Decision tree and decision analysis

Embed Size (px)

Citation preview

  • 7/28/2019 Decision tree and decision analysis

    1/20

    ASIGNMENT NO: 1

    Name: Mohammad Abdullah

    Enrollment: 2010-E-37

    Class: MBA (5th quarter)

    Course: Quantitative Analysis.

    Topic: Decision Analysis...

    Submitted To: Mr. Taimoor Shah

    Submission Date: 21-06-2012

    INSTITUTE OF MANAGEMENT SCIENCES UNIVERSITY OF

    BALUSHISTAN QUETTA

  • 7/28/2019 Decision tree and decision analysis

    2/20

    Question No: 2

    Finance manger's optimal policy would be Drill upto 20 meters because it has the lowest expected cost

    No water P= 0.8$ 275 000

    $ 125 000

    1

    2

    Water Struck P= 0.2

    Do not Drill

    Drill upto 25

    Drill upto 20 meter

    Do not drill

    No water P= 0.30

    Water struck P= 0.70

    $100,000

    2n

    1st

    Cost = 245 000$ 150,000

    $ 250,000

    $ 245,000

    Cost = $ 77,500

    $ 77,500

  • 7/28/2019 Decision tree and decision analysis

    3/20

    Problem No: 3-27

    a. Decision Table.

    State of nature/ activity

    Size of first stationGoodmarket($)

    Fairmarket($)

    PoorMarket($)

    Small$

    50,000.00$

    200,000.00$

    (10,000.00)

    medium$

    80,000.00$

    30,000.00$

    (20,000.00)

    large$

    100,000.00$

    30,000.00$

    (40,000.00)

    very large$

    300,000.00$

    25,000.00$

    (160,000.00)

    b. Optimistic decision criterion Maximax.

    Maximax = {Max in 1st row,Max in 2nd row,Max in 3rd row,Max in 4th row} = {Max}

    Maximax = {200000,80000,100000,300000} = {300000}

    Conclusion: Optimal decision is to build a very large size first station.

    c. Passimistic decision criterion (Maximin).

    Maximin = {-10000, -20000, -40000, -160000} = {-10000}

    Conclusion: Passimistic decision Is to build a small size of first station.

    d. Equallly likely decision criterion (Laplace).

    Small 50000+20000+(-10000)/3=60000/3=20000

    medium 80000+30000+(-20000)/3=90000/3=30000

    large 100000+30000+(-40000)/3=90000/30=30000

    very large 300000+25000+(-160000)/3=165000/3=55000

    Laplace={20000,30000,30000,55000}={55000}

    Conclusion: Equally likely decision is to build a Very large size of f irst station.

    e. Realism decision criterion (Hurwicz). a = 0.8

    Hurwicz={Max in row x + Min in row (1-)}

    Small = {200000 x 0.8 = (1- 0.8) (-10000)} = 158000

    Medium = {80000 x 0.8 = (1- 0.8) (-20000)} = 60000

    Large = {100000 x 0.8 = (1- 0.8) (-40000)} = 72000

    Very large = {300000 x 0.8 = (1- 0.8) (-160000)} = 208000

    Hurwicz={158000,60000,72000,208000} = {208000}

    Conclusion: Laplace decision Is to build a Very large size of first station.

    f. Loss Table

    State of nature/ activity

    Size of first stationGoodmarket($)

    Fairmarket($)

    PoorMarket($)

    Small$

    250,000.00$

    10,000.00$

    10,000.00

    medium$

    220,000.00 $ -$

    20,000.00

    large

    $

    200,000.00 $ -

    $

    40,000.00

    very large $ - $ $

  • 7/28/2019 Decision tree and decision analysis

    4/20

    5,000.00 160,000.00

    g. Minimax Regret decision criterion.

    Minimax={250000,220000,200000,160000} = {160000}

    Conclusion: Minimax regret decision Is to build a Very large size of first station.

    Question No: 2

    1st decision pay off tableDecision alternatives state of nature /activity

    highdemand

    lowdemand

    Expand small plant 2.5 m (-3.1 m)

    Do not expand small plant 1.5 m 1.1 m

    Probability 0.85 0.15

    Last decision pay off table

    Decision alternatives state of nature /activityhighdemand

    lowdemand

    construct full size pland 5 m (-2 m)construct small size plant 1.66 m 1 m

    Probability 0.85 0.15

    Full size plant high demand

    cost = 5 million

    payoff =1million/annum

    period = 10 years

    Net pay off = {(1 x 10)} - {5}

    10 - 5 = $ 5 million

    Full size plant low demand

    cost = 5 million

    payoff = 0.3 million/annum

    period = 10 years

    Net pay off ={(0.3 x 10)} -{5}

    3 - 5 = $ -2 million

    Expanded small plant high demand

    cost = $ 1 million

    expansion cost = $ 4.2 million

    High demand yeild = $ 0.25 million/annumHigh demad period = 2 years

  • 7/28/2019 Decision tree and decision analysis

    5/20

    expanded high demand yeild = $ 0.9 million/ annum

    expanded high demand Period = 8 years

    Net pay off ={(0.25 x 2 + 0.9 x 8)} - {1+4.2}

    7.7 - 5.2 = $ 2.5 million

    Expanded small plant low demand

    cost = $ 1 million

    expansion cost = $ 4.2 million

    High demand yeild = $ 0.25 million/annum

    High demad period = 2 years

    expanded low demand yeild = $ 0.2 million/ annum

    expanded low demand Period = 8 years

    Net pay off = {(0.25 x 2 + 0.2 x 8)} - {1 + 4.2}

    7.7 - 5.2 = $ -3.1 million

    Do not expand small plant high demand

    cost = 1 million

    High demand yeild = 0.25 million/annumHigh demad period = 10 years

    Net pay off = {(0.25 x 2 + 0.25 x 8)} - {1}

    2.5 - 1 = $ 1.5 million

    Do not expand small plant low demand

    cost = $ 1 million

    High demand yeild = $ 0.25 million/annum

    High demad period = 2 years

    Low demad yield = $ 0.2 million/ annum

    Low demad Period = 8 years

    Net pay off = {(0.25 x 2 + 0.2 x 8)} - {1}

    2.1 - 1 = $ 1.1 million

    Small plant low demand

    cost = $ 1 million

    Payoff = $ 0.2 million/annum

    High demad period = 2 years

    Period = 10 years

    Net pay off ={(0.2 x 10)} -{1}

    2 - 1 = $ 1 million

    Decision Table

    EMV AT Nod- 4 = {(0.85 x 2.5 ) + (0.15 x -3.1)} = {$ 1.66 million}

    EMV AT Nod- 3 = {(0.85 x 1.5 ) + (0.15 x 1.1)} = {$ 1.44 million}

    EMV AT Nod- 2 = {(0.85 x 5 ) + (0.15 x -2)} = {$ 3.95 million}

    EMV AT Nod- 1 = {(0.85 x 1.66 ) + (0.15 x 1)} = {$ 1.56 million}

  • 7/28/2019 Decision tree and decision analysis

    6/20

    Question No: 2

    No water struck

    Out source cost = Rs. 150000

    Drilling cost = Rs. 5000/meter

    Drill upto 25 meters Cost=(25 merters x Rs. 5000) + 150,000 = Rs.275,000

    Water struck

    Drilling cost =Rs.5000/meter

    Drill upto 25 meters Cost= 25 merters x Rs. 5000 = Rs. 125,000

    Do not drill further

    Outsource cost= Rs.150,000

    Drilling cost = Rs. 5000/meter

    Drill upto 20 meters= (Rs. 5000/meter x 20 Meters) + Rs. 150,000 =Rs. 250,000

    Water struck at 20 meters P= 0.70

    Drilling cost = Rs. 5000/meter

    Drill upto 20 meters= (Rs. 5000/meter x 20 Meters) = Rs. 100,000

    Do not drill any well

    Out source cost= Rs. 150,000

    Analysis Table

    Expected cost AT Node 2 = (275,000 x 0.8) + (125,000 x 0.2) = Rs. 245,000

    Decision at the decision point 2= Is to drill upto 25 meters i.e Rs. 245,000

    Expected cost AT Node 1 = (25,000 x 0.3) + (100,000 x 0.7) = Rs. 77,500Decision at the decision point 1= Is to drill upto 20 meters i.e Rs. 77,500

  • 7/28/2019 Decision tree and decision analysis

    7/20

    The optimal policy would be to construct full size plant because it has the highiest ecpected monitory value

    High demand P=$ 2.5 Million

    $ -3.1 Million

    2

    1

    3

    4

    $ 1.5 Million

    $ 1.1 Million

    Low demand P= 0.15

    High demand P=

    Low demand P= 0.15

    Do not Expand Small Plant

    Expand Small Plant

    Construct Small size

    Construct Full size

    High demand P=

    High demand P= 0.85

    Low demand P= 0.15

    Low demand P= 0.15

    $ 5 Million

    $ -2 Million

    $1 Million

    $ 1.66 Million

    2n

    1st

    EMV = $ 1.66 Million

    EMV = $ 1.44 Million

    $ 3.95 Million

    EMV= $ 1.56 Million

    EMV= $ 3.95 Million

  • 7/28/2019 Decision tree and decision analysis

    8/20

    Problem 1

    page 225

    D= 2500 units

    C = $ 110/unit

    F = $16/ orderr = 0.20/$/year

    Cr = $ 22/unit/year

    a.

    Q * = 2 D f/Cr

    Q * = 2 (2500) (16) / 22

    Q * = 60.3022 units / order

    b. Tc = Toc + Tcc

    Tc = F(D/Q) + Cr(Q/2)

    Tc = 16(2500/60.3022) + 22(60.3022/2)

    Tc = 663.347 + 663.242

    Tc = $ 1326.6321/year

    c. Q * = 60 units rounded of to the nearest

    Tc = F(D/Q) + Cr(Q/2)

    Tc = 16(2500/60) + 22(60/2)

    Tc = 666.67 + 660

    Tc = $ 1326.67/year

    %age increase = 1326.67 / 1326.6321 x 100 = 100.0028568 % = 0.0028568 %

  • 7/28/2019 Decision tree and decision analysis

    9/20

    `

    Problem 2

    Q * = 60.3022 units / order

    50 % above Q * = 90.4533 units / order

    Tc prior = $ 1326.6321/year

    Tc = F(D/Q) + Cr(Q/2)

    Tc = 16(2500/90.4533) + 22(90.4533/2)

    Tc = 442.2171 + 994.9863

    Tc = $ 1437.2034/year

    %age increase = 1437.2034 / 1326.6321 x 100 = 108.3347 % = 8.3347 %

    Problem 3

    (a) Ordering 10 % above than EOQ = 66.3324 units / order

    Tc = F(D/Q) + Cr(Q/2)

    Tc = 16(2500/66.3324) + 22(66.3324/2)

    Tc = 603.0233 + 729.6566

    Tc = $ 1332.6799/year

    %age increase = 1332.6799 / 1326.6321 x 100 = 100.45587% = 0.45587 %

  • 7/28/2019 Decision tree and decision analysis

    10/20

    (b) Ordering 10 % less than EOQ = 54.2719 units / order

    Tc = F(D/Q) + Cr(Q/2)

    Tc = 16(2500/54.2719) + 22(54.2719/2)

    Tc = 737.0285 + 596.9900

    Tc = $ 1334.020353/year

    %age increase = 1334.020353 / 1326.6321 x 100 = 100.55968 % = 0.55968 %

  • 7/28/2019 Decision tree and decision analysis

    11/20

    Problem 6-37

    N * = 5 orders/year

    F = $6/order

    Cr = $ 10 / grill / year

    Stockout Cost = $ 50 unit

    Current ROP = 650 units

    L = 12 days

    Probabilities = 0.3 0.2 0.1 0.1 0.05 0.05 0.05 0.05 0.05 0.03 0.02

    Alternatives Demand during lead time600 650 700 750 800 850 900 950 1000 1050 1100 EMV

    600 0 12500 25000 37500 50000 62500 75000 87500 100000 112500 125000 33375

    650 500 0 12500 25000 37500 50000 62500 75000 87500 100000 112500 24775

    700 1000 500 0 12500 25000 37500 50000 62500 75000 87500 100000 18775

    750 1500 1000 500 0 12500 25000 37500 50000 62500 75000 87500 17075

    800 2000 1500 1000 500 0 12500 25000 37500 50000 62500 75000 10675

    850 2500 2000 1500 1000 500 0 12500 25000 37500 50000 62500 7925

    900 3000 2500 2000 1500 1000 500 0 12500 25000 37500 62500 6075

    950 3500 3000 2500 2000 1500 1000 500 0 12500 25000 37500 4375

    1000 4000 3500 3000 2500 2000 1500 1000 500 0 12500 25000 3575

    1050 4500 4000 3500 3000 2500 2000 1500 1000 500 0 12500 3425

    1100 5000 4500 4000 3500 3000 2500 2000 1500 1000 500 0 3665

    Home Inc... should maintain safety stock level of inventory of 1050 units

  • 7/28/2019 Decision tree and decision analysis

    12/20

    Exercise :3

    P = 10,000 units / year

    C = $ 1.5/unit

    F = $ 500/ order

    r = 0.25/$/year

    Cr = $ 0.375/unit/year

    (a) D = 1800 units / year

    Q * = 2 D f/Cr(1-D/P)

    Q * = 2 (1800) (500) /(0.375)(1-1800/10000)

    Q * = 2419.4335 units / order

    Tc = Toc + Tcc

    Tc = F(D/Q) + Cr(Q/2)(1-D/P)

    Tc = 500 (1800/2419.43) + 0.375 (2419.43/2)(1-1800 / 10000)

    Tc = 371.98 + 371.98

    Tc = $ 737.96/year

    (b) D = 7200 units / year

    Q * = 2 D f/Cr(1-D/P)

    Q * = 2 (7200) (500) /(0.375)(1-7200/10000)

    Q * = 8280.7867 units / order

    Tc = Toc + Tcc

    Tc = F(D/Q) + Cr(Q/2)(1-D/P)

    Tc = 500 (7200/8280.7867) + 0.375 (8280.7867/2)(1-7200 / 10000)

    Tc = 434.7413 + 434.7413

    Tc = $ 869.4826 /year

    If ordered four fold than the last year's Q * = 9677.734 units / order

    Tc = Toc + Tcc

    Tc = F(D/Q) + Cr(Q/2)(1-D/P)

    Tc = 500 (7200/9677.734) + 0.375 (9677.734/2)(1-7200 / 10000)

    Tc = 371.9879 + 1487.9516

    Tc = $ 1859.9395 /year

    Q * 9677.734 Total Cost = $ 1859.9395

    Q * 8280.786 Total Cost = $ 869.4826

    Difference due to four fold = $ 990.4569

    Note: This difference is due to increasing the order size exactly by the factor of 4.

  • 7/28/2019 Decision tree and decision analysis

    13/20

    Insufficient order will lead to additional holding cost.

    Production manager should increase her order size by the factor of 3 and

    she should order 8280.7867 units / order.

    Exercise: 6

    Page 241

    D = 16,000 Ounce

    r = 0.10 / $ / year

    (a)Table6.7

    Vendeor Unit Cost/Ounce $ OrderingCost $ Term of Sales

    1 6.1 30 Q >= 1,600

    2 6.3 25 Q >= 1,200

    3 5.9 27 Q >= 1,800

    EOQ for 3rd region:

    Q * = 2 D F / Cnr

    Q * = 2 (16000) (27) /5.90 x 0.10

    Q * = 1210.1267 units

    Since Q * do not luy in the 3rd region there fore we will take the lowe limitof

    the 3rd region for the calculation of Total cost.

    Tc = F(D/Q) + Cnr(Q/2) + DCn

    Tc = 27 (16000 / 1800) + 0.59 (1800/2) + (16000 x 5.90)

    Tc = 240 + 537 + 94400

    Tc = $ 95177 / year

    EOQ for 2nd region:

    Q * = 2 D F / Cnr

    Q * = 2 (16000) (25) / 6.30 x 0.10

    Q * = 1126.8723 units

  • 7/28/2019 Decision tree and decision analysis

    14/20

    Since Q * do not luy in the 2nd region there fore we will take the lowe limitof

    the 2nd region for the calculation of Total cost.

    Tc = F(D/Q) + Cnr(Q/2) + DCn

    Tc = 25 (16000 / 1200) + 0.63 (1200/2) + (16000 x 6.30)

    Tc = 333.3333 + 378 + 100800

    Tc = $ 101511.3333 / year

    EOQ for 1st region:

    Q * = 2 D F / Cnr

    Q * = 2 (16000) (30) / 6.1 x 0.10

    Q * = 1254.50 units

    Since Q * is not luying in the 1st region there fore we will take lower

    limit of 1st region For calculation of Tc.

    Tc = F(D/Q) + Cnr(Q/2) + DCn

    Tc = 30 (16000 / 1600) + 0.61 (1600/2) + (16000 x 6.10)

    Tc = 300 + 488 + 97600

    Tc = $ 98,388 / year

    VendeorTerm ofSales

    Minimumcost

    3 Q >= 1,800$

    95,177

    2 Q >= 1,200$

    101,511

    1 Q >= 1,600$

    98,388

    Sandia should purchase from 3rd Vendor because it has the lowest Tc.

    (b) Optimal inventory policy

    L = 5 days

    w.d = 250 days

    T * = Q / D x w.d

    T * = 1600 / 16000 x 250

    T * = 25 days

    N * = D / Q

  • 7/28/2019 Decision tree and decision analysis

    15/20

    N * = 16000 / 1600

    N * = 10 orders / year

    ROP = L x Daily demand

    ROP = 5 x 64

    ROP = 320 units

    Problem: 1

    page 225

    C = $ 200/unit

    F = $ 11 / order

    r = 0.13/$/year

    Cr = $ 26/unit/year

    D = 50 units / month = 600 units / year

    L = 7days (1 + 1 + 3 + 2)

    w.d = 350 days / year(a) Q * = 2 D f/Cr

    Q * = 2 (600) (11) / 26

    Q * = 22.5320 units / order

    (b,c,d)

    Tc = Toc + Tcc

    Tc = F(D/Q) + Cr(Q/2)

    Tc = 11 (600/22.5320) + 26 (22.5320/2)

    Tc = 292.9167 + 292.9160

    Tc = $ 585.8327/year

    (e) Optimal inventory policy

    Q * = 22.5320 units / order

    T * = Q * / D x w.d

    T * = 22.5320 / 600 x 350

    T * = 13.14 or 13 days

    N * = D / Q*

    N * = 600 / 22.5320

    N * = 26.63 of 27 orders

    ROP = L x Daily demand

    ROP = 7 x 600 / 350 = 12 days

  • 7/28/2019 Decision tree and decision analysis

    16/20

    (Inventory level units)

    Q * = 23 units

    Average Inventory

    ROP = 12 units

    (Continue = 27 Orders)

    (Time = 300 days)

    7 days 13 days

    page 219

    Problem 1

    (a) C = $ 110 /unit

    F = $ 5 / order

    r = 0.12/$/year

    Cr = $ 13.2/unit/yearD = 6 units / month = 72 units / year

    w.d = 300 days / year

    (b)

    Q TOC TCC TC

    1 360 6.6 366.6

    2 180 13.2 193.2

    3 120 19.8 139.8

    4 90 26.4 116.4

    5 72 33 105

    6 60 39.6 99.6

    7 51 46.2 97.28 45 52.8 97.8

    9 40 59.4 99.4

    10 36 66 102

    page 215

    Problem 1 Q * = 2 D f/Cr

    Q * = 2 (72) (5) / 13.2

    Q * = 7.3854 units / order

    Problem 2 Tc = Toc + Tcc

    Tc = F(D/Q) + Cr(Q/2)Tc = 5 (72/7.3854) + 13.2 (7.3854/2)

  • 7/28/2019 Decision tree and decision analysis

    17/20

    Tc = 48.7448 + 48.7436

    Tc = $ 97.4884/year

    Yes our answer matching with previous answer.

    Problem 3

    D = 24 units / month = 288 units / yearQ * = 2 D f/Cr

    Q * = 2 (288) (5) / 13.2

    Q * = 14.7709 units / order

    Selly should not increase her order quantity by factor of 4.

    She should increase her order quantity be factor of 2.

    Optimal inventory policy

    Q * = 14.7709 units / order

    T * = Q * / D x w.d

    T * = 14.7709 / 288 x 300

    T * = 15.3864 or 15 days

    N * = D / Q*

    N * = 288 / 14.7709

    N * = 16.2062 of 16 orders / year

    Exercise 4

    C = $ 450 / unit

    F = $ 50 / order

    r = 0.25 / $ / year

    Cr = $ 112.5 / unit / year

    D = 90 units / year

    L = 10 days

    w.d = 270 days / year

    (a) Q * = 2 D F / Cr

    Q * = 2 (90) (50) / 112.5

    Q * =8.9442 units

    M * = 2 D F / Cr

    M * = 2 (90) (50) / 112.5

    M * =8.9442

    M * = 2.0902 units / order

    m = Q * - M *

    m = 8.9442 - 8.9442

    m = 0 units%age of EOQ met by M * = M * / Q* x 100

  • 7/28/2019 Decision tree and decision analysis

    18/20

    %age of EOQ met by M * = 8.9442 / 8.9442 x 100

    %age of EOQ met by M * = 100 %

    %age of EOQ met by m = m / Q* x 100

    %age of EOQ met by m = m / Q* x 100

    T * = Q * / d x w.d

    T * = 38.5695 / 90 x 270

    T * = 115.7085 or 116 days

    N * = D / Q *

    N * = 90 / 38.2695

    N * = 2.3517 or 2 orders

    ROP = L x daily demand

    ROP = 10 x 90 /270

    ROP = 3.3333 units

    Tc = F(D/Q) + CrM2 / 2Q + b (Q - M ) 2 /2Q

    Tc = 50(90/38.2695) +112.5(2.0902) 2/ 2 (38.2695) +6.5 (38.2695 - 2.0902 ) 2 /2(38.2695)

    Tc = 117.5871 + 6.4216 + 111.1606

    Tc = 117.5871 +117.5822

    Tc = $ 235.1693

    Tc = 117.5871 +117.5822

    Tc = $ 235.1693

    Tc = 117.5871 +117.5822

    Tc = $ 235.1693

    (b) C = $ 450 / unit

    F = $ 50 / order

    r = 0.25 / $ / year

    Cr = $ 112.5 / unit / year

    D = 90 units / year

    L = 10 days

    w.d = 270 days / yearb = $ 5 + Promotional $ 135 / 90 = $ 6.5 / unit

    Q * = 2 D F / Cr x b + Cr / b

    Q * = 2 (90) (50) / 112.5 x 6.5 + 112.5 / 6.5

    Q * =8.9442 units x 4.2787 units

    Q * = 38.2695 units / order

    M * = 2 D F / Cr x b / b + Cr

    M * = 2 (90) (50) / 112.5 x 6.5 / 6.5 + 112.5

    M * =8.9442 x 0.2337

    M * = 2.0902 units / order

  • 7/28/2019 Decision tree and decision analysis

    19/20

    m = Q * - M *

    m = 38.2695 - 2.0902

    m = 36.1793 units

    %age of EOQ met by M * = M * / Q* x 100

    %age of EOQ met by M * = 2.08 / 38.25 x 100%age of EOQ met by M * = 5.4617 %

    %age of EOQ met by m = m / Q* x 100

    %age of EOQ met by m = 36.1793 / 38.5695 x 100

    %age of EOQ met by m = 94.5382 %

    T * = Q * / d x w.d

    T * = 38.5695 / 90 x 270

    T * = 115.7085 or 116 days

    N * = D / Q *

    N * = 90 / 38.2695

    N * = 2.3517 or 2 orders

    ROP = L x daily demand

    ROP = 10 x 90 /270

    ROP = 3.3333 units

    Tc = F(D/Q) + CrM2 / 2Q + b (Q - M ) 2 /2Q

    Tc = 50(90/38.2695) +112.5(2.0902)2/ 2 (38.2695)+6.5 (38.2695 - 2.0902 )

    2/2(38.2695)

    Tc = 117.5871 + 6.4216 + 111.1606

    Tc = 117.5871 +117.5822

    Tc = $ 235.1693

    (c..) C = $ 450 / unit

    F = $ 50 / order

    r = 0.25 / $ / year

    Cr = $ 112.5 / unit / yearD = 90 units / year

    L = 10 days

    w.d = 270 days / year

    b = $ 5

    Q * = 2 D F / Cr x b + Cr / b

    Q * = 2 (90) (50) / 112.5 x 5 + 112.5 / 5

    Q * =8.9442 units x 4.8476 units

    Q * = 43.3586 units / order

    M * = 2 D F / Cr x b / b + Cr

    M * = 2 (90) (50) / 112.5 x 5 / 5 + 112.5

  • 7/28/2019 Decision tree and decision analysis

    20/20

    M * =8.9442 x 0.205684

    M * = 1.8450 units / order

    m = Q * - M *

    m = 43.3586 - 1.8450

    m = 41.5135 units%age of EOQ met by M * = M * / Q* x 100

    %age of EOQ met by M * = 1.8450 / 43.3856 x 100

    %age of EOQ met by M * = 4.2525 %

    %age of EOQ met by m = m / Q* x 100

    %age of EOQ met by m = 41.5135 / 43.3856 x 100

    %age of EOQ met by m = 95.6849 %

    T * = Q * / d x w.d

    T * = 43.3856 / 90 x 270

    T * = 130.1568 or 130 days

    N * = D / Q *

    N * = 90 / 43.3856

    N * = 2.0744 or 2 orders

    ROP = L x daily demand

    ROP = 10 x 90 /270

    ROP = 3.3333 units

    Tc = F(D/Q) + CrM2 / 2Q + b (Q - M ) 2 /2Q

    Tc = 50(90/43.3856) +112.5(1.8450) 2 / 2 (43.3856) + 5 (43.3856 - 1.8450 ) 2 /2(43.3856)

    Tc = 103.7210 + 4.4133 + 99.4351

    Tc = 103.7210 +103.8484

    Tc = $ 207.5694 / year

    Tabulated Comparison

    S # Particularsa. No

    Backorder

    b. withadditional

    $ 6.5

    c. $5without

    additional

    1 Q * 8.9442 38.2695 93.3586

    2 M * 8.9442 2.0902 1.8453 m 0 36.1793 41.5135

    4 M * %age 100% 5.46% 4.25%

    5 m %age 0% 94.54% 95.68%

    6 Toc 117.5871 117.5871 103.721

    7 Tcc 117.5822 117.5822 103.8484

    8 Tc 235.1693 235.1693 207.5694

    9 N * 2.3517 2.3517 2.0744

    10 T * 115.7085 115.7085 130.1568

    11 ROP 3.3333 3.3333 3.3333