Upload
adeelsiddiquepso
View
218
Download
0
Embed Size (px)
Citation preview
8/4/2019 Eproject Management and Change
http://slidepdf.com/reader/full/eproject-management-and-change 1/19
End of Module Assignment Autumn Term 2010
Managing e-projects and Change
Using the Deductive Technology Case Study you will be expected to hand in a report of
around 5000 words that contains 4 sections:
1. A management overview of how you see the project being managed and
implemented. A discussion of potential risks to successful implementation and
how they may be mitigated. (30%)
2. A project plan or Gantt chart, entered into a software package, showing the major
tasks, sub-tasks, resources required, deliverables, their relationship and expected
completion times. If there is no real start date please use Nov 8th 2010. Also show
any additional project management tasks. (30%)
3. A revised financial plan taking into account discounted cash flows, with your assumptions and an explanation of your financial plan. (10%)
4. A briefing paper to your management team on issues around change management
and changing established working practices. (30%)
Hand in Date on or before December 2, 2010
You should hand in copy on disk or similar to Reception in The Business School and
upload a copy of your report onto Turnitin via Blackboard before 3.00pm on before
December 2, 2010.
Work handed in up to one week late will be graded to a maximum pass mark of 40%. Work
handed in a week after an agreed hand in date will not be graded.
Pete Wraith
1 of 19
8/4/2019 Eproject Management and Change
http://slidepdf.com/reader/full/eproject-management-and-change 2/19
Deductive Technology Case Study for M.Sc e-Business
The project idea described in the attached pages was originally drawn up by Steve Pilchard
an employee of Deductive Technology in close collaboration with Helen Ford the
company’s Finance Director. He had expected to do most of the work himself and had
planned it out to be a two year project. For various reasons Steve is no longer with the
company but the ideas he and Helen worked out are still relevant. Rather than replace Steve
Pilchard with someone of a similar background the company have employed a junior web
developer, Jacqui Jones and a recent graduate, Billie Bond to keep the existing business
systems “up-and-running”. Both these two new employees will be able to work on aspects
of the project under your guidance and that of the Senior Management Team.
The CEO and major shareholder Martin Large wants the project to go ahead but says the
company can’t wait two years and wants all work completing by end of July 2010. This
will mean running activities in parallel and bringing in some project managementexperience into the company (your role) to help deliver results on budget and on time.
You may make assumptions (your best guess) about information you feel you need to know
but which is not available to you. In such cases please state your assumption. For example
you may need to know the cost of borrowing money. Your assumption might be that an
unsecured business loan will cost around 8% per annum from Deductive’s High Street
Bank.
You may work in a group to discuss ideas but you should submit an individual piece of work the majority of which has been done by you rather than the group.
Pete Wraith
04/10/2010
2 of 19
8/4/2019 Eproject Management and Change
http://slidepdf.com/reader/full/eproject-management-and-change 3/19
Project Background
Deductive Technology
Deductive Technology provides assistive technology; hardware and software for children
and adults with special educational needs, including access devices which enable those with physical or sensory difficulties to use a computer or communicate. Deductive’s software
helps develop skills such as understanding cause and effect, making choices, literacy and
numeracy.
Special Needs Market :
2% of children in the UK are educated in special schools and an additional 17% of children
have special needs but are educated in mainstream education. The total ICT spend in this
area per annum in the UK is £30m excluding PCs, networks, communications and
consumables.
There are additional opportunities in English speaking countries. Deductive Technology
has set up a subsidiary company in the US where the market is considered to be six times
that of the UK. Australasia and Canada are smaller but lucrative markets.
Additionally, the adult and aged population special needs sector is a market we have yet to
penetrate. We estimate this to be a market worth £50m.
Deductive Technology is the largest provider of Special Needs educational software and
hardware devices in the UK. It is also the second largest independent supplier of ICTequipment to Education in the United Kingdom. Deductive holds a unique position in the
market as not only a supplier but also as an information and training organisation. The
company has several competitors who offer elements of service provided by Deductive,
many of these are small owner managed enterprises, but only one offers a comparable
range of products and services. This company is Semerc, a division of Granada Learning
plc. Deductive holds a 25% share of this market. The company has a small share of the US
market but little in the Commonwealth and Adult Special Needs markets
Basic Company Financial Information :
The Company’s annual turnover last year was £7,238,160. Net profit pre-tax as stated in its last audited accounts was £693,539.
Value of exports as stated in its last audited accounts £243,225.
The balance sheet total was £776,798.
Number of Employees 29
Some Problems
Currently “home grown” business systems are in place. These enabled the company to
grow to its current size but further business development requires a radical restructuring
and integration of the company’s information systems. There can be no further growth insales till these issues are resolved. The company is seeking year on year growth of 10%
from the end of next financial year Oct. 2010. This will be facilitated by improved
3 of 19
8/4/2019 Eproject Management and Change
http://slidepdf.com/reader/full/eproject-management-and-change 4/19
marketing activities and the use of more robust and integrated business systems capable of
supporting entry into US and other English speaking markets.
Implementing an integrated suite of software applications and consequent internal re-
organisation will streamline business processes and increase the ability to process more
orders. A new marketing strategy will widen access to markets as will an e-shop, integrated
with back end systems.
The core of any new IT developments will be an integrated back-to-back, “tele-sales” order
processing, stock control and purchase order processing system directly linked to an
accounting package working over a Virtual Private Network (VPN).
An analysis of customer behaviour, current marketing activities and market research will
generate plans for developing new products and routes to new markets.
These developments will improve internal efficiency and growth in markets across English
speaking countries.
A set of integrated activities are required to review business processes, marketing and
operational procedures, implementation of software to integrate business systems across the
company and its overseas operations over the VPN. This will develop methods for the
semi-automatic generation of an electronic shop and paper catalogue from its enterprise
systems and feed orders from the electronic shop back to its core enterprise systems. The
major aim being to increase profitability and market share through increased efficiency and
improved marketing activities.
The company may require some assistance with: ICT strategy development, Business
Process Modelling and Software Requirements Specification, but they are competent at building web based applications and integrating them with enterprise systems. They also
have experience in market research, marketing communications, customer relationship
management, catalogue operations, financial management and developing software
products for the special needs community. There is a budget of £10,000 for project support
in the figures at the end of the case study this equates to a notional 30 days at £300 per day
and £1,000 for travel and expenses.
Project objectives
To improve internal efficiency and increase market penetration the project will :
• Develop ICT and Marketing strategies capable of supporting a business strategy of
growth.
• Document requirements for and manage the purchasing and implementation of a
new integrated suite of enterprise software applications.
• Devise a change management programme to enable internal re-organisation after a
business process re-engineering exercise.
• Develop an electronic shop integrated with enterprise systems.
• Manage the integration of telephone and computer applications.
• Develop technology driven marketing activities to make better use of improved
customer information and its management.
• Develop an application for semi-automatic generation of the product catalogue• Specify requirements for and manage the implementation of a virtual private
network linking UK and US operations.
4 of 19
8/4/2019 Eproject Management and Change
http://slidepdf.com/reader/full/eproject-management-and-change 5/19
Project Deliverables, Savings and Gains
Task No. Deliverables
4 & 11 Efficiency gains/ growth and Improved Management Information
available. £244k. ( Savings by not outsourcing IT support, redesigned work
flows requiring 2 less staff, better planning information. Growth: able to
process more orders)
13 Savings in Operational Efficiency worth £79k (reduction of 5 visits per year
to USA = £60K over 4 years, Staff time gained by not travelling £19K
21 Access to new markets via e-shop £287k (Efficieny savings in Telesales = 1
staff member over 3.5 years £87k, new market sales in other English speaking
countries = £200k)
22 Increased information and visitor tracking from web site statistics £29k
(Direct targeting of sales effort to existing customers and site visitors)
25 Automated Generation of catalogue £39k (Reduction in staff time equal to
0.5 of staff member over 3 years)23 Marketing strategy developed. Documentation complete and staff trained.
Improved marketing activities £125k (Generation of new sales)
Task Description Total
£k
Yr1
£k
Yr2
£k
Yr3
£k
Yr4
£k
Yr5
£k
4 &
11
Savings by not outsourcing IT support,
redesigned work flows requiring 2 less
staff. Growth: able to process more
orders
144 15 30 32 33 35
11 Improved management information better planning information and
inventory control
100 10 20 20 25 25
13 Efficiency in operation of group
reduction of 5 visits per year to USA =
£60K over 4 years, Staff time gained by
not travelling £19K via implementation
of VPN
79 3 18 18 20 20
21 Access to new markets via e-shop in
other English speaking countries =
£200k Efficiency savings in Telesales =
1.5 staff member over 3.5 years £87k,
287 0 37 50 100 100
22 Increased information and tracking from
website (Savings on targeting of sales
effort to existing customers and site
visitors)
29 0 5 8 8 8
25 Automated generation of catalogue,
reduction in staff time equal to 0.5 of
staff member over 3.5 years
39 0 6 11 11 11
23 Improved marketing activities
generating new sales.
125 0 0 25 50 50
Total 803 28 116 164 247 249
5 of 19
8/4/2019 Eproject Management and Change
http://slidepdf.com/reader/full/eproject-management-and-change 6/19
The Original list of tasks that sequentially would take two years to deliver benefits
Task
no.
Task description
(where appropriate, please state how
the task will be carried out)
Effort
(in
person
weeks)
Deliverables
(in terms of contribution to the
operation of the Company
Partner or decision points)
1 Induction and Review Company’s
Strategic Direction
Induction to Company and work
shadowing of team to get a
complete overview of methods
of working.
Interview the 3 senior directors
to establish their view on
Opportunities, Threats,
Strengths and Weaknesses.
Collate findings in SWOT
document
Use SWOT document and
previous iteration of Company
Strategy Document to confirm /
revise Company Strategy
Meeting with the 3 senior
directors to establish that the
project, IS and IT plans address
the issues identified in the
SWOT analysis.
4
SWOT Analysis Document
IT Strategy Workshop
facilitated by Your
Company
Draft 1 of company IT
Strategy Document
6 of 19
8/4/2019 Eproject Management and Change
http://slidepdf.com/reader/full/eproject-management-and-change 7/19
2Modelling Business Processes
Visit some customer sites,
attend Exhibition and / or Trade
Show
Shadow key staff to gainunderstanding of and document
sales order processing
procedures.
Shadow key staff to gain
understanding of and document
current nominal, sales and
purchase ledgers procedures
Shadow dispatch / warehouse
staff to gain understanding of
current product range and
document, stock movement
procedures.
Seek agreement from Key staff
that documentation is correct
4
Documented sales order
processing proceduresDocumented current
nominal, sales and purchase
ledgers procedures
Documented warehouse and
stock movement procedures.
Accuracy of documentation
agreed
3
Marketing Audits – Internal and
External
Internal Audit
Undertake an in-depth assessment and
analysis of Deductive Technology’smarketing related resources and
activities by primary (interviews) and
secondary research (internal
documentation):
Analyse:
Sales cycle
Customer information (previous,
existing and potential)
Internal marketing information
flows
Current marketing activityExisting corporate marketingimage/approach
2
Report on sales cycles,
internal information flows,
current marketing activities
and existing corporate
marketing image/approach.
7 of 19
8/4/2019 Eproject Management and Change
http://slidepdf.com/reader/full/eproject-management-and-change 8/19
4
IT strategy development and IT
management.
Through interviews and review of
existing documentation
Document current web-site and
company catalogue generation procedures.
Gather requirements for a
virtual private network (UK &
US)
Review current IT system
management procedures
Oversee Implementation of
remedial actions required
maintain current systems as a
secure and maintain businesscontinuity.
From products of task 2 produce
an integrated business systems
model of current operations plus
problem areas.
Identify with senior
management team redundant
procedures, outline new
operating procedures and
expected re-organisation Produce outline design of new
proposed integrated set of
business systems
Set KPIs expected from new
Business systems
4
Documented current web-
site and company catalogue
generation procedures
VPN requirements list
IT Procedures Report
Updated IT management
procedures communicated
to IT based staff
Integrated business systems
model of current operations
Identification of efficiency
gains
Required Business Systems
over view document.
KPIs defined
8 of 19
8/4/2019 Eproject Management and Change
http://slidepdf.com/reader/full/eproject-management-and-change 9/19
5
Completing the Requirements
Specification
Through interviews and working from
products of task 2 , the partially
completed specification documents
covering SOP, Stock, POP,Accounting requirements, web shop
and catalogue generation.
Establish additional data and
functional requirements
(Interviewing senior staff)
Establish non functional
requirements, support, training
etc.
Establish and document the
acceptance and evaluationcriteria. (Interviewing senior
staff)
Research pool of potential
software provides
Produce version 1 of proposed
IT strategy document including
software, hardware and IT
management plans.
4
Requirements Specification
Document
Acceptance Criteria
Document
Company IT strategy and
plans documented and
presented to relevant staff
6
Selecting the software application
suite
Issue invitation to tender and
organise demonstrations and
evaluation process
Presentation to key staff on
Tendering procedure.
Visit vendor customer sites. Manage software selection and
vendor in conjunction with
senior Company partners and
Academic Supervisors
Draw up Implementation plan
with chosen software vendor.
4
Invitation to Tender
Document
Milestone: Software selected
Implementation plan
communicated to staff
9 of 19
8/4/2019 Eproject Management and Change
http://slidepdf.com/reader/full/eproject-management-and-change 10/19
7 Business Process Restructuring
Attend product configuration
training
Establish and document work flow procedures for SOP, POP
and stock control modules of
the selected application, using
process flow software.
(Interviews with product vendor
and Senior management)
Compare new procedures with
integrated business systems
model of current operations
(Task 4) and establish scope &impact of change and propose
Change Management Plan
3
New work flow procedures
identified and documented
Change Management Plan
agreed with senior staff new
procedures documented.
8 Preparation for Phase 1 ( SOP , POP
and Financial applications)
Implementation
Review Change ManagementPlan
Review Implementation Plan
Prepare all staff for
implementation process
(meetings / briefing sessions)
Organise and/or deliver product
training for staff
Establish and document
Nominal Ledger requirements.(From existing package and
Interviewing senior staff)
Establish and document
management reporting and
management information
requirements. (Interviewing
senior staff)
Establish and document
additional software
requirements
4
Updated Implementation &
Change Management Plans
presented to staff
Staff trained in new
application
Documented Nominals
Documented MIS
requirements
Documented additional
requirements
10 of 19
8/4/2019 Eproject Management and Change
http://slidepdf.com/reader/full/eproject-management-and-change 11/19
9
Phase 1 Restructuring Work Flows
Review and communicate
Change Management Plan and
new procedures to staff via team
meetings and workshops.
Review and communicateImplementation Plan to staff via
team meetings.
Using ODBC links and SQL
write programmes to extract
data from :Stock files ,
Customer files , Sales ledger
files and Purchase ledger files
and reconfigure in preparation
for input into Test database
tables.
Implement new applications in
test mode
Carry out go live simulation – A
day in the life of Deductive
Technology using new
procedures
Agree plans with senior
managers and Vendors to
resolve system problems and
people issues
3
New procedures
documentedRevised implementation
plan for Phase 1.
Documented structure of
data tables for new
application
Document system problems
and people issues arising
from simulation
11 of 19
8/4/2019 Eproject Management and Change
http://slidepdf.com/reader/full/eproject-management-and-change 12/19
10
Phase 1 Implementation
Working with software vendors
review implementation plan &
manage the implementation of :
The core financial applications
(nominal, sales and purchaseledgers)
Sales order processing module
Stock control module
Purchase order processing
module.
Check data formats from Task 8
and reproduce current data for
live operation
Collect and copy all user
documentation and store
Implement
Management Information and
reporting modules
The additional software
requirements
Cross check accuracy of financials.
Review information management /
backup procedures.
4 Communicate revised
implementation plan to all
relevant staff
User documentation
reviewed and additional
staff training needsidentified
Updated information
management documentation
communicated to key staff.
11
Phase 1 Implementation review and
fine tuning
Carr out User Satisfaction survey and
document all :
reported configuration
difficulties
user errors & training needs
Software errors
With management accountant check
production of : month end routines
Management reporting task and
develop other management
information reports as required
Review and amend overall IT strategy
document and phase 2 plan
Organise meeting to discuss and
present revised plans
4
Implement remedial action
as required
Staff trained and using new
systems
Milestone : ImplementedSytsem
Efficiency gains/ growth and
Improved Management
Information available.
£244k
Updated information
management documentation
and .
revised Implementation plancommunicated to affected
staff
12 of 19
8/4/2019 Eproject Management and Change
http://slidepdf.com/reader/full/eproject-management-and-change 13/19
12 Specification of a Virtual Private
Network (Phase 2)
Identify potential VPN
hardware suppliers (Trade
Journals) Through interviews with
management team, University
staff and Vendors document
Business Needs ,Technical
Needs and Security Needs for
The Deductive Virtual Private
Network.
Submit specification document
to potential vendors
Evaluate potential solutions andchoose Vendor
Draw up VPN implementation
plan
4
VPN Requirements
Document
VPN implementation plan
13 Implemtation of a Virtual Private
Network
Purchase components
Install
Test security Test applications running over
VPN
Document normal operation and
recovery procedures
Communicate new procedures
to staff who will use
applications over VPN
2
Application running in UK and US over VPN
Updated IT management
plans
Staff trained in using
applications over VPN
Savings in Operational
Efficiency worth £79k
14 Build in vacation time 5
13 of 19
8/4/2019 Eproject Management and Change
http://slidepdf.com/reader/full/eproject-management-and-change 14/19
15 External Audit : Undertake a
detailed audit into Deductive
Technology’s market.
Through the development of a
questionnaire, interview a sample of
existing and potential customers toestablish
1. the level of customer
satisfaction.
2. CSFs by market segments.
3. market requirements with
respect to
Buying behaviour and the
decision making process
Attitudes to purchasing
Market size and shares
Technological requirements
After sales service
Undertake research into Deductive
Technology’ competitor’s
3
1
Report on existing customer
profiles and buying behaviour,and create a customer
satisfaction survey report.
Report on market perception
and position of Deductive
Technology
SWOT and PEST analysis
(The better understanding of
customers will improve
Deductive Technology’ abilityto operate efficiently which
will in turn increase turnover
and/or profits)
Produce a market analysis
report.
Competitor analysis and
present
report to Management Team
16 Market Research and Information
Prepare a research proposal to carry
out market research to identify market
opportunities.
Undertake research and facilitate in
house brain-storming, gap analysis to
identify potential new markets /
products for. Grade potentials based
barriers to entry, suitability of existing
product/technology, strength of the
economy, political stability, size of market etc.
Investigate opportunities for online,
overseas, adult and early years
markets for special needs products.
Based on the information from tasks 3
and 15 co-ordinate and present
findings to the Management team.
Include a review of any resources for
product / market development,
identification of critical successfactors and identification of target
market sectors.
3
1
Proposal and plan including
methodology, aims and
objectives. Include budget
figures and expenditure
justification.
Report on recommendationsfor targeting new markets /
products and potential
customers.
Opportunities for business in
areas identified to increase
turnover.
Establish key performanceindicators
14 of 19
8/4/2019 Eproject Management and Change
http://slidepdf.com/reader/full/eproject-management-and-change 15/19
17 Marketing Strategy based on tasks
15 and 16
Develop communications and
promotional strategy.
Develop marketing sub-strategy to
achieve the target growth in sales /
profits
Develop a marketing sub-strategy to
achieve the development of identified
markets / products to achieve target
growth in sales.
Develop outline a marketing
programme, plans for theimplementation of strategy and sub
strategies, resources, timescales and
budget implications, expenditure
justification. (To be implemented
during Task 23.)
2
2
1
1
Marketing strategy report
recommending company
approach to communications
and promotions.Report approved by senior
management
Marketing development
programme report, and
presentation for approval by
the Board.
Production of planned new
procedures and
implementation plan.
(Marketing programmes
approved by senior
management.)
18 Check quarterly reporting routines Review output from main financial
and Management Information
applications implemented in phase 1
adjust if necessary.
1
19 Preparation for Phase 3 (Electronic
Shop) Implementation
Gathering and documenting
technical, functional and
business requirements.(Interview key staff, ISP, review
existing site and competitor
sites)
Tools selection.
Devise phase 3 implementation
plan with key staff and
communicate it to staff involved
Undertake any required training
3
Electronic Shop requirements
specification document.
Phase 3 Implementation plan
communicated to affected
staff
15 of 19
8/4/2019 Eproject Management and Change
http://slidepdf.com/reader/full/eproject-management-and-change 16/19
20
Phase 3 Implementation Visual
Using the product(s) selected in
15 (e.g. Shop Creator tools ,
Java, VB, HTML) build the
shop templates.
With ISP manageimplementation of web hosting
requirements.
Document web hosting
information and communicate
procedures to operational staff
4
Templates developed and testedUser department staff trained to
manage hosted application
21 Phase 3 Implementation Procedural
Write programmes to produce
input and output linkages to
main financial and SOPapplications using ODBC and
SQL.
Upload shop and test
Write operational procedures
for shop generation and new
order processing.
Train staff
Launch new trading site
Review informationmanagement / backup and
system operation procedures.
4Integrated electronic shop
generateded from enterprise
systems.
Staff trained to generate e-
shop and process orders
Updated information
management
documentation.
Milestone New E-shop
launched
Access to new markets via e-shop £287k
22 Phase 3 Implementation review and
fine tuning
Use tools and write programmes
for capturing and interpreting
web site visiting statistics,
particularly non-purchasers,
using tools provided by ISP todownload into Access database.
Develop automatic web traffic
reports using Access database
macros.
Train users to produce reports
With key staff and marketing
department (task 23) review
web site promotion and search
engine placement strategy and
carry out any necessary
remedial action.
4
Traffic reporting system
produced
Staff able to generate visitor
statistics
Revised website promotion
strategy and information
management
documentation.
Increased information and
visitor tracking from web
site statistics £29k
16 of 19
8/4/2019 Eproject Management and Change
http://slidepdf.com/reader/full/eproject-management-and-change 17/19
23 Manage the implementation of the
approved marketing programme.
Development of promotional material
for the website and brochures as
required by the marketing strategy(task 17), to meet needs identified in
tasks 15 and 16.
Obtain feedback on company’s
products and marketing activity.
Establish and co-ordinate
marketing/PR activity through
external liaison with:
Customers, Agents, advertising
agencies,technical journals and press.
Implement market development
elements of the marketing programme
for current and proposed markets by
undertaking surveys of
customers
establish feedback system to
inform web team of findings on
perceived market direction and potential new products. (task
22)
2
1
1
Promotional material produced.
Promotional activities
undertaken and feedback
obtained.
Marketing plan for identified
market / product
implemented.
Produce procedures manual.
Summary report and
presentation on future market
development for approval.
Customer surveys report.
Feedback system to inform
technical personnel.
Improved marketing
activities £125k
24
Preparation for Phase 4 (Semi
automatic production of
Catalogues) Implementation
Gathering and documenting technical,
functional and business requirements,
through interviews with key staff and
print supplier.
Produce and issue Invitation to
Tender
Product and vendor selection.
Devise and communicate
implementation plan to key staff
Undertake any required training
4
Requirements Report and
Tender Documents
Phase 4 implementation
plan delivered to key staff
17 of 19
8/4/2019 Eproject Management and Change
http://slidepdf.com/reader/full/eproject-management-and-change 18/19
25
Phase 4 Implementation
Install software and generate
catalogue and product display
templates.
Write VB scripts using ODBCand SQL to populate product
templates.
Write programmes to generate
despatch list from customer
database
Produce technical
documentation
Write procedures and train staff
to use new system
Liase with printer and manage
catalogue distribution
4
Updated IT documentation
User staff trained using new
method
Milestone : Paper and CD
catalogues generated from
stock system
Automated Generation of
catalogue savings potentialof £39k
26
Phase 4 review
Update system documentation and
user instructions.
Vacation Time
1
4
Updated information
management
documentation.
27Monitoring, Evaluation andProcedures
Identify success criteria based on
strategic objectives in each market for
on-going monitoring, evaluation and
updating of marketing plan, including
develop monitoring and
evaluation procedures
undertake on-going monitoring
of market performance.
Establish marketing planning
procedures to update marketing plan
based on results of monitoring,
evaluation and updated marketing
information.
Produce procedures manual and hold
marketing team workshops to develop
skills to revisit tasks 3, 16, 17 and 23
and communicate procedures
2
1
Proposals for monitoring and
evaluation criteria.
Monitoring and evaluation
manual.
Updates to marketing
information.
Marketing planning
procedures manual written.
Staff trained
18 of 19
8/4/2019 Eproject Management and Change
http://slidepdf.com/reader/full/eproject-management-and-change 19/19
Estimates of Cost to deliver the project
Additional Company Costs
Description Estimate of costs (£)
Project management fees 10,000
Staff training in software use 5,600
Software purchases 40,000
Software server and E-Commerce / Web server 10,000
Fixed link Telecommunications Connectivity 6,000
Total 71,600