49
EQUIPMENT PERFORMANCE – SPILL PREVENTION AND PIPING 20 th ANNUAL NATIONAL TANKS CONFERENCE March 17-19, 2008 ATLANTA, GEORGIA KEVIN HENDERSON

EQUIPMENT PERFORMANCE – SPILL PREVENTION AND …neiwpcc.org/tanks2008old/presentations/National...SPILL PREVENTION AND PIPING 20th ANNUAL NATIONAL TANKS CONFERENCE March 17-19, 2008

  • Upload
    others

  • View
    4

  • Download
    1

Embed Size (px)

Citation preview

EQUIPMENT PERFORMANCE –SPILL PREVENTION AND PIPING

20th ANNUAL NATIONAL TANKS CONFERENCE

March 17-19, 2008

ATLANTA, GEORGIA

KEVIN HENDERSON

PETRO STOPPING CENTER – JACKSON, MS

SPILL BUCKETS: OPW “1”

Six 20,000 gallon tanks installed May 1999

One regular tank

One premium tank

Four diesel tanks all manifoldedtogether

Direct and remote fills for all six tanks (12 buckets)

Petro Stopping Center – Jackson, MS

DOUBLE-WALLED TANKS & PIPING

Interstitial Monitoring

Tanks – Hydrostatic

Piping – Electronic sump sensors

- Mechanical leak detectors

No indication of any suspected release with the release detection systems utilized by owner/operator (no alarms).

Observation wells installed at each corner of the tank bed but not utilized (never checked).

Petro Stopping Center – Jackson, MS

Petro Stopping Center – Jackson, MS

Inspected in May 2007

OPW “1”

OPW “1”

OPW “1”

OPW “1”

OPW “1”

OPW “1”

OPW “1”

OPW “1”

OPW “1”

OPW “1”

OPW “1”

“Duratuff”

OPW “1”

4800 Gallons Recovered

Petro Stopping Center – Jackson, MS

What’s Wrong With This Picture ?

Ball Float Valves

Flex Connectors

1-2

3-4

5-6

7-8

9-10

11-12

13-14

15-16

PREMIUM

REGULAR R-2R-1

P-1 P-2

R-2 replaced July 2006 by Contractor A because fuel found dripping from conduit into STP sump.

R-1, P-1 and P-2 replaced March 2007 by Contractor B.

Originally piped with Western flex pipe in rigid PVC electrical conduit May 1997.

STORE

PIPING: APT – XPThe Pantry - Flowood, MS

APT - XP

APT – XPDispenser 11-12 Premium

APT – XPDispenser 9-10 Premium

APT – XPDispenser 9-10 Premium

APT – XPDispenser 1-2 Premium

APT – XPDispenser 9-10 Premium

28 feet between dispensers

6 inches cut off pipe to get riser lined-up underneath dispenser 9-10

Represents 1.8 % swell rate

APT – XP

R-1 (installed July 2006) and R-2 (installed March 2007) have not significantly swelled.

P-1 installed March 2007 has swollen enough to crack shear valve at termination dispenser (1-2) at least once. No length had to be cut off this pipe.

P-2 installed March 2007 has swollen significantly:

Shear valve at terminating dispenser (9-10) has been broken at least twice. 6 inches cut off the length of this pipe.

Shear valve at dispenser 11-12 cracked at least once.

Installed October 2005

Passed precision tightness testing

Brought into use June 2006

Leak Reported July 2006

PIPING: UPP – EXTRA

MURPHY OIL -GREENWOOD, MS

Leaking Coupling Coupling Already Replaced

3rd Coupling Not Leaking (out of picture frame)

UPP – EXTRAMurphy Oil – Greenwood, MS

Leaking Coupling -Note fuel within sockets of welding pins.

Welding Sockets

Secondary to Primary Termination Fitting

Primary Piping

Termination Fitting

Coupling Welding “Indicators”

UPP – EXTRAMurphy Oil – Greenwood, MS

Pipe

Coupling

Termination Fitting

UPP – EXTRAMurphy Oil – Greenwood, MS

Analysis on reported leakage of fuel through welding pins

PetroTechnik

Analysis of the sample received• Pressure test on the sample could not

replicate the leak through the welding pins• The sample was subjected to X-Ray, and

the result highlighted two important facts:

Pipe and termination fitting were not fully insertedThe assembly was exposed to bending stress during welding

Incomplete insertion

X-ray:Resistor displacement induced by

welding under stress

Conclusions• The assembly was exposed to external loads and partial

insertion of either the pipe or fitting prior and during electrofusion. Both the partial insertion and external loading resulted in the molten material moving into the bore of the welding coupler. Molten material was forced out of the fusion area to form material tongues.

• This movement of molten material has resulted in unsatisfactory fusion welds. The movement of molten material has also resulted in the exposure of the welding coil.

• Thus the cause of the assembly failure is due to poor installation with the pipe and fitting not fully inserted squarely and also the assembly exposed to external forces prior to, during and after electrofusion.

• The x-ray results of the original Murphy sample conclude the original findings that poor installation of pipe and fitting was the cause of the assembly failure.

Actioned• Review of installation manuals and

documentation emphasizing the critical steps

• Efficiently communicate this information to installers

• Post the revised installation manual on Murphy Oil’s web site

• Petrotechnik is progressively recertifyingcontractors in line the Murphy new site build program

MURPHY OIL - INDIANOLA, MS

Installed October 2005

Passing precision tightness test results

Inspected May 2007

UPP – EXTRA

UPP – EXTRAMurphy Oil – Indianola, MS

Premium Sump

UPP – EXTRAMurphy Oil – Indianola, MS

Regular Sump

UPP – EXTRAMurphy Oil – Indianola, MS

ENVIRON – GeoFlex

ENVIRON – GeoFlex+Plus

ENVIRON – GeoFlex+Plus

601-961-5283

[email protected]

KEVIN HENDERSON