CURRICULUM of COMPETENCY UNIT (CoCU)Sub Sector ELECTRICAL POWER
Job Area SINGLE PHASE ELECTRICAL INSTALLATION & MAINTENANCE
Competency Unit Title SINGLE PHASE DRAWING
Competency Unit Descriptor
Single phase drawing is covering the scope of competency to carry out single phase wiring activities for Single Phase based ondrawing given by utilizing single phase wiring tools, equipment and materials in compliance with Electrical Act 1990, ElectricalRegulation 1994 and other related rules and regulations body and statutory requirements. The personnel who are competent in thesingle phase electrical drawing must be able to identify drawing specification for single phase single phase wiring and carry outdrawing according to standard requirements.
Competency Unit Code CompetencyType Core Level 2 Training
Duration 144 CreditHours
Work Activities Related Knowledge Applied Skills Attitude / Safety /Environmental
TrainingHours
Delivery Mode Assessment Criteria
1. Identify single phase drawing specifications and requirement
i. Procedure of site visit and evaluation
ii. Technique to produce lay-out drawing
iii. Calculation of diversity factor
iv. Bill of quantity (BQ)v. Types of calculation
Total connected load (TCL)
Maximum Demand (MD)
vi. Diversity factorvii. Various type of conduc-
tor: Copper Aluminum
8 hours Lecture i. Layout plan sketched according to require-ment
ii. MD & TCL calculated correctly
iii. Selection of protection devices, and cable list-ed out
8
Work Activities Related Knowledge Applied Skills Attitude / Safety /Environmental
TrainingHours
Delivery Mode Assessment Criteria
viii. Various type of cable, such as: XLPE/SCT/PVC PVC/PVC PVC/SWA/PVC XLPE/SWA/PVC
viii. Various type of protection devices: MCB,MCCB RCCB/ELCB Fuse
ix. Types of single phase wiring Surface wiring Conceal wiring Conduit wiring Conceal conduit
Wiring Ducting wiring Trunking/Casing Cable tray Underground
x. Earthing/grounding re-quirement
xi. Electrical Act & Regulationand Standard Energy Commission Act
2001 Electricity Supply Act
9
Work Activities Related Knowledge Applied Skills Attitude / Safety /Environmental
TrainingHours
Delivery Mode Assessment Criteria
1990 (Act 447) Electrical Regulation
1994 MS 1936: 2006 / IEC
60364 MS 1979: 2007 (COP)
Electrical Installation of Buildings – Code of practice (COP)
Based on latest instruc-tion by regulatory body
xii. Occupational Safety & Health Act 514 (OSHA) 1994
xiii. Authorisation requirement to access site such as: Green card Safety passport
i. Determine procedure to carry out site visit and evalua-tion
ii. Visit and evaluate site lo-cation
iii. Sketch layout planiv. Calculate total connected
load v. Calculate maximum de-
mandvi. Determine types of sin-
gle phase wiringvii. Determine types of pro-
24 hours Demonstration,Observation &
Practical
10
Work Activities Related Knowledge Applied Skills Attitude / Safety /Environmental
TrainingHours
Delivery Mode Assessment Criteria
tection devicesviii. Determine types of con-
ductorix. Determine types of cablex. Determine Authorisation
requirement to access site
Attitude:i. Meticulous in cal-
culating TCL & MD
ii. Adhere to safety regulation
2. Carry out layout drawing
i. Drawing setii. Computer Added Draw-
ing softwareiii. Computer operationiv. Measurement scale
techniquev. Building layout symbolvi. Application of
configurationvii. Electrical symbol, circuit
and measurements for layout drawing
viii. Electrical accessories and fittings
ix. Procedure to draw layout drawing
x. Format of layout drawing
12 hours Lecture i. Building layout sketched according tospecification
ii. Single phase wiring configuration determined
iii. Types of acces-sories and fittings de-termined
iv. Layout drawing drew according to re-quirement and speci-fication
v. Layout drawing format checked ac-cording to standard format
i. Acquire drawing setii. Utilise Computer Added
Drawingiii. Utilise computer systemiv. Utilise drawing softwarev. Interpret building layout plan
28 hours Demonstration,Observation &
Practical
11
Work Activities Related Knowledge Applied Skills Attitude / Safety /Environmental
TrainingHours
Delivery Mode Assessment Criteria
vi. Determine electrical symbol vii. Determine electrical acces-
sories/fittingsviii. Sketch building layoutix. Determine single phase
wiring configuration’x. Determine types of acces-
sories and fittings to be usedxi. Draw building layout (indoor
/ outdoor)Attitude:
i. Handle computerwith care
3. Carry out single line / schematic diagram drawing
i. Single line/schematic di-agram drawing require-ments and specifications as per rules and regulation
ii. Devices and cable specification Switches Protection Cable Socket outlet (Switch /
Unswitch)iii. Circuit connection
methodiv. Types of single phase
wiring Indoor single phase
wiring Outdoor single phase
wiring
12 hours Lecture i. Single line drawing re-quirements and specifi-cation determined
ii. Devices and cable specification deter-mined
iii. Electrical symbol circuitdetermined
iv. Single line drawing drew according to re-quirement and specifi-cation
v. Single line drawing for-mat checked accordingto standard format
12
Work Activities Related Knowledge Applied Skills Attitude / Safety /Environmental
TrainingHours
Delivery Mode Assessment Criteria
v. Electrical symbol circuitvi. Procedure to draw sin-
gle line drawingvii. Format of single line
drawingi. Determine electrical
symbolii. Determine electrical ac-
cessories and fittingsiii. Read and interpret blue
printiv. Determine types of sin-
gle phase wiring protectionv. Determine types of ac-
cessories and fittingsvi. Compare single line
drawing to layout drawingvii. Draw electrical single
line drawing
Attitude:i. Handle computer
with careii. Adhere to er-
gonomic require-ments
24 hours Demonstration,Observation &
Practical
4. Carry out single phase wiring drawing
i. Type of accessoriesii. Single phase wiring
connection, terms and speci-fication
iii. Single phase wiring pro-tection
iv. Earthing system layoutv. Cable size chartvi. Single phase wiring
8 hours Lecture i. Single phase wiring configuration determined
ii. Types of acces-sories and fittings de-termined
iii. Single phase sin-gle phase wiring drawing drew accord-
13
Work Activities Related Knowledge Applied Skills Attitude / Safety /Environmental
TrainingHours
Delivery Mode Assessment Criteria
specification and regulationvii. Procedure to draw sin-
gle phase wiring drawingviii. Format of single phase
wiring drawing
ing to requirement and specification
iv. Single phase sin-gle phase wiring drawing format checked according to standard format
i. Read and interpret blue print
ii. Determine types of elec-trical connection
iii. Differentiate type of loads
iv. Determine types of con-nection
v. Determine type of single phase wiring/accessories andfittings
vi. Draw single phase wiringdrawing
Attitude:i. Meticulous in
drawing
14 hours Demonstration,Observation &
Practical
5. Inspect single phase drawing
i. Types of drawingii. Procedure to check drawing
erroriii. Drawing specificationiv. Procedure to check Total
Connected Load (TCL) and Maximum Demand (MD) from drawing
v. Tender/clients requirementsvi. Procedure to submit single
phase wiring drawing for ap-proval
4 hours Lecture i. Drawing error checked correctly
ii. Drawing specification check according to format
iii. TCL & MD calculated
14
Work Activities Related Knowledge Applied Skills Attitude / Safety /Environmental
TrainingHours
Delivery Mode Assessment Criteria
i. Determine types of drawing
ii. Check drawing erroriii. Check drawing
specification against design requirements
iv. Calculate TCL & MDv. Print out single phase
drawingvi. Determine tender /
clients requirementsvii. Submit single phase
wiring drawing for approval tosuperior
vii. Carry out housekeep-ing activities
Attitude:i. Meticulous in cal-
culation
8 hours Demonstration,Observation &
Practical
15
Employability Skills
Core Abilities Social Skills
01.01 Identify and gather information01.02 Document information, procedures or processes02.01 Interpret and follow manuals, instructions and SOP’s02.04 Prepare brief reports and checklist using standard form03.01 Apply cultural requirements to the workplace03.05 Demonstrate safety skills06.02 Comply with and follow chain of command06.01 Understand system06.03 Identify and highlight problems
1. Communication skills2. Conceptual skills3. Interpersonal skills4. Multitasking and prioritizing5. Self-discipline6. Teamwork7. Learning skills8. Leadership skills
Tools, Equipment and Materials (TEM)
ITEMS RATIO (TEM : Trainees)
1. Schematic diagram 2. Block Diagram 3. Measuring Instruments 4. Electrical components/Parts Specification 5. Equipment Data Book6. Drawing instrument7. Computer8. Computer Added Drawing software
1 : 11 : 11 : 11 : 11 : 21 : 11 : 11 : 5
16
References
REF.ERENCES
1. Undang-Undang Malaysia. 2005. Akta Bekalan Elektrik 1990 dan Peraturan-Peraturan Elektrik 1994, Pindaan sehingga 2005. MDC Publisher Sdn Bhd Malaysia.
2. Suruhanjaya Tenaga Malaysia. Standard Pendawaian Malaysia (Electrical Installations Of Buildings - MS IEC 60364) Jabatan Standard Malaysia 3. The Institution of Electrical Engineers, 1998, Peraturan-Peraturan bagi Pemasangan Elektrik, Edisi 16. Golden Books Centre Sdn Bhd
4. Giesecke, F. E. et. Al. 2002. Technical Drawing. Prentice Hall
5. BS 7671: 2001 Requirements for Electrical Installations (IEE Wiring Regulations, Sixteenth Edition) Institution of Electrical Engineers
17
CURRICULUM of COMPETENCY UNIT (CoCU)Sub Sector ELECTRICAL POWER
Job Area SINGLE PHASE ELECTRICAL INSTALLATION & MAINTENANCE
Competency Unit Title SINGLE PHASE WIRING
Competency Unit Descriptor
Single phase wiring covering the scope of competency to carry out wiring activities for Single Phase based on drawing given byutilizing wiring tools, equipment and materials in compliance with Electrical Act 1990, Electrical Regulation 1994 and other relatedrules and regulations body and statutory requirements. The personnel who are competent in the single phase electrical wiring mustbe able to interpret single phase wiring specifications and procedures, single phase wiring requirement, carry out wiring activities,earthing system installation and carry out continuity, polarity, insulation and resistance testing on the single phase wiring system.
Competency Unit Code CompetencyType Core Level 2 Training
Duration 576 CreditHours
Work Activities Related Knowledge Applied Skills Attitude / Safety /Environmental
TrainingHours
Delivery Mode Assessment Criteria
1. Identify single phase wiring spec-ifications and pro-cedures
i. Procedure of site visit and evaluation/survey
ii. Technique to produce lay-out drawing
iii. Various type of conductor: Copper Aluminum
iv. Various types of cable: XLPE/SCT/PVC PVC/PVC PVC/SWA/PVC XLPE/SWA/PVC
v. Cable colour coding ac-cording to MS IEC 60364 Standard
vi. Various type of protection devices:
24 hours Lecture i. Wiring route and in-spection fitting and ac-cessories corrected
ii. Correct polarity and connection determined
18
Work Activities Related Knowledge Applied Skills Attitude / Safety /Environmental
TrainingHours
Delivery Mode Assessment Criteria
MCB,MCCB RCCB/ELCB Fuse
vii. Types of single phase wiring Surface wiring Conceal wiring Conduit wiring Conceal conduit Wiring Ducting wiring Trunking/ Casing Cable tray Underground
viii. Suitable fitting and acces-sories Switches Power Point (S/S/ 13A)
ix. Electrical Act & Regulation and Standard Energy Commission Act
2001 Electricity Supply Act
1990 (Act 447) Electrical Regulation
1994 MS 1936: 2006 / IEC
60364 MS 1979: 2007 (COP)
Electrical Installation of Buildings – Code of prac-
19
Work Activities Related Knowledge Applied Skills Attitude / Safety /Environmental
TrainingHours
Delivery Mode Assessment Criteria
tice (COP) Based on latest instruc-
tion by regulatory bodyx. Occupational Safety &
Health Act 514 (OSHA) 1994
xi. Authorisation requirement to access site such as: Green card Safety passport
i. Determine procedure tocarry out site visit and evalu-ation
ii. Determine location of the wiring route
iii. Determine types of wiring
iv. Determine types of pro-tection devices
v. Determine types of con-ductor
vi. Determine types of ca-ble
vii. Determine suitable fit-ting and accessories
viii. Determine Authorisationrequirement to access site
Attitude:i. Meticulousii. Housekeeping
Safety:
48 hours Demonstration,Observation &
Practical
20
Work Activities Related Knowledge Applied Skills Attitude / Safety /Environmental
TrainingHours
Delivery Mode Assessment Criteria
i. Use appropriate PPE during carryout wiring practi-cal
ii. Safety tools & equipment in proper order
2. Identify single phase wiring tools,equipment and materials
i. Single phase Wiring pro-cedure
ii. Single phase Wiring preparation
iii. Single phase Wiring in-spection
iv. Wiring tools, equipment and materials
20 hours Lecture i. Correct various type of tools used
ii. Correct devices cable used
i. Acquire single phase wiring works
ii. Select & use single phase wiring tools equipment need-ed
iii. Select & fix electrical acces-sories
iv. Select & fix electrical fittingsv. Select wiring tools, equip-
ment and materials Attitude:i. Handle wiring
tools with careSafety:
i. Ensure wiring tools in good working condition
44 hours Demonstration,Observation &
Practical
21
Work Activities Related Knowledge Applied Skills Attitude / Safety /Environmental
TrainingHours
Delivery Mode Assessment Criteria
3. Carry out wiring activities
i. Electrical hand toolsii. Types of electrical equipment
& materialsiii. Single phase wiring Standard
Operating Procedureiv. Cable marking techniquev. Types of cable size and
polarity
32 hours Lecture i. Wiring activities conducted according to correct procedure
ii. Installation and connection wiring identified
iii. All the earthing cable connected to frame earthing cor-rectly
i. Setup safe working area
ii. Conduct single phase wiring according layout plan and location wiring line
iii. Identify cable marking iv. Identify cable size & po-
larityv. Check all fitting & ac-
cessories connected to earthing
Attitude:i. Ensure no
wastage of cableSafety:
i. Use appropriate PPE during wiring activities
ii. Ensure safety tools & equip-ment in proper order
48 hours Demonstration,Observation &
Practical
4. Carry out single phase earthing system installation
i. Types of earthingii. Function of earthingiii. Earthing procedureiv. Electrical symbolv. Building structure
24 hours Lecture i. Single phase earthing system conducted
ii. Earthing system tested
22
Work Activities Related Knowledge Applied Skills Attitude / Safety /Environmental
TrainingHours
Delivery Mode Assessment Criteria
vi. Electrical hand toolsvii. Electrical equipment &
materialsviii. Electrical earthing acces-
sories & fittingix. Earthing layout
i. Determine types of eart-ing
ii. Determine function of earthing
iii. Install Distribution Fuse Board (DFB) consumer unit to earth rod
iv. Connect main frame electrical equipment to earth
v. Test earthing system vi. Construct earthing lay-
out
Attitude:i. Ensure no wastage
of cable
Safety:i. Use appropriate
PPE during wiring activitiesEnsure safety tools & equipment in proper order
50 hours
23
Work Activities Related Knowledge Applied Skills Attitude / Safety /Environmental
TrainingHours
Delivery Mode Assessment Criteria
5. Carry out single phase Distribution Board (DB)(metal-lic or insulated) installation
i. Distribution Board (metallic or insulated)
ii. Tools and equipment for single phase Distribution Board (metallic or insulated) installation
iii. Wiring drawingiv. Standard Operating Pro-
cedures (SOP) for testing in-strument
v. Types of electrical systemtesting, such as:- Insulation resistance test Polarity test Continuity test
24 hours Lecture i. Neatness of wiring checked
ii. Cable terminatedconsumer unit
iii. Cable terminatedto fitting and acces-sories
iv. Continuity, polari-ty, insulation resis-tance tested
i. Select and use correct wiring materials
ii. Select and use wiring tools and equipment needed
iii. Carry out various method of Consumer sur-face single phase wiring Domestic surface wiring Concealed wiring Conduit wiring Trunking wiring
iv. Carry out wiring work according to wiring drawing
v. Execute electrical test-ing on wiring system Attitude:
i. Housekeeping working area after
50 hours Demonstration,Observation &
Practical
24
Work Activities Related Knowledge Applied Skills Attitude / Safety /Environmental
TrainingHours
Delivery Mode Assessment Criteria
wiring activitiesSafety:
i. Use appropriate PPE during carryout earthing works
ii. Safety tools & equipment in proper order
6. Carry out fitting and accessories installation
i. Single phase wiring draw-ing
ii. Types of electrical acces-sories
iii. Types of electrical fittingsiv. Procedure to terminate ca-
bles, accessories and fit-tings
24 hours Lecture i. Cable terminatedto fitting and acces-sories
i. Determine location for fitting and accessories installation
ii. Select and fix electrical accessories
iii. Select and fix electrical fittings
iv. Terminate cables, accessories and fittings
Attitude:i. Housekeeping
working area af-ter wiring activi-ties
Safety:i. Use appropriate
PPE during carryout installation works
52 hours Demonstration,Observation &
Practical
25
Work Activities Related Knowledge Applied Skills Attitude / Safety /Environmental
TrainingHours
Delivery Mode Assessment Criteria
ii. Ensure safety tools & equip-ment in proper order
7. Carry out wiring system visual in-spection
i. Visual inspectionii. Wiring drawing according
to SOPiii. Wiring connection
16 hours Lecture i. Visual inspection conducted
ii. Fault identified
i. Execute visual inspec-tion on wiring system
ii. Identify fault on visual inspection
iii. Carry out housekeepingactivities Attitude:
i. Housekeeping working area af-ter wiring activi-ties
36 hours Demonstration,Observation &
Practical
8. Carry out dead circuit test
i. Types of circuit/connec-tion
ii. Electrical Testing Insulation resistance test
(IRT) Polarity test Earthing continuity test Earthing test
o Earth resistance testo Earth loop imped-
ance testiii. Testing instrument stan-
dard operating procedures (SOP)
iv. Procedure to interpret
16 hours Lecture i. Continuity, polarity, insulation resistance and earthing tested
26
Work Activities Related Knowledge Applied Skills Attitude / Safety /Environmental
TrainingHours
Delivery Mode Assessment Criteria
testing result
i. Determine circuit/con-nection
ii. Execute electrical test-ing on wiring system
iii. Interpret testing resultAttitude:
i. Handle testing equipment with care
32 hours Demonstration,Observation &
Practical
9. Carry out live cir-cuit test
i. ELCB/RCB functioning test-ing
ii. Supply voltage test
16 hours Lecture i. ELCB/RCB func-tioning testing de-termined
ii. Supply voltage test-ed
i. Determine ELCB/RCB functioning testing
ii. Test Supply voltage Attitude:i. Handle testing
equipment with care
32 hours Demonstration,Observation &
Practical
10. Prepare single phase work activi-ties report
i. Procedure to produce single phase wiring
ii. Procedure to submit sin-gle phase wiring for approval
iii. ‘As built’ drawing prepa-ration
iv. Test result v. Regulatory bodies and
tender requirements (Form G and Form H)
12 hours Lecture i. Procedure to pro-duce single phase wiring submitted
ii. Procedure of sin-gle phase wiring re-ported
i. Determine procedure toproduce single phase wiring
ii. Determine procedure to
24 hours Demonstration,Observation &
Practical
27
Work Activities Related Knowledge Applied Skills Attitude / Safety /Environmental
TrainingHours
Delivery Mode Assessment Criteria
submit single phase wiring for approval to superior
iii. Prepare as built draw-ing
iv. Check test resultv. Follow regulatory bod-
ies and tender requirementsAttitude:
i. Meticulous in writing report
Employability Skills
Core Abilities Social Skills
01.01 Identify and gather information01.02 Document information, procedures or processes02.01 Interpret and follow manuals, instructions and SOP’s02.04 Prepare brief reports and checklist using standard form03.01 Apply cultural requirements to the workplace03.05 Demonstrate safety skills04.02 Set and revise own objectives and goals04.03 Organize and maintain own workplace06.02 Comply with and follow chain of command06.01 Understand system06.03 Identify and highlight problems
1. Communication skills2. Conceptual skills3. Interpersonal skills4. Multitasking and prioritizing5. Self-discipline6. Teamwork7. Learning skills8. Leadership skills
28
Tools, Equipment and Materials (TEM)
ITEMS RATIO (TEM : Trainees)
1. Schematic diagram 2. Block Diagram 3. Measuring and Test Instruments 4. Components/Parts Specification 5. Distribution Boards6. Trunking Tools7. Equipment Data Book8. Electrical Equipment9. Electrical hand tools10. Electrical power tools11. Electrical Mechanical tools12. Electrical Accessories13. Electrical Fittings14. Electrical Testing Instrument15. Double Insulated cable16. Wiring lead17. Wiring neil18. Cables19. PVC Tape20. Standard Operating Procedure
1 : 11 : 11 : 11 : 11 : 21 : 11 : 11 : 11 : 11 : 11 : 11 : 11 : 11 : 11 : 11 : 11 : 11 : 11 : 11 : 1
29
References
REFERENCES
1. Undang-Undang Malaysia. (2005). Akta Bekalan Elektrik 1990 dan Peraturan-Peraturan Elektrik 1994, Pindaan sehingga 2005. MDC Publisher Sdn Bhd Malaysia.
2. Suruhanjaya Tenaga Malaysia. Standard Pendawaian Malaysia (Electrical Installations Of Buildings - MS IEC 60364) Jabatan Standard Malaysia 3. The Institution of Electrical Engineers. (1998). Peraturan-Peraturan bagi Pemasangan Elektrik, Edisi 16. Golden Books Centre Sdn Bhd
4. Giesecke, F. E. et. Al. 2002. Technical Drawing. Prentice Hall
5. BS 7671: 2001 Requirements for Electrical Installations (IEE Wiring Regulations, Sixteenth Edition) Institution of Electrical Engineers
30
CURRICULUM of COMPETENCY UNIT (CoCU)Sub Sector ELECTRICAL POWER
Job Area SINGLE PHASE ELECTRICAL INSTALLATION & MAINTENANCE
Competency Unit Title SINGLE PHASE WIRING MAINTENANCE
Competency Unit Descriptor
Single phase wiring is a list of maintenance activity to carry out maintenance work on wiring system for Single Phase based drawinggiven by utilizing wiring tools, equipment and materials in compliance with Electrical Act 1990, Electrical Regulation 1994 and otherrelated rules and regulations body and statutory requirements. The personnel who are competent in the single phase electrical wiringmaintenance must be able to interpret single phase wiring diagram, carry out electrical wiring inspection and maintenance and toconduct continuity, polarity, insulation resistance and earthing resistance testing
Competency Unit Code CompetencyType Core Level 2 Training
Duration 72 CreditHours
Work Activities Related Knowledge Applied Skills Attitude / Safety /Environmental
TrainingHours
Delivery Mode Assessment Criteria
1. Identify single phasewiringmaintenance re-quirement
i. Types of maintenance activi-ties Preventive Corrective
ii. Types of fault for single phasewiring Shorted Open Loose
iii. Types of schematic diagram for single phase wiring
iv. Procedure to carry out single phase wiring maintenance
v. Procedure to carry out site visit
vi. Electrical Act & Regulation and Standard Energy Commission Act
2001
4 hours Lecture i. Single phase wiring fault listed out
ii. Schematic diagram de-termined
31
Work Activities Related Knowledge Applied Skills Attitude / Safety /Environmental
TrainingHours
Delivery Mode Assessment Criteria
Electricity Supply Act 1990 (Act 447)
Electrical Regulation 1994
MS 1936: 2006 / IEC 60364
MS 1979: 2007 (COP)Electrical Installation of Buildings – Code of prac-tice (COP)
Based on latest instruc-tion by regulatory body
viii. Occupational Safety & Health Act 514 (OSHA) 1994
ix. Authorisation requirement to access site such as: Green card Safety passport
i. Determine types of maintenance activities
ii. Determine types of faultfor single phase wiring
iii. Determine schematic diagram single phase wiring
iv. Visit site to determine maintenance requirement
v. Determine procedure tocarry out single phase wiring
Attitude:i. Adhere to safety
8 hours Demonstration,Observation &
Practical
32
Work Activities Related Knowledge Applied Skills Attitude / Safety /Environmental
TrainingHours
Delivery Mode Assessment Criteria
regulation
Safety:i. Use appropriate
PPE during carryout wiring practi-cal
ii. Safety tools & equipment in proper order
2. Identify single phasewiring tool, equip-ment and material
i. Wiring tools and equip-ment
ii. Types of electrical cable for single phase
iii. Types of electrical equip-ment and accessories
iv. Electrical testing instru-ment
v. Calibration requirement for electrical testing instru-mentation
4 hours Lecture i. Tools, equipment and material of wiring iden-tified
i. Acquire wiring tools andequipment
ii. Determine types of electrical cable for single phase
iii. Determine types of electrical equipment and ac-cessories
iv. Determine types of electrical testing instrument
v. Determine calibration
8 hours Demonstration,Observation &
Practical
33
Work Activities Related Knowledge Applied Skills Attitude / Safety /Environmental
TrainingHours
Delivery Mode Assessment Criteria
requirement for electrical testing instrumentation
Attitude:i. Meticulous in in-
terpreting calibra-tion certificate
ii. Handle wiring tools, equipment and testing tools with care
Safety:i. Ensure tools and
equipment in good working condition
3. Carry out electrical wiring inspection
i. Interpreting single phase wiring schematic diagram
ii. Procedure to carry out inspection
iii. Single phase electrical wiring fault
4 hours Lecture i. Electrical wiring inspected
ii. Electrical wiring fault according speci-fication inspected
i. Interpret schematic dia-gram
ii. Utilise testing tools and equipment
iii. Inspect electrical wiringiv. Confirm single phase
electrical wiring faultAttitude:
i. Check thoroughlyfor electrical fault
Safety:i. Use appropriate
PPE (glove, gog-gle, safety boot) during carry out
12 hours Demonstration,Observation &
Practical
34
Work Activities Related Knowledge Applied Skills Attitude / Safety /Environmental
TrainingHours
Delivery Mode Assessment Criteria
wiring inspection activity
ii. Check safety tools & equip-ment in proper order
4. Carry out electrical wiring maintenance
i. Procedures to rectify electrical single phase wiringfault
ii. Single phase electrical wiring faulty part
iii. Tools, equipment and material of single phase wiring
iv. Testing and commissioning procedures for single phase wiring system
v. Testing method and procedures Short Long
4 hours Lecture i. Electrical wiring faulty part replaced
ii. Tools and equipment utilised
i. Determined procedure of electrical single phase wiring fault
ii. Select tools, equipment and material
iii. Interpret schematic drawingiv. Test troubleshoot single
phase electrical wiring faultyv. Repair and replace faulty
partvi. Perform functionality testingvii. Used testing equipment/tools
10 hours Demonstration,Observation &
Practical
35
Work Activities Related Knowledge Applied Skills Attitude / Safety /Environmental
TrainingHours
Delivery Mode Assessment Criteria
viii. Interpret test resultix. Utilise multitester or Direct
Current (DC) test lamp Attitude:i. Neatnessii. Housekeeping
Safety:i. Use appropriate
PPE (glove, gog-gle, safety boot)during carryout wiring practi-cal
ii. Safety tools & equipment in proper order
iii. Display safety sign board
iv. Lock main switchv. Ensure ‘OFF live
supply
5. Inspect electrical wiring functionality
i. Various testing and measuringinstruments
ii. Types and application and protection devices
iii. Types of testing Continuity Polarity Insulation Earthing
iv. Specification technical datav. Operation manual
4 hours Lecture i. Continuity, polari-ty, insulation resis-tance and earthing re-sistance tested
36
Work Activities Related Knowledge Applied Skills Attitude / Safety /Environmental
TrainingHours
Delivery Mode Assessment Criteria
i. Select testing and mea-suring instruments
ii. Check Protection de-vices
iii. Conduct continuity test-ing
iv. Conduct polarity testingv. Conduct insulation test-
ingvi. Conduct earthing test-
ing vii. Collect and record the
resultviii. Carry out housekeep-
ing activities
Attitude:i. Adhere the pro-
cedure and in-struction accord-ing operational manual
Safety:i. Use appropriate
PPE (glove, gog-gle, safety boot)during carryout wiring activi-ties
ii. Safety tools & equipment in proper order
iii. Adhere to main-tenance proce-dure
iv. Adhere to Code of ethics
8 hours Demonstration,Observation &
Practical
6. Record wiring sys-tem maintenance activities
i. Recording procedureii. Record format/form testingiii. Schedule maintenance iv. Report writing skills
2 hour Lecture i. Checklist, logbook and schedule mainte-nance report submit-ted
37
Work Activities Related Knowledge Applied Skills Attitude / Safety /Environmental
TrainingHours
Delivery Mode Assessment Criteria
i. Record checklist, logbook and schedule maintenance report
ii. Prepare single phase wiring maintenance report Attitude:
i. Submit report ac-cording to date-line
4 hours Demonstration,Observation &
Practical
Employability Skills
Core Abilities Social Skills
01.01 Identify and gather information01.02 Document information, procedures or processes02.01 Interpret and follow manuals, instructions and SOP’s02.04 Prepare brief reports and checklist using standard form03.01 Apply cultural requirements to the workplace03.05 Demonstrate safety skills04.02 Set and revise own objectives and goals04.03 Organize and maintain own workplace06.02 Comply with and follow chain of command06.01 Understand system06.03 Identify and highlight problems
1. Communication skills2. Conceptual skills3. Interpersonal skills4. Multitasking and prioritizing5. Self-discipline6. Teamwork7. Learning skills8. Leadership skills
Tools, Equipment and Materials (TEM)
ITEMS RATIO (TEM : Trainees)
38
1. Schematic diagram 2. Block Diagram 3. Measuring and Test Instruments 4. Components/Parts Specification 5. Distribution Boards6. Trunking Tools7. Equipment Data Book8. Electrical Equipment9. Electrical Mechanical tools10. Electrical hand tools11. Electrical power tools12. Electrical Accessories13. Electrical Fittings14. Electrical Testing Instrument15. Double Insulated cable16. Wiring lead17. Wiring neil18. Cables19. PVC Tape20. Standard Operating Procedure
1 : 11 : 11 : 11 : 11 : 21 : 11 : 11 : 11 : 11 : 11 : 11 : 11 : 11 : 11 : 11 : 11 : 11 : 11 : 1
References
39
REFERENCES
1. Undang-Undang Malaysia. 2005. Akta Bekalan Elektrik 1990 dan Peraturan-Peraturan Elektrik 1994, Pindaan sehingga 2005. MDC Publisher Sdn Bhd Malaysia.
2. Suruhanjaya Tenaga Malaysia. Standard Pendawaian Malaysia (Electrical Installations Of Buildings - MS IEC 60364) Jabatan Standard Malaysia 3. The Institution of Electrical Engineers, 1998, Peraturan-Peraturan bagi Pemasangan Elektrik, Edisi 16. Golden Books Centre Sdn Bhd
4. BS 7671: 2001 Requirements for Electrical Installations (IEE Wiring Regulations, Sixteenth Edition) Institution of Electrical Engineers
5. Giesecke, F. E. et. Al. 2002. Technical Drawing. Prentice Hall
40
CURRICULUM of COMPETENCY UNIT (CoCU)Sub Sector ELECTRICAL POWER
Job Area SINGLE PHASE ELECTRICAL INSTALLATION & MAINTENANCE
Competency Unit Title SINGLE PHASE MOTOR & MOTOR CONTROL INSTALLATION
Competency Unit Descriptor
Single phase motor and motor control installation is an activity that covers the competency requirements for the installation of SinglePhase motor and motor control based on installation specification and procedures in accordance with Electrical Act 1990, ElectricalRegulation 1994 and other related rules and regulations body and statutory requirements. The personnel who are competent in thesingle phase motor and motor control must be able to interpret installation manuals and procedures, carry out single phase motorand motor control installation, inspect single phase motor and motor control functionality and to conduct continuity, polarity,insulation resistance and earthing resistance testing.
Competency Unit Code CompetencyType Core Level 2 Training
Duration 200 CreditHours
Work Activities Related Knowledge Applied Skills Attitude / Safety /Environmental
TrainingHours
Delivery Mode Assessment Criteria
1. Identify single phase motor & motor control in-stallation specifi-cations and pro-cedures
i. Types of single phase mo-tor
Squirrel cage in-duction motor
Capacitor start Capacitor run Repulsion motor Shaded poles Universal motor Synchronous motor
ii. Types of single phase mo-tor control
Forward Reverse Direct Online (DOL)
iii. Single phase motor main control components and ac-
12 hours Lecture i. Installation single phase motor & mo-tor control accord-ing requirements
ii. All specification and requirements follow manufactur-ing manual/hand-book
41
Work Activities Related Knowledge Applied Skills Attitude / Safety /Environmental
TrainingHours
Delivery Mode Assessment Criteria
cessoriesiv. Single phase control circuit
components and acces-sories
v. Magnetic contactor and overload relay
vi. Electrical Act & Regulation and Standard Energy Commission
Act 2001 Electricity Supply Act
1990 (Act 447) Electrical Regulation
1994 MS 1936: 2006 / IEC
60364 MS 1979: 2007 (COP)
Electrical Installation ofBuildings – Code of practice (COP)
Based on latest instruc-tion by regulatory body
vii. Occupational Safety & Health Act 514 (OSHA) 1994
viii. Authorisation requirement to access site such as: Green card Safety passport
42
Work Activities Related Knowledge Applied Skills Attitude / Safety /Environmental
TrainingHours
Delivery Mode Assessment Criteria
i. Determine single phase motor
ii. Determine single phase motor control
iii. Determine single phase motor main compo-nents and accessories
iv. Determine single phase control circuit com-ponents and accessories
ix. Determine magnetic con-tactor and overload relay as required Attitude:
i. Adhere to safety regulation
Safety:i. Use appropriate
PPE during carryout wiring practi-cal
ii. Safety tools & equipment in proper order
24 hours Demonstration,Observation &
Practical
2. Prepare single phase motor andmotor control in-stallation,maintenance, tools, equipment
i. Single line drawing Main circuit Control circuit Protection devices
ii. Location of motor & motor control installation devices
16 hours Lecture i. Motor & motor con-trol installation in-cluding devices al-located
ii. Selection of sens-ing devices used atcorrected installa-
43
Work Activities Related Knowledge Applied Skills Attitude / Safety /Environmental
TrainingHours
Delivery Mode Assessment Criteria
including Platform structure Underwater Surface Weather proof Protection devices Sensing devices
o Timero Thermalo Limito Flowo Latching relay
iii. Single phase motor & motorcontrol maintenance Periodically check Preventive mainte-
nance Corrective mainte-
nanceiv. Single phase motor & motor
control installation tools, equipment and materials
v. Single phase motor & motorcontrol testing equipment LCR meter Rotation meter Multimeter Insulation tester meter
tionand materials
i. Select single line drawing
32 hours Demonstration,Observation &
44
Work Activities Related Knowledge Applied Skills Attitude / Safety /Environmental
TrainingHours
Delivery Mode Assessment Criteria
ii. Select location of mo-tor & motor control instal-lation devices
iii. Determine single phase motor & motor con-trol maintenance
iv. Select single phase motor & motor control tools
v. Select single phase motor & motor control testing equipment
Attitude:i. Comply to rules
and regulation
Practical
3. Carry out single phase motor in-stallation
i. Schematic diagramii. Single phase motor
symboliii. Main & control circuitiv. Motor sizing & ratingv. Installation procedurevi. Control panel accessoriesvii. Functionality of circuit
12 hours Lecture i. Selection drawing suitable with the require-ments and loca-tion
ii. Fault rectified and repaired
iii. Circuit tested
i. Read and interpret schematic drawing
ii. Identify motor size and rating
iii. Identify types of motorcomponents and acces-sories
iv. Install single phase motor and motor control
24 hours Demonstration,Observation &
Practical
45
Work Activities Related Knowledge Applied Skills Attitude / Safety /Environmental
TrainingHours
Delivery Mode Assessment Criteria
v. Testing the circuitvi. Repair the single
phase motor fault Attitude:i. Meticulous in
read and inter-preter diagram
Safety: i. Use PPE prop-
erlyii. Adhere to elec-
trical Act & reg-ulation
4. Carry out single phase motor control termina-tion
i. Installation termination & connection
ii. Types of circuit/connectioniii. Type of load/connectioniv. Accessories connection,
fittings and function of toolsv. Operation of hand tools and
equipmentvi. Cable color code/marking
8 hours Lecture i. Installation, termination & circuit connection,ensured fixed
ii. Platform in good stability and fixed firm
iii. Follow checklist and instruction manualaccording to the
iv. Marked cable according to codeat cable end
i. Connect control cir-cuit
ii. Fix components and accessories
iii. Identify type of circuit/controls
iv. Calculate electrical load/circuit
24 hours Demonstration,Observation &
Practical
46
Work Activities Related Knowledge Applied Skills Attitude / Safety /Environmental
TrainingHours
Delivery Mode Assessment Criteria
v. Identify correct loca-tion
vi. Identify accessories and fitting
vii. Identify connection terminal
viii. Identify type of hand tools and equipment
ix. Identify cable color code/marking
x. Inspect cable termina-tion and installation
xi. Apply test procedurestechnique
Attitude:i. Meticulous in
read and inter-preter diagram
Safety: i. Use PPE prop-
erlyii. Comply electri-
cal Act & regu-lation
iii. Comply Act 514(OSHA)
iv. Used a proper hand tools
5. Inspect single phase motor andmotor control functionality
i. Types and application of protection devices
ii. Types of testing Insulation
12 hours Lecture i. Continuity, polarity, insulationresistance and earthing resis-
47
Work Activities Related Knowledge Applied Skills Attitude / Safety /Environmental
TrainingHours
Delivery Mode Assessment Criteria
Continuity Polarity Earthing
iii. Specification technical dataiv. Operation manual
tance tested
i. Determine testing andmeasurement instruments
ii. Check Protection de-vices
iii. Conduct insulation test
iv. Conduct continuity test
v. Conduct polarity testvi. Conduct earthing test vii. Conduct motor test
run (on load and off load)viii. Collect and record the
dataix. Carry out housekeep-
ing activities
Attitude:i. Meticulous in
read and recorddata
Safety: i. Use PPE prop-
erlyii. Comply electri-
cal Act & regu-lation
iii. Comply Act 514(OSHA)
iv. Used a proper hand tools
24 hours Demonstration,Observation &
Practical
48
Work Activities Related Knowledge Applied Skills Attitude / Safety /Environmental
TrainingHours
Delivery Mode Assessment Criteria
v. Adhere mainte-nance proce-dure
vi. Code of ethics6. Record single
phase motor andmotor control in-stallation.
i. Recording procedureii. Test record format/formiii. Report writing skills
4 hours Lecture i. Checklist, logbookand schedule maintenance re-port submitted
i. Compile single phase motor and motor control maintenance data
ii. Prepare single phase motor and motor control installation report Attitude:
i. Neatnessii. Meticulous in
writing report
8 hours Demonstration,Observation &
Practical
49
Employability Skills
Core Abilities Social Skills
01.01 Identify and gather information01.02 Document information, procedures or processes02.01 Interpret and follow manuals, instructions and SOP’s02.04 Prepare brief reports and checklist using standard form03.01 Apply cultural requirements to the workplace03.05 Demonstrate safety skills04.02 Set and revise own objectives and goals04.03 Organize and maintain own workplace06.02 Comply with and follow chain of command06.01 Understand system06.03 Identify and highlight problems
1. Communication skills2. Conceptual skills3. Interpersonal skills4. Multitasking and prioritizing5. Self-discipline6. Teamwork7. Learning skills8. Leadership skills
Tools, Equipment and Materials (TEM)
ITEMS RATIO (TEM : Trainees)
1. Schematic diagram 2. Block Diagram 3. Measuring and Test Instruments 4. Components/Parts Specification 5. Distribution Boards6. Trunking Tools7. Equipment Data Book8. Electrical Equipment9. Electrical hand tools
1 : 11 : 11 : 11 : 11 : 21 : 11 : 11 : 11 : 1
50
10. Electrical Mechanical tools11. Electrical power tools12. Electrical Accessories13. Electrical Fittings14. Electrical Testing Instrument15. Double Insulated cable16. Wiring lead17. Wiring neil18. Cables19. PVC Tape20. Standard Operating Procedure
1 : 11 : 11 : 11 : 11 : 11 : 11 : 11 : 11 : 11 : 11 : 11 : 1
References
REFERENCES
1. Stephen Rahman. (2000). Industrial Motor Control. Cengage Learning
2. Undang-Undang Malaysia. 2005. Akta Bekalan Elektrik 1990 dan Peraturan-Peraturan Elektrik 1994, Pindaan sehingga 2005. MDC Publisher Sdn Bhd Malaysia.
3. Suruhanjaya Tenaga Malaysia. Standard Pendawaian Malaysia (Electrical Installations Of Buildings - MS IEC 60364) Jabatan Standard Malaysia
4. The Institution of Electrical Engineers, 1998, Peraturan-Peraturan bagi Pemasangan Elektrik, Edisi 16. Golden Books Centre Sdn Bhd
5. BS 7671: 2001 Requirements for Electrical Installations (IEE Wiring Regulations, Sixteenth Edition) Institution of Electrical Engineers
51
CURRICULUM of COMPETENCY UNIT (CoCU)Sub Sector ELECTRICAL POWER
Job Area SINGLE PHASE ELECTRICAL INSTALLATION & MAINTENANCE
Competency Unit Title SINGLE PHASE ELECTRICAL APPLIANCES MAINTENANCE
Competency Unit Descriptor
Electrical appliances maintenance is a set of competency to carry out repair work and maintenance on electrical appliances faulty byreferring to appliances service manual and standard operating procedures and in compliances with Electrical Act 1990, ElectricalRegulation 1994 and other related rules and regulations body and statutory requirements. The personnel who are competent in theelectrical appliances maintenance must be able to identify appliances specification and manuals, carry out maintenance activitiesand to conduct polarity, insulation, resistance and earthing resistance testing in accordance with manufacturer’s specificationrequirements.
Competency Unit Code CompetencyType Core Level 2 Training
Duration 72 CreditHours
Work Activities Related Knowledge Applied Skills Attitude / Safety /Environmental
TrainingHours
Delivery Mode Assessment Criteria
1. Identify electricalappliances main-tenance require-ment, specifica-tion and manuals
i. Types of home appliances, such as; Microwave Oven Iron Lamp Single Phase Air Condi-
tioning Water Heater Refrigerator Single phase motor
ii. Types of electrical appliances fault Short circuit Open circuit Loose contact Board faulty
iii. Types of schematic diagram
4 hours Lecture i. Single phase wiring fault listed out
ii. Schematic diagram de-termined
iii. Visual on the board checked
52
Work Activities Related Knowledge Applied Skills Attitude / Safety /Environmental
TrainingHours
Delivery Mode Assessment Criteria
viii. Electrical Act & Regulation and Standard Energy Commission Act
2001 Electricity Supply Act
1990 (Act 447) Electrical Regulation
1994 MS 1936: 2006 / IEC
60364 MS 1979: 2007 (COP)
Electrical Installation of Buildings – Code of prac-tice (COP)
Based on latest instruc-tion by regulatory body
ix. Occupational Safety & Health Act 514 (OSHA) 1994
x. Authorisation requirement to access site such as: Green card Safety passport
xi. Standard & Industrial Re-search Institute of Malaysia(SIRIM)
i. Determine types of home appliances fault
ii. Interpret schematic dia-gram
12 hours Demonstration,Observation &
Practical
53
Work Activities Related Knowledge Applied Skills Attitude / Safety /Environmental
TrainingHours
Delivery Mode Assessment Criteria
iii. Determine electrical ap-pliances fault
iv. Adhere standard of SIRIM
Attitude:i. Proactive in obtaining
manufacturer’s speci-fication and operation manual
2. Prepare single phase electrical ap-pliances mainte-nance tools, equip-ment and materials
i. Wiring tools, equipment and materials
ii. Types of electrical cable for single phase
iii. Types of electrical equip-ment and accessories
iv. Electrical testing instru-ment
v. Calibration requirement for electrical testing instru-mentation
vi. Electrical appliances manufacturer’s specification and operation manual
4 hours Lecture i. Tools, equipment and material selected
ii. Electrical appliances faulty part fixed accord-ing requirements
i. Acquire maintenance tools, equipment and materi-als
ii. Determine types of electrical cable for single phase electrical appliance
iii. Determine types of electrical testing instrument
iv. Determine calibration requirement for electrical testing instrumentation
vii. Obtain electrical appli-ances manufacturer’s speci-
8 hours Demonstration,Observation &
Practical
54
Work Activities Related Knowledge Applied Skills Attitude / Safety /Environmental
TrainingHours
Delivery Mode Assessment Criteria
fication and operation manu-al Attitude:
i. Handle equip-ment with care
ii. Peruse the man-ufacturer’s speci-fication and oper-ation manual manual for the
Safety: iii. Meticulous in in-
terpreting calibra-tion certificate
iv. Handle wiring tools, equipment and testing tools with care
v. Ensure tools andequipment in good working condition
3. Carry out electrical appliances inspec-tion
i. Schematic diagramii. Procedure to inspect single
phase electrical appliances condition
6 hours Lecture i. Electrical appli-ances inspected
ii. Electrical appli-ances fault recorded according specifica-tion
iii. Electrical appli-ances fault deter-mined
iv. Performance ver-ification tested
i. Interpret schematic dia-gram
ii. Utilise tools, equipment and material
iii. Inspect electrical appli-ance condition
iv. Confirm electrical appli-ances fault
v. Interpret single phase
18 hours Demonstration,Observation &
Practical
55
Work Activities Related Knowledge Applied Skills Attitude / Safety /Environmental
TrainingHours
Delivery Mode Assessment Criteria
electrical appliances manu-facturer’s manual
vi. Carry out housekeep-ing activities
Attitude:i. Thoroughly in in-
specting faulty
Safety: i. Used appropriate
PPEii. Comply to rules
and regulationiii. Use tools, equip-
ment and materi-al properly
4. Carry out electrical appliances mainte-nance
i. Procedures to rectify electrical appliances fault
ii. Electrical appliances faulty part
iii. Select tools, equipment and material for maintenance work
iv. Schematic drawingv. Procedure to acquire spare
parts for electrical appliancevi. Various testing and
measuring instrumentsvii. Types and application and
protection devicesviii. Types of testing
Insulation Continuity Polarity Earthing
ix. Specification technical datax. Operation manual for single
8 hours Lecture i. Electrical appliance faulty part replaced
ii. Tools and equipment utilised
iii. Testing and commis-sioning tested
iv. Continuity, polarity, in-sulation resistance andearthing resistance tested
v. Checklist, logbook and schedule maintenance report submitted
56
Work Activities Related Knowledge Applied Skills Attitude / Safety /Environmental
TrainingHours
Delivery Mode Assessment Criteria
phase electrical appliances
i. Select tools, equipment and material used for maintenance activities
ii. Interpret schematic drawingiii. Troubleshoot electrical
appliances faultyiv. Obtain electrical appliances
spare partsv. Rectify and replace faulty
partvi. Execute functionality testingvii. Interpret test resultviii.Select testing and measuring
instrumentsix. Check protection devices x. Conduct insulation testingxi. Conduct continuity testingxii. Conduct polarity testingxiii.Conduct earthing testing xiv.Collect and record
maintenance result for singlephase electrical appliances Attitude:
i. Proactive in maintenance work
Safety: i. Used appropriate
PPEii. Comply to rules
and regulationiii. Used tools,
equipment and
12 hours Demonstration,Observation &
Practical
57
Work Activities Related Knowledge Applied Skills Attitude / Safety /Environmental
TrainingHours
Delivery Mode Assessment Criteria
material properlyiv. Display safety
sign boardv. Lock main switchvi. Ensure ‘OFF live
supplyvii. Handle care
spare part and in-stall correctly
Employability Skills
Core Abilities Social Skills
01.01 Identify and gather information01.02 Document information, procedures or processes02.01 Interpret and follow manuals, instructions and SOP’s02.04 Prepare brief reports and checklist using standard form03.01 Apply cultural requirements to the workplace03.05 Demonstrate safety skills04.02 Set and revise own objectives and goals04.03 Organize and maintain own workplace06.02 Comply with and follow chain of command06.01 Understand system06.03 Identify and highlight problems
1. Communication skills2. Conceptual skills3. Interpersonal skills4. Multitasking and prioritizing5. Self-discipline6. Teamwork7. Learning skills8. Leadership skills
Tools, Equipment and Materials (TEM)
58
ITEMS RATIO (TEM : Trainees)
1. Schematic diagram 2. Block Diagram 3. Measuring and Test Instruments 4. Components/Parts Specification 5. Distribution Boards6. Trunking Tools7. Equipment Data Book8. Electrical Equipment9. Electrical Mechanical tools10. Electrical hand tools11. Electrical power tools12. Electrical Accessories13. Electrical Fittings14. Electrical Testing Instrument15. Double Insulated cable16. Wiring materials17. Cables18. PVC Tape
1 : 11 : 11 : 11 : 11 : 21 : 11 : 11 : 11 : 11 : 11 : 11 : 11 : 11 : 11 : 11 : 11 : 11 : 1
References
59
REFERENCES
1. Undang-Undang Malaysia. 2005. Akta Bekalan Elektrik 1990 dan Peraturan-Peraturan Elektrik 1994, Pindaan sehingga 2005. MDC Publisher Sdn Bhd Malaysia.
2. Suruhanjaya Tenaga Malaysia. Standard Pendawaian Malaysia (Electrical Installations Of Buildings - MS IEC 60364) Jabatan Standard Malaysia 3. The Institution of Electrical Engineers, 1998, Peraturan-Peraturan bagi Pemasangan Elektrik, Edisi 16. Golden Books Centre Sdn Bhd
4. BS 7671: 2001 Requirements for Electrical Installations (IEE Wiring Regulations, Sixteenth Edition) Institution of Electrical Engineers
5. R.Boylestad and L.Nashelsky. (1996). Electronic Devices and Circuit Theory. Prentice Hall- Gale
6. Albert Paul Malvino and Donald P. Leach. (1994). Digital Principles And Application. McGraw-Hill. (ISBN: 0028018214)
7. Joseph A. Risse. (1968). Understanding electronic test equipment. H. W
60
CURRICULUM of COMPETENCY UNIT (CoCU)Sub Sector ELECTRICAL POWER
Job Area SINGLE PHASE ELECTRICAL INSTALLATION & MAINTENANCE
Competency Unit Title SINGLE PHASE WIRING TESTING AND COMMISSIONING
Competency Unit Descriptor
Single phase wiring testing & commissioning is a competency to carry out testing and inspection on Single Phase wiring system forthe purpose of commissioning the wiring system according to Electrical Act 1990, Electrical Regulation 1994 and other related rulesand regulations body and statutory requirements. The personnel who are competent in the single phase electrical wiring must beable to identify single phase testing and commissioning specifications and procedures, carry out electrical testing includingresistance testing, polarity testing, continuity testing, earthing testing and carry out commissioning on the wiring system
Competency Unit Code CompetencyType Core Level 2 Training
Duration 144 CreditHours
Work Activities Related Knowledge Applied Skills Attitude / Safety /Environmental
TrainingHours
Delivery Mode Assessment Criteria
1. Identify single phase testing and commission-ing specifica-tions and proce-dures
i. Procedure of site visit eval-uation.
ii. Single phase schematic di-agram
iii. Technique to conduct test-ing and commissioning on single phase electrical wiring.
iv. Types of testing Insulation Polarity Continuity Earthing
v. Types of testing tool and equipment for single phasewiring
vi. Type of testing and com-missioning form for single phase wiring
4 hour Lecture i. Schematic diagram of single phase electrical wiring determined
ii. Testing for Single phase wiring listed out
iii. Testing of resistance test tool and equipmentlisted out.
iv. Testing of polarity test tool and equipment list-ed out
v. Testing of continuity test tool and equipmentlisted out
vi. Testing of earthing testtool and equipment
61
Work Activities Related Knowledge Applied Skills Attitude / Safety /Environmental
TrainingHours
Delivery Mode Assessment Criteria
vii. Safety regulation bodies(Add safety knowl-edge)
viii. Electrical Act & Regulation and Standard
Energy Commission Act 2001
Electricity Supply Act 1990(Act 447)
Electrical Regulation 1994 MS 1936: 2006 / IEC
60364 MS 1979: 2007 (COP)Electrical Installation of Build-
ings – Code of practice (COP)
Based on latest instruction by regulatory body
ix. Occupational Safety & Health Act 514 (OSHA) 1994
x. Authorisation requirement to access site such as:
Green card Safety passport
listed outvii. Tools, equipment and
material selectedviii. Testing and commis-
sioning form identified
i. Carry out site visit for evaluation
ii. Interpret single phase schematic diagram
iii. Determine types of test-ing
iv. Determine testing equip-
8 hours Demonstration,Observation &
Practical
62
Work Activities Related Knowledge Applied Skills Attitude / Safety /Environmental
TrainingHours
Delivery Mode Assessment Criteria
ment v. Determine testing tools
and equipment for single phase wiring
vi. Determine testing and commissioning form for single phase
vii. Comply Safety regulation bodies
viii. Determine authorisation requirement to access site Attitude:
i. Handle testing equipment with care
Safety:i. Used appropriate
PPEii. Used tools, equip-
ment and material properly
3. Prepare single phase testing and commission-ing tools, equip-ment and materi-als
i. Single Phase Schematic diagram
ii. Tools, equipment and materials used for single phase testing and commissioning tools, equipment and materials
iii. Procedure to obtain commissioning form
4 hours Lecture i. Testing tools utilise according to correct method
ii. Method of testing technique testing toolsand equipment cor-rectly applied
iii. Tools, equipment and materials listed out.
63
Work Activities Related Knowledge Applied Skills Attitude / Safety /Environmental
TrainingHours
Delivery Mode Assessment Criteria
i. Interpret schematic dia-gram
ii. Carry out preparation tools, equipment and ma-terial for testing and com-missioning activities
iii. Identify electrical circuit inthe single phase wiring
iv. Confirm electrical circuit in the single phase wiring. Attitude:
i. Handle equipment with care
6 hours Demonstration,Observation &
Practical
4. out single phase insulation resis-tance testing
i. Procedures to carry out single phase insulation resistance test.
ii. Polarity tools, equipment and material
iii. Testing data, method and procedure
8 hours Lecture i. Insulation resistance test carried out correct-ly
ii. Tools and equipment utilized
iii. Insulation resistance testing correctly exe-cutedi. Determine tools,
equipment and material ii. Execute insulation
resistance testingiii. Utilise testing tools,
equipment and materialiv. Record testing datav. Interpret test result Attitude:
i. Handle testing equipment with care
Safety:i. Used appropriate
PPE
16 hours Demonstration,Observation &
Practical
64
Work Activities Related Knowledge Applied Skills Attitude / Safety /Environmental
TrainingHours
Delivery Mode Assessment Criteria
ii. Used tools, equip-ment and material properly
5. Carry out single phase polarity testing
i. Procedures to carry out single phase polarity test.
ii. Polarity test tools, equipment and material
iii. Testing method and procedures
8 hours Lecture i. Polarity test carried out
ii. Tools and equipment utilized
iii. Testing of polarity tested as per proce-durei. Determine tools,
equipment and material ii. Execute polarity testingiii. Utilise testing tools iv. Record testing datav. Interpret test resultvi. Rectify / Coordinate
rectification work for non-compliance test result Attitude:
i. Handle testing equipment with care
Safety:i. Used appropriate
PPEii. Used tools, equip-
ment and material properly
16 hours Demonstration,Observation &
Practical
65
Work Activities Related Knowledge Applied Skills Attitude / Safety /Environmental
TrainingHours
Delivery Mode Assessment Criteria
6. Carry out single phase continuity testing
i. Procedures to carry out single phase continuity test.
ii. Continuity test tools, equipment and material
iii. Testing method and procedures
6 hours Lecture i. Single phase continuity testing carried out as per testing standard
ii. Tools, equipment and material for testing listed out
iii. Testing method and procedures complied
i. Determine tools, equipment and material
ii. Execute continuity testingiii. Utilise testing
equipment/tools iv. Record testing datav. Interpret testing resultvi. Rectify / Coordinate
rectification work for non-compliance test result Attitude:
i. Handle testing equipment with care
Safety:i. Used appropriate
PPEii. Used tools, equip-
ment and material properly
12 hours Demonstration,Observation &
Practical
7. Carry out single phase earthing resistance test-ing
i. Procedures to carry out single phase earthing resistance test.
ii. Select tools, equipment and material
iii. Testing method and procedures
6 hours Lecture i. Procedures to carry out single phase earthing resistance test complied
ii. Tools, equipment and material list out
iii. Testing method and
66
Work Activities Related Knowledge Applied Skills Attitude / Safety /Environmental
TrainingHours
Delivery Mode Assessment Criteria
procedures compliedi. Determine tools, equipment and material determined
ii. Execute earthing resistance testing
iii. Utilise testing equipment/tools
iv. Utulise earth resistance test meter
v. Interpret test resultAttitude:
i. Handle testing equipment with care
Safety:i. Used appropriate
PPEii. Used tools, equip-
ment and material properly
16 hours Demonstration,Observation &
Practical
8. Carry out testingcommissioning
i. Single phase wiring test and commissioning procedure
ii. Single phase electrical testand commissioning documentation.
iii. Testing record iv. Testing and
commissioning requirement
4 hours Lecture i. Procedures to commissioning of single phase electricalwiring followed
ii. Testing method and procedures followed
i. Determine tools, equipment and material
ii. Determine commissioningform for testing single
18 hours Demonstration,Observation &
Practical
67
Work Activities Related Knowledge Applied Skills Attitude / Safety /Environmental
TrainingHours
Delivery Mode Assessment Criteria
phase electrical wiringiii. Determine testing resultiv. Refer to standard limit of
testing need to single phase electrical wiring.
v. Interpret test and commissioning result
vi. Update commissioning form Attitude:
i. Meticulous in fill in commissioning form
9. Prepare testing and commission-ing report
i. Procedure to collect and gathered all testing result
ii. Standard form for testing and commissioning report
iii. Report writing skills
4 hour Lecture iii. Procedures to pre-pare report for test-ing and commis-sioning single phase electrical wiring followed
i. Compile testing and commissioning result
ii. Prepare commissioning document for approval
iii. Write testing and commissioning report
iv. Submit testing and commissioning report to superior
Attitude:i. Meticulous in pre-
paring reportii. Adhere to report
submission date-line
8 hours Demonstration,Observation &
Practical
68
Employability Skills
Core Abilities Social Skills
01.01 Identify and gather information01.02 Document information, procedures or processes02.01 Interpret and follow manuals, instructions and SOP’s02.04 Prepare brief reports and checklist using standard form03.01 Apply cultural requirements to the workplace03.05 Demonstrate safety skills04.02 Set and revise own objectives and goals04.03 Organize and maintain own workplace06.02 Comply with and follow chain of command06.01 Understand system06.03 Identify and highlight problems
1. Communication skills2. Conceptual skills3. Interpersonal skills4. Multitasking and prioritizing5. Self-discipline6. Teamwork7. Learning skills8. Leadership skills
69
Tools, Equipment and Materials (TEM)
ITEMS RATIO (TEM : Trainees)
1. Schematic diagram 2. Block Diagram 3. Measuring and Test Instruments 4. Components/Parts Specification 5. Equipment Data Book
1:11:11:11:11:2
References
REFERENCES
1. Joshi. (2008). Residential, Commercial and Industrial Electrical Systems: Protection, testing and commissioning. Tata McGraw-Hill Education.
2. Keith Harker. (1998). Power System Commissioning And Maintenance Practice. IET Limited
3. Undang-Undang Malaysia. 2005. Akta Bekalan Elektrik 1990 dan Peraturan-Peraturan Elektrik 1994, Pindaan sehingga 2005. MDC Publisher Sdn Bhd Malaysia.
4. Suruhanjaya Tenaga Malaysia. Standard Pendawaian Malaysia (Electrical Installations Of Buildings - MS IEC 60364) Jabatan Standard Malaysia 5. The Institution of Electrical Engineers, 1998, Peraturan-Peraturan bagi Pemasangan Elektrik, Edisi 16. Golden Books Centre Sdn Bhd
6. BS 7671: 2001 Requirements for Electrical Installations (IEE Wiring Regulations, Sixteenth Edition) Institution of Electrical Engineers
7.
70