12
1 MURPHY SABAH OIL COMPANY LTD. Deepwater Subsea Tie-Back Flow Assurance Overview

Deepwater Subsea Tie-Back Flow Assurance · PDF fileM U R P H Y S A B A H O I L C O M P A N Y L T D . 2 Case Study Overview Flow Assurance Basis/Data Results Pre-FEED/FEED Considerations

  • Upload
    ngodang

  • View
    217

  • Download
    2

Embed Size (px)

Citation preview

Page 1: Deepwater Subsea Tie-Back Flow Assurance · PDF fileM U R P H Y S A B A H O I L C O M P A N Y L T D . 2 Case Study Overview Flow Assurance Basis/Data Results Pre-FEED/FEED Considerations

1 M U R P H Y S A B A H O I L C O M P A N Y L T D .

Deepwater Subsea Tie-Back

Flow Assurance Overview

Page 2: Deepwater Subsea Tie-Back Flow Assurance · PDF fileM U R P H Y S A B A H O I L C O M P A N Y L T D . 2 Case Study Overview Flow Assurance Basis/Data Results Pre-FEED/FEED Considerations

2 M U R P H Y S A B A H O I L C O M P A N Y L T D .

Case Study Overview

Flow Assurance Basis/Data

Results

Pre-FEED/FEED Considerations Flow Assurance

Field Architecture

Technologies

Subsea Tie-Back Case Study

Contents

Page 3: Deepwater Subsea Tie-Back Flow Assurance · PDF fileM U R P H Y S A B A H O I L C O M P A N Y L T D . 2 Case Study Overview Flow Assurance Basis/Data Results Pre-FEED/FEED Considerations

3 M U R P H Y S A B A H O I L C O M P A N Y L T D .

Subsea Tie-Back Case Study

Preliminary Concept

Preliminary Concept • 15 km subsea tie-back • 3 manifold locations • 8 producers • 8 injectors

Page 4: Deepwater Subsea Tie-Back Flow Assurance · PDF fileM U R P H Y S A B A H O I L C O M P A N Y L T D . 2 Case Study Overview Flow Assurance Basis/Data Results Pre-FEED/FEED Considerations

4 M U R P H Y S A B A H O I L C O M P A N Y L T D .

New Process System

3 Gas Turbines

TEG and VRU

Gas Compression

Flare

Production Systems

Water Injection

Export Pump and

Fiscal Meter

4 Open Riser Slots

2 Steam Turbines

Subsea Tie-Back Case Study

Host Facilities

Page 5: Deepwater Subsea Tie-Back Flow Assurance · PDF fileM U R P H Y S A B A H O I L C O M P A N Y L T D . 2 Case Study Overview Flow Assurance Basis/Data Results Pre-FEED/FEED Considerations

5 M U R P H Y S A B A H O I L C O M P A N Y L T D .

Tie-back field distance from host: 10 to 15 km

Water depths: 1250 to 1400 m

Production flowrates: 0 to 40 kbpd (provisional)

WI flowrates: 0 to 70 kbwpd (provisional)

FPSO separator inlet pressures: 13 to 44 bar

Water cuts: 0 to 95 %

GORs: 500 to 1000 scf/bbl

Minimum seabed temperature: 2 - 4 deg C

FWHT: 60OC

Subsea Tie-Back Case Study

Provisional FA Basis/Data

Page 6: Deepwater Subsea Tie-Back Flow Assurance · PDF fileM U R P H Y S A B A H O I L C O M P A N Y L T D . 2 Case Study Overview Flow Assurance Basis/Data Results Pre-FEED/FEED Considerations

6 M U R P H Y S A B A H O I L C O M P A N Y L T D .

Production (provisional 40 kbpd flowrate) 2 x 8-inch piggable loop, or

Single 10-inch

Water Injection (provisional 70 kbwpd flowrate) Single 12-inch

Subsea Tie-Back Case Study

Preliminary Results – Flowline Sizes

Page 7: Deepwater Subsea Tie-Back Flow Assurance · PDF fileM U R P H Y S A B A H O I L C O M P A N Y L T D . 2 Case Study Overview Flow Assurance Basis/Data Results Pre-FEED/FEED Considerations

7 M U R P H Y S A B A H O I L C O M P A N Y L T D .

Subsea Tie-Back Case Study

Preliminary Results – Pressures

FPSO Separator Pressure

(barg)

Production Flowline Inlet Pressure Requirements at Subsea Wellheads

(FWHP)

Boosting

44 140 – 190 bara for 0 – 90% water cuts -

13 95 – 150 bara for 0 – 90% water cuts -

44 165 bara for 90% water cut Riser base gas lift (RBGL)

13 115 bara for 90% water cut Riser base gas lift (RBGL)

Potential 40 bar reduction in FWHP requirements with lower separator pressure.

Potential 25 - 35 bar reduction in FWHP requirements with RBGL.

Potential 75 bar reduction in FWHP requirements with RBGL + lower separator pressure.

Page 8: Deepwater Subsea Tie-Back Flow Assurance · PDF fileM U R P H Y S A B A H O I L C O M P A N Y L T D . 2 Case Study Overview Flow Assurance Basis/Data Results Pre-FEED/FEED Considerations

8 M U R P H Y S A B A H O I L C O M P A N Y L T D .

Subsea Tie-Back Case Study

Preliminary Results – Pressures

FWHP requirements are relatively insensitive to GOR, with a GOR of 1000 scf/bbl requiring a marginally lower FWHP than a GOR of 500 scf/bbl.

A large proportion of the total system pressure loss is due to elevation head loss up the production risers, i.e. between 80 and 100 bar for a range of water cuts between 0% and 90%.

Page 9: Deepwater Subsea Tie-Back Flow Assurance · PDF fileM U R P H Y S A B A H O I L C O M P A N Y L T D . 2 Case Study Overview Flow Assurance Basis/Data Results Pre-FEED/FEED Considerations

9 M U R P H Y S A B A H O I L C O M P A N Y L T D .

Subsea Tie-Back Case Study

Preliminary Results – Temperatures / Insulations

Insulation System

U Value (W/m2K)

Minimum Flowrate for a 30OC FPSO Arrival Temperature

(each 8” flowline)

Remark

Pipe-in-Pipe 1.0 10 kbpd Represents 50% turndown for one flowline, 75% for two flowlines

GSPU or Flexible Pipe

3.5 20 kbpd Represents no production turndown for 40 kbpd

The 30OC FPSO arrival temperature is provisional. Measured WATs range from 17 to 24OC.

Insulation selection depends on the wax appearance temperature (WAT) and production profile.

Page 10: Deepwater Subsea Tie-Back Flow Assurance · PDF fileM U R P H Y S A B A H O I L C O M P A N Y L T D . 2 Case Study Overview Flow Assurance Basis/Data Results Pre-FEED/FEED Considerations

10 M U R P H Y S A B A H O I L C O M P A N Y L T D .

Production Enhancement Assess feasibility and benefits of low FPSO separator pressure, subsea

boosting, riser base gas lift, and any combinations of the EOR options

Wax / Hydrate / Solids Mitigation and Management Evaluate dual piggable loop flowlines vs. single flowline

Assess insulation requirements, e.g. GSPU, PIP

Assess stabilized crude flushing requirements

Assess direct electrical heating requirements

Assess wax gel breaking requirements

Assess wax appearance temperature sensitivity

Assess wax/hydrate inhibitor injection requirements, e.g. low turndown rates

Subsea Tie-Back Case Study

Pre-FEED/FEED FA Considerations

Page 11: Deepwater Subsea Tie-Back Flow Assurance · PDF fileM U R P H Y S A B A H O I L C O M P A N Y L T D . 2 Case Study Overview Flow Assurance Basis/Data Results Pre-FEED/FEED Considerations

11 M U R P H Y S A B A H O I L C O M P A N Y L T D .

Seabed features and shallow hazards Existing man-made seabed infrastructures Seabed topography / properties Shallow gas, hydrates, active seabed channels

Constructability, including requirement and sequence for installation, pre-commissioning, commissioning and start-up Subsurface/drilling requirements, e.g. rig movement, well placement

Operability, including flow assurance, controls, normal operation, shutdown, pigging Through life conditions

HSE during construction and operation New technology risks

Reliability, Availability and Maintainability ROV intervention and inspection

Flexibility for addition of manifolds and future tie-in Phased development allows re-appraisal

Abandonment

Subsea Tie-Back Case Study

Field Architecture Considerations

Page 12: Deepwater Subsea Tie-Back Flow Assurance · PDF fileM U R P H Y S A B A H O I L C O M P A N Y L T D . 2 Case Study Overview Flow Assurance Basis/Data Results Pre-FEED/FEED Considerations

12 M U R P H Y S A B A H O I L C O M P A N Y L T D .

Challenging technologies include: Pipe-in-Pipe (PIP)

Direct electrical heating

Towed bundle flowlines

Riser base gas lift

Direct water injection

Subsea multiphase flow pump (MPFP)

Glassflake syntactic polyurethane (GSPU)

Consider and assess: Local capabilities, infrastructures and competition

Fabrication and installation requirements

Field proven experience

Subsea Tie-Back Case Study

Challenging Technologies