Upload
salim
View
54
Download
1
Embed Size (px)
DESCRIPTION
Eskom Energy Efficiency Programmes. Monkwe Mpye Eskom DSM Manager. Overview. Introduction DSM strategy Eskom energy efficiency programs CFLs SWH Energy efficient electric motor. Demand Profiles. Evening peak-to-date: 35 931 MW (14 th July 2008) !!!. Over the Years?. - PowerPoint PPT Presentation
Citation preview
Eskom Energy Efficiency Programmes
Monkwe Mpye
Eskom DSM Manager
Overview
• Introduction• DSM strategy• Eskom energy efficiency
programs– CFLs– SWH– Energy efficient electric motor
Demand Profiles
22000
24000
26000
28000
30000
32000
34000
36000
1 3 5 7 9 11 13 15 17 19 21 23 1 3 5 7 9 11 13 15 17 19 21 23
Time
MW
De
ma
nd
Winter 2007
Summer 2007
Evening peak-to-date: 35 931 MW (14th July 2008) !!!
Over the Years?
Residential Sector DSM 3-Year Plan
5
• The most cost effective technologies are Energy Efficient Lighting (CFLs), Aerated Showerheads and Smart Metering (limited to 20 Amps)
• Household Cooking conversion to gas is primarily constrained by the cost and availability of gas.
• Solar Water Heating (SWH) is constrained by lack of supplier capacity and higher costs.
Notes
Source: Avoided Generation Cost Model; Team Analysis
1.
Key:
Bubble Size: GWh Savings
Incentivised Programmes
Priority Areas
Commercial Sector DSM 3-Year Plan
6
• All technologies within the Commercial Sector are cost efficient.
Notes
Note: Scale not standardised relative to other sectorsSource: DSM Cost Model; Team Analysis
Key:
Bubble Size: GWh Savings
Incentivised Programmes
Priority Areas 1.
Industrial Sector DSM 3-Year Plan
7
• The Total Avoided Costs and the Project Costs per kWh for the Industrial Sector initiatives are nearly identical.
• Motor system efficiency initiatives however provide most MW savings and should therefore be the primary focus area of the sector.
Notes
Note: Scale not standardised relative to other sectorsSource: DSM Cost Model; Team Analysis
Key:
Bubble Size: GWh Savings
Incentivised Programmes
Priority Areas 1.
CFL Programs
2004/2005: 5 mil (national)
2006: 5.3 mil (CT) 2.5 mil (national)
2007: 4.5 mil (national)
2008/2009: 16.8 mil (national)
1999: Bonesa/Eskom/GEFCustomer education, advertising, and marketing.
2008: 0.7 milRetail program, nationalGame, PnP, Shoprite
2008: 1.3 milCorporate programLarge customers + Eskom staff
2008: 20 684 CFLsDefence department
CFL Rollouts: 2008/9 and Beyond
Eskom Region Completed
Due for completion
30 Nov.2008/9 Total
2009/10 Planned
Eastern - 2.5 million 2.5 million 0.25 million
Southern - 1.8 million 1.8 million 0.65 million
Western 1.2 million - 1.2 million 0.25 million
North West 1 million 2.3 million 3.3 million 0.5 million
Central - 4.2 million 4.2 million 1.5 million
Northern 1 million 2.8 million 3.8 million 5 million
Total 3.2 million 13.6 million 16.8 million 8.15 million
An estimated 15,750 temporary jobs will be created to support the 2008/9 roll out An estimated 15,750 temporary jobs will be created to support the 2008/9 roll out
Solar Water Heater
Rebate process
• Residential customers or developers who buy an accredited system from an accredited supplier and use an accredited installer can claim a rebate from the facilitating auditors
• Criteria apply, the most NB that the electrical geyser be disabled Industrial and commercial customers to be included in programme by end of the year
Progress to date
• 20 accredited SABS tested suppliers and 14 registered distributors • R 1.8-million rebates paid to date – an average of R 4 327 per installation
• Greatest uptake in Gauteng 266 , KwaZulu Natal 86
Business Objective
To replace (or install in series) approximately 900 000 geysers over the 5 years that will result in a saving of approximately 578MW.
Motor Systems• Electric motors ubiquitous in
industry• Globally, motor systems
account for ~40 % of industrial electricity
– SA: ~ 60 %– US: ~ 60 %– India ~ 50 %– Korea ~ 50 %
• Application (SA)– Pumps (largest)– Fan systems– Compressed air systems– Conveyors
Electrochem6,147 GWh
4%
Line Losses10527
7%
Homes & Hostels3,145 GWh
2%
Lighting8,781 GWh
5%
Pumping18,654 GWh
12%Fans
8,679 GWh5%Compressed air
15,040 GWh9%
Processing25,163 GWh
16%
Material Handling16,525 GWh
10%
Other motive3,622 GWh
2%
Process Heating12,541 GWh
8%
Arc Furnace26,447 GWh
16%
Industrial Cooling4,407 GWh
3%
HVAC1,424 GWh
1%
Motor Program General Conditions
• Launched in Nov. 2007• Aim: Replace 5100 motors with Eff 1
type• Estimated savings 2.48 MW• Slow start up• Gaining momentum, 200 motors
replaced to date• Not enough to make the desired impact
The Model
ESKOM DSMProject Manager
Energy Efficient Motor Suppliers
End-usersMetal
Recovery Shops
Facilitating Auditors M&V
ESKOM DSMProject Manager
Energy Efficient Motor Suppliers
End-usersMetal
Recovery Shops
Facilitating Auditors M&V
ESKOM DSMProject Manager
Energy Efficient Motor Suppliers
End-usersMetal
Recovery Shops
Facilitating Auditors M&V
Awareness
Commercial Technical
Thank You!
Comments and Questions
www.eskomdsm.co.za