Upload
kevin-steinbach
View
47
Download
3
Embed Size (px)
DESCRIPTION
N/A
Citation preview
ESP – Electric Submersible Pumps
• Candidates
• Sizing
• Application
• Operation
• Special Uses
8/25/2015 1 George E. King Engineering
GEKEngineering.com
ESP Well Candidates
• Can be run vertically to fully horizontal
• Capable of moving fluid volumes of 20,000 BPD+
• Cannot handle large amounts of gas and solids.
• Must be landed in a straight section of the wellbore.
8/25/2015 2 George E. King Engineering
GEKEngineering.com
Electrical Submersible Pumps ESPs
• ESPs are best used moving large volumes (>500 stb/d) of low GLR fluid (<100 scf/stb). They perform best when within +/- 25% of design rate.
• ESPs are particularly attractive for water supply wells, high water-cut producers and high deliverability, under-saturated oil wells.
• ESPs have moderate run life performance that can be significantly increase by instrumenting with temperature sensors that trip the pump power supply when cooling ability (flow) drops.
• Variable frequency drives (VFD) and/or wellhead chokes can be
used to increase the range of pumping rates (50 to 190% of
optimum), but increase capital and operating costs.
8/25/2015 3 George E. King Engineering
GEKEngineering.com
ESPs
• A submersible pump is a multi-staged centrifugal pump
connected by a short shaft to a downhole electric or
hydraulic motor.
• Each stage consists of a rotating impeller and stationary
diffuser.
8/25/2015 4 George E. King Engineering
GEKEngineering.com
ESPs
• Each impeller and diffuser stage is about 3 to 5 in long, and there may be 50 to 500 stages in a pump.
• The ESP is a dynamic displacement pump in which the differential pressure or total dynamic head (TDH) developed by the pump is a function of pump flow rate.
• TDH is approximately the sum of the head developed by each stage, which can be obtained from the manufacturers published test data.
TDH = Ns Hs
where: Ns = number of stages
Hs = head per stage
8/25/2015 5 George E. King Engineering
GEKEngineering.com
ESP Performance
• ESP pump characteristics are based on a constant
rotation speed, which depends on the frequency of the
AC supply:
– 3500 RPM with 60 Hertz
– 2915 RPM with 50 Hertz
• Because of high rotation speeds, sand production and
emulsions must be controlled.
• Field application of ESPs in silt producing areas (North
Africa) have been made, but start-up/shut-down cycles
had to be minimized.
8/25/2015 6
George E. King Engineering GEKEngineering.com
ESP Delivery Capacity
• Variables:
– Well IPR characteristics. Constant flow for cooling is essential.
– Reservoir pressure. Impacts both flow rate & gas breakout.
– Surface back-pressure. – Controls free gas at the pump.
– Electrical supply frequency –variations are a problem (lightning strikes, power stability, etc.)
– Pump size – larger pumps are more efficient, cheaper to buyt and cheaper to operate.
– Produced fluid viscosity – high viscosity decreases efficiency
8/25/2015 7 George E. King Engineering
GEKEngineering.com
Gas Effect on an ESP
• Gas may create a gas lock condition - or insufficient fluid movement to cool the pump.
• An ESP installation should be designed to allow downhole separation of any free gas before entering the pump inlet.
• The gas is vented up the annulus in most cases. This is particularly important when the downhole gas volume exceeds 10% of the total fluid volume.
• Gas busters, downhole separators, set points below the perfs and oversized initial stages have been used to control excess gas.
8/25/2015 8 George E. King Engineering
GEKEngineering.com
ESP Failures - Heat
• The conversion of electrical current to mechanical
energy produces significant heat.
• The produced fluids must dissipate the heat from the
pump or failures will occur. Since the downhole fluids
are often already hot, flow rate must be high to transfer
maximum heat (velocity > 1 ft/sec)
• If the pump must be set below the perfs or in large
casing (low flow velocity), a shroud is often used to
increase velocity and cool the motor.
8/25/2015 9 George E. King Engineering
GEKEngineering.com
ESP Considerations
• A minimum BHFP of 100 to 200 psi is normally recommended to prevent cavitation or gas locking.
• A large number of restarts (50 to 200) significantly reduces run life.
• ESP cables must be supported by banding to the tubing and protected at the couplings and other pinch points.
8/25/2015 10 George E. King Engineering
GEKEngineering.com
ESP – Short Run Life Causes
1. Poor handling procedures – cable breaks.
2. Inadequate flow for cooling
3. Inadequate cable insulation for the operating environment.
4. Pumping significant quantities (>10%) of free gas
5. Sand production or corrosion.
6. Frequent restarts without a soft start controller or VSD.
7. Scale formation on the pump impellers.
8. Omission of the viscosity considerations
9. Unstable supply voltage.
10. Not landing pump in a straight wellbore section.
8/25/2015 11 George E. King Engineering
GEKEngineering.com
Artificial Lift Comparative Efficiencies
12
18
3840
52
0
10
20
30
40
50
60
Intermittent GL
Continuous GL
ESP
Hydraulic Lift
Beam Lift
8/25/2015 12 George E. King Engineering
GEKEngineering.com
Brief Design Points for ESPs
• ESP design is a system approach:
– Tubing too small – high erosion/friction
– Tubing too large – gas slips through fluids
• Pump sizing software does not account for liquid hold-up and in extreme case a pump might be required to support a near full column of water in a dry well – pump would be understaged, operate in severe downthrust and suffer motor cooling problems.
BP ESP Best Practices Operating Guidelines - 2004 8/25/2015 13 George E. King Engineering
GEKEngineering.com
Brief Design Points for ESPs
• Motors that are not matched to surface electrical systems:
– May be limited in current or voltage.
– May not be able to tune the frequency of the pump to changing reservoir conditions.
BP ESP Best Practices Operating Guidelines - 2004 8/25/2015 14 George E. King Engineering
GEKEngineering.com
General Design Considerations ESP Pumps
• In general, the larger the diameter of the pump, the more efficient it will be. Consult performance curve of pump.
• Highly efficient pumps may have poor performance outside a narrow recommended operating range.
• If in doubt on well flow capacity, slightly undersize pump and choke well into the operating range of pump. – Cooling reliability increased
– Thrust loading control
BP ESP Best Practices Operating Guidelines - 2004 8/25/2015 15 George E. King Engineering
GEKEngineering.com
General Design Considerations ESP Motors
• In general, the larger the diameter of the motor, the more efficient it will be.
• For larger diameters, motors will be shorter. Less easily damaged.
• Motor winding insulation degrades at rate proportional to its operating temperature. Operating motors at less than 100% full current load factors reduces operating temp and increase motor life.
• If workover costs are high, it is generally cost effective to over specify the motor
BP ESP Best Practices Operating Guidelines - 2004 8/25/2015 16 George E. King Engineering
GEKEngineering.com
Types of ESP Cable
8/25/2015 17 George E. King Engineering
GEKEngineering.com
ESP cable pass through capability in a roller centralizer
8/25/2015 18 George E. King Engineering
GEKEngineering.com
ESPs in High GOR Wells
• Gas separators/handlers (also called gas busters and diffusers) deployed individually or in series
• Annular venting possible in packerless completions. Reduces free gas at intake.
BP ESP Best Practices Operating Guidelines - 2004 8/25/2015 19 George E. King Engineering
GEKEngineering.com
ESPs in High GOR Wells
• Mixed flow stage designs are less susceptible to gas locking than equivalent radial stages.
• Should be sized to operate at total fluid flow rates (liquid and gas) at upper end of the recommended flow range.
– Maximizes natural gas lift and reduces hydrostatic head (backpressure) on pump.
BP ESP Best Practices Operating Guidelines - 2004 8/25/2015 20 George E. King Engineering
GEKEngineering.com
ESPs in Solids Producing Wells
• Mixed flow stages preferred.
• Abrasion resistant pump bushings and impeller coatings.
• Plugging and sticking of pump may be severe.
• Avoid shut-downs.
BP ESP Best Practices Operating Guidelines - 2004 8/25/2015 21 George E. King Engineering
GEKEngineering.com
Artificial LIft ESP Power Distribution
Pump
37.0%Motor
15.0%
Surface
1.5%
Cable
7.0%
Output
38.5%
Pump
Motor
Surface
Cable
Output
8/25/2015 22 George E. King Engineering
GEKEngineering.com
ESP - Gas Solutions
• gas diffusers
• gas separators
• dip tubes
• set below the lateral
8/25/2015 23 George E. King Engineering
GEKEngineering.com
ESP
• Problems
– depth limited
– power requirements
– cable clearance
– large casing required (large pump sizes)
– doesn’t handle gas or solids well
8/25/2015 24 George E. King Engineering
GEKEngineering.com
ESP – Initial Design
1. Chose Production Rate (well PI, reservoir pressure and bubble point)
2. Determine bottom hole flowing pressure (bhfp) at perfs.
3. Set pump depth so that pressure at pump intake is at limit of free gas handling capacity of the pump.
BP ESP Best Practices Operating Guidelines - 2004 8/25/2015 25 George E. King Engineering
GEKEngineering.com
ESP – Initial Design
4. Check head requirement of the pump.
• Chose stage count and frequency so that pump operates at its best efficiency point.
• Frequency should be as close as possible to 60 hz to get max power from the motor.
Below 650 hz: power = rated hp x (running frequency / 60)
Above 60 hz, motor current is derated to reduce heating
BP ESP Best Practices Operating Guidelines - 2004 8/25/2015 26 George E. King Engineering
GEKEngineering.com
ESP – Initial Design
5. Check expected motor loading – if load is too high, the initial production rate is too high
and should be decreased slightly.
– If load is too low, there is potential to increase the designed flow rate
– If the flowrate takes the flowing pressure below the bubble point pressure, then a smaller motor is possible.
6. Iterate the design. • If rate is decreased, the bhfp will increase and the pump
can be raised in the well to keep the same intake pressure (if needed to optimize flow).
BP ESP Best Practices Operating Guidelines - 2004 8/25/2015 27 George E. King Engineering
GEKEngineering.com
ESP – Final Design
1. Pump operating at free gas limit
2. The motor is fully loaded
3. Pump flowrate is as close as possible to BEP
4. Motor is close to 60 hz
5. Cable heat, volts drop, motor shaft torque, pump shaft torque, and pump housing pressure differential are OK.
6. Pump position is not across doglegs.
BP ESP Best Practices Operating Guidelines - 2004 8/25/2015 28 George E. King Engineering
GEKEngineering.com
Cable Protection - Cable run on the outside of tubing
• Use clamp-on cross-coupling protectors. If bands are used, band 4 ft above and below coupling.
• Avoid use of most types of mid joint clamps for the majority of applications – they can turn and slide, damaging ESP cables.
• Use extra care in any banding to fasten the ESP cable to the tubing. Clamps are preferred to banding because of problems leaving broken banding materials in the well.
8/25/2015 29 George E. King Engineering
GEKEngineering.com
Cable Protection - Cable run on the outside of tubing
• COUNT – count and record the number of bands and clamps as the ESP is run. Count them as they come out so you have an idea of what is remaining in the hole.
8/25/2015 30 George E. King Engineering
GEKEngineering.com
ESP Startup Procedures
1. If a restart, correct what caused trip.
2. Allow time for pressure across pump to equalize. Backflowing fluid will cause the pump to backspin,
8/25/2015 31 George E. King Engineering
GEKEngineering.com
BP Global ESP summary
ESP Global active/inactive summary
0
50
100
150
200
250
300
Gupco Forties China DZO VEN Wytch Farm Indonesia Milne point PAE
Active Esp
Inactive Esp
Production Gross(mboed)
Asset Active Esp Inactive Esp Total ESP Production Gross(mboed) Production Net(mboed)
Forties 9 12 21 9.6 9.312
DZO VEN 34 3 37 18 18
Gupco 6 0 6 5 2.38
China 20 3 23 14 3.43
Indonesia 16 102 118 2.9 1.334
PAE 291 0 291 11.4 6.84
Wytch Farm 36 5 41 55 37.2955
Milne point 110 12 122 45 45
Sidanco 700 1800 2500 50 12.5
Total 1222 1937 3159 210.9 136.0915
•Some areas have low oil but high gross fluids(water)e.g PAE 386mbpf/d
•Some areas rely on ESP’s as water source wells (China/Gupco/Harding)
8/25/2015 32 George E. King Engineering
GEKEngineering.com
ESP Sealing Options
• Labyrinth Seals
– Avoid in high angle wells.
• Bag seals
– Avoid in vertical wells, especially if the well fluids will react with the seals.
• Tandem Seals
– Increased reliability. Friction increased?
BP ESP Best Practices Operating Guidelines - 2004 8/25/2015 33 George E. King Engineering
GEKEngineering.com
Special Case – Coiled Tubing Deployed ESP - Qatar Example
• Arco Field (Al Rayyan)– Schlumberger Service
8/25/2015 34 George E. King Engineering
GEKEngineering.com
8/25/2015
Qatar Example: Reservoir Fluid Properties
• Oil Gravity - 23o API
• GOR < 50 scf/bbl
• Viscosity > 10 cp
• BHT 155 0 F
• TVD 3,000 - 4,500 ft
• H2S 3.5%
• CO2 3.5%
35 George E. King Engineering
GEKEngineering.com
8/25/2015
Qatar Well Characteristics • 9-5/8 Casing
• 7 liner
• SCSSV, Chemical Injection, Permanent Guage
• Pump in Tangent Section (0, 38 - 63) deg
• Horizontal Section Though the Pay Zone
• Cable Internal
• Seating Shoe
• Bottom Intake
• Annular Flow
36 George E. King Engineering
GEKEngineering.com
8/25/2015
Initial Well Completion Schematic
7" Liner x 4-1/2" Tubing Crossover
Chemical Injection MandrelGuage MandrelSCSSV
9-5/8" Casing
Seating shoe
7" Liner
Locking discharge head
Universal Motor Base
CT and Power Cable
Lower Connector
Motor
Protector
Pump
Intake
Lower Protector
37 George E. King Engineering
GEKEngineering.com
8/25/2015 38 George E. King Engineering
GEKEngineering.com
8/25/2015 39 George E. King Engineering
GEKEngineering.com
8/25/2015
Learnings
• Lower Connector needs improving – Short due to well fluid influx
• Well head problems – unplugging due to movement
• Cable Suspension – additional splices during workovers
• Protector – Well fluid into motor
40 George E. King Engineering
GEKEngineering.com
8/25/2015
AL Rayyan ESP Performance - All ESP Pulls
95
350
95
103
339
420
153
46
113
602
108
49
50
42
194
84
235
304
327
8
189
281
72
448
485
232
220
377
79
315
153
2
22
0
30
60
90
120
150
180
210
240
270
300
330
360
390
420
450
480
510
540
570
600
630
660
690
720
750
780
810
840
870
900
930
960
990
1020
1050
1080
1110
1140
1170
1200
1230
1260
1290
AR-4
AR-5
AR-6
AR-7
AR-9
AR-10
AR-14
AR-15
days since project start
9 November, 1996
Start date
28 February, 2000
End date
pump - metal LC LC elective - replace LC elective - increase ESP size
elective - w ater shut-off motor burn
motor-brush w ire LC motor burn Spinning diffusers
elective - replaceburst disc LC LC protector shaft spinning diffusers, UMB shaft, dropped pump, rig w orkover
motor burn UMB shaft hanger penetrator
spinning diffusers motor-rotor strike
motor burn
motor burn Elective Pull - Acid Job
coiled tubing - cable external
coiled tubing - cable external
coiled tubing - cable internal, installed cable external after stimulation
41 George E. King Engineering
GEKEngineering.com
8/25/2015
Lower Connector
• Redesigned
– uses field attachable components
– feed through
– seals motor from CT ID
– mechanical release
• Tested
– Pressure
– Shock loading
• Implemented in Q4 1997
– No electrical failures to date 42
George E. King Engineering GEKEngineering.com
8/25/2015
Wellhead Disconnect
• Power cable unplug from well head penetrator – movement of 1/2”
• Solution - Add wellhead extension – Added power cable
• Result - No electrical wellhead failures
43 George E. King Engineering
GEKEngineering.com
8/25/2015
Horizontal
Well Head
44 George E. King Engineering
GEKEngineering.com
8/25/2015
Cable Suspension
• Cable Anchors
– Move due to deformation
– Require splice during workovers
Power cable
Cable support system
Coiled tubing
45 George E. King Engineering
GEKEngineering.com
8/25/2015
Cable Suspension Solution
• Friction Deployed System
– relies on friction
between power cable and CT ID
– Simplifies cable
installation
– Developed model to predict slippage
46 George E. King Engineering
GEKEngineering.com
8/25/2015
Friction Deployed Testing
• 5,000 ft vertical well
• Simulated ESP equipment
• Load cell at the lower connector
• No fluid in CT
• Multiple runs
• Cut to measure slippage
• Electrically test power cable
47 George E. King Engineering
GEKEngineering.com
8/25/2015
Downhole Load Down Hole 3, 9/22/98 @1:21 pm
-400
-350
-300
-250
-200
-150
-100
-50
0
50
100
150
0 1000 2000 3000 4000 5000 6000
Depth (ft)
Lo
ad
(lb
s)
{Neg
ati
ve #
's =
Co
mp
ress
ion
}
48 George E. King Engineering
GEKEngineering.com
8/25/2015
Testing Results
• Compressive loads acceptable
• Slippage measured - 150” @ 10,000 ft
• Model verified
• Installed in 3 wells
49 George E. King Engineering
GEKEngineering.com
8/25/2015
Protector
• Well fluid in motor
– H2S
– Sludge
• Used several configurations
• Redesign
• Installed in 6 wells
– Running +300 days
50 George E. King Engineering
GEKEngineering.com
8/25/2015
Bolt on Head
Pump
Protector
Motor
UMB
Conventional ESP
Equipment
CTDESP Cable Internal with
Shrouded Intake
CTDESP Cable Internal
with Seating Shoe and
Discharge Head
Power Cable
Coiled Tubing
Coiled Tubing Lower
Connector
7” x 23#/ft CSG
Motor
Power Cable
Coiled Tubing
Coiled Tubing
Lower Connector
7” x 23#/ft CSG
Motor
Motor
UMB
UMB
Protector Protector
Discharge Head
Pump
Seating Shoe &
Lockdown Discharge
HeadPump
Intake
Thrust Section
Intake and
shroud hanger
Thrust Section
5-1/2” Shroud
with Seal Stinger
Packer
Figure 1 - Equipment Comparison Schematics
51 George E. King Engineering
GEKEngineering.com
8/25/2015
Figure 2 - Cable External Equipment
The equipment in Figure 2 can be interchanged
with the equipment above the motor in the
CTDESP systems shown in Figure 1. This allows
cable external to be run as either a shrouded
intake systems or a seating shoe system . The
well head configuration is different to handle the
cable outside the coiled tubing.
Power Cable
Coiled Tubing
Modified Rope
Socket
Sealing Chamber
7” Casing
Motor
52 George E. King Engineering
GEKEngineering.com
8/25/2015
CTDESP – Bottom Intake
Property Comparisons - Conventional ESP Vs CTDESPSystems
Property
Co
nven
tion
al E
SP
on
join
ted
tub
ing
Seatin
g s
ho
e,
cab
le in
tern
al
Sh
rou
ded
inta
ke,
cab
le in
tern
al
Seatin
g s
ho
e,
cab
le e
xte
rnal
Sh
rou
ded
Inta
ke,
cab
le e
xte
rnal
Cable protected from mechanical damage No Yes Yes No No
Cable exposed to well fluids Yes No No Yes Yes
Requires one cable splice (round to flat) Yes No No No No
Allows 5.62” OD equipment inside 7” 23 lb/ft casing No Yes Yes Yes Yes
Annular flow – reduced friction pressure No Yes Yes Yes Yes
Utilize gas separators Yes No No No No
All gas must go through pump No Yes Yes Yes Yes
Potential sticking due to sand fall out No No Yes No Yes
Requires horizontal tree No Yes Yes Yes Yes
Protector and motor at discharge pressure No Yes Yes Yes Yes
Corrosion resistant materials readily available Yes No No No No
72 hours workover or less No Yes Yes Yes Yes
Requires rig or snubbing unit for workover Yes No No No No
Fast workover equipment lead time No Yes Yes Yes Yes
Lower day rate CTU vs Rig No Yes Yes Yes Yes
ESP equipment may see compressive forces No Yes Yes Yes Yes
53 George E. King Engineering
GEKEngineering.com
8/25/2015
AL Rayyan ESP Performance - All ESP Pulls
95
350
95
103
339
420
153
46
113
602
108
49
50
42
194
84
235
304
327
8
189
281
72
448
485
232
220
377
79
315
153
2
22
0
30
60
90
120
150
180
210
240
270
300
330
360
390
420
450
480
510
540
570
600
630
660
690
720
750
780
810
840
870
900
930
960
990
1020
1050
1080
1110
1140
1170
1200
1230
1260
1290
AR-4
AR-5
AR-6
AR-7
AR-9
AR-10
AR-14
AR-15
days since project start
9 November, 1996
Start date
28 February, 2000
End date
pump - metal LC LC elective - replace LC elective - increase ESP size
elective - w ater shut-off motor burn
motor-brush w ire LC motor burn Spinning diffusers
elective - replaceburst disc LC LC protector shaft spinning diffusers, UMB shaft, dropped pump, rig w orkover
motor burn UMB shaft hanger penetrator
spinning diffusers motor-rotor strike
motor burn
motor burn Elective Pull - Acid Job
coiled tubing - cable external
coiled tubing - cable external
coiled tubing - cable internal, installed cable external after stimulation
54 George E. King Engineering
GEKEngineering.com
8/25/2015
Uptime
• Cumulative Uptime from project start - 93.4%
• Eliminate early failures - Uptime 94.5% – LC
– Wellhead
55 George E. King Engineering
GEKEngineering.com
8/25/2015
Figure 11 - Uptime Comparison(Based on 1 Workover)
80%
85%
90%
95%
100%
6 9 12 18 24 30 36 42 48 54 60Runtime Months
% U
pti
me
CT Internal - BI 14
Day MOB, 2.5 Day
Workover
Jointed Tubing -30
Day Rig MOB, 4
Day Workover
Jointed Tubing -60
Day Rig MOB, 4
Day Workover
56 George E. King Engineering
GEKEngineering.com
8/25/2015
Figure 12 - Workover Efficiency Improvement
• Operation Time Results
» Equipment rig up
» Make up of ESP and assembly to the CT
» Deployment of ESP into the hole
» Hang off REDACoil system
0
5
10
15
20
25
30
35
40
45
50
Well 1 Well 2 Well 3 Well 4 Well 5
Time(hr)
Source: Arco/Schlumberger: Patterson, McHugh, Pursel 57 George E. King Engineering
GEKEngineering.com