Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
CONTRACTOR REPORT
SAND89 - 7067 Unlimited Release UC-721
r~$-82~2.~2/1017~~ 5 CJ t-f I ~IIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIIII 1111111111 11111111111111111111111 8232-21/070179
1111111111111111111111 111111111 III~IIIIIIIIII~IIII/lllmllllllllllllll 00000001 ----- - -- -----
Analysis of the Fluid-Pressure Responses of the Rustler Formation at H-16 to the Construction of the Air-Intake Shaft at the Waste Isolation Pilot Plant (WIPP) Site
John D. Avis, George J. Saulnier, Jr. INTERA Inc. 6850 Austin Center Blvd., Suite 300 Austin, TX 78731
Prepared by Sandia National Laboratories Albuquerque, New Mexico 87185 and Livermore, California 94550 for the United States Department of Energy under Contract DE-AC04-76DP00789
Printed March 1990
/ v
Issued by Sandia National Laboratories, operated for the United States Department of Energy by Sandia Corporation. NOTICE: This report was prepared as an account of work sponsored by an agency of the United States Government. Neither the United States Government nor any agency thereof, nor any of their employees, nor any of their contractors, subcontractors, or their employees, makes any warranty, express or implied, or assumes any legal liability or responsibility for the accuracy, completeness, or usefulness of any information, apparatus, product, or process disclosed, or represents that its use would not infringe privately owned rights. Reference herein to any specific commercial product, process, or service by trade name, trademark, manufacturer, or otherwise, does not necessarily constitute or imply its endorsement, recommendation, or favoring by the United States Government, any agency thereof or any of their contractors or subcontractors. The views and opinions expressed herein do not necessarily state or reflect those of the United States Government, any agency thereof or any of their contractors.
Printed in the United States of America. This report has been reproduced directly from the best available copy.
Available to DOE and DOE contractors from Office of Scientific and Technical Information PO Box 62 Oak Ridge, TN 37831
Prices available from (615) 576-8401, FTS 626-8401
Available to the public from National Technical Information Service US Department of Commerce 5285 Port Royal Rd Springfield, VA 22161
NTIS price codes Printed copy: A09 Microfiche copy: AOI
SAND89-7067 Unlimited Release Printed March 1990
Distribution Category UC-721
ANALYSIS OF THE FLUID·PRESSURE RESPONSES OF THE RUSTLER FORMATION AT H·16
TO THE CONSTRUCTION OF THE AIR· INTAKE SHAFT AT THE WASTE ISOLATION PILOT PLANT (WIPP) SITE*
John D. Avis and George J. Saulnier, Jr. INTERA Inc.
6850 Austin Center Blvd., Suite 300 Austin, Texas 78731
ABSTRACT
The construction of the air-intake shaft (AIS) at the Waste Isolation Pilot Plant (WIPP) site in 1987 and 1988 initiated fluid-pressure responses which were used to estimate the hydrologic properties of the Cu1ebra Dolomite, Magenta Dolomite, and Forty-niner Members of the Rustler Formation. F1uidpressure responses were monitored with downhole transducers at observationwell H-16, about 17 meters (m) northwest of the AIS, and water-level responses were observed and measured in observation wells H-1, ERDA-9, and WIPP-2l, the closest observation wells to the AIS.
The AIS pilot hole, with a 0.25-m diameter, was drilled to a depth of 650 m and reamed to a diameter of 0.37 m. The pilot hole remained open and draining to the underground facility for about three months. The pilot hole was then upreamed (raise bored) to a 6.17-m diameter shaft from the underground facility to land surface. The pilot hole was drilled and reamed using a bentonite-mud-based brine as a drilling fluid. During the construction period, the fluid-pressure responses of the the Cu1ebra dolomite were also affected by grouting and sealing of the Rustler Formation in the waste-handling shaft (WHS), by a mu1tipad/tracer test at the H-11 hydropad in the southern WIPP site, and by water-quality sampling at WIPP-19 and H-15.
The well-test simulator GTFM was used to analyze the fluid-pressure responses of the Culebra and Magenta dolomites and the Forty-niner claystone. The AIS was modeled as a test well with a zero-wel1borepressure boundary condition. H-16 was modeled as an observation well. The pilot-hole drilling/reaming period was modeled as a we11bore-history period and was simulated separately for each unit whose fluid-pressure responses
* The work described in this report was done for Sandia National Laboratories under Contract No. 32-1025.
were analyzed. A cement-invasion skin was used in simulating the Culebra dolomite's drilling/reaming period. A mud-filter-cake skin was used to create reduced we llbore pres sures in s imula ting the pilot - ho le drilling/reaming periods of the Magenta dolomite and Forty-niner claystone.
The estimated Culebra transmissivity ranged from l. 3 x 10- 7 to 6.6 x 10- 7 m2/s. The most representative transmissivity of the Culebra between H-16 and the AlS was estimated to be 6.6 x 10- 7 m2/s. This estimate was obtained by calibrating the simulation of the Culebra's H-16 fluid-pressure response to a measurement of the flow rate from the Culebra to the AlS made 133 days after the upreaming of the Culebra. The transmissivity of the Culebra between the AlS and observation-wells H-l, ERDA-9, and WlPP-2l was estimated to range from 1 x 10- 6 m2/s to 1 x 10- 7 m2/s.
Radial formation-heterogeneity boundaries were employed to simulate the H-16 fluid-pressure responses in the Magenta dolomite and the Forty-niner claystone. The formation-heterogeneity boundary for the Magenta dolomite was estimated to be 40 m from the AlS with a near-field transmissivity of 8.0 x 10- 8 m2/s and a far-field transmissivity of 3.5 x 10- 8 m2/s. The formation-heterogeneity boundary for the Forty-niner claystone was also estimated to be 40 m from the AlS with a near-field transmissivity of 9.0 x 10- 9 m2/s and a far-field transmissivity of 1.3 x 10- 9 m2/s.
GTFM was used to simulate the flow rates of ground water draining from the Culebra dolomite, the Magenta dolomite, and the Forty-niner claystone to the open AlS. The simulated Culebra flow rate on the day of the water-ring measurement in the AlS was 0.058 L/s and is in excellent agreement with the measured rate ·of 0.056 L/s indicating an acceptable model calibration. One hundred days after upreaming, the simulated Culebra flow-rate was 0.06 L/s, the simulated Magenta flow rate was 0.007 L/s, and the simulated Fortyniner flow rate was 0.0004 L/s. The simulated Forty-niner flow-rate curve indicated a transition to the less -permeable, far- field system after 15 days.
it
1.0 INTRODUCTION
1.1 Background
1.2 Objectives
CONTENTS
1-1
1-1
1-2
2.0 MONITORING SYSTEMS .... . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. 2-1
2.1 H-16 Mu1tipacker Monitoring System ............................... 2-2
2.2 Observation Wells 2-3
3.0 AIR-INTAKE SHAFT CONSTRUCTION HISTORy ............................... 3-1
3.1 Pilot Hole . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. 3-1
3.1.1 Drilling ..................................................... 3-2
3.1.2 Reaming ...................................................... 3 - 3
3.2 Upreaming of the Air-Intake Shaft ................................ 3-4
4.0 OTHER HYDROLOGIC ACTIVITIES AFFECTING HYDROLOGIC RESPONSES .......... 4-1
4.1 Aquifer Testing .................................................. 4-1
4.2 Water-Quality Sampling ........................................... 4-2
4.3 Grouting in the Waste-Handling Shaft
5.0 INTERPRETATION METHODOLOGY
5.1 GTFM Well-Test Simulator
4-2
5-1
5-1
5.2 Drilling-Period We11bore Boundary Conditions ..................... 5-5
5.2.1 Mud-Related Uncertainties .................................... 5-8
5.2.2
5.2.3
Flow Reduction
Filter-Cake Skin
5.3 We11bore Boundary Conditions After Penetration of the
5-8
5-10
Underground Facility ............................................. 5 -12
5.4 Formation Heterogeneities ....................................... .
5.4.1 Cement·· Invas ion Skin ........................................ .
5.4.2 Radial Heterogeneity Boundaries ............................. .
5.5 Diffusivity Relationship
iii
5-12
5-12
5-13
5-14
CONTENTS (cont.)
6.0 ESTIMATION OF TRANSMISSIVITIES 6-1
6.1 Cu1ebra Dolomite ................................................. 6-2
6.1.1 Simulation Results
6.1.2 Discussion of Simulation Results ............................ .
6.2 Magenta Dolomite ................................................ .
6.2.1 Simulation Results
6.2.2 Discussion of Simulation Results ............................ .
6.3 Forty-Niner Claystone ........................................... .
6.3.1 Simulation Results
6.3.2 Discussion of Simulation Results
6-5
6-8
6-10
6-11
6-15
6-16
6-19
6-22
7.0 POTENTIAL LEAKAGE INTO THE AIR-INTAKE SHAFT ........................ 7-1
8.0 SUMMARY AND CONCLUS IONS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. 8-1
8.1 General .......................................................... 8-1
8.2 Summary of Transmissivities ........................... '" ........ 8-4
8.2.1 Cu1ebra Dolomite ............................................... 8-4
8.2.2
8.2.3
Magenta Dolomite ................................... '" ... '" ... 8-5
Forty-Niner Claystone ........................................ 8-6
8.3 Conclusions 8-7
9.0 REFERENCES ......................................................... 9-1
APPENDIX A: Specified and Simulated We11bore Pressures and Simulated and
Observed Formation Fluid Pressures for the Drilling/Reaming
Periods of the Simulations of the H-16 Fluid-Pressure Responses
of the Cu1ebra Dolomite, the Magenta Dolomite, and the Forty-
Niner Claystone .............................................. A-l
iv
FIGURES
Figure 1.1 Locations of the·Air-Intake Shaft and Other Underground
Access Shafts Relative to the WIPP-Site Observation-Well
Network ...................................................... 1-3
Figure 1.2 Schematic Illustration of the WIPP-Site Underground-Access
Shafts and the Underground Facility ......................... ,. 1-4
Figure 1.3 Generalized Stratigraphy of the Formations Encountered by the
Shafts at the WIPP Site ...................................... 1-5
Figure 2.1 Schematic Illustration of the Multipacker Completion Tool
Installed in Observation-Well H-16 ........................... 2-4
Figure 3.1 Schematic Illustration of the Time Sequence of the Various
Phases of the Construction History of the AIS ................ 3-5
Figure 3.2 Schematic Illustration of the Different Segments of the
Drilling/Reaming History of the AIS Pilot Hole ............... 3-6
Figure 5.1 Fluid-Pressure Response for the Forty-Niner Claystone at H-16
During the Drilling/Reaming Period ........................... 5-16
Figure 5.2 Fluid-Pressure Response for the Magenta Dolomite at H-16
During the Drilling/Reaming Period ........................... 5-17
Figure 5.3 Fluid-Pressure Response for the Culebra Dolomite at H-16
During the Drilling/Reaming Period ........................... 5-18
Figure 5.4 Filter-Cake-Skin Simulation Pressure at the Skin/Formation
Interface .................................................... 5-19
Figure 5.5 Filter-Cake-Skin Simulation Pressure at Radius of
Observation-Well H-16 ........................................ 5-20
Figure 6.1 Observed Fluid-Pressure Responses of the Five Members of the
Rustler Formation at Observation-Well H-16 During the
Construction of the AIS ...................................... 6-23
v
FIGURES (cont.)
Figure 6.2 Fluid-Pressure Response of the Culebra Dolomite Observed
at Observation-Well H-16 During the Construction of
the AIS ...................................................... 6-24
Figure 6.3 Fluid-Pressure Responses of the Culebra Dolomite Measured at
Observation-Wells H-l, ERDA-9, and WIPP-2l During the
Construction of the AIS
Figure 6.4 Fluid-Pressure Response of the Culebra Dolomite Observed at
Observation-Well H-16 During the Drilling/Reaming Period of
6-25
the Construction of the AIS ...................... , ........... 6-26
Figure 6.5 Simulated and Observed Fluid-Pressure Responses for the Culebra
Dolomite at H-16 Without Using a Cement-Invasion Skin ........ 6-27
Figure 6.6 Simulated and Observed Fluid-Pressure Responses for the Culebra
Dolomite at H-l, ERDA-9, and WIPP-2l Using the H-16 Best-Match
Simulation Without Using a Cement-Invasion Skin .............. 6-29
Figure 6.7 Simulated and Observed Fluid-Pressure Responses for the Culebra
Dolomite at H-16 Using a Cement-Invasion Skin ................ 6-30
Figure 6.8 Simulated and Observed Fluid-Pressure Responses for the Culebra
Dolomite at H-l, ERDA-9, and WIPP-2l Using the H-16 Best-Match
Simulation Using a Cement-Invasion Skin ...................... 6-31
Figure 6.9 Simulated and Observed Fluid-Pressure Responses for the Culebra
Dolomite at H-16Matching the Culebra-to-AIS Flow Rate Using a
Cement-Invasion Skin ......................................... 6-32
Figure 6.10 Simulated and Observed Fluid-Pressure Responses for the Culebra
Dolomite at H-l, ERDA-9, and WIPP-21 Using the H-16 Best-Match
Simulation Matching the Culebra-to-AIS Flow Rate Using a Cement-
Invasion Skin ................................................ 6-33
Figure 6.11 Simulated and Observed Fluid-Pressure Responses for the Culebra
Dolomite at H-16 Matching the H-l Fluid-Pressure Response Using
a Cement-Invasion Skin ....................................... 6-34
vi
FIGURES (cont.)
Figure 6.12 Simulated and Observed Fluid-Pressure Responses for the Cu1ebra
Dolomite at H-1, ERDA-9, and WIPP-21 Matching the H-1
Fluid-Pressure Response Using a Cement-Invasion Skin ......... 6-35
Figure 6.13 Simulated and Observed Fluid-Pressure Responses for the Culebra
Dolomite at H-16 Showing Sensitivity to the Use of a Cement-
Invasion Skin ................................................ 6-36
Figure 6.14 Post-Upreaming Simulated and Observed Flow Rates from the
Culebra Dolomite to the AIS Using Four Values of
Transmissivity ............................................... 6-37
Figure 6.15 Fluid-Pressure Response of the Magenta Dolomite Observed at
Observation-Well H-16 During the Construction of the AIS 6-38
Figure 6.16 Fluid-Pressure Response of the Magenta Dolomite Observed at
Obsexvation-Well H-16 During the Drilling/Reaming Period of the
Construction of the AIS ...................................... 6 - 39
Figure 6.17 Simulation of the Magenta Dolomite Fluid-Pressure Response at
H-16 During the Construction of the AIS Using a Homogeneous-
Formation Characterization ................................... 6-40
Figure 6.18 Simulation of the Magenta Dolomite Fluid-Pressure Response at
H-16 During the Construction of the AIS Using a Formation-
Heterogeneity Boundary ....................................... 6-41
Figure 6.19 Simulation of the Magenta Dolomite Fluid-Pressure Response at
H-16 During the Construction of the AIS Using a Formation-
Heterogeneity Boundary and Showing Sensitivity to Ti ......... 6-42
Figure 6.20 Simulation of the Magenta Dolomite Fluid-Pressure Response at
H-16 During the Construction of the AIS Using a Formation-
Heterogeneity Boundary and Showing Sensitivity to To ......... 6-43
Figure 6.21 Simulation of the Magenta Dolomite Fluid-Pressure Response at
H-16 During the Construction of the AIS Using a Formation-
Heterogeneity Boundary and Showing Sensitivity to rb ......... 6-44
Figure 6.22 Semi-log Plot of the Fluid-Pressure Response of the Magenta
Dolomite at H-16 Showing Sensitivity to Ti, To. and rb During
the Post-Reaming Draining Period ............................. 6-45
vii
FIGURES (cont.)
Figure 6.23 Simulation of the Magenta Dolomite Fluid-Pressure Response
at H-16 Using a Homogeneous-Formation Characterization and
Showing Sensitivity of Tf to Ti and To of the Best-Match
Heterogeneous Characterization ............................... 6-46
Figure 6.24 Fluid-Pressure Response of the Forty-Niner Claystone
Observed at Observation-Well H-16 During the Construction of
the AIS ...................................................... 6-47
Figure 6.25 Fluid-Pressure Response of the Forty-Niner Claystone Observed
at Observation-Well H-16 During the Drilling/Reaming Period
of the Construction of the AIS ............................... 6-48
Figure 6.26 Simulation of the Forty-Niner Claystone Fluid-Pressure Response
at H-16 During the Construction of the AIS Using a Homogeneous-
Formation Characterization ................................... 6-49
Figure 6.27 Simulation of the Forty-Niner Claystone Fluid-Pressure Response
at H-16 During the Construction of the AIS Using a Formation-
Heterogeneity Boundary ....................................... 6-50
Figure 6.28 Simulation of the Forty-Niner Claystone Fluid-Pressure Response
at H-16 During the Construction of the AIS Using a Formation-
Heterogeneity Boundary and Showing Sensitivity to Ti ......... 6-51
Figure 6.29 Simulation of the Forty-Niner Claystone Fluid-Pressure Response
at H-16 During the Construction of the AIS Using a Formation-
Heterogeneity Boundary and Showing Sensitivity to To ......... 6-52
Figure 6.30 Simulation of the Forty-Niner Claystone Fluid-Pressure Response
at H-16 During the Construction of the AIS Using a Formation-
Heterogeneity Boundary and Showing Sensitivity to rb ......... 6-53
Figure 6.31 Semi-log Plot of the Fluid-Pressure Response of the Forty-Niner
Claystone at H-16 Showing Sensitivity to Ti, To, and rb During
the Post-Reaming Draining Period ............................. 6-55
viii
FIGURES (cont.)
Figure 6.32 Simulation of the Forty-Niner Claystone Fluid-Pressure
Response at H-16 Using a Homogeneous-Formation Characterization
and Showing Sensitivity of Tf to Ti and To of the Best-Match
Heterogeneous Characterization ............................... 6-S6
Figure 7.1 Calculated Flow Rate to the AIS Versus Time Since Upreaming
for the Culebra and Magenta Dolomites and the Forty-Niner
Claystone ...................................... ,............. 7 - 3
Figure A.l Specified and Simulated Wellbore Pressures and Simulated and
Observed Formation Fluid Pressures for the Culebra Dolomite
Drilling/Reaming Period Without a Cement-Invasion Skin and
Matching H-16 Fluid-Pressure Response ........................ A-3
Figure A.2 Specified and Simulated Wellbore Pressures and Simulated and
Observed Formation Fluid Pressures for the Culebra Dolomite
Drilling/Reaming Period Using a Cement-Invasion Skin ......... A-4
Figure A.3 Specified and Simulated Wellbore Pressures and Simulated and
Observed Formation Fluid Pressures for the Culebra Dolomite
Drilling/Reaming Period With a Cement-Invasion Skin and
Matching the Culebra-to-AIS Flow Rate ........................ A-S
Figure A.4 Specified and Simulated Wellbore Pressures and Simulated and
Observed Formation Fluid Pressures for the Culebra Dolomite
Drilling/Reaming Period with a Cement-Invasion Skin and Matching
the Observation-Well Responses
Figure A.S Specified and Simulated Wellbore Pressures and Simulated and
Observed Formation Fluid Pressures for the Culebra Dolomite
Drilling/Reaming Period Without a Cement-Invasion Skin and
A-6
Using a Tf = 1.3 x 10- 7 m2/s ................................. A-7
Figure A.6 Specified and Simulated Wellbore Pressures and Simulated and
Observed Formation Fluid Pressures for the Culebra Dolomite
Drilling/Reaming Period Without a Cement-Invasion Skin and
Using a Tf = 6.6 x 10- 7 m2/s ................................. A-8
ix
FIGURES (cont.)
Figure A.7 Specified and Simulated Wellbore Pressures and Simulated and
Observed Formation Fluid Pressures for the Magenta Dolomite
Drilling/Reaming Period Using a Homogeneous-Formation
Characterization
Figure A.8 Specified and Simulated Wellbore Pressures and Simulated and
Observed Formation Fluid Pressures for the Magenta Dolomite
Drilling/Reaming Period Using a Formation-Heterogeneity
A-9
Boundary ..................................................... A-10
Figure A.9 Specified and Simulated We1lbore Pressures and Simulated and
Observed Formation Fluid Pressures for the Magenta Dolomite
Drilling/Reaming Period Using a Formation-Heterogeneity Boundary
and Ti = 2.5 x 10- 8 m2/s ..................................... A-ll
Figure A.10 Specified and Simulated Wellbore Pressures and Simulated and
Observed Formation Fluid Pressures for the Magenta Dolomite
Drilling/Reaming Period Using a Formation-Heterogeneity
Boundary and Ti = 2.5 x 10- 7 m2/s ............................ A-12
Figure A.11 Specified and Simulated Wellbore Pressures and Simulated and
Observed Formation Fluid Pressures for the Magenta Dolomite
Drilling/Reaming Period Using a Formation-Heterogeneity
Boundary and To = 1.3 x 10- 8 m2/s ............................ A-13
Figure A.12 Specified and Simulated Wellbore Pressures and Simulated and
Observed Formation Fluid Pressures for the Magenta Dolomite
Drilling/Reaming Period Using a Formation-Heterogeneity
Boundary and To = 1.3 x 10- 7 m2/s ........................... A-14
Figure A.13 Specified and Simulated Wellbore Pressures and Simulated and
Observed Formation Fluid Pressures for the Magenta Dolomite
Drilling/Reaming Period Using a Formation-Heterogeneity
Boundary and rb = 20 m ....................................... A-15
Figure A.14 Specified and Simulated Wellbore Pressures and Simulated and
Observed Formation Fluid Pressures for the Magenta Dolomite
Drilling/Reaming Period Using a Formation-Heterogeneity
Boundary and rb = 80 m ....................................... A-16
x
FIGURES (cont.)
Figure A.15 Specified and Simulated Wellbore Pressures and Simulated and
Observed Formation Fluid Pressures for the Magenta Dolomite
Drilling/Reaming Period Without a Formation-Heterogeneity
Boundary and Tf = B.O x 10-B m2/s ............................ A-17
Figure A.16 Specified and Simulated Wellbore Pressures and Simulated and
Observed Formation Fluid Pressures for the Magenta Dolomite
Drilling/Reaming Period Without a Formation-Heterogeneity
Boundary and Tf = 4.0 x 10- B m2/s ............................ A-IB
Figure A.17 Specified and Simulated Wellbore Pressures and Simulated and
Observed Formation Fluid Pressures for the Forty-Niner Claystone
Drilling/Reaming Period Using a Homogeneous-Formation
Characterization A-19
Figure A.1B Specified and Simulated Wellbore Pressures and Simulated and
Observed Formation Fluid Pressures for the Forty-Niner Claystone
Drilling/Reaming Period Using a Formation-Heterogeneity
Boundary ..................................................... A- 20
Figure A.19 Specified and Simulated Wellbore Pressures and Simulated and
Observed Formation Fluid Pressures for the Forty-Niner Claystone
Drilling/Reaming Period Using a Formation-Heterogeneity Boundary
and Ti = 3.0 x 10- 9 m2/s ..................................... A-21
Figure A.20 Specified and Simulated Wellbore Pressures and Simulated and
Observed Formation Fluid Pressures for the Forty-Niner Claystone
Drilling/Reaming Period Using a Formation-Heterogeneity Boundary
and Ti = 3.0 x 10- B m2/s ..................................... A-22
Figure A.21 Specified and Simulated Wellbore Pressures and Simulated and
Observed Formation Fluid Pressures for the Forty-Niner Claystone
Drilling/Reaming Period Using a Formation-Heterogeneity Boundary
and To = 5.0 x 10- 10 m2/s .................................... A-23
Figure A.22 Specified and Simulated Wellbore Pressures and Simulated and
Observed Formation Fluid Pressures for the Forty-Niner Claystone
Drilling/Reaming Period Using a Formation-Heterogeneity Boundary
and To = 5.0 x 10- 9 m2/s ..................................... A-24
xi
FIGURES (cont.)
Figure A.23 Specified and Simulated Wellbore Pressures and Simulated and
Observed Formation Fluid Pressures for the Forty-Niner Claystone
Drilling/Reaming Period Using a Formation-Heterogeneity Boundary
and rb = 20 m A-25
Figure A.24 Specified and Simulated Wellbore Pressures and Simulated and
Observed Formation Fluid Pressures for the Forty-Niner Claystone
Drilling/Reaming Period Using a Formation-Heterogeneity Boundary
and ~ = 80 m A-26
Figure A.25 Specified and Simulated Wellbore Pressures and Simulated and
Observed Formation Fluid Pressures for the Forty-Niner Claystone
Drilling/Reaming Period Without a Formation-Heterogeneity Boundary
and Tf = 9.0 x 10- 9 m2/s ..................................... A-27
Figure A.26 Specified and Simulated Wellbore Pressures and Simulated and
Observed Formation Fluid Pressures for the Forty-Niner Claystone
Drilling/Reaming Period Without a Formation-Heterogeneity Boundary
and Tf = 1. 5 x 10- 9 m2/s ..................................... A-28
xii
Table 1.1
Table 5.1
Table 5.2
Table 5.3
Table 6.1
Table 6.2
Table 6.3
Table 7.1
Table 8.1
Table 8.2
TABLES
Nomerlclature and Abbreviations for Parameters and Terms Used
in the Text and on Figures and Tables ........................ 1-6
Depths and Thicknesses of the Rustler Units Analyzed
at H-16 ...................................................... 5-21
Calculated Rustler-Unit Mud Overpressures for Simulation of
the Drilling Periods of the AIS Pilot Hole ................... 5-22
Parameters for Simulations Including Filter-Cake Skin ........ 5-23
Values and Durations of Wellbore Pressures Used for Fixed
Pressure Wellbore Boundary Conditions During Simulation of
the Culebra Dolomite Drilling/Reaming Period ................. 6-57
Values and Durations of Wellbore Pressures Used for Fixed-
Pressure Wellbore Boundary Conditions During Simulation of the
Magenta Dolomite Drilling/Reaming Period ..................... 6-58
Values and Durations of Wellbore Pressures Used for Fixed-
Pressure Wellbore Boundary Conditions During Simulation of
the Forty-Niner Claystone Drilling/Reaming Period ............ 6-60
Calculated Flow Rates from the Units of the Rustler Formation
to the AIS on 1987 Calendar Day 667 .......................... 7-4
Summary of the Transmissivities Determined from the Analysis
of the Fluid-Pressure Responses of the Culebra Dolomite,
Magenta Dolomite, and the Forty-Niner Claystone .............. 8-8
Calculated Transmissivities for a Range of Storativities Using
the Diffusivities from the Results of the Analyses Presented
in this Report ............................................... 8 - 9
xiii
1.0 INTRODUCTION
1.1 Background
The decision to construct a fourth underground-access shaft, the air
intake shaft (AIS), at the Waste Isolation Pilot Plant (WIPP) site
(Figures 1.1 and 1.2) provided a unique opportunity to observe closely
the effect of a large point-discharge feature on the hydrology of the
five members of the Rustler Formation near the center of the WIPP site.
Figure 1.3 shows the generalized stratigraphy of the geologic units
encountered by the AIS and the other WIPP-site shafts. The hydrogeologic
influences of the other three shafts at the center of the WIPP site, the
waste-handling shaft (WHS) , the construction and salt-handling shaft
(C&SH), and the exhaust shaft (EXS) , have been analyzed in earlier
reports (Stevens and Beyeler, 1985; Haug and others, 1987; and LaVenue
and others, 1988). However, because of the limited data base available
for those reports the Rustle~' s hydrologic properties were determined
wi th a moderate degree of uncertainty. Observation-well H-16
(Figure 1.1) was drilled four months before the AIS pilot hole and is
located 16.97 meters (m) northwest of the AIS. H-lQ was equipped with a
multipacker completion tool with downhole pressure transducers to monitor
the formation-pressure changes in the five members of the Rustler
Formation during the drilling and upreaming (raise boring) of the AIS.
The combination of detailed fluid-pressure data from H-16, water-level
measurements at 3 of the Culebra dolomite observation wells near the
center of the WIPP site, and the construction history of the AIS and its
pilot hole provided an ideal setting to obtain estimates of the
transmissivi ty and formation pressure of the members of the Rustler
Formation.
1-1
1.2 Objectives
The fluid-pressure and water-level responses to construction of the AIS
were analyzed with the well-test simulator GTFM (Pickens and others,
1987). Because the source of the pressure changes, the AIS pilot hole
and shaft, was an uncontrolled hydrologic drain on the affected units,
the observation wells' responses were simulated using a fixed-pressure
boundary condition at the AIS. The drilling period was essentially a
series of constant-pressure inj ections to the Rustler and the draining
periods were atmospheric-pressure discharge periods with no control on
the quantity of discharge and no means of measuring the discharge during
most of the open period. The fixed-pressure boundary condition at the
point of discharge meant that the simulation of the effects of the
shaft's construction was governed by the diffusivity relationship in
which transmissivity and storativity are interrelated, as discussed in
detail in Section 5.0, thus preventing completely independent estimates
of these hydrologic parameters. Table 1.1 presents the nomenclature and
abbreviations used throughout this report and on figures and tables.
The objectives of the analysis of the effects of the construction of the
AIS on the fluid pressure of the Rustler Formation were to:
o estimate the transmissivity of the members of the Rustler Formation
from H-16 and observation-well responses to the construction of the
AIS; and
o estimate the potential leakage rate of ground water into the AIS under
the observed open-hole conditions.
1-2
~~ z z 55 Uu
~ is 8.J
0302,° L--'N-"E,-,:W;;=M'O'E~X",IC",O'---->.--'-' _____ -LL-1
TEXAS f---,-L~-I'9 mi.
~ 1~ ,'5 km.
WP-25 0
WP-26 0
OWP-29
UNDERGROUND SHAFTS A T CENTER OF WIPP SITE
Co,,'ructlon ood -25m r~p-21 H-16 16 97m SoIt-H(c~~5 ShoH
O,J_----\:)--1905m-r
AIr-Intake Shaft
.... 240m
Erllaust Shaft (EXS)
OWP-28
H-6
O'M'-JO
OWP-lJ
O'M'-12
OAEC-7
H-5(
H-180 01'01"-18
~~~~-19 ~-21
r----- WIPP-Site Boundary
OP-14 H-20 OERDA-90 H-15
H-1 OH-3
OH-14 000E-1
o D- 268 <L-P_--C1:::.S--,.,c:-;--,-----0-H---1-1---.J uH-4
°CB-1 OP-17 OH-17
OH-12
OH-7
OP-18
o H-10
(Al5) wo"._1~51~mr-Handling
Shoft o ERDA-10
t (VoH5) 122m
-395m
H-l
0---155m-
Drown by ABW
Checked by G.S.
Revisions
H09700R876
h (ROA-9
Dote
Date
Date
-15m
1/15/90
1/15/90
1/15/90
I ~t1L1\ Technologies
N
I OH-9
o ENGLE
8 Km
0r:::;;_~~_1"2~=-;;;.!J~""""I,,-=:::35 mi. A-o 2 4
SCALE
6 OH-8
Locations of the Air-Intake Shaft and Other Underground-Access Shafts Relative to the
WIPP-Site Observation-Well Network
Figure 1.1
1-3
Drown by ABW
Checked by G.S.
Revisions G.S.
H09700R876
Air-Intake Shaft
C & SH
C & SH Shaft
(Depth - 658 mol
Dote 1/12/89
Dote 1/12/89
Dote 6/6189
1/4/89
I NTER~ Technologies
All Shafts Li ned Above Keyways
Exhaust Shaft 3
Ilr~-i!\-o~.jjj..,, ___ Unlined Below Keys
NOT TO SCALE
NOTES:
1. Previously known as exploratory shaft.
2. Previously known as ventilation shaft.
3. Exhaust shaft not part of SPDV.
Schematic Illustration of the WIPP-Site Underground-Access Shafts and the
Underground Facility
Figure 1.2
1-4
GENERALIZED STRATIGRAPHY OF WIPP-SITE SHAFTS
DEPTH DUNE SAND
(METERS)- -AND CALICHE -GATUNA AND - .-
- - DOCKUM - -. - -- . -- -- .-- -- .-- -- .-- -
- --- -- --- -
- --- -- -- -- --
164 - _. -FORTY-NINER
182 - - MAGENTA
~~: = ~~ = TAMARISK 222 - - CULEBRA
r+-:-+-:-+-:-+-:-+- UNNAMED LOWER
w ~(/)
«0 ~w
>-m Wo :s:w wo:: o
Z 0::0 ~i= f-« (/):2 ::>0:: 0::0
257 - """"==='==9 _.....:M'-=-'E=M'-=-'B""E=R-'---____ .---.
1
LL
409 -
526 -
VACA TRIST[ SANDSTONE
MB 126
WIPP FACILITY
0::0:: WW a... CD 0... 2 ::>w
2
f-O:: f-W ::>m Z2 uw 22
0::0:: WW :;s:CD 0 2 ...Jw
2
z 0 -f-« :2 0:: 0 LL
0 0 « -.J « (/)
l 655 - '---------' - LEVEL _____ --L-~
Drawn by ABW Dote 1/24/89
D r=-=-=l. l::....=....::: • D ., ~ ~
Q + + + +
+ •
EXPLANA TION
SAND AND SANDSTONE
MUDSTONE AND SILTSTONE
ANHYDRITE/GYPSUM
HALITE
DOLOMITE
- -.f.--+-+
+-+- .. +-+-+
CLAYSTONE
HALITIC CLAYSTONE
GYPSUM/HALITE/POL YHALITE
1. All Rocks Below Dockum are Permian in Age.
2. All Levels are Measured from Collar at 1039 Meters amsl.
3. MB = Marker Bed.
Modified from Bechtel National, Inc. (1985)
Checked by G.S. Revisions G.S.
Dote 1/25/89
Dote 6/6189 Generalized Stratigraphy of the Formations
Encountered by the Shafts at the WIPP Site H09700R876 1/25/89
I f'frtIL,\ Technologies Figure 1.3
1-5
AIS C&SH EXS
- Air-Intake Shaft - Construction and Salt-Handling Shaft - Exhaust Shaft
WHS - Waste-Handling Shaft D - Diffusivity ft - Foot Ks - Skin Hydraulic Conductivity L - Liter m - Meter MPa - Megapascal Ps - Reduced Wellbore Pressure psi = Pounds per square inch ~ - Radius to Formation Boundary S ~ Storativity s = Second T - Transmissivity Tf - Formation Transmissivity Ti - Formation Transmissivity Inside Radial
Heterogeneity Boundary To - Formation Transmissivity Outside Radial
Heterogeneity Boundary X - Observed Data
Date Drawn by ~----~--------~~----------~Nomenclature and Abbreviations for Parameters
Checked by Date ~--------------~~----------~and Terms Used in the Text and on Figures
Revisions Date
I N"rtIL'\ Technologies Table 1.1 LlVJJVVI:\..U V
1-6
2.0 MONITORING SYSTEMS
The drilling of the AIS pilot hole and the upreaming of the AIS caused
fluid-pressure changes in the members of the Rustler Formation. The most
important observation well was H-16 which was drilled specifically to
observe and monitor the effects of the construction of the AIS on the
permeable members of the Rustler.
Water-level responses were also observed in other Culebra dolomite
observation wells around the center of the WIPP site. The closest Magenta
dolomite observation wells, at H-l and at the H-2 hydropad, did not appear
to respond to the AIS construction, apparently because of the lower
permeability of the Magenta relative to the Culebra.
Pressure transducers in the other shafts at the WIPP site were potentially
capable of monitoring the AIS construction. However, the transducers in
the WHS and the C&SH shaft were out of service during this period due to
the extensive grouting operations in the WHS and due to a complete overhaul
of the instrumentation in the C&SH shaft because of salt corrosion and
haulage damage. The transducers in the EXS were potentially able to
monitor the AIS construction. However, because the WHS lies between the
AIS and the EXS, the EXS fluid-pressure responses during the important
early period of the AIS construction were dominated by the grouting
activity in the WHS. Fluid-pressure data from the EXS were therefore not
analyzed.
The following sections describe the H-16 monitoring system and the
observation wells. Note that in this discussion and throughout this
report, especially on plots and tables, time will be referenced by the date
of occurrence and by the 1987 Calendar Day or the number of days counted
consecutively from January 1, 1987.
2-1
2.1 H-16 Mu1tipacker Monitorin~ System
Borehole H-16 was drilled in July and August 1987. The center of the
borehole was located 16.97 m northwest of the center of the AIS and was
installed to monitor the fluid pressures in the five members of the
Rustler Formation during the construction of the AIS. As described in
Stensrud and others (1988a), H-16 was drilled and cased to the lower
Dewey Lake Red Beds at a depth of 142.95 m below ground surface (BGS) ,
then extended open hole to a depth of 259.35 m BGS, about 2.74 m into the
upper Salado Formation. Each of the five members of the Rustler was
hydraulically tested during the drilling of H-16. The data collected
during the testing at H-16 are presented in Stensrud and others (1988a)
and interpretations of those tests are found in Beauheim (1987a).
In late August 1987, well H-16 was equipped with a multipacker completion
tool manufactured by Baker Service Tools (BST) , Houston, Texas (Figure
2.1). The device includes 5 fluid-inflatable packers which isolate the 5
members of the Rustler Formation, and 5 downhole pressure transducers
(see Stensrud and others, 1988a) which monitor the fluid pressures in
those isolated intervals. The data collected by the transducers are
transmitted by a data-link cable to a surface recorder and stored on
magnetic tape. The original data are recorded in pounds per square inch
(psi) and are adjusted to the temperature at the depths of the
transducers using correction curves supplied by the manufacturer. The
data and the correction curves are periodically published in hydrologic
data reports (Stensrud and others, 1988a, 1988b, 1989). Note that the
transducers do not share a common reference elevation datum.
2-2
2.2 Observation Wells
Hydrologic responses to the construction of the AIS were observed in
observation wells near the center of the WIPP site. The data and data
collection methods for these and other WIPP-site observation wells are
presented in Stensrud and others (1988a, 1988b, 1989). The data show
that only the Culebra observation wells within 1.25 km of the AIS, H-l,
H-2a, H-2b2, ERDA-9, WIPP-18, WIPP-19, WIPP-2l, and WIPP-22, showed
significant water-level responses to the presence of the AIS. Because
other hydrologically significant activities were concurrent with the
construction of the AIS, as described in Section 4.0, data from some of
these observation wells could not be analyzed.
Observation wells H-l, ERDA- 9, and WIPP- 21 were sufficiently isolated
from other hydrologic influences to provide data which could be used to
analyze the effect of the AIS on the Culebra dolomite. However, the
early-time responses in these wells could not be used because they were
affected by grouting operations in the WHS and only the post
drilling/reaming and post-upreaming periods were used for analysis. The
data collected at H-l, ERDA-9, and WIPP-2l are water levels measured with
electric water-level sounders. These data were converted to pressure in
MPa at the center of the Culebra intervals using the best available data
for borehole-fluid density in these wells as presented in Cauffman and
others (1990, Appendix F).
2-3
Inflation ~~~~~~~rliI
,---=--,-_1_03~8.39 m amsl"""\ Ibro39.00 m
I Packer 1 \ System F ~~~~~~~~:D~A:S~i~n~B~L~D~G~.~B~~49~
__ L=-a=-n,-,d'---..::S=-ur=-f=-ac::e:...::E:::le:.:v~a~tio::::n::.;I;0~3~9~.2~5~m~a~m~s~I __ ~ III 1 68 WlPP Site -, .~m .---2.43 x 2.43 m ellar 5.49 m HOLOCENE DEPOSITS -,. ,
Drawn by S, c. Checked by G.S.
Revisions ABW
H09700R876
11.27 m GATUNA FORMATION \j i . \ 1225-inch(.31 m} Hole 15 DCCKUM GROUP {" . \ 10.75-inch(.27 m) 40 Ib/ft
.84 m I: Conductor Casing
t " 10.97 m
DEWEY LAKE RED BEDS
F,~.f---- 9.625-inch(.24 m) Reamed Borehole
1I11tl'-ttlHH'I--- Packer-Inflation lines
!-+---7-inch(.18 m) 23 Ib/ft Well Casing
HiHt+I---- 2.375-inch(.06 m} Tubing
IlIlf .. :;J.--- Transducer Cables
IIlIr"'---142.95 m 162.12 m ------,---------1
oc ~~M!~~~~16~3t·5~I~m~~ 1i5 ANHYDRITE/ 164.76 mPacker #5 :::; GYPSUM Transducer #5 ~ 171.48 m _______ ~IIII SIN 2472 oc 167.06 m ~ CLA Y(STONE)
6::1 174.89 m --:~;;~-1~~I~~~~~t2:: ~ 175.42 m
ANHYDRITE/ 176.68 m Packer #4 o GYPSUM Transducer #4 u.. SIN 2475
-179.89 m MAGENTA 178.98 m
DOLOMITE T 187.63 m _-=M~E~M~BE~R~_--1111
~~ ~~~~~~~19~3f·6~7~m2 ~ Iff 194.92 m Packer #3
::E w ::E
'" III ;;: ..:
ANHYDRITE/ GYPSUM
~ 206.50 m -------11
"iII'-------- Transducer #3 SIN 2474 197.24 m
~ CLAYSTONE
C1oystoo.. ~~1~2~IO~.~3~4~m~:~~~~:~~~~l~~~~~-;; Siltstoo., ____ 213.24 m GYPSUM 210.59 m $ondstone 211.84 m Packer #2
214.12 m CUlEBRA Transducer #2
220.80 m DOLOMITE MEMBER SIN 2105
T CL STO 214.15 m
223.50 m =~~A~Y~~N=E~==~~~~~~~~~~~ '" 223.74 m 1i5 226.28 m GYPSUM 224.99 mPacker #1 ~ f--l-~=-:~;--:--:---- Transducer #1 ::E HALlTIC ~ 800 psi SIN 2174 '" CLAYSTONE/ I"-. Shear-Pin Plug 227.29 m
\!:' HALITE/GYPSUM I "227.84 m
'3 237.04 m ----------l o w :::; ~ SILTSTONE/ z CLAYSTONE ::>
1 255.76 m 256.49 m -'-____ -'G"""~' ... ""m!L~~oI1!!!!'t~.IP.C!:oI!!!lM<i!'!"'!!.':a~._l
1--6.125-inch('16 m) Open Hole
SALADO FORMATION '-----'---- Total Depth 259.35 m
All Depths in Meters Below Ground Surface Not To Scale
Date 1/4/89
Date 1/11/89 Schematic Illustration of the Multipacker Completion
Tool Installed in Observation-Well H-16 Date 6/23/89
(after Beauheim, 1987a) 1/4/89
I N'rtILI\ Technologies Figure 2.1
2-4
3.0 AIR-INTAKE SHAFT CONSTRUCTION HISTORY
Construction of the AIS consisted of drilling and reaming a pilot hole and
upreaming the shaft. The 0.25-m pilot hole was drilled using a bentonite
mud-based brine drilling fluid through the Dewey Lake Red Beds and the
Rustler and Salado Formations to a depth of 635 m, immediately above the
WIPP-site underground facility. With the pilot hole remaining full of
drilling fluid, the initial pilot hole was reamed to a 0.37-m diameter to
the same depth. The reamed 0.37-m pilot hole was then extended into the
underground facility, a depth of 655 m, and drained of drilling fluid. The
pilot hole provided a guide for the introduction of 0.35-m drill pipe which
controlled and raised a 6.l7-m diameter upreaming bit which raise bored the
AIS from the underground facility to ground surface. No drilling fluid was
used during upreaming. Following geologic mapping, the shaft was finished
with a concrete liner to a final inside diameter of 5.9 m.
The following sections present descriptions of each of the phases of the
AIS construction history, highlighting activities of hydrologic interest
which affected the fluid-pressure responses of the members of the Rustler
Formation analyzed in Section 6.0 (Figure 3.1). Construction information
was developed from the daily drilling reports (DDR) of CAP-STAR Drilling,
Inc. (the drilling contractor), discussions with Dana Downes of Frontier
Kemper, Inc. (the supervisor of construction operations), and Table 1.4,
Part D of Stensrud and others (1988b).
3.1 Pilot Hole
The following subsections describe the principal events of the
drilling/reaming history of the AIS pilot hole with particular attention
to events affecting the formation fluid pressures of the members of the
Rustler Formation. Figure 3.2 schematically illustrates the events of
the drilling/reaming period.
3-1
3.1.1 Drilling
The drilling of the 0.25 -m pilot hole began on December 5, 1987
(Calendar Day 339) using conventional rotary drilling methods and a
bentonite-based brine drilling mud as a circulating medium. The actual
mud weight was not recorded in the DDR on a daily basis. However, on
January 13, 1988 (Calendar Day 378) the DDR indicated that the drilling
fluid weighed 9.8 pounds per gallon (1174.44 kilograms/cubic meter
[kg/m3]) with a viscosity of 28 centipoises and a pH of 8. Subsequent
discussions with Frontier-Kemper and CAP-STAR have not uncovered any
additional information concerning the drilling fluid's parameters.
Therefore, the January 13, 1988, mud parameters were assumed to be in
effect throughout the drilling period.
Drilling of the initial stages of the pilot hole proceeded slowly due
to administrative delays concerning the safety of the drilling location
and technical delays caused by caving in the Gatufta Formation.
Drilling penetrated the Forty-niner and Magenta Members of the Rustler
on December 11 and 12, 1987 (Calendar Days 345 and 346). On December
12 (Calendar Day 346), after finding the borehole was slightly
deviated, CAP-STAR began reaming the upper part of the borehole to a
0.37-m diameter in an attempt to correct the deviation. From December
12 to 20 (Calendar Day 354) the pilot hole was reamed to a depth of
92.97 m BGS. Operations were halted until December 26 (Calendar Day
360) when the borehole was cemented from 190 to 130 m BGS in a further
attempt to correct borehole deviation. The borehole was flushed and
cleaned of drill cuttings and the drilling fluid was circulated until
preparations for cementing were completed.
3-2
The pilot hole was reentered on December 27 (Calendar Day 361) and the
cement and formations below 130 m BGS were redrilled in conformance
with deviation standards to a 0.25-m diameter. The Forty-niner and
Magenta Members were redrilled on December 29 and 30 (Calendar Days 363
and 364), respectively. The Culebra dolomite was penetrated on
January I, 1988 (Calendar Day 366). Drilling continued to 262 m BGS to
the upper part of the Salado Formation on January 3 (Calendar Day 368),
when excessive borehole deviation was again detected. The borehole was
cemented from 262 to 195 m BGS on January 6 (Calendar Day 371). On
January 7 (Calendar Day 372), the cemented interval was redrilled at a
0.25-m diameter to try to correct the deviation. The Culebra was
redrilled on January 8 and 9 (Calendar Days 373 and 374), and drilling
continued through the remainder of the Rustler and into the Salado.
Drilling to the total depth of the O. 25-m pilot hole at 635 m BGS
continued until January 30 (Calendar Day 395) with a short interruption
on January 16 and 17 (Calendar Days 381 and 382) when the Salado
Formation was cemented from 367 to 305 m BGS to correct excessive
borehole deviation.
3.1.2 Reaming
The 0.25-m borehole was reamed to a 0.37-m diameter from 91.5 to 655 m
BGS from January 31 to February 7, 1988 (Calendar Days 396 to 403) with
a full column of brine-based drilling mUd. The pilot hole penetrated
the WIPP underground facility on Calendar Day 403. The Forty-niner and
Magenta were reamed on February 1 (Calendar Day 397) and the Culebra
dolomite was reamed on February 2 (Calendar Day 398). The drilling
fluid was pumped from the pilot hole just before penetration of the
underground facility. The pilot hole remained open and the Culebra and
Magenta were draining to the pilot hole and later to the upreamed shaft
from 2330 hours on February 7 (Calendar Day 403) until the time of this
report.
3-3
3.2 Upreaming of the Air-Intake Shaft
Upreaming of the AIS began on May 1, 1988 (Calendar Day 487) after
2-1/2 months of preparatory work on the foundation for the AIS collar and
installation of the drill pipe for the 6.17 -m diameter upreaming tool.
Before installing the drill pipe, a 13-7/8-inch (0.35 m) drill bit was
used to clear hole obstructions at 80 m and 226 m BGS. The obstruction
at the 226-m depth, 5.2 m below the Cu1ebra, was cleared on April 7, 1988
(Calendar Day 463) using compressed air as a circulation medium. The
cleaning operation caused a slight offset in the H-16 fluid-pressure data
for the Cu1ebra but did not disturb the overall pressure trend.
The members of the Rustler Formation isolated in H-16 were encountered by
the upreaming tool from June 16 to 28 (Calendar Days 533 to 545).
Specifically, the Cu1ebra was upreamed on June 17 (Calendar Day 534), the
Magenta on June 23 (Calendar Day 540), and the Forty-niner claystone on
June 26 (Calendar Day 543). After upreaming of the Rustler, upreaming
slowed considerably in the Dewey Lake Red Beds. Due to construction
delays, the AIS upreaming was not completed until August 24, 1988
(Calendar Day 602). Throughout and after the upreaming period, the
Rustler members remained open and draining to the AIS.
3-4
DRILLING / REAMING PERIOD
Penetration of WIPP-Site Underground Facility 649 meters Below Ground Surface
~ Dec. 1 , 1987 Dec. 5, 1987 Jan. 1 , 1988 Feb. 1, 1988 Feb. 7, 1988
I ~I Drilling O.25-m-diameter Pilot Hole Hole reamed to 628.5 m from Ground Surface to O.37-m-diameter
r Forty-Niner Penetration 12/11/87 First M, Magenta Penetration 12/12/87
C, Culebra Penetration 12/31/87
OPEN-BOREHOLE PERIOD
Feb. 8, 1988 Mar. 1 , 1988 April 1, 1988 May 1, 1988
I I I
I Construction of Foundation for Upreaming Rig
UPREAMING PERIOD
August 23, May 1 , 1988 June 1 , 1988 July 1 , 1988 August 1, 1988 1988
I I I I I C M F
Upreaming Pilot Hole to 6.17-m Diameter from Underground Facility to Ground Surface
C, Upreaming Culebra June 16, 1988 M, Upreaming Magenta June 21, 1988 F, Upreaming Forty-Niner June 25, 1988
Drawn by ABW Date 2/9/89
Checked by G. S. Date 2/9/89 Schematic Illustration of the Time Sequence of the Revisions Date Various Phases of the Construction History
H09700R876 2/9/89 of the AIS
I NrtIl.,\ Technologies Figure 3.1
3-5
GROUND SURFACE 1039.25 masl
~ 83m w
DEWEY LAKE u « ......
RED BEDS LL
Cement '-.... ~:~:~ cr:: ::> .. ' iJ)
F>' .: 0 • ... 0· z .,' . ::> o· '0 ~ 164 0 ' .. . o· FORTY-NINER MEMBER ....... 182
cr:: .................. :: .. : :, .. W;~:, ~19:2~':~ ::::::.::::.:,:: MAGENTA DOLOMITt"··'::::' z 0
-~"j96m·:·· 189 cr::o ~ w- 3:
I I .... ' v Cement TAMARISK MEMBER -,f-
0 f-« ... 215 iJ):2 -' . ........ .......... , .. ... , .... :I:lRA 0 MITt: . ........... " . w ',0' 222 ::>cr:: CD -.' . UNNAMED LOWER cr::O
"" r--- .. i..J... iJ) ~ ""
.. MEMBER cr:: I - ~L259m- 259 w u 1O f-
W
"" I I
w 0 :2
U w
302m ~ 0
"" L.() ~ . '. SALADO I
z z .~.! v Cement f-« « FORMATION
0. ....., ....., : .. <10, W
.. ·0 t 0 f ~" .... ,. 367m
L.() 1O ~ ~
z z « «
FM FMC C ....., .....,
FMC PENETRADON OF UNDERGROUND FAOUTY
U CEMENT I I I CEMENT I CE~ENT II I DRILLING j REAMING 1'( DRILLlNCl 1 DRILLING 1 I REAMING RUSTLER UNITS DRAINING I j t6 ,It 12 2U7 2
1910 ~1 J J U ,~ t~ it \ 7 218
I DECEMBER 1987 ·1· JANUARY 1988 ·1· FEBRUARY 1988 ·1 NOTE: F M C Indicate days when drilling
or reaming penetrated the Forty-Niner (F), Magenta (M), or Culebro (C).
INTtlt.'\ Schematic Illustration of the Different Segments of the Figure 3.2 Technologies Drilling/Reaming History of the AIS Pilot Hole
H09700R876 ABW 3/2/89
4.0 OTHER HYDROLOGIC ACTIVITIES AFFECTING HYDROLOGIC RESPONSES
Water-level and fluid-pressure responses from over 50 observation wells and
shafts in the WIPP- si te observation-well network were recorded from
December 1987 to December 1988. During that time, hydrologically related
activities other than the AIS construction affected the members of the
Rustler Formation. A compilation of all such activities can be found in
Stensrud and others (1988a, 1988b, and 1989). The following sections
describe those activities that may have affected the area near the center
of the WIPP site during construction of the AIS.
4.1 Aquifer Testing
The major aquifer test conducted during the construction of the AIS was
the H-l1 multipad/tracer test (Stensrud and others, 1989). During this
test, well H-llbl was pumped at a relatively constant rate of 0.38 liters
per second (Lis) from May 5 to July 7, 1988 (Calendar Days 491 to 554).
Water-level responses to the H-ll mu1tipad/tracer test were recorded at
10 observation wells in addition to the fluid-pressure responses recorded
at H-llb2, H-llb3, and H-llb4 at the H-ll hydropad. H-l, ERDA-9, and
wells at the H-2 hydropad potentially could have responded to the H-ll
mu1tipad/tracer test, but the presence of the AIS dominated water-level
responses at these locations during the test.
Well development and a 3-day pumping test of the Culebra dolomite were
performed at H-18, located about 1.5 km northwest of the AIS, from
February 26 to March 14, 1988 (Calendar Days 422 to 439). The H-18
pumping test was followed by three weeks of pumping for water-quality
sampling as described in Section 4.2. The pumping at H-18 was observed
at DOE-2, WIPP-13, P-14, and the H-6 hydropad. No evidence of the H-18
pumping was detected at H-2, H-1, ERDA-9, and WIPP-21.
4-1
4.2 Water-Ouality Sampling
Water-quality sampling of the Culebra dolomite as part of the WIPP site's
Water Quality Sampling Program (Colton and Morse, 1985) was conducted at
WIPP-19, H-18, H-14, H-15, and DOE-2 during the period analyzed for this
report. The wells were pumped with an air-lift pump at pumping rates of
0.003 to 0.03 Lis. Responses to these pumping episodes were measured in
some nearby wells, but the influence of these exercises was limited.
The water-quality pumping at WIPP-19 from January 26 to February 12, 1988
(Calendar Days 391 to 408) was observed distinctly at WIPP-18 and
WIPP-22, but its effects could not be distinguished from drawdown induced
by AIS construction at other nearby wells such as WIPP-2l (Stensrud and
others, 1988b).
Water-quality sampling at H-15 was performed on January 7 to 13 and
October 25 to November 7, 1988. The January sampling was not observed at
nearby wells due to the dominating influence of activities in the AIS.
However, the August sampling exercise appears to have affected water
levels in ERDA-9 and H-l (see Section 6.0).
4.3 Grouting in the Waste-Handling Shaft
Grouting in the WIPP-site shafts affected the fluid pressure of the
Culebra dolomite as noted during pressure grouting in the exhaust shaft
from July through December 1986. Examination of grouting reports
indicated that drilling the grout- inj ection boreholes, which included
opening the shaft- instrumentation sleeves (Bechtel, 1985; Saulnier,
1987a) to prevent their being sealed by the grout, caused fluid-pressure
decreases in the more permeable members of the Rustler such as the
Culebra. These pressure decreases were observed at nearby observation
well WIPP-2l and in the EXS (Stensrud and others, 1987; Saulnier and
others, 1987).
4-2
The WHS was constructed as a 5.79-m-diameter shaft between November 1983
and August 1984 (Bechtel, 1985). Special grouting methods were employed
to seal the Culebra and Magenta dolomites. However, continued seepage
was observed from the Culebra as well as from the other Rustler units
(Saulnier, 1987a; Deshler and McKinney, 1988). In October 1987, an
extensive grouting and sealing program was initiated to stop leakage from
all members of the Rustler Formation in the WHS. The grouting procedures
involved drilling annular rings of 16 boreholes, 0.05 m in diameter,
through the WHS liner from 1.5 to 3 m apart vertically, and 0.6 minto
the formations in contact with the liner. Class C cement followed by a
chemical grout was then injected through these boreholes at pressures as
high as 4.8 MPa to seal the liner-to-formation contact, any shrinkage
cracks that may have developed in the liner itself, and to seal any
incompletely sealed construction joints (Deshler and McKinney, 1988).
Drilling and grouting of the Magenta, Culebra, and Forty-niner Members of
the Rustler Formation occurred according to the following schedule:
UNIT DRILLING GROUTING GROUT DATE (Calendar DATE (Calendar
Day) Day)
Culebra 12/15/87(349) 12/18/87(352) Cement
12/19/87(353) 02/07/88(403) Chemical
02/13/88(409) 02/14/88(410) Chemical
Magenta 12/29/87(363) 01/09/88(374) 01/21/88(386)
01/22/88(387) Cement 01/24/88(389) Cement
01/26/88(391) 01/27/88(392) Chemical 01/28/88(393) Chemical 02/14/88(410) Chemical
4-3
UNIT
Forty-niner
DRILLING DATE (Calendar
Day)
01/21/88(386)
02/13/88(409) .
GROUTING DATE (Calendar
Day)
01/21/88(386) 01/22/88(387) 01/26/88(391) 01/28/88(393)
02/14/88(410)
GROUT
Cement Cement
Chemical
Chemical
The decline in the Culebra fluid press.ure in H-16 from December 19, 1987
to January I, 1988 (Calendar Days 353 to 366) appears to have been caused
by the drilling of the chemical-grout holes in the Culebra interval of
the WHS liner. (Plots of the Culebra' s fluid-pressure response during
this time period are included in Section 6.0 of this report.) These
grout holes remained open and draining until they were sealed on
February 7, 1988 (Calendar Day 403). Similar fluid-pressure decreases
were not noted for the Magenta or the Forty-niner because their grout
holes were drilled and sealed on successive or near-successive days after
the start of the drilling of the AIS pilot hole, apparently allowing
insufficient time for any pressure decrease to be transmitted to the
observation wells.
4-4
5.0 INTERPRETATION METHODOLOGY
A consistent interpretation methodology was applied to ~he analysis of the
fluid-pressure- response data from the Forty-niner claystone, Magenta
dolomite, and Culebra dolomite in H-16. A well-test simulator was used to
simulate the response of each individual unit to stresses induced by the
events occurring during drilling of the pilot hole and upreaming of the
AIS. Simulation results for different formation parameters were compared
graphically to pressures measured in observation wells. Parameters
providing the best simulation of observed pressures in H-16 and water-level
responses from other observation wells were assumed to be representative of
the unit being analyzed. The Culebra simulations were also compared to a
single measurement of the flow rate from the Culebra to the AIS.
5.1 GTFM Well-Test Simulator
The GTFM well-test simulator (Pickens .and others, 1987) was used for all
interpretations. GTFM is a numeric simulator which models the response
of a radial-flow regime to boundary conditions applied at a well located
at the center of the flow system. Simulation results consist of
calculated fluid-pressure responses at radial distances from the well
corresponding to the locations of the observation wells, and of
calculated fluid pressure, flow rate, and production volume in the well
itself. A description of GTFM can be found in Pickens and others (1987).
Application of GTFM to the simulation of pulse testing in low
permeability formations is described in Saulnier and Avis (1988).
Assumptions inherent in the formulation of GTFM and capabilities of the
model relevant to the AIS simulations are described below.
5-1
GTFM assumes that the hydrogeologic unit subject to analysis is
horizontal, of constant thickness, and bounded above and below by
impermeable layers. For the AlS simulations, formation thicknesses and
formation depth were assumed identical to those described for H-16 in
Beauheim (1987a) and are given in Table 5.1. Although both formation
thicknesses and elevations vary over the WlPP site and surrounding area,
variability in the immediate vicinity of the AlS is assumed to be
minimal. Therefore, given the proximity of H-16 to the AlS, interval
thickness values derived from H-16 are considered to be representative.
Differences in formation thickness and elevation at the more distant
moni toring locations, ERDA- 9, WlPP - 21, and H-l, will introduce
uncertainty as to the accuracy of simulation results at the corresponding
radii. All intervals of concern are bounded above and below by low
permeability anhydrite beds with little or no production potential
(Beauheim, 1987a). Mapping in the WHS and EXS did not indicate any
leakage from these anhydrite units (Holt and Powers, 1984, 1986) and
these units were assumed to have had little impact on the observed fluid
pressure responses.
GTFM simulates a formation of finite radial extent centered on a finite
radius well. The well is assumed to be the only source of hydraulic
stress applied to the unit being analyzed. For the AlS simulations, the
well consisted initially of the pilot hole, and after upreaming, the AlS.
The radial extent of the formation was set at 10,000 m, large enough to
preclude external boundary conditions from having any effects on the
simulation results. The single-hydraulic-stress assumption is obviously
not representative of the entire modeled area. For example, drilling and
grouting operations in the WHS and hydraulic tests on other wells in the
monitoring system appear to have affected water levels and observed
pressures in the observation wells, including H-16. However, the AlS was
the closest and most significant stress on the portion of the formation
which includes the H-16 monitoring well. Within this area, the effects
of any other stress events were assumed to have only minimal impact on
5-2
the H-16 pressure response. Water-level responses at observation-wells
H-1, ERDA-9, and WIPP-21 were apparently more significantly affected by
non-AIS hydraulic stresses, particularly those due to drilling and
grouting operations in the WHS.
Boundary conditions at the external boundary can be either fixed pressure
or zero flow. The potential effects of external boundary conditions were
minimized by using a large formation radius. Fixed-pressure boundary
conditions were used in all simulations. Fluid pressures (corrected to
the center of the water-bearing interval under consideration) measured at
H-16 before the pilot-hole drilling intercepted the intervals (and
applied stress to the units) were used as initial formation pressures.
GTFM assumes that formation-fluid properties are constant. The only
formation-fluid property required for the AIS simulations was fluid
density. A value of 1020 kg/m3 (see Cauffman and others, 1990) was
assumed to be representative of formation-fluid density for all three
units of interest within the modeled area.
GTFM allows the interval being analyzed to contain a single radially
centered heterogeneity. The boundary of the heterogeneity is specified
at some distance from the we11bore, thus allowing the tested formation to
be represented by two zones with different hydraulic properties; an inner
zone comprising the portion of the formation between the we11bore and the
heterogeneity boundary, and an outer zone which includes the portion of
the formation between the heterogeneity boundary and the external
boundary of the modeled system. Formation properties such as
transmissivity and storativity are assumed to be constant in each radial
zone, but may be different between zones. Heterogeneities are most
frequently used to model skin zones where, due to the effects of
drilling, properties in the formation immediately surrounding the well
are assumed to differ from those of the remainder of the formation.
5-3
However, heterogeneities may be placed at much larger radii, allowing
simulation of the effects of larger-scale differences in formation
properties. Both of these approaches were used in the AIS simulations.
A skin zone was applied to portions of the Culebra simulations in order
to simulate the effects of cement invasion, while larger-scale
heterogeneities were used to simulate the fluid-pressure responses of the
Forty-niner and Magenta units.
As a numeric model, GTFM can simulate well tests with complex wellbore
boundary conditions. Testing periods are subdivided into a number of
discrete time intervals, known as sequences, which are distinguished by
differing wellbore boundary conditions, due to either the type or value
of the boundary conditions. Wellbore boundary conditions used in the AIS
simulations consisted primarily of specified pressure corresponding to
calculated mud overpressure during the pilot-hole drilling, and zero
pressure after penetration of the underground facility by the pilot hole.
A limited number of short-duration, specified-flow boundary conditions
were also applied during the drilling period to simulate: a) the
interval's fluid-pressure responses when the pilot hole was cemented to
aid in reorienting the hole; and b) the apparent reduction in flow from
the units caused by settling of drilling mud in the borehole which may
have blocked the formations. Wellbore boundary conditions are discussed
in greater detail in Sections 5.2 and 5.3. '
GTFM simulations are usually conducted with a constant wellbore radius.
H~wever, three wellbore radii were used for the AIS simulations. The
intervals whose responses were analyzed in this report were initially
penetrated by a 9-7/8-inch (0.25 m) diameter drilling bit. Shortly
before penetration of the underground facility, the pilot hole was reamed
to a diameter of 0.37 m. Subsequently, the intervals were upreamed to a
6.17 -m diameter. The effects of the different wellbore radii were
simulated by subdividing the entire period of interest into three
different sub-simulations corresponding to the times of the different
5-4
we11bore radii. For each sub-simulation performed, the pressure
distributions over the radial extent of the modeled flow regime were
adjusted to reflect the geometry of the subsequent sub-simulation. These
adjusted pressure distributions were then used as initial conditions for
the next sub-simulation.
5.2 Drilling-Period We11Bore Boundary Conditions
As described in the following paragraphs, the actual we11bore boundary
conditions in effect during the simulation periods corresponding to the
drilling phase of the AIS construction were not known exactly. The
principal areas of uncertainty were: 1) the degree to which the
formation overpressure from the column of drilling fluid above the
formation was reduced by mud-fi1ter-cake skin; and 2) the lengths of time
the formations were exposed to full-borehole mud pressure; i.e., before
the effects of filter-cake skin affected the formations overpressured
condition. Therefore, the approach used in the AIS simulations was to
vary the reduced formation overpressures due to filter-cake skin
arbi trari1y, and to vary the durations of time periods with fu11-
borehole-mud pressure (Section 5.2.2). These parameters were varied
until a satisfactory match to the H-16 fluid-pressure responses was
achieved. This approach was taken to increase the reliability of the
simulations for the period following penetration of the pilot hole into
the repository horizon, when the post-penetration we11bore boundary
conditions under open and draining conditions were known with much
greater certainty.
During the period from the initial interception of the intervals of
interest by the pilot hole until penetration of the underground facility,
we11bore boundary conditions show considerable complexity.
sequence of events common to all intervals was as follows:
5-5
The basic
1) initial interception - the time when the 9-7/8-inch (0.25-m)
drill bit used for drilling the pilot hole intersected the
centers of the intervals.
2) cementing - two cementing operations were performed to allow
correction of excessive deviation of the pilot hole. The
first occurred on December 26, 1987 (Calendar Day 360), when
the hole was cemented from 190 to 93 m, affecting only the
Forty-niner and Magenta units. The second cementation
occurred January 6, 1988 (Calendar Day 371) when the hole
was cemented from 259 to 195 m BGS, which affected only the
Culebra.
3) second unit interception - the time, after the cementation
events, when the pilot hole intercepted the centers of the
intervals for the second time.
4) reaming - the time at which the l4-3/4-inch (0.37-m) reaming
bit intersected the center of the intervals.
5) final penetration - the penetration of the pilot hole into
the WIPP-site underground facility on February 7, 1988
(Calendar Day 403).
Unit interception times for events I, 3, and 4 were calculated based
on hole-penetration data given in the pilot-hole DDR. Ideally, the
wellbore boundary conditions for the periods between subsequent
events would be described as follows:
5-6
Sequence 1, drilling - a fixed pressure corresponding to the
calculated pressure at formation center due to an annulus filled
with drilling mud. The pressure at formation center due to the
mud filled annulus was in excess of actual formation pressure (see
for example Stensrud, 1988a, 1988b) and is referred to as mud
overpressure. Mud-overpressure values were calculated using a mud
density of 1174 kg/m3 , as noted in the DDR for January 13, 1988
(Calendar Day 378), and a depth equivalent to the center of the
interval. Calculated mud overpressures for each of the three
intervals analyzed are given in Table 5.2.
Sequence 2, cementation - specified flow at a flow rate of zero.
Well diameter of 0.25 m.
Sequence 3, drilling - same conditions as Sequence 1.
Sequence 4, reaming - fixed pressure using the same parameters as
Sequence 1 and a well diameter of 0.37 m.
The actual types and values of the boundary conditions used in the
simulations of the intervals' responses were affected by the true mud
weight and height of the column of drilling fluid, by the amount of
decrease in flow from the borehole to the formation due to settling of
drilling mud in the borehole during periods when circulation was
interrupted, and by the thickness and character of the build-up of mud
filter cake on the face of the wellbore. The following subsections
describe the techniques used to compensate for the effects of these
factors.
5-7
5.2.1 Mud-Related Uncertainties
The pilot hole was assumed to be constantly full of mud during drilling
periods. This assumption is somewhat unrealistic considering that
installing and removing the drill string during bit changes and other
operations probably affected the mud level. In addition, this
assumption postulated that no mud was lost to the formations during
periods when drilling operations were suspended. Variations in mud
levels could have caused changes in mud overpressure at the int~rva1s,
which in turn would have affected the fluid-pressure responses at the
observation wells.
A second mud-related uncertainty is the actual density of the drilling
fluid used during drilling. Changes in drilling-fluid density due to
variations in the amount and/or quality of makeup water and loss or
gain of formation fluid can affect the fluid-pressure response of the
formation. The DDR for the AIS pilot hole includes very few notations
about the properties of the drilling fluid.
5.2.2 Flow Reduction
The measured formation-fluid pressures for the Forty-niner and Magenta
intervals at H-16 (Figures 5.1 and 5.2) show periods where the fluid
pressure responses appear to have been affected by events consistent
with an apparent loss of flow from the borehole to these intervals.
The timing of the onset of these events is coincident with periods when
pilot-hole drilling operations were suspended. Mud solids may have
settled in the borehole when drilling-fluid circulation stopped. The
settled solids may have partially occluded the formation causing
reduced flow from the borehole to the intervals, thus allowing the
interval fluid pressure to decrease toward formation pressure.
5-8
For the Magenta interval, flow reduction appears to have occurred over
a nine-day period starting on December 13, 1987 (Calendar Day 347).
During this period, drilling operations were suspended for safety
reasons from December 13 until December 16 (Calendar Days 347 to 350).
Drilling operations resumed with the reaming of the upper portion of
the pilot hole to a depth of 93 m on December 20 (Calendar Day 354).
Drilling of the O. 25-m pilot hole resumed on December 22 (Calendar
Day 356) and mud circulation was restored over the entire depth of the
pilot hole.
The H-16 fluid-pressure data indicate that flow to the Magenta was not
restored to the interval during the first abbreviated reaming
operation. The lack of circulation affecting the Magenta probably
occurred because this reaming took place only in the upper portion of
the pilot hole.
The H-16 fluid-pressure data for the Forty-niner interval (Figure 5.1)
indicate a flow reduction similar to that observed for the Magenta.
However, complete loss of flow to the Forty-niner apparently did not
occur until some time after the resumption of reaming on December 16
(Calendar Day 347). The delay in developing reduced flow was probably
because the Forty-niner claystone lies 5 m above the Magenta and the
fillup of drilling solids may have taken longer to reach this interval.
The actual reduced flow rates for the Magenta or Forty-niner intervals
could not determined. Therefore, the reduced-flow-rate periods were
assumed to result in complete flow loss and were simulated as
specified-flow boundary conditions with a zero flow rate.
5-9
5.2.3 Filter-Cake Skin
The H-16 fluid-pressure responses for all three units analyzed
indicates the probable development of filter-cake skins, or the buildup
of a layer of mud solids on the intervals' borehole faces, which
created a flow impedance at the wellbore. The relatively flat fluid
pressure responses for the H-16 Magenta and Culebra (Figures 5.2 and
5.3) intervals over the period from January 6 until February 1, 1988
(Calendar Days 371 to 397) can be interpreted as the result of some
mechanism substantially impeding flow into the intervals from the
wellbore. Similarly, the almost linear rate of fluid-pressure increase
in the Forty-niner interval over the same period (Figure 5.1) can be
attributed to less severe flow impedance.
Filter-cake-skin development is well understood qualitatively. One of
the reasons for using clay-based muds is to promote formation of such
skins, and thus prevent loss of drilling fluids to permeable
formations. However, quantifying filter-cake skin parameters such as
thickness and permeability, and estimating the rate of accumulation of
the filter cake are difficult because of their dependence on drilling
procedures and mud and formation properties (Krueger, 1986; Holditch
and others, 1983). There are few quantitative data available on the
actual dimensions of these filter-cake skins, primarily because the
impact of filter-cake skins is not severe in conventional hydraulic
testing where pretest well-development procedures are used to remove or
ameliorate the effects of the filter-cake skins.
The simulation of the proposed filter-cake skins was difficult
primarily because of the lack of justifiable parameters for specifying
the skins. Also, because GTFM can only simulate a single
heterogeneity, simulating the filter-cake skin as a heterogeneity would
have precluded the simulation of other, and potentially more
significant, formation heterogeneities. As an alternative approach,
5-10
the reduced formation-to-wellbore permeability of the filter-cake skins
was assumed to cause a constant pressure drop across the skins making
them appear to the formation as a fixed-pressure boundary condition
with wellbore pressure significantly less than the mud overpressure but
greater than the formation pressure.
The reduced-wellbore-pressure approach was validated by performing a
number of scoping simulations with GTFM. The results of these
simulations are shown in Figures 5.4 and 5.5. The formation and well
geometry parameters used for the scoping simulations are given in
Table 5.3. Figure 5.4 illustrates the simulated fluid-pressure
response at the skin/formation interface to an applied wellbore
pressure of 2.498 MPa, 1.618 MPa above the assumed formation pressure
of 0.88 MPa, for a range of skin hydraulic conductivities. Figure 5.4
shows that the wellbore pressure transmitted to the formation is
relatively constant. Figure 5.5 illustrates the differences in fluid
pressure responses, at a radial distance equivalent to the distance
between the pilot hole and observation-well H-16, between simulations
performed using a skin heterogeneity and those performed using reduced
wellbore pressures. The reduced pressures selected for the comparison
simulations were based on the skin/formation interface pressures from
Figure 5.4 at a time equal to 1 day. Figure 5.5 demonstrates that
reduced mud overpressures can produce reliable and defensible results
when simulating the impact of filter-cake skins.
Most periods when the formations of interest were exposed to mud
overpressures were simulated using two or more sequences. The initial
sequence had a relatively short duration and simulated the period
before the build-up of a significant filter-cake skin, when full mud
pressure was applied to the formation,
boundary condition. For subsequent
as a fixed-pressure wellbore
sequences, reduced wellbore
pressures were applied to simulate the effect of filter-cake skins on
formation fluid pressures.
5-11
5.3 Wellbore Boundary Conditions After Penetration of the Underground
Facility
After penetration of the pilot hole into the WIPP-site underground
facility, the complete wellbore was exposed to atmospheric pressure.
Wellbore boundary conditions for all interval- analyzed during this
period used a fixed wellbore pressure of 0 MPa.
Fil ter - cake skins that developed on the intervals' faces before
penetration of the WIPP-site underground facility were assumed to be
removed as soon as the formations' flow directions reversed, because the
removal of the drilling fluid from the pilot hole allowed the members of
the Rustler to drain into the open hole or the AIS after upreaming.
5.4 Formation Heterogeneities
5.4.1 Cement-Invasion Skin
Following cementation of the Culebra interval on January 5, 1987
(Calendar Day 370), the fluid-pressure response of the Culebra in H-16,
when compared to the fluid-pressure response after upreaming of the
shaft, indicates a flow-reduction condition similar to that caused by a
damage or skin zone (Figure 5.3). This condition persisted after the
pilot hole was reamed and drained of drilling fluid after penetration
of the underground facility. To simulate the Culebra's fluid-pressure
response after cementation, a radially-oriented cement- invasion skin
was added to the Culebra for the post-cementation drilling and reaming
periods and for the draining of the Culebra before upreaming
intercepted the Culebra. The vuggy and fractured nature of the Culebra
dolomite enhances its permeability and probably allowed relatively easy
penetration of the cement grout into the formation.
5-12
The cement-invasion skin zone was assumed to be a radial zone with a
finite thickness having a permanent reduced permeability due to the
presence of cement in the formation. The cement was assumed to be
responsible for the formation's slower response times and relatively
higher pressures during the post-cementation drilling and reaming
periods.
The simulations accounted for the cement-invasion skin by specifying a
radial zone with an assigned permeability lower than that of the rest
of the formation. In contrast to the use of reduced-we11bore-pressure
boundary conditions to simulate the effect of filter-cake skins as
described in Section 5.2.3, GTFM treated the cement-invasion skin as a
formation heterogeneity. The thickness and permeability of the cement
invasion-skin heterogeneity were determined in an iterative manner by
varying these parameters until a suitable match of observed and
simulated data for the Cu1ebra' s drilling and reaming periods was
achieved. Detailed descriptions of the use of the cement-invasion skin
in the analysis of the Cu1ebra fluid-pressure response to the
construction of the AIS accompanies the discussion of the Cu1ebra
simulations in Section 6.1
5.4.2 Radial Heterogeneity Boundaries
The H-16 fluid-pressure responses of the Magenta dolomite and the
Forty-niner claystone indicated that these units behaved as
heterogeneous formations. The formation heterogeneities were assumed
to correspond to zones of differing permeability within the formations.
The radial-flow model employed by GTFM dictates that formation
heterogeneities can only be included as radial boundaries at specified
distances from the pumping, injection, or, in the case of the AIS,
draining well. The direction to and physical character of the actual
boundaries must be derived from hydrogeologic and structural data.
5-13
The simulation of the H-16 fluid-pressure responses of the Magenta and
Forty-niner included specified formation transmissivities for inner
(near-field) and outer (far-field) zones radially oriented about the
AIS. The distances to the radial boundaries for both units and the
inner and outer transmissivities were determined empirically by varying
these parameters until achieving satisfactory matches of observed and
simulated data. Detailed descriptions of the use of the radia1-
heterogeneity boundaries used in the analysis of the Magenta and Forty
niner fluid-pressure responses to the construction of the AIS
accompanies the discussions of their simulations in Sections 6.2 and
6.3, respectively.
5.5 Diffusivity Relationship
As mentioned previously, with the exception of several short-duration
zero-flow boundary conditions, fixed-pressure boundary conditions were
applied at the wellbore the majority of the time. As a result of the
fixed-pressure boundary condition and the radial flow system simulated by
GTFM, unique formation responses at observation wells are a function of
the value of formation diffusivity, which is defined as:
D -T
S
where: D
T
S
(5-1)
diffusivity [L2 t -1]
transmissivity [L2 t -1]
storativity [ ]
Therefore, simulated interval responses cannot be used to provide
completely independent estimates of transmissivity and storativity.
Rather, the parameters are lumped, thus providing a single term to
characterize the individual intervals.
5-14
The approach used in the AIS simulations was to fix storativity at a
value assumed to be representative of the units analyzed. These data
were based on values determined by analyzing the results of previous
tests conducted at the WIPP site (Beauheim, 1987a, 1987b; Gonzalez, 1983;
Mercer, 1983; and Saulnier, 1987b) and a review of published estimates of
the intervals' rock and fluid properties (Touloukian and others, 1981).
After fixing the storativity, transmissivity was varied over appropriate
ranges until satisfactory simulations were achieved. Simulation of the
fluid-pressure responses of the Magenta and Forty-niner used formation
heterogeneity boundaries at various radii. Utilizing these boundaries,
those parameters or parameter combinations which produced the closest
matches between simulated and observed observation-well fluid-pressure
responses were determined to be most characteristic of the intervals
being simulated.
Interval transmissivities were calculated for the selected fixed
storativities and the upper and lower limits of storativity assumed to be
representative of the intervals whose fluid-pressure responses were
analyzed (see Section 8.1). Upper- and lower-transmissivity limits were
calculated from equation 5-1 and were not independently simulated.
5-15
1.3
-
-
0.9 -
-
0.7
~ xx x )«x
x
~ lEXX
FIRST PENETRATION
x
x X
x x x x ~ 9: x V x
x
OF FORTY-NINER 9:x~ x
\;: "xx 1 x X X X X >001«
DRILLING
I I
PENETRATION OF UNDERGROUND
FACILITY
REAMING
DRILLING I I I
325 3~5 3~5 DAYS)
405
Drawn by J.D. A. Date 1/16/89
Checked by G. S. Date 1/17/89
Revisions Date
H09700R876 1/19/89
I NrtIL'\ Technologies
(1987 CALENDAR
FLUID-PRESSURE RESPONSE FOR THE FORTY-NINER CLAYSTONE AT H-16 DURING THE DRILLING/REAMING PERIOD
Figure 5.1
5-16
~
0 0-. 2
'-....../
W et:: =:J U) U) w et::
1.4
-
1.2 -
-
x
>« x
xx
x x
X
-"" ](X >«x !>Ix x ~ "£xxxxx xx ~ ->of ~xx ~ \~ x
x
x
x
>OC X PENETRATION OF x >«\
x
X
x x x x
UNDERGROUND FACILITY
x
>
0-. 1.0 - FIRST PENETRATION ~
>« >«
X><
0.8
Drawn by J.D. A.
Checked by G. S.
Revisions
H09700R876
OF MAGENTA x
\
x
~ x xx><
x
xxx xx xx>< -
I I
325
Date 1/16/89
Date 1/17/89
~ate
1/19/89
CEMENTATION
III REAMING
DRILLING DRILLING I t I I I I I I I
345 365 385 405
TIME (1987 CALENDAR DAYS)
FLUID-PRESSURE RESPONSE FOR THE MAGENTA DOLOMITE AT H-16 DURING THE DRILLING/REAMING PERIOD
I NrtILl\ Technologies Figure 5.2
5-17
1.2
-
W 0:::: 1.0 -=:J (J) (J) W
X l!K
/<\ x~
FIRST PENETRATION OF CULEBRA
x
x
x
x
x
x
0:::: 0.-
_ ~x x \"''' \
>Xx,,: x
PENETRATION OF UNDERGROUND
FACILITY x
x
x x x
0.8 350
Drawn by J.D. A.
Checked by G. S.
Revisions
H09700R876
CEMENTATION
DRILLING III I I I
370
DRILLING
I 390
TIME (1987 CALENDAR DAYS)
Date 1/16/89
x
~ REAMING
I t I I
Date 1/17/89 FLUID-PRESSURE RESPONSE FOR THE CULEBRA DOLOMITE AT H-16 DURING THE DRILLING/REAMING PERIOD
Date
1/19/89
I NrtIl.'\ Technologies Figure 5.3
5-18
2.4
2.2
2.0 /""'0..
0 0.-:2
1.8 '--../
w 0::: => 1.6 (J) (J) W 0::: 0.- 1.4
1.2
1.0
0.8
Drawn by J.D.A.
Checked by G. S.
Revisions ABW
H09700R876
Ks=SKIN PERMEABILITY
Ks= 1 .OE -09 m/s\
Ks=3.0E-10 m/s"
Ks=1.0E-10
Ks=6.0E-11 m/sl
10 -3 10 -2 10 -1 10
TIME (OAYS)
THE SIMULATED PRESSURES AT THE SKIN/FORMATION INTERFACE ARE RELATIVELY CONSTANT OVER THE PERIOD OF INTEREST INDICATING THAT A SPECIFIED, REDUCED WELlBORE PRESSURE CAN BE USED TO SIMULATE THE EFFECT OF A FILTER-CAKE SKIN.
Qate 1/16/69
Oate 1/17/89
Date 6/23/89
1/19/89
FILTER-CAKE-SKIN SIMULATION PRESSURE AT THE SKIN/FORMATION INTERFACE
I NrtILl\ Technologies Figure 5.4
5-19
1.4
~
1.2 0 0... 2
'--..../
W 0::::: => (f) (f) W 0::::: 0...
1.0
0.8
0.01
Drawn by J.D.A. Date
Checked by G.S. Date
Revisions ABW Date
H09700R876
/,
/;
/, ./
0.1
./
/
./ ./
./ ./
./
Ks=1.0E-9 m/s / Ps=2.18 MPa '-... y
8 8
8 ~ a /-
;j /. ./
./ ./
1
TIME (DAYS)
'-... /' Ks=3.0E-ll m/s ~ Ps=1.76 MPa '-
./ ./
./
!7 Ks=1.0E-l0 m/s Ps= 1 .34 MPa '"
Ks=3.0E-ll m/s Ps=1.05 MPa
10
- Ks= SKIN PERMEABILITY --- Ps= REDUCED WELLBORE PRESSURE TO
SIMULATE THE PRESENCE OF A MUD-FILTER-CAKE SKIN
1/16/89
./
1/17189 FILTER-CAKE-SKIN SIMULATION PRESSURE AT RADIUS OF OBSERVATION-WELL H-16
6/23/89
1119/89
I NTER..,\ Technologies Figure 5.5
5-20
INTERVAL
Forty-Niner Magenta Culebra Claystone Dolomite Dolomite
Depth [meters]
Top 171.480 179.893 214.122 Bottom 174.894 187.635 220.797 Center 173 .187 183.764 217.460
Thickness [meters] 3.414 7.742 6.675
Drawn by Date Depths and Thicknesses of the Rustler Units
Checked by Date Analyzed at H-16 Revisions Date
I NrtIL'\ Technologies I Table 5.1
H09700R876 5-21
Depth to Interval Mud Overpressure Center
[meters] [MPa]
Interval
Forty-Niner 173.187 1.9895 Magenta 183.764 2.1110 Culebra 2l7.460 2.4980
Drawn by Date Calculated Rustler-Unit Mud Overpressures for
Checked by Date Simulation of the Drilling Periods of the AIS-Revisions Date Pilot-Hole
I ~t.R.." Technologies Table 5.2
H09700R876 5-22
FILTER-CAKE SKIN SIMULATION PARAMETERS
Formation Parameters
Formation transmissivity Formation storativity
Skin Parameters
Radial thickness of skin Skin-zone storativity Skin hydraulic conductivity
Value #1 Value #2 Value #3 Value #4 Value #5
Other Parameters
Test-interval length Test-interval radius Wellbore pressure Static formation pressure Fluid density
Calculated Skin Factor
Case #1 Case #2 Case #3 Case #4 Case #5
Drawn by Date
Checked by Date
Revisions Date
I NrtIL'\ Technologies
H09700R876
1. 30003E-07 9.99998E-06
10.0 9.99998E-06
1. 00000E-09 3.00000E-10 1.00000E-10 6.00000E-ll 3.00000E-ll
6.675 125 2.4980 0.8800
1020.00
Ks [m/sec]
1.00000E-09 3.00000E-10 1. 00000E-10 6.00000E-ll 3.00000E-ll
[m2/s] [ ]
[mm] [ ]
[m/s] [m/s] [m/s] [m/s] [m/s]
[m] [mm]
[MPa] [MPal
[kg/m ]
Skin Factor [ ]
1. 42l909E+00 4.919273E+00 1. 491174E+Ol 2.490421E+Ol 4.988538E+Ol
Parameters for Simulations Including FilterCake Skin
Table 5.3
5-23
6.0 ESTIMATION OF TRANSMISSIVITIES
The transmissivities of members of the Rustler Formation were estimated by
comparing simulation results from the GTFM well-test simulator to: the
observed fluid-pressure responses of those members in H-16; water-level
responses in observation wells H-1, WIPP-21, and ERDA-9 completed to the
Cu1ebra dolomite near the AIS; and a single flow-rate measurement from the
Cu1ebra dolomite to the AIS after upreaming the AIS.
The drilling of the AIS pilot hole included periods of drilling,
cementation, and reaming which provided a rather complex drilling history
(see Sections 3.0 and 5.2). Transmissivities were estimated with GTFM
after including the most important elements of the drilling history as they
were reflected in the fluid-pressure responses at H-16. Figure 6.1 shows
the H-16 fluid-pressure responses for all members of the Rustler isolated
in the H-16 borehole during the drilling/reaming of the pilot hole and the
upreaming of the AIS. These responses were used to develop the GTFM test
sequences used to simulate the responses of the Cu1ebra dolomite, the
Magenta dolomite, and the Forty-niner claystone. The simulations were
performed for a range of transmissivity values indicating the order of
magnitude and variability of formation transmissivity.
Figure 6.1 also shows that the fluid-pressure responses of the Tamarisk and
unnamed lower members of the Rustler were not suitable for analysis to
estimate their transmissivities. The unnamed lower member fluid pressure
did not appear to respond to the construction of' the AIS. The large and
sudden pressure decrease shown on Figure 6.1 on Calendar Day 650 was due to
a slug-withdrawal test of the unnamed lower member designed to establish
whether or not its pressure transducer was operating properly. The f1uid
pressure data from the Tamarisk Member show continued adjustment with no
identified trend during the pre-AIS period. Because the data did not
appear to approach a stable pre-AIS formation pressure, they could not be
used with confidence to estimate the Tamarisk's hydraulic parameters.
6·-1
The following sections will describe the GTFM simulation and analysis of
the fluid-pressure responses of the Culebra dolomite, the Magenta dolomite,
and the Forty-niner claystone. The simulations will be compared to their
H-16 fluid-pressure responses and the responses of other observation wells
near the WIPP site. As discussed in Section 5.5, the boundary conditions
applicable to the simulations resulted in the treatment of transmissivity
and storativi ty parameters as the combined parameter diffusivity.
Published estimates of formation hydraulic properties for the WIPP site
show that there is much less variability in storativity than in
transmissivi ty. Therefore, to determine representative values of
transmissivity, a fixed storativity value of 1 x 10- 5 , consistent with the
published literature on testing at the WIPP site (Gonzalez, 1983; Mercer,
1983; Beauheim, 1987b; LaVenue and others, 1988), was used for all
simulations. In the summary of results presented in Section 8.0, the
transmissivities are calculated for a range of storativities assumed to be
representative of the intervals studied. Refer to Table 1.1 for the
nomenclature used for the simulation parameters in the text and on the
figures and tables.
6.1 Culebra Dolomite
The Culebra dolomite's fluid-pressure response to the construction of the
AIS was simulated using the methodology described in Section 5.2.. The
analysis was based on the fluid-pressure response of the Culebra as
measured in H-16 (Figure 6.2). Because of the complex history of the
drilling and reaming of the pilot hole, more weight was given to the
fluid-pressure data observed after the pilot hole penetrated the
underground facility. The GTFM simulations of the Culebra dolomite's
fluid-pressure response were compared to the observed fluid-pressure
response at H-16, water levels measured at observation wells H-1, ERDA-9,
and WIPP-21 (Figure 6.3), and a single flow-rate measurement of 0.056 Lis
from the Culebra to the AIS measured on October 28, 1988 (Calendar
Day 667) (R. Deshler, IT Corporation, written communication, December
6-2
1988). The flow-rate measurement may be somewhat uncertain because some
of the following factors may have affected the measurement: evaporation
in the AIS was not taken into consideration; the water ring may not have
captured all the flow from the Cu1ebra; and small amounts of water from
grouting operations higher in the AIS and from a leaking water connection
on the AIS conveyance system may have contributed to the measured flow
rate. In spite of the potential inaccuracies, the estimate of 0.056 L/s
is considered good and was corroborated by an informal INTERA estimate of
0.063 L/s made during an AIS inspection on October 26, 1988 (Calendar
Day 665) (Saulnier, INTERA Inc. internal memorandum, October 28, 1988).
Six simulations were used to analyze the Cu1ebra dolomite's f1uid
pressure response. The simulations are distinguished by differences in
the simulation's formation transmissivity and by the inclusion or non
inclusion of a cement-invasion skin immediately surrounding the pilot
hole as described in Section 5.4. The simulations indicate the range of
variability in transmissivity and sensitivity to use of the cement
invasion-skin heterogeneity.
As discussed in Section 5.2, the actual we11bore boundary conditions
during the pilot-hole drilling and reaming phases were uncertain.
Simulation of this period required assumed we11bore pressures and flow
rates to account for the events which occurred during the
drilling/reaming period and to approximate the effect of filter-cake skin
at the we1lbore-formation interface. Using an iterative approach, the
boundary conditions which provided the best simulation of the H-16 fluid
pressure data observed during this period were assumed to be
representative of the formation's hydrologic conditions.
6-3
The simulation period for the Culebra was divided into six discrete time
segments (Figure 6.2), the first four of which cover the drilling/reaming
phase (Figures A.l to A. 6, Appendix A). The observed H-16 formation
fluid pressures for the drilling/reaming phase are shown in Figure 6.4.
Segments 1, 3, and 4 were simulated with fixed- wellbore-pressure
boundary conditions. As discussed in Section 5.2.3, the effect of a
filter-cake skin was simulated, when necessary, by subdividing the
drilling and reaming periods and applying reduced pressures to simulate
the effects of the assumed filter-cake skin. The period durations and
reduced pressures applied for each segment of the Culebra dolomite
simulation are given in Table 6.1. Figures A.l through A.6, Appendix A,
show the prescribed and simulated wellbore pressures
drilling/reaming period for each of the Culebra simulations.
during the
(Note that
for the period after cementation when the Culebra was isolated from the
pilot hole, the formation's fluid~pressure response was simulated using a
specified-flow boundary condition with a flow rate of 0.0 L/s to simulate
the effects of flow loss due to cementation.)
After the drilling period, the period when the Culebra was open and
draining through the pilot hole and/or the AIS to the underground
facility was simulated using fixed-pressure wellbore boundary conditions
with a value of 0.0 MPa, corresponding to atmospheric pressure. The well
diameters used in the simulations were 0.25 m for the pilot hole, 0.37 m
for the reaming period, and 6.17 m for the post-upreaming period 6.
All Culebra simulations assumed a static formation pressure of 0.88 MPa
before the start of the simulations. This value was based on the Culebra
fluid pressure in H-16 (Figure 6.4) immediately before the initial
interception of the interval by the pilot hole.
6-4
6.1.1 Simulation Results
The Cu1ebra simulations are described as follows:
Simulation 1 - Matching The H-16 Fluid-Pressure Response, No Cement
Invasion-Skin Zone
Because of the complex borehole history before penetration of the
underground facility, the first Cu1ebra simulation was intended to
provide an initial transmissivity estimate by matching the H-16 f1uid
pressure data during the period between penetration of the underground
facility and interception of the Cu1ebra by the upreaming of the AlS.
The simulation was conducted using homogeneous formation properties
with a formation transmissivity of 2.6 x 10- 8 m2/s. The simulated
formation pressures at the radii of H-16 and the other observation
wells are shown in Figures 6.5 and 6.6, respectively. The simulated
flow rate for Calendar Day 667 was 0.0031 L/s. Figure 6.5 shows that
the simulated fluid-pressure response during the period before
upreaming agrees .with the observed H-16 response, but that the
simulated response after upreaming does not agree. Figure 6.6 shows
that the simulations of the observation-well responses are poor.
Simulation 2 - Matching The H-16 Fluid-Pressure Response With A Cement
Invasion-Skin Zone
The first simulation indicated a need for increased formation
transmissivity. However, an increase in transmissivity, while
maintaining homogeneous formation parameters, adversely affected the
match to the H-16 data during the post-penetration/pre-upreaming
period. To account for this apparent difference in formation
transmissivity, a heterogeneity in the form of a reduced-permeability
skin zone surrounding the pilot hole caused by cement invasion after
cementation of the Culebra interval (see Section 3.1.1) was added to
6-5
the post-penetration/pre-upreaming period to restrict the formation's
fluid-pressure response. The DDR for January 8, 1988 reports "cement
and sand" in the cuttings during the period when the Cu1ebra unit was
redri11ed following cementation, indicating that the Cu1ebra was
probably in contact with, and may have been invaded by, cement.
The second simulation included a cement-invasion-skin heterogeneity
during the period from redri11ing following cementation until Cu1ebra
interception by the AIS upreaming. The skin zone was a radial
heterogeneity with a radius of 0.24 m from the borehole center and a
transmissivity of 3.0 x 10- 9 m2/s. The formation transmissivity used
in the simu~tion was 1.3 x 10- 7 m2/s, almost 2 orders of magnitude
higher. This combination of parameters yielded a calculated skin
factor of 3.64 during the drilling phase and 1. 44 during the period
between pilot hole reaming and AIS upreaming. The skin factor
quantifies the pressure difference between the borehole and the
formation across a thin skin zone at the borehole-formation interface.
The 'skin factor indicates the degree of damage (positive skin factor)
or improvement (negative skin factor) at the borehole - formation
interface. The choice of skin- zone parameters was based on those
parameter combinations that provided the best match to the H-16 f1uid
pressure data. Simulation results for formation fluid pressures at the
radius of H-16 and the other observation wells are shown in Figures 6.7
and 6.8. Figure 6.7 shows that the simulation results closely match
the H-16 fluid-pressure response. However, although the simulated
responses at the observation wells was improved compared to the first
simulation (Figure 6.6), Figure 6.8 indicates that a further increase
in formation transmissivity was required to match data from those wells
adequately.
The simulated flow rate for Calendar Day 667 was 0.013 L/s,
significantly less than the measured flow rate of 0.056 L/s, a further
indication that an increase in formation transmissivity was needed.
6-6
Simulation 3 - Matching the Culebra.-to-AIS Flow Rate Using a Cement
Invasion-Skin Zone
The third simulation attempted to match the flow rate from the Cu1ebra
to the AIS of 0.056 Lis measured on Calendar Day 667. A cement
invasion-heterogeneity was included in the simulation to provide an
acceptable match to the H-16 f1uid-pressure-response data for the post
penetration/pre-upreaming period. The calibrated simulation parameters
were a formation transmissivity of 6.6 x 10- 7 m2/s, a skin-zone
transmissivity of 6.0 x 10- 9 m2/s, and a skin-zone radius of 0.48 m.
The calculated skin factor was 10.26 for the drilling period and 4.05
for the post-reaming period. The simulations are presented in Figures
6.9 and 6.10. Figure 6.10 indicates reasonable agreement with the
general character of the observed data for wells ERDA-9 and WIPP-21,
but relatively poor agreement with the observed data for H-l. The
calculated flow rate at Calendar Day 667 was 0.058 Lis, which compares
favorably with the measured value of 0.056 Lis.
Simulation 4 - Matching Observation-Well Data Using a Cement-Invasion
Skin Zone
The fourth simulation included a cement- invasion skin, and used a
formation transmissivity midway between those used for simulations 2
and 3. This simulation was intended to provide a more reasonable match
to the water -level response in H-1 and to provide additional
sensitivity to the range of formation transmissivities needed to match
the WIPP-21 and ERDA-9 data. The simu1'ation used a formation
transmissivity of 2.6 x 10- 7 m2/s and assumed a cement-invasion-skin
zone with a radius of 0.48 m and a transmissivity of 3.5 x 10- 9 m2/s.
The calculated skin factors were 6.72 and 2.65 for the drilling period
and the period following pilot-hole reaming, respectively. Simulated
and observed fluid-pressure and water-level responses for these
simulations are presented in Figures 6.11 and 6.12. The Cu1ebra flow
rate to the AIS for this simulation was 0.025 Lis for Calendar Day 667,
a little more than half that calculated for simulation 3.
6-7
Simulations 5 and 6 - Sensitivity of H-l6 Fluid-Pressure Response to
Cement-Invasion-Skin Zone
Figure 6.13 shows the results of two simulations using the formation
transmissivities from simulations 2 and 3 (1.3 x 10- 7 m2/s and
6.6 x 10- 7 m2/s, respectively) without including a cement-invasion-skin
zone. The simulations show the sensitivity of the simulated fluid-
pressure response of the Culebra in H-16 to the use of a cement-
invasion-skin zone. The cement- invasion-skin zone has relatively
little impact on the simulated results for the period after upreaming.
The primary effect of adding the cement-invasion-skin zone was to
retard the formation response during the period when the Culebra was
draining to the pilot hole and improve the overall match to the
observed fluid-pressure response.
6.1.2 Discussion of Simulation Results
Assuming a storativity of 1 x 10- 5 , the estimated Culebra
transmissivities and the principal assumptions for the simulations
presented above can be summarized as follows:
ESTIMATED CULEBRA TRANSMISSIVITY
2.6 x 10- 8 m2js
1.3 x 10- 7 m2/s
6.6 x 10- 7 m2/s
2.6 x 10- 7 m2/s
6-8
SIMULATION ASSUMPTIONS
Match to H-16 Fluid-Pressure Response
Homogeneous Properties,
No Cement-Invasion-Skin Zone
Match to H-16 Fluid-Pressure Response,
Cement-Invasion-Skin Zone
Match to the Culebra to AIS Flow Rate
Cement-Invasion-Skin Zone
Match to H-l Water-Level Response
Cement-Invasion-Skin Zone
The estimated values of formation transmissivities from the four
calibration simulations range from 2.6 x 10- 8 m2/s to 6.6 x 10- 7 m2/s.
The lower value determined from the first simulation is considered
unrepresentative due to the inadequate match of the simulation results
to the post-upreaming fluid-pressure data from H-16, the water-level
responses at the observation wells, and the underestimate of flow to
the AIS. A revised range of estimated transmissivities for the Culebra
is therefore 1. 3 x 10- 7 m2/s to 6.6 x 10- 7 m2/s. The value of
6.6 x 10- 7 m2/s appears to be the most representative of the Culebra
between the AIS and H-16, between the AIS and ERDA-9, and between the
AIS and YIPP - 21. Simulation 3, which used this value, has the bes t
match to the H-16 and observation-well data, and Simulation 3 provided
the best estimate of the flow rate from the Culebra to the AIS. A
transmissivity value of 2.6 x 10- 7 m2/s for the Culebra appears to
provide the best approximation of the H-l response. It should be
noted, however, that the simulations of the observation-well responses
are less certain because other hydrologically-related influences (see
Section 4.0) affecting the observation-well water-level responses, such
as the WHS grouting, water-quality sampling, and the H-ll
multipad/tracer test, were not included in this analysis.
Figure 6.14 shows simulated flow rates from the Culebra to the AIS for
the four principal simulations for the period after upreaming. The
shapes of the flow-rate curves are similar, with the differences in the
magnitudes of the rates being relative to the differences in simulated
formation transmissivities.
6-9
6.2 Magenta Dolomite
The analysis of the fluid-pressure response of the Magenta dolomite in
H-16 (Figure 6.15) was performed using a methodology similar to that
described in Section 6.1.1 for the Cu1ebra dolomite. The H-16 fluid
pressure response (Figure 6.15) was the only observed data with which to
compare the simulated results. No measurements of the flow from the
Magenta to the AIS were available to use for simulation calibration.
Personnel mapping the geology in the AIS reported one O.9-m and one 1.5-m
"damp" zone in the Magenta interval (R. Holt and R. Williams,
International Technologies, personal communication, October 26, 1988).
As was noted in the analysis of the Cu1ebra dolomite (Section 6.1), the
complexity of the drilling/reaming period meant that the simulation
results were best judged by comparing the simulated fluid-pressure
response, at a radius equivalent to the distance between the AIS and
H-16, to the observed fluid-pressure data from H-16 after the pilot hole
penetrated the underground facility because borehole conditions were
known with the most certainty during this period.
We11bore boundary conditions for the Magenta dolomite simulations were
specified in a similar manner as discussed for the Cu1ebra dolomite. The
simulation period for the Magenta was divided into eight discrete time
segments (Figure 6.15), the first six of which covered the
drilling/reaming phase (Figures A.7 to A.16, Appendix A). Segments 1, 3,
5, and 6 were simulated with fixed-we11bore-pressure boundary conditions.
Where required, the effects of a filter-cake skin (see Section 5.2.3)
were simulated by subdividing the segments into two or more periods and,
where necessary, reduced pressures were applied to simulate the effects
of the assumed filter-cake skin. The period durations· and reduced
pressures applied for segments 1, 3, 5, and 6 of each simulation are
given in Table 6.2. Table 6.2 shows that the assumed filter-cake skin
was not required for some segments of some of the sens i ti vi ty
simulations. For these segments, the H-16 pressure response during the
drilling/reaming phase was either reproduced satisfactorily with full mud
6-10
pressure or could not be reproduced. Specified flow boundary conditions,
with a flow rate of 0.0 L/s were applied for segments 2 and 4 to simulate
the effects of flow loss due to mud settling and cementation,
respectively.
The observed H-16 fluid pressures for the Magenta during the
drilling/reaming phase are shown in Figure 6.16. Figures A.7 through
A. 16, Appendix A, show the prescribed (segments 1, 3, 5, and 6) and
simulated (segments 2 and 4) we11bore pressures for the drilling/reaming
period for each of the Magenta simulations and the simulated formation
fluid pressure at H-16 for the drilling/reaming period.
A static formation pressure of 0.928 MPa was used as the initial
condition for the Magenta dolomite simulations. This value was based on
the Magenta's fluid pressure in H-16 before the initial interception of
the interval by the pilot hole. The pressure measured at H-16 before
drilling the pilot hole is constant, indicating that the selected
formation pressure is representative of the interval.
6.2.1 Simulation Results
Ten simulations of the Magenta's fluid-pressure response in H-16 were
conducted. Two simulations, with and without formation-heterogeneity
boundaries, compare the simulated data to the Magenta's observed H-16
fluid-pressure response. Eight simulations were performed to show the
simulations' sensitivity to formation heterogeneity.
6-11
The Magenta simulations are described as follows:
Simulation 1 - Match to the H-16 Fluid-Pressure Response,
Homogeneous Formation
The first simulation (Figure 6.17) shows the best match to the H-16
fluid-pressure response using homogeneous formation properties and a
formation transmissivity of 2.5 x 10- 6 m2/s. Although the match
appears adequate for the late portion of the post-reaming/pre-upreaming
period and only slightly underestimates the post-upreaming period, the
match was unacceptable for the early and middle portions of the post
reaming and post-upreaming periods when the pilot hole or the AIS was
open and the Magenta was draining. Additionally, the simulated flow
rate from the Magenta to the AIS on Calendar Day 667 was 0.21 L/s, four
times higher than the O. 056-L/s flow rate measured for the Culebra
interval (see Section 6.1). This simulated flow rate is inconsistent
with the geologist's report of only "damp" zones in the Magenta in the
AIS (R. Holt and R. Williams, International Technologies, personal
communication, October 26, 1988) an indication that the transmissivity
of the Magenta interval is probably considerably lower than that of the
Culebra.
The H-16 fluid-pressure response of the Magenta, unlike that of the
Culebra interval, did not appear as if a cement- invasion skin was
affecting the Magenta's H-16 response because of the simulation's good
late-time matches to both the pilot-hole and AIS draining periods.
Moreover, the shape of the H-16 fluid-pressure-response curve for the
post-drilling/reaming period was consistent with that expected for a
heterogeneous formation, indicating the need to simulate the Magenta's
response as the result of a heterogeneous formation with a hydrologic
boundary at some distance from the AIS.
6-12
Simulation 2 - Match to the H-16 Fluid-Pressure Response,
Heterogeneous Formation
For the second simulation. the Magenta was divided into two radial
zones with different transmissivities separated by a hydrologic
boundary. The inner zone included the portion of the formation between
the wellbore and the heterogeneity boundary. The outer zone consisted
of the portion of the formation between the heterogeneity boundary and
the external boundary of the modeled system. The three parameters
which define the heterogeneity are: Ti. the inner-zone transmissivity;
To. the outer-zone transmissivity; and rb. the radius to the boundary
between the two zones.
The Magenta's fluid-pressure response was simulated with a Ti of
8.0 x 10- 8 m2/s. a To of 4.0 x 10- 8 m2/s. and an rb of 40 m.
Figure 6.18 shows that the match to the H-16 fluid-pressure response is
very good over the entire duration of the pilot-hole draining period
and the early-time period after the Magenta was intersected by
upreaming. and acceptable over the mid- and late-time portions of the
post-upreaming period. Furthermore. the simulated flow rate of
0.0063 L/s for Calendar Day 667 is more consistent with the reported
"damp" zones in the Magenta.
After achieving a reasonable match to the Magenta's fluid-pressure
response using a formation-heterogeneity boundary. sensitivity
simulations were performed to provide an indication of the ranges of
Ti. To. and rb. Following is a discussion of these simulations.
numbers 3 through 10.
6-13
Simulations 3 through 8 - Sensitivity of the Heterogeneity Parameters
of the Simulation of the Magenta's H-16 Fluid-Pressure Response
Six simulations were performed to assess the sensitivity of the Magenta
simulation using a formation-heterogeneity boundary. For each
simulation, one of the three heterogeneity parameters was changed while
the remaining two parameters were the same as the values used in
simulation 2. For To and Ti, values approximately ± one half an order
of magnitude of the calibration values were used for sensitivity, while
~ was increased and decreased by a factor of two. Simulations 3 and 4
used Ti's of 2.5 x 10- 8 m2/s and 2.5 x 10- 7 m2/s, respectively;
simulations 5 and 6 used To's of 1.3 x 10- 8 m2/s and 1.3 x 10- 7 m2/s,
respectively; and simulations 7 and 8 used rb' s of 20 and 80 m,
respectively. The results of the sensitivity simulations are presented
in Figures 6.19 through 6.22. Figures 6.19, 6.20, and 6.21 show the
simulated results for simulations 3 and 4, 5 and 6, and 7 and 8,
respectively, for the entire simulation period. Figure 6.22 shows
semi-log plots which compare the results of the sensitivity simulations
with the best-match simulation for the period between penetration of
the underground facility and Magenta interception by upreaming. Figure
6.22 illustrates explicitly the two-transmissivity nature of the
heterogeneous formation response. The early-time magnitude of the
simulated fluid-pressure response at H-16 is largely dependent on the
inner-zone transmissivity (Figure 6. 22a). Although there are
differences in the magnitude of the simulation's late-time fluid
pressure response, Figure 6.22a shows that the shape of the late-time
curve is similar for all values of Ti. In contrast, Figure 6. 22b
illustrates that the value of To primarily affects the simulation of
the late-time fluid-pressure response while having very little impact
on the early- time behavior. Figure 6. 22c shows that changing the
radius of the heterogeneity boundary primarily affects the time of the
transition between inner- and outer-zone-dominated fluid-pressure
responses.
6-14
Simulations 9 and 10 - Homogeneous-Formation Characterization Showing
S ens it i vi ty to T i and To of the Bes t -Ha tch He terogeneous
Characterization
Simulations 9 and 10 show the Magenta's simulated fluid-pressure
response using a homogeneous-formation characterization with formation
transmissivities equal to the inner- and outer-zone transmissivities of
the best-match heterogeneous simulation. Figure 6.23 shows the
simulated fluid-pressure responses at H-16 for a homogeneous formation
with transmissivities equal to 8.0 x 10- 8 m2/s and 4.0 x 10- 8 m2/s.
6.2.2 Discussion of Simulation Results
Simulation 1 indicated that the portion of the Magenta dolomite
responding to the influence of the pilot hole/AIS does not exhibit
behavior consistent with homogeneous formation properties. Therefore,
heterogeneous-formation parameters were used in simulation 2 in an
attempt to describe the assumed heterogeneity. However, the
description is probably not unique, and simulation of the pilot hole
drilling/AIS upreaming using models with other geometries, such as a
two-dimensional cartesian flow regime, could result in different
descriptions of the formation properties. Indeed, this is likely the
case as the formation heterogeneities simulated in the heterogeneous
simulations assume radial symmetry. The likelihood of radial symmetry
in formation transmissivity is remote. Furthermore, the abrupt spatial
change in properties used in the GTFM simulations, where the
transmissivity decreases by a factor of two at a discrete boundary, is
also unlikely.
6-15
The physical basis for a formation-heterogeneity boundary in the
Magenta is not immediately evident. Only a limited number of test
wells are completed to the Magenta and extensive aquifer testing of
this unit has not been performed (Mercer, 1983). While core samples
from the Magenta indicate a rather uniform geologic character to this
formation, Snyder (1985) describes patterns of halite dissolution in
the Rustler Formation which may have led to fracturing of the Magenta.
Areal differences in fracturing of the formation, such as could develop
in response to halite dissolution, could result in heterogeneity in the
areal distribution of the formation's hydrogeologic properties. This
heterogeneity could affect its fluid-pressure response to major
hydraulic stresses.
Notwithstanding the preceding discussion, the high sensitivity of
simulated formation response to changes in the heterogeneity properties
indicates that formation transmissivities used in the heterogeneous
formation-characterization simulations give a reasonable approximation
of effective formation properties for the Magenta dolomite near the
AIS. Therefore, the inner- and outer-zone transmissivities of
8.0 x 10- 8 m2/s and 4.0 x 10- 8 m2/s are considered representative of
the effective transmissivities for the Magenta dolomite in that area.
6.3 Forty-Niner Claystone
The analysis of the H-16 fluid-pressure response of the Forty-niner
Member of the Rustler Formation in H-16 was performed with the same
procedures used to analyze the Magenta dolomite's response (see Section
6.2). Although the entire Forty-niner was monitored in H-16, the fluid
pressure response was assumed to be derived from the Forty-niner
claystone unit (see Beauheim, 1987a for Forty-niner drill-stem-test
results) . The basic methodology for all simulations is described in
Section 5.2 with certain modifications as described in the following
paragraphs.
6-16
The H-16 fluid-pressure response (Figure 6.24) was the only observed data
with which to compare the simulated results. No flow-rate measurements
were made from the Forty-niner at the AIS. Geologic mapping of the
Forty-niner interval in the AIS indicated only that the unit was "moist"
(R. Ho 1 t and R. Williams, International Technologies, personal
communication, October 26, 1988). As was the case for the Cu1ebra and
Magenta dolomites, because of the complex drilling/reaming-period
history, the Forty-niner's simulated fluid-pressure response at a radius
equivalent to the distance between the AIS and H-16 was compared to the
observed fluid-pressure response in H-16 primarily for the period after
penetration of the underground facility by the pilot hole.
Unlike that of the more permeable Cu1ebra and Magenta dolomites, the
Forty-niner claystone's H-16 fluid-pressure response to events in the AIS
was often delayed by periods of a day or more. For example, according to
the DDR, the Forty-niner interval was penetrated on December 11, 1987
(Calendar Day 345) while the observed H-16 formation fluid pressure did
not definitively deviate from the constant pre-drilling pressure until
Calendar Day 347. Consequently, a direct connection between an event
described in the DDR and the Forty-niner's resulting H-16 fluid-pressure
response was sometimes difficult to establish. Therefore, the DDR was
used to determine segment durations and the Forty-niner's H-16 f1uid
pressure response was used only to corroborate the timing of events.
Preliminary simulations indicated that the Forty-niner interval exhibited
similar but more extreme heterogeneous behavior than that previously
described for the Magenta dolomite. Consequently, the simulation
approach for the Forty-niner claystone was identical to that performed
for the Magenta dolomite. We11bore boundary conditions for the Forty
niner claystone simulations were specified in a similar manner as
discussed for the Cu1ebra dolomite in Section 6.1.1. Like the Magenta
6-17
dolomite, the simulation period for the Forty-niner claystone was divided
into eight discrete time segments (Figure 6.24), the first six of which
covered the drilling/reaming phase (Figures A.17 to A. 26, Appendix A).
The observed H-16 fluid-pressure response for the drilling/reaming period
covered the first six segments as shown on Figure 6.25. Segments 1, 3,
5, and 6 of the drilling/reaming period were simulated with fixed
we11bore-pressure boundary conditions. As discussed in Section 6.2.1 for
the Magenta simulations, some of the simulations did not require the use
of filter-cake skin to reproduce the H-16 pressure response. The period
durations and reduced pressures applied for segments 1, 3, 5, and 6 of
each simulation of the drilling/reaming period are given in Table 6.3.
Specified- flow boundary conditions with a flow rate of 0.0 L/s were
applied for segments 2 and 4 to simulate the effects of flow loss due to
mud settling and cementation, respectively. Figures A.17 through A.26
display the prescribed (segments 1, 3, 5, and 6) and simulated (segments
2 and 4) we11bore pressures for each of the Forty-niner claystone
simulations and the simulated formation fluid pressure at H-16 for the
drilling/reaming period. (Note that when the Forty-niner was isolated
from the borehole during cementation, the formation's fluid-pressure
response was simulated with a specified 0.0 L/s boundary condition
simulating flow loss from the lower pressured borehole.)
The Forty-niner' s formation fluid pressure observed at H-16 before the
start of the drilling of the pilot hole was 0.796 Mpa (Figure 6.25).
This pressure was used as the static formation pressure for the Forty
niner claystone simulations. This pressure was observed during the pre
construction period, indicating that the selected formation pressure was
representative of the interval.
6-18
6.3.1 Simulation Results
Ten simulations of the Forty-niner claystone's fluid-pressure response
in H-16 were conducted. Two simulations evaluated the need for a
formation-heterogeneity boundary and eight simulations evaluated the
sensitivity of the results to the formation-heterogeneity parameters.
The Forty-niner claystone simulations are described as follows.
Simulation 1 - Match to the H-16 Fluid-Pressure Response,
Homogeneous Formation
The goal of the first simulation was to match the Forty-niner's H-16
fluid-pressure response using homogeneous formation properties. A
simulated transmissivity of 4.0 x 10- 7 m2/s resulted in the best match
as shown in Figure 6.26. The match offers a very poor fit to all
portions of the observed H-16 fluid-pressure response except for the
very late-time portion of the post-interception/pre-upreaming period.
The simulated flow rate from the Forty-niner to the AIS on Calendar Day
667 was 0.033 L/s, just slightly lower than the measured flow rate for
the Culebra interval, and inconsistent with the geologist's report that
the Forty-niner interval was only "moist".
Like the first simulation of the Magenta dolomite's fluid-pressure
response in H-16 (Section 6.2.1), the results of the Forty-niner
simulation indicated that the Forty-niner claystone interval was
exhibiting a fluid-pressure response characteristic of a strongly
heterogeneous formation.
6-19
Simulation 2 - Match to the H-16 Fluid-Pressure Response,
Heterogeneous Formation
The second Forty-niner simulation assumed a formation-heterogeneity
boundary and the Forty-niner was modeled with two radial zones having
different transmissivities. The inner zone included the portion of the
formation between the we11bore and the heterogeneity boundary. The
outer zone consisted of the portion of the formation between the
heterogeneity boundary and the external boundary of the modeled system.
The heterogeneous-formation simulation was performed with a Ti of 9.0 x
10- 9 m2/s, a To of 1.5 x 10- 9 m2/s, and an ~ of 40 m. Results of the
simulation are shown in Figure 6.27. The match to the H-16 fluid-
pressure response is very good over the entire duration of the pi1ot
hole draining period and is acceptable for the period after
intersection of the interval by upreaming. The simulated flow rate of
5.5 x 10- 4 L/s for Calendar Day 667 is consistent with the "moist"
interval noted during geologic mapping.
After achieving a reasonable match to the Forty-niner claystone's
fluid-pressure response using a formation-heterogeneity boundary,
sensitivity simulations were performed to provide an indication of the
ranges of Ti, To, and rb. Following is a discussion of these
simulations, numbers 3 through 10.
Simulations 3 through 8 - Sensitivity of the Heterogeneity Parameters
of the Simulation of the Forty-Niner's H-16 Fluid-Pressure Response
Six simulations were performed to assess the sensitivity of the Forty
niner simulation using a formation-heterogeneity boundary. For each
simulation, one of the three heterogeneity parameters was changed while
the remaining two parameters were the same as the values used in
simulation 2. The following parameter values were used for the
6-20
respective simulations: simulation 3, Ti - 3.0 x 10- 9 m2/s; simulation
4, Ti - 3.0 x 10- 8 m2/s; simulation 5, To - 5.0 x 10- 10 m2/s;
simulation 6, To - 5.0 x 10- 9 m2/s; simulation 7, r'b - 20 m; and
simulation 8, r'b - 80 m. Simulation results are shown on Figures 6.28
through 6.31. Figures 6.28, 6.29, and 6.30 show the simulated results
for simulations 3 and 4, 5 and 6, and 7 and 8, respectively, for the
entire simulation period. Figure 6.31 contains semi-log plots
comparing the results of the sensitivity simulations with the best
match simulation for the period between penetration of the underground
faci1i ty and the interception of the Forty-niner interval during
upreaming. In general, the heterogeneous sensitivity simulations for
the Forty-niner interval show results similar to those of the
corresponding Magenta dolomite simulations. For simulations 3, 6, and
8, the H-16 fluid-pressure response during the drilling/reaming period
could not be matched, and therefore the results for the period after
penetration of the underground facility are not directly comparable.
However, the shape of the simulated f1uid-pressure-response curve
yields results similar to the Magenta dolomite simulations. Due to the
more extreme permeability contrast between the inner and outer zones,
the Forty-niner heterogeneous best-match simulation shows more
sensitivity to the heterogeneity parameters than did the Magenta best
match simulation.
Simulations 9 and 10 - Homogeneous-Formation Characterization Showing
Sensitivity to Ti and To of the Best-Match Heterogeneous
Characterization
Simulations 9 and 10 illustrate the Forty-niner's fluid-pressure
response using a homogeneous-formation characterization with formation
transmissivities of 9.0 x 10- 9 m2/s and 1.5 x 10- 9 m2/s, the inner-zone
and outer-zone transmissivities of the best-match heterogeneous
6-21
characterization, respectively. Results of these simulations are shown
on Figure 6.32. Even though full-borehole mud pressure was applied for
the entire duration of each fixed-pressure segment of the
drilling/reaming period, the observed formation-fluid pressure at H-16
could not be matched. This provides further indication of the
heterogeneous nature of the Forty-niner interval.
6.3.2 Discussion of Simulation Results
The poor matches of all simulations using a homogeneous-formation
characterization, and the sensitivity of the simulation results to
variance in the parameters defining the heterogeneities, provide
conclusive evidence of heterogeneous behavior of the Forty-niner
claystone. The accuracy of the assumed heterogeneity geometry is
subj ect to the same uncertainties discussed in Section 6.2.2 for the
Magenta dolomite. However, as for the Magenta dolomite simulations,
the formation transmissivities used in the heterogeneous-formation
characterization simulations probably provide a reasonable
approximation of effective formation properties for the Forty-niner
claystone. The inner-zone and outer-zone transmissivities of
9.0 x 10- 9 m2/s and 1.5 x 10- 9 m2/s, respectively, can therefore be
considered representative of effective transmissivities of the Forty
niner claystone in the area near the AlS.
As discussed in Section 6.2.2, the physical basis for the existence of
a radial formation-heterogeneity boundary in the Forty-niner is not
readily apparent. The fluid-pressure response of the Forty-niner
suggests that a type of heterogeneity may exist in the Forty-niner.
The heterogeneity could be the result of areal differences in the
sedimentary fabric of the Forty-niner claystone.
6-22
1.50
------.. 1.00 0 0... 2 '---"
w 0::: ~ (f) (f) w 0::: 0...
0.50
0.00 200
+++++ unnamed lower member xxxxx Culebra /::;/::;/::;/::;/::; Tamarisk 00000 Magenta 00000 Forty-Niner
300 400 500 600 TIME (1987 CALENDAR DAYS)
700
TIME 0 JANUARY 1. 1987
Drawn by J.D.A. Date 2/27/89
Checked by G. S . Date 2/27/89
Revisions Date
H09700R876 2/27/89
I NrtILl\ Technologies
OBSERVED FLUID-PRESSURE RESPONSES OF THE FIVE MEMBERS OF THE RUSTLER FORMATION AT OBSERVATION-WELL H-16 DURING THE CONSTRUCTION OF THE AIS
Figure 6.1
6-23
1.4 Time Segments Used in Simulations
- 112131r' I
6
1.2 -
-
,,~ 1.0 -
..--.... J"o\<~\
x x 0 f 0... 1 :2
'-..-/ 0.8 -W 0:::: -:J (/) (/) 0.6 -w 0:::: 0... -
0.4 -
-
0.2 -
-
0.0
325
t FIRST
PENETRATION OF CULEBRA
xxxxxxxxxxx~x~
x X
x
PENETRATION OF UNDERGROUND FACILITY
l ~l/:XXXx )( x xx x xx >X
1 I DRI LLI NGI I POST REAMING
I POST UPREAMING
REAMING DIAM.=O.37m DIAM.=6.17m
I I I I I I I
sis I
5~5 I
6~5 I
375 425 475 675 TIME ( 1987 CALENDAR DAYS)
TIME 0 = JANUARY 1. 1987
Drawn by J.D.A. Dote 2/27/89
Checked by i3. S . Date 2/27/89
Revisions ABW Date 6/23/89
H09700R876 2/27/89
I N"rtIL'\ Technologies
FLUID-PRESSURE RESPONSE OF THE CULEBRA DOLOMITE OBSERVED AT OBSERVATION-WELL H-16 DURING THE CONSTRUCTION OF THE AIS
I Figure 6.2
6-24
H-1 0.95 -.----------------~~~--------------------~
,.-.... o
0..
0.90 -
2S 0.85 -
w 0::: ::::J (j) (j)
~ 0.80 -0..
0.75 -
0.70 .325
I 375 4i5 4+5 5i5 5+5 5i5
TIME (1987 CALENDAR DAYS)
TIME 0 = JANUARY 1, 1987
575
ERDA-9 0.95 -,------------------~--~~----------------_,
0.90 -
-
~ "20.85 - ! 0.. xX
r\ f 'i<
x
j 1<, x
x >x x x
.2 x x
w S 0.80 -(j) (j) W 0::: 0..
0.75 -
0.70 -
x ><x ~
x I( x
x
~ x x x x x
0.55 I J. 325 .375 4i5 4+5 5i5 5+5 5i5
TIME (1987 CALENDAR DAYS)
TIME 0 = JANUARY 1, 1987
675
Drown by J.D.A. Checked by G.S.
Revisions G.S.
H09700R876
Dote
Dote
Dote
0.95 J
0.90 -
"20.85 -0.. .2
w S 0.80 -(j) (j) w er:: 0..
0.75 -
0.70 -
I !
WIPP-21
xX
* x
0.65 -+---.--.---T,.......+jl-l..----.---r-I-.---.-I-.---,-I-r--,-I-r-I-I .325 375 425 475 525 575 625 575
TIME (1987 CALENDAR DAYS)
2/27/89
2/27/89
616189
2/27/89
I TIME 0 = JANUARY ,\, 1987
I FLUID-PRES~URE RESPONSES OF THE CULEBRA DOLOMITE MEASURED Nf OBSERVATION-WELLS H-l, ERDA-9, AND WIPP-21 DUFING THE CONSTRUCTION OF THE AIS
I NTEIl .. 1\ Technologies Figure 6.3
6-25
1.2
-
~
0 0.-2 '---"
w cr::: 1.0 -=> (}) (}) w cr::: 0.-
1<x
-
DRILLING
0.8 I
350
REPOSITORY PENETRATION
INITIAL PENETRATION
CEMENTATION
x
x
x
\: ~x :.:~ REPENETRATION
CEMENTATION
I tl I
370
DRILLING
I
REAMING
~ x
x
x
x
x x x x
~ REAMI NG
I t I I
TIME (1987 3~0
CALENDAR DAYS)
Drawn by J . D. A .
Checked by G . S .
Revisions
H09700R876
TIME 0 = JANUARY 1. 1987
Date 2/27/89
Dote 2/27/89
Date
2/27/89
FLUID-PRESSURE RESPONSE OF THE CULEBRA DOLOMITE OBSERVED AT OBSERVATION-WELL H-16 DURING THE DRILLING/REAMING PERIOD OF THE CONSTRUCTION OF THE AIS
I NrtIL'\ Technologies Figure 6.4
6-26
........... o
0... 2
1.4
-
1.2 -
-
1.0 -
-
'--'" 0.8 -W FIRST 0:::: => (J)
- ·PENETRATION OF CUlEBRA
(J) 0.6 -w 0:::: 0... -
0.4 -
-
CULEBRA SIMULATION #1
TI = 2.6E-08 m2/s S = 1.0E-05 X = OBSERVED DATA - = SIMULATION
x xxxx~x~ -...,
~
0.2 -
PENETRATION OF UNDERGROfND FACILITY
'\.~~lI(XXX-X--x-x--xx-x-x--x--"'*,~
-
I 0.0
325
DRllll NGI I REAMING
I I I
375
POST REAMING
DIAM.=O.37m
POST UPREAMING
DIAM.=6.17m
I r 1 r I I I I I 625
I
425 475 525 575 675
TIME (1987 CALENDAR DAYS)
TIME 0 = JANUARY 1, 1987
Drawn by J.D.A. Date 2/27/89
Checked by G. S . Date 2/27/89
Revisions Date
H09700R876 2/27/89
I f'lrt..Jt.1\ Technologies
SIMULATED AND OBSERVED FLUID-PRESSURE RESPONSES FOR THE CULEBRA DOLOMITE AT H-16 WITHOUT USING A CEMENT -INVASION SKIN
Figure 6.5
6-27
----... o
0..
0.95
0.90 -
:2 0.85 -'-.../
W 0::: :::) (j) (j)
-
w 0.80 -0::: 0..
-
0.75 -
0.70 I.!. 325 375
H-1
Tf = 2.6E-08 m2/s S = 1.0E-05 X = OBSERVED DATA - = SIMULATION
I I II I I I
425 475 525 575 625 675
TIME (1987 CALENDAR DAYS)
TIME 0 = JANUARY 1, 1987
0.95
0.90 -
CULEBRA SIMULATION #1
ERDA-9
7 x
Tf = 2.6E-08 m2/s S = 1.0E-05 X = OBSERVED DATA - = SIMULATION
0' 0.85 -0..
j*"x x x
XX
:2
w S 0.80 -(j) (j) W 0::: 0..
0.75 -
0.70 -
-
0.65
325
x x x
x *x
'" x * x
x
x
{
4~5 4j5 5~S 5+5 6~S TIME (1987 CALENDAR DAYS)
TIME 0 = JANUARY 1, 1987
675
Drawn by J.D.A.
Checked by G.S.
ReVisions G.S.
H09700R876
0.95
-
0.90 -
0' 0.85 -0.. :2
w S 0.80 -(j) (j) W 0::: 0..
0.75 -
0.70 -
0.65 325
WIPP-21
Tf = 2.6E-08 m2/s S = 1.0E-05 X = OBSERVED DATA - = SIMULATION
x
x x x x
\: '\: ~~
3jS 4i5 4+5 S~S 5j5 6is TIME (1987 CALENDAR DAYS)
675
T1ME 0 = JANUARY 1, 1987
Date 2/27/89
Date 2/27/89
Date 6116/89
2/27/89
SIMULATED AND OBSERVED FLUID~PRESSURE RESPONSES FOR THE CULEBRA, DOLOMITE AT H-l, ERDA-9, AND WIPP-21 USING THE H-16 BEST-MATCH SIMULATION WITHOUT USING A CEMENT -INVASION SKIN
1 NliR_1\ Technologies Figure 6.6
6-29
1.4
-
1.2 -
-
1.0 - ~ ~
~
o 0.. 2
_~I~
'--../ 0.8 - t W FIRST 0::: =::J (f)
- PENETRATION
(f) 0.6 -w 0::: 0.. -
0.4 -
OF CULEBRA
CULEBRA SIMULATION #2
Tf = 1.3E-07 m2/s S = 1.0E-05 X = OBSERVED DATA - = SIMULATION
- PENETRATION OF
0.2 -
-
I 0.0
325
UNOERGRO!"O FACILITY
DRI LUNGI REAMING I I
POST UPREAMING DIAM.=O.37m DIAM.=6.17m
POST REAMI NG
I I I I I I I I I I
425 475 525 575 625
TIME (1987 CALENDAR DAYS) 675
TIME 0 = JANUARY 1, 1987
Drawn by J.D.A. Dote 2/27/89
Checked by G . S . Dote 2/27/89
Revisions Dote
H09700R876 2/27/89
I N1IILI\ Technologies
SIMULATED AND OBSERVED FLUID-PRESSURE RESPONSES FOR THE CULEBRA DOLOMITE AT H-16 USING A CEMENT-INVASION SKIN
Figure 6.7
6-30
.---... o
0...
0.95
~
0.90 -
::::2: 0.85 -'--/
W 0::: ~ (j) (j)
W 0.80 -0::: 0...
0.75 -
0.70
325
I'x l ,
x '" x '"
H-1
Tr = 1.3E-07 m2/s S = 1.0E-05 X = OBSERVED DATA - = SIMULATION
I 375 4~5 4~5 5~5 5~5 6~5
TIME (1987 CALENDAR DAYS)
TIME 0 = JANUARY 1, 1987
675
0.95
0.90 -
CULEBRA SIMULATION #2
ERDA -9
x
x x
Tr = 1.3E-07 m2/s
S = 1.0E-05 X = OBSERVED DATA - = SIMULATION
~ 0.85 - I~ x x
0... ::::2: '--/
W 0::: ~ (j) (j) W 0::: 0...
xX x
x X
X *x
'" x !( 0.80 - x
x
x x ~
0.75 -
0.70 -
~ x x x x x
'\
'x~xx
0.65 -+-~I-~ I-~I-I~~-~ I~~I---'---"--I-'I-~I--r--~
325 375 425 475 525 575 625 675
TIME (1987 CALENDAR DAYS)
TIME 0 = JANUARY 1, 1987
Drown by J.D.A.
Checked by G.S.
Revisions G.S.
H09700R876
Date
Dote
Date
0.95
~
0.90 -
~ 0.85 -0... ::::2:
W
5 0.80 -(j)
~ ~ 0::: 0...
0.75 -
0.70 -
0.65
325
xX ')f
x x x
WIPP-21
Tr = 1.3E-07 m2/s S = 1.0E-05 X = OBSERVED DATA - = SIMULATION
x x x x x x
'%. \x
~xx
. 1 I 1 I I' -T I
425 475 525 575 625
TIME (1987 CALENDAR DAYS) 675
TIME 0 = JANUARY 1, 1987
2/27/89
2/27/89
6/6/89
2/27/89
SIMULATED AND OBSERVED FLUID-pr~ESSURE RESPONSES FOR THE CULEBRA DOLOMITE AT H-l, ERDA-9, AND WIPP-21 USING THE ~ -16 BEST-MATCH SIIv1ULMIOI\j USING A CEMENT-INVASION SKI~~
I NTER~ Technologies I
Figure 6.8
6-31
,--..... o
0... 2
1.4
-
1.2 -
-
1.0 -
-
'-...-/0.8 -w
~
-'"~ t
CULEBRA SIMULATION #3
Tf = 6.6E-07 m 2js S = 1.0E-05 X = OBSERVED DATA - = SIMULATION
0:::: ~ (f)
- PENETRATION FIRST ~
OF CULEBRA
(f) 0.6 -w 0:::: 0... -
0.4 -
-
0.2 -
-
0.0 325
I
'''''''X'~~X::XX0X'XXX)(j(X~X~XxC":7x:-C:x=>9<>O<~XXj_
PENETRATION OF
UNDERGROUND FACILITY x x xx x xx X><
DRI LLiNGI
REAMING
1 I I
POST UPREAMING
DIAM.=O.37m DIAM.=6.17m
POST REAMI NG
1 I I I I I I I I I
425 475 525 575 625
TIME (1987 CALENDAR DAYS) 675
TIME 0 = JANUARY 1, 1987
Drawn by J.D.A. Dote 2/27/89
Checked by G. S . Date 2/27/89
Revisions Dote
H09700R876 2/27/89
INitILl\ Technologies
SIMULATED AND OBSERVED FLUID-PRESSURE RESPONSES FOR THE CULEBRA DOLOMITE AT H-16 MATCHING THE CULEBRA-TO-AIS FLOW RATE USING A CEMENT -INVASION SKIN
Figure 6.9
6-32
o CL
0.95
0.90
:2 0.85 '--"
W 0:: =:) (j) (j)
~ 0.80 CL
0.75
0.70 325
H-1
Tf 6.6E-07 m2/s S = 1.0E-05 X = OBSERVED DATA - = SIMULATION
~x~ 'k x
" "'~xx
375 425 475 525 575 625
TIME (1987 CALENDAR DAYS)
TIME 0 = JANUARY 1, 1987
0.95
0.90
~0.85 CL :2 '--"
W 0:: 0.80 =:) (j) (j) W a:::: CL
0.75
0.70
0.65 675
j*>< xX
325
x x x x
x >Kx
'" x
* x x
x x
'):
CULEBRA SIMULATION #3
ERDA -9
Tf = 6.6E-07 m2/s S = 1.0E-05 X = OBSERVED DATA - = SIMULATION
~ x x x x x
375 425 475 525 575 625
TIME (1987 CALENDAR DAYS) 675
0.95
0.90
~ 0.85 CL :2
w S 0.80 (j) (j) W 0:: CL
0.75
0.70
0.65
x ,i"'x
325
x x x
x
WIPP-21
Tf = 6.6E-07 m2/s S = 1.0E-05 X = OBSERVED DATA - = SIMULATION
x x
x x x
\;
'~.
375 425 475 525 575 625
TIME (1987 CALENDAR DAYS) 675
TIME 0 = JANUARY 1, 1987 TIME 0 = JANUARY i, 1987 ~
I----Dr_aW_"_by __ J_._D_. A_._-+_D_at_e_2_'_2 _7 '_8_9-1S I M U LATED AN D OBSERVED FLU I D - PR ES SU R E RESPONSES FOR Checked by G.S. Date 2'27'89 THE CULEBRA DOLOMITE AT H-l, ERDA-9, AND WIPP-21
1-----------+---------1USING THE H-16 BEST-MATCH SIMULATION MATCHING THE Revisions G.S. Date 6'6'89 CULEBRA-TO-A!IS FLOW RATE USING A CEMENT -INVASION
I----H-O-9-7-0-0-R-8-7-6---+---2-'-27-'-8-9-iSKIN
I NTiR_" Technologies Figure 6.10
6-33
1.4
-
1.2 -
-
1.0 -
w FIRST
CULEBRA SIMULATION #4
Tf = 2.6E-07 m2 js S = 1.0E-05 X = OBSERVED DATA - = SIMULATION
0:::: ~ (/)
_ PENETRATION
~ 0.6 -0:::: 0... -
0.4 -
-
0.2 -
-
0.0 325
OF CULEBRA
I
PENETRATION OF UNDERGROUND FACILITY
~*xxxx x x xx x xx X'<
t DRILLINGI I REAMING
I I I
375
POST REAMING
DIAM.=O.37m
POST UPREAMING
DIAM.=6.17m
I I I I I I i'l I
425 475 525 575 625 675
TIME (1987 CALENDAR DAYS)
TIME 0 = JANUARY 1. 1987
Drown by J.D.A. Date 2/27/89
Checked by G. S . Date 2/27/89
Revisions Date
H09700R876 2/27/89
I'Nr~ Technologies
SIMULATED AND OBSERVED FLUID-PRESSURE RESPONSES FOR THE CULEBRA DOLOMITE AT H-16 MATCHING THE H-1 FLUID-PRESSURE RESPONSE USING A CEMENT-INVASION SKIN
Figure 6.11
6-34
H-1 0.95 -r----------------~~~--------------------~
o 0..
0.90
:2 0.85 '-.../
w n:: =:=J IJ) IJ)
~ 0.80 0..
0.75
0.70
325
x
'~l
Tf 2.6E -07 m2/s S = 1.0E-05 X = OBSERVED DATA - = SIMULATION
375 425 475 525 575 625
TIME (1987 CALENDAR DAYS)
TIME 0 = JANUARY 1, 1987
675
0.95
0.90
0 0 .85 0.. :2 '-.../
W n:: 0.80 =:=J IJ) IJ) w n:: 0..
0.75
0.70
0.65
t~ xX
x X
x x
x
CULEBRA SIMULATION #4
ERDA-9
x x x X
*x ~
* x
1< x
'x ~x
Tf = 2.6E-07 m2/s S = 1.0E-05 X OBSERVED DATA - = SIMULATION
x x x x x
1: ~X
325 375 425 475 525 575 625
TIME (1987 CALENDAR DAYS)
TIME 0 = JANUARY 1, 1987
Drown by J.D.A.
Checked by G. S.
Revisions G.S.
H09700R876
0.95
0.90
0 0 .85 0.. :2 '-.../
W
5 0.80 IJ) IJ) w n:: 0..
0.75
0.70
0.65 675
Date 2/27/139
Dote 2/27/89
Date 6/6/89
2/27/89
I N1I.R~ Technologies
() WIPP-21
Tf = 2.6E-07 m2/s S = 1.0E-05 X = OBSERVED DATA - = SIMULATION
x/'§ x x x
,x x
X , X x
325
x x ~ x x
xX ~
'ix
'X""" x x x x x x
\;
'~.
375 425 475 525 575 625
TIME (1987 CALENDAR DAYS) 675
TIME 0 = JANUARY 1, 1987
SIMULATED AND OBSERVED FLUID-PRESSURE RESPONSES FOR THE CU~EBRA DOLOMITE AT H-1, ERDA-9, AND WIPP-21 MATCHING THE H-l FLUID-PRESSURE RESPONSE USING A CEMENT -INVASION SKIN
Figure 6.12
6-35
1.4
1.2
1.0
~
0 £l. ::<
0.8 w ~
:::J Ul Ul 0.6 w ~ £l.
0.4
0.2
FIRST PENETRATION
OF CUlEBRA
CULEBRA SIMULATION #5
PENETRATION OF UNDERGROUND FACILITY
~XXXXXXXxxxxx~xxxx x
T, = 1.3E-07 m2/s S = 1.0E-05 x = OBSERVED DATA - = SIMULATION
))( x xx x x x xx
0.0 -i----,----,r----,----,----,----,----,----,----,-----,----.----,----,---~
375 DRllll NGI
425 475 525 575 625 675
REAMING I I
TIME (1987 CALENDAR fAYS) POST REAMING DIAM.=O.37m POST UPREAMING DIAM.=6.17m
1.4 -.-----------------------------------------------------------------------,
1.2
CULEBRA SIMULATION #6
T, = 6.6E-07 m2/s S = 1.0E-05
1.0
~
PENETRATION OF UNDERGROUND FACILITY
X = OBSERVED DATA - = SIMULATION
0 £l. ::<
0.8 w ~
:::J Ul Ul
0.6 w ~ (L
0.4
0.2
0.0
325
FIRST PENETRATION OF CUlEBRA
375 425
TIME 0 JANUARY 1, 1987
Drawn by J.D.A. Date 2/27/89
Checked by G. S . Date 2/27/89
Revisions Date
H09700R876 2/27/89
~xxxxxxxxxxxx~xxxx x x x
475 525
TIME (1987 CALENDAR DAYS)
)l( x xx x x x xx
575 625
SIMULATED AND OBSERVED FLUID-PRESSURE RESPONSES FOR THE CULEBRA DOLOMITE AT H-16 SHOWING SENSITIVITY TO THE USE OF A CEMENT-INVASION SKIN
675
I NrtIl.'\ Technologies Figure 6.13
6-36
0.1
r-.... (j)
~ '--""
W I-<t: 0.01 0:::
3: 0 -..l LL
0.001
0.0001
1 -= : ----
-
~ Match to Measured AIS Flow Rate -=1 ~~ ________ ~ = =~Match to H-l Observation-Well ~ =~------------____________ ~R~e~s£P~o~n:s~e~_ ~~ ~H-16 Fluid-Pressure Response =1 ~ with Cement-Invasion Skin
= ~H -1 6 FI u id - Pressure Response Withou t - Cement-Invasion Skin
-= : ---- * - Culebra to AIS Flow Rate 0.056 Lis.
Measured October 28, 1988 -
I I I I 1111I II I 11111I I I I 11111I I I I I 11111 I I
0.01 0.1 1 10 100
TIME SINCE UPREAMING (DAYS)
T!ME 0 = JANUARY 1, 1987
Drawn by J.D.A. Date 2/27/89
Checked by G. S. Date 2/27/89
Revisions Date
H09700R876 2/27/89
I N1I.R .. 1\ Technologies
POST -UPREAMING SIMULATED AND OBSERVED FLOW RATES FROM THE CULEBRA DOLOMITE TO THE AIS USING FOUR VALUES OF TRANSMISSIVITY
I Figure 6.14
6-37
1.4 3 1----- 7 ----~I----- 8 -----; 1112114/-5 -161 ~ - Ti me Segments Used in Si mulati ons
1.2 - ~: x ~ x
! \X x - x
x 11 ~
1.0 -~
0 -
~ST 0... :2 '-......-/0.8 -
PENETRATION W
OF MAGENTA 0:::: - , ~ (J) (J) 0.6 -w 0:::: 0... -
0.4 -
- PENETRATION OF
0.2 -
- I DRI LlI NGI REAMING
0.0 I I
330 380 I
FACILITY
POST REAM I NG
DIAM.=O.37m
I I I I I 430 480 530
I
XXx
POST UPREAMING
DIAM.=6.17m
TIME (1987 CALENDAR
5~0 I
DAYS)
TIME 0 = JANUARY 1, 1987
Drawn by J . D. A . Date 2/27/89 Checked by G. S. Date 2/27/89
Revisions ABW Date 6/23/89
H09700R876 2/27/89
I NrtlL'\ Technologies
FLUID-PRESSURE RESPONSE OF THE MAGENTA DOLOMITE OBSERVED AT OBSERVATION-WELL H-16 DURING THE CONSTRUCTION OF THE AIS'
Figure 6.15
6-38
1.4
-
~ 1.2 -0 0..-:2: '--./
W 0::: -=> (f) (f) W 0::: 0..-
FLOW REDUCTION
t I xf-:x I ~xxx
CEMENTATION:Z x
xx
xx
x x
x x
• x
:& x X<\
x
x x x x x
PENETRATION OF UNDERGROUND
FACILITY
x
x
x
x
x
>
> >
X< xx+- REPENETRATION 1.0 - FIRST PENETRATION x
x OF MAGENTA x
x
'" x »«Xxxx~ CIRCULATION RESTORED
x x x xx x~
-CEMENTATION
III REAMING
I DRI LLI NG DRILLING I t I 0.8 I I I I I I
325 345 365 3~5 405
Drawn by J.D.A.
Checked by G. S .
Revisions
H09700R876
TIME (1987 CALENDAR DAYS)
TIME 0 = JANUARY 1, 1987
Date 2/27/89
Date 2/27/89
Date
2/27/89
FLUID-PRESSURE RESPONSE OF THE MAGENTA DOLOMITE OBSERVED AT OBSERVATION-WELL H-16 DURING THE DRILLING/REAMING PERIOD OF THE CONSTRUCTION OF THE AIS
I NTIlt..'\ Technologies Figure 6.16
6-39
MAGENTA SIMULATION #1 1.4
-
&J~ Tf = 2.5E-06 m2js S - 1 .OE -05 -X - OBSERVED DATA 1.2 - :.~
-- - SIMULATION -
-
-----... o
0....
2S FIRST 0.8 - PENETRATI ON
W 0::: :=J !J)
-
!J) 0.6 -w 0::: 0.... -
0.4 -
-
0.2 -
-
0.0
OF MAGENTA
I DRI LLI NG/\ REAMI NG
I I 330 380
I
PENETRATION OF UNDERGROUND FACI LlTY
POST REAMING DIAM.= O.37m
:«x xx x xx-/'
POST UPREAMING DIAM.=6.17m
I I I I I I I I I I
430 480 530 580 630
TIME (1987 CALENDAR DAYS)
TIME 0 = JANUARY 1. 1987
Drawn by J.D.A. Date 2/27/89
Checked by G. S . Date 2/27/89
Revisions Date
H09700R876 2/27/89
I NrtlL'\ Technologies
SIMULATION OF THE MAGENTA DOLOMITE FLUID-PRESSURE RESPONSE AT H-16 DURING THE CONSTRUCTION OF THE AIS USING A HOMOGENEOUS-FORMATION CHARACTERIZATION
Figure 6.17
6-40
o 0... :2
1.4
-
1.2 -
-
'-----' O. 8 -W 0:::: => (f)
-
~ 0.6 -0:::: 0... -
0.4 -
-
0.2 -
MAGENTA SIMULATION #2
x
FIRST PENETRATION OF MAGENTA
~.
PENETRATION OF
UNDERGROUND FACILITY
~
T; = 8.0E-08 mJs To = 4.0E-08 m /s S = 1.0E-05 rb = 40 m X = OBSERVED DATA - = SIMULATION
xoxxxx )oX x xx x xx >2'
- I DRILLINGI I POST REAMING I POST UPREAMING REAMING 01 AM.= O.37m DIAM.= 6.17m
0.0
Drawn by J.D.A.
Checked by G. S .
Revisions
H09700R876
330 I 3~0 I 4jO I 4~0 I 5jO I 5~0 I 6jO I
TIME (1987 CALENDAR DAYS)
TIME 0 = JANUARY 1, 1987
Dote 2/27/89
Dote 2/27/89
Dote
2/27/89
SIMULATION OF THE MAGENTA DOLOMITE FLUID-PRESSURE RESPONSE AT H-16 DURING THE CONSTRUCTION OF THE AIS USING A FORMATION-HETEROGENEITY BOUNDARY
I NrtIL'\ Technologies Figure 6.18
6-41
1.4
1.2
1.0
~
0 0.. :::;:
O.B ~
w IY: :J (f) (f)
0.6 w IY: 0..
0.4
0.2
0.0
1.4
1.2
1.0
~
0 0.. :::;:
0.8 ~
w IY: :J (f) (f)
0.6 w IY: 0..
0.4
0.2
MAGENTA SIMULATION #3 ~ LOWER VALUE OF T j
~~I!\WI PENETRATION OF Ti = 2.5E -08 m2j s To = 4.0E-08 m Is S = 1.0E-05
330
I
FIRST PENETRATION OF MAGENTA
380
DRI LLI NGI REAMING
FIRST PENETRATION OF MAGENTA
UNDERGROUND FACILITY rb = 40 m X = OBSERVED DATA - = SIMULATION
"!ic~xxx xx x x x xX
430 480 530 580 630 I
TIME (1987 CALENDAR DAYS)
POST REAMI NG DIAM.= O.37m I POST UPREAMING DIAM.= 6.17m
MAGENTA SIMULATION #4 HIGHER VALUE OF T j
PENETRATION OF UNDERGROUND FACILITY
Ti = 2.5E-07 m2/s To = 4.0E-08 m Is S = 1.0E-05 rb = 40 m
X = OBSERVED DATA - = SIMULATION
-------- "!ic~xxx><xxx Xl!: X xx x x x xX
0.0 -+----.----,,----,----.----,----,----,-----.----.----,----,----,,----.--~
330 380 430
TIME 0 JANUARY 1, 1987
Drawn by J.D.A. Date 2/27/89
Checked by G . S . Date 2/27/89
Revisions Date
H09700R876 2/27/89
I NrtIL'\ Technologies
480 530 580 630
TIME (1987 CALENDAR DAYS)
SIMULATION OF THE MAGENTA DOLOMITE FLUID-PRESSURE RESPONSE AT H-16 DURING THE CONSTRUCTION OF THE AIS USING A FORMATION-HETEROGENEITY BOUNDARY AND SHOWING SENSITIVITY TO Ti
Figure 6.19
6-42
1.4
l.2
l.0
~
0 a.. :::; ~ 0.8
FIRST w n::: PENETRATION ~ (f) OF MAGENTA (f) w 0.6 n::: a..
0.4
0.2
0.0
330 380
I DRILLING/ REAMING
1.4
l.2
l.0
~
0 a.. :::;
0.8 ~
FIRST w n::: PENETRATION ~ (f) OF MAGENTA (f) w 0.6 n::: a..
0.4
0.2
MAGENTA SIMULATION #5 LOWER VALUE OF To
PENETRATION OF UNDERGROUND FACILITY
430 480 530 I
TIME (1987 CALENDAR DAYS)
T; = 8.0E-08 mfs To = 1.3E-08 m /s S = 1.0E-05 rb = 40 m X = OBSERVED DATA - = SIMULATION
580 630
POST REAMING DIAM.=O.37m I POST UPREAMING DIAM.=6.17m
MAGENTA SIMULATION #6 HIGHER VALUE OF To
PENETRATION OF UNDERGROUND FACI LlTY
T; = 8.0E-08 m2/s To = 1.3E -07 m /s S = 1.0E-05 rb = 40 m
X = OBSERVED DATA - = SIMULATION
l!X~xxx X>« X xx x xx xX
0.0 -+----,----,,----r----.----,----,----,,----r----r----,----,----,-----r--~
.3.30 380 4.30
TIME 0 JANUARY 1, 1987
Drawn by J.D.A. Date 2/27/89
Checked by G. S . Date 2/27/89
Revisions Date
H09700R876 2/27/89
I NrtlL'\ Technologies
480 530 580 630
TIME (1987 CALENDAR DAYS)
SIMULATION OF THE MAGENTA DOLOMITE FLUID-PRESSURE RESPONSE AT H-16 DURING THE CONSTRUCTION OF THE AIS USING A FORMATION-HETEROGENEITY BOUNDARY AND SHOWING SENSITIVITY TO To
Figure 6.20
6-43
~
o 0... :::;;
1.4
1.2
1.0
~ O.B w a:: ::> Vl
t3 0.6 a:: 0...
0.4
0.2
FIRST PENETRATION OF MAGENTA
MAGENTA SIMULATION #7 ~ LOWER VALUE OF rb
PENETRATION OF UNDERGROUND FACILITY T, = 8.0E-08 m2js
To = 4.0E -08 m /s S = 1.0E-05 rb = 20 m X = OBSERVED DATA - = SIMULATION
xx x x x xX
0.0 -+----.----.-----.----.----.----.----.-----.----.----.----.----.----,,--~
1.4
1.2
1.0
~
0 0...
~ O.B w a:: ::> Vl Vl 0.6· w a:: 0...
0.4
0.2
.3.30
I .380
DRILLI NG/ REAMING
FIRST PENETRATION OF MAGENTA
4.30 4BO 5.30 5BO 6.30
I TIME (1987 CALENDAR DAYS)
POST REAMING DIAM.= O.37m I POST UPREAMING DIAM.=6.17m
MAGENTA SIMULATION #8 HIGHER VALUE OF rb
PENETRATION OF UNDERGROUND FACILITY
T, = 8.0E-08 m2js To = 4.0E -08 m /s S = 1.0E-05 rb = 80 m
X = OBSERVED DATA - = SIMULATION
0.0 -+----.----.-----.----.----.----.----.-----.----.----.----.----.----,,--~
330 .3BO 430
TIME 0 JANUARY 1, 1987
Drown by J.D.A. Dote 2/27/89
Checked by G. S . Dote 2/27/89
Revisions Dote
H09700R876 2/27/89
I f'frtIL'\ Technologies
4BO 530 580 630
TIME (1987 CALENDAR DAYS)
SIMULATION OF THE MAGENTA DOLOMITE FLUID-PRESSURE RESPONSE AT H-16 DURING THE CONSTRUCTION OF THE AIS USING A FORMATION-HETEROGENEITY BOUNDARY AND SHOWING SENSITIVITY TO rb
Figure 6.21
6-44
o ~
::2'
1.4
1.2
1.0
'--./ 0.8 w n:::: =:J IJ)
~ 0.6 n:::: ~
0.4
0.2
0.01
x
0.1
a
To = 4.0E-08 m2/s S = 1.0E-05 rb = 40 m
T; = 8.0E-08
/' T; = 2.5E-07
10 100
ELAPSED TIME IN DAYS FROM PENETRATION OF THE UNDERGROUND FACILITY
b 1.4 -,------------------------------------------~
o ~
::2'
1.2
1.0
'--./ 0.8 w n:::: =:J IJ)
~ 0.6 n:::: ~
0.4
0.2
T; = 8.0E-08 m2/s S = 1.0E-05 rb = 40 m
/' To 1.3E-08
0.0 -+---,......,~~. I I I ITT~"""" I I I III I I I nTT-rr---
0.01 1 10 100
ELAPSED TIME IN DAYS FROM PENETRATION OF THE UNDERGROUND FACILITY
Drawn by J.D.A.
Checked by G. S.
Revisions
H09700R876
c 1.4 -,-----------+-------------------------------,
1.2
1.0
0 ~
::2' '--./ 0.8 w n:::: =:J IJ) IJ) w 0.6 n:::: ~
0.4
0.2
0.0
0.01
Date 2/ 27/ 8 9
Date 2/27/89
Date
2/27/89
x
0.1
T; = 8.0E-08 m2js To = 4.0E-08 m /s S = 1.0E-05
rb 40
rb 20
m
-'''''-TT Til I I I I I I III
10 100
ELAPSED TIME IN DAYS FFWM PENETRATION OF THE UNDERGROUND FACILITY
SEMI-LOq PLOT OF THE FLUID·-PRESSURE RESPONSE OF THE MAGENTA DOLOMITE AT H···16 SHOWING SENSITIVITY TO T;, To, AND rb DURING THE POST -REAMING DRAINING· PERIOD
I NTIIL '\ Technologies Figure 6.22
6-45
1.4
1.2
1.0
~
0 a... :::;
0.8 ~
w ~
::J Vl Vl 0.6 w ~ a...
0.4
0.2
0.0
FIRST PENETRATION OF MAGENTA
MAGENTA SIMULATION #9 Tf=T, OF BEST MATCH
HETEROGENEOUS SIMULATION
PENETRATION OF UNDERGROUND FACI L1TY
T, = 8.0E-08 m1/s S = 1.0E-05 X = OBSERVED DATA - = SIMULATION
~~xxx Xi)« x xx x xx xX
330 380 430 480 530 580 630
DRILLING/ I
TIME (1987 CALENDAR DAYS)
REAMING 1.4
POST REAMING DIAM.=O.37m I POST UPREAMING DIAM.=6.17m
1.2
1.0
0' a... :::;
0.8 w ~
::J Vl Vl 0.6 w ~
a...
0.4
0.2
FIRST PENETRATION OF MAGENTA
MAGENTA SIMULATION #10 Tf=To OF BEST MATCH
HETEROGENEOUS SIMULATION
PENETRATION OF UNDERGROUND FACILITY
T, = 4.0E-08 m2/s S = 1.0E-05 X = OBSERVED DATA - = SIMULATION
~~>OO¢(xxx »oK X xx x xx xX
0.0 -+----.-----,----r----,----,----,----,,----r----.----,----,-----,----.--~
330 380 430
TIME 0 JANUARY 1, 1987
Drawn by J.D.A. Oate 2/27/89
Checked by G. S . Date 2/27/89
Revisions Date
H09700R876 2/27/89
I NrtIl..'\ Technologies
480 530 580 630
TIME (i 987 CALENDAR DAYS)
SIMULATION OF THE MAGENTA DOLOMITE FLUID-PRESSURE RESPONSE AT H-16 USING A HOMOGENEOUS-FORMATION CHARACTERIZATION AND SHOWING SENSITIVITY OF Tf TO T; AND To OF THE BEST -MATCH HETEROGENEOUS CHARACTERIZATION
Figure 6.23
6-46
1 4
~2~;;~r--- 7-----+1--8------i Y i TIme Segments Used In Simulations
1.2 -
-
~* ~
~ \ ~ - x
1.0 -
i 0.8-J( W - FIRST §5 PENETRATION
(f) 0.6 - OF (f) FORTY-NINER W 0:::: -D...
0.4 -
- PENETRATION OF
0.2 -UNOERGROfO FACILITY
Xx X xx xx ~
-
I DRILLINGI I REAMING
POST REAMING
DIAM.=O.37m
POST UPREAMI NG
01 AM.= 6.17m 0.0 I I I I I I I I I I \
330 380 430 480 530 580 TIME (1987 CALENDAR DAYS)
TIME 0 = JANUARY 1, 1987
Drawn by J.O.A. Date 2/27/89
2/2 71 8 9 FLUID-PRESSURE RESPONSE OF THE FORTY -NINER CLAYSTONE
I-Ch_ec_k_ed---..:bY_G_.S_. __ -+-Dat_e ___ ---I OBSERVED AT OBSERVATION-WELL H-16 DURING THE Revisions ABW Date 6/23/89 CONSTRUCTION OF THE AIS ~-------+-----~
H09700R876 2/27/89
I Nr'tIL'\ Technologies Figure 6.24
6-47
1.3
-
~ 1.1 -0
~ x x
CEMENTATION
~
0..-:2 '----/
W cr:: -=:l (f) (f) w cr:: 0..-
x PENETRATION -: \ # OF UNDERGROUND x >sz.. FACILITY
FLOW REDUCTION ~
~ x REPENETRATION
0.9 -FIRST I I x PENETRATION OF FORTY-NINER ~ x
\ X* "xx Xl _ X+- CIRCULATION RESTORED
x XXXX)¢I§¢(
CEMENTATION
I t I REAMING
I DRILLING DRILLING I 0.7 I I I
3~5 I
3~5 I
325 345 405 TIME (1987 CALENDAR DAYS)
TIME 0 = JANUARY 1, 1987
Drawn by J.D.A. Date 2/27/89
Checked by G. S . Date 2/27/89
Revisions Date
H09700R876 2/27/89
I N'rtIL'\ Technologies
FLUID-PRESSURE RESPONSE OF THE FORTY-NINER CLAYSTONE OBSERVED AT OBSERVATION-WELL H-16 DURING THE DRILLING/REAMING PERIOD OF THE CONSTRUCTION OF THE AIS
Figure 6.25
6-48
1.2
1.0
..-----.... o
Q. 2 0.8 '---"'
W 0::::: ~ (J)0.6 (J) w 0::::: Q.
0.4
0.2
0.0
FORTY-NINER SIMULATION #1
FORTY-NI NER
T S X
PENETRATION OF UNDERGROUND FACILITY
~ I DRILLINGI I
REAMING POST REAMI NG
DIAM.=O.37m
4.0E-07 m2/s 1 .OE -05 OBSERVED DATA SIMULATION
Xx X xx xx
POST UPREAMING DIAM.=6.17m
330 380 430 480 530 580 630
Drawn by J.D.A.
Checked by G. S .
Revisions
H09700R876
TIME (1987 CALENDAR DAYS)
TIME 0 JANUARY 1, 1987
Date 2/27/89
Date 2/27/89
Date
2/27/89
SIMULATION OF THE FORTY-NINER CLAYSTONE FLUIDPRESSURE RESPONSE AT H-16 DURING THE CONSTRUCTION OF THE AIS USING A HOMOGENEOUS-FORMATION CHARACTERIZATION
I N"rtIL'\ Technologies Figure 6.26
6-49
1.2
1.0
~
o D-:2 0.8 '--'"
W 0::::: ::::J (J) 0.6 (J) w 0::::: D-
0.4
0.2
0.0
Drawn by J.D.A.
Checked by G. S .
Revisions
H09700R876
FORTY-NINER SIMULATION #2
"-FIRST PENETRATION
OF FORTY-NINER
PENETRATION OF
UNDERGROUND FACI LlTY
~
Tj = 9.0E-09 m2/s To = 1.5E-09 m /s S = 1.0E-05 rb 40 m X OBSERVED DATA
= SIMULATION
x" x x xx)¢(
DRILLINGI I POST REAMING REAMING DIAM.=O.37m
POST UPREAMING DIAM.=6.17m
330 380 430 480 530 580 630
TIME (1987 CALENDAR DAYS)
TIME 0 JANUARY 1. 1987
Date 2/27/89
Date 2/27/89
Date
2/27/89
SIMULATION OF THE FORTY-NINER CLAYSTONE FLUIDPRESSURE RESPONSE AT H-16 DURING THE CONSTRUCTION OF THE AIS USING A FORMATION-HETEROGENEITY BOUNDARY
I N1IILI\ Technologies Figure 6.27
6-50
1.2
1.0
0 Q., 0.6 ::::< ~
w 0:: => Vl 0.6 Vl w 0:: Q.,
0.4
0.2
0.0
1.2
1.0
-----0 Q., 0.8 ::::< ~
w 0:: => Vl 0.6 Vl w 0:: Q.,
0.4
0.2
0.0
FIRST PENETRATION
OF FORTY -NI NER
330 380
I DRILLINGI REAMING
PENETRATION
OF FORTY-NINER
330 380
FORTY-NINER SIMULATION #3
~ LOWER VALUE OF T;
PE NETRATION OF UNDERGROUND FACILITY
Ti = 3.0E -09 m/s To = 1.5E-09 m /s S = 1.0E-05 rb = 40 m X = OBSERVED DATA - = SIMULATION
** * * * ** *
430 480 530 I 580 630
TIME (1987 CALENDAR DAYS) POST REAMING DIAM.=O.37m IpOST UPREAMING DIAM.=6.17m
FORTY-NINER SIMULATION #4 HIGHER VALuE OF T;
Ti = 3.0[-08 m2/s To = 1.5E-09 m /s S = 1.0[-05 rb = 40 m X = OBSERVED DATA - = SIMULATION
** *' *' *' ** *
430 480 530 580 630
TIME (1987 CALENDAR DAYS)
TIME 0 JANUARY 1. 1987
Drawn by J . D. A. Dote 2/27/89
Checked by G. S . Dote 2/27/89
Revisions Dote
H09700R876 2/27/89
I NrtIL'\ Technologies
SIMULATION OF THE FORTY-NINER CLAYSTONE FLUIDPRESSURE RESPONSE AT H-16 DURING THE CONSTRUCTION OF THE AIS USING A FORMATION-HETEROGENEITY BOUNDARY AND SHOWING SENSITIVITY TO Tj
Figure 6.28
6-51
1.2
1.0
~
0 CL O.B :::;: ~
w a::: ::> (/) 0.6 (/) w a::: CL
0.4
0.2
0.0
1.2
1.0
~
0 CL 0.8 :::;: ~
w a::: ::> (/) 0.6 (/) w a::: CL
0.4
0.2
0.0
FIRST PENETRATION
OF FORTY-NINER
330 380
I DRI LLI NG/ REAMING
FIRST PENETRATION
OF FORTY-NINER
330 380
FORTY-NINER SIMULATION #5
~ LOWER VALUE OF To
PENETRATION OF UNDERGROUND FACI LITY
T; = 9.0E-09 m2/s To = 5.0E-10 m /s S = 1.OE-05 fb = 40 m X = OBSERVED DATA - = SIMULATION
Xx x x x xx x
430 480 530 580 630 I
TIME (1987 CALENDAR DAYS)
POST REAMING DIAM.=O.37m IpOST UPREAMING DIAM.=6.17m
FORTY-NINER SIMULATION #6 HIGHER VALUE OF To
T; = 9.0E-09 m2/s To = 5.0E-09 m /s S = 1.0E-05 fb = 40 m X = OBSERVED DATA - = SIMULATION
Xx x x x xx x
430 480 530 580 630
TIME (1987 CALENDAR DAYS)
TIME 0 JANUARY 1, 1987
Drown by J.D.A. Date 2/27/89
Checked by G. S . Dote 2/27/89
Revisions Dote
H09700R876 2/27/89
I NrtIL'\ Technologies
SIMULATION OF THE FORTY-NINER CLAYSTONE FLUIDPRESSURE RESPONSE AT H-16 DURING THE CONSTRUCTION OF THE AIS USING A FORMATION-HETEROGENEITY BOUNDARY AND SHOWING SENSITIVITY TO To
Figure 6.29
6-52
1.2
1.0
~
o CL 0.8 :::;; ~
w 0:: :J ~ 0.6 w a: CL
0.4
0.2
FIRST PENETRATION
OF FORTY-NINER
FORTY-NINER SIMULATION #7 LOWER VALUE OF r b
PENETRATION OF UNDERGROUND FACILITY
T; = 9.0E-09 m2js To = 1.5E-09 m /s S = 1.OE-OS rb = 20 m
X = OBSERVED DATA - = SIMULATION
Xx x x X >0< X
0.0 ~----,-----,----.----.----.----,-----,----,----.----.----.----,----,---~
330 430 480 530 I 580 630
I 380
DRI LLI NGI REAMI NG
TIME (1987 CALENDAR DAYS)
POST REAMING DIAM.=O.37m IpOST UPREAMING DIAM.=6.17m
FORTY-NINER SIMULATION #8 1.2
1.0
o CL 0.8 :::;; ~
w a: :J ~ 0.6 w a: CL
0.4
0.2
0.0
330
FIRST PENETRATION
OF FORTY -NI NER
380 430
TIME 0 JANUARY 1, 1987
Drawn by J.D.A. Date 2/27/89
Checked by G. S . Date 2/27/89
Revisions Date
H09700R876 2/27/89
I NrtILl\ Technologies
OF rb
480 530
T; = 9.0E-09 m2js To = 1.SE-09 m /s S = 1.0E-OS rb = 80 m X = OBSERVED DATA - = SIMULATION
Xx x X x xx x
580 630
TIME (1987 CALENDAR DAYS)
SIMULATION OF THE FORTY-NINER CLAYSTONE FLUIDPRESSURE RESPONSE AT H-16 DURING THE CONSTRUCTION OF THE AIS USING A FORMATION-HETEROGENEITY BOUNDARY AND SHOWING SENSITIVITY TO fb
Figure 6.30
6-53
1.4 -,-________ --=a'----_________ --,
o o~
::;:;
1.2
1.0
'---' 0.8 w a: ::J Ul t3 0.6 a: (l
0.4
0.2
Ti I. 2
3.0E-08 m /5
Ti
To = 1.5E-09 m2/s S = 1.0E-05 rb = 40 m X = OBSERVED DATA - = SIMULATION
/ 30E-09 m /5
0.0 - I I I I I
0.01 0.1 10 100
ELAPSED TIME IN DAYS FROM PENETRATION OF THE UNDERGROUND FACILITY
o (l ::;:;
1.4
1.2
1.0
'---' 0.8 w a: ::J Ul t3 0.6 a: (l
0.4
0.2
0.0
0.01
b
x_
To = ;(5E-09 m2/s
To = 5.0E-09 m2/s/
Ti == 9.0E-09 m2/s S == 1.0E-05 rb == 40 m X == OBSERVED DATA - == SIMULATION
111 IIIIIII I IIIIIIII IIIIII
0.1 1 10 100
ELAPSED TIME IN DAYS FROM PENETRATION OF THE UNDERGROUND FACILITY
Drawn by J.O.A.
Checked by G.S.
Revisions
H09700R876
C 1.4 -r--------~--------~~------------------~
,.---.. o (l ::;:;
1.2
1.0
'-.-/ 0.8 w a: ::J Ul t3 0.6 a: (l
0.4
0.2
80 ml
Ti == 9.0E-09 m2/s To == 15E-09 m /s S == 10E-05 X == OBSERVED DATA
SIMULATION
0.0 -+---'--'''TTTT"Tr---'-''rTTTTi'-rTTTrt III I I I IlTfTi
0.01
Date 2/27/89
Date 2/27/89
Date
2/27/89
0.1 1 10 100
ELAPSED TIME IN DAYS FROM PENETRATION OF THE UNDERGROUND FACILITY
SEMI-LOG PLOT OF THE FLUID-PRESSUf~E RESPONSE OF THE FORTY-NINER CLAYSTONE AT H-16 SHOWING SENSITIVITY TO Ti, To, AND rb DURING THE POST -REAMING DRAINING PERIOD
I NTER ... I\ Technologies Figure 6.31
6-55
~
0 0-:::. ~
w 0:: :::> Vl Vl w 0:: 0-
~
0 0-:::. ~
w 0:: :::> Vl Vl w 0:: 0-
1.2
1.0
0.8
0.6
0.4
0.2
0.0
330
I 1.2
1.0
0.8
0.6
0.4
0.2
FIRST PENETRATION
OF FORTY-NINER
380
DRILLINGI
FORTY-NINER SIMULATION #9
430 480 530 I
T, = 9.0E-09 m2/s S = 1.0E-05 X = OBSERVED DATA - = SIMCLATION
xxx xXxxx
580 630
REAMING TIME (1987 CALENDAR DAYS)
POST REAMING DIAM.=O.37m IpOST UPREAMING DIAM.=6.17m
FORTY-NINER SIMULATION #10 .A Tf=To OF BEST MATCH
~# _\' HETEROGENEOUS SIMULATION
"
1'-.t PENETRATION OF ~ UNDERGROUND FACILITY x
'x
FIRST PENETRATION
OF FORTY-NINER
T, = 1.5E-09 mIls S = 1.0E-05 X = OBSERVED DATA - = SIMULATION
Xx x x x xx x
0.0 -t--.---,--.---,--r---.---r---.---.----,----.----,-----,_---'
330 380 430 480 530 580 630
TIME (1987 CALENDAR DAYS)
TIME 0 JANUARY 1, 1987
Drawn by J.D.A. D<rte 2/27/89 SIMULATION OF THE FORTY-NINER CLAYSTONE FLUIDPRESSURE RESPONSE AT H-16 USING A HOMOGENEOUSFORMATION CHARACTERIZATION AND SHOWING SENSITIVITY OF T, TO T; AND To OF THE BEST -MATCH HETEROGENEOUS CHARACTERIZATION
Checked by G. S. D<rte 2/27/89
Revisions ABW D<rte 6/23/89
H09700R876 2/27/89
I NTER .. I\ Technologies Figure 6.32
6-56
Simulation Transmissivity Time at Time at Reduced Number Full Mud Reduced Pressure
Overpressure Pressure [m2/s] [hour] [hour] [MPa]
Segment 1 - initial penetration to cementing Total duration - 113.448 hours
1) Tf - 2.6E-08, no cement skin 16.432 97.016 1. 550
2) Tf - 1. 3E-07, cement skiLl 6.432 107.016 1. 380 3) Tf - 6.6E-07, cement skin 3.000 110.448 1.310 4) Tf - 2.6E-07, cement skin 1.000 112.448 1.240
5) Tf - 1. 3E-07 , no cement skin 6.432 107.016 1. 380 6) Tf - 6.6E-07, no cement skin 1.000 112.448 1.240
Segment 3 - post-cement penetration to reaming Total duration - 576.432 hours
1) Tf - 2.6E-08, no cement skin 29.776 546.656 1.500
2) Tf - 1.3E-07, cement skin 19.776 556.656 1. 550 3) Tf - 6.6E-07, cement skin 19.776 556.656 1. 690 4) Tf - 2.6E-07, cement skin 19.776 556.656 1. 760
5) Tf = 1.3E-07, no cement skin 9.776 566.656 1. 370 6) Tf = 6.6E-07, no cement skin 1. 776 574.656 1. 310
Segment 4 - reaming to underground facility penetration Total duration = 141.84 hours
1) Tf - 2.6E-08,
2) Tf = 1.3E-07, 3) Tf = 6.6E-07, 4) Tf - 2.6E-07,
5) Tf - 1.3E-07, 6) Tf = 6.6E-07,
Drown by Dote
Checked by Dote
Revisions Date
I NrtILI\ Technologies
no cement skin 4.800 137.040 1.450
cement skin 4.800 137.040 1.450 cement skin 4.800 137.040 1. 510 cement skin 4.800 137.040 1. 520
no cement skin 1.800 140.040 1.280 no cement skin 2.800 139.040 1.350
Values and Durations of We11bore Pressures Used for Fixed-Pressure We11bore Boundary Conditions During Simulation of the Cu1ebra Do1omi te Drilling/Reaming Period
1 Table 6.1
6-57
Simulation Number
Time at Full Mud Overpressure
[hour]
Time at Reduced Pressure
[hour]
Segment 1 - initial penetration to flow reduction Total duration - 40.0BO hours
Formation-Characterization Simulations 1) Homogeneous O.OBO 2) Heterogenous 22.000
Heterogeneity-Parameter-Sensitivity Simulations 3) Ti - 2.sE-OB m2/s 40.0BO 4) Ti - 2.sE-07 m2/s 5.000 5) To - 1.3E-OB m2/s 22.000 6) To - 1.3E-07 m2/s 40.0BO 7) ~ - 20 m 12.000 B) rb - BO m 40.0BO
40.000 lB.OBO
0.000 35.0BO 1B.OBO 0.000
2B.OBO 0.000
Homogeneous Characterization Showing Heterogeneity Simulation Parameters
Sensitivity to
9) Tf - B.OE-OB m2/s 40.0BO 10) Tf - 4.0E-OB m2/s 40.0BO
Segment 3 - circulation restoration to cementing Total duration - 63.000 hours
Formation-Characterization Simulations 1) Homogeneous 0.500 2) Heterogeneous lB.2s0
Heterogeneity-Parameter-Sensitivity Simulations 3) Ti - 2.5E-OB m2/s 63.000 4) Ti - 2.5E-07 m2/s 3.000 5) To - 1.3E-OB m2/s B.250 6) To - 1.3E-07 m2/s lB.2s0 7) ~ - 20 m B.250 B) ~ - BO m lB.250
0.000 0.000
62.500 44.750
0.000 60.000 54.750 44.750 54.750 44.750
Homogeneous Characterization Showing Heterogeneity Simulation Parameters
Sensitivyt to
9) Tf - B.OE-OB m2/s 23.250 10) Tf = 4.0E-OB m2/s 63.000
39.750 0.000
Reduced Pressure
[MPa]
1.600 2.000
n/a 1.600 1.900 n/a 1.BOO n/a
n/a n/a
1.500 1. 700
n/a 1.400 1.500 1. 950 1.500 1.BOO
1.900 n/a
Drawn by
Checked by
Revisions
Date
Dote
Dote
Values and Durations of Wellbore Pressures Used for Fixed-Pressure Wellbore Boundary Conditions During Simulation of the Magenta Dolomite Drilling/Reaming Period
I tfrtILl\ Technologies 1 Table 6.2
6-58
Simulation Number
Time at Full Mud Overpressure
[hour]
Times at Reduced Pressure
[hour]
Segment 5 - re-penetration to reaming interception Total duration - 799.536 hours
Formation-Characterization Simulations 1) Homogeneous 1.536 2) Heterogeneous 60.000
124.000 674.000 104.712 634.824
Heterogeneity-Parameter-Sensitivity Simulations 3) Ti - 2.5E-08 m2/s 284.712 4) Ti - 2.5E-07 m2/s 4.000 160.712
5) To - 1.3E-08 m2/s 12.000 116.712 6) To - l. 3E-07 m2/s 164.712 7) rb - 20 m 12.000 152.712 8) rb - 80 m 116.712
Homogeneous Characterization Showing Heterogeneity Simulation Parameters
9) Tf - 8.0E-08 m2/s 140.712 10) Tf - 4.0E-08 m2/s 236.712
Sensitivity to
514.824 634.824 670.824 634.824 634.824 682.824
658.824 562.824
Reduced Pressure
(MPa]
l. 700 l. 520 l. 800 l. 520
l. 950 l. 450 l. 330 l. 600 l.400
l. 850 l. 700 l. 500
1.600
l. 720 1.850
Segment 6 - reaming interception to underground facility penetration Total duration - 154.656 hours
Formation Characterization Simulations 1) Homogeneous 0.656 2) Heterogeneous 19.992
Parameter-Sensitivity Simulations 3) Ti - 2.5E-08 m2/s 154.656 4) Ti - 2.5E-07 m2/s 3.992 5) To = 1.3E-08 m2/s 15.992 6) To - 1.3E-07 m2/s 67.992 7) rb - 20 m 10.992 8) ~ = 80 m 31.992
Homogeneous Characterization Showing Heterogeneity Simulation Parameters
9) Tf - 8.0E-08 m2/s 43.992 10) Tf - 4.0E-08 m2/s 67.992
Sensitivity to
154.000 134.664
0.000 150.664 138.664 .86.664 143.664 122.664
110.664 86.664
l. 700 l. 750
n/a 1.450 l. 520 2.000 l. 650 1.800
1.900 2.000
Drawn by
Checked by
Revisions
Date
Date
Date
Wellbore Pressures and Durations used for Fixed Pressure Well-bore Boundary Conditions During Simulation of Magenta Dolomite Drilling/Reaming Period
I NrtIL'\ Technologies Table 6.2 (cont.)
6-59
Simulation Number
Time at Full Mud Time at Reduced Overpressure
[hour] Pressure
[hour]
Segment 1 - initial penetration to flow reduction Total duration - 48.000 hour
Calibration Simulations 1) Homogeneous 2) Heterogeneous
0.250 24.000
Heterogeneity Parameter Sensitivity Simulations 3) Ti - 3.0E-09 m2/s 48.000 4) Ti - 3.0E-08 m2/s 4.000 5) To = 5.0E-10 m2/s 24.000 6) To - 5.0E-09 m2/s 24.000 7) rb - 20 m 10.000 8) rb - 80 m 48.000
47.750 24.000
0.000 44.000 24.000 24.000 38.000 0.000
Homogeneous Characterization Showing Sensitivity to Heterogeneity Simulation Parameters
9) Tf - 9.0E-09 m2/s 48.000 10) Tf = 1.5E-09 m2/s 48.000
Segment 3 - circulation restoration to cementing Total duration ~ 90.000 hour
Calibration Simulations 1) Homogeneous 2) Heterogeneous
2.000 90.000
Heterogeneity Parameter Sensitivity Simulations 3) Ti = 3.0E-09 m2/s 90.000 4) Ti = 3.0E-08 m2/s 20.000 5) To = 5.0E-10 m2/s 90.000 6) To = 5.0E-09 m2/s 90.000 7) rb = 20 m 90.000 8) rb = 80 m 90.000
0.000 0.000
88.000 0.000
0.000 70.000 0.000 0.000 0.000 0.000
Homogeneous Characterization Showing Sensitivity to Heterogeneity Simulation Parameters
9) Tf - 9.0E-09 m2/s 90.000 10) Tf = 1.5E-09 m2/s 90.000
0.000 0.000
Reduced Pressure
[MPa]
1.000 1.600
n/a 1.300 1.600 1.600 1.300 n/a
n/a n/a
1.450 n/a
n/a l. 700 n/a n/a n/a n/a
n/a n/a
Drawn by
Checked by
Revisions
Date
Date
Date
Values and Durations of Wellbore Pressures Used for Fixed-Pressure Wellbore Boundary Conditions Durin~ Simulation of the Forty-Niner Claystone Dril11ng/Reaming Period
I NTI.R..,\ Technologies Table 6.3
6-60
Simulation Number
Time at Full Mud Time at Reduced Reduced Pressure
[MPa] Overpressure
[hour] Pressure
[hour]
Segment 5 - re-penetration to reaming interception Total duration - 806.232 hour
Formation Characterization Simulations 1) Homogeneous 5.232 2) Heterogeneous 156.232
801. 000 650.000
Heterogeneity-Parameter-Sensitivity Simulations 3) Ti - 3.0E-09 m2/s 806.232 0.000 4) Ti - 3.0E-08 m2/s 16.232 790.000 5) To - 5.0E-10 m2/s 98.232 708.000 6) To - 5.0E-09 m2/s 806.232 0.000 7) ~ - 20 m 26.232 780.000 8) ~ - 80 m 896.232 0.000
Homogeneous Characterization Showing Sensitivity to Heterogeneity Simulation Parameters
9) Tf - 9.0E-09 m2/s 806.232 10) Tf - 1.5E-09 m2/s 806.232
0.000 0.000
1.670 1. 780
n/a 1. 330 1.650
n/a 1.500
n/a
n/a n/a
Segment 6 - reaming interception to underground facility penetration Total duration - 157.776 hour
Formation Characterization Simulations 1) Homogeneous 2.776 2) Heterogeneous 17.776
155.000 140.000
Heterogeneity-Parameter-Sensitivity Simulations 3) Ti - 3. OE-09 m2/s 157.776 0.000 4) Ti - 3.0E-08 m2/s 1.776 156.000 5) To - 5.0E-10 m2/s 17.776 140.000 6) To - 5.0E-09 m2/s 157.776 0.000 7) ~ - 20 m 4.776 153.000 8) ~ - 80 m 157.776 0.000
Homogeneous Characterization Showing Sensitivity to Heterogeneity Simulation Parameters
9) Tf - 9.0E-09 m2/s 157.776 10) Tf - 1.5E-09 m2/s 157.776
0.000 0.000
1. 700 1. 750
n/a 1.300 1. 600 n/a
1.450 n/a
n/a n/a
Drawn by
Checked by
Revisions
Date
Date
Date
Values and Durations of We1lbore Pressures Used for Fixed-Pressure Wellbore Boundary Conditions Durin~ Simulation of the Forty-Niner Claystone Dri11~ng/Reaming Period
I NTER~ Technologies Table 6.3 (cont.)
6-61
7.0 POTENTIAL LEAKAGE INTO THE AIR-INTAKE SHAFT
GTFM was used to calculate the flow rate to the AIS for each of the three
members of the Rustler whose fluid-pressure responses were analyzed in this
report. Figure 7.1 is a log-log plot of the simulated flow rate from these
members to the AIS versus time since the interval was intercepted by the
up reaming of the AIS for the following simulations: the flow rate from the
Cu1ebra for the best-match simulation with a cement-invasion-skin zone for
the period before upreaming; the flow rate from the Cu1ebra for the best
match simulation with a cement- invasion-skin zone and calibrated to the
single measured flow rate from the Cu1ebra to the AIS after upreaming; the
flow rate from the Magenta for the best-match simulation using a formation
heterogeneity boundary; and the flow rate from the Forty-niner claystone
for the best-match simulation using a formation-heterogeneity boundary.
Also shown on the figure is the measured flow-rate of 0.056 Lis. Note that
the time scale on Figure 7.1 is elapsed time in days since interception by
the upreaming of the AIS, which occurred on different days for each of the
formations.
Assuming that the transmissivity used for the best-match simulation
calibrated to the single measured flow rate is the most representative for
the Cu1ebra, then the order-of magnitude differences in flow-rate estimates
for all the units, as shown on Figure 7.1, are consistent with the
published estimates of transmissivities for these units from observation
well H-16 (Beauheim, 1987a). As an additional comparison, Haug and others
(1987) and LaVenue and others (1988) estimated a s~eady-state water inflow
from the Cu1ebra to a single model grid block representing a composite open
shaft (comprising the open, unsealed time periods of the WHS, C&SH shaft,
and EXS) of 0.085 Lis.
7-1
Figure 7.1 also shows that after about 15 days of drainage, the Forty-niner
claystone flow rate begins to decrease at a higher rate, indicating
transition of the controlling flow regime from the higher permeability
inner or near-field zone to the lower permeability outer or far-field zone.
This transition is more obvious for the Forty-niner than for the Magenta
because the Forty-niner's permeability contrast between the inner and outer
zones is greater than that of the Magenta. However, the derivative of the
flow rate versus time shows a similar transition for the Magenta.
Table 7.1 provides a summary of simulated flow rates on Calendar Day 667
for the four simulations whose estimated flow rates are plotted on Figure
7.1. Table 7.1 also includes two calculations of total combined inflow to
the AIS from all three units analyzed. The first calculation is based on
the best-match simulation with a cement- invasion skin, and the second
calculation is based on the best-match simulation with a cement-invasion
skin and calibrated to the single flow-rate measurement. Using the highest
estimated inflow rates for each unit, and considering the consistent flow
rate decline indicated on Figure 7.1, total estimated inflow from the
Rustler Formation to the unsealed AIS would be less than 0.065 Lis.
7-2
0.1
...--... (f)
3-'-..../
W I-<t 0.01 0::::
S 0 -.J LL
0.001
0.0001
0.01
Drawn by J.D.A.
Checked by G.S.
Revisions ABW
H09700R876
Culebra - Best Match to H-16 Fluid-Pressure Response and Calibrated to Culebra -to-AIS Flow Rate
Culebra - Best Match to H-16 Fluid-Pressure Response with Cement Invasion Skin
Magenta
Forty-Niner
* - Culebra to AIS Flow Rate 0.056 Lis. Measured October 28. 1988
0.1 1 10 100 TIME SINCE UPREAMING (DAYS)
Date 3/15/89
Date 3/15/89
Date 6/23/89
3/15/89
CALCULATED FLOW RATE TO THE AIS VERSUS TIME SINCE UPREAMING FOR THE CULEBRA AND MAGENTA DOLOMITES AND THE FORTY-NINER CLAYSTONE
I NTIR ... " Technologies Figure 7.1
7-3
Rustler Unit
Culebra
Culebra
Magenta
Forty-Niner
Simulation
Best Match to H-16 Fluid-Pressure Response with Cement-Invasion Skin
Best Match to H-16 Fluid-Pressure Response with Cement-Invasion Skin and Calibrated to the Culebra for Culebra to AIS Flow-Rate Measurement
Heterogeneous-Formation Characterization
Heterogeneous-Formation Characterization
Total Rustler Flow Rate Using the Culebra Best-Match Simulation of the H-16 Fluid-Pressure Response with a Cement-Invasion Skin
Total Rustler Flow Rate Using the Culebra Best-Match Simulation of the H-16 Fluid-Pressure Response with a Cement-Invasion Skin and Calibrated to the Culebra to AIS Flow-Rate Measurement
Date
Flow rate [Lis]
1.3E-2
5.8E-2
6.4E-3
5.5E-4
1. 9E- 2
6.5E-2
Drawn by
Checked by
Revisions
Date
Date
Calculated Flow Rates From the Units of the Rustler Formation to the AIS on Calendar Day 667
I NltIL'\ Technologies Table 7.1
7-4
8.0 SUMMARY AND CONCLUSIONS
8.1 General
The effect of the construction of a fourth underground-access shaft, the
AIS, at the WIPP site on the hydrology of the Rustler Formation was
analyzed using the Rustler's fluid-pressure responses at observation-well
H-16, water-level responses at observation wells H-l, ERDA-9, and
WIPP-2l, and a single measurement of the flow rate from the Culebra
dolomite to the AIS. Well H-16 was drilled approximately 17 m northwest
of the AIS and is equipped with a mUltipacker completion tool which
monitors the formation fluid pressure of five packer-isolated members of
the Rustler Formation using downhole pressure transducers. The formation
fluid pressures of the isolated units were recorded before and during the
drilling of the 0.2S-m pilot hole for the AIS, the reaming of the pilot
hole to 0.37-m diameter, and the upreaming (raise boring) of the pilot
hole to a 6.17 -m diameter. The responses of three of the Rustler
members, the Cu1ebra dolomite, the Magenta dolomite, and the Forty-niner,
were analyzed to provide estimates of the hydraulic parameters of these
units near the center of the WIPP site. Fluid-pressure data from the
Tamarisk Member were not analyzed because they did not indicate that the
formation had achieved a stable formation pressure or was proceeding on a
definable trend before the construction of the AIS. The unnamed lower
member did not appear to respond to the construction of the AIS.
Transmissivity estimates for the three Rustler members were obtained
primarily by analyzing their H-16 fluid-pressure responses, as well as
other available response and flow-rate data using the well-test simulator
GTFM. The analysis required separate consideration of the
drilling/reaming period when the pilot hole was filled with drilling
8-1
fluid and the post-reaming/pre-upreaming period when the pilot hole had
penetrated the WIPP-site underground facility and all units were open and
draining to the pilot hole and/or shaft and subject to a zero-wellbore
pressure boundary condition.
The fluid-pressure data for the drilling/reaming period were influenced
by a complex sequence of drilling operations which were affected by
excessive borehole deviation and the use of a bentonite-mud-based-brine
drilling fluid. Drilling the O.25-m-diameter pilot hole included three
periods when borehole intervals, including the units analyzed, were
cemented and redrilled using directional-drilling techniques. In
addition, a drilling-mud-related filter-cake skin appeared to have
developed on the borehole walls of the more permeable units encountered
by the pilot hole during drilling and reaming. The drilling/reaming
periods were analyzed using primarily fixed-pressure wellbore boundary
conditions which corresponded to calculated mud overpressures and reduced
pressures representing the effect of the apparent filter-cake skins. In
addition, specified zero-flow boundary conditions were applied for short
periods to simulate the effects of cementation (which affected all units)
and apparent flow-reduction due to the settling of the fine particles in
the bentonite-mud-based drilling fluid (which affected the Magenta
dolomi te and Forty-niner claystone only). Zero-wellbore-pressure
boundary conditions, corresponding to formation exposure to atmospheric
pressure, were applied to the three units analyzed after the pilot hole
penetrated the WIPP-site underground facility.
The combination of predominantly fixed-wellbore-pressure boundary
conditions and the radial-flow system modeled by GTFM resulted in
simulated formation fluid-pressure responses as a function of formation
diffusivity or transmissivity divided by the storativity. Based on the
available literature on hydrologic tests at the WIPP site (Beauheim,
8-2
1987a, 1987b; Gonzalez, 1983; Mercer, 1983; and Saulnier, 1987b), the
transmissivity of the units analyzed appears to be more variable than the
storativity. Therefore, the approach used for the AlS simulations was to
fix storativity at a representative value for the unit analyzed, and to
use the simulation results to estimate transmissivity. The
transmissivity values which provided the closest match between the
observed and simulated fluid-pressure data were assumed to be
characteristic of the formations being analyzed. Transmissivity
estimates for the three units analyzed are discussed in Section 8.2.
The analysis of the Culebra dolomite's H-16 fluid-pressure response to
the construction of the AlS included fluid-pressure-response simulations
which indicated the presence of a heterogeneity corresponding to a
postulated cement- invasion skin assumed to be caused by cementation
operations during the pilot-hole drilling period.
The analysis of the H-16 fluid-pressure responses of the Magenta and
Forty-niner provided evidence of heterogeneity in these formations. The
heterogeneities were best characterized by considering that the Magenta
and Forty-niner contained near-field and far-field permeability zones
characterized by different transmissivities. A sensitivity analysis of
the simulation results with respect to the parameters characterizing the
heterogeneity, the inner-zone (near-field) transmissivity, the outer-zone
(far-field) transmissivity, and the radius of the heterogeneity boundary,
provided a degree of confidence in the estimated parameter values for the
assumed heterogeneity geometry.
The results of the simulations of the H-16 fluid-pressure responses were
used to estimate the inflow to the AlS from the Cu1ebra and Magenta
dolomites and the Forty-niner claystone. The simulations indicated that
the Culebra provided the majority of the inflow to the AlS, a conclusion
8-3
corroborated by observations in the AIS during geologic mapping. Inflow
from the Magenta dolomite was estimated to be one order of magnitude less
than that from the Culebra, and the inflow from the Forty-niner claystone
was estimated to be one order of magnitude less than inflow from the
Magenta.
8.2 Summary of Transmissivities
Table 8.1 summarizes the results of the analyses of the H-16 fluid
pressure responses of the Culebra and Magenta dolomites and the Forty
niner claystone. All transmissivity values were estimated assuming a
storativity of 1 x 10- 5 .
8.2.1 Culebra Dolomite
Figures 6.7 to 6.12 indicate that the best match between observed and
simulated data for the Culebra dolomite was achieved using a cement
invasion skin and a formation transmissivity ranging from
l.3 x 10- 7 m2/s (0.12 ft 2/day) to 6.6 x 10- 7 m2/s (0.62 ft 2/day).
However, the estimated transmissivity obtained using the single
measurement of the flow rate from the Culebra to the AIS as a
calibration point was 6.6 x 10- 7 m2/s (0.62 ft 2/day), a value
considered to be the most representative of the Culebra' s
transmissivity between the AIS and H-16, and between the AIS and
observation-wells ERDA-9 and WIPP-21. Beauheim (1987a) analyzed the
Culebra's fluid-pressure responses to drill-stem and slug tests in H-16
and reports a range of transmissivity of 9.13 x 10- 7 m2/s (0.85
ft 2/day) to 7.42 x 10- 7 m2/s (0.69 ft2/day). The transmissivity data
from Beauheim (1987a) and the transmissivity values in Table 8.1
indicate that the near-field transmissivity of the Cu1ebra dolomite in
the vicinity of the underground-access shafts is probably between
1 x 10- 7 and 1 x 10- 6 m2/s (0.093 to 0.93 ft 2/day). All the
simulations overestimated the drawdown (i.e., fluid-pressure response)
8-4
for the post-upreaming period during which all the units were open and
draining to the AlS. This lack of correspondence may be due to the
influences of other activities at the WlPP site, most probably due to
pressure recovery from grouting and sealing operations in the WHS, and
possible lesser influences from water-quality sampling in nearby wells
and recovery from the H-ll multipad/tracer test (see Section 4.0).
Table 8.2 shows the Culebra transmissivity ranges for a range of
Culebra storativities from 1 x 10- 6 to 1 x 10-4 using diffusivities
calculated from the results of the analyses presented in this report.
These diffusivi ties are of the same order of magnitude as the
diffusivities used by Stevens and Beyeler (1985) (4.6 x 10- 2 to
9.3 x 10- 2 m2/s) to model the Culebra responses at the H-l and H-3
hydropads during the construction of the C&SH shaft.
8.2.2 Magenta Dolomite
The results of the analyses and simulation of the Magenta dolomite's
H-16 fluid-pressure responses, Figures 6.17 and 6.18, indicate that the
Magenta dolomite is a heterogeneous formation. The inner- and outer
zone transmis s i vi ties were es tima ted to be 8.0 x 10 - 8 m2/s
(0.074 ft 2/day) and 4.0 x 10- 8 m2/s (0.033 ft 2/day), respectively, and
the heterogeneity boundary between the inner and outer zones was
located at a radial distance of 40 m from the center of the AlS. The
Magenta was not involved in any other testing or sampling activities
during the time its fluid-pressure response was analyzed. However,
part of the Magenta's response may have been affected by grouting
operations in the WHS.
Beauheim (1987a) analyzed drill-stem and slug tests of the Magenta in
H-16 and estimated the transmissivity to be 3.01 x 10- 8 m2/s
(0.028 ft2/day) and 2.58 x 10- 8 m2/sec (0.024 ft2/day), respectively.
Because of the potential non-uniqueness of the assumed heterogeneity
geometry, the best-match inner-zone and outer-zone transmissivities
provide only estimates of the range of effective formation
8-5
transmissivities for the Magenta dolomite. Table 8.2 shows the
possible range in estimated Magenta transmissivity for a representative
range of storativity of 1 x 10- 6 to 1 x 10-4 using diffusivities
calculated from the results of the analyses presented in this report.
As with the Culebra results, the Magenta diffusivities are of the same
order of magnitude as those presented in Stevens and Beyeler (1985)
(2.8 x 10- 3 m2/s).
8.2.3 Forty-Niner Claystone
The results of the analyses and simulation of the Forty-niner
claystone's H-16 fluid-pressure responses, Figures 6.26 and 6.27,
indicate that the Forty-niner is a strongly heterogeneous formation,
with a stronger transmissivity contrast than observed for the Magenta
dolomite (see Section 8.2.2). The inner-zone and outer-zone
transmissivities were estimated to be 9.0 x 10- 9 m2 /s
(8.4 x 10- 3 ft 2/day) and l.5 x 10- 9 m2/s (l.4 x 10- 3 ft 2/day),
respectively, and the heterogeneity boundary between the inner and
outer zones was located at a radial distance of 40 m from the center of
the AlS. Beauheim (1987a) analyzed pulse, slug, and drill-stem tests
in H-16 and estimated that the transmissivity of the Forty-niner
claystone ranges from 2.4 x 10-10 m2/s (2.2 x 10- 4 ft 2/day) from the
analysis of a pulse test, to 6.0 x 10- 9 m2/s (5.6 x 10- 3 ft 2/day) from
the analysis of a drill-stem test. As noted in Section 8.2.2 for the
Magenta dolomite, the potential non-uniqueness of the assumed
heterogeneity geometry means that the best-match inner-zone and outer
zone transmissivities for the Forty-niner provide estimates of the
range of its effective formation transmissivities. Table 8.2 shows the
possible range in estimated Forty-niner transmissivity for a
representative range of storativity of 1 x 10- 6 to 1 x 10-4 .
8-6
8.3 Conclusions
The results of the analysis of the H-16 fluid-pressure responses to the
construction of the AIS indicate:
o in the area between the AIS and H-16, the transmissivity of the
Culebra dolomite is approximately one order of magnitude greater
than the transmissivity of the Magenta dolomite, and the Magenta
transmis s i vi ty is one order of magnitude greater than the
transmissivity of the Forty-niner claystone;
o the cementing of the AIS pilot hole to correct excessive borehole
deviation during the drilling period created a cement-invasion skin
in the Culebra dolomite but not in the Magenta dolomite or Forty
niner claystone; cement invasion of the Culebra dolomite was
probably facilitated by its higher permeability and the vuggy,
fractured character of the dolomite which may have allowed easier
penetration of the formation by the cement grout;
o the water-level responses of Culebra observation wells H-l, ERDA-9,
and WIPP- 21 were affected by other hydrologic and construction
activities at the WIPP site, and the analyses of those responses
provided a general indication of the range of formation
transmissivity;
o the analysis of the fluid-pressure responses of the Magenta dolomite
and Forty-niner claystone indicated that both units behave as
heterogeneous formations in the vicinity of the AIS; and
o the estimated long-term flow rate from all of the Rustler units to
the unsealed AIS is less than 0.065 Lis.
8-7
GEOLOGIC UNIT APPLICABLE TRANSMISSIVITY STORATIVITY AREA (m2/s) (ft2/day)
CULEBRA DOLOMITE AIS to H-16 6.6E-7 6.2E-l lE-5 AIS to H-l 6.6E-7 6.2E-l lE-5 AIS to ERDA-9 2.6E-7 2.4E-l lE-5 AIS to WIPP-21 6.6E-7 6.2E-2 lE-5
MAGENTA DOLOMITE AIS to H-16 8.0E-8 7.4E-2 lE-5 >40 m from AIS 4.0E-8 3.7E-2 lE-5
FORTY-NINER AIS to H-16 9.0E-9 8.4E-3 lE-5 CLAYSTONE >40 m from AIS l. 5E-9 l. 4E- 3 lE-5
Drawn by Date Swrunary of the Transmissivities Determined Checked by Date From the Analls is of the Fluid- Pressure Revisions Date
Responses of t e Culebra Dolomite, Magenta Dolomite, and Forty-Niner Claystone
I NltIL'\ Technologies Table 8.1
H09700R876 8-8
DIFFUSIVITY* STORATIVITY TRANSMISSIVITY (TIS) (S) (T) [m js] [ ] [m2js]
CULEBRA 6.6E-02 1. OE-04 6.6E-06 1. OE-OS* 6.6E-07* 2.0E-OS 1. 3E-06 1.0E-06 6.6E-08
2.6E-02 1. OE-04 2.6E-06 1. OE-OS* 2.6E-07* 2.0E-OS S.2E-07 1. OE-06 2.6E-08
1. 3E-02 1.0E-04 1. 3E-06 1. OE-OS* 1.3E-07* 2.0E-OS 2.6E-07 1. OE-06 1. 3E-08
MAGENTA 8.0E-03 1. OE-04 8.0E-07 1. OE-OS* 8.0E-08* 2.0E-OS 1. 6E-07 1. OE-06 8.0E-09
4.0E-03 1. OE-04 4.0E-07 1. OE-OS* 4.0E-08* 2.0E-OS 8.0E-08 1.0E-06 4.0E-09
FORTY-NINER 9.0E-04 1. OE-04 9.0E-08 1.0E-OS* 9.0E-09* 2.0E-OS 1. 8E-08 1. OE-06 9.0E-1O
1. SE-04 1. OE-04 1. SE-08 1. OE-OS* 1. SE-09* 2.0E-05 3.0E-09 1.OE-06 1.SE-1O
* Values Determined From Simulations and Presented on Table 8.1.
Date Drawn by Calculated Transmissivities for a Range of
I-Ch_ec_ke_d_b_y ____ --+-D_o_te ___ --I Storativities Using the Diffusivities From the Results of the Analyses Presented in
~------~-----~ this Report Revisions Date
I Nrt.Il.'\ Technologies Table 8.2
H09700R876 8-9
9.0 REFERENCES
Beauheim, R.L., 1987a. Interpretations of Single-Well Hydraulic Tests
Conducted at and near the Waste Isolation Pilot Plant (WIPP) Site,
1983-1987. Sandia National Laboratories, SAND87-0039, 169 pp.
Beauheim, R.L., 1987b. Analysis of Pumping Tests of the Culebra Dolomite
Conducted at the H-3 Hydropad at the Waste Isolation Pilot Plant (WIPP)
Site. Sandia National Laboratories, SAND86-23ll, 169 pp.
Bechtel National Inc., 1985. Quarterly Geotechnical Field Data Report.
U. S. Department of Energy, Waste Isolation Pilot Plant Office,
Carlsbad, New Mexico, DOE-WIPP-2l8.
Cauffman, T. L., A.M. LaVenue, and J. P. McCord, 1990. Ground-Water Flow
Modeling of the Culebra Dolomite: Volume II - Data Base. Sandia
National Laboratories, Contractor Report SAND89-7068/2.
Colton, 1.D. and J. Morse, 1985. Water Quality Sampling Plan. U.S.
Department of Energy, WIPP-DOE-2l5.
Deshler, R. and R. McKinney, 1988. Construction and Water Inflow Histories
for the Shafts at the Waste Isolation Pilot Plant. IT Corporation,
February 1988, 14 pp.
Gonzalez, D.D., 1983. Hydrogeochemical Parameters of Fluid-Bearing Zones
in the Rustler and Bell Canyon Formations: Waste Isolation Pilot Plant
(WIPP) Southeastern New Mexico (SENM). Sandia National Laboratories,
SAND83-02l0, 37 pp.
9-1
Haug, A., V.A. Kelley, A.M. LaVenue, and J.F. Pickens, 1987. Modeling of
Ground-Water Flow in the Culebra Dolomite at the Waste Isolation Pilot
Plant (WIPP) Site: Interim Report.
Contractor Report SAND86-7l67.
Sandia National Laboratories,
Holditch, S.A., W.J. Lee, D.E. Lancaster, and T.B. Davis, 1983. Effect of
Mud Filtrate Invasion on Apparent Productivity in Drillstem Tests in
Low-Permeability Gas Formations.
Vol. 35, No.2, p. 299-305.
Journal of Petroleum Technology,
Holt, R.M. and D. W. Powers, 1984. Geotechnical Activities in the Waste
Handling Shaft, Waste Isolation Pilot Plant (WIPP) Proj ect,
Southeastern New Mexico. U.S. DOE, WTSD-TME-038.
Holt, R.M. and D.W. Powers, 1986. Geotechnical Activities in the Exhaust
Shaft. U.S. Department of Energy, DOE-WIPP-86-008.
Krueger, R.F., 1986. An Overview of Formation Damage and Well Productivity
in Oilfield Operations.
No.2, p. 131-152.
Journal of Petroleum Technology, Vol. 38,
LaVenue, A.M., A. Haug, and V.A. Kelley, 1988. Numerical Simulation of
Ground-Water Flow in the Culebra Dolomite at the Waste Isolation Pilot
Plant (WIPP) Site: Second Interim Report. Sandia National
Laboratories, Contractor Report SAND88-7002.
Mercer, J. W., 1983. Geohydrology of the Proposed Waste Isolation Pilot
Plant Site, Los Medanos Area, Southeastern New Mexico. U.S. Geological
Survey Water-Resources Investigation Report 83-4016, 113 pp.
9-2
Pickens, J.F., G.E. Grisak, J.D. Avis, D.W. Belanger, and M. Thury, 1987.
Analysis and Interpretation of Borehole Hydraulic Tests in Deep
Boreholes: Principles, Model Development, and Applications. Water
Resources Research, Vol. 23, No.7, p. 1341-1375.
Saulnier, G.J., Jr., 1987a. Appendix F., Review and Chronology of Known
Information of Ground-Water Leakage into the Shafts at the WIPP Site in
Modeling of Ground-Water Flow in the Cu1ebra Dolomite at the Waste
Isolation Pilot Plant (WIPP) Site: Interim Report, By Haug, A. and
others, Sandia National Laboratories, Contractor Report SAND86-7167.
Saulnier, G.J., Jr., 1987b. Analysis of Pumping Tests of the Cu1ebra
Dolomite Conducted at the H-ll Hydropad at the Waste Isolation Pilot
Plant (WIPP) Site. Sandia National Laboratories, Contractor Report
SAND87-7124.
Saulnier, G.J., Jr., G.A. Freeze, and W.A. Stensrud, 1987. WIPP Hydrology
Program Waste Isolation Pilot Plant Southeastern New Mexico.
Hydrologic Data Report #4. Sandia National Laboratories, Contractor
Report SAND86-7166.
Saulnier, G.J., Jr., and J.D. Avis, 1988. Interpretation of Hydraulic
Tests Conducted in the Waste-Handling Shaft at the Waste Isolation
Pilot Plant (WIPP) Site. Sandia National Laboratories, Contractor
Report SAND88-7001.
Snyder, R. P., 1985. Dissolution of Halite and Gypsum, and Hydration of
Anhydrite to Gypsum, Rustler Formation in the Vicinity of the Waste
Isolation Pilot Plant, Southeastern New Mexico. U.S. Geological Survey
Open-File Report 85-229, 11 p.
9-3
Stensrud, W.A., M.A. Bame, K.D. Lantz, A.M. LaVenue, J.B. Palmer, and G.J.
Saulnier, Jr., 1987. WIPP Hydrology Program, Waste Isolation Pilot
Plant, Southeastern New Mexico, Hydrologic Data Report #5. Sandia
National Laboratories, Contractor Report SAND87-7125.
Stensrud, W.A., M.A. Bame, K.D. Lantz, T.L. Cauffman, J.B. Palmer, and G.J.
Saulnier, Jr., 1988a. WIPP Hydrology Program, Waste Isolation Pilot
Plant Southeastern New Mexico, Hydrologic Data Report #6. Sandia
National Laboratories, Contractor Report SAND87-7166.
Stensrud, W.A., M.A. Bame, K.D. Lantz, J.B. Palmer, and G.J. Saulnier, Jr.
198 8b. WIPP Hydrology Program, Waste Isolation Pilot Plant
Southeastern New Mexico, Hydrologic Data Report #7. Sandia National
Laboratories, Contractor Report SAND88-7014.
Stensrud, W.A., M.A. Bame, K.D. Lantz, J.B. Palmer, and G.J. Saulnier, Jr.,
1990, in preparation. WIPP Hydrology Program, Waste Isolation Pilot
Plant Southeastern New Mexico, Hydrologic Data Report #8.
National Laboratories, Contractor Report SAND89-7056.
Sandia
Stevens, K. and W. Beye1er, 1985. Determination of Diffusivities in the
Rustler Formation from Exploratory-Shaft Construction at the Waste
Isolation Pilot Plant in Southeastern New Mexico. U. S. Geological
Survey Water-Resources Investigations Report 85-4020, 32 pp.
Tou1oukian, Y.S., W.R. Judd, and R.F. Roy, 1981. Physical Properties of
Rocks and Minerals. McGraw-Hi11/Cindas Data Series on Material
Properties, Y.S. Tou1oukian and C.Y. Ho, Editors, Volume 11-2, 548 p.
9-4
APPENDIX A:
SPECIFIED AND SIMULATED WELLBORE PRESSURES AND SIMULATED
AND OBSERVED FORMATION FLUID PRESSURES FOR THE
DRILLING/REAMING PERIODS OF THE SIMULATIONS OF THE
H-16 FLUID-PRESSURE RESPONSES OF THE CULEBRA DOLOMITE,
THE MAGENTA DOLOMITE, AND THE FORTY-NINER CLAYSTONE
A-l
CULEBRA SI MULATION ;; 1 2.8
- SIMULATED. AND SPECIFIEDT WELLBORE PRESSURES DURING DRILLING/REAMING PERIOD
-
-2.4 -
-
-
~ -0
(L 2.0 -:::;;:
~
-w (Y -::::> (f) (f) -w (Y 1.6 -(L
-
-
-1.2 -
-
--
0.8
350
1.2
T, S
= 2.6E-08 m2/s = 1.0E-05
I
.-(Lt-2* I 31"------+1- 4y - ~
I 370
Time Segments Used in Simulation
I I 390
TIME (1987 CALENDAR DAYS)
I
SIMULATED H-16 PRESSURE DURING THE DRILLING/REAMING PERIOD
~
0 (L :::;;: ~
w (Y
::::> (f) (f) w (Y (L
-
1.0 -
-
0.8
350
T, = 2.6E-08 m2/s S = 1.0E-05 X = OBSERVED DATA - = SIMULATION
'Xx x x
\
TIME 0 = JANUARY 1, 1987
Drown by J.D.A. Date 2/23/89
Checked by G. S. Date 2/23/89
Revisions ABW Date 6/23/89
H09700R876 2/23/89
I Nrt.R..,\ Technologies
x
~x )(X x'x
x
x
x
I I I
370
TIME (1987 CALENDAR DAYS)
SPECIFIED AND SIMULATED WELLBORE PRESSURES AND SIMULATED AND OBSERVED FORMATION FLUID PRESSURES FOR THE CULEBRA DOLOMITE DRILLING/REAMING PERIOD WITHOUT A CEMENT-INVASION SKIN AND MATCHING H-16 FLUID-PRESSURE RESPONSE
Figure A.1
A-3
x x x x
~
2.B CULEBRA SIMULATION #2
- SIMULATED* AND SPECIFIEDt WELLBORE PRESSURES
--
2.4 -
--
~ -0
a.. 2.0 -:::;
~
-w a:: -::::> (f) (f) -w a:: 1.6 -a..
--
-1.2 -
-
--
O.B
350
T, S
= 1.3E-07 m2/s = 1.0E-05
r
DURING DRILLINGIREAMING PERIOD
~1~2*1 3~-----------1~-4~
I 370
I
Time Segments Used in Simulation
I 390
TIME (1987 CALENDAR DAYS)
I
1.2 -.------------------------------________________________________________ ~
SIMULATED H-16 PRESSURE DURING THE DRILLINGIREAMING PERIOD
-
w ~ 1.0 -(f) (f) w a:: a..
O.B
-
T, = 1.3E-07 m2/s S = 1.0E-05 X = OBSERVED DATA - = SIMULATION
I
350
TIME o = JANUARY 1. 1987
Drawn by JoDoAo Date 2/23/89
Checked by GoS. Date 2/23/89
Revisions ABW Date 6/23/89
H09700R876 2123/89
I N"rt.R.'\ Technologies
I I I I 370 390
TIME (1987 CALENDAR DAYS)
SPECIFIED AND SIMULATED WELLBORE PRESSURES AND SIMULATED AND OBSERVED FORMATION FLUID PRESSURES FOR THE CULEBRA DOLOMITE DRILLING/REAMING PERIOD USING A CEMENT-INVASION SKIN
Figure A.2
A-4
CULEBRA SIMULATION #3 2.8
- SIMULATED* AND SPECIFIEDt WELLBORE PRESSURES DURING DRILLING/REAMING PERIOD
--
2.4 -
--
~ -0
0... 2.0 -:::;:
~
-w 0:: -:::> (fl (fl -w 0:: 1.6 -0...
--
-1.2 -
--
-0.8
350
1.2
T, = 6.6E-07 m2/s S = 1.0E-05
I
~1~2*1 3T-----------I~-4~
I
Time Segments Used in Simulation
TIME (1987 CALENDAR DAYS)
I
SIMULATED H-16 PRESSURE DURING THE DRILLING/REAMING PERIOD
-
w rs 1.0 -(fl (fl w 0:: 0...
0.8
-
T, = 6.6E-07 m2/s S = 1.0E-05 X = OBSERVED DATA - = SIMULATION
I
350
TIME 0 = JANUARY 1. 1987
Drawn by J.D.A. Date 2/23/89
Checked by G. S . Date 2/23/89
Revisions ABW Date 6/23/89
H09700R876 2/23/89
I Nrtll.'\ Technologies
I I
TIME (1987 CALENDAR DAYS)
SPECIFIED AND SIMULATED WELLBORE PRESSURES AND SIMULATED AND OBSERVED FORMATION FLUID PRESSURES FOR THE CULEBRA DOLOMITE DRILLING/REAMING PERIOD WITH A CEMENT -INVASION SKIN AND MATCHING THE CULEBRA-TO-AIS FLOW RATE
1 Figure A.3
A-5
2.8
--
CULEBRA SI MULATION /I 4
SIMULATED. AND SPECIFIED t WELLBORE PRESSURES DURING DRILLING/REAMING PERIOD
-2.4 -
Tr = 2.6E-07 m 2/s S = 1.0E-05
,--142. I 3 t -----+I- 4Y TIme Segments Used
in Simulation --
~ -0
0.. 2.0 -:::;; -
w ~ -::l (/) (/) -w ~ 1.6 -0..
-
-
-
1.2 -
---
0.8
350
1.2
-
~
0 0.. :::;; ~
w ~ 1.0 -::l (/) (/) W ~
0..
-
'Xx
I I I 370
TIME (1987 CALENDAR DAYS)
SIMULATED H-16 PRESSURE DURING THE DRILLING/REAMING PERIOD
Tr = 2.6E-D7 m 2/s
x x
S = 1.0E-05 X = OBSERVED DATA - = SIMULATION
X XlO!(XX
Xx
I
0.8 -r---------,Ir---------~I----------,-I---------.-I--------~I----~
350
TIME 0 = JANUARY 1, 1987
Drawn by J.D.A. Date 2/23/89
Checked by G.S. Date 2/23/89
Revisions ABW Date 6/23/89
H09700R876 2/23/89
I Nlt.R...'\ Technologies
370 390
TIME (1987 CALENDAR DAYS)
SPECIFIED AND SIMULATED WELLBORE PRESSURES AND SIMULATED AND OBSERVED FORMATION FLUID PRESSURES FOR THE CULEBRA DOLOMITE DRILLING/REAMING PERIOD WITH A CEMENT-INVASION SKIN AND MATCHING THE OBSERVATION-WELL RESPONSES
I Figure AA
A-6
CULEBRA SIMULATION #5 2.8
- SIMULATED. AND SPECIFIEDt WELLBORE PRESSURES DURING DRILLING/REAMING PERIOD
-
-2.4 -
--
~ -0
Q 2.0 -:::;:
~
-w 0:': -:::> If) If) -W 0:': 1.6 -Q
--
-1.2 -
-
-
-
0.8
.350
1.2
Tf = 1.3E-07 m2/s S = 1.0E-05
I
~1~2*1 3T----------rl--4~
I
TIme Segments Used in Simulation
TIME (1987 CALENDAR DAYS)
I
SIMULATED H-16 PRESSURE DURING THE DRILLING/REAMING PERIOD
-
w CS 1.0 -If) If) w 0:': Q
Tf = 1.3E-07 m2/s S = 10E-05 X = OBSERVED DATA - = SIMULATION
'Xx x x
-
0.8 I
.350
TIME 0 = JANUARY 1. 1987
Drawn by J.D.A. Date 2/23/89
Checked by G. S. Date 2/23/89
Revisions ABW Date 6/23/89
H09700R876 2/23/89
I N1IIl.,\ Technologies
)~ x
I .370
I
TIME (1987 CALENDAR DAYS)
I
SPECIFIED AND SIMULATED WELLBORE PRESSURES AND SIMULATED AND OBSERVED FORMATION FLUID PRESSURES FOR THE CULEBRA DOLOMITE DRILLING/REAMING PERIOD WITHOUT A CEM~NT -INVASION SKIN AND USING A Tf == 1.3 X 10- m2/s
Figure A.5
A-7
2.8
--
CULEBRA SIMULATION #6 SIMULATED. AND SPECIFIEDt WELLBORE PRESSURES
DURING DRILLING/REAMING PERIOD
T, = 6.6E-07 m2js S = 1.0E-05
r-1t-r2·' 3T----------~1 --4~ -
2.4 -
--
~ -0
0.. 2.0 -:::<
~
-w a::: -::> Ul Ul -w a::: 1.6 -0..
-
--
1.2 -
-
--
0.8
350 I I
370 I
TIme Segments Used in Simulation
TIME (1987 CALENDAR DAYS)
I
1.2 -,----------------------------------____________________________________ ~
SIMULATED H-16 PRESSURE DURING THE
~
0 0.. :::< ~
w a::: ::> Ul Ul w a::: 0..
-
1.0 -
-
0.8
350
'Xx
T, = 6.6E-07 m2js S = 1.0E-05 X = OBSERVED DATA - = SIMULATION
I
TIME 0 = JANUARY 1, 1987
Drawn by J,D.A. Date 2/23/89
Checked by G.S. Date 2/23/89
Revisions ABW Date 6/23/89
H09700R876 2/23/89
I NTIR..,\ Technologies
DRILLING/REAMING PERIOD
I I I I
370 390
TIME (1987 CALENDAR DAYS)
SPECIFIED AND SIMULATED WELLBORE PRESSURES AND SIMULATED AND OBSERVED FORMATION FLUID PRESSURES FOR THE CULEBRA DOLOMITE DRILLING/REAMING PERIOD WITHOUT A CEM~NT -INVASION SKIN AND USING A Tf = 6.6 X 10- m2/s
I Figure A.6
A-a
x x ~
2.8
---
2.4 -
MAGENTA SIMULATION #1
SIMULATED* AND SPECIFIEDt WELLBORE PRESSURES DURING DRILLING/REAMING PERIOD
T, = 2.5E-06 m'/s S = 1.0E-05 1 t Time Segments Used in Simulation
-~ 2~31-4*'~1-----st------+I- 6 t-1
-~ -0 CL 2.0 -:::;: ~
-w 0::: :J -if) if) -w 0::: CL
1.6 -
-
--
1.2 -
-
--
0.8 I I I I I I
325 345 385
TIME (1987 CALENDAR DAYS)
1.4 SIMULATED H-16 PRESSURE DURING THE DRILLING/REAMING PERIOD
-
~ 1.2 -o
CL :::;: ~
w 0::: ::::> if) if) W 0::: CL
-
1.0 -
-
0.8
325
x
T, = 2.5E-06 m2/s S = 1.0E-05 X = OBSERVED DATA - = SIMULATION
x x x x
I I 345
x
TIME 0 = JANUARY 1. 1987
Orawn by J.D.A. Date 2/23/89
Checked by G. S. Date 2/23/89
Revisions ABW Date 6/23/89
H09700R876 2/23/89
I N'rt.R...'\ Technologies
~~ x
Ix x x x
I I I 365
TIME (1987 CALENDAR DAYS)
I I
385
SPECIFIED AND SIMULATED WELLBORE PRESSURES AND SIMULATED AND OBSERVED FORMATION FLUID PRESSURES FOR THE MAGENTA DOLOMITE DRILLING/REAMING PERIOD USING A HOMOGENEOUS-FORMATION CHARACTERIZATION
Figure A.7
A-9
405
405
MAGENTA SIMULATION #2 2.8 -,--------------------------------------------------------------------------,
SIMULATED'" AND SPECIFIEDT WELLBORE PRESSURES DURING DRILLINGIREAMING PERIOD
2.4
T; = 8.0E-08 m2/s To = 4.0E-08 m /5 5 = 1.0E-05 1 t Time Segments Used in Simulation r. = 40 m
~ 2"'-----j31-4""~1-----st-----__+_ 6 t~ ~
0 (L
2.0 ::::;: ~
W 0:: :;) (Il Ul w 0:: 1.6 (L
1.2
0.8 -+---------.--------.--------.---------.--------.--------.---------.--------4 325
1.4
~ 1.2
0 (L ::::;: ~
W 0:: :;) Ul Ul w 0:: (L
1.0
345 365 385
TIME (1987 CALENDAR DAYS)
SIMULATED H-16 PRESSURE DURING THE DRILLING/REAMING PERIOD
T; = 8.0E-08 m2/s To = 4.0E-08 m /5 S = 1.0E-05 rb = 40 m
X = OBSERVED DATA - = SIMULATION
x x x X x x
405
0.8 -+---------.--------,--------.---------.--------,--------.---------,--------4 325 345
TIME 0 = JANUARY 1. 1987
Drawn by J.D.A. Dote 2/23/89
Checked by G. S. Dote 2/23/89
Revisions AS W Dote 6/23/89
H09700R876 2/23/89
I Nrt.R..'\ Technologies
.365 .385
TIME (1987 CALENDAR DAYS)
SPECIFIED AND SIMULATED WELLBORE PRESSURES AND SIMULATED AND OBSERVED FORMATION FLUID PRESSURES FOR THE MAGENTA DOLOMITE DRILLING/REAMING PERIOD USING A FORMATION-HETEROGENEITY BOUNDARY
Figure A.S
A-10
405
2.8
2.4
MAGENTA SIMULATION #3
SIMULATED'" AND SPECIFIEDt WELLBORE PRESSURES
Ti = 2.5E-08 m2/s To = 4.0E-08 m /5 S = 1.OE-05 rb = 40 m 1 t
DURING DRILLING/REAMING PERIOD
Time Segments Used in Simulation
I+-2~ 31- 4"'--+1-----st-----_+_ 6 t-i ~
0 !L
2.0 2 ~
w n: => (J) (J) w n: 1.6 !L
1.2
0.8 ~--------_,--------._------_,--------_,--------._------_,--------_.------__I
325 345 365 385 405
TIME (1987 CALENDAR DAYS)
1.4 -,--------------------------------------------------------------------------,
~ 1.2
0 !L 2 ~
w n: => (J) (J) w n: !L
1.0
SIMULATED H-16 PRESSURE DURING THE DRILLING/REAMING PERIOD
Ti = 2.5E-08 m2/s To = 4.0E-08 m /5 S = 1.0E-05 rb = 40 m X = OBSERVED DATA - = SIMULATION
x x x x x x
-r )¢(~xxxx x
x
0.8 -f--------_,--------._------_,---------r--------.-------_,--------_,------~
325 345
TIME 0 = JANUARY 1, 1987
Drown by J.D.A. Dote 2/23/89
Checked by G.S. Dote 2/23/89
Revisions ABW Dote 6/23/89
H09700R876 2/23/89
I NrtIL'\ Technologies
365 385
TIME (1987 CALENDAR DAYS)
SPECIFIED AND SIMULATED WELLBORE PRESSURES AND SIMULATED AND OBSERVED FORMATION FLUID PRESSURES FOR THE MAGENTA DOLOMITE DRILLING/REAMING PERIOD USING A FORMAIION-HETEROGENEITY BOUNDARY AND Ti == 2.5 X 10- m2/s
Figure A.9
A-ll
405
2.8
---
2.4 -
MAGENTA SIMULATION #4
SIMULATED* AND SPECIFIEDt WELLBORE PRESSURES
T; = 2.SE-07 m2/s To = 4.0E-08 m /s S = 1.0E-OS rb = 40 m 1 t
DURING DRILLING/REAMING PERIOD
TIme Segments Used in Simulation
- ~ 2*--13t}-4*--+-1-----st------+I- 6 t--1 -
~ -0
CL 2.0 -2-
-w 0:: -;:) (f) (f) -w 0:: 1.E -CL
-- ~ I -
1.2 -
-- ~ ~ -
0.8 I I I
3~5 I
3~5 I
345 405 325
TIME (1987 CALENDAR DAYS)
1.4 -,------------------------------------__________________________________ ~
SIMULATED H-16 PRESSURE DURING THE DRILLING/REAMING PERIOD
~
0 CL L ~
w 0:: ;:) (f) (f) w 0:: CL
-
1.2 -
-
1.0 -
-
0.8
325
T; = 2.SE-07 m2/s To = 4.0E-08 m /s S = 1.0E-OS rb = 40 m X = OBSERVED DATA - = SIMULATION
xxx xx xx>
I I 345
TIME 0 = JANUARY 1. 1987
Drawn by J.D.A. Date 2/23/89
Checked by G. S . Date 2/23/89
Revisions ABW Date 6/23/89
H09700R876 2/23/89
I N'rtILl\ Technologies
-~ xxxx
~XXX
I I I
TIME (1987 CALENDAR DAYS)
SPECIFIED AND SIMULATED WELLBORE PRESSURES AND SIMULATED AND OBSERVED FORMATION FLUID PRESSURES FOR THE MAGENTA DOLOMITE DRILLING/REAMING PERIOD USING A FORMAJION-HETEROGENEITY BOUNDARY AND T; = 2.5 X 10- m2/s
Figure A.10
A-12
405
2.8
2.4
MAGENTA SIMULATION #5
SIMULATED* AND SPECIFIEDi' WELLBORE PRESSURES
T; = 8.0E-08 m2/s To = 1.3E-08 m /5 S = 1.0E-05 r. = 40 m 1 t
DURING DRILLING/REAMING PERIOD
TIme Segments Used in Simulation
1+2~3tt-4*·-t-I-----5t------+- 6 t-i ~
0 a.. 2.0 :::. ~
w 0:: :;) U1 U1 W 0:: 1.6 a..
1.2
0.8 -+--------,--------.--------.--------.--------.--------.--------.-------~
325 345 365 385 405
TIME (1987 CALENDAR DAYS)
1.4 -,----------------------------------------------------------------------, SIMULATED H-16 PRESSURE DURING THE DRILLING/REAMING PERIOD
T; = 8.0E-08 m2/s To = 1.3E-08 m /5
1.2 0
a.. :::. ~
w 0:: :;) U1 U1 w 0:: a..
1.0
0.8
325
S = 1.0E-05 r. = 40 m X = OBSERVED DATA - = SIMULATION
xxx xx xX>l
.345
TIME 0 JANUARY 1. 1987
IKawn by J.D.A. Date 2/23/89
Checked by G. S. Date 2/23/89
Revisions ABW Date 6/23/89
H09700R876 2/23/89
I N"rtIL 1\ Technologies
xx
.365 .385
TIME (1987 CALENDAR DAYS)
SPECIFIED AND SIMULATED WELLBORE PRESSURES AND SIMULATED AND OBSERVED FORMATION FLUID PRESSURES FOR THE MAGENTA DOLOMITE DRILLING/REAMING PERIOD USING A FORMATION-HETEROGENEITY BOUNDARY AND To = 1 . .3 X 10-8 m2/s
Figure A.11
A-13
405
2.8
---
2.4 -
MAGENTA SIMULATION #6
SIMULATED* AND SPECIFIEDt WELLBORE PRESSURES
T; = 8.0E-08 m2/s To = 1.3E-07 m /s S = 1.0E-05 fb = 40 m 1 t
DURING DRILLING/REAMING PERIOD
TIme Segments Used in Simulation
- H- 2*--131]- 4*-t-1 ----st------;Ir- 6 t-1 -
,..... -0 a.. 2.0 -2- ~
-
1 -w
a:: -::> (/) (/) -w a:: 1.6 -a..
--
-1.2 -
-
-
-
0.8
325 I
I 3~S I I
405
TIME (1987 CALENDAR DAYS)
1.4 -,--------------------------------------------__________________________ ,
SIMULATED H-16 PRESSURE DURING THE DRILLING/REAMING PERIOD
-
,..... 1.2 -0
a.. ::;: ~
w a:: -::> (/) (/) w a:: a..
1.0 -
x -
0.8
325
T; = 8.0E-08 m2/s To = 1.3E-07 m /s S = 1.0E-05 fb = 40 m X = OBSERVED DATA - = SIMULATION
x x x x x >0-
I I 345
x
1
TIME 0 = JANUARY 1. 1987
Orawn by J.D.A. Oate 2/23/89
Checked by G. S . Date 2/23/89
Revisions ABW Date 6/23/89
H09700R876 2/23/89
I Nr~ Technologies
xxxx *: x
~ x )(
x
~
I I I
TIME (1987 CALENDAR DAYS)
SPECIFIED AND SIMULATED WELLBORE PRESSURES AND SIMULATED AND OBSERVED FORMATION FLUID PRESSURES FOR THE MAGENTA DOLOMITE DRILLING/REAMING PERIOD USING A FORMA~ION-HETEROGENEITY BOUNDARY AND To = 1.3 X 10- m2/s
Figure A.12
A-14
405
2.8
---
2.4 -
MAGENTA SIMULATION #7
SIMULATED. AND SPECIFIEDT WELLBORE PRESSURES
T; = 8.0E-08 m2/s To = 4.0E-08 m /5 S = 1.0E-05 fb = 20 m 1 t
DURING DRILLING/REAMING PERIOD
TIme Segments Used in Simulation
- H-2~3tt-4*'~I-----5t------I- 6 t-i -
~ -0 Q.
2.0 -:::;: ~
-w Ct: -::;) Ul Ul -W Ct: 1.6 -Q.
--
-1.2 -
--
-
0.8
325
1.4
I I 345
- I
I I I
365
TIME (1987 CALENDAR DAYS)
I 385
I
405
SIMULATED H-16 PRESSURE DURING THE DRILLING/REAMING PERIOD
~ 1.2
0 Q. :::;: ~
w Ct: ::;) Ul Ul W Ct: Q.
1.0
0.8
325
T; = 8.0E-08 m2/s To = 4.0E-08 m /5 S = 1.0E-05 fb = 20 m X = OBSERVED DATA - = SIMULATION
x x x x x x
345
TIME 0 = JANUARY 1. 1987
Drawn by J.D.A. Date 2/23/89
Checked by G.S. Date 2/23/89
Revisions ABW Date 6/23/89
H09700R876 2/23/89
I NTEIL,\ Technologies
365 385
TIME (1987 CALENDAR DAYS)
SPECIFIED AND SIMULATED WELLBORE PRESSURES AND SIMULATED AND OBSERVED FORMATION FLUID PRESSURES FOR THE MAGENTA DOLOMITE DRILLING/REAMING PERIOD USING A FORMATION-HETEROGENEITY BOUNDARY AND fb = 20 m
405
Figure A.13
A-I5
~
0 a.. ::::; ~
w a::: => Ul Ul w a::: a..
~
0 a.. ::::; ~
w a::: => Ul Ul w a::: a..
2.8 -,-___________ :.:.:M.:..;A:::G:::E.:..:Nc..:.T.:..:A--'S:::.;�:..:.:M~U~L:!.A.:..:.T...:..:IO:::.;N'_!....._'#'__'8~ __________ ---,
SIMULATED'" AND SPECIFIEDT WELLBORE PRESSURES
2.4
2.0
1.6
1.2
T; = 8.0E-08 m2/s To = 4.0E-08 m /s S = 1.0E-05 rb = 80 m
DURING DRILLING/REAMING PERIOD
1t Time Segments Used in Simulation
~2*--13tt-4··~I-----5t------I- st-1
0.8 -+--------.--------.--------.---____ -,-________ .-______ -,-________ .-______ ~ 325
1.4
1.2
1.0
345 365 385
TIME (1987 CALENDAR DAYS)
SIMULATED H-16 PRESSURE DURING THE DRILLING/REAMING PERIOD
T; = 8.0E-08 m2/s To = 4.0E-08 m /s S = 1.0E-05 rb = 80 m X = OBSERVED DATA - = SIMULATION
x x x x x x
405
0.8 -+--------.--------,---------.-------~--------~------~--------.-------~
325 345 365 385 405
TIME (1987 CALENDAR DAYS)
TIME 0 = JANUARY 1, 1987
Drawn by J.D.A. Date 2/23/89 SPECIFIED AND SIMULATED WELLBORE PRESSURES AND SIMULATED AND OBSERVED FORMATION FLUID PRESSURES FOR THE MAGENTA DOLOMlTE DRILLING/REAMING PERIOD USING A FORMATION-HETEROGENEITY' BOUNDARY AND
Checked by G. S. Date 2/23/89
Revisions ABW Date 6/23/89
H09700R876 2/23/89 rb = 80 m
I NTER..,\ Technologies Figure A.14
A-16
2.8
2.4
MAGENTA SIMULATION #9
SIMULATED'" AND SPECIFIEDt WELLBORE PRESSURES DURING DRILLING/REAMING PERIOD
T, = 8.0E-08 m2/s S = 1.0E-05 1 t
nme Segments Used in Sjmulation
~ 2~ 31- 4"'---t-I----- st--------t- 6 t-i ,....... 0
0.. 2.0 6 w (Y ::> if) if) w (Y 1.6 0..
1.2
0.8 -+---------r--------.--------.---------r--------.--------,---------r------~
325 345 365 385 405
TIME (1987 CALENDAR DAYS)
1.4 SIMULATED H-16 PRESSURE DURING THE DRILLING/REAMING PERIOD
T, = 8.0E-08 m2/s S 1.0E-05 X OBSERVED DATA - = SIMULATION
,....... 1.2 0
0.. L
x ~
w (Y ::> if) if) w (Y 0..
1.0
x x x x X X
0.8
325 .345
TIME 0 = JANUARY 1. 1987
Drown by J.D.A. Date 2/23/89
Checked by G. S. Date 2/23/89
Revisions ABW Date 6/23/89
H09700R876 2/23/89
I NltIL'\ Technologies
.365 .385 405
TIME (1987 CALENDAR DAYS)
SPECIFIED AND SIMULATED WELLBORE PRESSURES AND SIMULATED AND OBSERVED FORMATION FLUID PRESSURES FOR THE MAGENTA DOLOMITE DRILLING/REAMING PERIOD WITHOUT A FOR~ATION-HETEROGENEITY BOUNDARY AND Tf = 8.0 X 10- m2/s
Figure A.15
A-17
2.8
2.4
MAGENTA SIMULATION #10
SIMULATED'" AND SPECIFIED1" WELLBORE PRESSURES DURING DRILLING/REAMING PERIOD
TI = 4.0E-08 m2/s S = 1.0E-05 1 t
Time Segments Used in Simulation
I+-2~ 3 tt 4 "'-+-I -----5 t-------t- 6 t-i ~
0 Q..
2.0 2
w a::: :::> If) If) w a::: 1.6 Q..
1.2
0.8
325
1.4
1.2 0
Q.. 2 ~
w a::: :::> If) If) w a::: Q..
1.0
x
345 365 385
TIME (1987 CALENDAR DAYS)
SIMULATED H-16 PRESSURE DURING THE DRILLING/REAMING PERIOD
TI = 4.0E-08 m2/s S 1.0E-05 X OBSERVED DATA - = SIMULATION
x x
x x x x x
405
0.8 -+--------~--------._-------,--------~--------._------_,--------_.------~
325 345
TIME 0 = JANUARY 1. 1987
Drawn by J.D.A. Date 2/23/89
Checked by G.S. Date 2/23/89
Revisions ABW Date 6/23/89
H09700R876 2/23/89
INitIL'\ Technologies
365 385
TIME (1987 CALENDAR DAYS)
SPECIFIED AND SIMULATED WELLBORE PRESSURES AND SIMULATED AND OBSERVED FORMATION FLUID PRESSURES FOR THE MAGENTA DOLOMITE DRILLING/REAMING PERIOD WITHOUT A FORk1ATION-HETEROGENEITY BOUNDARY AND TI = 4.0 X 10- m2/s
405
Figure A.16
A-iS
FORTY-NINER SIMULATION #1
-2.3 -
SIMULATED. AND SPECIFIED t WELLBORE PRESSURES DURING DRILLING/REAMING PERIOD
-
-
Tf = 4.0E-07 m2/s S = 1.0E-05
Time Segments Used in Simulation
t4-2*--t3tt4*1 st-----t-I 6 t-i -
0' 1.9 -
D- -:::;; ~
-w ~ -::J If) If) 1.5 -w 0:: D- -
-
-1.1-
---
0.7
325
1.3
I I 345
I 3!5 I
TIME (1987 CALENDAR DAYS)
I 385
I
SIMULATED H-16 PRESSURE DURING THE DRILLING/REAMING PERIOD
-
~ 1.1 -o
D-:::;; ~
W 0:: ::J If) If) w ~
D-
-
0.9 -
-
0.7
Tf = 4.0E-07 m2/s S = 1.0E-05 X = OBSERVED DATA - = SIMULATION
x x x x x
I
x
325
TIME 0 = JANUARY 1, 1987
Drawn by J.D.A. Date 2/23/89
Checked by G.S. Date 2/23/89
Revisions ABW Date 6/23/89
H09700R876 2/23/89
I NTER_I\ Technologies
x~ x
I I I I
365
TIME (1987 CALENDAR DAYS)
SPECIFIED AND SIMULATED WELLBORE PRESSURES AND SIMULATED AND OBSERVED FORMATION FLUID PRESSURES FOR THE FORTY-NINER CLAYSTONE DRILLING/REAMING PERIOD USING A HOMOGENEOUS-FORMATION CHARACTERIZATION
I Figure A.17
A-19
405
405
2.3
FORTY-NINER SIMULATION #2
SIMULATED· AND SPECIFIED t WELLBOREPRESSURES Ti = 9.0E-09 rn,s To = 1.SE-09 m /s S = 1.0E-OS
DURING DRILLING/REAMING PERIOD
rb = 40 m TIme Segments Used in Simulation
H-2*----t3tt4*1 st-------jf- 6 t-i
,-.... 1.9 o
CL :::;;: ~
w ~
::J Ul Ul 1.5 w ~ CL
1.1
0.7 -+--------,--------,--------.--------, ________ ,-______ -. ________ .-______ ~ 325 345 365 385 405
TIME (1987 CALENDAR DAYS)
1.3 -,----------------------------------__ ~ ________________________________ ,
SIMULATED H-16 PRESSURE DURING THE DRILLING/REAMING PERIOD
Ti = 9.0E-09 m2/s
1.1 0
·CL :::;;: ~
w ~
::J Ul Ul w ~ CL
0.9
To = 1.SE-09 m /s S = 1.0E-OS rb = 40 m X = OBSERVED DATA - = SIMULATION
x x x x x
x x x
l\A x
0.7 -+--------,--------,--------.--------,--------,-______ -. ________ .-______ ~ 325 345
TIME 0 = JANUARY 1. 1987
Drawn by J.D.A. Date 2/23/89
Checked by G.S. Date 2/23/89
Revisions ABW Date 6/23/89
H09700R876 2/23/89
I N'rtIL'\ Technologies
365 385
TIME (1987 CALENDAR DAYS)
SPECIFIED AND SIMULATED WELLBORE PRESSURES AND SIMULATED AND OBSERVED FORMATION FLUID PRESSURES FOR THE FORTY-NINER CLAYSTONE DRILLING/REAMING PERIOD USING A FORMATION-HETEROGENEITY BOUNDARY
405
Figure A.18
A-20
-
2.3 -
-
FORTY-NINER SIMULATION #3
SIMULATED* AND SPECIFIED t WELLBORE PRESSURES T; = 3.0E-09 m2/s DURING DRILLING/REAMING PERIOD To = 1.5E -09 m /5 S = 1.0E-05
- rb = 40 m TIme Segments Used in Simulation
H-2*--t 3tt 4 *-+1------ 5 t ---------ll- 6 t-i - - -
~ 1.9 -
0 (L -~ ~
-w n::: -::::> if) if) 1.5 -w n::: (L -
--
1.1 -
-
- ~ \ -
0.7
325 I I I
3~5 I
3~5 I
345 '405
TIME (1987 CALENDAR DAYS)
1.3 SIMULATED H-16 PRESSURE DURING THE DRILLINGIREAMING PERIOD
T; = 3.0E-09 m2/s To = 1.5E-09 m /5
- = S 1.0E-05 rb = 40 m xxx
xxX ,""xx X = OBSERVED DATA - = SIMULATION
~ 1.1 -
0 (L
~ ~
w n::: -::::> if) if) w n::: (L
0.9 -
,*x
'* -~ x x x x x
0.7 I I
325 345
TIME 0 = JANUARY 1. 1987
Drown by J.D.A. Dote 2/23/89
Checked by G.S. Dote 2/23/89
Revisions ABW Dote 6/23/89
H09700R876 2/23/89
I ~tILl\ Technologies
x xxx"?-
xx
IXxXXX
~ xxx ~ )(Xx«-
>OX x x
x x V x
x x
x
x
I
3~5 I I I
385
TIME (1987 CALENDAR DAYS)
SPECIFIED AND SIMULATED WELLBORE PRESSURES AND SIMULATED AND OBSERVED FORMATION FLUID PRESSURES FOR THE FORTY-NINER CLAYSTONE DRILLING/REAMING PERIOD USING A FOR~ATlgN-HETEROGENEITY BOUNDARY AND T; = 3.0 X 10 - m /s
Figure A.19
A-21
405
-
2.3 -
-
--
~ 1.9 -
0 0.. -::;:
-w (Y -::J (f) (f) 1.5 -w (Y
0.. --
1.1 -
-
--
0.7
325
FORTY-NINER SIMULATION #4
SIMULATED* AND SPECIFIED t WELLBORE PRESSURES DURING DRILLING/REAMING PERIOD
T; = 3.0E-08 m2/s To = 1.5E-09 m /5 S = 1.0E-05 rb = 40 m
Time Segments Used in Simulation
ri-2*~3tt4·1 st
I
'--
I 345 I 3~5 I
TIME (1987 CALENDAR DAYS)
I
405
1.3 -,----------------------------------------______________________________ ~
SIMULATED H-16 PRESSURE DURING THE DRILLING/REAMING PERIOD
T; = 3.0E-08 m2/s To = 1.5E-09 m /5
w (Y
::J (f) (f)
.w (Y
0..
-
-
0.9 -
S = 1.0E-05 rb = 40 m X = OBSERVED DATA - = SIMULATION
x x x x x
x
x x
x
x
~
x x
V
x x xx
0.7 ~------.-I-----,-I----'I------'I------~I------'I------,-I----~
325 345 365 385 405
TIME 0 = JANUARY 1. 1987
Drown by J.D.A. Date 2/23/89
Checked by G. S. Date 2/23/89
Revisions ABW Date 6/23/89
H09700R876 2/23/89
I NTIIL,\ Technologies
TIME (1987 CALENDAR DAYS)
SPECIFIED AND SIMULATED WELLBORE PRESSURES AND SIMULATED AND OBSERVED FORMATION FLUID PRESSURES FOR THE FORTY-NINER CLAYSTONE DRILLING/REAMING PERIOD USING A FOR~ATlqN-HETEROGENEITY BOUNDARY AND Tj = 3.0 X 10 - m /s
I Figure A.20
A-22
FORTY-NINER SIMULATION #5
SIMULATED* AND SPECIFIED t WELLBORE PRESSURES DURING DRILLING/REAMING PERIOD
2.3 T; = 9.0E-09 m2/s To = 5.0E-l0 m /s S = 1.0E-05 rb = 40 m
Time Segments Used in SimUlation
~2*--t3tt4*1 5 t _____ 1- 6 t -i ----. 1.9 o
D-:::;;: ~
w IY: :::> U1 U1 1.5 w IY: D-
1.1
0.7
1.3
325 345 365 385
TIME (1·987 CALENDAR DAYS)
SIMULATED H-16 PRESSURE DURING THE DRILLING/REAMING PERIOD
T; = 9.0E-09 m2/s To = 5.0E-l0 m /s S = 1.0E-05
~ 1.1
0 D-:::;;:
w IY: :::> U1 U1 W IY: D-
0.9
0.7
Drawn by
Checked by
Revisions
rb = 40 m X = OBSERVED DATA - = SIMULATION
x x x x x
325 345
TIME 0 = JANUARY 1. 1987
J.D.A. Date 2/23/89
G.S. Date 2/23/89
ABW Date 6/23/89
H09700R876 2/23/89
I NTER .. '\ Technologies
365 385
TIME (1987 CALENDAR DAYS)
SPECIFIED AND SIMULATED WELLBORE PRESSURES AND SIMULATED AND OBSERVED FORMATION FLUID PRESSURES FOR THE FORTY-NINER CLAYSTONE DRILLING/REAMING PERIOD USING A FORMATI<;iN-HETEROGENEITY BOUNDARY AND To = 5.0 X 10- 0 m /s
Figure A.21
A-23
405
405
-
2.3 -
-
FORTY-NINER SIMULATION #6
SIMULATED* AND SPECIFIED t WELLBORE PRESSURES
T; = 9.0E-09 mis To = 5.0E-09 m /s S = 1.0E-05
DURING DRILLING/REAMING PERIOD
Time Segments Used in Simulation
- H-2*--t3tt4*1 st I 6t -1 rb = 40 m
- -
~ 1.9' -
0 D- -L ~ -w IX -:::> Ul Ul 1.5 -w IX D- -
-
-
1.1 -
-
-
~ \
-
0.7
325 I
315 I I I I I
365 385 405
TIME (1987 CALENDAR DAYS)
1.3 -,--------------------------------------------------____________________ ,
SIMULATED H-16 PRESSURE DURING THE DRILLING/REAMING PERIOD
T; = 9.0E-09 m2js To = 5.0E-09 m /s
- S = 1.0E-05 rb = 40 m X = OBSERVED DATA - = SIMULATION
~ 1.1 -
0 (L
L ~
W IX -::::> Ul Ul W IX (L
0.9 -
'* '* x -K x x x x x
0.7 I 315 325
TIME 0 = JANUARY 1. 1987
Drawn by J. D. A. Date 2/23/89
Checked by G. S . Date 2123/89
Revisions ABW Date 6/23/89
H09700R876 2/23/89
I Nrtlt.'\ Technologies
xxx xX" >«x X
x xxx-/'
xx
IXxXXX
.it!' xxx ~:oE:XX«
>OX x x
x ~ V X
X
x
I I I I I
365 385
TIME (1987 CALENDAR DAYS)
SPECIFIED AND SIMULATED WELLBORE PRESSURES AND SIMULATED AND OBSERVED FORMATION FLUID PRESSURES FOR THE FORTY-NINER CLAYSTONE DRILLING/REAMING PERIOD USING A FOR~ATION-HETEROGENEITY BOUNDARY AND To = 5.0 X 10- m2/s
Figure A.22
A-24
405
-2.3 -
---
~ 1.9 -
0 0.. -:::< ~ -w a:: -~ (j) (j) 1.5 -w a:: 0.. -
-
-
1.1 -
--
-
0.7
.325
1 . .3
-
~ 1.1 -o
0.. :::< ~
w a:: ~ (j) (j) w a:: 0..
-
0.9 -
0.7
.325
FORTY-NINER SIMULATION #7
SIMULATED. AND SPECIFIEDt WELLBORE PRESSURES DURING DRILLING/REAMING PERIOD
T; = 9.0E-09 mjs To = 1.5E -09 m /5 S = 1.0E-05 rb = 20 m
Time Segments Used in Simulation
ti-2·---t 3 tt 4 * I 5 t--------il!- 6 t--f
I
r--
I I 365
TIME (1987 CALENDAR DAYS)
I
SIMULATED H-16 PRESSURE DURING THE DRILLING/REAMING PERIOD
T; = 9.0E-09 m2js To = 1.5E-09 m /s S = 1.0E-05 rb = 20 m X = OBSERVED DATA - = SIMULATION
x x X X X
I
x Xx
x X
v
I 3~5 I
TIME (1987 CALENDAR DAYS)
I
TIME 0 = JANUARY 1. 1987
Drawn by J.D.A. Date 2/23/89 SPECIFIED AND SIMULATED WELLBORE PRESSURES AND SIMULATED AND OBSERVED FORMATION FLUID PRESSURES FOR THE FORTY-NINER CLAYSTONE DRILLING/REAMING PERIOD USING A FORMATION-HETEROGENEITY BOUNDARY AND rb = 20 m
Checked by G. S . Date 2/23/89
Revisions ABW Date 6/23/89
H09700R876 2/23/89
405
405
I N'rtIL,\ Technologies Figure A.23
A-25
FORTY-NINER SIMULATION #8
- SIMULATED. AND SPECIFIED t WELLBORE PRESSURES
2.3 -DURING DRILLING/REAMING PERIOD
-
-
T; = 9.0E-09 m':js To = 1.5E-09 m /s S = 1.0E-05 rb = 80 m
Time Segments Used in Simulation
~ 2*--t 3tt 4 * I 5 t---------1It-- 6 t-i - -
~ 1.9 -
0 0... -::;; ~
-w n:: -::J Vl Vl 1.5 -w n:: 0... -
-
-
1.1 -
-
- ~ \
-
0.7 I I I I I I I
325 345 365 385 405
TIME (1987 CALENDAR DAYS)
1.3 -,----------------------------------------------------------------------~ SIMULATED H-16 PRESSURE DURING THE DRILLING/REAMING PERIOD
T; = 9.0E-09 m2js To = 1.5E-09 m /s S = 1.0E-05 -rb = 80 m X = OBSERVED DATA - = SIMUUlTION
~ 1.1-o
0... ::;; ~
w n:: -::J Vl Vl W n:: 0...
0.9 -
-~
0.7
325
x x x x x
I I 345
jf:x jf: x
TIME 0 = JANUARY 1. 1987
Drawn by J.D.A. Date 2/23/89
Checked by G. S . Date 2/23/89
Revisions ABW Date 6/23/69
H09700R876 2/23/89
I NTEfLI\ Technologies
x
x
x x
tV x
I I I
365
TIME (1987 CALENDAR DAYS)
I 385
I
SPECIFIED AND SIMULATED WELLBORE PRESSURES AND SIMULATED AND OBSERVED FORMATION FLUID PRESSURES FOR THE FORTY-NINER CLAYSTONE DRILLING/REAMING PERIOD USING A FORMATION-HETEROGENEITY BOUNDARY AND rb = 80 m
Figure A.24
A-26
405
-
2.3 -
-
FORTY-NINER SIMULATION #9
SIMULATED· AND SPECIFIED t WELlBORE PRESSURES DURING DRILLING/REAMING PERIOD
-
T,= 9.0E-09 m2/s S = 1.0E-05
TIme Segments Used in Simulation
H-2·--t at14 ·:..j.I----- 5 t-------i/- 6 t-l - - ~
~ 1.9 -
0 a.. -:::;: ~ -w cr -:::l (/) (/) 1.5 -w cr a.. -
-
-
1.1 -
-
- ~ \
-0.7
325 405
I
315 I I I I I
365 385
TIME (1987 CALENDAR DAYS)
1.3 SIMULATED H-16 PRESSURE DURING THE DRILLING/REAMING PERIOD
T, = 9.0E-09 m2/s S = 1.0E-05
- X = OBSERVED DATA - = SIMULATION xxx
xxX ,""xx
~ 1.1 -
0 a.. :::;: ~
w cr -:::l (/) (/) w cr a..
0.9 -
,*X
'* -foe x x x x x x
0.7 I
315 325
. TIME 0 = JANUARY 1, 1987
Drawn by J.D.A. Date 2/23/89
Checked by G.S. Date 2/23/89
Revisions ABW Date 6/23/89
H09700R876 2/23/89
I NrtIl.,\ Technologies
X
xxxE xx
IXXXXX
.;:r. xxx #" ><:xX«
>OX x x
x >< V x
x x
x
I I I I I
365 385
TIME (1987 CALENDAR DAYS)
SPECIFIED AND SIMULATED WELLBORE PRESSURES AND SIMULATED AND OBSERVED FORMATION FLUID PRESSURES FOR THE FORTY-NINER CLAYSTONE DRILLING/REAMING PERIOD WITHOUT A FORf1ATION-HETEROGENEITY BOUNDARY AND T, = 9.0 X 10-9 m /s
Figure A.25
A-27
405
-
2.3 -
FORTY-NINER SIMULATION #10
SIMULATED* AND SPECIFIEDt WELLBORE PRESSURES DURING DRILLING/REAMING PERIOD
-
-
Tf = 1.SE-09 m2/s Time Segments Used in Simulation
S = 1.0E-OS H-2*----t3tt4"'1 st I 6t -i -
0-1.9 -
0.. -::::. ~ -w (Y -:J Vl Vl 1.5 -w (Y 0.. -
--
1.1 -
---
0.7
325
1.3
-
~ 1.1-o
0.. ::::.
w (Y ::J Vl Vl w (Y 0..
-
0.9 -
- -
~ \ I I I
3~5 I
3~5 I
345
TIME (1987 CALENDAR DAYS)
SIMULATED H-16 PRESSURE DURING THE DRILLING/REAMiNG PERIOD
Tf = 1.SE-09 m2/s S = 1.0E-OS X = OBSERVED DATA - = SIMULATION
x x x x x
405
0.7 ~------I~----~I------~I------~I------~I-----~I-----~I----~
325 345 365 385 405
TIME 0 = JANUARY 1. 1987
Drawn by J.D.A. Date 2/23/89
Checked by G.S. Date 2/23/89
Revisions ABW Date 6/23/89
H09700R876 2/23/89
I NrtIL'\ Technologies
TIME (1987 CALENDAR DAYS)
SPECIFIED AND SIMULATED WELLBORE PRESSURES AND SIMULATED AND OBSERVED FORMATION FLUID PRESSURES FOR THE FORTY-NINER CLAYSTONE DRILLING/REAMING PERIOD WITHOUT A FORf1ATION-HETEROGENEITY BOUNDARY AND Tf = 1.5 X 10-9 m/s
Figure A.26
A-28
DISTRIBUTION:
U. S. Department of Energy (5) Office of Civilian Radioactive Waste
Management Office of Geological Repositories Forrestal Building Washington, DC 20585
Deputy Director, RW-2 Associate Director, RW-10
Office of Program Administration and Resources Management
Associate Director, RW-20 Office of Facilities Siting and
Development Associate Director, RW-30
Office of Systems Integration and Regulations
Associate Director, RW-40 Office of External Relations and
Policy
U. S. Department of Energy (3) Albuquerque Operations Office P.O. Box 5400 Albuquerque, NM 87185
B. G. Twining J. E. Bickel R. Marquez, Director
Public Affairs Division
U. S. Department of Energy / AL Attn: National Atomic Museum Librarian P.O. Box 5400 Albuquerque, NM 87185
U. S. Department of Energy (9) WIPP Project Office (Carlsbad) P.O. Box 3090 Carlsbad, NM 88221
A. Hunt (4) T. Lukow V. Daub (2) R. Batra J. Carr
U. S. Department of Energy Research & Waste Management Division P.O. Box E Oak Ridge, TN 37831
W. R. Bibb, Director
U. S. Department of Energy Richland Operations Office Nuclear Fuel Cycle & Production
Division P.O. Box 500 Richland, WA 99352
R.E.Gerton
U. S. Department of Energy (5) Office of Defense Waste and
Transportation Management WaShington, DC 20545
T. B. Hindman ---- DP-12 C. H. George ----- DP-124 M. Duff ---------- DP-123 A. Follett ------- DP-122 J. Mather -------- DP-123
U. S. Department of Energy (2) Idaho Operations Office Fuel Processing and Waste
Management Division 785 DOE Place Idaho Falls, ID 83402
U. S. Department of Energy (4) Savannah River Operations Office Waste Management Project Office P.O. Box A Aiken, SC 29802
S. Cowan W. J. Brumley J. R. Covell D. Fulmer
U. S. Environmental Protection Agency Office of Radiation Programs (ANR460) Washington, DC 20460
D. J. Egan, Jr. M. Cotton
U. S. Nuclear Regulatory Commission (4) Division of Waste Management Mail Stop 623SS Washington, DC 20555
M. Bell H. Miller J.Philip NRC Library
U. S. Geological Survey Branch of Regional Geology MS913, Box 25046 Denver Federal Center Denver, CO 80225
R. Snyder
U. S. Geological Survey (2) Water Resources Division Suite 200 4501 Indian School, NE Albuquerque, NM 87110
C. Peters
New Mexico Institute of Mining and Technology (3)
Environmental Evaluation Group 7007 Wyoming Blvd., NE, Suite F-2 Albuquerque, NM 87109
R. H. Neill, Director
NM Department of Energy & Minerals P.O. Box 2770 Santa Fe, NM 87501
K. laPlante, Librarian
New Mexico State Engineers Office District II, 909 E. Second P.O. Box 1717 Roswell, NM 88201
A. Mason
U. S. Geological Survey Conservation Division P.O. Box 1857 Roswell, NM 88201
W. Melton
2
New Mexico Bureau of Mines and Mineral Resources (2)
Socorro, NM 87801 F. E. Kottolowski, Director J. Hawley
Battelle Pacific Northwest Laboratories (6)
Battelle Boulevard Richland, WA 99352
D. J. Bradley J. Relyea R. E. Westerman S. Bates H. C. BUrkholder L. Pederson
Bechtel Inc. (2) P.O. Box 3965 45-11-B34 San Francisco, CA 94119
E. Weber H. Taylor
Westinghouse Electric Corporation (8) P.O. Box 2078 Carlsbad, NM 88221
Library A. L. Trego W. P. POirer W. R. Chiquelin V. F. Likar R. F. Kehrman K. Broberg R. F. Cook
Oak Ridge National Laboratory (4) BoxY Oak Ridge, TN 37830
R. E. Blanko E. Bondietti C. Claiborne G. H. Jenks
INTERA Inc. (17) 6580 Austin Center Blvd., #300 Austin, TX 78731
G. E. Grisak J. F. Pickens G. J. Saulnier (5) J. L. Lolcama A. Haug J. D. Avis (5) M. Reeves T. L. Cauffman Library
INTERA Inc. (4) P.O. Box 2123 Carlsbad, NM 88221
W. A. Stensrud P. S. Domski R. Roberts J. B. Palmer
IT Corporation (2) P.O. Box 2078 Carlsbad, NM 88221
D. Deal
IT Corporation (4) 5301 Central Ave., NE Suite 700 Albuquerque, NM ,87108
R. F. McKinney M. E. Crawley R. M. Holt J. Myers
REjSPEC, Inc. (5) P.O. Box 725 Rapid City, SD 57709
L. L. Van Sambeek T. Pfeifle G. Callahan J. L. Ratigan J. D. Osnes
REjSPEC, Inc. (2) P.O. Box 14984 Albuquerque, NM 87191
W. E. Coons P. F. Gnirk
S-Cubed (3) P.O. Box 1620 La Jolla, CA 92038
E. Peterson P. Lagus K. Lie
University of Arizona Department of Nuclear Engineering Tucson, AZ 85721
J. G. McCray
University of Wisconsin-Madison Department of Geology and Geophysics 1215 W. Dayton St. Madison, WI 53706
M. P. Anderson
The Pennsylvania State University Materials Research Laboratory University Park, PA 16802
D.Roy
Texas A&M University Center of Tectonophysics College Station, TX 77840
J. Handin
University of Texas at EI Paso Department of Geological Sciences EI Paso, TX 79968
D. W. Powers
University of New Mexico (3) Geology Department Albuquerque, NM 87131
D. G. Brookins M. Campana Library
3
New Mexico Tech (3) Department of Geoscience Socorro, NM 87801
J. Wilson F. Phillips C.S.Chen
Argonne National Laboratory 9700 South Cass Avenue Argonne,IL 60439
D. Hambeley
Los Alamos National Laboratory Los Alamos, NM 87545
B. Erdal, CNC-11
Brookhaven National Laboratory Associated Universities, Inc. Upton, NY 11973
P. W. Levy, Senior Scientist
National Academy of Sciences, WIPP Panel:
4
Dr. Charles Fairhurst, Chairman Department of Civil and Mineral Engineering University of Minnesota 500 Pillsbury Dr., SE Minneapolis, MN 55455
Dr. Frank L. Parker Department of Environmental and
Water Resources Engineering Vanderbilt University Nashville, TN 37235
Dr. John O. Blomeke Route 3 Sandy Shore Drive Lenoir City, TN 37771
Dr. John D. Bredehoeft Western Region Hydrologist Water Resources Division U. S. Geological Survey 345 Middlefield Road Menlo Park, CA 94025
Dr. Karl P. Cohen 928 N. California Avenue Palo Alto, CA 94303
Dr. Fred M. Ernsberger 250 Old Mill Road Pittsburgh, PA 15238
Dr. Rodney C. Ewing Department of Geology University of New Mexico 200 Yale, NE Albuquerque, NM 87131
Dr. George M. Hornberger Department of Environmental Sciences Clark Hall University of Virginia Charlottesville, VA 22903
Dr. D'Arcy A. Shock 233 Virginia Ponca City, OK 74601
Dr. Christopher G. Whipple Electric Power Research Institute 3412 Hillview Avenue Palo Alto, CA 94303
Dr. Peter B. Meyers, Staff Director National Academy of Sciences Committee on Radioactive Waste
Management 2101 Constitution Avenue Washington, DC 20418
Ina Alterman National Academy of Sciences Board on Radioactive Waste
Management GF462 2101 Constitution Avenue Washington, DC 20418
Hobbs Public Library 509 N. Ship Street Hobbs, NM 88248
M. Lewis, Librarian
New Mexico Tech Martin Speere Memorial Library Campus Street Socorro, NM 87810
New Mexico State Library P.O. Box 1629 Santa Fe, NM 87503
I. Vollenhofer
Zimmerman Library University of New Mexico Albuquerque, NM 87131
Z. Vivian
WIPP Public Reading Room Atomic Museum Kirtland East AFB Albuquerque, NM 87185
G. Schreiner
WIPP Public Reading Room Carlsbad Municipal Library 101 S. Halagueno St. Carlsbad, NM 88220
L. Hubbard, Head Librarian
British Nuclear Fuels, PLC Risley, Warrington, Cheshire WA3 6AS 1002607 GREAT BRITAIN
D. R. Knowles
Institut fOr Tieflagerung (4) Theodor-Heuss Strasse 4 D-3300 Braunschweig FEDERAL REPUBLIC OF GERMANY
K.Kuhn
Bundesanstalt fOr Geowissenschaften und Rohstoffe (3)
Postfach 510153 D-3000 Hannover 51 FEDERAL REPUBLIC OF GERMANY
M. Langer P. Vogel K. Schelkes
Hahn-Meitner Institut fOr Kernforschung
Glienicker Strasse 100 100 Berlin 39 FEDERAL REPUBLIC OF GERMANY
W. Lutze
Bundesministerium fOr Forschung und Technologie
Postfach 200 706 D-5300 Bonn 2 FEDERAL REPUBLIC OF GERMANY
Rolf-Peter Randl
Physikalisch-Technische Bundesanstalt
Postfach 33 45 D-3300 Braunschweig FEDERAL REPUBLIC OF GERMANY
P. Brenneke
Kernforschung Karlsruhe Postfach 3640 D-7500 Karlsruhe FEDERAL REPUBLIC OF GERMANY
K. D. Closs
Japan Atomic Energy Research Institute Tokaii~uri, Naka-Gun I baraki-Ken 319-11, JAPAN
Shingo Tashiro
Svensk Karnbransleforsorjning AB Project KBS Karnbranslesakerhet Box 5864 S-102 48 Stockholm, SWEDEN
F. Karlsson
Svensk Karnbranslehantering AB (2) Box 5864 S-102 48 Stockholm, SWEDEN
A. Strom K.-E. Almen
5
Atomic Energy of Canada, Ltd. (4) Whiteshell Nuclear Research
Establishment Pinewa, Manitoba, CANADA ROE 1LO
P.Haywood J. Tait C. C. Davison D. Stevenson
Studiecentrum Voor Kernenergie Centre D'Energie Nucleaire SCK/CEN Boeratang 200 B-2400 Mol, BELGIUM
A Bonne
Ontario Hydro Research Lab (2) 800 Kipling Avenue Toronto, Ontario, CANADA M8Z 5S4
D. K. Mukerjee A T. Jakubick
Centre D'Etudes Nucleaires De La Vallee Rhone
CEN/ /yALRHO S.D.H.A. BP 171 30205 Bagnols-Sur-Ceze, FRANCE
C. Sombret
OECD Nuclear Energy Agency Division of Radiation Protection
and Waste Management 38, Boulevard Suchet 75016 Paris, FRANCE
J-P Olivier
Netherlands Energy Research Foundation ECN (2)
3 Westerduinweg P.O. Box 1 1755 ZG Petten, THE NETHERLANDS
T. Deboer, Mgr. L. H. Vons
6
Rijksinstituut voor Volksgezondheid en Milieuhygiene (2)
Antonie van Leeuwenhoeklaan 9 P.O. Box 1 3720 BA Bilthoven, THE NETHERLANDS
P. Glasbergen S. M. Hassanizadeh
Nationale Genossenschaft fur die Lagerung Radioaktiver Abfiille (3)
Parkstrasse 23 CH-5401 Baden, SWITZERLAND
P. Hufschmied C. McCombie M. Thury
Sveriges Geologiska AB Pusterviksgatan 2 S-41301 Goteborg, SWEDEN
A Winberg
Environment Canada National Water Research Institute Canada Centre for I nland Lakes 867 Lakeshore Road P.O. Box 5050 Burlington, Ontario L7R 4A6 CANADA
K. S. Novakowski
Energy, Mines and Resources Canada Geological Survey of Canada 601 Booth St. Ottawa, Ontario K1 A OE8 CANADA
D. Boyle
Technical Research Center of Finland Nuclear Engineering Laboratory P.O. Box 169 SF-00181 Helsinki, FINLAND
V. Taivassalo
Gartner-Lee Limited 140 Renfrew Drive Markham, Ontario L3R 6B3 CANADA
K. G. Kennedy
University of British Columbia Department of Geological Sciences Vancouver, British Columbia V6T 1 W5 CANADA
R. A. Freeze
ANDRA 31 Rue de la Federation 75015 Paris, FRANCE
D. Alexandre, Deputy Director
Oak Ridge National Laboratory Building 2001 Ecological Sciences Information
Center P.O. Box X Oak Ridge, TN 37830
C. S. Fore
Princeton University Department of Civil Engineering
Princeton, NJ 08504 G. Pinder
Rockwell International Rocky Flats Plant Golden, CO 80401
C. E. Wickland
National Ground Water Information Center
6375 Riverside Drive Dublin, OH 43017
J. Bix
University of California (3) Lawrence W. Berkeley Laboratory Berkeley, CA 94720
P. A. Witherspoon J. C. S. Long S. M. Benson
Kansas Geological Survey University of Kansas 1930 Constant Avenue, Campus West Lawrence, KS 66046
J. Butler
Roswell Public Library 301 N. Pennsylvania Avenue Roswell, NM 88201
N. Langston
U. S. Geological Survey Water Resources Division
521 W. Seneca St. Ithaca, NY 14850
R. M. Yager
U. S. Geological Survey (2) Water Resources Division 345 Middlefield Rd. Menlo Park, CA 94025
P. Hsieh A. F. Moench
Texas A&M University Department of Geology College Station, TX 77843
P. A. Domenico
Pannell Library New Mexico Junior College Lovington Highway
Hobbs, NM 88240 R. Hill
Government Publications Dept. General Library University of New Mexico Albuquerque, NM 87131
Savannah River Laboratory (6) Aiken, SC 29801
N. Bibler E. L. Albenisius M. J. Plodinec G. G. Wicks C. Jantzen J. A. Stone
Savannah River Plant Building 704-S Aiken, SC 29808
R. G. Baxter
7
Arthur D. Little, Inc. Acorn Park Cambridge, MA 01240-2390
C. R. Hadlock
University of Arizona Department of Hydrology Tucson, AZ 85721
S. P. Neuman
S. S. Papadopulos and Assoc., Inc. 12596 W. Bayaud Ave., Suite 290 Lakewood, CO 80228
J. W. Anthony
Golder Associates 4104 148th Avenue NE Redmond, WA 98052
T. W. Doe
Scientific Software-Intercomp 1801 California, 2nd Floor Denver, CO 80202
J. M. Sofia
SAIC 10260 Campus Point Drive San Diego, CA 92121
H. R. Pratt
SAIC Suite 1250 160 Spear St. San Francisco, CA 94105
M. B. Gross
SAIC 101 Convention Center Dr. Las Vegas, NV 89109
G. Dymmel
Thomas Brannigan Library 106 W. Hadley St. Las Cruces, NM 88001
D. Dresp, Head Librarian
8
Emcon Associates 1921 Ringwood Avenue San Jose, CA 95131
F. W. Fenzel
L. Lehman and Associates, Inc. 1103 W. Burnsville Parkway Suite 209 Minneapolis, MN 55337
L. Lehman
Sandia Internal:
1510 J. W. Nunziato 6342 K. Brinster 1511 D. F. McTigue 6342 M. G. Marietta 1520 C. W. Peterson 6342 R. P. Rechard 1521 R. D. Krieg 6343 T. M. Schultheis 1521 H. S. Morgan 6344 E. D. Gorham 3141 S. A. Landenberger (5) 6344 R. L. Beauheim (5) 3151 W. I. Klein (3) 6344 P. B. Davies 3154-1 C. L. Ward, for DOEjOSTI (8) 6344 S. J. Finley 6000 D. L. Hartley 6344 A. L. Jensen 6200 V. L. Dugan 6344 A. M. LaVenue 6232 W. R. Wawersik 6344 R. Z. Lawson 6233 T. M. Gerlach 6344 M. D. Siegel 6253 D. A. Northrup 6344 S. W. Webb 6253 N. R. Warpinski 6345 A. R. Lappin 6300 R. W. Lynch 6345 L. H. Brush 6310 T. O. Hunter 6345 K. L. Robinson 6311 A. L. Stevens 6346 J. R. Tillerson 6312 F. W. Bingham 6416 E. J. Bonano 6313 T. E. Blejwas 9300 J. E. Powell 6315 L. E. Shephard 9310 J. D. Plimpton 6316 R. P. Sandoval 9320 M. J. Navratil 6317 S. Sinnock 9325 R. L. Rutter 6340 W. D. Weart 9325 J. T. Mcllmoyle 6340 S. Y. Pickering 9330 J. O. Kennedy 6341 R. C. Lincoln 9333 O. L. Burchett 6341 R. L. Hunter 9333 J. W. Mercer 6341 Sandia WIPP Central Files (5) 9335 P. D. Seward
(700HIND) 8524 J. A. Wackerly (SNLL Library) 6342 D. R. Anderson
'" u.s. GOVERNMENT PRINTING OFFICE: 1990-773'118/20046 9
1111111111111111111111111111111111111111111111111111 111111111
8232-2/070179
1111111111/11111111111111111111111111111111111111111111111111111111111111II
00000001 ----- - - - - - -- ~ ------ -----
11111111111111111111111111111111111111111111111111111111111111111111111111111111
8232-2/070179
111111111111111111111111111111111111111111111111111111111111111111111111111
· 00000001 -- ---- -- ----- --------
11111111111111111111111111111111111111111111111111111111111111111111111111111111
· 8232-2/070179
· 111111111/11111111111111111111111111111111111111111111111111111111111111111 .
00000001 -