82
1 Water for All:Conserve, Value, Enjoy Deep Tunnel Sewerage System (DTSS) Phase 2 18 February 2016 Tunnelling & Underground Construction Society (Singapore) Woo Lai Lynn DTSS Phase 2 Project Unit Deputy Project Director Ganeshan BV+AECOM Joint Venture Manager (Tunnels) Disclaimer: The information provided in this presentation is correct at the time of presentation and is subject to change. We do not warrant the adequacy or completeness of the presentation and expressly disclaim liability for any error or omission in the presentation.

Deep Tunnel Sewerage System (DTSS) Phase 2

Embed Size (px)

Citation preview

Page 1: Deep Tunnel Sewerage System (DTSS) Phase 2

1

Water for All: Conserve, Value, Enjoy

Deep Tunnel Sewerage System (DTSS) Phase 2

18 February 2016

Tunnelling & Underground Construction Society (Singapore)

Woo Lai Lynn

DTSS Phase 2 Project Unit

Deputy Project Director

Ganeshan

BV+AECOM Joint Venture

Manager (Tunnels)

Disclaimer:

The information provided in this presentation is correct at the time of presentation and is

subject to change. We do not warrant the adequacy or completeness of the presentation and

expressly disclaim liability for any error or omission in the presentation.

Page 2: Deep Tunnel Sewerage System (DTSS) Phase 2

Commentary for Introduction slide

The presentation attached was delivered at the Tunnelling and Underground

Construction Society (Singapore) (TUCSS) Monthly Seminar on 18 Feb 2016.

With focus on the DTSS Phase 2 Conveyance system, the intent of the

presentation was to provide a brief introduction of the key features of our DTSS

Phase 2 Deep Tunnels to TUCSS participants as well as contractors/consultants

who might be interested in participating in our project.

The presentation was jointly presented by :

Ms Woo Lai Lynn – Deputy Project Director for DTSS Phase 2 Project Unit,

PUB, the National Water Agency

Dr Ganeshan Vallipuram – Manager (Tunnels),

BV&AECOM Joint Venture, PUB’s appointed consultant for DTSS Phase 2 Project

Unit

Page 3: Deep Tunnel Sewerage System (DTSS) Phase 2

33

Outline

• Background of Singapore’s Deep Tunnel Sewerage System (DTSS)

• Benefits of DTSS

• DTSS Phase 1

• DTSS Phase 2

• DTSS Phase 2 key features

Page 4: Deep Tunnel Sewerage System (DTSS) Phase 2

Commentary for Outline

This slide provides the outline of the presentation by Ms Woo Lai Lynn.

Page 5: Deep Tunnel Sewerage System (DTSS) Phase 2

Jurong WRP

Ulu Pandan WRP

Kranji WRP

Seletar WRP

Kim Chuan WRP

Bedok WRP

Water Reclamation PlantsWater Reclamation PlantsWater Reclamation PlantsWater Reclamation Plants

Used Water System Before DTSS

• 6 Water Reclamation Plants (WRPs) and

• >130 Sewage Pumping Stations

Page 6: Deep Tunnel Sewerage System (DTSS) Phase 2

Commentary for Used Water System Before DTSS

The used water system before DTSS consisted of 6 Water Reclamation Plants

(WRPs) and more than 130 sewage pumping stations scattered throughout the

island.

Page 7: Deep Tunnel Sewerage System (DTSS) Phase 2

How DTSS Works

Phase out existingpumping stations

Page 8: Deep Tunnel Sewerage System (DTSS) Phase 2

Commentary for How DTSS Works

Before DTSS, our sewerage system consisted of a network of gravity sewers

conveying used water to the water reclamation plants via multiple intermediate

pumping stations. With the introduction of DTSS, these intermediate pumping

stations scattered all over the island can be phased out and be replaced with a

single large diameter tunnel which conveys used water flow purely by gravity.

The used water is pumped up only once at the centralized pumping station

located at the WRP for treatment.

Page 9: Deep Tunnel Sewerage System (DTSS) Phase 2

9

• Link Sewers convey used water from existing sewerage network to the Deep

Tunnels

• Used water flows by gravity through the deep sewer tunnels to centralisedWater Reclamation Plants

• Treated used water will be channelled to the NEWater plant for further purification or discharged through the outfall

Deep Tunnel Sewers

Link Sewers

Outfall

Water Reclamation Plant

How DTSS Works

Page 10: Deep Tunnel Sewerage System (DTSS) Phase 2

Commentary for How DTSS Works

How does the DTSS works

• Link Sewers convey used water from existing sewerage network to the Deep

Tunnels

• Used water flows by gravity through the deep sewer tunnels to centralised

Water Reclamation Plants

• Treated used water will be channelled to the NEWater plant for further

purification or discharged through the outfall

Page 11: Deep Tunnel Sewerage System (DTSS) Phase 2

11

Benefits:

- More cost effective

- Free up valuable land

- Ensures sustainability of NEWater

- Robust, Reliable and Resilient

Benefits of DTSS

Existing WRPs & Pumping Stations – 300 ha

Page 12: Deep Tunnel Sewerage System (DTSS) Phase 2

Commentary for Benefits of DTSS

The DTSS brings about many benefits:

- It is more cost-effective than continually renewing and expanding existing

used water infrastructure;

- It frees up valuable land for other high value development;

- It ensures adequate conveyance and treatment capacity to meet Singapore’s

long term water needs

- It provides a more robust, reliable and resilient used water system.

Page 13: Deep Tunnel Sewerage System (DTSS) Phase 2

1313

Kranji WRP

& NEWater Factory

Changi WRP

& NEWater Factory

DTSS Phase 2

DTSS Phase 1

Deep Tunnel Sewerage System (DTSS)

Long-Term Used Water System (Phase 1 & 2)

• Used water superhighway to meet Singapore’s long-term needs

Tuas WRP

& NEWater Factory

Page 14: Deep Tunnel Sewerage System (DTSS) Phase 2

Commentary for Deep Tunnel Sewerage System (DTSS)

A superhighway for used water management, the Deep Tunnel Sewerage System

(DTSS) is an efficient and cost-efficient solution conceived by PUB to meet

Singapore’s long-term needs for used water collection, treatment, reclamation

and disposal. DTSS was envisaged to be implemented in two phases.

Page 15: Deep Tunnel Sewerage System (DTSS) Phase 2

1515

Kranji WRP

& NEWater Factory

Changi WRP

& NEWater Factory

DTSS Phase 1

Deep Tunnel Sewerage System (DTSS)

DTSS Phase 1 (2000 – 2008)

48km tunnels (3.3m to 6m ID)

60km link sewers (0.3m to 3m ID)

176MGD plant at Changi

5km outfall (3m ID)

Page 16: Deep Tunnel Sewerage System (DTSS) Phase 2

Commentary for Deep Tunnel Sewerage System (DTSS)

DTSS Phase 1 was completed in 2008 and consisted of

• 48km of tunnels

• 60km link sewers, and

• A 176MGD plant at Changi with outfall

Page 17: Deep Tunnel Sewerage System (DTSS) Phase 2

1717

Kranji WRP

& NEWater Factory

Changi WRP

& NEWater Factory

Tuas WRP

& NEWater Factory

Industrial Tunnel

South Tunnel

Deep Tunnel Sewerage System (DTSS)

South Spur Tunnel

DTSS Phase 2

40km tunnels (3m to 6m ID)

60km link sewers (0.3m to 3m ID)

176MGD plant at Tuas with

25MGD NEWater capacity

Project started in 2014

BV+AECOM Joint Venture

appointed as overall project

manager

Page 18: Deep Tunnel Sewerage System (DTSS) Phase 2

Commentary for Deep Tunnel Sewerage System (DTSS)

• DTSS Phase 2 consists of

• 40km of tunnels with internal diameters of 3m to 6m;

• 60km link sewers with internal diameters of 0.3m to 3m, and

• A 176MGD plant at Tuas with a 25MGD NEWater capacity.

• The DTSS Phase 2 project started in 2014 with the appointment of BV+AECOM

Joint Venture as overall project manager.

Page 19: Deep Tunnel Sewerage System (DTSS) Phase 2

19

DTSS Phase 2 Project | 19 Jan 2016

19

Scope of Tunnelling Works

• 50km of tunnelling works delivered via D&B contracts

• Tunnel ID ranges from 3m to 6m

• Includes construction of hydraulic structures & air management

facilities

Industrial

Tunnel

South Tunnel

Northwest

Link Sewer Tunnel

Southern Region

Link Sewer Tunnel

Pasir Panjang

Link Sewer Tunnel

Holland Link Sewer Tunnel

South Spur

Page 20: Deep Tunnel Sewerage System (DTSS) Phase 2

Commentary for Scope of Tunnelling Works

All 40km of Deep Tunnels and 10km of the larger diameter Link Sewers will be

constructed using Tunnel Boring Machines (TBM) via Design & Build (D&B)

contracts. The 50km of tunnelling works include:

• South Tunnel;

• South Spur Tunnel;

• Industrial Tunnel;

• Northwest Link Sewer;

• Pasir Panjang Link Sewer;

• Holland Link Sewer, and

• Southern Region Link Sewer

• In addition to the TBM tunnelling works, the contracts will also include the

construction of hydraulic structures and air management facilities.

Page 21: Deep Tunnel Sewerage System (DTSS) Phase 2

21

DTSS Phase 2 Project | 19 Jan 2016

21

Scope of Pipe-jacking Works

• 50km of pipe-jacking works delivered via DBB contracts

• Pipe ID ranges from 0.3m to 3m

Page 22: Deep Tunnel Sewerage System (DTSS) Phase 2

Commentary for Scope of Pipe-Jacking Works

The remaining 50km of smaller diameter Link Sewers will be constructed by

pipe-jacking via conventional Design-Bid-Build (DBB) contracts.

Page 23: Deep Tunnel Sewerage System (DTSS) Phase 2

2323

DT

SS

2

CO

NT

RA

CT

P

AC

KA

GI

NG

C3

C5

Contract Tunnel LengthTunnel Internal

Diameter

C1 10km 6.0m

C2 12km 3.3 - 4.0m

C3 8km 6.0m

C4 8km 3.5 - 6.0m

C5 12km 3.0 - 3.3m

Total 50km

Tunnel Contract Packaging

Page 24: Deep Tunnel Sewerage System (DTSS) Phase 2

Commentary for Tunnel Contract Packaging

The tunnel construction is expected to be let out in several contracts. This slide

shows how the tunnel contracts may be packaged.

Page 25: Deep Tunnel Sewerage System (DTSS) Phase 2

25

Pre-tender Qualification

C4 Tender

Contractor #1 Contractor #2 Contractor #3

Batch 2

D&B Contracts

Contractor #4

C5 Tender

Contractor #5

Tunnel Contract Packaging

C3 TenderC2 TenderC1 Tender

Batch 1

D&B Contracts

Page 26: Deep Tunnel Sewerage System (DTSS) Phase 2

Commentary for Tunnel Contract Packaging

There will be a pre-tender qualification exercise where interested contractors

can apply to be pre-qualified to tender for the subsequent D&B construction

tenders. These construction tenders will be let out in two batches

Page 27: Deep Tunnel Sewerage System (DTSS) Phase 2

27

Link Sewer Contract Packaging

Page 28: Deep Tunnel Sewerage System (DTSS) Phase 2

Commentary for Link Sewer Contract Packaging

The pipe-jack Link Sewer contracts are divided by areas as shown on this slide.

Page 29: Deep Tunnel Sewerage System (DTSS) Phase 2

29

Detailed Design

Consultant Tender

Area #1

3 Contracts

Area #2

4 Contracts

Link Sewer Contract Packaging

DDC Package 1 DDC Package 2 DDC Package 3

Construction Tender

Area #3

6 Contracts

Construction Tender

Area #4

3 Contracts

Area #5

2 Contracts

Construction Tender

Page 30: Deep Tunnel Sewerage System (DTSS) Phase 2

Commentary for Link Sewer Contract Packaging

As these pipe-jack Link Sewer contracts are DBB contracts, detailed design

consultants have to be first appointed before the construction tenders are let

out. It is envisaged that about 3 detailed design consultants will be appointed.

Subsequently, a number of construction contracts will be called. This slide shows

an example of how the Link Sewer contracts may be packaged.

Page 31: Deep Tunnel Sewerage System (DTSS) Phase 2

31

Water for All: Conserve, Value, Enjoy

Deep Tunnel Sewerage System (DTSS) Phase 2Tunnelling & Underground Construction Society (Singapore)

Ganeshan

BV+AECOM Joint Venture

Manager (Tunnels)

Page 32: Deep Tunnel Sewerage System (DTSS) Phase 2

Commentary for Introduction Page for Dr Ganeshan’s section

This section is presented by Dr Ganeshan from BV+AECOM Joint Venture.

Page 33: Deep Tunnel Sewerage System (DTSS) Phase 2

3333

DTSS Phase-2 Key Features• Geology

• Tunnel Inspection

• Tunnel Monitoring

• Air Management

• Tunnel Isolation

• BIM

• IDMS

Page 34: Deep Tunnel Sewerage System (DTSS) Phase 2

Commentary for Outline for DTSS Phase-2 Key Features

This slide provide the outline of the presentation by Dr Ganeshan.

Page 35: Deep Tunnel Sewerage System (DTSS) Phase 2

35

Geological Formation: DTSS Ph-1 & Ph-2

Page 36: Deep Tunnel Sewerage System (DTSS) Phase 2

Commentary for Geological Formation: DTSS Ph-1 & Ph-2

This slide shows the Geological Map of Singapore.

While DTSS Phase 1 was constructed mostly in Bukit Timah, Phase 2 is expected

to be in Jurong Formation.

Page 37: Deep Tunnel Sewerage System (DTSS) Phase 2

37

DTSS Phase 2 Project |

37

21

September2015Geological Formation along Proposed Alignment

Page 38: Deep Tunnel Sewerage System (DTSS) Phase 2

Commentary for Geological Formation along Proposed Alignment

This slide show the general geological formation expected along the DTSS Phase

2 alignment.

Page 39: Deep Tunnel Sewerage System (DTSS) Phase 2

39

DTSS Phase 2 Project |

39

EX

PE

RT

P

AN

EL

P

RE

SE

NT

AT

IO

N

Ground level

Jurong Formation (Soil)

S(VI), S(V), S(IV)

Jurong Formation (Rock)

S(III), S(II), S(I)

Fill

Tunnel Alignment (fully in rock)

21

September2015Typical Geological Profile along Tunnel Alignment

Page 40: Deep Tunnel Sewerage System (DTSS) Phase 2

Commentary for Typical Geological Profile along Tunnel Alignment

The DTSS Phase 2 tunnel is expected to go through rock.

Page 41: Deep Tunnel Sewerage System (DTSS) Phase 2

41

DTSS Phase 2 Project |21 September

2015

41

Tunnel Alignment FillJurong Formation (Soil)

S(VI), S(V), S(IV)

Jurong Formation (Rock)

S(III), S(II), S(I)

Tunnel Alignment (fully in soil)

Typical Geological Profile along Tunnel Alignment

Page 42: Deep Tunnel Sewerage System (DTSS) Phase 2

Commentary for Typical Geological Profile along Tunnel Alignment

The DTSS Phase 2 tunnel is also expected to go through soil.

Page 43: Deep Tunnel Sewerage System (DTSS) Phase 2

43

DTSS Phase 2 Project |21 September

2015

43

Jurong Formation (Soil)

S(VI), S(V), S(IV)

Jurong Formation (Rock)

S(III), S(II), S(I)

Fill

Tunnel Alignment (mixed ground)

Typical Geological Profile along Tunnel Alignment

Page 44: Deep Tunnel Sewerage System (DTSS) Phase 2

Commentary for Typical Geological Profile along Tunnel Alignment

There will also be many locations where the DTSS Phase 2 tunnel will encounter

mixed face conditions.

Page 45: Deep Tunnel Sewerage System (DTSS) Phase 2

45

Tunnel Inspection

Page 46: Deep Tunnel Sewerage System (DTSS) Phase 2

Commentary for Tunnel Inspection

The DTSS Phase 2 Tunnel will be designed with provisions for tunnel inspection

by Remotely Operated Vehicles (ROVs).

Page 47: Deep Tunnel Sewerage System (DTSS) Phase 2

47

Shaft – Tunnel Connections

Page 48: Deep Tunnel Sewerage System (DTSS) Phase 2

Commentary for Shaft – Tunnel Connections

Previously, in DTSS Phase 1, there were a mixture of off-line and on-line shafts.

To facilitate the launching of ROVs, DTSS Phase 2 Tunnels will have only on-line

shafts.

Page 49: Deep Tunnel Sewerage System (DTSS) Phase 2

49

Singapore DTSS Phase 2

Project |2 May 2014

49

Longitudinal installation :Fibre optic cables cast directly into CPL during its construction

Fibre Optic Strain Monitoring for Structural Integrity

Page 50: Deep Tunnel Sewerage System (DTSS) Phase 2

Commentary for Fibre Optic Strain Monitoring for Structural Integrity

As an added feature, DTSS Phase 2 will also explore the use of fibre optic cables

cast into the tunnel lining for structural integrity monitoring.

Page 51: Deep Tunnel Sewerage System (DTSS) Phase 2

51

Fibre Optic Strain Monitoring for Structural Integrity

Page 52: Deep Tunnel Sewerage System (DTSS) Phase 2

Commentary for Fibre Optic Strain Monitoring for Structural Integrity

This slide shows a typical fibre optic setup to monitor the structural integrity of

the tunnel.

Page 53: Deep Tunnel Sewerage System (DTSS) Phase 2

53

MIC

Resistant

Concrete

MIC - Micro-organism Induced Corrosion

Tunnel Cross Section - General

Page 54: Deep Tunnel Sewerage System (DTSS) Phase 2

Commentary for Tunnel Cross Section- General

The DTSS Phase 2 Tunnel will feature a secondary lining consisting of MIC

resistant concrete with HDPE lining.

Page 55: Deep Tunnel Sewerage System (DTSS) Phase 2

55

Tunnel Cross Section - Under Sea Crossings

Page 56: Deep Tunnel Sewerage System (DTSS) Phase 2

Commentary for Tunnel Cross Section- Under Sea Crossings

For undersea crossings, a waterproof membrane may be incorporated to ensure

water-tightness.

Page 57: Deep Tunnel Sewerage System (DTSS) Phase 2

57

Air Flow in Tunnel

Odour Control

Facility

OCF

Odour Control

Facility

OCF

Air

Jumper

AJ

Page 58: Deep Tunnel Sewerage System (DTSS) Phase 2

Commentary for Air Flow in Tunnel

The tunnel conveys both used water and air. To control the flow of this air and to

prevent any odour nuisance, air management facilities will be installed wherever

link sewers connect to the tunnel. These air management facilities consist of

both Odour Control Facilities (OCFs) and Air Jumpers (AJs).

Page 59: Deep Tunnel Sewerage System (DTSS) Phase 2

59

DTSS Phase 2 Project |

59

EX

PE

RT

P

AN

EL

P

RE

SE

NT

AT

IO

N

21

September2015

• Withdraws Air from both Link Sewer and Tunnel, Treats & Releases

Air from

Tunnel

Treated air from OCF

Drop Structure & Odour Control Facility

Air from

Link Sewer

Page 60: Deep Tunnel Sewerage System (DTSS) Phase 2

Commentary for Drop Structure & Odour Control Facility

The odour control facility draws air from both link sewer and tunnel and treats

the air before releasing it back to the atmosphere.

Page 61: Deep Tunnel Sewerage System (DTSS) Phase 2

61

DTSS Phase 2 Project |

61

EX

PE

RT

P

AN

EL

P

RE

SE

NT

AT

IO

N

21

September2015

• Negative pressure in tunnel may not be sufficient to pull incoming link sewer air.

• Air Jumper force the air into tunnel

Air into

the

tunnel

Air from Link

Sewer

Drop Structure & Air Jumper

Page 62: Deep Tunnel Sewerage System (DTSS) Phase 2

Commentary for Drop Structure & Air Jumper

An Air Jumper serves as forced ventilation to prevent air from the link sewer or

tunnel from escaping into the surroundings.

Page 63: Deep Tunnel Sewerage System (DTSS) Phase 2

63

Shafts - Gated

Page 64: Deep Tunnel Sewerage System (DTSS) Phase 2

Commentary for Shafts - Gated

Another new feature in the DTSS Phase 2 tunnel is the ability to isolate sections

of the tunnel using gates. This slide shows how a gated shaft will look like.

Page 65: Deep Tunnel Sewerage System (DTSS) Phase 2

65Tu

nn

el

I

so

la

ti

on

G

at

es

Si

ng

le

G

at

e

65

Singapore DTSS Phase 2

Project |14 August 2015Roller Gates

Page 66: Deep Tunnel Sewerage System (DTSS) Phase 2

Commentary for Roller Gates

A gate can be lowered in the shaft to block flow in the tunnel.

Page 67: Deep Tunnel Sewerage System (DTSS) Phase 2

67

67

Singapore DTSS Phase 2

Project |14 August 2015Roller Gates

Page 68: Deep Tunnel Sewerage System (DTSS) Phase 2

Commentary for Roller Gates

The gates to be used in the tunnel will be roller gates. This slide shows an

example of one such roller gate.

Page 69: Deep Tunnel Sewerage System (DTSS) Phase 2

69

� Example: Large sectional drop-in gates used for isolation within combined sewer tunnel conveyance system

69

McCook Reservoir Tunnel, Chicago

(TARP)

• Twin 9.0 x 7.6m gates

• The shaft depth is approx 90 m.

• Each gate is formed of three panels

Singapore DTSS Phase 2

Project |Roller Gates Assembled from 3 Modules

Page 70: Deep Tunnel Sewerage System (DTSS) Phase 2

Commentary for Roller Gates Assembled from 3 Modules

As the gates may be very large, they will be assembled from several modules. The

slide shows an example of such a gate made up of 3 modules.

Page 71: Deep Tunnel Sewerage System (DTSS) Phase 2

71

71

Tu

nn

el

I

so

la

ti

on

G

at

es

Mo

du

la

r

Ga

te

A

ss

em

bl

ySingapore DTSS Phase 2

Project |14 August 2015Roller Gates Assembled from 3 Modules

Page 72: Deep Tunnel Sewerage System (DTSS) Phase 2

Commentary for Roller Gates Assembled from 3 Modules

The slide shows how a single module of the gate may look like.

Page 73: Deep Tunnel Sewerage System (DTSS) Phase 2

73

BIM……. BEYOND 3D

DTSS Phase 2 BIM Execution Plan is to

Require all Design Consultants to Use a

Common “Data Scheme”.

This Scheme Combines Both Uniclass 2015

and COBie Standard Deliverables.

…….ASSET MANAGEMENT

Page 74: Deep Tunnel Sewerage System (DTSS) Phase 2

Commentary for BIM Beyond 3D

Building Information Modelling (BIM) will be an mandatory requirement for

DTSS Phase 2.

Page 75: Deep Tunnel Sewerage System (DTSS) Phase 2

75

DTSS Phase 2 Project | 4 February 2015

75

BIM - 3D

Page 76: Deep Tunnel Sewerage System (DTSS) Phase 2

Commentary for BIM – 3D

This slide shows an example of 3D BIM used in designing different sections of the

DTSS Phase 2 tunnel

Page 77: Deep Tunnel Sewerage System (DTSS) Phase 2

77

DTSS Phase 2 Project | 4 February 2015

77

Integrated Data Management System (IDMS)

During Construction;

1. Monitored Instrumentation Data,

2. Critical TBM Operational Data,

3. Current TBM Location

4. Completed Tunnel Rings,

5. Shaft Excavation Depth,

6. and other information

are brought on a web based visual platform

for all parties to have real time information

Page 78: Deep Tunnel Sewerage System (DTSS) Phase 2

Commentary for Integrated Management System (IDMS)

An Integrated Data Management System will also be introduced in the DTSS

Phase 2 project for the tracking of construction data so that all parties will be

updated with real time information on the progress of the construction and

associated instrumentation readings.

Page 79: Deep Tunnel Sewerage System (DTSS) Phase 2

79

THANK YOU

Page 80: Deep Tunnel Sewerage System (DTSS) Phase 2

Commentary

End of Presentation

Page 81: Deep Tunnel Sewerage System (DTSS) Phase 2

81

Singapore International Water Week (SIWW)

The Global Platform to Share and The Global Platform to Share and The Global Platform to Share and The Global Platform to Share and

CoCoCoCo----Create Innovative Water SolutionsCreate Innovative Water SolutionsCreate Innovative Water SolutionsCreate Innovative Water Solutions2012012012016666• Singapore’s Water-Energy-Waste Nexus Journey Booth

Date: 11 Jul (Mon) – 13 Jul (Wed)

Venue: The Marina Bay Sands, Basement 2

• Deep Tunnel Sewerage System Forum

Date: 13 Jul (Wed)

Time: 9.30 am – 12 pm

Venue: The Marina Bay Sands, Basement 2

Visit our site for more info on DTSS: http://www.pub.gov.sg/dtss

Page 82: Deep Tunnel Sewerage System (DTSS) Phase 2

Commentary for Singapore International Water Week (SIWW)

DTSS Phase 2 project team welcomes contractors/consultants who are

interested in participating in our DTSS Phase 2 project to visit the DTSS booth

and forum during SIWW from 11 – 13 July 2016.