Upload
vibhav
View
220
Download
0
Embed Size (px)
Citation preview
7/27/2019 Engineering Declaration Unit # 2 Jindal
1/16
GM (MTP)
UNIT # 2
2012-13
ENGINEERING
DECLARATION
7/27/2019 Engineering Declaration Unit # 2 Jindal
2/16
ENGINEERING DECLARATION
August 2012
FOR FINANCIAL YEAR 2012-13
1. Unit No: - 2 (250 MW BHEL Make)
2. Boiler License No: - CG-246
3. Boiler License validity (date) : 06.09.2012
4. Overhaul History (In reverse chronological order) for the past five years :
5. Unit Milestones / Major Event since inception:
S. No. Milestones / Events Data Remarks1 First synchronization (date) 07.03.2008
2 First commercial (date) 15.06.2008
3 BTL (Nos.) between two overhauls 3 OH 10 to OH 12
4 Trip (Nos.) between two overhauls 7 OH 10 to OH 12
S.No.
DescriptionOverhaul duration
Overhaulcategory
Operating Hrs.Since
prev. OH
Cumul.operating
Hours
Forced Outagesbetween two
overhauls ( nos )
Important& major
highlights
From To Total BTL Trip Total
1
Proposed
overhaul-
2012-13
01/09/
2012
17/09/
2012
17
days
Boiler &
auxilaries,
Turbine &
generator
Bearing & its
Auxilaries
16831.02 35118.794 3 7 10
2OH for FY
11-12
- - - - - - -
3OH For FY
10-11
01/09/
2010 at
3:22 Hrs
16/09/
2010
at
12:36
Hrs
15
days
9
Hrs
14
min
Boiler &
Turbine
auxilaries,
0 18287.774 - - -
7/27/2019 Engineering Declaration Unit # 2 Jindal
3/16
6. Unit performance History of Past Three years.
S. No. Parameters Previous 3 years
2011-12 2010-11 2009-10
1 Generation (MU) 2223.308 2141.018 2053.054
2 Availability (%) 99.27 94.90 93.77
3 Plant load factor (%) 101.24 97.76 93.75
4 Loading factor (%) 101.98 103.02 99.98
5 Total Generation Loss ( MU) 24.644 115.872 166.386
6 DM Make up (%) 0.44 0.48 0.70
7 Heat rate 2286 2293 2315
8 No. of BTL 0 2 6
9 No. of trips. 5 3 9
10 Total forced outage (%) 0.19 0.89 4.23
7. Boiler tube leakages detail since last overhauling.
7/27/2019 Engineering Declaration Unit # 2 Jindal
4/16
SL.
NO
DATE &
DURATIONFAILURE LOCATION TUBE DETAILS TYPE OF DAM
1
16/11/10(11:43 HRS.)
TO 18/11/10
(12:43hrs)
(i) LHS STEAM COOLED WALL
TUBE NO-3 FROM REAR TO
FRONT.(ii) LHS STEAM COOLED
WALL TUBE NO-1&2 FROM
REAR TO FRONT AND LTSH
INLET HEADER SHH-9 LHS
END DUMMY
STEAM COOLED WALL STRAIGHT TUBE 3NOS EACH1 MTR
LENGTH. (MATERIAL SA 210 GRADE-A1 DIA 44.5X4.5MM
THICK).
ORIGINAL FAILUR
FINS WELDING AN
SECONDARY DAM
CAUSE DUE TO HI
PRESSURE STEAM
2
03/05/12
(12.23 HRS)
TO 04.05.12
(12.00 HRS)
STEAM COOLED WALL LEFT,
ELEVATION IN METRE 41
MTR, PRIMARY FAILURE- LHS
STEAM COOLED WALL TUBE
NO-3RD FROM REAR,NEAR
LTSH INLET HEADER.
SECONDARY FAILURE- LHS
STEAM COOLED WALL TUBENO-2ND FROM REAR,NEAR
LTSH INLET HEADER
ORIGINAL TUBE DIMENSION: TUBE OD-44.5 IN MM
THIICKNESS -4.5 IN MM, TUBE MATERIAL :SA 210 Gr-C
SECONDARY FAILED TUBE DIMENSION: TUBE OD 44.5 IN
MM, THIICKNESS - 4.5 IN MM, TUBE MATERIAL :SA 210 Gr-C
SUSPECTED ROOT
OF PRIMARY FAILU
FLUE GAS EROSIO
SECONDARY TUBE
FAILURES DETAIL:
SECONDARY FAILU
TO HIGH PRESSUR
CUT.
3
23.08.12
(15.32HRS TO
25.08.12
(07.23 HRS)
FURNACE WW LEFT,
PRIMARY FAILURE - FROM
CENTER OF WB-26,TUBE NO-
6 TOWARDS FRONT,
SECONDARY FAILURE - FROM
CENTER OF WB-26,TUBE NO-
7 TOWARDS FRONT,
ORIGINAL TUBE DIMENSION:TUBE OD-63.5 IN MM
THIICKNESS - 5.6 IN MM, TUBE MATERIAL :SA 210
GRC SECONDARY FAILED TUBE DIMENSION: TUBE OD 63.5
IN MM, THIICKNESS - 5.6 IN MM, TUBE MATERIAL :SA 210
GRC
PRIMARY FAILURE
ATTACHMENT WE
SECONDARY FAILU
TO HIGHPRESSUR
CUT
7/27/2019 Engineering Declaration Unit # 2 Jindal
5/16
8. Unit / Equipment Performance & Efficiency Evaluation Before Overhauling
Plant performance of Unit # 2 is as follows
S.No. Parameters Pre OH
1 Boiler Efficiency (%) 86.501
2 Corrected Boiler Efficiency 86.34
3 Gross Turbine Cycle Heat rate 2022
4 Corrected Gross Turbine Cycle Heat rate 2009
5 Gross Unit Heat Rate 2338
6 Corrected Gross Unit Heat Rate 2327
7 Heat rate Deviation 79
8 Accountable loss 54
9 Unaccounted loss 26
9. Efficiency Tests
1) Turbine Efficiency Test
a) Turbine Report Sheet
Sl.
No.Parameters Design Pre OH
1 Unit Load (in MW) 250 254
2 MS pressure (in kg/cm2) 150 145.6
3 MS Temp(in oC) 537 535.2
4 1 st Stage Pressure (in kg/cm2) 136.63 140.7
5 CRH Pressure (HPTurbine exhaust) (in kg/cm2) 39.57 40.66 CRH Temperature (HPTurbine exhaust) (in oC) 343 349.8
7 HRH Pressure (in kg/cm2) 35.62 38.2
8 HRH Temperature (in oC) 537 535.0
9 IP Exhaust Pr (in kg/cm2) 6.96 7.7
10 IP Exhaust Temp (in oC) 306.5 310.2
11 Extraction Pressure to D/A (in kg/cm2) 7.7
12 Extraction Temp to D/A 310.2
13 COND. TO DEARATOR Pressure(in Kg/cm2) 9.9
14 COND. TO DEARATOR Temp 120.3
15 COND. TO DEARATOR flow 612 621.4
16 BFP Suction temp(deg C) 163.5
22 MS Flow (in TPH) 758.5
23 FW Flow (in TPH) 757.48 758.5
24 Reheater Spray (in TPH) 0 25.3
25 HPH6 FW O/L Temp(in oC) 245.9 247.2
26 CRH Flow Calculated 665.8 701.7
27 Condenser Vacuum -0.906 -0.902
7/27/2019 Engineering Declaration Unit # 2 Jindal
6/16
b) Turbine Performance Indices
1 Gross Turbine Cycle Heat rate (in Kcal/kwh) Design 1951
2 Gross Turbine Cycle Heat rate (in Kcal/kwh) 2022
3 Corrected Turbine Cycle Heat rate (in Kcal/kwh) 2009
4 Deviation (Corrected Design) (in Kcal/kwh) 58
c) Cylinder efficiency
1 Parameters Design Pre
2 HP Cylinder Efficiency 86.66 86.54
3 IP Cylinder Efficiency 91.90 90.52
2) Condenser Performance
Sl.
No.Description Unit
Date
Design Pre OH
1 Load MW 250 254.0
2 Condenser pressure Kg/cm2 -0.906 -0.897
3 Condenser back pressure mbar 101.13 98.31
4 Optimum back pressure mbar 91.6 93.05
5 Corresponding Saturation Steam Temperature Deg C 44 45.25
6 CW inlet Temperature Deg C 33 31.30
7 CW outlet Temperature Deg C 41.5 40.728 Optimum CW rise Deg C 8.5 8.50
9 Actual CW Rise Deg C 9.42
10 Optimum TTD Deg C 2.5 4.50
11 Actual TTD Deg C 4.53
12 Back pressure due to CW inlet (6+8+10) mbar 92.54
13 Back pressure due to CW flow & CW inlet (7+10) mbar 97.04
14 Variation due to CW inlet temp mbar -0.51
15 Variation due to CW Flow mbar 5.50
16 Variation due to air/ dirty tubes mbar 3.27
17 Total Variation mbar 10.77
18 Number of Vacuum Pumps in service nos 1
19
CONDENDER DUTY
HEAT ADDED MS=FlowMS*(hMS-hFW) Kcal/kg 425758305
HEAT ADDED CRH=FlowCRH*(hHRH-hCRH) Kcal/kg 73088791
HEAT ADDED RH=FlowCRH*(hHRH-hATT) Kcal/kg 15026650
TOTAL HEAT ADDED 513873746
HEAT LOSS THROUGH RADIATION kW 254
Pgen kW 254000
Pgen Losses kW 2540
7/27/2019 Engineering Declaration Unit # 2 Jindal
7/16
Total Heat lost 256794
CONDENDER DUTY Kcal/hr 293030906
20
CW FLOW= Cond Duty /((Cwout- Cwin)xdensityx
Cp) m3/hr 31104
Outer dia OD mm 29
Tube thickness (t) mm 1
Cross -Sectional area mm2 590Total No of Tubes nos 15664
21 WATER VELOCITY IN CONDENSER TUBE m/sec 1.870
3) Boiler Efficiency
ParametersDate 08.08.2012
Design Pre OH
Unit Load 250 254
Steam Flow 740 758.5
COAL FLOW 157 178APH GAS INLET TEMP 340 246.0
APH GAS OUTLET TEMP 132 138.7
AVG I/L PRIMARY AIR TEMP 34 34.01
PRIMARY AIR FLOW 239 291.79
AVG O/L PRIMARY AIR TEMP 310 296.8
AVG SECONDARY AIR I/L TEMP 34 32.1
AVG SECONDARY AIR O/L TEMP 320 302.1
SECONDARY AIR FLOW 571 520.8
AH INLET O2 % 3.5 2.7
AH OUTLET O2 % 5 5.4
AH OUTLET CO2 % 15.4 15.8AH OUTLET CO % 75 12
UNBURNT IN FLY ASH 0.6 0.3
UNBURNT IN BOTTOM ASH 1.5 1.33
AMBIENT AIR TEMP DRY 34 27
AMBINT AIR TEMP WET 28 25
AMBINT AIR TEMP RH 60.0 85
Proximate Analysis Result
Total Moisture 12 13.0
Ash 39 39.2
V.M 22 23.0
FC 27 24.9
GROSS CALORIFIC VALUE 3600 3507
Heat Losses (%) Design Pre OH
UNBURNT CARBON LOSS 1.2 0.412
HEAT LOSS DUE TO HEAT IN DRY FLUE GAS 4.211 5.235
HEAT LOSS DUE TO MOISTURE IN AS FIRED FUEL 2.067 2.314
HEAT LOSS DUE TO MOISTURE FROM BURNING OF
HYDROGEN4.309 4.048
7/27/2019 Engineering Declaration Unit # 2 Jindal
8/16
HEAT LOSS DUE TO MOISTURE IN AIR 0.16 0.175
HEAT LOSS DUE TO SURFACE RADIATION & CONVECTION 0.22 0.22
HEAT LOSS DUE TO RADAITION & UNACCOUNTED 0.54 0.74
HEAT CREDIT( HEAT EQI. OF POWER) -0.165
HEAT LOSS DUE TO MILL REJECT 0.020
MANUFACTURE MARGIN 0.5 0.5
TOTAL HEAT LOSS 13.207 13.501BOILER EFFICIENCY 86.79 86.50
CORRECTED BOILER EFFICIENCY 86.34
4) APH Performance
Parameters DesignPre OH
Pass A Pass B
O2 I/L (Oxygen at APH Inlet) 3.76 3.5 3.5
O2 O/L (Oxygen at APH outlet) 5 5.7 5.2
PA inlet Temp (Tpai) 34 37.5
PA outlet Temp (Tpao) 314 296.8
PA flow 238.6 301.4
SA inlet Temp (Tsai) 34 32.0
SA outlet Temp (Tsao) 319 302.1
SA flow 570.7 520.8
Weighted Avg intet Air temperature (Tai) 34 34.0
Weightyed Avg outlet Air temperature (Tao) 317.5 299.5
Flue gas inlet temperature (Tgi) 348 348.5 341.5
Flue gas outlet temperature (Tgo) 132 136.4 137.4
Flue gas outlet temperature with no leakage (Tgnl) = AL xCpa x (Tgo - Tai)/(100x Cpg) + Tgo; where Cpa(specific
heat of air) = 1 and Cpg (specific heat of gas) = 0.993
138.9 151.1 152.6
A/H LEAKAGE ( in %) 6.98 14.28 10.95
A/H Gas side Efficiency (GSE) 66.60 62.77 61.46
A/ H - X Ratio 0.74 0.74 0.71
5) ESP Performance
ParametersDate 28.08.2012
Pre OH
Design Pass - A Pass - B
Load 250 256.5
ESP I/L Draft(mmwcl) -203 -167.89 -167.43
ESP O/L Draft (mmwcl) -249 -296.18 -296.50
Pressure Drop 46 -128.29 -129.07
ESP I/L Temp(oC) 132 128.17 128.49
7/27/2019 Engineering Declaration Unit # 2 Jindal
9/16
ESP O/L Temp (oC) 122 113.72 112.01
Temperature Drop 10 14 16
Opacity 50 47.2
Fields not in Service NIL
ID Fan - A Current 190.53
ID Fan - B Current 191.88
6) Cooling Tower Performance
Sl.No. PARAMETERSDate
Design Pre OH
1 No of cells 14 13
2 CW O/L Temp 42 42
3 CW I/L Temp 33 32.3
4 DRY BULB TEMPERATURE 29.2
5 AMBIENT WET BULB TEMP 28.5 27.13
6 APPROACH(A) = Cwi - WBT (in oC) 4.5 5.2
7 RANGE(R) = CWo - Cwi (in oC) 9 9.6
8 EFFECTIVENESS(E) = (RX100)/ (R+A) 66.7 65
9
TOTAL WATER FLOW RATE CALCULATED
(CR)=(CW+ACW)40000 33578.08
10
EVAPORATION LOSS = CR x (Cwo- Cwin) /675 in
M3/hr
520at 90% RH
design479
11 COOLING CAPACITY in Kcal/Hr 360000 323577
12
CYCLES OF CONCENTRATION = TDS in CW/TDS in
makeup8 6.67
13
MAKE UP WATER CONSUMPTION = Evap Loss
/(COC - 1) in M3/Hr74.29 84.55
14 CW Flow to each Cell 3077 2583
7/27/2019 Engineering Declaration Unit # 2 Jindal
10/16
10. Scope of work
BOILER
PRESSURE PARTS
Complete Boiler water washing, wall scrapping & buffing.Erection & Dismantling of Quick Erect Scaffolding in first pass up to roof tubes at every 2mt
elevation including PSH
Thickness survey of tubes
Erection of scaffolding and platform in LTSH Terminal Tubes, Re-heater (both banks), Screen
Tubes, Hanger Tubes at every 2.0 mtr. elevation and complete platform below Economizer.
Pent house & dead chamber cleaning
DP test of weld joints & header stub and attachment welding.
Shifting, Dismantling, Erection & Alignment of Eco coils (Upper& Lower )
Lifting/Lowering of coils (lower & upper) for inspection
Welding of HP tubes up to 76.1mm dia.
Strengthening of boiler tubes by weld overlay.Refurbishment of header by weld overlay
Fabrication of HP bends up to 76.1mm dia.
Alignment of coils (PSH, RH, FSH, LTSH, Eco)
Fixing of protection shields /shrouds
Fin/skin casing welding by tested welder
Application of Plastic Refractory
Application of insulation & cladding sheet
Drum cleaning and inspection
Wall blower distance setting & sleeve fitting
Servicing of buckstays, manhole, peephole ( servicing of all buck stay pins, boiler expansion
indicators, manholes, peepholes, tie rod of dog house & pent house header hanger supports.)Repair & Re-installation of bottom seal plate and Woven Wire Mesh
Replacement/repair of fuel burners replacement of 24 Nos. coal nozzle , repairing of all oil &
air bucket, servicing of tilting mechanism ,repairing of wind box & servicing of SADC.
Cleaning of 12 Nos. coal pipes with water jet. Servicing of oil, air & steam atomizing lines valve
firing floor.
Reversal of coal pipe orifice.
Rotation of coal pipe (2 - 6 mtr. length)
Replacement of coal pipe
Repairing of coal pipe by patch welding of 500mmx500mm piece
Inspection and Servicing of coal pipe coupling
Alignment of coal pipe
Inspection/repair/replacement of coal pipe bends
Servicing of coal burner isolation gate.
Cold Air velocity Test
BOTTTOM SEAL TROUGH
Inspection of seal plates & thorough cleaning of seal trough
Inspection & checking of quenching nozzles & its direction
Repair/ Replacement of SS Mesh & Bottom Seal plate AT BAH
7/27/2019 Engineering Declaration Unit # 2 Jindal
11/16
VALVES
Overhauling Of HP Valves - Drain & Vents, Root Valves
Overhauling & Pressure setting of safety Valve SV1 to SV5
FUEL FIRING SYSTEM (COAL & OIL BURNERS, SADC )
Replacement of 24 nos coal nozzle ,servicing & alignment of burner tilts
Repairing of Wind Box & Servicing Of SADC & its synchronized movement
Condition checking of oil & air compartments
Healthiness checking of air guide vanes inside wind box
Inspection of all attachments in the burner zone near transition tubes to check whether wind
box is properly loaded on the water wall tubes & no attachment is missed out during
replacement of burner transition tubes
Thickness measurements of coal pipes
Condition based replacement of coal pipes
Inspection of elbow/bend , orifice & victaulic gasket randomly.
Servicing of knife edge gate valves for coal nozzle
APH A & B
All Baskets to be taken out &cleaned with High pressure water jet. Templates to be made for
covering the cleaned baskets so that foreign material does not fall into the basket.
Renewal of Outboard baskets (48 nos.) / APH
Seals And Baskets Inspection & Arrangement for Basket Cleaning, Seal setting (replacement of
damage seals)
Guide & Support Bearing, rotor post aluminum seal opening & inspection,
Hot end & cold end rotor post seal repair/replacement & kao wool packing
Lub oil system servicing of support & guide bearing
Guide & support bearing oil flushing & oil changing
Attending hot air leakages in guide bearingAir heater soot blower servicing & angle setting
Inspection of Gear box, fluid coupling & oil changing & realignment.
Servicing of Air motor
Support & Guide Bearing alignment after seal setting
Repairing of APH duct from GD1 & 2 to APH Hopper
Checking of healthiness of fire fighting system- replacement of eroded headers,
cleaning/replacement of nozzles
DUCT & DAMPERS OVERHAULING
Cleaning, Inspection and thickness measurements of ducts
Repair , replacement of eroded bracings, duct plates & guide vane plates/Expansion Bellowsof PA & FD , ESP I/L & O/L ducts with SAIL HARD/ SELMA STEEL
Servicing & repair of all dampers and gates along with seals
Replacement of eroded guide vanes
Checking of the operating mechanism of all the dampers & gates
Checking of the healthiness of the blower
Practices to be followed during Overhauling of Boiler
Steam/air blowing of new tubes before installation
Sponge ball test of new coils/bends to be done before installation
7/27/2019 Engineering Declaration Unit # 2 Jindal
12/16
All vertical tubes to be cut with grinders only
Immediate capping of tubes to be done after cutting
Deployment of tested cutter for tube cutting
Deployment of tested HP Welders for welding of joints.
All attachment welds to be done by tested welders
Attachment welds to be done by 2.5mm size electrodes only
All supports / clamps to be restored to original
FANS
Inspection, repair & maintenance of PA Fans, FD Fans, ID Fans, Seal Air fans.
COAL MILL & FEEDER.
Replacement of Grinder Roller of Mill 4A & 4C
Replacement of Bullring Segment of Mill 4A, 4B, 4C & 4D
Replacement of Clamping Ring of Mill 4A, 4B, 4C & 4D
Hard facing Inside Mill & JOC
Servicing/Replacement of of Journal Pressure Spring
Replacement/Servicing of Classifier Vane Assembly.
ESP
Thorough internal inspection of ESP electrodes to locate defects and repairing.
Cleaning and inspection of shaft insulators, support insulators and replacement of any
damaged insulators. Screen tube and Field suspension rod.
GD Test to be done
TURBINE
Overhauling of LP Turbine Module
Replacement of Hydrogen Seal Rings of Generator.
Overhauling of Generator & Exciter
Inspection of Bearing Nos. 1 to 7 and H2 Seal Ring.
Overhauling of MOP, MS Strainer (LHS), HRH Strainer (RHS), PHE A & B, CEP - 2A, 2B & 2C-
Provided we receive the Dummy sleeve reqd. for modification of CEP.
Servicing of Turning Gear, HPSV, HPCV, IPSV, IPCV & its Servomotor, HPBP Valves, HPBP Spray
valves, Butterfly Valves, Air Release valves.
Checking of Governing Characteristics
Cleaning of BFP & Booster pump suction strainers, De-aerator, FST, OCST & DMCW Tank, Hot
well, ACW Strainer Elements, Cooling Tower basin
Transferring of Oil in MOT to COT, Cleaning of MOT and again transferring of oil from COT to
MOT.Condenser Tube cleaning by Bullet Shot Method and applying of Chemical Resistant Coating
in Condenser tube sheets & water box
Carrying out Condenser Flood test, Air/H2 leak test of Generator, Hydro test of H2 & Exciter
Coolers
CW Duct Butterfly valve inspection and servicing
Attending identified leakages and defects booked by Operation dept.
CT Basin Cleaning, Cooling Tower nozzles & drift eliminators cleaning, repairs & replacement
7/27/2019 Engineering Declaration Unit # 2 Jindal
13/16
Electrical
Overhauling of Generator Generator overhang portion NFT Test & Inspection.
Exciter & PMG Dismantling, inspection & testing.
NGR, NGT & SPVT inspection, tightness checking & testing.
Preventive maintenance of Gen Aux Panel- ECB, CFA & CTE02 Panel.
Transformer Overhauling GT General Checking & OLTC inspection, UAT A&B oil filtration,OLTC inspection, ST2- OLTC inspection & general checking. Testing of GT , ST & UAt-2A &2B.
Unit & station auxiliary transformers cleaning, inspection, tightness checking & testing.
6.6 KV HT SWITCHGEAR(5 Nos of MAIN PLANT & BOP) - inspection & cleaning of bus bars &
feeders, connection tightness of power and control cables, sealing of spare holes ,inspection
of CT's and PT's.
415 V LT SWITCHGEAR (17 Nos. of MAIN PLANT & BOP)- inspection & cleaning of bus bars &
feeders, connection tightness of power and control cables, sealing of spare holes ,inspection
of CT's and PT's.
H.T.MOTORS OVERHAULING (15 nos )- ID Fan A&B, FD Fan A&B, PA Fan A&B, Coal Mill
A,B,C,D &E, 1 BFP, CEP- A, B&C. Cleaning, varnishing, painting, bearing inspection &
replacement and testing.
LT MOTORS OVERHAULING (81 Nos.) - Cleaning, varnishing, painting, bearing inspection &
replacement and testing.
Wall & soot blowers cleaning, inspection, motor bearing replacement if required.
MOV Actuators overhauling Cleaning, inspection, grease & oil replacement.
AVR cleaning, inspection, tightness, field breaker alignment testing, & Dynamic Testing
GRP-Cleaning, inspection, tightness, relays testing, annunciation checking.
ESP - BAPCON, RAPCON Panel, Rectifier Transformer Overhauling &testing, PMCC,MCC & Dry
transformer overhauling.BATTERY AND D.G. SET-Capacity test of 220 V UNIT-2 Main Battery & UPS battery, Battery
charger cleaning, tightness & inspection
220 KV Switchyard bay: Breaker, CT, Isolators general checking/ testing/ maintenance.
C&I
TG AREA
Cleaning of field equipments, JB's and ensuring the tightness of all connections.Checking and calibration of all critical instruments related to plant ,equipment tripping,
interlock and efficiency analysis.
Checking and calibration of control valves and hydraulic actuators.
Checking of TSI pick up response and calibration.
Servicing of UPS & ACDB
To install and commission electronic level switch in CRH.
Checking of protection interlock of turbine and its auxiliaries
DCS storian upgradation and HMI software setting and checking.
7/27/2019 Engineering Declaration Unit # 2 Jindal
14/16
Cleaning and checking of the DCS cards.
Flow nozzle of LPBP spray to be shifted before MOV.
To Replace HP exhaust thermocouples.
To replace MOT level transmitter with radar type LT to improve reliability and accuracy.
To install isolation valve in the downstream of CEP vent solenoid valve.
To shift orifice plate of DM makeup flow from downstream to upstream of CV.
Skin type RTD to be installed in BFP recirculation line to detect RC valve leakage.
RTD to be installed in place of temperature switch in Vacuum pump for improving condenser
performance.
ATRS/ATT establishment to be checked and to be made operative.
BOILER AREA
To check the overall instrumentation of HFO Station (FM,HOTV &HOFCV), LDO & Air Station
(FM,LOTV&LOFCV) & Station for Atomising Steam at Operating Floor
To check the operation of Oil Burner - AB Elevation (AANV,ASNV,HONV & LONV) and for CD &
EF Elevation (AANV,ASNV & HONV)
Servicing/checking of HEA Spark Rod/Igniter advancement / Flame Scanner functioning at all
elevations
To check/replace the T/C's of HOT end & cold end of APH-A&B, RTD of guide bearing of APH.
To check/inspect & Calibrate both Oxygen probes, PA Header Pressure Transmitters (03 Nos.)
& Switches (05 nos.), Furnace Pressure switches (06 NOS)
Cleaning & Calibration of SADC Power cylinders (56 Nos.)
Cleaning & Calibration of all Power cylinders for ID, FD, PA, HAD,CAD, HAG & Burner Tilt (Total
30 Nos.)
Checking and calibration of all critical instruments related to plant equipment tripping,
interlock and efficiency analysis.
All auto control loops performance checking and fine tuning.
AHP AREA
ESP level probe checking.
ESP vacuum transmitter calibrationSlurry pumps interlock & protection checking
Overhauling of all Power cylinders (Total 90 Nos)
Buffer hopper purging solenoid valves orientation to be changed from horizontal to vertical.
ASH HANDLING SYSTEM
Bottom Ash Hopper Refractory work.
Seal trough cleaning and repairing.
Inspection, Servicing and Assembly of fluidizing pads (128 Nos.)Replacement of all gaskets between hopper to M.S. adaptor & M.S. adaptor to knife gate
valve
Inspection, Servicing and Assembly of all MHV (72 Nos.) of ESP, Duct and APH hoppers and
their segregating valves (29 Nos.)
Inspection, Cleaning and Replacement of worn out parts of all collector towers.
Inspection , Replacement of worn out parts of rotating segregating valves of all Air lock
vessels.
Removal, Inspection, Replacement & Assembly of fluidizing pads of buffer hopper & air lock
vessels
7/27/2019 Engineering Declaration Unit # 2 Jindal
15/16
Inspection, Replacement of damaged bag, cage of bag house
Inspection & replacement of worn our parts of feed gate assemblies, hydro ejector.
Dismantling of flushing apparatus, inspection & replacement of gaskets, nozzles, pipe, fittings,
valves and reassembly of flushing apparatus in Economizer Hopper
11. Improvement & Modification Work
TMD
Modification of CEP. Installation of dummy stage in place of 2nd Stage, for existing3 No. CEPs.
Corrocoat Coating of CW & ACW Pumps Hydraulic passage of Unit#02.BMD
Application of Plastic Refractory. Burner nozzles to be modified and replaced during Overhauling.
C&I
Relocation of temperature element of after reheater desuperheter to avoidmeasurement error.
Flow nozzle of water injection flow of LPBP to be shifted before motorized valve asexisting installation does not cover flow through motorize valve .and to avoid unit
tripping in case of failure of pneumatic valve.
To replace head type RTD/Thermocouples with head less ones in critical areas likeexciter hot air temperature & seal oil temperature etc.
To replace MOT level transmitter with radar type LT to improve reliability andaccuracy.
Installation of RTD in place of Temp switches in Vacuum pump for monitoring andcontrol of temperature and improving condenser performance.
Provision for remote monitoring of HPBP system oil pressure and control of HPSUpump.
BFP trip contact of dearator level low to be derived from transmitters in addition toswitches to improve reliability.
To install isolation valve in the downstream of CEP vent Solenoid valve. To shift orifice plate of DM make up flow from downstream to upstream of CV to
avoid measurement errors.
UCP,ATRS & ATT establishment. Skin type RTD to be installed in BFP recirculation line to monitor RC valve passing. Buffer Hopper purging SOV'S Orientation to be changed from horizontal to vertical to
improve reliability.
To install & commission electronic level switch in CRH. Main Steam temperature low trip contact to turbine to be derived from soft to Hard
as an endeavor to improve reliability.
Relocation of Local Vibration Indicator Junction Boxes for ID, FD&PA Fans.
7/27/2019 Engineering Declaration Unit # 2 Jindal
16/16
ELD
Auto Bus transfer scheme at CTPMCC in UNIT-2 6.6 KV HT Board H.T. Motor tripping from Bus PT at main plant in UNIT-2 Redundant Power supply arrangement of AVR For unit -2 Provision of all H.V. motors over load alarm of unit -2 at CCR LVS Generator SPVT all voltage transformers of Prayog make shall be changed with Pragati
make voltage transformer total nine numbers
6 Amp MCB to be provided in place of low rated MPCB in motor feeder module
12. Pending defect & Opportunity Based jobs-
Pending defects are available on line, being attended and updated daily. Pending defect list to be taken before one month of unit shut down.
13. Justification/Evaluation of Overhauling
1. For Boiler license renewal, validity is up to 06/09/2012. The Boiler license is to berenewed up to for further two years duration.
2. During Annual Overhaul essential activities shall be carried out for safe and reliableoperation of the unit for next two years.
3. Overhauling of LP Turbine Module & Generator to be done.4. Due to Furnace Fouling Flue gas Temperature, SH spray & RH spray are of higher side,
which shall be reduced by High pressure Jet cleaning, scrubbing of Boiler etc. This will
reduce the Heat rate losses and improve the plant efficiency.
5. Due to air ingress in the boiler and ducts, ID fan currents is on higher side, which can bereduced by thorough inspection of ingress points in BA hopper, Seal trough area,
Replacement of rope gaskets in ESP manhole doors.
6. Air Heater Air ingress is on higher side, Air side gas side efficiency is also poor whichrequires APH seal setting, cleaning of basket and APH hot water washing.
7. Cleaning of ESP during shutdown will not only improve the performance but willbenefit help to meet the requirements of pollution norms.
8. Condenser cleaning by high pressure bullet jet and condenser flood test during OH willalso help to reduce any type of losses in performance of unit. Cooling Tower cleaning
during AOH will also benefit us for condenser performance improvement.
9. Passing of High pressure Energy drains has been already identified, which shall beattended during OH.