Cost & Management Accounting - MGT402 Power Point Slides Lecture 13

Embed Size (px)

Citation preview

  • 8/13/2019 Cost & Management Accounting - MGT402 Power Point Slides Lecture 13

    1/23

    Labor Costing

    Lecture-13

    Main Ahmad Farhan (ACA)

  • 8/13/2019 Cost & Management Accounting - MGT402 Power Point Slides Lecture 13

    2/23

    Time Base Bonus Plans

    Halsey Premium Plan. Halsey wire Premium Plan.

    Rowans Premium Plan.

  • 8/13/2019 Cost & Management Accounting - MGT402 Power Point Slides Lecture 13

    3/23

    Halsey Premium Plan

    Bonus pay = 50% of time saved x normal wage rate

    Halsey Wire Premium Plan.

    Bonus pay = 30% of time saved x normal wage rate

  • 8/13/2019 Cost & Management Accounting - MGT402 Power Point Slides Lecture 13

    4/23

    Rowans Premium Plan

    Time saved = Standard time Actual time taken

    Premium Rate =Time saved

    Standard time

    * 100

    Bonus Pay = Premium rate * Normal wages

  • 8/13/2019 Cost & Management Accounting - MGT402 Power Point Slides Lecture 13

    5/23

    Example

    Standard hours 40 hoursCompletion time 30 hours

    Time saved 10 hoursHourly rate Rs. 10 per hour

    i. Halsey Plan

    ii. Halsey wire planiii. Rowan plan

  • 8/13/2019 Cost & Management Accounting - MGT402 Power Point Slides Lecture 13

    6/23

    Solution

    Halsey Premium Plan 50%

    Normal wages = Actual time taken * wage rate

    = 30 * 10 = Rs. 300

    Bonus = 50% of time saved x normal wage rate

    (50% * 10 hours ) 5 x 10 = 50

    Gross wages = 50 + 300

    = 350

  • 8/13/2019 Cost & Management Accounting - MGT402 Power Point Slides Lecture 13

    7/23

    Effective Wage Rate

    Bonus Pay

    Actual time given

    350 = 11.667 per hours

    30

  • 8/13/2019 Cost & Management Accounting - MGT402 Power Point Slides Lecture 13

    8/23

    Halsey Wire Premium Plan

    Normal wages = Actual time taken * wage rate= 30 * 10 = Rs. 300

    30% of time saved x Normal wage Rate

    (30% * 10 hours) 3 x 10 = 30300 + 30 = 330

    Effective Wage Rate

    330 = 11 p/hr30

  • 8/13/2019 Cost & Management Accounting - MGT402 Power Point Slides Lecture 13

    9/23

    Rowans Premium Plan

    Basic wages = Actual time x normal wage rate

    30 x 10 = 300

    Time Saved = Standard hours-Actual hours taken

    40 - 30 = 10

    Time saved/standard time x 100

    10 / 40 x 100 = 25%

    300+(300 * 25%) = 375

  • 8/13/2019 Cost & Management Accounting - MGT402 Power Point Slides Lecture 13

    10/23

    Effective Wage Rate

    Gross pay

    Actual hours

    375 = Rs. 12.50 p/hr

    30

  • 8/13/2019 Cost & Management Accounting - MGT402 Power Point Slides Lecture 13

    11/23

    Piece Rate Base Premium Plans

    Straight Piece Rate plan

    Unit produced * Standard rate (p.u)

  • 8/13/2019 Cost & Management Accounting - MGT402 Power Point Slides Lecture 13

    12/23

    Example

    Hourly wage rate = Rs. 50

    One units produced = 30 minutes

    Normal production in 1 hour = 2 units50 = 25 P.U

    2

    Per Piece wages x units manufactured

    25 X 15 = 375

    Per Piece wages =

  • 8/13/2019 Cost & Management Accounting - MGT402 Power Point Slides Lecture 13

    13/23

    Piece Rate With Minimum Guarantee Time Base

    Wages

    A protections is given to the worker against lowproductivity and low wages caused by factors beyond

    their control.

  • 8/13/2019 Cost & Management Accounting - MGT402 Power Point Slides Lecture 13

    14/23

    Example

    Normal wage Rate Rs. 50 Per hours.Unit Rate Rs. 10 Per unitScenario

    1- Actual product (8hours) 20 units2- Actual product (8hours) 50 units

  • 8/13/2019 Cost & Management Accounting - MGT402 Power Point Slides Lecture 13

    15/23

    SolutionScenario-1

    Time base wage guaranteed 8x50 = 400

    Piece rate base wages 30x10 = 300Guaranteed wages given = 400

    Scenario-2

    Time base wage guarantee 8x50 = 400Piece Rate base wage 50x10 = 500

    Wages = 500

  • 8/13/2019 Cost & Management Accounting - MGT402 Power Point Slides Lecture 13

    16/23

    Differential Piece Rate Plans

    Tailors differential piece rate / Two piece rateplan

    Marix differential piece rate.

  • 8/13/2019 Cost & Management Accounting - MGT402 Power Point Slides Lecture 13

    17/23

    Tailors Piece Rate Plan

    Standard or at par

    Below Standard (Quantity wise)

    At standard

    50 x 12 p.u = 600

    Below standard

    40 x 10 p.u = 400

  • 8/13/2019 Cost & Management Accounting - MGT402 Power Point Slides Lecture 13

    18/23

    Marix Piece Rate

    At below (Rs 10 80% standard rate)

    At Par (Rs 15 80%-100%)

    At above (Rs 12 at above 100%)

  • 8/13/2019 Cost & Management Accounting - MGT402 Power Point Slides Lecture 13

    19/23

    Example

    Three workers A, B & C

    Standard out put 40 units

    Piece Rate 10 p.uA produced 25 units

    B produced 35 units

    C produced 45 units

    Calculate the wage rate by Tailor or Marix methods.

  • 8/13/2019 Cost & Management Accounting - MGT402 Power Point Slides Lecture 13

    20/23

    Solution

    Standard out put 40 units

    A&B are below standard

    C is above standard units

    Tailors Method.

    A 25 x 10 = 250

    B 35 x 10 = 250C 45 x 12 = 540By MatrixA 25 x10 = 250B 35 x 12 = 420

    C 45 x 15 = 765

    Below 80%

    80%-100%

    Above 100%

  • 8/13/2019 Cost & Management Accounting - MGT402 Power Point Slides Lecture 13

    21/23

    Contribution By employer

    The employer can be provide some benefits toemployee.

    Provident Fund.

    Group Insurance.

    E.O.B.I benefits.

  • 8/13/2019 Cost & Management Accounting - MGT402 Power Point Slides Lecture 13

    22/23

    Entries

    Employee benefit

    To Social Security

    To Provident Fund

    To E.O.B.I Fund

  • 8/13/2019 Cost & Management Accounting - MGT402 Power Point Slides Lecture 13

    23/23

    Entries

    Employee benefit 10,000

    To Social Security 3,000

    To Provident Fund 5,000

    To E.O.B.I Fund 2,000

    Distribution employer benefit

    Administration (25%) 2,500

    F.O.H Cost (60%) 6,000

    Selling Exp (15%) 1,500

    To employees benefit 10,000