13
Distribution Total Factor Productivity Preliminary Findings for Hydro One and the Ontario Industry STEVE FENRICK [email protected] WWW.POWERSYSTEM.ORG OCTOBER 5, 2016

Distribution Total Factor Productivity Preliminary ... · Distribution Total Factor Productivity Preliminary Findings for Hydro One and the Ontario Industry STEVE FENRICK [email protected]

  • Upload
    others

  • View
    22

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Distribution Total Factor Productivity Preliminary ... · Distribution Total Factor Productivity Preliminary Findings for Hydro One and the Ontario Industry STEVE FENRICK FENRICKS@POWERSYSTEM.ORG

Distribution Total Factor Productivity Preliminary Findings for Hydro One and the Ontario Industry

STEVE FENRICK

[email protected]

OCTOBER 5, 2016

Page 2: Distribution Total Factor Productivity Preliminary ... · Distribution Total Factor Productivity Preliminary Findings for Hydro One and the Ontario Industry STEVE FENRICK FENRICKS@POWERSYSTEM.ORG

Project Overview

Board’s March 12, 2015 Decision in EB-2013-0416, page 17:

“The OEB sees value in Hydro One measuring its own total factor productivity over time to be able to demonstrate improvement in productivity to its customers and the OEB. The OEB leaves it to Hydro One to determine its preferred total factor productivity study method. However, the period of the study should include years at least going back to 2002. The results of the study must be filed as part of Hydro One’s next rates application.”

2

Page 3: Distribution Total Factor Productivity Preliminary ... · Distribution Total Factor Productivity Preliminary Findings for Hydro One and the Ontario Industry STEVE FENRICK FENRICKS@POWERSYSTEM.ORG

TFP Study Items

Three key study items:1. Hydro One 2002-2015 TFP trend using revenue-related outputs

of # of customers, kWh deliveries, and peak demand2. Adjusted Hydro One TFP trend by incorporating employee

safety and reliability (SAIFI and CAIDI)3. Updated PEG (Board Staff Consultant) Ontario industry TFP

study to 2015 Previous result was 2002-2012

3

Page 4: Distribution Total Factor Productivity Preliminary ... · Distribution Total Factor Productivity Preliminary Findings for Hydro One and the Ontario Industry STEVE FENRICK FENRICKS@POWERSYSTEM.ORG

Research Item #1: Hydro One Unadjusted TFP

“Unadjusted” means the outputs are only based on revenue-related billing determinants Does not incorporate other performance-related

metrics

Outputs are # of customers, kWh’s delivered, and maximum peak demand

Outputs and output weights same as used in 4GIR OM&A expense definitions same as 4GIR Capital additions used HONI actual plant

additions rather than estimated amounts

4

Page 5: Distribution Total Factor Productivity Preliminary ... · Distribution Total Factor Productivity Preliminary Findings for Hydro One and the Ontario Industry STEVE FENRICK FENRICKS@POWERSYSTEM.ORG

One Major Difference from 4GIR Study

PSE used the North Atlantic U.S. Handy-Whitman of Public Utility Construction Cost Indexes for “Total Distribution Plant” to measure capital asset price inflation PEG used the Canadian Electric Utility Construction

Price Index (EUCPI) in 4GIR study

Reasons for Using Handy-Whitman Index:1. TFP study is for distribution functions only2. EUCPI appears to contain financing costs which

skews measure of asset price inflation3. EUCPI has been discontinued after its 2014 data

release

5

Page 6: Distribution Total Factor Productivity Preliminary ... · Distribution Total Factor Productivity Preliminary Findings for Hydro One and the Ontario Industry STEVE FENRICK FENRICKS@POWERSYSTEM.ORG

Hydro One Unadjusted TFP Preliminary Results

2002-2015 average annual TFP trend declining by 1.4%

Much of the decline occurred from 2005 to 2010

Since 2010 average trend is -0.4%

6

Year Output Quantity Index

Input Quantity Index TFP Index

2002 1.00 1.00 1.002003 1.02 1.01 1.002004 1.02 1.00 1.022005 1.04 1.03 1.012006 1.04 1.08 0.962007 1.05 1.17 0.892008 1.06 1.17 0.902009 1.06 1.22 0.862010 1.06 1.26 0.842011 1.07 1.26 0.842012 1.07 1.26 0.852013 1.07 1.32 0.812014 1.07 1.35 0.802015 1.08 1.30 0.83

Average Annual Growth Rates2002-2015 0.6% 2.0% -1.4%2002-2010 0.7% 2.9% -2.1%2010-2015 0.4% 0.7% -0.4%

Page 7: Distribution Total Factor Productivity Preliminary ... · Distribution Total Factor Productivity Preliminary Findings for Hydro One and the Ontario Industry STEVE FENRICK FENRICKS@POWERSYSTEM.ORG

Research Item #2: Hydro One Adjusted TFP

PSE incorporated within the Output Quantity index1. 3-year rolling average of HON’s employee safety

trend (no data prior to 2004) Weight based on trackable safety costs of HON

2. 3-year rolling average of HON’s SAIFI and CAIDI trends (no data prior to 2002) Weight based on 2009 paper on reliability costs issued

by the Lawrence Berkeley National Laboratory and prepared for the U.S. Department of Energy

Makes the TFP trend more indicative of the performance trend of HON More comprehensive than unadjusted TFP but still

not fully comprehensive

7

Page 8: Distribution Total Factor Productivity Preliminary ... · Distribution Total Factor Productivity Preliminary Findings for Hydro One and the Ontario Industry STEVE FENRICK FENRICKS@POWERSYSTEM.ORG

Hydro One Adjusted TFP Preliminary Results

2002-2015 average annual TFP trend declining by 0.9%

Much of the decline occurred from 2005 to 2010

Since 2010 average trend is +0.5%

8

Year TFP (unadjusted)

TFP with Safety

Adjustment Only

TFP with Reliability

Adjustment Only

TFP with Safety and Reliability

Adjustment2002 1.00 1.00 1.00 1.002003 1.00 1.00 1.00 1.002004 1.02 1.02 1.02 1.022005 1.01 1.01 1.02 1.022006 0.96 0.96 0.99 0.992007 0.89 0.90 0.91 0.912008 0.90 0.90 0.92 0.922009 0.86 0.86 0.88 0.882010 0.84 0.85 0.86 0.862011 0.84 0.85 0.86 0.882012 0.85 0.88 0.87 0.902013 0.81 0.84 0.83 0.862014 0.80 0.84 0.81 0.852015 0.83 0.88 0.84 0.88

Average Annual Growth Rate2002-2015 -1.4% -1.0% -1.4% -0.9%2002-2010 -2.1% -2.0% -1.9% -1.8%2010-2015 -0.4% 0.6% -0.5% 0.5%

Page 9: Distribution Total Factor Productivity Preliminary ... · Distribution Total Factor Productivity Preliminary Findings for Hydro One and the Ontario Industry STEVE FENRICK FENRICKS@POWERSYSTEM.ORG

Research Item #3: Ontario TFP Update

Updated Ontario TFP to 2015 PEG found 2002-2012 Ontario TFP trend = -0.3%

TFP trend used as basis for X-factor

Implemented PEG methodology and data except: Escalated EUCPI in 2015 by Handy-Whitman index

due to it being discontinued

Used OEB Yearbook values for 2013, 2014, and 2015 for capital additions

9

Page 10: Distribution Total Factor Productivity Preliminary ... · Distribution Total Factor Productivity Preliminary Findings for Hydro One and the Ontario Industry STEVE FENRICK FENRICKS@POWERSYSTEM.ORG

Purpose of Ontario TFP

PEG used Ontario TFP as basis for recommendation on 4GIR X-factor Purpose was not to examine individual distributors or

industry performance trend This is why revenue-related outputs are used and not

unrelated outputs PSE’s adjusted TFP is more comprehensive of

examining performance Ontario TFP update is more appropriate for X-factor

calibration given the current 4GIR construct Hydro One specific TFP should not be used for X-

factor calibration X-factor needs to be externally-driven and based on

revenue-related billing determinants

10

Page 11: Distribution Total Factor Productivity Preliminary ... · Distribution Total Factor Productivity Preliminary Findings for Hydro One and the Ontario Industry STEVE FENRICK FENRICKS@POWERSYSTEM.ORG

Ontario Industry TFP Preliminary Results

2002-2015 average annual TFP trend declining by 0.9%

Much of the decline occurring from 2010

11

Year Output Quantity Index

Input Quantity Index TFP Index

2002 100.0 100.0 100.0 2003 102.1 101.3 100.8 2004 104.0 101.8 102.1 2005 106.8 102.4 104.3 2006 108.2 103.5 104.5 2007 109.7 106.6 102.9 2008 110.6 108.1 102.3 2009 110.8 108.4 102.2 2010 111.8 108.6 103.0 2011 112.8 110.9 101.7 2012 114.0 116.7 97.7 2013 114.8 123.0 93.3 2014 115.6 126.5 91.4 2015 115.6 130.2 88.8

Average Annual Growth Rate2002-2015

1.1% 2.0% -0.9%2002-2010

1.4% 1.0% 0.4%2010-2015

0.7% 3.6% -3.0%

Page 12: Distribution Total Factor Productivity Preliminary ... · Distribution Total Factor Productivity Preliminary Findings for Hydro One and the Ontario Industry STEVE FENRICK FENRICKS@POWERSYSTEM.ORG

Interpretation of Negative TFP Trends

Measured outputs growing slower than measured inputs

Possible Causes:1. Declining efficiency2. Increasing of outputs not being measured within

TFP calculation (e.g., customer service, regulatory requirements, environmental stewardship, power quality)

Adjusted TFP of Hydro One partially corrects for this

3. External circumstances changing over time Slower output growth in western economies

4. Aging capital infrastructure past its useful life in need of replacement

12

Page 13: Distribution Total Factor Productivity Preliminary ... · Distribution Total Factor Productivity Preliminary Findings for Hydro One and the Ontario Industry STEVE FENRICK FENRICKS@POWERSYSTEM.ORG

Steve Fenrick, M.S.

Leader, Economics & Market Research Group

608-268-3549

608-334-5994 (mobile)

[email protected]

13

Thank You: