Design and Detail Report

Embed Size (px)

Citation preview

  • 8/2/2019 Design and Detail Report

    1/106

  • 8/2/2019 Design and Detail Report

    2/106

    CONTENTS

    INTRODUCTION

    project outline

    client

    urban context - high street 2012

    high street 2012 initiatives

    64-68 whitechapel high street

    proposed site

    project timeline

    urban context - failing high street

    urban context - encroaching development

    urban strategy - historical grain

    urban strategy - high street

    programme

    KEY SPACES

    high street

    market area

    exhibition space

    cinema suspended

    energy cells

    gym - visual connection

    greenhouse - energy cultivation

    circulation

    scheme diagram

    GENERAL ARRANGEMENT DRAWINGS

    basement plan

    ground floor plan

    first floor plan

    second floor planthird floor plan

    section a

    section b

    perspective section c

    perspective section d

    SUPERSTRUCTURE

    basement & ground floor

    steel frame & circulation

    pods & cinema

    facade

    steel frame

    FACADE

    facade render

    elgin marbles precedent

    historical photos

    breaking down facade

    recreating the facade

    recreating the facade cont.

    moment connections

    key views - aldgate east

    key views - osborn street

    key views - whitechapel high street

    GROUND FLOOR

    link to high street

    market

    exhibition space

    transformation

    CIRCULATION

    external space

    movement

    foyerstructure

    pressure pads

    exposed services

    lighting strategy - day

    lighting strategy - night

    4.0

    4.1

    4.2

    4.3

    4.4

    4.5

    5.0

    5.1

    5.2

    5.3

    5.4

    5.5

    5.6

    5.7

    5.8

    5.9

    5.10

    6.0

    6.1

    6.2

    6.3

    6.4

    7.0

    7.1

    7.2

    7.37.4

    7.5

    7.6

    7.7

    7.8

    1.0

    1.1

    1.2

    1.3

    1.4

    1.5

    1.6

    1.7

    1.8

    1.9

    1.10

    1.11

    1.12

    2.0

    2.1

    2.2

    2.3

    2.4

    2.5

    2.6

    2.7

    2.8

    2.9

    3.0

    3.1

    3.2

    3.3

    3.43.5

    3.6

    3.7

    3.8

    3.9

  • 8/2/2019 Design and Detail Report

    3/106

  • 8/2/2019 Design and Detail Report

    4/106

  • 8/2/2019 Design and Detail Report

    5/106

  • 8/2/2019 Design and Detail Report

    6/106

    1.3 URBAN CONTEXT - HIGH STREET 2012

    the high street 2012 project was initially

    conceived to enhance the proposed marathon

    route for the london 2012 games. the marathon

    was to pass along the a11 [whitechapel high

    street] to the olympic park in stratford.

    the marathon route has since been changed and

    will no long end in the olympic park and will

    not enter east london at all. however the high

    street 2012 project is still going ahead to

    enhance what will be one of the main routes to

    the olympic stadium for spectators and officials

    visiting the games but staying in central london.

    original london 2012 marathon route

    aldgate

    n

    central london

    olympic park

  • 8/2/2019 Design and Detail Report

    7/106

    whitechapel high st.

    St.Botolph

    St.

    commercialSt.

    lema

    n

    St.

    manse

    llst.

    A

    a. braham street park

    braham street park was completed in february 2010, funded by private

    sector s106 contributions and the lda. the new park sits on what was

    previously part of a busy road system and now provides a more tranquil

    space for local residents, visitors and people who work in the area.

    high street 2012

    braham street park sits on a narrow strip of land, flanked on both

    sides by tall office buildings. the park has a very corporate feel, the

    hard landscaping and sharp angled lines within the design of the park

    mimic those found within the city of london to the west. it is sold as a

    park for residents but it is sparsely populated with smokers from the

    adjoining office buildings and the occasional person eating their lunch.

    it is overshadowed for most of the day by the surrounding buildings and

    has no link the whitechapel high street itself. it is not obvious to anyone

    passing along the high street that there is even a park there.

    the high street 2012 route was split geographical sections and the

    partners identified area based initiatives for each of those areas. the

    proposed site falls within the aldgate section of the high street where

    the following projects have been undertaken.

    b. 64-68 whitechapel high street

    improvement works to the six buildings were concentrated on the front

    elevations and parts of the buildings that faced the high street. the

    buildings have benefitted from extensive conservation repair

    high street 2012

    the project involved the complete rebuilding of the two facades that face

    onto whitechapel high street, the original brickwork had been render over

    and the stonework damaged and removed. the render and original brick

    work was completely stripped off the elevation and new brick slips put in

    place. the project was more of a rebuild than a restoration with new stone

    work and mouldings being created using historic photographs to mimic the

    original building. there were no alterations to the interiors, or the rear

    elevations of the building, the project was merely a facelift.

    c. alt

    a series o

    tree plant

    seating ar

    stand on t

    the park w

    aimed to r

    a communit

    dig were u

    created a

    what was t

    and appre

    has been.

    1.4 HIGH STREET 2012 INITIATIVES

  • 8/2/2019 Design and Detail Report

    8/106

    1.5 64-68 WHITECHAPEL HIGH STREET

    improvement works to the six buildings were

    concentrated on the front elevations and parts

    of the buildings that faced the high street.

    the buildings have benefitted from extensive

    conservation repair.high street 2012

    the works to 64- 68 whitechapel high street were

    concentrated on the parts of the building that

    will be seen during the 2012 olympics, on the

    route from the city to the olympic park.

    they are creating a false facade which they have

    created based on photos and documents from the

    past. they claim they are restoring the building

    to its former glory but they are only creating an

    impression of an idealised past. by recladding the

    facades of the building the buildings only mimic

    what they once were; they are no longer used

    in the same way and their context has changed.

    the past is always looked on as a better time

    but realistically times were just as hard, if not

    harder back when the buildings were constructed;

    the area was full of some of the worst slums in

    london.

    replicating history is entirely different to retaining

    history. mimicking history cannot replicate the

    layers of history that build up on a building over

    its lifetime. rebuilding a facade completely removes

    these historical layers. conservation allows

    historical layers to build up whilst maintaining

    the original fabric. the proposed works are not

    conservation but a pastiche, creating a disneyfied

    version of the past.

  • 8/2/2019 Design and Detail Report

    9/106

    n

    conservation area

    site

    whitech

    apel

    highstreet

    osbornstreet

    0 0100 200m

    C

    D

    B

    A

    E

  • 8/2/2019 Design and Detail Report

    10/106

    1.7 PROJECT TIMELINE

    the project is set two years in the past, in 2010, when the it was announced that the

    london 2012 marathon route was no longer passing along the a11 through east london

    and was going to take place in central london instead. the project envisages that after

    this announcement the funding for the high street 2012 project aimed at improving the

    high streets along the original marathon route is dramatically reduced. therefore the

    projects that were originally proposed on the route are suspended until new investors

    come forward to take on the projects.

    already involved in the london 2012 olympics as the official energy s

    are looking to undertake projects along the olympic route and dec

    project at 64-68 whitechapel high street. the tight timescale between p

    the start of the olympic games when it must be completed and ready fo

    of effects on the professional context of the project which are descr

    the report.

    february 2009high street 2012 project initiated

    july 2008

    london wins olympic games

    may 2010

    announcement

    that london 2012

    marathon route

    no longer passing

    through east london

    may 2010

    funding for

    restoration works to

    64-68 whitechapel

    high street cut.

    all proposed works

    cancelled

    aug 2010

    edf energy, as official

    energy supplier to the

    london 2012 games,

    come forward as new

    investor.

    new brief formed for

    a building powered by

    movement.

    nov 2010application submitted

    to local authority for

    revised scheme.

    feb 2011

    planning approva

    received for rev

    scheme

    june 2010

    site start date for

    works to 64-68

    whitechapel high

    street

    nov 2010

    works to 64-68

    whitechapel high

    street completed

    jan 2010

    planning permission

    granted for works

    to 64-68 whitechapel

    high street

    redefined timeline for this project

    actual timeline

  • 8/2/2019 Design and Detail Report

    11/106

    n

    high street 1

    high street 1

    high street 2

    the only unchanged use 1841 -2

    pubs/restaurantsgroceries/dairy/butchers

    fabricschemist

    clothingprinting

    financialother

  • 8/2/2019 Design and Detail Report

    12/106

    1.9 URBAN CONTEXT ENCROACHING DEVELOPMENT

    CENTRAL HOUSE LONDON METROPOLITAN UNIVERSITY

    central house marks the point on the high street that the largescale, high rise office buildings of the city meet the smaller

    scale buildings of the high street. at 6 storeys it acts as an

    intermediate between the two.

    PROPOSED SITE

    the proposed site is the first

    set of surviving historical

    buildings on the south side

    of the road as you travel

    east along whitechapel high

    street.

    PLANNING APPLICATION PA/08

    this site has planning permissi

    which will provide 84,305sq.m

    retail use. once built it wil

    character of the high street

    for 5 years and closed off

    detrimental effect on the high

    prior to their demolition the

    summit sports centre serving t

  • 8/2/2019 Design and Detail Report

    13/106

  • 8/2/2019 Design and Detail Report

    14/106

    th

    hibl

    st

    fa

    st

    th

    an

    be

    br

    bo

    bu

    an

    gi

    re

    pr

    of

    th

    a

    af

    by

    re

    st

    1

  • 8/2/2019 Design and Detail Report

    15/106

  • 8/2/2019 Design and Detail Report

    16/106

  • 8/2/2019 Design and Detail Report

    17/106

  • 8/2/2019 Design and Detail Report

    18/106

    2.2 MA

    the open g

    area durin

    of market

    and go an

    usually ot

    plots. unl

    were previ

    never be

    their good

    reinvigora

    in decline.

  • 8/2/2019 Design and Detail Report

    19/106

    at night th

    the groun

    space for

    the doubl

    of the cin

    installatio

    structure

    the under

    used to pr

    the exhibit

    the ticket

    transluce

    centre ofpeople into

    2.3 EXH

  • 8/2/2019 Design and Detail Report

    20/106

  • 8/2/2019 Design and Detail Report

    21/106

    the gym pods, bar and greenhouses will be

    constructed as cells which combine in the

    steel frame to create a battery of energy

    producing components.

    2.5 ENERGY CELLS

  • 8/2/2019 Design and Detail Report

    22/106

    the cells will be constructed from

    translucent panels which will a light

    internal environment but will also allow a

    visual connection between their interiors

    and the high street. the translucent panelswill only allow the shadows of movement to

    be visible, giving an implied idea of motion

    within the building but not make it feel like a

    gold fish bowl for the users.

    when the pods are in use at night the internal

    lights will make them glow identifying which

    pods are being used to create energy. the

    pods will shut down when not in use.

    2.6 GYM VISUAL CONNECTION

  • 8/2/2019 Design and Detail Report

    23/106

    th

    bu

    al

    te

    feth

    wh

    to

    ou

    th

    ma

    2.

    north

    noon

    north

    north

    noon

    noon

    n

    greenhouse pods

    market area

    winter sunpath

    autumn/spring sunpath

    summer sunpath

    gym pods

    cinema

  • 8/2/2019 Design and Detail Report

    24/106

  • 8/2/2019 Design and Detail Report

    25/106

    2.9 SCHEME DIAGRAM

    n

    greenhouse pods

    tickets/reception

    market/exhibition area

    bar

    basement plant and service areas

    gym pods

    circulation/foyer

    cinema

    vertical circulation

    roof

    second floor

    first floor

    ground floor

    basement

    area schedule [m2]

    market/exhibition space

    tickets/reception

    circulation/foyer

    bar

    gym pods

    greenhouse pods

    external rooftop growing area

    cinema

    basement:

    changing/wcs

    office

    storage

    plant

    322

    12

    140

    25

    140

    100

    140

    90

    80

    15

    68

    67

  • 8/2/2019 Design and Detail Report

    26/106

  • 8/2/2019 Design and Detail Report

    27/106

    A B

    D

    E

    C

    D D D

    DF

    G

    H

    J

    LMNO

    I

    K

  • 8/2/2019 Design and Detail Report

    28/106

    R

    RR

    R

    QC

    P

  • 8/2/2019 Design and Detail Report

    29/106

    S

    V U U U U

    U

    C

  • 8/2/2019 Design and Detail Report

    30/106

    S

    V U U U U

    U

    C

  • 8/2/2019 Design and Detail Report

    31/106

    X

    Y

  • 8/2/2019 Design and Detail Report

    32/106

    3.6 SECTION A 1:100

    exhibition storemarket storeliftrooflight aboveunheated corridorofficefood storemale changing/showersmale wcsfemale changing/showersfemale wcsurine electrolysishydrogen combustionenergy storeventilation plantmarket/exhibition space

    tickets/receptionrooflight to basementmesh walkwaycinemagym podsbarexternal growing spaceheated greenhouses

    ABCDEFGHIJKLMnop

    qrstuvxy

    B M

    PQ

    U

    U S

    S

    YX

    T

    E

    R

  • 8/2/2019 Design and Detail Report

    33/106

    P

    T

    YYYYY

    HJLMNO

  • 8/2/2019 Design and Detail Report

    34/106

    T

    YYYY

    JLMNO

  • 8/2/2019 Design and Detail Report

    35/106

    3.9

    ex

    ma

    lif

    ro

    un

    of

    fo

    ma

    ma

    fe

    fe

    ur

    A

    B

    C

    D

    E

    F

    G

    H

    I

    J

    K

    L

    U

    UT

    P

    I H E

    S

    F

    YX

    S

  • 8/2/2019 Design and Detail Report

    36/106

    4.1 BASEMENT & GROUND FLOOR

  • 8/2/2019 Design and Detail Report

    37/106

    basement

    the basement will be constructed from in situ reinforced concrete. although a

    basement already existing on the site this will be dug out and completely rebuilt

    to create a stable base for the new building that can support all the new loads.

    the basement will be constructed as two large concrete spaces separated by

    a concrete corridor. the basement partitions will be constructed from timber

    studs allowing for flexibility in the space in the future

    ground floor

    the ground floor will be constructed from a o

    slab with integral supporting beams. it will sp

    walls and the central corridor walls on the

    will be positioned in the basement where extra

    4.2 STEEL FRAME & CIRCULATION

  • 8/2/2019 Design and Detail Report

    38/106

    steel frame

    a braced steel frame will provide the super-structure for the

    building above ground. the steel frame will sit along the lines of the

    concrete basement walls and on the lines of the floor slab beams to

    create a continuity of the structural load forces.

    circulation walkways

    the circulation walkways will sit on the steel

    be constructed of galvanized steel to differen

    steel frame. they will be one of the first parts

    allowing the construction team platforms to w

    4.3 PODS AND CINEMA

  • 8/2/2019 Design and Detail Report

    39/106

    cinema

    the cinema will be suspended in a void in the steel super-structure.

    it will hanging from the third floor section of the steel frame and

    be braced back to the frame at a lower level. its shell will be a

    lightweight steel construction, braced to create a rigid box.

    pods

    the gym, bar and greenhouse pods will be con

    insulated kalwall panels within a lightweigh

    floors and roofs will all be constructed from

    quick, simple construction. they will be su

    superstructure with bolted bracket connectio

    4.4 FACADE

  • 8/2/2019 Design and Detail Report

    40/106

    facade

    the historic facade panels will be precast concrete and will be

    craned into place on site and bolted with movement joints to the

    steel frame.

  • 8/2/2019 Design and Detail Report

    41/106

  • 8/2/2019 Design and Detail Report

    42/106

  • 8/2/2019 Design and Detail Report

    43/106

    5.1 FACADE RENDER

  • 8/2/2019 Design and Detail Report

    44/106

    niall mclaughlin architects have undertaken

    a project at the london 2012 olympic park

    where they have clad the building with casts

    concrete friezes of the elgin marbles from the

    parthenon. the elgin marbles which are housed

    at the british museum, were digitally scanned

    then grp lined rubber moulds were produced

    for the concrete casting process. the casts

    were made using a white cement to give them a

    brighter appearance.

    the casts elude to a history without becoming

    a pastiche of the parthenon. this projects

    has the same aim to recreate and celebrate a

    historical facade on whitechapel high street

    that sits within a conservation area. the facade

    will be recreated in concrete casts and broken

    up to elude to the history of the site by turning

    the facade into more of a sculpture than a

    pastiche.

    The Parthenon stones were made in a particular

    place at a particular time. Their deracination

    and constant re-idealisation has made them into

    something else something iconic that people

    recognise, like a picture of Elvis

    niall mclaughlin, concrete quarterly

    autumn 2011

    5.2 ELGIN MARBLES PRECEDENT

  • 8/2/2019 Design and Detail Report

    45/106

    the historical facade of 64-68 whitechapel

    high street has disappeared, only the

    structure of the facade remains. the

    historical stonework and window frames have

    been removed or damaged over time. to create

    casts of the facade as it was constructed

    a virtual 3d model will be produced which

    can then be used to create moulds for the

    casting of the concrete panels

    5.3 HISTORICAL PHOTOS

  • 8/2/2019 Design and Detail Report

    46/106

  • 8/2/2019 Design and Detail Report

    47/106

    5.5 RECREATING FACADE

    expanded polystyrene moulds will be cnc cut using the virtual 3d model.

    due to the variety of different casts required it would not be worth

    creating rubber or grp moulds as each mould will only be used a maximumof three times. once the moulds have been used they will be recycled

    where they can be broken down and used in the packaging industry or as

    an additive in lightweight concrete.

    steel fixing brackets will be added to the mould before the concrete is

    poured.

    the mould will be cast from a white cement to emphasise the play of light

    across the historical details. the fixing brackets will be cast into the

    precast panels

    the precas

    building.

  • 8/2/2019 Design and Detail Report

    48/106

    5.6 RECREATING FACADE

    the facade panels will be fixed to a steel i section ring beam that willterminate the cantilevered sections of the projecting steel frame.

    the facade panels will be fixed using two types of connection. the bottomconnection will be load bearing and the top connections will be for

    restraint. the bottom connection is made up of a steel plate, strengthened

    with flanges which bolts directly to the steel frame. the steel plate is

    drilled with elongated bolt holes to allow for alignment of the panel

    and steel structure. the top connections do not take any load but just

    tie the panels back to the frame. they allow movement in three directions

    via the elongated bolt holes and nylon or teflon washers. the aim of the

    top connections is to decouple the different movement of the steel from

    that of the concrete.

    single glathe window

    actually b

    rhythm of

  • 8/2/2019 Design and Detail Report

    49/106

    to support the proj

    the steel structure

    to do this the ste

    out of the facad

    the columns using

    effectively create a

    tied back all the w

    allowing it to cant

    required to create

    the perpendicular s

    in the adjacent imabeams are cantileve

    5.7 MOMENT CO

  • 8/2/2019 Design and Detail Report

    50/106

    ALDGATE

    EAST

  • 8/2/2019 Design and Detail Report

    51/106

    OSB

    ORN

    STREET

  • 8/2/2019 Design and Detail Report

    52/106

    5.10 KEY MASSING

    WHITECHAPE

    on the main route to

    west elevation will a

    approach closer and tit will become more ob

    has been morphed int

    WHITECHAPEL

    HIGH

    STREET[WEST]

  • 8/2/2019 Design and Detail Report

    53/106

  • 8/2/2019 Design and Detail Report

    54/106

    the

    flo

    sec

    high

    the

    str

    be a

    loc

    hapto h

    6.1

    A

    B

  • 8/2/2019 Design and Detail Report

    55/106

    6.2 MARKET

    C

    visual connection to walkways abovediffused light coming through gym pods abovewhite painted steel frame allows colours ofmarket to define the spacesteel frame allows traders to hang objects

    cinema blackback of site oplots will besmall plots plots at the m

    ABC

    D

    efgh

    B

  • 8/2/2019 Design and Detail Report

    56/106

    6.3 EXHIBITION SPACE

    A

    E

    F

    G

    C

    cinema ticket office glows and acts as a beacothe gym pods glow when in use identifying ththere is energy being created within them.the high street lighting leaks into the buildinblurring the buildings boundary.

    AB

    C

  • 8/2/2019 Design and Detail Report

    57/106

    ground floor

    basement

  • 8/2/2019 Design and Detail Report

    58/106

  • 8/2/2019 Design and Detail Report

    59/106

    the circulation space will be external space

    that cuts through the centre of the building.

    this happens for two reasons; to reduce the

    heating load on the building and its energy

    consumption by making the circulation space

    unheated and open to the elements and also

    to continue the theme of breaking down the

    boundaries between the building and the high

    street. whilst moving through the building

    you will feel the wind and elements reminding

    you that the building is conceived as an open

    structure for the local community that is

    one with the high street.

    7.1 EXTERNAL SPACE

    n

    market area

    circulation walkways

    external space

  • 8/2/2019 Design and Detail Report

    60/106

  • 8/2/2019 Design and Detail Report

    61/106

    at the we

    on the f

    walkways

    end pods

    are bars

    grown in

    be sold

    healthy,

    convert i

    in turn ca

    these spa

    cinema u

    directly

    space un

    7.3 FO

  • 8/2/2019 Design and Detail Report

    62/106

    A

    b

    c

    i

    j

    k

    def

    gh

  • 8/2/2019 Design and Detail Report

    63/106

    the walkways will generate

    people pass across them.

    of walkway will be support o

    pressure pads which will ea

    electricity as someone walks

    walkway. the pressure pads wil

    electric materials which crea

    as a mechanical force is app

    more information on the techn

    pressure pads is included in

    systems section of this report

    7.5 PRESSURE PADS

  • 8/2/2019 Design and Detail Report

    64/106

    the service runs o

    the circulation ro

    that the people pa

    become part of th

    so the circulation

    the exposed serv

    the energy system

    retro fitted with

    develop and test t

    7.6 EXPOSED

    A

    E

  • 8/2/2019 Design and Detail Report

    65/106

    B

    B

    C

    C

    C

    C

    G

    F

    diffuse daylight from the north

    daylight enters pods through

    translucent kalwall panels

    kalwall panels diffuse the light into

    the interior of the pods

    light from inside pod is diffused into

    circulation zone

    direct sunlight from south

    greenhouse pods heated by solar gain

    from direct sunlight from south

    mesh walkway between greenhouses onroof acts as solar shade to shade gym

    pods below

    a

    b

    c

    d

    e

    f

    g

    7.7 LIGHTING STRATEGY - DAY

  • 8/2/2019 Design and Detail Report

    66/106

    the circulation spaces will

    light tubes to create a low

    solution. the lights will be

    pressure pads which will

    lighting . this means the lig

    the movement of people throu

    at night creating a visual of t

    the lights will be fitted with s

    they only light the area of ci

    them that the movement is tak

    shade will also provide pro

    light from the elements as t

    is external space. the lights external grade.

    the lights will be on a timer w

    off after a short period of tim

    also be fitted with light sens

    not activated by people walk

    walkways during the day.

    7.8 LIGHTING STRATEGY

  • 8/2/2019 Design and Detail Report

    67/106

  • 8/2/2019 Design and Detail Report

    68/106

    grchemical energy [food]

    electrical energy

    JUICE

    BAR

    chemicalenergy>kineticenergy

    kineticenergy

    >electricalenergy

    grownproduce>highenergyjuices

    GYMPODS

    electrical energy to rest of building

    the pods are the main areas of

    energy production, there are 3

    types of pod in the building; the

    greenhouses which are used to

    test out growing technologies in

    the tight urban environment of the

    site, the juice bars that convert

    the grown produce into high energy

    drinks and food to be consumer by

    the users of the gym pods where

    the energy they expel is converted

    into electrical energy and heat to

    power the building.

    8.1 ENERGY CELLS

  • 8/2/2019 Design and Detail Report

    69/106

    the diagrams above show the relative

    locations of the 3 types of pods

    gym pods juice bar pods greenhouse

    8.2 PODS KEY

  • 8/2/2019 Design and Detail Report

    70/106

    kalwall is the most highly insulating, diffuse

    light-transmitting, structural composite

    technology in the world. the company has

    perfected a unique composite sandwich

    panel that combines controlled, usable,

    natural daylight with the ultimate in energy

    efficiency. lightweight, shatterproof, and

    rapidly installed, kalwall has unrivalled

    structural integrity... kalwall can be an

    entire freestanding structure.

    http://www.kalwall.com/about.htm

  • 8/2/2019 Design and Detail Report

    71/106

    the specification for the gym pods will be

    a panel with a high insulation value, low

    solar heat gain coefficient and medium light

    transmission value [the solar heat gain

    coefficient increases with light transmission

    so a medium light transmission value with give

    a low heat gain coefficient but still provide

    the translucent qualities required]

    this specification would be a 100mm thick

    panel with the white coating to the exterior

    face and crystal coating to the interior

    face with fibreglass insulation which would

    provide a u-value of 0.20 w/m2

    k, a lighttransmission value of 18% and heat gain

    coefficient of 0.24.

    acrylic face sheets impregnated

    with pigment

    translucent fibreglass insulation

    thermally broken aluminium is grid

    core

    a

    b

    c

  • 8/2/2019 Design and Detail Report

    72/106

  • 8/2/2019 Design and Detail Report

    73/106

    fram

    supe

    unde

    sect

    shap

    fram

    hole

    fram

    on t

    in th

    bracin 3

    to t

    allo

    supe

    bearing bracket

    restraint bracket

    8.6

    A

    B

    B

    A

  • 8/2/2019 Design and Detail Report

    74/106

    the

    that

    day

    be a

    crea

    lighglow

    be p

    glow

    and

    link

    the

    dire

    they

    so t

    pod

    wal

    so t

    in t

    ligh

    8.7

  • 8/2/2019 Design and Detail Report

    75/106

    the pods w

    services w

    sections o

    modified towill be fitt

    both the i

    can be at

    required.

    the servic

    and outpu

    and ventil

    component

    arrangeme

    the buildin

    to be cha

    disconnec

    plug-in pa

    this will a

    energy cr

    the buildin

    8.8 PLU

    A

    B

    C

    D

  • 8/2/2019 Design and Detail Report

    76/106

    A

    D

    E

    B

    C

    the gym pods will be mechanica

    to allow greater control than

    ventilation system. the pods wispaces heated only by the bod

    users and the heated produced

    machines.

    cool external air, or air from t

    cooling system when the

    temperature is high, will be ent

    low level and will be warmed b

    the gym [the average person g

    of heat whilst exercising] and

    air will be extracted through a

    at high level. the extracted a

    utilised to heat other parts o

    8.9 HEATING & COOLING

    mechanical ventilation inlet a

    heat produced form bodies an

    air warmed by bodies and equwarm air extracted at high le

    insulated kalwall panels sto

    a

    b

    cd

    e

  • 8/2/2019 Design and Detail Report

    77/106

  • 8/2/2019 Design and Detail Report

    78/106

    the cinema is designed

    rest of the building. this all about movement

    visualising movement

    and the energy creati

    linked to it.

    the cinema is a place

    area of the building t

    energy without creati

    is effectively the part

    leaches off the rest o

    the rest of the buildin

    and open the cinema is a

    the cinema is designed

    that hangs within a voi

    clad in black to creat

    it and the light in the

    9.1 HANGING ABO

  • 8/2/2019 Design and Detail Report

    79/106

    the suspended cinema structure w

    constructed from a steel shell. steel

    strong in tension which is important

    designing a hanging structure.

    the shell will be made up of a series of

    rings constructed from rolled steel se

    the roof and floor beams which have a m

    span of 8m will be constructed from

    deep castellated beams. by cutting a sta

    beam to create a castellated beam its d

    almost doubled whilst its self weight r

    the same. in the hanging structure the we

    the structure is very important so a caste

    9.2 STRUCTURE - SHELLabcd

    600mm castellated steel beam200mm uc rolled steel i sectionsteel c section cross bracing to all bays, except;steel c section symmetrical portal bracing to bays with door openings

    A

    B C

    D

  • 8/2/2019 Design and Detail Report

    80/106

    to suspend the cinema the steel super-

    structure of the building will need to be

    braced. by cross bracing the bays above the

    cinema the third floor structure that spans

    across the void that the cinema hangs in

    will effectively become a 1 storey deep beam

    creating a rigid structure to suspend the

    cinema from. a hanging structure will always

    have a tendency to swing or displace underforce so the cinema structure, as well as

    being hung from the structure above, will

    be braced to the structure below to prevent

    any movement.

    cross

    9.3 SUSPENDED WITHIN FRAME

    the drawing shows one of the rings that

    9.4 STRUCTURE - SUSPENSIONB

  • 8/2/2019 Design and Detail Report

    81/106

    the drawing shows one of the rings that

    will create the cinema shell and how it

    is suspended within the void in the steel

    superstructure. the rings of the cinema

    structure will be constructed individually

    and hung with the super-structure before

    being braced together to create the shell of

    the cinema.

    each ring will be suspended from three

    points from the structure above. the points

    of suspension will be on nodes where thebracing of the frame above meets vertical

    elements of the steel frame. these will be

    the strongest points of the frame where the

    loads can be transferred most efficiently.

    to match the wedge shaped cinema space the

    structure above has been splayed from the

    regular grid so that the suspension points

    follow the shape of the cinema below.

    each ring will be braced to the superstructure

    at a lower level to prevent it displacing

    under loads.

    steel ring section of cinema structure

    cross bracing of steel frame super-

    structure

    bracing node of super-structure

    cinema structure connected to super-

    structure at nodes

    cinema structure braced to super-

    structure at low level

    A

    B

    C

    D

    E

    E

    A

    D

    C

  • 8/2/2019 Design and Detail Report

    82/106

    A

    D

    D

    B

    C

    B

    C

  • 8/2/2019 Design and Detail Report

    83/106

    the hall will be

    construction, th

    internal acoustica

    external claddin

    will be of a t

    decoupled from acoustic suspens

    a layer of acous

    two building elem

    of noise through

    a layer of insula

    internal timber fr

    noise. to further

    the external cl

    resilient channel

    the wall, floor a

    clad in fibre ceme

    appearance of a s

    to contrast the c

    building. it will b

    facades as it wil

    exposed to the el

    9.6 EXPLODE

    A

    B

    C

    D

  • 8/2/2019 Design and Detail Report

    84/106

    E

    G

    H

    I

    J

    F

  • 8/2/2019 Design and Detail Report

    85/106

    ABCDEFGHIJKLMN

  • 8/2/2019 Design and Detail Report

    86/106

    LKJIHGFEDCBA

  • 8/2/2019 Design and Detail Report

    87/106

  • 8/2/2019 Design and Detail Report

    88/106

    eternit natura fibre cement cla

    aluminium z resilient fixing ch50mm aluminium channel fixingwaterproof membrane & 18mm w152mm uc steel column5Omm softwood timber studs i

    100mm insulation board behin50mm insulation board betwee18mm plywood sheathing to br50mm perforated timber insula480mm castellated steel beam

    a

    bcdefghijk

  • 8/2/2019 Design and Detail Report

    89/106

    th

    a

    h

    th

    tw

    th

    fr

    a

    ti

    pr

    th

    h

    st

    a

    a

    480mm castellated steel beamresilient channel floor hangetimber joists with integrated h150mm insulation board betwegypsum board22mm tongue and groove plywohardwood timber floor

    kLmnopq

    A

    B

    C

    D

    E

    F

    G

    H

    I

    J

    A B D C K L

    H

    C

    D

  • 8/2/2019 Design and Detail Report

    90/106

    the cinema space will be heated by the body heat

    of the users of the gym pods. the air from the gym

    pods will be mechanical extracted form the pods

    and will be passed through a heat exchange

    where it will warm cool fresh air which will then

    be mechanically ventilated into the cinema at low

    level. stale air will be extracted at high leve

    from the cinema.

    9.13 HEATING SCHEMATIC

    A

    BE

    F

    G

    warm air extracted for gym pods

    warm air from gym pods ducted to heat

    exchange unit in basement

    high level extract duct for exhaust air

    from gym pods after it passes through heat

    exchanger

    high level inlet for fresh air

    cool external air passes through hea

    exchanger where it is warmed by the warm ai

    extracted from the gym pods

    warmed air enters cinema at low leve

    providing the space heating

    stale air extracted from the cinema at hig

    levelexhaust air outlet for stale cinema air.

    a

    b

    c

    d

    e

    f

    g

    h

    warm air routes

    external air inlet

    exhaust air outlet

  • 8/2/2019 Design and Detail Report

    91/106

    9.15 HALL VENTILATION - COOLING

  • 8/2/2019 Design and Detail Report

    92/106

    realistically the hall should only need to be heated for short

    periods of time, once it is filled with over 100 people their combined

    body heat should keep the space at a warm temperature. the cooling

    system will be used to stop the cinema overheating when it is filled

    with people.

    when the external air temperature is lower than the required

    comfort temperature inside the building [17o - 20o] then fresh

    outside air can be ventilated into the cinema space to reduce the

    internal temperature. this will be ventilated at different speedsdepending on the relative temperatures of the external air and the

    internal environment - if the external air temperature is very low

    and the hall is not at full capacity the air change in the hall will

    be lower than if the external air temperature is higher and the hall

    is at capacity.

    cooling with external air evaporative cooling

    when the external air temperature is higher or very simila

    temperature of the cinema then cooling using untreated

    not be possible. the building will use an evaporative coo

    adds a mist of water vapour to the external air before it en

    the water vapour takes some of the heat out of the air

    then cool air enters the cinema to cool the space. the sy

    like the human body uses sweat to cool down, as the s

    from the body it removes heat from the surface of the s

    fits with the overall concept of the building which takes

    production from the movement and interaction of the huit [more information on evaporative cooling is contain

    systems section of this report]. the high level extract

    as it is warmed in the space and ensures a sufficient air

    moisture in the air building up in the space.

    9.16 PART M

  • 8/2/2019 Design and Detail Report

    93/106

    access to the cinema spac

    points, one at first floo

    bottom of the seating rak

    the cinema and the other a

    cinema into the top row

    floor is accessible by the l

    and two ambulant disabled

    part m of the building reg

    the requirement for whee

    auditorium spaces. in aud

    up to 600 people the req

    1% [rounded up to a who

    seating is given over to wh

    the cinema seats 125 peopl

    spaces will be required. pa

    that where this number is l

    must be a sufficient numb

    seats so that the numbe

    spaces can be increased to

    wheelchair spaces are 900

    removable sea

    permanent whe

    9.16 PART M

  • 8/2/2019 Design and Detail Report

    94/106

    10.1 THE BODY

  • 8/2/2019 Design and Detail Report

    95/106

    on a daily basis our average daily intake

    of energy is between 7030 - 10250 kj

    [1680 - 2450 kcal]. we use this to maintain

    passive bodily functions such as breathing

    , for physical activity and for growth and

    repair of our tissues. energy is never lost

    or created, it is just transferred between

    different mediums so the energy we take in

    must be expelled by the body.

    the body converts the chemical energy taken

    on as food into sound, heat and kinetic

    energy. this building aims to harness some of

    the energy expelled by the body and convert

    it into useful energy to power and heat the

    building.

    a body heat

    the body gives off two kinds of heat, radiated

    heat and sweat. sweat is hard to capture

    and would require a lot of energy to do so

    making it an inefficient system. radiated heat

    however can be used to heat spaces and the

    air within them. the air it heats can be moved

    around a building via ducts to heat other

    spaces.

    a human body at rest gives of about 100wof power, whilst a body working out will give

    off three times the amount, 300w.

    b breathing

    masks have been developed that convert the

    wind energy from heavy breathing during

    exercise into electrical energy. it is the

    equivalent of a small scale wind farm.

    c motor movements

    the kinetic energy involved in the motor

    movements of the human body can be used to

    create movement in other objects and that

    movement can be converted into electrical

    energy using dynamos and piezo electrics.

    d biomass

    the waste products of the body can be

    burned or decomposed, giving off heat

    which can be utilised in energy systems of

    buildings. however in a tight urban site the

    burning or decomposition of solid waste is

    not practical due to space requirements and

    the associated smells.

    it is possible to produce electricity through

    the electrolysis of urine and the waste

    products of this process are potassium and

    nitrogen which can be used as fertilisers.

    A

    C

    a

    bcd

    body heat - radiated and sweat

    breathing - windmotor movements - kineticbiomass - chemical

  • 8/2/2019 Design and Detail Report

    96/106

    10.2 environmental overview

    market/exhibition spaces

    exposed area open to the hinaturally ventilated, daylit by open sides and difcoming through pods above.lighting powered by pavegenglowing pods above.

    circulation

    unheated external space opabove, natural ventilated, lit by diffuse light comingpods, night lighting poweractivated by pressure padwalkway structure.

    gym pods

    sealed insulated units. hbody heat of gym users. comechanical ventilation and ecooling system. hot air cthe pods is passed througexchanger to heat the cinediffuse light through kalwaduring the day and led liactivated by motion sensorsspecialist gym equipment andcomponents generate electr

    cinemasealed insulated box, structure acoustically from external shell. black led lighting before and afpowered by electricity prthe gym. heated by body heagym. cooled by mechanical vand evaporative cooling sys

  • 8/2/2019 Design and Detail Report

    97/106

    10.3 PA

    pavegen

    footsteps

    walks ove

    energy is

    that can b

    each pa

    luminaire

    someone the user w

    process a

    footfall t

    the pads

    existing f

    in standa

    upper par

    100% rec

    of the lo

    componen

    recycled

    well in bo

    environme

  • 8/2/2019 Design and Detail Report

    98/106

    pavegen pa

    floor mar

    is funnell

    on heavily

    pavement,

    and betwe

    footflow t

    will be har

    will provilighting sy

    10.4 PAV

    n

    prop

    1

  • 8/2/2019 Design and Detail Report

    99/106

    grp mesh walkway

    galvanised steel c section walkway supportssteel bearing pad bolted to;

    walkway support pressure pad

    piezo electric material

    pressure pad bolted to steel superstructure

    electricity output

    sensor output for lighting

    force of footfall over walkway

    force causes pressure pad to compresspiezo electric material is compressed creating

    a current within the material

    electricity output to battery store

    sensor activates lighting at night

    a

    bc

    d

    e

    f

    g

    h

    1

    23

    4

    5

    A

    2

    b

    c

    d

    e

    3

    fg 4

    h

  • 8/2/2019 Design and Detail Report

    100/106

    through the use of dynamos

    to capture the energy of a

    workout. most gym equipment is

    rotating or oscillating part

    well with dynamos. These dy

    attached to a battery which is

    the electricity for later use.

    a dynamo uses rotating coil

    magnetic fields to conver

    rotation into a pulsing d

    current through faradays la

    a dynamo machine consists o

    structure, called the stator,

    a constant magnetic field,

    rotating coils called the a

    turn within that field. the moti

    within the magnetic field caus

    push on the electrons in the m

    an electric current in the wire

    http://en.wikipedia

    10.6 GREEN GYM - PRECEDENT

    the quoted energy consumption per square

    foot per hour of assembly buildings is;

    20.5 btu

    1 btu = 1055 joules

    therefore

    the following calculations are a comparison

    between the energy that can be produced by

    exercise equipment fitted with a dynamo in the

    gym pods and the required energy to power the

    cinema

    the energy requirement for A standard building of

    thistypecan beroughlycalculatedfromavailable

    the cinema would only be in use for a few hours

    when a film is showing, so this requirement will o

    over a short period of time.

    energy production in the gym:

    during a hard workout one human is capa

    producing 120 watts

    10.7 ENERGY CALCULATIONS

  • 8/2/2019 Design and Detail Report

    101/106

    therefore,

    20.5 btu = 21627.5 joules

    to convert this to power [watts] we can use;

    power [watts] = energy [joules]/time

    [seconds]

    power = 21627.5/3600

    power = 6w per square foot

    converted to square metres this is;

    65w per square metre

    using the energy administration information

    data the performance venue will require 65w

    of electrical power per square metre of the

    building.

    the areas of the cinemA is:

    90 sqm

    the total power requirement of the cinema

    would be:

    5,850 watts

    this type can be roughly calculated from available

    statistics of energy use by building type available

    from the energy information administration;

    commercial buildings energy consumption survey

    1999 in the usa.

    the survey provides information on energy

    consumption per square foot per hour for multiple

    building types.

    to calculate the amount of energy used by thecinema i will use the statistics for public assembly

    buildings.

    producing 120 watts.

    this means that the number of hours exercise re

    to create the 5,850 watts of energy required

    cinema for one hour is:

    49 hours.

    the cinema seats 126 people so at full capacity

    person using the cinema provided energy by us

    gym they would each only have to do:

    23 minutes of exercise per hour

    if the cinema is open for 3 hours [allowing 2 hou

    a film and an hour for opening and closing] t

    power it for the entire time each person will need

    69 minutes of exercise

    so the audience will get to see a 2 hour film in tu

    just over an hours workout.

    if two films are shown in the cinema per day the

    will be open for 6 hours meaning to obtain its

    requirement the number of hours exercise in t

    will need to be:

    294 hours

    cyclic motion & continuous

    generation

    cyclic motion & generative

    braking

    cyclic motion

    limb continually

    accelerates [+} &

    decelerates [-}

    generator resists

    acceleration & assists

    deceleration

    generator only assists

    deceleration

    many devices take advantage of human power capaci

    produce electricity, including hand-crank generas well as wind-up flashlights, radios, and mobile p

    chargers. a limitation of these conventional methods is

    users must focus their attention on power generati

    the expense of other activities, typically resulting in s

    bouts of generation. for electrical power generation

    longer durations, it would be desirable to harvest e

    from everyday activities such as walking.

    max donelan, professor of kinesiology, simon fraser univ

  • 8/2/2019 Design and Detail Report

    102/106

    workrate

    workrate

    workrate

    electricpower

    energy

    metabolic metabolic metabolicelectric electric

    add

    itionalenergy

    add

    itionalenergy

    electricpower

    electricpower

    +

    -

    researchers from simon fraser university in b

    columbia have developed a device which, worn much l

    knee support, generates electricity from the natural m

    of walking. the device harvests energy from the end

    walkers step, when the muscles are working to slo

    movement of the leg, the biomechanical energy harv

    uses sensors and a real-time control system to assis

    hamstring muscles in slowing the knee motion. the sy

    only turns on power generation at the end of the wal

    swing phase.

    the aluminium chassis contains a gear train convertin

    velocity and high torque at the knee into the high vel

    and low torque for the generator A one-way roller c

    allows for selective engagement of the gear train d

    knee extension only and no engagement during knee fl

    max donelan, professor of kinesiology, simon fraser univ

    wearing a device on each leg, an individual can gene

    up to 5 watts of electricity with normal physical ef

    walking quickly, however, generates as much as 13 watt

    that rate, when the energy is stored in a battery, one m

    of walking time could provide enough electricity to su

    30 minutes of talk-time on a mobile phone.

    people are an excellent source of portable powe

    average-sized person stores as much energy in fat

    1,000 kg battery. people recharge their body batte

    with food and, lucky for us, there is about as much u

    energy in a 35-gram granola bar as in a 3.5 kg lithiu

    battery.

    max donelan, professor of kinesiology, simon fraser univ

    the device comprises an aluminium chassis and gener

    mounted on a customized orthopaedic knee brace. with

    worn on each leg, its total mass is 1.6 kg but the devel

    are working on using lighter weight materials, suc

    carbon fibre to bring this down.

    10.9 MAS

  • 8/2/2019 Design and Detail Report

    103/106

    a brazilian

    aire mask,

    that contain

    powered by

    most effect

    due to the h

    be used whe

    designed to

    to charge thpower outpu

    into the gym

    on the equ

    applications

    the opportu

    means they

    space for

    energy while

    issues of hy

    a system cou

    member is is

    they then at

    it.

    10.10 URINE ELECTROLYSIS & HYDROGEN FUEL

  • 8/2/2019 Design and Detail Report

    104/106

    us researchers have developed an efficient

    way of producing hydrogen from urine - a

    feat that could not only fuel the cars of

    the future, but could also help clean up

    municipal wastewater.

    using hydrogen to power cars has become an

    increasingly attractive transportation fuel,

    as the only emission produced is water - but a

    major stumbling block is the lack of a cheap,

    renewable source of the fuel. gerardine

    botte of ohio university may now have found

    the answer, using an electrolytic approach

    to produce hydrogen from urine - the most

    abundant waste on earth - at a fraction of

    the cost of producing hydrogen from water.

    royal society of chemistry, http://www.rsc.org,

    july 2009

    the process of electrolysis of urine

    releases hydrogen atoms which can then be

    captured and burnt in a combustion chamber

    to produce large amounts of energy. the use

    of hydrogen fuel has already bee proven

    by its use as a fuel for vehicles. burning

    of hydrogen can produce large amounts of

    energy which can be converted into electrical

    energy to power the building.

    hydrogen has to be produced in its elemental

    state from its compounds that occur natural.

    the most common processes to obtain

    hydrogen are the electrolysis of water

    which requires relatively large amounts of

    energy to be input and the steam reforming

    of methane but this process produces both

    carbon dioxide and carbon monoxide which

    are harmful to the environment.

    the electrolysis of urine has been developed

    in the past few years and is being identified

    as a more efficient and environmentally

    friendly process for creating hydrogen.

    the main component of urine

    contains four hydrogen m

    important factor in urea is tha

    molecules are bond less st

    water meaning less energy is

    input into the electrolysis p

    the electrolysis of water.

    during the electrolysis procnickel based electrodes. dur

    hydrogen is given off at the

    can be collected and burn

    electricity. carbon dioxide is p

    the reaction but this reacts

    hydroxide in the electrolyt

    produce potassium carbonat

    products are nitrogen and

    both occur naturally in the a

    urine also contains phosphor

    as a fertiliser, once the el

    been completed the phosphor

    solution can be used as a f

    greenhouses.

    the heating system of using

    collected in the gym and a heat

    has already been discussed in pre

    10.11 COOLING

    f

  • 8/2/2019 Design and Detail Report

    105/106

    has already been discussed in pre

    of this report.

    when the outside air temperatur

    than the inside air temperature

    air will be mechanically ventilat

    gym and cinema spaces to pro

    cooling but when the outside air t

    is similar or high than the requir

    comfort level than another sysused.

    the ventilation system will use e

    cooling to effectively sweat whe

    high external air temperature. th

    the action of the human body, wh

    to cool down we sweat and in t

    of evaporating it extracts heat

    surface of our skin.

    an evaporative cooling system

    passing the external air through

    moist filter pads, as the water i

    evaporates it takes heat from the a

    its temperature. this air then

    building at a lower temperature

    the required cooling.

    warm external air drawn in mechanically

    warm air passes through moist filter pads

    evaporative process removes heat from the air

    filter pads remove dust and pollen particles

    cooled air enters internal spaces at low level

    high level mechanical extract draws moist air out

    of the building

    a

    b

    c

    d

    e

    f

    ab

    C

    d

    e

    10.12 FIR

    the cinema

  • 8/2/2019 Design and Detail Report

    106/106

    fire rated

    corridor p

    is accesse

    rooms. the

    fire rated

    smoke ven

    basement a

    the grouncirculation

    path to ri

    all the cir

    the buildin

    walkways w

    retains its

    mesh. to p

    gym pods

    where poss

    perimeter

    space. eac

    are constr

    shatter wh

    all the st

    required p

    1 hour fire rated construction

    smoke ventilation