325
International Conference on Deregulated Environment and Energy Markets, July22-23, 2011 1 Congestion Management based on Power Flow Contribution Factors 1 Vinod Kumar Pal, 2 Ashwani Kumar 1,2 NIT Kurukshetra 1 [email protected] 2 [email protected] AbstractIn this paper, an application of proportional sharing principle and power flow comparison method have been presented for congestion management deciding rescheduling of generators for congestion management. Contribution formulae based approach has been implemented and Power flow comparison method and contribution formulae have been presented for congestion management studies. The comparison of PFC and CF methods has been tested on IEEE-57 bus test system for congestion management. The comparison of PFC and CF based approaches has been implemented for 6-bus test system, IEEE-57 bus test system and 25-bus test system for congestion management. KeywordsCongestion management, contribution formulae, proportional sharing principle, power flow comparison method. I. INTRODUCTION Restructuring of the power industry aims at abolishing the monopoly in the generation and trading sectors, thereby, introducing competition at various levels wherever it is possible. Generating companies may enter into contracts to supply the generated power to the power dealers/distributors or bulk consumers or sell the power in a pool in which the power brokers and customers also participate. In a power-exchange, the buyers can bid for their demands along with their willingness to pay. Power generation and trading will, thus, become free from the conventional regulations and become competitive. According to Phillipson and Willis [1], ―Deregulation is a restructuring of the rules and economic incentives that governing authority sets up to control and drive the electric power industry. In a restructured electricity market environment, when the producers and consumers of electric energy desire to produce and consume in amounts that would cause the transmission network to operate at or beyond one or more transfer limits, the system is said to be congested [2]. The congestion in the system can not be allowed to persist for a long time, as it can cause sudden rise in the electricity price and threaten system security and reliability. Congestion management is one of the most challenging tasks of the SO in the deregulated environment. In different types of market, the method of tackling the transmission congestion differs. There are three different ways to tackle the network congestion: Price Area Congestion Management Available Transfer Capability (ATC) based Congestion Management Optimal Power Flow (OPF) based Congestion Management The first method is used in Nordic pool; the second one in US and the third is employed in UK. In Nordic pool, which consists of Norway, Sweden, Denmark, and Finland, when congestion is predicted, the system operator declares that the system is split into price areas at the predicted congestion bottlenecks. Spot market bidders must submit separate bids for each price area in which they have generation or loads. In case of no congestion, the market will settle at one price and in case of congestion, the price areas are separated settled at prices that satisfy transmission constraints. Area with excess generation will have lower prices, and those with excess load will have higher prices. The US Federal Energy Regulatory Commission (FERC),[3] established a system, where each SO would be responsible for monitoring its own regional transmission system and calculating its ATC for potentially congested paths entering, leaving, and inside its network. The ATC values for next hour and for each hour in the future are placed on OASIS, operated by SO. Anyone wishing to do transaction would access OASIS web pages and use ATC information available there to determine if system could accommodate transaction. Details of the regional congestion management methodologies applied in Europian electricity market is presented in final report [21]. The report summarizes the congestion management methods and procedures adopted in Europian region. A report on congestion management in Nordic region details out the rules for congestion management and nodal and zonal pricing based methods [22]. In an optimal power flow, (OPF) is performed to minimize generators‘ operating cost subject to set of constraints that represent a model of the transmission system within which the generator operate. The generator sends a cost function and those customers willing to purchase power send a bid function to the SO. The SO has a complete transmission model and performs OPF calculation. OPF solution gives cost/MW at each node of the system. In some countries zonal pricing method is followed in which the system is divided into various zones

Deem-2011 Proceedings

Embed Size (px)

Citation preview

  • International Conference on Deregulated Environment and Energy Markets, July22-23, 2011

    1

    Congestion Management based on Power Flow

    Contribution Factors 1Vinod Kumar Pal,

    2Ashwani Kumar

    1,2NIT Kurukshetra

    [email protected]

    [email protected]

    Abstract In this paper, an application of proportional sharing principle and power flow comparison method have

    been presented for congestion management deciding

    rescheduling of generators for congestion management.

    Contribution formulae based approach has been

    implemented and Power flow comparison method and

    contribution formulae have been presented for congestion

    management studies. The comparison of PFC and CF

    methods has been tested on IEEE-57 bus test system for

    congestion management. The comparison of PFC and CF

    based approaches has been implemented for 6-bus test

    system, IEEE-57 bus test system and 25-bus test system for

    congestion management.

    Keywords Congestion management, contribution formulae, proportional sharing principle, power flow comparison

    method.

    I. INTRODUCTION

    Restructuring of the power industry aims at abolishing

    the monopoly in the generation and trading sectors,

    thereby, introducing competition at various levels

    wherever it is possible. Generating companies may enter

    into contracts to supply the generated power to the power

    dealers/distributors or bulk consumers or sell the power in

    a pool in which the power brokers and customers also

    participate. In a power-exchange, the buyers can bid for

    their demands along with their willingness to pay. Power

    generation and trading will, thus, become free from the

    conventional regulations and become competitive.

    According to Phillipson and Willis [1], Deregulation is a

    restructuring of the rules and economic incentives that

    governing authority sets up to control and drive the

    electric power industry.

    In a restructured electricity market environment, when

    the producers and consumers of electric energy desire to

    produce and consume in amounts that would cause the

    transmission network to operate at or beyond one or more

    transfer limits, the system is said to be congested [2]. The

    congestion in the system can not be allowed to persist for a

    long time, as it can cause sudden rise in the electricity price

    and threaten system security and reliability. Congestion

    management is one of the most challenging tasks of the SO

    in the deregulated environment.

    In different types of market, the method of tackling the

    transmission congestion differs. There are three different

    ways to tackle the network congestion:

    Price Area Congestion Management

    Available Transfer Capability (ATC) based Congestion Management

    Optimal Power Flow (OPF) based Congestion Management

    The first method is used in Nordic pool; the second one

    in US and the third is employed in UK. In Nordic pool,

    which consists of Norway, Sweden, Denmark, and Finland,

    when congestion is predicted, the system operator declares

    that the system is split into price areas at the predicted

    congestion bottlenecks. Spot market bidders must submit

    separate bids for each price area in which they have

    generation or loads. In case of no congestion, the market

    will settle at one price and in case of congestion, the price

    areas are separated settled at prices that satisfy

    transmission constraints. Area with excess generation will

    have lower prices, and those with excess load will have

    higher prices.

    The US Federal Energy Regulatory Commission

    (FERC),[3] established a system, where each SO would be

    responsible for monitoring its own regional transmission

    system and calculating its ATC for potentially congested

    paths entering, leaving, and inside its network. The ATC

    values for next hour and for each hour in the future are

    placed on OASIS, operated by SO. Anyone wishing to do

    transaction would access OASIS web pages and use ATC

    information available there to determine if system could

    accommodate transaction. Details of the regional

    congestion management methodologies applied in

    Europian electricity market is presented in final report [21].

    The report summarizes the congestion management

    methods and procedures adopted in Europian region. A

    report on congestion management in Nordic region details

    out the rules for congestion management and nodal and

    zonal pricing based methods [22].

    In an optimal power flow, (OPF) is performed to

    minimize generators operating cost subject to set of

    constraints that represent a model of the transmission

    system within which the generator operate. The generator

    sends a cost function and those customers willing to

    purchase power send a bid function to the SO. The SO has

    a complete transmission model and performs OPF

    calculation. OPF solution gives cost/MW at each node of

    the system. In some countries zonal pricing method is

    followed in which the system is divided into various zones

  • International Conference on Deregulated Environment and Energy Markets, July22-23, 2011

    2

    on geographical basis. The zone prices obtained from OPF

    are used in the following manner:

    Generators are paid zone price of energy The loads must pay the zone price of energy

    In case of no congestion, the zone price will be same and

    the generators are paid the same price for their energy as

    the loads pay. When there is congestion, the zone prices

    will differ, each generator is paid its zone price and the

    loads also pay its zone price for the energy. Thus, the OPF,

    through different zonal pricing, performs the function of

    controlling the transmission flows and thus maintaining the

    transmission security. The goal of deregulation is to

    encourage lower electric utility rates by structuring an

    orderly transition to competitive bulk power markets. The

    key is to open up transmission services, the vital link

    between sellers and buyers. To achieve the benefits of

    robust, competitive bulk power markets, all wholesale

    buyers and sellers must have equal access to the

    transmission grid. Otherwise efficient trades cannot take

    place, and ratepayers will bear unnecessary costs. Problems

    arise because all transactions have to share the same

    transmission network simultaneously. What portion of the

    capacity of a particular transmission system is used by a

    certain transaction? How can a fair charge be calculated

    based on the capacity usage? Can some transactions be

    adjusted, or even canceled, when transmission congestion

    occurs? Which generator or transaction should be

    considered first for adjustment in congestion management,

    based on transmission capacity usage?

    To answer these questions, an algorithm was developed

    which can calculate the contribution from individual

    generator units to the flows and losses trough the

    transmission network and at the load centers. This is both

    an essential and challenging task. Scholars from England

    were the first to propose the Flow Based Proportional

    Sharing Method (PS), based on a strong proportional

    sharing assumption, which has not been proven either

    correct or incorrect at this time [4-8]. Among them, D.

    Kirschen proposed the famous Topological Trace

    Algorithm; J. Bialek proposed the Upstream-Looking and

    Downstream-Looking algorithms. R. Shoults, who

    proposed the Circuits Based Method to challenge the

    currently very popular Flow Based Proportional Sharing

    Method, believed that the correct method should be

    founded upon established circuits theories. The Circuits

    Based Method is comprised of two sub-methods:

    1. Current Division method

    2. Voltage Division method.

    A new method named the Power Flow Comparison Method (PFC) which makes an effort to conform to the physical concepts commonly understood and accepted by

    power system engineers. These methods are applied to an

    example of 6-bus power system, and the results are

    presented, compared and discussed to verify their

    correctness. Further applications in transmission charges

    [9-11] and transmission congestion management [12, 13]

    show the great practical value of tracing the flow of power

    from source to load. The impact of corrective actions on

    one group of lines to other heavily loaded lines is also

    shown.

    II.POWER FLOW CONTRIBUTION FACTORS METHOD

    The Power Flow Comparison Method (PFC) is

    comprised of the following procedure to find the

    contribution of each generator to the line flows, losses and

    loads:

    i) Calculate the base case power flow.

    ii) For the generator of interest, remove generation and a

    corresponding load from the power system in even

    quantities.

    iii) Make this generator bus the swing bus and calculate

    the power flow again

    iv) Find the line flow difference on each transmission

    line by comparing the two power flow results above.

    An example 3-bus power system, shown in Fig 1, is

    provided to illustrate this algorithm. Line resistance is

    ignored, and distributed capacitance is considered. Part I

    of Fig 1 is the base case power flow result. Part II of the

    Fig 1 is obtained by removing the generation at bus A

    (150 MW) and its corresponding loads at bus C (150MW)

    from the base case power system. The contribution of

    generator A to the line flows can be found by subtracting

    the line flow results in Part II from those in Part I. Part III

    of the Figis obtained by removing the generation at bus B

    (50MW) and its corresponding loads at bus C (50MW)

    from the base case power system. The contribution of

    generator B to the line flows can be obtained by

    subtracting the line flow results in Part IV from those in

    Part I. The final results are listed in Part IV. From this

    illustration, the reader may be reminded of the distribution

    factors method, which shows the sensitivity of the line

    flows to changes in generation. It is always easy to remove

    a generator (in a simulation.) It is rather difficult to find

    the corresponding loads of this generator, which are

    different from the contract loads. The term

    corresponding loads is used to mean the load served by

    this particular generator. How they are calculated is

    summarized in the following paragraphs. It is assumed

    that the voltage at each network node will not change

    much when a quantity of generation and its corresponding

    loads are evenly removed from the network. This is the

    constant voltage assumption used in the paper.

    Fig.1 (a): Base case power flow

    C

    B 50MW 150MW A

    200MW

  • International Conference on Deregulated Environment and Energy Markets, July22-23, 2011

    3

    Fig1 (b): Remove generator A and its load from base case power flow

    Fig1(c): Remove generator B and its load from base case power flow.

    Fig1 (d): Power flow comparison methods

    III. APPLICATION IN CONGESTION MANAGEMENT

    With the open access of transmission networks and the

    competitive bulk power market, transmission congestion

    has become a more and more serious problem in the

    deregulated world. However, based on the calculated

    contribution of line flows from each generator, the PFC

    Method and the Proportional Sharing (PS) Method can

    provide guidance to relieve these congestion problems.

    Test cases on the IEEE 57-bus system [17] are presented

    to show the details.

    Results of two test cases on the IEEE 57-bus system

    show the capability of the Power Flow Comparison (PFC)

    Method over the Proportional Sharing Method (PS) for

    solving the transmission congestion management

    problems. Key output data are given in the [18], which

    includes:

    Bus output of the load-flow study; Line flows of the load-flow study; Generator contributions to MW line flows based on the

    PFC Method;

    Generator contributions to MW line flows based on the PS Method.

    Case #1: Line 8 is heavily loaded with a total line flow

    of 174.0983 MW. Based on the MW contribution of each

    generator to the line flow, transmission congestion

    management methods are suggested by both the PS

    Method and the PFC Method as shown in Table 1. The PS

    Method predicts that decreasing G3 is the only way to

    lower the line flow. The PFC Method, on the other hand,

    predicts that the line flow can be decreased with more

    flexibility. In tests 1, 2, and 6, the line flow is decreased

    without changing G3. The TESTS portion of Table 2.1

    shows the sensitivities of line

    flow changes vs. the generation changes. Because line 15

    is also heavily loaded, the sensitivities of line 15 are listed

    in the TESTS table as well so that a management method,

    with a minimum impact online 15, can be found. Tests 1

    to 6 apply 1 MW to each generation change. Test 6 is able

    to lower the line flows at both lines 8 and 15. Test 5 is

    able to drop the line flow at line 8 dramatically while

    keeping the line flow increase at line 15 to a minimum.

    Case #2: Line 69 is loaded with a total line flow of

    5.8089 MW. Based on the MW contribution of each

    generator to the line flow, the transmission congestion

    management suggested by the PS Method and the PFC 40

    3.Method are quite different, as shown in the Table 2.The

    PS Method predicts that decreasing G3 is the only way to

    lower the line flow. Conversely, the PFC Method predicts

    that the line flow will be decreased, by increasing G3 and

    decreasing the power output of the other generators, or

    without changing G3. The TESTS table shows the

    sensitivities of line flow changes v/s the generation

    changes. Tests 1 to 8 apply 1 MW to each generation

    change. Tests 1 to 3 show that the PS Method leads to a

    change in the wrong direction because the line flow at line

    69 is increased when G3 is decreased. Tests 4 to 8 show

    that the PFC Method provides more usable guides and

    more alternatives for transmission congestion

    management.

    IV. REAL AND REACTIVE POWER CONTRIBUTION FACTORS

    Algorithm for calculating the contribution factors of each

    generator to the line flows, losses and loads as proposed in

    [16] is given below:

    (a) Perform the base case Newton-Raphson power flow.

    (b) Compute the sensitivity Sijk of the real and reactive

    power flow Pij and Qij of a line connected between

    bus-i and bus-j to real and reactive power output PGk

    and QGk of generator-k. The fast-forward/fast-

    backward substitution method allows an efficient

    computation of the sensitivity[15]:

    kG

    ij

    kG

    ij

    kG

    ijkijp

    P

    ggP

    P

    P

    dP

    dPS

    1

    (1)

    C

    B 50MW 0.0MW A

    50MW

    C

    B 0.0MW 150MW A

    150MW

    C

    B 50MW 150MW A A: 50.42MW

    B: 16.56MW

    A:

    99.58MW

    B: 16.56MW

    A: 50.42MW

    B: 33.44MW

    200MW

  • International Conference on Deregulated Environment and Energy Markets, July22-23, 2011

    4

    kG

    ij

    kG

    ij

    kG

    ijkijq

    Q

    ggQ

    Q

    Q

    dQ

    dQS

    1

    (2)

    kijpkijp MJNS

    1 (3)

    kijqkijq MJNS

    1 (4)

    where Nijp and Nijq are the sparse block vector with sub-

    vector [ -bij Vi Vj, 00] and [ bij Vi Vj, 00] and [ -gij Vi Vj,

    00] and [ gij Vi Vj, 00] in the ith

    and jth

    position,

    respectively. Mk is the sparse block vector with sub-vector

    [-1, 0] in the kth

    position. [J] is the Jacobian power flow

    matrix. g is the power flow equation vector and is the

    voltage angle vector.

    (c) As proved in [16], the contribution factor of slack

    generator to real and reactive power flow of line i-j is:

    NG

    k

    kG

    NG

    k

    Gk

    Gkijpij

    ijp

    P

    PPSP

    CF

    1

    2

    1)( (5)

    NG

    k

    kG

    NG

    k

    GkG

    kijqij

    ijq

    Q

    QQSQ

    CF

    1

    2

    1)(

    (6)

    where CFijp and CFijq are contribution factor of slack

    generator to the real and reactive power flow of line i-j.

    PG1 is the real power output of the slack generator.

    (d) The contribution factor of the mth generator (except

    slack generator-1) to the real power flow of line i-j is

    NG

    k

    kG

    mG

    NG

    k

    NG

    k

    kG

    mijp

    kG

    kijpij

    mijp

    P

    PPSPSP

    CF

    1

    2 1 (7)

    NG

    k

    kG

    mG

    NG

    k

    NG

    k

    kG

    mijq

    kG

    kijqij

    mijq

    Q

    QQSQSQ

    CF

    1

    2 1 (8)

    Where CFijpm and CFijq

    m is the contribution factor of

    generator-m (except slack generator) to real and reactive

    power flow of line i-j.

    (e) The contribution of each generator-m to losses of each

    line i-j can be calculated as: mjip

    mijp

    mlossij CFCFP , (9)

    mjiq

    mijq

    mlossij CFCFQ , (10)

    Where Pij,lossm and Qij,loss

    m is the contribution factor of

    generator-m to loss of line i-j.

    (f) The contribution of generator-m to load at the bus-i, is

    given as:

    ui

    j

    mijp

    mloadi CFP , (11)

    ui

    j

    mijq

    mloadi CFQ , (12)

    where iu is the set of nodes which are directly connected

    to node-i.

    The total contribution of all the generators to line i-j is

    equal to the real power flow of this line: NG

    m

    mijpij CFP

    1

    (13)

    NG

    m

    mijqij CFQ

    1

    (14)

    The contribution factors based on sensitivity of power

    flow are used to find the share of each generator on each

    line flow and consequently the generator share will help

    ISO to identify the generators to re-dispatch their

    generation in congestion management. This can be

    computed in advance and the SO can post the contribution

    of each generator to line flow, so that during the

    congestion hours the SO can send the signal in the market

    for rescheduling of real and reactive powers to manage

    congestion. An example 3-bus system is provided to

    illustrate the capability of the above formulas.

    Resistance is 0.01 p.u. Reactance is 0. 1 p.u. and

    the distributed capacitance is considered with a n-model in

    all transmission lines. Figs. 2 and 3 show the base case

    power flow result and contribution of each generator unit

    to each line flow in the above system, based on proposed

    CF formulas and the PFC method [20], respectively. The

    results of Fig 3.2 are similar to those of Fig 3.1, because

    the voltage at each network node does not change much

    when the quantity of generation and its corresponding

    loads arc 'evenly' removed from the network.

    Fig 2: Illustration of CF formulas for 3 bus system

    Fig.3: Illustration of PFC method by 3 bus system

  • International Conference on Deregulated Environment and Energy Markets, July22-23, 2011

    5

    The proposed CF formulas could have applications in,

    computation of contribution of generation to a DC-line or

    DC-link of an AC-DC power system [19], computation of

    contribution of' reactive generation to reactive power

    flows when the real power is replaced by reactive power i

    n the above formulas, application to individual customers

    for the apportionment of the use-of-the system charges,

    calculation of the sensitivity regarding corrections, that

    will affect the flows in the critical lines.

    V. POWER FLOW CONTRIBUTION FACTORS METHOD

    Test results for 6 bus system

    An example 6-bus power system with three generators

    and five load centers are shown to verify and compare the

    proposed CF formulas with the PFC method. Fig 4 gives

    the topology of the 6-bus test system and the line flow

    results. The contribution of the generator units to line

    flows, resulting from the implementation of CF formulas

    and PFC method, is shown in Tables 3 and 4, respectively.

    The contribution of the generators to load centers,

    resulting from the implementation or CF formulas and the

    PFC method, is shown in Tables 5 and 6, respectively.

    Table 7 shows the voltage at each network node changes,

    when the PFC method is enforced and the generation and

    'corresponding load' are removed. These results indicate

    that the 'constant voltage' assumption, which is applied in

    the PFC method, is not acceptable as accurate.

    250MW

    60

    40 50

    20 10

    30

    250MW

    350.145MW

    50MW

    100MW

    200 MW

    200MW

    300MW

    Fig 4: 6-bus system

    Application in Congestion Management

    In this Section, the implementation of the proposed CF

    formulas and PFC method [20] in the transmission

    congestion management are presented. The proposed CF

    formulas can provide guidance to relieve congestion

    problems. Results on the 25-bus test system show the

    ability and accuracy of CF over PFC for solving

    transmission congestion problems. In this test system,

    line-22 (130 bus-230 bus) is heavily loaded with a total

    line flow of 381.54MW. Based on the CF and PFC

    methods, transmission congestion management solutions

    are suggested as shown in Tables 8 and 9 respectively.

    Tables 8 and 9 show the contribution ( P) of each

    generator to line-22 based on the CF and PFC methods,

    respectively. The results of these tests show the

    sensitivities of line-22 flow changes vs. the generation

    changes ( line.22/ G ).This tests shown are chosen to

    decrease the flow of line-22 with more flexibility because

    they present the maximum value in the above sensitivities.

    Since line-21 (120 bus- 230 bus) is also heavily loaded

    (366.51 MW), the sensitivities of line-21 ( line.21/ G )

    are shown in Tables 7 and 8 as well, so that a management

    method, with a minimum impact on line-21, can he found.

    Tests 1 to 5 apply 1 MW to each generation change. In

    tests 1, 3, 4 and 5, generators whose power output changes

    (1 MW) have the same effect on the sensitivities ( P

    / G ) are indicated with '(or)'. Both methods predict

    that the line flows can be decreased with more flexibility.

    The difference between these methods is the proposed

    scenario for solving the congestion problem, and that

    occurs because of the inaccuracy of the 'constant voltage'

    assumption of the PFC method [20].

    IV. CONCLUSIONS

    In this paper, the Power Flow Comparison Method (PFC)

    and CF method has been analyszed and applied for

    congestion management by rescheduling the power

    available from the generators. Results of calculations

    applied to an example 6 bus power system and IEEE-57

    bus test systems are presented, compared and discussed to

    verify the correctness of the methods. An application of

    PFC and CF approaches has been carried-out and

    compared for 25-bus system for congestion management

    studies. In particular, the following conclusions are made

    Changes in generation suggested by all the methods

    will affect flows in other lines. Hence, other heavily

    loaded lines should be considered as well when solving

    a transmission congestion problem. The PFC Method

    provides convenient facilities for doing this.

    The sensitivities used in the congestion management

    change very little when the generation is increased.

    According to the PFC Method, all generators have

    some contribution to each line flow. Based on their

    contribution, the order in which the generators should

    be adjusted can be determined. When a generator has a

    positive contribution to the line flow, the output of this

    generator needs to be decreased to lower the

    transmission congestion and vice versa. When two

    generators have conflicts in congestion management,

    the one with higher MW contribution has more impact

    on the line flow changes.

    The Proportional Sharing Method sometimes may

    lead to changes in the wrong direction.

    The CF based approach expressing the contribution of

    each generator unit to loads or flows or losses or lines has

    been implemented based on [16].The proposed CF

    formulas are applicable independently to active and

  • International Conference on Deregulated Environment and Energy Markets, July22-23, 2011

    6

    reactive loads, flows and losses replacing the real power

    by reactive power in the load flow scheme. These

    formulas and other state-of-the-art methods have been

    tested on various test systems to compare results. The

    results obtained from CF are similar as obtained from PFC

    method. Also, the proposed CF formulas can provide

    guidance to relieve the congestion problems

    REFERENCES

    [1] L.PHILIPSON and H.LEE WILLIS, Understanding Electric Utilities and Deregulation, Marcell Dekker Inc., NY 1998.

    [2] R.S.FANG and A.K. DAVID, Transmission Congestion Management in Electricity Market, IEEE Transactions on Power Systems, Vol. 14, No. 3, August 1999, pp. 877-883.

    [3] North American Electric Reliability Council (NERC), Available Transfer Capability Definition and Determination, NERC Report,

    June 1996. [4] D. KIRSCHEN, R ALLEN and G. STRBAC, Contributions of

    Individual Generators to Loads and Flows. IEEE Transactions on Power Systems, Vol. 12, No. 1, pp. 52-60, February 1997.

    [5] G. STRBAC, D. KIRSCHEN, S. AHMED, Allocating Transmission System Usage on the Basis of Traceable Contributions of Generators and Loads to Flows, paper PE-222-PWRS-0-01-1997, IEEE, 1997.

    [6] J. BIALEK, Topological Generation and Load Distribution Factors for Supplement Charge Allocation in Transmission Open

    Access, IEEE Transactions on Power Systems, Vol. 12, No. 3, August 1997.

    [7] J. BIALEK, Identification of Source-sink Connections in Transmission Networks, Power Systems Control and Management, 16-18 April 1996.

    [8] R. SHOULTS and L.D. SWIFT, A comparison Between Circuits Based Methods and Topological Trace Methods for Determining

    the contribution of Each Generator to Load and Line Flows, Proceedings of the workshop on Available Transfer Capability, pp.

    167-182, University of Illinois at Urbana-Champaign, June 26-28,

    1997. [9] R. A. WAKEFIELD, J. S. GRAVES, A. F. VOJDANI, A

    Transmission Services Costing Framework, IEEE Transactions on Power Systems, Vol. 12, No. 2, May 1997.

    [10] C. W. YU, A. K. DAVID, Pricing Transmission Services in the Context of Industry Deregulation, IEEE Transactions on Power Systems, Vol. 12, No. 1, February 1997.

    [11] H. H. HAPP, Cost of Wheeling Methodologies, IEEE Transactions on Power System, Vol. 9, No. 1, February 1994.

    [12] J. D. FINNEY and H. A. OTHMAN, Evaluating Transmission Congestion Constraints in System Planning, IEEE Transactions on Power System, Vol. 12, No. 3, August 1997.

    [13] H. SINGH, S. HAO and A. PAPALEXOPOULOS, Transmission Congestion Management in Competitive Electricity Markets, paper PE-543- P WRS-2-06-2997, IEEE, 1997.

    [14] R. A. WAKEFIELD, J. S. GRAVES, A. F. VOJDANI, A Transmission Services Costing Framework, IEEE Transactions on Power Systems, Vol. 12, No. 2, May 1997.

    [15] A.G. BAKIRTZIS: Sensitivity computation of power flow control in electric power systems. Electric Power System. I991. 22. pp. 77-84

    [16] J.G.VLACHOGIANNIS: Accurate model for contribution of generation to transmission system effect on charges and congestion management. IEEE proceeding generation transmission vol.147 no.6 November 2000, pp342-348.

    [17] J. D. GLOVER and G. DIGBY, Software Manual, Power System Analysis and Design, Second Edition, PWS Publishing Company,

    Boston, 1994.

    [18] JIAN YANG, Power Systems Deregulation and Development of Powergraf, a PhD Dissertation, University of Missouri - Rolla, July, 1998.

    [19] J.G. VLACHOGIANNIS: Control Adjustment in Fast Decoupled load flow, Electric Power System Res. I994. 31..pp. 185-194.

    [20] J. YANG and M. D, ANDERSON,:Tracing the power flow of power in transmission networks foe use of transmission system charges and congestion management, IEEE Trans. Power System., 1998.13 (2), pp.399-405.

    [21] www. Constec.de, Towards a common coordinated congestion management methods in Europe, Final Report, 2007, Directorate-General Energy Transport, 2007.

    [22] www.nordiceenergyregulators.org, Congestion management in the Nordic region: A common regulatory opinion on congestion

    management, A report, 2007.

  • International Conference on Deregulated Environment and Energy Markets, July22-23, 2011

    7

    TABLE. 1 : CASE #1 - LINE 8 IS HEAVILY LOADED, G3 MUST BE DECREASED

    Method

    LF_G 1

    (MW)

    LF_G2

    MW)

    LF_ G3

    (MW)

    LF_G4

    (MW)

    Production of

    management

    PS

    PFC

    0

    -23.342

    0

    1.0689

    174.0983

    232.6123

    0

    -36.2409 G1 G2

    G3 G4

    G1 G2 G3 G4

    Test

    G1

    G2

    G3 G4

    G

    Pline

    G

    Pline 15

    1

    2

    3

    4

    5

    6

    +1

    0

    0

    +1

    0

    -1

    -1

    -1

    0

    0

    +1

    0

    0

    0

    -1

    -1

    -1

    0

    0

    +1

    +1

    0

    0

    +1

    -0.0841

    -0.1781

    -0.7031

    -0.090

    -0.5250

    -0.0941

    +0.3715

    +0.0343

    +0.0523

    +0.3795

    +0.0181

    -0.3372

    Method

    LF_G1(MW))

    LF_G2(MW)

    LF_G3(MW) LF_G4(MW) Production of management

    PS

    PFC

    0

    -23.342

    0

    1.0689

    174.0983

    232.6123

    0

    -36.24O9 G1 G2 G3 G4

    G1 G2 G3 G4

    TABLE. 2: CASE #2 - PS METHOD GIVES WRONG ANSWER AND PFC METHOD PROVIDES ALTERNATIVES

    TABLE 3: CONTRIBUTION OF GENERATION OF 6-BUS TEST SYSTEM TO LINE FLOWS RESULTING FROM CF FORMULAS

    Lines

    Contribution Of G-10

    (MW)

    Contribution

    Of G-20 (MW)

    Contribution of G-30

    (MW)

    10-20

    10-30 10-40

    20-50

    30-50 30-60

    40-60

    50-40

    90.617

    127.702 131.811

    70.038

    32.955 53.559

    49.415

    20.600

    106.71 0 41.184 65.552

    128.558

    -19.321 31.099

    06.723

    50.409

    14.695

    -58.830 44.123

    0.0104

    73.524 88.230

    -14.705

    14.707

    TEST G1MW G2MW G3MW G4 MW G

    Pline 8

    1

    2

    3

    4

    5

    6

    7

    8

    +1

    0

    0

    -1

    0

    0

    0

    -1

    0

    +1

    0

    0

    -1

    0

    +1

    +1

    -1

    -1

    -1

    +1

    +1

    +1

    0

    0

    0

    0

    +1

    0

    0

    -1

    -1

    0

    +0.0092

    +0.0048

    +0.0144

    -0.0092

    -0.0048

    -0.0144

    -0.0096

    -0.0044

  • International Conference on Deregulated Environment and Energy Markets, July22-23, 2011

    8

    TABLE 4: CONTRIBUTION OF GENERATION OF 6-BUS TEST SYSTEM TO LINE FLOWS RESULTING FROM PFC METHOD [20]

    Lines

    Contribution

    Of G-10 (MW)

    Contribution

    Of G-20 (MW) Contribution

    Of G-30 (MW)

    10-20 10-30

    10-40

    20-50 30-50

    30-60

    40-60 50-40

    89.725 126.897

    131.535

    70.144 32.987

    53.725

    49.114 20.736

    106.370 40.880

    65.490

    128.217 -19.051

    31.258

    6.657 50.315

    14.346 -58.527

    44.181

    0.378 73.261

    88.078

    -1 4.643 14.811

    TABLE 5: CONTRIBUTION OF GENERATION OF 6-BUS TEST SYSTEM TO LOAD CENTERS RESULTING FROM CF FORMULAS

    (Load centers)/ load (MW)

    Contribution of G-10 (MW)

    Contribution of G-20 (MW)

    Contribution of G-30 (MW)

    120)/50

    (30)/100 (40)/100

    (50)/200

    (60)/300

    20.579

    41.188 82.396

    82.393

    123.574

    14.732

    29.406 58.829

    58.828

    88.231

    14.684

    29.416 58.828

    58.827

    88.232

    TABLE 6: CONTRIBUTION OF GENERATION OF 6-BUS TEST SYSTEM TO LOAD CENTERS RESULTING FROM PFC METHOD [20]

    (Load centers)/

    load (MW)

    Contribution

    of G-10 (MW)

    Contribution

    of G-20 (MW)

    Contribution

    of G-30(MW)

    (20)/50 (30)/100

    (40)/100

    (50)/200 (60)/300

    19.581 40.185

    82.421

    82.395 123.575

    15.413 28.673

    58.833

    58.821 88.230

    13.968 30.134

    58.824

    58.828 88.246

    TABLE 7: VOLTAGE DIVERGENCES WHEN PFC METHOD [20] IS APPLIED IN 6-BUS TEST SYSTEM

    Load bus

    Base case Load flow solution

    (Voltage p. u.)

    bus voltage when Generation and

    corresponding load

    are removed

    V ( voltage divergences)

    (%s)

    20

    30

    40 50

    60

    1.000

    1.000

    0.993 0.996

    0.994

    0.967

    0.958

    0.959 0.954

    0.950

    3.3

    4.2

    3.4 4.2

    4.4

    TABLE 8: APPLICATION OF CF FORMULAS IN CONGESTION MANAGEMENT OF 25-BUS TEST SYSTEM (LINE-22 IS HEAVILY LOADED)

    Contribution of generation to flow of line-22

    Method G10 G20 G70 G130 G150 G160 G180 G210 G220 G230

    ( MW ) ( MW ) ( MW ) ( MW ) ( MW ) ( MW ) ( MW ) ( MW ) ( MW ) ( MW )

    CF 7.643 7.940 9.323 73,799 -19.957 -21.463 -50.060 -48.928 -54.131 -285.706

  • International Conference on Deregulated Environment and Energy Markets, July22-23, 2011

    9

    TABLE 9: APPLICATION OF PFC METHOD [20] IN CONGESTION MANAGEMENT OF 25-BUS TEST SYSTEM (LINE-22 IS HEAVILY LOADED)

    Proposed output changes of generation in order to lower line flows in line-22 to be achieved

    Test

    G10 G20 G70 G130 G150 G160 G180 G210 G220 G230

    ( MW ) ( MW ) ( MW ) ( MW ) ( MW ) ( MW ) ( MW ) ( MW ) ( MW ) ( MW )

    1

    2

    3

    4

    5

    (or)+1 (or)+1 (or)+1 -1

    +1 -1 (or)+1 (or)+1 (or)+1 (or)+1 (or)+1 -1

    +1 or)-1 (or)-1 (or)-1 (or)-1 (or)-1

    (or)-1 (or)-1 (or)-1 +1

    Results of tests line.22/ G line.21/ G

    1

    2

    3

    4

    5

    -0.29 -0.27

    -0.45 -0.25 -0.14 -0.11

    -0.31 -0.30

    -0.16 -0.04

    Contribution of generation to flow of line-22

    Method G10 G20 G70 G130 G150 G160 G180 G210 G220 G230

    ( MW ) ( MW ) ( MW ) ( MW ) ( MW ) ( MW ) ( MW ) ( MW ) ( MW ) ( MW )

    PFC 8.168 8.309 10.632 73.501 -20.312 -21.971 -51.110 -49.536 -54.203 -285.018

    Proposed output changes of generation in order to lower line flows in line-22 to be achieved

    Test

    G10 G20 G70 G130 G150 G160 G180 G210 G220 G230

    ( MW ) ( MW ) ( MW ) ( MW ) ( MW ) ( MW ) ( MW ) ( MW ) ( MW ) ( MW )

    1

    2

    3

    4

    5

    (or)+1 (or)+1 (or)+1 -1

    +1 -1

    (or)+1 (or)+1 (or)+1 (or)+1 (or)+1 -1 +1 or)-1 (or)-1 (or)-1 (or)-1 (or)-1

    (or)-1 (or)-1 (or)-1 +1

    Results of tests line.22/ G line.21/ G

    1

    2

    3

    4

    5

    -0.24 -0.22 -0.48 -0.19

    -0.26 -0.23

    -0.37 -0.35 -0.07 +0.11

  • International Conference on Deregulated Environment and Energy Markets, July22-23, 2011

    10

    Chaotic Particle Swarm Optimization for

    Reduced Order Model of Automatic Generation

    Control 1Cheshta Jain,

    2H. K. Verma

    1, 2SGSITS, Indore

    [email protected]

    [email protected]

    Abstract This paper presents a new approach to control frequency and tie line power changes of multi area

    interconnected system. AGC is very important in power

    system to maintain system frequency and tie-line power,

    when system subjects to small load perturbations. Chaotic

    particle swarm (CPSO) is used to optimize gains of PI

    controller and bias frequency, to maintain system frequency

    and tie-line power flow at scheduled values. In this paper,

    model order reduction technique has been used to obtain

    lower order model for study of automatic generation control

    (AGC). Model order reduction method can preserve the

    identity of each generating unit. With this technique, the

    computational complexity and effective time has been

    reduced by re-sorting the lower order generating unit

    models. This paper also presents the selection of suitable

    value for governor speed regulation parameter. The

    proposed method shows its robustness under critical

    conditions when conventional optimization methods fail.

    Keywords chaotic particle swarm optimization, automatic generation control, reduced order of AGC.

    NOMENCLATURE F = Frequency deviation. i = Subscript referring to area (i = 1,2,). Ptie (i,j) = Change in tie line power. Pdi = Load change of i

    th area.

    Di = PDi / Fi Ri = Governor speed regulation parameter for i

    th area.

    Thi = Speed governor time constant for ith area.

    Tti = Speed turbine time constant for ith area.

    TPi = Power system time constant for ith area.

    KPi = Power system gain for ith area.

    ACEi = Area control error of ith area.

    Hi = Inertia constant of ith area.

    Ui = Control input to ith area.

    Bi = Frequency bias for ith area.

    Us = Undershoot of ACE.

    Mp = Overshoot of ACE.

    ts = Settling time ACE.

    tr = Rise time of ACE.

    ess = Steady state error of ACE.

    W = Inertia weight.

    C1, C2 =acceleration coefficient.

    I. INTRODUCTION

    Automatic generation control is one of the most

    important issues in power system design. The purpose of

    AGC is fast minimization of area frequency deviation and

    mutual tie-line power flow deviation of areas for stable

    operation of the system.

    The overall performance of AGC in any power system

    depends on the proper design of speed regulation

    parameters and gains of controller. Fixed linear feedback

    controller fails to provide best control performance. There

    are no well defined methods available to compute tie-line

    constant for an area with non-coherent generators and

    multiple tie-line. The complexity of computation of tie-

    line increases with the increase in number of areas. This

    paper presents a reduced order AGC simulation technique

    that overcomes this problem. These reduced order systems

    overcome the need of identifying the non-coherent set of

    generators in order to control the areas. This technique is

    based on some assumptions. These assumptions follow the

    fact that, all areas are operating at same frequency and tie-

    line flow can no longer be computed in actual system. Tie-

    line flows are required to determine area control error [3].

    The conventional controller improves steady state error

    (ess) but with small overshoot. PI controller has such

    capability to improve transient performance with

    minimum steady state error. The aim of this paper is to use

    CPSO to find optimum gains of PI controller and

    frequency bias with proper system parameter. CPSO is an

    optimization approach based on the PSO with adaptive

    inertia weight factor methods. It provides more precise

    description of natural swarm behaviour.

    In the view of the above, following are main objectives

    of the proposed paper:

    1. To reduced the order of the generating unit of AGC system.

    2. To optimized the gains of PI controller and frequency bias coefficient using chaotic PSO algorithm in

    MATLAB.

    3. To examine the effect of speed regulation parameters on reduced system.

    The rest of the paper is organized as follow: section I

    presents AGC system model with proposed reduction

    technique. In section II chaotic particle swarm

    optimization is discussed in brief and an algorithm to

    implement CPSO based PI controller is presented in

    section III. Section VI shows the result with discussion

    and conclusion is drawn in section V.

  • International Conference on Deregulated Environment and Energy Markets, July22-23, 2011

    11

    II. SYSTEM MODEL

    A. Conventional AGC system

    Automatic control system of close loop system means

    minimizing the area control error (ACE) to maintain

    system frequency and tie-line deviation are set at nominal

    value [15]. Block diagram of two area system is shown in

    Fig 1.

    Fig 1: Linear model of two area system.

    The ACE of each area is linear combination of biased

    frequency and tie-line error.

    (1)

    Where, Bi is frequency bias coefficient of ith

    area. Fi is frequency deviation and Ptie is tie-line error of i

    th area.

    Based on the ACE a suitable control strategy can be taken

    up either continuously or discretely. A practical system

    consists of a number of generating units, which increases

    computational time and complexity. In this paper the

    reduction of order is used to reduce above effort.

    B. Reduced order generating unit

    Several methods are available for reducing the order

    of a system transfer function (TF) [14]. One way is to

    delete a certain insignificance pole of a transfer function,

    which has a negative real part that is much more negative

    than the other poles [14]. An effective approach is to

    match the frequency response of the reduced order transfer

    function with the original TF frequency response. Suppose

    the higher order system is described as:

    (2)

    This system has poles in the left hand s-plane and m n. The lower order approximate transfer function is:

    (3)

    Where, p q n. The gain K is the same for original and approximated system. This method is based on

    selection of c and d in such a way that GL(s) has a

    response very close to that of GH(s). These coefficients are

    evaluated as:

    (4)

    And

    (5)

    Where, M(s) and (s) are the numerator and denominator polynomials of GH(s)/GL(s) respectively. To

    determine total (cp + dq) no of unknowns, requires (cp + dq)

    no of equations. Therefore define

    (6)

    g = 0, 1, 2, ---- up to number required to solve the

    unknown coefficients. An analogous equation for 2g. the solution for c and d coefficient is obtained by equating

    M2g = 2g. In this paper two area AGC system is considered.

    This model has second order transfer function of

    generating unit of each area as:

    (7)

    The value of AGC parameters (TH and TL) are given

    in appendix. After reduction as above method the lower

    order generating unit becomes:

    (8)

    III.OVERVIEW OF CHAOTIC PARTICLE SWARM OPTIMIZATON

    a. General PSO method

    Particle swarm optimization (PSO) first proposed by

    Kennedy and Eberhart [5]. Like evolutionary algorithms,

    PSO techniques conducts search using a population of

    particles, corresponding to individuals. In PSO, particles

    changes their position by flying around in a search space

    until computation limitations are exceed. PSO is inspired

    by the ability of flocks of birds to reach unknown

    destination. In PSO each particle is defined as moving part

    in hyperspace. PSO is inherently continuous and must be

    modified to handle design variables.

    The basic PSO algorithm requires three steps [5].

    Step 1: Initialization

    PSO is initialized with the group of random particle

    positions (xki) and velocities (Vk

    i) between upper and

    lower bound of design variable values for N particles as

    expressed in equation 9.

    X0i = Xmin + rand*(Xmax Xmin) (9)

    Velocity is initialized as:

    (10)

  • International Conference on Deregulated Environment and Energy Markets, July22-23, 2011

    12

    i = 0,1,2,.N. Step II: Update velocity

    Velocity of all particle updated for next (k+1)th

    iteration

    using the particles fitness values, which is function of

    particle positions. These fitness function value determines

    which particle has a global best (gbestk) value in the

    current swarm (kth

    iteration) and also determine the best

    position (pbesti) of each i

    th particles.

    The global best value speed up the rate of convergence.

    gbest value maintains only single best solution across the

    entire particle in the search space. If all particles are

    converging to this position, the further improvement of

    each particle stops.

    After finding the two best values, the particles update its

    velocity using following equation:

    (11)

    Where w is inertia weight factor, c1 and c2 are self

    confidence and swarm confidence respectively.

    Combinations of these values usually lead to much slower

    convergence or sometimes non-convergence at all.

    Therefore proper selection of these particles is important.

    Step III: Update positions

    Now positions of particles are updated using

    following equation:

    (12)

    a. Chaotic PSO

    The parameters r1 and r2 in equation (11) are important

    control parameters. The use of chaotic sequence in PSO

    can be useful to escape from local minima than general

    PSO [4].

    Chaotic sequence based on Henon mapping is used for random value r1as:

    (14)

    Where, a and b are Henon map attractor. Another mapping uses the same equation for random value r2 to

    generate z 2(t) in range [0, 1]. Other parameters are same

    as in equation (10). Hence, velocity of particle is updated

    as:

    (15)

    IV. IMPLEMENTATION OF CPSO-PI CONTROLEER

    A. Fitness function

    The gain of PI controller can be selected based on degree

    of relative stability, minimum overshoot, undershoot and

    settling time. To satisfy all requirements following

    objective function is design.

    (16)

    B. Algorithm

    Step1. Choose the population size (N) and number of Step2. iteration (Nmax). Set the value of inertia weight w. Step3. Generate initial population (eq. 9) and velocities

    randomly as given in equation10:

    Step4. Set counter k=1. Step5. Run model of reduced AGC system and

    determine performance parameters for each

    particle.

    Step6. Calculate fitness function for each particle (eq.16). Calculate gbest and pbest position value.

    Using these values update velocity of each

    particle (eq.15).

    Step7. Update position of each particle (eq. 12). Step8. Calculate new fitness function for each updated

    particles position, if it is better than previous value of fitness function then the current value of

    particle position is set to pbesti.

    Step9. Set k = k + 1. Step10. If the last change of the best solution is greater

    than a pre specified number or the number of

    iteration reaches the maximum iteration, stop the

    process, otherwise go to step 4.

    V. RESULT AND DISCUSSION

    A comparative study of CPSO algorithm on reduced

    order and full order model is carried out in this paper. The

    time response plots of area control error of area 1 of the

    reduced order as well as full order AGC system is given in

    Fig2-5. These Figures shows the variation in system

    frequency, tie-line power flow and area control error for

    1% step load perturbation on area two. From these Figures

    it can be seen that the response of reduced order

    generating unit model and actual model are approximately

    identical.

    Table I presents computational result for a input data set

    1 (Tp=10, R= 8% frequency, T12=0.145). The results

    clearly established that reduced order model has less

    computational time than full order model with

    approximately same performance parameters. Hence,

    lower order model can be used to obtain desired response

    with saving in computation time.

    The gains of PI controller and frequency bias are

    obtained by chaotic PSO algorithm for different value of

    system parameters of reduced order AGC system. As Fig

    6-13 shows, PI controller act too fast to the generator

    inputs and also exhibits fast oscillations. In all cases, an

    acceptable overshoot and settling time on frequency

    deviation signal in each area is maintained.

    Table-II gives transient response parameters of CPSO

    based PI controller for different data set. Three sets of

    Input data have been used in this paper, namely data set1

    (Tp = 10, R = 8%, T12 = 0.145), data set2 (Tp=30, R=8%

    of frequency, T12=0.145) and data set3 have (Tp=30,

  • International Conference on Deregulated Environment and Energy Markets, July22-23, 2011

    13

    R=4% of frequency, T12=0.145). Table-II and Figures 10-

    13 shows that the large values of power system time

    constant (Tp=30) and low value of T12 (0.145) yield large

    value of undershoot, overshoot and settling time and hence

    high value of fitness function. These values (undershoot,

    overshoot, settling time for data set2) become lower as

    speed regulation, R decreases from 8% to 4% of

    frequency.

    The initial sharpness of the response in undershoot and

    overshoot lies due to choice of weighting factor (1000 and

    100) in the fitness function

    TABLE. I: COMPARISON OF ACTUAL AND REDUCED ORDER SYSTEM FOR DATA SET-I

    TABLE II: COMPARISON OF EFFECT ON INPUT SYSTEM PARAMETERS ON

    REDUCED ORDER AGC SYSTEM.

    Dataset1 (Tp=10, R=8% of freq, T12=0.145).

    Dataset2 (Tp=30, R=8% of freq, T12=0.145).

    Dataset3 (Tp=30, R=4% of freq, T12=0.145).

    Fig 2: Variation in area control error in reduced order and full order

    system

    Fig 3: Comparison of tie-line power for reduced order and full order

    AGC system

    Fig 4: Comparison of area frequency 1 for reduced order and actual

    system.

    Fig 5: Comparison of area frequency 2 for reduced and actual system

    Fig 6: Variation in area control error in dataset1 and dataset2

    Fig 7: Variation in area frequency 1 for dataset 1 and dataset 2.

  • International Conference on Deregulated Environment and Energy Markets, July22-23, 2011

    14

    Fig 8: Variation in area frequency2 for dataset 1 and dataset 2.

    0 5 10 15 20 25 30 35 40-2

    -1

    0

    1

    2

    3

    4x 10

    -3

    Step Response

    Time (sec)

    Am

    plitu

    de

    p12_dataset1

    p12_dataset2

    Fig 9: Comparison of tie-line power flow.

    0 5 10 15 20 25 30 35 40-4

    -3

    -2

    -1

    0

    1

    2

    3x 10

    -3

    Step Response

    Time (sec)

    Am

    plitu

    de

    ACE1_dataset3

    ACE1_dataset2

    Fig 10: Comparison of ACE for dataset 2 and dataset 3.

    0 5 10 15 20 25 30 35-0.025

    -0.02

    -0.015

    -0.01

    -0.005

    0

    0.005

    0.01

    Step Response

    Time (sec)

    Amplitude

    f1_dataset3

    f1_dataset2

    Fig 11: Variation in area frequency 1 for dataset 2 and dataset3.

    0 5 10 15 20 25 30 35-0.03

    -0.025

    -0.02

    -0.015

    -0.01

    -0.005

    0

    0.005

    0.01

    Step Response

    Time (sec)

    Amplitu

    de

    f2_dataset3

    f2_dataset2

    Fig 12: Comparison of area frequency 2 for dataset 2 and dataset3.

    0 5 10 15 20 25 30 35 40-2

    -1

    0

    1

    2

    3

    4x 10

    -3

    Step Response

    Time (sec)

    Am

    plitu

    de

    p12_dataset3

    p12_dataset2

    Fig 13: Comparison of tie-line power flow for dataset 2 and dataset 3.

    VI. CONCLUSION

    In this paper CPSO method is used to obtain optimum

    gains of PI controller and frequency bias coefficient.

    CPSO is new variant of PSO with faster speed because of

    strong selection principle. In simple PSO, after certain

    iterations, the populations set are almost identical and no

    further improvement is observed. Reduced order AGC

    system has shown saving in computation time with

    identical responses. Like any other algorithms, this

    method also somewhat sluggish in nature but positive

    aspect of this method is its reliability and the number of

    required generation for convergence decreases with

    increase of population size.

    APPENDIX

    Nominal parameters of two area test system [15]:

    H1= H1= 5 seconds

    D1= D2= 8.3310-3

    P.U. MW/Hz

    R1= R1=2.4 Hz/P.U. MW

    Th1= Th2=80 ms

    Tt1= Tt2=0.3 seconds

    Kp1= Kp2=120HzP.U. MW

    Parameters for CPSO:

    Population size= 20

    Number of iteration=100

    Wmin=0.6

    Wmax=1

    REFERENCES

    [1] Zhihua Cui, Xingjiuan Cai and Jianchao zeng, Chaotic performance dependent particle swarm optimization. Division of system simulation and computer application Taiyuan University of

    science and technology.

  • International Conference on Deregulated Environment and Energy Markets, July22-23, 2011

    15

    [2] C.F. Chen and L.S. Sheieh, A novel approaches to linear model simplification, International journal of control, 8, 561-570, 1968.

    [3] K.C. Divya and P.S. Nagendra Rao, A novel AGC simulation scheme based on reduced order prime mover models, IEEE transaction on control system and applications, 1099-1103, 2003.`

    [4] X. J. Cai, Z. H. Cui, J. C.Zeng and Y. Tan, Performance-dependent adaptive particle swarm optimization, International Journal of Innovative Computing, Information and Control, Vol.3,

    No.6B,pp.1697-1706, 2007.

    [5] J. Kennedy and R. Eberhart, Particle swarm optimization, in Proc. IEEE Int. Conf. Neural Networks, vol. IV, Perth, Australia,

    1995, pp. 19421948. [6] Z.-L. Gaing, A particle swarm optimization approach for

    optimum design of PID controller in AVR system, IEEE Trans. Energy Conversion, vol. 19, pp. 384-391, June 2004.

    [7] M. Clerc, The swarm and the queen: towards a deterministic and adaptive particle swarm optimization, Proceedings of the IEEE Congress on Evolutionary Computation (CEC 1999), pp.

    1951-1957, 1999. [8] .D.Goldberg, Genetic algorithm in search optimization and

    machine learning, Addison-Wesley, 1989. [9] Rania Hassan, Babak Cohanim, Oliver de Week, A comparison

    of Particle Swarm Optimization and the Genetic Algorithm American institute of aeronautics and astronautics.

    [10] R. C. Eberhart and J. Kennedy, A new optimizer using particle swarm theory, Proceedings of the Sixth International Symposium on Micro Machine and Human Science, Nagoya,

    Japan, pp.39-43,1995 [11] K.P. Wong, Z. Y. Dong, Special issue on evolutionary

    computation for system and control application international journal of system science, vol, 35, No. 13-14, 20 oct-15 Nov.2004, pp 729-730.

    [12] R. C. Eberhart and J. Kennedy, A new optimizer using particle swarm theory, Proceedings of the Sixth International Symposium on Micro Machine and Human Science, Nagoya, Japan, pp.39-

    43,1995.

    [13] G. Yu, and R. Hwang, Optimal PID speed Control of brush less DC motors using LQR Approach, in Proc. IEEE Int. Conf. Systems, Maand Cybernetics, 2004, pp. 473-478.

    [14] Richard C. Dorf and Robert H. Bishop, Modern control system, Pearson international edition 2003.

    [15] O.I. Elgerd, Electric energy system theory an introduction, McGraw Hill Co., 2001.

  • International Conference on Deregulated Environment and Energy Markets, July22-23, 2011

    16

    Combined Economic/Environmental Dispatch

    with Fuzzified Multi-Objective Particle Swarm

    Optimization considering Voltage Stability 1S. Surender Reddy,

    2A. R. Abhyankar,

    3P. R. Bijwe

    1, 2, 3Indian Institute of Technology Delhi

    [email protected] ,

    [email protected],

    [email protected]

    AbstractTraditional Economic Load Dispatch deals with minimizing generation cost while satisfying a set of equality

    and inequality constraints. The fossil fuel plants pollutes

    environment by emitting some toxic gases. Thus,

    conventional minimum cost operation cannot be the only

    basis for generation dispatch; emission minimization must

    also be taken care of. The objective of reactive power

    optimization problem can be seen as minimization of real

    power loss over the transmission lines. Large integrated

    power systems are being operated under heavily stressed

    conditions which imposes threat to voltage stability. The

    objectives economic dispatch, emission dispatch, loss

    minimization and voltage stability are to be met for efficient

    operation and control. The results of all the four objectives,

    considering one objective at a time are conflicting and non

    commensurable. Hence, an efficient control which meets all

    the specified objectives is required. Initially each objective is

    optimized individually using Particle Swarm Optimization

    (PSO) and then all the four objectives are optimized

    simultaneously using fuzzified PSO. The effectiveness of the

    proposed approach is tested on IEEE 30 bus system.

    Keywprds Economic load dispatch, emission dispatch, reactive power optimization, voltage stability, particle swarm

    optimization (PSO), fuzzy min-max approach.

    I. INTRODUCTION

    The Power system should be operated in such a way that

    both real and reactive power are optimized

    simultaneously. Real power optimization problem is the

    traditional economic dispatch which minimizes the real

    power generation cost. Reactive power should be

    optimized to provide better voltage profile as well as to

    reduce total system transmission loss. Traditional

    Economic Dispatch [1] aims at scheduling committed

    generating units outputs to meet the load demand at

    minimum fuel cost while satisfying equality and inequality

    constraints. On the other hand, thermal power plants

    (which contribute major part of electric power generation)

    create environmental pollution by emitting toxic gases

    such as carbon dioxide (CO2), sulphur dioxide (SO2),

    nitrogen oxides (NOx). Initially, Combined Economic and

    Environmental/Emission dispatch (CEED) problem was

    solved by minimizing fuel cost considering emission as

    one of the constraints. The CEED problem is one of the

    fundamental issues in power system operation. The

    operation and planning of a power system is characterized

    to maintain a high degree of economy and reliability [2].

    Among the options available to the power system

    operators to operate the generation system, the most

    significant is the economic dispatch. Traditionally electric

    power plants are operated on the basis of least fuel cost

    strategies and only little attention is paid to the pollution

    produced by these plants. The generation of electricity

    from the fossil fuel releases several contaminants, such as

    sulphur oxides (SO2), nitrogen oxides (NOx) and carbon

    dioxide (CO2) into the atmosphere. But, if pollution is

    decreased by suitably changing the generation allocation,

    the cost of generation increases deviating from economic

    dispatch. The characteristics of emissions of various

    pollutants are different and are usually non-linear. This

    increases the complexity of the CEED problem. Large

    integrated power systems are being operated under heavily

    stressed conditions which imposes threat to voltage

    stability. Voltage collapse occurs when a considerable part

    of the system attains a very low voltage profile or

    collapses. Hence, voltage stability of the system is also an

    important consideration and need to be taken care of

    simultaneously along with economic dispatch. The four

    objectives of minimization of fuel cost, minimization of

    emission, minimization of losses and minimization of

    system stability index are conflicting and non

    commensurable. Hence, trade off solution using fuzzy

    min-max approach is proposed in this paper. Assuming the

    decision maker (DM) has imprecise or fuzzy goals of

    satisfying each of the objectives, the multi-objective

    problem can be formulated as a fuzzy satisfaction

    maximization problem which is basically a minmax

    problem. PSO is an unconstrained optimization method. A

    PSO method that includes the constraints penalty factor

    approach is used to convert the constrained optimization

    to an unconstrained optimization problem [3]. In PSO, the

    search for an optimal solution is conducted using a

    population of particles, each of which represents a

    candidate solution to the optimization problem. Particles

    change their position by flying round a multidimensional

    space by following current optimal particles until a

    relatively unchanged position has been achieved or until

    computational limitations are exceeded. Each particle

    adjusts its trajectory towards its own previous best

    position and towards the global best position attained till

    then. PSO is easy to implement and provides fast

    convergence for many optimization problems and has

  • International Conference on Deregulated Environment and Energy Markets, July22-23, 2011

    17

    recently gained lot of attention in power system

    applications. In [4], it is demonstrated that PSO gets better

    results in a faster, cheaper way compared with other

    methods. In PSO, the potential solutions called particles,

    fly through the problem space by following the current

    optimum particles. Compared to GA, the advantages of

    PSO are that PSO is easy to implement and there are few

    parameters to adjust. PSO is initialized with a group of

    random particles (solutions) and then searches for optima

    by updating generations [5]. The description and

    applications of PSO are presented in [6, 7]. The main aim

    of this paper is to investigate the applicability of PSO to

    the various optimization problems and prove that this

    algorithm can be used effectively, to determine solutions

    to various complex problems. Fuzzified PSO approach is

    tested on several case studies which are extremely difficult

    to solve by standard techniques due to the non-convex,

    non-continuous and highly nonlinear solution space of the

    problem. The paper is organized as follows. Sections II,

    III, IV and V presents economic load dispatch with fuel

    cost minimization, emission dispatch with emission

    minimization, reactive power dispatch with active power

    loss minimization, voltage stability maximization with L-

    index minimization as single objective optimization

    subproblems using PSO. Section VI describes multi-

    objective optimization problem using fuzzified PSO.

    Finally, brief conclusions are presented in Section VII.

    II. ECONOMIC DISPATCH (ED) USING PSO

    The ED problem is to determine the optimal combination

    of power outputs of all generating units to minimize the

    total fuel cost while satisfying the load demand and

    operational constraints [8].

    A. Objective Function:

    The economic dispatch problem is a constrained

    optimization problem and it can be mathematically

    expressed as follows:

    (1)

    where ai, bi and ci are fuel cost coefficients, subjected to

    number of power system network equality and inequality

    constraints.

    B. Equality Constraint:

    The power balance constraint is an equality constraint that

    reduces the power system to a basic principle of

    equilibrium between total system generation and total

    system loads. Equilibrium is met only when the total

    system generation equals to the total system load (PD) plus

    the system losses (PLoss).

    (2)

    where,

    (3)

    (4)

    Bij are constants called B coefficients or loss coefficients.

    C. Inequality Constraint:

    The maximum active power generation of a source is

    limited by thermal consideration. Unless, we take a

    generator unit offline it is not desirable to reduce the real

    power output below a certain minimum value Pmin.

    Pi,min Pi Pi,max (5) Where Pi,min is minimum power output limit, Pi,max is

    maximum power output limit of ith generator (MW).

    D. Representation of individual:

    For an efficient evolutionary method [9], the

    representation of chromosome strings of the problem

    parameter set is important. The proposed approach uses

    the equal system incremental cost cost as individual (particles) of PSO [2]. Each individual within the

    population represents a candidate solution for solving the

    economic dispatch problem. The advantage of using

    system Lambda instead of generator units output is that, it

    makes the problem independent of the number of the

    generator units and also number of iterations for

    convergence decreases drastically. This is particularly

    attractive in largescale systems.

    E. Evaluation Function:

    We must define the evaluation function for evaluating the

    fitness of each individual in the population. In order to

    emphasize the best chromosome and speed up

    convergence of the iteration procedure, the evaluation

    value is normalized into the range between 0 and 1. The

    evaluation function [5] adopted is

    (6)

    where, k is a scaling constant (k = 50 in this study).

    III. EMISSION DISPATCH (ED) USING PSO

    Fossil-fuel fired electric power plants use coal, gas or

    combinations as the primary energy resource, and produce

    atmospheric emissions whose nature and quantity depend

    on the fuel type and its quality. Coal produces particulate

    matter such as ash and gaseous pollutants such as carbon

    oxides, sulphur oxides and oxides of nitrogen. The thermal

    energy dissipated in cooling water raises its temperature

    and may be considered as a pollutant. Hydro-plants

    produce no such emissions. Nuclear power produces

    radiation emissions, which are well contained. Most of the

    research work summarized aims at reducing oxides of

    sulphur SO2 and oxides of nitrogen NOx. A major effort

  • International Conference on Deregulated Environment and Energy Markets, July22-23, 2011

    18

    has been devoted in reducing one type of pollutants or a

    mixture of pollutants. The approaches are designed either

    to reduce the total production of emissions or to reduce the

    concentration of pollution at ground level at certain areas

    which depends on both emissions and meteorological

    factors.

    A. Objective function:

    The objective of emission dispatch is to minimize the total

    environmental degradation or the total pollutant emission

    due to the burning of fuels for production of power to

    meet the load demand [10]. Dispatch the power generation

    to minimize emissions instead of the usual cost objective

    of economic dispatch is economic and easy in operation

    [11]. The emission function can be expressed as the sum

    of all types of emissions such as NOx, SO2, particulate

    materials and thermal radiation with suitable pricing for

    each pollutant emitted. In this paper only NOx emission is

    taken into account, since it is more harmful than other

    pollutants. The NOx emission can be approximated as a

    quadratic function of the active power output from the

    generating units and it is shown in Fig 1.

    Fig 1: NOx Emission Function

    B. Objective Function:

    The emission dispatch problem is a constrained

    optimization problem and it can be mathematically

    expressed as [12],

    (7)

    where, E is total emission release (Kg/hr) and i, i, i are emission coefficients of the ith generating unit subject to

    demand constraint (8) and generating capacity limits (9).

    (8)

    Pi,min Pi Pi,max (9)

    C. Representation of Individual:

    The proposed approach uses the equal system incremental

    emission release emission as individual (particles) of PSO [13]. Each individual within the population represents a

    candidate solution for solving the emission dispatch

    problem.

    IV. REACTIVE POWER OPTIMIZATION USING PSO

    The purpose of Reactive Power Dispatch (RPD) is mainly

    to improve the voltage profile in the system and to

    minimize the real power transmission loss while satisfying

    the unit and system constraints [14]. This goal is achieved

    by proper adjustment of reactive power control variables

    like generator bus voltage magnitudes (Vgi), transformer

    tap settings (tk), reactive power generation of the capacitor

    bank (Qci) [15].

    A. Objective Function:

    The objective of RPD is to identify the reactive power

    control variables, which minimizes the real power loss

    (Ploss) of the system. This is mathematically stated as [16],

    (10)

    subjected to the following constraints.

    B. Equality Constraints:

    These are load flow constraints such as

    The power balance constraints includes real and reactive

    power balances.

    (11)

    (12)

    Where i, j are the bus indices, PGi and QGi are active and

    reactive power generations at bus i respectively.

    C. Inequality Constraints:

    These constraints represent the system operating

    constraints. Load bus voltages (Vload), reactive power

    generation of generator (Qgi) and line flow limit (Sl) are

    variables, whose limits are satisfied by adding a penalty

    terms in the objective function. These constraints are

    formulated as,

    (i) Voltage limits

    (13)

    (ii) Generator reactive power capability limit

    (14)

    (iii) Capacitor reactive power generation limit

    (15)

  • International Conference on Deregulated Environment and Energy Markets, July22-23, 2011

    19

    (iv) Transformer tap setting limit

    (16)

    (v) Transmission line flow limit

    (17)

    D. Evaluation Function:

    Each particle consists of voltages, taps and shunts encoded

    in it. The size of each particle is equal to sum of number

    of voltages excluding slack bus voltage, taps, and shunts.

    The fitness function [17] employed is

    (18)

    V. VOLTAGE STABILITY IMPROVEMENT USING PSO

    Voltage stability is concerned with the ability of a power

    system to maintain acceptable voltages at all nodes in the

    system under normal condition and after being subject to a

    disturbance [15]. A power system is said to have a

    situation of voltage instability when a disturbance causes a

    progressive and uncontrollable decrease in voltage level.

    An accurate knowledge of how close the actual systems operating point is from the voltage stability limit is crucial

    to operators [18]. Hence, to find a voltage stability index

    has become an important task for many voltage stability

    studies. These indices provide reliable information about

    proximity of voltage instability in a power system.

    Problem Formulation:

    Each particle consists of voltages, taps and shunts encoded

    in it. The size of each particle is equal to sum of number

    of voltages, taps, and shunts. The fitness function [17]

    employed is

    (19)

    where, index is the stability index value. Stability index

    of power system is computed [19] based on the solution of

    the power flow equations. Here, L-index is used, which is

    a quantitative measure for the estimation of the distance of

    the actual state of the system to the stability limit [20].

    The L index describes the stability of the complete system

    and is formulated as,

    where ng is number of generators, n is number of buses

    in the system. The Lindex value varies in a range between

    0 (no load) and 1 (voltage collapse) [21]. Stability Index

    of the system is computed as

    VI. FUZZIFIED PSO FOR MULTI-OBJECTIVE CEED

    The real power optimization sub-problem minimizes fuel

    cost by controlling controllable generator outputs while

    keeping the generator bus voltages unchanged. The system

    losses, stability index and emission computed at this

    power dispatch are very high compared with the results

    obtained when respective ones are taken as objective.

    Similarly the reactive power sub-problem deals with

    minimization of total transmission loss of the system by

    controlling all the reactive power sources such as taps,

    shunts etc. When loss minimization is taken as objective

    total system losses reduces but cost, emission and stability

    indices are high. The emission dispatch sub problem

    minimizes total emission output from the fossil fuel plants

    by controlling the generator outputs. At this power output

    of generator, the cost, total system losses and stability

    index are high [22]. In the same way Stability index sub

    problem minimizes the index by controlling the PV bus

    voltages and thus improves the system stability limit. But

    the cost, emission and system losses are very high. Thus,

    results of all the four sub problems are conflicting with

    one other. Hence, multiobjective PSO technique is used to

    find the best compromise solution. In this section results

    of all the four sub problems are fuzzified using fuzzy min-

    max approach and then PSO is used to determine the final

    trade off solution from all these fuzzified values.

    A. Problem Formulation:

    Each particle consists of active power generations,

    voltages, taps and shunts excluding slack bus voltages

    encoded in it. The size of each particle is equal to sum of

    active power generations, number of voltages excluding

    slack bus, taps, and shunts.

    Assuming the decision maker (DM) has imprecise or

    fuzzy goals of satisfying each of the objectives, the multi-

    objective problem can be formulated as a fuzzy

    satisfaction maximization problem which is basically a

    min-max problem [23]. The task here is to determine the

    compromise solution for all the four optimization sub

    problems. The goal is to minimize G(X) = compromised

    solution of G1(X1), G2(X2), G3(X3), G4(X4) [24], while

    satisfying the set of constraints Ax < B. where G1(X) is

    Fuel cost minimization sub problem, G2(X) is Loss

    minimization sub problem, G3(X) is emission

    minimization sub problem, and G4(X) is L-index

    minimization sub problem.

    Let F1(Xi) be fuel cost in $/hr for ith control vector, F2(Xi)

    be losses in p.u. for ith control vector, F3(Xi) be stability

    index for ith control vector, and F4(Xi) be emission release

    in kg/hr for ith control vector. Let the individual optimal

  • International Conference on Deregulated Environment and Energy Markets, July22-23, 2011

    20

    control vectors for the sub problems be X1 , X2 , X3

    ,X4 respectively. To find, the global optimal control

    vector X such that,

    The imprecise or fuzzy goal of the DM for each of the

    objective functions is quantified by defining their

    corresponding membership functions i as a strictly monotonically decreasing function with respect to the

    objective function f.

    Where i=1 to 4. In case of a minimization problem,

    i =0 or tends to zero, if fi > fmaxi and i =1 or tends to 1, if fi < fmini . where fmaxi and f mini are the unacceptable and desirable

    level for respectively. In the proposed approach, we have

    considered a simple linear membership function for f i

    because none of the objectives have very strict limits. The

    membership function, i for ith objective function is shown in Fig 2.

    VII. RESULTS AND DISCUSSION

    The proposed approach is tested on IEEE 30 bus system

    [25]. The PSO parameters used in CEED case studies are:

    number of particles 60, learning factors C1=2.05, C2=2.05,

    weight factor w=1.2, constriction factor K=0.7925.

    Maximum number of iterations=100. First, each objective

    is optimized individually at a time and then four objectives

    are optimized simultaneously using fuzzified PSO.

    1) Economic Dispatch using PSO : Table I shows all

    objective function values considering fuel cost

    minimization as single objective optimization subproblem

    and the optimum value obtained is 806.498 MW. The total

    system generation is 293.984 MW.

    2) Emission Dispatch using PSO : Table II gives all

    objective function values considering emission dispatch as

    single objective problem and the optimum value obtained

    is 229.145 (Kg/hr). The total system generation is 287.804

    MW.

    3) Reactive Power Optimization using PSO :

    The lower voltage magnitude limits at all buses are 0.95

    p.u. and the upper limits are 1.1 for all the PV buses and

    1.05 p.u. for all the PQ buses and the reference bus. The

    lower and upper limits of the transformer tapping are 0.9

    and 1.1 p.u. respectively. Table III presents all objective

    function values considering loss minimization as single

    objective optimization problem. Table IV and V gives the

    positions of tap changing transformers and shunt

    susceptance values respectively.

    4) Voltage Stability Improvement using PSO :

    Table VI gives all objective function values considering

    L-index minimization as single objective optimization

    problem. Table VII and VIII gives the positions of tap

    changing transformers and shunt susceptance values

    respectively.

  • International Conference on Deregulated Environment and Energy Markets, July22-23, 2011

    21

    5) Fuzzified PSO for Multi-objective Optimization :

    From the above single objective optimization techniques it

    is observed that when one objective is optimized it will

    give optimum value for that objective but other objective

    function values are deviating from optimum. Hence, there

    is a

    conflicting behavior between one objective with reference

    to other objective. To overcome this, multi-objective

    optimization using Fuzzified PSO technique is proposed in

    this paper. The compromise solution is given in Tables IX,

    X and XI. The total system generation is 288.035 MW,

    total load 283.4 MW.

    VIII. CONCLUSIONS

    In this paper, an approach to solve multi-objective

    optimization problem which aims at minimizing fuel cost,

    real power loss, emission release and improving stability

    index of the system has been proposed. The proposed

    algorithm has been tested on IEEE 30 bus system. The

    four objectives economic dispatch, emission dispatch,

    stability index and reactive power optimization are solved

    individually and the results from these individual

    optimizations are fuzzified and final best compromise

    solution is obtained. The multi-objective problem

    is handled using the fuzzy decision satisfaction

    maximization technique which is an efficient technique to

    obtain trade off solution in multi-objective problems. The

    proposed approach satisfactorily finds global optimal

    solution within a small number of iterations.

    REFERENCES

    [1] E. H. Chowdhury, S. Rahrnan, A Review of Recent Advances in Economic Dispatch, IEEE Trans. Power Syst., vol. 5, no. 4, pp. 1248- 1259, Nov. 1990.

    [2] J. Wood, B. F. Wollenberg, Power Generation, Operation and Control, John Wiley and Sona, Inc., New York, 2004.

    [3] O. Alsac and B. Stott, Optimal Load Flow with Steady State Security, IEEE Trans. Power Apparatus and Syst., vol. 93, no.3, pp. 745-751, May/June 1974.

    [4] M. R. AlRashidi and M. E. E. Hawary, A Survey of Particle Swarm Optimization Applications in Electric Power Systems, IEEE Trans.Evolutionary Computation., vol. 13, no. 4, pp. 913-918, Aug. 2009.

    [5] J. Kennedy and R. Eberhart, Particle swarm optimization, in Proc. IEEE Int. Conf. Neural Networks (ICNN95), vol. 6, pp. 942-1948, Perth, Australia, 1995.

    [6] M. A. Abido, Optimal power flow using particle swarm optimization, Electrical Power and Energy Systems, vol. 24, pp. 563571, 2002.

    [7] Mozafari, T. Amraee, A. M. Ranjbar and M. Mirjafari, Particle Swarm Optimization method for Optimal Reactive Power Procurement considering Voltage Security, Scientia Iranica, vol. 14, no. 6, pp. 534545, Dec. 2007.

    [8] Z. L. Gaing, Particle Swarm Optimization to Solving the Economic Dispatch Considering the Generator Constraints, IEEE Trans. Power Syst., vol. 18, no. 3, pp. 1187-1195, Aug. 2003.

    [9] J. B. Park, K. S. Lee, J. R. Shin, K. Y. Lee, A Particle Swarm Optimization for Economic Dispatch with Non-smooth Cost Functions, IEEE Trans. Power Syst., vol. 20, no. 1, pp. 34-42, Feb. 2005.

    [10] Keib, H. Ma, J. L. Hart, Economic dispatch in view of the Clean Air Act of 1990, IEEE Trans. Power Syst., vol. 9, no. 2, pp. 972- 978, May 1994.

    [11] J. H. Talaq, F. E. Hawary, and M. E. E. Hawary, A Summary of Environmental/Economic Dispatch algorithms, IEEE Trans. Power Syst., vol. 9, no. 3, pp. 1508-1516, Aug.

    1994. [12] S. Kumar, K. Dhanushkodi, J. J. Kumar, C. K. C. Paul,

    Particle Swarm Optimization Solution to Emission and Economic Dispatch Problem, IEEE TENCON, 2003.

    [13] P. Dutta , A. K. Sinha, Environmental Economic Dispatch constrained by voltage stability using PSO, IEEE Electrical Engineering, IIT Kharagpur., 2006.

    [14] k. Iba, Reactive power optimization by genetic algorithms, IEEE Trans. Power Syst., vol. 9, no. 2, pp. 685-692, May, 1994.

    [15] Q. H Wu and J. T. Ma, Power sys