COUNCIL WORK SESSION, FEBRUARY 19, 2019
City of Arlington, Texas 2
CITY COUNCIL PRIORITY: SUSTAIN CORE SERVICES(MAINTAIN AND IMPROVE CURRENT INFRASTRUCTURE)
CAPITAL BUDGET CYCLE REPEATS EACH YEAR WITH A BOND ELECTION EVERY 3-5 YEARS.
City of Arlington, Texas 3
Streets Water and sewer lines
Parks and the preservation of
green space
Recreations Facilities
City Facilities:• Libraries• Police and Fire
Stations• Water Treatment
Plants• City Buildings• Airport
City of Arlington, Texas 4
• Strategic planning or master planning to identify projects related to new capital needs
• Project evaluation, scope and cost
• Prioritize capital needs, projects and acquisitions by comparing with council priorities and available funding
• Determine capacity for construction of projects
• We have to ask ourselves:
• How many projects can we physically do in a given year?
• Will our own work crews implement a project, or will we hire outside contractors?
• How many projects can staff effectively manage in the span of a year?
BOND ISSUANCE PROVIDES FORSYSTEMATIC INVESTMENT IN CITYASSETS FOR MAINTENANCE, STRENGTH, & GROWTH
SIMILAR PROCESS TOREGULAR HOMEOWNERMAINTENANCE & INVESTMENTIN PROPERTY
CONSERVATIVE FINANCIALPRINCIPLES GUIDE CITY DEBT ISSUANCE
• DEBT TERMS DO NOT EXCEED THE EXPECTEDUSEFUL LIFE OF THE ASSET
• BONDS NORMALLY ISSUED WITH A LEVELPRINCIPAL STRUCTURE; ALLOWING DEBT RETIREMENTAT HALF THE LIFE OF ISSUANCE, ON AVERAGE
MAINTAINING & IMPROVINGASSETS YIELDS LASTING VALUE
City of Arlington, Texas 5
City of Arlington, Texas 6
GENERAL OBLIGATION BONDS ARE APPROVED BY CITY VOTERS AND ISSUED BY THE CITY • FUNDS COME FROM SALE OF
GENERAL OBLIGATION BONDS &CERTIFICATES OF OBLIGATION
• SALES OCCUR ON AYEARLY BASIS
• GO BOND RATINGSS&P: AAAMOODY’S: Aa1FITCH: AAA
• DEBT RATIOSTOTAL DEBT/TOTAL AD VALOREM TAX BASE = <2%TOTAL DEBT/GENERAL FUND BALANCE + DEBT SERVICE BALANCE = <20%TOTAL DEBT PER CAPITA = <$1,180/PERSON
City of Arlington, Texas 7
TOTAL FY18 BUDGET:
CAPITAL: $64,334,595STORMWATER: $16,440,000WATER UTILITIES: $64,935,777
TOTAL: $145,710,372
FINDLAY/VILLAGE CREEK LINEAR PARK
IMPROVEMENTS COMPLETE
CALENDER (HARRIS TO EDEN)CONCEPTUAL PLAN
STAGE
HARRIS (COOPER TO CALENDER)
IN DESIGN
BRANTLEY HINSHAW PARK IMPROVEMENTS
COMPLETE
SOUTHEAST RECREATION
CENTERIN DESIGN
HUGH SMITH RECREATION
CENTER/LIBRARYIN DESIGN
AVENUE H (360 TO GSW)
IN DESIGN
2016 RESIDENTIAL REBUILD PROGRAM
PHASE IICOMPLETE
City of Arlington, Texas 8
Election Year Bond Propositions FY19 FY20 FY21 FY22 FY23 FY24 FY25 Total
2014 Fire 900,000 8,880,000 9,780,000
2014 Parks and Recreation 1,900,000 1,000,000 2,900,000
2014 Streets and Transportation 46,900,000 33,863,000 80,763,000
2017 Active Adult Center 4,500,000 40,500,000 45,000,000
Sub-total 54,200,000$ 43,743,000$ 40,500,000$ -$ -$ -$ -$ 138,443,000$
2018 Fire & Police 2,350,000 4,500,000 8,650,000 800,000 8,200,000 24,500,000
2018 City Facilities 1,600,000 1,600,000 1,600,000 1,600,000 1,600,000 8,000,000
2018 Parks and Recreation 2,045,000 6,905,000 2,400,000 4,815,000 3,000,000 19,165,000
2018 Streets and Transportation 1,250,000 3,785,000 25,370,000 30,400,000 29,530,000 32,100,000 15,400,000 137,835,000
Sub-total 1,250,000 3,785,000 31,365,000 43,405,000 42,180,000 39,315,000 28,200,000 189,500,000
Grand Total 55,450,000$ 47,528,000$ 71,865,000$ 43,405,000$ 42,180,000$ 39,315,000$ 28,200,000$ 327,943,000$
City of Arlington, Texas 9
City of Arlington, Texas 10
FY19 Capital Budget Considerations
City of Arlington, Texas 11
TOTAL PROPOSED BUDGET:
CAPITAL: $61,482,336STORMWATER: $16,760,000WATER UTILITIES: $124,373,000
TOTAL: $202,615,336
COLLINS(SH 303 TO PARK ROW
CONSTRUCTION
JULIA BURGEN PARK PHASE IICONSTRUCTION
RIVER LEGACY PARKING LOT RENOVATIONSCONSTRUCTION
HARRIS (COOPER TO
COLLINS)
TURNER WARNELL (MATLOCK TO
COOPER) CONSTRUCTION
BOWMAN SPRINGS PARK RENOVATIONS CONSTRUCTION
ACTIVE ADULT CENTERDESIGN
• 2019 Capital Budget slated for consideration on March 19, 2019
City of Arlington, Texas 12
Project Project Amount Funding SourceFire Training Remodel $500,000 General Obligation (GO)Fire Station #1 Rebuild $400,000 General Obligation (GO)Julia Burgen Park Phase II $880,000 General Obligation (GO)Bowman Springs Park Renovations $500,000 General Obligation (GO)California Lane Park Renovations $520,000 General Obligation (GO)Active Adult Center $4,500,000 General Obligation (GO)Signal/ITS Annual Program $830,500 General Obligation (GO)Irrigation Repair Program $68,000 General Obligation (GO)Residential Rebuild Program $3,137,500 General Obligation (GO)Sidewalk Program $1,000,000 General Obligation (GO)Materials Testing Program $375,000 General Obligation (GO)Harris (Cooper to Calender) $6,796,000 General Obligation (GO)Matlock (Bardin to Green Oaks) $7,263,000 General Obligation (GO)Calender (Harris to Eden) $4,846,000 General Obligation (GO)Pleasant Ridge (I-20 to Enchanted Bay) $546,000 General Obligation (GO)Collins (SH 303 to Park Row) $9,831,000 General Obligation (GO)Collins (Mayfield to I-20) $2,607,000 General Obligation (GO)Avenue H (SH 360 to Great Southwest) $7,207,000 General Obligation (GO)Turner Warnell (Matlock to Cooper) $1,288,000 General Obligation (GO)Poly Webb (Pleasant Ridge to Shorewood) $316,000 General Obligation (GO)Avenue E (SH 360 to Great Southwest) $789,000 General Obligation (GO)Sublett Road (City Limit to Joplin) $1,250,000 General Obligation (GO)Airport Perimeter Fencing $100,000 Gas ReveuneFire Heavy Fleet Replacement $2,692,336 CO (Item proposed in Operating Budget)Tierra Verde HVAC $750,000 CO (Item proposed in Operating Budget)Playground Replacement $1,140,000 CO (Item proposed in Operating Budget)River Legacy Parking Lot Renovations $350,000 CO (Item proposed in Operating Budget)Facility Maintenance $1,000,000 CO (Item proposed in Operating Budget)
TOTAL $61,482,336
City of Arlington, Texas 13
• $350,000 for River Legacy Parking Lot Renovations
• $750,000 for Tierra Verde HVAC
• $1,000,000 for Facility Maintenance
• $1,140,000 for Playground Replacement
• $2,692,336 for Fire Heavy Fleet Replacement
All items were discussed during FY19 operating budget process and funding will be issued through COs.
City of Arlington, Texas 14
Project Project Amount Funding Source
Annual Localized Drainage Projects $425,000 Pay GoMatthews Court Drainage Improvements $8,500,000 Split ($7.3M Paygo/ $1.2M Bond)Tributary CC2(360 to Susan) Conceptual Study $250,000 Pay GoCalifornia Lane Drainage Improvements $330,000 Pay GoFlood Mitigation Buyouts $3,500,000 Revenue Bonds2017 Bridge Maintenance $150,000 Pay GoAnnual Bridge, Channel and Infrastructure Maintenance $285,000 Pay GoConstruction Materials Testing $100,000 Pay GoIrrigation $40,000 Pay GoDevelopment Review (Flood Study and Detention Analysis) $50,000 Pay GoStormwater Review Consulting $100,000 Pay GoWatershed Model Maintenance $50,000 Pay GoFlood Monitoring System $30,000 Pay GoKee Branch Trib 4 (Deaver Park to Andalusia Trail) Erosion $2,500,000 Revenue BondsWoodland Dr. Erosion $200,000 Pay GoLower Johnson Creek Dredging Evaluation $250,000 Pay Go TOTAL $16,760,000
City of Arlington, Texas 15
Programs FY19 FY20 FY21 FY22 Total CIPDrainage Projects $10,900,000 $5,800,000 $7,000,000 $6,500,000 $30,200,000Floodplain Management $1,000,000 $1,000,000 $1,000,000 $1,000,000 $4,000,000Maintenance $1,050,000 $850,000 $1,250,000 $850,000 $4,000,000Annual Contracts or Programs $610,000 $610,000 $610,000 $610,000 $2,440,000Erosion Protection/Repair Projects $6,600,000 $1,000,000 $1,000,000 $1,000,000 $9,600,000
$20,160,000 $9,260,000 $10,860,000 $9,960,000 $50,240,000
FY 2018 CIP
Programs FY19 FY20 FY21 FY22 Total CIPDrainage Projects $9,505,000 $9,600,000 $5,529,000 $7,934,000 $32,568,000Floodplain Management $3,500,000 $1,000,000 $500,000 $500,000 $5,500,000Maintenance $435,000 $810,000 $1,210,000 $810,000 $3,265,000Annual Contracts or Programs $370,000 $420,000 $420,000 $415,000 $1,625,000Erosion Protection/Repair Projects $2,950,000 $3,300,000 $3,000,000 $1,000,000 $10,250,000
$16,760,000 $15,130,000 $10,659,000 $10,659,000 $53,208,000
FY 2019 CIP
City of Arlington, Texas 16
Project Project AmountAvenue H (SH 360 to Great Southwest) $2,400,000Calender (Harris to Eden) $1,300,000Collins (Mayfield to I-20) $150,000Collins (SH 303 to Park Row) $1,800,000Eden (US 287 to Calender) $370,000Elevated Storage Tank $300,000Harris (Cooper to Calender) $4,000,000Joint Drainage Projects w/Public Works $1,100,000Meter Infrastructure $2,590,000Residential Water Renewal $3,000,000Technology and Equipment $785,000Water and Sanitary Sewer Main $15,740,000Water Operations $1,058,000Water Treatment $89,780,000
TOTAL $124,373,000
City of Arlington, Texas 17
Project FY19 FY20 FY21 FY22 Total CIPElevated Storage Tank $215,000 $25,000 $25,000 $25,000 $290,000Technology and Equipment $375,000 $35,000 $75,000 $0 $485,000Meter Infrastructure $2,590,000 $2,590,000 $2,590,000 $2,590,000 $10,360,000Operations Renewal Projects $1,830,000 $1,930,000 $2,030,000 $2,230,000 $8,020,000Joint Drainage Projects w/Public Works $800,000 $800,000 $800,000 $800,000 $3,200,000Residential Rebuilds $1,800,000 $1,800,000 $2,000,000 $2,500,000 $8,100,000Water and Sanitary Sewer Main $13,575,000 $5,725,000 $8,175,000 $12,625,000 $40,100,000Water Treatment $27,205,000 $73,000,000 $3,350,000 $7,350,000 $110,905,000Individual Street Projects $10,850,000 $3,660,000 $1,000,000 $0 $15,510,000
GRAND TOTAL $59,240,000 $89,565,000 $20,045,000 $28,120,000 $196,970,000
FY 2018 CIP
Project FY19 FY20 FY21 FY22 Total CIPElevated Storage Tank $300,000 $75,000 $155,000 $75,000 $605,000Technology and Equipment $785,000 $150,000 $75,000 $40,000 $1,050,000Meter Infrastructure $2,590,000 $2,590,000 $2,590,000 $2,590,000 $10,360,000Water Operations $1,058,000 $1,058,000 $1,660,000 $1,910,000 $5,686,000Joint Drainage Projects w/Public Works $1,100,000 $800,000 $800,000 $800,000 $3,500,000Residential Rebuilds $3,000,000 $1,800,000 $3,000,000 $2,000,000 $9,800,000Water and Sanitary Sewer Main $15,740,000 $11,405,000 $1,725,000 $10,025,000 $38,895,000Water Treatment $89,780,000 $27,600,000 $3,780,000 $4,950,000 $126,110,000Individual Street Projects $10,020,000 $3,510,000 $300,000 $500,000 $14,330,000
GRAND TOTAL $124,373,000 $48,988,000 $14,085,000 $22,890,000 $210,336,000
FY 2019 CIP
City of Arlington, Texas 18
Source of Funds FY19 FY20 FY21 FY22 Total CIPPayGo $20,385,000 $12,105,000 $14,895,000 $19,970,000 $67,355,000Debt Issuance $38,855,000 $77,460,000 $5,150,000 $8,150,000 $129,615,000TWDB Issuance $0 $0 $0 $0 $0
GRAND TOTAL $59,240,000 $89,565,000 $20,045,000 $28,120,000 $196,970,000
FY 2018 CIP
Source of Funds FY19 FY20 FY21 FY22 Total CIPPayGo (inc reimbursements) $15,977,152 $14,500,000 $5,595,555 $5,363,125 $41,435,832Debt Issuance $25,179,152 $26,488,000 $8,489,445 $9,526,875 $69,683,472TWDB Issuance $82,500,000 $7,000,000 $0 $7,000,000 $96,500,000TWDB Loan Forgiveness $716,695 $1,000,000 $0 $1,000,000 $2,716,695
GRAND TOTAL $124,372,999 $48,988,000 $14,085,000 $22,890,000 $210,335,999
FY 2019 CIP
City of Arlington, Texas 19
• FY18 Issuance – All in True Interest Cost (TIC)• WWS Revenue Bonds – 3.215% (TIC)• TWDB Bonds – 1.063% (TIC)
• FY19 CIP issuance of $82.5mil with TWDB• Projected interest savings $18.5mil over 20 years
City of Arlington, Texas 20
• February 19: Final Draft 2019 Capital Budget Presented to Council
• March 19: Capital Budget, Reimbursement Resolution considered by Council
• April 23: Parameters Ordinances considered by Council
• April 2019: Rating Agency meetings
• May / June 2019: Sell Bonds
City of Arlington, Texas 21
QUESTIONS?