Crane Lifting Plan

  • Upload
    101ar

  • View
    217

  • Download
    0

Embed Size (px)

Citation preview

  • 7/30/2019 Crane Lifting Plan

    1/20

    Crane Lifting PlanLIFTING OPERATION

    METHOD STATEMENT/LIFT PLAN & RISK ASSESSMENT

    DETAILS FOR THE PROVISION OF A LIFT OPERATION IN

    COMPLIANCE WITH

    BS7121 PARTS 1 & 3 AND LOLER REGULATIONS

    Please tick as appropriate:

    Completed by appointed person for crane hired by Weston Homes, or Completed by contractor who has hired a crane as part of their work

    Client Weston Homes Plc

    Project

    Site Address

    Date of OperationTime on Site

    Client/Site Contact

    Contact Number

    Appointed Person

    Contact Number

    Appointed Persons Acceptance of Responsibilities:I confirm that the lifts in the Method Statement have been planned and will be carried out in accordance with current

    legislation and British Standard 7121 and that I accept responsibility for the preparation of this Method Statement and RiskAssessment. I accept that it is my responsibility as the Appointed Person to ensure that the Lift Supervisor is adequately

    briefed on the contents of this Method Statement.

    Signed Date

    CONTENTS

    Page Page

    Introduction 28 Crane Set Up Procedure 37

    General Conditions 29 Lift Procedure 37

    Weather Conditions 29 Crane De-Rig Procedure 39

    Ground Conditions 29 On Site Changes 39

    Operation Outline 30 Risk Assessment 40Site Details 31 Site Register & Toolbox

    Talk

    43

    Load & Radius Details 32 Drawings Attached

    Crane & Lift Information 34

  • 7/30/2019 Crane Lifting Plan

    2/20

    1 INTRODUCTION

    1.1 It is the aim of this Method Statement to define and describe the equipment and safety procedures which are to be employedby the crane lifting company to carry out the lifting operation. The operation will be carried out in accordance with the following

    Legislation & Approved Codes of Practice.

    BS7121 Safe Use of Cranes (part 1) 2006 General & (part 3) 2000 Mobile Cranes

    Lifting Operations & Lifting Equipment Regulations 1998 (LOLER)

    Health & Safety at Work Act 1974 - Provision and Use of Work Equipment Regulations (PUWER) 1998

    Manual Handling Operations Regulations 1992 - Noise at Work Regulations 2006

    Control of Substances Hazardous to Health Regulations 2002 (COSHH)

    Construction Design and Management Regulations 2007 - Working at Height Regulations 2007

    1.2 THE LIFTThe lift will be carried out in line with the guidance contained in BS7121.

    1.3 SITE INSPECTIONThe Appointed Person shall carry out a detailed site inspection to ascertain the full requirements of the Site Manager and

    determine the required crane capacity and make an assessment as far as possible/practicable of any other site issues such as

    access, ground conditions, overhead obstructions, local authority interaction etc.

    1.4 THE APPOINTED PERSONThe Appointed Person who has prepared the Method Statement carries full responsibility for the safe completion of all works

    carried out during the operation. It is the responsibility of the Appointed Person to ensure that the Crane Supervisor is

    adequately briefed on the contents of this Method Statement.

    1.5 THE CRANE SUPERVISORPrior to the commencement of the works, the Crane Supervisor must ensure that all site personnel are adequately briefed on

    the contents of this Method Statement. This briefing shall take the form of a short Toolbox Talk. The Crane Supervisor must

    liaise with the Appointed Person should site circumstances require material change to the methods to be employed during the

    operation.

    1.6 THE CRANE OPERATOR or OPERATORSAll lifting operators or any operators working on behalf of the lifting company shall be fully trained and competent on themachines they operate and will have undergone full manufactures induction and training.

    1.7 PERSONNELAll lifting personnel or any personnel working on behalf of the lifting company will be fully trained and hold the relevant

    certification for the role they undertake on the day of operation. Any non lift company personnel or personnel supplied by the

    client that will be involved in the lifting operation and taking on a specified role will be required to produce the relevant

    certification to the Appointed Person or Crane Supervisor prior to the commencement of the operation. Failure to produce the

    required certification will result in the suspension and possible cancellation of the lifting operation.

    1.8 PERSONAL PROTECTIVE EQUIPMENTAll lifting personnel will be supplied with standard PPE which consists of, Hard Hat, Safety Boots, Overalls, Gloves, Hi-Vis (and

    Safety Goggles if required).

    The Site Manager must inform all Personnel of any specific requirements in advance of the operation date.

    1.9 CERTIFICATIONCopies of statutory test certification and inspection reports will be available for inspection prior to the lifting operation taking

    place.

  • 7/30/2019 Crane Lifting Plan

    3/20

    2 GENERAL CONDITIONS2.1 The Site Manager will provide details of all items to be lifted, including weights, dimensions and any specific lifting tackle

    requirements. The Site Manager is responsible for the structural integrity of all loads to be lifted including any specified lifting

    points or slinging recommendations.

    2.2 The Site Manager must ensure safe access to and egress from site for all lifting personnel and vehicles, and also ensure that theworking area is clear of all obstructions to allow the safe assembly and working of the crane. The Site Manager will beresponsible for supplying suitable floodlighting where necessary or when required.

    The Site Manager must carry out any enabling works required prior to crane arrival.

    2.3 The Site Manager must ensure that the area where the crane is to stand/operate is firm and level and this it is capable ofwithstanding the expected loadings that will be imposed upon it.

    2.4 The Site Manager must ensure that any Traffic Management (not supplied by the lift company) is in place prior to thepositioning of the crane.

    2.5 Any personnel not directly concerned with the lift must be kept out of the crane assembly and working area. The working areashould be cordoned off with barrier tape, temporary fencing or otherwise secured, to prevent non lift associated personnel or

    the general public from entering the lifting area.

    2.6 The Crane Supervisor shall make himself known to all relevant personnel on site, and conduct a Toolbox Talk prior tocommencing operations. The Site Manager should arrange for a site specific induction for the lifting personnel prior to the

    commencement of work. The Site Managers Site Risk Assessment, which identified any site hazards should be made available

    and brought to the attention of the lifting personnel.

    2.7 All cranes to be left unattended for a period, shall be left in safe condition (jib retracted or laid down if possible), with not loadon the crane hook. Cranes shall be shut down and isolated as per manufacturers instructions, secured and locked. Under no

    circumstances shall the crane be moved for lifting purposes if not under the instruction of the Crane Supervisor.

    2.8 In the event that specified cranes or lifting tackle, cannot be supplied on the day of operation due to operational issues,breakdown or any unforeseen circumstances. The lift company has the discretion to supply cranes or equipment that is of a

    suitable alternative to that detailed in this Method Statement, (at no extra cost to the client). In the event of this situation

    arising, the Appointed Person and the Site Manager will be notified. The AP/Crane Supervisor will ensure that any changes do

    not infringe on the factors or safety within this method statement.

    3 WEATHER CONDITIONS3.1 In the event of extreme weather conditions the lift company may need to suspend the lifting operation until such time as it is

    safe to proceed. Although the safe workable wind speed varies from crane to crane, as a guide, the maximum wind speed at

    which lifting operations can take place is 10 metres per second, (22mph).

    In the event that man riding duties are required the maximum workable wind speed reduces to 7 metres per second, (16mph).

    Please note that local conditions and the safety of personnel may dictate the Crane Supervisor and Crane Operator have to

    suspend lifting operations at a lower wind speed than specified in this Method Statement. In addition, lifting operations must

    stop during storms or when there is a risk of lightning strikes.

    4 GROUND CONDITIONS4.1 The lift company will endeavour to advise the client regarding ground conditions, after a visual inspection (or where

    necessary/provided, perusal of a client ground survey report) and supply suitable plates, mats where required. The Client is

    required to advise the lifting company of any known underground services, voids or vaults as state in BS7121. Safe Use of

    Cranes.

  • 7/30/2019 Crane Lifting Plan

    4/20

    5 OPERATION OUTLINE5.1 LIFT CLASSIFICATION

    LIFT CLASSIFICATION

    Basic Lift Standard Lift Complex Lift

    Full Contract Lift Supervisor Only Contract

    Lift

    Note:

    If a Supervisor Only Contract Lift is the chosen option, it is imperative that any personnel supplied by the client, be fully

    trained, competent and experienced in lifting operations and hold current, valid and legislatively required certification, which

    must be available for our Appointed Person or Crane Supervisor to inspect prior to commencement of the lifting operation.

    Any personnel supplied by the Site Manager must work under the instruction of the Appointed Person or Crane Supervisor.

    Failure to comply with the above will results in the suspension of lifting until the aforementioned is adhered to.

    5.2 PERSONNELThe following numbers of personnel for this lift are needed:

    Crane Operator Crane

    Supervisor

    Slinger/Signaller

    5.3 COMMUNICATIONSCommunications between the lifting crew and Crane Operator/s shall be maintained by means of

    Two-Way

    Radios Supplied

    by the Crane

    Company

    Two-Way

    Radios

    Supplied by

    Site Manager

    Hand

    Signals

    5.4 WEATHERCONDITIONSMaximum Workable Wind Speed for

    the Crane is:

    Weather forecast to be obtained on morning of lift, confirming wind

    direction and strength. Wind speed forecast 15.6mph.

    Guide: 10 metres per second (22mph) for load lifting. 7 metres per

    second (16mph) for man riding duties.

    5.5 BRIEFSCOPE OF WORK/NOTABLE FEATURES OF THIS LIFTING OPERATION

  • 7/30/2019 Crane Lifting Plan

    5/20

    6 SITE DETAILS6.1 ENABLINGWORKS

    Any enabling works discussed and agreed to at the site inspection, should be carried out prior to arrival of the crane.

    Are any enabling works required

    6.2 ACCESS&EGRESSThe Site Manager shall ensure that the crane and all associated vehicles have safe and unimpeded access and egress to and

    from site.

    Details of site access & egress

    6.3 GROUNDCONDITIONS including any underground services, voids or vaults.Details of ground conditions

    6.4 OVERHEAD CABLES, OBSTRUCTIONS OR REGULATIONS & ANY SLEWINGRESTRICTIONSDetails of any overhead or slewing

    restrictions

  • 7/30/2019 Crane Lifting Plan

    6/20

    6.5 TRAFFIC AND PEDESTRIAN MANAGEMENTTraffic Management Required Pedestrian

    Management

    Required

    Arranged by

    Details of any Restrictions & Local Authorities Concerned

    7

    LOAD & RADIUS DETAILS7.1 LOAD DETAILS(to be provided by The Site Manager)

    In the event of there being multiple lifts of different weights and dimensions, only the details of the maximum required lifts will

    be shown.

    Description Dimensions Weight

    7.2 LIFTINGPOINTSIt is the Site Managers/Plant Managers responsibility to ensure that any manufactured Lifting Points are certified & tested for

    lifting purposes. This also applies to specified slinging methods where no lifting points are provided.

    Does the load have Manufactured Lifting Points or Manufacturer guidance for the method

    of lifting that has been approved for use by the Site Manager?

    If No to the above:

    Has the Appointed Person assessed and agreed a method of slinging with the Site

    Manager?

    Has the Centre of Gravity been taken into account for all proposed lifts?

    Have the lifting points and/or the lifting method been approved for

    use by the Appointed Person?

  • 7/30/2019 Crane Lifting Plan

    7/20

    7.3 LIFTING TACKLE

    Please Note:

    In the event that the specified lifting tackle cannot be supplied on the day of operation due to operational changes, breakdown

    or any unforeseen circumstances. The crane company can supply and use lifting tackle/equipment that is of a suitable

    alternative to that detailed above. In the event of this situations arising, the Appointed Person and Site Manager should be

    notified. The AP/Crane Supervisor will ensure that any changes do not infringe on the factors of safety within this Method

    Statement.

    All Lifting Tackle certification to be available on site.

    The Crane Supervisor shall inspect all Lifting Tackle prior to each use.

    Any Lifting Tackle supplied by the Site Manager to be fit for purpose, fully certified and in good condition.

    Any damaged tackle shall be marked Not ForUse and returned to the depot for disposal.

    Nylon Slings must be protected from sharp edges using sling guards or suitable packaging.

    7.4 CALCULATEDMAXIMUM LIFT WEIGHTSIn the event of there being multiple lifts of different weights, only the details of the maximum required lift/s will be shown.

    Weight of Load

    Weight of Hook Block

    Weight of Lifting Tackle

    Weight of Fly/S-Lift on Boom

    7.5 CALCULATEDMAXIMUMRADIUSMaximum Required Radius

    7.6 MAXIMUMCALCULATEDLIFTSGross lift weight

    In the event that any loads (lighter than the maximum load) are required to be lifted to a greater radius than the maximum

    loads, see below:

    Maximum required radius

    Gross Lift Weight

    To be lifted to a radius of

    Weight to be lifted at max

    radius

  • 7/30/2019 Crane Lifting Plan

    8/20

    8 CRANE & LIFT INFORMATION8.1 CRANE/S DETAIL

    CRANE

    Crane (make & model)

    Registration and/orPlant No.

    4 Yearly Test and

    Thorough Examination

    12 Month Thorough

    Examination (6 Months

    if Crane is used for

    Lifting People)

    Weekly Crane

    Inspection

    YES NO

    Certificate Expiry Date YES NO

    8.2 REQUIREDWEIGHT&RADIUSGross Lift Weight

    Required Radius

    SWL of Crane at Required

    Radius

    Safety Margin

    In the event that any loads (lighter than the maximum load) are required to be lifted to a greater radius than the maximum

    loads, see below:

    LOAD

    Maximum Required Radius

    Gross Weight at Max Radius

    SWL of Crane

    Safety Margin

    8.3 OUTRIGGER LOADINGS &MATSOutrigger Point Load

    Mat Size

    Mat Area Provided

    Please Note that the Site Manager is responsible for ensuring that the ground conditions are suitable to accept the above

    loadings and pressures.

  • 7/30/2019 Crane Lifting Plan

    9/20

    REGISTER OF LIFTING EQUIPMENT TO BE COMPLETED BY CRANE SUPERVISOR

    Project:

    Lifting equipment (e.g. chains or strops)Description ID No. /

    Reg. Supplier: Test Cert.Expiry Date: 12 MonthlyThoroughExamination

    Expiry Date:

    Used for lifting

    persons? Y/N.

    (If so, 6 Monthly

    Thorough Examn?)

    Weekly

    Inspections

    carried out by:

  • 7/30/2019 Crane Lifting Plan

    10/20

    THIS PAGE IS INTENTIONALLY BLANK

  • 7/30/2019 Crane Lifting Plan

    11/20

    CRANE & LIFT INFORMATION (Continued)

    9 CRANE SET UP PROCEDURETHE CRANE TEAM

    Crane Supervisor:CITB CTA Card Expiry Date: Appointed Person:

    Slinger/Signaller(s):

    CITB CTA Card Expiry Date:

    Crane Driver:

    9.1 The crane, together with the associated operating crew will arrive on site at the specified and agreeddate and time.

    9.2 Crane Supervisor will meet the Site Manager and carry out Toolbox Talk with all personnel involved inthe lifting operation. Once this has been completed, all involved in the lifting operation must sign the

    register for this Method Statement. Any site inductions that are required will also be carried out.

    9.3 Any traffic management, ancillary pans, mats or temporary roadways etc that are required to bepositioned by hi-ab or other means, prior to the crane or cranes manoeuvring into position, will be

    done under the instruction of the Crane Supervisor.

    9.4 The crane will then manoeuvre into position as shown on attached drawing. All manoeuvring to becarried out under the guidance of a member of the lifting crew.9.5 The crane will then commence set-up procedure and rig to the configuration stated in section 8.1. All

    personnel assisting with rigging will be under the guidance of the crane operator, at all times. The set-

    up procedure will be carried out as per crane manufactures manual.

    9.6 Upon completion of the rigging procedure, the crane operator will carry out procedural safety andcomputer checks, implementing any specific operational requirements, i.e. slewing restrictions, short

    rig configurations or fly jib configurations.

    9.7 The Crane Supervisor will then carry out a radio communications check between the crane operatorand the lifting crew.

    9.8 Hook block of crane will then be lowered and required lifting tackle placed on the hook, Lift Supervisorwill ensure that the correct lifting tackle has been selected.

    9.9 The crane operator will then be instructed to hoist lifting tackle clear of any obstructions and positionthe crane ready for the first required lift. Any delivery/removal vehicles will now be positioned adjacent

    to the crane as per attached drawings, ready for work to commence.

    10 LIFTING PROCEDURE10.1 Slinger/Signallers will issue instructions via hand signals or two-way radios to the crane operator to

    position the crane over first required lift, Slinger/Signallers will plumb the boom head, directly over the

    load or set short to allow for jib deflection where necessary.

  • 7/30/2019 Crane Lifting Plan

    12/20

    10.2 The Slinger/Signallers will instruct crane operator, the lower the hooks with lifting tackle to allow

    Slinger/Signaller to attach lifting tackle to load.

    LIFTING PROCEDURE (Continued)10.3 All slinging will be carried out by fully trained, certificated and experienced slingers.

    Slinging methods adopted will be as specified by load manufacturers, using specified lifting points or, in

    the event that no manufacturer instruction or lifting points are provided, our Slingers will work to the

    Appointed Persons recommendations and to Health & Safety executives guidelines for safe slinging for

    lifting loads, (see section 7.2 & 7.3).

    The lifting tackle used, will be as stated in section 7.3 and will have current test certification available.

    10.4 Upon completion of the attachment of the lifting tackle to the load, the Slinger/Signaller will instructthe operator by hand signals or radios, to hoist up to take the slack out of the lifting tackle. Once the

    lifting tackle has started to take the weight and has tightened the Slinger/Signaller will instruct operator

    or operators to stop hoisting. The Slinger/Signaller will then carry out a check around the load to ensure

    that the lifting tackle is sitting correctly, angled correctly and also check any lifting points for security

    and correct operation.

    10.5 Once lifting tackle check has been carried out the Slinger/Signaller will instruct the crane operator oroperators, to hoist the load to a height that allows the lifting tackle to take the full weight of the load

    and again instruct the operator to stop hoisting when the load is just airborne to allow a final check of

    the lifting tackle and lifting points and also check the structural integrity of the load.

    10.6 Once the Slinger/Signaller is confident that the lifting tackle and the load are secure, any tag lines thatmay be required will be attached to the load. Instructions will then be given to the crane operator or

    operators to hoist the load clear of any obstructions, ensuring that any site specific risks are monitored

    throughout the hoisting procedure.

    10.7 Once the load is clear of all obstructions, the Slinger/signaller will give instructions to the craneoperator to manoeuvre the load as required for railing, or manoeuvre to the required landing area for

    single crane lifts.

    10.8 In the event that the landing area is at a different level or should access not permit, the Slinger/Signallerwill pass control of the crane signalling to a second strategically placed Slinger/Signaller at the landing

    area.

    10.9 The landing area Slinger/Signaller will then commence giving instructions to the crane operator oroperators to manoeuvre and lower the load to the required landing point, ensuring that any site specific

    risks are monitored throughout the landing procedure.

    10.10 The Slinger/Signaller will guide the load to the correct orientation as the load becomes contactable byhand or by attached tag lines.

    10.11 The Slinger/Signaller will instruct the crane operator to lower the load to just above the landing positionand then instruct the operator to stop lowering to allow the Site Manager to confirm position and

    orientation of load prior to landing.

    10.12 Once the position is confirmed by the Site Manager, the Slinger/Signaller will instruct the operator toslowly lower load into position. Once landed, a final position check will be made before the

    Slinger/Signaller instructs the operator to lower off all load weight.

    10.13 Slinger/Signaller will instruct the operator to lower off, to allow lifting tackle to be released from theload. In the event that any load is too large or high for safe access by ladder, powered access

    equipment or a lifted man basket will be used to remove slings from loads.

    10.14 Once lifting tackle is detached from the load, the Slinger/Signaller will instruct the operator to slowlyhoist the lifting tackle clear of the load and any site specific risks ensuring that no snagging occurs.

  • 7/30/2019 Crane Lifting Plan

    13/20

    10.15 Once the lifting tackle is clear of all obstructions the Slinger/signaller will instruct the crane operator to

    manoeuvre the crane ready for any further lifts that may be required and had over to another

    Slinger/Signaller were required.

    10.16 All other required lifts will be carried out as stated in sections 11.1 to 11.5. The Lift Supervisor willensure that all lifting and operational procedures are followed as per the Appointed Persons

    recommendations and that any queries or deviation from this Method Statement are notifiedimmediately to the Site Manager and the Appointed Person.

    11 DE-RIG PROCEDURE11.1 Upon completion of the lifting operation, the Crane Supervisor will instruct the crane operator to load

    any ancillary equipment or heavy lifting tackle onto relevant transport ready for removal from site.

    11.2 The Crane Supervisor will then instruct the crane operator to lower all lifting tackle to the ground toallow removal from hook.

    11.3 The crane operator will then instigate the removal of any lifting tackle stored on the crane and thencommence the de-rig procedure.

    11.4 All personnel assisting with de-rigging will be under the guidance of the crane operator at all times.The de-rig procedure will be carried out as per crane manufacturers manual.

    11.5 Once the crane has been de-rigged and all safety checks for road travel have been carried out the craneoperator will manoeuvre the crane/s off site, under the guidance of a member of the lifting crew. The

    crane will then proceed on its way.

    11.6 The remaining members of the lifting crew will ensure that any ancillary mats or equipment etc areremoved from site or placed in an appropriate position ready for collection prior to them leaving site.

    11.7 Any traffic or pedestrian management arranged by the lift company will be unimplemented andremoved.

    11.8 The Crane Supervisor will inform the Site Manager or site representative of the completion of theoperation and address any issues that may be raised and inform of any equipment left on site for later

    collection.

    12 ON SITE CHANGES/ADDITIONAL LIFTS12.1 Any changes to this Method Statement & Lifting Plan must be notified to and approved by the

    Appointed Person. Any crane position changes or amendments to drawings must also be notified and

    approved by the Appointed Person.

    Amendment Details

  • 7/30/2019 Crane Lifting Plan

    14/20

    1)

    2)

    3)

    4)

    5)

    6)

    7)

    8)

    9)

    10)

    Changed discussed with and approved by the Appointed Person

    Crane

    Supervisor

    Date

    (Sign & Print)

    13 RISK ASSESSMENTThe aim of this risk assessment is to highlight any possible hazards that are likely to occur during the lifting

    operation.

    Upon its completion with either a High, Medium, Low or N/A in the Risk Rating Box and either a

    orN/A in the Risk Managed box, the document coverts to a site specific assessment.

    Identified

    HazardsRisk

    Risk

    ratingPrevention Measures

    Risk

    Managed

    Access to and

    Egress from

    Site

    Interaction with public highway and

    members of the public. Interaction

    with other site operations and

    operatives. Interaction with delivery

    vehicles.

    Risk to: Public/ Operators/ Site

    Operatives

    High Banksman with hi-vis to control traffic and

    public while crane manoeuvring into site.

    Flashing amber lights and audible alarms

    when reversing.

    Site management to be aware of intended

    route on site.

    All other site operatives to be made aware

    of crane movement.

    Low

    Medium

    Low

    N/A

    Ground

    Conditions

    Crane travelling over unprepared or

    uneven ground possible damage to

    ground surface and or crane and

    property.

    Ground collapse beneath outriggers

    causing possible overturning.

    Risk to: Public/ Operators/ Site

    Operatives

    High

    Ground to be assessed at time of site

    inspection. Ground improvement to be

    implemented where needed.

    Operator/Crane Supervisor to inspect on

    day of operation.

    Outrigger pans to be used with additional

    heavy duty mats where needed. Client to

    inform the crane company of any known

    risks

    Low

    Medium

    Low

    N/A

    Underground

    Services

    Damage to sub-surface service lines

    causing possible flooding, explosion,High

    A full assessment and mapping of the

  • 7/30/2019 Crane Lifting Plan

    15/20

    asphyxiation or electrocution.

    Risk to: Public/ Operators/ Site

    Operatives

    Mediumtravelling and working area of the crane

    will be made at the site inspection.

    The Site Manager to make the crane

    operator aware of any known risk.

    Permit to work in place where applicable.

    Operator/ Crane Supervisor to check on day

    of operation for any new or unseen risks.

    Low

    Low

    N/A

    Crane

    Positioning

    -

    Set up

    Procedure

    -

    De-rig

    Procedure

    Crane positioned incorrectly for

    required lift.

    Possible damage to crane or property

    during set up or de-rig procedure.

    Risk to: Public/ Operators/ Site

    Operatives

    HighCrane working position clearly identified in

    Method Statement drawings and made

    known to crane operators and marked out

    where required.

    Crane manufacturers instructions for set

    up and de-rig procedure followed. Only

    trained and competent personnel to

    operate and assist with rigging. No one but

    lift associated personnel within crane set

    up area.

    Low

    Medium

    Low

    N/A

    Plant

    Operations

    Crane operation, causing damage to

    property or injury to personnel.

    Mechanical breakdown or structural

    damage.

    Risk to: Public/ Operators/ Site

    Operatives

    High

    Trained, certified and competent craneoperators.

    Cranes fully maintained with full service

    and testing history.

    Manufacturers instructions adhered to at

    all times.

    Low

    Medium

    Low

    N/A

  • 7/30/2019 Crane Lifting Plan

    16/20

    Identified

    HazardsRisk

    Risk

    ratingPrevention Measures

    Risk

    Managed

    Manual

    Handling-

    Sling of Loads

    -

    Signalling

    -

    Tailing

    Operations

    -

    Multiple

    Crane

    Operations

    Incorrect slinging of loads.

    Unsuitable lifting equipment used.

    Failure of lifting equipment.

    Incorrect signals give to crane

    operator causing damage to loads,

    property or injury to personnel. Crane

    operator lifting unseen loads.

    Risk to: Public/ Operators/ Site

    Operatives

    High

    Trained, certified and competent Slingers to

    sling all loads. Only specified lifting tackle

    and lifting tackle with current and valid

    certification to be used. Visual inspection to

    be carried out on all lifting tackle prior to

    use. Qualified Signallers to use recognised

    hand signals or radio commands to

    communicate with crane operators.

    Radios used for unsighted lifts.

    Low

    Medium

    Low

    N/A

    Working at

    Height

    -

    Ladders

    -

    Scaffolding

    -

    Access

    Platforms

    -

    Man Baskets

    Personnel falling from height during

    crane assembly and or lifting

    operations.

    Personnel falling from delivery

    vehicles during slinging of loads.

    Operation of mechanical platforms.

    Personnel working from man Baskets.

    Risk to: Public/ Operators/ Site

    Operatives

    High Operators to work from footed ladders forcrane assembly.

    Slingers to work from footed ladders for

    slinging loads where reasonably

    practicable.

    Work platforms or lifted man basket to be

    used where a height risk is deemed

    excessive. Access operators to be IPAF

    trained.

    Site to ensure all working areas at height

    are safe with suitable guard rails. Harnesses

    to be worn where required / practicable. All

    scaffolds to be certified for working use.

    Low

    Medium

    Low

    N/A

    Protection of

    Public & Site

    Operatives

    -

    Falling

    Objects

    Injury to public or site personnel from

    falling objects or materials.

    Damage to vehicles or property during

    lifting operations. Risk from

    suspended loads.

    Risk to: Public/ Operators/ Site

    Operatives

    High Work area to be cordoned off as anexclusion zone.

    Sufficient barrier & signage to be in place to

    warn non lift associated persons of

    overhead & ground level risks. All over-sail

    to be addressed, monitored and evacuation

    implemented where practicable. Lift crew

    to be aware of all lifting operations.

    Low

    Medium

    Low

    N/A

    Traffic

    Pedestrian

    Management

    Damage to property or plant. Risk of

    responsibility for collision or injury.

    Protection of personnel during works.

    Risk to: Public/ Operators/ Site

    Operatives

    High Full assessment of required restrictions onpublic highways, service roads or private

    roads to be made at site inspection. AnyTraffic Management contractors supplied

    by site or the crane company will be fully

    certified and competent. Traffic

    Management supplied by the site should be

    set up prior to arrival of crane.

    Low

    Medium

    Low

    N/A

    Adverse

    Weather

    Conditions

    Crane operation, load stability and

    control.

    Risk of injury to personnel and

    damage to property.

    Risk of lightning strike. Bad visibility.

    Risk to: Public/ Operators/ Site

    High Weather reports obtained before andduring lifting operations.

    Crane operator to monitor wind speed

    equipment.

    Suspension of lifting operation until risk

    subsides.

    Low

    Medium

    Low

  • 7/30/2019 Crane Lifting Plan

    17/20

    Operatives

    N/A

  • 7/30/2019 Crane Lifting Plan

    18/20

    Identified

    HazardsRisk

    Risk

    ratingPrevention Measures

    Risk

    Managed

    Overhead or

    slewingObstructions

    or

    Restrictions

    -

    Low

    Headroom

    Damage to crane or property if crane

    boom or superstructure comes into

    contact with any restriction.Infringement of unauthorised air

    space. Working in restricted work

    space.

    Risk to: Public/ Operators/ Site

    Operatives

    HighFull assessment of any risks made and

    addressed at site inspection. Safe system of

    work adhered to where implemented.

    Work to zone alarms where implemented.

    Implement crane swl computer working

    restrictions.

    All relevant authorities contacted and

    advised and any restrictions adhered to.

    Low

    Medium

    Low

    N/A

    ADDITIONAL SITE SPECIFIC RISKS

    ADDITIONAL RISKS IDENTIFIED ON DAY OF OPERATIONS

    ADDITIONAL RISKS DUE TO ON SITE CHANGES

    IdentifiedHazards

    Risk RiskRating

    Prevention Measures RiskManaged

  • 7/30/2019 Crane Lifting Plan

    19/20

    14 SITE REGISTER/TOOLBOX TALK

    All operational staff involved in this lifting operation must read this method Statement or have had the

    contents of it explained in detail to them prior to commencing work.

    All persons involved in this lifting operation are to sign below in acceptance that a detailed briefing of this

    operation has been given and understood.All certification has been checked and verified prior to the lifting operation commencing.

    Crane Supervisors Acceptance of Responsibilities:

    I confirm that I have been fully briefed on the contents of this Method Statement and Risk Assessment and that I

    accept the duty of ensuring that the lift/s will be carried out in accordance with the Methods and Procedures set

    out in this Document.

    Signed Date

    Print Name Position Signature Date

    Site Manager Acceptance of this Method StatementI confirm that I have read and understood this Method Statement and Risk Assessment and that I

    accept the responsibilities of the site management with respect to Safe Use of Cranes (part 1) 2006

    General and (part 3) 2000 Mobile Cranes.

    Signed Date

    SUMMARY

    Crane Detail Site

    ManagerCrane

    Site

    Project

    Detail

    Req Radius

    SWL SES

    Point Load Date Issue No

  • 7/30/2019 Crane Lifting Plan

    20/20

    THIS PAGE IS INTENTIONALLY BLANK