Engineering Declaration Unit # 2 Jindal

  • Upload
    vibhav

  • View
    220

  • Download
    0

Embed Size (px)

Citation preview

  • 7/27/2019 Engineering Declaration Unit # 2 Jindal

    1/16

    GM (MTP)

    UNIT # 2

    2012-13

    ENGINEERING

    DECLARATION

  • 7/27/2019 Engineering Declaration Unit # 2 Jindal

    2/16

    ENGINEERING DECLARATION

    August 2012

    FOR FINANCIAL YEAR 2012-13

    1. Unit No: - 2 (250 MW BHEL Make)

    2. Boiler License No: - CG-246

    3. Boiler License validity (date) : 06.09.2012

    4. Overhaul History (In reverse chronological order) for the past five years :

    5. Unit Milestones / Major Event since inception:

    S. No. Milestones / Events Data Remarks1 First synchronization (date) 07.03.2008

    2 First commercial (date) 15.06.2008

    3 BTL (Nos.) between two overhauls 3 OH 10 to OH 12

    4 Trip (Nos.) between two overhauls 7 OH 10 to OH 12

    S.No.

    DescriptionOverhaul duration

    Overhaulcategory

    Operating Hrs.Since

    prev. OH

    Cumul.operating

    Hours

    Forced Outagesbetween two

    overhauls ( nos )

    Important& major

    highlights

    From To Total BTL Trip Total

    1

    Proposed

    overhaul-

    2012-13

    01/09/

    2012

    17/09/

    2012

    17

    days

    Boiler &

    auxilaries,

    Turbine &

    generator

    Bearing & its

    Auxilaries

    16831.02 35118.794 3 7 10

    2OH for FY

    11-12

    - - - - - - -

    3OH For FY

    10-11

    01/09/

    2010 at

    3:22 Hrs

    16/09/

    2010

    at

    12:36

    Hrs

    15

    days

    9

    Hrs

    14

    min

    Boiler &

    Turbine

    auxilaries,

    0 18287.774 - - -

  • 7/27/2019 Engineering Declaration Unit # 2 Jindal

    3/16

    6. Unit performance History of Past Three years.

    S. No. Parameters Previous 3 years

    2011-12 2010-11 2009-10

    1 Generation (MU) 2223.308 2141.018 2053.054

    2 Availability (%) 99.27 94.90 93.77

    3 Plant load factor (%) 101.24 97.76 93.75

    4 Loading factor (%) 101.98 103.02 99.98

    5 Total Generation Loss ( MU) 24.644 115.872 166.386

    6 DM Make up (%) 0.44 0.48 0.70

    7 Heat rate 2286 2293 2315

    8 No. of BTL 0 2 6

    9 No. of trips. 5 3 9

    10 Total forced outage (%) 0.19 0.89 4.23

    7. Boiler tube leakages detail since last overhauling.

  • 7/27/2019 Engineering Declaration Unit # 2 Jindal

    4/16

    SL.

    NO

    DATE &

    DURATIONFAILURE LOCATION TUBE DETAILS TYPE OF DAM

    1

    16/11/10(11:43 HRS.)

    TO 18/11/10

    (12:43hrs)

    (i) LHS STEAM COOLED WALL

    TUBE NO-3 FROM REAR TO

    FRONT.(ii) LHS STEAM COOLED

    WALL TUBE NO-1&2 FROM

    REAR TO FRONT AND LTSH

    INLET HEADER SHH-9 LHS

    END DUMMY

    STEAM COOLED WALL STRAIGHT TUBE 3NOS EACH1 MTR

    LENGTH. (MATERIAL SA 210 GRADE-A1 DIA 44.5X4.5MM

    THICK).

    ORIGINAL FAILUR

    FINS WELDING AN

    SECONDARY DAM

    CAUSE DUE TO HI

    PRESSURE STEAM

    2

    03/05/12

    (12.23 HRS)

    TO 04.05.12

    (12.00 HRS)

    STEAM COOLED WALL LEFT,

    ELEVATION IN METRE 41

    MTR, PRIMARY FAILURE- LHS

    STEAM COOLED WALL TUBE

    NO-3RD FROM REAR,NEAR

    LTSH INLET HEADER.

    SECONDARY FAILURE- LHS

    STEAM COOLED WALL TUBENO-2ND FROM REAR,NEAR

    LTSH INLET HEADER

    ORIGINAL TUBE DIMENSION: TUBE OD-44.5 IN MM

    THIICKNESS -4.5 IN MM, TUBE MATERIAL :SA 210 Gr-C

    SECONDARY FAILED TUBE DIMENSION: TUBE OD 44.5 IN

    MM, THIICKNESS - 4.5 IN MM, TUBE MATERIAL :SA 210 Gr-C

    SUSPECTED ROOT

    OF PRIMARY FAILU

    FLUE GAS EROSIO

    SECONDARY TUBE

    FAILURES DETAIL:

    SECONDARY FAILU

    TO HIGH PRESSUR

    CUT.

    3

    23.08.12

    (15.32HRS TO

    25.08.12

    (07.23 HRS)

    FURNACE WW LEFT,

    PRIMARY FAILURE - FROM

    CENTER OF WB-26,TUBE NO-

    6 TOWARDS FRONT,

    SECONDARY FAILURE - FROM

    CENTER OF WB-26,TUBE NO-

    7 TOWARDS FRONT,

    ORIGINAL TUBE DIMENSION:TUBE OD-63.5 IN MM

    THIICKNESS - 5.6 IN MM, TUBE MATERIAL :SA 210

    GRC SECONDARY FAILED TUBE DIMENSION: TUBE OD 63.5

    IN MM, THIICKNESS - 5.6 IN MM, TUBE MATERIAL :SA 210

    GRC

    PRIMARY FAILURE

    ATTACHMENT WE

    SECONDARY FAILU

    TO HIGHPRESSUR

    CUT

  • 7/27/2019 Engineering Declaration Unit # 2 Jindal

    5/16

    8. Unit / Equipment Performance & Efficiency Evaluation Before Overhauling

    Plant performance of Unit # 2 is as follows

    S.No. Parameters Pre OH

    1 Boiler Efficiency (%) 86.501

    2 Corrected Boiler Efficiency 86.34

    3 Gross Turbine Cycle Heat rate 2022

    4 Corrected Gross Turbine Cycle Heat rate 2009

    5 Gross Unit Heat Rate 2338

    6 Corrected Gross Unit Heat Rate 2327

    7 Heat rate Deviation 79

    8 Accountable loss 54

    9 Unaccounted loss 26

    9. Efficiency Tests

    1) Turbine Efficiency Test

    a) Turbine Report Sheet

    Sl.

    No.Parameters Design Pre OH

    1 Unit Load (in MW) 250 254

    2 MS pressure (in kg/cm2) 150 145.6

    3 MS Temp(in oC) 537 535.2

    4 1 st Stage Pressure (in kg/cm2) 136.63 140.7

    5 CRH Pressure (HPTurbine exhaust) (in kg/cm2) 39.57 40.66 CRH Temperature (HPTurbine exhaust) (in oC) 343 349.8

    7 HRH Pressure (in kg/cm2) 35.62 38.2

    8 HRH Temperature (in oC) 537 535.0

    9 IP Exhaust Pr (in kg/cm2) 6.96 7.7

    10 IP Exhaust Temp (in oC) 306.5 310.2

    11 Extraction Pressure to D/A (in kg/cm2) 7.7

    12 Extraction Temp to D/A 310.2

    13 COND. TO DEARATOR Pressure(in Kg/cm2) 9.9

    14 COND. TO DEARATOR Temp 120.3

    15 COND. TO DEARATOR flow 612 621.4

    16 BFP Suction temp(deg C) 163.5

    22 MS Flow (in TPH) 758.5

    23 FW Flow (in TPH) 757.48 758.5

    24 Reheater Spray (in TPH) 0 25.3

    25 HPH6 FW O/L Temp(in oC) 245.9 247.2

    26 CRH Flow Calculated 665.8 701.7

    27 Condenser Vacuum -0.906 -0.902

  • 7/27/2019 Engineering Declaration Unit # 2 Jindal

    6/16

    b) Turbine Performance Indices

    1 Gross Turbine Cycle Heat rate (in Kcal/kwh) Design 1951

    2 Gross Turbine Cycle Heat rate (in Kcal/kwh) 2022

    3 Corrected Turbine Cycle Heat rate (in Kcal/kwh) 2009

    4 Deviation (Corrected Design) (in Kcal/kwh) 58

    c) Cylinder efficiency

    1 Parameters Design Pre

    2 HP Cylinder Efficiency 86.66 86.54

    3 IP Cylinder Efficiency 91.90 90.52

    2) Condenser Performance

    Sl.

    No.Description Unit

    Date

    Design Pre OH

    1 Load MW 250 254.0

    2 Condenser pressure Kg/cm2 -0.906 -0.897

    3 Condenser back pressure mbar 101.13 98.31

    4 Optimum back pressure mbar 91.6 93.05

    5 Corresponding Saturation Steam Temperature Deg C 44 45.25

    6 CW inlet Temperature Deg C 33 31.30

    7 CW outlet Temperature Deg C 41.5 40.728 Optimum CW rise Deg C 8.5 8.50

    9 Actual CW Rise Deg C 9.42

    10 Optimum TTD Deg C 2.5 4.50

    11 Actual TTD Deg C 4.53

    12 Back pressure due to CW inlet (6+8+10) mbar 92.54

    13 Back pressure due to CW flow & CW inlet (7+10) mbar 97.04

    14 Variation due to CW inlet temp mbar -0.51

    15 Variation due to CW Flow mbar 5.50

    16 Variation due to air/ dirty tubes mbar 3.27

    17 Total Variation mbar 10.77

    18 Number of Vacuum Pumps in service nos 1

    19

    CONDENDER DUTY

    HEAT ADDED MS=FlowMS*(hMS-hFW) Kcal/kg 425758305

    HEAT ADDED CRH=FlowCRH*(hHRH-hCRH) Kcal/kg 73088791

    HEAT ADDED RH=FlowCRH*(hHRH-hATT) Kcal/kg 15026650

    TOTAL HEAT ADDED 513873746

    HEAT LOSS THROUGH RADIATION kW 254

    Pgen kW 254000

    Pgen Losses kW 2540

  • 7/27/2019 Engineering Declaration Unit # 2 Jindal

    7/16

    Total Heat lost 256794

    CONDENDER DUTY Kcal/hr 293030906

    20

    CW FLOW= Cond Duty /((Cwout- Cwin)xdensityx

    Cp) m3/hr 31104

    Outer dia OD mm 29

    Tube thickness (t) mm 1

    Cross -Sectional area mm2 590Total No of Tubes nos 15664

    21 WATER VELOCITY IN CONDENSER TUBE m/sec 1.870

    3) Boiler Efficiency

    ParametersDate 08.08.2012

    Design Pre OH

    Unit Load 250 254

    Steam Flow 740 758.5

    COAL FLOW 157 178APH GAS INLET TEMP 340 246.0

    APH GAS OUTLET TEMP 132 138.7

    AVG I/L PRIMARY AIR TEMP 34 34.01

    PRIMARY AIR FLOW 239 291.79

    AVG O/L PRIMARY AIR TEMP 310 296.8

    AVG SECONDARY AIR I/L TEMP 34 32.1

    AVG SECONDARY AIR O/L TEMP 320 302.1

    SECONDARY AIR FLOW 571 520.8

    AH INLET O2 % 3.5 2.7

    AH OUTLET O2 % 5 5.4

    AH OUTLET CO2 % 15.4 15.8AH OUTLET CO % 75 12

    UNBURNT IN FLY ASH 0.6 0.3

    UNBURNT IN BOTTOM ASH 1.5 1.33

    AMBIENT AIR TEMP DRY 34 27

    AMBINT AIR TEMP WET 28 25

    AMBINT AIR TEMP RH 60.0 85

    Proximate Analysis Result

    Total Moisture 12 13.0

    Ash 39 39.2

    V.M 22 23.0

    FC 27 24.9

    GROSS CALORIFIC VALUE 3600 3507

    Heat Losses (%) Design Pre OH

    UNBURNT CARBON LOSS 1.2 0.412

    HEAT LOSS DUE TO HEAT IN DRY FLUE GAS 4.211 5.235

    HEAT LOSS DUE TO MOISTURE IN AS FIRED FUEL 2.067 2.314

    HEAT LOSS DUE TO MOISTURE FROM BURNING OF

    HYDROGEN4.309 4.048

  • 7/27/2019 Engineering Declaration Unit # 2 Jindal

    8/16

    HEAT LOSS DUE TO MOISTURE IN AIR 0.16 0.175

    HEAT LOSS DUE TO SURFACE RADIATION & CONVECTION 0.22 0.22

    HEAT LOSS DUE TO RADAITION & UNACCOUNTED 0.54 0.74

    HEAT CREDIT( HEAT EQI. OF POWER) -0.165

    HEAT LOSS DUE TO MILL REJECT 0.020

    MANUFACTURE MARGIN 0.5 0.5

    TOTAL HEAT LOSS 13.207 13.501BOILER EFFICIENCY 86.79 86.50

    CORRECTED BOILER EFFICIENCY 86.34

    4) APH Performance

    Parameters DesignPre OH

    Pass A Pass B

    O2 I/L (Oxygen at APH Inlet) 3.76 3.5 3.5

    O2 O/L (Oxygen at APH outlet) 5 5.7 5.2

    PA inlet Temp (Tpai) 34 37.5

    PA outlet Temp (Tpao) 314 296.8

    PA flow 238.6 301.4

    SA inlet Temp (Tsai) 34 32.0

    SA outlet Temp (Tsao) 319 302.1

    SA flow 570.7 520.8

    Weighted Avg intet Air temperature (Tai) 34 34.0

    Weightyed Avg outlet Air temperature (Tao) 317.5 299.5

    Flue gas inlet temperature (Tgi) 348 348.5 341.5

    Flue gas outlet temperature (Tgo) 132 136.4 137.4

    Flue gas outlet temperature with no leakage (Tgnl) = AL xCpa x (Tgo - Tai)/(100x Cpg) + Tgo; where Cpa(specific

    heat of air) = 1 and Cpg (specific heat of gas) = 0.993

    138.9 151.1 152.6

    A/H LEAKAGE ( in %) 6.98 14.28 10.95

    A/H Gas side Efficiency (GSE) 66.60 62.77 61.46

    A/ H - X Ratio 0.74 0.74 0.71

    5) ESP Performance

    ParametersDate 28.08.2012

    Pre OH

    Design Pass - A Pass - B

    Load 250 256.5

    ESP I/L Draft(mmwcl) -203 -167.89 -167.43

    ESP O/L Draft (mmwcl) -249 -296.18 -296.50

    Pressure Drop 46 -128.29 -129.07

    ESP I/L Temp(oC) 132 128.17 128.49

  • 7/27/2019 Engineering Declaration Unit # 2 Jindal

    9/16

    ESP O/L Temp (oC) 122 113.72 112.01

    Temperature Drop 10 14 16

    Opacity 50 47.2

    Fields not in Service NIL

    ID Fan - A Current 190.53

    ID Fan - B Current 191.88

    6) Cooling Tower Performance

    Sl.No. PARAMETERSDate

    Design Pre OH

    1 No of cells 14 13

    2 CW O/L Temp 42 42

    3 CW I/L Temp 33 32.3

    4 DRY BULB TEMPERATURE 29.2

    5 AMBIENT WET BULB TEMP 28.5 27.13

    6 APPROACH(A) = Cwi - WBT (in oC) 4.5 5.2

    7 RANGE(R) = CWo - Cwi (in oC) 9 9.6

    8 EFFECTIVENESS(E) = (RX100)/ (R+A) 66.7 65

    9

    TOTAL WATER FLOW RATE CALCULATED

    (CR)=(CW+ACW)40000 33578.08

    10

    EVAPORATION LOSS = CR x (Cwo- Cwin) /675 in

    M3/hr

    520at 90% RH

    design479

    11 COOLING CAPACITY in Kcal/Hr 360000 323577

    12

    CYCLES OF CONCENTRATION = TDS in CW/TDS in

    makeup8 6.67

    13

    MAKE UP WATER CONSUMPTION = Evap Loss

    /(COC - 1) in M3/Hr74.29 84.55

    14 CW Flow to each Cell 3077 2583

  • 7/27/2019 Engineering Declaration Unit # 2 Jindal

    10/16

    10. Scope of work

    BOILER

    PRESSURE PARTS

    Complete Boiler water washing, wall scrapping & buffing.Erection & Dismantling of Quick Erect Scaffolding in first pass up to roof tubes at every 2mt

    elevation including PSH

    Thickness survey of tubes

    Erection of scaffolding and platform in LTSH Terminal Tubes, Re-heater (both banks), Screen

    Tubes, Hanger Tubes at every 2.0 mtr. elevation and complete platform below Economizer.

    Pent house & dead chamber cleaning

    DP test of weld joints & header stub and attachment welding.

    Shifting, Dismantling, Erection & Alignment of Eco coils (Upper& Lower )

    Lifting/Lowering of coils (lower & upper) for inspection

    Welding of HP tubes up to 76.1mm dia.

    Strengthening of boiler tubes by weld overlay.Refurbishment of header by weld overlay

    Fabrication of HP bends up to 76.1mm dia.

    Alignment of coils (PSH, RH, FSH, LTSH, Eco)

    Fixing of protection shields /shrouds

    Fin/skin casing welding by tested welder

    Application of Plastic Refractory

    Application of insulation & cladding sheet

    Drum cleaning and inspection

    Wall blower distance setting & sleeve fitting

    Servicing of buckstays, manhole, peephole ( servicing of all buck stay pins, boiler expansion

    indicators, manholes, peepholes, tie rod of dog house & pent house header hanger supports.)Repair & Re-installation of bottom seal plate and Woven Wire Mesh

    Replacement/repair of fuel burners replacement of 24 Nos. coal nozzle , repairing of all oil &

    air bucket, servicing of tilting mechanism ,repairing of wind box & servicing of SADC.

    Cleaning of 12 Nos. coal pipes with water jet. Servicing of oil, air & steam atomizing lines valve

    firing floor.

    Reversal of coal pipe orifice.

    Rotation of coal pipe (2 - 6 mtr. length)

    Replacement of coal pipe

    Repairing of coal pipe by patch welding of 500mmx500mm piece

    Inspection and Servicing of coal pipe coupling

    Alignment of coal pipe

    Inspection/repair/replacement of coal pipe bends

    Servicing of coal burner isolation gate.

    Cold Air velocity Test

    BOTTTOM SEAL TROUGH

    Inspection of seal plates & thorough cleaning of seal trough

    Inspection & checking of quenching nozzles & its direction

    Repair/ Replacement of SS Mesh & Bottom Seal plate AT BAH

  • 7/27/2019 Engineering Declaration Unit # 2 Jindal

    11/16

    VALVES

    Overhauling Of HP Valves - Drain & Vents, Root Valves

    Overhauling & Pressure setting of safety Valve SV1 to SV5

    FUEL FIRING SYSTEM (COAL & OIL BURNERS, SADC )

    Replacement of 24 nos coal nozzle ,servicing & alignment of burner tilts

    Repairing of Wind Box & Servicing Of SADC & its synchronized movement

    Condition checking of oil & air compartments

    Healthiness checking of air guide vanes inside wind box

    Inspection of all attachments in the burner zone near transition tubes to check whether wind

    box is properly loaded on the water wall tubes & no attachment is missed out during

    replacement of burner transition tubes

    Thickness measurements of coal pipes

    Condition based replacement of coal pipes

    Inspection of elbow/bend , orifice & victaulic gasket randomly.

    Servicing of knife edge gate valves for coal nozzle

    APH A & B

    All Baskets to be taken out &cleaned with High pressure water jet. Templates to be made for

    covering the cleaned baskets so that foreign material does not fall into the basket.

    Renewal of Outboard baskets (48 nos.) / APH

    Seals And Baskets Inspection & Arrangement for Basket Cleaning, Seal setting (replacement of

    damage seals)

    Guide & Support Bearing, rotor post aluminum seal opening & inspection,

    Hot end & cold end rotor post seal repair/replacement & kao wool packing

    Lub oil system servicing of support & guide bearing

    Guide & support bearing oil flushing & oil changing

    Attending hot air leakages in guide bearingAir heater soot blower servicing & angle setting

    Inspection of Gear box, fluid coupling & oil changing & realignment.

    Servicing of Air motor

    Support & Guide Bearing alignment after seal setting

    Repairing of APH duct from GD1 & 2 to APH Hopper

    Checking of healthiness of fire fighting system- replacement of eroded headers,

    cleaning/replacement of nozzles

    DUCT & DAMPERS OVERHAULING

    Cleaning, Inspection and thickness measurements of ducts

    Repair , replacement of eroded bracings, duct plates & guide vane plates/Expansion Bellowsof PA & FD , ESP I/L & O/L ducts with SAIL HARD/ SELMA STEEL

    Servicing & repair of all dampers and gates along with seals

    Replacement of eroded guide vanes

    Checking of the operating mechanism of all the dampers & gates

    Checking of the healthiness of the blower

    Practices to be followed during Overhauling of Boiler

    Steam/air blowing of new tubes before installation

    Sponge ball test of new coils/bends to be done before installation

  • 7/27/2019 Engineering Declaration Unit # 2 Jindal

    12/16

    All vertical tubes to be cut with grinders only

    Immediate capping of tubes to be done after cutting

    Deployment of tested cutter for tube cutting

    Deployment of tested HP Welders for welding of joints.

    All attachment welds to be done by tested welders

    Attachment welds to be done by 2.5mm size electrodes only

    All supports / clamps to be restored to original

    FANS

    Inspection, repair & maintenance of PA Fans, FD Fans, ID Fans, Seal Air fans.

    COAL MILL & FEEDER.

    Replacement of Grinder Roller of Mill 4A & 4C

    Replacement of Bullring Segment of Mill 4A, 4B, 4C & 4D

    Replacement of Clamping Ring of Mill 4A, 4B, 4C & 4D

    Hard facing Inside Mill & JOC

    Servicing/Replacement of of Journal Pressure Spring

    Replacement/Servicing of Classifier Vane Assembly.

    ESP

    Thorough internal inspection of ESP electrodes to locate defects and repairing.

    Cleaning and inspection of shaft insulators, support insulators and replacement of any

    damaged insulators. Screen tube and Field suspension rod.

    GD Test to be done

    TURBINE

    Overhauling of LP Turbine Module

    Replacement of Hydrogen Seal Rings of Generator.

    Overhauling of Generator & Exciter

    Inspection of Bearing Nos. 1 to 7 and H2 Seal Ring.

    Overhauling of MOP, MS Strainer (LHS), HRH Strainer (RHS), PHE A & B, CEP - 2A, 2B & 2C-

    Provided we receive the Dummy sleeve reqd. for modification of CEP.

    Servicing of Turning Gear, HPSV, HPCV, IPSV, IPCV & its Servomotor, HPBP Valves, HPBP Spray

    valves, Butterfly Valves, Air Release valves.

    Checking of Governing Characteristics

    Cleaning of BFP & Booster pump suction strainers, De-aerator, FST, OCST & DMCW Tank, Hot

    well, ACW Strainer Elements, Cooling Tower basin

    Transferring of Oil in MOT to COT, Cleaning of MOT and again transferring of oil from COT to

    MOT.Condenser Tube cleaning by Bullet Shot Method and applying of Chemical Resistant Coating

    in Condenser tube sheets & water box

    Carrying out Condenser Flood test, Air/H2 leak test of Generator, Hydro test of H2 & Exciter

    Coolers

    CW Duct Butterfly valve inspection and servicing

    Attending identified leakages and defects booked by Operation dept.

    CT Basin Cleaning, Cooling Tower nozzles & drift eliminators cleaning, repairs & replacement

  • 7/27/2019 Engineering Declaration Unit # 2 Jindal

    13/16

    Electrical

    Overhauling of Generator Generator overhang portion NFT Test & Inspection.

    Exciter & PMG Dismantling, inspection & testing.

    NGR, NGT & SPVT inspection, tightness checking & testing.

    Preventive maintenance of Gen Aux Panel- ECB, CFA & CTE02 Panel.

    Transformer Overhauling GT General Checking & OLTC inspection, UAT A&B oil filtration,OLTC inspection, ST2- OLTC inspection & general checking. Testing of GT , ST & UAt-2A &2B.

    Unit & station auxiliary transformers cleaning, inspection, tightness checking & testing.

    6.6 KV HT SWITCHGEAR(5 Nos of MAIN PLANT & BOP) - inspection & cleaning of bus bars &

    feeders, connection tightness of power and control cables, sealing of spare holes ,inspection

    of CT's and PT's.

    415 V LT SWITCHGEAR (17 Nos. of MAIN PLANT & BOP)- inspection & cleaning of bus bars &

    feeders, connection tightness of power and control cables, sealing of spare holes ,inspection

    of CT's and PT's.

    H.T.MOTORS OVERHAULING (15 nos )- ID Fan A&B, FD Fan A&B, PA Fan A&B, Coal Mill

    A,B,C,D &E, 1 BFP, CEP- A, B&C. Cleaning, varnishing, painting, bearing inspection &

    replacement and testing.

    LT MOTORS OVERHAULING (81 Nos.) - Cleaning, varnishing, painting, bearing inspection &

    replacement and testing.

    Wall & soot blowers cleaning, inspection, motor bearing replacement if required.

    MOV Actuators overhauling Cleaning, inspection, grease & oil replacement.

    AVR cleaning, inspection, tightness, field breaker alignment testing, & Dynamic Testing

    GRP-Cleaning, inspection, tightness, relays testing, annunciation checking.

    ESP - BAPCON, RAPCON Panel, Rectifier Transformer Overhauling &testing, PMCC,MCC & Dry

    transformer overhauling.BATTERY AND D.G. SET-Capacity test of 220 V UNIT-2 Main Battery & UPS battery, Battery

    charger cleaning, tightness & inspection

    220 KV Switchyard bay: Breaker, CT, Isolators general checking/ testing/ maintenance.

    C&I

    TG AREA

    Cleaning of field equipments, JB's and ensuring the tightness of all connections.Checking and calibration of all critical instruments related to plant ,equipment tripping,

    interlock and efficiency analysis.

    Checking and calibration of control valves and hydraulic actuators.

    Checking of TSI pick up response and calibration.

    Servicing of UPS & ACDB

    To install and commission electronic level switch in CRH.

    Checking of protection interlock of turbine and its auxiliaries

    DCS storian upgradation and HMI software setting and checking.

  • 7/27/2019 Engineering Declaration Unit # 2 Jindal

    14/16

    Cleaning and checking of the DCS cards.

    Flow nozzle of LPBP spray to be shifted before MOV.

    To Replace HP exhaust thermocouples.

    To replace MOT level transmitter with radar type LT to improve reliability and accuracy.

    To install isolation valve in the downstream of CEP vent solenoid valve.

    To shift orifice plate of DM makeup flow from downstream to upstream of CV.

    Skin type RTD to be installed in BFP recirculation line to detect RC valve leakage.

    RTD to be installed in place of temperature switch in Vacuum pump for improving condenser

    performance.

    ATRS/ATT establishment to be checked and to be made operative.

    BOILER AREA

    To check the overall instrumentation of HFO Station (FM,HOTV &HOFCV), LDO & Air Station

    (FM,LOTV&LOFCV) & Station for Atomising Steam at Operating Floor

    To check the operation of Oil Burner - AB Elevation (AANV,ASNV,HONV & LONV) and for CD &

    EF Elevation (AANV,ASNV & HONV)

    Servicing/checking of HEA Spark Rod/Igniter advancement / Flame Scanner functioning at all

    elevations

    To check/replace the T/C's of HOT end & cold end of APH-A&B, RTD of guide bearing of APH.

    To check/inspect & Calibrate both Oxygen probes, PA Header Pressure Transmitters (03 Nos.)

    & Switches (05 nos.), Furnace Pressure switches (06 NOS)

    Cleaning & Calibration of SADC Power cylinders (56 Nos.)

    Cleaning & Calibration of all Power cylinders for ID, FD, PA, HAD,CAD, HAG & Burner Tilt (Total

    30 Nos.)

    Checking and calibration of all critical instruments related to plant equipment tripping,

    interlock and efficiency analysis.

    All auto control loops performance checking and fine tuning.

    AHP AREA

    ESP level probe checking.

    ESP vacuum transmitter calibrationSlurry pumps interlock & protection checking

    Overhauling of all Power cylinders (Total 90 Nos)

    Buffer hopper purging solenoid valves orientation to be changed from horizontal to vertical.

    ASH HANDLING SYSTEM

    Bottom Ash Hopper Refractory work.

    Seal trough cleaning and repairing.

    Inspection, Servicing and Assembly of fluidizing pads (128 Nos.)Replacement of all gaskets between hopper to M.S. adaptor & M.S. adaptor to knife gate

    valve

    Inspection, Servicing and Assembly of all MHV (72 Nos.) of ESP, Duct and APH hoppers and

    their segregating valves (29 Nos.)

    Inspection, Cleaning and Replacement of worn out parts of all collector towers.

    Inspection , Replacement of worn out parts of rotating segregating valves of all Air lock

    vessels.

    Removal, Inspection, Replacement & Assembly of fluidizing pads of buffer hopper & air lock

    vessels

  • 7/27/2019 Engineering Declaration Unit # 2 Jindal

    15/16

    Inspection, Replacement of damaged bag, cage of bag house

    Inspection & replacement of worn our parts of feed gate assemblies, hydro ejector.

    Dismantling of flushing apparatus, inspection & replacement of gaskets, nozzles, pipe, fittings,

    valves and reassembly of flushing apparatus in Economizer Hopper

    11. Improvement & Modification Work

    TMD

    Modification of CEP. Installation of dummy stage in place of 2nd Stage, for existing3 No. CEPs.

    Corrocoat Coating of CW & ACW Pumps Hydraulic passage of Unit#02.BMD

    Application of Plastic Refractory. Burner nozzles to be modified and replaced during Overhauling.

    C&I

    Relocation of temperature element of after reheater desuperheter to avoidmeasurement error.

    Flow nozzle of water injection flow of LPBP to be shifted before motorized valve asexisting installation does not cover flow through motorize valve .and to avoid unit

    tripping in case of failure of pneumatic valve.

    To replace head type RTD/Thermocouples with head less ones in critical areas likeexciter hot air temperature & seal oil temperature etc.

    To replace MOT level transmitter with radar type LT to improve reliability andaccuracy.

    Installation of RTD in place of Temp switches in Vacuum pump for monitoring andcontrol of temperature and improving condenser performance.

    Provision for remote monitoring of HPBP system oil pressure and control of HPSUpump.

    BFP trip contact of dearator level low to be derived from transmitters in addition toswitches to improve reliability.

    To install isolation valve in the downstream of CEP vent Solenoid valve. To shift orifice plate of DM make up flow from downstream to upstream of CV to

    avoid measurement errors.

    UCP,ATRS & ATT establishment. Skin type RTD to be installed in BFP recirculation line to monitor RC valve passing. Buffer Hopper purging SOV'S Orientation to be changed from horizontal to vertical to

    improve reliability.

    To install & commission electronic level switch in CRH. Main Steam temperature low trip contact to turbine to be derived from soft to Hard

    as an endeavor to improve reliability.

    Relocation of Local Vibration Indicator Junction Boxes for ID, FD&PA Fans.

  • 7/27/2019 Engineering Declaration Unit # 2 Jindal

    16/16

    ELD

    Auto Bus transfer scheme at CTPMCC in UNIT-2 6.6 KV HT Board H.T. Motor tripping from Bus PT at main plant in UNIT-2 Redundant Power supply arrangement of AVR For unit -2 Provision of all H.V. motors over load alarm of unit -2 at CCR LVS Generator SPVT all voltage transformers of Prayog make shall be changed with Pragati

    make voltage transformer total nine numbers

    6 Amp MCB to be provided in place of low rated MPCB in motor feeder module

    12. Pending defect & Opportunity Based jobs-

    Pending defects are available on line, being attended and updated daily. Pending defect list to be taken before one month of unit shut down.

    13. Justification/Evaluation of Overhauling

    1. For Boiler license renewal, validity is up to 06/09/2012. The Boiler license is to berenewed up to for further two years duration.

    2. During Annual Overhaul essential activities shall be carried out for safe and reliableoperation of the unit for next two years.

    3. Overhauling of LP Turbine Module & Generator to be done.4. Due to Furnace Fouling Flue gas Temperature, SH spray & RH spray are of higher side,

    which shall be reduced by High pressure Jet cleaning, scrubbing of Boiler etc. This will

    reduce the Heat rate losses and improve the plant efficiency.

    5. Due to air ingress in the boiler and ducts, ID fan currents is on higher side, which can bereduced by thorough inspection of ingress points in BA hopper, Seal trough area,

    Replacement of rope gaskets in ESP manhole doors.

    6. Air Heater Air ingress is on higher side, Air side gas side efficiency is also poor whichrequires APH seal setting, cleaning of basket and APH hot water washing.

    7. Cleaning of ESP during shutdown will not only improve the performance but willbenefit help to meet the requirements of pollution norms.

    8. Condenser cleaning by high pressure bullet jet and condenser flood test during OH willalso help to reduce any type of losses in performance of unit. Cooling Tower cleaning

    during AOH will also benefit us for condenser performance improvement.

    9. Passing of High pressure Energy drains has been already identified, which shall beattended during OH.