5
3/12/2014 DTSS experiences - TunnelTalk http://www.tunneltalk.com/Singapore-Arp04-DTSS-experiences.php 1/5 The good, bad and mixed on the DTSS Apr 2004 Fig 1. Alignment of the DTSS (Deep Tunnel Sewerage System) By early 2004, the six design-build contracts and eight EPBMs engaged on the first phase of the DTSS in Singapore had completed more than 87% (42km) of the 48km alignment. Tunnelling had started in early 2001 and when TunnelTalk visited the project in mid-January 2004, five of the eight TBMs had finished excavation and casting of the final in-situ concrete lining, with its integrated corrosion protective internal membrane, was underway. The sixth and seventh machines were just weeks from holing through as the last of the set continued to struggle through difficult mixed ground conditions in the north. For the most part the 48km alignment divides into two geological zones. The four contracts in the south-east run mostly through old alluvium deposits at up to 50m below the surface and beneath a high ground water table, while the two on the north and west (Contracts T-05 and T-06) run through more challenging hard rock and mixed hard rock/soft ground conditions. On the southern contracts in less permeable old alluvium, the four contractors used soft ground EPBMs with open spoke cutting wheels and operated at pressures up to 3 bar. These four machines of 5.5m to 7.26m in diameter (one from Germany and three from Japan), recorded consistent progress at averages anticipated by the client’s project engineers, the CH2M/ Parsons Brinckerhoff JV, and the design-buiId contractors and their consultants (Table 1). Penta-Ocean believes its 7.7km tunnel on Contract T-02 is the longest drive for a single EPBM of its size. The 7.16m o.d. NKK EPBM achieved a progress best of 602m/month and an overall average of 55m/week, working two 12h shifts/day, six days/week, to complete the 7.7km long drive in just under 35 months. The machine performed well in 65% of the alignment, in quite good sandy conditions, in which only water was required as a conditioning agent to create an effective pressure balancing plug in the 8m long screw. For the other 30%, polymers were needed to create a plug in more permeable, lower standard penetration test (SPT) soils. For SITE REPORT - SINGAPORE TunnelTalk Archive At 48km long, the Phase 1 network of the Deep Tunnel Sewerage System (DTSS) in Singapore passes through much of the island's highly variable geology. Conditions vary from soft compressible clays to loose running sands under high ground water pressures, to zones of very hard, highly abrasive, fresh granite and stretches of completely decomposed rock soils. Conditions change in some cases from metre to metre with menacing mixed faces in-between. All are taxing the skill and abilities of men and machines alike. Shani Wallis, TunnelTalk Editor, reported from Singapore. Contract Contractor Design-build manager Length EPB TBMs Finished dia Award price T-01 Woh Hup/Shanghai Tunnel Babtie BMTHarris & Southerland 5.8km 1 Herrenknecht 6m i.d. S$80.6m T-02 Penta-Ocean Construction Co T Y Lin South-East Asia 7.7km 1 NKK 6m i.d. S$95.6m T-03 Kumagai/SembCorp JV Hyder-Geo-Consultant 5.3km 1 Kawasaki Hl 6m i.d. S$68.8m T-04 Samsung Corporation Meinhardt/Halcrow 7.3km 1 Mitsubishi Hl 4.3m i.d. S$74.2m T-05 Philip Holzmann/SembCorp JV ST Architects & Engineers/Babtie 12.5km 2 Herrenknecht 3.6m i.d. S$139.5m T-06 Ed Züblin Meinhardt/Geoconsult 9.7km 2 Herrenknecht 3.6m i.d. S$91.8m

DTSS Experiences - TunnelTalk

Embed Size (px)

DESCRIPTION

Singapore outfall & tunnel structures

Citation preview

  • 3/12/2014 DTSS experiences - TunnelTalk

    http://www.tunneltalk.com/Singapore-Arp04-DTSS-experiences.php 1/5

    The good, bad and mixed on the DTSS Apr 2004

    Fig 1. Alignment of the DTSS (Deep Tunnel Sewerage System)

    By early 2004, the six design-build

    contracts and eight EPBMs engaged on

    the first phase of the DTSS in

    Singapore had completed more than

    87% (42km) of the 48km alignment.

    Tunnelling had started in early 2001

    and when TunnelTalk visited the

    project in mid-January 2004, five of the

    eight TBMs had finished excavation

    and casting of the final in-situ concrete

    lining, with its integrated corrosion

    protective internal membrane, was

    underway. The sixth and seventh

    machines were just weeks from holing

    through as the last of the set

    continued to struggle through difficult

    mixed ground conditions in the north.

    For the most part the 48km alignment

    divides into two geological zones.

    The four contracts in the south-east

    run mostly through old alluvium

    deposits at up to 50m below the surface and beneath a high ground water table, while the two on the north and

    west (Contracts T-05 and T-06) run through more challenging hard rock and mixed hard rock/soft ground

    conditions. On the southern contracts in less permeable old alluvium, the four contractors used soft ground EPBMs

    with open spoke cutting wheels and operated at pressures up to 3 bar. These four machines of 5.5m to 7.26m in

    diameter (one from Germany and three from Japan), recorded consistent progress at averages anticipated by the

    clients project engineers, the CH2M/ Parsons Brinckerhoff JV, and the design-buiId contractors and their

    consultants (Table 1).

    Penta-Ocean believes its 7.7km tunnel on Contract T-02 is the longest drive for a single EPBM of its size. The

    7.16m o.d. NKK EPBM achieved a progress best of 602m/month and an overall average of 55m/week, working two

    12h shifts/day, six days/week, to complete the 7.7km long drive in just under 35 months.

    The machine performed well in 65% of the alignment, in quite good sandy conditions, in which only water was

    required as a conditioning agent to create an effective pressure balancing plug in the 8m long screw. For the other

    30%, polymers were needed to create a plug in more permeable, lower standard penetration test (SPT) soils. For

    SITE REPORT - SINGAPORE

    TunnelTalk Archive

    At 48km long, the Phase 1 network of the Deep Tunnel Sewerage System (DTSS) in Singapore passes through

    much of the island's highly variable geology. Conditions vary from soft compressible clays to loose running

    sands under high ground water pressures, to zones of very hard, highly abrasive, fresh granite and stretches

    of completely decomposed rock soils. Conditions change in some cases from metre to metre with menacing

    mixed faces in-between. All are taxing the skill and abilities of men and machines alike. Shani Wallis,

    TunnelTalk Editor, reported from Singapore.

    Contract Contractor Design-build manager Length EPB TBMsFinished

    dia

    Award

    price

    T-01 Woh Hup/Shanghai Tunnel Babtie BMTHarris & Southerland 5.8km 1 Herrenknecht 6m i.d. S$80.6m

    T-02 Penta-Ocean Construction Co T Y Lin South-East Asia 7.7km 1 NKK 6m i.d. S$95.6m

    T-03 Kumagai/SembCorp JV Hyder-Geo-Consultant 5.3km 1 Kawasaki Hl 6m i.d. S$68.8m

    T-04 Samsung Corporation Meinhardt/Halcrow 7.3km 1 Mitsubishi Hl 4.3m i.d. S$74.2m

    T-05 Philip Holzmann/SembCorp JVST Architects &

    Engineers/Babtie12.5km 2 Herrenknecht 3.6m i.d. S$139.5m

    T-06 Ed Zblin Meinhardt/Geoconsult 9.7km 2 Herrenknecht 3.6m i.d. S$91.8m

  • 3/12/2014 DTSS experiences - TunnelTalk

    http://www.tunneltalk.com/Singapore-Arp04-DTSS-experiences.php 2/5

    The T-05 south drive Herrenknecht

    a 200m stretch through an outcrop of hard granite on the drive, the TBM required modification. The outcrop was

    discovered during additional site investigation work required by each design-build contractor after contract award

    and before start of construction.

    As a result, modifications were made during

    TBM manufacture as well as on site prior to

    entering into the granite zone. These

    modifications included installation of additional

    arms on the open spoke cutterhead, reduction

    of the cutterheads open ratio, installation of

    six thrust grippers in the forward can of the

    TBM shield, and an increased number of disc

    cutters.

    Design-build contracting

    While a great deal of the design criteria for the

    fully gravity-fed trunk sewer tunnels is fixed,

    the DTSS client team, part of the Singapore

    Governments Public Utilities Board (PUB),

    elected to award the construction contracts on

    a design-buiId basis, "principally to optimise

    the time saving advantages," explained

    Chiang Kok Meng, Director of the PUB DTSS

    Department.

    The scope and size of these large diameter tunnelling contracts is a new undertaking for the PUB. "Under the

    design-build concept, design, manufacture and delivery of the TBMs could progress concurrent with final design,

    saving several months on the overall project schedule. On the down side, as the client, we have less direct

    involvement than is possible under conventional design-bid-build contracts. Nevertheless we are pleased with the

    design-build experience and would follow the same approach for future projects."

    For the design-build contracting teams the room to manoeuvre is limited. The grade and alignment of the tunnels

    is fixed and the use of certain methods such as dewatering is restricted.

    T-06 Herrenknecht (2)

    "To avoid the potential for surface settlement

    we specified the use of positive closed-face

    slurry or EPB tunnelling, and disallowed

    dewatering without explicit approval," said

    Mrs Ang, Deputy Director of the PUB DTSS

    Department. "We also required the design-

    build contractors to undertake further site

    investigation borings, to supplement the

    geological investigation data provided by us

    during contract tender, and for them to

    prepare their own geotechnical interpretive

    report for the purpose of refining the design

    of the selected TBMs, confirming their

    methods for excavation, and for anticipating

    conditions to be encountered. In addition,

    and in all cases, contractors had to have

    their designs reviewed by an independent

    checker before they came to us for final

    checking and approval."

    For the most part the strategy has worked. The incidents of surface settlement above such a long distance of

    tunnelling, through ground conditions of known treacherous nature, and beneath vital surface traffic infrastructure

    has been low and of slight impact - by both Singapore and international standards.

    An incident at a launch shaft as one of the TBMs was mining through the tunnel eye into the drive is the most

    serious event of ground loss to date. It caused a face loss depression on a street some 40m above, which

    resulted in road closure during the night hours to fill the depression and have the road fully available once again

    for the morning rush hour. "We have had no other major face loss incidents and have not caused any major

    settlement of either the roads or the MRT transit network, under which the DTSS tunnels pass several times, said

    Robert Marshall, Project Director for the CM2M/Parsons Brinckerhoff (PB) JV. "Now, with most of the tunnel

    excavation finished, the highest risks of surface settlement are behind us and I believe the record is very good

    given the tunnelling conditions and DTSS tunnel routes"

    Greatest challenge

    The greatest challenge for contractors on the project is the most northerly of the eight tunnel drives. For

    Singapore contractor SembCorp (now fully responsible for the contract following collapse of its joint venture

  • 3/12/2014 DTSS experiences - TunnelTalk

    http://www.tunneltalk.com/Singapore-Arp04-DTSS-experiences.php 3/5

    T-02 NKK

    partner Philipp Holzmann in 2002) progress

    on Contract T-05 using two 4.93m

    Holzmann-procured Herrenknecht-supplied

    rock-face EPBMs has been particularly slow

    due to exceptional geological conditions.

    The North Drive in particular was running

    almost two years behind schedule when

    TunnelTalk visited in January 2004.

    One of the most difficult aspects is that the

    fixed tunnel horizon runs along the highly

    undulating interface between peaks of very

    hard, massive fresh granite, of recorded

    compressive strengths of 200MPa-30OMPa,

    and valleys of weathered to completely

    decomposed granite soils under a full head

    of up to 52m hydrostatic ground water

    pressure. "With a fixed gravity flow

    alignment we cannot move either deeper

    into more consistent hard rock conditions,

    or higher into longer reaches of soft ground conditions," said David Helliwell, Construction Manager for SembCorp.

    "As it is, the machine can drive out of an almost vertical interface of hard rock into a full face of water-charged

    decomposed soils. To avoid over-excavating the running soil, the TBM operator must change immediately from

    non-pressurised operations in full-face rock, to full EPB operation at the first indications of soft ground in the face.

    The same then applies in reverse."

    Also, the granite is highly abrasive. Discs break on impact with hard massive rock ledges in mixed faces, and

    others are worn into several flat spots by being jammed and released in succession by chips of hard, massive rock

    lodging in the housings. Interventions into the excavation chamber to replace worn discs can be as frequent as

    every stroke, with an inspection at least after every fourth ring or 4.8m.

    T-03 Kawasaki

    On Contract T-05, a large percentage of

    these interventions must be carried out in

    compressed air to the maximum 3.4 bar

    pressures allowable by Singapore law.

    Hydrostatic pressures have been higher

    however and on one occasion, ground

    freezing was required to provide stable

    enough conditions for an intervention.

    Maintenance has also required repair of

    excessive wear on the screw conveyor,

    cutterhead and body structure.

    Work has also been needed to strengthen

    the cutterhead support struts against fatigue

    caused by the high thrust pressures used to

    penetrate the rock and high torque

    encountered in the soft and mixed face

    conditions. "At the start of the project we

    did not expect to need such frequent

    interventions," said Tay Ching Khiang,

    Project Manager for SembCorp. "Also, most of the interventions we expected to undertake in free air in zones of

    full faces of rock. The reality has been at the other extreme."

    TBM design

    With no room on the forward bulkhead of the 4.93m diameter direct variable frequency electric drive TBM for

    modular air locks, a secondary bulkhead is located at the back of the 12m long leading shield can, just ahead of

    the segment erector and ring build area. The space between this and the leading bulkhead is the single large air

    lock. Through this, a maximum three workers can pass through into the forward chamber, as well as be

    decompressed back into free air. This is a major consumer of time, since at the maximum 3.4 bar working pressure

    and according to the German compressed air working tables that are being used, a maximum of 2hr working

    requires a minimum 3hr 49min in decompression, which provides for a maximum possible 8hr of working in each

    24hr period of man-entry intervention compressed air operation.

    To avoid the time and cost of having to apply ground freezing to execute interventions, the contractor applied for

    controlled dewatering along the alignment to lower the ground water and reduce hydrostatic pressures to the

    within the maximum 3.4 bar man-entry pressure.

    "Given the circumstances and the logistics of the alignment in this not so heavily urbanised area of the island, we

  • 3/12/2014 DTSS experiences - TunnelTalk

    http://www.tunneltalk.com/Singapore-Arp04-DTSS-experiences.php 4/5

    T-04 Mitsubishi

    agreed to strictly controlled dewatering at

    certain zones along the route of the most

    troubled North Drive," said Marshall for

    CH2M/PB and the client. "In addition, the

    tunnel route was moved horizontally within

    the easement under the 6-lane Seletar

    Expressway closer to the verge to allow for

    the installation of a limited number of

    dewatering wells and away from potentially

    more serious impacts of any dewatering-

    induced settlement. Tunnel alignment was

    also adjusted to allow otherwise offset

    access shafts to be directly overhead and

    create further opportunities for easier TBM

    wear repairs in free air."

    While the South Drive machine of the two

    identical Contract T-05 TBMs has struggled

    on in its original configuration to finish its

    shorter 4.8km long South Drive, conditions on the much longer 7.6km North Drive proved too onerous. In

    September 2003, the contractor decided to retrieve the machine from an intermediate shaft and undertake a

    major refurbishment that took two months. "Among other things, we fitted a longer screw conveyor and fitted a

    new, more abrasive resistant cutterhead with larger openings to help clear the spoil from the front," said Helliwell.

    T-01 Herrenknecht

    The new cutterhead, it was said, has shown

    a much-improved performance in the rapidly

    changing conditions. Reports from Singapore

    confirmed that the South Drive - scheduled

    for a hole-through in March 2004 when

    TunnelTalk visited in January 2004 - did

    actually hole-through on 8 March. Meanwhile,

    by late March, the North Drive had added

    about 600m since the start of the year. It

    had passed through another three sections

    of very abrasive, mixed face material, which

    required another complete replacement of

    screw conveyor due to wear. By the end of

    March, and with the ground conditions

    remaining highly variable, the TBM was some

    3.6km into the 7.6km long drive with 4km to

    go.

    On Contract T-06, through conditions that

    also required hard rock EPB TBM excavation,

    contractor Zblin made better progress. By January 2004, with one drive finished and the other about to hole

    through, the contracts two 4.48m Herrenknecht rock EPBMs had recorded a best monthly advance of 625m on its

    North Drive and an average weekly rate for both machines of 59m and 55m respectively. Conditions included full

    faces of both hard granite rock and soft decomposed granite soils but with a significantly lower percentage of

    mixed face conditions.

    The Contract T-05 North Drive is the tunnel causing undoubtedly the most delay to the project but fortunately it is

    the most northerly drive. The client will be able to commission the lower reaches of the network once they are

    complete and the network of new higher-level interceptor feeder sewers are commissioned.

    Protective inner lining

    As the T-05 North Drive is left to battle on, all other contractors are well into the final stages of casting the inner

    membrane-protected in-situ final lining. As part of the owner's 100-year maintenance-free design life criteria, the

    corrosion protection PVC or HDPE membrane must be applied integral with the cast concrete. For each contract,

    different methods of casting this lining are being applied. Some are casting the 330 membrane-protected arch

    first, and coming back to cast the invert, while others are casting the invert first and the arch as the second pass.

    The contractors have selected HDPE membrane from either AGRU of Austria, Steuler of Germany, or Engineered

    Linings of South Africa. "The key to effective membrane installation is to place enough tension on the tough

    inflexible minimum 2.5mm thick material as it lies draped over the arch shutter before starting the pour" said Owen

    Griffiths, CH2M/PB's Resident Engineer on Penta-Ocean's Contract T-02. "Otherwise ripples will form and sections

    of the membrane will have to be cut out and reinstalled."

    Only on Contracts T-02 and T-04 have contractors Penta-Ocean and Samsung elected to cast the final lining using

    a full round telescopic shutter. When on site, Penta-Ocean project manager, Nakayama, showed TunnelTalk an

  • 3/12/2014 DTSS experiences - TunnelTalk

    http://www.tunneltalk.com/Singapore-Arp04-DTSS-experiences.php 5/5

    Current Stay Connected Market Place Home Office Alert

    A completed section of the membrane-protected in-situ

    concrete final lining of the 6m i.d. tunnel on Contract T-01,

    with the 30 invert section yet to be cast as a second pass

    illustration of the two 37.5m long

    Japanese-manufactured shutters that

    were at the time being assembled at the

    mid-point of the 7.7km long tunnel. He

    described how the invert element will hold

    the membrane in tension while the full

    round lining will be cast to the tunnel's

    final 6m finished diameter. Hopes were

    high that the system, and the two

    shutters, would allow the lining to

    progress at up to 1,000m/month.

    One down, Phase 2 to go

    Back in 1999, keen international

    competition for the DTSS design-build

    contracts attracted between 10 and 12

    tenders for each, resulting in very

    competitive prices. Few of the bids

    received exceeded the projects budget

    estimates. Under the design-build

    procurement strategy and once

    completed, the owner of the DTSS will

    have acquired a 48km system of large diameter, 100-year design life infrastructure at a total contract bid price

    cost of US$329 million. This is within a project total of US$2 billion that includes a new high capacity treatment

    plant and a 5km long outfall comprising two 3m i.d. precast concrete pipes installed in sea bed trenches off the

    south east coast of the island.

    Phase 2 of the DTSS on the south-west side of the island comprises another planned network of deep level

    tunnels with another large treatment plant and outfall structure. It is scheduled for construction after 2015 - long

    after the current Phase 1 experiences have passed into the archive of Singapore's quite particular tunnelling

    history.

    Search Forward Back to top Archive Feedback Print

    2008-2014 TunnelTalk.com All rights reserved.