CORE Executive Board. December 1, 2010 Next CEB January , 2011. Agenda. Performance Metrics Self Sufficiency Resource Utilization Project/Enhancement Service Level Dashboard Completed Projects Business Services Change Requests Business Services Enhancement Service Requests - PowerPoint PPT Presentation
Citation preview
CORE Executive Board
December 1, 2010
Next CEB January , 2011
Agenda
Performance Metrics
Self Sufficiency Resource Utilization
Project/Enhancement Service Level Dashboard
Completed Projects
Business Services Change Requests
Business Services Enhancement Service Requests
SQL Requests/Problem Management Summary
Portfolio
Budget Status
Priority
Execution Delivery Schedule
Planning Delivery Schedule
Projects in Movement
Program Status
HCM
Financials
Application Development Service Request Summary
Scorecard
Executive Issues
2
CAPACITY 7/3- 10/2
3
CAPACITY 7/3- 10/2
4
Project/Enhancement Service Level DashboardGreen
Red
Met Expected Target
Did Not Meet Expected Target
Business Services Change Request on
Time (Detail)
Target
5
Business Services Projects on Time
(Detail)
80%
Business Services Projects on Budget
(Detail)
94%
Technical Service Projects on Time
(Detail
Technical Services Projects on Budget
(Detail)
70%
85%
Year Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
75%
2011
2010 75% 38% 86% 82% 100% 55% 92%
2011
2010 75% 75% 75% 80% 80% 80% 100% 100% 100%
2011
2010 100% 100% 100% 100% 100% 100%
2011
2010 27% 27% 27% 43% 43% 43% 57% 57% 57%
2011
2010 100% 100% 100% 86% 86% 86% 86% 86% 86%
100% 100% 100%
Projects Completed Since Last CEB
PeopleTools 8.49
Assets ODOT
DCS Vendor Registration
Schedule Budget
6
7
# ESRs completed # ESRs not completed # unplanned completed
January (FIN) February (HCM) March (FIN) 6 2 5April (HCM) May (FIN) 3 5 4June (HCM) July (FIN) 6 1 1August (HCM) 18 4 7September (FIN) 9 0 5October (HCM) 12 10 10November (FIN) 12 1 1December (HCM)
Business Services Change Requests On time (Detail)
8
Business Services Enhancement Service Requests
9
Functional ESRs Pending Config/Setup UAT Completed
CRM
ELM 1
EPM
FIN 3
HCM 33 8 2 9
Total 36 8 2 10
Technical ESRs Pending Dev UAT Completed
CRM 3
ELM 3 1
EPM 1
FIN 28 13 3 8
HCM 49 20 3 3
Total 84 33 7 11
Pending Dev UAT Completed
Total 120 41 9 21
Business Services Enhancement Service Requests - Nov, 2010
0
5
10
15
20
25
30
DBA/ System
Purchasing
ARBI
CRM
Procurement
HRMS
Financial
EPM
Problem Management SQL Requests
10
Problem Management Summary
Summary Total
Problems
Resolved or
Resolution In Process
Investigating Resolved by
Future Functionality
DR to be Created
Monitor
Financial 16 13 1 2 0 0
PO 2 1 1 0 0 0
HCM 19 14 1 0 4 0
DBA/System 3 3 0 0 0 0
TOTAL 40 31 3 2 4 0
11
Portfolio Priority
12
Project NameProject
ManagerDept Function
Current Project Phase
Priority within
FunctionBackfill Developers for Production support and Enhancments 2011
Fred Cantrell CORE Financial mgmt+
Human capital mgmt
Execution 1
Time and Labor Pilot Alex / Kim CORE Human capital mgmt Execution 2P-Card - BOA Transition Lisa
McKeithanCORE Financial Mgmt Execution 3
Grants/Projects/Contract A/R Billing/T&L Extended Commerce/DEQ
Alex / Kim CORE Enterprise service automation
Execution 4
Higher Education Interface Lisa McKeithan
CORE Human capital mgmt Execution 5
Inventory-ODOT Alex / Kim CORE Supply chain mgmt Execution 6GPC - ODOT Alex / Kim CORE Enterprise Service
AutomationInitiation> Planning
7
T&L Manager Self Service ODOT Pilot
Alex / Kim CORE Enterprise service automation
Execution 8
Treasury GL Implementation Alex CORE Financial mgmt Execution 9PeopleSoft Extract Staging Environment
Lisa McKeithan
CORE Other Execution 10
Business Intelligence/Financials Analytics
Lisa McKeithan
CORE Other Planning 11
OpenBooks - Phase III Lisa McKeithan
CORE Other Execution 12
data.gov Lisa McKeithan
CORE Transparency Initiation 13
Portfolio Priority
13
Project Name Project Manager Dept Function Current Project PhasePriority within
Function
Grants - Provisioning Lisa McKeithan CORE Other Planning 14
Licensing Lisa McKeithan CORE Other Planning 15
Enterprise Learning Management- Rollout Michael Grisser CORE Human capital mgmt Execution 16
Scanning and Bar-coding functionality for Phase II modules Alex CORE Assets Concept 17
Loans Processing Initiation> Planning 18
Expense Module Alex/Kim CORE Financial mgmt Planning 19
Budget Lisa McKeithan CORE Other Concept> Initiation 20
AM Rollout - Tax Commission Michael Grisser CORE Financial mgmt Planning> Execution 21
Department of Mines GPC AR/BI Alex Galley CORE Enterprise Service Automation Initiation> Planning 22
Broadband GPC/AR/BI Alex Galley CORE Enterprise Service Automation Initiation> Planning 23
Human Resources Dashboard Michael Grisser CORE Human capital mgmt Concept 24
14
Projects in Execution Delivery Schedule
J U N
J U L
A U G
S E P
O C T
N O V
D E C
J A N
F E B
M A R
A P R
M A Y
J U N
J U L
A U G
S E P
O C T
N O V
D E C
J A N
F E B
M A R
A P R
M A Y
J U N
J U L
A U G
S E P
O C T
N O V
D E C
Grants/Projects/Contract A/R Billing ODOT
Inventory ODOT
T&L Manager Self Service ODOT
PeopleSoft Extract Staging Environment
Time and Labor Pilot
Grants/Projects/Contract A/R Billing/T&L Extended Commerce/DEQ
OpenBooks - Phase III
P-Card - BOA Transition
Treasury GL Implementation
Asset Management Rollout - Tax Commission
FY11 Technical Backfill
ELM rollout
Higher education Interface
2009 2010 2011
15
Projects in Planning Delivery Schedule
O C T
N O V
D E C
J A N
F E B
M A R
A P R
M A Y
J U N
J U L
A U G
S E P
O C T
N O V
D E C
J A N
F E B
M A R
A P R
M A Y
J U N
J U L
A U G
S E P
O C T
N O V
D E C
Loans
Data.gov
Mines GPC/AR/BI
Broadband GPC/AR/BI
Financial Analytics
Grants Provisioning
Licensing
2010 2011 2012
16
Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
Milestone Task Bar
* Pilot agencies include: OSF, Wildlife, Board of Tests, DEQ & Conservation Commission.
* Go-live is planned for January but there will be clean-up work to complete DRs and automate processes.* Initial loads will likely require manual intervention until all processes are defined and programming is complete.
* Labor costs are based on OSF doing the development. This might increase if the DRs are given to Innovativ.
* Project kick-off is set for December 1st.
Issues/Assumptions
Per SB1759, provide transparency data in a downloadable format. The state has chosen Socrata to do this. OK.gov will be the 'front-end'. We will transfer files to OK.gov and they will write the interface to Socrata.
Milestone Plan +/- 50%
Prepare Development Requests and Define Process for Loading Data
CORE - 2822 - data.ok.gov
Develop and Test Programs
Go-Live
Migration to Production
2010 2011
17
Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
Only Required if Grants Provisioning can not satisfy functionality or is not timely
* 150 hours are Agency's consultant ($27,750)
Issues
ODOC HP System is unreliable and solution requires action.
2010 / 2011
Roll out / Conversion
Project Start
2833 - ODOC Loans Processing
Prototype Review
Development
Integration Testing / User Acceptance Testing / Training
Two options for implementing the Contracts module functionality are presented in this document:Option # 1 involves the development of a conversion process to convert open contract (Loan) definitions into PeopleSoft. After the Contract definitions are loaded, Contract Billing and Receivable history will be converted using the standard CORE conversion methodology. Option # 2 involves the agency converting open Contract definitions manually.
Milestone Schedule +/- 50%
18
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
Issues
2010 / 2011
Project Start
2837 - GPC AR/BI - Department of Mines
Fit Analysis
Develop a +-10% Plan for the implementation of GPC AR/BI Functionality for the Department of Mines.
Milestone Schedule +/-10%
19
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
2838 - GPC AR/BI - Broadband
Fit Analysis
Develop a +-10% Plan for the implementation of GPC AR/BI Functionality for the Statewide Broadband Project.
Milestone Schedule +/- 10%2010 / 2011
Project Start
Issues
20
Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
Issues
2010 / 2011
Project Start
2599 - GPC AR/BI - ODOT
Fit Analysis
Develop a +-10% Plan for the implementation of GPC AR/BI Functionality for the ODOT Phase II implementation.
Milestone Schedule +/- 10%
21
APR Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul
Milestone Task Bar
Original project completion was projected for 03/31/2011 - Tax has requested timeline be changed to 04/30/2011 due to the resources they can commit
Train SME and Agency
Newly converted Agency Go Live Support
Convert Agencies Asset Data and Validate
Technical Support as Needed
Agency Go Live 02/18/2011
Configure Agencies Asset Management Business Unit in Production
Issues
2839 - Tax Asset Management Rollout - Go-Live
Production Support
Configure and Verify Asset Conversion Data
Perform Test-Load and Validate Asset Data
Rollout of PeopleSoft Asset Management Tax Commission
Milestone Plan +/- 10%2010 2011
Prepare for Agency Kickoff
Program Status
HCM
22
CORE-1080 Higher Ed Payroll
Status: YELLOWYELLOW
Convert Higher Ed agencies from the legacy payroll system to the PeopleSoft system.
TASK Start Finish
Configuration – 95% complete 07/01/2010 11/01/2010
Conversion Scripts – 75% complete 07/01/2010 12/01/2010
Finish HR Interface Debugging/Testing 07/01/2010 12/01/2010
Complete PY Interface Coding/Debugging/Testing 09/10/2010 12/15/2010
UAT to begin with OU 01/01/2011 01/26/2011
OU go-live 01/26/2011 02/01/2011
Provided file layout to OSU, Cameron, UCO
Requires Awareness:
•Re-assessed, resources and timeline for implementing OU while maintaining the overall project schedule – OU has signed Roles and Responsibilities Document.•OU is on site weekly to assist in testing and manual creation – missing for 4 weeks of project•Payroll file from OU is 1 week late – 11/19
Key Activities
Key Overall Issues
23
CORE – 2666 Grants, Projects, Contracts with AR/Billing Monthly Extended Time & Labor
Status: GREENGREEN
Conversion / Implementation is underway and on schedule
TASK Start Finish
ODOC - User Acceptance Testing (UAT) 11/15/2010 11/18/2010
DEQ - Production 11/15/2010 12/06/2010
ODOC - Production 11/22/2010 12/13/2010
Requires Awareness:
Key Activities
Key Overall Issues
24
CORE – 2637 ELM Rollout
25
Status: GREENGREEN
Rollout of ELM to agencies to be completed in 3 groups. First Group go live date is 12/06/2010
Group A - Career Tech (800), ODOT (345), OSEEGIB (516)
Group B - OPM (548), State Dept of Health (340)
Requires Awareness:
No decision from (C), OSF (C), DCS (C), Rehab (C).
DHS demo completed 11/08/10
19 agencies plus appx. 40 shared services are in process of loading e-mails
Agencies that do not load employee e-mails in the system will have their nominating official loaded into ELM until they provide a file
Task Start End
Group A - Train agency SME’s on config and setup for testing 10/10/2010 11/30/2010
Group A - Complete UAT 11/08/2010 11/19/2010
Group A - Go Live 12/01/2010 12/06/2010
Group B - Update and Load HCM Fields in Prod 11/01/2010 11/25/2010
Group B - Train Agency SME’s 11/30/2010 12/15/2010
Group B – Go Live 01/24/2011 01/31/2011
Key Activities
Key Overall Issues
Program Status
Financials
Phase II Modules
26
CORE-2675 Data Staging Environment
Status: REDRED
Currently testing Assets. Will have to migrate to another environment to complete the testing due to data problems in FSTST2. Will work on contracts next.
TASK Start Finish ODOT Access
Phase I extracts (6) signed off by ODOT 07/02/2010
Assets (0523) 06/25/2010 12/31/2010 TBD
Billing (0512) TBD TBD
Contracts (0513) TBD TBD
Projects (0514) - will test along with roll-out TBD TBD
Sign-off on Phase II Modules TBD TBD
Requires Awareness:
• Have made some progress on testing. ODOT connectivity has been an issue. As of 11/19, connectivity has been restored.
Key Activities
Key Overall Issues
27
CORE-2676 OpenBooks Phase III
Status: GREENGREEN
Reviewed pcard and vendor screens with Brenda and Steve. Alpha list and ledger programming is complete to move data into the staging environment.
TASK Start Estimated Completion
Finish
ARRA Updates 07/01/2010 09/15/2010 08/26/2010
Expenditure & Funding (Build DIM/Create Rpts/Test) 10/01/2010 12/31/2010 Jan 2011
Pcard (Load/Build DIM/Create Rpts/Test/Automate) 06/01/2010 10/31/2010 Jan 2011
Vendor Payments (Build DIM/Create Rpts/Test) 08/01/2010 09/30/2010 Jan 2011
Payroll (Load/Build DIM/Create Rpts/Test/Automate) 08/01/2010 12/31/2010 Jan 2011
Go-Live Jan 2011
Requires Awareness:
• Need to complete development of pcard load into staging environment• Financials Analytics will not start until this is complete
Key Activities
Key Overall Issues
28
CORE-2800 PCard Transition to BOA
Status: GREENGREEN
Completed the GL Export and Voucher Build processes. Will work on the 1099 process in December. Other outstanding task is to automate the file transfers between the state and the bank.
TASK Start Finish
GL Export (0613) Segment values and combo code values 08/30/2010 09/30/2010
Voucher Build (0614) 08/30/2010 10/31/2010
1099 Processing (0xxx) 08/30/2010 12/31/2010
Requires Awareness:
• Pilot went well with a couple of DCS card holders. DCS will have all agencies transitioned by the end of December.•Danny will run the November statement (voucher build) with Lisa Martin’s assistance. Then Lisa will run the December upload with Danny’s assistance. She has already mentioned there have been process improvements built in to the new system.
Key Activities
Key Overall Issues
29
2692 – Treasury GL Implementation
Status: GREENGREEN
The Team is currently behind schedule. Additional requirements have been requested by the Client.
TASK Start Finish
Integration / User Acceptance Testing 11/04/2010 12/08/2010
System Roll out 12/11/2010 12/14/2010
Go-Live 12/31/2010 01/01/2011
Requires Awareness:
OST has requested that their Go-Live date be moved to 12/31/2010.
A Change Request is waiting to be approved for work to be done following go live.
Key Activities
Key Overall Issues
30
CORE – 2581 Time & Labor
31
Status: REDRED
This Project is to address Time & Labor functionality for bi-weekly agencies. The pilot agencies are OESC and ODOT. OESC went live on schedule May 17th. DEQ and ODOC will be going live in December.
Requires Awareness:
The three agencies listed above will have tested 90+ % of the rules. This project will be closed 12/31/2010.
Task Start End
DEQ go live 12/06/2010
ODOC go live 12/13/2010
Project complete 12/31/2010
Key Activities
Key Overall Issues
CORE – 2599 Grants, Projects, Contracts with AR/Billing
Status: REDRED
This Project is on hold.
TASK Start Finish
Functional Unit Testing – ODOT (see below)
Requires Awareness:
•ODOT cannot supply a date for conversion of legacy data.
Key Activities
Key Overall Issues
32
CORE – 2610 Inventory ODOT
Status: REDRED
On Hold.
TASK Start Finish
Integration Testing (see below)
Prepare for User Acceptance Testing
User Acceptance Testing
Go Live
Requires Awareness:
Key Activities
Key Overall Issues
33
Program Status
Within 10% of plan Within 20% of Plan Over 20% of plan
34
Project NameProject
Manager
Current Project Phase
Health Ind
Schedule
Project Phase Start Date
Project Phase Baseline
Completion
Project Phase Target
Completion
FY11 Technical Backfill Fred Cantrell Execution G 7/1/2010 6/30/2011 6/30/2011
Time and Labor Pilot Kim/Alex Execution R 3/1/2009 7/31/2010 12/31/2010P-Card - BOA Transition Lisa
McKeithanExecution G 8/18/2010 12/31/2010 12/31/2010
Grants/Projects/Contract A/R Billing/T&L Extended Commerce/DEQ
Kim/Alex Execution G 3/1/2010 12/31/2010 12/31/2010
Higher education Interface Michael Grisser
Execution Y 4/1/2010 12/31/2011 12/31/2011
Inventory ODOT Barbara Lawrence
Execution R 8/1/2009 7/31/2010 7/31/2010
Grants/Projects/Contract A/R Billing ODOT
Kim/Alex Execution R 7/1/2009 7/31/2010 7/31/2010
T&L Manager Self Service ODOT Kim/Alex Execution R 3/1/2010 7/31/2010 7/31/2010Treasury GL Implementation Alex Execution G 4/12/2010 1/31/2011 1/31/2011PeopleSoft Extract Staging Environment
Lisa McKeithan
Execution R 1/14/2010 6/18/2010 8/31/2010
Business Intelligence - FS Analytics
Lisa McKeithan
Planning R 4/1/2009 7/31/2009 12/31/2010
Program Status
Within 10% of plan Within 20% of Plan Over 20% of plan
35
Project NameProject
Manager
Current Project Phase
Health Ind
Schedule
Project Phase Start Date
Project Phase Baseline
Completion
Project Phase Target
Completion
Health Ind
BudgetBaseline Cost Target Cost Comments
OpenBooks - Phase III Lisa McKeithan
Execution G 6/1/2010 12/31/2010 12/31/2010 G $44,590.00 $44,590.00 Continuing to work on transparency initiatives. Reviewed some items with Brenda and Steve F.
data.ok.gov Lisa McKeithan
Initiation> Planning
G 8/1/2010 10/15/2011 11/30/2010 G $69,988.00 $69,988.00 In the process of finalizing the contract. Kick-off meeting is scheduled for 12/01/2010.
Grants - Provisioning Lisa McKeithan
Planning R 7/31/2008 7/15/2009 2/28/2011 G $1,961,335.00 $1,961,335.00 Project awarded. Kick-off meeting is set for 12/15. Jessica Vinson has been hired and will be starting xx/xx/xx.
Licensing Lisa McKeithan
Planning R 12/1/2008 8/15/2009 3/31/2011 G $2,245,240.00 $1,660,645.00 Finalizing contract negotiations and funding issues. Brett Johnson has been hired and will be starting xx/xx/xx.
ELM rollout Michael Grisser
Execution G 8/1/2010 7/31/2011 7/31/2011 G $118,100.00 $118,100.00 On schedule for Group A go-live, Group B is working on their tasks
Scanning and Barcoding functionality for Phase II Modules
Jerry Planning G G $50,000.00 $50,000.00 RFP being reviewed by procurement. No anticipated RFP posting date avaialble.
Loan Processing Alex Initiation> Planning
G 12/1/2010 2/28/2011 2/28/2011 G
Expense Module Kim/Alex Planning G G $729,620.00 $729,620.00 Proof of Concept complete. +- 10% Pilot presented. Waiting on approval.
Budget Pat Elwood Concept> Initiation
R 8/2/2010 9/15/2010 1/30/2011 G $500,000.00 $500,000.00 Estimate for Hyerion $3,500,000, EPM upgrade $500,000. Next steps Gartner analyst discussion, and demonstration of upgraded EPM functionality. Working to get decision for 2012 budget.
AM Rollout - Tax Commission Michael Grisser
Planning> Execution
G 10/15/2010 12/3/2010 12/3/2010 G $15,000.00 $15,000.00 Roll out Peoplesoft Asset Management to Tax Commission
Department of Mines GPC AR/BI Alex Initiation> Planning
G 1/3/2011 1/31/2011 1/31/2011 G $103,350.00 $103,350.00 Planning phase estimate.
IssuesIssue Status
1) ODOT Phase II ( Projects, Grants, AR, Billing Inventory) have not committed to a date to start integration testing.
Department of Mines and Broadband have been prioritized in front of the ODOT project. We are going to start a knowledge transfer process in January that will enable us to get to a 10% plan for this project. ODOT has still not committed to an integration start date.
2) Commerce will be going live on Phase 2 without a Grants Provisioning or Loans. They will utilize manual work around until we acquire a Grants Provisioning and/or Loans package.
Agate (Grants vendor) on site in December to review loans functionality. After this meeting we will determine if Loans will be added to PeopleSoft or if Agate will be utilized.
36
3) Assets rollout is on hold until additional resources are made available.
4) Expense module +- 10% plan is complete and we are waiting on decision to move into execution.
Set up executive review and determine when we want to proceed with expenses.