Upload
cora-kelley
View
218
Download
0
Embed Size (px)
Citation preview
Contracts
•We have taken the application
•Applicant has been selected for funding
•Now let’s talk about the contract
Remember the - Policy -
120 GM, Par. 404.00 Contracts are binding between
signatories
Spells out everyone’s responsibility
Explains consequences of violations (appendix)
Remember the - Policy -
Participant agrees to carryout contract items
Government agrees to provide technical assistance and make payments covering government’s share of cost.
120 GM, Par. 404.00
Plan of Operations (to support contract)
120-GM, part 404, subpart c Plan of operations is required Type of treatment to be documented within the
plan (including O &M if needed) Plan of operations should outline a logical
sequence of work to be accomplished within a reasonable amount of time
Plan of Operations should be keyed to a map Signatures needed
General Manual (or) Programs Manual?
The General Manual is just that – general guidance
The Conservation Programs Manual 440 has specific program guidance Always look in the progam specific manual
Part 510 - Appeals and Mediation Part 513 - RC&D Part 514 - Wetlands Reserve Prpgram Part 515 - Environmental Quality Incentives Program Part 517 - Wildlife Habitat Incentives Program
The Contract comes next
120-GM, part 404, subpart eParticipants must have control of the
land for the contract periodSignatures and authorities to signResponsibilities of those signingContents of contract and layout
See 6 part folder layout in thunderbook
Always look at program specific manual -- 440
CCC-1200
•Anyone involved in the contract must sign with appropriate contract shares (shares very important)
•Signatures must be accompanied by a Power of Attorney or “Evidence of Authority”(if participant is signing for; someone other than themselves or a group)
All par
ticip
ants
•Usually NRCS signs as CCC representative, see matrix for what NRCS person signs for a particular program
•For EQIP it is the Area ASTC or designee•For CRP it is the FSA County Committee
CCC-1200
NRCS sig
natu
re
TA VS FA (Technical Assistance) (Financial Assistance)
• Financial Assistance for entire contract is set aside at the time the contract is obligated
• Technical Assistance gets planned in the contracted but does not receive funding until time to do the work
(TA must be spent the same year requested)
HELP me
understand
Technical Assistance
TA will show up in the a NRCS-LTP-1155 for planning purposes
TA will not show up in the CCC-1200Actual NTE (not to exceed) rate for TA
will be updated when time for the work to be done
Modifications --
120-GM part 404, subpart f, (404.50)
Actions requiring a modification Those that don’t need a modificationOutlines procedures for modifications
Always look at program specific manual -- 440
Spending Adjustment?
Minor changes to quantities Money is available in the contractNo formal modification procedure is
required
GM 120 404.50
Always look at program specific manual for details (Manual – 440)
Contracts are legally binding
Significant contract changes require a modification, explaination and signatures
Substituting, adding, or deleting a practice Cost overruns (not enough money budgeted in the contract) Scheduling changes Changing participant(s) or land Adding TSP $$ Repairing a failure
It’s OK to do a modification
Always look at program specific manual -- 440
Explain the Modification
BLOOPERS Adding practice to utilize extra money in the contract More money needed because practice was over built
Good Descriptions During final design Sediment basin needed a higher
ridge height, more money added to contract. Additional WASCOB needed. Not in original plan
because it was overlooked.
Make sure anyone can understand
Modifications
Modification to Contract in ProTractsUpdated 2/23/05
Field Office Steps (Part 1)1) Use “Find a Contract”2) Select Modify3) Make changes4) Save changes5) When done with modification click on “Submit For
Approval” Enter detailed reason for contract modification
Thunder book
Terminating Contracts
120-GM Part 404, subpart f (404.56)Failure to satisfactorily complete all contract
itemsLand unit is transferreddeath of the participant Foreclosure, Bankruptcy
Participant may be subject to: refund the total cost-share payments, Liquidated damages or recovery costs
Terminating Contracts
State Conservationist can waive requirement to pay money back
Termination letters come from the District Conservationist, with concurrence from Area ASTC
Always look at program specific manual -- 440
Status Reviews
120-GM part 404, subpart f, (404.51)
Must be completed
annually for the life of the
contract.