42
CHINA: SICHUAN AND CHONGQING COOPERATIONGUANG’AN DEMONSTRATION AREA INFRASTRUCTURE DEVELOPMENT PROJECT ENVIRONMENTAL ASSESSMENT Executive Summary AUGUST 2014 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized

Executive Summary - World Bank...2014/10/13  · Zone (ETDZ) to be developed. Current land use is mainly farmland Sewage interceptor Two sewage interceptor pipelines (13.066km , DN400‐DN1200)

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

  • CHINA:SICHUANANDCHONGQINGCOOPERATION‐

    GUANG’ANDEMONSTRATIONAREAINFRASTRUCTUREDEVELOPMENTPROJECT

    ENVIRONMENTALASSESSMENTExecutiveSummary

    AUGUST2014

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    wb20439Typewritten Text91345

  • China:SichuanandChongqingCooperation:Guang’anDemonstrationAreaInfrastructureDevelopmentProject

    - 2 -

    TABLEOFCONTENTS1.  INTRODUCTION ......................................................................................................................................‐ 3 ‐ 

    2.  PROJECT DESCRIPTION ...........................................................................................................................‐ 4 ‐ 

    3.  REGULATORY AND LEGAL FRAMEWORK ............................................................................................... ‐ 10 ‐ 

    4.  ENVIRONMENTAL AND SOCIAL BASELINES ........................................................................................... ‐ 12 ‐ 

    4.1  NATURALENVIRONMENT ........................................................................................................................ ‐ 12 ‐ 4.2  SOCIO‐ECONOMICCONTEXT .................................................................................................................... ‐ 14 ‐ 4.3  ENVIRONMENTALLYANDSOCIALLYSENSITIVESITES ............................................................................... ‐ 15 ‐ 4.4  AMBIENTENVIRONMENTALQUALITY ...................................................................................................... ‐ 16 ‐ 4.5  EXISTINGENVIRONMENTALINFRASTRUCTURES ....................................................................................... ‐ 17 ‐ 

    5.  ANALYSIS OF ALTERNATIVES ................................................................................................................ ‐ 19 ‐ 

    5.1  WITH/WITHOUTPROJECT ..................................................................................................................... ‐ 19 ‐ 5.2  ALTERNATIVEANALYSISOFNO.3WWTPINLINSHUI ............................................................................ ‐ 19 ‐ 5.3  ALTERNATIVESOFROADPROJECTS ........................................................................................................ ‐ 20 ‐ 5.4  ALTERNATIVESOFSEWAGEINTERCEPTORPIPELINEINLINSHUI .............................................................. ‐ 21 ‐ 

    6.  ASSESSMENT OF IMPACTS AND MITIGATION MEASURES ...................................................................... ‐ 22 ‐ 

    6.1  IMPACTSDURINGCONSTRUCTIONSTAGE ................................................................................................. ‐ 22 ‐ 6.1.1ImpactsofLandAcquisitionandResettlement ............................................................................ ‐ 22 ‐ 6.1.2ImpactsonPhysicalCulturalResources ....................................................................................... ‐ 23 ‐ 6.1.3TrafficandCommunityDisturbance ............................................................................................. ‐ 24 ‐ 6.1.4ImpactonEcologicalEnvironment ................................................................................................ ‐ 24 ‐ 6.1.5ImpactsofNoise ................................................................................................................................ ‐ 25 ‐ 6.1.6ImpactsofDust ................................................................................................................................. ‐ 26 ‐ 6.1.7ImpactsofWastewater .................................................................................................................... ‐ 26 ‐ 6.1.8ImpactsofGroundwater .................................................................................................................. ‐ 27 ‐ 6.1.9ImpactsofSolidWaste ..................................................................................................................... ‐ 27 ‐ 

    6.2  IMPACTSDURINGOPERATIONSTAGE ...................................................................................................... ‐ 27 ‐ 6.2.1NoiseImpact ...................................................................................................................................... ‐ 27 ‐ 6.2.2ImpactsonAirQuality ..................................................................................................................... ‐ 28 ‐ 6.2.3ImpactsonSurfaceWater ............................................................................................................... ‐ 28 ‐ 6.2.4ImpactsonGroundwater ................................................................................................................. ‐ 29 ‐ 6.2.5ImpactsofSolidWaste ..................................................................................................................... ‐ 29 ‐ 6.2.6ImpactonEcologicalEnvironment ................................................................................................ ‐ 29 ‐ 

    6.3  INDUCEDANDCUMULATIVEIMPACTS ...................................................................................................... ‐ 29 ‐ 6.3.1InitialAssessmentofInducedandCumulativeImpacts ............................................................. ‐ 30 ‐ 6.3.2DetailedInducedandCumulativeImpactAssessment ............................................................... ‐ 34 ‐ 

    7.  PUBLIC CONSULTATION AND INFORMATION DISCLOSURE .................................................................... ‐ 35 ‐ 

    8.  ENVIRONMENTAL MANAGEMENT PLAN (EMP) ..................................................................................... ‐ 37 ‐ 

    8.1  ROLESANDRESPONSIBILITIES ................................................................................................................ ‐ 37 ‐ 8.2  MITIGATIONMEASURES ......................................................................................................................... ‐ 39 ‐ 8.3  MANAGEMENTOFCONTRACTORS ............................................................................................................ ‐ 39 ‐ 8.4  ENVIRONMENTALMONITORINGPLAN ..................................................................................................... ‐ 40 ‐ 8.5  ENVIRONMENTALREPORTING ................................................................................................................. ‐ 41 ‐ 8.6  ENVIRONMENTALTRAININGPLAN .......................................................................................................... ‐ 41 ‐ 8.7  EMPBUDGET ........................................................................................................................................ ‐ 41 ‐ 

  • China:SichuanandChongqingCooperation:Guang’anDemonstrationAreaInfrastructureDevelopmentProject

    - 3 -

    1. INTRODUCTIONTheproposedSichuanandChongqingCooperation:Guang’anDemonstrationAreaInfrastructureDevelopmentProjectislocatedinGuang’anPrefectureofSichuanProvince(Figure1).Sichuanisarelativelyunderdevelopedregionofthecountry,whichhasonlyrecentlybeguntoshareintheprosperityofthecountry'srecenteconomicgrowth.ItsneighbourChongqingMunicipality(Chongqing)isanautonomousmunicipalitywithprovince‐levelstatus,whichhasnowemergedasanindustrialhubdrivingeconomicgrowthinthemetropolitanarea.Despitetheiradministrativeseparation,thetwoareasremaincloseduetotheirculturalandeconomicties.TheSichuan‐ChongqingareaishighlightedinChina’sTwelfthFive‐YearPlanforNationalEconomicandSocialDevelopment(2011‐2015)asastrategicareaforurbanizationduetoanidentifiedpotentialforurbanagglomeration.Sichuan'sGuang’anPrefectureisidentifiedashavingafutureroleinfacilitatingcooperationbetweenSichuanandChongqingduetoitscloseproximitytoChongqing.However,thePrefectureisstillclassifiedprovincial‐levelpovertyarea,withpopulationdominatedbyruralpeople.Whiletheprefecturecityandkeytownsarefastdeveloping,theystillrequiresignificantimprovementsintheirinfrastructureservicesandhumancapitaltoplayaroleintheregionaleconomy.Theproposedprojectwillsupportinfrastructureinvestment(includingroads,stormwater/sewagedrainagepipelines,wastewatertreatmentplant,urbangreenspaceetc.)andhumancapitalcapacitybuildingintownsofLinhsuiCountyandQianfengDistrictoftheGuang’anPrefecture.Consideringitsenvironmentalandsocialcontext,althoughthephysicalactivitiesoftheprojectarefairlystraightforwardandtheassociatedenvironmentalimpactsareanticipatedtobelimited,theenvironmentalandsociallyrelatedissuesrelatedtochangesinlanduseandurban/industrialexpansionarepotentiallysignificant,therefore,theprojectisprudentlyassignedasCategoryAasperOP4.01.ThefollowingWorldBanksafeguardspoliciesaretriggered:(1)OP4.01EnvironmentalAssessment;(2)OP4.11PhysicalCulturalResources;(3)OP4.12InvoluntaryResettlement.Environmentalimpactassessment(EIA)reportshavebeenpreparedforLinshuisubprojectandQianfengsubprojectrespectively,basedonwhichtwostand‐aloneEnvironmentalManagementPlans(EMP)havebeendeveloped.ThepreparationofEIAsandEMPsfollowedtherelevantlawsandregulationsofChina,WorldBanksafeguardspolicies,aswellasEHSguidelines,withcommentsandguidancefromtheWorldBanktaskteam.Besidestheseenvironmentalsafeguardsdocuments,socialsafeguardsdocumentshavealsobeenpreparedfollowingtherequirementofOP4.12respectively.ThesedocumentsweresubmittedtotheBankinAugust2014,andfoundinconformitywithWorldBanksafeguardspolicies.Theyhavebeenlocallydisclosedinlocalnewspapers,ProjectManagementOffices,localcommunities,andarealsodisclosedintheInfoshop.ThisdocumentsummarizesthepotentialenvironmentalandsocialimpactsoftheproposedProjectbasedonabove‐mentionedsafeguardsdocuments.Ithighlightsthekey

  • China:SichuanandChongqingCooperation:Guang’anDemonstrationAreaInfrastructureDevelopmentProject

    - 4 -

    environmentalandsocialsafeguardsissuesrelatedtotheprojectconstructionandoperation,describesthemainfindingsandconclusionofimpactassessment,andsummarizesmainmitigationmeasuresandimplementationmanagementplans.Insummary,theproposedprojectwillhavesignificantpositiveimpactsbyimprovinginfrastructureservices,enhancingenvironmentalmanagementandincreasingemploymentopportunitiesandincomesoflocalresidents.Thedirectenvironmentalandsocialimpactsaremostlysite‐specific,notsignificantandarewellidentified.Thoroughenvironmentalandsocialmanagementplanshavebeendevelopedthatcanadequatelyavoid,minimize,mitigateandcompensatetheadverseimpactstoanacceptablelevel.Itisalsoenvisagedthattheprojectwillfacilitatelarge‐scalefutureurbanandindustrialdevelopmentintheprojectareas.Aninitialcumulativeimpactassessmenthasbeenconductedandconcludedthattherewillbesignificantlandusechangeduetofutureurbanandindustrialdevelopmentinbothtownareas,whilethesefuturedevelopmentsarewithinthecarryingcapacityofthelocalenvironmentsandresources.AmoredetailedcumulativeimpactassessmentisbuiltintotheTechnicalAssistancecomponentoftheproposedproject,andwillbeconductedduringtheprojectimplementationstage.

    2. PROJECTDESCRIPTION

    Figure1LocationofProposedProject

  • China:SichuanandChongqingCooperation:Guang’anDemonstrationAreaInfrastructureDevelopmentProject

    - 5 -

    ThedevelopmentobjectiveoftheproposedprojectistosupportLinshuiCountyandQianfengDistrictofGuang’anPrefecturetoimprovetransport,wastewater,skillsandinvestmentpromotionservicesforcurrentneedsandprojectedgrowth.Thiswouldbeachievedbyplanning,financingandmanagingtheseurbanassetsandservicesbasedoncredibleanalysisoftheregionaleconomy,industryandpopulationtrendsandanassessmentofthecumulativeenvironmentalimpactofthetowns’growthplans.Theprojectwillincludethefollowingcomponents:Component1:Preparingforcurrentneedsandprojectedurbangrowth(US$600,000).ThiscomponentwillprovidetechnicalassistanceconsultingservicestoLinshuiandQianfengtobetterplanandmanagebuiltassets,whiletakingintoaccountthewiderimpactsofurbangrowthontheenvironmentbyconductingacumulativeenvironmentalimpactassessment.ItwillalsosupportLinshuitoconductvaluechainanalysesforindustrieswithpotentialforgrowthintheChongqingEMRanddesigntargetedinvestmentpromotion,communicationandmarketingservices.Component2:LinshuiCountyTown(US$63.78million).Thiscomponentwill:(a)createapublictransportcorridorbetweenlow‐incomeareasintheurbancoreandindustrialareasandlinkingtotheGuang’an‐Chongqinghighway;(b)constructstormwaterdrainage,sewageinterceptors,sewagepipelinesandtreatedeffluentpipelinesforexistingandnewresidentsandindustries;(c)increasewastewatertreatmentcapacity;and(d)developindustry‐linkedskillstrainingforlow‐incomegroupsbasedontargetindustries.Component3:QianfengDistrictTown(US$40.12million).Thiscomponentwill:(a)developapassengerandcargoroutebetweentherailwaystationandindustrialarea,bypassingtheurbancore;and(b)revitalizeurbanpublicspaceandcreateaslow,greentransportcorridoralongtheLvxiRiver,connectinglow‐incomeareasoftheurbancorewithindustrialareas.Component4:ProjectManagementandCapacityBuilding(US$1.07million).Thiscomponentwillsupportdesign,reviewandadvisoryneedsforparticipatinginstitutionstoimplementtheproject.Thecomponentincludes:(a)consultingservicesforprojectmanagementandimplementationsupport;and(b)managementcapacitybuildingandtraining.Amongtheprojectcomponents,thephysicalinvestmentinLinshuiandQianfeng(Component2andComponent3)willhavepotentialenvironmentalandsocialimpact,thusaresubjecttoimpactassessment.TheenvironmentalandsocialconsiderationswillbeincorporatedintothescopeofworkandTORsoftechnicalassistanceactivitiesundercomponent1oftheproject.Inparticular,theprojectwillsupportcumulativeimpactassessmentsforLinshuiandQianfengduringprojectimplementation.BesidestheprojectactivitiesundertheproposedBankproject,therearealsoinfrastructureinvestmentprojects(includingroads,wastewatertreatmentplantsetc.)thatcomplementtheoveralldevelopmentplanofthenewindustrialzonesinbothLinshuiand

  • China:SichuanandChongqingCooperation:Guang’anDemonstrationAreaInfrastructureDevelopmentProject

    - 6 -

    Qianfeng.TheseadditionalinfrastructureinvestmentsarelocallyfundedprojectsandarenotincludedintheproposedBankproject.However,sincetheselocallyfundedprojects,togetherwithBankfundedprojectactivities,areintegralpartofnewindustrialparksdevelopmentintheprojectareas,andtheywillbeimplementedinthesameregionwithinatimeframethatcoincides/oroverlapswiththeBankfundedprojects,therefore,theenvironmentalimpactassessmentcoversboththeBankfundedprojectsandthelocallyfundedprojectactivities.ThedetailedprojectactivitiesinLinshuiandQianfengarelistedinTable1,thelocationsoftheseprojectactivitiesareshowninFigure2andFigure3.

    Table1DetailedProjectActivitiesinLinshuiandQianfengComponent Sub‐projects Activities Environmental

    setting

    LinshuiCountyTown

    Roadconstruction

    TheBank‐fundedactivities includeconstructionof5urbanroads,includingsewagepipelines,stormwaterpipelines,greenbeltandancillaryroadfacilities: No.1Road:urbantrunkroad,4.76kmlong,

    40mwide,designspeed50km/h,asphaltconcretesurface

    No.2Road:secondarytrunkroad,3.12kmlong,20mwide,40km/h,asphaltconcretesurface

    No.3Road:urbanbranchroad,1.85kmlong,16mwide,asphaltconcretesurface

    No.4Road:urbanbranchroad,1.07kmlong,16mwide,asphaltconcretesurface

    No.5Road:urbanbranchroad,0.84kmlong,16mwide,asphaltconcretesurface

    Thelocallyfundedroadprojectsinthesameareaincludeconstructionof13roads,withtotallengthof17km.

    NewEconomicDevelopmentZone(ETDZ)tobedeveloped.Currentlanduseismainlyfarmland

    Sewageinterceptor

    Twosewageinterceptorpipelines(13.066km,DN400‐DN1200)alongbothsidesofShibaRiver,andcollectedsewagewillbesenttoaproposednon‐bankfinancedNo.2WWTP

    Asewagemainpipeline(1.80km,DN800)connectingNo.2RoadtoNo.3WWTPandpumpingstation;andatreatedeffluentpipeline(2.65km,DN600)fromNo.3WWTPtoBajiaoRiver.

    Mainlyurbanbuilt‐upareaandnorthernpartofindustrialpark

    WastewaterTreatmentPlant

    Bank‐fundedprojectwillsupport: ConstructionofNo.3WWTPinthesouthof

    Linshui,withcapacityof4,000m3/d.

    Farmland

  • China:SichuanandChongqingCooperation:Guang’anDemonstrationAreaInfrastructureDevelopmentProject

    - 7 -

    TheNo.2WWTPistobefundedlocallytoreceivewastewatercollectedbyBank‐fundedsewageinterceptor.ThisNo.2WWTPhasaplannedcapacityof30,000m3/d,andwillbeimplementedduring2014‐2016.Yet,itsdesignhasnotstartedyet.

    QianfengDistrictTown

    Roadconstruction

    TheBank‐fundedactivities includeconstructionof3urbanroads,includingsewagepipelines,stormwaterpipelines,greenbeltandancillaryroadfacilities: GongyeAvenue:urbantrunkroad,3.30km

    long,30mwide,designspeed50km/h,asphaltconcretesurface

    NorthBinheRoad:urbanbranchroad,4.43kmlong,18mwide,designspeed20km/h,asphaltconcretesurface

    SouthBinheRoad:urbanbranchroad,7.66kmlong,18‐20mwide,designspeed20km/h,asphaltconcretesurface

    ThelocallyfundedroadprojectinthesameareaincludeconstructionofGangqianAvenue,1.6kmlong,24mwide,linkingGongyeAvenuewithanexistingroad.

    Ruralfarmland

    Sewageinterceptor

    Twosewageinterceptorpipelines(13.44km,DN400‐DN1200)alongbothsidesofLuxiRiver,undertheproposedNorthandSouthBinheroads.Theseinterceptorswillbecombineddownstreamandconnectedtoanon‐BankfinancedWWTP.

    CollectedsewageissenttotheproposedWestCowboyWWTPatthesouthofQianfengtown.TheWWTPwillbelocallyfunded,andwillbeconstructedduring2014‐2015.Thedesigncapacity(near‐term)ofWWTPis20,000m3/d.

    Rurallandandurbanarea

    RiverfrontRenovation

    Riverfrontrenovationofca.1.23km,withanareaof50,000m2,including:greenspace,pedestrianpaths,sportscourts,etc.

    Urbanarea

  • China:SichuanandChongqingCooperation:Guang’anDemonstrationAreaInfrastructureDevelopmentProject

    - 8 -

    Figure2DetailedProjectActivitiesinLinshuiCounty

  • China:SichuanandChongqingCooperation:Guang’anDemonstrationAreaInfrastructureDevelopmentProject

    - 9 -

    Figure3DetailedProjectActivitiesinQianfengDistrict

  • China:SichuanandChongqingCooperation:Guang’anDemonstrationAreaInfrastructureDevelopmentProject

    - 10 -

    3. REGULATORYANDLEGALFRAMEWORKTheEnvironmentalImpactAssessment(EIA)forbothLinshuiandQianfengprojectswasconductedinaccordancewithChineseEIAlaws/regulations/guidelines,andtheWorldBanksafeguardspolicies,aswellasEnvironmental,HealthandSafetyguidelinesofWorldBankGroup.WorldBankSafeguardPolicyRequirementsOftheWorldBankGroupstensafeguardspolicies,thefollowingaretriggered:1)OP4.01EnvironmentalAssessment;2)OP4.11PhysicalCulturalResources;3)OP4.12InvoluntaryResettlement.Compliancewiththesepolicies,andtheWorldBank’sdisclosureofinformationpolicy,issummarizedinTable2.

    Table2CompliancewithWorldBankSafeguardsPoliciesSafeguardPolicies Compliance

    OP/BP4.01EnvironmentalAssessment

    ‐ CategoryAproject.‐ FullEIAs,EMPsandEAExecutiveSummaryhavebeenprepared.‐ TworoundsofpublicconsultationconductedaspartofEIAprocess

    OP/BP4.11PhysicalCulturalResources

    ‐ FamilygravesaretoberelocatedinbothtownswhichhavebeenaddressedinRAPs;

    ‐ Alignmentofsewageinterceptorpipelineisadjustedtoavoidaprotectedculturalrelicsite;

    ‐ Chance‐findprocedurehasbeendevelopedinEMPOP/BP4.12InvoluntaryResettlement

    ‐ ResettlementActionPlanshavebeenpreparedforbothtowns.

    TheWorldBankGroupEnvironmental,HealthandSafetyGuidelines(WGBEHSGuidelines)alsoapplytotheproject,includingtheGeneralGuidelinesandspecificGuidelinesforWaterand Sanitation, Toll Roads, Waste Management Facilities. The general principles andmeasures in these Guidelines are consistent with the requirements of Chinese laws,regulations,guidelinesandconstructionmanagementnorms.

    Table3CompliancewithWBGEHSGuidelines

    EHSGuidelines EIA/EMPComplianceGeneralGuidelines EIA/EMPsaddressedtheenvironmentalissuesofair,

    noise,wastewater,wastemanagement,occupationalandcommunityhealthandsafety,andconstructionrelated

    impacts.WaterandSanitationGuidelines Treatmentorpre‐treatmentofindustrialwastewaterpriortodischargetothesewerorwaterbody

    AllindustrialwastewaterindevelopmentzonesmustcomplywithClassIIIstandardpriortodischargeintosewagenetworkforfurthertreatmentinWWTP

    Separation of stormwaterwith industrialandmunicipalwastewater

    Projectadoptsseparatedrainagepipelinesforstormwaterandsewage

    Compliance of effluent with national orinternationalacceptedstandards

    EffluentfromWWTPcomplieswiththeClass1AstandardofDischargeStandardofPollutantsforMunicipal

  • China:SichuanandChongqingCooperation:Guang’anDemonstrationAreaInfrastructureDevelopmentProject

    - 11 -

    WastewaterTreatmentPlant(GB18918‐2002)Odorcontrol Sealedorcovereddesignforodorgenerationprocesses

    adopted;greenspaceisplannedasabufferzone;offsetdistanceissettopreventnewresidentialbuildings

    Sludgedewateringandlandfill/incineration

    Mechanicaldewateringandfiltrationadopted,anddewateredsludgeissenttolandfill

    TollRoadGuidelines: Environmentalissuesofairemission,solidwaste,wastewater,noise,sanitation,occupationalandcommunityhealthandsafety

    ConsistentwithrequirementsofGeneralGuidelines,theseenvironmentalandsocialconcernshavebeenaddressedin

    EIAsandEMPs.WasteManagementFacilities: Wastecollectionandtransportation SanitationdepartmentsofLinshuiandQianfengare

    responsibleforcollectionofwasteandsendtoexistingurbansanitarylandfillsfordisposal

    ChineseLawsandRegulationsTheEIAispreparedfullyincompliancewithrelevantChinanationallaws,regulations,technicalguidelinesandprocedures.CompliancewithaselectivelistofkeyChineseregulationsandEIAtechnicalguidelinesaresummarizedinTable4.

    Table4CompliancewithKeyChinaDomesticLawsandRegulationsChinaLawsandRegulations ProjectCompliance

    EnvironmentalImpactAssessmentLaw

    • EIApreparedbylicensedEIAconsultant,reviewedandapprovedbylocalenvironmentalprotectionagency.

    ClassifiedDirectoryforEnvironmentalManagementofConstructionProject

    • Individual EIAs have been prepared according toproperclassification

    InterimMeasuresforthePublicParticipationinEnvironmentalImpactAssessment

    • Two rounds of public participation conducted insurrounding villages/towns, and info disclosurethroughwebsiteofGuilinMunicipalGovernment.

    NoticeonStrengtheningEIAManagementforConstructionProjectsFundedbyLoansfromInternationalFinancialInstitutions

    • EIAsandEMPsarepreparedincompliancewithWorldBanksafeguardspolicies.

    WaterandSoilConservationLaw • Water conservation and soil erosion control planhasbeenpreparedandapprovedbyrelevantauthority.

    CulturePropertyProtectionLaw • Projectadjustedtoavoidknownculturalproperty• ChancefindprocedureshavebeendevelopedinEMP

    EIATechnicalGuidelinesonAtmosphericEnvironment(HJ/T2.2‐2008),SurfaceWaterEnvironment(HJ/T2.3‐93),NoiseImpactAssessment(HJ/T2.4‐2009),EcologicalEnvironment(HJ/T19‐2011),Groundwater(HJ610‐2011),EnvironmentalRiskAssessment(HJ/T169‐2004),etc.

    • Impactassessmentfollowsthetechnicalrequirementsoftheseguidelines

  • China:SichuanandChongqingCooperation:Guang’anDemonstrationAreaInfrastructureDevelopmentProject

    - 12 -

    4. ENVIRONMENTALANDSOCIALBASELINES4.1 NaturalEnvironmentLocationGuang’anPrefecture(city)islocatedintheeasternpartofSichuanProvince,borderingwithChongqingintheeastandsouth.TheprojecttownofLinshuiCountyisinthesoutheastofGuang’an,betweenE106o41’~107o18’andN30o01’~30o33’.QianfengDistrictisintheeastofGuang’an,betweenE105o56’~107o18’andN30o01’~30o50’.TopographyLinshuiislocatedinbetweentwomountainridgesthatrunalongthedirectionofSW‐NE,withHuayingshanridgeinthewestandTongluoshanridgeintheeast.ThetopographyofLinshuiCountyfeaturesmildslopes,lowhillsandavalleybasin.QianfengislocatedinthewestofHuayingshanridge.ThetopographyofQianfengmainlyfeaturesflatlandandlowhills.ThetopographyoftheprojectareasisillustratedinFigure4.MeteorologyTheprojectareasofLinshuiandQianfengbelongtothesubtropicalmonsoonzonewheretheclimateiswarmandhumidclimate,withplentyofrain.Ithasamulti‐yearaveragetemperatureof16‐18oC,withhighesttemperaturesof40.5~41.2oCandlowestof‐3.8~‐

    Figure4TopographyofLinshuiCountyandQianfengDistrict

  • China:SichuanandChongqingCooperation:Guang’anDemonstrationAreaInfrastructureDevelopmentProject

    - 13 -

    4.5oC.Theaveragerelativehumidityis80~85%.Themulti‐yearaveragerainfallisabout1,100mm,withover70%precipitationduringMay–September.HydrologyLinshuiCountyTherearedenseriversystemswithintheareaofLinshuiwhichbelongstotheYangtzeRivercatchment.MainriverswithintheprojectareaofimpactincludeBajiaoRiver,XiaoxiRiver(moat),ShibaRiverandDanshuitanRiver.BajiaoRiver is on the east side of the Linshui Economic andTechnologicalDevelopmentZone (ETDZ), and is the wastewater discharge receiving river of the ETDZ. The averagewidththeBajiaRiverisc.50m,withmulti‐yearaverageflowof31.3m3/s(4.38m3/sat90%guaranteerate).XiaoxiRiver(moat)isatributaryofBajiaoRiver.ItflowsthroughtheLinshuiCounty,andreceives wastewater discharge from the existing urban built‐up area of Linshui. TheaverageflowofXiaoxiRiveris2.07m3/s.ShibaRiverisatributaryofXiaoxiRiverandflowsthroughafewtownsofLinshuiCounty.Ithas an average flow of 0.44m3/s, and joins in Xiaoxi River at Lingbaoshan Mountain ofLinshui.DanshuitanRiver isa tributaryofBajiaoRiver.TheproposedNo.3WWTPis locatedneartheriver.ItjoinsintheBajiaoRiveratabout1.5kmdownstreamoftheWWTPsite.QianfengDistrictThemainriverintheprojectareaofQianfengisLuxiRiver.ItisatributaryofQujiangRiver,asecondarytributaryofYangtzeRiver.TheLuxiRiveris47kmlong,withtotalcatchmentareaof183km2.LuxiRiverflowsthroughQianfengtown,andisthewastewaterdischargewaterbodyforQianfeng.ThesemainriversintheprojectareasareshowninFigure2andFigure3.EcologicalEnvironmentLinshuiCountyTheprojectactivities inLinshuiare located in itsETDZ in thesouthofLinshui.The totalplanned area of the ETDZ is 2,818ha, including 831 ha of industrial land. Currently, thedevelopedareaoftheETDZis393ha,withpresenceof40industrialenterprises.Therestof the undeveloped land in the ETDZ ismainly rural landscape dominated by farmland.

  • China:SichuanandChongqingCooperation:Guang’anDemonstrationAreaInfrastructureDevelopmentProject

    - 14 -

    Surfacevegetationintheprojectareaismainlyfarmlandcropsandplantedtrees.Thereisprotectedwildplantspeciesintheprojectarea.Duetointensivehumanactivitiesanddevelopment,thereisnolargewildanimalpresenceintheprojectarea.Animals intheareaareallcommonspecies inruralenvironment,e.g.rodents,frogsetc.According tohistorical records and survey, there is no large scale aquatic vascularplantcommunities, protected aquatic plant species and fish species in theBajiaoRiver and itstributaries.Basedonfieldsurveyandconsultationwithlocalcommunities,fishspeciesaredecreasingduetowaterpollutioninShibaRiverandXiaoxiRiver(themoat).QianfengTheproject activities inQianfengare located in the existingurbanbuilt‐up area and theplannednewtownandindustrialparkarea.Thecurrentstatusoftheundevelopedareaofthe new town and industrial park is mainly farmland, whose surface vegetation isdominatedbyfarmlandcrops,plantedtreesandbushes.Thereisnoprotectedwildplantandanimalspeciesidentifiedintheprojectarea.SimilartotheprojectareainLinshui,thereisnolargewildanimalpresenceintheprojectarea,besidescommonspeciesinruralenvironment,e.g.rodent, frogetc.duetointensivehumanactivities.Available informationonLuxiRiver indicatesthatthere isnoprotectedaquaticwildlifespeciesintheriver.4.2 Socio‐economicContextGuang’anPrefecture(City)wasestablishedin1998,andhasatotalareaof6,344km2,withatotalpopulationof4.7million.UrbanpercapitadisposableincomeinGuang’anPrefecturewas RMB 19,973 in 2012, just below the provincial average. Guang’an Prefecture isdesignatedasaprovincial‐levelpovertyarea.LinshuiCountyhasatotalpopulationofabout1millionandtotalareaof1,912km2.In2012,its urban per capita disposable incomewas RMB19,274 and rural per capita disposableincomewas7,404.Linshuiisaprovincial‐levelpovertycountyinSichuan.QianfengDistrictisanewlyestablisheddistrictinGuang’anin2013.Before,itwaspartofGuang’anDistrictwhichisdesignatedasanationalpovertyarea.In2013,theruralpovertylinewasRMB2734($448)andapproximately24,313peopleinQianfeng(about11%ofthetotalpopulation)and86,036peopleinLinshui(about12%ofthetotalpopulation)wereregisteredasruralpoor.

  • China:SichuanandChongqingCooperation:Guang’anDemonstrationAreaInfrastructureDevelopmentProject

    - 15 -

    4.3 EnvironmentallyandSociallySensitiveSitesDuringEApreparation,detailedsurveyofenvironmentallyandsociallysensitivesiteswithinintheareaofinfluencehasbeenconductedthroughfieldinvestigationandconsultationwithlocalagenciesandcommunities.Itisconcludedthatthereisnospecialprotectedarea,ecologicalsensitivearea,naturalhabitatwithintheareaofinfluenceoftheproposedproject.Thesensitivesitesinthevicinityoftheprojectareresidentialcommunitiesalongtheprojectroads,riversinthevicinityoftheprojectactivitiesandfamilygravestobeaffectedbytheproject.Basedonfieldsurvey,theenvironmentalandsociallysensitivesitesoftheproposedprojectinclude:QianfengDistrict(1) LuxiRiver(alongwhichtworiverbankroadsandsewageinterceptorswillbe

    constructed);(2) 21residentialcommunitiesnearbytheprojectroads;(3) 68familygravestobeaffectedandrelocated.LinshuiCounty(1) BajiaoRiver(receivingeffluentfromNo.2andNo.3WWTPs),ShibaRiver(alongwhich

    thetwosewageinterceptorpipelinewillbelaid)andDanshuitanRiver(bywhichtheNo.3WWTPislocated);

    (2) 1626familygravestobeaffectedandrelocated;(3) LingbaoshanStoneCarvingandBridgeprotectionareanearthesewageinterceptor

    pipelinesite.LingbaoshanStoneCarvingandBridgeRelicsSiteLingbaoshanmountainstonecarvingandthreeancientbridgesarelistedasprotectedculturalrelicsbyGuang’anCityin2000.ThesearerelicsfromtheSongDynasty,including11piecesofstonecarving,sculptureand3stonebridges,withculturalvalueofancientarchitecture,calligraphyandstonecarving(Figure5).Thealignmentofthesewageinterceptorpipelineisdesignedtoavoidtheprotectionzoneoftherelicssite.However,itisstillclosetothesite,15moutsidetheboundaryofconstruction‐restrictionzoneofthesite.ThedetailedrelationshipoftheprojectpipelineandtheLingbaoshanprotectionsiteisshowninFigure6.

  • China:SichuanandChongqingCooperation:Guang’anDemonstrationAreaInfrastructureDevelopmentProject

    - 16 -

    4.4 AmbientEnvironmentalQualityAmbientNoiseBaselinenoisewasmonitorrfforselectivesensitivesitesalongtheproposedprojectroadsinbothLinshuiandQianfengduringtheenvironmentalassessmentprocess.Monitoringresultsindicateagenerallygoodacousticenvironmentintheprojectareaswhichconformstotheapplicableambientnoisestandards,exceptonecommunityinQianfengwhichcannotmeetthenight‐timestandardduetoitsclosenesstoanexistingrailway.AmbientAirQualityAmbientairqualityatselectivesensitivesitesandsamplingpointsintheprojectareasofLinshuiandQianfengwasconducted,withmonitoringparametersofSO2,NO2andPM10.Theresultsshowtheoverallcompliancewiththeapplicableambientairqualitystandards.

    Figure5LingbaoshanStoneCarvingandAncientBridges

    Figure6RelationshipbetweenLingbaoshanRelicsSiteandSewageInterceptor

  • China:SichuanandChongqingCooperation:Guang’anDemonstrationAreaInfrastructureDevelopmentProject

    - 17 -

    SurfaceWaterQualityInLinshui,surfacewatermonitoringdataforBajiaoRiver,DanshuitanRiver,ShibaRiverandXiaoxiRiver(themoat)in2012(fromPlanEIAforETDZ)wereusedasreferences.TheparametersassessedincludeCOD,BOD5,NH3‐N,petroleum,pHandTP.ThedatashowsthatupstreamofBajiaoRiverandShibaRiverisgenerallygood,withoverallcompliancewithClassIIIstandardofSurfaceWaterEnvironmentalQualityStandards.While,theXiaoxiRiver(themoat)flowsthroughtheurbanareaofLinshuiwheredomesticsewageisdischargedintotheriver,leadingtonon‐complianceofNH3‐NandTP.InQianfeng,waterqualitymonitoringwasconductedforLuxiRiverduringthepreparationofEIA.Themonitoringresultsindicateoverallcompliancewiththeapplicablestandards,i.e.ClassIIIstandardofSurfaceWaterEnvironmentalQualityStandards.GroundwaterQualityGroundwatermonitoringwasconductedintheprojectareasinbothLinshuiandQianfeng,whichconfirmsoverallcompliancewithrelevantgroundwaterqualitystandards.4.5 ExistingEnvironmentalInfrastructureLinshuiThereisanexistingNo.1WWTPinLinshui,withacapacityof20,000m3/d,providingservicetoanareaof9.3km2.Forthoseareasoutsidetheservicescope,domesticsewageisdischargedintoirrigationcanalsordrainageditchesaftersimpletreatmentbyseptictank.Industrialenterprisesarerequiredtopre‐treattheirwastewateruptoClass1standardsoftheComprehensiveWastewaterDischargeStandard(GB8978‐1996)beforedischargedtotheenvironment.LinshuihasconstructedWuchasolidwastelandfillin2008,withatotalareaofca.6haandadailydisposalcapacityof125t.Thedesignlifeofthissanitarylandfillis14years.Duetorapidurbandevelopmentandincreasedpopulation,solidwastecollectionhasreached160t/d,andthetotalcapacityofthelandfillisnearlyreached.Currently,anexpansionofthelandfillisplannedwithadditional1.3halandarea,andwillbeputintooperationin2016.SolidwastecollectionandtransportationtolandfillisconductedbyLinshuiSanitationDepartment.QianfengCurrently,thereisnoWWTPinQianfeng.DomesticsewageintheoldurbanareaisdischargedintotheLuxiRiverwithoutorwithlittletreatment.Industrialenterprisesthatalreadyenteredtheindustrialparkarerequiredtohavepre‐treatmentfacilitiestotreat

  • China:SichuanandChongqingCooperation:Guang’anDemonstrationAreaInfrastructureDevelopmentProject

    - 18 -

    theirwastewateruptoClass1standardsoftheComprehensiveWastewaterDischargeStandard(GB8978‐1996)beforedischargedtoenvironment.Currently,allsolidwastecollectedfromQianfengissenttoPuanLandfillofGuang’anCity,about50kmfromQianfeng.PuanLandfillisasanitarylandfill,withcapacityof300t/d.SolidwastecollectionandtransportationtolandfillisconductedbyQianfengSanitationDepartment.

  • China:SichuanandChongqingCooperation:Guang’anDemonstrationAreaInfrastructureDevelopmentProject

    - 19 -

    5. ANALYSISOFALTERNATIVESAlternativeanalysishasbeenconductedfortheprojectwithcomprehensiveconsiderationsofenvironmental,social,technicalandeconomicfactors,basedonwhichtheoveralloptimumoptionisselected.Themainanalysisofalternativesissummarizedasfollows:5.1 With/WithoutProjectInMarch2011, the State Council approved the establishment of theChengdu‐Chongqing(Cheng‐Yu)EconomicZonetoboosteconomicgrowthinthisareaandmakeChengduandChongqing the hub ofwestern region development. According to theCheng‐YuEconomicZone'sRegionalPlan, Sichuan's Guang’an will be designated as a demonstration area ofcooperationbetweenSichuanandChongqing.The Master Plan for Cheng‐Yu Cooperation Demonstration Area explicitly planned anelectrical industrial park in Linshui. With implementation of theMasterPlan, more andmoreindustrialenterprisesareestablishedinLinshuiETDZ.TheexistingdevelopedpartoftheETDZwillnotbeabletoaccommodatetheexpectedincreaseofindustrialenterprises,andthus it isessential toprepare for infrastructuredevelopment in thesouthernpartoftheETDZ.Thebuilt‐upareaofETDZstillusescombinedstormwater/sewagesystems,andall wastewater is discharged directly into the Shiba River. The proposed roadinfrastructure in the southern part of the ETDZ, sewage interceptors in the existingindustrial areas of the ETDZ, and the No.3WWTP for the new development part of theETDZ (plus locally funded No. 2 WWTP for existing part of ETDZ) will facilitate thedevelopment of Linshui ETDZ with proper environmental infrastructure to addressenvironmentalissuesenvisagedfromfuturedevelopment.TheMasterPlanalsoclearlyplannedacentralbusinessdistrict/logisticsparkinQianfeng.With an increase of incoming enterprises, the existing built‐up area in Qianfeng can nolongeraccommodatesuchdevelopment,thusdevelopmentoftheindustrialparkandnewurbanareaisunavoidable.Currently, there isa lackofcompletesewageinterceptionandcollection system and no WWTP in Qianfeng. The proposed road infrastructure,wastewater collection system(plus locally fundedWWTP)areessential infrastructure topreparefortheexpectedfutureurbanandindustrialdevelopmentinQianfeng.Thus,itisenvisagedthatwithouttheproject,significantenvironmentalconsequenceswillbeexpectedfromsuchlarge‐scaleurbanandindustrialdevelopmentintheprojectareas.5.2 AlternativeAnalysisofNo.3WWTPinLinshuiLocationsTwolocationoptionswereconsideredduringEAanddesignstage:(1) Option1isatXinheVillage,southoftheETDZ,andbyDanshuitanRiver.

  • China:SichuanandChongqingCooperation:Guang’anDemonstrationAreaInfrastructureDevelopmentProject

    - 20 -

    (2) Option2isatShitaiVillage,southoftheETDZ,andbyLinmaziRiver.About2kmupstreamofOption1.

    Bothoptionshaveconvenientaccessibility,effluentdischargeintoBajiaoRiverandsimilargeologicalconditions.While,Option1haslittleresettlement,andOption2haslarge‐scaleresettlement.Therefore,Option1isselected.EffluentDischargeLocationBesidesconsiderationoflocation,thealternativeoptionsforeffluentdischargelocationswerealsoconsidered.AstheNo.3WWTPisbythesideofDanshuitanRiver,twooptionsofdischargelocationswerecompared:i.e.(1) DanshuitanRiverbytheWWTPsite;(2) BaojiaoRiveratca.1.5kmdownstreamofDanshuitanRiver.DanshuitanRiverisatributaryofBajiaoRiver,andhasasignificantvariedflowoverayear,withmorethan80%runoffduringMay‐October.While,BaijaoRiverhasamuchlargercatchmentarea,steadyandlargeflowrate.Theaverageflowattheproposedoutletlocationis28.3m3/s.Therefore,BajiaoRiverisselectedasthereceivingwaterfortheeffluentofNo.3WWTP.A2.65kmeffluentdischargepipelinewillbeconstructedalongtheDanshuitanRiverandendattheBajiaoRiver.WWTPTreatmentProcessesMoretechnicalanalysisonalternativetreatmentprocessesalsowereconsideredaspartofthefeasibilitystudyandprojectdesign,includingwastewatertreatmentprocess(oxidationditch,A2/Oandfoodchainreactorsapproaches),effluentdisinfectionprocess(UV,chemicalsofliquidchlorine/ClO2/Sodiumhypochlorite),sludgethickening/dewatering(gravitythickening/mechanicaldewateringvsmechanicalthickeninganddewatering).Thesealternativesaremainlytechnicalconsiderationswiththesameenvironmentalperformanceorresult.5.3 AlternativesofRoadProjectsTheproposedroadalignmentsinbothLinshuiandQianfengaredeterminedbytheexistinglocalmasterplans.Therefore,alternativeswereonlyconsideredatspecificlocations,includinganexpresswaycrossingNo.1RoadinLinshui,andabridgecrossingtheLuxiRiverbyGongyeAvenueinQianfeng.ExpresswayCrossingNo.1RoadinLinshuiTheNo.1RoadinLinshuiwillcrosstheHu‐RongExpressway.Twooptionswereconsidered:(1)underpass,and(2)viaductoverpass.Theunderpassoptionwillrequirelargeramountsofearth/stoneworksduetoconsiderationofelevation,andisnotinconformitywithdesignnormswhenconnectedwithplannedelevations.Itwillalsooccupy

  • China:SichuanandChongqingCooperation:Guang’anDemonstrationAreaInfrastructureDevelopmentProject

    - 21 -

    halfoftheexpresswayduringtheconstructionstage,while,theoverpassoptionwillnotaffectthenormaloperationoftheexpressway.Therefore,theoverpassoptionisselected.BridgeCrossingLuxiRiverbyGongyeAvenueinQianfengTwobridgeschemeswerecomparedforGongyeAvenuecrossingLuxiRiver:(1) One‐span25mpre‐stressedboxbeam;(2) Two‐span(2X12m)concreteframebridge.Theone‐spanbeambridgeiseasytobuild,willnotaffecttheriverchannelandavoidin‐waterpiers.Thetwo‐spanconcreteframebridgewillrequiretheoccupationofriverchannelduringconstruction,andrequirelongerconstructiondurationandhighercost.Therefore,theone‐spanbeamschemeisselectedduetoitsavoidanceofimpactonriverbody.5.4 AlternativesofSewageInterceptorPipelineinLinshuiTheoriginaldesignofsewageinterceptorpipelineinLinshuiwillpassthroughtheconstruction‐restrictionzoneoftheLingbaoshanStoneCarvingandBridgeprotectionsite,about2moutsidetheboundaryofthecoreprotectionzone.DuringtheEAprocess,analternativealignmentisproposedtomovethealignmentawayfromtheprotectionzone,asillustratedinFigure7.

    Figure7AlternativesofSewageInterceptorPipeline

  • China:SichuanandChongqingCooperation:Guang’anDemonstrationAreaInfrastructureDevelopmentProject

    - 22 -

    6. ASSESSMENTOFIMPACTSANDMITIGATIONMEASURESTheproposedprojectwillhavesignificantpositiveenvironmentalandsocialbenefitsthroughprovidingenvironmentalandurbaninfrastructure,improvingtheurbanlivingenvironment,creatingemploymentopportunitiesandfacilitatingsocio‐economicdevelopmentintheprojectareas.However,theprojectwillhavealsoadverseenvironmentalandsocialimpactsduringtheconstructionandoperationstage.Theseimpactsinclude:Table5PotentialImpactsduringConstructionandOperation(tobeupdatedlatterly)PotentialEnvironmentalandSocialImpacts

    duringConstructionPotentialEnvironmentalandSocialImpacts

    duringOperation Landacquisitionandresettlement Impactonphysicalculturalresources Trafficandcommunitydisturbance Ecologicalenvironmentalimpact Constructionnuisanceofdustandnoise Constructionwastewaterandsewage Constructionspoilandsolidwaste

    management

    Noiseimpactofroadoperation Airqualityimpactoftheprojectareas Impactonsurfacewaterandgroundwater WastemanagementofWWTPs Long‐terminducedandcumulativeimpacts

    Basedontheenvironmentalimpactassessment,theseimpactsarefoundtobestraightforward,limitedinscopeandcanbereadilymitigatedwithgoodconstructionandoperationmanagement.AdequatemeasureshavebeendevelopedinEMP/RAP.Insummary,theprojectwillnothavesignificantadverseenvironmentalandsocialimpacts,willnotresultinsignificantdegradationorconversionofnaturalhabitatandwillnothavesignificantimpactonanyphysicalculturalresources.MitigationmeasureshavebeendevelopedintheEMP,whichcaneffectivelyavoid,minimize,mitigateorotherwisecompensatepotentialenvironmentalandsocialimpacts.Thoughthedirectimpactsoftheprojectarestraightforwardandmanageable,thelong‐terminducedandcumulativeimpactsfromrapidurbanizationandindustrializationwhichtheprojectissupportingaresignificantandmorechallenging.Inthisregard,aninitialcumulativeimpactassessmenthasbeenconductedintheEIAs,andamoredetailedCumulativeImpactAssessmentisbuiltintotheTechnicalAssistancecomponentoftheprojecttobecarriedoutduringtheprojectimplementationstage.6.1 ImpactsduringConstructionStage6.1.1ImpactsofLandAcquisitionandResettlementTheprojectconstructionwillneedlandacquisitionandresettlement,includingpermanentlandacquisitionof58.7hainLinshui(1,264householdswithaffectedpeopleof4,442)and21.3hainQianfeng(453householdswithaffectedpeopleof1,630),resettlementofruralhousesof704households(2,468affectedpeople)inLinshuiand421households(1,515affectedpeople)inQianfeng.

  • China:SichuanandChongqingCooperation:Guang’anDemonstrationAreaInfrastructureDevelopmentProject

    - 23 -

    Toaddressimpactsoflandacquisitionandresettlement,aResettlementActionPlan(RAP)hasbeenpreparedforLinshuiandQianfengrespectivelyfollowingtherelevantChineselaws/regulationsandWorldBankOP4.12InvoluntaryResettlement,andhavebeenreviewedandapprovedbytheWorldBank.6.1.2ImpactsonPhysicalCulturalResourcesInLinshui,theproposedsewageinterceptionpipelinehasbeenadjustedtoavoidtheLingbaoshaoStoneCarvingandBridgeRelicsSite.However,thepipelineisstillclosetothesite,withclosestdistanceofca.15moutsidetheconstruction‐restrictionzone(asshowninFigure7).Constructionactivityofearthexcavationandpipelinelaying,ifnotwell‐managed,willhavepotentialadverseimpactsontherelicssite,i.e.stabilityofmountaincliffsandriverbeddisturbanceetc.Notwell‐trainedconstructionworkersmayalsoposepotentialthreattotherelicssitesduetointentional/unintentionaldamageactivitiesorgraffiti.Tominimizethepotentialimpacts,pipe‐jackingconstructiontechnologyisusedforsectionscrossingtheriver‐bedandmountainnearbytheprotectionarea(SeeFigure8.).Thisapproachwillavoidopenexcavationandblastingofriver‐bedandmountain,andthiswillminimizethepotentialimpactontherelicsprotectionarea.Inadditionaltouseofproperconstructiontechnology,trainingwillbeprovidedtoconstructionworkersintermsofprotectionofculturalresources,andprecautionswillbe

    Figure8Pipe‐jackingApproachUsedforLingbaoshanProtectionArea

  • China:SichuanandChongqingCooperation:Guang’anDemonstrationAreaInfrastructureDevelopmentProject

    - 24 -

    adoptedduringconstruction.Chance‐findprocedureshavebeendevelopedintheEMPandwillbeenforced.Theprojectwillalsoinvolverelocationof1,694familygraves(1,626inLinshuiand68inQianfeng)thatarescatterinfarmlandsintheprojectarea.Basedonfieldsurveyandconsultation,itisconcludedthattheselocalfamilygraveshaveinsignificantarchaeologicalandhistoricalvalue.Asacommonissueforinfrastructureprojects,therearewellestablishednational/localresettlementregulationsgoverningtheconsultation,relocationandcompensationprocessforfamilygraves.Consultationsonthegraverelocationhavebeenconducted,andrelocationandcompensationmeasureshavebeenfullyincorporatedintheRAPs.6.1.3TrafficandCommunityDisturbanceConstructionactivitiesoftheprojectwillhaveadverseimpactsonurbantrafficandcommunityaccessibilityduetoconstructionofpipelinesandtransportationofmaterials.Thoughpipelinescanbelaidsectionbysection,therewillbetemporaryexcavationatcertainsections,andsoil/materialsbetemporarilystoredon‐sitewhichwillaffectroadtrafficanddisturbcommunityaccessibility.Excavationworksmayalsoaffectutilitylinesforwatersupply,gas/electricityandcommunicationsetc.Insummary,suchimpactsaretemporaryinnature,andwilldisappearonceconstructionactivitiesarefinished.Tomitigatetheimpactoftrafficandcommunitydisturbance,mitigationmeasureshavebeendevelopedinEMPincluding: Coordinationwithutilitycompaniestosecureminimizeddisturbance,andpriornotice

    topublic; Properlyarrangetrafficdiversionandrestrictionincoordinationwithtrafficpolice

    departments,temporaryaccesspathsforcommunity; Enforcesafetyrulesasperrelevantnationallaws/regulations/norms; Bulletinboardswillbeinstalledonsitetodiscloseinformationontheprojectcontents,

    constructiontimeandcontactforcomplaints; Timelybackfilltorestoretraffic; Materialtransportationshallavoidpeakhoursoftraffic; Properfencingandclearwarningsignagewillbeinstalledaroundtheconstructionsite; Conductpublicconsultationsandinformationdisclosureduringconstructionstageto

    receivepublicfeedback.6.1.4ImpactonEcologicalEnvironmentTheprojectconstructionwillleadtolandusechange,thushasadverseimpactsonthelocalecologicalenvironmentintermsoflossofsurfacevegetationandbiodiversity.TheprojectareasinbothLinshuiandQianfengaretypicalruralenvironmentswhicharedominatedbyfarmlandsandplantedvegetation.Basedonfieldsurveys,thereisnoprotectedorendangeredwildplantoranimalspeciesintheareaofinfluence.Theconversionofruralfarmlandtourbanandindustriallandwillnotleadtosignificantlossofnaturalhabitatsor

  • China:SichuanandChongqingCooperation:Guang’anDemonstrationAreaInfrastructureDevelopmentProject

    - 25 -

    biodiversityinthearea.Intensivegreenbeltsandgreenspaceareplannedalongtheprojectroads/pipelinesandatrestoredprojectsites,whichwillpartiallyoffsetthelossofsurfacevegetationintheprojectarea.Constructionalong/crossingriversmayaffectthenaturalriverchannelandhaveadverseimpactsonriverecology.Earthexcavationactivitiesintheprojectwilldisturbtheoriginallandsurface,andifnotwellmanaged,willcausesoilerosionproblemsduringtherainyseason.Earthborrowpitsandspoildisposal,ifneeded,mayalsohavepotentialecologicalimpacts.Tominimizeecologicalenvironmentalimpacts,mitigationmeasureshavebeendevelopedintheEMPs,including: Relocateexistingtreesasmuchaspossibleforlatergreenspacerestorationafter

    completionofprojectconstruction; Limitconstructionactivitieswithright‐of‐waytominimizedisturbanceofsurface

    vegetation; Properbalanceofearthexcavationandbackfilling,sothatnoadditionalborrowsiteor

    spoildisposalsiteisneededforbothLinshuiandQianfeng; Properarrangeconstructionschedulestoavoidexcavationsonrainydays; Timelyrestorationofdisturbedareaswithgreenbelt/space; Rationallyarrangeconstructionschedulesofdifferentroadsinthesameareato

    minimizecumulativeimpacts; Properlyarrangethestorageofsoilandbulkmaterialsonsitetominimizeerosion,

    withfencing,drainageditches/settlingtanksandtemporarycoverwherenecessary; Educateworkersonecologicalprotectionknowledgeandrequirements; AcomprehensiveSoilErosionControlPlanhasbeendevelopedaspernational

    requirementsandincorporatedintoEMPs.6.1.5ImpactsofNoiseConstructionnoisemainlycomesfromconstructionmachinesandtransportationvehicles.Noiseimpactmayhaveaninfluencescopeof35mduringthedaytimeand200mduringthenighttime.Inparticular,nighttimeconstructionactivitieswillhavemuchlargerimpactonnearbycommunities.Tomitigatenoiseimpactsonnearbycommunities,aseriesofmitigationmeasureshavebeendevelopedintheEMPs,including: Rationallyarrangetheconstructionsitetokeepnoisymachines/vehiclesawayfrom

    sensitivereceptors; Restrictnight‐timeconstructionwithhigh‐noiseequipment,andforbidnight‐time

    (22:00–08:00)constructionnearcommunities;ifcasesofcontinuousconstructionisinevitable,priorapprovalofthelocalenvironmentalauthorityandpriornoticetothepublicmustbesecured;

    Properlyarrangematerialtransportationroutes,andenforcespeedlimitrequirements; Lownoiseconstructionequipmentwillbeused,withadequatemaintenance;

  • China:SichuanandChongqingCooperation:Guang’anDemonstrationAreaInfrastructureDevelopmentProject

    - 26 -

    Temporarynoisereductionmeasureswillbeadoptednearcommunities,suchasfences,mobilenoisebarrier,sound‐insulationcoveretc.

    6.1.6ImpactofDustAmajortemporaryenvironmentalimpactoftheconstructionofroadsandpipelinesisconstructiondust,mainlyfromearthexcavation,on‐sitestorage,backfillingandsecondarydustfrommaterial/wastetransportation,andcementmixingandasphaltpavement.Basedonsurveystatisticsfromsimilarconstructionprojects,constructiondustmayhaveanimpactscopeupto200m.Thesensitivereceptorsofnearbycommunitieswillbesubjecttodustimpactifnotenoughmeasuresareadopted.Tomitigatesuchimpacts,aseriesofmitigationmeasureshavebeendevelopedintheEMPs,including: Properlymaintainthecleannessofconstructionsitethroughwaterspraying,timely

    cleaning,wheel‐washing,timelyremovalofwasteetc.; Temporaryenclosurefencewillbeinstalledwherepossibletominimizedust

    generation; Strictlymanagetheloading/unloadingofearthandbulkmaterial,anduseproperly

    coveredtrucksfortransportation; Suspendconstructionactivitiesonwindydays(overClass4wind); Properfencingorcoveringfortemporarypilingofbulkmaterial,wastespoilonsite; Propermaintenanceofconstruction/transportationvehiclestominimizeemissions; Providemaskforworkers,etc.6.1.7ImpactofWastewaterDuringconstruction,therewillbealimitedamountofwastewatergeneratedfromconstructionsites,machine/vehiclecleaning,andsewagefromworkers.Themainpollutantsofconstructionwastewateraresuspendedsolid(SS)andsmallamountsofoil.Withoutpropercollectionandtreatment,randomlydischargedwastewateratconstructionsitedwillhaveadverseimpactsontheenvironment,especiallyconstructionactivitiesnearrivers.Pipesealingtestswillalsogeneratewastewater,whichismainlycleanwaterwithsomesuspendedsolidandcanbereusedfordustsuppressingandgreenspacewatering.Tomitigatesuchimpacts,aseriesofmitigationmeasureshavebeendevelopedintheEMP,including: Settlingtankswillbeconstructedatconstructionsitestotreatconstruction

    wastewaterforreuse;directdischargeofwastewaterwithouttreatmentisforbidden; Properlymanagesolidwastefromcampsandconstructionsitestoavoidpotential

    pollutionofsurfacewaters; Wasteoilfromvehiclesandconstructionmachineswillbespeciallycollectedandsent

    tolicensedfacilitiesforsafedisposal. Strengthenroutinemaintenanceofequipmentandvehiclestoavoidoilleakage;

  • China:SichuanandChongqingCooperation:Guang’anDemonstrationAreaInfrastructureDevelopmentProject

    - 27 -

    Reusingcleanwaterfrompipetestinganddewateringprocessoffoundationexcavation.

    6.1.8ImpactsofGroundwaterTheprojectconstructionofroads,sewageinterceptorsandWWTPsmaygeneratewastewaterwhichmaypollutegroundwater.ExcavationofdeepditchesforsewageinterceptorsandfoundationsofWWTPleadtogroundwaterleakage,orneeddewateringatthespecificsitelocations.However,suchimpactsaretemporaryandsite‐specific,itwillnotleadtochangesofthegroundwatertableintheprojectareas,norwillitblockthedrainageofgroundwaterintheregion.Tomitigatesuchimpacts,mitigationmeasureshavebeendevelopedintheEMPs,including: Properlyarrangeconstructionscheduletominimizegroundwaterpumpingtime

    periodorconcentrateddewateringwellsinthesamelocationatthesametime; Arrangeexcavationofdeepditchesatnon‐floodseason,etc.6.1.9ImpactsofSolidWasteSolidwasteduringconstructionmainlycomesfromexcavatedspoil,debrisfrombuildingdemolition,constructiondebrisofsand/aggregate/cement,aswellasgarbagegeneratedbyconstructionworkers.Tomitigatesuchimpacts,mitigationmeasureshavebeendevelopedintheEMPs,including: Balanceexcavationandbackfillingtoavoiddemandfordisposalofspoilmaterials; Constructionwastewillbecollectedandrecycledtotheextentpossible,non‐recyclable

    wastewillbesenttoconstructionwastelandfillsdesignatedbycitygovernment; Mixingconstructionwithdomesticsolidwasteisforbidden; Dumpingofsolidwasteintosurfacewatersisstrictlyforbidden; Constructionwastetransportationtruckswillbecoveredtoavoidlitteringandspills; Garbagefromconstructioncampswillbecollectedonsiteanddisposedofthrough

    establishedmunicipalsolidwastecollectionanddisposalsystem.6.2 ImpactsduringOperationStage6.2.1NoiseImpactDuringtheoperationstage,projectroadswillattractincreasedtrafficwhichwillleadtoincreaseofnoiselevelalongtheroadcorridors.Basedonsimulationofnoiseimpactmodelingfortheroadnetwork,noisecomplianceoffsetdistancehasbeencalculatedwhichwillbeusedforplanningoffuturebuildingsalongtheroads.Thecurrentruralcommunitiesintheprojectareascangenerallymaintainnoiselevelcompliance,exceptafewvillagesthatareclosetoexistingnationalhighwayandrailway.However,alltheseresidentswillberelocatedatthesametime/orsoonafterthe

  • China:SichuanandChongqingCooperation:Guang’anDemonstrationAreaInfrastructureDevelopmentProject

    - 28 -

    constructionoftheprojectroadsduetodevelopmentofindustrialparksaccordingtolocalmasterplans.OperationoftheNo.3WWTPinLinshuiwillalsohaveanoiseimpactontheambientenvironment.Basedonnoiseimpactprediction,thenoiseatthebordersoftheWWTPcanmeetapplicableambientnoisestandardsatalldirections.6.2.2ImpactonAirQualityVehicletrafficontheprojectroadswillincreaseairpollutionintheprojectareas.Airdispersionmodelingwasconductedfortheprojectroadsnetwork.Themodelingresultsindicatethattheairqualityintheprojectareawillremainincompliancewithapplicableambientairqualitystandards.TheoperationofNo.3WWTPinLinshuiwillhavepotentialodorimpactsontheambientenvironment.BasedonanalogiccomparisonandairdispersionmodelingforH2SandNH3,itisconcludedthatoperationofNo.3WWTPwillhavelittleimpactontheambientenvironment,i.e.theconcentrationofH2SandNH3attheboundaryoftheWWTPislessthan0.2%oftheapplicableambientenvironmentalstandards.ThemitigationmeasuresadoptedinWWTPdesigninclude: Arrangeodorsourcesinthemiddleoftheplantsite; Sealedbuildingdesignforcoarsescreen,pumpingroomandfinescreen,sludgetank

    andundergroundreturn‐sludgepumpingroom; CollectedodorgasistreatedwithUVde‐odorequipment Dailyremovalofdewateredsludge; Enhancedtreeplantationandgreenspace(over30%area)withinWWTP.6.2.3ImpactsonSurfaceWaterTheoperationofsewageinterceptorsandWWTPsinLinshuiandQianfengwillsignificantlyreducethewastewaterpollutiondischargedintolocalrivers,andhencehavepositiveenvironmentalbenefits.While,theeffluentdischargefromtheWWTPmayhavepotentialenvironmentalimpactsonthereceivingwaterbody,especiallyincaseofanemergencyattheWWTPwhenuntreatedsewageisdirectlydischargedintotheriverthroughthebypasspipeline.MathematicmodelingcalculationwasconductedtoassesstheimpactofeffluentdischargefromtheWWTP.Theresultsshowthatduringnormaloperation,theeffluentdischargewillhaveanimpactareaoflessthana1mscopearoundtheoutlet,andduringtheemergencyscenario,theimpactareaislessthana10mscopearoundtheoutlet.Therefore,thepotentialwaterqualityimpactofeffluentdischargefromWWTPislimited.FortheeffectiveoperationoftheWWTP,themainmitigationmeasureswillinclude: Establishoperationmanagementprocedures,providetrainingtoworkers;

  • China:SichuanandChongqingCooperation:Guang’anDemonstrationAreaInfrastructureDevelopmentProject

    - 29 -

    Installon‐linemonitoringequipmentforpH,SS,COD,NH3‐NandTPwithconnectiontolocalenvironmentalauthorities;

    Providebackupdesignforpowersupplyandmaintreatmentunitsforemergencyscenario,anddevelopemergencyresponseplans;

    EnforceindustrialwastewaterdischargestandardsforsourcesthatfeedintotheWWTPs.

    6.2.4ImpactsonGroundwaterDuringtheoperationstage,possibleleakageofsewagepipelinesandWWTPfacilitiesmayresultinpollutiontogroundwater.Tominimizesuchimpacts,mitigationmeasureswillinclude: Ensureanti‐seepagedesignofWWTPfacilitieswithimpermeablefoundationsfor

    buildings; Strengthenroutinemonitoringandmaintenanceinspection; Developemergencyresponseplan6.2.5ImpactsofSolidWasteThemainsolidwasteoftheprojectduringoperationisfromWWTPs,includingdebrisfromscreensandsludge,andsmallamountsofgarbagefromworkingstaff.Thesesolidwasteswillbesenttoexistinglocalsanitarylandfillsforfinaldisposal,andthuslittleimpactisexpected.6.2.6ImpactonEcologicalEnvironmentTheprojectwillleadtoachangeoflandusepatternintheprojectareas,i.e.convertingruralecologicalenvironmentintourbanandindustrialenvironment.Thesurfacevegetationofruralcropsandtreeswillbereplacedbyurbanbuilt‐uparea,whichwillleadtoanetdecreaseofgreenfieldandvegetation.Thisisaplannedprocessaccordingtolocaldevelopmentplans,andsuchimpactshavebeentakenintoconsiderationinthemasterplans.TheseinducedandcumulativeimpactswillbefurtherstudiesduringprojectimplementationundertheTAcomponent.6.3 InducedandCumulativeImpactsItcanbeconcludedthatthedirectenvironmentalandsocialimpactsoftheproposedprojectsarestraightforward,limitedinscopeandcanbereadilymitigatedwithwellknowmitigationmeasuresforconstructionandoperationmanagement.Themostchallengingaspectoftheproposedprojectistheinducedandcumulativeimpactsfromfuturedevelopmentintheprojectareas,i.e.rapidurbanizationandindustrializationtowhichtheproposedprojectwillsupport.Suchimpactswillbebeyondthedirectareaofinfluenceoftheproject,andifnotwelladdressed,significantadverseenvironmentalandsocialconsequencescanbeexpectedfromalong‐termpointofview.

  • China:SichuanandChongqingCooperation:Guang’anDemonstrationAreaInfrastructureDevelopmentProject

    - 30 -

    6.3.1InitialAssessmentofInducedandCumulativeImpactsReviewofCurrentDevelopmentLinshuiCurrently,LinshuiCountyhasatotalareaof1,919km2andpopulationof1.03million.Theurbanbuilt‐upareaofLinshuitownis11.12km2,withapopulationof170,000.TheLinshuiETDZwasestablishedin2006,andsofartheETDZhasadevelopedareaof7km2.About60industrialenterprisesenteredtheETDZ,includingagriculturalproductsprocessing,machinerymanufacturing,electricandinformation,sparepartsfortrainsandcars,non‐ferrousmetalmetallurgyandprocessingindustries.Basedonstatistics,thetotalpollutionemissionstatusinLinshuiis:industrialsourceCOD465.27t/a,NH3‐N26.8t/a,andmunicipalsourceCOD420.48t/a,NH3‐N42.05t/a;industrialsourceSO21,173.05t/a,NO2327.18t/a,dust993.4t/a,andmunicipalsourceSO221.3t/aanddust20.8t/a.Comparingthecurrentambientenvironmentalqualityofair,surfacewater,groundwaterandnoisewiththatofMarch2012,allmonitoredparameterscanmeettherelevantapplicableenvironmentalstandards.Thereisaslightimprovementofsurfacewater,airandgroundwater,whilethereisageneralincreaseinnoiselevelsduetonewroaddevelopmentintheETDZ.ItcanbeconcludedthatdevelopmentoftheETDZdidnotcausesignificantenvironmentalimpacts,whichcanbeattributedtotheemphasisplacedonenvironmentalmanagementconceptsbytheETDZauthority,i.e.restrictingenterprisestolightpolluting,labourintensiveandtechnology‐orientedindustries;promotingcleanenergy;andprovidingenvironmentalinfrastructureincludingtheWWTPandlandfill.QianfengQianfengDistrictisanewlyestablishedadministrativedistrictofGuang’anCity,approvedbytheStateCouncilin2013.AsofApril2014,thebuilt‐upareaofQianfengis5km2,withapopulationof170,000.TheindustrialparkofQianfengisinthesouthofthetown,andcurrentlyhas29enterprisescoveringsparepartsforautomobilesandmotorcycles,textilesandgarments.Accordingtoavailableemissionsdata,allenterprisesareincompliancewithapplicableemissionsstandards.Theemissionsoftheindustrialparkin2011were:industrialsourceCOD259.15t/a,NH3‐N31.76t/a,SO2328.45t/a,NOx105.75t/a;ruralnon‐pointsourceCOD111.2t/a,NH3‐N17.2t/a.Comparingthecurrentambientenvironmentalqualityofair,surfacewater,groundwaterandnoisewiththatof2011,allmonitoredparametersmeetrelevantapplicableenvironmentalstandards.

  • China:SichuanandChongqingCooperation:Guang’anDemonstrationAreaInfrastructureDevelopmentProject

    - 31 -

    FutureDevelopmentScenariosLinshuiAccordingtotheMasterPlanofLinshuiCounty(2009‐2030),Linshuihasanear‐termdevelopmentphasefor2014‐2019andalong‐termphasefor2020‐2030.Forthenear‐termphase,thebuilt‐upareaofLinshuiwillreach22km2,withmachinerymanufacturingandelectricandinformationasthedominantindustries.By2030,thebuilt‐upareaisexpectedtoincreaseto28.3km2,withthemainindustriesbeingstorageandlogistics,sparepartsfortrainsandnewenergycars,machinerymanufacturingandnon‐ferrousmetalmetallurgyandprocessingindustries.ThefuturedevelopmentplanisillustratedinFigure9.

    Figure9FutureDevelopmentPlanofLinshui

  • China:SichuanandChongqingCooperation:Guang’anDemonstrationAreaInfrastructureDevelopmentProject

    - 32 -

    QianfengAccordingtotheMasterPlanfortheIndustrialParkinQianfeng(2011‐2020),by2020,thebuilt‐upareawillreach35.48km2,withtwomaindevelopmentareasinbothnorthandsouth/southeastofthetown.Industrialenterprisesareplannedtofocusonautomobilespareparts,electronicproducts,garments,textilesandshoemanufacturing.ThefuturedevelopmentplanofQianfengisillustratedinFigure10EnvisagedInducedandCumulativeImpactsInitialassessmentofthepotentialinducedandcumulativeimpactsconcludedthatthefollowinglong‐termimpactsareenvisaged: Landusechangeandlossofgreenarea:therewillbesignificantlandusechange,i.e.

    thebuilt‐upareawillincreasefrom18km2to28.3km2inLinshuiandfrom5km2to35.48km2inQianfeng.Expansionoftheurbanandindustrialparkareawillconvertfarmland,andgreenspacesintourbanresidentialandindustrialbuildings.Sucha

    Figure10FutureDevelopmentPlanof Qianfeng

  • China:SichuanandChongqingCooperation:Guang’anDemonstrationAreaInfrastructureDevelopmentProject

    - 33 -

    changewillresultinlossofsurfacevegetation,turningaruralecologicalenvironmentintoanurbanbuilt‐upenvironment.Sincethelandismostlyagriculturallandwithintensivedisturbanceofhumanactivities,suchaconversionisunlikelytocausesignificantlossofnaturalhabitatsandregionalbiodiversity.

    Lossofagriculturalland:landuseconversionwillleadtolossofagriculturalland,thusreduceruralincomesoflocalfarmers.Suchachangeisaplannedresultthaturbanandindustrialdevelopmentintheprojectareawillconvertrurallivelihoodtourbanandindustrialemploymentwhichwillprovidehigher,non‐farmincomesforlocalpeople.

    Airpollution:apreliminarysimulationoftheworstcasescenario(i.e.allenterprisesusecoalasenergysources)indicatesthatairqualityintheprojectareascanmaintainitscompliancewithrelevantstandards.Anatmosphericcarryingcapacitycalculationalsoindicatesthatlong‐termairpollutionwillbewithintheenvironmentalcapacityofthearea.

    Surfacewaterquality:increasedurbanizationandindustrializationwillleadtoincreasedwastewaterwhich,ifnotwelladdressed,willcausepollutionofsurfacewaterbodies.Suchanimpactisenvisagedinthemasterplan,andWWTPsareplannedtobeconstructed,includingNo.3WWTPincludedintheproject.AdetailedenvironmentalcarryingcapacityofBajiaoRiverinLinshuiandLuxiRiverinQianfengiscalculatedintheEIAanditconfirmedthatthereisenoughcapacitytoaccommodatetheinducedincreaseofwastewater.

    Groundwater:GroundwaterreservesinLinshuiarenotrich,neitheraretheydevelopedaswaterresources.Groundwaterisrechargedbyriversandprecipitation.ThedevelopmentoftheETDZwillconvertnaturallandsurfacetoimpermeablesurface(buildingsorpavedroads),thuswillhaveimpactontheseepageofstormwaterasarechargingsourceforgroundwater.

    Solidwaste:Bothtownswillseeanincreaseinsolidwastegenerationfromboth

    municipalandindustrialsources.Itisenvisagedthattheexistingandplannedlandfillfacilitieswillhavethecapacitytohandletheincreasedsolidwaste.

    Regionaldrainage:Theplanneddevelopmentwillnotoccupynaturalriverchannels,

    thuswillnothavesignificantimpactonregionaldrainagepatterns.Whileduetolandusechange,morestormwatersurfacerunoffmayendupinriverssincelesscanseepintotheground.Thiswillincreaselocalfloodingprobabilitiesandhastobetakenintoaccountinthedesignandbuildingofdrainagesystem.

    Socialdevelopment:Itisenvisagedthattheurbanizationandindustrializationinboth

    LinshuiandQianfengwillsignificantlypromotelocalsocialdevelopmentbyprovidingbetterurbanandenvironmentalinfrastructure,creatingemploymentopportunitiesandimprovingthelivingenvironment.However,lossoffarmlandandagriculture‐

  • China:SichuanandChongqingCooperation:Guang’anDemonstrationAreaInfrastructureDevelopmentProject

    - 34 -

    basedlivelihoodsandconversiontourbanandindustrialbasedonespresentbothopportunitiesandchallengestolocalcommunities.

    6.3.2DetailedInducedandCumulativeImpactAssessmentBasedontheinitialassessmentofinducedandcumulativeimpactsassessment,bothLinshuiandQianfenghavehadsomeurbanexpansionandindustrialdevelopmentoverthepastyears.Theyalsohavemasterplansforfuturedevelopmentwithdifferenttimeframes.Theinducedandcumulativeimpactshavebeenscreenedandcouldbesignificantifurbanandindustrialdevelopmentisnotwellplanned.Thetwotownshavetakenactionstoaddresstheseissues,includingstipulatingdevelopmentboundaries,buildingwastewatercollectionandtreatmentfacilities,solidwastefacilities,restrictingenterprisestolightpolluting,laborintensiveindustries,buildingenvironmentalmonitoringandmanagementinstitutions.However,rapidurbanexpansionandindustrialdevelopmentareusuallyassociatedwithdeteriorationinenvironmentalqualityaroundcoreurbanareaswithpotentiallong‐termconsequencesonlocalcommunities.Theprojectwillsupportatechnicalassistanceactivitytoconductfollow‐upcumulativeimpactsassessmentduringprojectimplementationfollowingacontinuousstep‐by‐stepprocessbasedonthestatusofdevelopmentandcapacitiesofthelocalauthorities.Thiseffortwilltakeintoaccountahybridofinduced,cumulativeandstrategicissuesrelatedtotheurbanandindustrialdevelopmentsinthetwotowns,andenableamoredetailedassessmentthatisadaptivetoongoingactualdevelopmentsinthetwotowns.Itwillincludespecificmeasuresonhowindustries,wastes,andpollutionwillbemonitoredandhowtoguideindustrydevelopmentduringimplementation.Atermsofreferencehasbeendevelopedbuildinguponthepreliminaryassessmentalreadymade,andincludedintheEMP.

  • China:SichuanandChongqingCooperation:Guang’anDemonstrationAreaInfrastructureDevelopmentProject

    - 35 -

    7. PUBLICCONSULTATIONANDINFORMATIONDISCLOSUREPublicconsultationandinformationdisclosurehavebeenconductedfollowingnationallawsandregulations,aswellasWorldBanksafeguardspolicies.TworoundsofconsultationandinformationdisclosurewerecarriedoutduringApril–July2014throughacombinationofpublicmeetings,fieldinterviewsandquestionnairesurveysintheprojectaffectedcommunities.Priortoconsultations,briefprojectinformation,environmentalimpactsandmitigationmeasuresaswellaslinkageoffullenvironmentalimpactassessmentreportsweredisclosedthroughthewebsiteofGuang’anGovernment(http://www.gasfgw.gov.cn).Meanwhile,posterswereplacedinmaincommunitiesoftheprojectareas.Followingtheinformationdisclosure,publicconsultationswereconductedamongprojectaffectedcommunities,includingfieldinterviews,publicmeetingsandquestionnairessurveysamongthepublic.Intotal,morethan550projectaffectedpeopleparticipatedintheconsultation.Theprojectreceivedbroadsupportfromthepublicconsulted,mostofwhichexpressedstrongwishestospeedupthisinfrastructureandenvironmentalimprovementproject.Thekeyenvironmentalconcernsbythepublicmainlyfocuson: Properconstructionarrangementtominimizedust,noiseandvibrationimpacts; Trafficdisturbanceduringconstruction; Effectivemeasurestoreducenoiseduringoperationstage; Enhancedlandscapingandlivingenvironment;ThesepublicconcernshavebeengivendueconsiderationsintheEIA,andnecessarymitigationmeasureshavebeendevelopedintheEnvironmentalManagementPlans(EMPs)toavoid,minimize,mitigateorcompensatetheadverseimpacts.

    Figure11PublicConsultationandInformationDisclosureinProjectAreasTherevisedfulldraftEIAreportsforbothLinshuiandQianfengcomponentswerelocallydisclosedonAugust2222,2014atthewebsiteofGuang’anDRC,withnewspaper

  • China:SichuanandChongqingCooperation:Guang’anDemonstrationAreaInfrastructureDevelopmentProject

    - 36 -

    announcementonGuang’anDailyonAugust23,2014.ThedraftRAPswerelocallydisclosedinGuang’anonAugust25,2014.

  • China:SichuanandChongqingCooperation:Guang’anDemonstrationAreaInfrastructureDevelopmentProject

    - 37 -

    8. ENVIRONMENTALMANAGEMENTPLAN(EMP)Astand‐aloneEnvironmentalManagementPlan(EMP)hasbeendevelopedforLinshuiandQainfengcomponentrespectively,whichspecifiesenvironmentalmanagementandsupervisionrolesandresponsibilities,mitigationmeasures,environmentalmonitoring,capacitybuildingprogramsandEMPbudget.8.1 RolesandResponsibilitiesTheimplementationoftheEMPrequirestheinvolvementofmultistakeholders(Figure12),eachfulfillingadifferentbutvitalroletoensureeffectiveenvironmentalmanagementfortheproject.

    Figure12EnvironmentalManagementStructureoftheProject

    LinshuiYuanfengIndustrialDevelopmentCo.QianfengXinhongIndustrialInvestmentCo.

    (ProjectOwners)

    IndependentEnvironmentalConsultant

    EnvironmentalSupervisionEngineer

    EnvironmentalMonitoringConsultant

    Contractors

    Guang’anPMO

    ProjectOperators

    Linshuicomponent‐PMOQainfengcomponent‐PMO

    Guang’anEPB

    ConstructionStage OperationStage

  • China:SichuanandChongqingCooperation:Guang’anDemonstrationAreaInfrastructureDevelopmentProject

    - 38 -

    Table6KeyEnvironmentalManagementResponsibilities

    Stakeholder Responsibility

    Guang’anPMO Overallcoordinationofprojectimplementation; Overallresponsibleforimplementationofenvironmental

    managementplans LiaisonandreporttoWorldBankonimplementationof

    environmentalmanagementplans

    LinhsuiComponentPMOQianfengComponentPMO

    Responsibleforenvironmentalmanagementofitscomponent; EnsureEMPmitigationmeasuresbeincorporatedintobidding

    documentsandconstructioncontracts; Ensureenvironmentalsupervisionrequirementsbe

    incorporatedintosupervisioncontracts; Supervisetheimplementationofenvironmentalmitigation

    measuresbycontractors; Organizeandcoordinatesafeguardstrainings; EntrustexternalenvironmentconsultanttomonitortheEMP

    implementation; Entrustexternalenvironmentmonitoringinstitutetomonitor

    ambientenvironment.

    Projectowners Superviseenvironmentalperformanceofcontractors; TracktheEMPimplementationprogressandreporttolocal

    PMOs; Receive,investigateandhandleandpubliccomplaints

    Constructioncontractors

    Developdetailedenvironmentalmanagementplansforconstructionworks;

    Implementmitigationmeasuresasperbiddingdocuments,contractandEMPs;

    Receivesupervisionandguidancefromprojectowner,environmentalsupervisionengineersandlocalgovernments;

    Conductpublicconsultationduringconstruction

    EnvironmentalSupervisionEngineers

    ReviewdesigntoensurecompliancewithEMPrequirements; SupervisetheimplementationofEMPmeasuresby

    contractorsaspercontractrequirementsandprovideguidance;

    Verifytheeffectivenessofcontractor’simplementationEMP; ReporttoprojectownersabouttheEMPimplementation; VerifyandapprovepaymentbasedonEMPimplementation.

    IndependentEnvironmentalConsultant

    Conductperiodicindependentsupervisionontheenvironmentalperformanceofcontractorandsupervisionengineers;

    ProviderecommendationstoprojectownersonimprovementofEMPimplementation;

    AssistPMOtoprovidesemi‐annualenvironmentalreporttotheWorldBank.

    EnvironmentMonitoringConsultant

    ConductenvironmentalmonitoringaccordingtothemonitoringplaninEMP;

    Conductadhocmonitoringuponrequestofprojectowners.Operators ManagetheoperationofWWTPsandroads

    EnsureenvironmentalcomplianceofWWTPs

  • China:SichuanandChongqingCooperation:Guang’anDemonstrationAreaInfrastructureDevelopmentProject

    - 39 -

    8.2 MitigationMeasuresMitigationmeasureshavebeendevelopedforeachcomponentcoveringthefullcycleofprojectpreparation,constructionandoperation.Thedevelopmentofmitigationmeasuresfollowsnationallaws/regulations,technicalguidelinesandconstructionnorms,withreferencestoprevioussimilarprojectexperiencesandWorldBanksafeguardspoliciesandEnvironmental,Health,andSafetyGeneralGuidelines,Environmental,Health,andSafetyGuidelinesforWaterandSanitation,Environmental,Health,andSafetyGuidelinesforTollRoadandSanitationandEnvironmental,Health,andSafetyGuidelinesforWasteManagementFacilities.ThesemitigationmeasuresaredevelopedinseparateEMPsforLinshuiandQianfengcomponents,andwillbeincorporatedintothebiddingdocumentsandcontractstoensureeffectiveimplementation.Fordetailsofthemitigationmeasures,pleaserefertotheEMPsintheprojectfile.8.3 ManagementofContractorsContractorswillplayakeyroleinenvironmentalmanagement,pollutioncontrolandimpactmitigationduringconstruction.Duringtheconstructionperiod,contractorsaremainlyresponsibleforeffectiveimplementationofenvironmentalprotectionandpollutionmitigationmeasures.Therefore,environmentalawarenessandcapacityofcontractorsarecriticalforthegoodenvironmentalperformanceoftheproject.Inordertoensurestrongenvironmentalcapacityandsmoothimplementationofenvironmentalprotectionmeasures,thefollowingcontractormanagementmeasureswillbeimplemented:1) Duringpre‐qualification,environmentalmanagementwillbeincludedinthe

    authenticationclausewhenthecontractor’squalificationisreviewed.Underthesamecondition,priorityshallbegiventothebidderswhohavepassedtheISO9000andISO14000authentication;

    2) Inpreparationofbiddingdocuments,theprojectownerwillensuremitigationmeasuresincludedintheEMParefullyincorporated,andrequirethepotentialbidderstopreparethebidsthatfullycoverthebudgetaryestimatesforEMPimplementation.Therefore,theimplementationoftheenvironmentalprotectionmeasureswillbecometheobligationandresponsibilityofthesuccessfulbidder;

    3) EveryContractorwillberequiredtoprovidededicatedenvironmentalstaffoneachsectionoftheProject.Inordertobequalifiedforthejob,theenvironmentalstaffwillreceiveanenvironmentaltrainingprogrampriortoconstruction;

    4) Priortoconstruction,theContractorsarerequiredtosubmitsite‐specificEnvironmentalProtectionImplementationPlanandEnvironmentalProtection

  • China:SichuanandChongqingCooperation:Guang’anDemonstrationAreaInfrastructureDevelopmentProject

    - 40 -

    ConstructionOrganizationPlanforkeyprojectactivitieswithpotentialimpacts(ifany).ThePlansshalldemonstratecompliancewithdomesticenvironmentalregulations,themitigationmeasuresspecifiedintheEMP.TheplansshallprovidedetailssuchascommitmenttoenvironmentalprotectionbytheContractor’sprojectmanagementteam;methodologyofimplementingtheprojectEMP;detaileddesignsandinstallationofpollutioncontrolfacilities(e.g.drainagechannel,settlingtank,etc.);environmentalcontrolmechanism;detailedearthworksmanagementplansandsiteoperationplansoutliningthemeasuresthatareproposedtominimize,mitigateandmanagetheeffects,forthedurationoftheconstructionworks;andenvironmentalmonitoringprogramduringdifferentstagesofconstructionperiod.

    5) Priortothecommencementofconstruction,theContractorshallreceiveadequatetrainingonEMPandrelevantregulations.

    8.4 EnvironmentalMonitoringPlanAnenvironmentalmonitoringplanhasbeendevelopedtomonitorambientenvironmentalqualityandpollutiondischargeduringconstructionandoperation.Projectownerswillhirelicensedenvironmentalmonitoringconsultantstoconductmonitoring,andprovidemonitoringresultstolocalEPBsandtheWorldBank.ThemonitoringplansforLinshuiandQianfengaresummarizedinTable7.

    Table7EnvironmentalMonitoringPlanforLinshuiandQianfeng

    Stage Item Locations Parameters Frequency

    Construction

    AirMajorconstructionactivitiesnearsensitivesites

    TSPRandombasedonconstructionprogress

    NoiseMajorconstructionactivitiesnearsensitivesites

    LeqdB(A) Onceamonth

    Water Riversectionsnearconstructionsites COD,BOD5,SS,oil Quarterly

    Soilerosion

    Majorexcavationandbackfillingareas

    Areasofdisturbance;protectionmeasures;soilerosionstatus

    Monthlyforareasofdisturbance;quarterlyforsoilerosionfactormonitoring.

    Operation Noise Sensitivereceptorsofcommunities LeqdB(A) Quarterly

    Water EffluentdischargeoutletanddownstreamriverpH,CODCr,BOD5,NH3‐N,TP

    Continuousmonitoringforoutlet;monthlyfordownstreamriver

  • China:SichuanandChongqingCooperation:Guang’anDemonstrationAreaInfrastructureDevelopmentProject

    - 41 -

    Air DownwinddirectionattheboundaryofWWTPs H2S,NH3‐N,andodor Quarterly

    SoilerosionDrainageditchslopes,greenbeltalongroads/abovepipelines,WWTPsites

    Slopeprotection,erosioncontrolmeasures,greenspaceandsurvivalofplanation,cleannessofWWTP

    Quarterly

    8.5 EnvironmentalReportingDuringprojectimplementation,withassistanceoftheIndependentEnvironmentalConsultant,thePMOs/projectownersarerequiredtoprovideenvironmentalmonitoringreportstotheGuang’anEnvironmentalProtectionBureau(EPB)andtheWorldBank.ThepurposeofsuchreportingistoensureeffectiveimplementationofEMPmitigationmeasures,identifyanyinadequacyorproblemsatearlystagesinordertoimplementtimelyremedialaction,andlearnexperiences/lessonstoguidefutureworks.Themaincontentsofthereportinclude:1) Descriptionofprojectprogress;2) Environmentalmanagementorganizationsetupandresponsibilities;3) Keyconstructionactivities,associatedenvironmentalimpactsandactual

    implementationofEMPmitigationmeasures,includinganyproblemsandremedialactionsorplans;

    4) Implementationofenvironmentalmonitoringplanandkeyresults;5) Anypubliccomplaints(records,resolutionandpublicfeedback);Duringconstruction,contractorsandsupervisionengineersarerequiredtoprovideperiodicenvironmentalreportstotheprojectowners.8.6 EnvironmentalTrainingPlanEnvironmentalcapacitytrainingisanimportantpartoftheenvironmentalmanagementoftheproject,whichwillbeprovidedtoenvironmentalmanagementandsupervisionstaffinthePMO,projectowners,contractors,supervisionengineers.Priortocommencementofconstruction,Guang’anPMO/LinshuiandQianfengPMOsshallorganizeenvironmentaltrainingforcontractorsandworkers,aswellassupervisionengineersandprojectmanagementstaffinPMOsandprojectowners.8.7 EMPBudgetAllmitigationmeasureshavebeenbudgetedandfullyincorporatedinprojectcostsincludingmonitoringandsupervision.ThetotalEMPbudgetestimatefortheprojectisRMB87,955,500forLinshuiandRMB86,275,900forQianfeng,i.e.10.3%and14.9%oftotalprojectinvestment.

  • China:SichuanandChongqingCooperation:Guang’anDemonstrationAreaInfrastructureDevelopmentProject

    - 42 -

    ThedetailedEMPbudgetisshowninTable8.

    Table8EMPBudgetEstimate

    Stage Item Investment(RMB)Linshui Qianfeng

    Construction

    CommunityMedia,notice 100,000 100,000Bulletinboardsatconstructionsite 100,000 100,000

    SoilerosionStorageofearth/spoil

    69,744,000 61,430,000VegetationrestorationBulkmaterialcoverMonitoring 485,000 460,000

    DustWaterspraying 100,000 100,000Dustcontrolmeasures 100,000 100,000Monitoring 50,000 50,000

    WastewaterConstructionwastewater 300,000 50,000Monitoring 50,000 50,000Noise Noisereduction/barriersetc. 50,000 300,000Monitoring 50,000 50,000Solidwaste Spoilbackfilling 1,000,000 1,200,000Garbagedisposal 100,000 50,000Environmentalsupervision 600,000 550,000Independentenvironmentalconsultant 400,000 360,000Sub‐total 73,139,000 64,950,000

    Operation

    Ecology Greening 12,606,500 19,675,900Air Odorcontrolfacility 710,000 350,000Monitoring(1styear) 200,000 100,000Noise Noisecontrol 400,000 200,000Monitoring(1styear) 100,000 50,000Water Anti‐seepagemeasures 200,000 400,000Monitoring(1styear) 100,000 50,000Sub‐total 14,316,500 20,825,900

    Environmentaltraining 500,000 500,000Total 87,955,500 86,275,900

    TotalProjectInvestment 854,457,400 578,764,600PercentageofEMPbudgetintotalinvestment 10.3% 14.9%