Upload
hoangduong
View
219
Download
3
Embed Size (px)
Citation preview
Print Date 04/04/2017
ORIGINAL ISSUE DATE 1 June 2015
VERSION / DATE OF ISSUE 27 / March 2017
Page 1 of 26
DOC # DRA_
Printed copies created from this document are deemed to be uncontrolled
Anglo Coal (Drayton Management) Pty Ltd Policies and Procedures
Pollution and Incident Response Management Plan
Drayton Management System Standard
Pollution and Incident Response Management Plan
This document is controlled whilst it remains in the Drayton Intranet
Printed copies created from this document are deemed to be uncontrolled
Print Date 04/04/2017
ORIGINAL ISSUE DATE 1 June 2015
VERSION / DATE OF ISSUE 27 / March 2017
Page 2 of 26
DOC # DRA_
Printed copies created from this document are deemed to be uncontrolled
Revisions
Issue Issue Date Author Reviewer Authoriser
1 11 June 2015 KIRSTIN BLAIKIE JAMES BENSON PETER FORBES
2 11 February 2016 KIRSTIN BLAIKIE JAMES BENSON PETER FORBES
3 27 March 2017 JASON MARTIN MATT LORD DARREN PISTERS
Annual PIRMP Test History
Revision Test Date Tested by Action
1 11 August 2014 B York Original document posted to website
2 11 June 2015 K Blaikie Major amendment
3 11 February 2016 B York Minor amendment (audit recommendation)
4 27 March 2017 M Lord Major amendment (mine closure)
Print Date 04/04/2017
ORIGINAL ISSUE DATE 1 June 2015
VERSION / DATE OF ISSUE 27 / March 2017
Page 3 of 26
DOC # DRA_
Printed copies created from this document are deemed to be uncontrolled
Distribution List
Distributed to:
Mine Manager’s Office (current originals)
All Drayton Employees via Email or Toolbox Talks
Administration Central File (originals of previous versions)
Print Date 04/04/2017
ORIGINAL ISSUE DATE 1 June 2015
VERSION / DATE OF ISSUE 27 / March 2017
Page 4 of 26
DOC # DRA_
Printed copies created from this document are deemed to be uncontrolled
Table of Contents
1 BACKGROUND ............................................................................................................ 6
1.1 Purpose .............................................................................................................. 6
1.2 Objectives .......................................................................................................... 6
1.3 Scope ................................................................................................................. 7
1.4 Responsibilities .................................................................................................. 7
1.5 Definitions .......................................................................................................... 8
2 REGULATORY FRAMEWORK ..................................................................................... 8
3 PREMESIS DETAILS .................................................................................................. 12
3.1 Site Details ....................................................................................................... 12
3.2 Major Hazards .................................................................................................. 12
3.3 Chemicals and Potential Pollutant Inventory ..................................................... 16
4 MANAGEMENT AND RESPONSIBILITIES ................................................................. 18
4.1 Legal Duty to Notify .......................................................................................... 18
4.2 Relevant Site Contacts ..................................................................................... 19
5 INCIDENT MANAGEMENT ......................................................................................... 20
5.1 Emergency Response ...................................................................................... 20
5.2 Preventative Controls ....................................................................................... 20
6 NOTIFICATION PROCEDURES ................................................................................. 21
6.1 Determination of Material Harm ........................................................................ 21
6.2 Internal Notification of a Pollution Incident ........................................................ 21
6.3 External Notification of a Pollution Incident ....................................................... 21
Print Date 04/04/2017
ORIGINAL ISSUE DATE 1 June 2015
VERSION / DATE OF ISSUE 27 / March 2017
Page 5 of 26
DOC # DRA_
Printed copies created from this document are deemed to be uncontrolled
6.4 Communication with Neighbours and the Local Community ............................. 23
7 TRAINING, TESTING AND REVIEW .......................................................................... 25
7.1 Response Actions and Training ........................................................................ 25
7.2 Testing & Review Schedule .............................................................................. 25
7.3 Availability of the PIRMP .................................................................................. 25
7.4 References ....................................................................................................... 25
8 APPENDICES ............................................................................................................. 26
Figures
FIGURE 1 INCIDENT RESPONSE AND NOTIFICATION PROCESS .................................................................... 22
Tables
TABLE 1 PIRMP REQUIREMENTS ............................................................................................................... 9
TABLE 2 EPL 1323 LICENCE DETAILS ....................................................................................................... 12
TABLE 3 POSSIBLE HAZARDS .................................................................................................................... 14
TABLE 4 MAXIMUM INVENTORIES FOR MINE WATER, SEDIMENT LADEN WATER AND EFFLUENT ................... 17
TABLE 5 DRAYTON ENVIRONMENTAL INCIDENT CONTACTS ......................................................................... 19
TABLE 6 EXTERNAL ENVIRONMENTAL INCIDENT CONTACTS ........................................................................ 23
Print Date 04/04/2017
ORIGINAL ISSUE DATE 1 June 2015
VERSION / DATE OF ISSUE 27 / March 2017
Page 6 of 26
DOC # DRA_
Printed copies created from this document are deemed to be uncontrolled
Document Information
1 BACKGROUND
1.1 Purpose
Anglo Coal (Drayton Management) Pty Limited (Drayton) holds Environmental Protection
Licence (EPL) 1323 for its operation located at Drayton Mine, Thomas Mitchell Drive
Muswellbrook. Part 5.7A of the Protection of the Environment Operations Act 1997 (POEO
Act) and Chapter 7, Part 3A of the Protection of the Environment Operations (General)
Regulation 2009 (POEO(G) Regulation), requires Drayton as holder of an EPL to prepare,
keep, test and implement a Pollution Incident Response Management Plan (PIRMP).
The specific legal requirements for the PIRMP include:
Holders of an EPL must prepare a PIRMP (section 153A, POEO Act);
The PIRMP must include the information detailed in the POEO Act (section 153C) and
the POEO(G) Regulation (clause 98C) and be in the form required by POEO(G)
Regulation (clause 98B);
Licensees must keep the plan at the premises to which the EPL relates (section 153D,
POEO Act);
Licensees must test the plan at least every 12 months and after a pollution incident in
accordance with the in accordance with the POEO(G) Regulation (clause 98E); and
If a pollution incident occurs in the course of an activity so that material harm to the
environment is caused or threatened within the meaning of Part 5.7 of the POEO Act,
licensees must immediately implement the plan (section 153F, POEO Act).
This document addresses this requirement for a PIRMP associated with EPL 1323 at
Drayton Mine and has been prepared in accordance with the Environmental Protection
Authorities (EPA) Environmental guidelines: Preparation of pollution incident response
management plans (March 2012).
1.2 Objectives
The purpose of this PIRMP is to describe the way pollution incidents are reported, managed
and communicated to the general community.
The objectives of this plan are to:
Detail the procedures for notification of pollution incidents resulting in or having the
potential to cause material harm to the environment;
Ensure comprehensive and timely communication about a pollution incident to staff at
the premises, the EPA, other relevant authorities specified in the POEO Act and people
outside the facility who may be affected by the impacts of the pollution incident;
Print Date 04/04/2017
ORIGINAL ISSUE DATE 1 June 2015
VERSION / DATE OF ISSUE 27 / March 2017
Page 7 of 26
DOC # DRA_
Printed copies created from this document are deemed to be uncontrolled
Minimise and control the risk of a pollution incident at the facility by requiring
identification of risks and the development of planned actions to minimise and manage
those risks; and
Ensure that the plan is properly implemented by trained staff, identifying persons
responsible for implementing it, and ensuring that the plan is regularly tested for
accuracy, currency and suitability.
1.3 Scope
This PIRMP has been developed for the use of all Drayton personnel and contractors that
work on site. This PIRMP will be implemented only if material harm to human health or the
environment occurs or threatens to occur as determined by the personnel in this plan.
Drayton hold EPL 1323 for its operation located at Drayton Mine which is subject to
improvements in processes and practices from time to time. To accommodate these
ongoing changes along with site specific environmental assessment and management this
PIRMP will be progressively reviewed and if necessary updated.
This PIRMP is to clearly define the requirements of Drayton personnel to report and respond
to pollution incidents in accordance with the requirements of the POEO Act and the
POEO(G) Regulations.
1.4 Responsibilities
All Drayton personnel and contractors are responsible for understanding and
implementing this PIRMP as appropriately identified. This PIRMP identifies the general roles
and responsibilities of Drayton personnel and contractors to manage pollution incidents
onsite.
Supervisors and Managers are responsible for ensuring Drayton personnel and contractors
are aware of the PIRMP and their roles where appropriate. They are also responsible for
implementing training where necessary as applicable to individual roles.
The Environmental Superintendent and supporting officers are responsible for:
Assisting with advice, reporting and response processes;
Ensuring this PIRMP is made available for staff responsible for implementing the plan
and authorised offices under the POEO Act;
Providing advice as to whether environmental incidents need to be reported to external
agencies;
Providing notification of pollution incidents to external agencies;
Provision of maps associated with the PIRMP;
Assistance with the implementation of response actions to pollution incidents;
Communicate with neighbours and the local community about the PIRMP and when
incidents of certain nature occur;
Ensure that the appropriate level of training is provided to personnel responsible for
activating the PIRMP; and
Reviewing and testing of the PIRMP.
Print Date 04/04/2017
ORIGINAL ISSUE DATE 1 June 2015
VERSION / DATE OF ISSUE 27 / March 2017
Page 8 of 26
DOC # DRA_
Printed copies created from this document are deemed to be uncontrolled
The Mine Manager is responsible for:
Statutory requirements of the site;
Determining whether environmental incidents need to be reported to external agencies;
Ensuring this PIRMP is made available for staff responsible for implementing the plan
and authorised offices under the POEO Act;
Communicate with neighbours and the local community about the PIRMP and when
incidents of certain nature occur; and
Assisting with advice, reporting and response processes.
Advice from Legal Team will assist with investigations of pollution incidents and preparation
of reports for the EPA and other regulators for major incidents to ensure legal compliance
with applicable legislation.
1.5 Definitions
Land pollution or pollution of land means placing in or on, or otherwise introducing into or
onto, the land (whether through an act or omission) any matter, whether solid, liquid or
gaseous that causes or is likely to cause degradation of the land, resulting in actual or
potential harm to the health or safety of human beings, animals or other terrestrial life or
ecosystems, or actual or potential loss or property damage, that is not trivial.
A Pollution incident is an incident or set of circumstances during or as a consequence of
which there is or is likely to be a leak, spill or other escape or deposit of a substance, as a
result of which pollution has occurred, is occurring or is likely to occur. It includes an Incident
or set of circumstances in which a substance has been placed or disposed of on premises,
but it does not include an incident or set of circumstances involving only the emission of any
noise.
Material harm. A pollution incident is required to be notified if there is a risk of ‘material
harm to the environment’, which is defined in section 147 of the POEO Act as:
(a) harm to the environment is material if:
(i) it involves actual or potential harm to the health or safety of human beings or to
ecosystems that is not trivial, or
(ii) it results in actual or potential loss or property damage of an amount, or amounts
in aggregate, exceeding $10,000 (or such other amount as is prescribed by the
regulations), and
(b) loss includes the reasonable costs and expenses that would be incurred in taking all
reasonable and practicable measures to prevent, mitigate or make good harm to the
environment.
Immediately has its ordinary dictionary meaning of promptly and without delay.
2 REGULATORY FRAMEWORK
Part 5.7A, clause 153C of the POEO Act and Part 3A Clause 98C of the POEO(G)
Regulation describes the specific information to be included in PIRMP. Table 1 outlines
these statutory requirements and where each requirement has been addressed in this
PIRMP.
Print Date 04/04/2017
ORIGINAL ISSUE DATE 1 June 2015
VERSION / DATE OF ISSUE 27 / March 2017
Page 9 of 26
DOC # DRA_
Printed copies created from this document are deemed to be uncontrolled
Table 1
PIRMP Requirements
Legislative Requirement Where Addressed in
this document
Protection of the Environment Operations Act 1997
153C Information to be included in the plan
A pollution incident response management plan must be in the form required by the regulations and must include the following:
(a) the procedures to be followed by the holder of the relevant environment protection licence, or the occupier of the relevant premises, in notifying a pollution incident to:
This document
(i) the owners or occupiers of premises in the vicinity of the premises to which the environment protection licence or the direction under section 153B relates, and Section 3.1
(ii) the local authority for the area in which the premises to which the environment protection licence or the direction under section 153B relates are located and any
area affected, or potentially affected, by the pollution, and
Section 3.1 and Appendix A
(iii) any persons or authorities required to be notified by Part 5.7, Section 6.3
(b) a detailed description of the action to be taken, immediately after a pollution incident, by the holder of the relevant environment protection licence, or the occupier of the
relevant premises, to reduce or control any pollution
Section 6
(c) the procedures to be followed for co-ordinating, with the authorities or persons that have been notified, any action taken in combating the pollution caused by the incident
and, in particular, the persons through whom all communications are to be made,
Section 6.3
(d) any other matter required by the regulation (as set out below) This Table
Protection of the Environment Operations (General) Regulation 2009
98C Additional matters to be included in plan
(1) General. The matters required under section 153C (d) of the Act to be included in a plan are as follows:
(a) a description of the hazards to human health or the environment associated with the activity to which the licence relates (the relevant activity), Section 3.2
(b) the likelihood of any such hazards occurring, including details of any conditions or events that could, or would, increase that likelihood, Section 3.2
Print Date 04/04/2017
ORIGINAL ISSUE DATE 1 June 2015
VERSION / DATE OF ISSUE 27 / March 2017
Page 10 of 26
DOC # DRA_
Printed copies created from this document are deemed to be uncontrolled
Legislative Requirement Where Addressed in
this document
(c) details of the pre-emptive action to be taken to minimise or prevent any risk of harm to human health or the environment arising out of the relevant activity, Section 5.2
(d) an inventory of potential pollutants on the premises or used in carrying out the relevant activity, Section 3.2 and Section 3.3
(e) the maximum quantity of any pollutant that is likely to be stored or held at particular locations (including underground tanks) at or on the premises to which the
licence relates,
Section 3.2 and Section 3.3
(f) a description of the safety equipment or other devices that are used to minimise the risks to human health or the environment and to contain or control a pollution
incident,
Section 5
(g) the names, positions and 24-hour contact details of those key individuals who:
(i) are responsible for activating the plan, and
(ii) are authorised to notify relevant authorities under section 148 of the Act, and
(iii) are responsible for managing the response to a pollution incident,
Section 4.2
(h) the contact details of each relevant authority referred to in section 148 of the Act, Section 6.3
(i) details of the mechanisms for providing early warnings and regular updates to the owners and occupiers of premises in the vicinity of the premises to which the
licence relates or where the scheduled activity is carried on,
Section 6.4
(j) the arrangements for minimising the risk of harm to any persons who are on the premises or who are present where the scheduled activity is being carried on, Section 5
(k) a detailed map (or set of maps) showing the location of the premises to which the licence relates, the surrounding area that is likely to be affected by a pollution
incident, the location of potential pollutants on the premises and the location of any stormwater drains on the premises,
Appendix A
Note: No stormwater drains are
located on the premises
(l) a detailed description of how any identified risk of harm to human health will be reduced, including (as a minimum) by means of early warnings, updates and the
action to be taken during or immediately after a pollution incident to reduce that risk,
Section 5
(m) the nature and objectives of any staff training program in relation to the plan, Section 7
(n) the dates on which the plan has been tested and the name of the person who carried out the test, Title Block
Print Date 04/04/2017
ORIGINAL ISSUE DATE 1 June 2015
VERSION / DATE OF ISSUE 27 / March 2017
Page 11 of 26
DOC # DRA_
Printed copies created from this document are deemed to be uncontrolled
Legislative Requirement Where Addressed in
this document
(o) the dates on which the plan is updated, Title Block
(p) the manner in which the plan is to be tested and maintained. Section 7.2
Print Date 04/04/2017
ORIGINAL ISSUE DATE 1 June 2015
VERSION / DATE OF ISSUE 27 / March 2017
Page 12 of 26
DOC # DRA_
Printed copies created from this document are deemed to be uncontrolled
3 PREMESIS DETAILS
3.1 Site Details
Drayton is located near the township of Muswellbrook in the Upper Hunter Valley of NSW
(see Appendix A). Drayton has been in operation since 1982 commencing coal production
in 1983. It is an open cut mine and when operational utilised both dragline and truck and
shovel to produce up to eight million tonnes per annum (Mtpa) of Run of Mine (ROM) thermal
coal for export markets. Active mining operations at Drayton ceased in October 2016 with a
project team remaining to oversee rehabilitation and decommissioning activities.
Anglo Coal (Drayton Management) Pty Limited was issued EPL 1323 under section 55 of the
POEO Act on 18 September 2000. EPL 1323 authorises the carrying out of scheduled
activities at Drayton Mine. The facility details as described in EPL 1323 are identified in
Table 2.
The surrounding area which may potentially be impacted by a pollution incident at Drayton, in
addition to the premises itself may include the following:
Landholders adjacent to the premises boundary;
Downstream water courses and associated adjacent landholders; and
Nearby townships primarily Muswellbrook, Jerrys Plains and Singleton.
Table 2 EPL 1323 Licence Details
Company Name Anglo Coal (Drayton Management) Pty Ltd
Environmental Protection Licence Number
1323
Scheduled Activities Coal Works
Mining for Coal
Facility Name and Address
Drayton Coal Mine
Thomas Mitchell Drive
Muswellbrook NSW 2333
3.2 Major Hazards
Drayton maintains a Safety, Health, Environment and Community Management System
(SCHEMS) which is accredited to ISO 14001 standards. The SCHEMS is designed to:
Effectively manage its environmental issues;
Ensure compliance with regulatory requirements;
Continually improve its environmental performance through review and auditing; and
Satisfy the expectations of stakeholders.
The SCHEMS is based on a suite of legislative requirements, procedures and standards,
which have been prepared to ensure that operational activities, objectives and targets avoid
or have minimal impact to the environment. As a component of the SCHEMS, a number of
environmental management plans have been enforced. These plans cover a broad range of
Print Date 04/04/2017
ORIGINAL ISSUE DATE 1 June 2015
VERSION / DATE OF ISSUE 27 / March 2017
Page 13 of 26
DOC # DRA_
Printed copies created from this document are deemed to be uncontrolled
environmental aspects and outline operating procedures, standards and requirements under
which Drayton Mine’s performance is reviewed and audited against. All existing approved
management plans are available on the Anglo American Website
The primary hazards to human health or the environment associated with activities at
Drayton as applicable to this PIRMP are outlined below. The likelihood and control
measures for primary environmental hazards are summarised Table 3.
Water Discharge
All incidents resulting in offsite discharge of any quantity of mine affected water. This
includes all water from areas disturbed by mining activities and all water stored in dams and
voids connected to the mine water management system via pipelines, pumps and drains.
The rail loop dam and access road dam are higher risk dams for offsite discharge due to the
location of the dams and the nature of the local topography. Discharge of any water from
dams or disturbed areas into natural drainage lines (e.g. creeks) is to be reported
immediately in accordance with this procedure.
Blasting – Overpressure, Vibration and Fume
All blast events where recorded levels at monitors representative of private residences are
greater than:
Overpressure 120dBL (results over 115dBL must also be formally investigated); and
Vibration 10mm/sec (results over 5mm/sec must also be formally investigated).
Blasting outside of the approved hours of 9am – 5pm Monday to Saturday is not permitted.
Air Quality
All incidents of dust and/or fume observed leaving the lease boundary are to be reported to
the Environment Superintendent. This includes all incidents where dust and/or fume is
observed crossing a public road (e.g. Thomas Mitchell Drive) and any incident where dust
and/or fume generated from operations is deemed excessive or is observed entering the
atmosphere and moving off-lease in coherent “clouds” or “plumes” which may be visible to
the public.
If in doubt, excessive dust should be reported to the Environmental Superintendent for
further investigation.
Spills
Spills must be reported to the Environmental Superintendent immediately after containment
and clean-up has been initiated. Reportable spills include:
All spills from burst pipelines (except in the workshop);
All spills on undisturbed or vegetated areas;
All spills escaped from containment bunds;
All spills into waterways including dams and drains (except those reporting directly to
the oil pollution control dam);
All spills of greater than 20 litres; and
All spills affecting off-lease areas.
Print Date 04/04/2017
ORIGINAL ISSUE DATE 1 June 2015
VERSION / DATE OF ISSUE 27 / March 2017
Page 14 of 26
DOC # DRA_
Printed copies created from this document are deemed to be uncontrolled
Spills of many types of materials are reportable. If in doubt, contact the Environmental
Superintendent for advice. Report spills of:
Hydrocarbons (e.g. grease, oils, and fuels);
Tailings (though associated with cessation of mining in October 2016 are no longer
generated on the premises);
Chemicals; and
Waste products.
Note: Spills contained on sealed surfaces and spills contained within sealed bunds are not
reportable if immediate clean-up occurs. Spills to sealed surfaces and bunds are reportable
where immediate clean-up is not possible.
Bushfire
All fires onsite are immediately reportable to the OCE and the Mine Manager. The
Environmental Superintendent must also be notified in the event of a bushfire outbreak
onsite or encroaching on Drayton owned land from offsite. Bushfires are reportable to the
Rural Fire Service on 000 (refer to the site Emergency Response Plan for further actions).
Other Hazards
It is noted that other possible hazards relevant to Drayton are managed by the existing site
EMS regime including noise and odour (from spontaneous combustion). These hazards are
not considered a pollutant for the purposes of this PIRMP however are effectively managed
at Drayton in accordance with applicable criterion as listed in PA 06_0202 and EPL 1323.
Noise and Spontaneous Combustion are managed in accordance with the site Noise
Management Plan along with the Spontaneous Combustion Management Plan.
Table 3
Possible Hazards
Contaminant Hazard Likelihood Controls Contributing factors
Bulk
Hydrocarbon
(diesel, oils)
Spillage of large
volumes of
hydrocarbon onto
land or water.
Possible Bunding
Locked valves
Process
Signage
Regular inspections
Burst or leaking pipe
Failure of bulk storage
tank in conjunction with
failure of the bunded
containment system
Process water
Spillage of saline
water.
Inundation of
downstream areas
from dam wall
failure.
Possible Regulated dam
Regular inspections
Statutory dam inspections
by approved civil engineer
Exceptionally heavy
rainfall overtopping a
dam spillway.
Burst pipe
Pump failure
Process water Spillage of saline
water.
Inundation of
downstream areas
from dam wall
failure.
Rare Regular inspections
Statutory dam inspections
by approved civil engineer
Dam failure
Print Date 04/04/2017
ORIGINAL ISSUE DATE 1 June 2015
VERSION / DATE OF ISSUE 27 / March 2017
Page 15 of 26
DOC # DRA_
Printed copies created from this document are deemed to be uncontrolled
Contaminant Hazard Likelihood Controls Contributing factors
Effluent
Failure of water
treatment system
results in spill of
untreated effluent to
land or water.
Rare Regular inspections
Ash Ash Dam levee wall
failure.
Rare Regulated dam
Regular inspections
Statutory dam inspections
by approved civil engineer
Built to specifications
Spills would be contained
within pit
Bulk explosive Spillage of large
volumes of ANFO.
Unlikely Solid product, doesn’t
spread easily
Spontaneous
combustion
Burning waste or
coal stockpile.
Possible Minimise the time that
product is stockpiled (note
that this aspect is absent
during the post-mining
period)
Cover combustible
material with inert capping
material
Progressively rehabilitate
areas in accordance with
the schedule in the MOP
Uncapped or
inadequate capping
depth
Bush fire Activities on site
cause large bush
fire to start.
Rare Hot work permits
Fire load reduction
program
Maintain fire breaks and
firefighting capability
Maintain vegetation under
power lines and around
transformer stations
Build-up of flammable
material
Extreme weather
conditions
Lightning strike
Arching or fallen power
lines
Blast fume Unpredicted large
fume event from
blast carries off site.
Possible Blast planning.
Blast fume modelling of
predicted paths
Product selection.
Weather conditions.
Rainfall / Wind
Excessive
Dust
Excessive dust is
being generated or
is carried off site.
Possible Water truck
Competent use of
equipment
Maintenance of plant and
equipment
Management of operations
Weather conditions.
Rainfall / Wind
Print Date 04/04/2017
ORIGINAL ISSUE DATE 1 June 2015
VERSION / DATE OF ISSUE 27 / March 2017
Page 16 of 26
DOC # DRA_
Printed copies created from this document are deemed to be uncontrolled
3.3 Chemicals and Potential Pollutant Inventory
Hydrocarbons and chemicals have the potential to adversely affect the environment and
people. Before any substance may be used on site, an appropriate risk assessment is be
undertaken to determine the probability of a spill occurring and the most appropriate method
to manage the substance. The substance must also be registered on ChemAlert and have a
current Safety Data Sheet (SDS) readily accessible to all personnel handling the substance.
Management of hydrocarbons and chemicals at Drayton shall ensure the following:
Hazardous substances required onsite should only be purchased in minimum required
quantities, with the lowest hazardous rating available for the required application;
Hydrocarbons and Chemicals shall be stored and used in accordance with
manufacturer’s requirements and, where applicable, any additional Drayton Mine
requirements;
Any leaks and/or spills will be managed in accordance with the manufacturers SDS and
this procedure; and
Any substances that are no longer required or authorised for use onsite shall be
promptly returned to the supplier or classified as regulated waste and disposed of in
accordance with the sites ‘Waste, Overburden and Hazardous Materials Management
Plan’.
Drayton maintains a ChemAlert system which tracks the full inventory of potential pollutants
kept on site, most of which are only present in minor volumes.
The primary chemicals and the maximum volumes of each chemical that can be held on site
at any one time are:
Diesel – one 860kL tank near the main fuelling area, and two 110kL tanks at the inpit
refuelling area.
Hydraulic oils and greases – two 30 kL tanks and two 10 kL tanks at the main
workshop area, and 3 2.4 kL tanks at the inpit refuelling area.
Waste Oil – one 20 kL tank at the main workshop area.
Ammonium Nitrate – 80 tonnes at the reload facility
A plan of the premises identifying the above items is provided in Error! Reference source not
found..
All bulk storage tanks and containers of hydrocarbons are stored within appropriate bunding
and kept in a neat and tidy condition. Contamination is kept at a minimum, with any
moderate spillages (20 L or greater) being reported internally through Drayton’s incident
reporting system. Tanks and storage areas are located such that any incidents will not lead
to offsite discharge or impacts. Concrete and earthen bunds are inspected regularly for
structural integrity and cleanliness. After rainfall events, rainwater is removed from bunds to
ensure sufficient storage capacity in the bund in the event of a spill.
All storage facilities have been designed and are maintained in accordance with relevant
Australian Standards. Explosives are stored in a licensed explosives magazine (licence
XSTR100017) in accordance with Workcover requirements and applicable Australian
Standards.
Drayton operates a closed water system and does not draw water from surface water
sources (such as the Hunter River), or discharge water to the environment. All mine water is
Print Date 04/04/2017
ORIGINAL ISSUE DATE 1 June 2015
VERSION / DATE OF ISSUE 27 / March 2017
Page 17 of 26
DOC # DRA_
Printed copies created from this document are deemed to be uncontrolled
stored in established dams and voids. There are no clean water catchments located on site.
The primary water storage dams and their maximum storage capacities and supply sources
is provided in Table 4. Process water dams with the potential to leave the premises due to
their locations and local topography include the Access Road Dam and the Rail Loop Dam.
Table 4
Maximum Inventories for Mine Water, Sediment Laden Water and Effluent
Dam Names Approx.
Maximum Storage Capacity (ML)
Supply Source
ES Void 5,500 Tailings, run-off from disturbed
areas in pit, aquifer interception.
Industrial Dam 750 Runoff from industrial areas and
pumped from ES Void
Access Road Dam 615
Runoff from undisturbed and
rehabilitated land and pumped
from Industrial Dam and ES Void.
Rail Loop Dam 18 Runoff from CHP, coal stockpile
area
Pringles Dam 20 Pumped from ES Void, runoff from
undisturbed land.
Savoy Dam 145
Runoff from undisturbed and
rehabilitated land, ES Void
transfer point
West Pit Void 1,000 Runoff from Southern Offset and
excess water during wet weather.
SPE Void 8,140 Runoff from disturbed areas in pit,
water pumped from ES Void.
Effluent Ponds (2 ponds) 0.01 Bath house
Print Date 04/04/2017
ORIGINAL ISSUE DATE 1 June 2015
VERSION / DATE OF ISSUE 27 / March 2017
Page 18 of 26
DOC # DRA_
Printed copies created from this document are deemed to be uncontrolled
4 MANAGEMENT AND RESPONSIBILITIES
4.1 Legal Duty to Notify
All personnel on site are responsible for identifying and immediately reporting environmental
incidents or hazards to their supervisor which may result in environmental harm, regardless
of the nature or scale. ‘Immediately’ has its ordinary dictionary meaning of promptly and
without delay.
In the event of any environmental incidents or hazards (where there is no immediate threat to
human life or property) site personnel must notify their supervisor, who will then contact the
Environment Superintendent or delegate on 0438 914 725.
Notification responsibilities are detailed in the POEO Act (Section 148(3)(3A)), which
encompasses all site personnel, including contractors and sub-contractors. These can be
categorised broadly as applicable to Drayton as:
The duty of an employee or any person undertaking an activity:
o Any person engaged as an employee or undertaking an activity must, immediately
after becoming aware of any potential incident, notify their relevant supervisor of the
incident and all relevant information about it. This is to be undertaken as per
Section 6.3; and
The duty of the employer or occupier of a premises to notify:
o An employer or occupier of the premises on which the incident occurs, who is
notified (or otherwise becomes aware of) a potential pollution incident, must
undertake notification to the appropriate regulatory authority of any “material harm
incidents”, including all relevant information. Notification shall be undertaken as per
Section 6.3.
The decision on whether to notify the incident in accordance with Part 5.7 of the POEO Act
should not delay immediate actions to provide the safety of people or contain a pollution
incident. However, incident notification will be made as soon as it is safe to do so.
Print Date 04/04/2017
ORIGINAL ISSUE DATE 1 June 2015
VERSION / DATE OF ISSUE 27 / March 2017
Page 19 of 26
DOC # DRA_
Printed copies created from this document are deemed to be uncontrolled
4.2 Relevant Site Contacts
Table 5 identifies the key individuals responsible for activating the procedure outlined in this
PIRMP and managing the response.
Table 5
Drayton Environmental Incident Contacts
Name Contact Details Position Responsibility
Matt Lord 02 6542 0298
0438 914 725
Environment
Superintendent
Responsible for undertaking
notification as defined in this
PIRMP
Jointly responsible (with the Mine
Manager) for the determination of
‘material harm’
Responsible for coordinating the
response to a pollution incident
Responsible for arranging testing
and updating of the PIRMP
Responsible for ensuring
notification and training of PIRMP
Facilitate site personnel in
implementation of the PIRMP
Communication of the PIRMP to
site personnel.
Responsible for personal visits
and phone calls to neighbours as
required.
Darren Pisters 6542 0203
0417 618 876
Mine Manager Jointly responsible (with the
Environment Superintendent) for
the determination of ‘material
harm’
Responsible for deciding whether
community alerts are required.
Responsible for coordinating
media response.
Statutorily responsible for site
Corporate Communications
Manager
Responsible with Mine Manager
for coordinating media response.
Print Date 04/04/2017
ORIGINAL ISSUE DATE 1 June 2015
VERSION / DATE OF ISSUE 27 / March 2017
Page 20 of 26
DOC # DRA_
Printed copies created from this document are deemed to be uncontrolled
5 INCIDENT MANAGEMENT
5.1 Emergency Response
The Emergency Response Management Plan describes the actions to be taken by Drayton
personnel and service providers during an emergency and applies to all personnel who enter
the Drayton mine. The Emergency Response Management Plan is supported by the Fire
Control Management Procedure, First Aid Procedure and the Incident Reporting Notification
and Initial Investigation Procedure.
The Emergency Response Management Plan includes Trigger Action Response Plans
(TARPs) have been developed for the following potential emergency incidents.
TARP-01 Injury
TARP-02 Vehicle Accident
TARP-03 Fire and Explosion
TARP-04 Explosive Emergency
TARP-05 Hazardous Chemical Spill
TARP-06 Tyre Fire
TARP-08 Emergency
TARP-09 Nitrogen Oxides fume
TARP-10 Ash Dam
TARP-11 Orica Bulk Plant
The Emergency Response Management Plan may identify the need for the PIRMP to be
implemented. This PIRMP has been developed to satisfy the environmental pollution
incident reporting required by the POEO Act (see Section 2).
All personnel who work on the site will be made aware of this procedure at their induction
and through toolbox talks.
All visitors to site will be under the direction of a fully inducted person who is responsible at
all times for their visitor/s.
5.2 Preventative Controls
Environmental monitoring and reporting framework is a key component of Drayton’s
operation to ensure strict compliance with all relevant statutory approvals including the
conditions of EPL 1323. Monitoring undertaken includes air quality, surface and ground
water quality, blasting, noise and meteorology. All monitoring is conducted in accordance
with the appropriate Australian Standard, with collection of samples by site personnel or
contractors and the analysis of water and dust samples performed by an independent
laboratory that is NATA accredited.
Drayton’s Safety, Health and Environment Management System (SHE MS) is certified to
both ISO 14001 for its environmental management practices and ASOHS 18001, AS/NZ4801
for health and safety to manage the hazards identified in Section 3.2. This system is aimed
at ensuring continual improvement in SHEC performance as required by Anglo American.
Print Date 04/04/2017
ORIGINAL ISSUE DATE 1 June 2015
VERSION / DATE OF ISSUE 27 / March 2017
Page 21 of 26
DOC # DRA_
Printed copies created from this document are deemed to be uncontrolled
6 NOTIFICATION PROCEDURES
6.1 Determination of Material Harm
Following containment of the incident, immediate action must be taken to determine if the
incident can be classified as a ‘material harm incident’ as which is defined in section 147 of
the POEO Act (see Section 1.3).
The determination of a material harm incident will be made by the Environment
Superintendent together with the Mine Manager. If the Mine Manager and / or the
Environment Superintendent is not available immediately, the determination will be made
individually by either party.
The process for both the internal and external notification of a pollution incident is described
in below in Section 5.2 and Section 5.3 respectively.
6.2 Internal Notification of a Pollution Incident
Firstly, call 000 if the incident presents an immediate threat to human health or property. Fire
and Rescue NSW, the NSW Police and the NSW Ambulance Service are the first
responders, as they are responsible for controlling and containing incidents
If the incident did not require an initial combat agency, or once the ‘000’ call has been made,
notify your supervisor and / or the Environmental Superintendent.
6.3 External Notification of a Pollution Incident
The Environment Superintendent or delegate is responsible for reporting any pollutant
incident for which there is a risk of ‘material harm to the environment’ within the meaning of
section 147 of the POEO Act (see Section 1.3) immediately to the authorities listed in the
order presented in Table 6 and provide the following relevant information:
The time, date, nature, duration and location of the incident,
The location of the place where pollution is occurring or is likely to occur,
The nature, the estimated quantity or volume and the concentration of any pollutants
involved, if known*,
The circumstances in which the incident occurred (including the cause of the incident, if
known*),
The action taken or proposed to be taken to deal with the incident and any resulting
pollution or threatened pollution, if known*,
*The information required is the information known to the person notifying the incident when the
notification is required to be given. If information is not known to the person when the initial
notification is made but becomes known afterwards, that information must be notified immediately
after it becomes known to each authority listed in Table 6.
Print Date 04/04/2017
ORIGINAL ISSUE DATE 1 June 2015
VERSION / DATE OF ISSUE 27 / March 2017
Page 22 of 26
DOC # DRA_
Printed copies created from this document are deemed to be uncontrolled
Person identifies a possible environmental pollution incident
Notify Supervisor Immediately
Supervisor reviews incident detail and inspects site
Is the incident a pollution incident which may cause or
threaten material harm to the environment?
If it is not able to be determined the incident should be treated
as if it is causing or threatening to cause material harm to the
environment
Adopt internal incident
reporting procedures
No
Call Environment Superintendent 0438914725.
If Environment Superintendent is unavailable contact Mine
Manager 0417 618 876
Supervisor
Provides the following information:
- The time, date, nature, duration and location of the incident,
- The location of the place where pollution is occurring or is
likely to occur,
- The nature, the estimated quantity or volume and the
concentration of any pollutants involved, if known*,
- The circumstances in which the incident occurred (including
the cause of the incident, if known),
- The action taken or proposed to be taken to deal with the
incident and any resulting pollution or threatened pollution, if
known.
In the event that there is no
Supervisor available contact
the Environment
Superintendent
Environment Superintendent and Mine Manager
Review the incident and determine if it is reportable in
accordance with Part 5.7 of the POEO Act.
No
Yes
Yes
Environment Superintendent / Mine Manager call the following agencies
immediately:
- Environmental Protection Authority - 131 555
- Department of Planning and Environment - 02 6575 3405
- Division of Resources and Energy 1300 736 122 or 02 4931 6666
- Muswellbrook Shire Council 02 6549 3700
- SafeWork NSW 13 10 50
- Ministry of Health, Public Health Unit (Newcastle) 02 4924 6477 ask for Public-
Health Officer on call
- Fire and Rescue NSW 1300 729 579 or 000
- Affected Neighbours - As applicable
Report the following details:
- The time, date, nature, duration and location of the incident,
- The location of the place where pollution is occurring or is likely to occur,
- The nature, the estimated quantity or volume and the concentration of any
pollutants involved, if known*,
- The circumstances in which the incident occurred (including the cause of the
incident, if known*),
- The action taken or proposed to be taken to deal with the incident and any
resulting pollution or threatened pollution, if known*.
Environment Superintendent and Mine Manager
Continue to monitor the environmental incident and gather and
provide immediately any information which was not known at
the time the incident was reported but becomes available
afterwards.
Environment Superintendent and Mine Manager
Implement appropriate external communication with the local
community e.g. personal visits, media releases etc
Call ‘000’ if the incident presents an
immediate threat to human health or
property.
Figure 1 Incident Response and Notification Process
Print Date 04/04/2017
ORIGINAL ISSUE DATE 1 June 2015
VERSION / DATE OF ISSUE 27 / March 2017
Page 23 of 26
DOC # DRA_
Printed copies created from this document are deemed to be uncontrolled
Table 6
External Environmental Incident Contacts
Authority Contact Number
Environmental Protection Authority 131 555
Department of Planning and Environment 02 6575 3405
Division of Resources and Energy 1300 736 122 or 02 4931 6666
Muswellbrook Shire Council (MSC) 02 6549 3700
SafeWork NSW (formerly WorkCover) 13 10 50
Ministry of Health, Public Health Unit (Newcastle)
02 4924 6477 ask for Public Health Officer on call
Fire and Rescue NSW* 1300 729 579 or 000
Affected Neighbours As applicable
Note: If the situation warranted calling 000 as a first point of notification, you do not need to ring Fire and Rescue NSW again.
6.4 Communication with Neighbours and the Local Community
Communication with neighbours and the local community will be undertaken by the Mine
Manager and /or the Environment Superintendent, in consultation (as required on a case by
case basis) with the Corporate Communications Manager. Names and contact details for
neighbouring stakeholders are held in a stakeholder database which is maintained by the
Environment Superintendent.
Depending on the nature and extent of the pollution incident, Drayton will subsequently
advise neighbours and the local community using one or more of the below methods to
communicate a reportable environmental incident:
Phone calls;
Personal visits;
Media releases;
Statements via mail;
Radio announcements on local station/s;
Newspaper advertising; and
Emails.
Information provided to stakeholders and the community will be relevant to the particular
environmental incident and may include the following details:
Nature and type of the environmental incident;
Potential impacts to local landholders (with context applicable for individuals) and the
wider community;
Site environment personnel contact details;
Any recommendations or advice based on the incident type and scale; and
Print Date 04/04/2017
ORIGINAL ISSUE DATE 1 June 2015
VERSION / DATE OF ISSUE 27 / March 2017
Page 24 of 26
DOC # DRA_
Printed copies created from this document are deemed to be uncontrolled
Anticipated pathway forward including an indication as to whether further information
would be required to be developed and associated timing for the provision of any
material.
There are no sensitive facilities, such as schools, nursing homes or hospitals, in the vicinity
of the premises.
The welfare of people on site will continue to be managed per the Emergency Response
Management Plan.
Print Date 04/04/2017
ORIGINAL ISSUE DATE 1 June 2015
VERSION / DATE OF ISSUE 27 / March 2017
Page 25 of 26
DOC # DRA_
Printed copies created from this document are deemed to be uncontrolled
7 TRAINING, TESTING AND REVIEW
7.1 Response Actions and Training
Pending the final classification of the incident the actions to be taken in response to a
pollution incident described in this PIRMP may also relate to the Emergency Response
Management Plan and the Incident Reporting Notification and Initial Investigation document.
A detailed induction package is required to be completed by all site personnel and
contractors prior to work at Drayton. This induction includes information as to the notification
procedures for the identification and communication of an environmental incident.
All environmental incidents are maintained in incidents and complaints register managed by
the Environmental Superintendent. All environmental incidents are investigated and the
details, including any follow-up actions required, are recorded in Enablon, Anglo’s internal
reporting system. This register assists with record keeping, reporting and determining
improvements to incident response and review of necessary plans.
7.2 Testing & Review Schedule
The PIRMP is required to be tested once a year, and reviewed within one month of a
pollution incident occurring.
Tests will be carried out as a desktop exercise to ensure that the information included in this
PIRMP is accurate and up to date, and the plan is capable of being implemented in a
workable and effective manner.
Following each review annually the PIRMP Test History tracking table contained within this
document will be updated with the review date and who carried out the review. Should the
review lead to an update of this PIRMP then the revision schedule will also be updated and
content authorised by the Mine Manager (or delegate).
7.3 Availability of the PIRMP
This PIRMP we be kept in written form, and be available at the premises and able to be
provided to an authorised EPA officer on request and to any person who is responsible for
implementing the plan in accordance with the POEO Act and POEO(G) Regulations.
The PIRMP will be made publically available within 14 days of the plan (or subsequent
amendments) being signed off by the Mine Manager via the Anglo Coal, Drayton
Environment website located at http://australia.angloamerican.com/our-operations/operating-
sites-subpage/drayton-environment.
This plan also forms an appendix to the Incident Reporting, Notification and Initial
Investigation Procedure and is kept electronically on the Drayton SHECMS website.
7.4 References
Emergency Response Management Plan, Anglo American
Incident Reporting Notification and Initial Investigation Procedure, Anglo American
Print Date 04/04/2017
ORIGINAL ISSUE DATE 1 June 2015
VERSION / DATE OF ISSUE 27 / March 2017
Page 26 of 26
DOC # DRA_
Printed copies created from this document are deemed to be uncontrolled
8 APPENDICES
Appendix A Premises Plans
T
h
is
a
re
a
S
u
b
-L
e
a
s
e
to
A
r
t
h
u
r
C
o
a
l
This area S
ub-Lease
AUTH
173
t
o
M
o
u
n
t
A
r
t
h
u
r
C
o
a
l
Mount
This area Sub-Lease to
Mount Arthur Coal
CL 395
CL395
CL229
CL229
CL229
AUTH 173
NN PIT
SOUTH PIT
WEST
SOUTH PIT
EAST
SE15 VOID
ES27
VOID
EN PIT
WORKSHOP
ADMINISTRATION
CHPP
STOCKPILE
AREA
RAIL LOOP
SW13 VOID
V NOTCH
WEIR
EXPLOSIVES
FACILITY
WEST FUEL
FARM
SAVOY DAM
TURKEYS
NEST
PRINGLES
DAM
INDUSTRIAL
DAM
OIL
POLLUTION
CONTROL
DAM
RAIL LOOP
DAM
DC2 DAM
ACCESS
ROAD DAM
FUEL BAY
BULK FUEL
STORAGE
SEWERAGE
PONDS
All distances are in metres
LEGEND
Mine Lease Boundary
S
W
N
E
AngloAmerican
ANGLO COAL (DRAYTON MANAGEMENT) PTY LTD
Pollution Incident Response Management Plan
Figure 1 - Site Layout
Date
10.02.2017
Scale:
1:30,000
Drawn
RJV
Checked
JM
Approved
DP
Sheet
A0
Rev.
A
Dwg. No.
996-02
Job
DM500
RE
VIS
IO
NS
REV. DATE BY DESCRIPTION CHK.
A 10.02.2017 JJL Issued Drawing JM
0 100 200 300 500 700 900
EPL 1323 Premises Boundary
Mine Dam
Hydrocarbon Footprint
ANFO Footprint
Effluent Footprint
Potential Flow Path
All distances are in metres
LEGEND
Mine Lease Boundary
Anglo American
0 250 500 1000 1500
S
W
N
E
Mt Arthur Coal
AGL Macquarie
Private Freehold
Anglo American Owned Residence
Private Residence
State of NSW
AngloAmerican
ANGLO COAL (DRAYTON MANAGEMENT) PTY LTD
Pollution Incident Response Management Plan
Figure 2 - Land Ownership
Date
10.02.2017
Scale:
1:40,000
Drawn
BMF
Checked
JM
Approved
DP
Sheet
A0
Rev.
A
Dwg. No.
996-03
Job
DM500
RE
VIS
IO
NS
REV. DATE BY DESCRIPTION CHK.
A 10.02.2017 JJL Issued Drawing JM
EPL 1323 Premises Boundary