MADRAS SOLAR ENERGY FACILITY—EXHIBIT C
NOVEMBER 2019 PAGE C-i GES0531191410PDX
EXHIBIT C FACILITY LOCATION
OAR 345-021-0010(1)(c)
TABLE OF CONTENTS C.1 MAPS ........................................................................................................................................... C-1
C.2 LOCATION AND DISTURBANCE AREAS .................................................................................. C-1
C.3 RELATION TO OTHER ENERGY GENERATION FACILITIES .................................................. C-2
TABLE
C-1 Permanent and Temporary Disturbance ...................................................................................... C-2
FIGURES
C-1 Facility Layout C-2A Conceptual Site Plan Without Battery Storage C-2B Conceptual Site Plan With Maximum Battery Storage C-3 Other Permitted Energy Generation Facilities
MADRAS SOLAR ENERGY FACILITY—EXHIBIT C
NOVEMBER 2019 PAGE C-1 GES0531191410PDX.
OAR 345-021-0010(1)(c) Information about the location of the proposed facility, including:
C.1 MAPS OAR 345-021-0010(1)(c)(A) A map or maps showing the proposed locations of the energy facility site, all related or supporting facility sites and all areas that might be temporarily disturbed during construction of the facility in relation to major roads, water bodies, cities and towns, important landmarks and topographic features, using a scale of 1 inch = 2000 feet or smaller when necessary to show detail.
Response: Figure C-1 (Facility Layout) shows the proposed location of the Madras Solar Energy Facility (Facility), related or supporting facilities, and permanent and temporary disturbance areas using a scale of 1 inch = 500 feet.
C.2 LOCATION AND DISTURBANCE AREAS OAR 345-021-0010(1)(c)(B) A description of the location of the proposed energy facility site, the proposed site of each related or supporting facility and areas of temporary disturbance, including the total land area (in acres) within the proposed site boundary, the total area of permanent disturbance, and the total area of temporary disturbance. If a proposed pipeline or transmission line is to follow an existing road, pipeline or transmission line, the applicant shall state to which side of the existing road, pipeline or transmission line the proposed facility will run, to the extent this is known.
Response: All Facility components will be located in Jefferson County, Oregon. The Facility site boundary encompasses portions of Sections 030 and 031, in Township 10 South and Range 13 East. The site is located just east of Lake Simtustus, south and west of Willow Creek, and approximately 0.5 mile from the eastern boundary of the Warm Springs Reservation. The Facility components will be located on private land for which Madras PV1, LLC (Applicant) has already negotiated an exclusive, long-term option to lease.
The Facility site boundary covers approximately 284 acres and encompasses the solar modules, 34.5-kilovolt collector lines, power conversion stations, Facility substation, point-of-interconnection switching station, batteries, operations and maintenance enclosure, and service roads, along with security fencing and gates. Construction laydown (also known as staging) areas will be located within the Facility site boundary.
The Facility is proposed with two distinct conceptual site plans showing the proposed general arrangement of buildings, equipment, and structures (see Figures C-2A and C-2B). The difference between the two site plans is the inclusion of a battery storage system. The Facility may be constructed and operate without any battery storage, which is shown in the site plan on Figure C-2A. Alternatively, the Facility may be developed with a battery storage system housed within a maximum of 120 battery storage containers. The maximum battery storage scenario with up to 120 battery storage containers is shown in the site plan on Figure C-2B. The constructed Facility may have an amount of battery storage in between the two scenarios presented on Figures C-2A and C-2B, but not more than the 120 battery storage containers shown on Figure C-2B.
For the purpose of analyzing potential impacts to resources, the Applicant has defined analysis areas based on this site boundary consistent with OAR 345-001-0010(2) and (59). The analysis areas are identified in each relevant Exhibit (for example, in Exhibit J, Wetlands, and Exhibit P, Fish and Wildlife Habitats and Species). The acres potentially impacted within the site boundary during construction and operation are reflected in Table C-1. Figure C-1 shows an area between the solar modules and perimeter fence that will be temporarily disturbed during construction but will not likely contain permanent fixtures, facilities, and equipment. However, this area is included as permanent disturbance to maximize flexibility in final design of the Facility, and is included in the permanent disturbance acreage for solar modules in Table C-1 below. The Applicant requests flexibility in the final orientation of Facility components within the site boundary during final design before the start of construction, provided that the permanently and temporarily disturbed acres outlined in Table C-1 are not exceeded.
The permanently disturbed acres shown in Table C-1 represent impacts during construction that will remain during operations, and the temporarily disturbed acres represent additional impacts
MADRAS SOLAR ENERGY FACILITY—EXHIBIT C
PAGE C-2 NOVEMBER 2019 GES0531191410PDX
during construction. Temporarily disturbed acres will be restored following construction, and permanently disturbed acres will be restored following retirement.
Table C-1. Permanent and Temporary Disturbance
Disturbance Type Permanently Disturbed
(acres)
Temporarily Disturbed
(acres) Total Disturbed
(acres)
Solar modulesa 267.39 0 267.39
Facility substation 0.92 0 0.92
Point of interconnect switching station
0.06 0 0.06
Existing transmission line (Portland General Electric Pelton Dam to Round Butte 230-kV transmission line)b
0 4.78 4.78
O&M enclosure 0.01 0 0.01
Staging and laydown area 0.56 0 0.56
Access road segments 0.77 0.09 0.86
Perimeter fencec 0.47 1.90 2.37
Total 270.18 6.77 276.95
a Solar module blocks assume the entire block will be cleared for construction and therefore permanently disturbed, even though the ground-coverage ratio is only 40.2 percent. This includes all areas for inverters and battery storage. b Disturbance in existing transmission line right-of-way is to account for construction vehicle access to both sides of the right-of-way. c Perimeter fence assumes a permanent disturbance of 1 foot in width and 4 feet in width for temporary disturbance during fence installation.
C.3 RELATION TO OTHER ENERGY GENERATION FACILITIES OAR 345-021-0010(1)(c)(C) For energy generation facilities, a map showing the approximate locations of any other energy generation facilities that are known to the applicant to be permitted at the state or local level within the study area as defined in OAR 345-001-0010 for impacts to public services.
Response: Figure C-3 shows the proposed location of the Facility in relation to other energy generation facilities within 10 miles.
Figures
Figure C-1Facility LayoutApplication for Site CertificateMadras Solar Energy FacilityJefferson County, OR
\\BROOKSIDEFILES\GIS_SHARE\ENBG\00_PROJ\E\ECOPLEXUS\MADRASSOLARPROJECT\MAPS\REPORT\2019\SITECERTIFICATEAPP\C-1_191107.MXD KGRANT1 11/18/2019 6:32:34 PM
Willow Creek
NW
Elk Dr
44°4
0'N 44
°40'
N
LEGENDMadras Solar Energy Facility Site BoundaryExisting Pelton Dam to Round Butte 230-kV Transmission LineExisting RoadSolar Modules, Power Conversion Stations, and Battery Storage(permanent disturbance)Point of Interconnect (permanent disturbance)Existing Transmission Line (temporary disturbance)O&M Enclosure (permanent disturbance)Substation (permanent disturbance)Staging and Laydown Area (permanent disturbance)Access Road (permanent disturbance) Access Road (temporary disturbance)Perimeter Fence (permanent disturbance)Perimeter Fence (temporary disturbance)
Harney County
DeschutesCountyLane County
GilliamCounty
Hood RiverCountyClackamas
County
Washington County
Wasco County
ShermanCounty
MorrowCounty
Marion County
GrantCounty
Crook County
WheelerCounty
Linn County
JeffersonCounty
Oregon
1 inch equals 500 feet
$ Coordinate System: NAD 1983 UTM Zone 10N
VICINITY MAP
Facility Location
0 500 1,000 1,500250Feet
O
H
P
O
H
P
O
H
P
O
H
P
O
H
P
O
H
P
O
H
P
O
H
P
O
H
P
O
H
P
O
H
P
O
H
P
O
H
P
O
H
P
O
H
P
O
H
P
O
H
P
O
H
P
O
H
P
O
H
P
O
H
P
O
H
P
O
H
P
O
H
P
O
H
P
O
H
P
2
3
9
0
2
4
0
0
2
3
7
0
2
3
8
0
2250
2
3
0
0
2
3
5
0
2
3
7
0
2380
2
3
8
0
2350
2
3
0
0
2
2
5
0
2
2
0
0
2150
2410
2
3
0
0
2
3
5
0
2
3
7
0
2
3
8
0
2
3
9
0
2
4
0
0
2410
2
4
0
0
2
4
1
0
2
3
5
0
2
3
0
0
2
2
5
0
2
2
0
0
2
1
5
0
2
1
0
0
2
0
5
0
2
0
0
0
1
9
5
0
1
9
0
0
1
8
0
01
7
5
01
7
0
0
1
6
7
0
2
3
8
0
2
3
9
0
2390
2
3
7
0
2
3
8
0
2350 2300 2250
2200
2150
2100
2050
2000
1
9
5
0
1
9
0
0
1
8
5
0
2
3
5
0
2
3
0
0
2250
2200
2150
2100
2050
2000
1950
1
9
0
0
1850
23
80
2
3
9
0
2
4
0
0
2
3
9
0
LINE BEARING DISTANCE
L1 N82°39'27"W 82.82'
L2 N40°53'32"W 112.34'
L3 N64°39'02"W 121.89'
L4 N78°31'42"W 409.74'
L5 N00°54'57"E 765.34'
L6 S00°42'40"W 1105.30'
CURVE RADIUS ARC DELTA CHORD BEARING
C1 500.00' 364.47' 41°45'55" 356.45' S61°46'29"E
C2 250.00' 103.67' 23°45'30" 102.92' N52°46'17"W
C3 250.00' 60.55' 13°52'40" 60.41' S71°35'22"E
C4 250.00' 346.64' 79°26'39" 319.53' N38°48'22"W
L7 N89°18'07"W 162.54'
L8 S25°26'39"W 297.31'
L9 N89°18'07"W 164.97'
L10 S25°27'51"W 227.13'
File
: G
:\M
y D
rive
\P
ro
je
cts\O
RE
GO
N\0
4 P
ro
je
cts\M
ad
ra
s P
V1
\0
2 D
esig
n\C
ivil\C
AD
\M
ad
ra
s P
V1
- C
on
ce
pt P
la
n L
eve
l C
P
V o
nly - 1
91
00
8.d
wg
, L
ayo
ut: E
CO
P, B
y: B
en
, P
lo
tte
d: T
ue
O
ct 0
8, 2
01
9 a
t 3
:5
3p
m, X
RE
Fs U
se
d: , IM
AG
ES
U
se
d:
RE
VD
AT
ED
ES
CR
IP
TIO
N
THIS DRAWING IS THE PROPERTY OF ECOPLEXUS, LLC. THIS INFORMATION IS
CONFIDENTIAL AND IS TO BE USED ONLY IN CONNECTION WITH WORK DESCRIBED
BY ECOPLEXUS, LLC. NO PART IS TO BE DISCLOSED TO OTHERS OR REPRODUCED
WITHOUT WRITTEN PERMISSION FROM ECOPLEXUS, INC. OR ITS SUBSIDIARIES.
PRELIMINARY
DO NOT USE
FOR
CONSTRUCTION
EC
OP
LEX
US
, In
c.
10
1 S
eco
nd
S
treet, S
te. 1
25
0
San
Fran
cisco
, C
A 9
41
05
Ph
: 4
15
-6
29
-1
80
2
Fx: 4
15
-4
49
-3
46
6
JH
NR
PV1.1
BAB
BAB
1" = 300'
10/01/2019
MA
DR
AS
P
V1
JE
FF
ER
SO
N C
OU
NT
Y
OR
EG
ON
A07/03/2019
IN
IT
IA
L LA
YO
UT
150'
SCALE: 1" = 300'
300' 0 300'
MODULE:
QUANTITY:
INVERTER:
QUANTITY:
MOUNTING SYSTEM:
MOUNTING SYSTEM TYPE:
SYSTEM SIZE (DC):
SYSTEM SIZE (AC):
UTILIZED AREA:
HANWHA Q.PEAK DUO L-G5.2 400
177,498
SMA SUNNY CENTRAL 4000-UP-US
19
TBD
SINGLE AXIS TRACKING, 60° TILT, 90° AZIMUTH, 40.2% GCR
71.0 MW
63.0 MW
274.9 ACRES
PROJECT NAME:
PROJECT ADDRESS:
DEVELOPER NAME:
DEVELOPER ADDRESS:
MADRAS PV1
LAT.: 44.65°, LON.:-121.25°
ECOPLEXUS
101 2ND ST., STE. 1250, SAN FRANCISCO, CA 94105
GENERAL PROJECT INFORMATION
GENERAL SYSTEM INFORMATION
CITY
OF
MADRAS
AIRPORT
NW BIRCH
LANE
NW
E
LK
D
RIV
E
SW BELMONT
LANE
H
W
Y
9
7
H
W
Y
2
6
H
W
Y
9
7
H
W
Y
2
6
W
IL
L
O
W
C
R
E
E
K
OHP OHP OHP OHP OHP
SECTION OR SECTION SUBDIVISION LINE
PARCEL BOUNDARY
ROADWAY CENTERLINE
RIGHT OF WAY BOUNDARY
EASEMENT BOUNDARY
EXISTING FENCE LINE
OVERHEAD POWER LINE
EDGE OF ASPHALT ROAD
EDGE OF DIRT ROAD
ONSITE STREAM DETERMINED BY OTHERS
10-FOOT CONTOUR LINE
100-FOOT CONTOUR LINE
UTILITY POLE
FOUND MONUMENT AS NOTED
VICINITY MAP
NOT TO SCALE
LEGEND & SYMBOLS
SOLAR PV MODULE:
TRACKER TABLE (STOWED):
TRANSFORMER PAD:
SUBSTATION:
GENERATOR TIE LINES:
O & M BUILDING:
1960 x 991 x 40 mm, 22.5 kg
1960 mm WIDE, 4.5 FT TALL, UP TO 400 FT LONG
20 x 40 x 10FT TALL MAXIMUM DIMENSIONS
300 x 300 FT MAXIMUM DIMENSIONS
HEIGHT WILL COMPLY WITH LOCAL CODES
HEIGHT WILL COMPLY WITH LOCAL CODES
1 DRY STORAGE BUILDING 8 x 40 x 8.5 FT HIGH
DESIGN BASIS DIMENSIONS
20' WD. GRAVEL
ACCESS ROAD
24' WD. ACCESS
GATE
NEW CHAINLINK FENCE (TYP.)
30'
24' WD. ACCESS
GATE
24' WD. ACCESS
GATE
NOTE:
THIS MAP OR PLAT AND THE SURVEY PROVIDED BY PBS
ENGINEERING AND ENVIRONMENTAL INC., BY GREG E. FLOWERS, ON
WHICH IT IS BASED WERE MADE IN ACCORDANCE WITH THE 2016
MINIMUM STANDARD DETAIL REQUIREMENTS FOR ALTA/NSPS LAND
TITLE SURVEYS, JOINTLY ESTABLISHED AND ADOPTED BY ALTA AND
NSPS, AND INCLUDES ITEMS 2, 3, 4, 5, 8, 9, 11, 13, 18, AND 20 OF
TABLE A THEREOF. THE FIELD WORK WAS BEGUN ON OCTOBER 25,
2018, AND CONCLUDED ON NOVEMBER 7, 2018. DATE OF PLAT OR
MAP: FEBRUARY 1, 2019
PROPOSED SUBSTATION
LOCATION (200'x200')
INVERTER LOCATIONS
(INV: 15'X30')
O&M TRAILER
(8'X40')
30' SLOPE
SETBACK (TYP)
30' PROPERTY
SETBACK (TYP)
PROPOSED SUBSTATION
ACCESS RD (24' WIDE,
50' RADIUS, TYP)
24' WD. ACCESS
GATE
B07/19/2019
SE
TB
AC
K A
ND
A
CC
ES
S R
OA
D R
EV
C07/23/2019
60' R
OA
D S
ET
BA
CK
,A
DD
ED
R
AC
KS
60' ROAD R/W
SETBACK (TYP.)
POI SWITCHING
STATION (50'x50')
STAGING AND
LAYDOWN AREA
D07/31/2019
MO
VE
D S
UB
LO
CA
TIO
N &
A
CC
ES
S R
D
EXISTING FENCE TO BE
REMOVED AS NEEDED
FIG
UR
E C
-2A
CONCEPTUAL SITE PLAN WITHOUT BATTERY STORAGE
O
H
P
O
H
P
O
H
P
O
H
P
O
H
P
O
H
P
O
H
P
O
H
P
O
H
P
O
H
P
O
H
P
O
H
P
O
H
P
O
H
P
O
H
P
O
H
P
O
H
P
O
H
P
O
H
P
O
H
P
O
H
P
O
H
P
O
H
P
O
H
P
O
H
P
O
H
P
LINE BEARING DISTANCE
L1 N82°39'27"W 82.82'
L2 N40°53'32"W 112.34'
L3 N64°39'02"W 121.89'
L4 N78°31'42"W 409.74'
L5 N00°54'57"E 765.34'
L6 S00°42'40"W 1105.30'
CURVE RADIUS ARC DELTA CHORD BEARING
C1 500.00' 364.47' 41°45'55" 356.45' S61°46'29"E
C2 250.00' 103.67' 23°45'30" 102.92' N52°46'17"W
C3 250.00' 60.55' 13°52'40" 60.41' S71°35'22"E
C4 250.00' 346.64' 79°26'39" 319.53' N38°48'22"W
L7 N89°18'07"W 162.54'
L8 S25°26'39"W 297.31'
L9 N89°18'07"W 164.97'
L10S25°27'51"W
227.13'
File
: G
:\M
y D
rive
\P
ro
je
cts\O
RE
GO
N\0
4 P
ro
je
cts\M
ad
ra
s P
V1
\0
2 D
esig
n\C
ivil\C
AD
\M
ad
ra
s P
V1
- C
on
ce
pt P
la
n L
eve
l C
P
V +
S
TO
RA
GE
- 1
91
00
8.d
wg
, L
ayo
ut: E
CO
P, B
y: B
en
, P
lo
tte
d: T
ue
O
ct 0
8, 2
01
9 a
t 4
:0
1p
m, X
RE
Fs U
se
d: , IM
AG
ES
U
se
d:
RE
VD
AT
ED
ES
CR
IP
TIO
N
THIS DRAWING IS THE PROPERTY OF ECOPLEXUS, LLC. THIS INFORMATION IS
CONFIDENTIAL AND IS TO BE USED ONLY IN CONNECTION WITH WORK DESCRIBED
BY ECOPLEXUS, LLC. NO PART IS TO BE DISCLOSED TO OTHERS OR REPRODUCED
WITHOUT WRITTEN PERMISSION FROM ECOPLEXUS, INC. OR ITS SUBSIDIARIES.
PRELIMINARY
DO NOT USE
FOR
CONSTRUCTION
EC
OP
LEX
US
, In
c.
10
1 S
eco
nd
S
treet, S
te. 1
25
0
San
Fran
cisco
, C
A 9
41
05
Ph
: 4
15
-6
29
-1
80
2
Fx: 4
15
-4
49
-3
46
6
JH
NR
PV1.1
BAB
BAB
1" = 300'
10/1/2019
MA
DR
AS
P
V1
JE
FF
ER
SO
N C
OU
NT
Y
OR
EG
ON
A0
7/0
3/2
01
9IN
IT
IA
L L
AY
OU
T
150'
SCALE: 1" = 300'
300' 0 300'
MODULE:
QUANTITY:
INVERTER:
QUANTITY:
MOUNTING SYSTEM:
MOUNTING SYSTEM TYPE:
SYSTEM SIZE (DC):
SYSTEM SIZE (AC):
UTILIZED AREA:
HANWHA Q.PEAK DUO L-G5.2 400
175,446
SMA SUNNY CENTRAL 4000-UP-US
19
TBD
SINGLE AXIS TRACKING, 60° TILT, 90° AZIMUTH, 40.2% GCR
70.2 MW
63.0 MW
274.9 ACRES
PROJECT NAME:
PROJECT ADDRESS:
DEVELOPER NAME:
DEVELOPER ADDRESS:
MADRAS PV1
LAT.: 44.65°, LON.:-121.25°
ECOPLEXUS
101 2ND ST., STE. 1250, SAN FRANCISCO, CA 94105
GENERAL PROJECT INFORMATION
GENERAL SYSTEM INFORMATION
CITY
OF
MADRAS
AIRPORT
NW BIRCH
LANE
NW
E
LK
D
RIV
E
SW BELMONT
LANE
H
W
Y
9
7
H
W
Y
2
6
H
W
Y
9
7
H
W
Y
2
6
W
IL
L
O
W
C
R
E
E
K
OHP OHP OHP OHP OHP
SECTION OR SECTION SUBDIVISION LINE
PARCEL BOUNDARY
ROADWAY CENTERLINE
RIGHT OF WAY BOUNDARY
EASEMENT BOUNDARY
EXISTING FENCE LINE
OVERHEAD POWER LINE
EDGE OF ASPHALT ROAD
EDGE OF DIRT ROAD
ONSITE STREAM DETERMINED BY OTHERS
10-FOOT CONTOUR LINE
100-FOOT CONTOUR LINE
UTILITY POLE
FOUND MONUMENT AS NOTED
VICINITY MAP
NOT TO SCALE
LEGEND & SYMBOLS
SOLAR PV MODULE:
TRACKER TABLE (STOWED):
TRANSFORMER PAD:
BATTERY CONTAINER:
SUBSTATION:
GENERATOR TIE LINES:
O & M BUILDING:
1960 x 991 x 40 mm, 22.5 kg
1960 mm WIDE, 4.5 FT TALL, UP TO 400 FT LONG
20 x 40 x 10FT TALL MAXIMUM DIMENSIONS
8 x 40 x 9.5FT TALL MAXIMUM DIMENSIONS
300 x 300 FT MAXIMUM DIMENSIONS
HEIGHT WILL COMPLY WITH LOCAL CODES
HEIGHT WILL COMPLY WITH LOCAL CODES
1 DRY STORAGE BUILDING 8 x 40 x 8.5 FT HIGH
DESIGN BASIS DIMENSIONS
20' WD. GRAVEL
ACCESS ROAD
24' WD. ACCESS
GATE
NEW CHAINLINK FENCE (TYP.)
30'
24' WD. ACCESS
GATE
24' WD. ACCESS
GATE
NOTE:
THIS MAP OR PLAT AND THE SURVEY PROVIDED BY PBS
ENGINEERING AND ENVIRONMENTAL INC., BY GREG E. FLOWERS, ON
WHICH IT IS BASED WERE MADE IN ACCORDANCE WITH THE 2016
MINIMUM STANDARD DETAIL REQUIREMENTS FOR ALTA/NSPS LAND
TITLE SURVEYS, JOINTLY ESTABLISHED AND ADOPTED BY ALTA AND
NSPS, AND INCLUDES ITEMS 2, 3, 4, 5, 8, 9, 11, 13, 18, AND 20 OF
TABLE A THEREOF. THE FIELD WORK WAS BEGUN ON OCTOBER 25,
2018, AND CONCLUDED ON NOVEMBER 7, 2018. DATE OF PLAT OR
MAP: FEBRUARY 1, 2019
PROPOSED SUBSTATION
LOCATION (200'x200')
INVERTER AND
BATTERY LOCATIONS
(INV: 15'X30'; BATT:8'X40')
O&M TRAILER
(8'X40')
30' SLOPE
SETBACK (TYP)
30' PROPERTY
SETBACK (TYP)
PROPOSED SUBSTATION
ACCESS RD (24' WIDE,
50' RADIUS, TYP)
24' WD. ACCESS
GATE
B0
7/1
9/2
01
9S
ET
BA
CK
A
ND
A
CC
ES
S R
OA
D R
EV
C0
7/2
3/2
01
96
0' R
OA
D S
ET
BA
CK
,A
DD
ED
R
AC
KS
60' ROAD R/W
SETBACK (TYP.)
POI SWITCHING
STATION (50'x50')
STAGING AND
LAYDOWN AREA
D0
7/3
1/2
01
9M
OV
ED
S
UB
L
OC
AT
IO
N &
A
CC
ES
S R
D
E0
8/2
7/2
01
9A
DD
ED
B
AT
TE
RY
B
AN
KS
EXISTING FENCE TO BE
REMOVED AS NEEDED
7-CONTAINER PAD
6-CONTAINER PAD FIG
UR
E C
-2B
CONCEPTUAL SITE PLAN WITH MAXIMUM
BATTERY STORAGE
Figure C-3Other Permitted Energy Generation FacilitiesApplication for Site CertificateMadras Solar Energy FacilityJefferson County, OR
\\BROOKSIDEFILES\GIS_SHARE\ENBG\00_PROJ\E\ECOPLEXUS\MADRASSOLARPROJECT\MAPS\REPORT\2019\SITECERTIFICATEAPP\C-3_OTHERPERMITTEDENERGYGENFAC.MXD KGRANT1 9/26/2019 4:25:48 PM
!
")
")
")
") The
Dalle
s-Ca
liforn
ia H
wy
NW W
arm Springs Hwy
SW C
ulve
r Hwy
Hw
y 97
SW U
S H
wy 9
7
Madras
Hw
y
SEUS
Hwy26
Sta
teH
wy
361
US H
wy 9
7
US Hwy 26
LakeBilly
Chinook
PeltonRegulatingReservoir
LakeSimtustus
Madras MuniAirport
Crooked RiverNational
Grassland
DeschutesNationalForest
CULVER
MADRAS
METOLIUS
Croo
kedRiv
era n
d Nort
h Fork
Deschutes Riv e r
Desch
utes R
iver
Metolius River
RoundButte Dam
Pelton Dam
Elbe SolarCenter
Adams SolarCenter
121°0'W
121°0'W
121°10'W
121°10'W
121°20'W
121°20'W44
°40'
N 44°4
0'N
0 2 41
Miles
LEGENDMadras Solar Energy Facility SiteBoundaryScenic and Aesthetic Resources andPublic Services Areas (10-mile)
") Energy Generation FacilityCity of Madras City LimitsUrban Growth BoundaryMajor HighwayExisting RoadWatercourseWaterbody
! Airport/HeliportNational ForestNational Grassland
Harney County
DeschutesCountyLane County
GilliamCounty
Hood RiverCountyClackamas
County
Washington County
Wasco County
ShermanCounty
MorrowCounty
Marion County
GrantCounty
Crook County
WheelerCounty
Linn County
JeffersonCounty
Oregon
1 inch equals 2.16 miles
$Coordinate System: NAD 1983 UTM Zone 10NData Sources: Site Boundary, City Limits, UrbanGrowth Boundary: Jefferson County 2018; NationalForest/Grassland: US Forest Service 2013;National Wilderness Area: Wilderness Connect;ESRI ArcGIS online; Airport: US Dept ofTransportation;
VICINITY MAP
Facility Location