59
EASTERN POWER DISTRIBUTION COMPANY OF A.P.LIMITED CORPORATE OFFICE:: VISAKHAPATNAM Memo.No.CGM/Proj-I,EA&IT/GM.P/DE.P1/ADE.P1/F.Cost Data/D.No.109614 Dt.25-09-14. Sub:- EPDCL - Cost Data of materials, equipment, H.T & L.T Lines, Services and 33/11KV Substation to be adopted for the year 2014-15 – Reg. * * * 1. The Cost Data 2014-15 will come into force with effect from the date of 07.10.2014 and will be in force till next revision takes place. 2. The field officers are requested to strictly adhere to the following instructions while sanctioning the estimates. a) In case where the estimates are pending to be sanctioned on or after the date of communication of cost data 2014-15, the same should be revised with latest cost data 2014-15. b) In case, where the applicants paid the necessary charges for the estimates on or before the date of communication of cost data 2014-15, the estimates need not be revised. c) In case where the applicants come forwards after the date of communication of revised cost data 2014-15 and willing to pay the necessary charges for the estimates sanctioned prior to the date of communication of revised cost data 2014-15, within the stipulated time as mentioned in the intimation letter from the concerned authority, the estimates need not be revised upto stipulated time period as communicated in the estimates. d) In case where the applicants come forwards after the date of communication of revised cost data 2014-15 and willing to pay the necessary charges for the estimates sanctioned prior to the date of communication of revised cost data 2014-15, after lapse of stipulated time as mentioned in the intimation letter from the concerned authority, the estimates should be revised with the latest cost data 2014-15. 3. For service connection estimates in non REC scheme areas and execution of 33/11KV Substations with other than REC funds, extra amounts should be added are 11% Establishment and General charges on Materials and 3% contingencies on materials also. 4. 1% Cess is adopted on total cost of the construction as per the rules laid down in the Building and other construction workers welfare Cess Act 1996. Sd/-XXXX Chief General Manager Projects-I, EA & IT APEPDCL::VISAKHAPATNAM To All Superintending Engineers/ All Divisional Engineers/ADEs/AEs Copy submitted to the Director/Projects/APEPDCL/Visakhapatnam Copy submitted to the Director/Operation & Comml./APEPDCL/Visakhapatnam Copy to: The Chief General Managers The Chief Project Manager/REC Ltd., Hyderabad The Managing Director/RESCO/Anakapalli & Chepurupalli The Chief Engineer/O & RE/V.S/Hyderabad The Dy. General Manger/IT/APEPDCL/Visakhapatnam for uploading the Cost Data 2014-15 in EPIMRS

epdcl cost data 2014-15

  • Upload
    hakiet

  • View
    232

  • Download
    4

Embed Size (px)

Citation preview

Page 1: epdcl cost data 2014-15

EASTERN POWER DISTRIBUTION COMPANY OF A.P.LIMITED CORPORATE OFFICE:: VISAKHAPATNAM

Memo.No.CGM/Proj-I,EA&IT/GM.P/DE.P1/ADE.P1/F.Cost Data/D.No.109614 Dt.25-09-14.

Sub:- EPDCL - Cost Data of materials, equipment, H.T & L.T Lines, Services and 33/11KV Substation to be adopted for the year 2014-15 – Reg.

* * * 1. The Cost Data 2014-15 will come into force with effect from the date of 07.10.2014 and will be in force till next revision takes place. 2. The field officers are requested to strictly adhere to the following instructions while sanctioning the estimates.

a) In case where the estimates are pending to be sanctioned on or after the date of communication of cost data 2014-15, the same should be revised with latest cost data 2014-15.

b) In case, where the applicants paid the necessary charges for the estimates on or before the date of communication of cost data 2014-15, the estimates need not be revised.

c) In case where the applicants come forwards after the date of communication of revised cost data 2014-15 and willing to pay the necessary charges for the estimates sanctioned prior to the date of communication of revised cost data 2014-15, within the stipulated time as mentioned in the intimation letter from the concerned authority, the estimates need not be revised upto stipulated time period as communicated in the estimates.

d) In case where the applicants come forwards after the date of communication of revised cost data 2014-15 and willing to pay the necessary charges for the estimates sanctioned prior to the date of communication of revised cost data 2014-15, after lapse of stipulated time as mentioned in the intimation letter from the concerned authority, the estimates should be revised with the latest cost data 2014-15.

3. For service connection estimates in non REC scheme areas and execution of 33/11KV Substations with other than REC funds, extra amounts should be added are 11% Establishment and General charges on Materials and 3% contingencies on materials also. 4. 1% Cess is adopted on total cost of the construction as per the rules laid down in the Building and other construction workers welfare Cess Act 1996.

Sd/-XXXX Chief General Manager Projects-I, EA & IT

APEPDCL::VISAKHAPATNAMTo All Superintending Engineers/ All Divisional Engineers/ADEs/AEs Copy submitted to the Director/Projects/APEPDCL/Visakhapatnam Copy submitted to the Director/Operation & Comml./APEPDCL/Visakhapatnam Copy to: The Chief General Managers The Chief Project Manager/REC Ltd., Hyderabad The Managing Director/RESCO/Anakapalli & Chepurupalli The Chief Engineer/O & RE/V.S/Hyderabad The Dy. General Manger/IT/APEPDCL/Visakhapatnam for uploading the Cost Data 2014-15 in EPIMRS

Page 2: epdcl cost data 2014-15

COST DATA2014-15

CORPORATE OFFICE :: VISAKHAPATNAM

Page 3: epdcl cost data 2014-15

Sl.No. Description Page No.

A ABSTRACT of rates of 33 KV / 11 KV / LT Lines 1B Rates for CENTRALIZED MATERIALS 2 - 11C Cost Data for Hilly and Tribal areas as adopted by Irrigation Department in the State 121 33 KV Line over 9.1 Mts. PSCC Poles at 105 Mts.Span WL 280 Kgs 132 33 KV Line over 9.1 Mts. PSCC Poles at 80 Mts.Span WL 280 Kgs 143 11 KV Line over 8 Mts. PSCC Poles at 60 Mts.Span WL 140 Kgs 154 11 KV Line over 8 Mts. PSCC Poles at 65 Mts.Span WL 200 Kgs 165 11 KV Line over 8 Mts. PSCC Poles at 60 Mts.Span WL 140 Kgs 176 11 KV Line over 8 Mts. PSCC Poles at 65 Mts.Span WL 200 Kgs 187 6.3 KV Line over 8 Mts. PSCC Poles at 90 Mts.Span WL 140 Kgs 198 6.3 KV Line over 8 Mts. PSCC Poles at 90 Mts.Span WL 200 Kgs 209 LT 3 Ph.5 Wire line (Horizontal) over 8 Mts. PSCC Poles at 65 Mts.Span WL 140 Kgs 2110 LT 3 Ph.5 Wire line (Horizontal) over 8 Mts. PSCC Poles at 60 Mts.Span WL 200 Kgs 2211 LT 3 Ph.5 Wire line (Horizontal) over 8 Mts. PSCC Poles at 65 Mts.Span WL 140 Kgs 2312 LT 3 Ph.5 Wire line (Horizontal) over 8 Mts. PSCC Poles at 60 Mts.Span WL 200 Kgs 2413 LT 3 Ph.4 Wire line (Horizontal) over 8 Mts. PSCC Poles at 65 Mts.Span WL 140 Kgs 2514 LT 3 Ph.4 Wire line (Horizontal) over 8 Mts. PSCC Poles at 60 Mts.Span WL 200 Kgs 2615 LT 3 Ph.4 Wire line (Horizontal) over 8 Mts. PSCC Poles at 65 Mts.Span WL 140 Kgs 2716 LT 3 Ph.4 Wire line (Horizontal) over 8 Mts. PSCC Poles at 60 Mts.Span WL 200 Kgs 2817 LT 1 Ph. 3 Wire line (Horizontal) over 8 Mts. PSCC Poles at 65 Mts.Span WL 140 Kgs 2918 LT 1 Ph. 2 Wire line (Horizontal) over 8 Mts. PSCC Poles at 65 Mts.Span WL 140 Kgs 3019 L.T.AB Cable (3x16+25 Sqmm) over 8 Mts. PSCC Poles at 65 Mts.Span WL 140 Kgs 3120 L.T.AB Cable (2x16+25 Sqmm) over 8 Mts. PSCC Poles at 65 Mts.Span WL 140 Kgs 3221 L.T.AB Cable (1x16+25 Sqmm) over 8 Mts. PSCC Poles at 65 Mts.Span WL 140 Kgs 3322 L.T.AB Cable (3x16+25 Sqmm) over 8 Mts. PSCC Poles at 65 Mts.Span WL 200 Kgs 3423 L.T.AB Cable (2x16+25 Sqmm) over 8 Mts. PSCC Poles at 65 Mts.Span WL 200 Kgs 3524 L.T.AB Cable (1x16+25 Sqmm) over 8 Mts. PSCC Poles at 65 Mts.Span WL 200 Kgs 3625 Erection of 100 KVA 11/433 KV Conventional Distribution Transformer 3726 Erection of 16 KVA 11/433 KV Conventional Distribution Transformer on single pole structure 3827 Erection of 63 KVA 11/433 KV Conventional Distribution Transformer 3928 Erection of 25 KVA 11/433 KV Conventional Distribution Transformer on single pole structure 4029 Erection of 40 KVA 11/433 KV Conventional Distribution Transformer on single pole structure 4130 Erection of 15 KVA 6.3/0-240V CSP Transformer(Oil immersed) on 9.1Mtr PSCC Pole 4231 Erection of 15 KVA 6.3/0-240V CSP Transformer(Oil immersed) on 8 Mts PSCC Pole 4332 Erection of 15 KVA 6.3/0-240V Amorphous metal core Transformer(Oil immersed) on 8 Mts PSCC Pole 4433 Release of single phase Agl. Service erected on support 4534 Release of poly phase Agl. Service erected on support 4635 Release of 1 ph ( high quality). Domestic & non-domestic service 4736 Release of 1 ph (electronic). Domestic & non-domestic service 4837 Release of 1 ph Domestic & non-domestic service 4938 Release of 3 ph. ( electronic meter) Domestic & non-domestic service 5039 Release of 3 ph. (electronic meter) Domestic & non-domestic service 5140 Release of poly phase ( high quality) Indl.service upto 15 HP 5241 Release of Industrial service with poly phase CT operated meter upto 15 HP 5342 Release of Industrial service with poly phase CT operated meter above 15 HP 5543 Release of Street light service (1 -ph electonic meter) 55

44 Erection of 33/11 KV Sub-station with1 No.Power Transformer & 3 Nos. 11 KV feeders( with 11 KV 2 MVAR Capacitor Bank) 56

INDEX

Page 4: epdcl cost data 2014-15

Sl. No. Particulars of items Wind.pr.

in kg/m2W.Load in kg.

Type of pole being used

No. of poles/

KM

Span in

Mtrs.Size of Conductor Cost

inRs.

1 33 KV Line 75 280 9.1 Mtr. PSCC 12 105 100 Sqmm AAAC 413060

2 33 KV Line 100 280 9.1 Mtr. PSCC 14 80 100 Sqmm AAA 439220

3 11 KV Line 75 140 8 Mtr PSCC 18 60 55 Sqmm AAAC 292780

4 11 KV Line 100 200 8 Mtr PSCC 17 65 55 Sqmm AAA 293450

5 11 KV Line 75 140 8 Mtr PSCC 18 60 34 Sqmm AAA 246080

6 11 KV Line 100 200 8 Mtr PSCC 17 65 34 Sqmm AAA 246750

7 6.3 KV Line 75 140 8 Mtr PSCC 13 90 34 Sqmm AAAC 156030

8 6.3 KV Line 100 200 8 Mtr PSCC 13 90 34 Sqmm AAA 162600

9 L.T. 3Ph 5 Wire Line(Horizontal) 75 140 8 Mtr PSCC 16 65 3x55+2x34 Sqmm AAA 310670

10 L.T. 3Ph 5 Wire Line(Horizontal) 100 200 8 Mtr PSCC 18 60 3x55+2x34 Sqmm AAA 334290

11 L.T. 3Ph 5 Wire Line(Horizontal) 75 140 8 Mtr PSCC 16 65 5x34 Sqmm AAAC 263970

12 L.T. 3Ph 5 Wire Line(Horizontal) 100 200 8 Mtr PSCC 18 60 5x34 Sqmm AAAC 287590

13 L.T. 3Ph 4 Wire Line(Horizontal) 75 140 8 Mtr PSCC 16 65 3x55+1x34 Sqmm AAA 279290

14 L.T. 3Ph 4 Wire Line(Horizontal) 100 200 8 Mtr PSCC 15 60 3x55+1x34 Sqmm AAA 279820

15 L.T. 3Ph 4 Wire Line(Horizontal) 75 140 8 Mtr PSCC 16 65 4x34 Sqmm AAA 232600

16 L.T. 3Ph 4 Wire Line(Horizontal) 100 200 8 Mtr PSCC 15 60 4x34 Sqmm AAA 233160

17 L.T. 1Ph 3 Wire Line(Horizontal) 75 140 8 Mtr PSCC 16 65 34 Sqmm AAA 203880

18 L.T. 1Ph 2 Wire Line(Horizontal) 75 140 8 Mtr PSCC 16 65 2x34 Sqmm AAA 174040

19 L.T. AB Cable 75 140 8 Mtr PSCC 16 65 3x16+25 Sqmm 188810

20 L.T. AB Cable 75 140 8 Mtr PSCC 16 65 2x16+25 Sqmm 173910

21 L.T. AB Cable 75 140 8 Mtr PSCC 16 65 1x16+25 Sqmm 157170

22 L.T. AB Cable 100 200 8 Mtr PSCC 16 65 3x16+25 Sqmm 196890

23 L.T. AB Cable 100 200 8 Mtr PSCC 16 65 2x16+25 Sqmm 181990

24 L.T. AB Cable 100 200 8 Mtr PSCC 16 65 1x16+25 Sqmm 165240

25 Erection of 100KVA Conventional Distribution transformer 250720

26 Erection of 63 KVA Conventional Distribution transformer 216,640

27 Erection of 3-Ph 16KVA Conventional Distribution transformer 128560

28 Erection of 3-Ph 25KVA Conventional Distribution transformer 141480

29 Erection of 3-Ph 40KVA Conventional Distribution transformer 176540

30 Erection of 15 KVA S-Ph 6.3 KV/0-240V CSP Oil Immersed Transformer 65880

31 Erection of 15 KVA S-Ph 6.3 KV/0-240V Amorphous metal core Transformer 51730

32 Erection of S-Ph 15 KVA CSP Transformer 9.1M PSCC Pole 51540

33 Release of Single phase Agl. Service erected on support 3380

34 Release of poly phase Agl. Service erected on support 6950

35 Release of single phase domestic and non domestic service with High Quality meter 3720

36 Release of single phase domestic and non domestic service with High Quality meter 3290

37 Release of single phase domestic and non domestic service with High Quality meter 3620

38 Release of single phase domestic and non domestic service with 3 Phase Energy meter 9170

39 Release of single phase domestic and non domestic service with Electronic meter 9020

40 Release of poly phase Industrial service upto 15 H.P with Energy meter 11210

41 Release of poly phase industrial service upto 15 HP with CT meter 16570

42 Release of poly phase Industrial service upto 15 H.P with C.T. operated meter 13290

43 Release of Single Phase Street light service with Electronic Meter 3240

44 Erection of 33/11 K.V. Substation with 1x5MVA power transformer & 3 Nos. 11KV feeders 10847000

Abstract of schedule of rates for 2014-15 with modified rates : Cost Data per Km of 33/11 KV/LT Lines

DATA FOR R.E. SCHEMES

1

Page 5: epdcl cost data 2014-15

Sl. No. SAP Code Name of the Material Unit Rupees

SUBHEAD-I : SUPPORTS AND FIXTURES, IRON, STEEL AND CEMENT

1 MST00029 RS Joists 150 x 150mm MT 56155

2 MST00032 RS Joists 175 x 85mm MT 56402

3 MST00030 RS Joists 150 x 75mm MT 55347

4 PLS00013 11 mts. PSCC poles 365 Kgs Each 6250

5 PLS00004 9.1 mts. PSCC poles 280 Kgs. Each 3105

6 PLS00001 8 mts. PSCC poles 140 Kgs. Each 1504

7 PLS00002 8 mts. PSCC poles 200 Kgs. Each 1844

8 PLS00003 8 mts. PSCC poles 300 Kgs. Each 2015

9 PLS00007 11 mts. Spun Poles Each 11000

10 PLS00008 12.5 mts. Spun Poles Each 12802

11 MST00025 Rail poles upto 7 Mtrs MT 84506

12 MST00024 52 Kg (105 lb) Rails (up to 13 mtrs. length) MT 46895

13 MST00012 MS Channel 100 x 50mm MT 55000

14 MST00013 MS Channel 75 x 40mm MT 55000

15 MST00003 MS Angle 65 x 65 x 6mm MT 54500

16 MST00002 MS Angle 50 x 50 x 6mm MT 54500

17 MST00014 MS Flat 50 x 6mm MT 55200

18 MST00015 MS Flat 75 x 8mm MT 55200

19 MST00019 MS Rod 20mm MT 55536

20 MST00018 MS Rod 16mm MT 55250

21 Cement MT 5800

22 WRS00011 HT Steel wire-4mm MT 60743

23 WRS00007 GI Stay wire 7/3.15 mm MT 63738

24 WRS00006 GI Stay wire 7/2.5 mm MT 65104

25 WRS00005 GI Wire 4 mm MT 61640.6926 BNT00024 GI Bolts and Nuts with Washers full thread(5/8"X6', 7', 9') MT 8062827 BNT00026 GI Bolts and Nuts with Washers full thread(5/8" X 2 1/2 ', 3', 4') MT 8062828 C R Sheet 1.6mm MT 42000

29 MST00046 M S Plate 12mm/6mm MT 36600

30 Torsteel 10mm/12mm MT 34200

COST DATA OF CENTRALISED MATERIALS FOR R.E. AND DISTRIBUTION WORKS

2014-15

2

Page 6: epdcl cost data 2014-15

Sl.No SAP CODE Name of the Material

REC Specification

No.Unit Rupees

SUBHEAD-II : INSULATORS AND HARDWARE

1 INS30001 33 KV Pin Insulator 13/1979 E 197

2 HWR00003 33 KV GI Pin -do- E 168

3 INS30003 33 KV Post Insulator Stack -do- E 920

4 HWR00004 33 KV String Insulator Fittings (B&S) -do- E 188

5 a)33 KV polymer disc insulator/string insulator (B&S) E 649b)33 KV Polymer Pin Insulator with pins E 405

6 INS10001 a)11 KV Pin Insulator 3/1971(R-1993) E 49

b)11 KV Polymer Pin Insulator with Pins E 1437 HWR00001 11 KV GI Pin -do- E 62.42

8 INS10008 11 KV Post Insulator -do- E 234

9 INS10004 11 KV String Insulator (B&S) -do- E 275

10 INS10002 11 KV String Insulator (C&T) -do- E 192

11 HWR00002 11 KV String Insulator Fittings (C&T) 3/1991(R-1993) E 80

12 INS10003 11 KV Polymer string insulator (C&T) E 138.85

13 INS00001 LT Pin Insulator 4/1972 D-1 (R-1979) E 16.25

14 HWR00015 LT GI Pin -do- E 27

15 INS00002 LT Shackle Insulator -do- E 10

16 HWR00016 LT Shackle Hardware -do- E 34

17 INS10005 HT Guy Insulator 21/1981 E 28

18 INS00003 LT Guy Insulator -do- E 15.75

19 INS30002 33 KV Solid Core Insulators -do- E 1113

20 INS10006 11 KV Solid Core Insulators for AB Switches -do- E 220.5

21 INS10007 11 KV Solid Core Insulators for 11 KV HG Fuse sets E 151

22 1.53 Mts Channel Cross arms without clamp E 1418

23 1.07 Mts Channel Cross arms without clamp E 511

24 FBR10004 11KV Tapping Cross arm E 508

25 FBR30006 Top clamp with cleat (for 33 KV) E 375

26 FBR10007 Top clamp with cleat (for 11 KV) E 214

27 FBR00012 Top clamp for LT E 208

28 FBR30002 Stay set with clamp (for 33 KV) E 1146

29 Stay set with clamp (for 11 KV) E 424

30 Stay set with clamp (for 6.3 KV) E 358

31 Stay set with clamp (for LT) E 394

32 FBR00008 LT 3-Ph Cross arm (for 5 Wire line) E 435.54

33 FBR00007 LT 3-Ph Cross arm (for 4 Wire line) E 327.42

34 FBR00006 LT S-Ph Cross arm (for 3 Wire line) E 319

35 FBR00005 LT S-Ph Cross arm (for 2 Wire line) E 268

3

Page 7: epdcl cost data 2014-15

Sl.No SAP CODE Name of the Material

REC Specification

No.Unit Rupees

36 FBR00002 Back Clamp for 9.1 Mts PSCC pole E 172

37 FBR00001 Back Clamp for 8 Mts PSCC pole E 123

38 HWR00001 D Clamp for 8.0 M poles E 132

39 Bracing set with double X arms with 9.1 Mts PSCC poles set 7335

40 Bracing set with double X arms with 8 Mts PSCC poles set 6171

41 STR10019 DPC aluminium Winding Wire 1.25 mm Kg 193

42 STR10021 DPC aluminium Winding Wire 1.6 mm Kg 193

SUBHEAD - III : CONDUCTORS1 CDR00011 ACSR Zebra Conductor KM 235223

2 CDR00010 200 Sq.mm Panther Conductor 1/1971(R-1993) KM 140627

37/3.0 Sq.mm ACSR

3 CDR00004 100 Sq.mm AAA Conductor or 33/1984(R-1993) KM 49166

7/4.26 AAAC

4 CDR00003 55 Sq.mm AAA Conductor or -do- KM 28149(7/3.15 AAAC/RABBIT)

5 CDR00002 34 Sq.mm AAA Conductor or -do- KM 178707/2.50 AAAC/Weasel

SUBHEAD-IV : CABLES

SUBHEAD-IV : (A) LT XLPE SINGLE CORE CABLES1 2.50 Sq.mm 26/1993

(R-1987) KM 2627

2 4.00 Sq.mm - do - KM 4172

3 6.00 Sq.mm - do - KM 5253

4 10.00 Sq.mm - do - KM 8343

5 CBP00011 25.00 Sq.mm - do - KM 23072

6 CBX00001 50.00 Sq.mm - do - KM 38146

7 CBX00002 70.00 Sq.mm - do - KM 55149.64

8 CBX00003 95.00 Sq.mm - do - KM 66320.59

9 CBX00004 120.00 Sq.mm - do - KM 76896.46

10 150.00 Sq.mm - do - KM 94500

11 185.00 Sq.mm - do - KM 115710

SUBHEAD-IV : (B) LT PVC SINGLE CORE CABLES1 CBX00017 25.00 Sq.mm KM 22104

2 CBX00005 50.00 Sq.mm KM 40479

3 CBX00006 70.00 Sq.mm KM 52839

4 CBX00008 120.00 Sq.mm KM 77250

4

Page 8: epdcl cost data 2014-15

Sl.No SAP CODE Name of the Material

REC Specification

No.Unit Rupees

SUBHEAD-IV : (C) LT CONTROL CABLES 1 2 X 2.5 Sq.mm (Cu) KM 36889

2 CBP00002 4 X 2.5 Sq.mm (Cu) KM 83997

3 CBP00006 10 x 2.5 Sq.mm (Cu) KM 167596

4 4 x 4.0 Sq.mm (AL) KM 25000

SUBHEAD-IV : (D) ) LT XLPE CABLES

1 CBX00016 3 1/2 X 300 sqmm LT XLPE cable KM 659613

2 CBX00015 3 1/2 X 185 sqmm LT XLPE cable KM 448114

3 3 1/2 X 150 sqmm LT XLPE cable KM 358432

4 CBX00014 3 1/2 X 120 sqmm LT XLPE cable KM 320330

5 CBX00013 3 1/2 X 95 sqmm LT XLPE cable KM 264384

6 CBX00012 3 1/2 X 70 sqmm LT XLPE cable KM 183620

7 3 1/2 X 50 sqmm LT XLPE cable KM 143795

8 CBX00010 3 1/2 X 25 sqmm LT XLPE cable KM 87742

SUBHEAD -IV: (E) LT AERIAL BUNCHED CABLES1 CBA00001 1 x 16+25 Sq.mm LT AB Cable 32/1984 KM 26000

2 CBA00002 2 x 16+25 Sq.mm LT AB Cable KM 37276.75

3 CBA00003 3 x 16+25 Sq.mm LT AB Cable KM 47316

4 3 x 70 + 1x16 +1x50 Sqmm LT AB Cable KM 167000

SUBHEAD -IV: (F) LT AERIAL BUNCHED CABLE FITTINGS

1 HWR00019 Suspension Clamp with eye hook 32/1984 E 175

2 LT Connector with Insulator Cover - do - E 82

3 Dead-end Clamp with eye hooks - do - E 113

SUBHEAD -IV: (G) 11 KV XLPE POWER CABLES

1 CBX10002 3 x 35 Sq.mm 63/1993 KM 317665.84

2 CBX10005 3 x 95 Sq.mm - do - KM 454303

3 CBX10006 3 x 120 Sq.mm - do - KM 576934

4 CBX10007 3 x 185 Sq.mm - do - KM 680070

5 CBX10008 3 x 300 Sq.mm - do - KM 1001492

6 SCB1003811 KV 3CX35 Sq.mm Heat shrinkable Cable Termination Kits suitable for Indoor type. E 5763

7 SCB1003711 KV 3CX35 Sq.mm Heat shrinkable Cable Termination Kits suitable for Outdoor type. E 9910

5

Page 9: epdcl cost data 2014-15

Sl.No SAP CODE Name of the Material

REC Specification

No.Unit Rupees

8 SCB1004711 KV 3CX185 Sq.mm Heat shrinkable Cable Termination Kits suitable for Indoor type. E 8914

9 SCB1004211 KV 3CX185 Sq.mm Heat shrinkable Cable Termination Kits suitable for Outdoor type. E 11958

10 SCB1005811KV 3x300 Sqmm Heat shrinkable cable Termination Kits suitable for Indoor type. E 8775

11 SCB1005711KV 3x300 Sqmm Heat shrinkable cable Termination Kits suitable for Outdoor type. E 13411

12 SCB1002833KV 3X185Sqmm heat shrinkable cable Termination Kits suitable for Outdoor type. E 23637

13 SCB1006833KV 3X400Sqmm heat shrinkable cable Termination Kits suitable for Indoor type. E 20565

14 SCB1006233KV 3X400Sqmm heat shrinkable cable Termination Kits suitable for Outdoor type. E 31176

SUBHEAD - IV (H)11 KV AB Cable (Aluminum)

1 3x35+35 Sqmm. KM 219898

2 CBA10005 3x70+70 Sqmm. KM 318653

3 3x120+70 Sqmm. KM 476000

4 3x185+70 Sqmm. KM 621517

SUBHEAD -IV: (I) 33 KV XLPE POWER CABLES

1 CBX30001 3 x 400 Sq.mm 63/1993 KM 1918507.20

2 CBX30003 3 x 185 Sq.mm KM 1156566

SUBHEAD -V: POWER TRANSFORMERS, CAPACITORS AND TRASFORMER OIL

1 PTR00005 33/11 KV 3.15 MVA Power Transformer E 2856190

2 PTR00006 33/11 KV 5 MVA Power Transformer 7/1974(R-1993) E 2959845.30

3 PTR00008 33/11 KV 8 MVA Power Transformer E 4251490.30

4 33/11 KV 12.5 MVA Power Transformer E 6413000

5 OFO10009 Transformer Oil KL 93168.32

6

Page 10: epdcl cost data 2014-15

Sl.No SAP CODE Name of the Material

REC Specification

No.Unit Rupees

SUBHEAD -VI: DISTRIBUTION TRANSFORMERS (CRGO)

1 DTC10001 S-Ph 5 KVA DTR 6.3 KV/0-240 V E 24139

2 1-Phase 10kVA 11kV/250V (CSP) (Aluminium) E 27501

3 DTC10004 S-Ph 16 KVA CSP DTR 6.3 KV/0-240V (Cu) E 43671.51

4 DTC10007 S-Ph 15 KVA CSP DTR 6.3 KV/230-0-230V (Al) E 37522

5 1-Phase 25 KVA (CSP) (Copper) E 43590

6 DTA30016 3-Ph 16 KVA Amorphous/CRGO core conventional type copper wound DTR with BEE 5 star rating Conventional DTR (Cu) E 65749.88

7 DTA30017 3-Ph 25 KVA Amorphous/CRGO core conventional type copper wound DTR with BEE 5 star ratingConventional DTR (Cu) E 71611.71

7(a) 3-Ph 25 KVA Amorphous/CRGO core conventional type Alluminum wound DTR with BEE 5 star ratingConventional DTR (Cu) E 58492.28

8 DTA30015 3-Ph 40 KVA Amorphous/CRGO core conventional type copper wound DTR with BEE 5 star rating Conventional DTR (Cu) E 95500

9 DTA30012 3-Ph 63 KVA Amorphous/CRGO core conventional type copper wound DTR with BEE 5 star ratingConventional DTR (Cu) E 108500

10 DTA30013 3-Ph 100 KVA Amorphous/CRGO core conventional type copper wound DTR with BEE 5 star rating Conventional DTR (Cu) E 137261.94

11 DTA30014 3-Ph 160 KVA Amorphous/CRGO core conventional type copper wound DTR with BEE 5 star rating Conventional DTR (Cu) E 214221.95

12 250 KVA CSP DTR (Cu) E 315618

13 DTC30009 315 KVA CSP DTR (Cu) Conventional E 464400

14 DTC30110 500 KVA Conventional (Al) E 531833

15 Single Phase 15 KVA Transformer (Amorphous) E 37522

SUBHEAD -VII: SWITCH CONTROL AND PROTECTIVE GEAR(A) 33KV & 11KV VCBs

1 BRK30004 33 KV VCB with CRPs & CTs ratio (400-200-100/1-1-1A) 12/1979(R-1993) E 521348

2 BRK30002 33KV Feeder VCBs with CTs & CR panels E 413788

3 BRK10002 11 KV VCB with CTs & Panels (Feeder Control) 22/1983 E 224886.06

4 BRK10014 11 KV VCB with CTs & Panels ( LV Control ) without differential protection E 321065

5 BRK10009 11 KV VCB with CTs & Panels ( LV Control ) with differential protection E 401546

7

Page 11: epdcl cost data 2014-15

Sl.No SAP CODE Name of the Material

REC Specification

No.Unit Rupees

(B) 33KV & 11KV CTs

1 ITR30028 33 KV CTs 400-200-100/1-1-1A ratio 0.2s class accuracy E 23394

2 ITR30030 33 KV CTs 400-200-100/1-1A ratio 0.5 class accuracy E 23394

3 ITR30019 33 KV CTs (200-100/1-1A) 0.2 class accuracy E 23394

4 ITR30029 33 KV CTs (100-50/1-1A) 0.2 class accuracy E 23394

5 11 KV feeder CTs (400-200-100/1-1A) (0.5 class) E 16758

6 ITR10015 11 KV CTs (50-25/1-1A) 59/1993 E 14640

7 ITR10018 11 KV CTs 200-100/5-5A E 14463

8 ITR10013 a)11 KV CTs 400-200/1-1A E 13564

ITR10037 b)11KV CTs 0.2S accuracy of ratio 400-200-100/1-1A E 16758

9 ITR10014 11 KV CTs 200-100/1-1A E 13125

10 ITR10023 11 KV CTs (600-300/1-1-0.577A) E 15200

(C) 33KV & 11KV PTs - CTs

1 ITR30001 33 KV PT (Single Phase) class 0.5 E 18960

2 ITR30020 33 KV PT (Single Phase) class 0.2 E 18723

3 ITR30017 33 KV PT (Three Phase) of 0.5 class accuracy E 44263

4 ITR10021 11 KV PT (3 Phase) 60/1993 E 18334

5 ITR10004 11KV C.T.P.T. set 10/5A E 30758

(D) AB Switches, LAs, HG Fuse sets, Batteries, Capacitors, RMUs etc.

1 ABS30004 33 KV 800 Amps AB Switch Double break with solid core insulator E 43050

2 ABS10015 11 KV 800 Amps AB Switch Double break with insulators 43/1987 E 19949

3 11 KV 400 Amps AB Switch Double break E 14980

4 ABS10009 11 KV 400 Amps AB Switch Double break with insulators E 13738

5 ABS10002 a)11 KV 200 Amps AB Switch (Tilting)Porcelin type E 8250

ABS10016 b)11 KV 200 Amps AB Switch (Tilting)polymer 8550

8

Page 12: epdcl cost data 2014-15

Sl.No SAP CODE Name of the Material

REC Specification

No.Unit Rupees

6 ABS10004 a)11 KV 200 Amps AB Switch (Horizontal) E 7901

ABS10018 b) 6.3KV Single Phase 100A TT AB switches with insulators 3788.58

7 LAS00004 30 KV 10 KA Metal Oxide Lightning Arrester (station type) 16/1981 (R-55/1987) E 4336

8 LAS00003 (Line type) 33 KV Line type Lighting Arrester E 1670

9 LAS00002 (Station type) 9 KV 10 KA Metal Oxide Lighting Arrester E 1726

10 LAS00001 (Line type) 9 KV 5 KA Metal Oxide Lighting Arrester 55/1987 E 372

11 HGF30002 33 KV HG Fuse set Set 9450

12 HGF10002 11 KV HG Fuse Set Set 1649

13 HGF10003 6.3 KV HG Fuse Set Set 707.20

14 HGF00004 LT HG Fuse Set Set 1313

15 BAT00027 24 Volts 40 AH Battery set including Battery charger E 15900

16 BAT00027 24V, 40 AH Batteries with chargers of conventional type E 18220

17 24 Volts 40 AH Battery set without Battery charger E 6371

18 12 V, 40 AH SMF Batteries cells E 3244

19 BAT00015 12 V, 80 AH SMF Batteries cells E 8475

20 BAT00020 220 V, 80 AH SMF Batteries and Chargers & DCDB E 234824

21 BAT00022 220 V, 80 AH SMF Batteries E 201454.41

22 LT Switched capacitors

a 1x9 KVAR E 2548

b 1x10 KVAR E 2614

23 CPT10027 11 KV 2 MVAR Capacitor banks with associated equipment

a Type A E 1000000

b Type B with 40 Mtrs HT UG cable E 895869

c Type C (Indoor Type) with HT UG cable E 1295000

24 Sectionalizers E 588444

25 Auto - Reclosures E 925206

26 BRK00001 11 KV 3 Way RMU (Conventional) E 171658

27 BRK00002 11 KV 3 Way RMU (SF6) E 269592.50

9

Page 13: epdcl cost data 2014-15

Sl.No SAP CODE Name of the Material

REC Specification

No.Unit Rupees

28 BRK00002 (5 way) 11 KV SF6 5 Way RMU E 518040.49

29 33 KV Indoor twin feeder control panel E 285007

30 BRK30014 33KV twin feeder control and relay panel (220V DC) E 147136

31 Indoor type VCB with control panel (LV) E 376368

32 Indoor type VCB with control panel (feeder) E 274818.43

33 11 VCB for bus coupler E 210677

34 11KV switch Fuse unit (SFU) E 100000

35 33KV switch Fuse unit (SFU) E 200000

36 33KV 3-way RMU without VCB E 1020110

37 33KV 3-way RMU with VCB E 1445325

38 11KV metering panel with CTS& PTS (Indoor) E 150000

39 33KV metering panel with CTS&PTS (Indoor) E 300000

SUBHEAD -VIII: ENERGY METERS AND METERING EQUIPMENT

1 MTE10002 a) LT Single Phase High quality Meter Class 1 accuracy ( 5-20A) E 730

MTE10019 b) 1 Ph 5-30 Meter IR port, Sup Capacitor - PP Box E 819

MTE10015 c) LT Single Phase Electronic Energy Meter 2.5 - 10A E 447

MTE10019 d) LT Single Phase Class 1 accuracy (push fit type box Non push fit type TC) 5-30A E 796

2 MTE30001 a) Three Phase Electronic Meter 10A - 40A with P P Box E 1940

No code b) Three Phase High Quality Meter 10 - 40A (Counter type display without Box) E 2150

3 MCT30036 a) LT 3-Ph Class-0.5 Accuracy CT Operated Electronic TVR Meter 200/5A E 6899

MCT30035 b) LT 3-Ph Class-0.5 Accuracy CT Operated Electronic TVR Meter 125/5A E 6525

MCT30051 c) LT TVR METER 125/5A CTS IN PP BOX. 0.5S ACCR WITH DLMSDL E 6840

4 MHT10003 a) HT Trivector Meter 0.5 class accuracy(10/5A) E 4244

MHT10047 b) HT Trivector Meter 0.5 class accuracy (200/1,100/1A) E 3746

MHT10055 c) HTTVR3P4W11KV/110V 10/5A 0.5S 30M DLMS-C E 3400.80

MHT30062 d) HTTVR 3P4W 33KV/110V 200/1A 0.2S 30MIN IPDLMS E 7560.57

e) HTTVR3P4W11KV/110V 200/1A 0.2S DLMS-C E 7560.57

MTE10032 f)Single phase 10-60A Net meter with PP Box E 1565

MTE30019 g)Three phase 10-60A Net meter with PP Box E 5582

MHT30060 h)(11KV-400KV)/110V,(40A-1000A)ABT Energy meters 0.2S Class E 10267

10

Page 14: epdcl cost data 2014-15

Sl.No SAP CODE Name of the Material

REC Specification

No.Unit Rupees

5 11 KV Metering cubicles ITR10039 a) 10/5 A class 0.2S(O/D) accuracy E 39326.78

ITR10040 b) 20/5 A(O/D),0.2S Class accuracy E 41678.92

c)20/5 A(I/D),0.2S Class accuracy E 42886.03

ITR10029 d) 30/5A(O/D),0.2S Class accuracy E 41678.92

e) 40/5A(O/D),0.2S Class accuracy E 41678.92

ITR10006 f) 40/5A(I/D),0.5S Class accuracy 29989.87

ITR10042 g) 75/5 A(O/D),0.2S Class accuracy E 39014.76

ITR10041 h) 60/5 A, (O/D),0.2S Class accuracy E 39014.76

i)10/5 A class 0.2S(I/D) accuracy E 42886.03

6 BXS00024 Moulded Box for Single Phase service E 250

7 BXS00024 Moulded Box for 3 Phase service E 420

8 Moulded box for CT Meter(Poly phase) E 1647

9 BXS00004 HT Meter Box E 5731

10 BXS00022 A Type Distribution type BOX E 7342.06

11 BXS00021 B Type Distribution type BOX E 1963.50

12 SMC Meter Box with fixing clamps (3 phase meters) E 6750

13 SMC Meter Box with fixing clamps (S- phase meters) E 408

14 BXS00034 LT Distribution Boxes (SMC) suitable for duble feeder E 11194

15 BXS00035 LT Distribution Boxes (SMC) suitable for single feeder E 4500

SUBHEAD -IX: EARTHING MATERIALS

1 EMT00020 GI Earth pipe 40 mm , (1.8 mts. Length) E 418

2 EMT00022 GI Earth pipe 40 mm (2.5 mts. Length) E 497.26

3 EMT00006 CI Earth pipe 80mm dia, (2.5 mts. Length) E 2471

SUBHEAD -X: OTHER MATERIALS

1

CAH00101-Hand held Collection machines

Hand Held Computers with Printer E 8145

2 OMT10004 CMRI E 30700

3 OMT10049 IAMR unit for DTRs E 6000

11

Page 15: epdcl cost data 2014-15

Note:1

2

3 The extra percentage on cost of materials in Agency/Tribal areas can be allowed onthe labour component only, if they are manufactured in the Agency/Tribal areasitself except Forest produce.

a.       25% extra is allowed for the works located within the interior Agency / Tribal limits.(i.e.) for the works located within and upto 16 Kilometers from any all weather routeinside Agency/Tribal.

a.       40% extra is allowed for the works located within the interior Agency / Tribal Areai.e., for the works located beyond 16 Kilometers from any all weather route insideAgency/Tribal.

For hilly and tribal areas, the following EXTRA RATES are allowed over and aboveapproved cost data of labour.

COST DATA FOR HILLY AND TRIBAL AREASAS ADOPTED BY IRRIGATION DEPARTMENT IN THE STATE

No extra percentage is permissible in respect of Forest produce such as Bamboo,Rellu grass and all materials obtained from outside the Agency/Tribal.

The extra percentage under Agency/Tribal areas allowance may be allowed on thelabour component and on the labour charges in the rates for conveyance ofmaterials.

12

Page 16: epdcl cost data 2014-15

Sl. No. Particulars Qty. Rate

in Rs.Per Unit

Amountin Rs.

1 9.1 M PSCC Pole 12 3105 Each 37260

2 1.53M Cross Arm (Channel) without clamps 10 1418 Each 14180

3 Top Clamp with cleat 10 375 Each 3750

4 Back Clamp 10 172.00 Each 1720

5 Stay sets with clamps 6 1146 Each 6876

6 Bracing Set with double cross arm 1 7335 Set 7335

7 100 Sq.mm AAA Conductor 3.06 49166 K.M. 150448

8 33 KV Pin - Insulator with Pin 33 365 Each 12045

9 Strain Insulator set with metal parts( 3x 11 KV B&S Insulator with 33 KV Hard ware fitting) 6 1013 Set 6078

10 Concreting of Pole, Stay sets & Base concreting LS LS LS 34162

11 Misc. Items like coil earthing, pipe earthing, danger-boards, bolts & nuts, etc. LS LS LS 5160

Total Cost of Material 2790143% storage & handling charges on items (1) to (9) 239692 71913% Contingencies on Materials 8370Labour 69754Transport 1395111% Estt. & Genl. Charges On Materials 306921% cess 4090

Total 413061or say 413,060

1. R.E.C. - Construction Standard No. M11/1979 (R-1989) Costdata per Km of 33 KV Line with 100 Sq.mm AAA Conductor over 9.1 Mts.

PSCC Poles at 105 Mts. Span, 75 Kg/Sq.Mt wind pressure, working load 280 Kgs.

13

Page 17: epdcl cost data 2014-15

Sl. No. Particulars Qty. Rate

in Rs.Per Unit

Amountin Rs.

1 9.1 M PSCC Pole 14 3105 Each 43470

2 1.53M Cross Arm (Channel) without clamps 12 1418 Each 17016

3 Top Clamp with cleat 12 375.00 Each 4500

4 Back Clamp 12 172 Each 2064

5 Stay sets with clamps 6 1146 Each 6876

6 Bracing Set with double cross arm 1 7335 Set 7335

7 100 Sq.mm AAA Conductor 3.06 49166 K.M. 150448

8 33 KV Pin - Insulator with Pin 39 365 Each 14235

9 Strain Insulator set with metal parts 6 1013 Set 6078

10 Concreting of Pole, Stay sets & Base concreting LS LS LS 38704.38

11 Misc. Items like coil earthing, pipe earthing, danger-boards, bolts & nuts, etc. LS LS LS 6020

Total Cost of Material 296746

3% storage & handling charges on items (1) to (9) 252022 7561

3% Contingencies on Materials 8902Labour 74187Transport 1483711% Estt. & Genl. Charges On Materials 326421% cess 4349

Total 439224or say 439,220

2. R.E.C. - Construction Standard No. M11/1979 (R-1989)Costdata per Km of 33 KV Line with 100 Sq.mm AAA Conductor over 9.1 Mts.

PSCC Poles at 80 Mts. Span, 100 Kg/Sq.Mt wind pressure, working load 280 Kgs.

14

Page 18: epdcl cost data 2014-15

Sl. No. Particulars Qty. Rate

in Rs.Per Unit

Amountin Rs.

1 8.0 M PSCC Pole 18 1504 Each 27072

2 1.07M Cross Arm (Channel) without clamps 16 511 Each 8176

3 Top Clamp with cleat 16 214 Each 3424

4 Back Clamp 16 123 Each 1968

5 Stay sets with clamps 6 424 Each 2544

6 Bracing Set with double cross arm 1 6171 Set 6171

7 55 Sq.mm AAA Conductor 3.06 28149 K.M. 86136

8 11 KV Pin - Insulator with Pin 51 111 Each 5682

9 Strain Insulator set with metal parts 6 272 Set 1632

10 Concreting of Pole, Stay sets & Base concreting LS LS LS 47789

11 Misc. Items like coil earthing, pipe earthing, danger-boards, bolts & nuts, etc. LS LS LS 7740

Total Cost of Material 198334

3% storage & handling charges on items (1) to (9) 142805 4284

3% Contingencies on Materials 5950Labour 49583Transport 991711% Estt. & Genl. Charges On Materials 218171% cess 2899

Total 292783or say 292,780

3. R.E.C. - Construction Standard No. A-5/1972Costdata per Km of 11 KV Line with 55 Sq.mm AAA Conductor over 8 Mts.

PSCC Poles at 60 Mts. Span, 75 Kg/Sq.Mt wind pressure, working load 140 Kgs.

15

Page 19: epdcl cost data 2014-15

Sl. No. Particulars Qty. Rate

in Rs.Per Unit

Amountin Rs.

1 8.0 M PSCC Pole 17 1844 Each 31348

2 1.07M Cross Arm (Channel) without clamps 15 511 Each 7665

3 Top Clamp with cleat 15 214 Each 3210

4 Back Clamp 15 123 Each 1845

5 Stay sets with clamps 6 424 Each 2544

6 Bracing Set with double cross arm 1 6171 Set 6171

7 55 Sq.mm AAA Conductor 3.06 28149 K.M. 86136

8 11 KV Pin - Insulator with Pin 48 111 Each 5348

9 Strain Insulator set with metal parts 6 272 Set 1632

10 Concreting of Pole, Stay sets & Base concreting LS LS LS 45518

11 Misc. Items like coil earthing, pipe earthing, danger-boards, bolts & nuts, etc. LS LS LS 7310

Total Cost of Material 198727

3% storage & handling charges on items (1) to (9) 145899 4377

3% Contingencies on Materials 5962Labour 49682Transport 993611% Estt. & Genl. Charges On Materials 218601% cess 2905

Total 293449or say 293,450

4. R.E.C. - Construction Standard No. A-5/1972Costdata per Km of 11 KV Line with 55 Sq.mm AAA Conductor over 8 Mts.

PSCC Poles at 65 Mts. Span, 100 Kg/Sq.Mt wind pressure, working load 200 Kgs.

16

Page 20: epdcl cost data 2014-15

Sl. No. Particulars Qty. Rate

in Rs.Per Unit

Amountin Rs.

1 8 M PSCC Pole 18 1504.00 Each 270722 1.07M Cross Arm (Channel) without clamps 16 511 Each 8176

3 Top Clamp with cleat 16 214 Each 3424

4 Back Clamp 16 123 Each 1968

5 Stay sets with clamps 6 424 Each 2544

6 Bracing Set with double cross arm 1 6171 Set 6171

7 34 Sq.mm AAA Conductor 3.06 17870 K.M. 54682

8 11 KV Pin - Insulator with Pin 51 111 Each 5682

9 Strain Insulator set with metal parts 6 272 Set 1632

10 Concreting of Pole, Stay sets & Base concreting LS LS LS 47789

11 Misc. Items like coil earthing, pipe earthing, danger-boards, bolts & nuts, etc. LS LS LS 7740

Total Cost of Material 166880

3% storage & handling charges on items (1) to (9) 111351 3341

3% Contingencies on Materials 5006Labour 41720Transport 834411% Estt. & Genl. Charges On Materials 183571% cess 2436

Total 246084or say 246,080

PSCC Poles at 60 Mts. Span, 75 Kg/Sq.Mt wind pressure, working load 140 Kgs.

5. R.E.C. - Construction Standard No. A-5/1972Costdata per Km of 11 KV Line with 34 Sq.mm AAA Conductor over 8 Mts.

17

Page 21: epdcl cost data 2014-15

Sl. No. Particulars Qty. Rate

in Rs.Per Unit

Amountin Rs.

1 8 PSCC Pole 17 1844 Each 31348

2 1.53M Cross Arm (Channel) without clamps 15 511 Each 7665

3 Top Clamp with cleat 15 214 Each 3210

4 Back Clamp 15 123 Each 1845

5 Stay sets with clamps 6 424 Each 2544

6 Bracing Set with double cross arm 1 6171 Set 6171

7 34 Sq.mm AAA Conductor 3.06 17870 K.M. 54682

8 11 KV Pin - Insulator with Pin 48 111 Each 5348

9 Strain Insulator set with metal parts 6 272 Set 1632

10 Concreting of Pole, Stay sets & Base concreting LS LS LS 45518

11 Misc. Items like coil earthing, pipe earthing, danger-boards, bolts & nuts, etc. LS LS LS 7310

Total Cost of Material 167273

3% storage & handling charges on items (1) to (9) 114445 3433

3% Contingencies on Materials 5018Labour 41818Transport 836411% Estt. & Genl. Charges On Materials 184001% cess 2443

Total 246748or say 246,750

6. R.E.C. - Construction Standard No. A-5/1972Costdata per Km of 11 KV Line with 34 Sq.mm AAA Conductor over 8 Mts.

PSCC Poles at 65 Mts. Span, 100 Kg/Sq.Mt wind pressure, working load 200 Kgs.

18

Page 22: epdcl cost data 2014-15

Sl. No. Particulars Qty. Rate

in Rs.Per Unit

Amountin Rs.

1 8 M PSCC Pole 13 1504 Each 19552

2 Top Clamp with cleat 10 214 Each 2140

3 D clamp 10 132 Each 1320

4 MS Stay sets 6 358 Each 2148

5 34 Sq.mm AAA Conductor 2.04 17870 K.M. 36455

6 11 K.V.Pin-Insulator with Pin 11 111 Each 1226

7 Strain Insulator set 4 272 Set 1088

8 Concreting of Pole,Stay sets & Base concreting L.S. 36433

9 Misc. Items like coil earthing,pipe earthings, danger-boards, bolts L.S. 5590& nuts, etc.

Total Cost of Material 105952

3% storage & handling charges on items (1) to (7) 63929 1918

3% Contingencies on Materials 3179Labour 26488Transport 529811% Estt. & Genl. Charges On Materials 116551% cess 1545

Total 156034or say 156,030

7. R.E.C. - Construction Standard No. A-17/1972Costdata per Km of 6.3 KV S-ph Line with 34 Sq.mm AAA Conductor over 8 Mts.PSCC Poles at 90 Mts. Span, 75 Kg/Sq.Mt wind pressure, working load 140 Kgs.

19

Page 23: epdcl cost data 2014-15

Sl. No. Particulars Qty. Rate

in Rs.Per Unit

Amountin Rs.

1 8 M PSCC Pole 13 1844.00 Each 23972

2 Top Clamp with cleat 10 214 Each 2140

3 D clamp 10 132 Each 1320

4 MS Stay sets 6 358 Set 2148

5 34 Sq.mm AAA Conductor 2.04 17870 K.M. 36455

6 11 K.V.Pin-Insulator with Pin 11 111 Each 1226

7 Strain Insulator set 4 272 Set 1088

8 Concreting of Pole,Stay sets &

Base concreting L.S. 364339 Misc. Items like coil earthing,

pipe earthings, danger-boards, bolts L.S. 5590& nuts, etc.

Total Cost of Material 110372

3% storage & handling charges on items (1) to (7) 68349 2050

3% Contingencies on Materials 3311Labour 27593Transport 551911% Estt. & Genl. Charges On Materials 121411% cess 1610

Total 162596or say 162,600

8. R.E.C. - Construction Standard No. A-17/1972Costdata per Km of 6.3 KV S-ph Line with 34 Sq.mm AAA Conductor over 8 Mts.PSCC Poles at 90 Mts. Span, 100 Kg/Sq.Mt wind pressure, working load 200 Kgs.

20

Page 24: epdcl cost data 2014-15

Sl. No. Particulars Qty. Rate

in Rs.Per Unit

Amountin Rs.

1 8 M PSCC Pole 16 1504.00 Each 24064

2 L.T. 3 Phase cross arms 18 436 Each 7840

3 Back Clamp 18 123 Each 2214

4 Stay sets 4 394 Each 1576

5 55 Sq.mm AAA Conductor 3.06 28149 K.M. 86136

6 34 Sq.mm AAA Conductor 2.04 17870 K.M. 36455

7 Shakle Insulator set 42 44 Set 1848

8 L.T.pin insulator with pin 48 43.25 Set 2076

9 C.I. Knob 16 12 Each 192

10 Concreting of Pole,Stay sets &

Base concreting L.S. 4094311 Misc. Items like coil earthing,

pipe earthings, danger-boards, bolts L.S. 6880& nuts, etc.

Total Cost of Material 210224

3% storage & handling charges on items (1) to (9) 162401 4872

3% Contingencies on Materials 6307Labour 52556Transport 1051111% Estt. & Genl. Charges On Materials 231251% cess 3076

Total 310671or say 310,670

3 x 55 Sq.mm + 2 x 34 Sq.mm AAAC over 8 Mts.PSCC Poles at 65 Mts. Span, 75 Kg/Sq.Mt wind pressure, working load 140 Kgs.

9. R.E.C. - Construction Standard No. B-5/1972Costdata per Km of LT 3-Ph 5 Wire Line(Horizontal formation ) with

21

Page 25: epdcl cost data 2014-15

Sl. No. Particulars Qty. Rate

in Rs.Per Unit

Amountin Rs.

1 8 M PSCC Pole 18 1844 Each 33192

2 L.T. 3 Phase cross arms 20 436 Each 8711

3 Back Clamp 20 123 Each 2460

4 LT Stay sets 4 394 Each 1576

5 55 Sq.mm AAA Conductor 3.06 28149 K.M. 86136

6 34 Sq.mm AAA Conductor 2.04 17870 K.M. 36455

7 Shakle Insulator set 42 44 Set 1848

8 L.T.pin insulator with pin 56 43 Set 2422

9 C.I. Knob 18 12 Each 216

10 Concreting of Pole,Stay sets & L.S. 45485

Base concreting11 Misc. Items like coil earthing,

pipe earthings, danger-boards, bolts L.S. 7740& nuts, etc.

Total Cost of Material 226241

3% storage & handling charges on items (1) to (9) 173016 5190

3% Contingencies on Materials 6787Labour 56560Transport 1131211% Estt. & Genl. Charges On Materials 248871% cess 3310

Total 334288or say 334,290

10. R.E.C. - Construction Standard No. B-5/1972Costdata per Km of LT 3-Ph 5 Wire Line(Horizontal formation ) with

3 x 55 Sq.mm + 2 x 34 Sq.mm AAAC over 8 Mts.PSCC Poles at 60 Mts. Span, 100 Kg/Sq.Mt wind pressure, working load 200 Kgs.

22

Page 26: epdcl cost data 2014-15

Sl. No. Particulars Qty. Rate

in Rs.Per Unit

Amountin Rs.

1 8 M PSCC Pole 16 1504.00 Each 24064

2 L.T. 3 Phase cross arms 18 436 Each 7840

3 Back Clamp 18 123 Each 2214

4 LT Stay sets 4 394 Each 1576

5 34 Sq.mm AAA Conductor 5.10 17870 K.M. 91137

6 Shakle Insulator set 42 44 Set 1848

7 L.T.pin insulator with pin 48 43 Set 2076

8 C.I. Knob 16 12 Each 192

9 Concreting of Pole,Stay sets &

Base concreting L.S. 4094310 Misc. Items like coil earthing,

pipe earthings, danger-boards, bolts L.S. 6880& nuts, etc.

Total Cost of Material 178770

3% storage & handling charges on items (1) to (8) 130947 3928

3% Contingencies on Materials 5363Labour 44693Transport 893911% Estt. & Genl. Charges On Materials 196651% cess 2614

Total 263971or say 263,970

11. R.E.C. - Construction Standard No. B-5/1972Costdata per Km of LT 3-Ph 5 Wire Line(Horizontal formation ) with

5 x 34 Sq.mm AAAC over 8 Mts.PSCC Poles at 65 Mts. Span, 75 Kg/Sq.Mt wind pressure, working load 140 Kgs.

23

Page 27: epdcl cost data 2014-15

Sl. No. Particulars Qty. Rate

in Rs.Per Unit

Amountin Rs.

1 8 M PSCC Pole 18 1844 Each 33192

2 L.T. 3 Phase cross arms 20 436 Each 8711

3 Back Clamp 20 123 Each 2460

4 LT Stay sets 4 394 Each 1576

5 34 Sq.mm AAA Conductor 5.10 17870 K.M. 91137

6 Shakle Insulator set 42 44 Set 1848

7 L.T.pin insulator with pin 56 43 Set 2422

8 C.I. Knob 18 12 Each 216

9 Concreting of Pole,Stay sets &

Base concreting L.S. 4548510 Misc. Items like coil earthing,

pipe earthings, danger-boards, bolts L.S. 7740& nuts, etc.

Total Cost of Material 194787

3% storage & handling charges on items (1) to (8) 141562 4247

3% Contingencies on Materials 5844Labour 48697Transport 973911% Estt. & Genl. Charges On Materials 214271% cess 2847

Total 287588or say 287,590

12. R.E.C. - Construction Standard No. B-5/1972Costdata per Km of LT 3-Ph 5 Wire Line(Horizontal formation ) with

5 x 34 Sq.mm AAAC over 8 Mts.PSCC Poles at 60 Mts. Span, 100 Kg/Sq.Mt wind pressure, working load 200 Kgs.

24

Page 28: epdcl cost data 2014-15

Sl. No. Particulars Qty. Rate

in Rs.Per Unit

Amountin Rs.

1 8 M PSCC Pole 16 1504.00 Each 24064

2 L.T. 3 Phase cross arms 18 327 Each 5894

3 Back Clamp 18 123 Each 2214

4 LT Stay sets 4 394 Each 1576

5 55 Sqmm AAA Conductor 3.06 28149 K.M. 86136

6 34 Sq.mm AAA Conductor 1.02 17870 K.M. 18227

7 Shakle Insulator set 32 44 Set 1408

8 L.T.pin insulator with pin 36 43.25 Set 1557

9 C.I. Knob 16 12 Each 192

10 Concreting of Pole,Stay sets &

Base concreting L.S. 4094311 Misc. Items like coil earthing,

pipe earthings, danger-boards, bolts L.S. 6880& nuts, etc.

Total Cost of Material 189091

3% storage & handling charges on items (1) to (9) 141268 4238

3% Contingencies on Materials 5673Labour 47273Transport 945511% Estt. & Genl. Charges On Materials 208001% cess 2765

Total 279295or say 279,290

3 x 55 Sq.mm + 1 x 34 Sqmm AAAC over 8 Mts.PSCC Poles at 65 Mts. Span, 75 Kg/Sq.Mt wind pressure, working load 140 Kgs.

13. R.E.C. - Construction Standard No. B-12/1981Costdata per Km of LT 3-Ph 4 Wire Line(Horizontal formation ) with

25

Page 29: epdcl cost data 2014-15

Sl. No. Particulars Qty. Rate

in Rs.Per Unit

Amountin Rs.

1 8 M PSCC Pole 15 1844.00 Each 27660

2 L.T. 3 Phase cross arms 17 327 Each 5566

3 Back Clamp 17 123 Each 2091

4 LT Stay sets 4 394 Each 1576

5 55 Sqmm AAA Conductor 3.06 28149 K.M. 86136

6 34 Sq.mm AAA Conductor 1.02 17870 K.M. 18227

7 Shakle Insulator set 32 44 Set 1408

8 L.T.pin insulator with pin 33 43 Set 1427

9 C.I. Knob 15 12 Each 180

10 Concreting of Pole,Stay sets &

Base concreting L.S. 3867211 Misc. Items like coil earthing,

pipe earthings, danger-boards, bolts L.S. 6450& nuts, etc.

Total Cost of Material 189393

3% storage & handling charges on items (1) to (9) 144271 4328

3% Contingencies on Materials 5682Labour 47348Transport 947011% Estt. & Genl. Charges On Materials 208331% cess 2771

Total 279824.97or say 279,820

14. R.E.C. - Construction Standard No. B-12/1981Costdata per Km of LT 3 Ph 4 Wire Line(Horizontal formation ) with

3 x 55 Sq.mm + 1 x 34 Sqmm AAAC over 8 Mts.PSCC Poles at 60 Mts. Span, 100 Kg/Sq.Mt wind pressure, working load 200 Kgs.

26

Page 30: epdcl cost data 2014-15

Sl. No. Particulars Qty. Rate

in Rs.Per Unit

Amountin Rs.

1 8 M PSCC Pole 16 1504.00 Each 24064

2 L.T. 3 Phase cross arms 18 327 Each 5894

3 Back Clamp 18 123 Each 2214

4 LT Stay sets 4 394 Each 1576

5 34 Sq.mm AAA Conductor 4.08 17870 K.M. 72910

6 Shakle Insulator set 32 44 Set 1408

7 L.T.pin insulator with pin 36 43 Set 1557

8 C.I. Knob 16 12 Each 192

9 Concreting of Pole,Stay sets &

Base concreting L.S. 4094310 Misc. Items like coil earthing,

pipe earthings, danger-boards, bolts L.S. 6880& nuts, etc.

Total Cost of Material 157638

3% storage & handling charges on items (1) to (8) 109815 3294

3% Contingencies on Materials 4729Labour 39410Transport 788211% Estt. & Genl. Charges On Materials 173401% cess 2303

Total 232597or say 232,600

15. R.E.C. - Construction Standard No. B-12/1981Costdata per Km of LT 3-Ph 4 Wire Line(Horizontal formation )

with 4 x 34 Sqmm AAAC over 8 Mts.PSCC Poles at 65 Mts. Span, 75 Kg/Sq.Mt wind pressure, working load 140 Kgs.

27

Page 31: epdcl cost data 2014-15

Sl. No. Particulars Qty. Rate

in Rs.Per Unit

Amountin Rs.

1 8 M PSCC Pole 15 1844 Each 27660

2 L.T. 3 Phase cross arms 17 327 Each 5566

3 Back Clamp 17 123 Each 2091

4 LT Stay sets 4 394 Each 1576

5 34 Sq.mm AAA Conductor 4.08 17870 K.M. 72910

6 Shakle Insulator set 32 44 Set 1408

7 L.T.pin insulator with pin 33 43 Set 1427

8 C.I. Knob 17 12 Each 204

9 Concreting of Pole,Stay sets &

Base concreting L.S. 38672

10 Misc. Items like coil earthing,pipe earthings, danger-boards, bolts L.S. 6450& nuts, etc.

Total Cost of Material 157964

3% storage & handling charges on items (1) to (8) 112842 3385

3% Contingencies on Materials 4739Labour 39491Transport 789811% Estt. & Genl. Charges On Materials 173761% cess 2309

Total 233162or say 233,160

with 4 x 34 Sqmm AAAC over 8 Mts.

16. R.E.C. - Construction Standard No. B-12/1981Costdata per Km of LT 3-Ph 4 Wire Line(Horizontal formation )

PSCC Poles at 60 Mts. Span, 100 Kg/Sq.Mt wind pressure, working load 200 Kgs.

28

Page 32: epdcl cost data 2014-15

Sl. No. Particulars Qty. Rate

in Rs.Per Unit

Amountin Rs.

1 8 M PSCC Pole 16 1504.00 Each 24064

2 L.T. 1 Phase cross arms 18 319 Each 5742

3 Back Clamp 18 123 Each 2214

4 LT Stay sets 4 394 Each 1576

5 34 Sq.mm AAA Conductor 3.06 17870 K.M. 54682

6 Shakle Insulator set 22 44 Set 968

7 L.T.pin insulator with pin 24 43 Set 1038

8 C.I. Knob 16 12 Each 192

9 Concreting of Pole,Stay sets &

Base concreting L.S. 4094310 Misc. Items like coil earthing,

pipe earthings, danger-boards, bolts L.S. 6880& nuts, etc.

Total Cost of Material 138299

3% storage & handling charges on items (1) to (8) 90476 2714

3% Contingencies on Materials 4149Labour 34575Transport 691511% Estt. & Genl. Charges On Materials 152131% cess 2019

Total 203884or say 203,880

Note : Substitute the cost of 8 mts PSCC pole in above data for wind pressure of 100 kgs/Sqmts,and working load of 200 kgs

17. R.E.C. - Construction Standard No. B-14/1981Costdata per Km of LT S-Ph 3 Wire Line(Horizontal formation )

with 34 Sqmm AAAC over 8 Mts.PSCC Poles at 65 Mts. Span, 75 Kg/Sq.Mt wind pressure, working load 140 Kgs.

29

Page 33: epdcl cost data 2014-15

Sl. No. Particulars Qty. Rate

in Rs.Per Unit

Amountin Rs.

1 8 M PSCC Pole 16 1504.00 Each 24064

2 L.T. 1 Phase cross arms 18 268 Each 4824

3 Back Clamp 18 123 Each 2214

4 LT Stay sets 4 394 Each 1576

5 34 Sq.mm AAA Conductor 2.04 17870 K.M. 36455

6 Shakle Insulator set 12 44 Set 528

7 L.T.pin insulator with pin 12 43 Set 519

8 C.I. Knob 16 12 Each 192

9 Concreting of Pole,Stay sets &

Base concreting L.S. 4094310 Misc. Items like coil earthing,

pipe earthings, danger-boards, bolts L.S. 6880& nuts, etc.

Total Cost of Material 118195

3% storage & handling charges on items (1) to (8) 70372 2111

3% Contingencies on Materials 3546Labour 29549Transport 591011% Estt. & Genl. Charges On Materials 130011% cess 1723

Total 174036or say 174,040

18. R.E.C. - Construction Standard No. B-14/1981

with 2 x 34 Sqmm AAAC over 8 Mts.PSCC Poles at 65 Mts. Span, 75 Kg/Sq.Mt wind pressure, working load 140 Kgs.

Costdata per Km of LT S-Ph 2 Wire Line(Horizontal formation )

30

Page 34: epdcl cost data 2014-15

Sl. No. Particulars Qty. Rate

in Rs.Per Unit

Amountin Rs.

1 8 M PSCC Pole 16 1504.00 Each 24064

2 Suspension clamp assembly with eye hook 12 175 Each 2100

3 Dead end clamp assembly with eye hook 6 113 Each 678

4 LT Stay sets 4 394 Set 1576

5 L.T. A.B. Cable 3 x 16 + 25 Sqmm 1 47316 K.M. 47316

6 Insulated connectors with covers 56 82.00 Each 4592

7 Concreting of Pole,Stay concreting &

Base concreting L.S. 40943

8 Misc. Items like coil earthing,

bolts & nuts, etc. L.S. 6880

Total Cost of Material 128149

3% storage & handling charges on items (1) to (6) 80326 2410

3% Contingencies on Materials 3844Labour 32037Transport 640711% Estt. & Genl. Charges On Materials 140961% cess 1869

Total 188814or say 188,810

19. R.E.C. - Construction Standard No. B-32/1984Costdata per Km of LT line with 3 x 16 + 25 Sqmm AB Cable over 8 Mts.

PSCC Poles at 65 Mts. Span, 75 Kg/Sq.Mt wind pressure, working load 140 Kgs.

31

Page 35: epdcl cost data 2014-15

Sl. No. Particulars Qty. Rate

in Rs.Per Unit

Amountin Rs.

1 8 M PSCC Pole 16 1504.00 Each 24064

2 Suspension clamp assembly with eye hook 12 175 Each 2100

3 Dead end clamp assembly with eye hook 6 113 Each 678

4 LT Stay sets 4 394 Set 1576

5 L.T. A.B. Cable 2 x 16 + 25 Sqmm 1 37277 K.M. 37277

6 Insulated connectors with covers 56 82.00 Each 4592

7 Concreting of Pole,Stay concreting &

Base concreting L.S. 40943

8 Misc. Items like coil earthing,

bolts & nuts, etc. L.S. 6880

Total Cost of Material 118110

3% storage & handling charges on items (1) to (6) 70287 2109

3% Contingencies on Materials 3543Labour 29528Transport 590611% Estt. & Genl. Charges On Materials 129921% cess 1722

Total 173909or say 173,910

20. R.E.C. - Construction Standard No. B-32/1984Costdata per Km of LT line with 2 x 16 + 25 Sqmm AB Cable over 8 Mts.

PSCC Poles at 65 Mts. Span, 75 Kg/Sq.Mt wind pressure, working load 140 Kgs.

32

Page 36: epdcl cost data 2014-15

Sl. No. Particulars Qty. Rate

in Rs.Per Unit

Amountin Rs.

1 8 M PSCC Pole 16 1504.00 Each 24064

2 Suspension clamp assembly with eye hook 12 175 Each 2100

3 Dead end clamp assembly with eye hook 6 113 Each 678

4 LT Stay sets 4 394 Set 1576

5 L.T. A.B. Cable 1 x 16 + 25 Sqmm 1 26000 K.M. 26000

6 Insulated connectors with covers 56 82.00 Each 4592

7 Concreting of Pole,Stay concreting &

Base concreting L.S. 40943

8 Misc. Items like coil earthing,

bolts & nuts, etc. L.S. 6880

Total Cost of Material 106833

3% storage & handling charges on items (1) to (6) 59010 1770

3% Contingencies on Materials 3205Labour 26708Transport 534211% Estt. & Genl. Charges On Materials 117521% cess 1556

Total 157166or say 157,170

21. R.E.C. - Construction Standard No. B-32/1984Costdata per Km of LT line with 1 x 16 + 25 Sqmm AB Cable over 8 Mts.

PSCC Poles at 65 Mts. Span, 75 Kg/Sq.Mt wind pressure, working load 140 Kgs.

33

Page 37: epdcl cost data 2014-15

Sl. No. Particulars Qty. Rate

in Rs.Per Unit

Amountin Rs.

1 8 M PSCC Pole 16 1844 Each 29504

2 Suspension clamp assembly with eye hook 12 175 Each 2100

3 Dead end clamp assembly with eye hook 6 113 Each 678

4 LT Stay sets 4 394 Set 1576

5 L.T. A.B. Cable 3 x 16 + 25 Sqmm 1 47316 K.M. 47316

6 Insulated connectors with covers 56 82.00 Each 4592

7 Concreting of Pole,Stay concreting &

Base concreting L.S. 40943

8 Misc. Items like coil earthing,

bolts & nuts, etc. L.S. 6880

Total Cost of Material 133589

3% storage & handling charges on items (1) to (6) 85766 2573

3% Contingencies on Materials 4008Labour 33397Transport 667911% Estt. & Genl. Charges On Materials 146951% cess 1949

Total 196891or say 196,890

22. R.E.C. - Construction Standard No. B-32/1984Costdata per Km of LT line with 3 x 16 + 25 Sqmm AB Cable over 8 Mts.

PSCC Poles at 65 Mts. Span, 100 Kg/Sq.Mt wind pressure, working load 200 Kgs.

34

Page 38: epdcl cost data 2014-15

Sl. No. Particulars Qty. Rate

in Rs.Per Unit

Amountin Rs.

1 8 M PSCC Pole 16 1844 Each 29504

2 Suspension clamp assembly with eye hook 12 175 Each 2100

3 Dead end clamp assembly with eye hook 6 113 Each 678

4 LT Stay sets 4 394 Set 1576

5 L.T. A.B. Cable 2 x 16 + 25 Sqmm 1 37277 K.M. 37277

6 Insulated connectors with covers 56 82.00 Each 4592

7 Concreting of Pole,Stay concreting &

Base concreting L.S. 40943

8 Misc. Items like coil earthing,

bolts & nuts, etc. L.S. 6880

Total Cost of Material 123550

3% storage & handling charges on items (1) to (6) 75727 2272

3% Contingencies on Materials 3707Labour 30888Transport 617811% Estt. & Genl. Charges On Materials 135911% cess 1802

Total 181986or say 181,990

23. R.E.C. - Construction Standard No. B-32/1984Costdata per Km of LT line with 2 x 16 + 25 Sqmm AB Cable over 8 Mts.

PSCC Poles at 65 Mts. Span, 100 Kg/Sq.Mt wind pressure, working load 200 Kgs.

35

Page 39: epdcl cost data 2014-15

Sl. No. Particulars Qty. Rate

in Rs.Per Unit

Amountin Rs.

1 8 M PSCC Pole 16 1844 Each 29504

2 Suspension clamp assembly with eye hook 12 175 Each 2100

3 Dead end clamp assembly with eye hook 6 113 Each 678

4 LT Stay sets 4 394 Set 1576

5 L.T. A.B. Cable 1 x 16 + 25 Sqmm 1 26000 K.M. 26000

6 Insulated connectors with covers 56 82.00 Each 4592

7 Concreting of Pole,Stay concreting & Base concreting L.S. 40943

8 Misc. Items like coil earthing, bolts & nuts, etc. L.S. 6880

Total Cost of Material 112273

3% storage & handling charges on items (1) to (6) 64450 1934

3% Contingencies on Materials 3368Labour 28068Transport 561411% Estt. & Genl. Charges On Materials 123501% cess 1636

Total 165243or say 165,240

PSCC Poles at 65 Mts. Span, 100 Kg/Sq.Mt wind pressure, working load 200 Kgs.

24. R.E.C. - Construction Standard No. B-32/1984Costdata per Km of LT line with 1 x 16 + 25 Sqmm AB Cable over 8 Mts.

36

Page 40: epdcl cost data 2014-15

Sl. No. Particulars Cost of Material(Rs.)

Labour & Transport(Rs.)

1 11 KV/433V 100KVA Conventional Transformer 137262 4,563

2 Erection of 11 KV AB Switch (200A) Horizantal 7901 956

3 D.P.Structure (Including all Earthing) 28819 9,702

4 Erection of 11 KV H.G. Fuse set 1649 583

5 Installation of L.T.H.G. Fuse sets (2 Nos.) including connections 2626 1,166

6 LT Metering arrangements with CTs including cable connections and cleat arrangement 9003 940

7 Installation of A type distribuion box 7342 162

8 Installation of HT Lightening Arrestors (3No.s) 1116 605

9 Misc. Items 500

Total Cost of Material 196,218 18,6773% storage & handling charges on items (1) to (8) 5872

3% Contingencies on Materials 5887

Labour & Transport 18,677

11% Estt. & Genl. Charges on Materials 21584

1% cess 2482

250,719 or say : 250,720

Note:

25. R.E.C. - CONSTRUCTION STANDARD SPECIFICATION NO. F3&F4/1981COST DATA FOR ERECTION OF 100KVA-11KV/433V CONVENTIONAL TRANSFORMER

Total Cost in Rs.

Whenever a DTR is required in R-APDRP Towns, one IAMR unit, one LT TVR meter and its accessories should be included in the estimate.

37

Page 41: epdcl cost data 2014-15

Sl. No. Particulars Cost of Material(Rs.)

Labour & Transport(Rs.)

1 11 KV/433V 63KVA ,5 Star,Amorphous/CRGO with Conventional Distribution Transformer 108500 4,563

2 Erection of 11 KV AB Switch (200A) 7901 956

3 D.P.Structure (Including all Earthing) 28819 9,702

4 Erection of 11 KV H.G. Fuse set 1649 583

5 Installation of L.T.H.G. Fuse sets (2 Nos.) including connections 2626 1,166

6 LT Metering arrangements with CTs including cable connections and cleat arrangement 9003 940

7 Installation of A type distribuion box 7342 162

8 Installation of HT Lightning Arrestors with earth connection 1116 605

9 Misc. Items 420

Total Cost of Material 167,376 18,677

3% storage & handling charges on items 1 to 8 5,009

3% Contingencies on Materials 5,021

Labour & Transport 18,677

11% Estt. & Genl. Charges on Materials 18411

1% cess 2,145

Total Cost in Rs. 216,639 or say : 216,640

Note:

26. COST DATA FOR ERECTION OF 63KVA-11KV/433V CONVENTIONAL TRANSFORMER

Whenever a DTR is required in R-APDRP Towns, one IAMR unit, one LT TVR meter and its accessories should be included in the estimate.

38

Page 42: epdcl cost data 2014-15

Sl. No. Particulars Cost of Material(Rs.)

Labour & Transport(Rs.)

1 11 KV/433V 16KVA Conventional Distribution Transformer 65750 1,616

2 Erection of 11 KV AB Switch (200A) 7901 956

3 Single Pole.Structure with 9.1Mtr PSCC Pole (Including Earthing) 13186 3,448

4 Erection of 11 KV H.G. Fuse set 1649 583

5 CT Distribution box including CT wiring with 1x25 sqmm XLPE cable and cleat wiring 12067 940

6 Misc. Items(Danger boards,Bolts &Nuts,Concreting etc.) 1650 214

Total Cost of Material 102203 7757

3% storage & handling charges on items (1) to (5) 3,017

3% Contingencies on Materials 3,066

Labour & Transport 7,757

11% Estt. & Genl. Charges on Materials 11242

1% cess 1,273

Total Cost in Rs. 128,558 or say : 128,560

Note:

27. Cost Data For Erection of 3 Phase 16 KVA-11KV/433V

Whenever a DTR is required in R-APDRP Towns, one IAMR unit, one LT TVR meter and its accessories should be included in the estimate.

Conventional Distribution Transformer On Single Pole Structure

39

Page 43: epdcl cost data 2014-15

Sl. No. Particulars Cost of Material(Rs.)

Labour & Transport(Rs.)

1 11 KV/433V 25KVA Conventional Distribution Transformer 71612 1,616

2 Erection of 11 KV AB Switch (200A) 7901 956

3 Single Pole.Structure with 9.1Mtr PSCC Pole (Including Earthing) 13186 3,448

4 Erection of 11 KV H.G. Fuse set 1649 583

5 CT Distribution box including CT wiring with 1x50 sqmm XLPE cable and cleat wiring 17300 940

6 Misc. Items(Danger boards,Bolts &Nuts,Concreting etc.) 1500 196

Total Cost of Material 113,148 7,739

3% storage & handling charges on items (1) to (5) 3,349

3% Contingencies on Materials 3,394

Labour & Transport 7,739

11% Estt. & Genl. Charges on Materials 12446

1% cess 1,401

Total Cost in Rs. 141,478 or say : 141,480

Note:

28. Cost Data For Erection of 3 Phase 25 KVA-11KV/433VConventional Distribution Transformer On Single Pole Structure

Whenever a DTR is required in R-APDRP Towns, one IAMR unit, one LT TVR meter and its accessories should be included in the estimate.

40

Page 44: epdcl cost data 2014-15

Sl. No. Particulars Cost of Material(Rs.)

Labour & Transport(Rs.)

1 11 KV/433V 40KVA Conventional Distribution Transformer 95500 1,616

2 Erection of 11 KV AB Switch (200A) 7901 956

3 Single Pole.Structure with 9.1Mtr PSCC Pole (Including Earthing) 13186 3,448

4 Erection of 11 KV H.G. Fuse set 1649 583

5 CT Distribution box including CT wiring with 1x70 sqmm XLPE cable and cleat wiring 23082 940

6 Misc. Items(Danger boards,Bolts &Nuts,Concreting etc.) 1500 196

Total Cost of Material 142,818 7,739

3% storage & handling charges on items (1) to (5) 4,240

3% Contingencies on Materials 4,285

Labour & Transport 7,739

11% Estt. & Genl. Charges on Materials 15710

1% cess 1,748

Total Cost in Rs. 176,539 or say : 176,540

Note: Whenever a DTR is required in R-APDRP Towns, one IAMR unit, one LT TVR meter and its accessories should be included in the estimate.

29. Cost Data For Erection of 3 Phase 40 KVA-11KV/433VConventional Distribution Transformer On Single Pole Structure

41

Page 45: epdcl cost data 2014-15

Sl. No. Particulars Cost of Material(Rs.)

Labour & Transport(Rs.)

1 9.1 Mtr PSCC Pole 3105 994

2 15KVA Single Phase CSP Distribution Transformer 37522 437

3 Mounting arrangements for transformer 2743 618

4 Earthing with 1No 2.5 Mts Long 75 mm CI earth pipe 3160 431

5Distribution box with 1 No 100A Fuse unit and cleat wiring with 50 sqmm XLPE cable & LT side arm with strut

5865 303

6 Misc. Items(Danger boards,Bolts &Nuts,Concreting etc.) 1000

Total Cost of Material 53,395 2,783

3% storage & handling charges on items (1) to (5) 1,572

3% Contingencies on Materials 1,602

Labour & Transport 2,783

11% Estt. & Genl. Charges on Materials 5873

1% cess 652

Total Cost in Rs. 65,877 or say : 65,880

Note: Whenever a DTR is required in R-APDRP Towns, one IAMR unit, one LT TVR meter and its accessories should be included in the estimate.

30. Cost Data For Erection of Single Phase 15 KVA-6.3KV/0-240VCSP Transformer(Oil immersed) On 9.1Mtr PSCC Pole Support

42

Page 46: epdcl cost data 2014-15

Sl.No. Particulars Qty. Rate in Rs. Per Unit Amount in

Rs.

1 15KVA Single Phase CSP Distribution Transformer 1 No. 37,522 Each 37,522

2 Mounting arrangements for Transformer 1 Set 2,743 Each 2,743

3 Pipe earthing 1 No. 810 Each 810

4 Misc. Items L.S. L.S. L.S. 500

Total Cost of Material 41,575

3% storage & handling charges on items (1) to (3) 1,232

3% Contingencies on Materials 1,247

Labour & Transport 2,592

11% Estt. & Genl. Charges On Materials 4,573

1% Cess 512Total Cost in Rs. 51,732

Or say : 51,730

Note:

31. R.E.C. - CONSTRUCTION STANDARD SPECIFICATION NO. F3&F4/1981COST DATA FOR ERECTION OF 15KVA SINGLE PHASE 6.3KV/0-240V

C.S.P TRANSFORMER (OIL IMMERSED) ON EXISTING 8M PSCC SUPPORT

Whenever a DTR is required in R-APDRP Towns, one IAMR unit, one LT TVR meter and its accessories should be included in the estimate.

43

Page 47: epdcl cost data 2014-15

Sl.No. Particulars Qty. Rate in Rs. Per Unit Amount in

Rs.

1 15 KVA Oil Immersed Single Phase 6.3KV/0-240V Amorphous Metal Core Transformer 1 No. 37,522 Each 37,522

2 Mounting arrangements for Transformer 1 Set 2,743 Each 2,743

3 Pipe earthing 1 No. 810 Each 810

4 Misc. Items L.S. L.S. L.S. 500

Total Cost of Material 41,575

3% storage & handling charges on items (1) to (3) 1,232

3% Contingencies on Materials 1,247

Labour & Transport 2,403

11% Estt. & Genl. Charges On Materials 4,573

1% Cess 510Total Cost in Rs. 51,541 Or say : 51,540

Note: Whenever a DTR is required in R-APDRP Towns, one IAMR unit, one LT TVR meter and its accessories should be included in the estimate.

COST DATA FOR ERECTION OF 15KVA SINGLE PHASE 6.3KV/0-240VAMORPHOUS METAL CORE C.S.P TRANSFORMER (OIL IMMERSED)

ON EXISTING 8M PSCC SUPPORT

32. R.E.C. - CONSTRUCTION STANDARD SPECIFICATION NO. F3&F4/1981

44

Page 48: epdcl cost data 2014-15

Sl.No. Particulars Qty. Rate in Rs. Per Unit Amount in

Rs.

1 1 Phase (5-30A) Energy meter 1 879 Each 879

2 1 Phase 15A M.C.B./Fuse Unit 1 201 Each 201

3 P.V.C. Cable 6 Sq.mm Single Core 20 28 Each 560

4 Moulded Distribution Box 1 250 Each 250

5 P.V.C. Bends 38mm 1 22 Each 22

6 Bolts, Nuts etc. L.S. L.S. L.S. 80

Total Cost of Material 1,992

3% Contingencies 60

Labour & Transport 1,076

11% Estt. & Genl. Charges 219

1% Cess 33Total Cost in Rs. 3,380 Or say : 3,380

33. R.E.C. - CONSTRUCTION STANDARD SPECIFICATION NO. H1&H3/1981COST DATA FOR SINGLE PHASE AGRICULTURE SERVICE ERECTED ON SUPPORT

45

Page 49: epdcl cost data 2014-15

Sl.No. Particulars Qty. Rate in Rs. Per Unit Amount in

Rs.

1 3 Phase (10A-40A ) Energy meter 1 1,940 Each 1,940

2 3 Phase 40A M.C.B./Fuse Unit (3 Nos.) 1 729 Each 729

3 P.V.C. Cable 6 Sq.mm Single Core 30 28 Each 840

4 Moulded Distribution Box 1 420 Each 420

5 Installation of 2KVAR Capacitor 1 500 1 500

6 Misc. items such as Bolts, Nuts & Board etc. L.S. L.S. L.S. 80

Total Cost of Material 4,509

3% Contingencies 135

Labour & Transport 1,739

11% Estt. & Genl. Charges 496

1% Cess 69Total Cost in Rs. 6,948 Or say : 6,950

34. R.E.C. - CONSTRUCTION STANDARD SPECIFICATION NO. H6&H8/1981COST DATA FOR RELEASE OF POLY PHASE AGRICULTURE SERVICE ERECTED ON

SUPPORT

46

Page 50: epdcl cost data 2014-15

Qty . Amount Qty. Amount

1 Single Phase electronic Energy Meter 5-30A,IRPort withPP Box 819 1 819 819

2 15A M.C.B./Fuse Unit 120/E 1 201 201

3 P.V.C. Cable single core 2.5 Sq.mm 20/M 60 1200 1200

4 Moulded Distribution Box 250/E 1 250 250

5 G.I. Wire No.8 60/Kg 1 Kg. 60 60

6 P.V.C. Pipe 20mm 25/M 2 M 50 50

7 P.V.C. Bends 20mm 5/E 2 Nos. 10 10

8 Misc. L.S 85 85

Total 1270 1405 2675

3% Contingencies on Materials 38 42 80

Labour & Transport 202 430 633

11% Estt. & Genl. Charges 140 155 294

1% Cess 37Total Cost in Rs. 1650 2032 3,719 Or say : 3,720

Note : Item Nos. 4 to 7 are to be borne & arranged by the Consumer.

35. R.E.C.-CONSTRUCTION STANDARD SPECIFICATION NO.H1 TO H3/1981COST DATA FOR DOMESTIC AND NON-DOMESTIC SERVICE CONNECTION (SINGLE PHASE)

WITH QUALITY METER

Sl. No. Particulars Rate Chargable to Chargable to Amount in Rs.

47

Page 51: epdcl cost data 2014-15

Qty . Amount Qty. Amount

1 Single Phase electronic Energy Meter 2.5-10A 447 1 447 447

2 15A M.C.B./Fuse Unit 115/E 1 201 201

3 P.V.C. Cable single core 2.5 Sq.mm 20/M 60 1200 1200

4 Moulded Distribution Box 250/E 1 250.00 250

5 G.I. Wire No.8 60/Kg 1 Kg. 60 60

6 P.V.C. Pipe 20mm 25/M 2 M 50 50

7 P.V.C. Bends 20mm 5/E 2 Nos. 10 10

8 Misc. L.S 85 85

Total 898 1405 2303

3% Contingencies on Materials 27 42 69

Labour & Transport 202 430 633

11% Estt. & Genl. Charges 99 155 253

1% Cess 33Total Cost in Rs. 1226 2032 3,290 Or say : 3,290

Note : Item Nos. 4 to 7 are to be borne & arranged by the Consumer.

36. R.E.C.-CONSTRUCTION STANDARD SPECIFICATION NO.H1 TO H3/1981COST DATA FOR DOMESTIC AND NON-DOMESTIC SERVICE CONNECTION (SINGLE PHASE)

WITH ELECTRONIC METER

Sl. No. Particulars RateChargable to

DISCOMChargable to

Consumer Amount in Rs.

48

Page 52: epdcl cost data 2014-15

Qty . Amount Qty. Amount

1 Single Phase Quality Energy Meter 5-20A 730 1 730 730

2 15A M.C.B./Fuse Unit 120/E 1 201 201

3 P.V.C. Cable single core 2.5 Sq.mm 20/M 60 1200 1200

4 Moulded Distribution Box 250/E 1 250.00 250

5 G.I. Wire No.8 60/Kg 1 Kg. 60 60

6 P.V.C. Pipe 20mm 25/M 2 M 50 50

7 P.V.C. Bends 20mm 5/E 2 Nos. 10 10

8 Misc. L.S 85 85

Total 1181 1405 2586

3% Contingencies on Materials 35 42 78

Labour & Transport 202 430 633

11% Estt. & Genl. Charges 130 155 284

1% Cess 36

Total Cost in Rs. 1549 2032 3,616 Or say : 3,620

Note : Item Nos. 4 to 7 are to be borne & arranged by the Consumer.

Chargable to DISCOM

Chargable to Consumer Amount in

Rs.

37. R.E.C.-CONSTRUCTION STANDARD SPECIFICATION NO.H1 TO H3/1981COST DATA FOR DOMESTIC AND NON-DOMESTIC SERVICE CONNECTION (SINGLE PHASE)

WITH QUALITY METER

Sl. No. Particulars Rate

49

Page 53: epdcl cost data 2014-15

Qty . Amount Qty. Amount

1 Three Phase electronic Energy Meter 10-40A 1940.00 1 1940 1940

2 3 Phase 60A M.C.B./Fuse Unit 1477/E 1 1477 1477

3 Moulded Distribution Box 420/E 1 420 420

4 P.V.C. Cable single core 6 Sq.mm 28/M 120 3360 3360

5 G.I. Wire No.8 60/Kg 1 Kg. 60 60

6 P.V.C. Pipe 20mm 25/M 2 M 50 50

7 P.V.C. Bends 20mm 5/E 2 Nos. 10 10

8 Misc. L.S 95 95

Total 3837 3575 7412

3% Contingencies on Materials 115 107 222

Labour & Transport 202 430 633

11% Estt. & Genl. Charges 422 393 815

1% Cess 91Total Cost in Rs. 4577 4506 9,173 Or say : 9,170

Note : Item Nos. 4 to 7 are to be borne & arranged by the Consumer.

38. R.E.C.-CONSTRUCTION STANDARD SPECIFICATION NO.H1 TO H3/1981COST DATA FOR DOMESTIC AND NON-DOMESTIC SERVICE CONNECTION (THREE PHASE)

Sl. No. Particulars RateChargable to

DISCOMChargable to

Consumer Amount in Rs.

50

Page 54: epdcl cost data 2014-15

Qty . Amount Qty. Amount

1 3 Phase Electronic Energy Meter Housed in box 10-40A 1940.00 1 1940 1940

2 3 phase 60A M.C.B./Fuse Unit 1477/E 1 1477 1477

3 P.V.C. Cable single core 6 Sq.mm 28/M 120 Mts. 3360 3360

4 G.I. Wire No.8 60/Kg 1 Kg. 60 60

5 P.V.C. Pipe 20mm 25/M 2 M 50 50

6 P.V.C. Bends 20mm 5/E 2 Nos. 10 10

7 Misc. L.S 95 95

Total 3417 3575 6992

3% Contingencies on Materials 103 107 210

Labour & Transport 405 557 961

11% Estt. & Genl. Charges 376 393 769

1% Cess 89Total Cost in Rs. 4300 4632 9,022 Or say : 9,020

Note :

COST DATA FOR DOMESTIC AND NON-DOMESTIC SERVICE CONNECTION (THREE PHASE)WITH ELECTRONIC METER

39. R.E.C.-CONSTRUCTION STANDARD SPECIFICATION NO.H1 TO H3/1981

Sl. No. Particulars RateChargable to

DISCOMChargable to

Consumer Amount in Rs.

Item Nos. 4 to 7 are to be borne & arranged by the Consumer.

51

Page 55: epdcl cost data 2014-15

Qty . Amount Qty. Amount

1 Poly Phase Energy Meter housed 10 - 40A 1940 1 1940 1940

2 3 phase 60A M.C.B./Fuse unit 1477/E 1 1477 1477

3 Moulded Box for CT Meter 1647/E 1647 1647

4 P.V.C. Cable single core 10 Sq.mm 43/M 80 3440 3440

5 G.I. Wire No.8 60/Kg 1 Kg. 60 60

6 P.V.C. Pipe 38mm 41.4/M 2 M 83 83

7 P.V.C. Bends 38mm 22/E 2 Nos. 44 44

8 Misc. items viz. link clips, wooden box, Bolts & Nuts. L.S 75 125 200

Total 5139 3752 8891

3% Contingencies 154 113 267

Labour & Transport 405 557 961

11% Estt. & Genl. Charges 565 413 978

1% Cess 111Total Cost in Rs. 6263 4834 11,208 Or say : 11,210

40. R.E.C.-CONSTRUCTION STANDARD SPECIFICATION NO.H-5/1981POLY PHASE SERVICE CONNECTION CHARGES FOR

ERECTION OF 1 NO. INDUSTRIAL SERVICE (UPTO 15 H.P.)

Sl. No. Particulars RateChargable to

DISCOMChargable to

Consumer Amount in Rs.

52

Page 56: epdcl cost data 2014-15

Qty . Amount Qty. Amount

1 3 Phase LTTVR 125/5A,0.5cLASS without DLMS 6525.00 1 6525 6525

2 3 phase 60A M.C.B./Fuse unit 1477/E 1 1477 1477

3 P.V.C. Cable single core 10 Sq.mm 43/M 120 5160 5160

4 G.I. Wire No.8 60/Kg 1 Kg. 60 60

5 P.V.C. Pipe 38mm 41.4/M 2 M 83 83

6 P.V.C. Bends 38mm 22/E 2 Nos. 44 44

7 Misc. items viz. link clips, wooden box, Bolts & Nuts. L.S 75 125 200

Total 8077 5472 13549

3% Contingencies 242 164 406

Labour & Transport 405 557 961

11% Estt. & Genl. Charges 888 602 1490

1% Cess 164

Total Cost in Rs. 9613 6795 16,571 Or say : 16,570

41. R.E.C.-CONSTRUCTION STANDARD SPECIFICATION NO.H-5/1981COST DATA FOR POLY PHASE SERVICE CONNECTION CHARGES FORERECTION OF 1 NO. INDUSTRIAL SERVICE (UPTO 15 H.P.) (C T METER)

Sl. No. Particulars RateChargable to

DISCOMChargable to

Consumer Amount in Rs.

53

Page 57: epdcl cost data 2014-15

Qty. Amount Qty. Amount

1L.T. 3-Phase class-0.5 Accuracy CT Operated(200/5A) Energy Meter Housed in a box

6899.00 1 6899 6899

2 P.V.C. Cable single core 10 Sq.mm 43/M 80 3440 3440

3 G.I. Wire No.8 60/Kg 1 Kg. 60 60

4 P.V.C. Pipe 38mm 41.4/M 2 M 83 83

5 P.V.C. Bends 38mm 22/E 2 Nos. 44 44

6 Misc. items viz. link clips, wooden box, Bolts & Nuts. L.S 75 100 175

Total 6974 3727 10701

3% Contingencies 209 112 321

Labour & Transport 405 557 961

11% Estt. & Genl. Charges 767 410 1177

1% Cess 132

Total Cost in Rs. 8355 4805 13,292 Or say : 13,290

42. R.E.C.-CONSTRUCTION STANDARD SPECIFICATION NO.H-5/1981COST DATA FOR POLY PHASE SERVICE CONNECTION FOR

ERECTION OF 1 NO. INDUSTRIAL SERVICE (ABOVE 15 H.P.) (C.T. METER)

Sl. No. Particulars RateChargable to

DISCOMChargable to

Consumer Amount in Rs.

54

Page 58: epdcl cost data 2014-15

Sl. No. Particulars Qty. Ratein Rs. Per Unit Amount

in Rs.

1 LT 1 phase Electronic Meter 5-30A 1 No. 796 Each 796

2 1 phase 15A M.C.B./Fuse Unit 1 No. 201 Each 201

3 Light sensitive switch 1 No. 400 Each 400

4 P.V.C. Cable 4 Sq.mm Single Core 15 M 24 360

5 P.V.C. Pipe 25mm 2 Mts 40 79

6 P.V.C. Bends 25mm 2 No. 6.0 Each 12

7 Moulded Distribution Box 1 No. 250 Each 250

8 Wooden, plugs, clamps, bolts, L.S. L.S. L.S. 50nuts link clips etc

Total 2,148

3% Contingenics 64

Labour & Transport 759

11% Estt. & Genl. Charges 236

1% Cess 32

Total Cost in Rs. 3,240 Or say : 3,240

43. COST DATA FOR STREET LIGHT SERVICE CONNECTION (SINGLE PHASE)

55

Page 59: epdcl cost data 2014-15

Sl. No Particulars Qty. Rate

(Rs. in lakhs) Unit Amount (Rs. in lakhs)

1(a) Lands and Rights LS As per local conditions 0.000

(b) Plantation of Trees LS LS 0.061

2 Control Room and Consumer service centre(including furniture) LS LS 5.000

3 Station Auxillaries

a) Peripheral, Security Fencing, Approach road, retaing wall around switchward with gravel filling, gate and bore well LS LS 10.000

b) Yard lighting 0.600c) Fire fighting Equipment LS LS 0.660d) P&T Phone and wireless set LS LS 1.500

4 Foundations for structures, PTRs & breakers LS LS 3.0005 Bus bars, Jumpers, Connectors claps etc. LS LS 1.2006 Control Cables LS LS 1.0807 Structural Steel 15 0.562 MT 8.4238 Transformers

a) 33/11KV, 5 MVA Power Transformer 1 29.598 Each 29.598b) 11KV/ 415V 16KVA Stn. Transformer 1 0.657 Each 0.657

9 Circiut Breakres (including trivector meters)a) 20 KA 11 kv feeder VCB including Control panel and CTs (NF=3) 3 2.249 Each 6.747b) 20 KA 11 kv LV VCB including Control panel and CTs 1 3.211 Each 3.211

10 Control Circiut Panelsa) AC Supply Panel 1 0.330 Each 0.330b) DC Aunnciation Panel 1 0.330 Each 0.330

11 Instrument Transformersa) 11kv P.T (3 Phase) 1 0.183 Each 0.183

12 Lightning Arrestorsa) 33KV 10KA station type 6 0.043 Each 0.260b) 33KV 10KA Line type 3 0.017 Each 0.050c) 11KV Line Type (NFX3) 9 0.017 Each 0.155d) 11KV Station Type 10 KA 3 0.017 Each 0.052

13 Isolating Switchesa) 33KV 800A double break centrally operated Horizantal AB Switch 3 0.431 Each 1.292b) 11KV 800A double break centrally operated Horizantal AB Switch (NT X 1+1) 2 0.199 Each 0.399c) 11KV 400A Horizantal AB Switch (NF X 2+2) 8 0.150 Each 1.198d) 11KV 200A Horizantal AB Switch for station transformer 1 0.079 Each 0.079e) 33KV Horn Gap Fuse Set (1XNT) 1 0.095 Each 0.095

14 2MVAR 11KV Capacitor Bank along with Associated Equipment 1 10.000 Each 10.00015 24V, 40 AH Battery Set including Battery Charger 4 0.182 Each 0.72916 Earthing of PTR, VCBs, AB Swicthes, Strucutres with 75x8mm GI Flat LS 1.815

88.7046.3791.9140.6389.7571.074

108.466108.470

Note : NF = No. of 11 KV Feeders, The number of outgoing feeders at substation limited to the demand in MVA i.e. if substation demand is 5 MVA, the number of feeders should not exceed five.

Total Rs. in LakhsOr say (Rs. lakhs)

Sub TotalErection and transport and commissioning charges on items 7 to 15 at 10%Contingencies on items 7 to 15 at 3%T&P Charges on items No. 7 to 15 at 1%Establishment and General Charges at 11% 1% Cess

44. DETAILED ESTIMATE FOR ERECTION OF 1No. 33/11 KV SUBSTATION WITH (NT) X 5 MVA POWER TRANSFORMERS AND NF = 3 NO. 11 KV FEEDERS

56