EXCAVATION AND BASE PREPARATION
LNG TANKErection Sequence
DEVELOPED BY P.S.Tomer
BASE SLAB REBAR AND CONCRETE
EXCAVATION AND BASE PREPARATION
LNG TANKErection Sequence
DEVELOPED BY P.S.Tomer
WALL CONSTRUCTIONROOF ERECTION
2- TOWER CRANES OUTSIDE2-PLACER BOOM WITH CONC. PUMP & POURER
LNG TANKErection Sequence
5M X 5M OPENING IN CONCRETE WALL
DEVELOPED BY P.S.Tomer
WALL CONSTRUCTIONROOF ERECTION
BASE VAPOUR BARRIER INSTALLATIONINSIDE CRANES TAKEN OUT
LNG TANKErection Sequence
DEVELOPED BY P.S.Tomer
WALL CONSTRUCTIONROOF ERECTION
BASE VAPOUR BARRIER INSTALLATION
LNG TANKErection Sequence
DEVELOPED BY P.S.Tomer
WALL CONSTRUCTIONROOF ERECTION
SUSPENDED DECK ERECTION
LNG TANKErection Sequence
DEVELOPED BY P.S.Tomer
WALL CONSTRUCTIONROOF ERECTION
SUSPENDED DECK ERECTION ON STAGING
LNG TANKErection Sequence
DEVELOPED BY P.S.Tomer
WALL CONSTRUCTIONCOMPRESSION PLATE INSTALLATION
ROOF ERECTIONSUSPENDED DECK ERECTION
LNG TANKErection Sequence
DEVELOPED BY P.S.Tomer
WALL CONSTRUCTIONCOMPRESSION PLATE INSTALLATION
ROOF ERECTIONSUSPENDED DECK ERECTION
LNG TANKErection Sequence
DEVELOPED BY P.S.Tomer
WALL CONSTRUCTIONCOMPRESSION PLATE INSTALLATION
ROOF ERECTIONSUSPENDED DECK ERECTION
LNG TANKErection Sequence
DEVELOPED BY P.S.Tomer
INSTALL AIRLIFT EQUIPMENTCOMPLETE AIR LIFT PREPARATION
KING POST REMOVEDACCESS OPENING CLOSED
LNG TANKErection Sequence
DEVELOPED BY P.S.Tomer
COMMENCE AIR LIFT
LNG TANKErection Sequence
DEVELOPED BY P.S.Tomer
AIR LIFT
LNG TANKErection Sequence
DEVELOPED BY P.S.Tomer
AIR LIFT COMPLETEDWELD ROOF TO
COMPRESSION PLATE
LNG TANKErection Sequence
DEVELOPED BY P.S.Tomer
INSTALL AT THE ANNULAR SPACE OF 3.5 M WIDTH CONC. SCREED, FOAM BLOCK, SAND SCREED,SECONDARY BOTTOM,
CRYOGENIC RING BEAM, PAVING SLAB AND INNER TANK ANNULARS
ERECT ROOF WALKWAYSPOST TENSION TANK OUTER WALL
LNG TANKErection Sequence
DEVELOPED BY P.S.Tomer
INSTALL AT THE ANNULAR SPACE OF 3.5 M WIDTH CONC. SCREED, FOAM BLOCK, SAND SCREED,SECONDARY BOTTOM,
CRYOGENIC RING BEAM, PAVING SLAB AND INNER TANK ANNULARS
ERECT ROOF WALKWAYSPOST TENSION TANK OUTER WALL
LNG TANKErection Sequence
DEVELOPED BY P.S.Tomer
INSTALL AT THE ANNULAR SPACE OF 3.5 M WIDTH CONC. SCREED, FOAM BLOCK, SAND SCREED,SECONDARY BOTTOM,
CRYOGENIC RING BEAM, PAVING SLAB AND INNER TANK ANNULARS
ERECT ROOF WALKWAYSPOST TENSION TANK OUTER WALL
LNG TANKErection Sequence
DEVELOPED BY P.S.Tomer
ERECT INNER TANK AND WALL VAPOUR BARRIERINSTALL ROOF FITTINGS AND TANK INTERNALS
ERECT ROOF PLATFORMSPOST TENSION TANK OUTER WALL
LNG TANKErection Sequence
DEVELOPED BY P.S.Tomer
ERECT INNER TANK SHELL AND VAPOUR BARRIERCOMPLETE BOTTOM INSULATION, SECONDARY BOTTOM AND
INNER TANK BOTTOMINSTALL ROOF FITTINGS AND TANK INTERNALS
ERECT ROOF PLATFORMSPOST TENSION TANK OUTER WALL
LNG TANKErection Sequence
DEVELOPED BY P.S.Tomer
ERECT INNER TANK AND VAPOUR BARRIERINSTALL ROOF FITTINGS AND TANK INTERNALS
ERECT ROOF PLATFORMSPOST TENSION TANK OUTER WALL
LNG TANKErection Sequence
DEVELOPED BY P.S.Tomer
INSTALL FOAM GLASS TO WALLS AND 36% NICKELINSTALL ROOF FITTINGS AND TANK INTERNALS
POST TENSION TANK OUTER WALL
LNG TANKErection Sequence
DEVELOPED BY P.S.Tomer
COMMENCE HYDROTESTINSTALL ELECTRICSINSTALL PIPEWORK
INSTALL INSTRUMENTS
LNG TANKErection Sequence
DEVELOPED BY P.S.Tomer
COMMENCE HYDROTESTINSTALL ELECTRICSINSTALL PIPEWORK
INSTALL INSTRUMENTS
LNG TANKErection Sequence
DEVELOPED BY P.S.Tomer
PERFORM HYDROTESTINSTALL ELECTRICSINSTALL PIPEWORK
INSTALL INSTRUMENTS
LNG TANKErection Sequence
DEVELOPED BY P.S.Tomer
PUMP OUT WATER AND CLEAN DOWN INNER TANKINSTAL ELECTRICSINSTAL PIPEWORK
INSTALL INSTRUMENTS
LNG TANKErection Sequence
DEVELOPED BY P.S.Tomer
INSULATE INNER TANK SHELLINSULATE SUSPENDED DECK
LNG TANKErection Sequence
DEVELOPED BY P.S.Tomer
INSULATE INNER TANK SHELLINSULATE SUSPENDED DECK
LNG TANKErection Sequence
DEVELOPED BY P.S.Tomer
FILL INTERSPACE WITH PERLITE
LNG TANKErection Sequence
DEVELOPED BY P.S.Tomer
COMMISSION TANK
LNG TANKErection Sequence
DEVELOPED BY P.S.Tomer