
approach are survey, experimental survey, longitudinal survey, and cross-sectional
survey.
Methodology Chapter Five
105
5.4.2 Interpretivism
Interpretivism is based on research paradigm that is contrary to the positivistic view
on knowledge. The interpretivist believes that research in social science cannot be
conducted as in natural science research, since human behaviour and phenomena
which social research is associated with cannot be easily measured as applicable in
the natural sciences (Collin and Hussey, 2003). The proponents argued that social
science research involves people, institutions, settings, and organisations which are
fundamentally unique from the natural science research, thus a unique approach that
gives consideration to human behaviour should be adopted in conducting a social
science research (Bryman, 2012). It focuses on understanding human behaviour and
phenomena from the participant’s point of view which is contrary to the positivistic
approach that tends to explain behaviour from the researcher’s perspective (Bryman,
2012; Neville, 2007).
This suggests that the approach allows participants to make meaning out of the world
around them. Neville, (2007) argued that people have the ability to influence the
event around them in order to improve their condition, thus research methods that
examine and investigate problems or trend of events from the participants’ perceptive
should be adopted. According to Bryman (2008 Pp, 16), “social reality has a
meaning for human beings and therefore human action is meaningful”. This implies
that the need for adopting philosophical viewpoints that allow human action to come
into play in the research process (especially in social science research) cannot be
underestimated.
The commonly used research strategy with interpretivistic views is the qualitative
research strategy. Qualitative strategy incorporates the following research methods;
case study, action research, ethnography, participative enquiry, feminist perspectives
and ground theory. Table 5.1 indicates the key differences between positivist and
interpretivist research philosophies.
From the foregoing, interpretivist point of view tends to support the goal of this study
which seeks to know how the current understanding and application of
“Collaborative Planning” (CP) for delivering construction projects in the UK from a
production planning and control perspective aligns with the advocated principles and
Methodology Chapter Five
106
theories of the Last Planner System (LPS) in a social setting (UK). But no decision
could be made here without the examination of other paradigms.
Table 5.1: Comparing Positivist and Interpretivist Research Philosophies
Positivist Interpretivist
Knowledge is based on phenomena that is
directly observable
Knowledge is based on understanding,
interpretations and meanings that are not
directly observable
The social world should be researched using
the principles of natural science
The social world should be studied in its
natural state, using participants observation
and in-depth interviews
An explanation is achieved through the
formation of causal laws
Explanation is achieved through description
of social meanings/reasons
It uses deductive method with emphasis on
hypothesis testing
It is based on inductive method in which
theory is generated from data
Methods imply researcher/ respondent
detachment in the objective collection of
data
Methods imply insider approach, researcher/
respondent closeness in joint collection of
subjective data
Analysis is based on statistical testing of
given theories
Analysis is based on verbal, action and
situation description from which theories
evolve
There is stress on reliability and
generalisation
There is no stress on generalisation
Research methods: survey, experimental
studies, longitudinal studies and cross
sectional studies
Research methods: case study, action
research, participant observations,
participative enquiry etc.
Sources: (Bryman, 2012; Sanders et al., 2012; Henn et al., 2006)
5.4.3 The Chosen Paradigm and the Rationale
Having critically examined the various research paradigms in the preceding sections,
it is now germane for this study to take its own philosophical stance which should be
capable of driving the study to achieve its ultimate goal. The importance of taking a
philosophical stance and its role in shaping the research process has been emphasised
by numerous authors (Saunders et al., 2012; Lipscomb, 2011; Dainty, 2008; Fellow
and Liu, 2008; Henn, 2006; Grix, 2002). Johnson and Duberly (2000) suggested that
researchers should take philosophical stances that match the researcher’s profile, the
nature of the study and with the potential of assisting to understand and address the
concerns of the study. As discussed in sections 5.4.1 to 5.4.3, the most utilised
research paradigm in social science research and by extension construction
Methodology Chapter Five
107
management are positivism and interpretivism. All of these and some of the
justification for their use in this study have been discussed in section 5.4.1.
Furthermore, interpretivism paradigm is more aligned with research methodologies
that enable the researcher to develop an understanding of problem when there is
limited knowledge on the subject under investigation. It also allows the views,
positions, concerns and the meaning ascribed to the problem by the participants to be
known and not limited to that obtained from the literature (Fellow and Liu, 2008;
Cole, 2006). All these align with the aim of the study earlier described.
However, the study also seeks to objectively identify the impact of production
planning and control practice based on the LPS on construction process improvement
(CPI). It is to also objectively evaluate and validate the Last Planner System Path
Clearing Approach (LPS-PCA) developed to support construction stakeholders in the
implementation of the LPS in construction, which requires research methodology
associated with positivism. Based on this understanding, the chosen paradigm in this
study is a mixture of interpretivism and positivism ( Saunders et al., 2012; Henn et
al., 2006), as it enabled the study to achieve the study aim and objectives.
The effective combination of interpretivism and positivism in conducting
construction management research has been widely reported in the literature (Dainty,
2008; Fellow and Liu, 2008). Dainty (2008) asserted that positivism (quantitative)
and interpretivism (qualitative) research both have their root in ontology and
epistemology, thus they can be combined.
5.5 Research Strategy
Naoum (2013 pp.39) defined research strategy as “the way in which research
objectives can be questioned” while Bryman (2008 pp.22) referred to it as “the
general orientation for conducting social science research”. Both authors identified
quantitative and qualitative approaches or the combination of both as the main
research strategy. These research strategies will be critically examined in the next
section to further help in positioning the study.
5.5.1 Quantitative Approach
Quantitative research is based on positivist research paradigm as outlined in Table
5.1. It emphasises the need for data quantification and establishment of causal
Methodology Chapter Five
108
relationships between variables (Dainty, 2008; Bryman, 2012). Henn et al., (2006)
observed that with the quantitative approach, there is pre-conceptualisation with
regard to research question, research design and the likely findings. This implies that
when the research design is highly structured, the methods should be reliable. The
research design also aims at generating large scale statistical information in order to
generalise the findings. Although the approach allows large data collection for
generalisation and reproduction of findings, the highly structured research design
poses a great limitation to such findings as there could be various ways to explain
why a particular event occurs. Quantitative approach tends to be objective in focus,
while also trying to establish a trend in a study; it is concerned with answering
questions such as, what? how much? and how many? (Naoum, 2013; Bouma, 2000).
Basically, sample survey and experiment are the methods used in quantitative
approach. The aim of this study is not to test theory, hypothesis or make any form of
generalisations, however, quantitative method such as survey will be adopted on a
lower scale at some points in the study for evaluation and validation purposes.
5.5.2 Qualitative Approach
Qualitative research approach is based on interpretivist paradigm as outlined in Table
5.1. Qualitative research can be defined as “an approach to inquiry that begins with
assumptions, worldviews, possible theoretical lens, and the study of research
problems exploring the meaning individuals or groups ascribe to social or human
problems” (Creswell, 2007 pp.50). Unlike the quantitative approach, it emphasises
the use of words in the collection and analysis of data rather than measurement and
quantification. This will enable the study to closely explore the problem and develop
solution. It seeks to know why, what, how or where of an event and the likely
meaning ascribed to such event by the participants in that setting (Fellow and Liu,
2008); which aligns with the aim of this study.
It is worth noting that this strategy has been criticised for lack of objectivity and that
the data are not large enough to generalise findings. In this study, effort was made to
improve this, as the study used multiple approaches in collecting data and
triangulating methods. According to Berg (2007), the essence of research is not just
to assemble data, rather, it is to adopt a logical and systematic process that helps in
answering the research question. Thus, qualitative research seeks to answer the
Methodology Chapter Five
109
research question by investigating the social settings and individuals in the settings
(Berg, 2007; Henn, 2006). In this study, the social setting is the UK construction
industry and the people inhibiting it are the construction industry professionals and
organisations.
Qualitative strategy is considered appropriate for this study based on its attributes
identified by Naoum (2013); Bryman (2012); Fellow and Liu (2008); Henn et al.,
(2006); which align with the aim and objectives of the study. Firstly, it allows the
study to be conducted in a real life social setting in order to understand the current
phenomenon investigated, and this is in line with aim of the study. Furthermore,
qualitative research can be conducted under different methods such as interviews,
case study, action research, ethnography (participant observations), and participative
enquiry (Henn et al., 2006; Bryman, 2012). Table 5.2 clearly outlines the major
differences between quantitative and qualitative strategy.
Table 5.2: Differences between Quantitative and Qualitative Strategies
Features Quantitative strategy Qualitative strategy
Aim and objectives
Measurement of views and
opinions
To gain full insight into the
research problem
The goal is to establish cause
and effect
Focus on describing the problem
and process
Focus on data quantification
and generalisation of findings
Focus on understanding the
research problem and the
motivations
Hypothesis/
research question
Stated before the
commencement of the study
No defined hypothesis before the
study
Investigation is based on
theory and it uses deductive
approach
Theory is usually developed
inductively after the investigation
Study variable
The independent variable is
usually controlled and
manipulated
Does not focus on any variable, its
focus is to investigate the social or
natural settings.
Data collection
method
Fixed and objective approach.
Uses closed and structured
questionnaire, experimental
methods
Flexible approach. Uses open
ended, semi-structured and
unstructured interviews, case
studies, observations, focus group
etc
Research design Fixed research design, usually
developed before the study
No pre-determined research design,
it keeps developing as the study
progresses
Method of data Descriptive statistics with Content analysis and coding of
Methodology Chapter Five
110
analysis focus on numerical values,
percentages, mean etc.
themes
Validity and
reliability
Uses statistical analysis and
data to ascertain and validate
data
Use of multiple approach known as
“triangulation” helps in validation
of information
Study sample
The selected sample should
represent the population for
the study
Purposive sampling is usually used
for the study, sample size is not the
focus
External validity
Uses statistical data (size of
population) and inference to
validate results and generalise
findings
The focus here is not to generalise
findings, but multiple sources are
used in validating and enriching
findings
Focus is on the research
design and the data collected
Based on the procedures used in
carrying out the investigation
The research problem is
investigated in a simplified
and objective manner
The research problem is
investigated from all perspectives
(holistically)
Strength
Findings can be easily
generalised
Multiple sources of data collection
help in enriching information
The selected variables can be
easily measured
Detailed information about the
problem can be easily obtained
Data is obtained from large
sample, which supports
finding generalisations
Participants’ opinions and views
about the phenomenon can be
readily obtained
Weakness
The approach is rigid which
could limit the development
of theories
Findings cannot be easily
generalised due to small sample
size. Knowledge generated may not
be readily applicable in other
settings
Sources: Sanders, 2012; Bryaman, 2008; Creswell, 2007; Henn et al., 2006; Denzin and Lincoln, 2012
Having examined the characteristics of the quantitative and qualitative strategies
which further align with the aim and objectives of this study, the combination of both
approaches which is commonly termed mixed strategy or approach was chosen for
this study. However, within each strategy, specific methods were used.
5.6 Research Method Consideration and Choice of Research Method
for the Study
In the introductory section of this chapter, an attempt was made to explain the
differences between research methodology and research methods. The relationship
that exists between them was further shown in Figure 5.1. However, Fellow and Liu
(2008) suggested that in order to determine the appropriate method to adopt, it is
Methodology Chapter Five
111
necessary to consider the logic that exists between data collection and analysis from
using the method. Also, the method should be sufficient enough to achieve the
overall research objectives. This suggests that it is paramount to critically examine
some available research methods before selecting the appropriate method for the
study. In view of this, the following research methods were critically examined
because of their relevance to the current study. They include: Design science/Action
research, Ethnography, Surveys and Case study.
5.6.1 Ethnography Evaluation
It is a qualitative method used to study groups of people, their culture, and the
interactions and practices that occur among them within their social environment or
settings (Saunders et al., 2012; Fellow and Liu, 2008). The study occurs through
close observation of the participants in their natural setting by the researcher. The
empirical data for the study is usually obtained by questioning the participants
formerly or informally so as to gain an understanding of the problem (Fellow and
Liu, 2008). Henn et al., (2006) suggested that the use of an informal approach in
conducting the investigation will enable the researcher to observe and gain
understanding of the problem without being viewed by the participant as
surveillance. In this approach, the goal of the researcher is to study the participants in
the setting so as to understand the problem without causing any form of obstruction
to the work being done by the participants.
From the above mentioned, ethnography approach could have been a potential
approach to use in exploring how the current understanding and application of CP
from delivering construction projects from production planning and control (PP&C)
perspective in the UK construction aligns with theory and principles of the LPS. This
is because of its ability to interact and observe a specific practice in a given context
(Saunders et al., 2012; Fellow and Liu, 2008). However, ethnographic approach is
dominated by participant observations over a long period of time which makes it less
suitable for this study that has a limited time frame. Again, the focus of the study is
not only to observe participants but to also understand the meaning the participants
ascribe to the problem under investigation.
Methodology Chapter Five
112
5.6.2 Design Science/ Action Research Evaluation
Design science research (DSR) is similar to action research in many areas (Cole et
al., 2005). DSR method is a problem solving approach that focuses on providing an
innovative solution by identifying problems while also developing and implementing
the right approach for addressing the problems (Hevner et al., 2004). The method
incorporates exploratory and action research approaches which has been identified as
proactive research methods that directly influence real world problems in order to
provide practical solutions to such problems in real life (Cole et al., 2005; Berg,
2007). It is commonly used in operation management and information system but it
has now diffused into construction management research especially lean construction
research (Cole et al., 2005; Hevner et al., 2004; Ahiakwo et al., 2013; Formoso et
al., 2012).
Considering the fact that the construction industry is dynamic and at the same time
complex, the best approach to initiate change within the industry could be via
research methods that encourage learning through associated actions.
DSR relies on existing knowledge including those from literature, practice, and
iteration of processes in order to develop an innovative and systematic approach for
addressing the identified problem (Hevner et al., 2004). Like in the case of action
research, the researcher must be actively involved in identifying, developing, and
implementing the solution for the identified problem. The approach reduces the gap
that exists between practice and theory in research (Koskela, 2008
Given the proactive and practical nature of action research (AR) and DSR, in
addition to the recommendation for its use by lean construction scholars for
researches in lean construction (Koskela, 2008), this could be a potential approach
for conducting this study which focuses on the application of lean principles in
planning.
However, the focus of AR/DSR is on developing and implementing a practical
system in an iterative process to address the problem with active involvement of the
researcher. This study only created and piloted an approach to support LPS
implementation towards the end of the study, which implies there is no intention for
iteration of the process, hence AR/DSR is less feasible. Furthermore, as much as the
study is not claiming to generalise its finding, it seeks to explore different approaches
Methodology Chapter Five
113
to present a fairer picture of LPS/CP in the UK construction industry, in order to
suggest a means to support the process. This cannot be achieved with AR/DSR
alone; hence, the method was discounted. There could be feedback delay from the
iteration process which may not be good for this time constrained study.
5.6.3 Surveys Approach Evaluation
Survey method is used to obtain response from a large sample of respondents in a
structured format. It is usually based on statistical analysis and uses a deductive
approach (Saunders et al., 2012; Henn et al., 2006). The knowledge acquired from
the process could be generalised since the approach could be used to reach large
number of respondents. It is worth to state that the respondents must be a true
representation of the population of the study before such conclusions can be valid.
The limitation with this approach is that it does not allow for new perspectives on the
subject or phenomenon under investigation to be gained from respondents. This is
because the factors to be investigated are already predetermined by the researcher
especially in questionnaire survey, thus limiting the view of the respondents (Henn et
al., 2006).
Survey data are collected via face to face, telephone interview and postal
questionnaire. The type of survey technique used has influence on the quality of data
and also on cost (Naoum, 2014; Bryman, 2012). It is worth noting that, survey
method is not limited to questionnaire survey as commonly believed. It includes
other structured approaches such as structured observations, structured and semi-
structured interviews among others (Henn et al., 2006). Although, questionnaire
survey is relatively cheap compared with interview survey, interviews generate more
quality data.
Considering the exploratory nature of the study, going into the study with a
predetermined question such as in questionnaire survey will not support the aim of
the study, as this would limit the respondents from sharing their experience on the
problem being investigated. Even though some of the interview questions were
developed from the literature review, they were open ended questions and flexible.
Thus, questionnaire survey was discarded. Also, the focus of the study is not to
generalise the findings, and considering the fact that lean construction in general, and
LPS in particular is an emerging concept in the construction industry, obtaining
Methodology Chapter Five
114
representative sample for statistical analysis will be unlikely. For instance, there is no
database for lean construction practitioners in the UK construction industry.
However, structured survey was used to evaluate and validate the LPS-PCA
developed in this study and also in the assessment of the impact of the LPS
implementation on construction process improvement. This was done to obtain
objective data on these objectives.
5.6.4 Interviews
Interview is a common approach used in data collection in social science research.
There are different types of interviews; open-ended, semi-structured and unstructured
interviews. Interviews could be conducted face-to-face, via telephone conversations,
use of online medium such as Skype, computer mode supported interview, and e-
mail correspondence among others (Bryman, 2012; Sanders et al., 2012; Creswell,
2007). However, Bryman (2012) and Yin (2014) observed that semi-structured
interview is the most used approach in qualitative research. Bryman (2012) observed
that semi-structured interview is commonly used because it promotes standardisation
in the asking and recording of responses to the interview questions. The goal of using
semi-structured interview is to be able to aggregate the responses of the interviewees.
However, unlike questionnaire survey where the respondents are restricted by the
rigid nature of the questions, the semi-structured interview process is flexible. This
enables respondents to bring out in-depth information based on their experience.
Naoum (2013) pointed out that in a semi-structured interview process, the
interviewer has a great deal of freedom to probe the respondents on specific areas for
further insight, which further enriches the quality of the data collected. Thus, semi-
structured interview was used in the study. But it has been claimed that the attribute
of the interviewers could influence the responses of the interviewees in a semi-
structured interview (Naoum, 2013; Bryman, 2012). Bryman (2012) argued that there
is no clear evidence to support such claims. This implies that interview has its own
strengths and limitations. Table 5.3 presents the strengths and limitations of
interviews as summarised in Recker (2008 pp109) and Robson (2002 pp.269-290).
However, effort was made by the researcher to minimise the limitations associated
with interview in the study. This was achieved by ensuring invitation letters/e-mails
were sent out to the interviewees ahead of time. In the mail, the purpose of the study
Methodology Chapter Five
115
was made known to the research participants. This process builds trust between the
researcher and the interviewees.
Table 5.3: Strengths and Weaknesses of the Interview Approach
S/NO Strength of interviews Some limitations with interviews
1 Can be used for thematic and
issue analysis
Time consuming in terms of actual interview and
corresponding analysis
2 Useful for small samples Training of interviewers and the need for
interpersonal skills
3 Allows subjects to speak for
themselves
Usually needs to be transcribed
4 Allows teasing out of underlying
issues
Potential lack of precision
5 Enabling gathering of rich and
deep knowledge
Need for rigorous thematic analysis
6 Can serve as foundation for
extending the study
Potential lack of trust
7 Formally tests the emergence of
patterns and relationships
Source: (Recker, 2008; Robson, 2002)
Also, interviews can be used in different qualitative methods, such as action research,
ethnography, grounded theory, and case studies among others. However, the nature
of the study usually determines the type of interview to be used. Table 5.4 presents
interview types in relation to the focus of the study.
Table 5.4: Interview Type in Relation to the Nature of the Study
Type Exploratory study Descriptive study Explanatory study
Structured More frequent Less frequent
Semi-structured Less frequent More frequent
Unstructured More frequent
Source: Sanders et al., 2012, pp377
Sanders et al., (2012) observed that two or more of these interview approaches could
be used in a single study with each building on each other to enrich the data. This
informed the use of semi-structured interview in the exploratory phase of this study
and structured interview in the descriptive phase.
Methodology Chapter Five
116
5Specifically, exploratory interviews was used since the study examined the current
understanding and application of PP&C based on the LPS in the UK construction
industry, by exploring the social settings (the UK construction industry sector) and
the individuals in it (the UK construction practitioners). Creswell (2013) observed
that exploratory interviews are appropriate when a study seeks to know the meaning
people ascribe to an event and not the meaning from literature alone; which aligns
with the aim of this study.
Additionally, the interview approach was considered appropriate as it has been
identified as an effective means of learning about a phenomenon in a particular
setting. It has been observed that no research method “can provide the detailed
understanding that comes from directly observing people and listening to what they
have to say at the scene” (Taylor and Bogdan, 1984, p. 79). Thus, interview and
observation were used in the second, third and fourth stages of this research.
5.6.5 Case Study
Yin (2009 Pp.18) defined case study as “an empirical inquiry that investigates a
contemporary phenomenon in depth and within its real-life context, especially when
the boundaries between phenomenon and context are not clearly evident”. This
suggests that the case study method is used to explore research problems or
phenomena in a real life situation or context. According to Eisenhardt and Graebner,
(2007); Amaratunga et al., (2002), the case study approach allows the researcher to
gain deeper understanding of the research problem or the phenomenon in relation to
context in which the study is being conducted. Saunders et al., (2012) asserted that
unlike in the survey approach, the boundaries within which the phenomenon is being
studied in case study is not restricted by any variable. Yin (2014) suggested three
conditions that should inform the choice of the case study method; (1) when the
study seeks to answer research questions such as “how” or “why” (2) when the goal
of the study is not to have full control over the phenomenon being investigated and
(3) when the goal of the study is to focus on real life situations in a given context. All
these align with the research questions this study answered;
5 Part of this have been published in Daniel et al., 2015c
Methodology Chapter Five
117
How does the current understanding and application of “Collaborative
Planning” (CP) for delivering construction projects in the UK align with the
advocated principles and theories of the Last Planner System (LPS)?
How can construction stakeholders be supported for rapid and successful
implementation of the Last Planner System?
Yin (2014) observed that the case study approach is appropriate when a study seeks
to know the how or why of an event. For instance, the goal of this study is to
understand how PP&C as currently practiced in the UK construction industry aligned
with the LPS and how to support construction organisation for rapid and successful
implementation of LPS. Also, the case study approach could entail investigating a
single case or multiple cases, which is usually determined by the overall aim of the
study or how the case study has been designed. The techniques used in collecting
data include but are not limited to interviews, semi-structured interview, observation,
exploring documents, and audio visual materials. As shown in Table 5.5, each
technique has its own weaknesses and strengths (Yin, 2014).
To overcome these weaknesses, the study combined these techniques to supplement
the weaknesses. The key advantage of adopting multiple case studies is that it allows
the researcher to gain a better understanding of little known problems or phenomena
in a particular context using data from various sources known as “triangulation”
(Yin, 2014; Leedy and Ormrod, 2001). Since this research aimed at developing a
better understanding of the phenomenon under investigation in order to develop a
holistic support, the multiple case study approach was adopted. This also supports
triangulation. The triangulation approach has been identified as a mechanism that
adds rigour to case study research method (Yin, 2014). The approach could also be
used to develop a new theory, confirm an existing theory or in modifying it when
necessary based on findings from the study.
Table 5.5: Strengths and Weaknesses of Sources of Evidence in Case Study
Source of evidence Strength Weakness
Documentation Stable – can be reviewed
repeatedly
Unobtrusive - not constructed
as a result of the case study
Exact - contain exacts names,
reference, and details of events
Retrievability - can be
difficult to find
Biased selectivity
(Collection is incomplete)
Reporting bias
Access - may be deliberately
Methodology Chapter Five
118
withheld
Interviews Target –focuses on the case
study
Insightful- provides perceived
causal inferences and
explanation
Bias due to articulated
questions
Response bias
Inaccuracy due to bias
Reflexivity - interviewee
gives what interviewer wants
to hear
Direct and
participants
observation
Reality –covers event in real
time
Contextual cover
Insightful into interpersonal
behaviour
Time consuming
Selectivity - broad coverage
difficult
Reflexivity - event may
proceed differently because it
is being observed
Bias due to participant-
observer manipulation of
event
Source: Yin, 2014
The case study method has been criticised for lack of rigour and defined procedure
for carrying out the investigation. However, Yin (2014) argued that the issue of lack
of rigour can be overcome when different techniques are used in collecting data, as
adopted in this study.
Accordingly, in this study, multiple methods were used in collecting data as
discussed in section 5.6.6. The case study method has been used extensively in
understanding and addressing real life situations in social sciences, business,
information system, and construction management among others. This could be due
to its potential to enable the researcher to develop an understanding of the problem
contextually, unlike the experimental method that tends to divorce the context when
collecting data. All the above highlighted points informed the choice of case study
method in this research.
5.6.6 Rationales for Choosing Mixed Method
The choice of mixed method for this study is mainly informed by the mixed research
paradigm chosen for the study, which has been justified in section 5.4.4. As earlier
stated, research paradigm influences research strategy or methodology. Mixed
approach refers to the incorporation of both quantitative and qualitative approach in
the research process. The use of mixed approach in construction management
research has been widely reported in literature (Dainty, 2008; Fellow and Liu, 2008).
Bryman (2012); Greene (1989) stated that the purpose of using mixed approach in
Methodology Chapter Five
119
research could be for triangulation, facilitation, sequential research development,
credibility, to compliment, gain fresh perspectives, expansion i.e. adding breadth to
scope, enhancement etc.
For this study, the essence of using mixed approach is not limited to but includes
triangulation, to complement, gain fresh perspectives, sequential development of the
research and ‘expansion’ adding breadth to scope. To be specific, the study used
triangulation as it combined techniques such as exploratory interviews, structured
snapshot observations, and multiple case study, which enriches the quality of the data
obtained. Multiple sources (triangulation) were used in order to validate the data, and
to ensure the LPS-PCA developed to support LPS implementation in this study is
holistic.
Also, the sequential development of the research and adding breadth to scope
approach was adopted. For instance, the structured snapshot observations on LPS
practice questions was developed based on the findings from the first exploratory
interviews and the initial literature review in phases 2 and 1 of this study
respectively. This demonstrated adding breadth to scope. Also, the findings from the
exploratory interviews and the snapshot observations informed the choice the three
case studies conducted in the study. Henn et al., (2006) observed that the
combination of methods in research does not only appear in the gain from the
individual method’s strengths when combined, but also stands to remedy the
drawbacks that are inherent with the use of a singular method.
Furthermore, while the exploratory interview enabled the study to obtain detailed
information on the current understanding and application of PP&C based on the LPS,
the snapshot observation presents some objective view on current practices. The case
study also reveals further information on the current practice and the nature of
support to be provided for successful implementation. It has been acknowledged that
combining two or more research approaches in a single study could be problematic
due to time constraints, money, the required resources and most especially the
different philosophical thoughts that underpins each method (Fellow and Liu, 2008;
Henn et al., 2006). However, Henn et al., (2006) argued that the adoption of different
research methods makes the research findings more credible as the approach adds
more breadth and depth to the study.
Methodology Chapter Five
120
In addition, Dainty (2008) further observed that quantitative and qualitative
approaches both have their root in ontology and epistemology, thus they can be
combined. The mixed method approach selected forms the basis of the overall
research design.
5.7 Research Design and Phases
The preceding sections of this chapter examined the research philosophical positions,
the methodology, methods, and justification for their choice in this study. This
section fully examines the research design and processes involved in the study. The
importance of research design cannot be overemphasised in any research endeavour.
Yin (2014, pp28) defined research design as “the logical sequence that connects the
empirical data to a study’s initial research questions and, ultimately to its
conclusions”. Research design enables the researcher to reflect on how the data for
the study will be collected, analysed and how meanings can be made to the data.
Similarly, Sauder et al., (2012) asserted that research design is very crucial to the
success of a research as it usually helps the researcher to present clear objectives for
the study from the research questions, propose how data will be collected and
analysed, give consideration for ethical issues and likely limitation to the study. It is
worth stressing here that research design is not just a mere plan of work to be carried
out by the researcher. According to Yin (2014), the essence of the research design is
to enable the study to avoid the circumstance in which findings or evidence(s) from
the study do not really address the original research question(s). Figure 5.3 presents
the overall research design for this study and the processes involved. As shown
Figure 5.3, the study comprised three key phases. The First stage highlighted in
green is mainly the literature review. The literature review supported the
development of the research question. The second stage highlighted in grey is the
data collection phase. The final phase, which is highlighted in red, represented the
creation and validation of the LPS-PCA. These three key phases are further divided
into six specific stages.
The key stages of the study include:
1. Literature review
2. Semi-structured interviews
3. Structured snapshot observations
Methodology Chapter Five
121
Literature Review
Develop an
understanding of
the Research
Problem
Identify gap in
Knowledge
The theory of
the Last
Planner
System
collaboration
and
continuous
process
improvement
Development
of
collaborative
planning in
URP and
software
development
Develop
Research
Question
Research
Strategy
Qunatitative
Qualitative
Interviews
Review of
IGLC LPS
implementat
ion
Empirical
case study
Sample:
Construction
professionals
Sample:
IGLC paper
1993-2014
Sample: 3
construction
organisations
Project observation/
evaluation
Snapshot
survey on
LPS
practice
Data : Open-
end and Semi-
structured
interview
Data : Site
observation
and semi-
structured
interview
Data
analysisContent Analysis
Descriptive
statistics Outcomes: Core
components of LPS
implemented, LPS
success factors,
barriers, impacts
Rate current
planning
practices in
UK
Collate and correlate
results
Development of LPS
pre-disposition
Validate and refine pre-
disposition
Conclusions and submission of thesis
Quantitative
KEY
Phase 1
Phase 2
Phase 3
Research Design
Figure 5.3: Research Design and Process
Methodology Chapter Five
122
4. Multiple case studies
5. Development of Last Planner System Path Clearing Approach(LPS-PCA) and
evaluation, validation and piloting of LPS-PCA.
Table 5.6 shows how each phase of the study linked with the objectives set out in
Chapter One. It is worth to state that all the objectives are interlinked.
Table 5.6: Relationship between the Research Objectives and Phases of the Study
Objective 1 Objective 2 Objective 3 Objective 4 Objective 5 Objective 6
Phase 1 Phase 1 Phase 1
Phase 2
Phase 3
Phase 4
Phase 1 to 5
5.7.1 Stage 1: Literature Review
Literature review plays a vital role in a research process. Literature review has been
defined as the “the selection of available documents (both published and
unpublished) on the topic, which contains information, ideas, data and evidence
written from a particular standpoint to fulfil certain aims or express certain views on
the nature of the topic and how it is to be investigated, and the effective evaluation of
these documents in relation to the research being proposed” (Hart, 1998, pp13).
Bryman (2012) observed that the essence of conducting a literature review is to
understand what has been done in the area, the theories, and methods used in
researching the area, and unanswered questions in the area among others. This will
further position the researcher well to identify the importance of the present research
and in framing the argument for the study accordingly. This implies that the literature
review guides against researchers doing what others have already done.
Similarly, Naoum (2013) and Fisher (2007) observed that literature review enables
the researcher to build on existing knowledge and expand the scope of the present
study. Literature review played a major role in this study, ranging from the research
question to the aim and objectives. For instance, the knowledge gap and the research
question were partly identified from the literature as presented in Chapter One. Also,
objectives 2, 3 and 4 were solely achieved via literature, while all the objectives were
Methodology Chapter Five
123
supported by the literature review as shown Table 5.6. Figure 5.4 shows the flow of
the literature review chapters.
Figure 5.4: Literature Review Chapter Flowchart
The study reviewed the development of PP&C based on the LPS and the need for
CPI in the UK. This included the review of the construction industry reports and the
Lean Construction Improvement Programme (CLIP) demonstration projects. The
development of collaboration in planning in the UK and other field of knowledge
specifically in urban planning (UP) and software developments were reviewed. Also,
the current theoretical understanding and application of production planning and
control in the construction industry with focus on the LPS was considered.
Furthermore, a comprehensive literature review on the LPS case study
implementations as reported by the International Group for Lean Construction
(IGLC) between 1993 and 2014 was done. This particular review enabled the study
to compare the current practice of PP&C in the UK with the LPS and also in
development of LPS-PCA.
In achieving this, a robust literature survey protocol that selects publications based
on source, time frame and its relationship to the study was developed. Publications
and collections from databases such as Emerald, Elsevier, Construction industry
Institute, the International Group for Lean Group for Lean Construction (IGLC),
Construction Economic and Management Journals, Journals of construction
engineering and management, and Lean Construction Journals among others were
examined. These databases were chosen because they house peer reviewed
Chapter 2:Construction process improvement and the development of production planning and control based on the Last Planner System in the UK construction industry.
Chapter 3:Collaboration in construction and the developments of collaboration in planning in other fields: implication for construction management
Chapter 4: Production planning and control in construction based on the Last Planner System
Methodology Chapter Five
124
publications on lean construction and construction project management. The review
was restricted to only published and peer reviewed materials. However, other
materials that were considered important and not published were reviewed. This was
done to ensure that important information in the study area was not neglected.
The search also extended to other academic and scholarly publications, database
searches, journals, technical reports, conference proceedings, case study reports, text
books, Nottingham Trent University (NTU) database, google scholar, and Scopus
among others. For instance, publications that were not available on the NTU
database were sourced through inter library loan. Each literature review chapter
commenced with an introduction, the arguments, and the summary of the chapter
which highlighted the conclusions from the arguments in the chapter. The literature
was constantly updated throughout the research process and all the materials used in
the review were referenced.
5.7.2 Stage 2: Semi-structured Interviews
Sanders et al., (2012) observed that semi-structured interview is appropriate when
undertaking an exploratory study and when the goal of the study is to understand the
meaning ascribed to the subject investigated, which aligned with the focus of this
study. From the initial literature review and knowledge gaps identified in phase 1 of
this study, an exploratory semi-structured interview was designed (see Appendix 1
for a sample copy). The aim of the exploratory interview was to investigate the
current understanding and applications of PP&C principles in the UK construction
industry through in-depth interviews with construction industry practitioners. This
empirical investigation became essential as a result of the knowledge gap caused by
the dearth of study that empirically explored the application of production planning
and control practice based on the LPS across the major sector of the UK construction
industry.
More importantly, since the study aimed to develop an approach to support
stakeholders (client, main contractors, and subcontractors) in the implementation of
LPS in the construction industry, in-depth interviews with these major practitioners
was considered essential to ascertain the current situation. The interview process
consisted of 6 key processes as presented in Figure 5.5, each process was carefully
examined.
Methodology Chapter Five
125
5.7.2.1 Interview Plan
The interview plan entailed a critical consideration of the overall data collection and
analysis process to ensure that the research question could be answered sufficiently
at the end of the process. This includes the drawing up of the interview process as
presented in Figure 5.5. The double arrow heads in Figure 5.5 indicate the feedback
loop that was observed throughout the interview stage. Also, at this stage, the
researcher further reviewed the study aim and objectives to ensure that the above
developed process will support the achievement of the aim and objectives of the
study.
Also, all the needed skills, resources, and training required for conducting the
research were identified by the researcher and the supervisory team. Subsequently,
the researcher acquired and sought the appropriate support needed for conducting the
research from within and outside the institution. For instance at this time, approval
was sought from the college ethical committee (see Appendix 2 for a copy of the
ethical approval letter).
5.7.2.2 Interview Protocol
The importance of developing interview protocol in an interview process cannot be
overemphasised. Naoum (2013) observed that developing a robust interview protocol
increases the confidence of the respondents in the interview process, which further
Plan Interview
protocol
Analyse and
make
meaning
Sampling
Interview
session
Transcription
Figure 5.5: Interview Process
Methodology Chapter Five
126
supports the quality of the responses received from the respondents. In developing
the interview protocol, the ten criteria for successful interview suggested by Kvale
(1996) were adopted. These include; knowledge of the research focus, giving clear
purpose of the interview, making question simple and easy, being gentle and patient
with respondents among others.
Also, the need for ethical consideration as suggested by Bryman (2012) was not
neglected. In doing this, ethical approval was sought and given from the college
ethical committee with full description of the proposed study, (see Appendix 2 for
the approval letter). Following the ethical approval from the ethical committee, the
invitation/consent letter to participate in the research interview was designed, (see
Appendix 3 for a copy of the letter). A copy of the invitation letter to participate in
the interview was sent to each of the respondents and the arrangement for interviews
was made following a formal response indicating their interest to participate in the
study. This is essential as it assured the respondents of the confidentiality of their
responses.
The interview protocol also included the development of the semi-structured
interview guide. Figure 5.6 presents the protocol used in developing the interview
questions. The interview questions were formulated based on the research question
and the specific objectives, which was internally validated by the researcher’s
Director of Studies, a Professor of Lean Project Management and the supervisor, a
senior lecturer in the school of Architecture Design and the Built Environment at
Nottingham Trent University. Subsequently, the interview guide was piloted with 3
PhD research students at NTU and 1 business improvement manager working for a
contracting organisation. As shown in Figure 5.6, the development of the interview
questions was an iterative process as indicated by the double head arrow. This was
done to improve the quality of the questions and invariably the quality of data
collected.
Methodology Chapter Five
127
Figure 5.6: Interview Questions Development Protocol
This was done to enable the researcher understand the flow in the questions, ensure
clarity of the questions to the respondents, and the likely duration of the interview
among other things. Following the feedback from the pilot interview, the interview
guide was revised and the final version developed. The interview instrument
consisted of 6 sections. The first section focused on the background of the
respondents, section 2 focused on the current views and practice of LPS and CP,
section 3 investigated the current drivers for implementing LPS and CP. Section 4
investigated the success factors for implementing LPS and CP, while sections 5 and
6 investigated the current benefits and barriers (See Appendix 1 for a sample of the
interview guide). The questions were open ended to allow the respondents to express
their thought on the phenomenon under investigation, to reduce bias and to improve
the richness of the findings. However, the questions were structured to keep the
respondents on track.
5.7.2.3 Sampling
Sampling is the process of selecting the population for the study. Sanders et al.,
(2012) pointed out that selecting the right sample determines largely if the research
question would be sufficiently answered. Bryman (2012) identified two main
sampling principles in research; probability and non-probability sampling principles.
While probability principle is commonly associated with quantitative methods, the
Literature review and specific research questions
Formulate interview questions
Validate and pilot interview questions
Revise interview questions
Develop final interview questions
Methodology Chapter Five
128
non-probability principle is associated with qualitative methods. According to
Sanders et al., (2012), non-probability sampling approach is appropriate when
statistical inference and sample representation of the population is not a must in a
study. Thus, non-probability principles are the adopted in the study. Sanders et al.,
(2012) identified the following non-probability sampling techniques; quota,
purposive, snowballing, self-selection and convenience sampling.
Quota sampling techniques are associated with a large population as in the case of
some surveys. Bryman (2012) argued that quota sampling is more of probability
sampling than non-probability. In purposive sampling, sample cases/participants are
selected by the researcher such that the population sampled are relevant in answering
the research question (Bryman, 2012). Purposive sampling is used extensively in
exploratory qualitative research to obtain balanced information. On the other hand,
Sanders et al., (2012) observed that the snowballing approach is used when it is
difficult to identify the members of the proposed population for the study from the
onset. This would require the identified population to suggest other members who
could also participate in the study. It could entail referring the researchers to similar
case projects elsewhere.
While convenience sampling technique is concerned with using the available
population to the researcher by chance, self-selection focuses on individuals who
agree to be selected to participate in the study without consideration if they have met
the criteria for participating in the study. This implies that quota, convenience
sampling, and self-selection sampling may not fully support the aim of this study,
thus purposive sampling and snowballing were used in the research. These
approaches would enable the researcher to only include those who qualify to
participate in the study. For example, in order to present a holistic view on the
current practice of PP&C based on the LPS in the UK construction industry,
purposive sampling was used in selecting the key stakeholders interviewed. They
include lean construction consultants, main contractors, clients, and subcontractors in
the UK construction industry. The criteria used in selecting the respondents include:
1. Having over 3 years’ experience in the UK construction industry
2. Having one year and above experience in the use of PP&C principles based
on the LPS in the UK and
3. Awareness on current deployment of lean construction principles in the UK.
Methodology Chapter Five
129
This was done to ensure that only those who have good knowledge on the use of
PP&C based on the LPS in the UK construction industry were included in the
interview. This was achieved by utilising the researcher’s Director of Studies who is
a Professor in Lean Project Management and a Director and Trustee of Lean
Construction Institute UK, while the researcher’s second supervisor has over 20
years work experience in senior management position in the UK construction
industry. Their extensive network in the UK construction industry was used in
contacting the interviewees.
The initial respondents purposively sampled and accessed were small. This is due to
the absence of a database for lean construction practitioners in the UK. Thus
snowballing approach was subsequently used. This implied that the initial contacts
would further recommend other lean construction consultants, main contractors,
clients, and subcontractors that are adopting PP&C practice based on the LPS on
their projects in the UK to the researcher. Although, the sample size for the interview
was not predetermined, the data collection continued to the point of saturation, that
is, where additional data provides little or no new information (Sanders et al., 2012).
Thirty in-depth interviews were conducted over a period of 18 months comprising 18
main contractors, 2 clients, 4 lean construction consultants, and 6 subcontractors.
Respondents interviewed all had over 3 years’ experience in the use of PP&C
principles based on the LPS and were drawn from building construction, highways
infrastructures and rail sectors. The respondents occupied various posts such as lean
improvement managers, project director, director, principal planning engineers,
planners, project managers, lean improvement directors, and business improvement
manager among others.
5.7.2.4 Conducting the Interview
Kvale (1996) suggested ten criteria that support quality interview. These include (1)
the researcher being knowledgeable in the research area, (2) making the purpose of
the interview known to the respondents, (3) openness and flexible to the
interviewees, and (5) relating your questions to what has been previously said by the
interviewee (6) Be patient with the interviewee (7) Be ready to challenge what the
interviewee has said (8) use questions and prompt question to steer the process (9)
respond to what is important to the interviewee (10) Provide summary on what has
Methodology Chapter Five
130
been said. These criteria were adhered to in conducting the interviews. Also, the
consideration of ethical issues and maintaining a balance between the interviewer
and the interviewee was done in the process (Bryman, 2012). The researcher
observed all of these in conducting the interview. In doing this, the researcher sent
out an email to each of the respondents describing the aim of the research with the
consent form attached (see Appendix 3 for a copy). A Sample of the interview guide
was sent to respondents who accepted to participate in the study a week ahead of the
interview day. This was to enable the respondents familiarise with the subject of the
interview so as to prepare well ahead of time. The interviews were conducted in an
environment neutral and familiar to the respondents, for instance, the majority of the
interviews were done face-to face in the respondent’s project site office or office.
Although, the cost implication to the researcher is high, as he had to travel to those
locations, it improved the richness of the data collected as the researcher was able to
probe further through reading the eye contact and body language of the respondent
on interesting points.
However, due to time constraints and distance, some respondents preferred to be
interviewed via skype and phone. In all, 26 respondents were interviewed face-to-
face, 3 via Skype and 1 via telephone. The duration of the interviews varied from one
respondent to another, but was between 60 and 90 minutes. The average time spent
in each interview session is 70 minutes, thus a total of 2,170 minutes was used in
conducting the interviews.
Having received the consent of the respondents, each of the interview session was
recorded on Recordium (a digital recording application), the researcher also took
hand written notes during the interview session. These were to ensure all information
was captured in real time. At the end of each interview, the researcher allowed the
respondent to say what was on their mind in relation to the study aim. It was
observed that this part of the interview session brought in new and rich insight to the
study. For example, one of the interviewees said “I never thought I have all this stuff
in me and I have given it out, can I have a copy of the result of your study please?
[Operation Director]. The researcher promised to send the outcome of the study to
respondents who requested for it.
Methodology Chapter Five
131
5.7.2.5 Interview Transcription
According to Bryman (2012) recording and transcribing interview helps to correct
natural limitation in our memories and the likelihood of omitting what the respondent
might have said during the interview. It also, allows for repeated evaluation of
respondents’ responses. Hence, all the 2,170 minute interview sessions were
transcribed and word processed since they were audio recorded. Considering the fact
that it takes 5 to 6 hours to transcribe a 1 hour interview, the researcher ensured that
each interview session was immediately transcribed after the interview session. This
helped in easing the work at the data analysis stage.
All the interviews were transcribed verbatim (word for word) in the exploratory stage
and in the case study (see Appendix 4 for a sample of the interview transcript).
However, parts of the recordings that were not clear to the researcher were denoted
with question marks such as this (?????) to avoid guesswork. Bryman (2012)
observed that this approach increases the confidence of the reader in the research
process. The study ensured that each direct quote from the interview was placed in
open and close quotes (“ ”). This was done to ensure that no part of the
interviewee’s response is paraphrased, which could be misleading to the readers.
5.7.2.6 Analysis of Interview
It has been observed that there is no rigid approach for analysing qualitative data as
common with quantitative research, as most times the data type and the creativity of
the researcher prevails (Berg and Lune, 2014; Henn et al., 2006). Content analysis
and coding of themes is the common approach used in analysing qualitative data
(Bryman, 2012; Sanders et al., 2012; Berg, 2007). In this study, the analysis focused
on understanding the trend emerging from the transcribed interviews while also
conceptualising this with the existing knowledge identified in the literature.
The transcribed interviews were grouped into data sets and analysed via content
analysis and coding process. The three coding approaches used in qualitative data
analysis were utilised. These include; axial coding, open coding and selective coding.
While open coding entails close examination of data, breaking down of data into
little chunks, comparing the data, making meaning out of data and data
categorization, axial coding focuses on transforming the data and establishing
relationship between them (Bryman, 2012). On the other hand, selective coding helps
Methodology Chapter Five
132
in validating the identified relationships. The qualitative data analysis process
suggested in Berg and Lune (2014) and Sanders et al., (2012) and as presented in
Figure 5.7 was used in the analysis of the transcribed data. The arrow shows the kind
of iteration that occurred in the data analysis process. This was done to ensure that no
likely themes and subthemes for the study were omitted in the data analysis process.
Figure 5.7: Interview Data Analysis Process used in the Study
Also, the study considered the use of the qualitative software; 6’Nvivo’ to analyse the
interview data given its potentials in managing large data sets (Bryman, 2012).
However, following a closer examination of the nature of the interview questions, the
stage of study, and the size of data collected, manual analysis was considered
appropriate at this stage of the study. Specifically, since this was the first stage of
interviews in this exploratory study, the researcher believed that analysing the data
entirely via a manual means offered the researcher more opportunity to interact with
the data.
This implied that the researcher was actively involved in organising the data and
making sense out of it. Henn et al., (2006) argued that in analysing qualitative data,
computer should be viewed only as a tool to help in storing data, since sense making
out of the data rests with the researcher. Also, considering the fact that the data is not
so large, the manual approach was deemed suitable. However, ’Nvivo’ was still used
in analysing the qualitative data from the multiple case study in the fourth phase of
the study.
6 Software that supports in the analysis of qualitative data
Relate emerging themes to
existing theory and identify new
theory
Review data to identify emerging
themes and patterns
Systematically sort out data
into categories
Read through data to
establish & categorise meaning
Trancription of interviews
verbatim
Methodology Chapter Five
133
The analysis of the interviews commenced with coding. 7The code and themes for
the study were developed based on (A) the interview questions and (B) emerging
themes recognised from the transcribed interview. As earlier explained, the analysis
used both inductive and abductive approaches; this implied that there was a
continuous cross evaluation of the current practice of LPS and CP observed in the
UK with principles of the LPS (Dubois and Gadde, 2002). While an inductive
approach entails making meaning from the analysis to generate theory, a deductive
approach uses predetermined theory to explain the data obtained (Sporrong and
Kadefors, 2014; Dubois and Gadde, 2002). An abductive approach on the other hand
is the third form of inference that seeks the simplest explanation for observations.
Sober (2001) described abductive reasoning as the "inference to the best
explanation". This approach was adopted as it allowed the study to gain new
theoretical insight through the empirical data and the established theoretical model of
the LPS (Sporrong and Kadefors, 2014; Dubois and Gadde, 2002).
Codes were used to identify all the interviewees involved in the study. Code such as
MC01, CO01, CL01 and SC01 were used, where MC= main contractor, CO=
consultants, CL= clients, and SC= subcontractors while 01 indicate the numbering.
Through this, the researcher was able to capture the responses of all the interviewees.
In doing the analysis, the qualitative data analysis protocol in Figure 5.8 was
systematically adhered to. The emerging themes from the analysis were explored to
identify relationship with existing theories of the LPS and detect new emerging
themes. The findings from the analysis, the emerging themes, grouping, and
categorisation of meanings among others are presented and discussed in Chapter 6 of
this thesis. Each finding is critically discussed in Chapter Six in light of the existing
literature and in relation to the objectives of the research.
5.7.3 Stage 3: Structured Observation
Following the second stage of the study (the exploratory interviews), a structured
observation was conducted on projects on the current practice of CP for delivering
construction projects from the PP&C perspective in the UK. Structured observation
also known as systematic observation is a structured approach used to record
behaviour or practice (Bryman, 2012). The aim of the structured observation is to
7 Part of this has been published in Daniel et al, 2016 The relationship between of LPS and CP in the
UK
Methodology Chapter Five
134
enable the study to aggregate the current practice of CP for delivering construction
projects from PP&C in the UK in all aspects of the projects observed. This was done
in a systematic manner in relation to the identified production planning and control
principles advocated in the LPS, so as to identify the level of implementations on the
projects observed and to compare the implementation across sectors.
Structured observation was considered appropriate as the approach allows the study
to capture real time information on PP&C in relation to LPS in the UK construction
industry. According to Bryman (2012), structured observation identifies behaviour or
practice directly, which improves the quality of the data collected rather than relying
on information from questionnaire survey. Also, Cooper and Schindler (2008)
confirmed that structured observation is used when a study is aimed at answering a
research question and it usually provides valid and reliable account of what
happened. It could be used as a primary method or to supplement other methods. In
this study, the structured observation is used as both. All of these supported the aim
of the study at this stage thus, structured observation was used.
5.7.3.1 Observation Schedule
It has been observed that observation schedule influences the reliability and validity
of the data obtained through structured observation (Cooper and Schindler, 2008).
The researcher adhered to the rules for designing structured observation schedule
suggested in Bryman (2012). An observation can be behavioural or non-behavioural
observation approach. However, in this study, only the non-behavioural approach
was used and it includes (Cooper and Schindler, 2008);
Record analysis.
Physical condition analysis.
Physical process analysis.
In record analysis, the researcher observed past records of PPC charts, PPC
calculation sheet, RNC charts, snapshots image of past collaborative or phase
planning meetings and Weekly Work Planning meetings. While in the physical
conditions analysis the researcher observed the currently displayed PPC chart, RNC
chart, collaborative planning /phase planning room, phase planning board or wall
with ‘sticky notes’, the duration of the look-ahead plan on the phase planning board
and the location of information display board. The last phase of the structured
Methodology Chapter Five
135
observation was the physical process analysis, here the researcher developed a
structured survey guide to capture the PP&C based LPS practice as done on each
project (see Appendix 5 for copy on the instrument). The questions were based on a
15 PP&C practices used in examining the degree of implementation of the LPS. This
metric is generally called Planning Best Practice (PBP) index. The PBP indexes were
identified from LPS implementation on several construction projects (Bernardes and
Formoso, 2002; Sterzi et al., 2007; Viana et al., 2010). The identified practices have
been used to examine the implementation of production planning and control practice
in relation to the LPS on construction projects. For example, it was used to examine
12 projects in Israel (Priven and Sacks, 2015); 6 case study projects in Brazil
(Bernardes and Formoso 2002) and in observing 5 projects in Brazil (Sterzi et al.,
2007). It has the capacity to reveal LPS implementation efficacy (Sterzi et al., 2007;
Bernardes and Formoso, 2002). Also, two other PP&C practices identified from the
literature review which the author considered to be crucial were added. In all, 17
PP&C practices were observed across the projects. During the interviews the
researcher was able to obtain further clarifications on all the observations made in the
record and physical condition analysis which was used in rating the level of
implementation on each project.
5.7.3.2 Observation Checklists
The PBP index checklist had three scales; full implementation, partial
implementation and no implementation to capture the state of current implementation
on the projects sampled. This scale was arrived at from previous academic research
on PP&C practices based on the LPS in construction (Bernardes and Formoso, 2002;
Sterzi et al., 2007), and has also been used in observing the level of LPS
implementations in construction (Priven and Sacks, 2015). As this is a snapshot
study, the three point Likert scale was adopted to capture production planning
practices on the projects observed and to also reduce response bias. Dolnicar, et al.,
(2011) and Paulhus (1991) observed from their study that 5-7 point Likert scale
suffers from response bias. More importantly, Dolnicar et al., (2011) Jacoby and
Matell (1974) concluded from their study that the reliability and validity of the
information obtained from an evaluation process has no relationship with number of
steps on the Likert scale. However, Bryman (2012) argued that structured
observation could lack reliability and validity if the observation schedule is not
Methodology Chapter Five
136
followed as supposed. To overcome this, the researcher ensured the observation
schedule described in section 5.7.3.1 was strictly adhered to on the all the 15 projects
observed. Results of the analysis and discussion are presented in Chapter Six of this
thesis.
5.7.3.3 Structured Observation Sampling
This study examined the available sampling strategies in section 5.7.2.5. In
conducting the structured observations, purposive sampling and snowballing
approach was adopted (Bryman, 2012). Purposive sampling was adopted as it
enabled the researcher to identify the projects that met the predetermined criteria
before selection. For instance, the following criteria must be satisfied before
inclusion for observation for PP&C practices based on the LPS:
The project must be managed with PP&C based on LPS
The use of PP&C principle on the project must not be less than a year
The project must be on-going
The project must be domiciled in the United Kingdom
These criteria were used to ensure only projects that claimed to use LPS principles
were observed. According to Bryman (2012), and Cooper and Schindler (2008), for
structured observation data to be valid and reliable, the observation criteria must be
uniform across the sampling elements. The sample elements were drawn from
building, highways infrastructures, and rail projects. The three sectors were chosen
as the study aimed at presenting the current PP&C practices across the major sectors
in the UK construction industry. Originally, 15 projects were targeted with 5 from
each of the sectors.
Although 15 projects were accessed, they were not equally distributed as proposed
earlier in the study. This was due to the inability of the researcher to gain access to
sufficient rail projects that are using PP&C principles based on the LPS. The actual
15 projects observed comprised; 8 highways infrastructure, 5 building, and 2 rail
projects. The building projects observed include; a social housing, and new build for
an institution of higher learning among others. The projects were coded with
alphabets (A= highway infrastructure project; B= building projects and C= rail
projects, while the numeric 01 represents the project numbering).
Methodology Chapter Five
137
On each of the projects observed, in addition to record and physical condition
analysis, semi-structured interviews were conducted with all those involved with the
implementation of PP&C principles based on LPS on the projects. The respondents
interviewed include lean improvement managers, principal planning engineers,
planners, project managers, site managers, site agents, and excellence manager.
Purposive sampling was used in selecting the projects and respondents. This was to
ensure that only those with experience in PP&C practices were interviewed and
projects where PP&C principles were used were observed.
5.7.3.4 Data Collection and Analysis of Structured Observation
In collecting the data, the researcher personally visited the physical setting (the
project site). An average of 5 hours was spent on each of the projects on a day site
visit. This afforded the opportunity to collect data on ‘record analysis’, ‘physical
condition analysis’, and conduct of interviews. A camera was also used to capture
parts of the physical setting that are of interest to the study after securing necessary
approvals. However, during the site visit, the researcher was only able to have access
to the middle line managers such as the planners, site engineers, site managers, site
agents among others.
Other project members such as the top managers, subcontractors and supply chain
members, foremen etc were not reached. This was due to the day access visit given to
the researcher on each of the 15 projects observed, which was not sufficient to have
conversation with all the stakeholders concerned with PP&C practice. This was
considered as a major limitation of this approach, as there is a high possibility that
the responses could be one sided. However, the limitation was overcome in phase 3
of the study.
All the data collected from the projects observed were grouped into data set under
the three main schedules used in collecting the data. Data from the record and
physical condition analysis were analysed using content analysis. The procedure for
conducting content analysis as suggested in Berg and Lune (2014) was adopted.
Simple descriptive statistics such as percentages was used in analysing the level of
PP&C practices based on the LPS on the projects observed. The result was presented
using tables, and charts and discussed in Chapter Six of this thesis.
Methodology Chapter Five
138
5.7.4 Stage 4: Multiple Case Study
The justification for the use of case study has been discussed in section 5.6.5 of this
thesis. This section presents a detailed account of how the case study was conducted.
Figure 5.8 presents the overall case study design.
Understand
theory
Findings
from
interviews/
structured
observed
Literature
and IGLC
reviews on
LPS and CP
Select case
Design data
collection
protocol
Conduct
case study
1: Highway
Case study
2: Highway
Case study
3: Building
Write
individual
case report
Write
individual
case report
Write
individual
case report
Draw cross-
case
conclusion
Check for
alignment
with theory
Write cross-
case report
Figure 5.8: Case Study Research Design
The major aims of the case study were;
To identify the nature of support to provide for effective implementation of
the LPS;
To identify the impact of the current practice of PP&C based on LPS on
construction process improvement;
To examine the influence of procurement route on the implementation of
PP&C principles based on the LPS and
To further validate the findings from the exploratory interviews and snapshot
observations on the current practice
To achieve the above objectives, the study needed a detailed consideration and
interaction with the physical settings (the project site) which could not be addressed
in stages 1-3 of this study. Thus, the case study approach was adopted. Bryman
(2012) observed that the case study approach focuses on intensive examination of the
physical setting in order to provide empirical evidences of the phenomenon being
investigated. The case study also offers the study the opportunity to interact with all
the major stakeholders in order to fully understand the support needed for effective
implementation of the LPS. It also supports the development of LPS-PCA.
Methodology Chapter Five
139
Multiple case studies were considered appropriate at this stage, as they best support
the study to holistically achieve the above mentioned objectives. According to Yin
(2014), the analytic results from two or more cases are more powerful compared to a
single case situation. The subsequent section describes the case study planning, case
study selection, data collection protocol, and process among others.
5.7.4.1 Case Study Planning
Planning has been identified as a crucial element to consider in conducting a case
study (Yin, 2014). Here, the researcher considered the overall case study research
process with due recognitions of the likely issues (weakness and strength of the
approach) that could occur in each phase of the case study. In view of this, an
extensive literature review in section 5.6.5 of this thesis was devoted to it. In
planning the case study, all the likely constraints such as the difficulty in having
access to the site, research respondents, and documents, which all have an influence
on the overall case study duration were considered. For instance, the negotiation for
case study started immediately after the researcher’s project approval, which was six
months ahead of the proposed case study commencement date as stipulated in the
researcher’s programme for the study.
The 3 case studies were conducted independently, but simultaneously between
January and October 2015. The process was demanding and cost intensive as the
researcher had to travel several miles each week since the 3 projects are widely
dispersed geographically. However, it paid off as the researcher was able to complete
all the case studies as programmed.
5.7.4.2 Case Study Selection
In selecting the cases, various factors associated with case study design as suggested
in Yin (2014) and Bryman (2012) were adhered to. It is important that cases are
selected carefully to avoid a condition where the evidence obtained is insufficient to
answer the research question (Yin, 2014). In view of this, the researcher and the
supervisory team selected 3 cases to be studied from the major sectors of the UK
construction industry. These case studies were chosen as they would allow the study
to also compare practices across the industry. Two of the cases are from the
Highways and infrastructure and one from the building sector.
Methodology Chapter Five
140
No case was chosen from the rail sector as it has already been observed from the
snapshot study in stage 3 that rail projects, share similar characteristics (linear
construction) with highway and infrastructure projects. The focus of the study was to
develop an approach that could support LPS implementation across the UK
construction industry, thus selecting case studies from the major sectors was
considered appropriate. This was also to ensure that the cases were sufficient to give
a true reflection of the current state of the practice in the UK construction industry.
The three cases were selected from the top 100 UK construction companies.
Purposive sampling was used in selecting the cases. Bryman (2012) stressed that
purposive sampling allows the researcher to select case(s) in order to answer the
research question. For instance, the researcher and supervisory had to agree on the
criteria for selecting the cases. The criteria used include:
The project must be managed using PP&C based on LPS principles
The project must be on-going
The project must be in the construction sector and domiciled in the UK and
Must be in a safe zone and accessible to the researcher in terms of the cost of
visiting the project site as required for the study
Initially, the researcher sent out invitation letter to construction organisations in the
UK construction industry based on background information acquired on them in
stages 2 and 3 of this study. Four organisations accepted to participate in the case
study. In order to ensure that the criteria above are satisfied, further investigation was
done with the respective project managers before signing of the consent form (see
Appendix 6 for a copy) and commencing of the study. From the background check, it
was observed that in one of the projects, LPS principles were not being used as
claimed; rather, the project was only attempting to adopt work zoning in a sloppy
way. Thus, only the 3 case studies that satisfied the above criteria were studied.
It has been observed that it is essential to maintain a balance in selecting the cases to
be investigated, as it helps in strengthening the study results (Yin, 2014; Stake,
1995). The researcher ensured this was observed in selecting the cases. For instance,
the two cases selected from the highways and infrastructures were chosen because
the researcher desired to maintain a balance in the procurement routes. While one
used Design & Build (D&B) procurement route, the other used traditional Design,
Methodology Chapter Five
141
Bid, and Build (DBB). The choice was made since the study aimed at understanding
the influence of procurement routes on the implementation of LPS in construction.
The third case was from the building sector and it used Design & Build procurement.
This balance enabled the study to sufficiently compare the practices across projects
and sectors. On all the projects studied, the population sample had similar
characteristics. The population was broadly classified into four categories; the top
managers, the middle managers, subcontractors and the lower managers.
The researcher believed that focusing on all of these categories was necessary as
their inputs were essential in developing an approach that supports construction
stakeholders in implementing the LPS in construction. Two of the case study projects
were located in Yorkshire (one in the North of Yorkshire and the other in the West of
Yorkshire). The third case study project was located in the Midlands. All the three
case study projects were located in England. The researcher’s institution of study is
based in England, which offered more opportunity for detailed investigation at a
reasonable travelling cost and time. The finding on this is discussed in Chapter
Seven.
5.7.4.3 Data Collection Protocol
According to Yin (2014), preparation for data collection is crucial in every case
study, as failure in this aspect could thwart all the efforts committed into formulating
the research question and the case study in general. In view of this, after selecting the
cases a data collection protocol was developed in conjunction with the researcher’s
supervisory team. Contact was made with a senior manager on each of the projects
selected and the researcher discussed the major evidence sourced from the case
study. The overall aim of the study was discussed with the senior manager and the
formal consent form signed. The evidence sourced by the researcher on each case
includes; analysis of documents (past and present), observations, and conduction of
interview with top manager, middle managers, subcontractors, and bottom managers.
These three sources were used in order to triangulate the findings.
The schedule of site visits (to attend look-ahead planning meetings & weekly
production planning meetings) was also agreed with the head of the team on each
case study project. This allowed the researcher to visit each of the sites routinely.
Furthermore, the researcher informed each of the case study project, representatives
Methodology Chapter Five
142
of his involvement in other case studies. This was to ensure that there was no clash in
fixing the site visits. Additionally, ethical issues were considered at this point, and
formal invitation letter was given to all the proposed research participants (see
Appendix 3 for a copy of the invitation letter to the interview participants). This was
done to reassure the research participants of confidentiality. It has been observed that
when research participants are reassured of their confidentiality, the quality of the
information given out is improved (Creswell, 2007). Through this, the researcher was
able to develop a strong relationship with the research participants and also build
their confidence in the study.
5.7.4.4 Data Collection
On each of the case study projects, data were collected from three major sources.
This includes; documentary evidence, observations and semi-structured interviews.
The three approaches were used in deepening and authenticating the results (Yin,
2014). Although, the data collection from the three sources as shown in Figure 5.9
continued throughout the case study period, each case study actually started with
observations and document analysis as soon as the researcher was given access to
project.
Figure 5.9: Case Study Data Collection Sources
This approach enabled the researcher to seek further clarification on the findings
from the observations and documentary evidences during the interviews. Each
approach is now discussed in detail in the next section.
A. Documentary Evidence
Documentary evidence has been identified to provide useful information in
collecting both primary and secondary data to answer research questions (Sanders et
Data
collection s
ourc
e
Documentary evidence
Observation
Semi-structured interview
Methodology Chapter Five
143
al., 2012). In this study, all the documentary evidences sourced were those relating to
production planning. This includes documents such as construction programme,
Look-ahead plan, weekly work plan sheet, progress reports, published PPC,
published RNC, minute of collaborative programming or phase planning meetings,
and work make-ready worksheet among others. Bryman (2012) asserted that
document evidences are credible and non-reactive since they were not designed
specifically for the study. However, Berg and Lune (2014) observed that having
access to documents in an organisation could be difficult as some ‘gatekeepers’
(those responsible for granting access to the site) could be reluctant about it.
The researcher built personal relationship with the gatekeeper on each case project
and this allowed full access to the necessary documents. Even after the formal
completion of the case study, minutes of meetings were still being sent to the
researcher as he was put on the project team email list. The documentary evidence
obtained in each case study were critically reviewed. Through this, the researcher
was able to establish some of the current practices of production planning and control
practice on the projects. Snapshots of documents displayed visually on the case
project were also taken, others were photocopied, and some sent electronically to the
researcher’s email. The result of the document analysis is presented in Chapter Seven
of this thesis.
B. Observation
To gain full understanding of the current practices of production planning and
control on the projects and to further identify issues associated with the practice,
practical observation was considered essential. This approach allowed the researcher
to relate the observed practice with the project setting. Bryman (2012) stressed that
observation of the social setting where the phenomenon is being investigated allows
the researcher to sufficiently map out the link between participant behaviours and the
context. In this study, the focus in the observation was production planning and
control based on LPS principles.
Specifically, the researcher observed each production planning and review meetings
on all the three case study projects. This was considered essential as it enabled the
researcher to observe core principles advocated in the LPS while conducting the
production planning meeting. Such principles include the nature of conversation
Methodology Chapter Five
144
(collaborative or non-collaborative) used during production planning meetings, the
level of involvement of stakeholders in the projects, the number of stakeholders in
each meeting, the process of making reliable promises, how plans are reviewed and
recorded, and consideration for the flow of information during planning among
others. It is worth to mention here that unlike the third stage of the study, the
observation is unstructured. However, the researcher kept an up to date diary of all
the observations on each project for cross case analysis and development of themes
and reflected on this for further observations.
The observation was unstructured to enable the researcher widen the scope and to
allow the themes to emerge naturally. On the project sites, the researcher also
observed information display boards, location where PPC and RNC information were
displayed and images of some of the observed features of interest were taken. Further
information was sought on some of the observed features during the interview.
C Semi-structured Interview
The rationale for the use of semi-structured interview has been justified in the earlier
part of this chapter. In developing the semi-structured interview guide, the literature
review, findings from the document analysis and observation on each case projects
were used. More importantly, the interview questions were such that all the
objectives of the case study identified earlier in the section 5.7.4 were sufficiently
answered. The semi-structure interview guide consists of five major sections (see
Appendix 7 for a copy). As earlier explained, some of the case study questions, in
particular sections 2 to 4 were asked to further validate the findings from the
exploratory interviews.
However, the semi-structured interviews on the case study were more holistic as
major stakeholders on the project were interviewed, thus reducing the level of bias in
the overall finding. The respondents interviewed were drawn from top managers,
middle managers, subcontractors, and bottom line managers on each case project.
In conducting the interviews, the process used in stage two of this study was adopted.
On each of the case study projects the manager charged with the responsibility of
managing production planning arranged the interviews for the researcher from the
list of desired interviewees designed and made available to him/her by the researcher.
Most of the interviews took place before or after the phase planning or collaborative
Methodology Chapter Five
145
programming meetings. This approach enabled the researcher to maximise his time
during each project visit and minimise cost of travelling.
Before the actual date of each interview, the researcher sent out an invitation to
interview letter to the interviewee through the production planning manager or
facilitator on the project. Also, the personal relationship developed with the
interviewees during production planning meetings improved the quality of response
received during the interview session. The researcher audio recorded all the
interviews with a mobile recording application known as ‘Recordium’.
5.7.4.5 Data Analysis
Evidence for the analysis was obtained from four major sources; documentary
analysis, observation, semi-structured interviews and the mini survey. All the data
collected were grouped into data set and placed in folders/files for each case study.
The interviews were transcribed verbatim and cross checked with findings from
documents analysis and observation. All the data obtained were analysed
qualitatively, except the closed ended mini-survey that was analysed using simple
descriptive statistics. The four sources were fully triangulated to improve the validity
of the case study. Each source of evidence was analysed individually and cross
analysed to arrive at the converging point of inquiry. Figure 5.10 presents the data
analysis process.
Documentary
evidence
Observation
Semi-structured
interviews
Analysis
Analysis
Analysis
Cross case analysis
Case study analysis
process
Mini-survey Analysis
Figure 5.10: Case Study Analysis Process
Yin (2014) observed that triangulating data from multiple sources supports the
development of the converging point for research findings and, thus strengthens the
validity of the study. In addition to transcribing the interview verbatim, other
Methodology Chapter Five
146
qualitative data, such as observation, and document analysis were word processed to
enable the researcher to make appropriate meaning out of them. This process is time
consuming, but it enabled the researcher to maintain flow in interacting with the data
and making meaning out of them. The case studies were coded thus; CSP01, CSP02,
and CSP03 which referred to case study projects 1, 2, and 3 respectively. The case
studies were denoted with these codes for confidentiality purpose. On each case
study, senior manager (SM), middle manager (MM), operational managers (OP), and
subcontractors (SC) were interviewed. Figure 5.11 shows the distribution of
interviewees across the case studies. A total of 28 interviews were conducted from
the three case study projects (11 on CSP01, 10 on CSP02, and 7 on CSP03). This
was to enable the study to have a holistic view on the current practice and the nature
of support to be provided for rapid and successful implementation of the LPS in the
UK construction industry.
Figure 5.11: Distribution of Interviewees across the Case Studies
Full description of the case studies is presented in Chapter Seven. The interview
analysis process described in section 5.7.2.6 was used in analysing the interview
results from the case studies. However, in this phase, the process was fully supported
by the Computer Aided Qualitative Data AnalysiS (CAQDAS) software known as
‘NVivo’. The software was used due to the large nature of the data. According to
Silver and Lewin (2014) and Bryman (2012), ‘NVivo’ software does not only manage
large data set, but it also supports transparency, replicability and validation of
0
1
2
3
4
5
6
CSP01 CSP02 CSP03
Distribution of interviewee across the case studies
Senior manager Middle managers Operational manager Subcontractors
Methodology Chapter Five
147
qualitative data. This is made possible as it provides a single platform to
systematically organise and interrogate qualitative data from different sources. It also
supports the analysis of quantitative data such as survey alongside qualitative data
such as interviews among others (Silver et al., 2015). In this study, qualitative data
were obtained from three sources; interviews; observation and documents analysis,
and different folders were created for them using NVivo version 10 in the internal
source folder. A folder was created for the mini-survey here too. This supported the
researcher in managing the collected data effectively and efficiently.
The obtained qualitative data were reduced as suggested by Miles and Huberman
(1994). The recorded interviews were transcribed verbatim and word processed. The
collated data were grouped into data sets and analysed via content analysis and
coding process. In doing this, the data was categorised based on qualitative data
analysis techniques after Miles and Huberman (1994). The word processed
interviews from the three case studies were exported into NVivo 10 for coding of the
emerging theme. The code and themes for study were developed based on (A)
identified theme from literature (B) the interview questions and (C) emerging themes
recognised from the transcribed interview. The concept tree presented in Figure 5.12
was used in capturing the emerging themes and sub-themes before their coding and
linking of ‘Nodes’ in NVivo 10.
Emerging theme 1 Emerging
theme 2 Emerging theme 3
Emerging theme 4
Sub-theme
Sub-theme Sub-
themeSub-
theme
Figure 5.12: Emerging Concept and Theme Tree
Again, this shows that the strategy for analysing the data was developed by the
researcher and not the software, thus the richness and quality of the result of the
Methodology Chapter Five
148
interview were still preserved as a result of the full interaction of the researcher with
data in the analysis process. Silver and Woolf (2015) observed that strategies are
developed outside the software, while tactics relies on the software tools to analyse
the data. The emerging themes and sub-themes were coded and linked with Nodes to
enable the researcher capture what the respondents are saying on the emerging
themes and cross analysis of the findings. The ‘model’ tool in NVivo 10 was used to
analyse and graphically present emerging themes and sub-themes. Figure 5.13 shows
a sample on emerging themes and sub-themes on procurement practice on CSP01 as
exported from NVivo 10 using ‘model tool’. The remaining findings are presented
and discussed in Chapter Seven.
Figure 5.13: Result of procurement practice on CSP01 graphically presented with ‘model
tool’ as exported from NVivo 10
5.7.4.6 Cross Case Analysis
The three case studies were analysed individually and then subjected to cross case
analysis. Yin (2014) suggested that a case study report should contain the individual
case study and cross case analysis. Also, Miles and Huberman (1994) observed that
cross case analysis supports the generalisation of findings across the case and offers a
better understanding of the phenomenon investigated. The cross case study analysis
Methodology Chapter Five
149
enabled the study to identify the current practices and the nature of support required
for effective implementation of LPS and the impact of the current practices on
construction process improvement. The cross case study analysis is presented and
discussed in relation to literature in Chapter Eight.
5.7.4.7 Post Case Study Evaluation Survey
At the end of the case study, a mini survey was designed to access the impact of
PP&C practices on construction process improvement. Participants were drawn from
stakeholders that participated in the case study. The post case study evaluation
instruments consisted of two major sections (see Appendix 8 for a copy). The
instrument has both closed end and open ended questions. The closed ended
questions were used by the researcher to seek some objectivity with regard to the
impact of the PP&C practices and to also compare this across the cases. According to
Bryman (2012), closed ended questions enhance comparison of results and also
reduce variability in recording responses.
The closed ended questions focused on understanding the impact of PP&C practices
on time, quality, rework, safety, and collaboration among others on each case study.
This was measured on five point Likert scale with 1= strongly disagree and 5=
strongly agree. Three points Likert scale was not used here because it would limit the
research participants’ response. The five point Likert scale provides allowance for
more choice to be made. It also has the potential to relay or measure the level of
agreement of the respondents with the statement. Unlike one indicator that could
limit the response of the respondents (Bryman, 2012). The last part of the survey
questions were open ended, and they centred on the respondents’ views on PP&C
practices as witnessed on the project and the identification of likely support needed
for its effective implementation. The results are presented and discussed in Chapter
Seven.
5.7.5 Phase 5: Development and Validation of Last Planner System Path
Clearing Approach
Stage 5 which was the last stage of the study, dealt with the creation and evaluation
of the LPS-PCA. The aim of the LPS-PCA was to support construction stakeholders
(client, main contractor, subcontractor) to develop an understanding of what needed
to be in place for the implementation of the LPS. Stages 1 to 4 of this study formed
Methodology Chapter Five
150
the building blocks for the development of the LPS-CPA. In developing this
approach, the requirements for implementing LPS in construction were identified in
stages 1 to 4 of this study. Also, the drivers, success factors, barriers, and mismatches
in the current practice of implementing LPS were identified and characterised. To
access the usability of the LPS-PCA, an evaluation checklist was developed (see
Appendix 9 for copy). Ten participants were purposively sampled to participate in
the evaluation, while six participated, four did not. Full description of the evaluation
process is provided in chapter 8 of this thesis. The feedback from the evaluation was
used to refine the initial LPS-PCA approach developed. All the major stakeholders
were involved in the evaluation process to reduce bias in the result. The result from
the evaluation and preliminary findings from pilot implementation of LPS-PCA are
presented and discussed in Chapter Eight.
5.8 Quality of Research
In assessing credibility and quality of a research, criteria such as validity and
reliability are used (Bryman, 2012; Sanders et al., 2012). According to Bryman
(2012), reliability and validity are commonly used in quantitative researches and
have also been adapted in assessing the quality of qualitative researches. However,
Guba and Lincoln (1994) suggested parallel names for this in qualitative research as
shown in Table 5.7.
Table 5.7: Research Quality Criteria
Name in Quantitative Research Equivalent name in Qualitative Research
Internal validity Credibility
External validity Transferability
Reliability Dependability
Objectivity Confirmability
The efforts made by the researcher to improve the quality of the research by
minimising or achieving these are highlighted below.
5.8.1 Credibility (Internal validity)
The key question asked here is how believable are the research findings (Bryman,
2012)? The study overcame this by collecting data on the social reality being
Methodology Chapter Five
151
investigated (PP&C practices) from multiple sources such as on building, highways,
and rail projects using different methods. The researcher observed all the standard
procedures required for the study by diligently explaining the purpose of the study to
the participants. This was done in addition to the invitation to participate in the study
letter sent earlier to the respondents which captured the purpose of the study. Also,
the final research output, that is, the LPS implementation approach was made
available to the research participants for validation and feedback. All the methods
were fully triangulated. The researcher had a prolonged engagement with the social
setting as it supports the quality of the research result (Seale, 1999; Guba and
Lincoln, 1994); in this study, over 12 months was spent in interacting with social
setting.
5.8.2 Transferability (External validity)
This focuses on ascertaining the application of the findings in another context for
generalisation. Although, the focus of this study was not to generalise the findings,
effort was made in achieving external validity in the findings via the use of
replication logic in conducting the 3 case studies in different project environments
(settings) (Yin, 2014). Findings were also obtained from external participants who
were not part of the case studies such as the interview participants in stage 2 and
structured observation participants in stage 3. Also, detailed description of the case
study context was given. This would provide readers with sufficient information to
judge the application in another setting (Seale, 1999). Furthermore, the study sample
cuts across the major high profile companies in the UK and the sample comprises the
major stakeholders in the industry.
5.8.3 Dependability (Reliability)
This refers to the possibility of applying the current findings at other times. It has
been observed that to achieve this, full documentation of the research process is
imperative (Bryman, 2012; Seale, 1999; Guba and Lincoln, 1994). The study
achieved this by developing standard protocols for data collection for the exploratory
interviews, structured observation, case study and the mini post case study
implementation survey (see Appendices 1 and 6). Only in very few cases were some
of these protocols altered slightly to meet the reality on site. These standard protocols
were used in collecting data at each stage to maintain consistency. In addition to
Methodology Chapter Five
152
keeping field notes and memos, the interviews were audio recorded and transcribed.
Detailed description of the methodology and the methods used for the study were
fully documented. Also, the research instrument and the data collected were further
audited by the researcher’s supervisory team.
5.8.4 Confirmability (Objectivity)
The consideration here is to know what extent the researcher’s personal values
influenced the research findings. It is well known that complete objectivity cannot be
realised in a social science research (Bryman, 2012), however, this study used
various approaches to improve it. The study used multiple approaches to collect data
and the data from each source were analysed independently. Also, more objective
responses were collected in stage 3 in the post implementation survey which further
helped in confirming the qualitative data in stages 2 and 4 and in the evaluation of
the developed LPS-PCA in stage 5. Standard data collection protocol was developed
for each stage of the study which guided in collecting and interpreting the data. This
helped the researcher in maintaining a neutral position. Furthermore, all stages of the
study were constantly audited by the researcher’s supervisory team.
5.9 Summary of Chapter
This chapter established the philosophical assumptions underpinning this study.
From the description of the various research paradigms such as positivism and
interpretivism, the chapter demonstrated why mixed research paradigm is the
appropriate paradigm for the study. This was because the study required both
qualitative and quantitative approaches to answer the research aim and objectives.
The chapter showed that research philosophy and paradigm influence the choice of
research methodology and methods used in a study. However, some researchers pay
less attention to this, thus mixing up the research process. The chapter provided
detailed description of the various stages (1 to 5) of the research and the justification
for the methods adopted.
This chapter demonstrated that the study was built on robust research methodology
and methods. This suggests that the evidences provided and discussed in the
subsequent chapters could be relied upon. The chapter captured some of this by
providing the detailed account on how each method and approach were fully
Methodology Chapter Five
153
triangulated. This includes research approach triangulation as demonstrated in the
mixed method approach and also the triangulation within methods such as collecting
evidences from different sources as in the case of the structured observation and the
case study. The chapter also showed the measures taken to improve the quality of the
research findings with regard to the validity and reliability of the study. The next
chapter (Chapter Six) presents and discusses the findings from the 30 exploratory
interviews and the structured observations.
154
CHAPTER SIX: RESULTS AND
DISCUSSIONS ON EXPLORATORY
INTERVIEWS AND STRUCTURED
OBSERVATIONS
6.1 Introduction
The previous chapter provided detailed information on the methodology and methods
used in gathering evidence for answering the research question. This chapter presents
and discusses the evidence gathered from the exploratory interviews and structured
observations. Section 6.2 discusses the findings from the semi-structured interview
on the current understanding and application of production planning and control
principles based on the LPS in the UK. In section 6.3, the results from the structured
observations on these practices from three different sectors in the UK construction
industry are discussed. The chapter presents a general discussion on all the findings
in section 6.4. It also provides an overview of the chapter summary in section 6.5.
This chapter provides empirical evidences on how the current understanding and
application of “Collaborative Planning” (CP) for delivering construction projects in
the UK align with the advocated principles of the LPS.
6.2 Phase 2: Semi-Structured Interviews
6.2.1 Analysis, Presentation, and Discussion of Semi-Structured
Interviews
In this chapter, the term Last Planner System/ Collaborative Planning (LPS/CP) is
used to describe the application of production planning and control (PP&C)
principles based on the LPS in the UK construction industry. This chapter only
presents and discusses the findings as the process used in collecting the data has been
discussed extensively in the methodology chapter (Chapter Five). The findings
presented and discussed in this section include: current view on construction
planning and programming, current industrial perception on Last Planner System and
Collaborative Planning in the UK, current success factors and drivers for
Exploratory Interview and Structured Observation Chapter Six
155
implementing LPS/CP in the UK and the current benefits and barriers for
implementation of the process in the UK.
6.2.2 Demographic Information of Interviewees
8Table 6.1 gives an overview of the distribution of the respondents across the 3
sectors (building, highway infrastructure, and rail) considered in the study. This
suggests that the findings from this study should broadly reflect the current practice
of production planning and control in the UK construction industry. The analysis of
the interview response reveals that 60% are from main contractors, 20% are
subcontractors, 13.3% are consultants, and 6.7% of respondents are clients. Since all
the major stakeholders are represented in the interview, the level of bias in the
findings is minimised and objectivity is improved.
Table 6. 1: Descriptions and Distribution of Interviewees across the UK Construction Sector
Respondents Code Sector Years of exp. in
PP&C
Years of exp. in
construction
MC01 Highway and
Infrastructure
5 18
MC02 Highway and
Infrastructure
3 17
MC03 Highway and
Infrastructure
4 15
MC04 Highway and
Infrastructure
4 6
MC05 Highway and
Infrastructure
5 11
MC06 Highway and
Infrastructure
5 10
MC07 Highway and
Infrastructure
4 10
MC08 Building 10 10
MC09 Building 10 30
MC010 Building 12 20
MC011 Building 5 15
MC012 Building 6 15
MC13 Highway and
Infrastructure
6 18
8 Part of this has been published in Daniel, Pasquire Dickens and Ballard(2016). The relationship
between the Last Planner System and collaborative planning in UK construction
Exploratory Interview and Structured Observation Chapter Six
156
MC14 Highway and
Infrastructure
5 10
MC15 Highway and
Infrastructure
4 30
MC16 Rail and
Infrastructure
12 30
MC17 Rail and
Infrastructure
3 30
MC18 Building 4 4
SC01 Highway and
Infrastructure
5 21
SC02 Highway and
Infrastructure
4 20
SC03 Building 6 15
SC04 Highway and
Infrastructure
4 10
SC05 Building 5 15
SC06 Highway and
Infrastructure
3 6
CO01 All sectors 10 32
CO02 All sectors 14 26
CO03 All sectors 15 15
CO04 All sectors 10 20
CL01 Building 3 11
CL02 Highway and
Infrastructure
10 30
MC= Main contractor, SC subcontractor, CO= Consultants, CL= Client
In terms of experience in the application of production planning and control (PP&C)
principles, the analysis reveals that, 53.3% claim to have 3-5 years’ experience while
43.7% have 6-15 years’ experience. This suggests that the respondents have some
knowledge of the practice. Also, in terms of the interviewees’ experience in the
construction industry 46.7% have 6-15 years’ experience, 30% have 16-25 years’
experience, and 23.3% have over 26 years’ experience. This implies that the majority
of the respondents have significant experience in the UK construction industry, thus
enhancing the quality and richness of the data obtained. It is worth stating that this
also indicates that the practice of PP&C based on the LPS is still new in the UK
construction industry. However, one of the respondents (CO03) claimed to be
Exploratory Interview and Structured Observation Chapter Six
157
practising PP&C since joining the construction industry. This could be so since the
respondent is a consultant and could have come into the industry as a lean consultant
from another sector.
Comparing the knowledge of the respondents in PP&C practice to their years of
experience in the construction industry gives an indication that the traditional
approach of managing construction has been the dominant practice in the industry.
The implication of this is that undoing or unlearning this traditional approach could
be difficult. Ballard and Howell, (2004) observe that construction projects have since
been viewed as managing contracts rather than managing production.
Figure 6.1: Positions Occupied by Interviewees
The respondents occupy various posts in their organisations as shown in Figure 6.1.
The figure reveals that majority of the respondents are those charged with the
responsibility of managing and developing construction programmes in their
organisation. This implies that the information provided by them on the application
of PP&C principles could be relied on. Also, all the respondents occupied positions
at levels ranging from strategic to operational in the organisation, which supports the
study to capture a wide perspective on the current practice in the industry. It further
shows that the respondents are directly involved in the implementation process as
well as preparation.
0
2
4
6
8
10
12
SeniorPlanner/programme
manager
Improvementmanager
Site engineer Project manager Director
Exploratory Interview and Structured Observation Chapter Six
158
6.2.3 Current View on Construction Planning and Programming.
All the respondents interviewed agreed that construction planning is usually driven
by the master programme which is developed for the client, with professional advice
depending on the nature of the contract. For example, in a design and build (D&B)
contract with reference to the client, the master programme is developed by the D&B
contractor. While in a traditional arrangement, the main contractor may develop the
contract programme. However, the start and finish dates are still determined by the
client in both cases. One of the interviewees stated that:
“We start the programme in the traditional way with the Primarvera and Bar
Chart programme, the client gives the start and finish date” [Senior Planner
MC05].
Again, this shows the use of master programme or contract programme in
construction planning has not changed, and the drive for its use in the future is still
very strong. On all the projects observed, the master programme form the basis of
other programmes developed and used in managing the construction processes. From
the analysis of the interviews, four major themes emerged that describe the master
programme as currently seen by construction practitioners. This is shown in Figure
6.2.
Figure 6.2: Current View on Master Programme
Un-collaboratively developed
Too much assumptions and unrealistic
Complex and unfriendly
Contract and reporting document to client
Exploratory Interview and Structured Observation Chapter Six
159
6.2.3.1 Un-collaboratively developed
The respondents were of the opinion that the master programme is usually developed
by the planner and activities durations are usually arrived at based on the experience
of the planner. This was clearly captured by one of the respondents;
“The client planner will develop this information based on the outline design
available at the time resulting in a very high level master programme.
Overall durations, sequence, and logic are stipulated by the client’s planner
in the master plan and are dependent on the knowledge and experience of the
client’s planner to produce a realistic programme”.[MC11 Senior Planner]
This suggests that those responsible for doing the work are not actually involved in
developing the master programme, that is the concept and the implementation are
separated. This evidence further supports the claim that the current approach used in
the design, planning and construction could be likened to the rational comprehensive
model (RCM) where it is believed that the knowledge needed for planning is with the
chief planner alone (Daniel, et al., 2014). However, according to Hayek, (1945) the
knowledge needed for planning and allocating of resources is usually dispersed
among individuals. The implication of developing the master programme un-
collaboratively is that it cannot benefit from the expertise of the people doing the
work, thus cannot be used to manage production and resources effectively on site.
6.2.3.2 Too much Assumption and Unrealistic
The study revealed that the duration of activities in the master programme are based
on assumptions of the programme and they are unrealistic. A main contractor
explained that though they usually received input from the subcontractors and
specialist contractors in developing the tender programme, he stated that these
durations were not realistic. He stated that:
“As you know, the duration given by subcontractors at this time is usually
wrong”. [MC16 Senior Planner]
Another respondent also mentioned that at the tender stage, information may be
limited.
“It must be noted that at this stage, the contractor is very much in ‘sales mode’
and there is an increased emphasis on winning the project and giving the client
Exploratory Interview and Structured Observation Chapter Six
160
what they want so as not to disadvantage themselves in the face of
competition” [MC11, Senior Planner]. “
These findings also conform with those of Johansen and Greenwood, (1999) where
they concluded that construction programming is usually done under pressure and the
desired commitment to develop a realistic programme is lacking. They observed that
in reality, construction programme is based on ‘guesstimation’ and activity durations
are usually fudged.
6.2.4 Current Industrial Perception of Last Planner System and
Collaborative Planning in the UK
The analysis of the interview results reveals 5 major themes on the current industrial
perception on the LPS and CP in the UK construction industry as production
planning and control approaches. These themes are presented in Figure 6.3 and
discussed in section 6.2.4.1
Figure 6.3: Current industrial perceptions on LPS and CP in the UK
CP and LPS
6.2.4.1 Use of the terms “Collaborative Planning” and “Last Planner System”
The study revealed that there is confusion over the use of the terms “Last Planner
System” and “Collaborative Planning” in the UK. Respondents all recognised the
term CP and approximately 70% recognised the term “LPS” although often calling it
simply “Last Planner”. Some respondents used the terms CP and LPS
interchangeably without any distinction in meaning. Some of the respondents stated
that they were not using the term due to the trademark on the LPS. Here are some of
the transcripts:
Current industrial perceptions on LPS and CP in the UK
Use of the term CP and LPS
Meaning ascribed to CP and LPS
Time and programme
compression
Common understanding of
construction programme
Use as an intervention
measure on the project
Exploratory Interview and Structured Observation Chapter Six
161
“We are not using the term ‘Last Planner’ on our project because of the
trademark on it, we choose to call it collaborative planning, it is easier for
the team to understand” (MC02), “To us here, collaborative planning and
last planner are the same, we take the principles of the last planner to suit
our project” (MC08) “Collaborative planning is the name for LPS in the
UK” (CO01).
To understand this confusion of terms, it is worth noting that majority of the
respondents had received some form of support from external lean construction
consultants before the application of CP/LPS on their projects. These consultants do
not as a rule use the term “Last Planner System” because the trademark registered in
the USA by Lean Construction Institute prohibits unregistered consultants from
selling LPS training and consultancy (U.S. Patent No. 3020113, 2005).
However, regarding the direct impact of the US trademark on UK practitioners, the
information available from the United State Patent and Trademark Office (USTPO)
indicates that: a mark is only protected in the country where it is registered except if
such mark is registered in another country under the international Madrid protocol
(USPTO, 2016). Also, Trademark legal practitioners have also offered explanations
on the impact of a mark in a country outside it registration. For instance BITLAW
states that:
“A mark is infringed under U.S. trademark law when another person uses a
device (a mark) so as to cause confusion as to the source or sponsorship of
the goods or services involved. Multiple parties may use the same mark only
where the goods of the parties are not so similar as to cause confusion among
consumers. Where a mark is protected only under common law trademark
rights, the same marks can be used where there is no geographic overlap in
the use of the marks. Federally registered marks have a nation-wide
geographic scope, and hence are protected throughout the United States”
(BITLAW, 2015).
All of the above statements suggest that the direct impact of the US trademark on UK
practitioners is more about perception than legally valid restriction. Also, Last
Planner has a registered trademark in the EU (EU Patent No. 004516324, 2006).
However, most of the practitioners interviewed were not aware of the EU trademark
Exploratory Interview and Structured Observation Chapter Six
162
and only made reference to the US trademark. The impact of the trademark
registered in the EU is unclear and is currently being contested by the LCI (EU
Patent No. 013369863, 2014). This does not entirely explain the confusion in the
terms as other names such as “plan to save”, “detail planning to completion”, and
“interactive planning” among others were also used. Also, some of the consultants
still use the term “Last Planner”.
Furthermore, most of the respondents agreed that CP is based on the LPS, while
other respondents argued that there are other practices advocated in CP in the UK
that were not in the LPS. For instance, one respondent stated that: “To me LPS and
CP are the same, but there is an amalgamation of other practices in CP such as the
visual management that is not in the LPS” (CO02). This further underlines the
confusion around the practice as visual management is an established lean production
practice (Liker 2004) directly imported from the automotive sector into lean
construction and can support both CP and LPS equally if required.
6.2.4.2 Meaning Ascribed to the Last Planner System and Collaborative
Planning
The study revealed that there is a consensus among the respondents that the LPS and
CP are seen as the application of production planning and control (PP&C) principles
in construction. However, further analysis of the interview shows that the meaning
ascribed to them seems to be disjointed. Table 6.2 shows the current understanding
of the respondents on LPS and CP by practitioners in the UK.
Table 6.2: Meaning ascribed to the Last Planner System and Collaborative Planning
Understanding on LPS and CP Inference View
Influencers
Respondent
Code
“We did not use the LPS in detail due
to the fact that this has not been
taught to us. No detailed information
on it. We are planning to do it on a
new scheme”
Only CP concept
taught by the
consultant
Lean consultant
& CLIP
MC01, Director
“CP is an active part of CLIP, it
helps us to map out programme
collaboratively with the supply chain.
The LPS helps balance the flow of
work better”
“LPS” and “CP”
viewed as two
separate processes
CLIP CL02, Director
“CP is all about having 2 weeks
look-ahead, weekly and daily
Lean consultant
driven
Lean consultant MC03
Improvement
Exploratory Interview and Structured Observation Chapter Six
163
production meetings. This process is
led by the consultant”
manager
“CP is a process of bringing people
together, while LPS is way of
measuring performance.”
“LPS” and “CP”
viewed as separate
processes
Lean consultant MC13, Senior
planner
“Collaborative programming is the
first step in the LPS known as pull
planning, phase planning,
collaborative programming. It means
the working together of
subcontractor/main contractor to
agree at a mutually agreed plan.”
CP viewed as an
element characterised
in the LPS
Experience
from practice &
Lean
construction
Institute, USA
CO01, Director
LPS is about measuring commitment
in the 6 weeks look-ahead and weekly
planning meeting
Narrow view on LPS The practice in
the organisation
MC16, senior
planner
Table 6.2 reveals that the disjointed view held by the respondents was largely
influenced by lean construction consultants in the UK who seem to be facilitators for
most of the organisations attempting to implement PP&C based on the LPS on their
projects for the first time. As shown in Table 6.2, some of the respondents (CL02,
MC13) believed that the LPS is a separate process from CP, but this view was
somehow refuted by another respondents as he stated that:
“Collaborative programming is the first step in the LPS known as pull
planning, phase planning. It means the working together of
subcontractor/main contractor to agree at a mutually agreed plan. [CO01,
Director]
According to Ballard, (2000) the LPS comprises of 5 key processes; the milestone
planning, phase planning- (which is the collaborative element), look-ahead planning
& make ready process, Weekly Work plan, and measurement and learning. It can be
argued that the partial implementation of PP&C practice reported in the UK could
have been influenced by the ‘separation view’ on LPS and its associated
collaborative elements (Daniel et al., 2016; Koch et al., 2015).
This could have also been influenced by the distorted message received by the supply
chain from some of the UK lean construction consultants on the application of PP&C
principles based on the LPS in construction. However, respondent CO01 seem to
maintain a balanced view on the application and practice of PP&C in construction as
advocated in the LPS.
Exploratory Interview and Structured Observation Chapter Six
164
6.2.4.3 Time and Programme Compression
Most of the respondents interviewed agreed that CP focuses on programme and time
compression of construction activities. One of the respondents stated that: “The CP
has been helping us to reduce our programme significantly, we enjoy twice as fast
delivery of our process with CP” (MC06). Furthermore, most of the respondents
interviewed indicated that they used collaborative programming/phase scheduling,
and Weekly Work Planning meetings. However, other elements of the LPS such as
the make-ready process, look-ahead planning, constraint analysis, consideration for
flow and learning with action were not mentioned or demonstrated as much. One of
the respondents stated that “We are not doing all the bits, the site people are too
busy, we only do high level collaborative programming” (MC05).
6.2.4.4 Common Understanding of Construction Programme
The study revealed that the CP process is viewed as an avenue to understand and
develop a sound construction logic that is often lacking when the traditional project
management approach is used. Some of the interviewees stated that:
“It (CP) raises the awareness of collaboration among the supply chain.
Usually, we expect the supply chain to deliver our programme even without
involving them but now CP makes it better” (MC02); “We get ideas from the
supply chain to develop a more workable programme” (CL01).
This suggests that the CP as practiced enables the project team to develop a better
understanding of the relationship between activities on the programme. According to
Pasquire (2012), for construction projects to flow as expected, all stakeholders need
to have a common understanding of the tasks to be executed. This implies that the
conversations that occur during the CP process have the potential to develop
collaborative relationships among the project stakeholders thus helping to reduce
fragmentation and engender stable workflow (Gonzalez et al., 2015).
6.2.4.5 Intervention Measure
The study showed that CP is commonly used in UK construction when there are
signs of failure on a project, especially in meeting the time requirement. For instance,
some of the respondents stated that:
“Our management decided we use (LPS and) CP on this project because of
the failure of our previous process, we have rebased this programme many
Exploratory Interview and Structured Observation Chapter Six
165
times. We have been working in isolation” (MC16). “The key driver is the
MD, because things are not going as initially planned” (MC17).
This is an indication that CP is used as an intervention measure rather than for
transformation of the business process. The danger with such approach is that the
organisation will only reap a one-off (and overall less) benefit from the practice.
Additionally, the statements indicates that construction clients are not the only driver
of the process, higher management from the contracting firm have an influence too.
6.2.5 Current Success Factors for Implementing LPS/CP in the UK
The analysis of the interviews revealed these key factors as presented in Figure 6.4.
These factors are based on the emerging themes from the interview analysis and
there is no weighting attached to them.
Figure 6.4: LPS/CP success factors in the UK Construction industry
Current success factors for LPS
and CP implementation in
the UK
Use of mock-up session
Selection of supply chain
based on collaborative
working practice
Use of integrated supply chain
model
Appointment of lean champions and consultant
support
Early involvement with the supply
chain
Leadership support and
training
Inclusion of LPS and CP practice in
the contract
Exploratory Interview and Structured Observation Chapter Six
166
6.2.5.1 Early Engagement with the Supply Chain
The study revealed that the early engagement with the supply chain contributes to the
LPS/CP implementation on the projects. For example, some of the respondents stated
that:
“The early involvement of the subcontractors with the development of
framework has helped” [MC01, Director]. “The engagement of the
subcontractors is key to the success of the process and also their buy-in”
[MC02, Improvement Manager].
This finding aligns with previous studies such as the recent review of IGLC papers
on LPS by this author as presented in Chapter Four; Hamzeh and Bergstrom, (2010);
and Ballard et al., (2007) among others. While this is not new, it showed that
production planning and control practice implementation success factors observed in
the UK are similar to those found elsewhere. Also, there seemed to be a consensus
among the respondents with regards to subcontractor engagement. However, one of
the subcontractors observed that this does not always happen in practice on all
projects that claim to use PP&C principles based on the LPS in the UK.
6.2.5.2 Use of Integrated Supply Chain Model
Most of the respondents interviewed observed that the use of what is best described
as an “integrated supply chain model” is one of the major success factors in LPS/CP
implementation in UK construction. The integrated supply chain model focuses on
developing a long term relationship with the supply chain. This is done through a
framework agreement with the supply chain which affords them the opportunity to
work with a particular client or contractor over time. Some of the respondents stated
that:
“The use of integrated supply has helped in our CP implementation. As a
client, we select, develop, and maintain our supply chain. We also train them
on CP and encourage them to train their staff too at the workforce level
which adds to their point during lean maturity assessment” [CL02,
Director]. The desire or wish of the supply chain is continuity. Also, they
want to be sure of the labour requirement each day and this need to be
consistent, so that they can book their profit [MC13, Senior Planner].
Exploratory Interview and Structured Observation Chapter Six
167
Again, this does not only show the need for maintaining the supply chain from one
project to another, but also the need to take responsibility for working together,
training of the supply chain, as well as lessons learnt. The benefits from this cannot
be overemphasised, as it supports learning on the project. It also allows for the
transfer of learning to other projects and the development of collaborative working
relationship among the supply chain. A respondent stated that:
“To transfer lessons learned goes down to having a stable supply chain. A
stable supply chain helps learning from the CP process. It is the supply chain
philosophy that helps in transferring skills and lesson learned” [CO02,
Director].
However, the narrow view thata construction project is a one-off activity could limit
the embracement of this approach across the industry. Vrijhoef and Koskela, (2000)
observed that the construction industry supply chain tends to be fragmented and
unstable due to the one-off nature of construction projects.
6.2.5.3 Inclusion of LPS/CP in the Contract
The analysis of the interviews provides evidence that the formal inclusion of LPS/CP
practice in the contract supports the buy-in from the supply chain. About 80% of the
respondents comprising main contractors and client agreed that LPS/CP practice was
included in the contract agreement with the supply chain. About 20% claimed not to
have formally included it in the contract, though the supply chain members were
aware that they will be doing it. Some of the respondents stated that:
“We include LPS practice in the contract with our supply chain; they know
they will be doing it. This means we have paid for it ??????” [MC09, Senior
Planner].
“Early and prompt payment within 28 days to the subcontractors encourages
them to participate and get [them] more committed and also the CP is signed
into the contract at the early stage” [MC01, Director].
This shows that the early inclusion of LPS/CP practice as part of the contract, will
prepare the mind of the supply chain to get involved with process even before the
commencement of the project. This implies that both clients and main contractors
should make their expectations on production planning and control practice known to
Exploratory Interview and Structured Observation Chapter Six
168
their supply chain early on the project. This will ensure there are no surprises to
them at the start of work on site. It could be argued that the commitment to LPS/CP
by the supply chain could be low on projects where the process is used as an
intervention measure. This is because on such projects, the supply chain would not
have been informed about the process. Thus, they would be reluctant to commit to
the process. Some could also argue that the cost of attending production planning
meetings is not part of their tender.
6.2.5.4 Appointment of Lean Champions and Support from Lean Consultants
All the respondents shown in Table 6.1 observed that the appointment of internal
lean champions contributed to the implementation success. This shows the value of
developing internal capacity in sustaining new practices in an organisation. Alarcon
et al., (2002) asserted that formation of internal lean committee both at the project
and organisation levels help in driving the LPS implementation in construction
organisations in South America. Again, this means that the internal lean champions
should not be limited to the project level alone, but should also be extended to the
organisational level. The study revealed that clients, main contractors, and
subcontractors have had some form of support from independent lean construction
consultants in the implementation process.
6.2.5.5 Procurement of Supply chain based Collaborative Practice
The study revealed that majority of the respondents comprising mainly clients, main
contractor, and consultants agreed that the selection of the supply chain using some
collaborative working practice contributed to the success of the LPS/CP
implementation. Some respondents stated that:
“Procurement method has massive influence on the LPS/CP approach. In the
LPS and CP process, one thing that is key is that both parties should know
the ‘spirit of the contract’ and ‘not just the letter’ which most time leads to
adversarial relationship. The contract should be win-win. We select our
supply chain based on 80% quality and 20% cost and collaborative culture”
[CL02, Director]. “We use more of selective tendering we select our supply
chain based on key element of CP, their previous performance, and their like
for CP” [MC01, Director].
Exploratory Interview and Structured Observation Chapter Six
169
This shows that in selecting the supply chain for LPS/CP implementation in
construction, the focus should not be on cost only, but rather on previous
performance of the supply chain, collaborative working record and in developing
robust relationship with the supply chain. This implies that the focus here is for every
stakeholder on the project to benefit equally from the process. This is opposed to the
traditional project management approach that focused on managing cost, contract,
and individualistic self-interest (Pasquire, et al., 2015; Ballard and Howell, 2004).
However, the LPS focuses on managing project production, and the interrelationship
that exists between the activities and those required to perform them (the supply
chain) (Fueman et al., 2014; Mossman, 2014; Ballard and Howell, 2003). The study
further revealed that the supply chain were physically engaged in collaborative
working exercises, which gives the supply chain an understanding of what the
customer wants. One of the clients stated that:
“The selection process of the team actually helped in the process. We do
activities such as prototype workshop, prototype work, design for
construction workshop. Their willingness to collaborate is a condition for
their selection” [CL01, Director].
It could be argued that if the supply chains are exposed to these practices before
moving on to the project, the probability of committing to the process could be high.
6.2.6 Current Drivers for Implementing LPS/CP in UK Construction
Figures 6.5 presents the current drivers for implementing LPS/CP in the UK
construction industry from the interview results. There is no weighting attached to
the factors in the figure as it is based on the emerging themes obtained from the
interview results. Some of these drivers are discussed under this section.
Exploratory Interview and Structured Observation Chapter Six
170
LPS and CP
Implementation
Drivers in UK
Internal desire for
improvement by
organisation
Client and public
sector demand Less
conversation with
the common
programming
tools
Quest for timely
delivery of project
Quest for improved
communication and
good working
relationship with
team
Benefit from
previous
implementation
Project
complexity and
recession
Figure 6.5: Drivers for implementing LPS/CP in the UK construction industry
6.2.6.1 Client and Public sector Demand
The study revealed that the demand for its use by the public sector clients remains
the main driver for the use of LPS/CP on construction projects in the UK. Some
respondents stated that:
“We are working to achieve our client’s expectations; we are required to use
it on this project. Also, we have a drive for efficiency within our organisation
for continuous process improvement” [MC03, Improvement Manager].
“Client is the major driver, much of the leadership is coming from the client
and the public sectors such as Highway Agency and Ministry of Justice”
[MC05, Improvement Manager].
The drive coming from the client and public sector in the UK seems contrary to what
is commonly reported in other parts of the world such as North America and Brazil.
In those places, contractors were the active agent in initiating and deploying the LPS
in their businesses (Alarcon and Calderon, 2003 Miles, 1998; Soares et al., 2002). It
can be argued that, the slow and partial uptake of LPS/CP in the UK could be due to
the push for the use of the system from public sector clients, rather than an internal
Exploratory Interview and Structured Observation Chapter Six
171
motivation or pull from within the contractors. Although, the pace of uptake within
the UK is slow, it has been observed that the uptake of lean production principles in
construction is slow globally (Stevens, 2014).
However, the demand from the public sector shows the UK Government’s
continuous effort in improving the performance of the construction industry through
all available opportunities (Egan, 1998; Latham, 1994).
6.2.6.2 Internal Drive for Continuous Improvement by Organisation
The analysis of the interviews revealed that 80% of the respondents agreed that client
demands and the internal desire for continuous process improvement are among the
core motivators for using LPS/CP on their construction projects. While only 20%,
mainly main contractors, indicated that it was part of their internal process for
driving continuous improvement across their business. Some main contractors stated
that:
“The LPS/CP is adopted for our company and we use it across our projects.
We have a standard process for carrying out CP on all our projects” [MC07,
Business Improvement Manager]; “I can say the LPS/CP process on this
project is internally motivated 70% from the organisation and 30% from the
client” [MC06, Improvement Manager].
Again, this shows that the push for an effective planning approach is not coming
from the client alone. Even though the percentage is still very low, it gives an
indication that more contractors could take personal initiative to embark on this as
they see benefits from the process.
6.2.6.3 Benefit from Previous Implementation and Quest for Improved Working
Relationship
Most of the respondents, mainly clients and main contractors observed that, the
benefits from their previous implementations are among the current drivers for using
it on their project. One of the clients stated that:
“We have seen the benefits from the process on our previous pilot projects.
We were able to deliver our project on time and better profit of course”
[CL02, Director]
Exploratory Interview and Structured Observation Chapter Six
172
This shows the need for measuring the benefits realised from the implementation
process, as people would not be interested to commit to the system if there is lack of
evidence of its benefit. Smith, (2013) declared that measuring, reporting, and proper
communication of benefits is critical to the success of lean in construction. This is
true as no organisation or supply chain would be motivated to apply LPS/CP for the
sake of the name.
However, the desire for improved communication and better working relationship
seems to be the driver for the subcontractors. One of the subcontractors stated that:
“I love working in the best way. I love the CP approach to work, it makes our
working process and relationship better” [SC01, Director].
6.2.6.4 Quest for on Time delivery of Project and to Overcome Past Failures
Most of the respondents agreed that the need to complete the project on time is a key
driver for implementing LPS/CP on their project. A main contractor observed that:
“Time saving is the most important motivating factor for us, people making
saving in time is now essentials especially after the recession to avoid
liquidation and damages” [MC09, Assistant Site Manager].
This emphasises the need to have time certainty in the delivery of construction
project. The quest for this by most of the respondents is no surprise, since it has been
reported that 50% of construction projects suffer time and cost overruns (Crotty,
2012). However, the LPS as a PP&C methodology uses its collaborative elements in
stabilising the production process, thereby improving time certainty of the
construction programme (Papke and Dove, 2013; Ballard and Howell, 2003; Ballard,
2000).
6.2.7 Benefits of Implementing LPS/CP Observed in the UK construction
The analysis of the interviews revealed the various benefits associated with the
implementation of LPS/CP in the UK construction industry. The identified benefits
are classified into three categories. These are: (1) general benefits (2) process
benefits and (3) social benefits as presented in Figure 6.6.
Exploratory Interview and Structured Observation Chapter Six
173
Figure 6.6: Categorisation of the benefits of implementing LPS/CP in the UK
6.2.7.1 General Benefits of Implementing LPS/CP Observed in the UK
Figure 6.6 show the general benefits of implementing LPS/CP on projects in the UK.
General benefits here refer to the gain made from the implementation process in
relation to the key project performance indicators. Almost all the respondents
identified the factors listed under the general benefits in Figure 6.6. Majority of the
respondents stated that they observed time reduction and more certainty in the
construction programme. Some of the interviewees stated that:
“The process has helped us to save a lot of time, we shall meet the finish date
despite all the challenges” [MC06, Improvement Manager] “The process
gives us some security of finishing the job on time” [MC12, Senior Planner].
The process enables my clients to experience twice faster in delivery [CO01,
Director].
The time reduction and certainty observed could have occurred as a result of the
phase planning or collaborative programming meeting, WWP meetings and look-
ahead planning process (Mossman, 2014; Ballard, 2000). However, the focus of
implementing PP&C principles in construction as advocated in the LPS goes beyond
time reduction to stabilising and making the work process more reliable and
Time certainty and
reliable programme
Better resource
utilisation
More productive and
effective work
Generation of
innovative ideas
On time completion
of work
Improved trust and
relationship
Reduced disputes
and claims
Decentralisation of
decision process
Effective
management of
supply chain
Improved
communication
Common
understanding on
project goal
Improved
coordination on
project
Elimination of
wasteful processes
Early identification
of problems
Visible work load to
subcontractors
Reduced weekly
work variation
Prevention of trade
work overlap
General
benefits
Social
benefits
Process
benefits
Exploratory Interview and Structured Observation Chapter Six
174
predictable (Hamzeh et al., 2015; Ballard et al., 2009). Actually, the process is
centred on workflow and creation of value for customers (Koskela, 2000).
Some of the respondents claimed not to have measured these benefits in detail but
believed they had made some gain in time, cost, quality, client satisfaction, and
safety. The respondents observed that the subcontractor also used their labour
resource more productively and effectively on site. For instance a main contractor
stated:
“You know the certainty and predictability nature of our work, a
subcontractor working on six projects needs to be certain on how to move his
workforce around the project which CP has helped on this project” [MC06,
Improvement Manager].
This shows the importance of work certainty and predictability. However, it is worth
noting that to achieve certainty and predictability in the production process as
advocated in the LPS, more attention must be given to workflow, levelling of load
and batch sizing (Pasquire et al., 2015; Ballard and Howell, 2003; Alves and
Formoso, 2000).
6.1.7.2 Social Benefits of Implementing LPS/CP in Construction
Social benefits as used here refer to those benefits that address relationship issues
among stakeholders on the project. These benefits are listed in Figure 6.6. Majority
of the respondents explained that there had been obvious improvement in
communication and a better working relationship. Some of the respondents
commented that:
“The process has helped us greatly. It has improved our communication with
our supply chain. It brings closer working relationship with all the members
on the project” [CL02, Director]. The process enables us to improve the
level of communication among us; the team working on this project [SC01,
Director].
All the respondents agreed that the process had greatly improved the level of
communication among the stakeholders on the project. This indicates that
traditionally, there is little avenue for construction stakeholders to communicate on
projects. According to Dainty et al., (2007) the project based nature of construction
Exploratory Interview and Structured Observation Chapter Six
175
projects and the sheer number of stakeholders involved in the process makes
communication complex. This also contributes to the adversarial relationship.
However, Toor and Ogunlana (2008), suggested that if all the required stakeholders
constantly communicate, confrontation could be reduced, this includes face to face
communication. This is clearly supported in the various conversation processes that
occur in the LPS such as, phase planning and WWP among others. As observed by
the respondents, this reduce disputes among the parties on the project.
Also, the respondents observed that the process enabled them to build more trust in
the team. This is a key benefit in managing construction project based on the LPS
principles. Kim and Ballard, (2010) observed that trust is usually developed among
project participants when there is reliability in the programme. They argued that the
trust developed here is based on relationship and not on mere commitment to the
contract.
6.2.7.3 Process Benefits of Implementing LPS/CP Observed in the UK
Process benefits refer to the gains observed in the delivery process from the
implementation of LPS/CP on the project. The specific benefits associated with the
process are itemised in Figure 6.6. Majority of the respondents observed that the
process had improved the coordination of project activities and elimination of
wasteful processes. Some of the respondents stated that:
“The CP has helped us to reduce non-value adding activities from the
construction process. We do a mock-up session to eliminate wasteful
processes. The mock session enable us to identify the problem areas and get
them addressed before construction” [MC01, Director].
“We are enjoying better coordination on our project sites now as the site
engineers now work closer with the foremen on site. Also, the team now
understand each other’s work better” [MC05, Project Manager].
This shows the importance of collaborative conversation in improving the delivery of
construction products. The mock-up session used in eliminating the non-value adding
(NVA) activities is technically known as the First Run Studies (FRS) in the LPS. The
process allows the team to collaboratively explore opportunities and identify the best
approach to deliver the product more efficiently before the commencement of
construction on site. According to Ballard and Howell, (1998) it is used on critical
Exploratory Interview and Structured Observation Chapter Six
176
production processes and repetitive products. However, Mossman, (2014) argued
that FRS should not be limited to repetitive activities alone as all activities are
critical to the success of the project.
6.2.7.4 Level of Benefits from LPS/CP Implementation on Projects in the UK
To examine the level of benefits observed from LPS/CP implementation in the UK,
the respondents were asked to identify which of the stakeholders benefited most from
the implementation process. The study revealed that 100% of the stakeholders
interviewed agreed that all the stakeholders benefited from the process, however
their view on which of the stakeholders benefited most is diverse. Below are the
transcripts from some of the respondents:
“I believe the process enables the entire team to develop an understanding of
the construction process, but I think the potential benefit in terms of time goes
to the client” [MC10, Senior Planner].
“Based on my experience in implementing LPS and CP in construction, it is
the project as whole that benefits from the process and not just an individual”
[MC05, Improvement Manager].
“To me, the project as a whole benefits, but the subcontractors benefit more
because they spend less time on site when CP is used, thus making more
profits” [MC12, Project Manager].
The benefits from the process is pretty whole rather than looking at the output
being for one single party, but of course, the potential benefits goes to the
client [MC17, Planner].
“Everyone benefits from the process; to me everyone is a winner when it
works well” [SC01, Director]
“The subcontractor gets a general benefit of the process because there will
be less rework, completion of work on time and high quality” [MC07,
Improvement Manager]
From the above transcripts, it is clear that all stakeholders benefit, however there is
no clear consensus on who benefits most. Each stakeholder seems to hold a different
view on who benefited most from the process. This suggests that to assume all the
Exploratory Interview and Structured Observation Chapter Six
177
stakeholder benefits equally from the implementation process may not be true.
However, going into the extreme of believing that one stakeholder benefits more
could hinder the buy-in and commitment to the process from others who may feel
they do not benefit as much. Stevens, (2014) emphasised the need to develop and
refocus the benefits of implementing lean principles in construction with due
consideration to the stakeholders involved in the process. This shows the need to
model and prioritise the benefits of implementing LPS in construction projects using
the lens of the different stakeholders involved in the process.
6.2.7.5 Modelling the Benefits of Implementing LPS/CP Observed in the UK
The study revealed that the respondents tend to emphasise the benefit which is of
high priority to them in performing their role on the project. Table 6.3 presents the
priority of the benefits as seen through the lens of stakeholders interviewed. In the
Table, level 1 means very high priority while level 2 means high priority.
Table 6.3: Prioritisation of LPS/CP benefits using the lens of the stakeholders
LPS/CP Benefits Observed Stakeholder’s view on LPS/CP Benefits
Level 1 Level 2
1 Visibility of work to subcontractor and
other stakeholders SC MC
2 Development of more predictable and
reliable overall programme CL MC, SC
3 Cheaper price from subcontractors based
on long term relationship MC
4 Reduced variation, weekly overhead and
time overrun CL MC
5 Improvement in the quality of final product
and better client satisfaction CL MC
6 Improved communication and coordination SC MC
7 Better resource utilisation SC MC
8 On time completion of work SC, MC, CL
8 Better management of supply chain CL MC
10 Elimination of wasteful processes SC MC
12 Prevention of trade overlap SC MC
13 Improved trust and relationship CL, MC, SC
Key: CL= client, MC= main contractor, SC= subcontractor; Level 1= very high priority, level 2 =
high priority
Exploratory Interview and Structured Observation Chapter Six
178
These benefit levels were determined based on the number of times they were
mentioned by the interviewees. As shown Table 6.3, developing a more reliable and
predictable overall construction programme and improvement in the quality of final
product is of a very high priority to the client. On the other hand making the
workload visible and better utilisation of resources on the project seems to be a major
priority to subcontractors. The findings above shed more light on the areas of benefit
to focus on when integrating stakeholders in the implementation of the LPS in
construction. Although, all the stakeholders (main contract, client and subcontractor)
collectively agreed that they benefited from the process, their priority area of benefits
differed. This has not been clearly highlighted in previous research on the application
of LPS principles in construction projects. The absence of a clear model of the
benefits of LPS in construction to stakeholders could have contributed to its low
uptake by stakeholders in the industry.
For instance, it has been observed that there is low adoption of lean construction
principles among contractors (Stevens, 2015; McGraw Hill, 2013). Furthermore,
Stevens, (2015); Stevens, (2014) concluded that this could be due to the
misalignment of lean methodologies with the values of the stakeholders on the
project. Again, all these demonstrate the need to prioritise LPS implementation
benefits from the perspectives of the stakeholders as this could support their buy-in.
6.2.8 Barriers to Implementing LPS/CP in the UK Construction
Figure 6.7 indicates the current barriers to implementing LPS/CP in the UK
construction industry as revealed from the interview results. Some of these barriers
are discussed in relation to previous studies in the section below.
6.2.8.1 Cultural Issues at Project and Organisational Levels
Although, some of the challenges identified in this study are similar to those reported
globally with regard to the implementation of lean principles (Alsehaimi et al., 2014,
Gao and Pheng, 2014; Fernandez-Solis et al., 2012), it is striking to know that 9100%
of the respondents identified cultural issues as the major barrier to LPS/CP
implementations on the project. This finding is contrary to previous studies such as
the review of LPS implementation barriers from the review of IGLC papers between
9 Part of this work has been published in Pasquire, Daniel and Dickens, 2015c. Snapshot Report
Exploratory Interview and Structured Observation Chapter Six
179
1993 and 2014 presented in Chapter Four, and Porwal et al., (2010) where lack of
training was identified as the topmost barrier.
Figure 6.7: Current LPS/CP implementation barriers in the UK
The cultural issues identified occur both at project and organisational levels. One of
the cultural issues that occurs both at the project and organisational levels is
“resistance to change”. All the respondents interviewed identified it as a major
barrier at the project phase and in the organisation implementing the process. Some
transcripts from the respondents are presented below:
“They like doing it their own way, people are too busy, they go into
firefighting approach”. [CO01, Director]
“Changing the way people work is very challenging. It is difficult to embrace
all the tools. We only do the high level planning. The site people are too busy
to do all the bits.” [MC05, Improvement Manager]
“The guys doing the job for 30 years will always ask; why do you want me to
do it differently?” [CO03, Operation Director].
Current LPS/CP
implementation barriers in the UK
Inadequate manpower
Use of fragmented subcontracti
ng model
Self protectionis
m
Partial invovement
of subcontracto
rs
Labour shortage and geographical dispersion of
project
Time pressure and
lack of discipline
Cultural barriers
Exploratory Interview and Structured Observation Chapter Six
180
The above statements present an overview of the resistance to the new way of
working in the UK construction industry. Although this finding may not be
necessarily new, it shows how deep rooted the cultural issues affecting the
implementation of the LPS/CP in UK construction are. For instance, Johansen and
Porter, (2003) identified cultural and structural issues as barriers to the
implementation of the LPS in the UK construction industry.
6.2.8.2 The Use of Fragmented Subcontracting Model
The use of “fragmented subcontracting model” was also seen as a barrier to the
implementation of LPS/CP on projects. “Fragmented subcontracting model” is an
approach that supports the changing of subcontractors as well as viewing
subcontractors as tools to be used and dumped. This model does not encourage the
development of collaborative relationship among project stakeholders as
organisations tend to change subcontractors as they move from one project to
another. Here are transcripts from some of the respondents:
“The use of fragmented subcontracting model makes most company focus on
their engineers and management staff alone, while they keep changing the
subcontractors which will affect the LPS/CP development in the
organisation” [CL02, Director].
“The difference between manufacturing and the construction industry is that
we keep changing the team, which is a barrier. Too much ‘going for
shopping’ in the construction industry” [CO01, Director].
Subcontracting is a common practice on construction projects and in the UK in
particular. 80% of construction works are undertaken by subcontractors and the UK
construction industry houses over 280,000 companies (BIS, 2013). This shows the
different firms operating in the UK construction industry (BIS UK construction,
2013). The implication of using fragmented subcontractor’s model in the
implementation of LPS/CP is that, it reduces the ability of the supply chain to work
collaboratively (BIS Supply chain analysis, 2013).
6.2.8.3 Partial Involvement of Subcontractors
The study revealed that subcontractors were only partially involved in the LPS/CP
implementation process. A subcontractor stated that:
Exploratory Interview and Structured Observation Chapter Six
181
“There are projects where the subcontractors are not involved in the
LPS/CP implementation process, writing it in the contract could help in this
regard” [SC01, Director].
Again, this shows the need to formally include the implementation of LPS/CP
practice in the contract. This would put more obligations on the main contractor to
include the subcontractors in the process, which would benefit the entire project.
6.2.8.4 Time Pressure and Lack of Discipline
Another barrier is time pressure and lack of discipline in implementing the PP&C
principles. Some of the research participants complained that it was time consuming.
Some of the respondents stated that:
“The challenge is in the implementation of all the tools into the business.
There is reluctance towards forward and weekly planning. We did not
measure PPC at all time. What works well is the collaborative
programming?” [MC05, Improvement Manager]
“People believe they don’t have the time to do it” [CO01, Operation
Director]
“The site guys and men are too busy to do all the bits of the system” [MC07,
Improvement Manager]
These comments clearly indicate that there is lack of discipline and commitment to
the implementation of LPS principles at the projects level in the UK. Kalsaas et al.,
(2014) also observed partial implementation of LPS principles at the project level in
their Norway study. These findings show that the major barriers to LPS
implementation are around people and not the process or technology.
6.2.8.5 Self Protectionism
The study revealed that protection of self-interest by some of the stakeholders
especially between the main contractors and the subcontractor is a barrier to the
process. A main contractor observed that:
“There is lack of openness to collective decision making a lot of self -
protection subcontractors trying to protect their interest not minding what
happens to the team” [MC12, Assistant Site Manager]
Exploratory Interview and Structured Observation Chapter Six
182
Previous studies have shown that construction stakeholders tend to distrust each
other and are always trying to protect their own interest (Briscoe and Dainty, 2003).
This is not expected to occur on lean projects where the goal is to ‘collaborate and
deliver value’ for the client. The emergence of this on a lean project shows that some
of the stakeholders have not truly thrown away the traditional ideas of managing
projects.
6.3 Stage 3: Structured Observations
The aim of the structured observation was to enable the study obtain the current
practice of production planning and control based on the LPS in all aspects on the
projects observed. Fifteen (15) projects were observed. This was done in a systematic
manner in relation to the identified production planning and control principles
advocated in the LPS so as to identify the level of implementations on the projects
observed and to compare the implementation across sectors.
6.3.1 Results and Discussion
Data were obtained from 3 sources:
record analysis,
physical condition analysis and
physical process analysis.
The above three processes have been described in detail in Chapter Five. The results
and discussion are presented below.
6.3.2 Description of Projects Observed
Table 6.4 gives an overview of the construction projects observed in the study. 10
All
the organisations observed are among the top 20 UK construction contractors and
their facilitators claimed to be knowledgeable in production planning and control
practice in construction. Additionally, the observation was not limited in scope, as it
includes its use in highway, building, and rail projects, thus giving a wider
perspective. Also, the project durations are long enough to enable a trend in the
current practice to be clearly captured.
10
Part of this work has been published in Daniel, Pasquire and Dickens, (2015b). Assessing the impact of PPM on construction process improvement based on the LPS in UK
Exploratory Interview and Structured Observation Chapter Six
183
Table 6.4: Description of project observed & evaluated for production planning and control
Practice
Project
code
Sector Project
Duration
Point of
Application
Facilitation PP&C
exp.
Yrs.
A01 Highway &
infrastructure
36 months Construction Internal improvement
manager
5
A02 Highway&
infrastructure
119
months
Design/
construction
Project manager &
internal lean
practitioner
3
A03 Highway&
infrastructure
40 months Construction Principal planner &
project manager
4
A04 Highway &
infrastructure
36 months Construction External consultant &
internal lean team
4
A05 Highway &
infrastructure
22 months Construction External consultant &
internal lean team
5
A06 Highway &
infrastructure
39 months Construction Internal improvement
manager
5
A07 Highway &
infrastructure
22 months Construction Internal site agent 4
A08 Highway&
infrastructure
36 months Construction Internally facilitated 5
B01 Building 18 months Construction Internal senior
planner
10
B02 Building 13 months Construction Consultant/Internal
site manager
10
B03 Building 30 months Construction Internal senior
planner
12
B04 Building 24 months Construction Internal lean team 5
B05 Building 12 months Construction Internal lean team 10
C01 Rail and
infrastructure
36 months Construction External consultant
and principal planner
6
C02 Rail and
infrastructure
36 months Construction External consultant 3
Exploratory Interview and Structured Observation Chapter Six
184
The analysis revealed that all the projects observed had been using PP&C based on
the LPS principles for a period of between 3 and 12 years. This implies that the
observations and their responses could be relied upon.
6.3.3 Results of Record and Physical Condition Analysis
On all the projects observed, a designated meeting space was provided for production
planning and controls. This was usually tagged “CP” meeting room or production
planning and control centre.
Figure 6.8: Pull Planning or Collaborative Programming board with Sticky-Notes for
scheduling
Figure 6.9: Pull Planning or Collaborative Programming board with temporary marker for
scheduling
Exploratory Interview and Structured Observation Chapter Six
185
Most of the projects observed made provision for a permanent collaborative
programming or pull planning board and either used sticky-notes on the board for
scheduling of activities or temporary markers of different colours as shown in
Figures 6.8 and 6.9 respectively.
Also, magnetic collaborative programming boards (Figure 6.10) were used on some
projects to provide a robust working medium while other projects were working
towards using electronic collaborative programming boards. Other record analysis
observed in the physical condition includes the display of PPC chart, RNC chart,
display of RNC observed, and display of monthly project objective target
achievement.
In addition to the collaborative programming meetings or pull planning meetings,
Weekly Work Planning meetings were also held. However, on some of the projects
observed, the activities within these meetings had become fragmented to the extent
that they were separated out into additional meetings with a different team of people.
For example, look-ahead activities took place in a separate meeting from make-ready
activities. Also, the daily stand-up meeting was observed on some of the projects
which could be likened to the “daily Huddle meeting” in the LPS.
However, there are differences in the practice of daily stand up meeting on some of
the projects observed when compared with the daily Huddle meeting in LPS. For
instance, the daily stand-up meeting as observed seemed to be the reporting of
progress daily which was done individually. This approach does not create the
needed platform that could result in collaborative conversations among the team in
order to collaboratively agree on how an identified constraint can be solved before
the next day work. The use of a form of visual management to communicate progress
was seen on some of the projects as shown in Figure 6.10. Document analysis
revealed that the collaborative programme/phase planning was usually developed
from the Primavera programme known as P6, which is generally considered to be the
contract programme.
Exploratory Interview and Structured Observation Chapter Six
186
Figure 6.10: Visual Management Board to Communicate Progress of Work
6.3.4 Results of Physical Process Analysis
The aim of the physical process analysis is to enable the study objectively identify
how the current practice of ‘Collaborative Planning’ used in delivering construction
projects in the UK align with the advocated principles of the LPS.
6.3.4.1 Production Planning and Control Practices Observed
11To identify how the current practice of “CP” for delivering construction projects in
the UK aligned with the LPS, 17 major practices associated with the implementation
of LPS were identified.
11
Part of this has been published in Daniel, Pasquire and Dickens, Ballard, G. (2016 ) The
relationship between the LPS and CP in UK construction
Exploratory Interview and Structured Observation Chapter Six
187
Figure 6.11: Level of Implementation of production planning and control principles on
projects observed
These are presented in Figure 6.11 along with the incidences of observed practice.
How these practices were identified and the evaluation process has been described in
0 10 20 30 40 50 60 70 80 90
Programming workable backlog
Formal communication of result to the supplychain
Formal system to take action on reasons fornon-completion of task
Consideration for flow
Make Ready and analysis of constraints
Constant evaluation and learning
Formalised shared decision making process
Use of prototyping/First Run Studies
Analysis of physical flow
Lookahead Planning
Planning and control process standardisation
Detail specification of task
Recording reasons for non-completion of task
Involvement of subcontractors in planning anddecision process
Measurement of Percentage Plan Completed(PPC)
Formalisation of Weekly Work Plan (WWP)
Initial collaborative programming/phaseplanning meeting
P1
7P
16
P1
5P
14
P1
3P
12
P1
1P
10
P9
P8
P7
P6
P5
P4
P3
P2
P1
Full Implementation Partial Implementation No Evidence to judge
Exploratory Interview and Structured Observation Chapter Six
188
Chapter Five.In Figure 6.11, it can be seen that only one practice (‘having initial
collaborative programming/phase scheduling meetings’) was fully implemented on
86% of the projects observed, whilst five practices were fully implemented on
between 40 – 80% of the projects observed. These are: ‘measurement of Percent
Plan Complete (PPC) at 60% ’; ‘having Weekly Work Plan (WWP) meetings at
80%’; ‘planning and control process standardisation’at 40%; ‘involvement of
subcontractors’ at 60% and ‘look-ahead planning’ at 40%. Recording of ‘reasons
for non-completion (RNC) of task’ was fully implemented on 53% of the projects
observed.
However, full implementation of a ‘formal system to take action on the RNC of
tasks’ practice was not observed on 60% of the projects. The study further revealed
that constant evaluation and learning was only partially done on most projects
observed, specifically, it was done partially on 86.67% of the projects. Again, this
shows that the full benefits of the implementation of LPS principles in UK
construction has not been fully harnessed, since no clear mechanism has been put in
the place to achieve this on most of the project observed. Learning is a key element
of the LPS, it supports continuous improvement both at the project and organisation
levels.
The study also identified other practices that were absent on 40% – 80% of the
projects observed. These include: ‘programming a workable backlog’ was not done
on 80% of the projects observed; ‘Consideration for flow’ was not done on 46.67%
of the projects; ‘use of prototype/first run study’ was not done on 66.67% of the
project observed; and ‘make ready and constraint removal’ was not done on 40% of
the projects observed .
Furthermore ‘analysis of physical flow’ was done partially on 53.3% of the project
observed. Analysis of physical flows focuses on the criteria for tasks to be included
in a production plan (such as information, materials, tools, equipment, prior work,
people, external conditions). Consideration for flow focuses on what needs to be
done when there is a change in the production.
For instance, during the interview, the respondents were asked; what do you do when
a task is completed earlier than planned? Some of the respondents said (a) “we do
nothing”, (b) “we re-plan”, (c) we take it as a bonus. Responses (a) and (c) show that
Exploratory Interview and Structured Observation Chapter Six
189
there is a lack of consideration for maintaining synchronised work flow. The
respondents interviewed here failed to recognise that some changes had occurred in
production, which needed to be addressed either by re-planning, increasing, or
decreasing resource in order to keep production stable and prevent a knock-on effect.
6.3.4.2 Effectiveness of Production Planning and Control Practices Observed
Across Projects in the UK
Table 6.5 indicates the effectiveness of PP&C practices based on the LPS principles
as observed on the projects. The study revealed that the most comprehensive
implementation observed on any project was 67.7% of the principles. This was
observed on only three projects (A06, A07, and B01). No single project implemented
all the practices. Previous studies such as Priven and Sacks, (2015), Bernades and
Formoso, (2002) also observed lack of implementation of all the principles in an
Israeli and Brazilian study respectively. Table 6.5 reveals that the least
implementation observed was 29.4% on project (C02). The reason is not far-fetched,
as it was observed that PP&C principles were used on the project mainly to repair
when things went wrong. The site team could have discontinued with some of the
other practices after the initial gain from the collaborative programming or phase
planning. Also, the initial process was externally facilitated and it is possible the
process was not developed further in the organisation. Again, this shows the need for
developing internal capacity to drive the process. For instance, most of the projects
with high implementation score were internally facilitated.
The analysis also revealed that these practices can be implemented effectively on any
type of project. For instance, 67.7% implementation was observed on highway (A06)
and building projects (B01), while 58.8% was observed on a rail project (C01). This
shows that the nature of the project does not influence the effectiveness of the LPS
principles. It can thus be argued that low scores on some projects could be due to
lack of discipline on the part of the team rather than the nature of the project.
According to Mossman (2014), the LPS principle is applicable to any system that
requires the management of human and physical resources.
However, the use of prototyping/First Run Studies was only observed on building
projects. For instance, it was observed on 80% of the building projects, while none
was observed on the highway and rail projects. This could be due to the large number
of different activities on building projects. The study observed that the prototyping or
First run studies was used during the finishing stage of the project.
Exploratory Interview and Structured Observation Chapter Six
190
Table 6.5: Practices observed across projects
Production Planning and control practice Project code
A01 A02 A03 A04 A05 A06 A07 A08 B01 B02 B03 B04 B05 C01 C02
Initial collaborative programming/phase planning meeting F F F F F F F F F F P F F F P
Formalisation of Weekly Work Plan (WWP) F F P F F F F F F F F P P F F
Measurement of Percentage Plan Completed (PPC) F F F N F F F F F P P F N P P
Planning and control process standardisation F F F N F P P F P P P P P F P
Involvement of subcontractors in planning and decision
process
F P P P P F F P F F F F P F P
Formalised shared decision making process P P P P N P P P P P P N P F P
Look-ahead Planning F P P P P F F F F N P P P F P
Detail specification of task F F F P P F F P F P P P F P P
Recording reasons for non-completion of task F P F F F F F F F P P P P P N
Formal system to take action on reasons for non-
completion of task
N P N N N P P N P N N N P P N
Analysis of physical flow P F F P P F F N P P P F P P N
Make Ready and analysis of constraints P P P N N P P N P N N P P P N
Use of prototyping/First Run Studies N N F N N N N N F F N F F N N
Constant evaluation and learning P P P P P P P P P P P N N P P
Formal communication of result to supply chain using
visual device
N N N N N P P N P P N N N N N
Detail consideration for flow N P P P P N P N N P N P P N N
Programming workable backlog N N P N N P N N N N N N N P N
Score expressed in (%) 58.8 58.8 64.7 38.2 50 67.7 67.7 47.1 67.7 47.1 38.2 50 47.1 58.8 29.4
F - fully implemented =1.0, P- partially implemented= 0.5, N- no evidence of implementation= 0.0
A01- A05= Highways and Infrastructure, B01- B05= Building projects, C01- C02= Rail projects
Exploratory Interview and Structured Observation Chapter Six
191
6.3.5 Mapping of Collaborative Planning Practice in the UK with the Last
Planner System
The degree to which the observed practices map across to components of LPS is
shown in Figure 6.12.
P6 Contract Programme
Milestone Programme
Collaborative Planning practices in
the UK
Last Planner System
components
Phase planning
High Level Programme
(Collaborative programme)
Lookahead planning
Lookahead planning Constraint analysis
Make-ready Workable backlog
Full consideration for flow
Weekly Work Planning meeting
Measurement of progress
Weekly Work Plan
measurement and
learningRecording of PPC & RNC
Comm. of results
Acting on RNC
KEY
PPC- Percent plan complete
RNC-Reasons for non-completionNo clear evidence
Common practice
Partial adoption
Figure 6.12: Comparing Collaborative Planning in the UK with the Last Planner System
Components
The figure shows a strong correlation between the current practice and the LPS at
Contract/Milestone programme and the high-level programme/phase planning
Exploratory Interview and Structured Observation Chapter Six
192
elements. There is an equally strong relationship at the levels of recording PPC,
WWP and RNC. However, WWP was only supplemented with daily huddle
meetings on few projects. As observed on the projects, the daily huddle meeting was
more of activity reporting rather than an avenue to make needed adjustments to tasks
that were slipping off schedule. The depth of application of the more complex
attributes contained in the LPS is weak or missing in the CP practice in the UK.
Overall, Figure 6.12 shows that there is only partial alignment of current CP practice
in the UK to the elements of the LPS on the projects observed.
6.4 Discussion of Findings on Collaborative Planning Practice
Observed with LPS Principles
All the interviewees felt the CP approach offered benefit. In general, not formally
implementing the full range of components within the LPS means maximum benefit
is not being realised. The comparison of current practice of CP with the LPS
components in Figure 6.12 partially aligns with practices elsewhere in the world.
Previous studies such as (Daniel et al., 2015; Sterzi et al., 2007; Bernardes, and
Formoso, 2002) show the measurement of PPC, WWP meetings (short-term
planning) and collaborative programming/phase scheduling to be among the
elements of the LPS most consistently reported as implemented in previous studies
published by the IGLC12
. However, the practices varied in detail from one project to
another. While CP was done with full involvement of the supply chains on some
projects, the supply chains were only partially involved on other projects as revealed
by the interview.
For instance, a senior planner interviewed on MC03 stated that: “We only involve the
principal subcontractors in the collaborative programming, we plan and give the
programme to the smaller subcontractors”. This implies that not all the supply
chains are involved in developing the high-level collaborative programme.
Furthermore, gauging the current CP practice with the LPS prescriptions such as
planning backwards, defining plan scope by the players involved, narrowing scope
when needed to untie knots, building floats into plans and allocating them to risky
and critical tasks, (Ballard, 2000), reveals they only occurred partly on some of the
projects observed. CP as practiced tends to only provide the platform for
12
International Group for Lean Construction www.iglc.net
Exploratory Interview and Structured Observation Chapter Six
193
stakeholders to have conversations on the proposed schedule and is deficient in the
process rigor as prescribed in the LPS. This is due to too much focus on the
execution of tasks and the absence of robust supporting mechanisms to enable flow
in the approach.
Clearly, a number of key LPS elements are missing in the present approach. The
most apparent of these is the lack of formal action on the RNC recorded. For
example, an interviewee stated that “We used to log the reason for non-completion of
task into an excel sheet but we have not developed any formal approach for
analysing this data” (MC07). According to Ballard, (2000) the purpose of recording
RNC in the LPS is to enable the team collectively act on identified issues and to
prevent future occurrence, which enhances learning. It can be argued that if no
formal actions are taken to address the RNC recorded, the recording itself becomes a
waste of time and resources. Typical action on RNC should include at least a formal
root cause analysis. That no collaborative actions (either formally or informally) are
taken on the reason for non-completion recorded removes the opportunity to generate
innovation, provide learning, enable action and improve collaboration among the
project stakeholders.
Other missing elements are the development of a workable backlog (Plan B) and the
consideration for flow, which forms part of the make-ready process in the LPS. The
lack of consideration and analysis of flow was evident on most of the projects
evaluated. For instance, during the interview, one of the respondents was asked;
“what action do you take when an action is completed earlier than planned?” The
response is “we don’t do anything; we take it as a bonus” (MC01). This shows a lack
of understanding of flow and the importance of load levelling and stability in the
production process once the phase plan is agreed. Unplanned early completion is
most likely to be a benefit for a contractor who is only managing the sub-contract
packages but may be benefit neutral or detrimental to subcontractors as it increases
uncertainty across their multi-project environment. When the focus of the production
system is shifted from the management of workflow to the pursuit of cost and/or time
reduction, the entire production system could collapse (Conte et al., 1998).
It can be argued that the prevailing practice of CP focuses more on time reduction
and programme reduction than achieving a smooth workflow across the project.
Finishing early is most likely to be the result of planning too little work in the first
Exploratory Interview and Structured Observation Chapter Six
194
place or from the removal of a constraint not identified in the make-ready process
which permitted work that did not meet the four criteria (sound, sized, sequenced,
and detailed) into the WWP. It is clear then that a reduced make-ready process that
sends work to the work phase (weekly or daily) without meeting the four criteria of
production planning results in reduced productivity and associated programme and
margin slippage (Court et al., 2009). It is important to note that PPC is a predictor of
productivity because of the 4 requirements for a committable task; i.e., sound,
sequenced, sized, and well defined (see Liu and Ballard, 2008, Ballard, 1999).
However, PPC can be 100% and the project still behind schedule because work is not
being made ready in the right sequence and rate (Hamzeh, et al., 2012).
Related to the make-ready process is the look-ahead process. Observation of this also
indicated some limitation in practice, notably, a look-ahead window of two weeks
was too short to allow sound assignments to be developed. Additionally, whilst
metrics such as PPC were measured and recorded, these metrics were not formally
communicated to the supply chain on some of the projects observed. For instance,
one of the respondents stated that;
“We do not publish PPC and RNC to the subcontractors, if I am showing this
to the subcontractors, I am going too low. We only make this available to the
senior management team. Some of the subcontractors get confrontational and
defensive about this, especially if the work was delayed by the main
contractors” (MC08).
This is another indication of a limit to the scale of adoption of collaborative practices
despite the use of the term “CP” to describe the approach. The safeguarding practices
observed appear to be deeply embedded in the prevailing practice and serve as a
significant barrier to collaboration (Pasquire et al., 2015)
6.5 Chapter Summary
This chapter presented empirical evidence on the current understanding and
application of CP and LPS in the UK construction industry. It determined how the
current practice of CP for delivering construction projects in the UK align with
advocated principles of the LPS. The chapter demonstrated that the term “Last
Planner” and “Collaborative Planning” are used interchangeably to describe the
Exploratory Interview and Structured Observation Chapter Six
195
application of production planning and control principles based on the LPS by
construction practitioners in the UK. The chapter showed that there is variation in the
current understanding of production planning and control principles based on the
LPS among the practitioners interviewed.
The chapter identified the current industrial practitioners’ perception on LPS and CP,
drivers, success factors, benefits and barriers in implementing LPS/CP in the UK
construction industry. The chapter showed that the drivers, benefits, barriers, and
successful factors for implementing LPS/CP observed in the UK are not entirely
different from what had been reported in previous studies elsewhere. However,
cultural issues were seen as a major barrier while the push from public sector clients
was among the major drivers for implementing LPS/CP in the UK. It also showed
that modelling and prioritising the benefits of LPS implementation could support the
integration of the stakeholders in the LPS implementation process.
The chapter established that the currents practice of CP as observed in the major
sectors of the UK construction industry aligned with some of the generally advocated
principles of the LPS acknowledged in the literature; specifically, the high level
collaborative programming, WWP meetings, and the measurement of PPC and the
charting RNC. However, the chapter revealed that the current practice of CP in the
UK has not explored all components of the LPS. Overall, the chapter showed that
there is only partial alignment of current CP practice in the UK to the elements of the
LPS on the projects observed. This situation inhibits the extent of benefit that can be
realised and even the advancement of industry performance.
The chapter revealed the components of the LPS missing in the current practice. The
components not used include look-ahead planning; aspects of the make-ready
process such as consideration for workflow and developing a workable backlog; and
acting on reasons for non-completion of tasks among others. Furthermore, the
absence of these elements indicates a poor understanding of construction as a
production process and the importance of flow in successful project delivery and
benefit realisation. The next chapter (Chapter Seven) presents and discusses the
findings from the three case studies.
196
CHAPTER SEVEN: MULTIPLE CASE STUDY
DATA ANALYSIS, CROSS CASE-
COMPARISON AND DISCUSSION
7.1 Introduction
The previous chapter (Chapter Six) presented and discussed the findings from the
exploratory interviews and the structured observation. This chapter focuses on the
three multiple case studies conducted. The case study investigates the nature of
support required for Last Planner System/Collaborative Planning (LPS/CP)
implementation in the UK construction industry. The chapter is structured thus;
sections 7.1, 7.2 and 7.3 present the findings from the three individual case study
projects, while section 7.4 presents the cross case-comparison and discussion. Each
case study identifies LPS/CP practice, the impacts of procurement practice on its
implementation, the support for rapid and successful LPS/CP implementation, and its
impacts on construction process improvement. Some of the findings were also
triangulated with the findings in stage 3 to authenticate the results from each
stage.The chapter closes with the chapter summary in section 7.5 which brings
section 7.1 to 7.4 together.
7.2 Stage 4: Multiple Case Studies Overview
Three case study projects were conducted; two on highways infrastructure projects
and one on a building project. In each case, vital information such as the description
of the case study project and the demographic data on the research participants are
presented. This was done to enable the researcher to discuss the result in the context
of the real life project. Evidence was obtained through four sources, namely:
documents analysis, unstructured observation, semi-structured interviews, and
structured survey. The main reason for selecting multiple cases study projects has
already been discussed in Chapter Five.
Case Study Anaysis and Discussion Chapter Seven
197
7.3 Case Study Project One (CSP01): Highways and Infrastructure
a. Description of Case Study Project One
The case study project one (CSP01) is located in the North of Yorkshire, England. It
is a highway infrastructure project which is an upgrade to replace a dual carriageway
with a three lane motorway. The full description of the project attribute is presented
Table 7.1. It also includes the construction of associated facilities such as bridges
among others. Other aims of the project include the provision of a new local access
road alongside the new motorway, and provision of access to the strategic road
network so as to improve safety and journey time reliability. The project comprises
of different facets and many stakeholders, which requires coordination and
management. This shows the complexity of the project. For effective coordination
and management of the project; the project was divided into three sections: the north,
the south, and the central section. All the sections of the project were managed using
the LPS/CP with three different supervisors and one central coordinator.
Table 7.1: CSPO1 Project Attributes
Project Attributes Observed attributes on CSP01
Nature of project Highway and Infrastructure
Location of project North of Yorkshire, England
Nature of work Upgrade to replace existing dual carriage way with three
new lane
Type of client Public client
Mode of contractor selection Framework agreement and ECI
Proposed project duration 30 months
Stage of the project at the end
of the case study
57% completion
Procurement arrangement D&B, joint venture
Contract sum £380 million
Current number of
subcontractors on site
10
Point of application of
LPS/CP principles
Construction
LPS/CP facilitation process Internally facilitated
The two main contractors on the project were into a joint venture (JV), the two
contractors are among the UK top 10 contractors by the value of work won in 2015
(Construction news, 2015). Both contractors have a long history and expertise in the
delivery of construction and engineering projects. However, one of the contractors
Case Study Anaysis and Discussion Chapter Seven
198
has a strong record in the delivery of mega highways infrastructure projects with
sustainable approaches. The JV was formed to benefit from this, due to the scale and
critical nature of the project.
Both contractors claimed to have used LPS/CP principles on their previous projects.
Also, the use of LPS/CP principles was mandated by the client on this project.
Design and Build (D&B) and Early Contractor Involvement (ECI) were used in
procuring the project. Table 7.1 presents the project characteristics. The table shows
that CSP01 project duration is long enough to capture LPS/CP practices on the
project. The researcher observed CSP01 over a period of 10 months, which started at
the construction phase. This enabled the study to gain insight into the nature of
support to be put in place for effective implementation of the LPS. Project status
indicated that CSP01 was at 57% completion when the researcher left the site, this
shows that LPS/CP practice on this project could have matured to a level. Thus, a
pattern could be identified from the case study findings. Also, since the two main
contractors in the joint venture claimed to have used LPS/CP principles on their
previous projects, their previous experience could be brought to bear on this project.
b. Demographic Information of Respondents on CSP01
Table 7.2 indicates the respondents interviewed on CSP01. These include; 5 senior
managers (SM01-05); 2 middle managers (MM01-02); 2 operation manager (OM01-
02) and 2 subcontractors (SC01-02).
The Table reveals that the respondents interviewed on CSP01 cut across the major
stakeholders that are directly involved in making decisions on production planning
on the project. This suggests a balanced view could be received from the interview
response. All respondents have between 1 and 5 years’ experience in LPS/CP
practice. The table reveals that only few subcontractors participated in the interview.
The low number of subcontractors interviewed is largely due to their unavailability
for interview, as they complained of lack of time to talk to the researcher and the
variableness of their stay on site due to the nature of their work. Furthermore, the
analysis reveals that 82% of the respondents on CSP01 have over 10 years’
experience in construction, however only 18% have above 4 years’ experience in
LPS/CP. This could imply that the use of collaborative approach in construction
planning was less practiced in scheduling of work in the past.
Case Study Anaysis and Discussion Chapter Seven
199
Table 7.2: Description of respondents interviewed CSP01
S/NO Respondent code Role
categorisation on
the project
Specific role in
organisation
Years
of exp.
in
LPS/C
P
Year of
Exp. in
const.
1 CSP01SM01 Senior manager Planning manager 2 10
2 CSP01SM02 Senior manager Excellence
manager
5 18
3 CSP01SM03 Senior manager Construction
manager
5 20
4 CSP01SM04 Senior manager Senior planner 1 16
5 CSP01SM05 Senior manager Senior engineer 1 9
6 CSP01MM01 Middle manager Section engineer 3 10
7 CSP01MM02 Middle manager Section engineer 1 20
8 CSP01OM01 Operational
manager
Site Agent 1 14
9 CSP010M02 Operation
manager
Planner 1 3
10 CSP01SC01 Subcontractor Director 3 15
11 CSP01SC02 Subcontractor Project manager 2 12
7.3.1 Last Planner/Collaborative Planning Practice on CSP01
The data on LPS/CP practice on CSP01 were obtained via documents analysis,
unstructured observation, and interviews. The practices observed are discussed under
the following emerging themes: (1) application of LPS/CP principles (2) pre-
construction practice (3) Nature of LPS/CP meetings and (4) Percent Plan Complete
(PPC) and reason for non-completion (RNC) practice.
7.3.1.1 Application of Last Planner/Collaborative Planning on CSP01
The application of LPS/CP on CSP01 started with the first activity on the
construction programme on the project and its use on the project was agreed by the
stakeholders on the project. A workshop was held with stakeholders to reiterate this
before the commencement of construction activities on site. The three sections
(North, South, and Central) of CSP01 were independently managed with LPS/CP
principles. However, the process was centrally coordinated by the Senior Excellence
Operational Manager and an Assistant Excellence Operational Manger with the
support of the planners, section engineers, and construction managers. This implies
Case Study Anaysis and Discussion Chapter Seven
200
that the central coordinators are not required to always be present at all the sessions
as the teams are capable of facilitating the process also. However, it was observed
that the level of discipline in applying the LPS/CP principles varied across the three
sections.
For instance, the teams at the North and Central sections were committed to LPS/CP
process as the researcher was opportune to be in several sessions. This was not the
case in the south section, as there seemed to be a tussle among senior project team
members in the section, thus, most of the LPS/CP principles were not followed. It is
worth noting that the researcher was not even provided the opportunity to attend any
LPS/CP session at the south section throughout the case study. Again, this shows that
even when LPS/CP is mandated on a project, if the traditional mind-set is not
removed, the process could still be faced with challenges. Some of the conflicting
LPS/CP practices on south section include; not publishing of constraint log, lack of
detailed plan with sticky-note on board, PPC not published, and no constraint
analysis. However, the LPS/CP process in the south section of CSP01 was later
reviewed and repositioned. On all the project sections, the collaborative
programme/phase planning was developed from the master programme. It is worth
mentioning that the two contractors in the JV operated as a single organisation. The
implementation of the LPS/CP was a project based initiated driven by the JV partners
and the client.
7.3.1.2 Pre-construction Practice
The study revealed that some collaborative processes were applied on CSP01 at the
pre-construction phase. These include the collaborative involvement of the key
stakeholders in the early stage and the engagement of the main contractor in the
development of the design. One SM stated that:
”At the early stage or phase 1 of the project, we did a lot of collaborative meetings
with the stakeholders such as the land management, client, designers, and the main
contractors” [CSP01SM01, Planning manager]
This shows that the construction team members were involved in the collaborative
meetings at the pre-construction phase. It can be argued that the approach adopted
here could have also been favoured by the procurement route used. The planning
manager further explained that: “we did this to enable us hit the date, because our
Case Study Anaysis and Discussion Chapter Seven
201
goal is to accelerate the scheme. It is one of the fastest scheme and the collaborative
meetings helps”.
7.3.1.3 Nature of Last Planner/Collaborative Planning Meeting on CSP01
Various meetings were held to support the implementation of LPS/CP principles on
CSP01. These included; monthly project brief meeting, central senior managers’
look-ahead planning meeting, and weekly production planning meeting. During the
monthly project brief meeting, the project director, section managers, and the health
and safety manager made presentations on the status of the project in terms of time,
cost, quality, and safety. The central senior management look-ahead planning
meeting mostly involves the construction managers where strategic decisions on the
project are made.
It is worth noting that the senior management look-ahead meeting done here was not
the same with the look-ahead planning as advocated in the LPS (Ballard, 2000), as it
did not involve any form of make-ready process. In addition to this, weekly
production planning was done with the subcontractors, construction managers, and
work package managers among others. Also, a six week look-ahead, some
constraints, and the make-ready process were observed in the North and Central
sections. However, there was less discipline and commitment to the constraints and
make-ready process in some of the process observed. For instance, during one of the
sessions, the constraints board was not logged and on another occasion, no one was
assigned to address the identified constraint.
7.3.1.4 Percentage Plan Complete and Reason for Non-Completion Practice
This section presents the findings on LPS/CP practice, from document analysis and
observation. The study reveals that PPC and RNC were recorded on CSP01. Figure
7.1 shows a sample of PPC chart on CSP01. Figure 7.1 shows that the average PPC
on CSP01 for period consider here (10 weeks) was 72.29%, however, there seems to
be a lot of variableness in the weekly PPC as shown in the figure. For instance, 0%
was recorded in one of the weeks. When the planner was asked to explain the reason
for this, he stated that: “It is due to overestimation of work by those doing the work.
Some of the subcontractors make promises with little resource on site”
[CSP01SM04, Senior Planner].
Case Study Anaysis and Discussion Chapter Seven
202
Figure 7.1: Average PPC on CSP01 (A sample of document analysed)
Source: CSP01 production planning document file (used with permission)
It could be argued that the lack of make-ready process and clear removal of
constraints from the planned activities was also a contributory factor to this
occurrence. Additionally, the statement by the senior planner further shows the
importance of honesty and truth in making reliable promises.
The reasons for non-completion (RNC) were also published on CSP01 as shown in
Figure 7.2. However, it seems not much was being done with it. For instance, the
planning manager stated that “we record RNC but I don’t think the guys do anything
with it” [CSP01SM01, Senior Manager]. The figure shows previous activity not
complete and under estimation as some of the causes of RNC on CSP01. This could
mean that the make-ready process was insufficiently done.
Figure 7.2: Reason for non-completion of activities on CSP01
Source: CSP01 production planning document file (used with permission)
Case Study Anaysis and Discussion Chapter Seven
203
7.3.2 Support required for LPS/CP Implementation as Observed on
CSP01
Figure 7.3 reveals the emerging themes and sub-themes from the interview data
analysis on the support required for the successful implementation of LPS principles.
Figure 7.3 was generated using Nvivo 10 model tool. Nvivo is a qualitative data
analysis software used in analysing the data at this stage. The emerging themes are
categorised into three; (1) support required at the organisational level (2) support
required at the project level and (3) external support.
7.3.2.1 Process and Support required at the Organisational Level.
The analysis of the interview result reveals four key factors required from the
organisation for smooth implementation of LPS/CP. Some of these key factors as
shown in Figure 7.3 are discussed below.
a. Provision of Training
Some of the respondents suggested that the organisation must be committed to
training of its employees on the new approach. Some of the respondents on CSP01
stated that:
“There is need to educate others on the project on LPS/CP and invite other
site representative to be involved in the process” [CSP01MM01, Section
Engineer]. Also, a senior manager (SM) stated that “for an organisation that
is venturing into it, there is need to provide training and demonstration of
tangible benefits from previous implementation” [CSP01SM01, Planning
Manager]
This shows that at the organisational level, procedure should be put in place to
support training and facilitate the practice of LPS/CP across different business units
b. Inclusion of Last Planner/Collaborative Planning Practice in contract
Furthermore, some of the respondents were of the view that the process should be
part of the company policy for delivering its business and could include mandating it
in the contract with the supply chain. Some of the respondents stated that:
“There should be a point where it has to be mandated and written into the contract
and benefits should be shared” [CSP01SM02, Excellence Manager].“Make
it a company policy” [CSP01MM01, Section Engineer].
Case Study Anaysis and Discussion Chapter Seven
204
The subcontractors on CSP01 are also strongly in support of the inclusion of LPS/CP
practice in the contract.
c. Continuous Support from the Management
Full management support and the use of collaborative form of procurement were also
viewed as necessary at the organisational level. This entails making it a company
policy. A construction manager stated that:
“The project director is very proactive on the application of collaboration
principles on this project, the full support of the management is key to
bringing the subcontractor into the session” [CSP01SM03, Construction
Manager]
Again, this shows that the management has an important role to play for the
successful implementation of LPS/CP principles on a project.
Case Study Anaysis and Discussion Chapter Seven
205
Figure 7.3: Support for successful implementation of Last Planner/Collaborative Planning
Case Study Anaysis and Discussion Chapter Seven
206
7.3.2.2 Process and Support required at the Project Level
The analysis of the interviews revealed some of the support required at the project level as
observed on CSP01. Five key supports were identified. These include; (1) Appointment of
facilitator, (2) Involvement of the team required, (3) Digitalisation of Post-It Note, (4)
Provision of LPS/CP room on site, and (5) Proactive involvement of the construction
manager. These factors are now discussed below.
a. Appointment of a Facilitator and Involvement of Team Members Required
Some of respondents were of the view that a facilitator is an essential support required at the
project level. For instance, one of the middle managers stated that: “A facilitator is needed to
coordinate the process for the initial start, this is an early stage support” [CSP01MM02,
Section Engineer]. This is because the process cannot really progress if it is not duly
facilitated, as observed in the South section of this project. However, some of the respondents
were of the view that facilitators should be limited to the early stage only. This is with the
belief that the team could carry on with the process after the initial facilitation. One of the
respondents argued that: My view is that initially, it needs facilitation, but as the process goes,
the team should do it themselves [CSP01SM01, Planning Manager]. It is worth noting that
this respondent has only two years’ experience in LPS/CP practice.
b. Digitalisation of the use of Post-It® Notes
Some of the respondents suggested that digitising the sticky-notes and collaborative
programming board could improve the level of interaction among the men on site. Thus, it
could reduce non-value adding activities by the men on site which may arise from
movements. The Planning Manager stated that: “We are planning to use ‘touch screen’
instead of post-it note. The post-it note is stock in the room and cannot be distributed”,
CSP01SM01, Planning Manager].
Digitalisation of the LPS/CP could support the process, however, this cannot in any way
replace the face to face meeting which is essential in developing the programme in the first
instance. Previous studies have shown that face-to-face discussion is the most efficient
communication channel in construction (Murray et al., 2000; Gorse et al., 1999). However,
the digitalisation of the LPS process has shown to support the implementation on projects
(Ghafari 2015; Couch, 2015). For instance, Cough (2015), observed that ‘Touch Screen Plan’,
Case Study Anaysis and Discussion Chapter Seven
207
(a software that has been integrated with the LPS), saves time in making changes to the
handwritten sticky notes and provides real time information to the team on promises and
commitments made.
c. Provision of Production Planning and Control Centre on Site
The respondents were of the view that a designated room for LPS/CP meetings should be
provided on site. One of the subcontractors stated that: “Allow for a suitable rooms/facility on
site for CP meetings and session” [CSP01SC02, Project Manager]. This is essential as such
room/facility could further provide information visually to other members of the team who
were unable to participate in meetings in real time. Also, visiting the room would give
everyone an idea of project activities on site.
However, setting the room outside the project site could reduce such benefits and could
contribute to non-value adding activities. This is because it would require site workers
travelling to the head office to view the board. But siting the production planning and control
centre on site would create a feeling of belonging to the site team.
d. Proactive Involvement of Construction Manager
The active involvement of the construction manager in the LPS/CP meetings was also seen as
an essential support required at the project level for LPS/CP implementation on CSP01. The
active involvement of the construction or project manager at the project level would help the
project team to see the process as the company process of delivering its business. Practically,
this entails attending and contributing in production planning meetings by the project
manager. According to McConaughy and Shirkey, (2013) and Hamzeh and Bergstrom,
(2010), when a process on a project is viewed as external or ad hoc, there would be less
commitment from the team.
7.3.2.3 External Process Support Required
The external support and process referred to here are those supports needed that could be
coming from outside the organisation and the project environment. Two of these supports
were identified by the respondents on CSP01. These are: (1) Development of standard metrics
for LPS/CP implementation (2) Industry and academic partnership.
Case Study Anaysis and Discussion Chapter Seven
208
a. Development of LPS/CP Principle Standard/ Metrics
LPS/CP implementation process standardisation was identified as an external support and
process required for successful LPS/CP implementation. For instance, a Senior Manager
stated that: “There is need to bring out CP principle implementation metrics” [CSP01SM04,
Senior Planner].
The above statement shows that there is lack of consistency in the current application of
CP/LPS practiced on projects. Also, this may be due to ignorance, since the LPS has standard
principles and metrics (Ballard, 2000). This indicates that more awareness and support is still
required for effective implementation.
b. Industry and Academic Partnership
Some of the respondents on CSP01 observed that a close partnership between the construction
companies and the academic institution could further support the LPS/CP implementation in
the industry. One of the managers suggested that:
“There is a need for more alliance between the academia and the industry. More
articulation and pro-activeness in communicating improvement and findings to
industry. More emphasis should be placed on the correlation between the industry and
the institution” [CSP01SM02, Excellence Manager].
7.3.3 Procurement and LPS/CP on CSP01
Two broad themes emerged from LPS/CP practice in relation to the procurement approach
used on CSP01. These are; the procurement practice and the impact of the procurement
practice on LPS/CP implementation on CSP01.
7.3.3.1 Procurement Practice Observed on CSP01
The two main contractors on the project were into a joint venture and the researcher was made
to understand that the team is viewed as a single entity. This implies that all members of staff
on the project have to ignore their original company culture or identity in performing their
responsibility on the project and create a shared culture. One of the strategies adopted to
reduce parent company culture and integration of the team was; the recruitment of some staff
directly on the JV, hence such staff only had one identity at the time. According to Smith,
Case Study Anaysis and Discussion Chapter Seven
209
(1994) for a joint venture to work successfully, there is a need to make provision for cultural
compatibility, shared ownership, and joint control.
The other factor that also supported the joint venture on CSP01 was the fact that the two
contractors had been in a similar joint venture in the past. However, every project is unique
and the team on the previous could be different from the current team. Also, the
subcontractors were into a framework agreement with the joint venture. The project was
procured using design and build (D&B) and early contractor involvement (ECI) approach.
This integrated approach to project delivery contributed to the level of collaborative working
experienced on CSP01. Dave et al., (2015b) pointed out that an integrated project delivery
process breaks organisational boundaries and aligns the goals of the parties in the process to
achieve the project objectives. This is largely supported by lean principles (Howell, 2013).
However, this does not sum it all as there were issues with the design not meeting up with the
construction, in term of time. This was because the design was only at 50% completion when
construction commenced on site. Thus, much pressure was on the design team as the
construction programme was being accelerated. The planning manager stated that:
“The design phase has a lot of issues, we spent a lot of time in design. The problem is
not in the quality of the design, but the time the design needs to be complete. The key
issue is the need for alignment between design and construction. It was more a just-in-
time approach that was used for design and construction” [CSP01SM01, Planning
Manager].
Apparently, since design was only at 50% completion before construction, this could be
expected.. More so since the construction programme was accelerated as a result of the use of
LPS/CP principles. However, this shows the need to properly and carefully plan on how
design and construction would align on a D&B project, especially when there is an
understanding that the construction programme could be accelerated.
7.3.3.2 Impact of Procurement Practice on LPS/CP on CSP01
The study reveals three impacts of procurement on LPS/CP practice on CSP01. These are: (1)
Opportunity for buildability/constructability review (2) Allowing for early stakeholders
involvement and (3) Management of design and design team. Some of these are discussed
below.
Case Study Anaysis and Discussion Chapter Seven
210
a. Opportunity for Buildability/Constructability Review
The study revealed that using the D&B and ECI approach on CSP01 allowed the construction
team and the design team to engage in constructability review. One of the respondents stated
that:
“Using the ECI, all the designs are reviewed by the construction team to get things
out early. We get value out of the process since we make all the decisions together”
[CSP01SM03, Construction Manager]
It can be argued that the benefit coming from the process is not only in getting the design out
early but also the value created as a result of the input from the construction team. According
to Othman, (2011) design constructability/buildability review improves the performance of
the constructed facility by reducing cost, improving quality of the end product and
accelerating completion time. Traditionally, design tends to be separated from construction
which also contributes to the poor performance of the industry (CIOB Report, 2010).
However, lean construction principles such as the LPS encourage collaboration from design to
delivery, thus improving the final product (Howell, 2013; Koskela, et al., 1997).
b. Management of Design and the Design Team
The study also observed that the project managers were in charge of the design process and
the design team. This is largely due to the fact that the designers are part of the joint venture
and they all work to achieve the overall project goal. The planning manager argued that:
“We will not be able to do this in a traditional approach! We do have everything
ourselves. We are in a better position to manage the design and also manage the
design team” [CSP01SM01, Planning Manager].
In addition, it was observed that the designers, the contractors, and subcontractors shared the
same office. This increased the level of conversation between the design and construction
teams. The design team was also involved in the key production planning meetings. This
contributed to the quick feedback the construction team received from the design team when
required.
However, it could be argued that the contract alone cannot make the team on the project to
collaborate, rather, it is the paradigm shift from the traditional mind-set among the project
Case Study Anaysis and Discussion Chapter Seven
211
team. Ballard and Howell, (2005) observed that on D&B projects where the traditional mind-
set and practice dominate, design could still be separated from construction. This suggests
that the conversations that occurred during the various LPS/CP meetings on CSP01
contributed to the development of collaborative working practice on the project. The
procurement approach is more of a platform for .collaborative working practice to develop.
7.3.4 Impact of LPS/CP Practice on Construction Process Improvement on
CSP01
The evidence on the impact of LPS/CP practice on construction process improvement (CPI)
was sourced through the semi-structured interviews and structured survey. Both the
interviews and survey were used for methodological triangulation. The structured survey
enabled the study to obtain objective data on the impact and to triangulate the findings from
the interviews. Figure 7.4 reveals the findings from the semi-structured interview as generated
and exported from Nvivo 10 using “Model tool”. While Figure 7.5 presents the survey results
analysed using Statistical Package for Social Science 21 (SPSS 21). The findings presented in
Figures 7.4 and 7.5 on the impacts of LPS/CP on construction process improvement are
discussed concurrently in the next section.
Figure 7.4: Impacts of LPS/CP on CPI observed on CSP01 (interview results)
Case Study Anaysis and Discussion Chapter Seven
212
7.3.4.1 Impact on Time
The analysis in Figure 7.5 reveals that 100% of the respondents on CSP01 agreed to have
gained more time from the use of LPS/CP principles on the project. This was further
confirmed by the construction manager from the interview:
“It has positive impact on the project, things are done on time on the project, and we
work better because we plan ahead” [CSP01SM03, Construction Manager].
The result further showed that 85.7% of the respondents indicated that the LPS/CP
implementation did not slow down the progress of work on CSP01
7.3.4.2 Collaborative Working Practice, Communication, and Process Transparency
Figure 7.5 reveals that 100% of the respondents agree that their collaborative working
practice has improved for better on the project. This could have occurred as a result of
improvement in communication among the project stakeholders which the LPS principles
support. For instance, 57.1% of the respondents strongly agreed that the implementation of
LPS/CP had improved the level of communication among the stakeholders on the project.
This was further confirmed in the interview responses: Some of the respondents stated that:
It helps us to bring the people together to impact on their action, people like to
remain in silo in their areas. This helps to bring them together. It helps improve
communication which influences the process [CSP01SM01, Planning Manager]. “It
gets everyone at the site level involved in the delivery process” [CSP01SM05, Senior
Engineer]
This shows the LPS/CP implementation supports collaborative communication and the
holistic involvement of stakeholders in the decision making process. For example, the survey
revealed that 100% of the respondents had good understanding of the project goal as a result
of their involvement in the LPS/CP meetings. This shows the importance of engagement and
involvement in developing common understanding of project activity and objectives.
According to Pasquire, (2012) developing a common understanding of the project goals
drives out unnecessary work and keeps the team productive. This was further confirmed with
this statement
Case Study Anaysis and Discussion Chapter Seven
213
Figure 7.5: Last Planner/Collaborative planning impacts on construction process improvement on
CSP01
0 50 100
Good understanding of the purpose of PPM on thisproject
Working practice has changed for better on this projectas a result of my involvement in PPM meetings
My understanding of the project has greatly improved asa result of my involvement in the PPM meetings
The application of PPM has improved the level ofcommunication among the project stakeholders
The PPM process has improved my trust and confidencein other members of the project team
The PPM process has enabled us to reduce the level of re-work on this project significantly
The PPM process has enabled us to be more efficient inour construction processes
We have observed significant increase in constructionprocess
We have gain more time as a result of using PPMprinciples on this project
The PPM process has reduced the adversarial relationshipon this project
Our safety record has improved on this project as a resultof the PPM process
The PPM process has slowed our progress on this project
PPM process slowed down our progress initially, butspeed it up after a while
It is time consuming
I am yet to see the value in the PPM process
I like working in this manner
F16
F15
F14
F13
F12
F11
F10
F9F8
F7F6
F5F4
F3F2
F1
Respondents' agreement on the level of impacts in percentages
Imp
rove
me
nt
fact
ors
me
asu
red
on
th
e p
roje
ct
Strongly agree Agree Not sure Disagree Strongly disagree
Case Study Anaysis and Discussion Chapter Seven
214
by the planning manager: “It helps everyone to understand what is required, it keeps
everyone on the same page”. This shows that the LPS/CP process supports
transparency.
7.3.4.3 Impact on Re-work, Safety, and General Process Improvement
The analysis in Figure 7.5 reveals that 85.7% of respondents believe that the LPS/CP
process significantly reduced the level of re-work on the project. Practices such as
buildability design review, collaborative programming/phase planning, and look-
ahead planning meetings among others could have contributed to this. From the
study, 57.1% of the respondents agreed that the LPS/CP process enabled the team to
be more efficient in the construction process. This is because the LPS/CP process
supports transparency and visualisation of processes on the project. During the
interview, one of the respondents stated that:
“The collaborative programming session using Post-It Notes help us to put
our thought on the wall, which makes us to see the difference in what works”
[CSP01SM01, Planning Manager].
In term of safety, 71.4% of the respondents claimed not to be sure if the safety record
had improved as a result of the LPS/CP process on the project while 28.6% agreed it
had. This could mean that majority of the respondents have not really recognised the
impact of the LPS/CP processes on safety performance on the project. For instance,
the safety record data board on CSP01 indicated that 1.5 million hours of work had
been done without accident. Also, during the interview, one respondent stated that:
“Since the CP process allows one to determine what to be done, it makes the
process clear. It helps coordination, thus, it helps with health and safety”
[CSP01MM02, Section Engineer].
Furthermore, majority of the respondents (85.7%) agreed to have experienced
significant improvement in all construction processes on the project. Thus, it is no
surprise that over 80% indicated they were happy to work using the current
approach.
Case Study Anaysis and Discussion Chapter Seven
215
7.4 Case Study Project Two (CSP02): Highways Infrastructure
a. Description of CSP02
The case study project two (CSP02) is located in the West of Yorkshire, England. It
is a highway infrastructure project. The aim of the project was to reduce congestion
on the network using technology to vary speed limits. The project was divided into
two main sections; North bound and South bound sections. Each section was further
divided into three links, to help in managing the entire project with the LPS/CP
process. A single production planning session was held for all the sections at the
project site office. The process was internally facilitated by the site agent with the
support of the programme manager and the work package managers.
The two main contractors on CSP02 were not exactly the same with those on CSP01.
For instance, contractor A on CSP02 was not involved in CSP01, but contractor B
was involved on CSP01. This could be due to the framework agreement the client
has entered with with these contractors. It is worth mentioning that CSP01 and
CSP02 are for the same client.
The project is an improvement of an existing motorway to a smart motorway.
Contractor A on CSP02 has expertise in transforming roads into intelligent network
using technology, while contractor B has a good record of successful delivery of
highways infrastructure projects. The JV was formed to harness the skills and
expertise from the different organisations. Both contractors claimed to have used
LPS/CP on their previous projects. The attributes of CSP02 are presented in Table
7.3.
Table 7.3: CSPO2 Project Attributes
Project Attributes Observed attributes on CSP02
Nature of project Highway and Infrastructure
Location of project West of Yorkshire, England
Nature of works Improve of motorway to Smart motorway
Type of client Public client
Proposed project duration 24 months
Stage of project at the end of
the case study
80% completion
Procurement arrangement Traditional design bid build
Procurement mode Joint venture
Case Study Anaysis and Discussion Chapter Seven
216
Contract sum £120 million
Number of subcontractors on
site
9
Subcontracting arrangement Framework agreement
Point of application of LPS/CP
principles
Construction
LPS/CP facilitation process Internally facilitated
Based on the data collected, CSPO2 was procured with traditional design-bid-build
(DBB). However, the subcontractors on the project were on a framework agreement.
As at the end of the case study, the project was at 80% completion. This shows the
project had progressed enough to capture LPS/CP practices and its impact on
construction process improvement on the project.
b. Demographic Information of the Respondents on CSP02
Table 7.4 reveals that the respondents interviewed on CSP02 have some practical
experience on the application of LPS/CP as revealed in their years of experience.
This implies that the respondents would be able to explain the process currently used
on the project.
Also, the respondents are fairly distributed across the various stakeholders on the
project, which could further minimise the level of bias in their response. Table 7.4
shows that the respondents have a lot of experience in LPS/CP this could be due to
their working together on previous projects where LPS/CP was used. This suggests
that their response in this study could be relied on. Also, the findings could be used
as one of the basis for developing an approach to improve the current LPS/CP
practice in the UK construction industry.
Table 7.4: Demographic Information of the Respondents on CSP02
S/NO Respondent
code
Categorisation of
role on the project
Specific
Position
Years of
exp. in
LPS/CP
Year of
exp. in
const.
1 CSP02SM01 Senior manager Planning
manager
7 28
2 CSP02SM02 Senior manager Senior
excellence
manager
2 16
3 CSP02SM03 Senior manager Construction 6 30
Case Study Anaysis and Discussion Chapter Seven
217
manager
4 CSP02MM01 Middle manager Senior planner 4 25
5 CSP02MM02 Middle manager Senior engineer 4 20
6 CSP02OM01 Operational manager Section engineer 3.5 12
7 CSP02OM02 Operation manager Section engineer 1 15
8 CSP02SC01 Subcontractor Project manager 4 16
9 CSP02SC02 Subcontractor Project
Coordinator
3 15
7.4.1 Last Planner/Collaborative Planning Practice Observed on CSP02
The data on LPS/CP practice on CSP02 were obtained via documents analysis,
unstructured observation, and semi-structured interviews. The LPS/CP practice
observed are discussed under the following emerging themes: (1) Application of
principles (2) Pre-construction practice (3) Nature of production planning meetings
and (4) PPC and RNC practices.
7.4.1.1 Application of Last Planner and Collaborative Planning on CSP02
The application of LPS/CP on CSP02 started at the construction stage and it was
among the key processes adopted in the delivery of the project. . On CSP02, there
was a dedicated room and collaborative programming board for production planning
meetings. Non-permanent markers of different colours were used for activity
scheduling on the collaborative programming board. Visual management was also
used to indicate the status of the project. Document analysis revealed that PPC and
RNC were usually sent to the management and also made available on the notice
board on the project site. It was further observed that the subcontractors shared the
same office with the main contractor which offered them the opportunity to see the
published PPC and RNC.
7.4.1.2 Pre-construction Practice
It was observed that the contractors did not have much input at the pre-construction
stage. For instance, the contractors were not involved in the design phase due to the
nature of the contract, one of the respondents stated that:
“The designers were employed by the client but the risk is borne by the joint
venture. The joint venture was not involved in the design stage and the design
is incomplete and the scope of work has changed over this time. If it is D&B
Case Study Anaysis and Discussion Chapter Seven
218
it would be better, because it will give us the opportunity to control the
designers, for instance, we have the designers on site, but if we have design
issues it takes time to get back to us” [CSP02SM02, Site Agent/Production
Planning Manager].
Again, this shows that even with the DBB procurement, the design was still not at
100% completion before the commencement of the construction phase.
7.4.1.3 Nature of Production Planning Meetings on CSP02
There were various meetings during the construction stage, designed to support the
production planning and control on the project. These meetings include: the
collaborative programming/phase planning meetings, technical planning meetings,
and the weekly planning meetings. Initially, the collaborative programing meeting
was held once in a month, but this was later increased to twice a month at the peak of
the project. During the collaborative programming meeting, the subcontractors,
construction managers, the planner, and subcontractor’s work package managers
were involved.
However, further investigation revealed that only major subcontractors were
frequently involved in the sessions. The smaller subcontractors were only involved
when their task was on the critical path. The six week look-ahead planning was
usually done during the collaborative programming meeting. Constraints were also
identified and the responsibility for constraint removal assigned.
However, it was observed that not all the people assigned to remove the identified
constraints were involved in the meeting, for example, the designers. This further
impacted the level of commitment that was made by the participants at the meeting.
To address this, technical meetings were held with the design team to sort out the
observed design issues at the collaborative programming meeting on another day.
This shows that the make-ready process was done outside the look-ahead meeting.
WWP planning was also held on CSP02 and it was called weekly production
planning meeting/senior management meeting.
7.4.1.4 Percentage Plan Complete and Reason for Non-completion Practice
The document analysis revealed that PPC and RNC were recorded on CSP02. As
shown in Figure 7.6 (A sample of the document analysed), the average PPC observed
Case Study Anaysis and Discussion Chapter Seven
219
on the project was 90% (for a 5 month period). PPC was also described as a
programme certainty monitor on CSP02. Figure 7.6 further shows that the PPC
average on CSP02 was fairly stable over some weeks.
Figure 7.6: Average PPC chart on CSP02 (A sample of document analysed).
Source: CSP02 production planning document file (used with permission)
However as indicated in Figure 7.7, frequent changes in priority, changes to design,
insufficient labour, and late design were the main RNC which influenced the PPC
weekly average.
Figure 7.7: Reasons for non-completion of activities (A sample of document analysed)
Source: CSP02 production planning document file (used with permission)
0.0%
20.0%
40.0%
60.0%
80.0%
100.0%
120.0%
12
/01
/14
19
/01
/14
26
/01
/14
02
/02
/14
09
/02
/14
16
/02
/14
23
/02
/14
02
/03
/14
09
/03
/14
16
/03
/14
23
/03
/14
30
/03
/14
06
/04
/14
13
/04
/14
20
/04
/14
27
/04
/14
04
/05
/14
11
/05
/14
18
/05
/14
25
/05
/14
Percentage Plan Complete chart
ProgrammeCertaintyUpper Control Limit
012345
A -
Des
ign
Ch
ange
/La
te…
B -
Insu
ffic
ien
tLa
bo
ur
/…
C -
Insu
ffic
ien
tm
ate
rial
s
D -
Un
de
r-es
tim
atio
n
E -
Po
or
wo
rkm
ansh
ip
F -
Ch
ange
in p
rio
riti
es
G -
Wea
ther
H -
Ext
ern
alIn
flu
en
ces
J -
Gro
un
dco
nd
itio
ns
K -
Cab
lesTo
tal N
um
be
r
Reason for Non-completion
Reason for non completion of activities
Case Study Anaysis and Discussion Chapter Seven
220
It was observed that on CSP02, when the client made changes to the design and
scope of work, the construction team had to shift focus to the current client demand.
One of the respondents stated that:
“The biggest problem we have got is to have a client who does not know
what he wants, is always changing things. The problem is how to manage
those changes” [CSP02SM01, Programme Manager]
This further shows that these changes could be impromptu, since the activities have
to be included in the WWP. Also, there could be some issues in the constraint
removal (make-ready process) in the look-ahead planning with regard to the late
design information. However, this may not sum it all as the joint venture did not have
control over the design team, thus, not much could be done when such issues came
up.
7.4.2 Support required for Last Planner/Collaborative Planning
Figure 7.8 reveals the emerging themes and sub-themes from the interview data on
the support required for successful implementation of LPS/CP as observed on
CSP02.
7.4.2.1 Support required at the Organisational Level
The support required from the organisation for successful implementation of LPS/CP
observed on CSP02 include; (1) Provision of training, (2) Mandating it in contract
and (3) Creation of awareness.
a. Training Support
Majority of the respondents, including the subcontractors and those working directly
for the joint venture on CSP02, identified the need for provision of training by clients
and main contractors. For instance, some of the respondents stated that:
“There is need for guidance on LPS/CP right from conception by the
management, we do receive some training on LPS/CP” [CSP02SC01,
Project Manager]. The need for provision of training was also identified by
the programme manager “Training is very essential, without it the facilitation
would not work” [CSP02SM01, Senior Manager].
Case Study Anaysis and Discussion Chapter Seven
221
Another senior manager suggested that the nature of training to be provided should
be tailored for each stakeholder on the project. For instance, it was argued that the
initial training for the smaller subcontractor should be to explain the benefits of the
process in order to get their buy-in before full implementation.
b. Awareness Creation and Mandating it in the Contract
The respondents observed that creation of awareness on LPS/CP practice and its
inclusion in the contract with the supply chain are essential. One of the respondents
stated that:
“The company intranet, newsletter should be used and more importantly,
making it part of the company procedure that could be rolled”
[CSP02SM02, Site Agent].
Making LPS/CP a part of the company policy could further support the practice in
the organisation and across its supply chain. Furthermore, the respondents on CSP02
suggested that the process should be formally included in the contract by the
organisation [CSP02MM01, Agent; CSP02SM02, Site Agent; CSP02SM01, Site
Agent].
Case Study Anaysis and Discussion Chapter Seven
222
Figure 7.8: Support for successful implementation of LPS/CP
Case Study Anaysis and Discussion Chapter Seven
223
7.4.2.2 Support Required at the Project Level
The support required at the project level as observed on CSP02 include; (1) Pre-
planning by the team before production planning session (2) Discipline of all team
and transparency (3) Facilitation and appointment of champions (4) Involvement of
the required stakeholders.
a. Pre-planning by the Team before Production planning session.
The respondents interviewed on CSP02 observed that pre-planning by the
subcontractors and work packages managers before CP session is essential for
success at the project level. Some of the respondents stated that:
“The subcontractors must come with realistic programme, not just the
duration on the contract programme” [CSP02MM02, Site Agent]. “Prepare
a plan before the collaborative planning session (base programme)”
[CSP02SM02, Production Planning Manager].
The need for pre-planning before the collaborative production planning sessions
cannot be overemphasised, as it keeps all the team in the right state to make
meaningful contribution during the session.
b. Discipline of all Team and Transparency
The study reveals that discipline and transparency are essential at the project level for
successful implementation of LPS/CP. The discipline and transparency required here
are in terms of telling the truth. Some of the respondents stated that:
“One of the biggest thing during the CP session is people not telling the
truth, you got to be honest with yourself and rest member of the team, it is no
use to say I will finish the work today while you know you still need 3 or more
days. It is no good to say I will do it next week and you know you have not got
the men to do” [CSP02SM01, Programme Manager].
The above statement suggests that some project team members make unrealistic
promises.
c. Facilitation and Appointment of Champions
The study reveals the need for appointment of a facilitator and champions to be
essential at the project level. Some of the respondents stated that:
Case Study Anaysis and Discussion Chapter Seven
224
“A facilitator is needed to promote the benefits of LPS/CP, an external
facilitator within the 1-4 weeks and internal facilitation to continue the
process. Also, appoint lean managers, both at the project and organisational
levels to promote the practice across the business” [CSP02SM01,
Programme Manager]. “The session should be facilitated by someone who
has knowledge of the work involved to present a bigger picture”
[CSP02MM02, Site Agent]. “Have a champion to promote it”
[CSP02MM01, Section Engineer].
The above statements from respondents show the need for facilitators and champions
for driving the process. The statement further suggests that the facilitator should have
some level of understanding on the nature of work executed. For example, this
knowledge of the construction process would be particularly useful in making
effective decision in scheduling of activity.
d. Involvement of all the Required Stakeholders
The respondents believed that full engagement of all “required stakeholder” (those
that have the required capability to make decisions during production planning
meetings), is essential for its success at the project level. One of the respondents
stated that:
“The collaborative programming session should involve the client, the
designers, main contractors, and subcontractors” [CSP02SM03, Manager].
Again, this call by the respondents shows that not all the required stakeholders are
engaged in the collaborative programming session. For instance, it was observed that
the designers were not usually involved in the session due to the nature of the
procurement used; DBB. The implication of non-all-inclusive engagement of the
stakeholders in the process is that the make-ready and constraint removal process
would be incomplete. This increases the level of uncertainty in the activity
scheduled.
7.4.2.3 External Support required for LP and CP Implementation
The external support for LPS/CP implementation identified on CSP02 include: (1)
Industry and academic partnership and (2) Process standardisation.
Case Study Anaysis and Discussion Chapter Seven
225
a. Industry and Academic Partnership
Some of the respondents believed that higher education institutions which provide
training in construction project management, and civil engineering among others
have a role to play in passing on the knowledge to their students. This could support
the implementation of the process. One of the respondents argued that:
“There is need to adopt some of this concept such as collaborative planning
in their training and teaching. The curriculum should be updated to what is
happening in the industry, CP should be included in the project management
programme” [CSP02SM02, Production Planning Manager].
This shows that construction management and civil engineering training should not
only focus on the hard or technical skills alone, but other soft management skills
such as those encouraged in lean principles should also be taught. It has been
observed that the current traditional approach to construction project management is
that of “command and control” with little or no opportunity to receive feedback as
encouraged in the LPS processes (Parrish, 2014; Ballard, 2000; Ballard, 1997).
Studies have shown that previous academic knowledge on lean principles support the
implementation of LPS on construction projects (Kim and Jang, 2006; Alarcon et al.,
2002). It is no surprise that higher institutions offering programmes in construction
project management and civil engineering are now offering modules in lean
construction. Example of such institutions are; University of California, Berkeley
USA, Nottingham Trent University, UK, and Michigan State University, USA, USA
among others (Nottingham Trent University, 2016; UC Berkeley, 2016; Michigan
State University, 2016).
b. Process Standardisation
On CSP02, the respondents observed that a common or standard approach to LPS/CP
implementation would support its rapid implementation. Some of the respondents
interviewed are of the opinion that the approach seem to vary from one project to
another. One of the subcontractors stated that:
“People tend to view collaborative planning differently, there is need to have
one format or approach. There should be one approach across projects”
[CSP02SC01, Subcontractor’s Project Manager].
Case Study Anaysis and Discussion Chapter Seven
226
This statement further shows that LPS/CP practices as observed by the respondents
are not consistent across the projects they have been involved in, in the past.
However, that does not mean the LPS does not have a standard process (see Ballard,
(2000)), the variation observed could be due to lack of discipline in the
implementation of the components or ignorance on the process.
7.4.3 Procurement and LPS/CP on CSP02
Two broad themes emerge from LPS/CP practices in relation to the procurement
approach used on CSP02. These are; the procurement practice and the impact of the
procurement practice on CSP02.
7.4.3.1 Procurement Practice on CSP02
CSP02 is a joint venture project comprising of two major top UK contractors. The
project was procured using Design Bid Build, this means the design has been
completed before the main contractors, and subcontractors were brought in. This also
influenced the implementation of LPS/CP on the project.
7.4.3.2 Impact of Procurement on LPS/CP Practice on CSP02
The study reveals that the procurement approach used had some impact on the
implementation of LPS/CP on CSP02. Some of the impacts include; (1) frequent
occurrence of constructability issues (2) long lead time in response to design issues
from the designers and (3) design changes and absence of designers in CP meetings.
a. Frequent occurrence of Buildability/Constructability Issues
The study reveals that constructability was a reoccurring incidence on CSP02 as
captured in the interview and observation. One of the subcontractors stated that:
“The barrier here has that the design is not been met. When you set out to
work in a particular area and the design is not ready there is not much you
can do. The drawing is not working as expected by the contractor. Some of
the information used in the design were wrong and also client changes his
decision at some point” [CSP02SC01, Project Manager].
This shows that the lack of involvement of the construction team in the design
process, coupled with the use of wrong information by the designers further
contributed to the constructability issues observed in the construction phase. The
implication of this for the implementation of LPS/CP principles on the CSP02 is that
Case Study Anaysis and Discussion Chapter Seven
227
the promises made at the various production planning meetings could still be faced
with other design challenges on site. However, this should be expected when there is
no constructability review of design before construction (Othman, 2011). On CSP02,
constructability or buildability review was limited due to the nature of procurement
adopted.
b. Long-lead Time in Response to Designs Issues from the Designer Team
The study reveals that there is long lead time in receiving response from the
designers on design issues. This could be largely due to the fact that the designers
were not employed by the joint venture. Some of the respondents stated that:
“If it were D&B it will be better because it will give us the opportunity to
control the designer. We have the designers on site but if we have design
issues it takes time to get back to us” [CSP02SM02, Production Planning
Manager].
“The designers are employed by the client and it does affect the collaborative
planning, we only have liaison meeting with the designer rather than CP to
try and focus on the priority, but it does not help. The best way to control
somebody is when you are paying them. If you are paying somebody, they
listen more than when someone else is paying them. It is not as it used to be
initially, they try to listen a bit. The designers have little appreciation of the
commercial implications of what they do and they don’t do. It is very difficult
but we have to manage it” [CSP02SC01, Project Manager].
The above statements show the impact of the procurement approach on LPS/CP
implementation. The argument that the designers seem not to understand the
commercial implication of their action somewhat suggests that the design team was
only working to achieve their individualist goal on the project not minding what
became of other stakeholders on the project. This could have been largely informed
by the traditional mind-set or approach to managing construction project as they also
exhibited signs of unwillingness to get involved in the collaborative programming
meeting session with other stakeholders on the project. However, the idea of
controlling the designers as expressed by the contractors [CSP02SM02;
CSP02SC01], still shows frustration.
Case Study Anaysis and Discussion Chapter Seven
228
7.4.4 Impact of LPS/ CP Practice on Construction Process Improvement
on CSP02
Figure 7.9 presents findings on the impact of LPS/CP implementation on CSP02 on
CPI captured from the interviews. Figure 7.10 presents the impacts from the survey.
The findings shown in both figures are discussed concurrently below.
Figure 7.9: Impacts of LPS/CP practice on CPI observed on CSP02 (interview results)
7.4.4.1 Impact on Time and Programme
The analysis results of the survey as presented in Figure 7.10 reveals that 50% of the
respondents agreed to have gained more time on the project through the use of
LPS/CP while 50% claim not to be sure. The uncertainty expressed by some of the
respondents could be due to the fact that the project was still on-going. The interview
result further confirmed measurable gain with respect to time. Some of the
respondents stated that:
Our initial programme was 80 weeks and we have reduced it to 60 week and
now we are on week 57, the collaborative planning has helped in achieving
this. The remaining time will be used to do extra work [CSP02SC01,
Subcontractor’s Project Manager].
“We did collaborative planning on pre-cast concrete on the road, through
this, we were able to reduce the activity duration by four days”
[CSP02SM02, Production Planning Manager].
Case Study Anaysis and Discussion Chapter Seven
229
“On this scheme the client has introduced many changes, if it is added end to
end, it will take many months to build. We have been asked to finish it in two
months as addition to the contract time, this is how big an issue it is, without
collaborative planning and Last Planner approach we can’t do
it”.[ CSP02SM01, Programme Manager]
This shows that LPS/CP processes have significant impact on the time gain on the
project. However, majority of the respondents (about 62.5%) indicated that the
process was time consuming. It is interesting to note that majority of them (62.5%)
also believe there is added value in the time spent in the process.
7.4.4.2 Collaborative Working Practice, Communication, and Process
Transparency
Figure 7.10 reveals that 85% of the respondents agreed that their working practice
had improved for better on the project as a result of the LPS/CP process. Also, all
respondents indicated that the implementation of LPS and CP had improved the level
of communication among the stakeholders on the project. The level of adversarial
relationship also reduced, as indicated by over 75% of the respondents. Furthermore,
the survey result reveals that 100% of the respondents have good understanding of
the project as a result of their involvement in the LPS/CP meetings. This was further
confirmed from the interview response, as one of the respondents stated that:
“There is less conversation with the Gantt chart and primavera, but high
conversation in the CP process. It helps the foremen to understand the
programme. The white board and the post it-note help to increase and create
better understanding of the project to the least team on site” [CSP02SM02,
Production Planning Manager].
This shows that the LPS/CP process supports transparency and process visualisation.
A study by Tezel et al., (2010) revealed that process visualisation does not only
support transparency, but also leads to improved communication across the project
team members. In addition, about 50% of the respondents indicated that their
confidence and trust in other stakeholders on the project had improved as a result of
the LPS/CP process on the project, 25% disagreed while 25% claimed not to be sure.
Case Study Anaysis and Discussion Chapter Seven
230
Figure 7.10: Last Planner/Collaborative planning impacts on construction process
improvement on CSP02
0 50 100
Good understanding of the purpose of PPM on thisproject
Working practice has changed for better on thisproject as a result of my involvement in PPM…
My understanding of the project has greatlyimproved as a result of my involvement in the PPM…
The application of PPM has improved the level ofcommunication among the project stakeholders
The LPS/CP process has improved my trust andconfidence in other members of the project team
The LPS/CP process has enabled us to reduce the levelof re-work on this project significantly
The LPS/CP process has enabled us to be moreefficient in our construction processes
We have observed significant increase in constructionprocess
We have gain more time as a result of using PPMprinciples on this project
The LPS/CP process has reduced the adversarialrelationship on this project
Our safety record has improved on this project as aresult of the PPM process
The LPS/CP process has slowed our progress on thisproject
LPS/CP process slowed down our progress initially,but speed it up after a while
It is time consuming
I am yet to see the value in the PPM process
I like working in this mannerF1
6F1
5F1
4F1
3F1
2F1
1F1
0F9
F8F7
F6F5
F4F3
F2F1
Respondents' agreement on the level of impact of PPM in percentages
Imp
rove
me
nt
fact
ors
me
asu
red
on
th
e p
roje
cts
Impact of production planning and management on construction process improvement on case project 2
Strongly agree Agree Not sure Disagree Strongly disagree
Case Study Anaysis and Discussion Chapter Seven
231
7.4.4.3 Impact on Re-work, Safety, and General Process Improvement
87.5% of the respondents indicated to have observed a substantial increase in the
construction process improvement on the project. Also, 75% of the respondents
agreed that the level of re-work had reduced significantly on the project. This was
further confirmed in the interview where a subcontractor stated that:
“We become more efficient and we can drive the programme which we may
not do normally. Since issues get resolved early, you do not have to go back
and do rework” [CSP02SC01, Subcontractor’s Project Manager].
The above statement could also indicate that the process has enabled the team to be
more efficient. However, in terms of safety record improvement, the survey results
revealed that 62.5% claimed not to be sure, while only 37.5% indicated that the
practice had improved the safety record on the project. Some of the respondents
interviewed stated that the LPS/CP process supports better safety decisions, for
instance, one of the respondents stated that:
“One thing with CP is that people are entitled to their opinion about safety. A
subcontractor could say, hang on a minute, the safety barrier has been
removed we will not work in such area. You remember the guy said during
the meeting we can’t do it, the safety guard has been removed”
[CSP02SM01, Programme Manager]
This shows that the LPS/CP process could have supported safety decisions on the
project. However, with many claiming not be sure, could mean it was not clearly
measured and understood by some of the respondents.
7.5 Case Study Project Three (CSP03): Educational New Build
a. Description of Case Study Project Three
The case study project three (CSP03) is located in the West Midland, England. It is a
new educational building project. The educational building comprised of three floors
and occupied a total floor area of 9290.30m2. The new build was to provide facilities
such as teaching spaces, school hall, office space for staff, and laboratories among
others. The main contractor on the project is one of the top UK building construction
contractors with over 30 years’ experience in the UK building construction industry.
Case Study Anaysis and Discussion Chapter Seven
232
In the past, the contractor had been involved in various construction process
improvements championed by the UK Government, such as the Construction Lean
Improvement Programme (CLIP) conducted by the Building Research Establishment
and the Department of Trade and Industry (BRE, 2006). Also, the main contractor
had been in a framework agreement with all its supply chain for over five years. The
mode of procurement used is design and build (D&B). Table 7.5 gives further
attributes of CSP03. LPS/CP principles were used in managing the production
processes. Although, the client on CSP03 is a public client, the use of LPS/CP on the
project was motivated by the main contractor. It is worth noting that the application
of LPS/CP is part of the process used by the main contractor in delivering services to
its numerous clients over the years.
Table 7.5: CSP01 Project Attributes
Project Attributes Observed attributes on CSP03
Nature of project Building construction project
Location of project West Midland, England
Nature of works Educational new build
Type of client Public client
Mode of contractor selection Framework agreement and ECI
Proposed project duration 30 months
Project status at end of case
study
85% completion
Procurement arrangement D&B
Contract sum £20 million
Current number of
subcontractors on site
16
Point of application of LPS/CP Construction
Facilitation process Internally facilitated
b. Demographic Information of Respondents on CSP03
Table 7.6 indicates that the respondents interviewed cut across all the key people
managing production on the project. However, over 50% of the interviewees were
drawn from the subcontractors. This is because the project had more subcontractors
and they were equally willing to participate in the study.
Case Study Anaysis and Discussion Chapter Seven
233
Table 7.6: Demographic information of respondents interviewed on CSP03
S/NO Respondent
code
Role
categorisation on
the project
Specific role in the
organisation
Years of
exp. in
LPS/CP
Years
of exp.
in
const.
1 CSP03SM01 Senior manager Senior planner 10 30
2 CSP03MM01 Middle manager Build manager 3 37
3 CSP03SM02 Middle manager Build manager 1 34
4 CSP03SC01 Subcontractor Senior site manager 6 14
5 CSP03SC02 Subcontractor Senior project engineer 10 26
6 CSP03SC03 Subcontractor Contract manager 8 10
7 CSP03SC04 Subcontractor Project manager 5 10
All the respondents have vast experience in the UK construction industry. They also
claim to have valuable experience in the application of LPS/CP principles in
construction.
7.5.1 Last Planner /Collaborative Planning Practice Observed on CSP03
The LPS/CP practices on CSP03 are discussed under the following emerging themes:
(1) Application of principles (2) pre-construction practice (3) Nature of production
planning meetings and (4) PPC and RNC practice.
7.5.1.1 Application of Last Planner and Collaborative Planning on CSP03
The formal application of LPS/CP on CSP03 started at the construction stage, as it
was part of the main contractor’s approach for delivering its business. All the
subcontractors were aware of this. However, some of the subcontractors and
specialist contractors were involved in the design stage. There was a dedicated room
and collaborative programming board for LPS/CP meetings. Sticky-notes of different
colours were used for activity scheduling on the collaborative programming board.
However, it was said that on a different project handled by the same main contractor,
the process was done electronically. The senior planner stated that:
“On this project as you have seen, we use post-it notes on the wall, although
it seems to be old fashioned. On other projects we do it electronically with
projector. It depends on the nature of the project, each format you use
produce the same result” [CSP03SM01, Senior Planner].
Case Study Anaysis and Discussion Chapter Seven
234
The use of electronic board for phase scheduling/collaborative programming further
shows a progression in the current practice. Both approaches could produce some
similar results, if managed properly. However, this cannot replace the face to face
conversation that occurs during the production planning sessions.
The LPS/CP was internally facilitated by the senior planner on the project. It was
observed that most of the subcontractors were usually present at the production
planning meeting. The document analysis revealed that other forms of visual
management such as project safety performance status, project monthly performance
etc., were used to indicate project status, KPIs, and set targets on mobile board on
site.
7.5.1.2 Activity Scheduling as Observed on CSP03
It was observed on CSP03 that the working drawing was used in scheduling of
activities during production planning meetings. The working drawings were labelled
with different colours to show each work section or zone .This could suggest that
LPS/CP was implemented with other production planning principles such as Line of
Balance and working zoning. However, as observed, this was not a formal process. It
was only an approach used on the project to assist the team in the collaborative
programming/phase scheduling process.
This could be due to the large number of activities involved on the project and
prototype nature of floors and rooms. Also, ‘Prototyping’ or ‘First Run Studies’ was
done for various activities scheduled on the project. The process enabled the team to
identify constraints and drive out waste before the actual construction. The
interphase between activities seems to be short (in hours and days) in some cases
compared to the operation on highway and infrastructure project. The interphase
between some activities on the project was in hours and days.
7.5.1.3 Nature of Production Planning and Control Meetings on CSP03
On CSP03, there were various meetings designed to support the production planning
and control process on the project. These include; collaborative programming
meeting, and weekly planning meetings. The 6 week look-ahead planning was done
during the collaborative programming meeting. The researcher was in attendance on
some of the collaborative programming meetings as an observer. Constraints to
Case Study Anaysis and Discussion Chapter Seven
235
planned activities were also identified, and then developed into an action lists which
was sent out electronically.
Although constraints were identified, they were not published openly in the
collaborative programming room. Such practice could reduce the level of
transparency in communication. The weekly work planning was held each week and
the process was championed by the site managers alongside the subcontractors. One
of the respondents stated that:
“The weekly planning meeting focuses on everyday activity that will occur
next week and review of last week’s work planned. In addition to this, is the
work that would be done in that week, we have daily huddle every morning,
looking at the weekly plan seeing what needs to be doing in the week”
[Subcontractor’s, Senior Project Engineer].
PPC was claimed to be recorded on CSP03 and it was called ‘percentage activity
complete’ the RNC was also tracked. However, for confidentiality, this data is not
published here as done on CSP01 and CSP02. The data were not made available to
the researcher, thus it is not presented in this report. This was due to the company
policy.
7.5.2 Procurement and LPS/CP on CSP03
Two broad themes emerge from LPS/CP practice in relation to the procurement
approach used on CSP03. They are: the procurement practice and the impact of the
procurement practice on LPS/CP.
7.5.2.1 Pre-construction Practice
On CSP03, the major subcontractors and specialist subcontractors were involved
right from the design stage. They were also involved in developing the construction
programme which was called the ‘delivery programme’. This process was largely
supported by the D&B and ECI procurement approach was adopted.
One of the respondents stated that:
“Delivery programme is a more detailed programme. In the delivery
programme, the main subcontractors were involved in developing it. For
example, the M&E produced a detailed programme for their insulation work,
Case Study Anaysis and Discussion Chapter Seven
236
and it was subsequently integrated into the construction programme”
[CSP03SM01, Senior Planner].
Also, the subcontractors were into a framework agreement with the main contractor.
7.5.2.2 Impact of Procurement Practice on LPS/CP Implementation on CSP03
In terms of the influence of the procurement practice on the implementation of
LPS/CP on CSP03, there seemed to be divergent views. While some of respondents
believed that the procurement process supported the implementation of LPS/CP on
the project, other respondents argued that the LPS/CP could have been still been
applied successfully irrespective of the procurement route taken. Here are some of
their responses:
“I am not sure if things could have worked differently if another procurement
route is used. To me, irrespective of how the job is procured we can still
involve the people in the LPS/CP process and still have the same outcome.
However if the subcontractors are involved at the tender stage the
construction programme will be better” [CSP03SM0, Senior Planner]
“The procurement route helps in the implementation. On this project, we are
using standard JCT and D&B contract which actively support collaboration
between the subcontractors. It is opposed to NEC contract which is more
programme focused and rigid, but with this contract we rather pull together”
[Subcontractor’s, Project Manager].
The above statements indicate that the success of the LPS/CP implementation cannot
be attributed to the procurement route alone, however it creates the platform for the
process to function.
a. Transfer of Lessons Learned and Long Term Working Relationship
The study reveals that the framework agreement used on the project supports the
transfer of lessons learned from project to project among the subcontractors. Some of
the respondents stated that:
“We are in a framework agreement, we have been working with the M&E,
the building envelop subcontractor. We have worked together on four
different projects which is a benefit to us all on this project. We passed on the
Case Study Anaysis and Discussion Chapter Seven
237
lesson learned from the previous projects to this which makes us more
successful” [Subcontractor’s, Contract Manager].
It was further explained that, “each subcontractor on this project have worked
together previously, thus, we understand each other’s capability and we know we are
all working to achieve the same goal”. Again, this shows that the procurement
approach supports the development of good working relationship among the team.
7.5.3 Support required for Last Planner/Collaborative Planning
Figure 7.11 reveals the emerging themes and sub-themes from the interviews data on
the process/support required for successful implementation of LP/CP principles from
CSP03.
7.5.3.1 Support required at the Organisational Level
The support required from the organisation for successful implementation of LPS/CP
as identified on CSP03 includes: (1) Inclusion of the commercial team in the LPS/CP
process (2) Mandating of LPS/CP in the contract and (3) Use of collaborative form
of contract and supply chain working together on a regular basis
a. Inclusion of the Commercial Team in the LPS/CP Process
Some of the interviewees on CSP03 believed that the inclusion of the commercial
team such as the quantity surveyor, commercial managers, cost controllers, and cost
engineers among others in the LPS/CP process would further support the system in
the organisation. One of the respondents stated that:
“I think the built environment team and the planning team are involved in
this process, the commercial side of the business tend to be in the loop in
term of delays or acceleration in the programme. The commercial side of the
business should be kept in the loop” [Subcontractor’s, Contract Manager].
Case Study Anaysis and Discussion Chapter Seven
238
Figure 7.11: Support required for successful implementation of LPS/CP Observed on CSP03
Case Study Anaysis and Discussion Chapter Seven
239
b. Mandating LPS/CP in the Contract and Use of Collaborative form of Contract
Mandating the process and use of collaborative forms of contract were also identified
on CSP03 as part of the support the organisation could provide for smooth
implementation of the process. For instance, one of the respondents observed that
because the LPS/CP was part of the contract, it motivated everyone on the project to
get committed to the process [CSP03SM01, Senior Planner]. Also, a subcontractor
stated that:
“It is part of the main contractor’s policy, so if we do not want to do it, we
can’t go away with it. My signing into it in the contract supports my
commitment to it and it benefits us as subcontractors” [Subcontractor’s,
Senior Site Manager].
Provision of training and formalisation of the process both at organisational and
project levels were also suggested by the respondents. One of the subcontractor
interviewed stated that: “we also provide internal training to our team on this”
[Subcontractor’s, Contract Manager].
7.5.3.2 Process and Support required at the Project Level on CSP03
From the analysis of the interviews conducted on CSP03, five key processes and
supports were identified. These are; (1) Honesty and truth in promising (2) Pre-
planning before CP session by the team (3) Engagement and collaborative plan of
work at site level (4) Whole process facilitation and (5) Internal and external training
on LPS. Considering that majority of the factors identified here are similar to those
on CSP01 and CSP02, only the new ones identified will be discussed.
a. Honesty and Truth in making promise at the project level.
Some of the respondents interviewed stated that honesty in making promises and
giving out of information especially at the production planning meetings is essential.
Some of the respondents stated that:
“Some subcontractors agree dates knowing they cannot achieve it!!!”
[Subcontractor’s, Senior Site Manager].
“The process is fine, one of the barriers is people committing to things they
cannot do and also unrealistic expectation from the main contractor”
[Subcontractor’s, Contract Manager].
Case Study Anaysis and Discussion Chapter Seven
240
The statements above further highlights why the stakeholders at the project level
should not be pressurised into making promises or commitments, as such promises
could turn out to be unrealistic sometimes. In making promises in the LPS approach
of managing construction project, workers are not pressured into making promises,
rather, they are empowered to make promises on what they can do. This approach
supports reliable promising. According to Macomber and Howell, (2001); Macomber
and Howell, (2003) in the LPS workflow reliability is achieved via reliable
promising.
b. Pre-planning before CP Session by the Team and Facilitation
On CSP03 the need for the team to make a realistic plan before coming to the session
and the appointment of a facilitator to manage the process was identified. One of the
subcontractors stated that: “The way the process is facilitated supports our buy-in,
we can’t do this without the support of the main contractor and their planning staff”
[Subcontractor’s, Contract Manager].
7.5.3.3 External Support required for LPS/CP implementation
The external support observed on CSP03 include: (1) Refresher training on the
process (2) Standardisation of Process. Both main contractors and subcontractors
interviewed on CSP03 identified the need for standardisation of the process across
projects.
Refresher training
The need for refresher courses was identified. Here is a transcript:
“We use to have some form of external support when we started years ago,
the idea is to educate myself and the project managers. We are having a
refresher course next month on LPS/CP across the business to standardise
how we do it, some people tend to do it differently, we need a standard
approach to do it with our subcontractors” [CSP03SM01, Senior Planner].
The refresher trainings provide an opportunity for those facilitating the LPS/CP
process to update their knowledge based on current practice. This could be done
internally in an organisation to standardise the process across projects and to also
ensure everyone is operating on the same page.
Case Study Anaysis and Discussion Chapter Seven
241
7.5.4 Impact of LPS/CP Practice on Construction Process Improvement
Figures 7.12 and 7.13 present findings on the impact of LPS/CP implementation on
CSP03. While Figure 7.12 presents the impacts of LPS/CP observed from the semi-
structured interviews, Figure 7.13 presents the result of the survey. Both results are
discussed concurrently under this section.
Figure 7.12: Impacts of LPS/CP on CPI observed CSP03 (interview results)
7. 5.4.1 Impact on Time and Programme
Figure 7.13 reveals that 50% of the respondents agreed that the LPS/CP
implementation on CSP03 had enabled the team to make significant time saving.
This was further confirmed in the interview as one of the respondents stated that:
“Overall, the process has worked well on this project, it helps us to recover
lost months. On this project, we were 8 months late before the commencement
of work on site, now we are only 4 weeks late which we hope to recover
before the end of the project” [CSP03SM01, Senior Planner].
Furthermore, 66.7% of the respondents indicated that the implementation did not
slow down the progress work on the project. In term of time committed to the
process, 50% of the respondents claimed that the process was not time consuming.
However, from the interview and observation, some of the respondents complained
that the 2.5 hours collaborative programming meeting should be reduced.
Nevertheless, 83.3% strongly agreed there are benefits in implementing the
principles on the project. It is no surprise that all the respondents would like to work
in this manner. This evidence demonstrates that the LPS/CP implementation has
positive impact on construction process improvement.
Case Study Anaysis and Discussion Chapter Seven
242
Figure 7.13: Last Planner/Collaborative planning impacts on construction process
improvement on CSP03
0 50 100
Good understanding of the purpose of LPS/CP onthis project
Working practice has changed for better on thisproject as a result of my involvement in LPS/CP…
My understanding of the project has greatlyimproved as a result of my involvement in the…
The application of PPM has improved the level ofcommunication among the project stakeholders
The LPS/CP process has improved my trust andconfidence in other members of the project team
The LPS/CP process has enabled us to reduce thelevel of re-work on this project significantly
The LPS/CP process has enabled us to be moreefficient in our construction processes
We have observed significant increase inconstruction process
We have gain more time as a result of using PPMprinciples on this project
The LPS/CP process has reduced the adversarialrelationship on this project
Our safety record has improved on this project as aresult of the LPS/CP process
The LPS/CP process has slowed our progress on thisproject
LPS/CPprocess slowed down our progress initially,but speed it up after a while
It is time consuming
I am yet to see the value in the LPS/CP process
I like working in this mannerF1
6F1
5F1
4F1
3F1
2F1
1F1
0F9
F8F7
F6F5
F4F3
F2F1
Respondents' level of agreement on the level of PPM impacts in percentages
Impro
vem
ent fa
cto
rs m
easure
d o
n t
he p
roje
ct
Impact of Production plannning and management on construction process improvement obsereved on case project 3
Strongly agree Agree Not sure Disagree Strongly disagree
Case Study Anaysis and Discussion Chapter Seven
243
7.5.4.2 Collaborative Working Practice, Communication, and Process
Transparency
Figure 7.13 reveals that 83.3% of the respondents believed that their understanding
of the project had greatly improved as a result of their involvement in the LPS/CP
processes. However, 66.7% of the respondents claimed not to be sure if their
working practices had changed for better as result of their involvement in the
process. Furthermore, all the respondents indicated that the application of the
LPS/CP principles on the project had improved the level of communication on the
project. This was also confirmed in the interview as one of the respondents stated
that:
“The more time you spend with each other in planning, the better. It has
improved the relationship between us” [Subcontractor’s, Contract
Manager].
From the study, 50% of the respondents on CSP03 indicated that the implementation
of LPS/CP principles had improved their trust and confidence in stakeholders on the
project.
7.5.4.3 Impact on Re-work, Safety, Non-value Adding Activities, and General
Process Improvement
Figure 7.13 reveals that majority of the respondents (66.7%) believed that the
application of LPS/CP principles had reduced the level of re-work significantly on
the project. This finding is further supported by the interview response. For example,
the room activity programming that involves some form of prototyping or First Run
Studies helps to reduce re-work and drives out non-value adding activities from the
process. One of the respondents stated that:
“It helps us to check quality at each stage through the room fitting monitoring
schedule developed collaboratively” [CSP03MM01, Build Manager].
Furthermore, the study indicated that majority of the respondents (66.7%) agreed that
the implementation of LPS/CP had made the team more efficient on the project,
although 16.7% strongly disagreed.
In terms of its impact on safety, 66.7% of the respondents claimed not to be sure if
their safety record had actually improved, while 33.3% agreed that the safety record
Case Study Anaysis and Discussion Chapter Seven
244
had improved. However, from the interviews conducted, some of the respondents
explained that since LPS/CP supports proper work sequencing and organisation, it
makes the site tidy and supports safe working on the project. Again, with majority
claiming not to be sure, it could mean the relationship between LPS/CP and safety
had not been clearly understood by some of the respondents.
7.6 Cross Case Study Analysis and Discussion
The individual case studies and findings have been presented and partly discussed in
sections 7.3, to 7.5. The focus of this section is to compare the findings across the
cases and to discuss the implication of the findings in developing a strategy for the
rapid and successful implementation of the LPS. The comparison focuses on the case
study context, the LPS/CP practice observed, procurement practice, support required
for implementation and the impact of the current practice on CPI. To simplify this
section, the interview transcripts are not presented here as they have already been
presented in the individual cases. The discussion focuses more on points that cut
across the three case studies.
7.6.1 Case Study Context and Description of Case Study Projects
The aim of the cross case-study context comparison is to ensure the findings are
properly interpreted in line with the context from which the data were obtained.
Table 7.7 presents cross case comparison of the projects’ attributes. The table shows
that the case studies on which LPS/CP application was investigated cut across the
major sectors of the UK construction industry. This suggests that the outcome of the
study could offer wider lessons for the UK construction industry.
Table 7.7: Cross -case Comparison of Project Attributes
Project Attributes CSP01 CSP02 CSP03
Nature of project Highway and
Infrastructure
Highways and
Infrastructure
Building construction
project
Location of project North of Yorkshire,
England
West of Yorkshire,
England
West Midland, England
Nature of works Upgrade to replace
existing dual carriage way
with three new lanes
Improvement of
motorway to Smart
motorway
Educational new build
Case Study Anaysis and Discussion Chapter Seven
245
Type of client Public client Public client Public client
Mode of
contractor
selection
Framework agreement and
ECI
Framework agreement Framework agreement
and ECI
Proposed project
duration
30 months 24 months 30 months
Stage of project at
end of the case
study
57% completion 80% completion 85% completion
Procurement
arrangement
D&B, joint venture Traditional design bid
and build, joint venture
D&B
Contract sum £380 million £120 million £20 million
Current number
of subcontractors
on site
10 9 16
Point of
application of LPS
principles
Construction Construction Construction
LPS facilitation
process
Internally facilitated Internally facilitated Internally facilitated
7.6.2 Demographic Information of Research Participants
In all, 28 semi-structured interviews were conducted across the three case studies as
shown on Figure 7.14. The research participants interviewed comprise of 9 SM, 6
MM, 6 OM, and 7 SC. This shows all the key stakeholders were involved in the
interviews, although the number interviewed varied across the projects. While
CSP01 recorded the highest in the number of SM interviewed, the highest number of
subcontractors interviewed was on CSP03. The variation in the number of
respondents interviewed would further complement each other in the cross case
analysis. It is worth stating that the reason for the variation has been offered in the
individual case section. The high number of SC interviewed on CSP03 could be due
to the high number SC on the project. Furthermore, the respondents’ years of
experience in the application of LPS/CP and in the UK construction sector is evenly
distributed across the three cases, hence responses should be credible.
Case Study Anaysis and Discussion Chapter Seven
246
Figure 7.14: Cross Case-comparison of research participants
7.6.3 Cross-case Comparison of Last Planner/ Collaborative Planning
Practice
Table 7.8 presents the Last Planner/Collaborative Planning practice as observed
across the three case studies.
Table 7. 8: Cross-case Analysis of Last Planner System/Collaborative Planning
LPS Practice Observed CSP01 CSP02 CSP03
Collaborative
programming/phase
planning
Implemented Implemented Implemented
6 Week look-ahead
planning
Implemented Implemented, but
later reduced to 2
weeks at the tail
end of the project
Implemented
Weekly Work Planning Implemented, 13
daily
huddle meeting was
introduced later.
Implemented Implemented,
with daily
huddle meeting
Constraint analysis and
removal
(Make-ready process)
Implemented, but
lacked the rigour to
remove constraints
Implemented, with
partial strategy to
remove constraints
Implemented,
with partial
strategy to
remove
constraints
13
Daily huddle meeting was called daily stand up meeting on CSP01, and this was later introduced
following some observation the researcher made to the facilitator in the course of the study.
0
1
2
3
4
5
6
CSP01 CSP02 CSP03
Nu
mb
er
of
resp
on
den
ts i
nte
rvie
wed
Categories of respondents interviewed
Senior manager Middle managers Operational manager Subcontractors
Case Study Anaysis and Discussion Chapter Seven
247
Developing workable
backlog
Not implemented Not implemented Not
implemented
Prototyping/First Run
Studies
Not implemented Not implemented Implemented
Average PPC 72.29% 90% 14
90%
Recording of RNC Recorded, with no
much action on it
Recorded with
some action
Recorded with
some action
Learning It occurred partially Some level of
learning occurred
Some level of
learning
occurred
Last Planner metrics measured
PPC Implemented Implemented Implemented
Task Make Ready Not implemented Not implemented Not
implemented
Task Anticipated Not implemented Not implemented Not
implemented
Frequency of plan failure Not implemented Not implemented Not
implemented
Table 7.8 shows that the LPS practice implemented across the three case studies
include, phase planning, WWP, measurement of PPC and RNC. This finding is
similar to those identified from the exploratory interviews and the structured
observation presented in Chapter Six. The findings were further triangulated to
confirm the earlier results from stage three of this study. The study shows that daily
huddle meeting was held on CSP03 and later on CSP01, but was not done on CSP02.
Although daily huddle meeting was not part of the initial element of LPS (Daniel et
al., 2015, Ballard et al., 2009 ), its use in monitoring how the production system is
performing on the day of production on site is on the increase (LCI, 2015; Daniel et
al., 2015; Salem et al., 2006). This could be due to its potential in checking the
production system on the day of production and to also re-plan in case of any
deviation. For instance, it was not done on CSP01 initially, but it was later
introduced.
Constraint analysis was observed on all the three case study projects, however only
CSP03 developed partial strategy to remove the identified constraints. On CSP03,
14
For confidential purpose the researcher is not allowed to published the PPC and RNC result on
CSP03
Case Study Anaysis and Discussion Chapter Seven
248
constraints and action log were collaboratively developed by the team with actions
assigned. However, the action log was only circulated via email to the distribution
list at the end of the look-ahead planning meeting. It was also not published visually
in the collaborative programming as expected. Publishing it visually not only
improves process transparency but also keeps all the stakeholders on the project
conscious of the actions required of them. On CSP01, constraints were only partially
logged with no personnel given the clear action to address the identified constraints.
Also, on CSP02, constraints were logged but not all the responsible persons for
actions were usually available at the look-ahead planning session, especially the
designers. Hence, another separate meeting had to be arranged with the team.
This show there is lack of discipline in the constraint removal process on the case
study projects. Previous studies have also shown that there is lack of rigour in the
implementation of more complex elements of the LPS such as the make-ready
process (Daniel et al., 2015; Dave et al., 2015; Lindhard and Wandahl, 2014; Ballard
et al., 2009; Alarcon and Caldron, 2005). Furthermore, Table 7.8 reveals that CSP01
has the least PPC average of 72.29 %. Though this may seem good, however, going
by the meaning and goal of PPC in showing workflow reliability (Ballard, 2000), this
may not be true on CSP01. This is because it was observed from the interview that
sometimes there were cases of over and under estimation of the amount work to be
done by those doing the work. For example, Figure 7.1 shows PPC of 0% and 100%
in some weeks on CSP01 which further attests to this fact. In some cases, PPC could
be 100% with work still behind schedule when tasks are not properly made ready
(Hamzeh, et al., 2012).
Also, RNC were recorded on all the three case studies. The main causes of RNC on
CSP01 were previous work not done and under estimation, while on CSP02 it was
design changes and change of priority (see Figure 7.2 and 7.7). On CSP01, the lack
of rigour in the make-ready or constraint removal process could have contributed to
the frequent occurrence of previous work not been completed on the project and also
the lack of honesty in making promises. Dishonesty and insincerity in promising was
seen as barrier to LPS/CP implementation on the three case study projects.
The study reveals that among the many LPS metrics, only PPC was measured on the
projects. Metrics such as Task Made Ready (TMR), Task Anticipated (TA), and
frequency of plan failure were not measured on any of the projects (Ballard, 2015;
Case Study Anaysis and Discussion Chapter Seven
249
Ballard et al., 2009). This could be due to the ignorance of the existence metrics and
the level of maturity of the use of LPS. According to Hamzeh et al., 2015; Ballard et
al., 2009, the above mentioned LPS metrics are less practiced even on projects that
claim to use LPS, this implies the situation is not peculiar to the UK construction
industry alone.
The study reveals that some form of learning occurs on all the projects, however, the
amount of rigour required to actively translate the learning is inadequate. For
instance, on CSP01, though RNC was recorded, one of the respondents stated that
not much was done with it. Also, developing workable backlog was not done on any
of the case study projects.
7.6.4 Cross-case Comparison and Discussion on Procurement and
LPS/CP Practice
Table 7.9 presents the cross-case comparison from the three case study projects on
procurement and LPS/CP implementation. This is discussed under two themes;
procurement practice and procurement impact on LPS/CP implementation. Table 7.9
shows the summary of procurement practices and their impact on LPS/CP
implementation on the three case studies. As shown in the table, it is clear that the
procurement practice had influence on the implementation of the LPS/CP on the
three case study projects. However, it is not the major determining success factor for
the LPS/CP implementation. For instance, one respondent on CSP03 argued that, the
success achieved in the LPS/CP implementation on the project will still be possible
even if other forms of procurements was used. This shows procurement is not
actually the gateway to LPS/CP implementation, rather, it is helpful in creating a
collaborative working environment.
In some previous studies, it was perceived that the LPS could only work more
effectively on D&B and on other collaborative contracts (Fuemana et al., 2013). For
example, Fuemana et al., (2013.) in a New Zealand study that was based on
perception of the respondents, opined that the full potentials of LPS implementation
can be mostly realised on D&B and negotiated contract. However the study reported
in this thesis provides empirical evidences that rebut such perceived narrow view, as
the study reveals that the LPS/CP worked well on projects where DBB and D&B
were adopted.
Case Study Anaysis and Discussion Chapter Seven
250
However, the role of using some form of collaborative approach in procuring
projects alongside the use of LPS cannot be overlooked as all the three case study
projects used some form of this. . For instance, on CSP02 where DBB was used, the
subcontractors had been in a framework agreement for over five years. This
supported the development of common understanding among the team and also the
implementation of LPS/CP on the project. This suggests that the procurement
approach to be used on a project should not be too rigid, but flexible to incorporate
other collaborative practices.
Table 7.9: Cross-case Comparison of Procurement Practice
Procurement
and LPS/CP
CSP01 CSP02 CSP03
Practice
Procurement
practice
Joint venture,
framework agreement,
ECI
Joint venture,
framework
agreement
Framework agreement,
ECI,
Mode of contract D & B DBB D&B
Impact
Constructability
issues
Regular
Buildability/constructabi
lity
Frequent occurrence
of constructability
issues
Extensive constructability
review at design stage
Design and scope
changes
Less design changes
observed, but design was
lagging 15
behind
Frequent design and
scope changes
Less design changes
observed
Response to design
issues
Just-in-time approach
was used initially
Long lead time in
receiving 16
response
from design team
On-time response, but less
design issues
Level of
collaboration
between
construction and
design team in
LPS/CP meetings
Strong, the joint venture
managed the design
team
Weak, the joint
venture had no
power over the
design team.
Strong, the main
contractor managed the
design team
Other
impacts/strategy
Early involvement of the
key 17
stakeholders who
were not part of the
production team
The expected
response time from
the design team was
factored into the
look-ahead planning
process
Transfer of lessons learned
by the team as a result of
the framework
15
Design was only at 50% completion before the commencement of construction work on CSP01. 16
The design team on CSP02 do not attend the production planning meetings and it takes 9 days to
receive feedback on design issues. 17
Project governance bodies, such as the planning authority, local community, legal team etc were
involved at the pre-construction stage.
Case Study Anaysis and Discussion Chapter Seven
251
Also, the use of LPS/CP on CSP02 alleviated other issues that could have occurred
on the project considering the traditional mind-set the design team were adopting on
the project. However, with the strategy of factoring in the design team’s response
time into the look-ahead and constraints removal process, the effects of their actions
were minimised on the project. This is one of the key benefits of the LPS; it reveals
bad news early which guides the team to plan better (Ballard, 2000; Mossman,
2014). Specifically, many months’ worth of extra work as a result design and client
changes, were completed within two months through the implementation of LPS/CP
on CSP02 that used DBB.
7.6.5 Cross-case Comparison and Discussion on the nature of Support
Required for LPS/CP Implementation.
Table 7.10 shows the nature of support required for the rapid and successful
implementation of LPS/CP as gathered from the three case studies.
Table 7.10: Summary of the nature support required for LPS/CP implementation from the
Case Studies
Category of
support required
CSP01 CSP02 CSP03
Support/process
at organisational
level
Provision of training.
Inclusion of it in the
contract.
Continuous mgt.
support.
Training support
Mandating in contract
Awareness
Use of collaborative
form of contract
Involvement of the
commercial team in the
process
Mandating it in
contract
Use of collaborative
form of contract
Support/process
at project level Appointment of a
facilitator.
Involvement of all
required team.
Digitalisation of Post-
It Note.
Provision of LPS/CP
room on site.
Active involvement
of construction
manager.
Pre-plan before
session
Pre-plan before
session
Discipline and
transparency
Facilitation and
appointment of
champions
Involve all the
required stakeholders
Honesty and truth in
promising
Pre-plan before
session
Facilitation
Training
Engagement with all
required at the site
level
External
support/process Development of
standard metrics for
LPS/CP
implementation
Industry and
Educational
institution support
Process
standardisation
Education and
training support
Standardisation of
the process
Case Study Anaysis and Discussion Chapter Seven
252
academic partnership
As shown in Table 7.10, the support required is all encompassing; that is, at the
organisational level, project level and also external support. The study reveals that
the nature of support identified on each of the project studied are similar, even with
different type of project and management structure. This shows that the requirement
for the successful and rapid implementation of LPS on building projects would not
be different from that of highways infrastructure, ship building, and rail projects
among others. This supports the assertion that the LPS is applicable to any
production system that requires the management of material and human resource
(Mossman, 2014).
7.6.5.1 Support Required for LPS/CP Successful Implementation at the
Organisation Level
At the organisational level, various supports were identified on the three case studies.
The reoccurrence of some of these factors on all three case studies shows their
importance in the successful implementation of the LPS/CP in construction projects.
For instance, the inclusion of LPS/CP in the contract was mentioned on all the case
studies. Doing this is essential as it makes it a formal process on the project, thus
encouraging more commitment to the process. Also, it would ensure that all the
required stakeholders get engaged in the process as expected. This is important, as it
was observed in a previous study, that subcontractors were not involved in
production planning meeting on a project managed with the LPS/CP (Pasquire et al.,
2015).
Furthermore construction is filled with many formal processes (Kadefors, 2004),
which sometime may not even support the goal of the project. However, the goal of
LPS is to engender collaboration among the project team, while also focusing the
team to achieve the common goal of the project (Ballard and Howell, 2004).
According to Kadefors (2004), formalisation of construction process should not be in
relation to cost alone, but should include other practices that would support the
actualisation of the project objectives. The LPS should be considered to be among
such formal practices or processes too. As demonstrated on CSP02, LPS/CP could
still be included in the contract even when a contract approach such as DBB is used.
Case Study Anaysis and Discussion Chapter Seven
253
Furthermore, the inclusion of the commercial arm of the business in the LPS
implementation loop was considered to be essential to the organisation in LPS/CP
implementation. The place of involving the commercial team in the process cannot
be overemphasised, since every change in the programme from the LPS/CP meetings
as a result of reliable promising has its own commercial imperative to the project.
Hence, their involvement in the production planning meeting as and when required
could reduce the time required in making decisions that relate to commercial matters
(cost, contractual implication etc.) during the make-ready and look-ahead planning
sessions. However, this must be done with caution, as it has been observed that when
the production shifts too much attention, the production system could fail (Conte,
1998).
7.6.5.2 Support required for LPS/CP Successful Implementation at the Project
Level
Comparing the number of support identified for each category, the support required
at the project level is the highest numerically. This is no surprise as the LPS itself is a
project production management method designed for construction (Daniel et al.,
2015; Ballard, 2000). This shows that much attention is required at the project level
for the system to function effectively especially at the implementation stage.
However, this cannot happen without both organisational and external supports.
At the project level, the need for a facilitator and the appointment of champions to
drive the process was identified on the three case studies. This is crucial as the
process would not progress if there are no capable and experienced personnel to
manage the process. On all the case study projects, the process was internally
facilitated. However, on CSP01, it was argued that after the initial facilitation, the
process should be left with the team. As good as this may seem, it could lead to the
abandonment of the entire process as each member of the team has a specific role to
perform on the project. Leaving the process to the team to do it, means no one would
be held accountable. However, on all the three projects, LPS/CP facilitation was the
primary responsibility of the facilitators which yielded better results. Furthermore,
the need for discipline, transparency, and truthfulness especially in conversation and
making promises by the stakeholders in production planning sessions were
considered as essential at the project level on all the three case studies. This
underscores the importance of realistic expectations and promises. Macomber and
Case Study Anaysis and Discussion Chapter Seven
254
Howell, (2001) identified five elements in making a reliable promise among project
stakeholders. These are: (1) understanding the condition for satisfaction (2)
competency to perform the task (3) capacity to perform the task (4) sincerity and (5)
commitment to clean the mess, if failing. This clearly suggests that in making
promises during production planning sessions, the team must be transparent and
sincere that the capacity required to deliver the task is available before making the
promise. It is through reliable promising in the LPS that trust and confidence
increases/develops among the project stakeholders (Macomber and Howell, 2001).
7.6.5.3 External Support Required for LPS/CP Successful Implementation
As shown in Table 7.10, the need to standardise the approach or process was
identified on all the case studies. Again, this shows that there are variations in the
current implementation of LPS principles on the projects investigated in the UK.
Daniel et al., (2016); Dave et al., (2015); Koch, et al., (2015) also observed
variations in the implementation of LPS principles on construction projects in the
UK. It is worth noting that the partial implementation of LPS is not only in UK
construction, a Norwegian study (Kalsaas et al,. 2014); a Vietnamese study (Khanh
and Kim, 2015) and a Danish study (Lindhard and Wandahl, 2014) all reported that
not all the components of the LPS were implemented as expected.
These shows that external support is needed as it will be too simplistic to conclude
that the LPS does not need improvement. Studies have shown that the LPS is
dynamic and it is now being incorporated with BIM, Location based management,
and Takt planning among others (Daniel et al., 2015; Seppanen et al., 2010; Sacks et
al., 2009). Also, it is interesting to note that the LPS is currently being benchmarked
by Glenn Ballard with input from current practitioners, research institutes,
consultants, and the academia to improve the initial framework on which it was
developed (Ballard, 2015).
Furthermore, partnership between the construction industry and academic institutions
on research, with focus on LPS was suggested as an external support required. This
partnership is important, as academic institutions would be able to communicate
recent developments on its application and principles to the industry practitioners.
For example, in Brazil, it was reported that the active engagement between
construction companies and academic institutions on LPS principle implementation
Case Study Anaysis and Discussion Chapter Seven
255
on projects has yielded positive results and similarly in Chile (Alarcón et al., 2005;
Formoso et al., 2002). In the UK, institutions such as Nottingham Trent University,
University of Cardiff, University of Salford, Lean Construction Institute UK and
Costain Plc among others are into such research partnership with Highways England
(Highways Agency, 2014).
7.6.6 Cross-case Comparison and Discussion on the Impact of LPS/CP
Implementation on Construction Improvement.
Figures 7.4, 7.5, 7.9, 7.10, 7.12 and 7.13 present the results of the interviews and the
survey on the impact of LPS/CP implementation on construction process
improvement from the three case studies conducted. LPS/CP implementation impacts
on construction time and programme, collaborative working practice, rework and
quality and safety are compared across the three case studies below.
7.6.6.1 Impact on Time and Programme.
The study reveals that on CSP01, all the respondents indicated that more time had
been gained as a result of the use of LPS/CP, while on CSP02 and CSP03 50%
indicated to have gained more time. This was further confirmed from the interviews
as various time gained were identified on all three projects at various points. For
example, on CSP02, a subcontractor reduced 80 weeks’ programme to 50 weeks.
Also, on CSP03, 8 months delay was reduced to 4 weeks as at the completion of this
case study. The construction manager on CSP01 observed that the LPS/CP process
had a positive impact on the project as things were always done on time as a result of
the phase planning or collaborative programming.
This shows that majority of the respondents believed that the LPS/CP
implementation helps in improving the construction time and programme, since it
allowed the team to identify the right logic for activities. A realistic hand over date is
also made possible in the phase planning or collaborative programming process.
Previous case studies have also reported the impact of LPS implementation on
construction time or programme reduction (Adamu and Howell, 2012; Leal and
Alarcón, 2010; Alsehaimi, et al., 2009).
Case Study Anaysis and Discussion Chapter Seven
256
7.6.6.2 Impact on Collaborative Working Practice
All the respondents on CSP01 and 85% on CSP02 indicated that their collaborative
working practice had improved on the project as a result of the use of LPS/CP
principles. However, the nature of relationship that develops in the LPS arises from
the social conversation which supports the development of collaborative working
relationships (Priven and Sacks, 2015; Daniel et al., 2014; Mossman, 2014). This is
opposed to the traditional approach of project management that uses technical
conversation (Daniel et al., 2014; Ballard, 1997).
However, on CSP03, 66.7% of the respondents claimed not to be sure if their
working practice had improved for the better. This could mean that even with the use
of LPS/CP on the project, the mind-set change had not fully occurred in some of the
project members on CSP03. According to Liker (2004), the foundation for the
implementation of lean principles is the mind-set change.
7.6.6.3 Impact on Rework and Quality
Looking at the impact of LPS/CP on re-work, the study reveals there was a positive
substantial impact on all three case studies. For example, 85.7% of the respondents
on CSP01, 75% on CSP02 and 66.7% on CSP03 agreed to have observed a
significant reduction on the level of re-work on their project. This shows the
potentials of the LPS in helping the stakeholders to understand all the intricacies in
the construction processes, thus reducing re-work and non-value adding activities.
This was further confirmed in the interview by a subcontractor:
“We become more efficient and we can drive the programme which we may
not do normally, since issues get resolved early, you do not have to go back
and do re-work”.
Furthermore, on CSP03, the finishing schedule for the rooms was done using
LPS/CP processes such as ‘First Run Studies’ or ‘Prototyping’, collaborative
programming/phase scheduling which reduced rework and snagging. The level of
reduction in rework observed on all the case studies could be due to the collaborative
processes adopted and some level of consideration for work flow especially on
CSP03. According to Ballard (2000), work flow reliability reduces waste and
rework.
Case Study Anaysis and Discussion Chapter Seven
257
7.6.6.4 Impact on Safety
The survey results on the impact of LPS/CP implementation on safety revealed that
the respondents were not sure if the process had an impact on the safety performance
of the project. For example, on CSP01, 71.4% claimed not to be sure, on CSP02 and
CSP03, 62.5% and 66.7% respectively claimed not to be sure. This shows that
majority of the respondents were unaware of the impact of LPS/CP implementation
on safety performance on the project. The results show that safety performance
seems not to be the focus of the implementation of LPS/CP on those case studies.
7.7 Chapter Summary
This chapter presented the results from the multiple case studies which form phase 4
of this study. This includes; the analysis of the three case studies, cross-case
comparison and discussion of the findings. The chapter identified the impact of
procurement practice on LPS/CP implementation, the support/process required for
successful and rapid implementation, the impact of LPS/CP practice on CPI and the
current LPS/CP practices observed on the three case studies considered.
The chapter shows that procurement practice has an influence on the implementation
of the LPS principles. However, the chapter established that procurement is not the
gateway to effective and successful implementation of the LPS as empirically
demonstrated on the three case studies investigated. This implies that the LPS
process could still work or yield less result irrespective of the procurement route
adopted. For instance, the study shows that there is no significant difference in the
level of implementation of the core elements of the LPS in relation to the different
procurement approach used. This suggests that irrespective of the procurement route
used, a mind-set change towards collaboration is essential for it to work successfully.
However, collaborative form of procurement creates a supportive platform for the
implementation of the process compared to the traditional forms of procurement. The
chapter demonstrates that creating a collaborative working environment is crucial to
LPS/CP implementation.
Furthermore, the chapter identified and categorised the nature of support required for
the rapid and successful implementation of LPS in construction. These are;
support/process at the organisational level, support/process at the project level and
external support. Various factors were considered under this categorisation and the
Case Study Anaysis and Discussion Chapter Seven
258
chapter concludes that all the factors are the foundation that needs to be in place for
the successful implementation of the LPS/CP.
The chapter demonstrates that LPS/CP implementation has a positive impact on
construction process improvement with regard to improvement in activity scheduling
and programme reduction, collaborative working practice, better understanding of
project goal and task, better communication and relationship among project team,
significant reduction in rework, and efficient working among others. The chapter
demonstrates that LPS implementation has a positive impact on construction
programming time reliability.
In comparing the LPS/CP principles practiced on the three case studies, there seems
to be some level of improvement compared to practices observed in structured
observation in stage 3. However, the more complex elements of the LPS are still
partially implemented and in some case not implemented at all both stages. Based on
the findings in this chapter, and previous chapters an approach to support
construction stakeholders for successful implementation of LPS on construction
project is now proposed and presented in the next chapter (Chapter Eight).
259
CHAPTER 8: DEVELOPMENT AND
EVALUATION OF THE LAST PLANNER
SYSTEM PATH CLEARING APPROACH
8.1 Introduction
The previous chapter (Chapter Seven) presented the findings from the three empirical
case studies on the application of production planning and control principles. This
chapter builds on those empirical findings and those from the exploratory and
structured interviews in Chapter Six to propose an approach that supports
construction stakeholders (clients, main contractors, and subcontractors) in the
implementation of the LPS in construction. It also builds on the literature review
conducted in phase one of this study. Section 8.2 presents the rationale for
developing the proposed approach known as the “Last Planner System Path Clearing
Approach” (LPS-PCA). The theoretical and the general overview of the approach are
presented in section 8.3 and 8.4 respectively. The block and schematic diagrams of
the proposed LPS-PCA are also presented in section 8.4 while the descriptions are
provided in section 8.5. The chapter further presents the rationale for the evaluation
and results of the evaluation in section 8.6. The chapter demonstrates that the
proposed LPS-PCA has the potential to guide construction stakeholders in
developing an understanding of what needs to be in place for the successful and rapid
implementation of the LPS. The chapter summary is presented in section 8.7.
8.2 Rationale for the Last Planner System-Path Clearing Approach
The need for supporting the implementation of new techniques, and practices using
some sets of guideline, framework, roadmap, and approach among others has been
acknowledged in the literature (Nesensohn, 2014; Ogunbiyi, 2014, Sacks et al., 2009,
Ballard et al., 2007). However, studies that have attempted to propose an approach
for implementing specific lean techniques such as LPS in construction tend to focus
more on the project level (Lindhard and Wandahl, 2014; Hamzeh, 2011; Hamzeh and
Bergstrom (2010), Dombrowski et al., 2010 ); with less focus on a holistic approach
that would support construction stakeholders in the implementation process. This is
Development of the LPS-PCA Chapter Eight
260
despite the fact that, it has been suggested that the implementation of lean techniques
should expand beyond project focus and include other organisational and human
factors that could influence the process (Pevez and Alarcon, 2006). The dearth of
holistic approach to support construction stakeholders in the implementation of the
LPS informed the development of the LPS-PCA. The objectives of the proposed Last
Planner System Path Clearing Approach (LPS-PCA) are as follows:
To highlight the foundational factors or path levels that needs to be in
place for the rapid and successful implementation of the LPS in
construction.
To offer a structured and holistic view for LPS of the implementation
in construction.
To offer an insight on how to sustain the implementation of the LPS
in construction using a systemic view.
Among other things, the proposed approach would pay attention to the above
mentioned objectives.
8.3 Theoretical Overview of the Proposed Approach
The proposed approach is built on various theories that have been used to explain the
working of LPS in construction. It also reflected on the shift from an RCM approach
in urban planning to CP and similar reflections on software design and development
in the IT sector. Studies on planning in economics, collaborative working practice,
and relational contract were also considered. Some of these theories have been
explained in the literature review chapters.
These theories include: Transformation, Flow, Value theory (Koskela and Ballard,
2006); the language/action perspectives (Macomber and Howell, 2003; Flores,
1982); management-as-planning and management-as-organising (Johnston and
Brennan, 1996); the shift from RCM to CP in urban planning (Gunton et al., 2003)
and Hayek’s, (1945) comment about the way knowledge needed for planning is
dispersed among individuals. The proposed approach is also explained from a
relational contracting theory perspective (Macneil, 1980). The theory posits that
when parties to a contract have confidence or expect to work together in the future by
the provision of the contract, this would further influence the behaviour of parties on
Development of the LPS-PCA Chapter Eight
261
the project (Macneil, 1980). The main components of the proposed approach are
presented in the succeeding sections.
8.4 Background to the Last Planner System Path Clearing Approach
The Last Planner System Path Clearing Approach (LPS-PCA) development is
supported by the extensive literature review conducted in phase one of this study as
presented in Chapters Two to Five and the empirical data collected in the UK in
phases two and three as presented in Chapters Six and Seven. Through the literature
review, LPS implementation barriers, success factors, components implemented, and
trends in implementation from previous implementations across the world were
identified, and recent developments in the LPS were examined. This brings in a
universal perspective into the current approach proposed.
The empirical data on production planning and control practice in construction was
sourced from the major sectors of the UK construction industry through various
methods. These methods include: the interviews, structured observed, and multiples
case studies. Through this, data on the current LPS practice, its current drivers,
current success factors, current benefits, current barriers, the nature of the support
required for its successful implementation and its impact on construction process
improvements among others were identified. In all, a total of 58 interviews were
conducted. This supports the contextualisation of the proposed approach and also
presents the current evidence from the industry.
8.4.1 The LPS Path Clearing Approach
The LPS-PCA is to guide construction stakeholders (client, main contractors, and
subcontractors) in developing an understanding of what needs to be in place for the
successful implementation of LPS and also in sustaining the implementation. The
proposed approach consists of three major components:
• organisational level path clearing,
• project path clearing and
• external enabler
Development of the LPS-PCA Chapter Eight
262
8.4.2 What the proposed Approach is not
The proposed approach is not prescriptive; it is only a guide or roadmap to help in
developing an understanding of what needs to be in place (Path Clearing) for the
implementation of LPS in construction. This means it is not rigid and could be
adopted/adapted to various situations. Also, the proposed approach is not intended to
provide a detailed description of the methodology for LPS implementation as this is
available in various publications (Mossman, 2014; Ballard, 2000).
8.4.3 The Reason for Using LPS-PCA
It enables users (clients, main contractors, and subcontractors) to develop an
understanding on what is required for the successful implementation of LPS in both
process and behaviour wise. The proposed approach is presented diagrammatically in
Figures 8.1 (basic diagram) and 8.2 (schematic diagram).
8.4.4 Basic Diagram of LPS Path Clearing Approach
Figure 8.1 presents the basic diagram of the “LPS Path Clearing Approach” (LPS-
PCA). The basic diagram indicates how components in the proposed approach are
closely integrated. For instance, the figure shows that the organisational level feeds
into the pre-project activities, while pre-project activities contribute to
implementation on the project. The external enabling factors on the other hand
support all the operations as shown in Figure 8.1.
Pre-project
Organisational
level
External
enabler
On Project
Figure 8.1: LPS Path Clearing Approach Block Diagram
Figure 8.1 shows that each part requires some form of input from other components
for effective functioning. It is worth noting that both pre-project and project
Development of the LPS-PCA Chapter Eight
263
components fall under the project level i path clearing level as will be described later
in Figure 8.2.
8.4.5 Schematic Diagram of LPS Path Clearing Approach
Figure 8.2 presents the schematic diagram of the LPS-PCA. It consists of:
• organisational level path clearing,
• project path clearing and
• external enabler
To improve understanding of the requirements at each path clearing levels, an
industry guidance note was developed (see Appendix 11 for copy). This was done
since the LPS-PCA focuses in supporting industry practitioners such as clients, main
contractors, and subcontractors in corporate implementation of the LPS. However, in
addition to this, a general description and definition of the components in Figure 8.2
are provided in this section, and each component is discussed in relation to previous
studies. This was done to provide further insight into the theories that underpin the
proposed approach.
Development of the LPS-PCA Chapter Eight
264
The overall aim of the proposed approach is to guide construction stakeholders (client, main
contractors, and subcontractors) in understanding what needs to be in place for the successful
implementation of Last Planner System(LPS) and also in sustaining the implementation.
Organisational Level Project Level External Enabler“Path
Clearing
Levels”
Current
practice in
the
organisation
LPS
principles/
theory
Evaluate & review for
alignment
The imperative for LPS /Leadership
Identify and understand the drivers
and benefits for LPS implementation
Align OL strategic capability with
project level strategy
Create enabler for
implementation: Physical and
human factors
Continuous learning action
So
cia
l B
eh
avio
ur
Transparency and
discipline
Honesty and truthfulness
in promising
Select and involve all the
required team
Pre-plan before
production planning
meetings
Strategic capability
commitment to
support LPS
implementation
Create awareness
on the strategic
capability
commitment for
implementation at
all level
Pro
ce
ss
In
pu
t F
ac
tors
Co
nte
xtu
al
In
pu
t
Fa
cto
rsLast Planner System Path Clearing Approach
Legend
Gauge
practice
© Emmanuel Daniel 2016
Process flow
Feedback loop
Separation
line
Allo
catin
g s
trate
gic
cap
ab
ility
Adopt
standard approach
LPS
implement
Pre
-pro
ject
On
Pro
ject
Beh
avio
ur
ari
sin
g f
rom
the
co
ntr
act
Use of collaborative form of
contract
Keep commercial arm of the
business in LPS/CP loop
Inclusion of LPS/CP in contract
Collaborative working culture
Relational contracting
Industry/academia
research partnership
CPD training on LPS/CP
Link with Lean
construction events
Proven lean consultants
En
ab
lein
g fa
cto
rs
Last Planner System Path Clearing Approach
Continuous learning action loop for successful implementation
Inte
rnal fe
ed
back
lo
op
Figure 8.2: LPS Path Clearing Approach
8.4.6 Definitions of Key Components in the LPS-PCA
Path Clearing Levels: refers to the essential paths that need to be cleared for the
rapid and successful implementation of LPS.
Organisational Level: this path identifies and defines what needs to be in place at
the organisational level for LPS implementation. The organisational level factors also
support the implementation of the LPS at the project level. It consists of the two
input factors; the process input factor and the contextual input factor.
Development of the LPS-PCA Chapter Eight
265
Process Input Factors: this refers to the processes that need to be created
and practiced at the organisational and project levels to support the
implementation of LPS.
Contextual Inputs Factors: behaviours that need to be in place both at the
organisation and project levels to support the process inputs. This is part of
the culture change required to implement LPS successfully.
Project Level: defines what needs to be in place at the project level for LPS
implementation.
External Enablers: operates outside the organisational and project levels. They are
strategically positioned to support the implementation of the LPS.
8.5 Description of the Composition of the LPS-PCA
The three path clearing levels and its associated components would be described in
this section.
8.5.1 Organisational Level
Organisation plays a central role in the implementation of lean principles and
techniques. The implementation of lean techniques has failed on projects in the past,
because it was somehow disconnected from the organisation’s vision and with too
much focus on tools and methods (Pekkuri et al., 2014). The conditions required at
the organisational level (OL) for rapid and successful implementation of LPS as
shown in Figure 8.2 are categorised into: (1) organisational process input factors (2)
organisational contextual input factors. The process input factors are discussed
below.
8.5.1.1 Organisational Level Process Input Factors
This refers to the processes that need to be created and practiced at the organisation
level in the implementation of LPS. As it is called, it defines the processes that need
to be in place at the organisational level (OL) for the LPS implementation. These
include;
identifying the imperative for LPS implementation/ leadership
identifying and understanding the drivers for LPS implementation
strategic capability commitment to support LPS implementation
Development of the LPS-PCA Chapter Eight
266
creating awareness on the strategic capability created across the business
a. The Imperative for LPS Implementation and Leadership
An organisation must identify the imperatives for the implementation of the LPS in
its business. The imperative here is beyond having a goal of fulfilling an expectation
from the client. For instance, in the UK, the demand from some public sector clients
seems to be among the top imperative factors driving some supply chain companies
in the implementation of the LPS. Such imperative factor or driver cannot sustain the
implementation of the LPS, and indeed is a weak imperative factor.
Ideally, the imperative for LPS implementation should be based on the desire to
become an active agent to support collaborative behaviour among employees. This
implies that both the client and supply chain have a role in championing the LPS
implementation. Also, it shows that the LPS implementation should not be
championed by client companies alone, as perceived by some supply chain
companies. Also, this imperative should be made explicit, as it has the potential of
stimulating the top management in supporting the implementation. This could be on
financial basis, time basis, risk or all three.
In addition to this, a high level leadership support is required to drive the process.
Previous studies have shown that top management support and leadership are
essential in the successful implementation of lean techniques such as the LPS
(Drysdale, 2013; Hamzeh and Bergstrom 2010; Kim et al., 2007). The expected
leadership style is not just top down or bottom up; it is better described as
‘empowered leadership’ emanating within the team. It means each member of the
team is empowered with the capacity to rise to the occasion when the need arises.
Furthermore, the factors (drivers) that cause the imperative must be identified.
b. Identify and Understand the Drivers and Benefits for LPS Implementation
The specific drivers for the implementation of LPS should be identified. This is
important as the drivers for LPS implementation in a client organisation could vary
from that of a contracting organisation and even from one client or contracting
organisation to another.
This implies each organisation must identify its own drivers as evidenced from this
study. The drivers for LPS in clients’ organisations could include:
Development of the LPS-PCA Chapter Eight
267
quest to overcome past failures
quest for time compression and more realistic time
cost saving and risk reduction
price reduction from supply chains
quest for better working relationship with supply chains and
benefits from previous implementation.
Drivers for supply chain companies could include:
client and public sector demand
quest for time completion
internal desire for continuous improvement
project complexity
time certainty and efficient working
avoidance of time overrun that could lead to liquidation and damages
quest for improved communication with team
The early identification of these drivers is an essential process input which should be
in place, as it has the capacity to put pressure on organisations (client and supply
chain companies) to create the needed change that could support the implementation.
According to Ogunbiyi, (2014) identifying the drivers for lean implementation could
support change in the organisation. Also, the benefits of LPS implementation should
be explained to the top managers in the organisation as it would drive the
management to develop strategic capability to support the implementation.
c. Strategic Capability Commitment to Support LPS Implementation
After identifying the imperatives and drivers for LPS implementation, it is important
to develop a clear strategy and capability to support the implementation. Without a
clear strategy, the LPS implementation cannot be sustained in the organisation. Both
construction client and supply chain companies must create their own strategy.
This should focus on deliberate commitment to develop the required capability at the
OL that would support the implementation. Findings from this study reveal that
cultural issues were among the most reported barriers to the implementation of the
LPS. This could be minimised through the development of the right strategy and
creating policies that could influence the organisational culture in the implementation
process.
Development of the LPS-PCA Chapter Eight
268
This implies that the strategy should not be selected in isolation. Karim and Arif,
(2013) observed that selection of the wrong strategy in the implementation of lean
principles could lead to the disruption of the process it intends to improve. The
strategy could include: provision of training for staff and the supply chains, supply
chain assessment, changes to contract, and creation of lean business department
among others. When there is clear strategy, the chances of hitting the targeted goal is
high. In doing this, a clear contextual behaviour should be put in place at the OL to
support the strategy.
d. Create Awareness on the Strategic Capability Commitment LPS
The identified strategic commitment capability for LPS implementation and the
process created to formalise them at the organisational level must be communicated
through training at all levels. This could entail the use of company intranet to
communicate such an approach and information. The information guiding such an
approach should be located in areas where it would be prominent and accessible.
Also, workshops and training on the strategic capability commitment required should
be organised at all levels. Specific avenues and approaches that could be used to
create awareness on this include:
company intranet, newsletters, updates from formal project meetings
workshops, trainings, and
monthly project briefing among others
This would enable all the departments within the business to understand what the
organisation is doing, which would influence their own individual commitment to the
strategic capability identified at the OL. The importance of creating awareness on
company strategy at all levels has been emphasised in literature (Hodgkinson et al.,
2006; Elving; 2005). Elving, (2005) pointed out that creating awareness on the
chosen strategy should be a fundamental consideration in the strategy development at
the OL.
8.5.1.2 Contextual Inputs Factors (Behaviours arising from the contract)
Contextual input factors are the appropriate behaviours that should be in place at the
OL to support the strategic capability commitments for LPS implementation. It
focuses on the behaviours arising from the contract and its application in the process.
It helps in formalising the strategic capability identified, thus, it should form the key
Development of the LPS-PCA Chapter Eight
269
components of the strategic capability commitment process. The behaviours arising
from the contract include:
the inclusion of LPS in the contract
use of collaborative form of contract
relational contracting
collaborative working culture and
keeping the business arm of the organisation in the LPS loop
a. Inclusion of LPS in the Contract
Findings from this research reveal that LPS practice was formally included in the
contract agreement between the main contractor, client, and subcontractors on most
of the projects investigated. The essence of its inclusion in the contract was to
encourage all the required stakeholders to get involved and benefit from the process.
This is necessary because of the numerous formal processes that dominate the
construction industry. It has been suggested that formal process should not be in
relation to cost alone, rather it should include other soft practices that contribute to
the project’s success (Kadefors, 2004). Undeniably, the LPS process is not an
exception to this, and thus should be formalised.
b. Use of Collaborative Form of Contract
The use of collaborative form of contract is an essential element in the contractual
behaviour that needs to be in place at the OL for LPS implementation. Empirical
evidence from this study reveals that on most of the projects investigated, a
collaborative form of contract was used. This include; framework agreement, ECI,
D&B and joint venture. The study reveals that even when design bid build (DBB) is
used on a project, and the supply chain has been in framework agreement,
collaborative relationship still develops.
The contractual behaviour that occurs here could be better explained with relational
contracting theory. According to Macneil, (1980) as parties to the contract have more
and frequent conversation on the project, the relationship begins to develop. Also, the
assurance of the possibility of securing a future job, for example, in a framework
agreement, could motivate the team to get committed to each other on the project.
Harper, (2014) asserted that when there is shared expectation between teams on a
project, it would influence their behaviour on the project. This suggests that
Development of the LPS-PCA Chapter Eight
270
contractual behaviour has the potential of supporting collaborative behaviour on a
project.
c. Inclusion of the Commercial Arm of the Business in the LPS Loop
Another contractual behaviour that should be keyed into the organisation’s strategy is
the inclusion of the commercial arm of the business in the LPS implementation loop.
Although this was only mentioned on one project, it seems to be an essential pre-
condition to be considered at the OL. Currently, the commercial arms on projects are
less involved in the production planning meetings in the LPS process. The
involvement of this business group in the production planning session could improve
the make-ready process, as it could enable the team to make real time decision that
requires commercial judgements.
This implies that commercial decisions may not necessarily need to be logged as
constraints, thus reducing decision making time on the project. In addition to all the
factors discussed above, it is important that a new approach or strategy to working
should be communicated to other parts of the business from the organisational level.
8.5.2 Project Level
The project level (PL) factors are linked to the organisational level factors. The
implication of this is that the strategic capability commitment for LPS
implementation at the OL must be allocated appropriately at the project level. The
PL is sub-divided into pre-project and project implementation activities as shown in
Figure 8.2. Similar to the OL, the project level (PL) consists of the process input
factor and contextual input factor.
8.5.2.1 Project Level Process Input Factors
This refers to the processes that need to be created and practised at the project level
in the implementation of LPS. It defines the processes that need to be in place at the
project level (PL) for LPS. This includes:
Project level strategic capability commitment
Identify and understand production planning practice on the project
Evaluate practice with LPS principle and theory
Adopt standard approach
Create enabler for implementation
Development of the LPS-PCA Chapter Eight
271
Implement and gauge implementation
a. Align and Allocate Strategic Capability with Project Level Strategy
It is essential for a strategy to also be developed at the PL, and aligned with the OL
strategy. This is important as the team on the project would be coming from different
organisations. For example, an organisation can tell its employees it wants them to
embrace a process and educate them on why. However, projects should develop their
own identity due to the vast array of companies required to deliver a project.
In view of this, the project set-up; the companies involved including client,
contractor, suppliers and designer should establish a joint strategy that considers the
unique characteristics of the project. This should be aligned with the strategic support
for LPS implementation.
b. Identify and Review Production Planning and Control Practice
At this point, it is essential for the production planning and control practice to be
understood and streamlined to meet the strategic support allocated to the PL for the
LPS implementation. To achieve this, the current production planning practice
should be evaluated with an enhanced production planning and control principles
such as the LPS principles.
c. Evaluate and Review Practice Using the LPS Principles
The LPS is a production planning and control method developed for the construction
industry and it is among the most used lean techniques in construction. Thus, the
production planning and control practice on the project should be evaluated and
reviewed for alignment with the advocated principles/theory of the LPS (Ballard,
2000). The underlying theories of the LPS revolve around planning, execution, and
control (Ballard et al., 2009). The LPS is based on five principles which are to:
ensure tasks are planned in increasing detail the closer the task execution
approaches
ensure tasks are planned with those who are to execute them
identify constraints on the planned task to be removed by the team
beforehand
ensure promises made are secure and reliable and
Development of the LPS-PCA Chapter Eight
272
continuously learn from failures that occur when executing tasks to prevent
future reoccurrence.
Evaluating the practice based on the LPS principles would enable the identification
of areas that need improvement. The evaluation entails reviewing the practice with
the six core components of the LPS (See section Chapter 5 for detail discussion of on
LPS components). The evaluation should identify what is working well and the areas
that need improvement. This is important as it has been observed by a notable
management science theorist, Peter Drucker in one of his quotes as cited in
Hasseberth, (2008) that: “what cannot be measured cannot be improved”. A similar
evaluation and review conducted showed high potential in revealing the level of
alignment in the practice and identifying areas that need support/improvement
(Priven and Sacks, 2015; Daniel et al., 2016). This in no doubt would provide an
understanding on the improved/standard approach to be adopted on the project.
d. Adoption of Standard Approach (Specific Capability commitments required)
Based on the evaluation and review, a standard LPS approach should be adopted.
The absence of such typical approach could result into varied implementation of the
process across projects executed in the same organisation. This means a project could
be reinventing its own wheel which could hinder the intended benefits from the
system. It is worth noting that the standard approach is not rigid, thus, it could be
positioned to meet the reality on the project. However, since the LPS has 6 standard
components (Mossman, 2014; Ballard, 2000), the team should develop the specific
capability commitments required for the implementation of the components on the
project.
e. Create Implementation Enablers for LPS implementation
For the adopted approach to work, implementation enabler should be created. The
implementation enablers are grouped into two: physical and human factor enablers.
The physical factors entail the allocation of designated room for production planning
and control. This should include creating physical space such as co-location for
working and visual production planning and control centre. Such location should be
readily accessible to all the required stakeholders on the project including the
subcontractors. Also, this needs to close to work stations to prevent non-value adding
activities that could come from unnecessary movement. Furthermore, the board
Development of the LPS-PCA Chapter Eight
273
located in the room has the potential of communicating information visually to the
team during and out of meeting time.
The human factor on the other hand is concerned with the appointment of facilitators
and lean champions in driving the process on site. In the context of this study, all the
research participants identified facilitation as an essential process that needs to be in
place for the successful implementation of the process at the project level. It includes
both external and internal facilitation. External facilitation such as the use of proven
lean construction consultants could prove useful at the initial start. However, over
reliance on consultants should be avoided. This is because it could make the team to
view the process as an external initiative, thus reducing their commitment to the
process. Previous studies have also identified the importance of facilitation and
appointment of lean champions in LPS implementation (Mossman, 2015; BRE,
2006; Salem et al., 2005).
f. Gauge Practice
As the implementation process continues, it is important that the practice is
constantly gauged using both internal and external mechanisms. To gauge the
practice internally, the Planning Best Practice (PBP) guide should be used to access
the level of implementation on the project (Bernades and Formoso, 2002; Priven and
Sacks, 2015). The PBP guide is developed based on extensive research on the
application of LPS principles in construction. These studies identified 15 LPS
practices. The PBP has been used to assess the implementation of the LPS in
different parts of world such as Brazil, Israel Chile, and UK among others (Bernades
and Formoso, 2002; Priven and Sacks, 2015). However, a recent study identified two
other practices that are considered to be essential to the practice of the LPS, which
makes it 17 LPS practices (Daniel et al., 2016).
In addition, the LPS implementation maturity guide could be used. The guide was
originally developed by Gregory Howell in 2005, one of the inventors of the LPS
(Lean Project Consulting, 2005). Through this, the efficacy of implementation could
easily be assessed internally and areas that need improvement could be identified and
addressed appropriately. Gauging of the practice also requires input from the external
enabling factors.
Development of the LPS-PCA Chapter Eight
274
8.5.2.2 Project Level Contextual Input Factors (Social Behaviour)
To successfully implement the adopted common approach, contextual input factors
embedded as social behaviours are required at the project level. Social behaviours are
those soft skill behaviours that need to be practiced by the team on the project for the
successful implementation of the LPS at the PL. These factors include:
transparency and discipline,
honesty, trust and truthfulness in promising,
selection and involvement of all the required team,
pre-planning before production planning, and
proactive involvement of the construction manager and subcontractors
These are among the social behaviours that should be in place at the PL for the rapid
and successful implementation of the LPS. The need to be cautious about lack of
honesty and poor promising in the implementation of the LPS has been explained
theoretically from the Language/action perspective theory (Macomber and Howell,
2001). Practically, it entails making promises that are realistic and achievable within
the timeframe. This suggests that no stakeholder on the project should be pressurised
into making undue commitments. The five conditions for making reliable promise
should be adhered to in LPS implementation (Macomber and Howell, 2001). These
are:
understand the condition of satisfaction (CoS)
access competency before making promise
ensure capacity available and allocated
empower the team to say YES OR NO (sincerely)
accept responsibility for failure and re-review the process for learning
The action expected here is informed by social information exchange (conversation)
(Gonzalez et al., 2015; Macomber and Howell, 2003) as opposed to the technical
information exchange that dominates traditional project management (Ballard and
Howell, 1997). In such social conversations, as advocated in the LPS, every
stakeholder is empowered to make promises which could be YES! or NO!.. It has
been observed empirically that where such social network of conversation exists on a
project, the LPS works in managing the production on site effectively (Priven and
Sacks, 2015).
Development of the LPS-PCA Chapter Eight
275
Also, reliable promising supports workflow and programme reliability which is the
core focus of the LPS (Macomber and Howell, 2001). This shows the importance of
social behaviour in the implementation of LPS at the project level. Furthermore, all
the required team members should be involved in the process including the
subcontractors. The proactive involvement of the construction manager in production
planning also increases the buy-in of other stakeholders on the project.
8.5.3 External Enablers
External enablers can help in gauging practice, and can bring in new strategies and
innovations to improve current practice both at PL and OL as shown in Figure
8.2.These external enablers include:
research partnership between the industry and the academia
CPD training courses on LPS
engagement with proven lean construction consultants, and
Lean Construction Institute events.
Also, there is need to deliberately engage with the identified external enabling factors
presented above. This is essential as it has been observed that the LPS is dynamic
and it always uses various avenues to improve practice, for example, its use of theory
to explain practice (Daniel et al., 2015). Such external forum and partnership could
be an avenue for communicating and learning about improvements or findings.
Research partnership with the industry and facilitation of the process supports the
implementation of the LPS. Previous studies have also shown that research
partnership with the industry and facilitation of the process proven facilitators could
support the success of the LPS implementation in construction (Mossman, 2015;
Alarcón et al., 2005; Formoso et al., 2002).
8.5.4 Continual Learning Action and Feedback Loop
The continual learning action is the loop that sustains the implementation of the LPS.
It focuses on learning and taking action at each level. The continual action learning
advocated occurs at every point in the process as shown in Figure 8.2. This implies
that learning does not just occur at the end of the entire process only, since there is an
internal feedback loop. As shown in Figure 8.2, there is an internal feedback loop
Development of the LPS-PCA Chapter Eight
276
between the OL and PL; this is done to ensure issues that need addressing are
attended to before the process is rolled out completely.
For instance, with the roll out of a set of strategies, unintended consequences may
occur and it is helpful to understand these sooner than later. This shows the
importance of creating internal feedback loop as shown in Figure 8.2. In the
implementation of the LPS “bad news early could be said to be good news”.
To sustain the implementation of lean techniques, the organisation must be
positioned to be a learning organisation (Henrich et al., 2006). This implies that
individuals within the organisation should not only learn, but should be willing to
change from the old ways of working. According to Mohd-Zainal et al., (2013)
organisations do not learn, it is only the individuals in the organisation that learn.
This further show the important role people play in the sustenance of LPS
implementation. An inference could then be drawn thus that; the more individuals in
the organisation learn, the more the organisation learns, and the higher the chances of
sustaining lean practice. Mohd-Zainal et al., (2013) asserted that there is a strong
relationship between organisational learning and sustaining of lean practice.
Renowned researchers in lean such as Jeffrey Liker also recognised the relationship
between lean implementation and organisation learning (Liker, 2004).
Furthermore, all the learning actions feedback into the entire system to support the
internal feedback loop as the system continues. For effective learning, action data
should be captured and a formal strategy should be developed to act on them to
support continual learning. New ideas and innovations emerging from the
implementation process should feedback into the system for improvement as shown
in Figure 8.2.
8.6 Evaluation and Refinement of the LPS-PCA
8.6.1 Rationale for Evaluation of the Proposed Approach
The LPS-PCA was evaluated to achieve the following specific objectives:
To confirm if the three path clearing levels categorised in the proposed
approach should be the core areas to focus on in LPS implementation.
Development of the LPS-PCA Chapter Eight
277
To assess the adequacy of the content of each of the path clearing levels
identified.
To evaluate the usefulness of the proposed approach in supporting
construction stakeholders in the implementation of LPS.
To identify areas that need to be removed, included, or improved.
8.6.2 LPS-PCA Evaluation Method
The importance of validating research outcomes from research participants and other
stakeholders which the research output could benefit cannot be over emphasised.
Bazeley, (2013) described respondent validation or member checking as a process of
arriving at an agreement between those that participated in the study and/ or did not
participate in the study to comment on the output from the study. Such approach has
been identified as a good strategy to guide the quality of the research outcome and in
the interpretation of the data (Bazeley, 2013; Silverman, 2011; Cresswell, 2007). In
evaluating and validating the proposed LPS-PCA approach, expert opinion was
sought from lean construction practitioners through semi-structured open ended
interview and survey. It has been suggested that complex and non-quantitative
models could be validated using qualitative interviews and surveys (Smith 1983).
Lean construction practitioners were used in evaluating and validating the LPS-PCA.
The lean construction practitioners were categorised into two: the original study
participants (SP) and the non-study participants (NSP). This was done to understand
the level of difference in the perception of those who participated in the study and
those who did not participate in the study on the proposed approach. The feedback
from those that participated in the study provides internal validity, while those from
non-research participants support external validity. Silverman, (2011) stated that
verifying research outcomes with the research participants further increases the
confidence in the credibility of research results. However, Bazeley, (2013) cautioned
that the feedback from the research participants only may not necessarily be final, as
there could be possibility that the researchers conclusion could differ from the
respondents’ views.
Twelve questions were developed (see Appendix 9) to evaluate the LPS-PCA. The
questions were structured and open-ended to enable the respondents’ air their views
appropriately as required. The evaluators were drawn from the UK, US and
Development of the LPS-PCA Chapter Eight
278
Australia; this was done to bring a wider perspective on the approach. However,
majority of the respondents were from the UK, this is because the study was
conducted in the UK. The results of the evaluation are presented and discussed
below.
8.6.3 Demographic Information of Participants used in the Evaluation
The respondents that participated in the evaluation of the “Last Planner System Path
Clearing Approach” (LPS-PCA) are in two categories: those that participated in the
study are denoted with a code (SP) and the non-study participants denoted with a
code (NSP). However, all have some level of experience in the use of production
planning and control principles based on the LPS in construction as shown in Table
8.1. The respondents were drawn from client, main contracting, subcontracting, and
consulting organisations. This shows that the evaluation results would sufficiently
represent the view of key practitioners the proposed approach is targeted at. Also, all
the respondents have sufficient experience in the use of LPS which means their view
could be relied on.
Table 8. 1: Background Information of the Participant used for the evaluation
Participant
code
Position Country of
Operation
Years of
exp. in LPS
Years of
const.
exp.
SP01 Senior Excellence manager UK 15 20
SP02 Production planning manager UK 3 18
SP03 Programme manager UK 6 40
SP04 Senior consultant UK 3 7
NSP05 Assistant operation manager UK 1 1
NSP01 Lean process deployment manager Australia 10 30+
NSP02 Lean Advisor US 1 3
NSP03 Continuous Process improvement
manager
UK 1 1
NSP04 Senior consultant UK 4 11
NSP05 Senior Planner UK 1 18
However, those with low number of years’ of experience in the use of LPS were
purposively included in the sample to show how easy the proposed approach would
be to new users. Table 8.1 shows that the respondents were drawn across different
Development of the LPS-PCA Chapter Eight
279
countries. This enabled the study to demonstrate the possibility of adopting/adapting
the approach in other parts of the world outside the United Kingdom where the
original study was conducted.
8.6.4 Discussion of the Evaluation Results
Table 8.2 presents the mean responses from the two categories of the respondents
(SN and NSP) that participated in the evaluation of LPS-PCA. The response was
measured on Likert scale 1 to 4 (where 1= Very low coverage, 2 = low coverage, 3 =
high coverage and 4 = very high coverage). The results indicate that there is no
significant difference in their responses on the key aspects of the LPS-PCA
evaluated.
Table 8. 2: Results of LPS-PCA Evaluation
Aspect of LPS Path Clearing Approach Evaluated
Part
icip
an
t
Cod
e
Appropriaten
ess of the
identified
three path
clearing
levels
Level of
completeness
of factors
considered at
the OL
Level of
completeness
of the factors
considered at
the PL
Level of
completeness
of factors
considered as
eternal enabler
Usefulness of
the approach in
LPS
implementatio
n
Study participants response
SP01 3 2 3 4 Yes
SP02 4 4 4 3 Yes
SP03 2 3 3 3 Yes
SP04 3 3 2 4 Yes
SP05 3 3 3 3 Yes
Mean
response
3 3 3 3.4
Non study participants responses
NSP01 4 3 3 3 Yes
NSP02 3 3 2 3 Yes
NSP03 4 3 3 3 Yes
NSP04 4 3 3 3 Yes
NSP05 4 3 3 3 Yes
Mean
response
3.8 3 2.75 3
Overall
mean
response
3.4 3 2.89 3.2 Yes
Development of the LPS-PCA Chapter Eight
280
For example, the mean responses for the completeness of the factors consider at the
OL by the SP and the NSP is 3. This shows that there is no significant variation in
their responses in relation to the LPS-PCA. It also implies that both those that
participated in the study and those who did not, believed that the factors considered
at the OL are comprehensive in relation to LPS implementation. This finding
reinforces the internal and external validity of the proposed approach. Furthermore,
Table 8.2 revealed that the consistency is not just across the two groups only, but
within the groups also.
8.6.4.1 Completeness of Components and Contents of the Proposed Approach
The evaluation results reveal that both the SP and NSP believed that the three path
clearing levels considered in the LPS-PCA are essential areas to focus on in LPS
implementation with a total mean response of 3.4. Majority of the respondents also
agreed that the factors considered in each path clearing level have a high coverage.
For example, the total mean response for OL is 3, PL is 2.89 and external enabler is
3.2. This shows that the key factors that would enable clients, main contractors, and
subcontractors to develop an understanding of what needs to be in place for the
successful implementation of the LPS are adequately considered in the proposed
approach. One of the respondents stated that: “All was covered sufficiently” [NSP05,
UK]
However, the level of coverage of the content at the project level seems to shows the
least response from the research participants, with a total mean response of 2.98.
This could be due to the high expectation of the respondents on this, since LPS is a
project based production management system. For instance, some of the respondents
suggested a step by step guide for LPS implementation on a project. However, this is
not the aim of the proposed approach, since such steps have already been published
(see Mossman, 2014; Ballard, 2000). Nevertheless, in response to this, an industry
guide was developed to enable the stakeholders understand the step actions required
at each path clearing levels (see Appendix 11 for a copy). Also, the results in Table
8.2 indicate that both the SP and NSP believed that the factors considered as external
enablers are comprehensive with an average mean response of 3.4 and 3 respectively.
Development of the LPS-PCA Chapter Eight
281
8.6.4.2 Application and Usefulness of the Proposed Approach
All the respondents agreed that the proposed approach would definitely support the
implementation of the LPS in construction. Since this question was open-ended the
respondents were able to air their views on the usefulness of the LPS-PCA. Some of
the respondents stated that:
“Yes, as it gives structured approach to planning with the project team
including the supply chains, it helps draw upon a vast amount of knowledge
and experience” [SP02, Production Planning Manager- UK]. “Yes, it gives
more clarity and structure” [NSP01, Lean Process Deployment Manager-
Australia]. “Yes, having a framework/guide to clearing path for
implementation would help” [NSP04, Senior Consultant- UK]. “Yes, a
structured approach is essential” [SP03, Programme Manager- UK]. “Yes,
it will provide a high level strategy path for implementation across our
business” [NSP05, Senior Planner-UK]
The above statements clearly show that the proposed approach would be useful to
construction stakeholders in the implementation of the LPS in construction.
However, some of the respondents recommended that the proposed approach should
be used with the support of an experienced coach for maximum benefit. Here are
some of the comments:
“The approach should be used with support of a facilitator/lean champion”
[NSP01, Lean Process Deployment Manager- Australia]. “The approach
should be used with the support of an industry experienced coach” [SP03,
Programme Manager- UK] “As it stands, I would recommend that the
proposed approach should be used with some form of consultation with
experts” ” [NSP04, Senior Consultant- UK].
The above statements show the need for engaging experienced facilitators and lean
champions in using the approach. A previous study has highlighted the importance of
facilitation in the implementation of the LPS (Mossman, 2015). Furthermore,
majority of the respondents indicated that the proposed approach can be
adopted/adapted in any part of the world. Some of the respondents stated that:
“I am sure it could be adapted anywhere, as the overall objective is the
same” [SP03, Programme Manager- UK]. “My view is that the proposed
Development of the LPS-PCA Chapter Eight
282
approach could be adopted on any construction project irrespective of the
location” [NSP02, Lean Advisor- US].
This shows that the usefulness of the proposed approach is not just limited to the UK
construction industry where the study was originally conducted. Since this assertion
is also supported by other research participants drawn from the US and Australia.
However, some of the respondents suggested that the proposed approach should be
rolled out to the senior management team first. Some of them stated that: “The
approach should be rolled to the senior management team first, then cascaded down
to project and site level” [NSP05, Senior planner-UK]. Again, this further confirms
that the way in which the LPS-PCA is structured is appropriate.
8.6.4.3 Refinements to LPS-PCA Following Evaluation Feedbacks
One of the objectives of the evaluations is to identify areas that need improvements
in the proposed approach. Some of the respondents suggested that an industry
tailored guidance note should be developed to supplement the proposed approach.
Some of the respondents stated that: “It needs to be supported with accompanying
notes for the site team” [SP02, Production Planning Manager- UK]. “Guidance
note that explains each component should be provided” [SP01, Senior Excellence
Manager- UK].
In response to this feedback on the need for a guidance note to support construction
practitioners in the use LPS-PCA, a 25 page industry tailored guidance that describes
each component and the step actions required at each stage was developed. Please
see Appendix 10 and 11 for an A3 copy of LPS-PCA and an industry guidance note.
Some further evaluation was done using the guidance with those that participated in
the initial evaluation. They agreed that the guidance has further improved their
understanding on the use of the LPS-PCA.
8.6.4.4 Emerging Influence of the LPS-PCA and the Pilot Implementation
It is worth mentioning that piloting the LPS-PCA on a live project is not part of the
objectives of this study. This is due to the limited time frame of the study and the
methodology adopted for this study which is exploratory and descriptive rather than
an action research. However, during the evaluation process, some of the respondents
indicated an interest to pilot it on some live project. One of the clients stated that: “I
would recommend the use of the approach; my team would pilot it in our
Development of the LPS-PCA Chapter Eight
283
organisation” [SP03, Programme Manager- UK]. This shows the proposed
approach is already in the process of influencing the implementation of the LPS in
construction. It could also imply that there is not a set process such as LPS-PCA at
the moment.
8.6.4.4 Feedback on Pilot Implementation LPS-PCA in a Client Organisation
It is interesting to note a client has commenced the pilot implementation of LPS-PCA
in its organisation and this process is still on-going. The focus of the implementation
at the moment has been on “the organisation path clearing level and the engagement
with some “external enablers” as proposed in the approach. For example, the
Continuous Process Improvement Manager for the client has had some engagement
with some Lean Construction Institute affiliate bodies and lean construction
researchers in the academia.
Following these engagements, various presentations on LPS were made and the
imperative for the use LPS was made to the company management team. This
presentation and the business case for LPS supported the management buy-in. At
present, an experienced lean construction professional has been employed by the
client through an academic and industry partnership to implement the approach on its
projects. Again, this empirically shows that management support and engagement
with external enabler is important to the process.
Currently, an experienced lean construction professional employed by the client uses
the LPS-PCA in LPS implementation in the organisation without any influence from
the researcher. Again, this does not only demonstrate the functionality of the LPS-
PCA but also reduces bias that usually occurs when such implementation is done by
the researcher. Training and workshops is being organised and they are now in the
process of establishing the strategic capability required to support the
implementation at the organisation level.
This preliminary finding indicates that the proposed LPS-PCA support construction
stakeholders in the implementation of the LPS. Since the process is still on-going, a
follow up to see how the piloting process progresses would be done, and this will be
reported in future publications.
Development of the LPS-PCA Chapter Eight
284
8.7 Chapter Summary
This chapter focused on answering one of the research questions set out in this study
that states that: how can construction stakeholders be supported to successfully
implement the LPS? The chapter established the rationale for developing a structured
approach that would support the implementation of the LPS in construction. The
chapter shows that previous approaches developed or proposed to support the
implementation of the LPS in construction seem to focus more on the project level,
with less attention to other factors. To address this gap, the Last Planner System Path
Clearing Approach (LPS-PCA) was proposed. The aim of the LPS-PCA is to enable
construction stakeholders (clients, main contractors, and subcontractors) to develop
an understanding of what needs to be in place for the rapid and successful
implementation of the LPS. The LPS-PCA comprises of three path clearing levels,
these are: organisational, project and external enablers.
The chapter shows that these path clearing levels are essential areas to focus on in the
LPS implementation. The chapter also highlighted the necessary step actions to
follow in adopting the proposed approach in the implementation of the LPS at each
path clearing level. The step actions required at each path clearing level were
classified into process input and contextual input factors. The chapter demonstrates
that the proposed LPS-PCA would support the implementation of production
planning and control in construction. This is based on the feedback received from the
evaluation of the proposed approach. To further support this, it was suggested that an
industry guide be developed to assist practitioners in using the LPS-PCA, thus, a full
guidance was developed and a copy is available in Appendix 11.
The evaluation results indicate that the issues covered in the proposed approach are
adequate to support and guide construction stakeholders in understanding what needs
to be in place for the successful implementation of the LPS. It is worth mentioning
that a client is currently piloting the proposed approach in its organisation and
preliminary findings indicate that the approach supports LPS implementation. This
further demonstrates the potential and practical application of the proposed approach
in supporting the application of the LPS in construction. The chapter shows that the
approach could easily be adopted/adapted anywhere in managing project production
based on the LPS. The next chapter presents the conclusion to the study.
Conclusion and Recommendations Chapter Nine
285
CHAPTER 9: CONCLUSIONS AND
RECOMMENDATIONS
9.1 Introduction
This final chapter captures the main conclusions and recommendations from this
study. The chapter commences with the re-statement of the research aim and
objectives and goes further to presents the summary of the main findings. The
chapter also presents the conclusions on each research objective and the research
questions. The original contribution of the study to knowledge and the implication of
the research findings for industry are identified. Finally, the chapter identifies the
study limitations and makes recommendations for further research and the industry.
9.2 Re-statement of Research Aim, Objectives and Process
The aim this research is to know how the current understanding and application of
“Collaborative Planning” (CP) for delivering construction projects in the UK from a
production planning and control perspective aligns with the advocated principles and
theories of the Last Planner System (LPS). In addition to this, to finally, propose an
approach that would support construction stakeholders (Client, Main contractors and
Subcontractors) for rapid and successful implementation of the Last Planner system
for construction process. To achieve this aim, six objectives were identified as
presented in Chapter One and in section 9.4.
Empirical data on the current application of CP for delivering construction projects
in the UK from production planning and control based on the LPS perspective were
aggregated. These data were obtained from the major sectors (building, road, and
rail) of the UK construction industry through various methods. These methods
include: interviews, structured survey, and case studies. In all, a total of 58
interviews were conducted, 15 projects observed, 3 in-depth case studies conducted
and 10 survey responses. The summary of findings is presented in the next section.
9.3 Summary of Research Findings
The summary of the research findings from stages 1 to 4 are presented below:
Conclusion and Recommendations Chapter Nine
286
The literature review established that there is dearth in empirical study on the
relationship between collaborative planning practice for construction delivery
projects from a production planning and control perspective in the UK and
the advocated principles of the LPS of production control.
Findings from the literature also indicate that previous frameworks proposed
to support the implementation of the LPS tend to focus more on the project
level.
The study reveals that the LPS has shown its potential to improve
construction project management practice, evidenced within many published
examples from across the major continents of the world.
The study reveals that Collaborative Planning and Last Planner are used
interchangeably to describe the application of production planning and
control principles in the UK on most of the projects evaluated.
Collaborative programming/phase planning, WWP meetings and the
measurement of PPC were done on most of the projects evaluated.
Practices such as the make-ready process, look-ahead planning, consideration
for work flow, and acting on reasons for non-completion of tasks among
others were only partially implemented.
The study established that the current practice of CP in the UK construction
industry aligns partially with the LPS principles.
The study shows that client demand and the desire for continuous
improvement are among the major drivers for implementing production
planning and control practice based on the LPS in the UK construction
industry.
Currently, LPS is mostly used as an intervention measure within the UK
construction industry rather than for transformation.
The study further reveals that cultural issues, dishonesty, “old thinking”,
“poor promising”, and lack of trust are among the major barriers to LPS
implementation in the UK.
The study identified and categorised the nature of support required for the
rapid and successful implementation of LPS in construction. These are;
support/process at the organisational level, support at the project level and
external enablers.
Conclusion and Recommendations Chapter Nine
287
Study reveals that the batching (reduced batch sizing) of the highways
infrastructure projects support the implementation of the LPS on highways
projects.
The study confirms that the LPS can be implemented with any form of
procurement method.
The study reveals that the formal inclusion of the LPS in the contract clause
influences the commitment of the supply chain to the process.
The study also confirms that the use of collaborative form of contract and
long term relationship influences the implementation of the LPS.
The study developed an approach to support construction stakeholders
(clients, main contractors & subcontractors) in developing an understanding
of what needs to be in place for the successful implementation of the LPS.
The evaluation and pilot implementation results indicate that the proposed
approach supports the application of production planning and control practice
in construction.
The study reveals that LPS implementation has a positive impact on
construction process improvement with regard to improvement in activity
scheduling and programme reduction, collaborative working practice, and
better understanding of project goal and task among others.
9.4 Conclusions on Research Objectives
Table 9.1 presents the identified six objectives of the study and how they were
achieved in this study. The conclusions on each research objectives are subsequently
discussed.
Table 9. 1: Research Objectives and How they were Achieved
No Research Objectives Method Used Chapter
1 To critically review the need for
construction process improvement (CPI)
and the development of production
planning and control practice in the UK
construction industry.
Review the extant literature on CPI
initiatives and the development of
production planning control practice
in the UK construction industry.
Chapter
Two
2 To critically evaluate the development of
collaboration in design, planning and
execution of work in other fields and
identify the implication for construction
planning theory and practice.
Review the extant literature on
collaboration and collaborative
working and the development of
collaboration in urban planning and
software development.
Chapter
Three
Conclusion and Recommendations Chapter Nine
288
3 To critically evaluate the applications and
developments in the Last Planner System
in managing project production system in
the construction industry globally.
Review extant literature on LPS
implementation case studies, theories
publications and recent developments
Chapter
Four
4 To investigate the current understanding
and application of production planning
and control practice in the UK
construction and its alignment with the
LPS
Conducted 30 exploratory interviews
and a structured observation of 15
projects.
Chapter
Six
5 To determine the nature of support needed
for rapid and successful implementation
of the LPS and to identify the impacts of
LPS on CPI.
Three in-depth case studies were
conducted and data was collected via
interviews, document analysis and
physical observation.
Chapter
Seven
6 To propose and validate an approach that
would support construction stakeholders
in implementing the LPS.
Development of Last Planner Path
Clearing (LPS-PCA) approach based
on the findings from Stages 1 to 4 of
the study. LPS-PCA was evaluated
with research participants and non-
research participants
Chapter
Eight
9.4.1 Objective 1
To understand the need for construction process improvement and the development
of Production Planning and Control Practice in UK Construction
The aim of objective one was to explore the need for construction process
improvement (CPI) and the development of production planning and control practice
in the UK construction industry. The review established that the demand for
construction process improvement is not limited to the UK construction industry
alone; rather it is a global call across the world. More importantly, the review shows
that the demand for construction process improvement was hinged on collaboration
in the design, planning and in the execution of the planned task, especially as
detailed in the UK construction industry reports. However, the lack of genuine
framework for CPI has retarded its application in the industry.
The review shows that the earliest application of production planning and control
principles under the name “Last Planner System” for delivering construction projects
in the UK was on the Heathrow T4 coaching gate, T4 Arrival phase 2, and T1
International Arrivals projects in 1999. It was then fully implemented on Heathrow
T5 project in 2001 by the BAA. LPS was piloted on a building project by research
team at Northumbria University in 2003. This was followed by the Lean
Construction Improvement Programme (CLIP) under the term “Collaborative
Conclusion and Recommendations Chapter Nine
289
Planning” (CP) which was implemented on demonstration projects. The review
shows that the reported practice of CP in the demonstration project has some
resemblance with the LPS, while other elements of the LPS were not reported.
However, this could not be fully substantiated from the review as empirical data
from the industry is required for authentication. This became the knowledge gap
which informed the overall research question for the study.
9.4.2 Objective 2
To Evaluate the Development of Collaboration in Planning in Urban Planning and
Software Engineering Development and the implication for Construction Planning
This objective was motivated by the quest to appreciate the development of
collaboration in design, planning, and execution of work in other fields and identify
learning and implications for construction planning theory and practice.
The review reveals that the dissatisfaction with the non-collaborative approach used
in the fields of urban planning (UP) and software engineering development informed
their eventual journey towards more collaborative approaches. The study established
that the paradigm shift in these fields have implications for construction planning
practice and theory. The study shows that the Rational Comprehensive Model
(RCM) and the waterfall process model that previously formed the basis of planning
decisions in UP and in software development lack the capacity to support
collaboration in planning. This has also been established to form the basis of
planning practice in the construction industry as seen in the CPM. However, with the
realisation of the negative impact of these approaches to planning decisions, both UP
and software engineering design opted for a more collaborative model.
The successful adoption of collaborative approaches in these knowledge areas shows
that the construction industry could also move from its current technical approach to
a more social approach that encourages collaboration. This entails focusing on
system thinking rather than the current functional ‘activity to activity’ thinking that
dominates the industry. The review shows that the application of the current theory
of project planning alone, that is, ‘management-as-planning’ (the Transformation
view), lacks the capacity to develop collaborative relationships among project
stakeholders. To overcome this, construction planning and management should
include the concept of management-as-organising that supports the ‘Flow’ and
Conclusion and Recommendations Chapter Nine
290
‘Value’ view for smooth running of the production (construction) system as
demonstrated in Scrum and the LPS.
9.4.3 Objective 3
To understand the Application and Developments in the Last Planner System in
managing production planning and control
This objective aims to develop an understanding on the application and
developments in the Last Planner System in managing project production in the
construction industry globally. General and systematic review of publications on the
LPS was conducted, including the review of IGLC publications between 1993 and
2014. The review established that the LPS is a production planning and control
methodology for managing project production in construction, which was developed
by Ballard and Howell from research in the industrial construction sector.
The review demonstrates that the LPS has developed in terms of its level of
implementation, and theory, and is now used as a vehicle to improve construction
management practice in different parts of the world. In fact, it is one of the most
implemented lean construction techniques. The study indicates that it has been
implemented across 16 countries which cut across the major continents of the world
and with significant impacts. The study shows that the LPS is not static, but has
evolved greatly in managing production in construction. This is demonstrated in its
integration with other emerging concepts such as BIM, and vplanner. Also, the trend
in the implementation of its elements, progress on LPS research, and its building
practice on sound theory among others attest to its development. The LPS is
currently being benchmarked by Glenn Ballard with input from across the world; the
participants are drawn from both industry and academia. The intention of this is to
reflect on the initial framework and to correlate that with current practice in the
industry in order to strengthen its application and influence.
9.4.4 Objective 4
To investigate how the current understanding and application of “Collaborative
Planning” (CP) for delivering construction projects in the UK from a Production
Planning and control perspective align with the advocated principles and theories of
the Last Planner System (LPS)
The aim of this objective is to identify how Collaborative Planning (CP) for
delivering construction projects from the production planning and control perspective
Conclusion and Recommendations Chapter Nine
291
in the UK construction industry aligns with the advocated principles of the LPS. To
achieve this objective, 30 construction professionals drawn from the major sectors
(Building, road, and rail) of the UK construction industry were interviewed. In
addition to this, 15 projects from these sectors were observed and findings were
triangulated to obtain a wider perspective.
The study established that the current practice of CP as observed in the major sectors
of the UK construction industry align partially with some of the generally advocated
principles of the LPS acknowledged in the literature. The study reveals that the
current practice of CP in the UK has not explored all components of the LPS. The
depth of application of the more complex attributes contained in the LPS is weak or
missing. This situation inhibits the extent of benefit that can be realised and even the
enhancement of industry performance.
9.4.5 Objective 5
To identify the nature of support needed for rapid and successful implementation of
the LPS and to identify the current impacts of production planning and control
practice on construction process improvement.
To achieve this objective, three in-depth case studies drawn from building and
highways infrastructure projects were conducted. Evidence was obtained from
interviews, document analysis, and observations. The study identified and
categorised the nature of support/process required for the rapid and successful
implementation of LPS in construction into three. These are; support required at the
organisational level, support required at the project level and the external enablers.
Various factors were considered under this categorisation and the study concludes
that all the factors are the foundation that needs to be in place for the successful
implementation of the LPS.
The study demonstrated that the LPS implementation has a positive impact on
construction process improvement with regard to improvement in activity scheduling
and programme reduction, collaborative working practice, better understanding of
project goal and task, better communication and relationship among project team,
significant reduction in rework, and efficient working among others. However, its
impact on safety was not clear, as it was not measured in relation to LPS/CP
implementation on the case studies.
Conclusion and Recommendations Chapter Nine
292
9.4.6 Objective 6
To propose and validate an approach that would support construction stakeholders
in implementing the LPS.
The aim of this objective is to develop an approach that would support construction
stakeholders (clients, main contractors, subcontractors) in the implementation of the
LPS. To achieve this objective, 3 in-depth case studies were conducted over a 12
month period. A non-prescriptive approach known as “Last Planner System Path
Clearing Approach” (LPS-PCA) was developed and validated using 10 construction
industry professionals. Previous approaches developed or proposed to support the
implementation of the LPS in construction seemed to focus more on the project level,
with less attention on other factors. The LPS-PCA developed in this study comprises
of three path clearing levels, these are: organisational, project and external enablers.
A guidance note that highlights the necessary step actions to follow in the
implementation of LPS using the LPS-PCA was developed, see Appendix 11.
The evaluation and pilot implementation results reveal that the proposed LPS-PCA
has the potential to support stakeholders in the implementation of the LPS in
construction. This is based on the feedback received from the evaluators and the pilot
implementation. The evaluation results indicate that the issues covered in the
proposed approach are adequate to support and guide construction stakeholders in
understanding what needs to be in place for the successful implementation of the
LPS. It is worth mentioning that the pilot implementation is still on-going.
9.5 Conclusion on Research Questions
Two overarching research questions informed this research:
3. How does the current understanding and application of “Collaborative
Planning” (CP) for delivering construction projects in the UK from a
Production Planning and Management perspective align with the advocated
principles of the LPS?
4. How can construction stakeholders (client, main contractors, and
subcontractors) be supported for rapid and successful implementation of the
LPS?
The above research questions were answered through the achievements of the six
study objectives. Specifically, it emerged from the study that the current practice of
CP in the UK construction industry only aligns partially with the advocated
Conclusion and Recommendations Chapter Nine
293
principles of the LPS. The second research question was answered through the
achieved aim of developing an approach called LPS-PCA that was proved to have
the potential to support construction stakeholders in the implementation of the LPS
in construction.
9.6 Original Contribution of Research to Knowledge
The Nottingham Trent University Research Degree Regulations states that PhD
research should generate “the creation and interpretation of new knowledge and / or
the invention and generation of ideas through original research in an academic
discipline.” Accordingly, this research has made a number of original contributions
to the existing body of knowledge in construction project management, lean project
management and in particular to the future application of production planning and
control principles in construction. The original contribution of this thesis to
knowledge is itemised under; (1) contribution to theory and (2) contribution to
practice.
9.6.1 Contribution to Theory.
The original contribution to theory is evidenced in these points:
it identifies the mismatches in the current practice of collaborative planning
for delivering construction projects from a production planning and control
perspective in the UK construction industry by exposing and exploring the
current practice across the major sector of the UK construction industry. It
also generates new insights into the prevailing application of production
planning and control principles through the lens of the Last Planner System.
the development of a non-prescriptive but all-inclusive approach for
supporting construction stakeholders (client, main contractors and
subcontractors) in the implementation of the LPS in construction known as
“Last Planner System Path Clearing Approach” that includes organisational
and external path clearing levels. This expands previous approaches to the
implementation of the LPS in construction which focused more on the project
level.
a contribution to the limited literature and theory on collaboration in
construction planning. This by providing evidence through a critical
evaluation of extant literature in urban planning, software engineering and
Conclusion and Recommendations Chapter Nine
294
construction management on planning that construction project management
could also move from its current technical approach in planning to a more
social approach that encourages collaboration.
9.6.2 Contribution to Practice
The practical contribution of the research to construction project management and
lean construction practice are itemised below:
The practical application of the developed LPS-PCA enables construction
stakeholders (clients, main contractors, and subcontractor) to understand what
needs to be in place for the successful implementation of the LPS, especially
intending stakeholders. Thus, enabling them to make the right decision with
regard to process and behaviour in the LPS implementation process.
The provision of evidence on the impact of LPS on construction process
improvement in the UK construction industry addresses a problem of
initiating change without evidence.
It identified the need for path clearing in full Last Planner System
implementations. The identification of the three “path clearing levels”
(organisational, project and external enabler) provides a focal point for
construction practitioners to focus on in the implementation of production
planning and control principles based on the LPS in construction
The clear identification of the elements of the current practice of CP
compared to the components of the LPS and the mapping out of the identified
matches and mismatches guide the future practice of the LPS among
construction practitioners in the construction industry.
9.6 Research Publications
As part of the contribution of this research to lean construction and construction
project management body of knowledge, the following papers have been developed
and published from this research.
9.6.3 Conference papers
1. Daniel, E.I., Pasquire, C., and Dickens, G. (2016). “Exploring the factors that
influence the implementation of the Last Planner System on joint venture
infrastructure projects: A case study approach.” In: Proc. 24th
Ann. Conf. of
Conclusion and Recommendations Chapter Nine
295
the Int’l. Group for Lean Construction, Boston, MA, USA, pp. xx–xx.
Available at: <www.iglc.net>.
2. Daniel, E.I., Pasquire, C. and Dickens, G. (2015), “Exploring the
Implementation of the Last Planner® System Through IGLC Community:
Twenty One Years of Experience”. In:, Seppänen, O., González, V.A. &
Arroyo, P., 23rd Annual Conference of the International Group for Lean
Construction. Perth, Australia, 29-31 Jul 2015. pp 153-162
3. Daniel, E. I, Pasquire, C and Dickens, G (2015b). “Assessing the practice and
impact of production planning and management in UK construction based on
the Last Planner® System”. 2nd School of Architecture Design and Built
environment Doctoral Conference, 8-9 June, 2015, NTU, Nottingham UK
4. Daniel, E. I, Pasquire, C and Dickens, G., (2014). “Social perspective of
planning in construction: The UK experience In: Raiden, A B and Aboagye-
Nimo, E (Eds) Procs 30th Annual ARCOM Conference, 1-3 September 2014,
Portsmouth, UK, Association of Researchers in Construction Management,
1355- 1365
9.6.4 Journal Publications
1. Daniel, E .I, Pasquire, C Dickens, G. and Ballard, G. (2016). The relationship
between the Last Planner® System and collaborative planning practice in UK
construction. Engineering , Construction and Architectural management
(2016)
2. Daniel, E .I, Pasquire, C., and Dickens, G. (under review) Collaboration in
planning in other fields and its implication for construction project
management. Journal of Construction Economics and Management.
9.6.5 Future Publication Plan
1. Framework for supporting construction stakeholders in the implementation of
the Last Planner System in the construction industry
2. An identification of the nature of support for the rapid and successful
implementation of the Last Planner System in Construction
3. The influence of procurement on the implementation of the Last Planner
System in construction
Conclusion and Recommendations Chapter Nine
296
4. Assessing the impact of Last Planner System on construction process
improvement: The UK experience
9.7 Research Limitations
Every research has its limitations and this not an exception. The main limitations to
this research are itemised as follows:
The empirical data aggregated for this research are mainly on the construction
phase. This implies that the application of production planning and control
principles based on the LPS explored did not capture the practice in the
design phase sufficiently. In addition, views from design practitioners are not
fully represented; future studies should include this.
Although, a client is currently piloting the validated LPS-PCA on a live
project in its organisation, evidence of this is only partially reported in this
thesis due to the time required to generate such evidences. Implementing the
approach on a project over a long period would offer further improvement to
the proposed approach. Future work should consider this.
While effort was made to draw LPS-PCA evaluators from across globe to
reflect a wider perspective, majority of those that eventually participated are
largely practitioners from Europe, North America, and Australia. Since they
are all Westerners, the Western culture could influence their judgement.
9.8 Recommendations
This study has explored the practice of production planning and control based on the
LPS in construction and has developed an approach to support construction
stakeholders in implementing the LPS in construction. There is opportunity for future
study to build on the work reported in this thesis and also recommendation for
industry practitioners for better benefit realisation. Recommendation is therefore
made for industry practitioners and researchers.
9.8.1 Recommendation for Industry Practitioners
Based on the outcome of this study, the following recommendations are made for
construction industry practitioners and stakeholders:
Conclusion and Recommendations Chapter Nine
297
Key practices associated with the LPS such as the make-ready process, look-
ahead planning, full consideration for workflow, strategy to act on RNC, and
communication of results to subcontractors among others that are currently
only partially implemented should be done fully.
The “make-ready process” and the development of a workable backlog
should be fully integrated into the look-ahead planning. Commitment to this
is essential and the project team should acknowledge the importance of
releasing only sound tasks into the production system.
The “Planning Best Practice” (PBP) checklist should be used by the project
team to evaluate the level of LPS principles on the project.
Initially, the developed LPS-PCA should be used in consultation with an
experienced lean construction practitioner.
Lean champions and facilitators should be appointed both at the project and
organisation levels to drive the implementation of the LPS on the project and
in the organisation as a whole.
Project managers and facilitators should endeavour to select and ensure all
the required stakeholders are present at the production planning meetings.
For smooth implementation of the LPS at the project level, the step actions
identified at organisational level and the external enablers should be deployed
as appropriate.
Organisations should develop a long-term strategic plan for LPS
implementation and integrate such plan into their business delivery model for
better benefits.
9.8.2 Recommendation for Further Research
There are various scopes for future study to build on from the outcome this research,
some of these are itemised below:
This study has successfully explored and identified the mismatches in the
current practice of the LPS in the UK and developed an approach (LPS-PCA)
to support construction stakeholders for successful implementation. However,
this approach has not been fully tested on any live project to measure its
impacts in supporting LPS implementation. Future studies should consider
using action research method to implement the LPS-PCA on live projects.
Conclusion and Recommendations Chapter Nine
298
This would provide empirical evidence that could be used to improve the
approach as appropriate.
It emerged from this study that “poor promising” is among the major barriers
in the implementation of production planning and control practice based on
the LPS on the projects. Future studies should investigate the fundamental
principles and apparatus that support effective commitment/promising among
construction stakeholders on projects so as to grow trust within the project
team.
Also, considering the increasing report on the use of the LPS in the design
phase in other parts of the world, future studies should explore the application
of the LPS at the design phase in the UK construction industry and compare
such findings with this study. The study should then extend the LPS-PCA and
integrate the design phase into it.
Considering the increasing call by the Government for the use of BIM in
delivering construction projects the UK, future studies should examine how
LPS and BIM could be used to manage project production planning and
control using a case study approach.
References
299
References
A
ABS, (2010). A statistical overview of the construction industry [Online] Available
at :
http://www.abs.gov.au/AUSSTATS/[email protected]/Lookup/1350.0Feature+Artic
le1Oct+2010 Accessed: 20 July 2015
Adamu, I. and Howell, G., (2012). Applying Last Planner in the Nigerian
construction industry. In:, Tommelein, I.D. & Pasquire, C.L.,20th Annual
Conference of the International Group for Lean Construction. San Diego,
USA, 18-20 Jul 2012.
Ahiakwo, O., Oloke, D., Suresh, S. and Khatib, J., (2013). A Case Study of Last
Planner System Implementation in Nigeria' In:, Formoso, C.T. &
Tzortzopoulos, P., 21th Annual Conference of the International Group for
Lean Construction. Fortaleza, Brazil, 31-2 Aug 2013. pp 699-707
Alarcón, L. and Ashley, D., (1999). Playing Games: Evaluating the Impact of Lean
Production Strategies on Project Cost and Schedule, 7th Annual Conference
of the International Group for Lean Construction, IGLC-7, Berkeley CA,
USA.
Alarcon, L. F., and Calderón, R., (2003). Implementing lean production strategies in
construction companies. In ASCE, Construction Research Congress.
Alarcón, L. F., Diethelm, S., Rojo, O., and Calderon, R. (2005). Assessing the
impacts of implementing lean construction. In Proceedings of the 13th
International Group for Lean Construction Conference (p. 387).
Alarcón, L.F. , Diethelmand, S. and Rojo, O. 2002, 'Collaborative Implementation of
Lean Planning Systems in Chilean Construction Companies' In:, Formoso,
C.T. & Ballard, G., 10th Annual Conference of the International Group for
Lean Construction. Gramado, Brazil, 6-8 Aug 2002. pp 541-551
Alberts, D. S., & Hayes, R. E., (2007). Planning: complex endeavours. Assistant
Secretary of Defence (C3I/Command Control Research Program)
Washington DC. Chicago
References
300
Allmendinger, P and Mark, T., (2002) Planning Futures: New DirectionsFor
Planning Theory. London: Routledge
AlSehaimi, A. , Tzortzopoulos, P. and Koskela, L., (2009). Last Planner System:
Experiences From Pilot Implementation in the Middle East. In:, Cuperus, Y.
& Hirota, E.H., 17th Annual Conference of the International Group for
Lean Construction. Taipei, Taiwan, 15-17 Jul 2009. pp 53-66
Alsehaimi, A. O., Tzortzopoulos Fazenda, P. and Koskela, L. J., (2014). Improving
construction management practice with the Last Planner System: A case
study. Engineering, Construction and Architectural Management, 21(1), 51-
64
Amaratunga, D., Baldry, D., Sarshar, M. and Newton, R., (2002). Quantitative and
qualitative research in the built environment: application of “mixed”
research approach. Work Study, 51 (1), 17-31.
Amundson, S. D. (1998). Relationships between theory-driven empirical research in
operations management and other disciplines. Journal of Operations
Management, 16(4), 341-359
Anderson, S, Shane, J S, and Schexnayder, C (2010) Strategies for planned project
acceleration. Journal of Construction Engineering and Management,
137(5), 372-381.
Arditi D., 1981, A comparison of attitudes to planning in industrialised and
developing countries, Proceedings PMI Internet joint symposium 641-649
Arroyo, P. , Tommelein, I.D. & Ballard, G. 2014, 'Comparing Weighting Rating and
Calculating vs. Choosing by Advantages to Make Design Choices ' In:,
Kalsaas, B.T., Koskela, L. & Saurin, T.A., 22nd Annual Conference of the
International Group for Lean Construction. Oslo, Norway, 25-27 Jun 2014.
pp 401-412
Atikins, K., H., (2013) Collaborative Planning & BIM [online].Available at
http://assets.highways.gov.uk/specialist-information/knowledge-
compendium/2011-
13knowledgeprogramme/Collaborative%20Planning%20%26%20BIM%20-
References
301
%20M4_M5%20VisiLean%20Implementation%20Report.pdf [Accessed:
14.08.2015]
Attaran, M., & Attaran, S. (2007). Collaborative supply chain management: the most
promising practice for building efficient and sustainable supply chains.
Business Process Management Journal, 13(3), 390-404
Austen, A. D., & Neale, R. H. (1984). Managing construction projects: a guide to
processes and procedures. International Labour Organization.
Austin S A, Baldwin A N, J L Steele J L (2002) Improving building design through
integrated planning and control Engineering Construction and Architectural
Management, 9 (3) (2002), pp. 249–258
B
BAA, (2000). Heathrow airport terminal 1 future concept project execution plan.
Baiden, B.K., Price, A.D.F. and Dainty, A.R.J., (2006). The extent of team
integration within construction projects. International Journal of Project
Management, 24(1), pp. 13-23.
Ballard G, Howell G., 1995, Towards Construction JIT, Proceedings of 11th
ARCOM
Ballard, (2015). Last Planner current process benchmark. [Online] Symposium
presentation Project Production Institute. Available at:
http://projectproduction.org/resources/presentations/ [Accessed: 4 February
2016]
Ballard, (2015). Last Planner current process benchmark. Project production
laboratory, University of California, Berkerly.
Ballard, G. (1997), “Lookahead Planning: The Missing Link in Production Control”
in, Tucker, S.N., 5th Annual Conference of the International Group for
Lean Construction, Gold Coast, Australia, 16-17 July, 1997, pp. 13-
26.pp.11-17.
References
302
Ballard, G. (2006). “Rethinking Project Definition in terms of Target Costing”.
Proceedings of the 14th annual conference of the International Group for
Lean Construction, Santiago, Chile, July 25-27, pp. 77-89
Ballard, G., Hammond, J. and Nickerson, R. (2009), “Production Control Principles”,
in, Cuperus, Y. and Hirota, E.H. Eds proceedings of 17th Annual
Conference of the International Group for Lean Construction, Taipei,
Taiwan, 15-17 July 2009, pp 489-500.
Ballard, G. and Howell, G. (1994) Implementing lean construction: stabilizing work
flow, in Proceedings of the 2nd Annual Conference of the International
Group for Lean Construction, Santiago, Chile.
Ballard, G. and Howell, G. (1997). Implementing lean construction: improving
downstream performance,in Alarcon, L., (Ed.), Lean Construction,
Rotterdam, Balkema, pp. 111-125.
Ballard, G. and Howell, G. (1998). Shielding Production: Essential Step in
Production Control. J. Const. Engr. Mgmt., ASCE, 124, (1), pp. 11-17
Ballard, G. and Howell, G., 2004. Competing construction management
paradigms. Lean Construction Journal, 1(1), pp.38-45.
Ballard, G. and Howell, G.A. (2003), “An Update on Last Planner”, in, 11th Annual
Conference of the International Group for Lean Construction, Virginia,
USA,
Ballard, G. and Howell, G.A., (2005). Relational contracting and lean
construction. Lean Construction Journal, 2(1), pp.1-4.
Ballard, G. and Paul, R. (2004). “The St. Olaf College Fieldhouse Project: A Case
Study in Designing to Target Cost”. Proceedings of the 12th annual
conference of the International Group for Lean Construction, Elsinore,
Denmark, August, 2004.
Ballard, G., & Howell, G. (1998). Shielding production: essential step in production
control. Journal of construction Engineering and Management, 124(1), 11-
17.
References
303
Ballard, G., & Howell, G. (2003). Lean project management. Building Research &
Information, 31
Ballard, G., & Howell, G. (2004). Competing construction management paradigms.
Lean Construction Journal, 1(1), 38-45.
Ballard, G., & Koskela, L. (2011). A response to critics of lean construction. Lean
Construction Journal, special IGLC issue, pp 13-22
Ballard, G., (2015a). Crew Level Planning. Lean Construction Journal, pp 15-24
Ballard, G., 1999. Improving Work Flow Reliability. Proceedings of the 7th Annual
Conference for International Group for Lean Construction Pp. 275-286
Ballard, G., and Howell, G. (1994), “Implementing lean construction: stabilizing
work flow”, in Alarcon, L., (Ed.), Lean Construction, Rotterdam, Balkema,
pp.101-110.
Ballard, G. and Howell, G. (1997), “Implementing lean construction: improving
downstream performance,” in Alarcon, L., (Ed.), Lean Construction,
Rotterdam, Balkema, pp. 111-125.
Ballard, G., and Howell, G. (1998). Shielding production: essential step in
production control. Journal of Construction Engineering and Management,
124(1), 11-17.
Ballard, G., Howell, G. and Castern, M. (1996) PARC: a case study, in Proceedings
of the 4th Annual conference of the International Group for Lean
Construction, University of Birmingham, Birmingham, UK.
Ballard, G., Kim, Y.W., Jang, J.W. and Liu, M., (2007). Roadmap for lean
implementation at the project level. The Construction Industry Institute.
Ballard, G1 (994) The Last Planner”[ online] Lean Construction Institute. Available
at: http://www.leanconstruction.org/pdf/lastplanner.pdf
Ballard, H. G. (2000), The Last Planner System of Production Control, PhD. Thesis,
University of Birmingham.
Barlow, J. (2000). Innovation and learning in complex offshore construction projects.
Research policy, 29(7), 973-989.
References
304
BEA), Bureau for Economic Analysis, US Department of Commerce, (2014). New
Quarterly Statistics Detail Industries’ Economic Performance. [Online].
Available at:
http://www.bea.gov/newsreleases/industry/gdpindustry/2014/pdf/gdpind413
.pdf [Accessed: 08/05/2015]
Beale, W., Maquet, M., Tua. J., (2007). Resources for Implementing the WWF
Project & Programme Standards [online] Available at
https://intranet.panda.org/documents/folder.cfm?uFolderID=60980.
[Accessed: 15 August 2015]
Beck, K., (2000) Extreme Programming Explained: Embrace Change. Reading, MA:
Addison-Wesley,
Beierle, T and Cayford J. (2002) Democracy in practice: Public participation in
environmental decisions. Washington, D.C.: Resources for the Future.
Berelson, B., (1952). Content analysis in communication research. New York: New
York University Press
Berg, B. (2007). Qualitative research methods for the social sciences (6th ed.;
Pearson International ed.). Boston, Mass.; London: Pearson.
Berg, B. and Lune, H., 2014. Qualitative research methods for social sciences. 8th
Edition. Pearson new international edition; London, UK
Berggren, C. (1993) Lean Production – the end of History? Work, Employment and
Society Vol. 7 (2) pp 163-188
Bernardes, M.M. and Formoso, C.T. (2002), “Contributions to the Evaluation of
Production Planning and Control Systems in Building Companies” in,
Formoso, C.T. and Ballard, G. (Eds.), 10th Annual Conference of the
International Group for Lean Construction, Gramado, Brazil, 6-8 Aug
2002.
Bertelsen, S., Henrich, G., Koskela, L. J., & Rooke, J. A. (2007). Construction
physics. In Proceedings of the 15th Annual Conference of the International
Group for Lean Construction (pp. 13-26)
References
305
Bhaskar, R. (2002). From science to emancipation: alienation and the actuality of
enlightenment. Delhi: Sage
Birrell G S., 1980, Construction Planning - Beyond the Critical Path Journal of
Construction Division ASCE 106 (3) 389-407
BIS, (2013). Supply chain analysis into the construction industry [online] A report
for the construction industry strategy. Available at:
https://www.gov.uk/government/uploads/system/uploads/attachment_data/fi
le/252026/bis-13-1168-supply-chain-analysis-into-the-construction-
industry-report-for-the-construction-industrial-strategy.pdf [Accessed
10/1/2015]
Bisman, J. E. (2002). The critical realist paradigm as an approach to research in
accounting. Poster presentation at the Accounting Association of Australian
and New Zealand Annual Conference, Perth, Australia.
Blaikie, N., (2007). Approaches to Social Enquiry. 2nd edn. Cambridge, UK: Polity
Press.
Blaxter, L., Hughes, C., and Tight, M. (2010). How to research. McGraw-Hill
International.
Bouma, G.D, (2000). The research process. 4th edn. London, Oxford UK : Oxford
University Press
BRE, (2006). “Profiting together from process improvement. Available at:
http://www.bre.co.uk/filelibrary/pdf/CLIP/BRE-
_CLIP_Vol_2_reprint_2006.pdf (accessed 27 March 2016)
Brehmer B (2006) One loop to rule them all. Proceedings of the 11th
International
command and control research and technology symposium, Cambridge, UK
Bresnen, M., Edelman, L., Newell, S., Scarbrough, H. and Swan, J. (2003). Social
practices and the management of knowledge in project environments.
International Journal of Project Management, 21(3), pp.157-166.
Bryman, A. (2012). Social research methods. Oxford university press.
References
306
Burke, R. (2013), Project Managemen : Planning and Control techniques, Wiley,
Chichester.
C
Cain, T. C. (2004), Profitable Partnering for Lean Construction, Blackwell
Publishing, Oxford.
Cambridge Dictionary, (2015). Meaning of a process [online] Available at:
http://dictionary.cambridge.org/dictionary/british/process [Accessed: 20
July 2015]
Cardwell H and Redican, K (2009) Collaborative Planning Toolkit, US Army Corps
of Engineers. [online]. Available at :
http://sharedvisionplanning.us/cptoolkit/Content.asp?ID=1.1
Chan, A. P., & Chan, A. P. (2004). Key performance indicators for measuring
construction success. Benchmarking: an international journal, 11(2), 203-
221.
Chan, D. W., & Kumaraswamy, M. M. (1997). A comparative study of causes of
time overruns in Hong Kong construction projects. International Journal of
Project Management, 15(1), 55-63.
Chee, T. M., Raphael, B., and Pheng, L. S. (2009). Lean Construction Principles and
their Practice in Singapore. Construction Information Quarterly, 11(1), 24-
28.
CIOB Report, (2010). Report exploring procurement in the construction industry
[online]. Available at:
https://www.ciob.org/sites/default/files/CIOB%20research%20-
%20Procurement%20in%20the%20Construction%20Industry%202010_1.p
df. Accessed: 9 June 2016.
Cohenca, D., Laufer, A. and Ledbetter, W.B., 1989. Factors affecting construction
planning efforts. Journal of construction engineering and
management, 115(1), pp.70-89.
Cole, R., Purao, S., Rossi, M., & Sein, M. (2005). Being proactive: where action
research meets design research. ICIS 2005 Proceedings, 27.
References
307
Collins, J., and Hussey, R. (2003). Business Research: a practical guide for
undergraduate and postgraduate students. New York: Palgrave Macmillan.
Common, G., Johansen D.E., Greenwood D. (2000) A survey of the take up of lean
concepts in the UK construction industry, Proc. 8th Ann. Conf. Intl. Group
for Lean Constr. Brighton, 17 - 19 July
Constructing Excellence Report 2007. Realising the Power of Collaborative
Construction Frameworking Agenda.[ online]. Issue 6. Available at:
http://www.constructingexcellence.org.uk/pdf/lgtf/LGTFNY07.pdf
Construction (2025). Industrial Strategy: government and industry in partnership.
[online] Available at:
https://www.gov.uk/government/uploads/system/uploads/attachment_data/fi
le/210099/bis-13-955-construction-2025-industrial-strategy.pdf [Accessed:
18 March 2015]
Construction news, (2015). Top 50 contractors by value of work won. [online]
Available at : http://www.constructionnews.co.uk/data/league-tables/
[Accessed: 12 December 2015].
Construction statistics annual, (2007). [online] Department for business enterprise
and regulatory reforms. Available at:
http://www.bis.gov.uk/files/file42061.pdf [Accessed:23 July 2015]
Conte, A.S.I. (1998). Last Planner, look ahead, planning : A driver to the site
operations. In: 6th Annual Conference of the International Group for Lean
Construction, Guarujá, Brazil, 13-15 August, 1998.
Cooper, D.R., and Schindler, P.S., (2008). Business Research Methods. Tenth
international edition, London: McGraw-Hill Education.
Cough, (2015), Last Planner® System and Touchplan [online] Available at :
http://www.touchplan.io/2015/10/last-planner-system-and-touchplan/#more-
1004
Creswell, J. (2007). Qualitative inquiry and research design: Choosing among five
traditions (2nd ed.). London: SAGE.
References
308
Creswell, J. (2013). Qualitative inquiry and research design: Choosing among five
approaches (3rd ed.). Thousand Oaks: SAGE Publications.
Creswell, J., (2009). Research Design: Quantitative and Qualitative Approach.3rd
edn. London, UK: Sage Publication
Crotty, M. (1998). The foundations of social research [electronic resource]:
Meaning and perspective in the research process. London: SAGE.
Crotty, R. (2012), The Impact of Building Information Modelling: Transforming
Construction, Spon Press, Oxon.
D
Dainty, A.R.J. (2008), “Methodological pluralism in construction management
research”. in Knight, A. and Ruddock (Eds.) , Advanced Research Methods
for the Built Environment, Wiley‐Blackwell, Oxford, pp.1-13
Daniel, E I, Pasquire, C and Dickens, G (2014) Social perspective of planning in
construction: The UK experience In: Raiden, A B and Aboagye-Nimo, E
(Eds) Procs 30th Annual ARCOM Conference, 1-3 September 2014,
Portsmouth, UK, Association of Researchers in onstruction Management,
1355- 1365.
Daniel, E. I, Pasquire, C and Dickens, G (2015). Assessing the Practice and Impact
of Production Planning and Management in UK Construction Based on the
Last Planner® System. In the proc. of 2nd CADBE Doctoral Conference,
Nottingham, UK June 8th & 9th.
Daniel, E. I, Pasquire, C and Dickens, G., (2015a). Assessing the Practice and Impact
of Production Planning and Management in UK Construction Based on the
Last Planner® System. In: Proc. of 2nd CADBE Doctoral Conference,
Nottingham, UK, June 8- 9.
Daniel, E. I., Pasquire, C. and Dickens, G. (2014b), “Social perspective of planning
in construction: The UK experience”, in Raiden, A.B. and Aboagye-Nimo,
E.,(Eds) 30th Annual ARCOM Conference, Portsmouth, UK, 1-3 September
2014, pp. 1355- 1365.
References
309
Daniel, E.I. , Pasquire, C. and Dickens, G. (2015b), “Exploring the implementation
of the Last Planner® System through IGLC community: Twenty one years
of experience” in, Seppänen, O., González, V.A. and Arroyo, P. (Eds.) 23rd
Annual Conference of the International Group for Lean Construction,
Perth, Australia, 29-31 July 2015, pp. 153-162,.
Daniel, E.I., Pasquire, C and Dickens, G. Ballard, G. (2016). The Relationship
between the Last Planner® System and Collaborative Planning Practice in
UK Construction. Engineering Construction and Architectural Management
Journal.
Darrington, J. (2011). Using a design-build contract for lean integrated project
delivery. Lean Construction Journal pp, 85, 91.
Dave, B., Hämäläinen, J-P., and Koskela, L., 2015. Exploring the Recurrent
Problems in the Last Planer Implementation on Construction Projects. In:
Proc. Indian Lean Const. Conference, Mumbai, India, February 6-7.
Dave, B., Pikas, E., Kerosuo, H. and Mäki, T. (2015)b. ViBR–Conceptualising a
virtual big room through the framework of people, processes, and
technology. 8th Nordic Conference on Construction Economics and
Organization, Procedia Economics and Finance, Vol 21, pp.586–593.
Davidoff, P. (1965). Advocacy and pluralism in planning. Journal of the American
Institute of Planners, 31(4), 331-338.
Deming, E.W., (1950). Elementary Principles of the Statistical Control of Quality,
Japanese Union of Scientists and Engineers.
Deming, W. E, (1986) Out of the crisis. Cambridge: Massachusetts Institute of
Technology Press
Denzin, N., & Lincoln, Yvonna S. (2012). Strategies of qualitative inquiry (4th ed.).
Thousand Oaks, Calif. ; London: SAGE.
Dilworth, J.B. (1992) Operations Management: Design, Planning and Control for
Manufacturing and Services McGraw-Hill, New York (1992)
References
310
Do, D., Chen, C., Ballard, G. and Tommelein, I.D. 2014. Target Value Design as a
Method for Controlling Project Cost Overruns. In: Proc. 2nd Ann. Conf. of
the Int’l. Group for Lean Construction. Oslo, Norway, Aug 25-27.
Docherty, P. (1972). The management of Contingencies. Stockholm, Sweden: The
Economic Research Institute.
Dolnicar, S., Gurn, B., Leisch, F.. and Rossiter, J., (2011). Three good reasons NOT
to use five and seven point Likert items. 21st CAUTHE National
Conference.
Dombrowski, U., Zahn, T. and Mielke, T., (2010). Roadmap for the implementation
of Lean Production Systems. In Proceedings of the 5th Americas
International Conference on Production Research, Bogota.
Drysdale, D. (2013). 'Introducing Lean Improvement into the UK Highways Agency
Supply Chain' In:, Formoso, C.T. & Tzortzopoulos, P., 21th Annual
Conference of the International Group for Lean Construction. Fortaleza,
Brazil, 31-2 Aug 2013. pp 1067-1074
Dubois, A., and Gadde, L. E. (2002). Systematic combining: an abductive approach
to case research. Journal of Business Research, 55(7), 553–560.
Dybå, T. and Dingsøyr, T. (2008). Empirical studies of agile software development:
A systematic review. Information and Software Technology, 50(9-10),
pp.833-859.ed., Addison-Wesley, 2004, ISBN 978-0321278654.
E
Easterby-Smith, M., Thorpe, R., and Jackson, P. (2012). Management research.
London: Sage
Egan, J. (1998). Rethinking construction: The report of the construction task force.
DETR, London.
Egan, J. (2002). Accelerating change: a report by the strategic forum for
construction. Rethinking Construction. SF f. Construction, London.
References
311
Eisenhardt, K.M., and Graebner, M.E., (2007). Theory building from cases:
opportunities and challenges. Academy of Management Journal, 50 (1), 25-
32.
Elving, W.J., 2005. The role of communication in organisational change. Corporate
Communications: An International Journal, 10(2), pp.129-138.
Endsley, M., R. (2004). Situation awareness: Progress and directions. A cognitive
approach to situation awareness: Theory, measurement and application,
Endsley, M., R. (1994) Situation awareness in dynamic human decision making:
theory. In: Gilson RD et al (eds) Situation awareness in complex systems:
proceedings of a CAHFA conference. Embry-Riddle Aeronautical
University Press, Dayton Beach, pp 27–58
Erickson, J., Lyytinen, K. and Siau, K. (2005). Agile Modeling, Agile Software
Development, and Extreme Programming. Journal of Database
Management, 16(4), pp.88-100.
Evbuomwan, N.F.O and C.J. Anumba , C.J (1998). An integrated framework for
concurrent life-cycle design and construction. Adv. Eng. Software, 29 (7–9)
(1998), pp. 587–597
F
Faniran, O. O., Oluwoye, J. O. and Lenard, D. (1994a) A conceptual process of
construction planning for meeting client objectives. Journal of Real Estate
and Construction, National University of Singapore, 4(1), 48-57.
Faniran, O. O., Oluwoye, J. O., and Lenard, D. (1997). Application of the lean
production concept to improving the construction planning process. In Proc.
IGLC (Vol. 5).
Fellows, R.F., and Liu, A.M., (2009). Research methods for construction. John Wiley
& Sons. framework for mixed-method evaluation designs. Educational
Evaluation and Policy Analysis, 11, pp. 255-274.
Fernandez-Solis, J. L., Porwal, V., Lavy, S., Shafaat, A., Rybkowski, Z. K., Son, K.,
& Lagoo, N. (2012). Survey of motivations, benefits, and implementation
References
312
challenges of last planner system users. Journal of Construction
Engineering and Management, 139(4), 354-360.
Fiallo, M., and Revelo, V. (2002). Applying the last planner control system to a
construction project: a case study in Quito, Ecuador. In Proceedings of the
10th Annual conference of the International Group for Lean Construction.
Flores, F., (1982). Management and Communication in the Office of the Future, PhD
Dissertation, University of California at Berkeley, p.4
Forbes L.H, Ahmed S.M, and Barcala M. (2002), Adapting Lean Construction
Theory for Practical Application in Developing Countries. Proceedings of
the 1st CIBW107 International Conference: Stellenbosch, South Africa,
Forbes, L. H., and Ahmed, S. M. (2011). Modern construction: lean project
delivery and integrated practices. New York: USA, CRC press Taylor and
Francis group
Formoso, C.T., da Rocha, C.G., Tzortzopoulos-Fazenda, P., Koskela, L., and Tezel,
A., (2012) Design Science Research in Lean Construction: An analysis of
Process and Outcomes.In Proceedings of the 20th Annual Conference of the
International Group for Lean Construction
Formoso, C.T., Tzortzopoulos, P., and Liedtke, R., (2002). A Model for Managing
the Product Development Process in House Building. J. Engr. Const. and
Architectural Management, 9(5-6), pp. 419-432.
Forsberg, Kevin, Mooz, Hal & Cotterman, Howard. 1996. Visualizing Project
Management. John Wiley & Sons, New York. 298 p.
Fugate, Mary & Knapp, Joan. 1998. The Development of Bodies of Knowledge in
the Professions. Appendix B in: Project Management Institute. 1999. The
Future of Project Management. Newtown Square. Pp. 101 – 113.
Fullalove, L.H. 2013, 'Examples of Lean Techniques and Methodology Applied to
Uk Road Schemes' In:, Formoso, C.T. & Tzortzopoulos, P., 21th Annual
Conference of the International Group for Lean Construction. Fortaleza,
Brazil, 31-2 Aug 2013. pp 1057-1066
G
References
313
Gann, D. M. (1996). Construction as a manufacturing process? Similarities and
differences between industrialized housing and car production in Japan.
Construction Management & Economics, 14(5), 437-450.
Ghafari, A., (2015). VPlanner®: The Visual Planning Solution for Lean Project
Gil, N and Ward, D (2011). Leadership in megaprojects and production
management: lessons from the T5 project [online] CID technical report no.
1. Avaialble at:
https://research.mbs.ac.uk/infrastructure/Portals/0/docs/Leadership%20in%2
0Megaprojects%20and%20Production%20Management%20Lessons%20fro
m%20the%20T5%20Project%20CID%20Report%20No1.pdf [Accessed:
14/03/2015]
Gilbreth, Frank B and Gilbreth, L.M. (1922). Process Charts and Their Place in
Management. Mechanical Engineering, Jan., 38 - 41, 70.
González, V., Alarcón, L. F., & Mundaca, F. (2007). Investigating the relationship
between planning reliability and project performance: A case study. In
Proceedings for the 15th Annual Conference of the International Group for
Lean Construction, Michigan, USA (pp. 98-108)
González, V., Alarcón, L. F., Maturana, S., Mundaca, F., and Bustamante, J. A.
(2009). Rational commitment model: Improving planning reliability and
project performance. In Annual Conference on Lean Construction (Vol. 17).
González, V., Alarcón, L.F. and Mundaca, F. (2008a). Investigating the Relationship
between Planning Reliability and Project Performance. Prod. Plan. Control,
19, (5),461-474
González, V.A., Sacks, R., Pavez, I., Poshdar, M., Ben Alon, L. and Priven, V.,
(2015). Interplay of Lean Thinking and Social Dynamics in Construction.
In: Proc. 23rd Ann. Conf. of the Int’l. Group for Lean Construction. Perth,
Australia, July 29-31, 681-690,
Gorse, C. A, Emmitt, S. and Lowis, M. (1999) Problem Solving and Appropriate
Communication Medium. ARCOM 15th Conference, Liverpool John
Moores University, pp.: 511-517.
References
314
Green, S., (1999). “The Missing Arguments of Lean Construction”, Construction
Management and Economics, Vol. 17, No. 2, 1999, pp. 133 – 137.
Green, S., (2002). “The Human Resource Management Implications for Lean
Construction: Critical Perspectives and Conceptual Chasms”, Journal of
Construction Research, Vol. 3, No. 1, pp. 147 – 166.
Green, S., and May, S., (2005). “Lean Construction: Arenas of Enactment, Models of
Diffusion and the meaning of ‘Leanness’”, Building Research and
Information, Vol. 33, No. 6, 2005, pp. 498 – 511.
Greene, J. C., Caracelli, V. J., & Graham, W. F. (1989). Toward a conceptual
framework for mixed-method evaluation designs. Educational evaluation
and policy analysis, 11(3), 255-274.
Grimsley, S. (2014). Frederick Taylor and Scientific Management [online]. Available
at: http://education-portal.com/academy/lesson/frederick-taylor-
theories-principles-contributions-to-management.html [Accessed:
23/10/2015]
Grix, J., (2002). Introducing students to the generic terminology of social research.
Politics, 22 (3), 175-186.
Guba, E. G., and Lincoln, Y. S. (1994). Competing paradigms in qualitative
research. Handbook of qualitative research, 2(163-194).
Guba, E. G., and Lincoln, Y. S. (2005). Paradigmatic controversies, contradictions,
and emerging confluences. In N. K. Denzin & Y. S. Lincoln (Eds.), The
SAGE handbook of qualitative research (3rd ed., pp. 191–215). Thousand
Oaks, CA: SAGE.doi:10.1002/ev.1427
Gunder, Michael ( 2010). "Planning as the ideology of (neoliberal) space." Planning
Theory 298-314.
Gunn, T., M., (2011) Lean Construction and Integrated Project Delivery[Online]
Available at :http://www.slccc.net/documents_pdf/Tim%20Gunn%20-
%20Alberici%20Lean%20Const%20110825.pdf [Accessed: 20 July 2015]
References
315
Gunton, T. I, Day, J C, Williams, P. W. (2003) The role of collaborative planning in
environmental management: The North American experience.
Environments: Journal of interdisciplinary studies, 31(2).
Gunton, Thomas I. (1984) Role of the Professional Planner. Canadian Public
Administration 27(4): 399-417.
H
HA report, (2010). An Introduction to the Collaborative Planning System
[online]. Available at : http://assets.highways.gov.uk/specialist-
information/lean-deployment-
guides/Introduction_to_Collaborative_Planning.pdf [ Accessed:
10/03/2014]
Hackett, V. , Pasquire, C. , Stratton, R. & Knight, A. 2014, 'Use of a Pilot Study to
Assess the Development of Virtual First Run Studies (VFRS)' In:, Kalsaas,
B.T., Koskela, L. & Saurin, T.A., 22nd Annual Conference of the
International Group for Lean Construction. Oslo, Norway, 25-27 Jun 2014.
pp 1331-1341
Hahmann, T., (2006) Software development Process[online] Available at :
http://www.cs.toronto.edu/~torsten/THahmann_CSC444_Tutorial1_SWDev
Processes.pdf [Accessed: 28/04/2015]
Halpin, D. (1993). Process-based research to meet the international challenge. J. of
the Const. Engr. And Mgmt. Div., ASCE, (119) (3) 417-425.
Hamzeh, F. R., Saab, I., Tommelein, I. D. and Ballard, G., (2015). Understanding the
Role of Tasks Anticipated in Lookahead Planning Through Simulation.
Automation in Construction, 49, PP.18-26.
Hamzeh, F. R., Zankoul, E., and Rouhana, C. (2015a). How can ‘tasks made ready’
during lookahead planning impact reliable workflow and project duration?.
Construction Management and Economics, 1-16.
Hamzeh, F., Ballard, G. and Tommelein, I., (2012). Rethinking lookahead planning
to optimize construction workflow. Lean Construction Journal, pp.15-34.
References
316
Hamzeh, F., Tommelein, I. D., Ballard, G., & Kaminsky, P. (2007). Logistics centres
to support project-based production in the construction industry. In
Proceedings of the 15th Annual Conference of the International Group for
Lean Construction pp. 181-191.
Hamzeh, F.R. (2009). Improving Construction Workflow - The Role of Production
Planning and Control. Ph.D Dissertation, University of California,
Berkeley, CA, pp 246.
Hamzeh, F.R., and Bergstrom, E. (2010). “The Lean Transformation: A Framework
for Successful Implementation of the Last Planner System in Construction” ,
Proc. 46th Ann. Int'l Conf. of the Associated Schools of Construction, ASC
46. 07-10 April, Boston, Massachusetts.
Hamzeh, G. Ballard, I.D. Tommelein, Rethinking lookahead planning to optimize
Harper, C. M, (2014). Measuring Project Integration Using Relational Contract
Theory. PhD dissertation, University of Colorado.
Harrington, H.J. (1991) Business process improvement. US: McGraw-Hill
Harris, B. (1967). The limits of science and humanism in planning. Journal of the
American Institute of Planners, 33(5), 324-335.
Hass, K B (2007) The blending of traditional and agile project management. PM
world today, 9(5), 1-8.
Hasseberth,J.(2008). Enabling analysis[online]. Available at:
http://www.synygy.com/private/Magazine/EnablingAnalysis_Synygy_Sum
mer08.pdf
Hay, C. (2002), Political Analysis. A Critical Introduction, Basingstoke: Palgrave
Hayek, F. A. (1945). The use of knowledge in society. The American economic
review, pp. 519-530
Hayes - Roth B, Hayes - Roth F., 1979, A cognitive model of Planning Cognitive
Science, Ablex: New Jersey 3 275-310
Healey, P (2003) Collaborative planning in perspective. Planning theory, 2(2), 101-
123.
References
317
Henn, M., Weinstein, M. and Foard, M.N., (2006). A short introduction to social
research. London: Sage.
Henrich, G., Abbott, C. & Koskela, L. 2006, 'Drivers for Innovation in Production
Management' In 14th Annual Conference of the International Group for
Lean Construction. Santiago, Chile, 1-. pp 533-541
Herrmann, J. W. (Ed.). (2006). Handbook of production scheduling (Vol. 89).
Springer.
Hevner, A., March, S. T., Park, J., and Ram, S. (2004). Design science in information
systems research. MIS quarterly, 28(1), 75-105.
Highsmith, J. and Cockburn, A. (2001). Agile software development: the business of
innovation. Computer, 34(9), pp.120-127.
Highways Agency, (2014). Collaborative lean research projects MoU 2014-
15.[Online] Available at :
http://www.highways.gov.uk/knowledge/projects/collaborative-lean-
research-projects-mou-2014-15/ [Accessed: 25 January 2016]
Hirokawa, R. Y. (1985). Discussion procedures and decision‐making
hyjunjperformance. Human Communication Research, 12(2), 203-224
Hodgkinson, G. P., Whittington R., Johnson G. and Schwarz M. (2006). The Role of
Strategy Workshops in Strategy Development Processes: Formality,
Communication, Co-ordination and Inclusion. Long Range Planning, 39 (5):
479-496.
Hollenbeck, J. R., & Klein, H. J. (1987). Goal commitment and the goal-setting
process: Problems, prospects, and proposals for future research. Journal of
applied psychology, 72(2), 212.
Hopp, W.J., and Spearman, M.L. (2008). Factory Physics, 3rd Ed., McGraw-Hill,
Boston, 720 pp
House of commons, (2008) Business and enterprise committee [Online] construction
Matters: Ninth report of session 2007-08. house of commons, London.
Available at:
http://scholar.google.co.uk/scholar?q=House+of+Commons+Business+and+
References
318
Enterprise+Committee+Construction+matters&btnG=&hl=en&as_sdt=0%2
C5 [Accessed:24 July 2015]
Howell, G. & Ballard, G. 1998, 'Implementing Lean Construction: Understanding
and Action' In:, 6th Annual Conference of the International Group for Lean
Construction. Guarujá, Brazil, 13-15 Aug 1998.
Howell, G., & Ballard, G. (1999). Bringing light to the dark side of lean
construction: a response to Stuart Green. In Proc. 7th Ann. Conf. Intl. Group
for Lean Constr (pp. 33-37).
Howell, G.A. 1999, 'What Is Lean Construction - 1999' In:, 7th Annual Conference
of the International Group for Lean Construction. Berkeley, USA, 26-28 Jul
1999.
Howell, J., (2014). Lean construction. Public Infrastructure Bulletin, 1 (9), pp.5.
Hunter, A. (1979). The Urban Neighbourhood Its Analytical and Social Contexts.
Urban Affairs Review, 14(3), 267-288.
I
Imai, M. (1986) Kaizen: The Key to Japanese Competitive Success, McGraw‐Hill,
New York, NY
J
Jacobs, G. F. (2010). Review of lean construction conference proceedings and
relationship to the Toyota Production System framework (Doctoral
dissertation, Colorado State University).
Jacoby, J., and Matell, M. S. (1971). Three-point Likert scales are good enough.
Journal of Marketing Research, 495-500.
Jaitly, S. (2014). Implementation of quality in an Agile software development
environment to quicken delivery of software based on customer
requirements (Doctoral dissertation, California state University, Dominguez
Hills).
Jang, J.W. and Kim, Y.W. 2008, 'The Relationship Between the Make-Ready
Process and Project Schedule Performance' In:, Tzortzopoulos, P. &
References
319
Kagioglou, M., 16th Annual Conference of the International Group for Lean
Construction. Manchester, UK, 16-18 Jul 2008. pp 647-656
Jensen, E. (2009). Sensemaking in military planning: a methodological study of
command teams. Cognition, Technology & Work, 11(2), 103-118.
Jeong, K. S., Siriwardena, M. L., Amaratunga, R. D. G., Haigh, R. P., & Kagioglou,
M. (2004). Structured process improvement for construction enterprises
(SPICE) level 3:. Industry report
Johansen, E. & Porter, G. 2003, 'An Experience of Introducing Last Planner Into a
Uk Construction Project. In:, 11th Annual Conference of the International
Group for Lean Construction. Virginia, USA, 1-.
Johansen, E. , Porter, G. & Greenwood, D. 2004, 'Implementing Lean: UK Culture
and System Change' In:, Bertelsen, S. & Formoso, C.T., 12th Annual
Conference of the International Group for Lean Construction. Helsingør,
Denmark, 3-5 Aug 2004.
Johansen, E. and Porter, G. (2003), “An Experience of introducing Last Planner into
a UK” Construction,11th Annual Conf. of the International Group for Lean
Construction, Virginia, USA,
Johansen, E., & Walter, L. (2007). Lean construction: Prospects for the German
construction industry. Lean Construction Journal, 3(1), 19-32.
Johansen, E., (1995) Hard or soft: Planning on medium size construction projects. In:
Proceedings 11th Annual ARCOM Conference. Annual Association of
Researchers in Construction Management, Loughborough.
Johansen, E., and Greenwood, D., (1999) Hard, Soft or Lean? Planning in medium
sized construction projects. In: Hughes W, (Ed.), 15th Annual ARCOM
Conference, 15-17 September 1999, Liverpool John Moores University.
Association of Researchers in Construction Management, Vol. 2, 385-394
Johnson, P., & Clark, Murray. (2006). Business and management research
methodologies SAGE library in business and management. London: SAGE.
References
320
Johnson, P., Duberley, J., (2000). Understanding management research An
introduction to epistemology. London ; Thousand Oaks: SAGE
Publications.
Johnston, R.B. & Brennan, M. 1996. Planning or Organizing: the Implications of
Theories of Activity for Management of Operations. Omega, Int. J. Mgmt.
Sc., Vol. 24, No. 4, pp. 367-384.
Johnston, R.B. 1995. Making manufacturing practices tacit: a case study of computer
aided production management and lean production. J. Opl. Res. Soc. 46,
1174-1183.
Joseph, R., (2012). Learning in operational planning. United States Naval Institute.
Proceedings, Volume 138, Issue 1
Junior, J.A. , Scola, A. & Conte, A.S.I. (1998) 'Last Planner as a Site Operations
Tool' In:, 6th Annual Conference of the International Group for Lean
Construction. Guarujá, Brazil, 13-15 Aug 1998.
Juran, J. M. (1992). Juran on quality by design: the new steps for planning quality
into goods and services. Simon and Schuster.
K
Kadefors, A., 2004. Trust in project relationships—inside the black box.
International Journal of Project Management, 22(3), pp.175–182.
Kalsaas, B. J, Koskela, L, Saurin T .A(2014a). Understanding and improving
project based production. Proceedings of the 22nd Conference of the
International Group for Lean Construction, Oslo, Norway.
Kalsaas, B. T. (2012). The last planner system style of planning: its basis in learning
theory. Journal of Engineering, Project, and Production Management, 2(2),
88-100.
Kalsaas, B.T. , Grindheim, I. and Læknes, N. (2014), “Integrated Planning vs. Last
Planner System,” in, Kalsaas, B.T., Koskela, L. and Saurin, T.A., 22nd
Annual Conference of the International Group for Lean Construction, Oslo,
Norway, 25-27 June 2014, pp. 639-650.
References
321
Karim, A. and Arif-Uz-Zaman, K., (2013). A methodology for effective
implementation of lean strategies and its performance evaluation in
manufacturing organizations. Business Process Management Journal, 19(1),
pp.169-196.
Kastalli I. V and Neely, A. (2013). Collaborate to innovate . How business
ecosystems unleash business Value [online]. The Cambridge Service
Alliance. Available at:
http://www.ifm.eng.cam.ac.uk/uploads/Resources/Collaborate_to_Innovate_
-_ecosystems_-_final.pdf [Accessed: 20 May 2016]
Kelley Jr, J. E., and Walker, M. R. (1959) "Critical-path planning and scheduling."
Proc., Papers presented at the December 1-3, 1959, Eastern joint IRE-AIEE-
ACM computer conference, ACM, 160-173.
Khan, S. and Tzortzopoulos , P., (2014) Effects of the Interactions Between LPS and
BIM on Workflow in Two Building Design Projects. In: Proceedings of the
22nd Annual Conference of the International Group for Lean Construction,
Oslo, Norway, pp. 933-944. 4
Khanh, H. D., and Kim, S. Y. (2015). A survey on production planning system in
construction projects based on Last Planner System. KSCE Journal of Civil
Engineering, 1-11.
Kharbanda, O.P. and Pinto, Jeffrey K. 1996. What Made Gertie Gallop: Learning
from Project Failures? Van Nostrand Reinhold. 368 p.
Kim, Y. and Jang, J. (2006). Applying Organizational Hierarchical Constraint
Analysis to Production Planning. In:, 14th Annual Conference of the
International Group for Lean Construction. Santiago, Chile, 1-. pp 371-382
Koch, C., Sage, D., Dainty, A. and Simonsen, R. (2015), "Understanding operations
strategizing in project-based organisations: middle managers’ interaction
and strategy praxis", Engineering Project Organization Journal, Vol.5
No.2-3, pp. 106-117.
Koenigsberg and K.N. McKay (2010) A taxonomy for understanding the origins of
production
References
322
Koskela, L J and Howell, G (2002) The underlying theory of project management is
obsolete. In Proceedings of the PMI Research Conference (pp. 293-302).
PMI
Koskela, L. (1992). Application of the new production philosophy to construction
(No. 72). (Technical Report No. 72, Center for Integrated Facility
Engineering, Department of Civil Engineering). Stanford, CA: Stanford
University
Koskela, L. (1997). Lean production in construction. Lean Construction, 1-9.
Koskela, L. (2000). An exploration towards a production theory and its application
to construction. PhD Dissertation, Helsinki University of Technology.
Koskela, L. (2000). We need a theory of construction. In Berkeley-Stanford
Construction Engineering and Management Workshop: Defining a Research
Agenda for AEC Process/Product Development
Koskela, L. (2008). Which kind of science is construction management?,
proceedings of the 16th IGLC conference, Manchester, UK
Koskela, L. (2011). Lean Construction as a Movement Towards Theory-based
Construction Management.
Koskela, L. , Howell, G. , Pikas, E. & Dave, B. 2014, 'If CPM Is So Bad, Why Have
We Been Using It So Long' In:, Kalsaas, B.T., Koskela, L. & Saurin, T.A.,
22nd Annual Conference of the International Group for Lean Construction.
Oslo, Norway, 25-27 Jun 2014. pp 27-37
Koskela, L. and Ballard, G (2006). Should project management be based on theories
of economics or production?', Building Research and Information, 34 (2) ,
pp. 154-163.
Koskela, L. J. (1999). Management of production in construction: a theoretical view.
In Proceedings of the 7th Annual Conference of the International Group for
Lean Construction. Berkeley, California, USA.
Koskela, L. J. (2004). Making do-the eighth category of waste. In Proceedings of the
12th annual conference of the International Group for Lean Construction.
References
323
Koskela, L. J., Stratton, R., and Koskenvesa, A. (2010). Last planner and critical
chain in construction management: comparative analysis. In Proceedings of
the 18th Annual Conference of the International Group for Lean
Construction (pp. 538-547). National Building Research Institute,
Technion-Israel Institute of Technology.
Koskela, L., & Howell, G. (2002a). The theory of project management: Explanation
to novel methods. In Proceedings 10th Annual Conference on Lean
Construction, IGLC
Koskela, L., Ballard, G., and Tanhuanpaa, V., (1997). Towards Lean Design
Management”. Proceedings of the 5th annual conference of the
International Group for Lean Construction, Gold Coast, Australia.
Koskela, Lauri (1999). Management of production in construction: a theoretical
view. 7th
Conference of the International Group for Lean Construction,
IGLC-7. Berkeley, 26 – 28 July 1999. University of California , pp. 241 -
252.
Krauss, S.E., (2005). Research paradigms and meaning making: A primer. The
Qualitative Report, 10 (4), 758-770.
Kvale, S. (1996). Interviews: An introduction to qualitative research interviewing .
Thousand Oaks, CA: Sage.
L
Latham, M. (1994), Constructing the Team, Final Report on Joint Review of
Procurement and Contractual Agreements in the UK Construction
Industry, HMSO, London.
Laufer, A. and Tucker, R.L., 1987. Is construction project planning really doing its
job? A critical examination of focus, role and process. Construction
Management and Economics, 5(3), pp.243-266.
LCI, (2015) “The Last Planner”, available at:
http://www.leanconstruction.org/training/the-last-planner/ (accessed: 16
February 2015)
References
324
Lead, C., Nelson, G. C., & Bennett, E. (2005). Drivers of change in ecosystem
condition and services. Ecosystems and Human Well-Being: Scenarios:
Findings of the Scenarios Working Group, 2, 173.
Leal, M. and Alarcon, L.F. (2010). Quantifying Impacts of Last Planner™
Implementation in Industrial Mining Projects. In:, Walsh, K. & Alves,
T., 18th Annual Conference of the International Group for Lean
Construction. Haifa, Israel, 14-16 Jul 2010. pp 518-527
Lean Construction Institute, (2005), “Last Planner”, US Patent 3020113, available
from : US Patent and Trademark Office,
http://tmsearch.uspto.gov/bin/showfield?f=doc&state=4806:91112d.2.1
(accessed: 17 December 2015)
Lean Project Consulting, (2005). Assessing the Last Planner System Maturity.
[online] Available at: https://www.google.co.uk/webhp?sourceid=chrome-
instant&ion=1&espv=2&ie=UTF-
8#q=Assessing+the+Last+Planner+System+Maturity. [Accessed: 22
February 2016]
Leedy, P. D., & Ormrod, J. E. (2010). Practical research: Planning and design (9th
ed.). Upper Saddle River, NY: Pearson Merrill Prentice Hall.
Lewis, M. A (2000) Lean Production and sustainable competitive advantage.
International Journal of Operations and production management. Vol
20(8), pp 959-978.
Lichfield, N., Kettle, P., & Whitbread, M. (2013). Evaluation in the Planning
Process: The Urban and Regional Planning Series (Vol. 10). Elsevier.
Liff, S & Posey, P A (2004), Seeing is Believing: How the New Art of Visual
Management Can Boost Performance Throughout Your Organization,
AMACOM, New York.
Liker, J.K. (2004). The Toyota Way: 14 Management Principles from the World’s
Greatest Manufacturer. McGraw-Hill, New York.
References
325
Lim, C., Yu, J. & Kim, C. 2006, 'Implementing PPC in Korea’s Construction
Industry' In:, 14th Annual Conference of the International Group for Lean
Construction. Santiago, Chile, 1-.
Lindblom, Charles E. 1959. The Science of Muddling. Through. Public
Administration Review 19, 1: 79-88
Lindhard, S. and Wandahl, S., (2014). A Lean Framework for Production Control in
Complex and Constrained Construction Projects. In Optimization and
control methods in industrial engineering and construction (pp. 233-257).
Springer Netherlands.
Lindhard, S., and Wandahl, S. (2014a). Scheduling of large, complex, and
constrained construction projects–an exploration of LPS application.
International Journal of Project Organisation and Management, 6(3), 237-
253.
Lindhard, S., and Wandahl, S.(2013). Looking for Improvement in the Last Planner
System: Defining Selection Criteria. In ICCREM @ Construction and
Operation in the Context of Sustainability, 27-35. ASCE.
Liu, M., & Ballard, G. (2008). Improving labour productivity through production
control. In Proceedings 11th Annual Conference of International Group for
Lean Construction.
Liu, Y. (2009), Critical Factors for Managing Project Team Communication at the
construction stage. PhD Thesis. www.lib.polyu.edu.hk ISBN:
9781109493122
Loosemore, M., Dainty A. and Lingard, H. (2003). Managing People in Construction
Projects: Strategic and Operational Approaches, London: Spon Press.
Love, P.E. and Gunasekaran, A., (1996). Towards concurrency and integration in the
construction industry. Advances in Concurrent Engineering: CE96
Proceedings, p.232.
Love, P.E., Holt, G.D. and Li, H., 2002. Triangulation in construction management
research. Engineering Construction and Architectural Management, 9 (4),
294-303.
References
326
Lussier, R. (2011). Management fundamentals: Concepts, applications, skill
development. Cengage Learning.
M
Macneil, I.R., (1980). The new social contract: An inquiry into modern contractual
relations. Yale University Press.
Macomber, H. and Howell, G., (2003). Linguistic action: contributing to the theory
of lean construction. In: Proceedings of the 11th Annual Meeting of the
International Group for Lean Construction, Virginia, USA, pp. 1-10.
Macomber, H., and Howell, G., (2001). Reforming project management: the role of
reliable promising. Lean Construction Institute’s 2001 Implementation
Workshop, Denver, CO
Margerum, R. D. (2002). Collaborative planning building consensus and building a
distinct model for practice. Journal of Planning Education and Research,
21(3), 237-253.
Marks, M. A., Mathieu, J. E., & Zaccaro, S. J. (2001). A temporally based
framework and taxonomy of team processes. Academy of management
review,26(3), 356-376.
Mazziotti, D. F. (1971). Advocacy Planning-toward the Development of Theory and
Strategy. Council of Planning Librarians.
McChrystal, S. A., Gardner, J. D., & McHale, T. P. (1997). Bridging the Competence
Gap: Developing Tactical Leaders for the Army of 2015. ARMY WAR
COLL CARLISLE BARRACKS PA
McConaughy, T. & Shirkey, D. 2013, 'Subcontractor Collaboration and Breakdowns
in Production: The Effects of Varied Lps Implementation ' In:, Formoso,
C.T. & Tzortzopoulos, P., 21th Annual Conference of the International
Group for Lean Construction. Fortaleza, Brazil, 31-2 Aug 2013. pp 649-658
McCrary, S. W., Smith, M. R. R., and Callahan, R. N. 2006. Comparative Analysis
between Manufacturing and Construction Enterprises on the use of
Formalized Quality Management Systems. Journal of Industrial
Technology, 22(3), 1-8.
References
327
McGraw Hill Construction Smart Market Report, 2013. Lean Construction :
Leveraging Collaboration and Advanced Practice to increase Project
Efficiency[Online]. Available at: http://bradleybim.com/2013/11/24/downlo
ad-mcgraw-hill-lean-construction-bim-report-2013/ [Accessed: 14 May
2015]
Michel G. (1991), “The Visual Factory: Building Participation through Shared
Information”, Productivity Press
Michigan State University, (2016). Lean construction light house.[Online]. Available
at: http://www.leanconstruction.msu.edu/ . [Accessed: 10 June 2016]
Miles, M. B., and Huberman, A. M. (1994). Qualitative data analysis. Beverly Hills:
Sage Publications.
Mitchell, K.,(1999) "House and City: An analysis of public and private space in
Plato’s utopian polis". The Nordic Journal of Architecture
Mitchell, W.N., 1939, Organization and Management of Production, McGraw-Hill
Book
Mohd-Zainal, A., Goodyer, J. and Grigg, N., (2011). Zealand manufacturing
companies 2011 3rd International Conference on Information and
Financial Engineering IPEDR vol.12
Mossman, 2005. Last Planner: Collaborative production, collaborative
programming[online] Available at :
http://www.obom.org/DOWNLOADS2/LPSoverview.pdf [Accessed: 10
August 2015]
Mossman, A (2014) Collaborative Planning: 5 + 1crucial and Collaborative
Conversations for Predictable Design & Construction Delivery [online].
Available at. Http://bit.ly/CPS-5cc
Mossman, A (2014) Last Planner: collaborative conversations for predictable design
and construction [online]. Available at:
http://www.academia.edu/1267793/Last_Planner_collaborative_conversatio
ns_for_predictable_design_and_construction_delivery [Accessed: 8
August 2015]
References
328
Mossman, A. (2009). “Why isn’t the UK construction industry going lean with
gusto”?. Lean Construction Journal, Vol. 5 No.1, pp. 24-36.
Mossman, A. (2015). Bringing Lean Construction to Life: Developing Leaders,
Consultants, Coaches, Facilitators, Trainers & Instructors. In:, Seppänen,
O., González, V.A. & Arroyo, P., 23rd Annual Conference of the
International Group for Lean Construction. Perth, Australia, 29-31 Jul
2015. pp 413-423
Munassar, N. M. A., & Govardhan, A. (2010). A comparison between five models of
software engineering. IJCSI, 5, 95-101
Murdick, R.G., B. Render, and R.S. Russell. (1990). Services Operation
Management. Needham
Murray, M D, Tookey, J E, Langford, D A and Hardcastle, C (2000) Project
communication variables: a comparative study of US and UK construction
industry perceptions.
Mustapha F. H., Langford D., 1990, What skills do effective Site Managers bring to
their work Building Economics and Construction Management 4 346-356
Muther, R., 1944, Production-Line Technique, McGraw-Hill Book Company, New
York.
N
Naoum, S.G., (2012). Dissertation research and writing for construction students.
Routledge: London.
Nasir, H., Ahmed, H., Haas, C. and Goodrum, P. (2013), "An analysis of
construction productivity differences between Canada and the United
States", Construction Management and Economics, Vol. 32 No.6, pp. 595-
607.
NATO science committee report, (1968). Software Engineering: NATO scientific
conference, 7th to 11th October Garmisch, Germany,
References
329
Nesensohn, C., Bryde, D. J., Ochieng, E., & Fearon, D. (2014). Maturity and
maturity models in lean construction. Australasian Journal of Construction
Economics and Building, 14(1), 45-59.
Neville, C, (2007) Introduction to Research and Research Methods [online].
Bradford University School of management. Available at :
http://www.brad.ac.uk/management/media/management/els/Introduction-to-
Research-and-Research-Methods.pdf [Accessed: 10 June 2015]
Nottingham Trent University, (2016). Introduction lean construction.[online]
Availabel at:
http://www.ntu.ac.uk/apps/pss/course_finder/1188661/39/introduction_to_le
an_construction.aspx#howtoapply [Accessed: 10 June 2016]
O
Ofori, G. (2001). Challenges Facing Construction Industries in Southern Africa.
Proceedings of Conference on Developing the Construction Industries of
Southern Africa, Pretoria, Southern Africa.
Ogunbiyi, O.E., (2014). Implementation of the lean approach in sustainable
construction: a conceptual framework. PhD thesis , University of Central
Lancashire.
Ohno, T. (1988). Toyota production system : Beyond large-scale production.
Cambridge, Mass.: Productivity Press.
Oliva, C.A. & Granja, A.D. 2013, 'An Investigation Into Collaborative Practices in
Social Housing Projects as a Precondition for Target Value Design
Adoption' In:, Formoso, C.T. & Tzortzopoulos, P., 21th Annual Conference
of the International Group for Lean Construction. Fortaleza, Brazil, 31-2
Aug 2013. pp 429-437
Oluwakiyesi, T., (2011). Construction Industry Report: Haven of Opportunities.
[Online] Available at:
http://www.proshareng.com/admin/upload/reports/VetivResearchConstructi
oSectorReportMay2011.pdf [Accessed: 2/2/2016]
References
330
Othman, A.A.E. (2011). Improving building performance through integrating
constructability in the design process. International Journal of
Organisation, Technology and Management in Construction, Vol. 3, No. 2,
pp. 333-347.
Ould, M. (1995). Business processes : Modelling and analysis for re-engineering and
improvement. Chichester: Wiley.
P
Papke, B. and Dove, R. (2013), “Combating uncertainty in the workflow of systems
engineering projects”, in INCOSE International Symposium, Philadelphia,
pp.24-27.
Parrish, K. (2014).Towards a Language-Action Paradigm - Experiences of a Trade
Contractor' In:, Kalsaas, B.T., Koskela, L. & Saurin, T.A., 22nd Annual
Conference of the International Group for Lean Construction. Oslo,
Norway, 25-27 Jun 2014. pp 1169-1179.
Pasquire, C. & Connor, P. 2011, 'Where does the Theory Informing the International
Group for Lean Construction Come From?' In:, Rooke, J. & Dave, B., 19th
Annual Conference of the International Group for Lean Construction. Lima,
Peru, 13-15 Jul 2011.
Pasquire, C. (2012) “The 8th Flow – Common Understanding” in, Tommelein, I.D.
and Pasquire, C.L., 20th Annual Conference of the International Group for
Lean Construction, San Diego, USA, 18-20 July 2012,
Pasquire, C. , Sarhan, S. & King, A. (2015a), 'A Critical Review of the Safeguarding
Problem in Construction Procurement: Unpicking the Coherent Current
Model' In:, Seppänen, O., González, V.A. & Arroyo, P., 23rd Annual
Conference of the International Group for Lean Construction. Perth,
Australia, 29-31 Jul 2015. pp 309-318
Pasquire, C., Daniel, E., & Dickens, G. (2015) Scoping study on the implementation
of last Planner System, collaborative planning and collaborative working in
the UK road transport sector [online]. A final report research report
prepared for the Highways England by the Centre of Lean Projects,
References
331
Nottingham Trent University. Available at
http://assets.highways.gov.uk/specialist-information/knowledge-
compendium/2014-2015/Snapshot+Final+Report.pdf [Accessed: 18 August
2015]
Pasquire, C.L. and Connolly, G.E., 2002. Leaner Construction through off-site
Manufacturing. Proceedings of the 10th Annual Conference of the
International Group for Lean Construction. Pp.163-176.
Paulhus, D.L. (1991). Measurement and control of response bias. In J.P. Robinson,
P.R.Shaver & L.S. Wrightsman (Eds.), Measures of Personality and Social
Psychological Attitudes
Paulk, M.C., Weber, C.V., Curtis, B. and Chrissis, M.B. (1995), The Capability
Maturity Model: Guidelines for Improving the Software Process, Addison‐
Wesley, MA.
Pavez, I. and Alarcón, L.F., (2006). Qualifying people to support lean construction in
contractor organizations. In Proc. Fourteenth Annual Conference of the
International Group for Lean Construction (pp. 513-524).
Pekuri, A., Pekuri, L. & Haapasalo, H. 2014, 'Lean as a Business Model' In:, Kalsaas,
B.T., Koskela, L. & Saurin, T.A., 22nd Annual Conference of the
International Group for Lean Construction. Oslo, Norway, 25-27 Jun 2014.
pp 51-60
Pheng, L. S., and Tan, S. K. L., (1998). “How `Just-In-Time’ Wastages Can Be
Quantified: Case Study of a Private Condominium Project”, Construction
Management and Economics, 16, (6), pp. 621 – 635.
Picchi, F. and Granja, A. (2004) “Construction sites: using lean principles to seek
broader implementations.” Proceedings of International group of lean
construction, 12th annual conference, Copenhagen, Denmark, August 3-5.
Porwal, V., Fernandez-Solis, J., Lavy, S., & Rybkowski, K. (2010). Last Planner
System Implementation Challenges. In Proceedings of the 18th annual
conference of the International Group for Lean Construction, Haifa, Israel
(pp. 548-556)
References
332
Pressman, R. S. (2005). Software engineering: a practitioner's approach. London:
Palgrave Macmillan:
Priven, V. and Sacks, R., (2015). Effects of the Last Planner System on Social
Networks among Construction Trade Crews. ASCE, Journal of
Construction Engineering and Management, 141(6).
Priven, V. and Sacks, R., (2016). Impacts of the Social Subcontract and Last Planner
System Interventions on the Trade-Crew Workflows of Multi-storey
Residential Construction Projects. Journal of Construction Engineering and
Management.
Project Management Institute (PMI) (2004). A guide to the project management
book of knowledge (PMBOK guide). 3rd ed. Upper Darby, PA: Project
Management Institute
Purcell, J., Kinnie, N., Swart, J., Rayton, B. and Hutchinson, S. (2009) People
Management and Performance. London: Routledge.
R
Rayl, A.J.S. (2008). "NASA Engineers and Scientists-Transforming Dreams Into
Reality"[Online]Available at :. http://www.nasa.gov/index.html [Accessed:
20 May 2015]
Recker, J., (2008). Understanding Process Modelling Grammar Continuance: A
study of the consequences of representational capabilities, PhD Thesis,
Queensland University of Technology, Australia.
Reynold, M., (1999) Last Planner, first results. Report on Last Planner
implementation on Heathrow- T4 Coaching Gate, T1 British Midland, T4
Arrivals Phase 2 and T1 International Arrivals[Online]. Available at:
file:///C:/Users/n0526998/Downloads/Reynolds%252c%20Mark%20(1999)
%20Last%20Planner%252c%20First%20results-%20LPS-
%20In%20Context%20jan%20pp.24-25.pdf [Accessed: 8 August 2015]
Rhodes, C (2014). The construction industry: statistics and policy. House of
Commons Library.
References
333
Rising, L. and Janoff, N. (2000). The Scrum software development process for small
teams. IEEE Softw., 17(4), pp.26-32.
Ritchie, J. and Lewis, J. (2003).Qualitative Research Practice- A Guide for Social
Science Students and Researchers, London: Sage Publications Ltd.
Robson, C. (2002). Real world research: A resource for social scientists and
practitioner-researchers. Oxford, England: Wiley-Blackwell Publication.
Robson, C., (2002). Real World Research: A Resource of Social Scientists and
Practitioners-Researchers. 2nd ed. Blackwell, Oxford
Roger, F., Ury, W., & Patton, B. (1991). Getting to Yes: Negotiating Agreement
Without Giving In.”. Harvard Negotiation Project. Bruce Payton Editor.
Roscoe, E.S., and Freark, D.G., 1971, Organization for Production, fifth edition,
USA: Irwin (Richard D
Ryall, T., Fitzpatrick, S., Parsloe, R., & Morris, J. (2012). Collaborative planning on
the Borough viaduct project, London. In Proceedings of the ICE-Civil
Engineering 165, (5), pp. 45-49). Thomas Telford
S
Sabol, L. (2007). Technology, change, and the building industry. Real Estate Review,
36(3), 87.
Sacks, R., Koskela, L., Dave, B. A., & Owen, R. (2010). Interaction of lean and
building information modeling in construction. Journal of construction
engineering and management, 136(9), 968-980.
Sacks, R., Treckmann, M. and Rozenfeld, O., (2009). Visualization of Work Flow to
Support Lean Construction. ASCE, J. Constr. Eng. Manage., 135(12), pp.
1307- 1315
Salem, O. et al.., 2005. Site Implementation and Assessment of Lean Construction
Techniques. Lean Construction Journal, 2(2), pp.2–21.
Salem, O., Solomon, J., Genaidy, A. and Minkarah, I. (2006), “Lean Construction:
From Theory to Implementation”, Journal of Management in Engineering,
Vol.22 No.4, pp.168-175.
References
334
Samudio, M. , Alves, T.D.C. & Chambers, D. 2011, 'Employing the Principle of
“Going and Seeing” to Construction' In:, Rooke, J. & Dave, B., 19th Annual
Conference of the International Group for Lean Construction. Lima, Peru,
13-15 Jul 2011.
Santos, A., Powell, J.A. and Formoso, C.T. (2000) Setting stretch targets for driving
continuous improvement in construction: analysis of Brazilian and UK
practices, Work Study, 49, 2, pp.·50-
Sarhan, S., & Fox, A. (2013). Barriers to Implementing Lean Construction in the UK
Construction Industry. The Built & Human Environment Review, 6.
Sarshar, M., Haigh, R., & Amaratunga, D. (2004). Improving project processes: best
practice case study. Construction Innovation, 4(2), 69-82.
Saunders, M.N., Saunders, M., Lewis, P. and Thornhill, A., 2011. Research methods
for business students, Pearson Education: India.
Scacchi, W. (2001). Process models in software engineering. in, J.J. Marciniak (ed.),
Encyclopedia of Software Engineering, 2nd
Edition, John Wiley and Sons,
Inc, New York, December 2001.
Schmidt, B. (2011). Improving the Operational Planning Process. Fire Engineering,
164(8), 118-120.
Schneiderjans, M.J., 1993. Topics in Just-in-time Management. Boston. London :
Allyn & Bacon.
Shingo, S. (1988). Non-Stock Production: the Shingo System for Continuous
Improvement. Cambridge : Productivity Press
Schrage, M. (1990). Shared Minds: The New Technologies of Collaboration, , New
York: Random House
Schwaber, K. and Beedle, M. (2002). Agile software development with Scrum.
Upper Saddle River, NJ: Prentice Hall.
Seale, C. (1999). Quality in qualitative research. Qualitative Inquiry, 5(4), 465-478
References
335
Senior, A.B, (2009). Critical Path Method Implementation Drawbacks: A Discussion
Using Action Theory [online] Available at :
http://ascpro0.ascweb.org/archives/cd/2009/paper/CPGT142002009.pdf
[Accessed: 06/06/2015]
Seppänen, O., Ballard, G. and Pesonen, S., (2010). The Combination of Last Planner
System and Location-based Management System. Lean Construction
Journal, 6(1), pp.43-54.
Seymour, D. (1998), 'Getting UK Construction People to Think Lean - Where to
Start? A Case Study' In:, 6th Annual Conference of the International Group
for Lean Construction. Guarujá, Brazil, 13-15 Aug 1998.
Seymour, D., Crook, D., & Rooke, J. (1997). The role of theory in construction
management: a call for debate. Construction Management & Economics,
15(1), 117-119.
Shah, R., & Ward, P. T. (2007). Defining and developing measures of lean
production. Journal of operations management, 25(4), 785-805.
Shang, G.; Pheng, L. S. 2014. The last planner system in China’s construction
industry-a SWOT analysis on implementation, International Journal of
Project Management 32(7): 1260–1272.
Sarshar, M., Haigh, R., Finnemore, M., Aouad, G., Barrett, D., Baldry, D. and
Sexton, M., (2000). SPICE: A business process diagnostics tool for
construction projects, Vol 7, No 3, pp241-250.
Shelbourn, M, Sheriff, A., Bouchlagham, D., El-Hamalawa and Yeomans, S., (2012).
Collaboration Key concepts. In Bouchlaghem, Collaborative working in
construction. London;: Spon Press.
Shelbourn, M., Bouchlaghem, D., Koseoglu, O.O. and Erdogan, B. (2005),
“Collaborative working and its effect on the AEC organisation”,
Proceedings of the International Conference on Computing in Civil
Engineering, Cancun, Mexico, 11‐15 July
References
336
Shewhart, W. A. and Deming, W. E., (1939). Statistical Method from the Viewpoint
of Quality Control. The Graduate School, Department of Agriculture,
Washington.
Shewhart, W.A. 1931. Economic Control of Quality of Manufactured Product. New
York:. Van Nostrand,
Shrader, C. B., Mulford, C. L., & Blackburn, V. L. (1989). Strategic and operational
planning, uncertainty, and performance in small firms. Journal of Small
Business Management, 27(4), 45.
Silver, C., & Lewins, A. (2014). Using Software in Qualitative Research: A step-by-
step Guide (2nd Edition.). London: Sage Publications.
Silver, C., & Woolf, N. H. (2015). From guided-instruction to facilitation of learning:
the development of Five-level QDA as a CAQDAS pedagogy that
explicates the practices of expert users. International Journal of Social
Research Methodology, 18(5), 527-543.
Silverman, D., (2013). Doing qualitative research: A practical handbook. London:
Sage Publications.
Skinnarland, S. (2012) 'Norwegian Project Managers and Foremen’s Experiences of
Collaborative Planning' In:, Tommelein, I.D. & Pasquire, C.L., 20th Annual
Conference of the International Group for Lean Construction. San Diego,
USA, 18-20 Jul 2012.
Smith, A.C., (1994). Joint ventures in the UK construction industry: a critical
examination of the determinants of success and failure. PhD thesis,
Loughborough University.
Smith, J. K. (1983). Quantitative versus qualitative research: An attempt to clarify
the issue. Educational researcher, 12(3), 6-13.
Sporrong, J., and Kadefors, A. (2014). Municipal consultancy procurement: new
roles and practices. Building Research & Information.
Sterzi, M. P., Isatto, E. L., and Formoso, C. T. (2007). Integrating strategic project
supply chain members in production planning and control. In 15th annual
References
337
Conference of the International Group for Lean Construction proceedings,
pp. 159-169.
Stevens J. D., 1993, Techniques for Construction Network Scheduling. New
York :McGraw Hill:
Stewart, R. A., and Spencer, C. A. (2006). Six‐sigma as a strategy for process
improvement on construction projects: a case study. Construction
Management and Economics, 24(4), 339-348.
Stiftel, B. (2000). Planning Theory. The National AICP Examination Preparation
Course Guidebook.
Susskind, L, Mieke van der W, and Armand, C ( 2000). Mediating land use disputes:
Pros and Cons. Cambridge, Mass.: Lincoln Institute of Land Policy.
T
Taylor, F. W. (1939). Scientific management. Critical studies in organization and
bureaucracy,, 44-54.
Taylor, F.W., 1911. The Principles of Scientific Management [online].Available at:
http://www.marxists.org/reference/subject/economics/taylor/principles/ch02
.htm [Accessed: 13/02/2016]
Tezel, A. , Koskela, L.J. , Tzortzopoulos-Fazenda, P. , Formoso, C.T. , Alves, T. ,
Neto, B. , Viana, D. & Mota, B. (2010)., 'Process transparency on
construction sites: examples from construction companies in brazil ' In:,
Walsh, K. & Alves, T., 18th Annual Conference of the International Group
for Lean Construction. Haifa, Israel, 14-16 Jul 2010. pp 296-302
Thomas, M., (2012) Why Aristotle's less authoritarian philosophy is the new spirit of
business [online] Guardian professional business. Available
at :http://www.theguardian.com/sustainable-business/leadership-style-
collective-changing-behaviour [Accessed: 18 August 2015]
Tommelein, I. D., Riley, D. R. and Howell G. A. (1999). Parade Game: Impact of
WorkFlow Variability on Trade Performance. J. Const. Engr. Mgmt.,
ASCE, 125, (5), 304-310.
References
338
Toth, J., Hu, Y.M., Richardson, D., Dowling , C., Spyropoulos, E.,
(2015).Australia’s construction industry: Profile and outlook[online].
Available at :
http://www.aigroup.com.au/portal/binary/com.epicentric.contentmanagemen
t.servlet.ContentDeliveryServlet/LIVE_CONTENT/Economic%2520Indicat
ors/Construction%2520Survey/2015/Construction%2520industry%2520prof
ile%2520and%2520Outlook.pdf [Accessed: 7 June 2016]
Trauner T. J., 1993, Managing the Construction Project: A practical guide for the
Project Manager. London: Wiley
Turner, J. (2006). Towards a theory of project management: The nature of the project
governance and project management. International Journal of Project
Management, 24(2), pp.93-95
Turner, J. Rodney. 1999. Project management: A profession based on knowledge or
faith? (Editorial). International Journal of Project Management, Vol. 17,
No. 6, pp. 329-330.
U
UC Berkeley, (2016). Engineering and project management programme at UC
Berkeley.[online] Available at : http://www.ce.berkeley.edu/programs/epm.
[Accessed: 10 June 2016]
Udom, K., (2013) Improving collaborative construction contracts [ online]
publication of NBS. Available at :
http://www.thenbs.com/topics/contractslaw/articles/Improving-
collaborative-construction-contracts.asp [Accessed: 9/08/2015]
US Bureau for Economic Analysis(BEA), (2014). New Quarterly Statistics Detail
Industries’ Economic Performance. [Online]. Available at :
http://www.bea.gov/newsreleases/industry/gdpindustry/2014/pdf/gdpind413
.pdf [Accessed: 08/08/2014]
V
Van der Aalst, W. M. P., Stoffele, M., & Wamelink, J. W. F. (2003). Case handling
in construction. Automation in Construction, 12(3), 303-320.
References
339
Viana, D. D., Formoso, C. T., & Isatto, E. L.(2011) Modelling the network of
commitments in the Last Planner System. Lean Construction .
Viana, D. D., Mota, B., Formoso, C. T., Echeveste, M., Peixoto, M., and Rodrigues,
C. (2010). A survey on the Last Planner System: Impacts and difficulties for
implementation in Brazilian companies. In Proceedings of the 18th Annual
Conference of the International Group for Lean Construction, 497-507.
W
Weber, R. P. (1985). Basic content analysis. Beverly Hills: Sage Publications
Weick, K. E. (1995). Sensemaking in organizations (Foundations for organizational
science). Thousand Oaks: Sage Publications
Wilkinson, P. (2005). Construction collaboration technologies: the extranet
evolution. London:. Taylor & Francis
Williams, K., Haslam, C., Johal, S., Williams, J., Adcroft, A and Willis, R. (1995)
Management practice or structural factors: the case of America versus Japan
in Car industry. Economic and industrial democracy .16. pp9-37
Winch, G. M (2005) Construction as Production by projects. In S. Kazi (ed):
Learning from Experience: New Challenges, theories and practices in
construction In: proceedings of the CIB joint Symposium, combing forces –
Advancing facilities management and construction through innovation.
VTT Helsinki. Vol. 7 pp. 25-41
Winch, G. M (2006) Towards a theory of construction as production of projects.
Building research and information. 34(2) pp. 164-174
Winch, G.M. (2010) Managing Construction Projects: an Information Processing
Approach, 2nd edition, Chichester: Wiley-Blackwell.
Wirth, N. (1971). Program development by stepwise refinement. Communication of .
ACM, 14(4), pp.221-227.
Wolstenholme, A. (2009). Never waste a good crisis: a review of progress since
Rethinking Construction and thoughts for our future. Constructing
Excellence
References
340
Womack, J. P., & Jones, D. T. (2003). Lean thinking: banish waste and create
wealth in your corporation. London: Simon and Schuster.
Wondolleck, J M, and Steven, L Y (2000). Making Collaboration Work: Lessons
from Innovations in Natural Resource Management. Washington,
D.C:Island Press.
Wu, S., Greenwood, D. and Steel, G., (2008). Exploring the attributes of
collaborative working in construction industry. Northumbria Working Paper
Series: Interdisciplinary Studies in the Built and Virtual Environment, 1(2),
pp.135-147.
X
Xue, X., Shen, Q., & Ren, Z. (2010). Critical review of collaborative working in
construction projects: business environment and human behaviors. Journal
of Management in Engineering, 26(4), 196-208.
Y
Yin, R.K., (2014). Case study research: Design and methods. Sage publications.
Z
Zaghloul, R and Hartman F (2003) Construction contracts: the cost of mistrust.
International Journal of Project Management, 21 (2003), pp. 419–424
Zhang, L., Falzon, L., Davies, M., & Fuss, I. (2000). On relationships between key
concepts of operational level planning. In Proceedings of 5th International
Command and Control Research and Technology Symposium.
Zimina, D., and Pasquire, C., (2012). “The Last Planner System
Insights[online]Available at:
http://www.ntu.ac.uk/research/document_uploads/132937.pdf [Accessed: 20
May 2015]
Zimina, D., Ballard, G. and Pasquire, C. (2012). Target Value Design: Using
Collaboration and a Lean Approach to Reduce Construction Cost.
Construction Management and Economics, 30(5), pp. 383-398.
Appendices
341
APPENDICES
Appendix 1: Sample of Semi –structured interview guide
An Exploratory study on Last Planner System (LPS) and
Collaborative Planning (CP) Practice in the UK Construction
Industry
(Open-ended Interview Guide)
Background information of respondent:
A Planning practices
1. How do you plan and execute work on this project or in your organisation?
2. Could you please describe the key process involved in your planning and
execution process and what do you call this approach?
3. For how long do you plan your work ahead of time and how has it help so
far on this project?
4. How do you measure the reliability of your planning?
B Impact, benefit and drivers of planning approach
5. What do you think has helped in your planning process with other
stakeholders on your project?
6. From your experience what are the major benefits you have achieved from
your planning approach?
7. Based on your experience how has the following construction projects
stakeholders benefited from the approach used in planning and execution of
work? Clients, Contractors, Consultants, Subcontractors and Foremen and
site operatives
8. What other factors do you think could encourage your subcontractors or
supply chain to get commitment to the way you plan and execute your
work?
9. How do you hope to sustain this planning approach in your organisation and
down to your supply chain say tier 3, 4 &5 C
C Barriers
10. Based on your experience what are the barriers have you observed from the
implementation of this planning approach, in term of organisational,
contextual and cultural issues and others; how can they be overcome?
11. How has your procurement methods influenced or affected the use of this
planning approach on this project with other stakeholders? ( e.g.
subcontracting options)
Appendices
342
12. What do you suggest should be done to support your organisation and other
construction organisations such as medium and large construction
organisation in using this approach effectively ( academia, Government,
client, contractors etc)
D Intellectual origins
13. How do you personally learn about this planning approach
14. What motivated your organisation to adopt this planning approach and what
form of support have you received from internal and external consultant in
implementing this planning approach.
15. Which of these describe your planning approach ? Collaborative Planning [ ]
Last Planner System [ ] Critical Path Method [ ] Line of Balance [ ] Gantt
Chart [ ] Takt time Planning [ ] Location based Planning[ ] Others, please
specify………………………………………
For how long have you been using it…………………………….
Appendices
343
Appendix 2: Approval Letter from College Ethical Committee
Appendices
344
Appendix 3: Sample of Interview Invitation/Consent Letter Issued
Invitation to participate in research study
Research Project:
Exploratory study into the use of Last Planner® System and collaborative planning for construction process improvement in the UK
Researcher: Supervisory team: Emmanuel I. Daniel Professor, Christine Pasquire Dr. Graham Dickens You are being invited to take part in a research study. Before you decide, it is important that you
understand why the research is being undertaken and what it involves. Please take time to read
the following information. Ask us if there is anything that is not clear, or if you would like more
information. Finally, take time to decide if you want to take part or not.
Purpose of the study:
The aim of this case study is to gather knowledge for the purpose of understanding how the Last
Planner System and collaborative planning is currently understood and applied in the UK
construction industry and how construction organisations can be supported for successful
implementation. The research will develop a methodology to assist a rapid and successful
implementation of the Last Planner System for construction process improvement. It is expected
that the study will reveal the current LPS and CP practices from across construction organisations
in the UK.
Must I participate?
No. It is up to you to decide whether or not to take part. If you do, you will be asked to sign a
consent form. You are still free to withdraw at any time without giving a reason.
What happens, if I participate? You will be involved in an interview, which will take not more than 45 minutes
The interview may be voice recorded
The results will be used in the creation of the proposed pre-disposition
The data will be treated with anonymity and confidentiality
Are there any risks / benefits involved? There are NO risks or monetary benefit involved in participating in this study.
However, copy of the thesis or a summary of the major findings can be made available. Please
provide an email if interested……………………………………………………………
Will my taking part in the study be kept confidential? All data will be coded and anonymised so that no individual can be identified in future
publications.
Please sign below and retain a copy of this and the consent form and do not hesitate to contact us
if you need further clarification on this. xxxxxxxxxxxxxxxxxxxxxxxxxxx
Yours faithfully,
Emmanuel I Daniel
Doctoral Researcher
Nottingham Trent University
Appendices
345
Appendix 4: Transcribed Interview Sample
Position of interviewee: Programme Manager
Code:
RH= Researcher
SM = interviewee
RH - What are the key issues with construction planning?
SM03 – Generally speaking it is coping with change
RH – How was the planning done on this project?
SM01 – At the initial phase we develop the tender programme with limited
information because of the commercial nature to enable us hit the target price. Very
limited information is required at the tender stage
RH – Do you involve the subcontractor at this stage?
SM – We only consult the key subcontractors. Some time we use preferred
contractors which we did on this project. The programme drawn up at this point is
one man view on how the work would be done. As far as I am concern they is no
wrong or right programme, it is a view. When contract is awarded, when we get the
work we go into detail discussion in the CP session with key subcontractors, material
suppliers, etc. we bring them into a strategically at the early stage. Then they say is
better done this way or perhaps this way
RH - How do you develop the collaborative programme?
SM- We uses the contract programme as the module to work around to develop the
collaborative programme. You could end working in a different sequence. We define
change and the effect of the change in the CP session. We review the programme, the
CP session did not necessarily improve the programme, it might identify some flaws
in the programme which could lead to extension. It is not always good news. It is a
live document and cannot be rigid because of uncertainties. The software monitors
changes. It is very fluid we match reality with the base programme.
RH – Do you plan for entire duration of the project?
SM – No we plan in phases, if we try to do for all you will be there for days. We do
six weeks lookahead. We started with six weeks lookahead, but as things get critical
we went down to 4 weeks lookahead. Now we are doing 2 week lookahead. The
frequency of the meeting or shortness is due to the volume of work.
RH – How do you measure the reliability of your programme?
SM01 – What we do every month we send turn around documents which take a
snapshot of the programme. We record progress on day to day basis. The software
usually pick this up. It shows the actual start and finish date. I can let you have a
copy of the turnaround document. We put progress against what has been proposed
to be achieved, with any comments. Like on this project we are doing very well
above the programme. We measure and report this every month.
Appendices
346
RH – How do you incorporate this into the weekly work plan?
SM 01– The team does the day to day planning at the weekly level, they are aware of
the overall programme. They do their programme to meet it or beat it. I look at the
overall programme and tell the team if they are deviating from it.
RH – How do you define CP?
SM01 – CP introduces lean process into the programme, as good as one can possibly
make it. It takes the whole programme and betters it by working together rather than
individual subcontractors working separately. It makes the programme sleek and as
quick as possible.
RH – what motivate the team into doing CP?
SM – Because 9 out 10 subcontractors would want to be on site as short as possible.
The quicker you finish the job, the quicker you get on your new job. The quicker the
subcontractors complete the job, the more the profit. The lesser time on the project
the lesser risk of financial loss. The subcontractor would want to work efficiently and
effectively while on site. We work together as a team everyone fully integrated.
RH – Is the idea that of the joint venture?
SM – No, it is the client initiative but to be fair outside of the tis project we do some
CP . But, not on grounded scale as this, not as formal as this.
RH – What is your own definition of CP
SM – Is about getting the key players to the room to go through ultimately the
contract programme to look at where conflict are arising in the activities. It brings the
us together as one team. Without CP will have many down time due to conflicts. It
helps to organise and decide activity to deliver the programme. It is an opportunity to
flag up any constraint. We talk on technical issues and design query.
RH - What do you think has made CP to work on this project?
SM – what helped is the formalisation of the CP process on this project, it is not an
ad hoc thing. It is a serious process. It gets everybody’s mind thinking in the right
direction. It helps as the planner to get better insight on how the various teams can
work together so I take that benefit to the next scheme.
Now, the HA are tasking the team to deliver the project 50% ahead of the
programme. The only way that can be achieved is through CP. The idea is not about
the physical building of the job, but CP should be applied to the approval system, the
design also. It should be applied to the system. It would be beneficial for the
subcontractor, main contractor to sit with the designer as [he is] doing the design. It
should be applied to all aspects of the scheme. To me 50% saving can easily come in
if CP is used in the approval system and in the production of the design. The major
saving is in the design.
RH – Challenges of the scheme.
SM – the biggest problem we have got is to have a client who does not know what he
wants, his always changing things. The problem is how to manage those changes. On
this scheme the client has introduced 300 weeks of work, if it is added end to end, it
Appendices
347
will take another four years to build. We have been asked to finish in two months as
addition to the contract time, this is how big an issue it is, that is why CP came in.
It reduces any potential delay.
RH – Benefits of CP
SM – one thing about CP; people are entitled to voice their opinion about safety. A
subcontractor could say hang on a minute, the safety barrier has been removed, we
will not work in such area.
You remember the guy said during the meeting, he can’t do it, the safety guard has
been removed. Safety is a big thing. It gives the benefit to know what is going on
other people’s mind. It is a two way thing.
RH – Who benefits more.
SM – No one benefit more. I think everyone benefits from the process. But the main
contractor may benefit more because their work supersedes other people on the
project. But it is a team thing. Initially, we use to have the client rep in the meeting.
If all the team benefit, it means the whole process benefits.
RH – Is there CPI
SM – it is a mindset thing. The more you talk to each other the more you learn.
People will grow up to see how to improve the process. It is a mindset thing. We
have daily and weekly meetings with the team.
RH - What do see as the challenge to the implementation of the process on this
project?
SM - There are subcontractors employed directly by the client, which we do not pay
but have to manage them. They tend to be stock in the old ways. For example, if we
have an outside 3rd
party employed, the client, this operation originally is 12 weeks,
let’s see if we can do it in a shorter time, they would say no, it is 12 weeks, 12 weeks
must be 12 weeks. Some organisations like working in the old way. The contractors
employed by the client tend to be stock in their own ways.
RH – Do you think CP will work more is it is done by direct labour?
SM – No, if we have people working for us directly, by the nature of who they are,
they would be put to work by our foreman, the foremen will be the one that will be
invited into the CP meeting. The reason we invite much people is because they have
specialist subcontractor. For example, people that put barriers, the drainage,
earthwork are all specialist. If we are to do it all ourselves, we will be master of our
own destiny and there is very little collaboration you can do with yourself. The main
positive feature of the collaboration in my view is that it gives the subcontractors,
anyone else invited the confidence, reassurance that their opinion, views are being
listened to and taken on board. Not you will do it in my own way.
RH - In term of facilitation, do you think the facilitation process has actually helps in
the implementation?
SM – Yes, it is a learning process, when we started, it was a paper more crude and
we use the post-it note, but most time they fall off. We invite too many people in, if
Appendices
348
we feel we should invite representatives only. When we first started, we had outside
facilitators coming in. some of us have received training and we are now doing it on
our own.
We started off with the CP, to me the biggest thing in the CP session is to have the
planner present in the session, because if he is not there he can’t get first-hand
information on what people say. The planner also draws the attention of the team to
what needs to be done on the programme. The other problem with the CP is at the
initial time when we ask the subcontractors, how long will you do this? They will say
no, no, I won’t say it. But with time, they gain confidence in the process and they are
now contributing.
RH – what do you see as the barrier to the process?
SM - …em, one of the biggest things during the CP sessions is people not telling the
truth, you’ve got to be honest with yourself and the rest members of the team. It is no
use to say I will finish that work today while you know you still need 3 or more days.
It is no good to say I will do it next week and you know you have not got men to do
it. This makes mockery of the whole process. People need to be absolutely honest
with themselves and with each other. If people are not telling the truth CP is a
complete waste of time.
RH – How has the procurement method actually helped in the CP process?
SM – As earlier mentioned, we take the view s on our previous project M62, we talk
to a number of subcontractors on the CP. A subcontractor who is not interested in CP
may not be engaged.
The designers are employed by the client and it does not affect the collaborative
planning, we only have liaison meeting with the designer rather than CP to try and
focus on the priority, but it does not help. The best way to control somebody is when
you are paying them. if you are paying somebody, they listen more than when
someone else is paying them. it is not as it used to be initially, they try to listen a bit.
The designers have little appreciation of the commercial implications of what they do
and they don’t do. It is very difficult but we have to manage it.
RH – Client support
SM – So we have several workshops where we have done presentation to members
of staff, the client, the head of the scheme and designers to express their views. To
me it is not the main crux, the main crux is the collaborative planning. The HA
project manager has also supported, without it, we will not be where we are now.
The support of the project manager does help, some project managers use to choose
to stay in the office.
RH – how about training?
SM – Training has helped. It is very difficult to stand out there to hold CP session
without any training. Without the training, the facilitation wouldn’t progress. We
receive both internal and external training sessions.
RH – Does this include the subcontractors?
SM – As far as I am aware, it only involves the internal team. I am not aware of
subcontractors that are invited for the training.
Appendices
349
RH – Do you think it will work differently on a building project?
SM – No, no. All it does is turning it from this way to that way, it is the same
principle. The benefit will still be the same if it is used in house building, in ship
building, highway, aeroplane. It gets everybody working together as a team. It is not
just restricted to linear scheme.
RH – What form of support can be provided for effective implementation?
SM – A facilitator is needed to promote the benefits of collaborative planning.
Internal facilitation of CP session, for the 1-4 sessions, provision of training course
for internal members.
RH – Support from the organisation?
SM – appointment of lean managers to promote the practice across the business.
High profile members of staff to promote the idea. Lean managers, senior
management staff.
RH – What change is required?
SM – You can’t force change on anyone, the best way is to talk to them, explain and
demonstrate the benefits of what you do. For example if I am to be on another
scheme, I would say the benefit of CP is that we were able to do 3 years’ worth of
additional work in 2 months. This is the only way to sell with physical evidence.
RH – How do you hope to sustain the practice?
SM – On some of the schemes, it would be part of the criteria for awarding the
schemes. To sustain is to spread the benefit across the organisation, provision of
training for people to become lean managers.
RH – External factor
SM – The main understanding is the sense of belief that it is achievable, it is the
realistic nature of the approach.
Appendices
350
Appendix 5: Last Planner System Practice Evaluation Instrument
Evaluation Production Planning and Control practices based on the
Last Planner System in the UK
Structured Interview
1. organisation name: Nature of organisation
Tier 1 – 2 – 3 - 4
2. Interviewee Position in organisation
How long in the industry Yrs. of experience- LPS
Production Planning and Control Evaluation Criteria
S/N0 Practices Weighting 1 Planning and control process
standardization
2 Formalized collaborative programming or phase planning
3 Analysis of constraints 4 Programming Workable backlog 5 Analysis of physical flow 6 Detailed specification of task 7 Formalization of short-term planning
(WWP)
8 Formalized Shared decision making process
9 Measurement of programme reliability (PPC)
10 Recording reasons for non-completion of task
11 Formal meeting to take action on reasons for non-completion of task
12 Taking a formal action for early completion task
13 Formal communication of results using visual devices
14 Constant evaluation and learning 15 Use of prototyping or First Run
studies
16 17
Development of workable backlog Lookahead planning
1.0 Full implementation
0.5 Partial implementation
0.0 No evidence of implementation
Appendices
351
Appendix 6: Sample of Case Study Consent Letter Issued
Case Study Consent Form
Research Project:
Exploratory study into the use of Last Planner® System and collaborative
planning for construction process improvement in the UK
Case Study Project:
Relevant data will be collected via:
Documentary evidence
Observation
Interviews
I agree to participate in the study
I understand that my participation is voluntary, that I can choose not to
participate in part or all of the project, and that I can withdraw at any stage of the
project without being penalised or disadvantaged in any way.
I understand that details of the material discussed are confidential and agree not
to disclose any of the information given to any other party.
I agree to the interview being audio recorded for the interviewer’s reference only.
I agree to the use of anonymised quotes in this thesis and other academic
publications
Participant’s name:xxxxxxxxxxxxxxxxx
Signature:xxxxxxxx
Date:xxxxxxxxxxxxxxx
Researcher: Supervisory team:
Emmanuel I Daniel Professor, Christine Pasquire
Doctoral Researcher Dr. Graham Dickens
Nottingham Trent University
Note: This consent form is to be retained by you and the researcher . At the completion of the
research it should be disposed in a secure fashion.
Appendices
352
Appendix 7: Case Study Interview Guide
Project:
An exploratory study into the use of Last Planner® System and collaborative
planning for construction process improvement Target populations and sample
Senior level managers
Middle level managers
Bottom level managers
Underlying philosophy of the study:
The aim of this case study is to gather knowledge for the purpose of understanding how the Last
Planner System and collaborative planning is currently understood and applied in the UK
construction industry and how construction organisations can be supported for successful
implementation. The case study is to enable the researcher obtain information that will aid the
development of a methodology to create a pre-disposition within project teams to enable a rapid
and successful implementation of the Last Planner System for construction process improvement.
It is expected that the study will reveal the current LPS and CP practices from across construction
organisations in the UK.
Section 1:
This section attempts to obtain background information on the organisation and respondents
participating in the study.
Nature of organisation………………………………….. Nature of
project………...…………...................
Position in organisation………………………………….Professional membership
attained…………….
Years of experience in LPS and CP…………………..…Years of experience in
construction…………...
Section 2: Construction planning and the Last Planner System
This section attempts to explore issues with construction planning, and determine how mature the
LPS and CP implementation are in the organisation.
1. Based on your experience, what are the issues with planning in the construction industry?
2. How do you plan and execute work on this project or in your organisation?
3. Can you please describe the key processes involved in your planning and execution of work on
this project and what the approach is called?
4. How long do you plan ahead of time and how has it helped in meeting your targets?
5. How do you measure the reliability of your planning?
6. What is your own definition of CP and the LPS? Do you think they are there to achieve the
same goal on the project?
7. What motivated you or your organisation in adopting LPS and CP, and for how long?
Section 3: Benefits and drivers
This section examines the impacts of LPS and CP on construction process improvement and also
attempts to identify the core drivers for implementing the process.
Appendices
353
8. From your experience, what do you see as the major benefits of using LPS and CP on this
project? How do the following stakeholders benefit from the process? Clients, Contractors,
subcontractors, foremen and site operatives
9. Can you please identify (if any) the construction process improvement (CPI) you have
observed on your projects since the use of LPS and CP?
10. What do you see as the major relationships between LPS and CP implementation and CPI
11. What are the factors that have helped in using this planning approach with other stakeholders
on the project?
12. What do see as the core drivers for implementing LPS and CP in construction?
13. How does LPS and CP facilitation process impact the success of the implementation on this
project? Is continual external facilitation a disadvantage?
Section 4: Barriers and success factors
This section seeks to identify and categorise the barriers and success factors for LPS and CP
implementations.
14. Based on your experience, what are the barriers and challenges observed during
implementation in terms of people, process, organisation, cost, culture, technology etc. How
do you overcome these barriers and challenges?
15. How has the procurement method used on this project contributed to the success or failure of
the implementation process?
16. Based on your experience what are the major success factors you have observed over this
time? Please can you categorise these success factors?
17. What nature of support or training have you and your team received on LPS and CP?
Who are those involved in the training, is this beneficial to the implementation?
How does the site team react to this approach of working? Are they satisfied?
18. Please share your view. Do you think LPS and CP works effectively on road projects than
building? Why?
Section 5: Support for effective implementation
This section explores and seeks to understand factors that support rapid implementation of LPS
and CP for construction organisations.
19. What form of support do you think is required for rapid implementation of the LPS and CP in
construction?
20. Can you please classify these supports? E.g. at organisational level, project level, Client,
contractor, academia, and Government among others
21. What further support do you think should be given to SME’s since 70% of these work
packages are executed by them?
22. Based on your experience, can you suggest some changes that need to be put in place at
organisational level, project level, by the SME contractors and clients to support rapid
implementation?
23. What factors do you think could motivate and sustain this planning approach down the supply
chain?
24. Based on your experience, what do you see as the key enablers for LPS and CP
implementation in construction?
Please add further comments you feel will contribute to the aim of this
study..............................................
Thank you
Appendices
354
Appendix 8: Post Case Study Survey Instrument
Case Study Post Implementation Evaluation Survey Section 1: Background information 1. Nature of organisation: Main contractor [ ] Subcontractor [ ] Client [ ] Others please
specify……… 2. Position in organisation…………………………….
Nature of project……………………………….
3. Years of experience in collaborative planning .…………. Years of experience
construction………
4. Professional body membership
status……………………………………………………………..
Section 2: Specific question on collaborative planning/Last Planner System
Based on your experience on this project kindly indicate your view on the following
based on 5 point Likert scale
S/N0 Collaborative planning practice
Strongly disagree
Disagree
Not sure Agree Strongly agree
1 I have a good understanding of the purpose of collaborative planning on this project?
2 I feel my working practice has changed for better on this project as a result of my involvement in the collaborative planning meetings
3 My understanding of the project has greatly improved as a result of my involvement in the collaborative planning meetings
4 The application of collaborative planning has improved the level of communication among the project stakeholders
Appendices
355
5 The collaborative planning process has improved my trust and confidence in other members of the project team
6 The collaborative planning process has enabled us to be more efficient in our construction processes
7 The collaborative planning process has enabled us to reduce the level of re-work on this project significantly
8 We have observed significant increase in construction process improvement on this project as a result of the collaborative planning process
8 The collaborative planning process has reduced the adversarial relationship on this project
9 Our safety record has improved on this project as a result of the collaborative planning process
10 The collaborative planning process has slowed our progress on this project
11 Collaborative planning process slowed down our progress initially, but speed it up after a while
12 It is time consuming 13 I am yet to see the
value in the collaborative planning process
14 Do you like working in this manner?
2. Who do you think benefit more from the collaborative planning process as implemented on
this project?
Appendices
356
The client [ ] the subcontractor[ ] the main contractor[ ] site workers and supervisors[ ] All the
stakeholders on the project [ ] Others please specify………………………………………..
Please share briefly the reason for your answer in question 2
above…………………………………
………………………………………………………………………………………………………………………
………..
………………………………………………………………………………………………………………………
………..
………………………………………………………………………………………………………………………
………..
3. Based on your experience kindly suggest what is needed or can be done to support the rapid
and successful implementation of collaborative planning on construction projects
………………………………………………………………………………………………………….
………………………………………………………………………………………………………….
…………………………………………………………………………………………………………..
…………………………………………………………………………………………………………..
………………………………………………………………………………………………………….
………………………………………………………………………………………………………….
………………………………………………………………………………………………………….
………………………………………………………………………………………………………….
Please share something of your experience on the use of this new approach on this
project………………….………………………………………………………………………………
…………………………………..
Appendices
357
Appendix 9: Last Planner Path Clearing Approach Evaluation
Survey Guide
Structured and Semi-structured Survey to Evaluate, Refine, and Validate Last Planner System Path Clearing
Approach. (Please note: The LPS is also known as Collaborative Planning (CP) by some practitioners in the United Kingdom)
Overall aim of the proposed approach.
The overall aim of the proposed approach is to guide construction stakeholders (client, main
contractors, and subcontractors) in understanding what needs to be in place for the successful
implementation of LPS/CP and also in sustaining the implementation.
Background of research participants:
1. Background: Academia [ ] Industry [ ]
2. Years of experience in LPS/CP… …… Years of experience in construction……………
3. Country: …………… Highest educational qualification……………………….
Evaluation Question:
Having studied the proposed approach for LPS/CP implementation( attached). Please rate the
following questions regarding the approach on scale of 1 to 4. Indicate your response by
inserting the appropriate number in the box provided and comments as appropriate.
Description of scale: 1 = Very low coverage 2 = Low coverage 3 = High coverage
4 = Very high coverage
4. Based on your experience how would you rate or describe the appropriateness of the three
structural levels identified to be essential areas of focus for LPS/CP implementation in the
proposed approach [ ] N.B: Substructural levels in the proposed approach refers to the
essential phases where the supports required for LPS/CP implementation should be focused.
Please insert comments if any:
5. Based your experience, please rate the level of completeness of the issues considered at
the organisational sub-structural level: [ ]
Please insert comments if any:
6. Based your experience please rate the level of completeness of the issues considered in the
project sub-structural level: [ ]
Please insert comments if any:
7. Based your experience kindly rate the level of completeness of the issues considered in the
external sub-structural level: [ ]
Appendices
358
Please insert comments if any:
8. How easily can the proposed approach be understood (please use the scale below)
[ ] 1= Very difficult to understand 2 = Difficult to understand 3 = Easy to understand
4 = Very easy to understand.
Please insert comments if any:
9. Do you think the proposed approach would in any way support the implementation of
LPS/CP in construction?
Please give reasons for your comment:
10. Do you think the proposed approach could be adopted/adapted in your country?
Please give reasons for your response :
11. Would you recommend the use of this proposed approach for LPS/CP implementation?
Please give reasons for your response:
12. How would you recommend the use of the proposed approach?
Please insert comments:
12. Please suggest further improvements that can be considered in this proposed approach
that aims to guide construction stakeholders (client, main contractors, and subcontractors) in
understanding what needs to be in place for the successful implementation of LPS/CP?
Please insert comments:
Thank you for your contribution to this study.
Appendices
359
Appendix 10: Last Planner System Path Clearing Approach A3 Size
Figure 8.2 Last Planner Path Clearing Approach
Appendices
360
Appendix 11: Last Planner System Path Clearing Approach Industry
Guide
Appendices
361
Appendices
362
Appendices
363
Appendices
364
Appendices
365
Appendices
366
Appendices
367
Appendices
368
Appendices
369
Appendices
370
Appendices
371
Appendices
372
Appendices
373
Appendices
374
Appendices
375
Appendices
376
Appendices
377
Appendices
378