Control Plan
10-1
TheQualityImprovementModel
Develop Control Plan to
Maintain Current Process
Collect & Interpret
Data
Select Measures
IsProcessCapable
?
Improve Process
Capability
IsProcessStable
?
Investigate & Fix
Special Causes
No
Yes
No
Yes
Maintain Current Process
Purpose:•Develop a control plan to
maintain the improvements for the process
•Document control plan
Define Process
Control Plan
10-2
• Explore the steps for setting up controls for your project
• Review Control Plan elements
• Review the need for well documented control plans to “sustain the gains”
• Introduce the concept of Mistake Proofing
Objectives
Control Plan
10-3
3 to 6Critical Input Variables
Process Maps• Identify Outputs• Identify Inputs
C&E Matrix
Failure Modes and Effects Analysis
Exploratory Data Analysis (EDA)
Design of Experiments (ASM / DOE)
A Control Plan to:
“Sustain The Gains”
The Funneling Effect
Control Charts (SPC)
Control Plan
10-4
StatisticalProcessControl
Control to a Standard
EngineeringProcessControl
Three Ways to Control Key Variables in a Process
Control Plan
10-5
1) Monitor variables for out of control conditions
2) Develop alarm and recording strategy
3) Finalize process sampling plan
4) Document control plan for each key variable
Major Focus on
KPIV’S to
Minimize
Production of
Defects 5) Identify Opportunities for Mistake Proofing
Control Strategy Roadmap
Control Plan
10-6
Step 1 - Monitor Variables For Out Of Control Conditions
Key Relationships Identified After DOE Completion
Strength = 6.6444 + 1.4466 Press
Yield = - 1690 + 15.7 Temp + 41.7 Press - 0.0338 TempSqr - 0.281 PressSqr
- 0.169 TempPress
What Should We Monitor?
Control Strategy Roadmap
Control Plan
10-7Strength Seems To Be In Control
Control Strategy Roadmap Step 1 - Monitor Variables For Out Of Control Conditions
Control Plan
10-8
Looks Like a Problem With Yield – What Now ??
Control Strategy Roadmap Step 1 - Monitor Variables For Out Of Control Conditions
Control Plan
10-9
Experimental Results Indicated Yield Is A Function Of Pressure And Temperature
RememberYield = - 1690 + 15.7 Temp + 41.7 Press - 0.0338 TempSqr - 0.281 PressSqr - 0.169 TempPress
Let’s Take A Look At The KPIV’s Pressure and Temperature
Control Strategy ImplementationStep 1 - Monitor Variables For Out Of Control Conditions
Control Plan
10-10
Pressure seems to be in good control, though the pattern should be investigated.
Control Strategy Roadmap Step 1 - Monitor Variables For Out Of Control Conditions
Control Plan
10-11
Historic Mean 124Historic StdDev 2.7Big Trouble on Temperature !!
Control Strategy Roadmap Step 1 - Monitor Variables For Out Of Control Conditions
Control Plan
10-12
Step 2 - Develop Alarm and Recording Strategy
Process Alarms• Online alarms key to process waste reduction• Identify key alarm points throughout the process• Do not alarm too many points – they will be ignored• SPC - Control Charts are effective alarm mechanisms
Data Recording• Record alarms to identify patterns of out of control conditions• Online data trending assists in monitoring process shifts • Record and analyze KPIV’s to prevent waste production
Developing an Effective Process Alarm Strategy is Key To Reducing Waste and Defects
Control Strategy Roadmap
Control Plan
10-13
Step 3 - Finalize Process Sampling Plan
• Use KPOV = f(KPIV1, KPIV2, …) predictive relationships to minimize routine process sampling
• Take product samples when SPC and on-line alarms indicate out of control conditions (In theory not practice)
• Be sure sample size is adequate through use of sample size calculations
• Document sampling plan and communicate to production, lab, technical, order processing and other key groups
Control Strategy Roadmap
Control Plan
10-14
Revise QuarterlyRevise Quarterly
The Purpose Of An Effective Control Plan Is To:
• Operate processes on target with minimum variation
• Minimize process tampering (over-adjustment)
• Assure that process improvements become institutionalized (ISO 9000 can assist here)
• Provide for adequate training in all procedures
• Identify required maintenance schedules
Control Plan PurposeStep 4 - Document Control Plan For Each Key Variable…
Control Plan
10-15
Control Plan
ProceduresImprovement
Activities
Preliminary Analysis
Measurement System
Process Maps
C&E Matrix
FMEA
Measurement System Analysis %R&R, %P/T
Calibration Requirements
Sampling & Testing Plans
SPC Plans
Operating Windows
DOE's
Maintenance Schedules
Training Materials
SOP's
Customer Requirements
Short Term Capability
Long Term Capability
Noise Variable Compensation
Reaction Plans
Trouble Shooting
Aids
Initial Control Plan Assessment
These need to be updated before proceeding
Factors Impacting a Good Control Plan
Step 4 - Document Control Plan For Each Key Variable…
Control Plan
10-16
Control Plan.XLSControl Plan.XLS
Product: Date (Orig):Key Contact:Phone: Date (Rev):
OUTPUTS
Y Process Step LSL Target USL Cp Cpk Pp Ppk Measurement
Technique%Variation %R&R P/T Sample Frequency Control Method Reaction Plan
INPUTS
X Process Step LSL Target USL Cp Cpk Pp Ppk Measurement
Technique%Variation %R&R P/T Sample Frequency Control Method Reaction Plan
Control Plan Summary Sheet
Step 4 - Document Control Plan For Each Key Variable…
Control Plan
10-17
• Process map steps
• Key process output variables, targets & specs
• Key process input variables with control limits
• Important noise variables (uncontrollable inputs)
• Short and long term capability analysis results
• Designated control methods including:
Sampling & Testing Meas. Sys. Analysis Training Materials Maintenance schedules Reaction Plan and
Procedures
SPC Automated process control Checklists Mistake proofing systems Standard Operating
Procedures
Control Plan Components
Step 4 - Document Control Plan For Each Key Variable…
Control Plan
10-18
New Process
Step 1
Step 2
Step 3
Step 4
Project
• Utilize your team and / or affected individuals
• Test the procedure exactly as it is documented
• Outline a method for updating procedures
• Date your procedures
• Destroy obsolete procedures
• Have an audit plan to verify compliance
• Responsibility for documenting control plan and updates
Other Tips in Documenting Improvements
Step 4 - Document Control Plan For Each Key Variable…
Control Plan
10-19
• Directly
By Observation
Are people actually doing what the procedure says?
Are all the steps being followed?
Are people referring to the procedure?
By asking those using the procedure
Is each step in the procedure clear?
Are you having difficulty in following the procedure?
Could we improve the procedure and still get results?
• Indirectly
By Observation
When was the last time the instruction was revised?
Auditing ProceduresStep 4 - Document Control Plan For Each Key Variable…
Control Plan
10-20
Control PlanControl Plan
Scope CustomerSummary
MapsMSA FMEA’s
Capability
Critical Parameters
SOP’s
TrainingMaint.
TroubleShooting
ReactionPlans
Documentation Package
Control Plan
10-21
Explored the steps for setting up controls for your project
Reviewed Control Plan elements
Reviewed the need for well documented control plans to “sustain the gains”
Control plan derived from tools and learning's in implementing model discussed in this course
Identify person who will be accountable for control plan documentation and updates
Summary
Control Plan
10-22
1.)Your Catapult Team should complete page 13 of the blue “Catapult Process” handout.
Limit yourselves to 15 minutes for this exercise.
Exercise