    introducton

    Dear Customer,

    Please find enclosed the Construction Progress Report of all our projects. Should you have anyfurther queries, please feel free to contact our sales teams.

    Thank you

    Ananta Singh RaghuvanshiDirector- Sales and Marketing

    Bangalore l Chennai Hyderabad Jalandhar Kasauli l Kochi l Lucknow l New Chandigarh l Panchkula l Shimlal l l

    nd22 April 2013

  • 7/30/2019 DLF India Wide Projects Construction Update 04 2013

    2/12

    External Development

    1. Laying of sewer and stormwater pipelines is in progress2. Level difference wall by macceferri in progress3. External electrical work awarded

    Construction Status of Independent Floors

    1. Total number of cast at various levels - 816

    2. Total number of plinths complete - 420

    3. Internal electrical and plumbing work is in progress

    4. Internal plastering work has begun

    slabs

    229 acre

    Integrated Township

    in Panchkula

  • 7/30/2019 DLF India Wide Projects Construction Update 04 2013

    3/12

    External Services

    1. The laying of sewer and stormwater pipelines - 95% complete2. Electrical work is under progress in R1 and R2.3. Sewage Treatment Plant(STP) in progress.4. The work on parks and horticulture is in progress5. Tubewell boring is almost complete in R1 and R2.

    Hyde Park Terraces - Construction by

    Shapoorji Pallonji Co. Ltd.

    Construction has begun for all floors.

    Hyde Park Estate is a229 acres

    Integrated Township

    in New ChandigarhSE R R A C EE R R A C E A R C A D E

  • 7/30/2019 DLF India Wide Projects Construction Update 04 2013

    4/12

    A 250 acres

    Integrated Township

    in Lucknow

    1. Foundation work for electric poles is complete

    2. Construction of compound wall in A Block has begun.

    3. Laying of services i.e. sewer, stormwater

    pipelines and water supply line is in progress.

    4. Work for underground water tank and sewage

    treatment plant (STP) is in progress.

    5. Road work including black top is in progress.

  • 7/30/2019 DLF India Wide Projects Construction Update 04 2013

    5/12

    1. Villa reaching completion stage - External finishes in progress

    2. External roads and retention walls work in progress

    Spread over 58 acres of

    forest bed, in Kasauli,

    Himachal Pradesh

  • 7/30/2019 DLF India Wide Projects Construction Update 04 2013

    6/12

    Luxury cottages in over1.6 acres of cedar forest

    in Shimla

    S.No. Cottage

    No.

    Foundation 1st Slab 2

    nd Slab 3

    rd Slab

    1 1, 4, 5, 8, 9, 18,19, 20, 23, 24, 25

    Completed

    2

    21, 22

    ---

    CompletedCompletedCompleted

    Completed Completed Completed

  • 7/30/2019 DLF India Wide Projects Construction Update 04 2013

    7/12

    External Development

    1. Landscaping work in finishing stage

    2. Club work finished

    3. Squash court work in final stage

    4. STP 90% complete

    5. Driveways work complete

    6. Finishing completed

    7. Final coat paint of lobbies in progress

    River facing luxury

    apartments in

    Vytilla, Kochi

  • 7/30/2019 DLF India Wide Projects Construction Update 04 2013

    8/12

    External Development

    1. STP raft slab & side wall works in progress

    2. Macaferri works for entrance road in progress

    3. Compound wall and drainage works in progress

    4. Tower area slab complete

    5. Plastering of walls and ceiling almost complete

    6. AC drains in place

    7. Kitchen and toilet walls tiling in progress

    An Integrated Townshipspread over 26 acres

    in Kochi

  • 7/30/2019 DLF India Wide Projects Construction Update 04 2013

    9/12

    Structure works

    1. LMR (Lift Machine Room), OHT (Over Head

    Tank) & structure works completed at Tower

    D1 & D2

    2. LMR & OHT works in progress at Cluster

    A, B & C

    3. Non tower upper ground / podiumslab works

    in progress at Cluster A, B, C & D

    4. Compound wall, underground tank and other

    external structure works in progress

    Finishing & Services work

    1. Block work near completion at all towers and

    plastering work in progress

    2. External plastering work nearing completion in

    Tower D1 & D2.

    3. MS railing fabrication and fixing for the Living &

    Bedrooms in progress in all towers

    4. Toilet waterproofing work in progress in Cluster

    A, B, C & D

    5. Toilet wall & floor tiling work begun

    6. Electrical conduiting and allied works in progress

    in all the towers

    7. Plumbing & fire fighting work in progress in all

    the towers

    8. Preliminary works for the lift installation in Tower

    D1 & D2 started

    High rise apartments in

    a 75 acresIntegrated Township

    called DLF New Town on

    Banerghatta Road,Bengaluru

  • 7/30/2019 DLF India Wide Projects Construction Update 04 2013

    10/12

  • 7/30/2019 DLF India Wide Projects Construction Update 04 2013

    11/12

    Luxury Apartments at

    Ethiraj Salai, Chennai

    L&T is the Construction Partner

  • 7/30/2019 DLF India Wide Projects Construction Update 04 2013

    12/12

    1. Mall structure is ready. Offered units for fit outs.

    2. Soft launch of Clubhouse is scheduled by in Aug/ Sep- 2013.th3. PSBB MillenniumSchooloperational upto 10 class

    Under Completion of Towers:

    1. Entire block of T-34 to T-42 ready. 100 families moved in

    2. T-5 is being handed over

    3. In T-2, T-3, T-4 and T-6, internal finishing work is under way

    and lifts are being fitted

    4. In T-24 to 27, internal tiling, electrical and plumbing work is in

    progress. Plastering is complete.

    with 1700 students

    A 52 acre

    Integrated Township

    on OMR, Chennai