l Contract Name: Upgradation and Upliftment of existing drainage pumping Stations in Srinagar City. LOT -B "Pumping stations on Right Bank of River Jehlum". Package No : JKUSDIP Srinagar/SWD/ 03. S. No. 1. 2. Reference Clause Section 6 Employer requirement page 6-67 Initial Environmental Examination Executive summary Section 8 PCC Part B Page reference I items Page P6-67 P age P8-4 Addendum No: 01 Position as per bid document In para 1, after the following line.- In this connection Conunissioner of Srinagar Municipal Corporati on vide letter no SMC/PS/COM/1160-62 DATED 16/04/2015 has requested J&K ERA to arrange financing for all the 76 No. of existing Pumping stations (List enclosed as Appendix 5 ) in view of damage rendered to these pumping st ations during recent floods. General provisions 1.6 Contract agreement Modified as · Insert the following at the end of the p ara H owever the stations were prioritized as 27 stations in two lots, Lot A comparing of 15 Nos. and Lot B 12 Nos. stations as per table 3. Add the following in section 8 PCC Part B- Specific Provisions before sub clause 1.6 1.5 Priority of Documents The documents forming the Contract are to be taken as mutually explanatory of one another. For the purposes of interpretation, the priority of the documents shall be in accordance with the following sequence: (a) the Letter of Acceptance (b) the technical bid, (c) the Letter of price bid, (d) the addendums if any (e) the Particular Conditions of Conh·act- Part A, (f) the Particular Conditions of Contract- Part B, (f) the General Conditions of Contract, Page 1 of 6

Contract Name: Upgradation and Upliftment of existing drainage …jkera.org/TenderedProjects/OtherDocs/143-Add-01.pdf · 2015-06-27 · BOQ of item enclosed. Every Clause 10. APFC

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Contract Name: Upgradation and Upliftment of existing drainage …jkera.org/TenderedProjects/OtherDocs/143-Add-01.pdf · 2015-06-27 · BOQ of item enclosed. Every Clause 10. APFC

l ~

Contract Name: Upgradation and Upliftment of existing drainage pumping Stations in Srinagar City. LOT -B "Pumping stations on Right Bank of River Jehlum".

Package No: JKUSDIP Srinagar/SWD/ 03.

S. No.

1.

2.

Reference Clause

Section 6 Employer requirement page 6-67 Initial Environmental Examination Executive summary Section 8 PCC Part B

Page reference I items

Page P6-67

Page P8-4

Addendum No: 01 Position as per bid document

In para 1, after the following line.-In this connection Conunissioner of Srinagar Municipal Corporation vide letter no SMC/PS/COM/1160-62 DATED 16/04/2015 has requested J&K ERA to arrange financing for all the 76 No. of existing Pumping stations (List enclosed as Appendix 5 ) in view of damage rendered to these pumping stations during recent floods.

General provisions 1.6 Contract agreement

Modified as ·

Insert the following at the end of the para However the stations were prioritized as 27 stations in two lots, Lot A comparing of 15 Nos. and Lot B 12 Nos. stations as per table 3.

Add the following in section 8 PCC Part B- Specific Provisions before sub clause 1.6 1.5 Priority of Documents The documents forming the Contract are to be taken as mutually explanatory of one another. For the purposes of interpretation, the priority of the documents shall be in accordance with the following sequence: (a) the Letter of Acceptance (b) the technical bid, (c) the Letter of price bid, (d) the addendums if any (e) the Particular Conditions of Conh·act- Part A, (f) the Particular Conditions of Contract- Part B, (f) the General Conditions of

Contract,

Page 1 of 6

Page 2: Contract Name: Upgradation and Upliftment of existing drainage …jkera.org/TenderedProjects/OtherDocs/143-Add-01.pdf · 2015-06-27 · BOQ of item enclosed. Every Clause 10. APFC

S.No. Reference Page reference I Position as per bid document Mofiified as Clause items

(g) list of eligible countries ........ (h) the Specification, (i) the Drawings, and . G) the complete scheduled or bill of quantities (k) any other documents listed in the PCC as forming part of the Contract. If an ambiguity or discrepancy is found in the documents, the Engineer shall issue the necessary clarification or instruction with the approval of Employer" .

3. Section 6 Page LOT-B (Pumping Stations Right bank Before the table Lot B add this I

Employer P6-80 of River Jehlum) LOT-A (Pumping Stations along left requirement S.No Name bank of River Jehlum) Initial 1 Abiguzar S.No. Name Environmental 2 Barbarshah 1 Alochi Bagh Examination 3 Bishembernagar 2 Darish Kadal Table 3 4 Mandir Bagh 3 Nursing Garh

5 Khidmat Press 4 Qamarwari 6 Shivpora 5 Syed Hamidpora 7 Court Road

6 SMHS 8 Golf Club 9 SonvarBagh 7 Patlipora

10 Sonvar Davis 8 Tengpora

11 Shora Khan 9 Batamaloo

12 Noor bagh 10 KawajiAda 11 Old Gadhanjipora 12 lkhrajpora

13 Rajbagh 14 Polytechnic

New Gadhehanjipora 15

4. Section 6

Page 2 of 6

Page 3: Contract Name: Upgradation and Upliftment of existing drainage …jkera.org/TenderedProjects/OtherDocs/143-Add-01.pdf · 2015-06-27 · BOQ of item enclosed. Every Clause 10. APFC

:J

l

S. NP· I ~e~er~nce · Clause

Employer requirement vide page

P6-189 P6-199

the following are articles de icted

5. I Section 7 General Conditions of Contract

I'age reference l ·· items

Page P6-189 P6-199

Page P7-1

Position as per bid document ~:!;~ ~\_ ~d?!:_

Para Nos. 15,15.1,15.2,15.3, 15.4 ... . .. ... . . ... .. 15.48 16

The General Conditions that follow are the Conditions of Contract for Construction for Building and Engineering Works Designed by the Employer, Multilateral Development Bank Harmonized Edition June 2010, prepared by the Federation Internationale des Ingenieurs-Conseil, or FIDIC (FIDIC MDB version 2010) available at FIDIC MDB June 2010.

Nrodified as ~ ,(· ./· .

Para Nos. Now to be read as 1,

!ll

~r

1.1,1.2,1.3,1.3,1.4,1.5 ......... . ......... 1.48 2.

Insert the following after the para below. The contractor shall refer to all general conditions as per this section. This publication is exclusive for the use of ADB Borrowers and their project implementing agencies as provided under the License Agreement dated June 9th, 2005, between the ADB and FIDIC, and, consequently, no part of tl1.is publication may be reproduced, b·anslated, adapted, stored in a retrieval system or commwucated, in any form or by any means, whether mechanical, electronic, magnetic, photocopying, recording or otherwise, without prior pernuss10n in writing from FIDIC, except by the Employer identified above and only for the exclusive purpose of preparing bidding documents for ADB financed contracts.

Page 3 of 6

Page 4: Contract Name: Upgradation and Upliftment of existing drainage …jkera.org/TenderedProjects/OtherDocs/143-Add-01.pdf · 2015-06-27 · BOQ of item enclosed. Every Clause 10. APFC

S. No.

"'· ... 6.

7.

8.

j

Referenc~ Claus·~

Section 8 Particular conditions of contract Part B- specific Provision

Electrical Drawings Lot­B

Page refeJ:ence / ~tems

Page P8-5

Page P4-68 to 4-74

BOQ (Part -B I Page Electro- P 6-212 mechanical works) II. - Electrical Items

l.(!()sjtion as per bid document i ~~~ 0 w ' - ,, "' ,,~,-

8. Commencement, Delays and Suspension 8.7 Delay damages for the Works Add following at the end of clause:

Work program will be prepared by the contractors to achieve the following minimum milestones. The progress of work will be monitored regularly in respect of the following progress milestones and delay damages will be imposed for the under achieved progress (shortfall) by the contractor or bonus will be paid for the over achieved progress as under.

Bill of Quantities Part B Electrical Mechanical works S No 1-llpump station Bishamber nagar

Standards;

Modified as ~' ~ ' ' !!£,,.,",11

8. Commencement, Delays and Suspension 8.7 Delay damages for the Works Delete from the para the words "or bonus will be paid for the over achieved progress as detailed under". Further add to the last para of this sub clause at the end as under:

A bonus will be paid for the over achieved progress before the agreement contract period of completion.

Please delete BOQ item No 1-11 part B Electrical Mechanical works for pumping station Bishamber nagar (revised BOQ). Issued as addendum-Please insert before the standards:

All the equipment covered under these specifications I as below shall ·comply fully with latest issues of relevant 11 KV, Air break Isolator

The 11KV A. B switch set shall be the outdoor type suitable for horizontal mounting on the support structure. The A B switch shall be 3 phase, 3 Pin type gang operated and of rotating type having 1 post insulators per stack and single throw, double break characteristic. It would be complete with arching horns, down pipe and operating mechanism. The operating mechanism shall be suitable for manual operation from the ground level and shall be so designed that all the three phases shall open or

Page 4 of 6

Page 5: Contract Name: Upgradation and Upliftment of existing drainage …jkera.org/TenderedProjects/OtherDocs/143-Add-01.pdf · 2015-06-27 · BOQ of item enclosed. Every Clause 10. APFC

l"

l ·~s~ No. Refe:t;e!lce Clause·

9. I Section- 6 16. Technical specifications of Mechanical and Electrical Equipment

Clause 6 (B) -DIESEL ENGINE (Turbo-charged) of required kva {eage 6-204}

10.1 Volume 2 Part B Electro Mechanical works

Page r~ference I _ _ , .. ~ __ . Position as per bid document 'h Modifi~tl ~

tif,ems "'·· I·,., :'!11c !N~ J. m

I Page P6-204

I Page P4-37 to 38

I Page P4-153

B. Diesel Engine (turbo charged) of required KV A: The turbocharged Diesel Engine of 40 kva shall be water cooled, as specified, electrfc start developing required BHP at 1500 RPM with class A-2 or better governing to deliver specified continuous KVA output at 0.8 Power Factor Lag at NTP conditions.

Pumping station Abi guzar Item No 1 Storm water discharge Total head: 9 M Rating of motor 50 Pumping station Shora Khan Item No. 06 DG set

close simultaneously. The Switches shall be robust in construction, easy in operation and shall be protected against over travel or staining that might that might adversely affect any of its parts. The required base M.S Channel (hot dip galvanized) phase coupling rod, operation rod with intermediate guide braded with flexible electrolytic copper tail piece of required current carrying capacity and operation mechanism with "ON" & "OFF" positions shall be provided. The operation rod shall be medium gage of 32 mm dia meter nominal bore G.I pipe single length 6 meters. Delete para-6

Pumping station Abi guzar Item No 1 Storm water discharge Total head: 10M Rating of motor 60 Pumping station Shora Khan Item No. 06 DG set

Page 5 of 6

Page 6: Contract Name: Upgradation and Upliftment of existing drainage …jkera.org/TenderedProjects/OtherDocs/143-Add-01.pdf · 2015-06-27 · BOQ of item enclosed. Every Clause 10. APFC

S. No. Reference Page reference I Position as per bid document Modified as Clause items

100KV 140KV Page Pumping station Noor Bagh Pumping station Noor Bagh p 4-162 Item No. 02 DG set Item No. 02 DG set

100KV 140KV Section- 6 Page Clause 10. APFC Panel Clause 10. APFC Panel 16. Technical P6-208 The panel has to be capacitor contractor based, The panel has to be capacitor specifications of vertically mounted and designed to raise the power contactor based, vertically mounted Mechanical and factor from 0.8 to 1 and designed to raise the power Electrical factor from 0.8 to 0.95 Equipment BOQ of item enclosed. Every Clause 10. APFC electrical distribution panel shall be Panel

inclusive of APFC in the bid 1

document. 11. BOQ (Part -B - Please insert Bill of quantity of

Electro- APFC panel enclosed after page 4-mechanical 167of Bill of Quantity (Volume 2 of works) 3) II. - Electrical Items

Page 6 of 6

a.:

Page 7: Contract Name: Upgradation and Upliftment of existing drainage …jkera.org/TenderedProjects/OtherDocs/143-Add-01.pdf · 2015-06-27 · BOQ of item enclosed. Every Clause 10. APFC

Providing, Installation and commissioning of Electrical equipment in Pump Station Bishember Nagar of

Unit Rate +

S.NO Particulars of Works Unit Quantity (Rs) Amount

In Figures In words (INR) (INR) (INR)

Stabilizer: Design & Supply (including Packaging, Handling, Transportation, Insurance, Storage and Inspection & Testing at the manufacturer's works) of 250 KV A capacity servo control automatic voltage stabilizers copper wound, 3 phase input : 200 V to 450 V, output: 415 V, + 1%, complete with

1 voltmeters, auto I manual control etc, oil cooled suitable for No. 1 three phase unbalanced I balanced load; and for all Power factor. Operating temperature -15 Deg. to 55 Deg. above ambient confirming 9815/2026 suitable for balanced load and provided with high/low voltage cut off system as required. supply side one no 400amp MCCB with enclosure.

2 DG Sets

Supply (including Packaging, Handling, Transportation, l:t:tsurance, Storage and Inspection & Testing at the manufacturer's works), Installation, Testing and Commissioning at site of 3 phase, elech·ic silent generation sets, consisting of water cooled diesel engine, producing required BHP under normal temperature pressure condition having four cylinders, 12 volt elech·ic start arrangement, naturally aspirated coupled to 140 KV A, 3 phase, 415 V, 0.8 Power factor, 50 Hz alternators on a common base frame, complete with control panels, starting battery with leads, fuel tank and sound proof acoustic enclosure and other accessories of following capacities:

140 KVA No. 1 3 Electrical Distribution Panel

Supply , delivery , fixing , testing & commissioning (including Packaging, Handling, Transportation, Insurance, Storage and No. 1 Inspection & Testing at the manufacturer's works),

-~

Page 1 of 5

Page 8: Contract Name: Upgradation and Upliftment of existing drainage …jkera.org/TenderedProjects/OtherDocs/143-Add-01.pdf · 2015-06-27 · BOQ of item enclosed. Every Clause 10. APFC

Providing, Installation and commissioning of Electrical equipment in Pump Station Bishember Nagar

Unit Rate ,

S.NO Particulars of Works Unit Quantity (Rs) Amount

In Figures In words (INR) (INR) (INR)

Installation, Testing and Commissioning at site of LT panel.

LT Circuit Breaker: 2 Nos. incoming feeders (1 no. for power connection from transformer and 1 no. for DG set) fitted with draw out type ACB of suitable capacity and change over switch of suitable rating complete with thermal overload and instantaneous elech·omagnetic short circuit relays.400 amps LT air circuit breakers, 4 pole draw out type, micro processed ACB complete.

4Nos. Outgoing feeders for individual motor complete with suitable MCCBs 2x 125amp and 2X 30amp for individual panel of motor complete in all respects.

2 nos. auxiliary panels for lighting & miscellaneous load provided with required MCCBs and complete in all respects.

8 Cable LT

Supply and laying (including Packaging, Handling, Transportation, Insurance, Storage and Inspection & Testing at the manufacturer's works), Laying, testing and Commissioning at site of LT XLPE/ PVC insulated sheathed armored cable with aluminum conductor of required sizes from main panel, to individual and DG set to main panel.

4 x95:mm2 M 30

4x35mm2 M 20

4x10mm2 M 20

Page 2 of 5

Page 9: Contract Name: Upgradation and Upliftment of existing drainage …jkera.org/TenderedProjects/OtherDocs/143-Add-01.pdf · 2015-06-27 · BOQ of item enclosed. Every Clause 10. APFC

Providing, Installation and commissioning of Electrical equipment in Pump Station Bishember Nagar

Unit Rate -·

S.NO Particulars of Works Unit Quantity _(Rs) Amount

In Figures In words (INR) (INR) (INR)

9 Earthing

Supply and laying (including Packaging, Handling, Transportation, Insurance, Storage and Inspection & Testing at the manufacturer's works), Installation, Testing and Commissioning at site of earthing grid for all electrical equipments, with earth plates of suitable sizes including earthing strips, accessories and providing masonry enclosure with cover plate having locking arrangement and watering pipe etc , charcoal and salt for earth electrode complete in all Job 8 respects.

Providing and fixing 25mm x Smm aluminum strip in 40mm dia pipe from earth electrode to DG set/Panel etc

Fixing 25mm x Smm aluminum strip on surface or in recess for connection· etc. as required, all as specified for connecting of electrical accessories

I 10 Electrification

Internal

1 Providing and fixing (including Packaging, Handling, Transportation, Insurance, Storage and Inspection & Testing at the manufacturer's works) of lighting points complete with switch, conduit, cable 3/ 0 .. 036 with following luminaries Job 1 '

General purpose industrial compact bottom suitable for 28W (TSFTL) double Fluorescent lamp with powder coated or aluminum reflector-4nos(Opera tors-2nos+ lcorridoor+2room)

Page 3 of 5

Page 10: Contract Name: Upgradation and Upliftment of existing drainage …jkera.org/TenderedProjects/OtherDocs/143-Add-01.pdf · 2015-06-27 · BOQ of item enclosed. Every Clause 10. APFC

Providing, Installation and commissioning of Electrical equipment in Pump Station Bishember Nagar

Unit Rate ..

(Rs) All!ount I

S.NO Particulars of Works Unit Quantity In Figures In words (INR)

.(INR) (INR) Providing and fixing (including Packaging, Handling, Transportation, Insurance, Storage and Inspection & Testing at the manufacturer's works) of Exhaust fans complete with wiring switches etc.The capacities of exhaust fans in crew cabin has to be such that there will be six air changes/hr.One exhaust fan has to be provided and installed in panel room. The combined capacity of two exhaust fans in the panel room should be such that there will be six air changes/hr in the plant room

11 Trial run / Operation and maintenance of equipment for month 3

three months

Total Bill No.

i

Page 5 of 5

Page 11: Contract Name: Upgradation and Upliftment of existing drainage …jkera.org/TenderedProjects/OtherDocs/143-Add-01.pdf · 2015-06-27 · BOQ of item enclosed. Every Clause 10. APFC

Providing, Installation and commissioning of Electrical equipment in Pump Station Bishember Nagar

S.NO Particulars of Works

2 I Providing and fixing (including Packaging, Handling, Transportation, Insurance, Storage and Inspection & Testing at the manufacturer 's works) of heating point complete with switch, conduit 7/0.036 with pin sockets 15 amp.-3nos(one oprator+2 panel room)

3 I Providing and fixing (including Packaging, Handling, Transportation, Insurance, Storage and Inspection & Testing at the manufacturer's works) of two pin socket complete with switch consists cable 3/0.036-3nos(2 operators room+1 Bath room)

4 I Providing and fixing (including Packaging, Handling,

1

Transportation, Insurance, Storage and Inspection & Testing at the manufacturer's works) of inverter assembly SOOW complete with battery from lighting circuit with one switch and one 20W CFL in bath room and operators rooms one panel room(3nos)

External

Providing and fixing (including Packaging, Handling, Transportation, Insurance, Storage and Inspection & Testing at the manufacturer's works) of Flood lights aasembly flood light 1000W capacity pressure die cast aluminum lumanari for linear tungstun halogen lamp installed one each focusing the light on sumps. The light lumunari should have a flexible base and fittings to rotate it to different base and fittings to rotate it different directions at the time of need-3nos

Unit I Quantity In Figures In words

(INR) (INR)

Job 1

An;l.ount (INR)

Page 4 of 5

Page 12: Contract Name: Upgradation and Upliftment of existing drainage …jkera.org/TenderedProjects/OtherDocs/143-Add-01.pdf · 2015-06-27 · BOQ of item enclosed. Every Clause 10. APFC

LOT-B (Pumping Stations Left bank of Left Jehlum) Bill of Quantities

1'

Unit Rate ~

S.NO Particulars of Works Unit Quantity (Rs

Amount (INR) In Figures In words (INR) (INR)

APFC Panel: Supply Installation, testing and Commissioning (including Packaging, Handling, Transportation, Insurance,

1 Storage and Inspection & Testing at the manufacturer's works)of APFC panel

LOT-B (Pumping Stations along Right bank of River Jehlum)

S. No. Name KVAR

1 Abiguzar 20 No. 1

2 Barbarshah 15 No. 1

3 Bishembernagar 24 No. 1

4 MandirBagh 5 No. 1

5 Khidmat Press 14 No. 1

6 Shivpora 52 No. 1

7 Court Road 18 No. 1

8 GolfOub 29 No. 1

9 Sonvar Bagh 32 No. 1

10 Sonvar Davis 30 No. 1

11 Shora Khan 20 No. 1

12 Noor bagh 13 No. 1

Page lof 1

...

Page 13: Contract Name: Upgradation and Upliftment of existing drainage …jkera.org/TenderedProjects/OtherDocs/143-Add-01.pdf · 2015-06-27 · BOQ of item enclosed. Every Clause 10. APFC

LOT-8 {Pumping Stations Right bank of River Jehlum) Annexure -1

Capacity of pump Internal Dimension of sumps and Span of Capacity of

Proposed Pumps to be installed S.No Name Manorial manorial

(m3/hr) NO Existing sump Proposed sump (m) (tons)

1 Abiguzar 1020 1

2 .. 2 5.2 4 100 2

2 Barbarshah 1530 1 2.25 5.25 5

100 2 2.0 5.0 2

3 Bishembernagar 700 2

4.0 5.3 3.0 100 2

4 Mandir Bagh 280 2 1.8 4.8 2

510 2 2.6 5.6 3

5 Khidmat Press 100 2 2 5 2 6 Shivpora 1530 2 4 7 5

7 Court Road 510 2 2 5 3

Golf Club 1020 2 3 6 4

8 200 2 2.8 5.8 2

9 Sonwar Bagh 770 2 4 7 3

Sonvar Davis 1020 2 3 5.2 4

10 150 2 2.5 5.5 2

Shora Khan 800 1 2 5 4

11 800 1 2.6 5.6 4

12 Noor bagh 1020 2 3.65 6.65 4

Page 1 of 1 •

Page 14: Contract Name: Upgradation and Upliftment of existing drainage …jkera.org/TenderedProjects/OtherDocs/143-Add-01.pdf · 2015-06-27 · BOQ of item enclosed. Every Clause 10. APFC

S.No

1

2

3

4

5 6

7

8

9

10 11 12

Annexure-Ill

LOT-B (Pumping Stations Right bank of River Jehlum)

PUM P Motor Units

Name Type

Abiguzar sw ow

Barbarshah sw ow

Bishembernagar sw ow

Mandir Bagh SW/DW sw

Khidmat Press ow Shivpora sw

I Court Road SW/DW

sw . Golf Club DW Sonwar Bagh sw

sw Sonvar Davis DW

Shora Khan sw Noor bagh sw SW:

OW:

Capacity of each Head pump (M)

(m3/hr) 1020 9 100 10

1530 7

100 9 700 10 100 11 280 8 510 7 100 10

1530 11

510 10 1020 8 200 9 770 11 1020 7 150 8 800 7

1020 7

Storm weather Pump Dry weather Pumps

No: ERA/PM/JKUSDIP/ 3(}~ tf Dated: )4 06-2015

Rating Speed of (RPM) Motor

(HP) 990 50 1450 10 990 40 1450 5 1450 40 1450 10 1450 15 1450 15 1450 10 990 100

1450 35 990 50 1450 10 1450 50 990 40 1450 10 1450 40

990 40

Maximum ..

working Capacity

Quantity Load of DG set Sub Station Capacity

(No) (KVA) (KW)

1 37.3

2 100 Proposed 100KVA(11Kv/440V)

1 Proposed 100KVA(11Kv/440V)

2 47.46 100

2 59.68

2 140 Existing 250KVA(11Kv/440V)

2 22.38 so Proposed 100KVA(11Kv/440V) 2

Proposed 100KVA(11Kv/440V) 2

22.38 50

2 149.2 400 Existing 250KVA(11Kv/440V) Proposed 250KVA(11Kv/440V)

2 52.22 125 Existing 100KVA(11Kv/440V) . 2

250KVA(11Kv/440V) 2 74.6

180 Existing

2 74.6 180 Proposed 250KVA(11Kv/440V) 2

59.68 150 Existing 250KVA(11Kv/440V) 2

2 59.68 140 Proposed 200KVA(11Kv/440V) 2 59.68 140 Existing 250KVA(11Kv/440V)

~ Pr · 1/V' ...........s.x.~~~~

Page 1 of 1

Stabilizer Capacity

(KVA)

100 I

100 i

250

100

100 250 250 100

250

250

250

200

250