5
Euston Demolitions and Utilities Jack Lawrence Community Engagement Manager

Euston Demolitions and Utilities · London Euston North Ibis Hotel • The Ibis has been demolished, • The site is now processing material from the tower demolitions. • This will

  • Upload
    others

  • View
    9

  • Download
    1

Embed Size (px)

Citation preview

Page 1: Euston Demolitions and Utilities · London Euston North Ibis Hotel • The Ibis has been demolished, • The site is now processing material from the tower demolitions. • This will

Euston Demolitions and Utilities

Jack Lawrence

Community Engagement Manager

Page 2: Euston Demolitions and Utilities · London Euston North Ibis Hotel • The Ibis has been demolished, • The site is now processing material from the tower demolitions. • This will

London

Euston South

Wolfson House

• A tower crane

dedicated to Wolfson

House was erected at

the end of July

• This crane will allow

the demolition to

proceed

independently from

Walkden House.

Walkden House

• Demolition is

underway, with the

structure being saw-

cut into sections.

The Towers

• Structural demolition

of Grant Thornton

House commenced

in early July

• One Euston Square

in early August.

• Demolition is due to

complete mid-2020.

2

Page 3: Euston Demolitions and Utilities · London Euston North Ibis Hotel • The Ibis has been demolished, • The site is now processing material from the tower demolitions. • This will

London

Euston North

Ibis Hotel

• The Ibis has been

demolished,

• The site is now

processing material

from the tower

demolitions.

• This will remove

around 600 lorry

movements.

St James’s Gardens

• The first section of archaeological excavations is complete and

the tent structure that shielded the works has been removed.

• Archaeological excavations will continue under Cardington

Street and up to the Thistle boundary wall.

• These works will also need to be shielded from public view.

Thistle Hotel

• Demolition is

progressing well.

• Demolition is due to

complete in

November 2019.

.

3

Page 4: Euston Demolitions and Utilities · London Euston North Ibis Hotel • The Ibis has been demolished, • The site is now processing material from the tower demolitions. • This will

North Gower Street utilities North Gower Street utilities – Utilities works between Drummond Street

and Stephenson Way

• Phase one: 21 October to 15 November - Southbound lane, between the

junctions of Drummond Street and Euston Street.

• Phase two: 18 November to 13 December - Northbound lane, between

the junctions of Drummond Street and Euston Street.

• Phase three: 16 December to 31 January 2020 – Southbound lane

between the junctions of Euston Street and Stephenson Way.

• Phase four: 2 February to 28 February 2020 – Northbound lane between

the junctions of Euston Street and Stephenson Way.

North Gower Street – utility works between Hampstead Road and

Starcross Street

• Phase one: 21 November to 20 December – between the junctions of

Hampstead Road and Starcross Street.

• Phase two: 6 January to 16 January – Between Starcross Street and the

junction with Drummond Street.

Page 5: Euston Demolitions and Utilities · London Euston North Ibis Hotel • The Ibis has been demolished, • The site is now processing material from the tower demolitions. • This will

Eversholt Street 16’’ water main relining

• Thames Water need to carry out further

works on the water main on Eversholt

Street – starting 14 October (3 week

closure)

• HS2 works to reline the Thames Water

main on Eversholt Street will follow only

once the Thames Water work is

successfully completed

• The HS2 works are estimated to start

around the beginning of November