Upload
others
View
4
Download
0
Embed Size (px)
Citation preview
Contract N°: IEE/13/824/SI2.675067
Energy Saving Policies and Energy
Efficiency Obligation Scheme
D7.4: Final Conference in Brussels
Project Coordinator: Joint Implementation Network - JIN
Responsible partner: VITO
July 2016
The sole responsibility for the content of this [webpage, publication etc.] lies with the
authors. It does not necessarily reflect the opinion of the European Union. Neither
the EACI nor the European Commission are responsible for any use that may be made
of the information contained therein.
Co-funded by the IEE Programme of the EU
Contract N°: IEE/13/824/SI2.675067
D7.4: Final Conference in Brussels
Co-funded by the IEE Programme of the EU
Contract N°: IEE/13/824/SI2.675067
D7.4: Final Conference in Brussels Page 1
Table of Contents
1 Agenda of the final conference........................................................................................... 2
2 Some impressions of the conference ................................................................................. 4
3 Participant List..................................................................................................................... 6
4 Group discussions on EE challenges ................................................................................... 9
4.1 White Certificates ........................................................................................................ 9
4.2 From monopoly to liberalized markets ..................................................................... 11
4.3 Deemed savings......................................................................................................... 13
Co-funded by the IEE Programme of the EU
Contract N°: IEE/13/824/SI2.675067
D7.4: Final Conference in Brussels Page 2
1 Agenda of the final conference
ENERGY SAVING POLICIES AND ENERGY EFFICIENCY OBLIGATION SCHEMES
Final Conference Agenda
Venue: VLEVA www.vleva.eu Kortenberglaan 71 1000 Brussel Date: 13.06.2016
Date: 13 June 2016
9:30 – 10:00 Registration and Coffee
10:00-10:20
Welcome, short ENSPOL introduction and overview of the Final Conference
Vincent Berrutto, EASME
Vlasis Oikonomou, JIN, coordinator ENSPOL
10:20-10:40 General findings of the ENSPOL project
Vlasis Oikonomou, JIN
10:40-12:30
ENSPOL, NEVER-ENDING SCHOOL: INSIGHTS FROM POLICY EVALUATIONS AND CROSS-
COUNTRY EXCHANGE
Moderators: VITO, EST
Smaller group discussions on EE challenges, starting from interesting stories from
Member States (30’):
- France: Elodie Trauchessec, ADEME
- Poland: prof. T. Skoczkowski, KAPE
- Denmark: Nikolaj Nørregård Rasmussen, DEA
Break 15’
Group discussions on EE challenges:
- ENSPOL guidelines: implementation of Article 7, JIN (10’)
- Introduction to discussion, VITO (10’)
- 3 topics to be discussed: deemed savings, EE obligations ‘from monopoly to liberalized
markets’, white certificates (45’, including wrap-up)
12:30-14:00 Lunch
14:00 – 14:20 Status of Article 7 implementation
DG Energy
Co-funded by the IEE Programme of the EU
Contract N°: IEE/13/824/SI2.675067
D7.4: Final Conference in Brussels Page 3
14:20 – 16:15
3RD EU OBSERVATORY: OBSERVATORY NETWORKS & STAKEHOLDER ENGAGEMENT
WITHIN ENSPOL
Moderators: AEA, SEI
EU-Observatory (20’)
- Overview and feedback of ENSPOL activities, AEA
- Case studies: Italy, Alberto Pela, GSE
National Observatories (20’)
- Overview and feedback of ENSPOL activities, FIRE
- Case studies: Croatia, Mia Dragovic, EIHP
Stakeholder Knowledge Platform (20’)
Feedback on ENSPOL stakeholder platform, EST
BREAK 20’
Is there life after ENSPOL? The future of the ENSPOL Observatory network & stakeholder
platform (35’)
- Presentation Christian Deconninck, ATEE
- Plenary discussion, moderator SEI
16:15 – 16:30 Closure of the conference
Vlasis Oikonomou, JIN
Co-funded by the IEE Programme of the EU
Contract N°: IEE/13/824/SI2.675067
D7.4: Final Conference in Brussels Page 4
2 Some impressions of the conference
All the information material of ENSPOL Final Conference are available in Final conference’s
webpage: http://enspol.eu/events/enspol-final-conference-13-june-2016-brussels
Article 7 of Directive 2012/27/EU on
energy efficiency
By Lelde Kiela-Vilumsone, DG ENER.C.3
ENSPOL guidelines
By Vlasis Oikonomou (ENSPOL Coordinator),
JIN Climate and Sustainability
National observatories under the ENSPOL
project
By Dario Di Santo, Italian Federation for
Energy Efficiency (FIRE)
Co-funded by the IEE Programme of the EU
Contract N°: IEE/13/824/SI2.675067
D7.4: Final Conference in Brussels Page 5
Knowledge sharing platform Article 7 EED
By Emilie Carmichael, Energy Saving Trust
(EST)
Obervatory networks & Stakeholders
engagement within ENSPOL
By Alberto Pela, Regulatory Affairs – GSE
Photos from the Final Conference
Co-funded by the IEE Programme of the EU
Contract N°: IEE/13/824/SI2.675067
D7.4: Final Conference in Brussels Page 6
3 Participant List
ENERGY SAVING POLICIES AND ENERGY EFFICIENCY OBLIGATION SCHEMES
Final Conference List of Participants
Venue: VLEVA www.vleva.eu Kortenberglaan 71 1000 Brussel Date: 13.06.2016
Date: 13 June 2016
Name First name Company
Alessi Monica CEPS
Bassaglia Gaël GEO PLC
Bayer Edith Regulatory Assistance Project
Bean Frances Stefan Scheuer Consulting
Becker Stefan E.ON SE
Berrutto Vincent EASME
Böck Elisabeth Austrian Energy Agency
Broad Will Department of Energy and Climate Change
Bruel Renée ECF
Brunson Aurore IBGE
Carmichael Emilie EST
Cavalcanti Juliana Effy Global Services
Cosier Joseph Energy Saving Trust
Deconninck Christian ATEE
Di Santo Dario FIRE
Dr. Duvigneau Johann Ludwig Federal Ministry for Economic Affairs and Energy
Dragović Mia Energy Institute Hrvoje Požar
Duvielguerbigny arnaud COGEN Europe
Elena Taxeri CRES
Fawcett Tina OUCE
Co-funded by the IEE Programme of the EU
Contract N°: IEE/13/824/SI2.675067
D7.4: Final Conference in Brussels Page 7
Flamos Alexandros University of Piraeus Research Center
Flamos Alexandros University of Piraeus
Georgiev Zdravko Association of Bulgarian Energy Agencies ABEA
Gkonis Nikolaos Greece
Gonçalves Stéphanie SIPLEC
Greenwood Marianne ENR'CERT
Haeder Henning EURELECTRIC
Hamdouch Jawad GEO PLC
Heerma van Voss Bas Ministry of Economic Affairs, Netherlands
Hofman Erwin JIN Climate and Sustainability
Holme Philippa Ofgem
Ioannis Vougliouklakis Greece
Izabela Kielichowska Ecofys
Jose Manuel Vega Barbero Stockholm Environment Institute at U. of York
Karásek Jirí SEVEn
Katarzyna Wardal EFIEES
Kiela-Vilumsone Lelde DG Energy
Kulevska Tsvetomira Sustainable Energy Development Agency
Lambertucci Stefano European Solar Thermal Industry Federation
Laumanns Ulrich GIZ
Moorkens Ils VITO
Pela Alberto GSE
Petersone Andzela Ministry of Economics of Latvia
Petroula Dora CAN Europe
Rasmussen Nikolaj Danish Energy Association
Renders Nele VITO, Flemish Institute for Technological Research
Romon Xavier EDF
Sakellaridis NIKOS Hellenic Electricity Distribution Network Operator
Sansoni Michele EASME
Co-funded by the IEE Programme of the EU
Contract N°: IEE/13/824/SI2.675067
D7.4: Final Conference in Brussels Page 8
Sartre Hugues GEO PLC
Skoczkowski Tadeusz Warsaw University of Technology
Spyridaki Niki-Artemis University of Piraeus Research Center
Stubner Heiko EU ProSun
Thenius Gregor Austrian Energy Agency
Toporek Marta ClientEarth
Trauchessec Elodie ADEME
Valente Claire Department of Energy and Climate Change
Vlasis Oikonomou JIN
Vuyk Ernst Vuyk Onderzoek Ontwerp en Advies
Weglarz Arkadiusz KAPE S.A.
Willenbrock Lisanne Evolution Energie
Co-funded by the IEE Programme of the EU
Contract N°: IEE/13/824/SI2.675067
D7.4: Final Conference in Brussels Page 9
4 Group discussions on EE challenges
4.1 White Certificates
Question 1. The evidence shows that incremental targets work. How new schemes could
increase their targets quickly and effectively? How can MS reduce their learning period
(or whether this is possible)?
Administrative issues were perceived as contributing the most to the (high) costs of WC
systems.
First the possibility to combine WC with EU ETS was explored. Participants did not agree on
this idea whereas energy efficiency is local and ETS global. It is also complicated to calculate
the effect from electricity on CO2 emissions.
The costs are the highest when setting up the EEO. The EED is only designed until 2020 but
participants perceived it as necessary to go beyond and to have a long –term, stable
framework.
On the EU level the comparability between schemes is difficult. Energy savings have
different costs in different MS. The cost of establishing a system should not be
underestimated and realising the measures costs a lot of money.
It was agreed that transparency to the broad public about the costs is necessary. But even
more about how the subsidy schemes work. The cost of energy efficiency was perceived
higher than the cost of RE.
Also the verification for EE measures is costly and there can be a lot of doubt about the
results. There is a lot of discussion on additionality and materiality and not many countries
take these factors into account transparently and comparably.
Deemed savings with low costs (low hanging fruit) are implemented already a lot. Metered
savings (in industry) are more costly. Usually during the scheme history there is a move to
metered savings.
ESCO’s are not perceived as strictly necessary at the beginning of the scheme. But you need
eligible parties to get the scheme running from the start.
Savings in households are very small while transaction costs might be considerable, should
they be in the WC scheme? Via deemed savings this can be possible.
Co-funded by the IEE Programme of the EU
Contract N°: IEE/13/824/SI2.675067
D7.4: Final Conference in Brussels Page 10
Question 2. How to ensure cost-efficiency, both for the state as for the obliged parties?
How can the administrative costs of running the WC system be reduced? Is there any
learning curve of managing the system leading to cost reduction?
Can ICT tools be helpful?
Rising targets result in higher costs. It is not sure that the cost per energy saved also
increases in the same way. This depends on the mix of technologies implemented. An
increasing target results in two effects: (1) measures can be implemented in a more
productive way (decreasing cost); (2) the easy to do measures will have been done (resulting
in higher costs).
Question 3. For which sectors the white certificates will be eligible? The choice of sectors
eligible might influence more directly the scope of the scheme and its degree of ambition.
Countries which focus on residential would have things to learn from those who have a
broader scope
If individual housing is included, then this has to be with a proof system which is simple for
deemed savings. In industry it can be a tool for industrial development. It has to be clear
that the system cannot be perceived as state aid. IF the market price for which certificates
can be sold on the market is unsure than WC cannot be perceived as subsidy.
Question 4. Urgent messages
It is very important that these will be a continuation from the EED after 2020.
Forget additionality compared to other policies. This is very complex and costly. It was
perceived better to set targets slightly higher and to consider every energy saving.
An evaluation of schemes is needed.
Keep existing schemes and try to establish schemes in countries which do not have in force
yet.
Exchange best practices like in ENSPOL.
Establish standardized and simplified verification reporting. Baseline can be different /
methodology can be the same.
It is inconsistent not to include transport. Dedicated measures to transport are necessary.
Co-funded by the IEE Programme of the EU
Contract N°: IEE/13/824/SI2.675067
D7.4: Final Conference in Brussels Page 11
4.2 From monopoly to liberalized markets
Context
Denmark has had an EEO for about 20 years where the obligated parties have been the
distribution companies (DSO), which are regulated monopolies. This scheme is widely
considered to be successful. However, currently politicians are proposing that the obligation
should be moved from distributors to retailers. This is in part due to their belief that this
would deliver more competition and ultimately result in cheaper energy efficiency / energy
savings, benefiting customers.
However, there are clearly a great number of risks associated with making this sort of
fundamental change to a policy, particularly in the short timescales proposed (one year).
These include:
• Uncertainty about delivery of projects which have been planned by DSOs to meet their
obligations up to 2020
• Projects within the industrial sector - which are dominant in the Danish scheme - can
take years to introduce and to demonstrate savings - how does this time scale fit with
the proposed change in obligated parties?
• Several of the retailers are not keen on this idea
• Some retailers are integrated with distribution companies, but customer numbers for
distribution are not necessarily the same as retail customers, meaning that even if the
overall organization remains the same, the obligation will change
• The impact on efficiency delivery businesses of this change
The context for discussion was set by a general presentation from Nikolaj Nørregård
Rasmussen, Dansk Engeri, about the proposed transition within the Danish EEO to the
whole meeting. At the beginning of the workshop session he gave a few more details of the
scheme, which were relevant to the discussion.
Questions
The general questions used to begin discussions were:
• Have any other countries got experience of this kind of policy re-design, whether in an
EEO or other type of policy?
• If this is going to happen, how could the transition period best be managed? What
should be done to reduce the potential adverse impacts of change and uncertainty?
How can DSO be helped to exit the market?
Co-funded by the IEE Programme of the EU
Contract N°: IEE/13/824/SI2.675067
D7.4: Final Conference in Brussels Page 12
• Is there (good) evidence that having retailers as the obligated parties delivers more cost-
effective savings?
• Are any benefits likely to outweigh the costs / risks? What is the evidence for this?
Discussion
Both the UK and France have experience changes to who participates in their EEO - although
neither has changed as radically as the Danish proposal. In France, the extent to which
enterprises could take part in the scheme changed somewhat between phases. In the UK,
there was an experience with including large electricity generators in one phase of the EEO
(2009-2012)- this was not successful and they were removed from future phases. The UK
experience is that any major change equals ‘disaster for at least 8 months’ (in terms of large
reduction in delivered savings in this period).
There might be a ‘third way’ - as in Vermont, putting the obligation on DSO but creating an
energy utility to collect the money and deliver savings. This is something Denmark is
considering.
The general view was that it was very unusual thing to do - to change a scheme so radically.
This is particularly the case at present, when the inclusion of EEOs in EU energy efficiency
policy beyond 2020 is not yet confirmed.
Cost of the transition: there are two Danish studies about this, one official and one
unofficial. There were suggestions that it would be easier / more effective to take greater
control of distributor costs rather than shift the EEO to retailers.
Other options - the NL asked whether anyone has considered shifting the obligation to the
end user? In the NL, this might be an option if retailers are unwilling to be involved in the
EEOs. There has been experience in AT of suppliers very directly passing obligations on to
their customers: ‘if you don’t make savings we will put your energy prices up’.
ESCOs - there has been mixed development of ESCOs, with very little occurring in the UK
(where the EEO is only in the residential sector) but more in France. The French experience
is that more ESCOs arose once suppliers other than just the big gas and electricity
companies were made obligated parties.
There was little support for the change proposed in Denmark, with a straw poll at the end
of the identifying that none of the experts present thought it a good idea.
Co-funded by the IEE Programme of the EU
Contract N°: IEE/13/824/SI2.675067
D7.4: Final Conference in Brussels Page 13
4.3 Deemed savings
Context
In general, deemed savings are applied in many Member States, because of its cost
effectiveness and easiness to use in in case of large volumes of simple and similar measures.
This holds certainly true for the buildings sector.
Question 1. The adequacy of using deemed savings
This depends on the sector we look at:
• Deemed savings are widely used in the residential sector since more quantity of data
are available. Within the residential sector, deemed saving are used to set a starting
point (ex ante evaluation) of electricity and heating consumption per household. The
obtained values are compared to metered values (ex post evaluation).This option is
more inexpensive than having meters installed in every single households.
• As far as the Industrial sector is concerned, deemed savings is less appropriate given the
variability from one industry to another.
• Regarding the transport sector, deemed savings are used too, because it is very
complicated to collect actual savings. But, not many countries deal with measures in
the transport sector.
Participants give examples of additional uses of deemed energy savings beyond the
residential sector. In some cases energy distributors host campaigns in which engineers
calculate the accuracy of deemed savings of industry, an alternative is the set up of a
measurement and verification office where they check the savings estimated in detail by
the individual companies/industry.
Question 2. What do MS use to monitor and check whether deemed savings are accurate?
Trying to obtain accurate and detailed data verify the deemed savings, can get extremely
expensive an complex. The following alternatives can be more cheap:
• To assign deemed savings scores to different types of dwellings/buildings, based on
surveys.
• Use simple and basic data so that the data collection process doesn’t become too
demanding in terms of time and money.
Co-funded by the IEE Programme of the EU
Contract N°: IEE/13/824/SI2.675067
D7.4: Final Conference in Brussels Page 14
Generally speaking MS don’t run these types of monitoring campaigns, because the more
detailed the data we pretend to obtain, the more expensive and time demanding it will get.
Furthermore, the deeper you go on energy issues the more you get into social issues.
Some participants stated that actual consumption doesn’t reflect the total amount of
savings. So, it’s difficult to get good savings results from monitoring campaigns based on a
sample of households.
However, in some countries companies responsible for implementation of saving measures
are forced to monitor 10% of their houses where measures were put into practice.
Quality control of the installers can also be an important aspect.
Question 3. Responsibility for estimating energy savings
There was a general consensus on the fact that governmental agencies and/or bodies
should be in charge of setting initial targets that should be, in further steps, shared and
agreed by relevant stakeholders, like the obligated parties.