ERTMS Baseline 3 Implementation and experience from first commissioned line at Nordjyske Jernbaner. First mover in Denmark or guinea pig? Johannes Flyvbjerg Jakobsen NJ Safety Manager Peter Boll BDK SP West Safety Manager Joanna Wisniewska BDK SP Onboard Safety Manager

ERTMS Baseline 3 Implementation and experience from first … · 2019. 10. 23. · ERTMS –Baseline 3 Implementation and experience from first commissioned line at Nordjyske Jernbaner

  • Upload
    others

  • View
    6

  • Download
    0

Embed Size (px)

Citation preview

Page 1: ERTMS Baseline 3 Implementation and experience from first … · 2019. 10. 23. · ERTMS –Baseline 3 Implementation and experience from first commissioned line at Nordjyske Jernbaner

ERTMS – Baseline 3 Implementation and experience from first

commissioned line at Nordjyske Jernbaner. First mover in Denmark

or guinea pig?

Johannes Flyvbjerg Jakobsen – NJ Safety Manager

Peter Boll – BDK SP West Safety Manager

Joanna Wisniewska – BDK SP Onboard Safety Manager

Page 2: ERTMS Baseline 3 Implementation and experience from first … · 2019. 10. 23. · ERTMS –Baseline 3 Implementation and experience from first commissioned line at Nordjyske Jernbaner

Before Implementation.

Page 3: ERTMS Baseline 3 Implementation and experience from first … · 2019. 10. 23. · ERTMS –Baseline 3 Implementation and experience from first commissioned line at Nordjyske Jernbaner

The road to the digital signal system in North Jutland

• Project launch in 2012.• Official roll-out date in week 43

2018

Consequences afterimplementation

• No other rail operators in the ERTMS equipped area.

Early deployment line

Page 4: ERTMS Baseline 3 Implementation and experience from first … · 2019. 10. 23. · ERTMS –Baseline 3 Implementation and experience from first commissioned line at Nordjyske Jernbaner

Preparing the company for ERTMS L2

• SLS - Obtain new NSA Approval as the First RU in Denmark

• Rolling stock - Obtain new NSA Approval as the first RU in Denmark

• Trusted cooperation with the NSA

Page 5: ERTMS Baseline 3 Implementation and experience from first … · 2019. 10. 23. · ERTMS –Baseline 3 Implementation and experience from first commissioned line at Nordjyske Jernbaner

Level 2 Baseline 3, new Interlocking, and new TMS

Replace the wheels while driving

▪ The Signalling programme is a brownfield project

▪ Commissioning of the system should minimise impact on the line in operation

Interlocking elements were the biggest challenge for EDL

▪ ‘Change over system’ area allows for full functional test of generic system

▪ Point Machines and Level Crossings were not installed outside the COS area

▪ Virtual Balise Covers were used to allow for the ETCS tests

Page 6: ERTMS Baseline 3 Implementation and experience from first … · 2019. 10. 23. · ERTMS –Baseline 3 Implementation and experience from first commissioned line at Nordjyske Jernbaner

Joint Test Lab, SIT

Joint Test Lab

▪ Development and external interfaces, more than 2 years of test

Site Integration Tests

▪ installation of components and connectivity test

Page 7: ERTMS Baseline 3 Implementation and experience from first … · 2019. 10. 23. · ERTMS –Baseline 3 Implementation and experience from first commissioned line at Nordjyske Jernbaner

Onboard approval

• Few approval received for level NTC/level 0

• Work on the delta to obtain first approval for level 2

• ESC test report

• ESC statement

• Key aspects:

➢Collaboration with the NSA

➢ Transparency with the RU´s during entire safety process

➢ Assessor, DeBo involvement

new process

Test & Transport

Fitment and Commissioning

HandoverFrom RU

STM and ETCS Dynamic Tests on

closed trackL0/LNTC

Test Train(Litra MR/MRD)

Test & Transport

Fitment and Commissioning

HandoverFrom RU

STM and ETCS Dynamic Tests on

closed trackL0/LNTC

FoC(Litra xx)

Fitment and Commissioning

HandoverFrom RU

Series N.1(Litra xx)

Covering thewhole train series

Handback to RU

Handback to RU

L2Test &

TransportSoftware Upgrade

and CommissioningHandoverFrom RU

Train Track Validation Tests

(On specific TS CCS) on closed tracks

Test Train(Litra MR/MRD)

Software Upgrade and Commissioning

HandoverFrom RU

Handback to RU

FoC(Litra xx)

Software Upgrade and Commissioning

HandoverFrom RU

Handback to RU

Series N.1(Litra xx)

Covering thewhole train series

L2

Handback to RU

Approval Level 2 (additional to Level 0 and Level NTC)

Handback to RU

Poss ible site tests based ondelta approach

depending on FoC

Approval Level 0 and Level NTC

Page 8: ERTMS Baseline 3 Implementation and experience from first … · 2019. 10. 23. · ERTMS –Baseline 3 Implementation and experience from first commissioned line at Nordjyske Jernbaner

During implementation.

Page 9: ERTMS Baseline 3 Implementation and experience from first … · 2019. 10. 23. · ERTMS –Baseline 3 Implementation and experience from first commissioned line at Nordjyske Jernbaner

During implementation.

• Line closed for 2 weeks

• 52 drivers to be trained.

• Onboard and supplier team present – key part to handle any findings

• Consequences

• 100% production are affected of the change to ERTMS.

Page 10: ERTMS Baseline 3 Implementation and experience from first … · 2019. 10. 23. · ERTMS –Baseline 3 Implementation and experience from first commissioned line at Nordjyske Jernbaner

SAT, Trial Run, and Commissioning

Site Acceptance Test

▪ all external interfaces tested, final evidence to the safety documentation

Trial Run

▪ Evidence of operational readiness

Commissioning period

▪ Majority of Point Machines and Level Crossings installed and final day of training of the drivers

Page 11: ERTMS Baseline 3 Implementation and experience from first … · 2019. 10. 23. · ERTMS –Baseline 3 Implementation and experience from first commissioned line at Nordjyske Jernbaner

After implementation.

Page 12: ERTMS Baseline 3 Implementation and experience from first … · 2019. 10. 23. · ERTMS –Baseline 3 Implementation and experience from first commissioned line at Nordjyske Jernbaner

Surprice and breaking news! - the press wrote:

Finally, good news from the trains.

The trains in North Jutland have increasing punctuality.

Page 13: ERTMS Baseline 3 Implementation and experience from first … · 2019. 10. 23. · ERTMS –Baseline 3 Implementation and experience from first commissioned line at Nordjyske Jernbaner

NJ – train punctuality after implementation in 2018NJ – Train punctuality August 2019Tr

ain

pu

nct

ual

ity

ERTMS overall impact punctuality Punctuality 2018

tota

l im

pac

t

Page 14: ERTMS Baseline 3 Implementation and experience from first … · 2019. 10. 23. · ERTMS –Baseline 3 Implementation and experience from first commissioned line at Nordjyske Jernbaner

Future Challenges

Infrastructure

How to test and commissioning without impacting the already commissioned lines ?

How to implement track layout changes in the roll out plan ?

Onboard

Handling configuration changes correctly according to 2018/545 and IO

One stop shop

Update to MR1 3.4.0

Compatibility with two types of line – not done yet

Page 15: ERTMS Baseline 3 Implementation and experience from first … · 2019. 10. 23. · ERTMS –Baseline 3 Implementation and experience from first commissioned line at Nordjyske Jernbaner

Sharing of knowledge as first mover.

Page 16: ERTMS Baseline 3 Implementation and experience from first … · 2019. 10. 23. · ERTMS –Baseline 3 Implementation and experience from first commissioned line at Nordjyske Jernbaner

Lessons learned

• Share knowledge from NJ til other RU in Denmark. Do not built fence around knowledge that are accumulatet in the company.

• Retraining has to be taken into considertion while the system har a high performance.

• Share knowledge and best practice across railways