Deep tubewell installation Situation Analysis: As a part of project implementation AMRF Conducted 100% Arsenic screening of tubewell in the project area . Most of the Shallow tubewell are arsenic affected. Maximum community people use Arsenic contaminated water for all purpose. As per community action plan (CAP), there was a need to install alternative water facilities in the community level. One of most popular water technology is Deep tubewell for community. Initiative Taken: AMRF is working with the community people by forming CBO in every ward of Union Parishad. With this consistence CBO representatives visited the venerable area where less number of Arsenic free Tubewell . As per community demand CBO felt it need to installed Deep tubewell for Arsenic free safe water as on priority based and subsequently they decided to apply to AMRF for Deep Tw installation. Construction Process: Application: Every CBO chairmen have applied to AMRF on behalf of community people for the Installed of tubewell with the appropriate prescribed format. Approval: Based on CBO’s application union supervisor and project engineer visited the proposed tubewell site, then union supervisor recommended installed those platform. On the other hand engineer recommended that there are no technical obligations to installation of Deep tubewell. Contribution money: According to WAB cost sharing strategy CBO decided to take cost sharing money approximate 8% of of total installation of every single tubewell as per wellbeing ranking. Contractor/Boring Mistree Selection: Selection of contractor as per organizational financial policy.

Deep Tube Well Installation

  • Upload
    crelisr

  • View
    105

  • Download
    1

Embed Size (px)

DESCRIPTION

Deep Tube Well Installation

Citation preview

Page 1: Deep Tube Well Installation

Deep  tubewell  installation    

Situation  Analysis:  As   a   part   of   project   implementation   AMRF  Conducted   100%   Arsenic       screening   of  tubewell     in   the   project   area   .   Most   of   the  Shallow   tubewell   are   arsenic   affected.  Maximum   community   people   use   Arsenic  contaminated   water   for   all   purpose.     As   per  community   action   plan   (CAP),   there   was   a  need   to   install   alternative   water   facilities   in  the   community   level.   One   of   most   popular  water   technology   is   Deep   tubewell   for  community.      

Initiative  Taken:  AMRF   is  working  with  the  community  people  by   forming   CBO   in   every   ward   of   Union  Parishad.   With   this   consistence   CBO  representatives   visited   the   venerable   area  where  less  number  of  Arsenic  free  Tubewell  .  As   per   community   demand   CBO   felt   it   need   to   installed  Deep   tubewell   for   Arsenic   free   safe  water   as   on   priority   based   and   subsequently   they   decided   to   apply   to   AMRF   for   Deep   Tw  installation.    

Construction  Process:  • Application:  Every  CBO  chairmen  have  applied  to  AMRF  on  behalf  of  community  people  

for  the  Installed    of  tubewell  with  the  appropriate  prescribed  format.    • Approval:  Based  on  CBO’s  application  union  supervisor  and  project  engineer  visited  the  

proposed  tube-­‐well  site,  then  union  supervisor  recommended  installed  those  platform.  On   the   other   hand   engineer   recommended   that   there   are   no   technical   obligations   to  installation  of  Deep  tubewell.  

• Contribution  money:  According  to  WAB  cost  sharing  strategy  CBO  decided  to  take  cost  sharing  money  approximate  8%  of  of   total   installation  of   every   single   tubewell   as  per  wellbeing  ranking.    

• Contractor/Boring   Mistree   Selection:   Selection   of   contractor   as   per   organizational  financial  policy.  

 

Page 2: Deep Tube Well Installation

• Tubewell  installation  work:  Installation    work  has  started  as  priority  basis.  Both  of  CBO  and  Engineer  monitor  the  TW  installation  work  for  ensuring  the  quality  of  materials  and  installation  work.  

• Handover:  After  the  completion  (Installation,  platform  construction,  Water  quality  test  etc)   of   installation   work   AMRF   handed  over   the   Tubewell     for     using   water  facilities.      

Covered   Population:     In   the   last   WAB   financial  year   (  April  2014  to  March  2015)  AMRF   installed  14   numbrr   of   Deep   Tubewell   in   4   union   of  sreenagar   and   Louhajong   upzila.   Now   1712  people  get  safe  water  from  those  Tubewell.